The master production schedule (MPS) sets production quantities for finished products to be completed over a short-term planning horizon, usually weeks or months. It is developed by reviewing forecasts, orders, inventory, and capacity. The MPS translates aggregate plans into specific finished goods, evaluates alternative schedules, and generates material and capacity requirements to facilitate production planning and ensure priorities and capacities are managed effectively.
Copyright:
Attribution Non-Commercial (BY-NC)
Available Formats
Download as PPT, PDF, TXT or read online from Scribd
The master production schedule (MPS) sets production quantities for finished products to be completed over a short-term planning horizon, usually weeks or months. It is developed by reviewing forecasts, orders, inventory, and capacity. The MPS translates aggregate plans into specific finished goods, evaluates alternative schedules, and generates material and capacity requirements to facilitate production planning and ensure priorities and capacities are managed effectively.
The master production schedule (MPS) sets production quantities for finished products to be completed over a short-term planning horizon, usually weeks or months. It is developed by reviewing forecasts, orders, inventory, and capacity. The MPS translates aggregate plans into specific finished goods, evaluates alternative schedules, and generates material and capacity requirements to facilitate production planning and ensure priorities and capacities are managed effectively.
Copyright:
Attribution Non-Commercial (BY-NC)
Available Formats
Download as PPT, PDF, TXT or read online from Scribd
The master production schedule (MPS) sets production quantities for finished products to be completed over a short-term planning horizon, usually weeks or months. It is developed by reviewing forecasts, orders, inventory, and capacity. The MPS translates aggregate plans into specific finished goods, evaluates alternative schedules, and generates material and capacity requirements to facilitate production planning and ensure priorities and capacities are managed effectively.
Copyright:
Attribution Non-Commercial (BY-NC)
Available Formats
Download as PPT, PDF, TXT or read online from Scribd
Download as ppt, pdf, or txt
You are on page 1of 5
MASTER PRODUCTION
SCHEDULING MEANING
Master production schedule (MPS) sets the quantity of
each end item (finished product) to be completed in each time period (week ,month or quarter) of the short range planning horizon. MPS are developed by reviewing market forecasts ,custom orders, inventory levels and capacity information regularly.
The MPS is a plan for future production of end items over
a short planning horizon that usually spans from a week to several months. It is important link between marketing and production. FUNCTIONS OF MPS Translating aggregate plans into specific end items Evaluating alternative schedules Generating material requirement Generating capacity requirement Facilitating information processing Maintaining valid priorities Utilizing capacities effectively 1 Translating aggregate plans : This plan translates the specific no of end products to be produced in specific time period.the MPS represents a manufacturing plan of what the firm intends to produce and not the forecast of what the firm hope to produce
2 Evaluating alternative schedules : MPS is made on trial
and error basis.MPS can be done by simulation using computers. Detailed material and capacity required are then derived from the firm MPS.
3 Generating material requirement : The MPS providing
for purchasing and manufacturing the necessary items in sufficient time to meet the final assembly dates specified, based on the mps of the end product. 4 Generating capacity requirements: MPS fulfill the capacity requirements of labour and equipment capacities etc.
5 Facilitating information processing: by controlling the
workloads on work centre, the MPS determines the delivery schedules for end products both for make to stock and made to orders items.
6 Maintaining valid priorities: MPS maintaining the
priorities for various jobs. When customers change their orders or material get scrapped sometimes MPS need to be changed automatically so as the main priorities are set first always 7 Utilizing capacity facilities: by specifying the end items requirements over a time period, the MPS establishes the load and utilization parameters for labour and equipments.