PT. Sutindo Project Ind BETARA COMPLEX DEVELOPMENT PROJECT Job No.

: BCD-090-CA

PIPELINE WELDING AND INSTALLATION


ISSUED Date : 08/12/03 TRACEABILITY PROCEDURE Page : 1 of 7

PIPELINE WELDING AND INSTALLATION


TRACEABILITY PROCEDURE

QC. ENG QC. MGR PRJ MGR


0 08/12/03 ISSUED FOR APPROVAL
SALEH H.K. AHN

REV DATE DESCRIPTION PREPARED/SIGN CHECKED/SIGN APPROVED/SIGN

DOCUMENT NO

JK – BCD – 090 - CA – JKP - 205