S/N Description Unit A Steel Structure Definitions: Prepared by 1305 Engineering and Construction LTD

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 18
At a glance
Powered by AI
The document describes the bill of quantities for a steel structure building including structural steel works, concrete works, and cladding works.

Column C1, Column C2, horizontal and roof beams, bracings, purlins, and cladding are described.

Concrete works for foundations, ground beams and slabs. Reinforcing steel and formwork are also included.

Prepared by 1305 Engineering and Construction Ltd.

S/N Description Unit

A Steel Structure

Definitions

Welding is deemed to be in accordance with the specification


and for the material to which it is to be used. Gusset plates,
shoe plates, ends, caps, cleats, brackets, stiffeners, bolts,
etc., have been included to the rate of the associated steel
works.

Note:
a) For the description of materials and workmanship refer
Specification of works.

b) Rate shall include for:

b.1) All shop fabrication work, making, delivery, unloading


hoisting, erecting and fixing as per detail drawings.

b.2 All welds are 6mm thick fillet weld & allowance for
rolling margin.

b.3) The weight of weld metal in welded constructions.

b.4 Members of any length

b.5 Cutting to size and shape and joints in the running


length.

b.6 Grinding to a smooth, unless otherwise requred.

b.7 Machine drilled bolts, holes, bolts, nuts and washers, cleats,
shoe and gusset plates and all other connections.

.8 After fabrication wire brushed to clean the all steel surfaces

Page 1
Prepared by 1305 Engineering and Construction Ltd.

and spray painted with two coats of quick drying metal


primer zinc phosphate & two coats of matt anti corrosive
with necessary accessories

Page 2
Prepared by 1305 Engineering and Construction Ltd.

S/N Description Unit

Fabricating and Erecting Framed Structures

1.00 Column, C1; Structural steel Section UB 203*103*23.1kg/m (IPE200)


welded to plate connectors/gusset plate all as per detail drawing. kg
Rate shall include for base plates, anchorage bolts, painting
as specified.

2.00 Column, C2; Structural steel Section SHS 100*100*3.0mm (SHS100/3)


welded to plate connectors/gusset plate all as per detail drawing. kg
Rate shall include for base plates, anchorage bolts, painting
as specified.

3.00 Horizontal beam B1; Structural steel Section, UB152*89*16kg/m


(IPE60) spanning 5.663m in length welded to plate connectors/ kg
gusset plate all as per detail drawing. Rate shall include for base
plates, anchorage bolts, painting as specified.

4.00 Horizontal beam B2; Structural steel Section, UNP80 spanning


5.663m in length welded to plate connectors/gusset plate all kg
as per detail drawing. Rate shall include for base plates, anchorage
bolts, painting as specified.

5.00 Roof Rafter Beam; Structural Steel section UB 152*89*16kg/m (IPE60)


welded to plate connectors, haunch beams and all as per detail kg
drawing. Rate shall include for base plates, anchorage bolts, painting
as specified.

6.00 Roofing rafter; Structural steel Section, UNP80 spanning 12.0m


welded to plate connectors, haunch beams and all as per detail kg
drawing. Rate shall include for base plates, anchorage bolts, painting
as specified.

7.00 Horizontal Bracing HBR1; Round tubular profile, ROR 60.3/2.9


welded to plate connectors/gusset plate all as per detail drawing kg
Rate shall include for anchorage bolts, painting as specified.

Page 3
Prepared by 1305 Engineering and Construction Ltd.

8.00 Wind Bracing VB1; Round tubular profile RHS100*50*3.0mm


(RHS100/3) welded to plate connectors/gusset plate all as per detail kg
drawing. Rate shall include for base plates, anchorage bolts, painting
as specified.

9.00 Purlins
Supply & fixing of double channel purlins, 80*45*3mm; welded to
rafter beams (measured separately) at 1000m centers; complete with kg
all the required paint works and all necessary supports.

Steel Structure To Summary

S/N Description Unit

10.00 Cladding siding


Supply & fixing of double channel purlins, 80*45*3mm; welded to
columns (measured separately) at 1000m centers; complete with kg
all the required paint works and all necessary supports.

Sag rods for purlins


11.00 Supply and fix purlin stiffeners, 12mm dia. steel sag rods at purlin
midspans; complete with all the required paint works and all m
necessary supports

Sag rods for cladding siding


1.00 Supply and fix purlin stiffeners, 25mm dia. steel sag rods at purlin
midspans; complete with all the required paint works and all m
necessary supports

Page 4
Prepared by 1305 Engineering and Construction Ltd.

2.00 Allow sum for any other item required for the construction and SUM
completion of the roof framework, which are not covered under the
above items.

Roof Coverings, Plumbing


Rate shall include

All, rivets, nails, clips, strips and delivering and fixing in positon

Roof plumbing shall be measured & grouped separately;

3.00 Roof covering


Supply & fix 0.7mm aluminimum profile sheeting; fixed with
self drilling screws to the purlins (measured separately) and m
rubber capping to tops of bolts

4.00 Ridges
Supply and fix 0.7mm thk. Aluminimum ridge cap; 650mm girth
(average) in position complete with all necessary roofing screws or m
hooks as required.

5.00 Gutters
Supply and fix moulded mild steel/galvanised 2.5mm thick plate
storm wate gutters; 650mm girth 650mm girth (average) in position m
complete with all necessary roofing screws or hooks as required.

Flashings
6.00 Supply and fix 0.7mm thk aluminimum profile sheeting end flashing;
650mm girth (average) in position complete with all necessary m
roofing screws or hooks as required.

Steel Structure To Summary

Page 5
Prepared by 1305 Engineering and Construction Ltd.

S/N Description Unit

Cladding
1.00 Supply & fix 0.7mm aluminimum profile sheeting; fixed with m
self drilling screws to the purlins (measured separately

Anchor bolts
2.00 Supply and install 16mm dia. Anchor bolts Nos.

Plumbing
3.00 100mm dia PVC pressure pipe downspout with all accessories Nos.

B Civil Works (Labour, Equipment, Overhead and Profit)

Concrete Works

Plain in-situ concrete to strength 10N/mm as described in:

1.00 100mm lean concrete cushion under foundation footing m

Reinforced in-situ vibrated concrete to strength 30N/mm


filled into formwork and around reinforcement in:

2.00 600mm thk. ground beam m

3.00 200mm thk. slab m

Steel deformed bars to BS4449 of characteristic strength 420N/mm


as described in:

4.00 14mm dia. bar in ground beam kg

5.00 10mm diameter bar as stirrups in ground beams kg

Page 6
Prepared by 1305 Engineering and Construction Ltd.

6.00 12mm diameter bar in 200mm thk. slab kg

Fair finish Formwork to: (Materials Included)

7.00 Sides of lean concrete m

8.00 Sides of ground beams m

Steel Structure To Summary

S/N Description Unit

Summary

Page 1

Page 2

Page 3

Sub Total

Page 7
Prepared by 1305 Engineering and Construction Ltd.

Preliminaries and General Conditions of Contract

Total

Page 8
Prepared by 1305 Engineering and Construction Ltd.

Page 9
Prepared by 1305 Engineering and Construction Ltd.

Unit Price
Qty Total GHS
GHS

Page 10
Prepared by 1305 Engineering and Construction Ltd.

Page 11
Prepared by 1305 Engineering and Construction Ltd.

Unit Price
Qty Total GHS
GHS

1,478.40 12.00 17,740.80

172.80 10.00 1,728.00

2,944.00 12.00 35,328.00

3,440.00 5.00 17,200.00

1,664.00 12.00 19,968.00

1,651.20 5.00 8,256.00

1,068.60 9.00 9,617.40

Page 12
Prepared by 1305 Engineering and Construction Ltd.

907.20 9.00 8,164.80

6,880.00 5.00 34,400.00

188,779.00

Qty Unit Price Total GHS

7,155.20 5.00 35,776.00

120.00 5.00 600.00

132.00 5.00 660.00

Page 13
Prepared by 1305 Engineering and Construction Ltd.

1.00 5,000.00 5,000.00

528.00 120.00 63,360.00

40.00 65.00 2,600.00

80.00 80.00 6,400.00

80.00 65.00 5,200.00

119,596.00

Page 14
Prepared by 1305 Engineering and Construction Ltd.

Qty Unit Price Total GHS

416.00 120.00 49,920.00

112.00 50.00 5,600.00

14.00 390.00 5,460.00

8.64 200.00 1,728.00

40.56 200.00 8,112.00

96.00 200.00 19,200.00

2,003.76 3.50 7,013.16

1,065.60 3.50 3,729.60

Page 15
Prepared by 1305 Engineering and Construction Ltd.

8,986.56 3.50 31,452.96

20.80 70.00 1,456.00

124.80 70.00 8,736.00

142,407.72

Unit Price
Qty Total GHS
GHS

188,779.00

119,596.00

142,407.72

414,406.72

Page 16
Prepared by 1305 Engineering and Construction Ltd.

10% 41,440.67

455,847.39