User Training Manual - PS - TP - End User V1.2
User Training Manual - PS - TP - End User V1.2
User Training Manual - PS - TP - End User V1.2
User Manual
Project System
Transmission Projects
Reference Business Process No.-BSNL_BBP_PS_TP
Version:1.2
25.03.2011
PS_UTM_TP_01
Project System
Transmission Projects
Version Control
Date
Version
0.1
0.2
1.0
1.1
1.2
Author
Gaurav Verma
Rajeev Sharma
Rajesh Jain/Rajeev
Sharma/Gaurav
Verma/Pawan Yadav
Abhinav Bhalla
Nimish Goswamy/Abhinav
Bhalla
Change Description
Draft
Review
Final Submission and agreement
Updated CE fields
Review and update after FIT
End Users Performing day to day transactions as per their Roles and Authorizations in SAP
System.
Core Team Directly involved in the Projects and supporting the various activities in Project
Phases
Business Process Owners Respective Business Leaders, involved in validating the
process design.
Important Note:
The information in this document is only meant to be a reference for ERP Process configured as
per the Business Process approved by BSNL Management for Project System Module and is not a
complete description of the SAP product and its functionalities. Its main purpose is to serve as a
reference Document for User Training and Support.
Page 1 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Course Overview
SAP Project System supports comprehensive functions for planning, controlling and organizing
all the activities carried out during the course of a project. It helps you manage your project
structures, dates, costs, and resources throughout the entire project lifecycle. Course provides
you with an overview of the functions in SAP Project System.
Target Audience
This course is intended for the following audiences:
Project managers
Project team members
Consultants
Course Prerequisites
Course Goals
This course will prepare you to:
Discuss the basic functions of SAP Project System for RTPC MOM
Discuss the basic functions of SAP Project System for structuring, planning,
executing, and monitoring projects
Course Objectives
After completing this course, you will be able to:
Page 2 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Table of Contents
1.
2.
3.
4.
SEND WBS ELEMENT FOR DETAILING / SURVEY USING NOTE SHEET ................................. 24
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24. SEND WBS FOR PE CUM DE APPROVAL TO COMPETENT AUTHORITY USING NOTE
SHEET ................................................................................................................................................................ 67
25.
26.
27.
28.
29.
30.
31.
Page 3 of 108
PS_UTM_TP_01
Project System
Transmission Projects
32.
PLAN FOR PROJECT WISE ACTIVITIES (SKF STATISTICAL KEY FIGURE) .......................... 75
33.
34.
35.
36.
37.
38.
39.
40.
41.
42.
43. UPDATE THE WBS STATUS TO LIST OF PENDING POINTS / SHORTCOMING FROM AT (IF
ANY) .................................................................................................................................................................. 89
44.
UPDATE THE WBS STATUS TO CLEARANCE OF PENDING POINTS (IF ANY) ...................... 90
45. UPDATE THE WBS STATUS TO RELAXATION FOR PENDING POINTS NOT CLEARED (IF
ANY) .................................................................................................................................................................. 92
46.
47.
48.
49.
50.
51.
52.
53.
UPDATE THE WBS STATUS TO OFFERED FOR TAKING OVER ............................................... 102
54.
55.
56.
Page 4 of 108
PS_UTM_TP_01
Project System
Transmission Projects
OVERVIEW
SAP Project System supports comprehensive business Process for Planning, Controlling
& Organizing all the activities carried out during the course of a Project. It helps you to
manage your Project structure, dates, cost & task throughout the entire Project lifecycle.
Western Telecom Projects is responsible for planning, survey and execution of various
long distance Telecom Transmission Projects and Switching Projects for building up
National Telecom Infrastructure in different Zone for Optical Fiber Cable system,
Digital Microwave, Trunk Automatic Exchange (TAX) and Satellite based
communication systems in entire Western part of the country which includes states of
Maharashtra
Gujarat
Madhya Pradesh
Chattisgarh
Goa
Page 5 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Create Document
Menu path
Transaction
CV01N
Page 6 of 108
PS_UTM_TP_01
Project System
Transmission Projects
2.
Page 7 of 108
PS_UTM_TP_01
Project System
Transmission Projects
3. Select the Class Project Details and select the Characteristics Approval
Channel and
4. Press
6. Press
PS_UTM_TP_01
Project System
Transmission Projects
8. And press
Page 9 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Change Document
Menu path
Transaction
CV02N
Page 10 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Page 11 of 108
PS_UTM_TP_01
Project System
Transmission Projects
NOTE: The system will give the list of documents on the search criteria.
4. Open the document by double clicking it and see the List of projects by opening
the attached file in it.
5. Click on Send to send the list of Approved projects to the person concerned
Page 12 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Click on
Page 13 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Create Project
Menu path
Transaction
CJ01
2. Enter the appropriate coding mask (For example TP/11/00001) for Project
Definition in the Start value. Definition-Open Number-This is the free number
available in the System.
3. Press Find
4. Click on copy
(Note: Please use Project Coding Mask TP/11/00001 for Financial Year
2011-12)
Page 14 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Click on Open
Number
Page 15 of 108
PS_UTM_TP_01
Project System
Transmission Projects
(Project profile: This contains default values and control parameters for processing
objects and functions in the Project System)
6. If you want to copy an existing Project, enter the Project Definition / Standard
Project Definition (Project to be copied) in the Template section (Refer Fig. below)
Description field
is mandatory
and,
Enter Company Code; Business Area & Plant (Refer Fig.) For Example:
Field
Description
Person
Responsible
Start Date
Finish Date
Company Code
Business area
Plant
Remarks
Enter the Person Responsible
Enter the Start date of Project
Enter the Planned finish date of Project
Select the relevant Project circle
Select the Project Area
Select the relevant Plant
Page 16 of 108
PS_UTM_TP_01
Project System
Transmission Projects
10. Click on Details > Project Definition customer fields & enter the data
Open the below file to view the Project Definition Customer Fields;
Project Definition
Customer Enhancement Field.xlsx
Page 17 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Note: Above Screen will appear when the new project is created by copying the existing
project.
12. Deselect the line which is not required as per the project structure of current project
button,
Page 18 of 108
PS_UTM_TP_01
Project System
Transmission Projects
14. A pop up screen will appear, mention the last two digit of the project which is to be
copied in Search and last two digit of the new project number.
button.
16. Ensure that the PE (Planning Element) indicator is ticked for all the WBS Elements
(Except for the Level 1, Level 2 WBS Elements)
Page 19 of 108
PS_UTM_TP_01
Project System
Transmission Projects
17. Ensure that the Acct (Account Assignment Element) indicator is ticked for all the
WBS Elements (Except for the Level 1, Level 2 WBS Elements)
(Definition-Account Assignment Element: An Element of a work breakdown structure
on which Actual Costs can be posted)
If this is un-ticked for a particular WBS Element, system will not allow Posting of actual
cost on that WBS Element.
Project Type
Planning
Indicator
Page 20 of 108
Account
Assignment
Indicator
PS_UTM_TP_01
Project System
Transmission Projects
19. Now, Click on the Dates Tab. Enter the Basic start & Basic Finish Dates for the WBS
Element.
Page 21 of 108
20. Click on
PS_UTM_TP_01
Project System
Transmission Projects
or press Enter.
Page 22 of 108
PS_UTM_TP_01
Project System
Transmission Projects
22. Click on to the below file to view the WBS Element Customer Fields.
WTP WBS ELEMENT
CE FIELDS
Note: WBS Element Customer Fields are to be filled for each WBS mentioned in the
Project.
CJ02
Change Project
Menu path
Transaction
CJ02
For making any changes in the parameters once the Project is created the above menu
path OR the Transaction is to be used.
CJ03
Display Project
Menu path
Transaction
CJ03
Page 23 of 108
PS_UTM_TP_01
Project System
Transmission Projects
1. Select the WBS element & Click on details WBS Element Customer fields
Enter the WBS element and employee id of the person to whom the note sheet is
to be sent.
Page 24 of 108
PS_UTM_TP_01
Project System
Transmission Projects
If you want to see the details of the WBS element in edit mode press
If you want to see the details of the WBS element in display mode press
If you want to see the document attached to the WBS Element press
This button should be used by the Competent authority, at the Root WBS
Element, to approve the PE of all WBS Elements in a single shot.
Note: Project Estimate shall be approved by the competent authority.
Alternatively you can use the T-Code ZPS_NOTESHEET to open the note
sheet.
Office Workplace
Transaction
SBWP
1.
2. Click on the
Note: The note sheet screen will appear. Add the details and forward it to next level, as
explained in the Step 4.
Page 25 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Create Document
Menu path
Transaction
Page 26 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Page 27 of 108
PS_UTM_TP_01
Project System
Transmission Projects
7. To assign the document to a WBS Element, click on the Object Links tab and
then go to the WBS Element Tab. Enter the WBS Element No. and press enter.
Create Document
Menu path
Transaction
1. On the entry screen, enter the Document Type e.g. ZCD /ZED (Civil / Electrical
Drawings).
2. Enter the Document version.
3. Press Enter.
Page 28 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Page 29 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Page 30 of 108
PS_UTM_TP_01
Project System
Transmission Projects
7. To assign the document to a WBS Element, click on the Object Links tab and then
go to the WBS Element Tab. Enter the WBS Element No. and press enter.
Page 31 of 108
PS_UTM_TP_01
Project System
Transmission Projects
8. Save the document. An internal no. will be generated. Note down the Document
No.
Create Document
Menu path
Transaction
Page 32 of 108
PS_UTM_TP_01
Project System
Transmission Projects
5. Repeat the procedure described above and change the Document Status to
Final Approval.
Page 33 of 108
PS_UTM_TP_01
Project System
Transmission Projects
9.
Change WBS
Menu path
Transaction
PS_UTM_TP_01
Project System
Transmission Projects
Change WBS
Menu path
Transaction
1. Select the WBS element & click on details -WBS Customer fields
Page 35 of 108
PS_UTM_TP_01
Project System
Transmission Projects
3. Enter the WBS element and Employee id of the person to whom the note sheet is
to be sent.
Page 36 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Page 37 of 108
PS_UTM_TP_01
Project System
Transmission Projects
6. Choose the relevant Personnel Area from the input help. Alternatively use the
search option (with the help of Binoculars) Enter WTP
Click on
Click on
7. Choose the relevant Personnel Sub area from the input help, Select 7600 in the
restrictions to get the Personnel Sub Area relevant to WTP Only and find Nagpur
from the list.
Page 38 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Press Enter
Page 39 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Page 40 of 108
PS_UTM_TP_01
Project System
Transmission Projects
If you want to see the details of the WBS element in edit mode press
If you want to see the details of the WBS element in display mode press
If you want to see the document attached to the WBS Element press
This button should be used by the competent authority, at the Root WBS
Element, to approve the PE of all WBS Elements in a single shot.
Note: Project Estimate shall be approved by the competent Authority
Create Document
Page 41 of 108
Menu path
Transaction
PS_UTM_TP_01
Project System
Transmission Projects
Page 42 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Page 43 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Change WBS
Menu path
Transaction
Page 44 of 108
PS_UTM_TP_01
Project System
Transmission Projects
4. Click on
Page 45 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Create Network
Menu path
Transaction
Remarks
Select ZPS2
Select the relevant Plant
Select the Relevant MRP Controller
3. Enter the Std. Network (If required) from which data is to be copied.
Network Profile
Page 46 of 108
PS_UTM_TP_01
Project System
Transmission Projects
5. Go to the Assignments tab and Enter Project Definition and WBS Element (Operative
Project).
6. Click on Save
7.
CN22
Change Network
Menu path
Transaction
For making any changes in the Network once it is created the above menu path or the
Transaction Code CN22 is to be used.
Page 47 of 108
PS_UTM_TP_01
Project System
Transmission Projects
CN23
Display Network
Menu path
Transaction
To view the Network created the above menu path or the Transaction Code CN23 is to be used.
Change Network
Menu path
Transaction
1. Enter the Network number created and press Enter (Refer Fig. below)
2. Go to the Activity Overview
4.
Click on
5. Click on Save
Page 48 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Change Network
Menu path
Transaction
CN22
1. Enter the Network number created and press Enter (Refer Fig. below).
4. Go to Component Overview
5. Search the relevant Material code through the Search option (F4)
Page 49 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Page 50 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Material
Requirement Qty
Item Category
Procurement type
Page 51 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Change Network
Menu path
Transaction
1. Enter the Network number created and press Enter (Refer Fig. below)
2. Click on Activity Overview
3. Select the Activity & Click on Component Overview
Page 52 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Line wise enter the Material code required for the Activity
Enter quantity to be procured.
Enter L for stock item.
A submenu opens, where we have to select the required
button.
6. Click on Continue
7. Double click on the Material.
Page 53 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Page 54 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Page 55 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Change Network
Menu path
Transaction
1.
Enter the Network number created and press Enter (Refer Fig. below)
2.
Go to Activity Overview
and click.
Page 56 of 108
3.
PS_UTM_TP_01
Project System
Transmission Projects
Press Enter.
Page 57 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Change Network
Menu path
Transaction
1. Enter the Network number created and press Enter (Refer Fig. below)
2. Go to Activity Overview
3. On the Prim. Costs tab, enter the relevant description and assign it to the relevant
WBS Element. (Refer Fig. below)
Page 58 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Change Network
Menu path
Transaction
Page 59 of 108
4. Click on
PS_UTM_TP_01
Project System
Transmission Projects
Page 60 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Change Network
Menu path
Transaction
1. Enter the Network number created and press Enter (Refer Fig. below)
2. Go to Activity Overview
3. Select the Activity.
4. Click on Milestone Overview.
5. Milestone can be attcahed by following methods :
a) Use Standard Milestone Click on Standard Milestone
Page 61 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Page 62 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Change WBS
Menu path
Transaction
1. Enter the WBS Element and press Enter (Refer Fig. below)
2. Go to WBS Overview
3. Select the WBS.
4. Click on Milestone Overview.
Page 63 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Project Scheduling
Menu path
Transaction
Page 64 of 108
PS_UTM_TP_01
Project System
Transmission Projects
4. Click on Execute
5. Click on
Page 65 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Change WBS
Menu path
Transaction
3. Click on
Page 66 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Note sheet
1. Select the WBS element Details - click on Customer fields:
Enter the WBS element and Employee ID of the person to whom the Note Sheet
is to be sent.
Page 67 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Enter the WBS element and Employee ID of the person to whom the Note Sheet is to be
sent.
If you want to see the details of the WBS element in edit mode press
If you want to see the details of the WBS element in display mode press
If you want to see the document attached to the WBS Element press
This button should be used by the competent authority, at the Root WBS Element, to
approve the PE of all WBS Elements in a single shot.
Page 68 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Note sheet
Menu path
Office Workplace
Transaction
SBWP
1.
2. Click on
3. The note sheet screen will appear. Add the details and forward it to next level, as
explained in the Step-6.
Page 69 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Structure Overview
Menu path
Transaction Code
3. Click on Execute.
4. Check the Plan, Actual & Commitment column.
5. Click on Back.
Page 70 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Change WBS
Menu path
Transaction
4. Click on
PS_UTM_TP_01
Project System
Transmission Projects
Change WBS
Menu path
Transaction
4. Click on
Page 72 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Menu path
Transaction
N/A
ZPEDE / CJ02
2. Click on Execute
3. Click on the Document number
Page 73 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Note: Document is appeared and the same can be downloaded in the local system
Alternatively, Approved PE/DE/RE can be viewed through CJ02 also,
1. Select the Relevant WBS Element
Page 74 of 108
PS_UTM_TP_01
Project System
Transmission Projects
4. Click on
32. Plan for Project Wise Activities (SKF Statistical Key Figure)
CJS2
Plan SKF
Menu path
Transaction
1. Enter Version, From & To Period, Fiscal Year, Relevant WBS Element, &, Stat.
Key Figure
2.
3.
PS_UTM_TP_01
Project System
Transmission Projects
4. Click on
Period Screen
Project Release
Menu path
Transaction
Page 76 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Following error message might appear while changing the status to Release.
In that case, co-ordinate with Finance to run the transaction IM52 (Budget Distribution)
/CJBV (Activate Availability Control).
5. Check the status
6.
Similarly change the status of all other WBS Elements & the the Project Definition.
7.
Click on Save.
Page 77 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Change Network
Menu path
Transaction
PS_UTM_TP_01
Project System
Transmission Projects
SKF Posting
Menu path
Transaction
2.
4. Enter Quantity
Page 79 of 108
PS_UTM_TP_01
Project System
Transmission Projects
5. Click on Save
Change WBS
Menu path
Transaction
4. Click on
Page 80 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Change WBS
Menu path
Transaction
Page 81 of 108
PS_UTM_TP_01
Project System
Transmission Projects
4. Click on
Click on Save
Change WBS
Menu path
Transaction
Page 82 of 108
PS_UTM_TP_01
Project System
Transmission Projects
4. Click on
Page 83 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Change Network
Menu path
Transaction
1. Go to the Activity Overview on the Header Details screen of the Network :2. Go to the tab for Int. Processing as shown below and select the internal activity
4. On the Next screen carry out the following steps for Partial Confirmation of the
Activity:5. Enter the Start and Finish Date in the respective fields as shown below:-
Page 84 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Page 85 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Change WBS
Menu path
Transaction
1. Enter the WBS Element No. and press Enter (Refer Fig. below)
2. Go to WBS Element Overview.
3. Select the WBS Element.
4. Click on Milestone Overview.
5. Select the Row of a Milestone & Click on details
Change Network
Menu path
Transaction
1. Enter the Network no. and press Enter (Refer Fig. below)
2. Go to Activity Overview.
3. Select the relevant Activity.
Page 86 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Page 87 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Change WBS
Menu path
Transaction
4. Click on
Page 88 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Note: - At this status user can attach any relevant documents on the WBS element to
carry out AT (for reference.)
43. Update the WBS Status to List of Pending Points / Shortcoming from
AT (If Any)
CJ02
Change WBS
Menu path
Transaction
Page 89 of 108
PS_UTM_TP_01
Project System
Transmission Projects
4. Click on
44. Update the WBS Status to clearance of Pending Points (If Any)
CJ02
Change WBS
Menu path
Page 90 of 108
Transaction
PS_UTM_TP_01
Project System
Transmission Projects
CJ02
4. Click on
Page 91 of 108
PS_UTM_TP_01
Project System
Transmission Projects
45. Update the WBS Status to Relaxation for Pending Points Not Cleared
(If Any)
CJ02
Change WBS
Menu path
Transaction
4. Click on
Page 92 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Change WBS
Menu path
Transaction
4. Click on
Page 93 of 108
PS_UTM_TP_01
Project System
Transmission Projects
Change WBS
Menu path
Transaction
Page 94 of 108
PS_UTM_TP_01
Project System
Transmission Projects
4. Click on
Change WBS
Menu path
Transaction
PS_UTM_TP_01
Project System
Transmission Projects
6. Click on Save
Change Network
Menu path
Transaction
PS_UTM_TP_01
Project System
Transmission Projects
Note: At TECO status the user will not be allowed to expand the project structure.
Planning in Projects as such is not allowed at this status, Actual cost can however be
posted to the WBS element.
Change WBS
Menu path
Transaction
Page 97 of 108
PS_UTM_TP_01
Project System
Transmission Projects
3. Click on details
4. Click on
Change WBS
Menu path
Transaction
PS_UTM_TP_01
Project System
Transmission Projects
3. Click on details
and then go to
tab
4. Select field key Transmission Project Equipment from the drop down
Page 99 of 108
PS_UTM_TP_01
Project System
Transmission Projects
5. Press Enter
6. Enter the Equipment PO Number
8. Press Enter or
9. Click on Save
Change WBS
Menu path
Transaction
PS_UTM_TP_01
Project System
Transmission Projects
Settlement Period
Fiscal Year
Processing Type
6. Click on Execute
Note: The Above step is carried out for test run the settlement process so that any
error can be checked. For Actual Settlement please Uncheck/Deselect the Test
Run
PS_UTM_TP_01
Project System
Transmission Projects
Change WBS
Menu path
Transaction
4. Click on
8. Click on Save
PS_UTM_TP_01
Project System
Transmission Projects
Change WBS
Menu path
Transaction
CJ02
4. Click on
PS_UTM_TP_01
Project System
Transmission Projects
Change WBS
Menu path
Transaction
PS_UTM_TP_01
Project System
Transmission Projects
Note: Once Closed Status is set ,no actual cost can be posted to the WBS element.
PS_UTM_TP_01
Project System
Transmission Projects
Press Execute
Remarks:- In the output of this report user can access information as per a no. of
categories viz.
PS_UTM_TP_01
Project System
Transmission Projects
Press Execute
Press Execute