Marine Corps Amphibious Combat Vehicle (ACV) and Marine Personnel Carrier (MPC
Summary
On January 6, 2011, after spending approximately $3 billion in developmental funding, the
Marine Corps cancelled the Expeditionary Fighting Vehicle (EFV) program due to poor reliability
demonstrated during operational testing and excessive cost growth. Because the EFV was
intended to replace the 40-year-old Amphibious Assault Vehicle (AAV), the Pentagon pledged to
move quickly to develop a more affordable and sustainable vehicle to replace the EFV. The
Amphibious Combat Vehicle (ACV) is intended to replace the AAV, incorporating some EFV
capabilities but in a more practical and cost-efficient manner. In concert with the ACV, the
Marines were developing the Marine Personnel Carrier (MPC) to serve as a survivable and
mobile platform to transport Marines when ashore. The MPC was not intended to be amphibious
like an AAV, EFV, or the ACV but instead would be required to have a swim capability for inland
waterways such as rivers, lakes, and other water obstacles such as shore-to-shore operations in the
littorals. Both vehicles are intended to play a central role in future Marine amphibious operations.
On June 14, 2013, Marine leadership put the MPC program on ice due to budgetary pressures
but suggested the program might be resurrected some 10 years down the road when budgetary
resources might be more favorable.
In what was described as a drastic shift, the Marines decided to resurrect the MPC in March
2014. The Marines designated the MPC as ACV Increment 1.1 and planned to acquire about 200
vehicles. The Marines also plan to develop ACV Increment 1.2, a tracked, fully amphibious
version, and to acquire about 470 vehicles and fund an ongoing high water speed study. Although
ACV Increment 1.1 will have a swim capability, a connector will be required to get the vehicles
from ship to shore.
On November 5, 2014, it was reported the Marines released a draft Request for Proposal (RFP)
for ACV Increment 1.1. The Marines are looking for information from industry regarding
program milestones, delivery schedules, and where in the program cost savings can be achieved.
On November 24, 2015, the Marine Corps awarded BAE Systems and SAIC contracts to develop
ACV 1.1 prototypes for evaluation. BAEs contract was for $103.8 million and SAICs for $121.5
million, and each company is to build 16 prototypes to be tested over the next two years. Both
vendors are expected to start delivering their prototypes in the fall of 2016 for testing, and the
Marines expect to down select to a single vendor in 2018.
The Administrations FY2016 Budget Request for the ACV was $219.1 million in Research,
Development, Testing and Evaluation (RDT&E) funding. Congress approved the
Administrations FY2016 ACV budget request.
A potential issue for Congress is the Marines new MPC/ACV acquisition strategy and its
associated challenges and risks. This report will be updated.
Marine Corps Amphibious Combat Vehicle (ACV) and Marine Personnel Carrier (MPC
Contents
Background ..................................................................................................................................... 1
Significance for Congress................................................................................................................ 2
The Marines Justification for the ACV and MPC .......................................................................... 2
ACV .......................................................................................................................................... 2
MPC .......................................................................................................................................... 2
Desired Operational Capabilities ..................................................................................................... 2
ACV .......................................................................................................................................... 2
MPC .......................................................................................................................................... 3
Is There a Need for a Marine Corps Amphibious Assault Capability? ............................................ 4
Expeditionary Force 21 and Finding the Seams .................................................................... 5
The Shift Toward Connectors.................................................................................................... 6
Program Information ....................................................................................................................... 7
2013 Decision to Shelve the MPC ......................................................................................... 7
Major Change to Marine Corps Modernization Strategy .......................................................... 7
Marines Release Request for Information (RFI) for ACV Increment 1.1 ................................. 7
Marines Release Draft Request for Proposal (RFP) for ACV Increment 1.1 ............................ 8
Additional Details on 2015 ACV 1.1 RFP ................................................................................ 8
ACV 1.1 Fielding Plan ........................................................................................................ 8
Marines Award ACV 1.1 Contracts ........................................................................................... 9
Budget Activity................................................................................................................................ 9
FY2016 Budget Request ........................................................................................................... 9
H.R. 1735, National Defense Authorization Act for Fiscal Year 2016 .................................... 10
Funding ............................................................................................................................. 10
S. 1376, National Defense Authorization Act for Fiscal Year 2016 ........................................ 10
Funding ............................................................................................................................. 10
H.R. 2685, Department of Defense Appropriations Bill, 2016 ............................................... 10
Funding ............................................................................................................................. 10
S. 1558, Department of Defense Appropriations Bill, 2016 ................................................... 10
Funding ............................................................................................................................. 10
Conference Report to Accompany H.R. 1735, National Defense Authorization Act for
FY2016 ................................................................................................................................ 10
Funding ............................................................................................................................. 10
Potential Issue for Congress ........................................................................................................... 11
The Marines New ACV/MPC Acquisition Strategy ............................................................... 11
Contacts
Author Contact Information ........................................................................................................... 11
Marine Corps Amphibious Combat Vehicle (ACV) and Marine Personnel Carrier (MPC
Background
U.S. Code, Title 10, Section 5063, United States Marine Corps: Composition and Functions,
dated October 1, 1986, states:
The Marine Corps will be organized, trained and equipped to provide an amphibious and
land operations capability to seize advanced naval bases and to conduct naval land
campaigns.
In this regard, the Marines are required by law to have the necessary equipment to conduct
amphibious operations and land operations. The ACV and MPC are considered integral systems
by the Department of Defense (DOD) and Marine Corps to meet this legal requirement.
On January 6, 2011, after spending approximately $3 billion in developmental funding, the
Marine Corpswith encouragement from DODcancelled the Expeditionary Fighting Vehicle
(EFV) program. The EFV was intended to replace the 40-year-old Amphibious Assault Vehicle
(AAV), which currently transports Marines from ships to shore under hostile conditions. The EFV
was cancelled due to excessive cost growth and poor performance in operational testing.
Recognizing the need to replace the AAV, the Pentagon pledged to move quickly to develop a
more affordable and sustainable vehicle to take the place of the EFV. The Amphibious Combat
Vehicle (ACV) is intended to replace the AAV, incorporating some EFV capabilities but in a more
practical and cost-efficient manner.
In concert with the ACV, the Marines were developing the Marine Personnel Carrier (MPC) to
serve as a survivable and mobile platform to transport Marines when ashore. At present, the
Marines do not have a wheeled armored fighting vehicle that can operate as a dedicated infantry
carrier with Marine maneuver forces inland. The MPC was not intended to be amphibious like an
AAV, EFV, or the ACV but instead would be required to have a swim1 capability for inland
waterways such as rivers, lakes, and other water obstacles such as shore-to-shore operations in the
littorals. Because of a perceived amphibious redundancy, some have questioned the need for
both the ACV and MPC. In June 2013, citing budgetary pressures, the Marines reportedly put the
MPC program on ice and suggested that it might not be resurrected for about 10 years.2
With the Marines involved in decades-long land conflicts in Iraq and Afghanistan and
proliferating anti-access technologies such as guided missiles, some analysts questioned if the
Marines would ever again be called on to conduct a large-scale amphibious assault operation. In
response to these questions and the perceived need to examine the post-Iraq and Afghanistan
Marine Corps, the Department of the Navy and DOD studied the requirement to conduct largescale amphibious operations and in early 2012 released a strategic vision for how amphibious
operations will be conducted in the future. The primary assertion of this study is that the Marine
Corps and Navys amphibious capabilities serve a central role in the defense of the global
interests of a maritime nation. The need to maintain an amphibious assault capability is viewed by
Marine Corps leadership as establishing the requirement for the ACV and MPC (as discussed in
greater detail below).
An amphibious capability generally refers to a vehicles ability to debark from a ship offshore at a considerable
distance and then move under fire to shore. A swim capability refers to a vehicles ability to traverse limited water
obstacles such as streams, rivers, and smaller bodies of inland water.
2
Lee Hudson, Marines Put Marine Personnel Carrier on Shelf Due to Budget Constraints, InsideDefense.com, June
14, 2013.
Marine Corps Amphibious Combat Vehicle (ACV) and Marine Personnel Carrier (MPC
MPC
While the AAV has some armor protection and can operate inland to a limited extent, it is not
intended for use as an infantry combat vehicle. The Marines do have the LAV-25, Light Armored
Vehicle-25, an eight-wheeled armored vehicle that carries a crew of three and six additional
Marines. The LAV-25 is armed with a 25 mm chain gun and a 7.62 mm machine gun but is not
fully amphibious as it cannot cross a surf zone and would get to the beach via some type of
connector such as the Landing Craft, Air Cushioned (LCAC). The LAV-25 has been in service
since 1983. According to the Marine Program Executive Office (PEO) Land Systems, the LAV is
not employed as an armored personnel carrier and usually carries a four-person Marine
scout/reconnaissance team in addition to its crew.3 In this regard, the MPC was viewed as
necessary by Marine leadership for the transport and enhanced armor protection of Marine
infantry forces.
Program Executive Office (PEO) Land Systems Marine Personnel Carrier Fact Sheet, 2010.
Unless otherwise noted, information in this section is taken from the Amphibious Vehicle Request for Information
(RFI) issued by the Marine Corps Systems Command on February 11, 2011.
5
The Federal Acquisition Regulation defines an RFI as a document used to obtain price, delivery, other market
(continued...)
4
Marine Corps Amphibious Combat Vehicle (ACV) and Marine Personnel Carrier (MPC
The proposed vehicle must be able to self-deploy from amphibious shipping and
deliver a reinforced Marine infantry squad (17 Marines) from a launch distance at
or beyond 12 miles with a speed of not less than 8 knots in seas with 1-foot
significant wave height and must be able to operate in seas up to 3-foot
significant wave height.
The vehicle must be able to maneuver with the mechanized task force for
sustained operations ashore in all types of terrain. The vehicles road and crosscountry speed as well as its range should be greater than or equal to the M-1A1.
The vehicles protection characteristics should be able to protect against direct
and indirect fire and mines and improvised explosive device (IED) threats.
The vehicle should be able to accommodate command and control (C2) systems
that permit it to operate both at sea and on land. The vehicle, at a minimum,
should have a stabilized machine gun in order to engage enemy infantry and light
vehicles.
MPC6
The Marine Corps 2011 Request for Information (RFI)7 to industry provided an overview of the
operational requirements for the MPC. These requirements included the following:
The vehicle must accommodate nine Marines and two crew members and have a
robust tactical swim capability (shore-to-shore [not designed to embark from an
amphibious ship]) and be capable of operating at 6 knots in a fully developed
sea.8
The vehicle must be able to operate on land with M-1A1s in mechanized task
forces across the Marine Corps mission profile.
The vehicle shall provide protection for the occupants from the blasts, fragments,
and incapacitating effects of attack from kinetic threats, indirect fire, and
improvised explosive devices and mines.
The vehicle shall be capable of firing existing Marine anti-structure and antiarmor missiles and should be able to accommodate existing command and
control (C2) systems.
(...continued)
information, or capabilities for planning purposes when the Government does not presently intend to issue a
solicitation. [FAR 15.202(e)].
6
Unless otherwise noted, information in this section is taken from Annex A: Marine Personnel Carrier (MPC) Family
of Vehicles (FOV) Requirements Set to the Marine Personnel Carrier Request for Information (RFI), February 17,
2011.
7
The Federal Acquisition Regulation defines an RFI as a document used to obtain price, delivery, other market
information, or capabilities for planning purposes when the Government does not presently intend to issue a
solicitation. [FAR 15.202(e)].
8
Annex A: Marine Personnel Carrier (MPC) Family of Vehicles (FOV) Requirements Set to the Marine Personnel
Carrier Request for Information (RFI), February 17, 2011.
Marine Corps Amphibious Combat Vehicle (ACV) and Marine Personnel Carrier (MPC
In April 2012, the Marine Corps published the results of an Amphibious Capabilities Working
Group study on naval amphibious capability. The study, Naval Amphibious Capability in the 21st
Century: Strategic Opportunity and a Vision for Change, contends the United States is a maritime
nation with critical maritime interests, noting 90% of global commerce that travels by sea is most
vulnerable where sea meets land in the littorals.13 The study further finds for a maritime nation
with global interests, a minimal two brigade amphibious force represents a sound investment in
ensuring access for the rest of the joint force.14 While the study did not explicitly call for the
9
Tony Perry and Julian E. Barnes, U.S. Rethinks a Marine Corps Specialty: Storming Beaches, Los Angeles Times,
June 21, 2010.
10
Ibid.
11
Information in this section was taken from Gaining and Maintaining Access: An Army-Marine Corps Concept,
authored by the United States Armys Army Capabilities Integration Center and the U.S. Marine Corps Combat
Development Command, March 2012.
12
Ibid., pp. 9-10.
13
Information in this section was taken from Naval Amphibious Capability in the 21 st Century: Strategic Opportunity
and a Vision for Change, a report of the Amphibious Capabilities Working Group, April 27, 2012.
14
Ibid., p. 12.
Marine Corps Amphibious Combat Vehicle (ACV) and Marine Personnel Carrier (MPC
development of the ACV or MPCthe study recommendations are characterized as resourceinformed, program-neutralthe ACV and MPC are used in the study for evaluating the ability to
project power ashore. While large-scale, World War II-type amphibious operations might no
longer be the norm, the study suggests there are other roles for the ACV and MPC. Noting that
emerging battlefield capabilities could mean that small teams might now have the ability to
generate effects once associated with larger forces, the Marines propose that company landing
teams (CLTs) might now be a more appropriately sized force for most amphibious operations.15
CLTs are viewed as being small enough to be inserted in a single wave but large enough to
provide a capable force immediately. Another alternative to large scale amphibious operations are
small-scale amphibious raids described as an historical forte of the Marine Corps.16 These raid
forces go ashore only for the duration of the operation and then return to the sea. These raids
could be useful in denying terrorist sanctuary, securing potential weapons of mass destruction
(WMD) sites, destroying pirate safe havens, or destroying threat capabilities in port.17 In this
sense, Naval Amphibious Capability in the 21st Century: Strategic Opportunity and a Vision for
Change might be viewed as redefining thinking about the role of amphibious operations and
making an argument for the need for the ACV and MPC.
15
Ibid., p. 48.
Ibid., p. 49.
17
Ibid.
18
Department of the Navy, Headquarters U.S. Marine Corps, Expeditionary Force 21 - Forward and Ready: Now and
in the Future, March 4, 2014.
16
Marine Corps Amphibious Combat Vehicle (ACV) and Marine Personnel Carrier (MPC
- Are deployable, employable and sustainable given the power projection means
available.
- Operate with reduced signature to multiple penetration points.
- In coordination with the Navy, employ low-signature landing craft and boats with
increased range and speed, as well as the ability to penetrate an unimproved coastline.
- Provide the means to conduct surface maneuver from amphibious ships beyond 65 nm
offshore.
- Provide the capability to maneuver through the complex terrain of the littorals.
- Provide a mechanism to identify, bypass, and if required breach shore-laid obstacle
belts (explosive and non-explosive) to secure entry points.
- Provide maneuver options to extend operations within constraints of fuel resupply
resources.
- Increase ability to work with space assets and develop capabilities within the cyber
realm.19
Marine leadership has emphasized the need for high-speed connectorssurface and air vehicles
that can transport Marines, vehicles, and equipment from ships to shoreto accomplish these
goals. Instead of confronting an enemy head on, Marine leadership envisions using high-speed
connectors and associated vehicles such as the MPC to side step the full force of an enemy,
instead penetrating its seam.20 This concept of finding the seams is viewed as necessary to
avoid confronting a growing array of anti-access technologies and weapon systems available to
both hostile nations and non-state actors that could pose a significant threat to connectors
associated with Marine amphibious operations.
Marine Corps Amphibious Combat Vehicle (ACV) and Marine Personnel Carrier (MPC
Program Information
2013 Decision to Shelve the MPC
As previously noted, in June 2013, citing budgetary pressures, the Marines reportedly put the
MPC program on ice and suggested it might not be resurrected for about 10 years.22 At the time
of the decision, the Marines acquisition priorities were refocused to the ACV as well as the Joint
Light Tactical Vehicle (JLTV).23 While the Marines refocused budgetary resources to the ACV,
difficulties in developing an affordable high water speed capability for the ACV continued to
confront Marine leadership.24
22
Lee Hudson, Marines Put Marine Personnel Carrier on Shelf Due to Budget Constraints, InsideDefense.com, June
14, 2013.
23
For information on the JLTV, see CRS Report RS22942, Joint Light Tactical Vehicle (JLTV): Background and
Issues for Congress, by Andrew Feickert
24
Christopher J. Castelli, General: Marine Corps Could Shelve Development of High-Speed ACV,
InsideDefense.com, October 25, 2013 and Jason Sherman, Marine Corps Dials back ACV, Capability, Defers High
Water Speed Plans, InsideDefense.com, March 25, 2014.
25
Information in this section is taken from Department of Defense Fiscal Year (FY) 2015 Budget Estimates, Navy,
Justification Book, Volume 2, Research, Development, Test & Evaluation, Navy, Budget Activity 4, March 2014, pp.
417-421, and Lee Hudson, Marine Corps Drastically Shifts Ground Vehicle Modernization Strategy,
InsideDefense.com, March 14, 2014.
26
Lee Hudson, Marines Release Amphib Vehicle RFI, Seek Accelerated Schedule, InsideDefense.com, April 25,
2014.
Marine Corps Amphibious Combat Vehicle (ACV) and Marine Personnel Carrier (MPC
The RFI includes a requirement for industry to deliver 16 prototype vehicles nine months after
contract award in April 2016 at a rate of four vehicles per month.28 The Marines estimate ACV
Increment 1.1 will cost about $5 million to $6 million per vehicle, about $10 million less than
what the previous ACV version was expected to cost.29
Ibid.
Ibid.
29
Lee Hudson, Next-Generation Amphibious Vehicle Estimated to Cost $5-$6M Per Copy, InsideDefense.com, June
27, 2014.
30
Information in this section is taken from Megan Eckstein, Marines Expect ACV RFP in Spring; Will Choose 2
Winners for Prototype Production, Testing, Defense Daily, September 29, 2014, and Lee Hudson, Marines Release
Next-Gen Amphibious Vehicle Draft Request for Proposal, InsideDefense.com, November 6, 2014.
31
Megan Eckstein, Marines Expect ACV RFP in Spring; Will Choose 2 Winners for Prototype Production, Testing,
Defense Daily, September 29, 2014.
32
Information in this section is taken from Joe Gould, Marine Amphibious Vehicle RFP Due in March, Defense
News, February 16, 2015.
33
Ibid.
28
Marine Corps Amphibious Combat Vehicle (ACV) and Marine Personnel Carrier (MPC
Budget Activity
FY2016 Budget Request35
The FY2015 budget request for the ACV was $219.1 million in RDT&E funding. Program
activities planned for FY2016 included ACV 1.1 activities including Milestone B decision, and
award of an EMD contract as well as continuing studies/technology development to advance
high-water speed capability.
34
Dan Parsons, Marine Corps Awards BAE, SAIC $225 Million Amphibious Combat Vehicle Contracts, Defense
Daily, November 25, 2015; Lee Hudson, BAE and SAIC Both Win Contracts for USMC Next-Gen Amphib Vehicle,
InsideDefense.com, November 24, 2015; Jen Hudson, BAE, SAIC Named as Finalists in Marines ACV Competition,
Defense News, November 24, 2015.
35
Office of the Undersecretary of Defense (Comptroller)/Chief Financial Officer, United States Department of Defense
Fiscal Year 2016 Budget Request, Program Acquisition Cost by Weapon System, February 2015, pp. 3-9.
Marine Corps Amphibious Combat Vehicle (ACV) and Marine Personnel Carrier (MPC
H.R. 1735, National Defense Authorization Act for Fiscal Year 2016
Funding36
The House authorized the FY2016 presidential budget request for ACV 1.1 RDT&E funding.
H.Rept. 114-102, Report of the Committee on Armed Services House of Representatives on H.R. 1735, National
Defense Authorization Act for Fiscal Year 2016, May 5, 2015, p. 463.
37
S.Rept. 114-49, Report to Accompany S. 1376, National Defense Authorization Act for Fiscal Year 2016, May 19,
2015, p. 405.
38
H.Rept. 114-139, Report of the Committee on Appropriations, Department of Defense Appropriations Bill, 2016,
June 5, 2015, pp. 227 & 235.
39
S.Rept. 114-63, Report of the Committee on Appropriations, Department of Defense Appropriations Bill, 2016, June
11, 2015, p. 159.
40
Conference Report to Accompany H.R. 1735, National Defense Authorization Act for FY 2016, Sept 22, 2015, p
535.
10