Nothing Special   »   [go: up one dir, main page]

Slfe DPR

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 5

GSF - DAILY PROGRESS REPORT

Client SLFE Progress Date 15-Nov-20


Job No. FAB/20/36 Day Sunday
Project Name Upgrade Ethane Facility at Juaymah NGL Fraction Plant Shift A
Lost Time Accidents Today Nil To Date Nil Tool Box Talk Today
HSE STATUS:
Near Miss Incident Today 0 To Date 0 Working Hours: 8 Hrs
DAY'S PROGRESS
Shop Activity
SLUDGE COLLECTION DRUM WATER DEGASSING VESSEL Total
Activities Unit % %
Todays Total Total Todays Total Total Total
Scope Completio Completio % Completion
Achieved Achieved Scope Achieved Achieved Scope Achieved
n n
Engineering % 10.0 0.0 5.0 50.0 10.0 0.0 5.0 50.0 20.0 10.0 50.0

Quality % 10.0 0.0 5.0 50.0 10.0 0.0 5.0 50.0 20.0 10.0 50.0

Procurement % 20.0 0.0 10.0 50.0 20.0 0.0 10.0 50.0 40.0 20.0 50.0

Fabrication % 60.0 0.0 0.0 0.0 60.0 0.0 0.0 0.0 120.0 0.0 0.0

Total % 100.0 0.0 20.0 20.0 100.0 0.00 20.0 20.0 0.0 0.0 0.0 #DIV/0! 0.0 0.0 0.0 #DIV/0! 200.0 40.0 20.0

Remarks& Concerns: Procurement status:


1. UT Technician Revised procedure approval pending -SLFE 1. Plate material received
2. Dishend Procedure approval Pending - SLFE 2. Nozzle material PO placed
3. CP & Internal details not received - AIFC & NOV 3. Welding electrodes, store consumables PO placed, payment balance
4. NMR-601 approval pending - GSCC/SLFE
5. SVL approval pending - SLFE

Manpower / Equipment Status


Direct Manpower Indirect Manpower Equipment
Crafts Present Crafts Present Item Present Remarks
Mech Foreman Fabshop Manager Bandsaw cutting Radial drilling machine breakdown
Vessel Fabricator Planning Engineer CNC Plasma cutting Rolling machine limit switch problem
Fitter Production Engineer Rolling Machine Pipe bevelling machine program error
CNC operator Mechanical supervisor SAW column & Boom SAW tractor sent for services
Rolling operator Welding Supervisor SAW Tractor
Machinist Material controller Welding Rectifier/HF
Forklift operator Storekeeper Radial Drilling
Electrode controller QC Manager CNC Pipe Bevelling
Helper Fitup inspector Compressor
Welding foreman Welding inspector Diesel Generator
SAW Welder NDT cordinator Forklift
6G welder Doc controller Mobile Crane
FCAW welder Engineering Manager Trailer
Multi welder Design engineer - Mech/Struct Pug Cutting machine
IDLE 27 Draftsman Magnetic Drilling machine
Admin Blasting & Painting Pot
Safety Officer
IDLE
TOTAL 27 TOTAL 0 TOTAL 0 TOTAL 0

PREPARED BY Reviewed by
Planning/Production Engineer Fabrication Manager
GSF - DAILY PROGRESS REPORT
Client SLFE Progress Date 14-Nov-20
Job No. FAB/20/36 Day Saturday
Project Name Upgrade Ethane Facility at Juaymah NGL Fraction Plant Shift A
Lost Time Accidents Today Nil To Date Nil Tool Box Talk Today
HSE STATUS:
Near Miss Incident Today 0 To Date 0 Working Hours: 8 Hrs
DAY'S PROGRESS
Shop Activity
SLUDGE COLLECTION DRUM WATER DEGASSING VESSEL Total
Activities Unit % %
Todays Total Total Todays Total Total Total
Scope Completio Completio % Completion
Achieved Achieved Scope Achieved Achieved Scope Achieved
n n
Engineering % 10.0 0.0 5.0 50.0 10.0 0.0 5.0 50.0 20.0 10.0 50.0

Quality % 10.0 0.0 5.0 50.0 10.0 0.0 5.0 50.0 20.0 10.0 50.0

Procurement % 20.0 0.0 10.0 50.0 20.0 0.0 10.0 50.0 40.0 20.0 50.0

Fabrication % 60.0 0.0 0.0 0.0 60.0 0.0 0.0 0.0 120.0 0.0 0.0

Total % 100.0 0.0 20.0 20.0 100.0 0.00 20.0 20.0 0.0 0.0 0.0 #DIV/0! 0.0 0.0 0.0 #DIV/0! 200.0 40.0 20.0

Remarks& Concerns: Procurement status:


1. UT Technician Revised procedure approval pending -SLFE 1. Plate material received
2. Dishend Procedure approval Pending - SLFE 2. Nozzle material PO placed
3. CP & Internal details not received - AIFC & NOV 3. Welding electrodes, store consumables PO placed, payment balance
4. NMR-601 approval pending - GSCC/SLFE
5. SVL approval pending - SLFE

Manpower / Equipment Status


Direct Manpower Indirect Manpower Equipment
Crafts Present Crafts Present Item Present Remarks
Mech Foreman Fabshop Manager Bandsaw cutting Radial drilling machine breakdown
Vessel Fabricator Planning Engineer CNC Plasma cutting Rolling machine limit switch problem
Fitter Production Engineer Rolling Machine Pipe bevelling machine program error
CNC operator Mechanical supervisor SAW column & Boom SAW tractor sent for services
Rolling operator Welding Supervisor SAW Tractor
Machinist Material controller Welding Rectifier/HF
Forklift operator Storekeeper Radial Drilling
Electrode controller QC Manager CNC Pipe Bevelling
Helper Fitup inspector Compressor
Welding foreman Welding inspector Diesel Generator
SAW Welder NDT cordinator Forklift
6G welder Doc controller Mobile Crane
FCAW welder Engineering Manager Trailer
Multi welder Design engineer - Mech/Struct Pug Cutting machine
IDLE 27 Draftsman Magnetic Drilling machine
Admin Blasting & Painting Pot
Safety Officer
IDLE
TOTAL 27 TOTAL 0 TOTAL 0 TOTAL 0

PREPARED BY Reviewed by
Planning/Production Engineer Fabrication Manager
GSF - DAILY PROGRESS REPORT
Client SLFE Progress Date 12-Nov-20
Job No. FAB/20/36 Day Thursday
Project Name Upgrade Ethane Facility at Juaymah NGL Fraction Plant Shift A
Lost Time Accidents Today Nil To Date Nil Tool Box Talk Today
HSE STATUS:
Near Miss Incident Today 0 To Date 0 Working Hours: 8 Hrs
DAY'S PROGRESS
Shop Activity
SLUDGE COLLECTION DRUM WATER DEGASSING VESSEL Total
Activities Unit % %
Todays Total Total Todays Total Total Total
Scope Completio Completio % Completion
Achieved Achieved Scope Achieved Achieved Scope Achieved
n n
Engineering % 10.0 0.0 5.0 50.0 10.0 0.0 5.0 50.0 20.0 10.0 50.0

Quality % 10.0 0.0 5.0 50.0 10.0 0.0 5.0 50.0 20.0 10.0 50.0

Procurement % 20.0 0.0 10.0 50.0 20.0 0.0 10.0 50.0 40.0 20.0 50.0

Fabrication % 60.0 0.0 0.0 0.0 60.0 0.0 0.0 0.0 120.0 0.0 0.0

Total % 100.0 0.0 20.0 20.0 100.0 0.00 20.0 20.0 0.0 0.0 0.0 #DIV/0! 0.0 0.0 0.0 #DIV/0! 200.0 40.0 20.0

Remarks& Concerns: Procurement status:


1. UT Technician Revised procedure approval pending -SLFE 1. Plate material received
2. Dishend Procedure approval Pending - SLFE 2. Nozzle material PO placed
3. CP & Internal details not received - AIFC & NOV 3. Welding electrodes, store consumables PO placed, payment balance
4. NMR-601 approval pending - GSCC/SLFE
5. SVL approval pending - SLFE

Manpower / Equipment Status


Direct Manpower Indirect Manpower Equipment
Crafts Present Crafts Present Item Present Remarks
Mech Foreman Fabshop Manager Bandsaw cutting Radial drilling machine breakdown
Vessel Fabricator Planning Engineer CNC Plasma cutting Rolling machine limit switch problem
Fitter Production Engineer Rolling Machine Pipe bevelling machine program error
CNC operator Mechanical supervisor SAW column & Boom SAW tractor sent for services
Rolling operator Welding Supervisor SAW Tractor
Machinist Material controller Welding Rectifier/HF
Forklift operator Storekeeper Radial Drilling
Electrode controller QC Manager CNC Pipe Bevelling
Helper Fitup inspector Compressor
Welding foreman Welding inspector Diesel Generator
SAW Welder NDT cordinator Forklift
6G welder Doc controller Mobile Crane
FCAW welder Engineering Manager Trailer
Multi welder Design engineer - Mech/Struct Pug Cutting machine
IDLE 27 Draftsman Magnetic Drilling machine
Admin Blasting & Painting Pot
Safety Officer
IDLE
TOTAL 27 TOTAL 0 TOTAL 0 TOTAL 0

PREPARED BY Reviewed by
Planning/Production Engineer Fabrication Manager
GSF - DAILY PROGRESS REPORT
Client SLFE Progress Date 11-Nov-20
Job No. FAB/20/36 Day Wednesday
Project Name Upgrade Ethane Facility at Juaymah NGL Fraction Plant Shift A
Lost Time Accidents Today Nil To Date Nil Tool Box Talk Today
HSE STATUS:
Near Miss Incident Today 0 To Date 0 Working Hours: 8 Hrs
DAY'S PROGRESS
Shop Activity
SLUDGE COLLECTION DRUM WATER DEGASSING VESSEL Total
Activities Unit % %
Todays Total Total Todays Total Total Total
Scope Completio Completio % Completion
Achieved Achieved Scope Achieved Achieved Scope Achieved
n n
Engineering % 10.0 0.0 5.0 50.0 10.0 0.0 5.0 50.0 20.0 10.0 50.0

Quality % 10.0 0.0 5.0 50.0 10.0 0.0 5.0 50.0 20.0 10.0 50.0

Procurement % 20.0 0.0 10.0 50.0 20.0 0.0 10.0 50.0 40.0 20.0 50.0

Fabrication % 60.0 0.0 0.0 0.0 60.0 0.0 0.0 0.0 120.0 0.0 0.0

Total % 100.0 0.0 20.0 20.0 100.0 0.00 20.0 20.0 0.0 0.0 0.0 #DIV/0! 0.0 0.0 0.0 #DIV/0! 200.0 40.0 20.0

Remarks& Concerns: Procurement status:


1. UT Technician procedure approval pending - GSCC/SLFE 1. Plate material received
2. Dishend Procedure approval Pending - SLFE 2. Nozzle material PO placed
3. CP & Internal details not received - AIFC & NOV 3. Welding electrodes, store consumables PO placed, receiving pending
4. NMR-601 approval pending - GSCC/SLFE
5. SVL approval pending - SLFE

Manpower / Equipment Status


Direct Manpower Indirect Manpower Equipment
Crafts Present Crafts Present Item Present Remarks
Mech Foreman Fabshop Manager 1 Bandsaw cutting Radial drilling machine breakdown
Vessel Fabricator Planning Engineer CNC Plasma cutting Rolling machine limit switch problem
Fitter Production Engineer Rolling Machine Pipe bevelling machine program error
CNC operator Mechanical supervisor SAW column & Boom SAW tractor sent for services
Rolling operator Welding Supervisor SAW Tractor
Machinist Material controller Welding Rectifier/HF
Forklift operator Storekeeper Radial Drilling
Electrode controller QC Manager CNC Pipe Bevelling
Helper Fitup inspector Compressor
Welding foreman Welding inspector Diesel Generator
SAW Welder NDT cordinator Forklift
6G welder Doc controller 1 Mobile Crane
FCAW welder Engineering Manager Trailer
Multi welder Design engineer - Mech/Struct Pug Cutting machine
IDLE 27 Draftsman Magnetic Drilling machine
Admin Blasting & Painting Pot
Safety Officer
IDLE
TOTAL 27 TOTAL 2 TOTAL 0 TOTAL 0

PREPARED BY Reviewed by
Planning/Production Engineer Fabrication Manager
GSF - DAILY PROGRESS REPORT
Client SLFE Progress Date 10-Nov-20
Job No. FAB/20/36 Day Tuesday
Project Name Upgrade Ethane Facility at Juaymah NGL Fraction Plant Shift A
Lost Time Accidents Today Nil To Date Nil Tool Box Talk Today
HSE STATUS:
Near Miss Incident Today 0 To Date 0 Working Hours: 8 Hrs
DAY'S PROGRESS
Shop Activity
SLUDGE COLLECTION DRUM WATER DEGASSING VESSEL Total
Activities Unit % %
Todays Total Total Todays Total Total Total
Scope Completio Completio % Completion
Achieved Achieved Scope Achieved Achieved Scope Achieved
n n
Engineering % 10.0 5.0 50.0 10.0 5.0 50.0 20.0 10.0 50.0

Quality % 10.0 5.0 50.0 10.0 5.0 50.0 20.0 10.0 50.0

Procurement % 20.0 10.0 50.0 20.0 10.0 50.0 40.0 20.0 50.0

Fabrication % 60.0 0.0 0.0 60.0 0.0 0.0 120.0 0.0 0.0

Total % 100.0 0.0 20.0 20.0 100.0 0.00 20.0 20.0 0.0 0.0 0.0 #DIV/0! 0.0 0.0 0.0 #DIV/0! 200.0 40.0 20.0

Remarks& Concerns: Procurement status:


1. UT Technician procedure approval pending - GSCC/SLFE 1. Plate material received
2. Dishend Procedure approval Pending - SLFE 2. Nozzle material PO placed
3. CP & Internal details not received - AIFC & NOV 3. Welding electrodes, store consumables PO placed, receiving pending
4. NMR-601 approval pending - GSCC/SLFE
5. SVL approval pending - SLFE

Manpower / Equipment Status


Direct Manpower Indirect Manpower Equipment
Crafts Present Crafts Present Item Present Remarks
Mech Foreman Fabshop Manager 1 Bandsaw cutting Radial drilling machine breakdown
Vessel Fabricator Planning Engineer CNC Plasma cutting Rolling machine limit switch problem
Fitter Production Engineer Rolling Machine Pipe bevelling machine program error
CNC operator Mechanical supervisor SAW column & Boom SAW tractor sent for services
Rolling operator Welding Supervisor SAW Tractor
Machinist Material controller Welding Rectifier/HF
Forklift operator Storekeeper Radial Drilling
Electrode controller QC Manager CNC Pipe Bevelling
Helper Fitup inspector Compressor
Welding foreman Welding inspector Diesel Generator
SAW Welder NDT cordinator Forklift
6G welder Doc controller 1 Mobile Crane
FCAW welder Engineering Manager Trailer
Multi welder Design engineer - Mech/Struct Pug Cutting machine
IDLE 27 Draftsman Magnetic Drilling machine
Admin 1 Blasting & Painting Pot
Safety Officer
IDLE
TOTAL 27 TOTAL 3 TOTAL 0 TOTAL 0

PREPARED BY Reviewed by
Planning/Production Engineer Fabrication Manager

You might also like