Nothing Special   »   [go: up one dir, main page]

Primavera Project Planner-Updated Programme

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5
At a glance
Powered by AI
The document outlines the schedule for the construction of The Corner Tower at Business Bay project. It provides details on activities, durations, start and finish dates across multiple pages.

The overall project schedule spans from April 2008 to March 2013. It provides 'Baseline Early Start' and 'Baseline Early Finish' dates to track progress against the original plan.

Some of the major milestones mentioned are Foundation Completion planned for June 2010 and Sub-Structure Completion planned for October 2010.

Activity

ID

Activity
Description

Orig
Dur

Rem
Dur

%
Comp

Baseline
Early
Start

Baseline
Early
Finish

Update
Early
Start

Update
Early
Finish

08APR10A

31OCT12

MAR

Total Variance
Float Early Finish

APR
13

21

22

23

24

25

26

27

28

29

30

31

10

11

12

13

14

15

16

The Corner Tower at Business Bay


General

PL010

Prelimns

789

488

38 08APR10

GEN010

Commencement Date

100 08APR10

GEN020

Design NOC's

100 08APR10

GEN040

Mobilisation

26

GEN030

Issuance of Construction Drawings by Engineer

07NOV12

6 Prelimns

08APR10A

14APR10

08APR10A 14APR10A

100 08APR10

08MAY10

08APR10A 08MAY10A

100 12APR10

18APR10

12APR10A 18APR10A

14

100 08APR10

24APR10

10APR10A 15APR10A

-66

Building Permit

GEN050

Building Permit - by Engineer

Key Milestones

KM010

Foundation Completion

100

30JUN10

18SEP10A

KM020

Sub - Structure Completion

16OCT10

27MAR11

-98

-133

24MAR11*

27MAR11*

49

-2

Sub - Structure Completion

Provisional Sum Items

PS010

Lifts - to be finalized by client

Lifts - to be finalized by client

Engineering
Pre-Qualification - Major Subcontractor
Submittal
PQS020

Foundation / Water Tank Waterproofing

100 22APR10

25APR10

22APR10A 25APR10A

PQS010

MEP 1st Fix

100 15APR10

18APR10

18MAY10A 20MAY10A

-28

PQA020

Foundation / Water Tank Waterproofing

18

100 26APR10

16MAY10

13MAY10A 22JUN10A

-32

PQA010

MEP 1st Fix

18

100 19APR10

09MAY10

20MAY10A 01JUN10A

-20

Approval

Start Date
Finish Date
Data Date

08APR10
06MAR13
28MAR11

Early Bar
Target
Progress Bar
Critical Activity

Primavera Systems, Inc.

UP49

The Corner Tower at Business Bay


Clause 14.1 Programme
Updated Programme 2011_03_28
(Two Week Look Ahead programme)

Sheet 1 of 5

Clause 14.1 Programme


Date
18MAR10
26APR10
10MAY10
14JUN10

Revision
Rev 00 (00)
Rev 00 (01)
Rev 00 (02)
Rev 00 (03)

Checked
SB
SB
SB
SB

Approved
MA
MA
MA
MA

17

Activity
ID

Activity
Description

Orig
Dur

Rem
Dur

%
Comp

Baseline
Early
Start

Baseline
Early
Finish

Update
Early
Start

Update
Early
Finish

MAR

Total Variance
Float Early Finish

APR
13

21

22

23

24

25

26

27

28

29

30

31

Material Submittals
Structure
SMS060

Anti-termite treatment

100 22APR10

25APR10

18MAR10A 22MAR10A

29

SMS020

Reinforcement

100 22APR10

25APR10

20MAR10A 22MAR10A

29

SMS010

Cement

100 22APR10

25APR10

07APR10A 10APR10A

13

SMS040

Concrete

100 28APR10

01MAY10

10APR10A 12APR10A

16

SMS080

Water Stopper

100 22APR10

25APR10

10APR10A 11APR10A

12

SMS070

Granular fill

100 22APR10

25APR10

19APR10A 22APR10A

SMS090

Foundation Water Proofing

100 22APR10

25APR10

22APR10A 25APR10A

SMS100

MEP 1st Fix

100 15APR10

18APR10

07JUN10A 10JUN10A

-46

SMS050

Expansion Joint

0 28APR10

01MAY10

28MAR11

30MAR11

141

-278

18

18

0 03APR11

23APR11

05APR11

25APR11

49

-2

Expansion Joint

Provisional Sums Items


Provisional Sums
PMS220

Lifts Materials

Lifts Materials

Material Approvals
Structure
SMA020

Reinforcement

18

100 26APR10

16MAY10

23MAR10A 16APR10A

26

SMA060

Anti-termite treatment

18

100 26APR10

16MAY10

23MAR10A 31MAR10A

39

SMA010

Cement

18

100 26APR10

16MAY10

10APR10A 05MAY10A

SMA040

Concrete

18

100 02MAY10

22MAY10

13APR10A 27APR10A

21

SMA070

Granular fill

18

100 26APR10

16MAY10

22APR10A 10MAY10A

SMA090

Foundation Water Proofing

18

100 26APR10

16MAY10

26APR10A 20JUN10A

-30

SMA080

Water Stopper

18

100 26APR10

16MAY10

27APR10A 04MAY10A

10

SMA100

MEP 1st Fix

18

100 19APR10

09MAY10

10JUN10A 16JUN10A

-33

SMA050

Expansion Joint

18

18

0 02MAY10

22MAY10

31MAR11

20APR11

141

Expansion Joint

-278

Shop Drawing Submittals


Structure
SSDSU005

S/D - Raft

100 28APR10

08MAY10

19APR10A 07JUN10A

-26

SSDSU010

S/D Submittals - B3 to GF

21

100 09MAY10

01JUN10

24MAY10A 01SEP10A

-79

SSDSU020

S/D Submittals - P1 to P3

42

100 02JUN10

20JUL10

19OCT10A 21DEC10A

-126

SSDSU030

S/D Submittals - L1 to L18 and Roof

78

70

10 21JUL10

21OCT10

11JAN11A

16JUN11

-71

-198

26

26

0 26MAR11

24APR11

28MAR11

26APR11

60

-2

18

100 09MAY10

29MAY10

20APR10A 13JUL10A

Provisional Sums Items


PSDSU220

Lifts - S/D Submittals

Shop Drawing Approvals


Structure
SSDAP005

S/D Approvals - Raft

-39

Sheet 2 of 5

Lifts - S/D Submittals

10

11

12

13

14

15

16

17

Activity
ID

Activity
Description

Orig
Dur

Rem
Dur

%
Comp

SSDAP010

S/D Approvals - B2 to GF

21

Baseline
Early
Start
100 30MAY10

Baseline
Early
Finish
22JUN10

Update
Update Total Variance
Early
Early
Float Early Finish
Start
Finish
21
25MAY10A 06SEP10A
-65

SSDAP020

S/D Approvals by Engineer - P1 to P3

42

100 23JUN10

10AUG10

24OCT10A 17JAN11A

SSDAP030

S/D Approvals by Engineer-L1toL18 & Roof

78

70

10 11AUG10

11NOV10

11JAN11A

16JUN11

-71

-180

26

26

0 16APR11

15MAY11

18APR11

17MAY11

60

-2

MAR

APR
13

22

23

24

25

26

27

28

29

30

31

10

11

12

13

14

15

16

17

-130

Provisional Sums Items


PSDAP220

Lifts - S/D Approvals

Lifts - S/D Approvals

Procurement and Delivery


Procurement
Structure
SPR060

Anti-termite treatment

100 29APR10

02MAY10

31MAR10A 03APR10A

25

SPR080

Water Stopper

100 02MAY10

04MAY10

02MAY10A 04MAY10A

SPR010

Cement

100 02MAY10

04MAY10

06MAY10A 08MAY10A

-3

SPR070

Granular fill

100 29APR10

02MAY10

11MAY10A 12MAY10A

-9

SPR090

Foundation Water Proofing

100 17MAY10

19MAY10

12JUN10A 17JUN10A

-25

SPR020

Reinforcement

100 08MAY10

10MAY10

09JUL10A

11JUL10A

-53

SPR040

Concrete

100 08MAY10

10MAY10

29JUL10A 01AUG10A

-71

SPR100

MEP 1st Fix

100 10MAY10

12MAY10

23AUG10A 25AUG10A

-90

SPR050

Expansion Joint

0 08MAY10

10MAY10

SDE060

Anti-termite treatment

100 04MAY10

10MAY10

04APR10A 08APR10A

27

SDE080

Water Stopper

100 08MAY10

13MAY10

04MAY10A 07MAY10A

SDE010

Cement

399

41 08MAY10

23JUL12

08MAY10A

SDE070

Granular fill

100 03MAY10

09MAY10

13MAY10A 18MAY10A

-8

SDE090

Foundation Water Proofing

18

100 20MAY10

09JUN10

18JUN10A 23AUG10A

-64

SDE020

Reinforcement

12

100 13MAY10

26MAY10

15JUL10A

01SEP10A

-84

SDE040

Concrete

12

100 13MAY10

26MAY10

31JUL10A

17SEP10A

-95

SDE100

MEP 1st Fix

24

100 13MAY10

09JUN10

24AUG10A 01SEP10A

-72

SDE050

Expansion Joint

12

12

0 13MAY10

26MAY10

12APR11

25APR11

06APR11

09APR11

141

-278

Expansion Joint

Delivery
Structure

675

16JUL12

95

141

6 Cement

-278

Construction
Tower Crane
TOW005

Foundation for Tower Crane

26

100 01JUL10

31JUL10

21JUL10A

18SEP10A

-40

TOW010

Installation Of Tower Crane

18

100 01AUG10

21AUG10

07OCT10A 26OCT10A

-55

100 09MAY10

15MAY10

20APR10A 27APR10A

15

Substructure
Foundation
SFNEX10

Excavation For Lift Pit

Sheet 3 of 5

Expansion Joint

Activity
ID

Activity
Description

Orig
Dur

Rem
Dur

%
Comp

SFNWP20

Blinding

Baseline
Early
Start
100 13MAY10

Baseline
Early
Finish
20MAY10

Update
Update Total Variance
Early
Early
Float Early Finish
Start
Finish
21
10JUN10A 02AUG10A
-63

SFNEX30

Foundation Water Proofing

100 22MAY10

31MAY10

05JUL10A 29AUG10A

-77

SFNEX40

Raft Foundation

26

100 01JUN10

30JUN10

17JUL10A

18SEP10A

-66

MAR

APR
13

22

23

24

25

26

27

28

29

30

31

Basement 3
SB3CL10

Columns and Walls

12

100 01JUL10

14JUL10

20SEP10A 27OCT10A

-88

SB3CL30

Waterproofing for Walls

100 01JUL10

11JUL10

20SEP10A 27OCT10A

-91

SB3C05

Core Wall

12

100 01JUL10

14JUL10

26SEP10A 25OCT10A

-86

SB3WT10

Watertanks

12

100 01JUL10

14JUL10

26SEP10A 08NOV10A

-98

SB3CL20

Retaining Wall

12

100 05JUL10

18JUL10

30SEP10A 08NOV10A

-95

SB3RM10

Ramps

100 05AUG10

11AUG10

22NOV10A 06DEC10A

-95

SB3ST10

Staircase (ST1,ST2,ST3 & St4)

100 05AUG10

11AUG10

22NOV10A 24JAN11A

-135

Slab - Basement 2

18

100 15JUL10

04AUG10

07OCT10A 18NOV10A

-87

SB2C05

Core Wall

12

100 05AUG10

18AUG10

04NOV10A 10DEC10A

-91

SB2CL10

Columns and Walls

12

100 05AUG10

18AUG10

04NOV10A 10DEC10A

-91

SB2CL30

Waterproofing for Walls

100 05AUG10

15AUG10

09NOV10A 14DEC10A

-98

SB2CL20

Retaining Wall

12

100 09AUG10

22AUG10

12NOV10A 21DEC10A

-98

SB2WT10

Watertanks

12

100 05AUG10

18AUG10

15NOV10A 09DEC10A

-91

SB2ST10

Staircase (ST1,ST2,ST3 & St4)

80 09SEP10

18SEP10

25JAN11A

28MAR11

SB2RM10

Ramps

100 09SEP10

18SEP10

25JAN11A

30JAN11A

-110

Slab - Basement 1

18

100 19AUG10

08SEP10

18NOV10A 27DEC10A

-88

SB1C05

Core Wall

12

100 09SEP10

25SEP10

11DEC10A 28DEC10A

-77

SB1CL10

Columns and Walls

12

100 09SEP10

25SEP10

11DEC10A 03JAN11A

-81

SB1CL30

Waterproofing for Walls

100 09SEP10

21SEP10

11DEC10A 16JAN11A

-95

SB1CL20

Retaining Wall

12

100 15SEP10

28SEP10

15DEC10A 22JAN11A

-94

SB1ST10

Staircase (ST1,ST2,ST3 & St4)

80 17OCT10

23OCT10

01FEB11A

28MAR11

SB1RM10

Ramps

100 17OCT10

23OCT10

01FEB11A

07FEB11A

-87

Slab - Ground Floor

18

100 26SEP10

16OCT10

16DEC10A 28JAN11A

-84

SGFC05

Core Wall

100 17OCT10

25OCT10

12JAN11A 01MAR11A

-103

SGFCL10

Columns

100 17OCT10

25OCT10

12JAN11A 01MAR11A

-103

SGFRM10

Ramps

0 09NOV10

21NOV10

07FEB11A

07APR11

-98

-114

SGFST10

Staircase (ST1,ST2,ST3 & St4)

20 09NOV10

15NOV10

21MAR11A

03APR11

-95

-113

Basement 2
SB3PSL10

-98

-158

Staircase (ST1,ST2,ST3 & St4)

Basement 1
SB2PSL10

-98

-128

Staircase (ST1,ST2,ST3 & St4)

Superstructure
Ground Floor
SB1PSL10

Sheet 4 of 5

Ramps
Staircase (ST1,ST2,ST3 & St4)

10

11

12

13

14

15

16

17

Activity
ID

Activity
Description

Orig
Dur

Rem
Dur

%
Comp

Baseline
Early
Start

Baseline
Early
Finish

Update
Early
Start

Update
Early
Finish

MAR

Total Variance
Float Early Finish

APR
13

21

22

23

24

25

26

27

28

29

30

31

10

11

12

13

Podium 1
Slab - Podium 1

SGFPSL10

Slab - Podium 1

12

95 26OCT10

08NOV10

22JAN11A

28MAR11

-98

-114

SP1RM10

Ramps

0 08DEC10

18DEC10

07FEB11A

19APR11

-92

-103

SP1CL10

Columns

80 09NOV10

21NOV10

09FEB11A

30MAR11

-92

-107

Columns

SP1CO5

Core Wall

80 09NOV10

21NOV10

15FEB11A

30MAR11

-92

-107

Core Wall

SP1ST10

Staircase (ST1,ST2,ST3 & St4)

0 08DEC10

14DEC10

10APR11

16APR11

-98

-103

Slab - Podium 2

12

80 22NOV10

06DEC10

22FEB11A

09APR11

-98

-103

SP2CL10

Columns

80 08DEC10

18DEC10

05MAR11A

11APR11

-94

-96

SP2CO5

Core Wall

100 08DEC10

18DEC10

14MAR11A 20MAR11A

Slab - Podium 3

12

10

15 19DEC10

02JAN11

22MAR11A

27APR11

-98

-98

60 23APR12

01MAY12

01MAR11A

21AUG12

-90

-93

40 02MAY12

10MAY12

04MAR11A

27AUG12

-81

-90

20 12MAY12

20MAY12

06MAR11A

03SEP12

-81

-88

Staircase (ST1,ST2,ST3 & St4)

Podium 2
SP1PSL10

-77 Core Wall

Podium 3
SP2PSL10

Finishes Post Employer's Decison


Basement 3
Block Work
B3FBW010

Block Work

Basement 2
Block Work
B2FBW010

Block Work

Basement 1
Block Work
B1FBW010

Block Work

Sheet 5 of 5

Slab - Podium 2
Columns

14

15

16

17

You might also like