Nothing Special   »   [go: up one dir, main page]

Al Ihsaa - Educational Complex in Al Jubail - Update 11-06-2020

Download as pdf or txt
Download as pdf or txt
You are on page 1of 19

UPDATED TIME SCHEDULE Al Ihsaa- Educational Complex in Al Jubail D.

D 11-Jun-20

Activity ID Activity Name Original Duration BL1 Start BL1 Finish Start Finish Schedule % Performance %Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Complete Complete
A A A A A A A A A A A A A A
Al Ihsaa- Educational Complex in Al Jubail - 11-06-2020 437 02-Mar-20 04-Aug-21 02-Mar-20 A 04-Aug-21 2.93% 0.98% 04-Aug-21, Al Ihsaa- Educational Complex in Al Jubail - 11-06-2020

Milestones 437 02-Mar-20 04-Aug-21 02-Mar-20 A 04-Aug-21 0% 0% 04-Aug-21, Milestones

General 437 02-Mar-20 04-Aug-21 02-Mar-20 A 04-Aug-21 0% 0% 04-Aug-21, General


A17860 Project Start 0 02-Mar-20 02-Mar-20 A 100% 100% Project Start, 02-Mar-20 A
A17870 Project Finish 0 04-Aug-21 04-Aug-21 0% 0% Project Finish,
Construction 14 21-Jun-21 06-Jul-21 21-Jun-21 06-Jul-21 0% 0% 06-Jul-21, Construction
A17900 Building B Finish 0 21-Jun-21 21-Jun-21 0% 0% Building B Finish,
A17890 Building A Finish 0 21-Jun-21 21-Jun-21 0% 0% Building A Finish,
A17910 Building C Finish 0 06-Jul-21 06-Jul-21 0% 0% Building C Finish,
Submission & Approvals 347 11-Jun-20 27-Jul-21 11-Jun-20 27-Jul-21 0% 0% 27-Jul-21, Submission & Approvals

General 347 11-Jun-20 27-Jul-21 11-Jun-20 27-Jul-21 0% 0% 27-Jul-21, General


A21950 Civil Defense Shop Drawing Submission 7 11-Jun-20 18-Jun-20 11-Jun-20 18-Jun-20 100% 0% Civil Defense Shop Drawing Submission
A21940 Safety Plan Submission 7 11-Jun-20 18-Jun-20 11-Jun-20 18-Jun-20 100% 0% Safety Plan Submission
A21930 Qulaity Plan Submission 7 11-Jun-20 18-Jun-20 11-Jun-20 18-Jun-20 100% 0% Qulaity Plan Submission
A21960 Civil Defense Approval 13 20-Jun-20 04-Jul-20 20-Jun-20 04-Jul-20 100% 0% Civil Defense Approval
A21990 Safety Plan Approval 14 20-Jun-20 05-Jul-20 20-Jun-20 05-Jul-20 100% 0% Safety Plan Approval
A21980 Qulaity Plan Approval 14 20-Jun-20 05-Jul-20 20-Jun-20 05-Jul-20 100% 0% Qulaity Plan Approval
A21970 As Built Drawings Submission 5 22-Jul-21 27-Jul-21 22-Jul-21 27-Jul-21 0% 0% As Built Drawings Submission
Engineering 45 11-Jun-20 08-Aug-20 11-Jun-20 08-Aug-20 0% 0% 08-Aug-20, Engineering
Shop Drawings Submittal & Approval 45 11-Jun-20 08-Aug-20 11-Jun-20 08-Aug-20 0% 0% 08-Aug-20, Shop Drawings Submittal & Approval
A21000 Electrical Shop Drawings Submission 15 11-Jun-20 28-Jun-20 11-Jun-20 28-Jun-20 100% 0% Electrical Shop Drawings Submission
A20990 HVAC Shop Drawings Submission 15 11-Jun-20 28-Jun-20 11-Jun-20 28-Jun-20 100% 0% HVAC Shop Drawings Submission
A20980 Plumping Shop Drawings Submission 15 11-Jun-20 28-Jun-20 11-Jun-20 28-Jun-20 100% 0% Plumping Shop Drawings Submission
A20970 Architectural Shop Drawings Submission 15 11-Jun-20 28-Jun-20 11-Jun-20 28-Jun-20 100% 0% Architectural Shop Drawings Submission
A20960 Structural & Civil Shop Drawings Submission 15 11-Jun-20 28-Jun-20 11-Jun-20 28-Jun-20 100% 0% Structural & Civil Shop Drawings Submission
A20950 Electrical Shop Drawings Approval 30 29-Jun-20 08-Aug-20 29-Jun-20 08-Aug-20 100% 0% Electrical Shop Drawings Approval
A20940 HVAC Shop Drawings Approval 30 29-Jun-20 08-Aug-20 29-Jun-20 08-Aug-20 100% 0% HVAC Shop Drawings Approval
A20930 Plumping Shop Drawings Approval 30 29-Jun-20 08-Aug-20 29-Jun-20 08-Aug-20 100% 0% Plumping Shop Drawings Approval
A20920 Architectural Shop Drawings Approval 30 29-Jun-20 08-Aug-20 29-Jun-20 08-Aug-20 100% 0% Architectural Shop Drawings Approval
A20910 Structural & Civil Shop Drawings Approval 30 29-Jun-20 08-Aug-20 29-Jun-20 08-Aug-20 100% 0% Structural & Civil Shop Drawings Approval
Procurement 248 29-Jun-20 20-Apr-21 29-Jun-20 20-Apr-21 0% 0% 20-Apr-21, Procurement

Civil 193 29-Jun-20 15-Feb-21 29-Jun-20 15-Feb-21 0% 0% 15-Feb-21, Civil


Concrete 40 29-Jun-20 19-Aug-20 29-Jun-20 19-Aug-20 0% 0% 19-Aug-20, Concrete
A21020 Vender Approval 14 29-Jun-20 14-Jul-20 29-Jun-20 14-Jul-20 100% 0% Vender Approval
A21030 P.O 5 15-Jul-20 20-Jul-20 15-Jul-20 20-Jul-20 100% 0% P.O
A21040 Material Supplying 21 21-Jul-20 19-Aug-20 21-Jul-20 19-Aug-20 100% 0% Material Supplying
Doors 188 29-Jun-20 09-Feb-21 29-Jun-20 09-Feb-21 0% 0% 09-Feb-21, Doors
A21090 Vender Approval 14 29-Jun-20 14-Jul-20 29-Jun-20 14-Jul-20 100% 0% Vender Approval
A21100 Material Approval 9 15-Jul-20 25-Jul-20 15-Jul-20 25-Jul-20 100% 0% Material Approval
A21110 P.O 5 26-Jul-20 30-Jul-20 26-Jul-20 30-Jul-20 100% 0% P.O
A21120 Materials Supplying 160 06-Aug-20 09-Feb-21 06-Aug-20 09-Feb-21 25% 0% Materials Supplying
Windows 188 29-Jun-20 09-Feb-21 29-Jun-20 09-Feb-21 0% 0% 09-Feb-21, Windows
A21370 Vender Approval 14 29-Jun-20 14-Jul-20 29-Jun-20 14-Jul-20 100% 0% Vender Approval
A21380 Material Approval 9 15-Jul-20 25-Jul-20 15-Jul-20 25-Jul-20 100% 0% Material Approval
A21390 P.O 5 26-Jul-20 30-Jul-20 26-Jul-20 30-Jul-20 100% 0% P.O
A21400 Materials Supplying 160 06-Aug-20 09-Feb-21 06-Aug-20 09-Feb-21 25% 0% Materials Supplying
Waterproofing 93 29-Jun-20 21-Oct-20 29-Jun-20 21-Oct-20 0% 0% 21-Oct-20, Waterproofin g
A21130 Vender Approval 14 29-Jun-20 14-Jul-20 29-Jun-20 14-Jul-20 100% 0% Vender Approval
A21140 Material Approval 9 15-Jul-20 25-Jul-20 15-Jul-20 25-Jul-20 100% 0% Material Approval

Actual Level of Effort Remaining Work Milestone Date Revision Checked Approved
Page 1 of 19
Actual Work Critical Remaining Work summary 11-Jun-20 UTS
UPDATED TIME SCHEDULE Al Ihsaa- Educational Complex in Al Jubail D.D 11-Jun-20

Activity ID Activity Name Original Duration BL1 Start BL1 Finish Start Finish Schedule % Performance %Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Complete Complete
A A A A A A A A A A A A A A
A21150 P.O 5 26-Jul-20 30-Jul-20 26-Jul-20 30-Jul-20 100% 0% P.O
A21160 Materials Supplying 65 06-Aug-20 21-Oct-20 06-Aug-20 21-Oct-20 61.54% 0% Materials Supplying
Floor finishing materials 193 29-Jun-20 15-Feb-21 29-Jun-20 15-Feb-21 0% 0% 15-Feb-21, Floor finishing materials
A21170 Vender Approval 14 29-Jun-20 14-Jul-20 29-Jun-20 14-Jul-20 100% 0% Vender Approval
A21180 Material Approval 9 15-Jul-20 25-Jul-20 15-Jul-20 25-Jul-20 100% 0% Material Approval
A21190 P.O 5 26-Jul-20 30-Jul-20 26-Jul-20 30-Jul-20 100% 0% P.O
A21200 Materials Supplying 165 06-Aug-20 15-Feb-21 06-Aug-20 15-Feb-21 24.24% 0% Materials Supplying
Wall finishing materials 193 29-Jun-20 15-Feb-21 29-Jun-20 15-Feb-21 0% 0% 15-Feb-21, Wall finishing materials
A21450 Vender Approval 14 29-Jun-20 14-Jul-20 29-Jun-20 14-Jul-20 100% 0% Vender Approval
A21460 Material Approval 9 15-Jul-20 25-Jul-20 15-Jul-20 25-Jul-20 100% 0% Material Approval
A21470 P.O 5 26-Jul-20 30-Jul-20 26-Jul-20 30-Jul-20 100% 0% P.O
A21480 Materials Supplying 165 06-Aug-20 15-Feb-21 06-Aug-20 15-Feb-21 24.24% 0% Materials Supplying
Ceiling finishing materials 168 29-Jun-20 17-Jan-21 29-Jun-20 17-Jan-21 0% 0% 17-Jan-21, Ceiling finishing materials
A21490 Vender Approval 14 29-Jun-20 14-Jul-20 29-Jun-20 14-Jul-20 100% 0% Vender Approval
A21500 Material Approval 9 15-Jul-20 25-Jul-20 15-Jul-20 25-Jul-20 100% 0% Material Approval
A21510 P.O 5 26-Jul-20 30-Jul-20 26-Jul-20 30-Jul-20 100% 0% P.O
A21520 Materials Supplying 140 06-Aug-20 17-Jan-21 06-Aug-20 17-Jan-21 28.57% 0% Materials Supplying
Mechanical 228 29-Jun-20 28-Mar-21 29-Jun-20 28-Mar-21 0% 0% 28-Mar-21, Mechanical
Pipes 158 29-Jun-20 05-Jan-21 29-Jun-20 05-Jan-21 0% 0% 05-Jan-21, Pipes
A21210 Vender Approval 14 29-Jun-20 14-Jul-20 29-Jun-20 14-Jul-20 100% 0% Vender Approval
A21220 Material Approval 9 15-Jul-20 25-Jul-20 15-Jul-20 25-Jul-20 100% 0% Material Approval
A21230 P.O 5 26-Jul-20 30-Jul-20 26-Jul-20 30-Jul-20 100% 0% P.O
A21240 Materials Supplying 130 06-Aug-20 05-Jan-21 06-Aug-20 05-Jan-21 30.77% 0% Materials Supplying
Pumps 178 29-Jun-20 28-Jan-21 29-Jun-20 28-Jan-21 0% 0% 28-Jan-21, Pumps
A21530 Vender Approval 14 29-Jun-20 14-Jul-20 29-Jun-20 14-Jul-20 100% 0% Vender Approval
A21540 Material Approval 9 15-Jul-20 25-Jul-20 15-Jul-20 25-Jul-20 100% 0% Material Approval
A21550 P.O 5 26-Jul-20 30-Jul-20 26-Jul-20 30-Jul-20 100% 0% P.O
A21560 Materials Supplying 150 06-Aug-20 28-Jan-21 06-Aug-20 28-Jan-21 26.67% 0% Materials Supplying
Valves 193 29-Jun-20 15-Feb-21 29-Jun-20 15-Feb-21 0% 0% 15-Feb-21, Valves
A21570 Vender Approval 14 29-Jun-20 14-Jul-20 29-Jun-20 14-Jul-20 100% 0% Vender Approval
A21580 Material Approval 9 15-Jul-20 25-Jul-20 15-Jul-20 25-Jul-20 100% 0% Material Approval
A21590 P.O 5 26-Jul-20 30-Jul-20 26-Jul-20 30-Jul-20 100% 0% P.O
A21600 Materials Supplying 165 06-Aug-20 15-Feb-21 06-Aug-20 15-Feb-21 24.24% 0% Materials Supplying
Tanks 198 29-Jun-20 21-Feb-21 29-Jun-20 21-Feb-21 0% 0% 21-Feb-21, Tanks
A21610 Vender Approval 14 29-Jun-20 14-Jul-20 29-Jun-20 14-Jul-20 100% 0% Vender Approval
A21620 Material Approval 9 15-Jul-20 25-Jul-20 15-Jul-20 25-Jul-20 100% 0% Material Approval
A21630 P.O 5 26-Jul-20 30-Jul-20 26-Jul-20 30-Jul-20 100% 0% P.O
A21640 Materials Supplying 170 06-Aug-20 21-Feb-21 06-Aug-20 21-Feb-21 23.53% 0% Materials Supplying
Fire Hose Cabinet 228 29-Jun-20 28-Mar-21 29-Jun-20 28-Mar-21 0% 0% 28-Mar-21, Fire Hose Cabinet
A21650 Vender Approval 14 29-Jun-20 14-Jul-20 29-Jun-20 14-Jul-20 100% 0% Vender Approval
A21660 Material Approval 9 15-Jul-20 25-Jul-20 15-Jul-20 25-Jul-20 100% 0% Material Approval
A21670 P.O 5 26-Jul-20 30-Jul-20 26-Jul-20 30-Jul-20 100% 0% P.O
A21680 Materials Supplying 200 06-Aug-20 28-Mar-21 06-Aug-20 28-Mar-21 20% 0% Materials Supplying
HVAC Duct & AC Units 198 29-Jun-20 21-Feb-21 29-Jun-20 21-Feb-21 0% 0% 21-Feb-21, HVAC Duct & AC Units
A21690 Vender Approval 14 29-Jun-20 14-Jul-20 29-Jun-20 14-Jul-20 100% 0% Vender Approval
A21700 Material Approval 9 15-Jul-20 25-Jul-20 15-Jul-20 25-Jul-20 100% 0% Material Approval
A21710 P.O 5 26-Jul-20 30-Jul-20 26-Jul-20 30-Jul-20 100% 0% P.O
A21720 Materials Supplying 170 06-Aug-20 21-Feb-21 06-Aug-20 21-Feb-21 23.53% 0% Materials Supplying
Sanitary Fixtures 148 29-Jun-20 24-Dec-20 29-Jun-20 24-Dec-20 0% 0% 24-Dec-20, Sanitary Fixtures
A21730 Vender Approval 14 29-Jun-20 14-Jul-20 29-Jun-20 14-Jul-20 100% 0% Vender Approval

Actual Level of Effort Remaining Work Milestone Date Revision Checked Approved
Page 2 of 19
Actual Work Critical Remaining Work summary 11-Jun-20 UTS
UPDATED TIME SCHEDULE Al Ihsaa- Educational Complex in Al Jubail D.D 11-Jun-20

Activity ID Activity Name Original Duration BL1 Start BL1 Finish Start Finish Schedule % Performance %Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Complete Complete
A A A A A A A A A A A A A A
A21740 Material Approval 9 15-Jul-20 25-Jul-20 15-Jul-20 25-Jul-20 100% 0% Material Approval
A21750 P.O 5 26-Jul-20 30-Jul-20 26-Jul-20 30-Jul-20 100% 0% P.O
A21760 Materials Supplying 120 06-Aug-20 24-Dec-20 06-Aug-20 24-Dec-20 33.33% 0% Materials Supplying
Electrical 248 29-Jun-20 20-Apr-21 29-Jun-20 20-Apr-21 0% 0% 20-Apr-21, Electrical
Cables 178 29-Jun-20 28-Jan-21 29-Jun-20 28-Jan-21 0% 0% 28-Jan-21, Cables
A21290 Vender Approval 14 29-Jun-20 14-Jul-20 29-Jun-20 14-Jul-20 100% 0% Vender Approval
A21300 Material Approval 9 15-Jul-20 25-Jul-20 15-Jul-20 25-Jul-20 100% 0% Material Approval
A21310 P.O 5 26-Jul-20 30-Jul-20 26-Jul-20 30-Jul-20 100% 0% P.O
A21320 Materials Supplying 150 06-Aug-20 28-Jan-21 06-Aug-20 28-Jan-21 26.67% 0% Materials Supplying
Lighting Fixtures 248 29-Jun-20 20-Apr-21 29-Jun-20 20-Apr-21 0% 0% 20-Apr-21, Lighting Fixtures
A21770 Vender Approval 14 29-Jun-20 14-Jul-20 29-Jun-20 14-Jul-20 100% 0% Vender Approval
A21780 Material Approval 9 15-Jul-20 25-Jul-20 15-Jul-20 25-Jul-20 100% 0% Material Approval
A21790 P.O 5 26-Jul-20 30-Jul-20 26-Jul-20 30-Jul-20 100% 0% P.O
A21800 Materials Supplying 220 06-Aug-20 20-Apr-21 06-Aug-20 20-Apr-21 18.18% 0% Materials Supplying
Panel boards 218 29-Jun-20 16-Mar-21 29-Jun-20 16-Mar-21 0% 0% 16-Mar-21, Panel boards
A21330 Vender Approval 14 29-Jun-20 14-Jul-20 29-Jun-20 14-Jul-20 100% 0% Vender Approval
A21340 Material Approval 9 15-Jul-20 25-Jul-20 15-Jul-20 25-Jul-20 100% 0% Material Approval
A21350 P.O 5 26-Jul-20 30-Jul-20 26-Jul-20 30-Jul-20 100% 0% P.O
A21360 Materials Supplying 190 06-Aug-20 16-Mar-21 06-Aug-20 16-Mar-21 21.05% 0% Materials Supplying
Fire Alarm system 218 29-Jun-20 16-Mar-21 29-Jun-20 16-Mar-21 0% 0% 16-Mar-21, Fire Alarm system
A21810 Vender Approval 14 29-Jun-20 14-Jul-20 29-Jun-20 14-Jul-20 100% 0% Vender Approval
A21820 Material Approval 9 15-Jul-20 25-Jul-20 15-Jul-20 25-Jul-20 100% 0% Material Approval
A21830 P.O 5 26-Jul-20 30-Jul-20 26-Jul-20 30-Jul-20 100% 0% P.O
A21840 Materials Supplying 190 06-Aug-20 16-Mar-21 06-Aug-20 16-Mar-21 21.05% 0% Materials Supplying
telphone & Data System 218 29-Jun-20 16-Mar-21 29-Jun-20 16-Mar-21 0% 0% 16-Mar-21, telphone & Data System
A21850 Vender Approval 14 29-Jun-20 14-Jul-20 29-Jun-20 14-Jul-20 100% 0% Vender Approval
A21860 Material Approval 9 15-Jul-20 25-Jul-20 15-Jul-20 25-Jul-20 100% 0% Material Approval
A21870 P.O 5 26-Jul-20 30-Jul-20 26-Jul-20 30-Jul-20 100% 0% P.O
A21880 Materials Supplying 190 06-Aug-20 16-Mar-21 06-Aug-20 16-Mar-21 21.05% 0% Materials Supplying
Public address System 203 29-Jun-20 27-Feb-21 29-Jun-20 27-Feb-21 0% 0% 27-Feb-21, Public address System
A21890 Vender Approval 14 29-Jun-20 14-Jul-20 29-Jun-20 14-Jul-20 100% 0% Vender Approval
A21900 Material Approval 9 15-Jul-20 25-Jul-20 15-Jul-20 25-Jul-20 100% 0% Material Approval
A21910 P.O 5 26-Jul-20 30-Jul-20 26-Jul-20 30-Jul-20 100% 0% P.O
A21920 Materials Supplying 175 06-Aug-20 27-Feb-21 06-Aug-20 27-Feb-21 22.86% 0% Materials Supplying
Construction Works 367 23-Apr-20 06-Jul-21 28-Mar-20 A 06-Jul-21 2.96% 0.99% 06-Jul-21, Construction Works

Mobilization 5 23-Apr-20 28-Apr-20 04-Apr-20 A 13-Aug-20 100% 90% 13-Aug-20, Mobilization


A18110 Preparation and processing for the start of work 5 23-Apr-20 28-Apr-20 04-Apr-20 A 13-Aug-20 100% 90% Preparation and processing for the start of work
General Site Works ( A & B & C ) 276 27-Jul-20 21-Jun-21 05-Apr-20 A 21-Jun-21 0% 0.48% 21-Jun-21, General Site Works ( A & B & C )
Civil Work 276 27-Jul-20 21-Jun-21 05-Apr-20 A 21-Jun-21 0% 0.9% 21-Jun-21, Civil Work
Sub-Structure 118 27-Jul-20 19-Dec-20 05-Apr-20 A 19-Dec-20 0% 24.29% 19-Dec-20, Sub-Structure
A22010 Boreholes surrounding the main building 5 27-Jul-20 06-Aug-20 05-Apr-20 A 04-Nov-20 0% 65% Boreholes surrounding the main building
A22030 Excavation for fence foundation 5 04-Nov-20 10-Nov-20 04-Nov-20 10-Nov-20 0% 0% Excavation for fence foundation
A22000 Soil termite treatment 2 10-Nov-20 12-Nov-20 10-Nov-20 12-Nov-20 0% 0% Soil termite treatment
A22070 Slab on grade 9 12-Nov-20 23-Nov-20 12-Nov-20 23-Nov-20 0% 0% Slab on grade
A22020 Backfilling 3 15-Dec-20 19-Dec-20 15-Dec-20 19-Dec-20 0% 0% Backfilling
Super Structure 180 23-Nov-20 21-Jun-21 23-Nov-20 21-Jun-21 0% 0% 21-Jun-21, Super Structure
Concrete work 36 23-Nov-20 04-Jan-21 23-Nov-20 04-Jan-21 0% 0% 04-Jan-21, Concrete work
A22060 Necks 5 23-Nov-20 29-Nov-20 23-Nov-20 29-Nov-20 0% 0% Necks
A22050 Beams 9 05-Dec-20 15-Dec-20 05-Dec-20 15-Dec-20 0% 0% Beams
A18230 Columns 14 19-Dec-20 04-Jan-21 19-Dec-20 04-Jan-21 0% 0% Columns

Actual Level of Effort Remaining Work Milestone Date Revision Checked Approved
Page 3 of 19
Actual Work Critical Remaining Work summary 11-Jun-20 UTS
UPDATED TIME SCHEDULE Al Ihsaa- Educational Complex in Al Jubail D.D 11-Jun-20

Activity ID Activity Name Original Duration BL1 Start BL1 Finish Start Finish Schedule % Performance %Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Complete Complete
A A A A A A A A A A A A A A
Paving 104 28-Jan-21 30-May-21 28-Jan-21 30-May-21 0% 0% 30-May-21, Paving
A10300 Leveling Works 14 28-Jan-21 14-Feb-21 28-Jan-21 14-Feb-21 0% 0% Leveling Works
A10350 Curbstone 21 14-Feb-21 10-Mar-21 14-Feb-21 10-Mar-21 0% 0% Curbstone
A10360 Sand Works 3 10-Mar-21 14-Mar-21 10-Mar-21 14-Mar-21 0% 0% Sand Works
A10320 Interlock Works 28 14-Mar-21 15-Apr-21 14-Mar-21 15-Apr-21 0% 0% Interlock Works
A10330 Cement Tiles Works 24 15-Apr-21 13-May-21 15-Apr-21 13-May-21 0% 0% Cement Tiles Works
A10310 Artificial grass Installation for umbrellas 7 13-May-21 22-May-21 13-May-21 22-May-21 0% 0% Artificial grass Installation for umbrellas
A10340 Precast Concrete Chairs & Baskets Work 7 22-May-21 30-May-21 22-May-21 30-May-21 0% 0% Precast Concrete Chairs & Baskets Work
Finishing Works 175 29-Nov-20 21-Jun-21 29-Nov-20 21-Jun-21 0% 0% 21-Jun-21, Finishing Works
A18260 Waterproofin g works for substructure works 5 29-Nov-20 05-Dec-20 29-Nov-20 05-Dec-20 0% 0% Waterproofin g works for substructure works
A18240 Masonry works 21 04-Jan-21 28-Jan-21 04-Jan-21 28-Jan-21 0% 0% Masonry works
A18120 Plastering works 21 28-Jan-21 22-Feb-21 28-Jan-21 22-Feb-21 0% 0% Plastering works
A18250 Metal Works 28 22-Feb-21 27-Mar-21 22-Feb-21 27-Mar-21 0% 0% Metal Works
A18160 External Painting (Profile) 14 05-Jun-21 21-Jun-21 05-Jun-21 21-Jun-21 0% 0% External Painting (Profile)
Mechanical Works 67 14-Feb-21 02-May-21 14-Feb-21 02-May-21 0% 0% 02-May-21, Mechanical Works
Plumping 32 14-Feb-21 22-Mar-21 14-Feb-21 22-Mar-21 0% 0% 22-Mar-21, Plumping
A10640 Connection to public water 7 14-Feb-21 22-Feb-21 14-Feb-21 22-Feb-21 0% 0% Connection to public water
A10650 water valves 7 24-Feb-21 03-Mar-21 24-Feb-21 03-Mar-21 0% 0% water valves
A10670 Manholes 7 04-Mar-21 11-Mar-21 04-Mar-21 11-Mar-21 0% 0% Manholes
A10660 Sanitary & Waste pipe system 9 13-Mar-21 22-Mar-21 13-Mar-21 22-Mar-21 0% 0% Sanitary & Waste pipe system
Fire 35 23-Mar-21 02-May-21 23-Mar-21 02-May-21 0% 0% 02-May-21, Fire
A10630 Fire piping intsallation 14 23-Mar-21 07-Apr-21 23-Mar-21 07-Apr-21 0% 0% Fire piping intsallation
A10620 Gate Valve including valve box 7 08-Apr-21 15-Apr-21 08-Apr-21 15-Apr-21 0% 0% Gate Valve including valve box
A18270 Fire Hose Cabinet & Accessories 7 17-Apr-21 24-Apr-21 17-Apr-21 24-Apr-21 0% 0% Fire Hose Cabinet & Accessories
A18280 Siamese pipe connection 7 25-Apr-21 02-May-21 25-Apr-21 02-May-21 0% 0% Siamese pipe connection
Electrical Works 108 28-Jan-21 03-Jun-21 28-Jan-21 03-Jun-21 0% 0% 03-Jun-21, Electrical Works
A22120 Lighting First Fix 24 28-Jan-21 25-Feb-21 28-Jan-21 25-Feb-21 0% 0% Lighting First Fix
A22130 Lighting Second Fix 3 04-Apr-21 07-Apr-21 04-Apr-21 07-Apr-21 0% 0% Lighting Second Fix
A22150 Cables installation 9 07-Apr-21 18-Apr-21 07-Apr-21 18-Apr-21 0% 0% Cables installation
A22100 Inspection Chambers 7 18-Apr-21 26-Apr-21 18-Apr-21 26-Apr-21 0% 0% Inspection Chambers
A22110 Board & Elec distribution system installation 30 26-Apr-21 31-May-21 26-Apr-21 31-May-21 0% 0% Board & Elec distribution system installation
A22140 Lighting Third Fix 3 31-May-21 03-Jun-21 31-May-21 03-Jun-21 0% 0% Lighting Third Fix
BUILDING (A) 357 29-Apr-20 30-Jun-21 28-Mar-20 A 30-Jun-21 6.1% 1.39% 30-Jun-21, BUILDING (A)
Main Building (A) 356 29-Apr-20 30-Jun-21 28-Mar-20 A 30-Jun-21 7.43% 1.7% 30-Jun-21, Main Building (A)
Civil Works 356 29-Apr-20 30-Jun-21 28-Mar-20 A 30-Jun-21 9.43% 2.16% 30-Jun-21, Civil Works
Sub-Structure 5 29-Apr-20 04-May-20 28-Mar-20 A 19-Aug-20 100% 80% 19-Aug-20, Sub-Structure
A18290 Remove of residues 5 29-Apr-20 04-May-20 28-Mar-20 A 19-Aug-20 100% 80% Remove of residues
Super Structure 334 30-May-20 30-Jun-21 12-May-20 A 30-Jun-21 9.26% 2.02% 30-Jun-21, Super Structure
Concrete Works 159 30-May-20 08-Dec-20 12-May-20 A 08-Dec-20 27.51% 5.99% 08-Dec-20, Concrete Works
Supporting Works 118 30-May-20 21-Oct-20 30-May-20 A 21-Oct-20 44.92% 10.31% 21-Oct-20, Supporting Works
A22200 Columns 21 30-May-20 22-Jun-20 30-May-20 A 15-Oct-20 0% 30% Columns
A22280 Foundations 24 30-Aug-20 28-Sep-20 30-Aug-20 28-Sep-20 75% 0% Foundations
A22190 Beams 5 15-Oct-20 21-Oct-20 15-Oct-20 21-Oct-20 0% 0% Beams
Check and treatment 26 19-Jul-20 23-Aug-20 12-May-20 A 30-Aug-20 100% 19.36% 30-Aug-20, Check and treatment
A22170 Treatments 7 19-Jul-20 26-Jul-20 12-May-20 A 30-Aug-20 100% 20% Treatments
A22160 Checking 3 20-Aug-20 23-Aug-20 20-Aug-20 23-Aug-20 100% 0% Checking
Casting Works 41 21-Oct-20 08-Dec-20 21-Oct-20 08-Dec-20 0% 0% 08-Dec-20, Casting Works
A22300 Slab on grade 7 21-Oct-20 29-Oct-20 21-Oct-20 29-Oct-20 0% 0% Slab on grade
A22270 Slabs & Beams 21 29-Oct-20 23-Nov-20 29-Oct-20 23-Nov-20 0% 0% Slabs & Beams
A22260 Columns & Beams (parapet) 5 23-Nov-20 29-Nov-20 23-Nov-20 29-Nov-20 0% 0% Columns & Beams (parapet)
A22310 Rambs 3 29-Nov-20 02-Dec-20 29-Nov-20 02-Dec-20 0% 0% Rambs

Actual Level of Effort Remaining Work Milestone Date Revision Checked Approved
Page 4 of 19
Actual Work Critical Remaining Work summary 11-Jun-20 UTS
UPDATED TIME SCHEDULE Al Ihsaa- Educational Complex in Al Jubail D.D 11-Jun-20

Activity ID Activity Name Original Duration BL1 Start BL1 Finish Start Finish Schedule % Performance %Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Complete Complete
A A A A A A A A A A A A A A
A22290 Staircases and entrance 5 02-Dec-20 08-Dec-20 02-Dec-20 08-Dec-20 0% 0% Staircases and entrance
Finishing Works 175 08-Dec-20 30-Jun-21 08-Dec-20 30-Jun-21 0% 0% 30-Jun-21, Finishing Works
A11440 Masonry Works 21 08-Dec-20 02-Jan-21 08-Dec-20 02-Jan-21 0% 0% Masonry Works
A11610 External Cement Plastering 18 02-Jan-21 23-Jan-21 02-Jan-21 23-Jan-21 0% 0% External Cement Plastering
A22650 Roof sandwich panels 26 23-Jan-21 22-Feb-21 23-Jan-21 22-Feb-21 0% 0% Roof sandwich panels
A11560 Internal Cement Plastering 24 23-Jan-21 20-Feb-21 23-Jan-21 20-Feb-21 0% 0% Internal Cement Plastering
A11640 Gypsum board 9 20-Feb-21 02-Mar-21 20-Feb-21 02-Mar-21 0% 0% Gypsum board
A22660 Ceiling Tiles 24 22-Feb-21 22-Mar-21 22-Feb-21 22-Mar-21 0% 0% Ceiling Tiles
A11480 Waterproofin g for Bathroom & Kitchen 5 02-Mar-21 08-Mar-21 02-Mar-21 08-Mar-21 0% 0% Waterproofin g for Bathroom & Kitchen
A22450 Tile s for Walls 14 08-Mar-21 24-Mar-21 08-Mar-21 24-Mar-21 0% 0% Tile s for Walls
A22640 Roof finishes 28 22-Mar-21 24-Apr-21 22-Mar-21 24-Apr-21 0% 0% Roof finishes
A11700 Specialies 9 24-Mar-21 04-Apr-21 24-Mar-21 04-Apr-21 0% 0% Specialies
A11630 Aluminium strip 5 24-Mar-21 30-Mar-21 24-Mar-21 30-Mar-21 0% 0% Aluminium strip
A11460 Handrail & Protections 14 24-Mar-21 10-Apr-21 24-Mar-21 10-Apr-21 0% 0% Handrail & Protections
A11570 Internal Painting Works (Primer + Filler + 1st Coat) 21 30-Mar-21 24-Apr-21 30-Mar-21 24-Apr-21 0% 0% Internal Painting Works (Primer + Filler + 1st Coat)
A11520 Floor Finish (tiling & scerting) 30 24-Apr-21 29-May-21 24-Apr-21 29-May-21 0% 0% Floor Finish (tiling & scerting)
A11660 Counters 7 29-May-21 06-Jun-21 29-May-21 06-Jun-21 0% 0% Counters
A11620 External Painting works 7 29-May-21 06-Jun-21 29-May-21 06-Jun-21 0% 0% External Painting works
A11510 Windows 28 29-May-21 30-Jun-21 29-May-21 30-Jun-21 0% 0% Windows
A11500 Doors 21 29-May-21 22-Jun-21 29-May-21 22-Jun-21 0% 0% Doors
A22440 Painting Works (Final Coat) 10 06-Jun-21 17-Jun-21 06-Jun-21 17-Jun-21 0% 0% Painting Works (Final Coat)
Mechanical Works 101 02-Mar-21 28-Jun-21 02-Mar-21 28-Jun-21 0% 0% 28-Jun-21, Mechanical Works
Plumbing 80 27-Mar-21 28-Jun-21 27-Mar-21 28-Jun-21 0% 0% 28-Jun-21, Plumbing
A10980 Domestic Water Supply System 14 27-Mar-21 12-Apr-21 27-Mar-21 12-Apr-21 0% 0% Domestic Water Supply System
A10990 Isolation valve 3 12-Apr-21 15-Apr-21 12-Apr-21 15-Apr-21 0% 0% Isolation valve
A11000 Electric Water Heaters 5 24-Apr-21 29-Apr-21 24-Apr-21 29-Apr-21 0% 0% Electric Water Heaters
A11930 Water Storage Tanks 5 29-Apr-21 05-May-21 29-Apr-21 05-May-21 0% 0% Water Storage Tanks
A11940 Sanitary System 11 05-May-21 18-May-21 05-May-21 18-May-21 0% 0% Sanitary System
A11950 Roof Scupper Drain 3 18-May-21 22-May-21 18-May-21 22-May-21 0% 0% Roof Scupper Drain
A11960 Plumbing Fixtures 9 17-Jun-21 28-Jun-21 17-Jun-21 28-Jun-21 0% 0% Plumbing Fixtures
Fire Fighting 35 01-Apr-21 12-May-21 01-Apr-21 12-May-21 0% 0% 12-May-21, Fire Fighting
A11010 Piping 21 01-Apr-21 26-Apr-21 01-Apr-21 26-Apr-21 0% 0% Piping
A11020 Fire Hose Cabinet & Accessories 9 26-Apr-21 06-May-21 26-Apr-21 06-May-21 0% 0% Fire Hose Cabinet & Accessories
A18300 fire extinguisher 5 06-May-21 12-May-21 06-May-21 12-May-21 0% 0% fire extinguisher
HVAC 75 02-Mar-21 29-May-21 02-Mar-21 29-May-21 0% 0% 29-May-21, HVAC
A10970 HVAC Ducts and Casings 14 02-Mar-21 17-Mar-21 02-Mar-21 17-Mar-21 0% 0% HVAC Ducts and Casings
A10960 General Exhaust Fan 9 18-Mar-21 28-Mar-21 18-Mar-21 28-Mar-21 0% 0% General Exhaust Fan
A11150 Air Curtain 5 29-Mar-21 03-Apr-21 29-Mar-21 03-Apr-21 0% 0% Air Curtain
A10950 DX-Split wall mounted type air conditioning units 21 24-Apr-21 18-May-21 24-Apr-21 18-May-21 0% 0% DX-Split wall mounted type air conditioning units
A18310 Dx - Split units 9 18-May-21 29-May-21 18-May-21 29-May-21 0% 0% Dx - Split units
Electrical Works 124 02-Jan-21 25-May-21 02-Jan-21 25-May-21 0% 0% 25-May-21, Electrical Works
Electrical 124 02-Jan-21 25-May-21 02-Jan-21 25-May-21 0% 0% 25-May-21, Electrical
A12050 Conductors and cables 21 02-Jan-21 26-Jan-21 02-Jan-21 26-Jan-21 0% 0% Conductors and cables
A12010 Lighting System First Fix (Conduits) 14 26-Jan-21 11-Feb-21 26-Jan-21 11-Feb-21 0% 0% Lighting System First Fix (Conduits)
A22320 Lighting System Second Fix (Wires) 14 20-Feb-21 08-Mar-21 20-Feb-21 08-Mar-21 0% 0% Lighting System Second Fix (Wires)
A12020 Power Installation 9 08-Mar-21 18-Mar-21 08-Mar-21 18-Mar-21 0% 0% Power Installation
A11990 Panel Boards 7 25-Mar-21 01-Apr-21 25-Mar-21 01-Apr-21 0% 0% Panel Boards
A12070 Lightening Protection System 7 03-Apr-21 10-Apr-21 03-Apr-21 10-Apr-21 0% 0% Lightening Protection System
A12060 Earthing system 7 11-Apr-21 18-Apr-21 11-Apr-21 18-Apr-21 0% 0% Earthing system
A12030 Bells system 5 19-Apr-21 24-Apr-21 19-Apr-21 24-Apr-21 0% 0% Bells system

Actual Level of Effort Remaining Work Milestone Date Revision Checked Approved
Page 5 of 19
Actual Work Critical Remaining Work summary 11-Jun-20 UTS
UPDATED TIME SCHEDULE Al Ihsaa- Educational Complex in Al Jubail D.D 11-Jun-20

Activity ID Activity Name Original Duration BL1 Start BL1 Finish Start Finish Schedule % Performance %Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Complete Complete
A A A A A A A A A A A A A A
A12040 Sockets & Switches 11 25-Apr-21 06-May-21 25-Apr-21 06-May-21 0% 0% Sockets & Switches
A22330 Lighting System Third Fix (Fixtures) 14 10-May-21 25-May-21 10-May-21 25-May-21 0% 0% Lighting System Third Fix (Fixtures)
Communications 59 26-Jan-21 04-Apr-21 26-Jan-21 04-Apr-21 0% 0% 04-Apr-21, Communications
A12120 Fire Alarm System First Fix 20 26-Jan-21 18-Feb-21 26-Jan-21 18-Feb-21 0% 0% Fire Alarm System First Fix
A12080 Telephone & Data Communication System First Fix 14 26-Jan-21 11-Feb-21 26-Jan-21 11-Feb-21 0% 0% Telephone & Data Communication System First Fix
A22360 Telephone & Data Communication System Second Fix 14 20-Feb-21 08-Mar-21 20-Feb-21 08-Mar-21 0% 0% Telephone & Data Communication System Second Fix
A22340 Fire Alarm System Second Fix 14 20-Feb-21 08-Mar-21 20-Feb-21 08-Mar-21 0% 0% Fire Alarm System Second Fix
A12110 Public Address system 14 08-Mar-21 24-Mar-21 08-Mar-21 24-Mar-21 0% 0% Public Address system
A22370 Telephone & Data Communication System Third Fix 9 25-Mar-21 04-Apr-21 25-Mar-21 04-Apr-21 0% 0% Telephone & Data Communication System Third Fix
A22350 Fire Alarm System Third Fix 9 25-Mar-21 04-Apr-21 25-Mar-21 04-Apr-21 0% 0% Fire Alarm System Third Fix
Canteen (A) 114 18-Feb-21 30-Jun-21 18-Feb-21 30-Jun-21 0% 0% 30-Jun-21, Canteen (A)
Civil Works 114 18-Feb-21 30-Jun-21 18-Feb-21 30-Jun-21 0% 0% 30-Jun-21, Civil Works
Sub-Structure 34 18-Feb-21 29-Mar-21 18-Feb-21 29-Mar-21 0% 0% 29-Mar-21, Sub-Structure
A19140 Excavation for foundation 3 18-Feb-21 21-Feb-21 18-Feb-21 21-Feb-21 0% 0% Excavation for foundation
A19150 Soil termite treatment 2 22-Feb-21 23-Feb-21 22-Feb-21 23-Feb-21 0% 0% Soil termite treatment
A22380 PCC 2 24-Feb-21 25-Feb-21 24-Feb-21 25-Feb-21 0% 0% PCC
A22390 Footing 3 27-Feb-21 01-Mar-21 27-Feb-21 01-Mar-21 0% 0% Footing
A22410 Neck Column 5 02-Mar-21 07-Mar-21 02-Mar-21 07-Mar-21 0% 0% Neck Column
A19190 bitumen paint 2 08-Mar-21 09-Mar-21 08-Mar-21 09-Mar-21 0% 0% bitumen paint
A22430 Grade Beam 5 10-Mar-21 15-Mar-21 10-Mar-21 15-Mar-21 0% 0% Grade Beam
A22400 Slab on grade 9 16-Mar-21 25-Mar-21 16-Mar-21 25-Mar-21 0% 0% Slab on grade
A19160 Backfilling 3 27-Mar-21 29-Mar-21 27-Mar-21 29-Mar-21 0% 0% Backfilling
Super Structure 80 30-Mar-21 30-Jun-21 30-Mar-21 30-Jun-21 0% 0% 30-Jun-21, Super Structure
Concrete Works 28 30-Mar-21 01-May-21 30-Mar-21 01-May-21 0% 0% 01-May-21, Concrete Works
A22420 Column 7 30-Mar-21 06-Apr-21 30-Mar-21 06-Apr-21 0% 0% Column
A19170 Beams 7 07-Apr-21 14-Apr-21 07-Apr-21 14-Apr-21 0% 0% Beams
A19180 Slabs 14 15-Apr-21 01-May-21 15-Apr-21 01-May-21 0% 0% Slabs
Finishing Works 52 02-May-21 30-Jun-21 02-May-21 30-Jun-21 0% 0% 30-Jun-21, Finishing Works
A22670 Masonry Works 14 02-May-21 17-May-21 02-May-21 17-May-21 0% 0% Masonry Works
A22730 Internal Cement Plastering 5 18-May-21 23-May-21 18-May-21 23-May-21 0% 0% Internal Cement Plastering
A22780 Gypsum board 5 24-May-21 29-May-21 24-May-21 29-May-21 0% 0% Gypsum board
A22750 External Cement Plastering 7 24-May-21 31-May-21 24-May-21 31-May-21 0% 0% External Cement Plastering
A22690 Waterproofin g for Bathroom & Kitchen 3 24-May-21 26-May-21 24-May-21 26-May-21 0% 0% Waterproofing for Bathroom & Kitchen
A22820 Tile s for Walls 3 27-May-21 30-May-21 27-May-21 30-May-21 0% 0% Tile s for Walls
A22830 Roof finishes 7 01-Jun-21 08-Jun-21 01-Jun-21 08-Jun-21 0% 0% Roof finishes
A22720 Floor tiling 3 09-Jun-21 12-Jun-21 09-Jun-21 12-Jun-21 0% 0% Floor tiling
A22790 Counters 5 13-Jun-21 17-Jun-21 13-Jun-21 17-Jun-21 0% 0% Counters
A22710 Windows 5 13-Jun-21 17-Jun-21 13-Jun-21 17-Jun-21 0% 0% Windows
A22700 Doors 5 13-Jun-21 17-Jun-21 13-Jun-21 17-Jun-21 0% 0% Doors
A22760 Painting works 7 23-Jun-21 30-Jun-21 23-Jun-21 30-Jun-21 0% 0% Painting works
Mechanical Works 31 18-May-21 22-Jun-21 18-May-21 22-Jun-21 0% 0% 22-Jun-21, Mechanical Works
Plumbing 31 18-May-21 22-Jun-21 18-May-21 22-Jun-21 0% 0% 22-Jun-21, Plumbing
A14180 Sanitary Waste Piping Specia ltie s 3 18-May-21 20-May-21 18-May-21 20-May-21 0% 0% Sanitary Waste Piping Specia ltie s
A13320 Domestic Water Supply System 3 18-May-21 20-May-21 18-May-21 20-May-21 0% 0% Domestic Water Supply System
A14150 Sanitary System 5 22-May-21 26-May-21 22-May-21 26-May-21 0% 0% Sanitary System
A14160 Roof Scupper Drain 4 27-May-21 31-May-21 27-May-21 31-May-21 0% 0% Roof Scupper Drain
A13340 Electric Water Heaters 3 13-Jun-21 15-Jun-21 13-Jun-21 15-Jun-21 0% 0% Electric Water Heaters
A14170 Plumbing Fixtures 4 19-Jun-21 22-Jun-21 19-Jun-21 22-Jun-21 0% 0% Plumbing Fixtures
Fire Fighting 3 19-Jun-21 21-Jun-21 19-Jun-21 21-Jun-21 0% 0% 21-Jun-21, Fire Fighting
A13350 fire extinguisher 3 19-Jun-21 21-Jun-21 19-Jun-21 21-Jun-21 0% 0% fire extinguisher

Actual Level of Effort Remaining Work Milestone Date Revision Checked Approved
Page 6 of 19
Actual Work Critical Remaining Work summary 11-Jun-20 UTS
UPDATED TIME SCHEDULE Al Ihsaa- Educational Complex in Al Jubail D.D 11-Jun-20

Activity ID Activity Name Original Duration BL1 Start BL1 Finish Start Finish Schedule % Performance %Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Complete Complete
A A A A A A A A A A A A A A
HVAC 4 24-May-21 27-May-21 24-May-21 27-May-21 0% 0% 27-May-21, HVAC
A13300 General Exhaust Fan 1 24-May-21 24-May-21 24-May-21 24-May-21 0% 0% General Exhaust Fan
A13290 DX-Split wall mounted type air conditioning units 3 25-May-21 27-May-21 25-May-21 27-May-21 0% 0% DX-Split wall mounted type air conditioning units
Electrical Works 16 18-May-21 05-Jun-21 18-May-21 05-Jun-21 0% 0% 05-Jun-21, Electrical Works
Electrical Power 16 18-May-21 05-Jun-21 18-May-21 05-Jun-21 0% 0% 05-Jun-21, Electrical Power
A22840 Lighting System First Fix (Conduits) 5 18-May-21 23-May-21 18-May-21 23-May-21 0% 0% Lighting System First Fix (Conduits)
A22850 Lighting System Second Fix (Wires) 2 24-May-21 25-May-21 24-May-21 25-May-21 0% 0% Lighting System Second Fix (Wires)
A14260 Conductors and cables 7 24-May-21 31-May-21 24-May-21 31-May-21 0% 0% Conductors and cables
A14200 Power and Lighting panel 3 26-May-21 29-May-21 26-May-21 29-May-21 0% 0% Power and Lighting panel
A14250 Disconnect Switches 2 30-May-21 31-May-21 30-May-21 31-May-21 0% 0% Disconnect Switches
A14230 Power Installation 2 01-Jun-21 02-Jun-21 01-Jun-21 02-Jun-21 0% 0% Power Installation
A22860 Lighting System Third Fix (Fixtures) 2 03-Jun-21 05-Jun-21 03-Jun-21 05-Jun-21 0% 0% Lighting System Third Fix (Fixtures)
Communications 8 24-May-21 01-Jun-21 24-May-21 01-Jun-21 0% 0% 01-Jun-21, Communications
A22880 Fire Alarm System First Fix 4 24-May-21 27-May-21 24-May-21 27-May-21 0% 0% Fire Alarm System First Fix
A22870 Telephone & Data Communication System First Fix 4 24-May-21 27-May-21 24-May-21 27-May-21 0% 0% Telephone & Data Communication System First Fix
A22910 Telephone & Data Communication System Second Fix 2 29-May-21 30-May-21 29-May-21 30-May-21 0% 0% Telephone & Data Communication System Second Fix
A22890 Fire Alarm System Second Fix 2 29-May-21 30-May-21 29-May-21 30-May-21 0% 0% Fire Alarm System Second Fix
A22920 Telephone & Data Communication System Third Fix 2 31-May-21 01-Jun-21 31-May-21 01-Jun-21 0% 0% Telephone & Data Communication System Third Fix
A22900 Fire Alarm System Third Fix 2 31-May-21 01-Jun-21 31-May-21 01-Jun-21 0% 0% Fire Alarm System Third Fix
Guard House ( A ) 218 26-Sep-20 06-Jun-21 26-Sep-20 06-Jun-21 0% 0% 06-Jun-21, Guard House ( A )
Civil Works 218 26-Sep-20 06-Jun-21 26-Sep-20 06-Jun-21 0% 0% 06-Jun-21, Civil Works
Sub-Structure 22 26-Sep-20 20-Oct-20 26-Sep-20 20-Oct-20 0% 0% 20-Oct-20, Sub-Structure
A23610 Excavation for foundation 2 26-Sep-20 27-Sep-20 26-Sep-20 27-Sep-20 0% 0% Excavation for foundation
A23630 Soil termite treatment 2 28-Sep-20 29-Sep-20 28-Sep-20 29-Sep-20 0% 0% Soil termite treatment
A23650 PCC 2 30-Sep-20 01-Oct-20 30-Sep-20 01-Oct-20 0% 0% PCC
A23660 Footing 5 03-Oct-20 07-Oct-20 03-Oct-20 07-Oct-20 0% 0% Footing
A23680 Neck Column 3 08-Oct-20 11-Oct-20 08-Oct-20 11-Oct-20 0% 0% Neck Column
A23690 Grade Beam 3 12-Oct-20 14-Oct-20 12-Oct-20 14-Oct-20 0% 0% Grade Beam
A23670 Slab on grade 3 15-Oct-20 18-Oct-20 15-Oct-20 18-Oct-20 0% 0% Slab on grade
A23620 Backfilling 2 19-Oct-20 20-Oct-20 19-Oct-20 20-Oct-20 0% 0% Backfilling
Super Structure 196 21-Oct-20 06-Jun-21 21-Oct-20 06-Jun-21 0% 0% 06-Jun-21, Super Structure
Concrete Works 51 21-Oct-20 19-Dec-20 21-Oct-20 19-Dec-20 0% 0% 19-Dec-20, Concrete Works
A23720 Column 21 21-Oct-20 14-Nov-20 21-Oct-20 14-Nov-20 0% 0% Column
A23700 Beams 9 15-Nov-20 24-Nov-20 15-Nov-20 24-Nov-20 0% 0% Beams
A23710 Slabs 21 25-Nov-20 19-Dec-20 25-Nov-20 19-Dec-20 0% 0% Slabs
Finishing Works 145 20-Dec-20 06-Jun-21 20-Dec-20 06-Jun-21 0% 0% 06-Jun-21, Finishing Works
A23010 Masonry Works 5 20-Dec-20 24-Dec-20 20-Dec-20 24-Dec-20 0% 0% Masonry Works
A23090 External Cement Plastering 5 26-Dec-20 30-Dec-20 26-Dec-20 30-Dec-20 0% 0% External Cement Plastering
A23110 Aluminium strip 7 31-Dec-20 07-Jan-21 31-Dec-20 07-Jan-21 0% 0% Aluminium strip
A23070 Internal Cement Plastering 5 31-Dec-20 05-Jan-21 31-Dec-20 05-Jan-21 0% 0% Internal Cement Plastering
A23030 Waterproofin g for Bathroom & Kitchen 7 06-Jan-21 13-Jan-21 06-Jan-21 13-Jan-21 0% 0% Waterproofin g for Bathroom & Kitchen
A23580 Roof finishes 5 27-Jan-21 01-Feb-21 27-Jan-21 01-Feb-21 0% 0% Roof finishes
A23570 Tile s for Walls 17 02-Feb-21 21-Feb-21 02-Feb-21 21-Feb-21 0% 0% Tile s for Walls
A23390 Specialies 4 22-Feb-21 25-Feb-21 22-Feb-21 25-Feb-21 0% 0% Specialies
A23130 Counters 7 27-Feb-21 06-Mar-21 27-Feb-21 06-Mar-21 0% 0% Counters
A23050 Windows 28 27-Feb-21 30-Mar-21 27-Feb-21 30-Mar-21 0% 0% Windows
A23040 Doors 21 27-Feb-21 22-Mar-21 27-Feb-21 22-Mar-21 0% 0% Doors
A23060 Floor Finish (tiling & scerting) 17 19-Apr-21 08-May-21 19-Apr-21 08-May-21 0% 0% Floor Finish (tiling & scerting)
A23100 Painting works 11 25-May-21 06-Jun-21 25-May-21 06-Jun-21 0% 0% Painting works
Mechanical Works 129 26-Dec-20 24-May-21 26-Dec-20 24-May-21 0% 0% 24-May-21, Mechanical Works

Actual Level of Effort Remaining Work Milestone Date Revision Checked Approved
Page 7 of 19
Actual Work Critical Remaining Work summary 11-Jun-20 UTS
UPDATED TIME SCHEDULE Al Ihsaa- Educational Complex in Al Jubail D.D 11-Jun-20

Activity ID Activity Name Original Duration BL1 Start BL1 Finish Start Finish Schedule % Performance %Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Complete Complete
A A A A A A A A A A A A A A
A26490 Sanitary Specialties 14 26-Dec-20 10-Jan-21 26-Dec-20 10-Jan-21 0% 0% Sanitary Specialties
A22960 Domestic Water Supply System 14 26-Dec-20 10-Jan-21 26-Dec-20 10-Jan-21 0% 0% Domestic Water Supply System
A23150 Sanitary System 11 11-Jan-21 23-Jan-21 11-Jan-21 23-Jan-21 0% 0% Sanitary System
A23160 Roof Scupper Drain 3 24-Jan-21 26-Jan-21 24-Jan-21 26-Jan-21 0% 0% Roof Scupper Drain
A22940 General Exhaust Fan 9 07-Mar-21 16-Mar-21 07-Mar-21 16-Mar-21 0% 0% General Exhaust Fan
A22930 DX-Split Units 28 17-Mar-21 18-Apr-21 17-Mar-21 18-Apr-21 0% 0% DX-Split Units
A23370 fire extinguisher 14 09-May-21 24-May-21 09-May-21 24-May-21 0% 0% fire extinguisher
A23170 Plumbing Fixtures 14 09-May-21 24-May-21 09-May-21 24-May-21 0% 0% Plumbing Fixtures
A22980 Electric Water Heaters 14 09-May-21 24-May-21 09-May-21 24-May-21 0% 0% Electric Water Heaters
Electrical Works 76 16-Feb-21 15-May-21 16-Feb-21 15-May-21 0% 0% 15-May-21, Electrical Works
Electrical 76 16-Feb-21 15-May-21 16-Feb-21 15-May-21 0% 0% 15-May-21, Electrical
A23220 Lighting System First Fix (Conduits) 14 16-Feb-21 03-Mar-21 16-Feb-21 03-Mar-21 0% 0% Lighting System First Fix (Conduits)
A23500 Lighting System Second Fix (Wires) 14 04-Mar-21 20-Mar-21 04-Mar-21 20-Mar-21 0% 0% Lighting System Second Fix (Wires)
A23260 Conductors and cables 16 22-Mar-21 08-Apr-21 22-Mar-21 08-Apr-21 0% 0% Conductors and cables
A23200 Panel Boards 14 25-Mar-21 10-Apr-21 25-Mar-21 10-Apr-21 0% 0% Panel Boards
A23230 Power Installation 9 10-Apr-21 19-Apr-21 10-Apr-21 19-Apr-21 0% 0% Power Installation
A23250 Sockets & Switches 14 11-Apr-21 26-Apr-21 11-Apr-21 26-Apr-21 0% 0% Sockets & Switches
A23510 Lighting System Third Fix (Fixtures) 14 29-Apr-21 15-May-21 29-Apr-21 15-May-21 0% 0% Lighting System Third Fix (Fixtures)
Communications 54 16-Feb-21 19-Apr-21 16-Feb-21 19-Apr-21 0% 0% 19-Apr-21, Communications
A23330 Fire Alarm System First Fix 24 16-Feb-21 15-Mar-21 16-Feb-21 15-Mar-21 0% 0% Fire Alarm System First Fix
A23290 Telephone & Data Communication System First Fix 24 16-Feb-21 15-Mar-21 16-Feb-21 15-Mar-21 0% 0% Telephone & Data Communication System First Fix
A23540 Telephone & Data Communication System Second Fix 15 16-Mar-21 01-Apr-21 16-Mar-21 01-Apr-21 0% 0% Telephone & Data Communication System Second Fix
A23520 Fire Alarm System Second Fix 15 16-Mar-21 01-Apr-21 16-Mar-21 01-Apr-21 0% 0% Fire Alarm System Second Fix
A23550 Telephone & Data Communication System Third Fix 15 03-Apr-21 19-Apr-21 03-Apr-21 19-Apr-21 0% 0% Telephone & Data Communication System Third Fix
A23530 Fire Alarm System Third Fix 15 03-Apr-21 19-Apr-21 03-Apr-21 19-Apr-21 0% 0% Fire Alarm System Third Fix
Electrical Room (A) 200 07-Oct-20 27-May-21 07-Oct-20 27-May-21 0% 0% 27-May-21, Electrical Room (A)
Civil Works 200 07-Oct-20 27-May-21 07-Oct-20 27-May-21 0% 0% 27-May-21, Civil Works
Sub-Structure 58 07-Oct-20 13-Dec-20 07-Oct-20 13-Dec-20 0% 0% 13-Dec-20, Sub-Structure
A24300 Excavation for foundation 5 07-Oct-20 12-Oct-20 07-Oct-20 12-Oct-20 0% 0% Excavation for foundation
A24320 Soil termite treatment 2 13-Oct-20 14-Oct-20 13-Oct-20 14-Oct-20 0% 0% Soil termite treatment
A24340 PCC 9 15-Oct-20 25-Oct-20 15-Oct-20 25-Oct-20 0% 0% PCC
A24350 Footing 9 26-Oct-20 04-Nov-20 26-Oct-20 04-Nov-20 0% 0% Footing
A24370 Neck Column 9 05-Nov-20 15-Nov-20 05-Nov-20 15-Nov-20 0% 0% Neck Column
A24380 Grade Beam 9 16-Nov-20 25-Nov-20 16-Nov-20 25-Nov-20 0% 0% Grade Beam
A24330 bitumen paint 3 26-Nov-20 29-Nov-20 26-Nov-20 29-Nov-20 0% 0% bitumen paint
A24360 Slab on grade 9 30-Nov-20 09-Dec-20 30-Nov-20 09-Dec-20 0% 0% Slab on grade
A24310 Backfilling 3 10-Dec-20 13-Dec-20 10-Dec-20 13-Dec-20 0% 0% Backfilling
Super Structure 142 14-Dec-20 27-May-21 14-Dec-20 27-May-21 0% 0% 27-May-21, Super Structure
Concrete Works 51 14-Dec-20 10-Feb-21 14-Dec-20 10-Feb-21 0% 0% 10-Feb-21, Concrete Works
A24410 Column 21 14-Dec-20 06-Jan-21 14-Dec-20 06-Jan-21 0% 0% Column
A24390 Beams 9 07-Jan-21 17-Jan-21 07-Jan-21 17-Jan-21 0% 0% Beams
A24400 Slabs 21 18-Jan-21 10-Feb-21 18-Jan-21 10-Feb-21 0% 0% Slabs
Finishing Works 91 11-Feb-21 27-May-21 11-Feb-21 27-May-21 0% 0% 27-May-21, Finishing Works
A23810 Masonry Works 14 11-Feb-21 27-Feb-21 11-Feb-21 27-Feb-21 0% 0% Masonry Works
A23870 Cement Plastering 28 28-Feb-21 31-Mar-21 28-Feb-21 31-Mar-21 0% 0% Cement Plastering
A24270 Roof finishes 14 01-Apr-21 17-Apr-21 01-Apr-21 17-Apr-21 0% 0% Roof finishes
A23850 Windows 14 01-Apr-21 17-Apr-21 01-Apr-21 17-Apr-21 0% 0% Windows
A23840 Doors 14 01-Apr-21 17-Apr-21 01-Apr-21 17-Apr-21 0% 0% Doors
A23860 Floor finish (concrete screed & epoxy) 17 18-Apr-21 06-May-21 18-Apr-21 06-May-21 0% 0% Floor finish (concrete screed & epoxy)
A23900 Painting works 11 16-May-21 27-May-21 16-May-21 27-May-21 0% 0% Painting works

Actual Level of Effort Remaining Work Milestone Date Revision Checked Approved
Page 8 of 19
Actual Work Critical Remaining Work summary 11-Jun-20 UTS
UPDATED TIME SCHEDULE Al Ihsaa- Educational Complex in Al Jubail D.D 11-Jun-20

Activity ID Activity Name Original Duration BL1 Start BL1 Finish Start Finish Schedule % Performance %Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Complete Complete
A A A A A A A A A A A A A A
Mechanical Works 30 01-Apr-21 05-May-21 01-Apr-21 05-May-21 0% 0% 05-May-21, Mechanical Works
A23740 General Exhaust Fan 12 01-Apr-21 14-Apr-21 01-Apr-21 14-Apr-21 0% 0% General Exhaust Fan
A23960 Gargouri drainage 9 15-Apr-21 25-Apr-21 15-Apr-21 25-Apr-21 0% 0% Gargouri drainage
A24160 fire extinguisher 9 26-Apr-21 05-May-21 26-Apr-21 05-May-21 0% 0% fire extinguisher
Electrical Works 66 28-Feb-21 15-May-21 28-Feb-21 15-May-21 0% 0% 15-May-21, Electrical Works
A24020 Lighting System First Fix (Conduits) 24 28-Feb-21 27-Mar-21 28-Feb-21 27-Mar-21 0% 0% Lighting System First Fix (Conduits)
A24130 Fire Alarm System First Fix 24 06-Mar-21 01-Apr-21 06-Mar-21 01-Apr-21 0% 0% Fire Alarm System First Fix
A24190 Lighting System Second Fix (Wires) 14 28-Mar-21 12-Apr-21 28-Mar-21 12-Apr-21 0% 0% Lighting System Second Fix (Wires)
A24060 Conductors and cables 12 28-Mar-21 10-Apr-21 28-Mar-21 10-Apr-21 0% 0% Conductors and cables
A24210 Fire Alarm System Second Fix 15 03-Apr-21 19-Apr-21 03-Apr-21 19-Apr-21 0% 0% Fire Alarm System Second Fix
A24030 Power Installation 9 11-Apr-21 20-Apr-21 11-Apr-21 20-Apr-21 0% 0% Power Installation
A24070 Earthing system 7 13-Apr-21 20-Apr-21 13-Apr-21 20-Apr-21 0% 0% Earthing system
A24000 Panel Boards 7 13-Apr-21 20-Apr-21 13-Apr-21 20-Apr-21 0% 0% Panel Boards
A24220 Fire Alarm System Third Fix 15 20-Apr-21 06-May-21 20-Apr-21 06-May-21 0% 0% Fire Alarm System Third Fix
A24200 Lighting System Third Fix (Fixtures) 14 29-Apr-21 15-May-21 29-Apr-21 15-May-21 0% 0% Lighting System Third Fix (Fixtures)
Gate (A & B) 218 19-Sep-20 31-May-21 19-Sep-20 31-May-21 0.34% 0% 31-May-21, Gate (A & B)
Civil Works 218 19-Sep-20 31-May-21 19-Sep-20 31-May-21 0.37% 0% 31-May-21, Civil Works
Sub-Structure 58 19-Sep-20 25-Nov-20 19-Sep-20 25-Nov-20 2.17% 0% 25-Nov-20, Sub-Structure
A24990 Excavation for foundation 5 19-Sep-20 24-Sep-20 19-Sep-20 24-Sep-20 60% 0% Excavation for foundation
A25010 Soil termite treatment 2 26-Sep-20 27-Sep-20 26-Sep-20 27-Sep-20 0% 0% Soil termite treatment
A25030 PCC 9 28-Sep-20 07-Oct-20 28-Sep-20 07-Oct-20 0% 0% PCC
A25040 Footing 9 08-Oct-20 18-Oct-20 08-Oct-20 18-Oct-20 0% 0% Footing
A25060 Neck Column 9 19-Oct-20 28-Oct-20 19-Oct-20 28-Oct-20 0% 0% Neck Column
A25070 Grade Beam 9 29-Oct-20 08-Nov-20 29-Oct-20 08-Nov-20 0% 0% Grade Beam
A25020 bitumen paint 3 09-Nov-20 11-Nov-20 09-Nov-20 11-Nov-20 0% 0% bitumen paint
A25050 Slab on grade 9 12-Nov-20 22-Nov-20 12-Nov-20 22-Nov-20 0% 0% Slab on grade
A30060 Backfilling 3 23-Nov-20 25-Nov-20 23-Nov-20 25-Nov-20 0% 0% Backfilling
Super Structure 160 26-Nov-20 31-May-21 26-Nov-20 31-May-21 0% 0% 31-May-21, Super Structure
Concrete Works 51 26-Nov-20 24-Jan-21 26-Nov-20 24-Jan-21 0% 0% 24-Jan-21, Concrete Works
A25100 Column 21 26-Nov-20 20-Dec-20 26-Nov-20 20-Dec-20 0% 0% Column
A25080 Beams 9 21-Dec-20 30-Dec-20 21-Dec-20 30-Dec-20 0% 0% Beams
A25090 Slabs 21 31-Dec-20 24-Jan-21 31-Dec-20 24-Jan-21 0% 0% Slabs
Finishing Works 109 25-Jan-21 31-May-21 25-Jan-21 31-May-21 0% 0% 31-May-21, Finishing Works
A24500 Masonry Works 18 25-Jan-21 14-Feb-21 25-Jan-21 14-Feb-21 0% 0% Masonry Works
A24560 Cement Plastering 14 15-Feb-21 02-Mar-21 15-Feb-21 02-Mar-21 0% 0% Cement Plastering
A24960 Roof finishes 21 03-Mar-21 27-Mar-21 03-Mar-21 27-Mar-21 0% 0% Roof finishes
A24520 Waterproofin g for Bathroom & Kitchen 7 03-Mar-21 10-Mar-21 03-Mar-21 10-Mar-21 0% 0% Waterproofin g for Bathroom & Kitchen
A24950 Tile s for Walls 17 11-Mar-21 30-Mar-21 11-Mar-21 30-Mar-21 0% 0% Tile s for Walls
A24600 Aluminium strip 7 28-Mar-21 04-Apr-21 28-Mar-21 04-Apr-21 0% 0% Aluminium strip
A24870 Specialies 4 31-Mar-21 04-Apr-21 31-Mar-21 04-Apr-21 0% 0% Specialies
A24550 Floor Finish (tiling & scerting) 17 05-Apr-21 24-Apr-21 05-Apr-21 24-Apr-21 0% 0% Floor Finish (tiling & scerting)
A24970 External metal shades 14 25-Apr-21 10-May-21 25-Apr-21 10-May-21 0% 0% External metal shades
A24540 Windows 7 25-Apr-21 02-May-21 25-Apr-21 02-May-21 0% 0% Windows
A24530 Doors 7 25-Apr-21 02-May-21 25-Apr-21 02-May-21 0% 0% Doors
A24510 Handrail & Protections 14 25-Apr-21 10-May-21 25-Apr-21 10-May-21 0% 0% Handrail & Protections
A24590 Painting works 11 19-May-21 31-May-21 19-May-21 31-May-21 0% 0% Painting works
Mechanical Works 80 15-Feb-21 18-May-21 15-Feb-21 18-May-21 0% 0% 18-May-21, Mechanical Works
A24450 Domestic Water Supply System 14 15-Feb-21 02-Mar-21 15-Feb-21 02-Mar-21 0% 0% Domestic Water Supply System
A24640 Sanitary System 11 03-Mar-21 15-Mar-21 03-Mar-21 15-Mar-21 0% 0% Sanitary System
A26500 Sanitary Specialties 9 16-Mar-21 25-Mar-21 16-Mar-21 25-Mar-21 0% 0% Sanitary Specialties

Actual Level of Effort Remaining Work Milestone Date Revision Checked Approved
Page 9 of 19
Actual Work Critical Remaining Work summary 11-Jun-20 UTS
UPDATED TIME SCHEDULE Al Ihsaa- Educational Complex in Al Jubail D.D 11-Jun-20

Activity ID Activity Name Original Duration BL1 Start BL1 Finish Start Finish Schedule % Performance %Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Complete Complete
A A A A A A A A A A A A A A
A24660 Plumbing Fixtures 12 25-Apr-21 08-May-21 25-Apr-21 08-May-21 0% 0% Plumbing Fixtures
A24430 General Exhaust Fan 9 25-Apr-21 04-May-21 25-Apr-21 04-May-21 0% 0% General Exhaust Fan
A24420 DX-Split units 7 05-May-21 12-May-21 05-May-21 12-May-21 0% 0% DX-Split units
A24850 fire extinguisher 7 11-May-21 18-May-21 11-May-21 18-May-21 0% 0% fire extinguisher
A24470 Electric Water Heaters 5 11-May-21 16-May-21 11-May-21 16-May-21 0% 0% Electric Water Heaters
Electrical Works 77 15-Feb-21 15-May-21 15-Feb-21 15-May-21 0% 0% 15-May-21, Electrical Works
Electrical 77 15-Feb-21 15-May-21 15-Feb-21 15-May-21 0% 0% 15-May-21, Electrical
A24710 Lighting System First Fix (Conduits) 14 15-Feb-21 02-Mar-21 15-Feb-21 02-Mar-21 0% 0% Lighting System First Fix (Conduits)
A24880 Lighting System Second Fix (Wires) 15 03-Mar-21 20-Mar-21 03-Mar-21 20-Mar-21 0% 0% Lighting System Second Fix (Wires)
A24750 Conductors and cables 15 03-Mar-21 20-Mar-21 03-Mar-21 20-Mar-21 0% 0% Conductors and cables
A24690 Panel Boards 14 25-Mar-21 10-Apr-21 25-Mar-21 10-Apr-21 0% 0% Panel Boards
A24720 Power Installation 15 07-Apr-21 24-Apr-21 07-Apr-21 24-Apr-21 0% 0% Power Installation
A24740 Sockets & Switches 12 11-Apr-21 24-Apr-21 11-Apr-21 24-Apr-21 0% 0% Sockets & Switches
A24890 Lighting System Third Fix (Fixtures) 14 29-Apr-21 15-May-21 29-Apr-21 15-May-21 0% 0% Lighting System Third Fix (Fixtures)
Communications 54 15-Feb-21 18-Apr-21 15-Feb-21 18-Apr-21 0% 0% 18-Apr-21, Communications
A24820 Fire Alarm System First Fix 24 15-Feb-21 14-Mar-21 15-Feb-21 14-Mar-21 0% 0% Fire Alarm System First Fix
A24780 Telephone & Data Communication System First Fix 24 15-Feb-21 14-Mar-21 15-Feb-21 14-Mar-21 0% 0% Telephone & Data Communication System First Fix
A24920 Telephone & Data Communication System Second Fix 15 15-Mar-21 31-Mar-21 15-Mar-21 31-Mar-21 0% 0% Telephone & Data Communication System Second Fix
A24900 Fire Alarm System Second Fix 15 15-Mar-21 31-Mar-21 15-Mar-21 31-Mar-21 0% 0% Fire Alarm System Second Fix
A24930 Telephone & Data Communication System Third Fix 15 01-Apr-21 18-Apr-21 01-Apr-21 18-Apr-21 0% 0% Telephone & Data Communication System Third Fix
A24910 Fire Alarm System Third Fix 15 01-Apr-21 18-Apr-21 01-Apr-21 18-Apr-21 0% 0% Fire Alarm System Third Fix
A24810 Public Address system 15 01-Apr-21 18-Apr-21 01-Apr-21 18-Apr-21 0% 0% Public Address system
Water Tank & Pump Room (A) 142 02-Jan-21 16-Jun-21 02-Jan-21 16-Jun-21 0% 0% 16-Jun-21, Water Tank & Pump Room (A)
Civil Works 125 02-Jan-21 27-May-21 02-Jan-21 27-May-21 0% 0% 27-May-21, Civil Works
A25680 Excavation 5 02-Jan-21 07-Jan-21 02-Jan-21 07-Jan-21 0% 0% Excavation
A25700 Soil termite treatment 2 07-Jan-21 10-Jan-21 07-Jan-21 10-Jan-21 0% 0% Soil termite treatment
A25720 PCC 9 10-Jan-21 20-Jan-21 10-Jan-21 20-Jan-21 0% 0% PCC
A25730 Footing 9 20-Jan-21 31-Jan-21 20-Jan-21 31-Jan-21 0% 0% Footing
A25790 Wall 21 31-Jan-21 24-Feb-21 31-Jan-21 24-Feb-21 0% 0% Wall
A25210 Waterproofin g membrane 7 24-Feb-21 04-Mar-21 24-Feb-21 04-Mar-21 0% 0% Waterproofin g membrane
A25190 Masonry Works 4 04-Mar-21 09-Mar-21 04-Mar-21 09-Mar-21 0% 0% Masonry Works
A25690 Backfilling 3 09-Mar-21 13-Mar-21 09-Mar-21 13-Mar-21 0% 0% Backfilling
A25780 Slab 21 13-Mar-21 06-Apr-21 13-Mar-21 06-Apr-21 0% 0% Slab
A25770 Pumps foundation 9 06-Apr-21 17-Apr-21 06-Apr-21 17-Apr-21 0% 0% Pumps foundation
A26510 Pump Room 14 17-Apr-21 03-May-21 17-Apr-21 03-May-21 0% 0% Pump Room
A25200 Cover & Ladder 14 17-Apr-21 03-May-21 17-Apr-21 03-May-21 0% 0% Cover & Ladder
A25250 Waterproof cement plaster 14 03-May-21 19-May-21 03-May-21 19-May-21 0% 0% Waterproof cement plaster
A26520 Waterproofin g Epoxy 7 19-May-21 27-May-21 19-May-21 27-May-21 0% 0% Waterproofing Epoxy
Mechanical Works 8 24-May-21 02-Jun-21 24-May-21 02-Jun-21 0% 0% 02-Jun-21, Mechanical Works
A25150 Piping & Valves 3 24-May-21 27-May-21 24-May-21 27-May-21 0% 0% Piping & Valves
A25320 Water Transfer Pumps 5 27-May-21 02-Jun-21 27-May-21 02-Jun-21 0% 0% Water Transfer Pumps
A25180 Fire Pump 5 27-May-21 02-Jun-21 27-May-21 02-Jun-21 0% 0% Fire Pump
Electrical Works 12 02-Jun-21 16-Jun-21 02-Jun-21 16-Jun-21 0% 0% 16-Jun-21, Electrical Works
A25430 Sockets & Switches 12 02-Jun-21 16-Jun-21 02-Jun-21 16-Jun-21 0% 0% Sockets & Switches
BUILDING (B) 318 30-May-20 10-Jun-21 30-May-20 A 10-Jun-21 0.1% 1.43% 10-Jun-21, BUILDING (B)
Main Building (B) 307 30-May-20 29-May-21 30-May-20 A 29-May-21 0.1% 1.48% 29-May-21, Main Building (B)
Civil Works 307 30-May-20 29-May-21 30-May-20 A 29-May-21 0.15% 2.11% 29-May-21, Civil Works
Sub-Structure 7 19-Sep-20 27-Sep-20 19-Sep-20 27-Sep-20 42.86% 0% 27-Sep-20, Sub-Structure
A26960 Remove of residues 7 19-Sep-20 27-Sep-20 19-Sep-20 27-Sep-20 42.86% 0% Remove of residues
Super Structure 307 30-May-20 29-May-21 30-May-20 A 29-May-21 0% 2.11% 29-May-21, Super Structure
Concrete Works 70 28-Sep-20 17-Dec-20 28-Sep-20 17-Dec-20 0% 0% 17-Dec-20, Concrete Works
Actual Level of Effort Remaining Work Milestone Date Revision Checked Approved
Page 10 of 19
Actual Work Critical Remaining Work summary 11-Jun-20 UTS
UPDATED TIME SCHEDULE Al Ihsaa- Educational Complex in Al Jubail D.D 11-Jun-20

Activity ID Activity Name Original Duration BL1 Start BL1 Finish Start Finish Schedule % Performance %Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Complete Complete
A A A A A A A A A A A A A A
Supporting Works 42 22-Oct-20 09-Dec-20 22-Oct-20 09-Dec-20 0% 0% 09-Dec-20, Supporting Works
A27060 Foundations 21 22-Oct-20 15-Nov-20 22-Oct-20 15-Nov-20 0% 0% Foundations
A27020 Beams 7 16-Nov-20 23-Nov-20 16-Nov-20 23-Nov-20 0% 0% Beams
A27030 Columns 14 24-Nov-20 09-Dec-20 24-Nov-20 09-Dec-20 0% 0% Columns
Check and treatment 21 28-Sep-20 21-Oct-20 28-Sep-20 21-Oct-20 0% 0% 21-Oct-20, Check and treatment
A27000 Checking 7 28-Sep-20 05-Oct-20 28-Sep-20 05-Oct-20 0% 0% Checking
A27010 Treatments 14 06-Oct-20 21-Oct-20 06-Oct-20 21-Oct-20 0% 0% Treatments
Casting Works 7 10-Dec-20 17-Dec-20 10-Dec-20 17-Dec-20 0% 0% 17-Dec-20, Casting Works
A27090 Rambs 7 10-Dec-20 17-Dec-20 10-Dec-20 17-Dec-20 0% 0% Rambs
Finishing Works 307 30-May-20 29-May-21 30-May-20 A 29-May-21 0% 3.33% 29-May-21, Finishing Works
A26630 Waterproofin g (check & treatment) 14 30-May-20 14-Jun-20 30-May-20 A 14-Feb-21 0% 70% Waterproofin g (check & treatment)
A26610 Masonry Works 24 19-Dec-20 14-Jan-21 19-Dec-20 14-Jan-21 0% 0% Masonry Works
A26670 Internal Cement Plastering 21 16-Jan-21 08-Feb-21 16-Jan-21 08-Feb-21 0% 0% Internal Cement Plastering
A26720 Gypsum board 14 14-Feb-21 02-Mar-21 14-Feb-21 02-Mar-21 0% 0% Gypsum board
A26660 Floor finish (check & treatment) 23 24-Feb-21 22-Mar-21 24-Feb-21 22-Mar-21 0% 0% Floor finish (check & treatment)
A27200 Ceiling Tiles 9 02-Mar-21 13-Mar-21 02-Mar-21 13-Mar-21 0% 0% Ceiling Tiles
A27170 Tile s for Walls 9 02-Mar-21 13-Mar-21 02-Mar-21 13-Mar-21 0% 0% Tile s for Walls
A26990 Specialies 9 13-Mar-21 23-Mar-21 13-Mar-21 23-Mar-21 0% 0% Specialies
A26620 Handrail & Protections 14 23-Mar-21 07-Apr-21 23-Mar-21 07-Apr-21 0% 0% Handrail & Protections
A26710 Aluminium strip 12 08-Apr-21 21-Apr-21 08-Apr-21 21-Apr-21 0% 0% Aluminium strip
A26680 Internal Painting Works (Primer + Filler + 1st Coat) 14 10-Apr-21 25-Apr-21 10-Apr-21 25-Apr-21 0% 0% Internal Painting Works (Primer + Filler + 1st Coat)
A26700 External Painting works 21 22-Apr-21 16-May-21 22-Apr-21 16-May-21 0% 0% External Painting works
A26730 Counters 7 26-Apr-21 03-May-21 26-Apr-21 03-May-21 0% 0% Counters
A26650 Windows 20 26-Apr-21 18-May-21 26-Apr-21 18-May-21 0% 0% Windows
A26640 Doors 18 26-Apr-21 16-May-21 26-Apr-21 16-May-21 0% 0% Doors
A27160 Painting Works (Final Coat) 9 19-May-21 29-May-21 19-May-21 29-May-21 0% 0% Painting Works (Final Coat)
Mechanical Works 104 16-Jan-21 16-May-21 16-Jan-21 16-May-21 0% 0% 16-May-21, Mechanical Works
Plumbing 104 16-Jan-21 16-May-21 16-Jan-21 16-May-21 0% 0% 16-May-21, Plumbing
A26560 Domestic Water Supply System 15 16-Jan-21 01-Feb-21 16-Jan-21 01-Feb-21 0% 0% Domestic Water Supply System
A26750 Sanitary System 7 02-Feb-21 09-Feb-21 02-Feb-21 09-Feb-21 0% 0% Sanitary System
A26760 Roof Scupper Drain 8 10-Feb-21 18-Feb-21 10-Feb-21 18-Feb-21 0% 0% Roof Scupper Drain
A26570 Isolation valve 7 24-Feb-21 03-Mar-21 24-Feb-21 03-Mar-21 0% 0% Isolation valve
A26740 Water Storage Tanks 14 04-Mar-21 20-Mar-21 04-Mar-21 20-Mar-21 0% 0% Water Storage Tanks
A26770 Plumbing Fixtures 17 21-Mar-21 08-Apr-21 21-Mar-21 08-Apr-21 0% 0% Plumbing Fixtures
A26580 Electric Water Heaters 11 04-May-21 16-May-21 04-May-21 16-May-21 0% 0% Electric Water Heaters
Fire Fighting 102 16-Jan-21 13-May-21 16-Jan-21 13-May-21 0% 0% 13-May-21, Fire Fighting
A26590 Piping 24 16-Jan-21 11-Feb-21 16-Jan-21 11-Feb-21 0% 0% Piping
A26600 Fire Hose Cabinet & Accessories 9 26-Apr-21 05-May-21 26-Apr-21 05-May-21 0% 0% Fire Hose Cabinet & Accessories
A26970 fire extinguisher 7 06-May-21 13-May-21 06-May-21 13-May-21 0% 0% fire extinguisher
HVAC 45 06-Mar-21 26-Apr-21 06-Mar-21 26-Apr-21 0% 0% 26-Apr-21, HVAC
A26550 HVAC Ducts and Casings 9 06-Mar-21 15-Mar-21 06-Mar-21 15-Mar-21 0% 0% HVAC Ducts and Casings
A26540 General Exhaust Fan 9 16-Mar-21 25-Mar-21 16-Mar-21 25-Mar-21 0% 0% General Exhaust Fan
A26530 DX-Split units 24 27-Mar-21 22-Apr-21 27-Mar-21 22-Apr-21 0% 0% DX-Split units
A26950 Air Curtain 3 24-Apr-21 26-Apr-21 24-Apr-21 26-Apr-21 0% 0% Air Curtain
Electrical Works 103 16-Jan-21 15-May-21 16-Jan-21 15-May-21 0% 0% 15-May-21, Electrical Works
Electrical 103 16-Jan-21 15-May-21 16-Jan-21 15-May-21 0% 0% 15-May-21, Electrical
A26820 Lighting System First Fix (Conduits) 21 16-Jan-21 08-Feb-21 16-Jan-21 08-Feb-21 0% 0% Lighting System First Fix (Conduits)
A27210 Remove Pre-Installed Electrical Works 24 09-Feb-21 08-Mar-21 09-Feb-21 08-Mar-21 0% 0% Remove Pre-Installed Electrical Works
A27100 Lighting System Second Fix (Wires) 21 09-Feb-21 04-Mar-21 09-Feb-21 04-Mar-21 0% 0% Lighting System Second Fix (Wires)
A26860 Conductors and cables 24 09-Mar-21 05-Apr-21 09-Mar-21 05-Apr-21 0% 0% Conductors and cables

Actual Level of Effort Remaining Work Milestone Date Revision Checked Approved
Page 11 of 19
Actual Work Critical Remaining Work summary 11-Jun-20 UTS
UPDATED TIME SCHEDULE Al Ihsaa- Educational Complex in Al Jubail D.D 11-Jun-20

Activity ID Activity Name Original Duration BL1 Start BL1 Finish Start Finish Schedule % Performance %Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Complete Complete
A A A A A A A A A A A A A A
A26880 Lightening Protection System 14 25-Mar-21 10-Apr-21 25-Mar-21 10-Apr-21 0% 0% Lightening Protection System
A26870 Earthing system 14 25-Mar-21 10-Apr-21 25-Mar-21 10-Apr-21 0% 0% Earthing system
A26850 Sockets & Switches 24 25-Mar-21 21-Apr-21 25-Mar-21 21-Apr-21 0% 0% Sockets & Switches
A26840 Bells system 14 25-Mar-21 10-Apr-21 25-Mar-21 10-Apr-21 0% 0% Bells system
A26800 Panel Boards 14 25-Mar-21 10-Apr-21 25-Mar-21 10-Apr-21 0% 0% Panel Boards
A26830 Power Installation 18 06-Apr-21 26-Apr-21 06-Apr-21 26-Apr-21 0% 0% Power Installation
A27110 Lighting System Third Fix (Fixtures) 14 29-Apr-21 15-May-21 29-Apr-21 15-May-21 0% 0% Lighting System Third Fix (Fixtures)
Communications 102 16-Jan-21 13-May-21 16-Jan-21 13-May-21 0% 0% 13-May-21, Communications
A26890 Telephone & Data Communication System First Fix 30 16-Jan-21 18-Feb-21 16-Jan-21 18-Feb-21 0% 0% Telephone & Data Communication System First Fix
A26930 Fire Alarm System First Fix 30 09-Feb-21 15-Mar-21 09-Feb-21 15-Mar-21 0% 0% Fire Alarm System First Fix
A27140 Telephone & Data Communication System Second Fix 30 20-Feb-21 25-Mar-21 20-Feb-21 25-Mar-21 0% 0% Telephone & Data Communication System Second Fix
A27120 Fire Alarm System Second Fix 30 16-Mar-21 19-Apr-21 16-Mar-21 19-Apr-21 0% 0% Fire Alarm System Second Fix
A26920 Public Address system 21 27-Mar-21 19-Apr-21 27-Mar-21 19-Apr-21 0% 0% Public Address system
A26910 Floor Boxes 21 27-Mar-21 19-Apr-21 27-Mar-21 19-Apr-21 0% 0% Floor Boxes
A27150 Telephone & Data Communication System Third Fix 21 20-Apr-21 13-May-21 20-Apr-21 13-May-21 0% 0% Telephone & Data Communication System Third Fix
A27130 Fire Alarm System Third Fix 21 20-Apr-21 13-May-21 20-Apr-21 13-May-21 0% 0% Fire Alarm System Third Fix
Electrical Room (B) 126 16-Jan-21 10-Jun-21 16-Jan-21 10-Jun-21 0% 0% 10-Jun-21, Electrical Room (B)
Civil Works 106 16-Jan-21 18-May-21 16-Jan-21 18-May-21 0% 0% 18-May-21, Civil Works
Sub-Structure 42 16-Jan-21 04-Mar-21 16-Jan-21 04-Mar-21 0% 0% 04-Mar-21, Sub-Structure
A27420 Excavation for foundation 5 16-Jan-21 20-Jan-21 16-Jan-21 20-Jan-21 0% 0% Excavation for foundation
A27440 Soil termite treatment 2 21-Jan-21 23-Jan-21 21-Jan-21 23-Jan-21 0% 0% Soil termite treatment
A27460 PCC 2 24-Jan-21 25-Jan-21 24-Jan-21 25-Jan-21 0% 0% PCC
A27470 Footing 5 26-Jan-21 31-Jan-21 26-Jan-21 31-Jan-21 0% 0% Footing
A27490 Neck Column 7 01-Feb-21 08-Feb-21 01-Feb-21 08-Feb-21 0% 0% Neck Column
A27500 Grade Beam 7 09-Feb-21 16-Feb-21 09-Feb-21 16-Feb-21 0% 0% Grade Beam
A27450 bitumen paint 2 17-Feb-21 18-Feb-21 17-Feb-21 18-Feb-21 0% 0% bitumen paint
A27480 Slab on grade 7 20-Feb-21 27-Feb-21 20-Feb-21 27-Feb-21 0% 0% Slab on grade
A27430 Backfilling 5 28-Feb-21 04-Mar-21 28-Feb-21 04-Mar-21 0% 0% Backfilling
Super Structure 64 06-Mar-21 18-May-21 06-Mar-21 18-May-21 0% 0% 18-May-21, Super Structure
Concrete Works 23 06-Mar-21 31-Mar-21 06-Mar-21 31-Mar-21 0% 0% 31-Mar-21, Concrete Works
A27530 Column 7 06-Mar-21 13-Mar-21 06-Mar-21 13-Mar-21 0% 0% Column
A27510 Beams 7 14-Mar-21 21-Mar-21 14-Mar-21 21-Mar-21 0% 0% Beams
A27520 Slabs 9 22-Mar-21 31-Mar-21 22-Mar-21 31-Mar-21 0% 0% Slabs
Finishing Works 41 01-Apr-21 18-May-21 01-Apr-21 18-May-21 0% 0% 18-May-21, Finishing Works
A27230 Masonry Works 15 01-Apr-21 18-Apr-21 01-Apr-21 18-Apr-21 0% 0% Masonry Works
A27270 Internal Cement Plastering 9 19-Apr-21 28-Apr-21 19-Apr-21 28-Apr-21 0% 0% Internal Cement Plastering
A27410 Roof finishes 5 29-Apr-21 04-May-21 29-Apr-21 04-May-21 0% 0% Roof finishes
A27250 Windows 5 29-Apr-21 04-May-21 29-Apr-21 04-May-21 0% 0% Windows
A27240 Doors 5 29-Apr-21 04-May-21 29-Apr-21 04-May-21 0% 0% Doors
A27260 Floor finish (concrete screed & epoxy) 5 05-May-21 10-May-21 05-May-21 10-May-21 0% 0% Floor finish (concrete screed & epoxy)
A27280 External Painting works 7 11-May-21 18-May-21 11-May-21 18-May-21 0% 0% External Painting works
Mechanical Works 10 29-Apr-21 10-May-21 29-Apr-21 10-May-21 0% 0% 10-May-21, Mechanical Works
A27220 General Exhaust Fan 4 29-Apr-21 03-May-21 29-Apr-21 03-May-21 0% 0% General Exhaust Fan
A27290 Gargouri drainage 3 04-May-21 06-May-21 04-May-21 06-May-21 0% 0% Gargouri drainage
A27360 fire extinguisher 3 08-May-21 10-May-21 08-May-21 10-May-21 0% 0% fire extinguisher
Electrical Works 46 19-Apr-21 10-Jun-21 19-Apr-21 10-Jun-21 0% 0% 10-Jun-21, Electrical Works
A27350 Fire Alarm System First Fix 5 19-Apr-21 24-Apr-21 19-Apr-21 24-Apr-21 0% 0% Fire Alarm System First Fix
A27310 Lighting System First Fix (Conduits) 5 19-Apr-21 24-Apr-21 19-Apr-21 24-Apr-21 0% 0% Lighting System First Fix (Conduits)
A27330 Conductors and cables 3 25-Apr-21 27-Apr-21 25-Apr-21 27-Apr-21 0% 0% Conductors and cables
A27320 Power Installation 3 28-Apr-21 01-May-21 28-Apr-21 01-May-21 0% 0% Power Installation

Actual Level of Effort Remaining Work Milestone Date Revision Checked Approved
Page 12 of 19
Actual Work Critical Remaining Work summary 11-Jun-20 UTS
UPDATED TIME SCHEDULE Al Ihsaa- Educational Complex in Al Jubail D.D 11-Jun-20

Activity ID Activity Name Original Duration BL1 Start BL1 Finish Start Finish Schedule % Performance %Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Complete Complete
A A A A A A A A A A A A A A
A27390 Fire Alarm System Second Fix 5 19-May-21 24-May-21 19-May-21 24-May-21 0% 0% Fire Alarm System Second Fix
A27370 Lighting System Second Fix (Wires) 5 19-May-21 24-May-21 19-May-21 24-May-21 0% 0% Lighting System Second Fix (Wires)
A27300 Panel Boards 5 25-May-21 30-May-21 25-May-21 30-May-21 0% 0% Panel Boards
A27340 Earthing system 5 31-May-21 05-Jun-21 31-May-21 05-Jun-21 0% 0% Earthing system
A27400 Fire Alarm System Third Fix 5 06-Jun-21 10-Jun-21 06-Jun-21 10-Jun-21 0% 0% Fire Alarm System Third Fix
A27380 Lighting System Third Fix (Fixtures) 5 06-Jun-21 10-Jun-21 06-Jun-21 10-Jun-21 0% 0% Lighting System Third Fix (Fixtures)
BUILDING (C) 279 15-Aug-20 06-Jul-21 15-Aug-20 06-Jul-21 1.94% 0% 06-Jul-21, BUILDING (C)
Main Building (C) 265 15-Aug-20 20-Jun-21 15-Aug-20 20-Jun-21 2.37% 0% 20-Jun-21, Main Building (C)
Civil Works 265 15-Aug-20 20-Jun-21 15-Aug-20 20-Jun-21 3.1% 0% 20-Jun-21, Civil Works
Sub-Structure 9 15-Aug-20 24-Aug-20 15-Aug-20 24-Aug-20 100% 0% 24-Aug-20, Sub-Structure
A27920 Remove of residues 9 15-Aug-20 24-Aug-20 15-Aug-20 24-Aug-20 100% 0% Remove of residues
Super Structure 256 25-Aug-20 20-Jun-21 25-Aug-20 20-Jun-21 2.87% 0% 20-Jun-21, Super Structure
Concrete Works 113 25-Aug-20 04-Jan-21 25-Aug-20 04-Jan-21 11.15% 0% 04-Jan-21, Concrete Works
Supporting Works 66 21-Sep-20 07-Dec-20 21-Sep-20 07-Dec-20 1.7% 0% 07-Dec-20, Supporting Works
A27990 Foundations 28 21-Sep-20 24-Oct-20 21-Sep-20 24-Oct-20 3.57% 0% Foundations
A27980 Columns 24 25-Oct-20 21-Nov-20 25-Oct-20 21-Nov-20 0% 0% Columns
A27970 Beams 14 22-Nov-20 07-Dec-20 22-Nov-20 07-Dec-20 0% 0% Beams
Check and treatment 23 25-Aug-20 20-Sep-20 25-Aug-20 20-Sep-20 100% 0% 20-Sep-20, Check and treatment
A27950 Checking 9 25-Aug-20 03-Sep-20 25-Aug-20 03-Sep-20 100% 0% Checking
A27960 Treatments 14 05-Sep-20 20-Sep-20 05-Sep-20 20-Sep-20 100% 0% Treatments
Casting Works 24 08-Dec-20 04-Jan-21 08-Dec-20 04-Jan-21 0% 0% 04-Jan-21, Casting Works
A28120 Slabs & Beams 14 08-Dec-20 23-Dec-20 08-Dec-20 23-Dec-20 0% 0% Slabs & Beams
A28110 Columns for staircase 5 24-Dec-20 29-Dec-20 24-Dec-20 29-Dec-20 0% 0% Columns for staircase
A28000 Rambs 5 30-Dec-20 04-Jan-21 30-Dec-20 04-Jan-21 0% 0% Rambs
Finishing Works 143 05-Jan-21 20-Jun-21 05-Jan-21 20-Jun-21 0% 0% 20-Jun-21, Finishing Works
A28130 Masonry Works 14 05-Jan-21 20-Jan-21 05-Jan-21 20-Jan-21 0% 0% Masonry Works
A28210 External Cement Plastering 17 21-Jan-21 09-Feb-21 21-Jan-21 09-Feb-21 0% 0% External Cement Plastering
A28190 Internal Cement Plastering 14 21-Jan-21 06-Feb-21 21-Jan-21 06-Feb-21 0% 0% Internal Cement Plastering
A28150 Waterproofin g for Bathroom & Kitchen 3 07-Feb-21 09-Feb-21 07-Feb-21 09-Feb-21 0% 0% Waterproofin g for Bathroom & Kitchen
A28300 Roof sandwich panels 9 10-Feb-21 20-Feb-21 10-Feb-21 20-Feb-21 0% 0% Roof sandwich panels
A28240 Gypsum board 9 10-Feb-21 20-Feb-21 10-Feb-21 20-Feb-21 0% 0% Gypsum board
A28260 Specialies 14 13-Feb-21 28-Feb-21 13-Feb-21 28-Feb-21 0% 0% Specialies
A28310 Ceiling Tiles 21 21-Feb-21 16-Mar-21 21-Feb-21 16-Mar-21 0% 0% Ceiling Tiles
A28290 Roof finishes 14 21-Feb-21 08-Mar-21 21-Feb-21 08-Mar-21 0% 0% Roof finishes
A28280 Tile s for Walls 7 01-Mar-21 08-Mar-21 01-Mar-21 08-Mar-21 0% 0% Tile s for Walls
A28170 Windows 24 09-Mar-21 05-Apr-21 09-Mar-21 05-Apr-21 0% 0% Windows
A28160 Doors 15 09-Mar-21 25-Mar-21 09-Mar-21 25-Mar-21 0% 0% Doors
A28140 Handrail & Protections 14 09-Mar-21 24-Mar-21 09-Mar-21 24-Mar-21 0% 0% Handrail & Protections
A28220 External Painting works 14 17-Mar-21 01-Apr-21 17-Mar-21 01-Apr-21 0% 0% External Painting works
A28230 Aluminium strip 7 25-Mar-21 01-Apr-21 25-Mar-21 01-Apr-21 0% 0% Aluminium strip
A28200 Internal Painting Works (Primer + Filler + 1st Coat) 14 06-Apr-21 21-Apr-21 06-Apr-21 21-Apr-21 0% 0% Internal Painting Works (Primer + Filler + 1st Coat)
A28250 Counters 16 22-Apr-21 10-May-21 22-Apr-21 10-May-21 0% 0% Counters
A28180 Floor Finish (tiling & scerting) 24 22-Apr-21 19-May-21 22-Apr-21 19-May-21 0% 0% Floor Finish (tiling & scerting)
A28270 Painting Works (Final Coat) 9 10-Jun-21 20-Jun-21 10-Jun-21 20-Jun-21 0% 0% Painting Works (Final Coat)
Mechanical Works 120 21-Jan-21 09-Jun-21 21-Jan-21 09-Jun-21 0% 0% 09-Jun-21, Mechanical Works
Plumbing 113 21-Jan-21 01-Jun-21 21-Jan-21 01-Jun-21 0% 0% 01-Jun-21, Plumbing
A27750 Sanitary System 9 21-Jan-21 31-Jan-21 21-Jan-21 31-Jan-21 0% 0% Sanitary System
A27570 Domestic Water Supply System 9 21-Jan-21 31-Jan-21 21-Jan-21 31-Jan-21 0% 0% Domestic Water Supply System
A27580 Isolation valve 3 01-Feb-21 03-Feb-21 01-Feb-21 03-Feb-21 0% 0% Isolation valve
A27760 Roof Scupper Drain 6 09-Mar-21 15-Mar-21 09-Mar-21 15-Mar-21 0% 0% Roof Scupper Drain

Actual Level of Effort Remaining Work Milestone Date Revision Checked Approved
Page 13 of 19
Actual Work Critical Remaining Work summary 11-Jun-20 UTS
UPDATED TIME SCHEDULE Al Ihsaa- Educational Complex in Al Jubail D.D 11-Jun-20

Activity ID Activity Name Original Duration BL1 Start BL1 Finish Start Finish Schedule % Performance %Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Complete Complete
A A A A A A A A A A A A A A
A27770 Plumbing Fixtures 11 20-May-21 01-Jun-21 20-May-21 01-Jun-21 0% 0% Plumbing Fixtures
A27740 Water Storage Tanks 11 20-May-21 01-Jun-21 20-May-21 01-Jun-21 0% 0% Water Storage Tanks
A27590 Electric Water Heaters 11 20-May-21 01-Jun-21 20-May-21 01-Jun-21 0% 0% Electric Water Heaters
Fire Fighting 102 07-Feb-21 05-Jun-21 07-Feb-21 05-Jun-21 0% 0% 05-Jun-21, Fire Fighting
A27600 Piping 5 07-Feb-21 11-Feb-21 07-Feb-21 11-Feb-21 0% 0% Piping
A27610 Fire Hose Cabinet & Accessories 21 22-Apr-21 16-May-21 22-Apr-21 16-May-21 0% 0% Fire Hose Cabinet & Accessories
A27930 fire extinguisher 7 20-May-21 27-May-21 20-May-21 27-May-21 0% 0% fire extinguisher
A28320 Testing and calibrating existing works 7 29-May-21 05-Jun-21 29-May-21 05-Jun-21 0% 0% Testing and calibrating existing works
HVAC 56 06-Apr-21 09-Jun-21 06-Apr-21 09-Jun-21 0% 0% 09-Jun-21, HVAC
A27550 General Exhaust Fan 9 06-Apr-21 15-Apr-21 06-Apr-21 15-Apr-21 0% 0% General Exhaust Fan
A27560 HVAC Ducts and Casings 14 17-Apr-21 02-May-21 17-Apr-21 02-May-21 0% 0% HVAC Ducts and Casings
A27540 DX-Split units 28 03-May-21 03-Jun-21 03-May-21 03-Jun-21 0% 0% DX-Split units
A27910 Air Curtain 5 05-Jun-21 09-Jun-21 05-Jun-21 09-Jun-21 0% 0% Air Curtain
Electrical Works 116 21-Jan-21 05-Jun-21 21-Jan-21 05-Jun-21 0% 0% 05-Jun-21, Electrical Works
Electrical 116 21-Jan-21 05-Jun-21 21-Jan-21 05-Jun-21 0% 0% 05-Jun-21, Electrical
A27800 Power Installation 9 21-Jan-21 31-Jan-21 21-Jan-21 31-Jan-21 0% 0% Power Installation
A27790 Lighting System First Fix (Conduits) 7 21-Jan-21 28-Jan-21 21-Jan-21 28-Jan-21 0% 0% Lighting System First Fix (Conduits)
A27830 Conductors and cables 7 01-Feb-21 08-Feb-21 01-Feb-21 08-Feb-21 0% 0% Conductors and cables
A28010 Lighting System Second Fix (Wires) 7 15-Apr-21 22-Apr-21 15-Apr-21 22-Apr-21 0% 0% Lighting System Second Fix (Wires)
A27850 Lightening Protection System 9 24-Apr-21 03-May-21 24-Apr-21 03-May-21 0% 0% Lightening Protection System
A27840 Earthing system 9 24-Apr-21 03-May-21 24-Apr-21 03-May-21 0% 0% Earthing system
A27810 Bells system 9 24-Apr-21 03-May-21 24-Apr-21 03-May-21 0% 0% Bells system
A27780 Panel Boards 9 24-Apr-21 03-May-21 24-Apr-21 03-May-21 0% 0% Panel Boards
A27820 Sockets & Switches 14 04-May-21 19-May-21 04-May-21 19-May-21 0% 0% Sockets & Switches
A28020 Lighting System Third Fix (Fixtures) 14 20-May-21 05-Jun-21 20-May-21 05-Jun-21 0% 0% Lighting System Third Fix (Fixtures)
Communications 112 21-Jan-21 31-May-21 21-Jan-21 31-May-21 0% 0% 31-May-21, Communications
A27900 Fire Alarm System First Fix 12 21-Jan-21 03-Feb-21 21-Jan-21 03-Feb-21 0% 0% Fire Alarm System First Fix
A27860 Telephone & Data Communication System First Fix 12 21-Jan-21 03-Feb-21 21-Jan-21 03-Feb-21 0% 0% Telephone & Data Communication System First Fix
A28050 Telephone & Data Communication System Second Fix 9 22-Apr-21 02-May-21 22-Apr-21 02-May-21 0% 0% Telephone & Data Communication System Second Fix
A28030 Fire Alarm System Second Fix 9 22-Apr-21 02-May-21 22-Apr-21 02-May-21 0% 0% Fire Alarm System Second Fix
A27890 Public Address system 9 03-May-21 12-May-21 03-May-21 12-May-21 0% 0% Public Address system
A27880 Floor Boxes 9 03-May-21 12-May-21 03-May-21 12-May-21 0% 0% Floor Boxes
A28330 Check in and check out monitoring system 7 13-May-21 20-May-21 13-May-21 20-May-21 0% 0% Check in and check out monitoring system
A28060 Telephone & Data Communication System Third Fix 9 22-May-21 31-May-21 22-May-21 31-May-21 0% 0% Telephone & Data Communication System Third Fix
A28040 Fire Alarm System Third Fix 9 22-May-21 31-May-21 22-May-21 31-May-21 0% 0% Fire Alarm System Third Fix
Canteen (C) 143 21-Jan-21 06-Jul-21 21-Jan-21 06-Jul-21 0% 0% 06-Jul-21, Canteen (C)
Civil Works 143 21-Jan-21 06-Jul-21 21-Jan-21 06-Jul-21 0% 0% 06-Jul-21, Civil Works
Sub-Structure 42 21-Jan-21 10-Mar-21 21-Jan-21 10-Mar-21 0% 0% 10-Mar-21, Sub-Structure
A28480 Excavation for foundation 4 21-Jan-21 25-Jan-21 21-Jan-21 25-Jan-21 0% 0% Excavation for foundation
A28500 Soil termite treatment 1 26-Jan-21 26-Jan-21 26-Jan-21 26-Jan-21 0% 0% Soil termite treatment
A28540 PCC 2 27-Jan-21 28-Jan-21 27-Jan-21 28-Jan-21 0% 0% PCC
A28550 Footing 7 30-Jan-21 06-Feb-21 30-Jan-21 06-Feb-21 0% 0% Footing
A28570 Neck Column 7 07-Feb-21 14-Feb-21 07-Feb-21 14-Feb-21 0% 0% Neck Column
A28590 Grade Beam 7 15-Feb-21 22-Feb-21 15-Feb-21 22-Feb-21 0% 0% Grade Beam
A28530 bitumen paint 3 23-Feb-21 25-Feb-21 23-Feb-21 25-Feb-21 0% 0% bitumen paint
A28560 Slab on grade 9 27-Feb-21 08-Mar-21 27-Feb-21 08-Mar-21 0% 0% Slab on grade
A28490 Backfilling 2 09-Mar-21 10-Mar-21 09-Mar-21 10-Mar-21 0% 0% Backfilling
Super Structure 101 11-Mar-21 06-Jul-21 11-Mar-21 06-Jul-21 0% 0% 06-Jul-21, Super Structure
Concrete Works 39 11-Mar-21 25-Apr-21 11-Mar-21 25-Apr-21 0% 0% 25-Apr-21, Concrete Works
A28580 Column 9 11-Mar-21 21-Mar-21 11-Mar-21 21-Mar-21 0% 0% Column

Actual Level of Effort Remaining Work Milestone Date Revision Checked Approved
Page 14 of 19
Actual Work Critical Remaining Work summary 11-Jun-20 UTS
UPDATED TIME SCHEDULE Al Ihsaa- Educational Complex in Al Jubail D.D 11-Jun-20

Activity ID Activity Name Original Duration BL1 Start BL1 Finish Start Finish Schedule % Performance %Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Complete Complete
A A A A A A A A A A A A A A
A28510 Beams 9 22-Mar-21 31-Mar-21 22-Mar-21 31-Mar-21 0% 0% Beams
A28520 Slabs 21 01-Apr-21 25-Apr-21 01-Apr-21 25-Apr-21 0% 0% Slabs
Finishing Works 62 26-Apr-21 06-Jul-21 26-Apr-21 06-Jul-21 0% 0% 06-Jul-21, Finishing Works
A28600 Masonry Works 14 26-Apr-21 11-May-21 26-Apr-21 11-May-21 0% 0% Masonry Works
A28660 External Cement Plastering 7 12-May-21 19-May-21 12-May-21 19-May-21 0% 0% External Cement Plastering
A28650 Internal Cement Plastering 7 20-May-21 27-May-21 20-May-21 27-May-21 0% 0% Internal Cement Plastering
A28680 Gypsum board 5 29-May-21 02-Jun-21 29-May-21 02-Jun-21 0% 0% Gypsum board
A28710 Roof finishes 7 03-Jun-21 10-Jun-21 03-Jun-21 10-Jun-21 0% 0% Roof finishes
A28610 Waterproofin g for Bathroom & Kitchen 3 03-Jun-21 06-Jun-21 03-Jun-21 06-Jun-21 0% 0% Waterproofin g for Bathroom & Kitchen
A28700 Tile s for Walls 7 07-Jun-21 14-Jun-21 07-Jun-21 14-Jun-21 0% 0% Tile s for Walls
A28640 Floor tiling 5 15-Jun-21 20-Jun-21 15-Jun-21 20-Jun-21 0% 0% Floor tiling
A28690 Counters 7 21-Jun-21 28-Jun-21 21-Jun-21 28-Jun-21 0% 0% Counters
A28630 Windows 5 21-Jun-21 26-Jun-21 21-Jun-21 26-Jun-21 0% 0% Windows
A28620 Doors 5 21-Jun-21 26-Jun-21 21-Jun-21 26-Jun-21 0% 0% Doors
A28670 External Painting works 7 29-Jun-21 06-Jul-21 29-Jun-21 06-Jul-21 0% 0% External Painting works
Mechanical Works 37 12-May-21 23-Jun-21 12-May-21 23-Jun-21 0% 0% 23-Jun-21, Mechanical Works
Plumbing 37 12-May-21 23-Jun-21 12-May-21 23-Jun-21 0% 0% 23-Jun-21, Plumbing
A28470 Sanitary Waste Piping Specia ltie s 3 12-May-21 15-May-21 12-May-21 15-May-21 0% 0% Sanitary Waste Piping Specia ltie s
A28400 Sanitary System 3 12-May-21 15-May-21 12-May-21 15-May-21 0% 0% Sanitary System
A28360 Domestic Water Supply System 3 12-May-21 15-May-21 12-May-21 15-May-21 0% 0% Domestic Water Supply System
A28410 Roof Scupper Drain 3 20-May-21 23-May-21 20-May-21 23-May-21 0% 0% Roof Scupper Drain
A28420 Plumbing Fixtures 3 21-Jun-21 23-Jun-21 21-Jun-21 23-Jun-21 0% 0% Plumbing Fixtures
A28370 Electric Water Heaters 3 21-Jun-21 23-Jun-21 21-Jun-21 23-Jun-21 0% 0% Electric Water Heaters
Fire Fighting 2 21-Jun-21 22-Jun-21 21-Jun-21 22-Jun-21 0% 0% 22-Jun-21, Fire Fighting
A28380 fire extinguisher 2 21-Jun-21 22-Jun-21 21-Jun-21 22-Jun-21 0% 0% fire extinguisher
HVAC 6 03-Jun-21 09-Jun-21 03-Jun-21 09-Jun-21 0% 0% 09-Jun-21, HVAC
A28350 General Exhaust Fan 3 03-Jun-21 06-Jun-21 03-Jun-21 06-Jun-21 0% 0% General Exhaust Fan
A28340 DX-Split wall mounted type air conditioning units 3 07-Jun-21 09-Jun-21 07-Jun-21 09-Jun-21 0% 0% DX-Split wall mounted type air conditioning units
Electrical Works 28 12-May-21 13-Jun-21 12-May-21 13-Jun-21 0% 0% 13-Jun-21, Electrical Works
Electrical Power 28 12-May-21 13-Jun-21 12-May-21 13-Jun-21 0% 0% 13-Jun-21, Electrical Power
A28720 Lighting System First Fix (Conduits) 5 12-May-21 17-May-21 12-May-21 17-May-21 0% 0% Lighting System First Fix (Conduits)
A28460 Conductors and cables 3 18-May-21 20-May-21 18-May-21 20-May-21 0% 0% Conductors and cables
A28440 Power Installation 2 22-May-21 23-May-21 22-May-21 23-May-21 0% 0% Power Installation
A28750 Lighting System Second Fix (Wires) 5 29-May-21 02-Jun-21 29-May-21 02-Jun-21 0% 0% Lighting System Second Fix (Wires)
A28430 Power and Lighting panel 3 03-Jun-21 06-Jun-21 03-Jun-21 06-Jun-21 0% 0% Power and Lighting panel
A28450 Disconnect Switches 1 07-Jun-21 07-Jun-21 07-Jun-21 07-Jun-21 0% 0% Disconnect Switches
A28760 Lighting System Third Fix (Fixtures) 5 08-Jun-21 13-Jun-21 08-Jun-21 13-Jun-21 0% 0% Lighting System Third Fix (Fixtures)
Communications 15 12-May-21 29-May-21 12-May-21 29-May-21 0% 0% 29-May-21, Communications
A28740 Fire Alarm System First Fix 5 12-May-21 17-May-21 12-May-21 17-May-21 0% 0% Fire Alarm System First Fix
A28730 Telephone & Data Communication System First Fix 5 12-May-21 17-May-21 12-May-21 17-May-21 0% 0% Telephone & Data Communication System First Fix
A28790 Telephone & Data Communication System Second Fix 5 18-May-21 23-May-21 18-May-21 23-May-21 0% 0% Telephone & Data Communication System Second Fix
A28770 Fire Alarm System Second Fix 5 18-May-21 23-May-21 18-May-21 23-May-21 0% 0% Fire Alarm System Second Fix
A28800 Telephone & Data Communication System Third Fix 5 24-May-21 29-May-21 24-May-21 29-May-21 0% 0% Telephone & Data Communication System Third Fix
A28780 Fire Alarm System Third Fix 5 24-May-21 29-May-21 24-May-21 29-May-21 0% 0% Fire Alarm System Third Fix
Guard House (C) 143 21-Jan-21 06-Jul-21 21-Jan-21 06-Jul-21 0% 0% 06-Jul-21, Guard House (C)
Civil Works 143 21-Jan-21 06-Jul-21 21-Jan-21 06-Jul-21 0% 0% 06-Jul-21, Civil Works
Sub-Structure 40 21-Jan-21 08-Mar-21 21-Jan-21 08-Mar-21 0% 0% 08-Mar-21, Sub-Structure
A29150 Excavation for foundation 5 21-Jan-21 26-Jan-21 21-Jan-21 26-Jan-21 0% 0% Excavation for foundation
A29170 Soil termite treatment 2 27-Jan-21 28-Jan-21 27-Jan-21 28-Jan-21 0% 0% Soil termite treatment
A29190 PCC 2 30-Jan-21 31-Jan-21 30-Jan-21 31-Jan-21 0% 0% PCC

Actual Level of Effort Remaining Work Milestone Date Revision Checked Approved
Page 15 of 19
Actual Work Critical Remaining Work summary 11-Jun-20 UTS
UPDATED TIME SCHEDULE Al Ihsaa- Educational Complex in Al Jubail D.D 11-Jun-20

Activity ID Activity Name Original Duration BL1 Start BL1 Finish Start Finish Schedule % Performance %Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Complete Complete
A A A A A A A A A A A A A A
A29200 Footing 7 01-Feb-21 08-Feb-21 01-Feb-21 08-Feb-21 0% 0% Footing
A29220 Neck Column 7 09-Feb-21 16-Feb-21 09-Feb-21 16-Feb-21 0% 0% Neck Column
A29230 Grade Beam 7 17-Feb-21 24-Feb-21 17-Feb-21 24-Feb-21 0% 0% Grade Beam
A29210 Slab on grade 7 25-Feb-21 04-Mar-21 25-Feb-21 04-Mar-21 0% 0% Slab on grade
A29160 Backfilling 3 06-Mar-21 08-Mar-21 06-Mar-21 08-Mar-21 0% 0% Backfilling
Super Structure 103 09-Mar-21 06-Jul-21 09-Mar-21 06-Jul-21 0% 0% 06-Jul-21, Super Structure
Concrete Works 36 09-Mar-21 19-Apr-21 09-Mar-21 19-Apr-21 0% 0% 19-Apr-21, Concrete Works
A29260 Column 7 09-Mar-21 16-Mar-21 09-Mar-21 16-Mar-21 0% 0% Column
A29240 Beams 9 17-Mar-21 27-Mar-21 17-Mar-21 27-Mar-21 0% 0% Beams
A29250 Slabs 20 28-Mar-21 19-Apr-21 28-Mar-21 19-Apr-21 0% 0% Slabs
Finishing Works 67 20-Apr-21 06-Jul-21 20-Apr-21 06-Jul-21 0% 0% 06-Jul-21, Finishing Works
A28850 Masonry Works 14 20-Apr-21 05-May-21 20-Apr-21 05-May-21 0% 0% Masonry Works
A28910 External Cement Plastering 9 06-May-21 16-May-21 06-May-21 16-May-21 0% 0% External Cement Plastering
A28930 Aluminium strip 7 17-May-21 24-May-21 17-May-21 24-May-21 0% 0% Aluminium strip
A28900 Internal Cement Plastering 9 17-May-21 26-May-21 17-May-21 26-May-21 0% 0% Internal Cement Plastering
A29140 Roof finishes 14 25-May-21 09-Jun-21 25-May-21 09-Jun-21 0% 0% Roof finishes
A28860 Waterproofin g for Bathroom & Kitchen 3 27-May-21 30-May-21 27-May-21 30-May-21 0% 0% Waterproofing for Bathroom & Kitchen
A29130 Tile s for Walls 5 31-May-21 05-Jun-21 31-May-21 05-Jun-21 0% 0% Tile s for Walls
A29060 Specialies 3 06-Jun-21 08-Jun-21 06-Jun-21 08-Jun-21 0% 0% Specialies
A28890 Floor Finish (tiling & scerting) 5 09-Jun-21 14-Jun-21 09-Jun-21 14-Jun-21 0% 0% Floor Finish (tiling & scerting)
A28940 Counters 3 15-Jun-21 17-Jun-21 15-Jun-21 17-Jun-21 0% 0% Counters
A28880 Windows 5 15-Jun-21 20-Jun-21 15-Jun-21 20-Jun-21 0% 0% Windows
A28870 Doors 5 15-Jun-21 20-Jun-21 15-Jun-21 20-Jun-21 0% 0% Doors
A28920 External Painting works 9 27-Jun-21 06-Jul-21 27-Jun-21 06-Jul-21 0% 0% External Painting works
Mechanical Works 44 06-May-21 26-Jun-21 06-May-21 26-Jun-21 0% 0% 26-Jun-21, Mechanical Works
A29270 Sanitary Specialties 5 06-May-21 11-May-21 06-May-21 11-May-21 0% 0% Sanitary Specialties
A28830 Domestic Water Supply System 3 06-May-21 09-May-21 06-May-21 09-May-21 0% 0% Domestic Water Supply System
A28950 Sanitary System 5 12-May-21 17-May-21 12-May-21 17-May-21 0% 0% Sanitary System
A28960 Rain water Pipe & Scupper Drain 3 18-May-21 20-May-21 18-May-21 20-May-21 0% 0% Rain water Pipe & Scupper Drain
A29050 fire extinguisher 3 15-Jun-21 17-Jun-21 15-Jun-21 17-Jun-21 0% 0% fire extinguisher
A28970 Plumbing Fixtures 5 15-Jun-21 20-Jun-21 15-Jun-21 20-Jun-21 0% 0% Plumbing Fixtures
A28840 Electric Water Heaters 2 15-Jun-21 16-Jun-21 15-Jun-21 16-Jun-21 0% 0% Electric Water Heaters
A28820 General Exhaust Fan 5 15-Jun-21 20-Jun-21 15-Jun-21 20-Jun-21 0% 0% General Exhaust Fan
A28810 DX-Split Units 5 21-Jun-21 26-Jun-21 21-Jun-21 26-Jun-21 0% 0% DX-Split Units
Electrical Works 40 06-May-21 21-Jun-21 06-May-21 21-Jun-21 0% 0% 21-Jun-21, Electrical Works
Electrical 40 06-May-21 21-Jun-21 06-May-21 21-Jun-21 0% 0% 21-Jun-21, Electrical
A28990 Lighting System First Fix (Conduits) 7 06-May-21 13-May-21 06-May-21 13-May-21 0% 0% Lighting System First Fix (Conduits)
A29020 Conductors and cables 5 15-May-21 19-May-21 15-May-21 19-May-21 0% 0% Conductors and cables
A29000 Power Installation 5 20-May-21 25-May-21 20-May-21 25-May-21 0% 0% Power Installation
A29070 Lighting System Second Fix (Wires) 7 27-May-21 03-Jun-21 27-May-21 03-Jun-21 0% 0% Lighting System Second Fix (Wires)
A28980 Panel Boards 3 05-Jun-21 07-Jun-21 05-Jun-21 07-Jun-21 0% 0% Panel Boards
A29010 Sockets & Switches 5 08-Jun-21 13-Jun-21 08-Jun-21 13-Jun-21 0% 0% Sockets & Switches
A29080 Lighting System Third Fix (Fixtures) 7 14-Jun-21 21-Jun-21 14-Jun-21 21-Jun-21 0% 0% Lighting System Third Fix (Fixtures)
Communications 28 06-May-21 07-Jun-21 06-May-21 07-Jun-21 0% 0% 07-Jun-21, Communications
A29040 Fire Alarm System First Fix 5 06-May-21 11-May-21 06-May-21 11-May-21 0% 0% Fire Alarm System First Fix
A29030 Telephone & Data Communication System First Fix 5 06-May-21 11-May-21 06-May-21 11-May-21 0% 0% Telephone & Data Communication System First Fix
A29110 Telephone & Data Communication System Second Fix 5 27-May-21 01-Jun-21 27-May-21 01-Jun-21 0% 0% Telephone & Data Communication System Second Fix
A29090 Fire Alarm System Second Fix 5 27-May-21 01-Jun-21 27-May-21 01-Jun-21 0% 0% Fire Alarm System Second Fix
A29120 Telephone & Data Communication System Third Fix 5 02-Jun-21 07-Jun-21 02-Jun-21 07-Jun-21 0% 0% Telephone & Data Communication System Third Fix
A29100 Fire Alarm System Third Fix 5 02-Jun-21 07-Jun-21 02-Jun-21 07-Jun-21 0% 0% Fire Alarm System Third Fix

Actual Level of Effort Remaining Work Milestone Date Revision Checked Approved
Page 16 of 19
Actual Work Critical Remaining Work summary 11-Jun-20 UTS
UPDATED TIME SCHEDULE Al Ihsaa- Educational Complex in Al Jubail D.D 11-Jun-20

Activity ID Activity Name Original Duration BL1 Start BL1 Finish Start Finish Schedule % Performance %Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Complete Complete
A A A A A A A A A A A A A A
Electrical Room (C) 127 21-Jan-21 17-Jun-21 21-Jan-21 17-Jun-21 0% 0% 17-Jun-21, Electrical Room (C)
Civil Works 127 21-Jan-21 17-Jun-21 21-Jan-21 17-Jun-21 0% 0% 17-Jun-21, Civil Works
Sub-Structure 41 21-Jan-21 09-Mar-21 21-Jan-21 09-Mar-21 0% 0% 09-Mar-21, Sub-Structure
A29480 Excavation for foundation 3 21-Jan-21 24-Jan-21 21-Jan-21 24-Jan-21 0% 0% Excavation for foundation
A29500 Soil termite treatment 2 25-Jan-21 26-Jan-21 25-Jan-21 26-Jan-21 0% 0% Soil termite treatment
A29520 PCC 2 27-Jan-21 28-Jan-21 27-Jan-21 28-Jan-21 0% 0% PCC
A29530 Footing 7 30-Jan-21 06-Feb-21 30-Jan-21 06-Feb-21 0% 0% Footing
A29550 Neck Column 7 07-Feb-21 14-Feb-21 07-Feb-21 14-Feb-21 0% 0% Neck Column
A29560 Grade Beam 7 15-Feb-21 22-Feb-21 15-Feb-21 22-Feb-21 0% 0% Grade Beam
A29510 bitumen paint 2 23-Feb-21 24-Feb-21 23-Feb-21 24-Feb-21 0% 0% bitumen paint
A29540 Slab on grade 9 25-Feb-21 07-Mar-21 25-Feb-21 07-Mar-21 0% 0% Slab on grade
A29490 Backfilling 2 08-Mar-21 09-Mar-21 08-Mar-21 09-Mar-21 0% 0% Backfilling
Super Structure 86 10-Mar-21 17-Jun-21 10-Mar-21 17-Jun-21 0% 0% 17-Jun-21, Super Structure
Concrete Works 44 10-Mar-21 29-Apr-21 10-Mar-21 29-Apr-21 0% 0% 29-Apr-21, Concrete Works
A29590 Column 14 10-Mar-21 25-Mar-21 10-Mar-21 25-Mar-21 0% 0% Column
A29570 Beams 9 27-Mar-21 05-Apr-21 27-Mar-21 05-Apr-21 0% 0% Beams
A29580 Slabs 21 06-Apr-21 29-Apr-21 06-Apr-21 29-Apr-21 0% 0% Slabs
Finishing Works 42 01-May-21 17-Jun-21 01-May-21 17-Jun-21 0% 0% 17-Jun-21, Finishing Works
A29290 Masonry Works 12 01-May-21 13-May-21 01-May-21 13-May-21 0% 0% Masonry Works
A29330 Internal Cement Plastering 5 15-May-21 19-May-21 15-May-21 19-May-21 0% 0% Internal Cement Plastering
A29320 Floor finish (concrete screed & epoxy) 5 20-May-21 25-May-21 20-May-21 25-May-21 0% 0% Floor finish (concrete screed & epoxy)
A29310 Windows 5 26-May-21 31-May-21 26-May-21 31-May-21 0% 0% Windows
A29300 Doors 5 26-May-21 31-May-21 26-May-21 31-May-21 0% 0% Doors
A29470 Roof finishes 5 01-Jun-21 06-Jun-21 01-Jun-21 06-Jun-21 0% 0% Roof finishes
A29340 External Painting works 5 13-Jun-21 17-Jun-21 13-Jun-21 17-Jun-21 0% 0% External Painting works
Mechanical Works 15 26-May-21 12-Jun-21 26-May-21 12-Jun-21 0% 0% 12-Jun-21, Mechanical Works
A29280 General Exhaust Fan 5 26-May-21 31-May-21 26-May-21 31-May-21 0% 0% General Exhaust Fan
A29350 Gargouri drainage 5 01-Jun-21 06-Jun-21 01-Jun-21 06-Jun-21 0% 0% Gargouri drainage
A29420 fire extinguisher 5 07-Jun-21 12-Jun-21 07-Jun-21 12-Jun-21 0% 0% fire extinguisher
Electrical Works 20 15-May-21 06-Jun-21 15-May-21 06-Jun-21 0% 0% 06-Jun-21, Electrical Works
A29410 Fire Alarm System First Fix 5 15-May-21 19-May-21 15-May-21 19-May-21 0% 0% Fire Alarm System First Fix
A29370 Lighting System First Fix (Conduits) 5 15-May-21 19-May-21 15-May-21 19-May-21 0% 0% Lighting System First Fix (Conduits)
A29450 Fire Alarm System Second Fix 5 20-May-21 25-May-21 20-May-21 25-May-21 0% 0% Fire Alarm System Second Fix
A29430 Lighting System Second Fix (Wires) 5 20-May-21 25-May-21 20-May-21 25-May-21 0% 0% Lighting System Second Fix (Wires)
A29390 Conductors and cables 5 20-May-21 25-May-21 20-May-21 25-May-21 0% 0% Conductors and cables
A29400 Earthing system 5 26-May-21 31-May-21 26-May-21 31-May-21 0% 0% Earthing system
A29380 Power Installation 5 26-May-21 31-May-21 26-May-21 31-May-21 0% 0% Power Installation
A29360 Panel Boards 5 26-May-21 31-May-21 26-May-21 31-May-21 0% 0% Panel Boards
A29460 Fire Alarm System Third Fix 5 01-Jun-21 06-Jun-21 01-Jun-21 06-Jun-21 0% 0% Fire Alarm System Third Fix
A29440 Lighting System Third Fix (Fixtures) 5 01-Jun-21 06-Jun-21 01-Jun-21 06-Jun-21 0% 0% Lighting System Third Fix (Fixtures)
Gate (C) 139 21-Jan-21 01-Jul-21 21-Jan-21 01-Jul-21 0% 0% 01-Jul-21, Gate (C)
Civil Works 139 21-Jan-21 01-Jul-21 21-Jan-21 01-Jul-21 0% 0% 01-Jul-21, Civil Works
Sub-Structure 45 21-Jan-21 14-Mar-21 21-Jan-21 14-Mar-21 0% 0% 14-Mar-21, Sub-Structure
A29940 Excavation for foundation 3 21-Jan-21 24-Jan-21 21-Jan-21 24-Jan-21 0% 0% Excavation for foundation
A29950 Soil termite treatment 2 25-Jan-21 26-Jan-21 25-Jan-21 26-Jan-21 0% 0% Soil termite treatment
A29970 PCC 2 27-Jan-21 28-Jan-21 27-Jan-21 28-Jan-21 0% 0% PCC
A29980 Footing 5 30-Jan-21 03-Feb-21 30-Jan-21 03-Feb-21 0% 0% Footing
A30000 Neck Column 7 04-Feb-21 11-Feb-21 04-Feb-21 11-Feb-21 0% 0% Neck Column
A30010 Grade Beam 7 13-Feb-21 20-Feb-21 13-Feb-21 20-Feb-21 0% 0% Grade Beam
A29960 bitumen paint 2 21-Feb-21 22-Feb-21 21-Feb-21 22-Feb-21 0% 0% bitumen paint

Actual Level of Effort Remaining Work Milestone Date Revision Checked Approved
Page 17 of 19
Actual Work Critical Remaining Work summary 11-Jun-20 UTS
UPDATED TIME SCHEDULE Al Ihsaa- Educational Complex in Al Jubail D.D 11-Jun-20

Activity ID Activity Name Original Duration BL1 Start BL1 Finish Start Finish Schedule % Performance %Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Complete Complete
A A A A A A A A A A A A A A
A29990 Slab on grade 14 23-Feb-21 10-Mar-21 23-Feb-21 10-Mar-21 0% 0% Slab on grade
A30070 Backfilling 3 11-Mar-21 14-Mar-21 11-Mar-21 14-Mar-21 0% 0% Backfilling
Super Structure 94 15-Mar-21 01-Jul-21 15-Mar-21 01-Jul-21 0% 0% 01-Jul-21, Super Structure
Concrete Works 37 15-Mar-21 26-Apr-21 15-Mar-21 26-Apr-21 0% 0% 26-Apr-21, Concrete Works
A30040 Column 9 15-Mar-21 24-Mar-21 15-Mar-21 24-Mar-21 0% 0% Column
A30020 Beams 7 25-Mar-21 01-Apr-21 25-Mar-21 01-Apr-21 0% 0% Beams
A30030 Slabs 21 03-Apr-21 26-Apr-21 03-Apr-21 26-Apr-21 0% 0% Slabs
Finishing Works 57 27-Apr-21 01-Jul-21 27-Apr-21 01-Jul-21 0% 0% 01-Jul-21, Finishing Works
A29640 Masonry Works 14 27-Apr-21 12-May-21 27-Apr-21 12-May-21 0% 0% Masonry Works
A29700 Cement Plastering 7 13-May-21 20-May-21 13-May-21 20-May-21 0% 0% Cement Plastering
A29720 Aluminium strip 3 22-May-21 24-May-21 22-May-21 24-May-21 0% 0% Aluminium strip
A29660 Waterproofin g for Bathroom & Kitchen 5 22-May-21 26-May-21 22-May-21 26-May-21 0% 0% Waterproofing for Bathroom & Kitchen
A29650 Handrail & Protections 5 25-May-21 30-May-21 25-May-21 30-May-21 0% 0% Handrail & Protections
A29910 Tile s for Walls 5 27-May-21 01-Jun-21 27-May-21 01-Jun-21 0% 0% Tile s for Walls
A29930 External metal shades 14 31-May-21 15-Jun-21 31-May-21 15-Jun-21 0% 0% External metal shades
A29840 Specialies 3 02-Jun-21 05-Jun-21 02-Jun-21 05-Jun-21 0% 0% Specialies
A29690 Floor Finish (tiling & scerting) 7 06-Jun-21 13-Jun-21 06-Jun-21 13-Jun-21 0% 0% Floor Finish (tiling & scerting)
A29680 Windows 5 14-Jun-21 19-Jun-21 14-Jun-21 19-Jun-21 0% 0% Windows
A29670 Doors 5 14-Jun-21 19-Jun-21 14-Jun-21 19-Jun-21 0% 0% Doors
A29920 Roof finishes & mosaic tile 7 16-Jun-21 23-Jun-21 16-Jun-21 23-Jun-21 0% 0% Roof finishes & mosaic tile
A29710 External Painting works 7 24-Jun-21 01-Jul-21 24-Jun-21 01-Jul-21 0% 0% External Painting works
Mechanical Works 34 13-May-21 21-Jun-21 13-May-21 21-Jun-21 0% 0% 21-Jun-21, Mechanical Works
A29730 Sanitary System 7 13-May-21 20-May-21 13-May-21 20-May-21 0% 0% Sanitary System
A29620 Domestic Water Supply System 7 13-May-21 20-May-21 13-May-21 20-May-21 0% 0% Domestic Water Supply System
A29610 General Exhaust Fan 5 22-May-21 26-May-21 22-May-21 26-May-21 0% 0% General Exhaust Fan
A29600 DX-Split units 7 27-May-21 03-Jun-21 27-May-21 03-Jun-21 0% 0% DX-Split units
A30050 Sanitary Specialties 5 14-Jun-21 19-Jun-21 14-Jun-21 19-Jun-21 0% 0% Sanitary Specialties
A29740 Plumbing Fixtures 7 14-Jun-21 21-Jun-21 14-Jun-21 21-Jun-21 0% 0% Plumbing Fixtures
A29630 Electric Water Heaters 5 14-Jun-21 19-Jun-21 14-Jun-21 19-Jun-21 0% 0% Electric Water Heaters
Electrical Works 18 13-May-21 02-Jun-21 13-May-21 02-Jun-21 0% 0% 02-Jun-21, Electrical Works
Electrical 18 13-May-21 02-Jun-21 13-May-21 02-Jun-21 0% 0% 02-Jun-21, Electrical
A29760 Lighting System First Fix (Conduits) 7 13-May-21 20-May-21 13-May-21 20-May-21 0% 0% Lighting System First Fix (Conduits)
A29850 Lighting System Second Fix (Wires) 5 22-May-21 26-May-21 22-May-21 26-May-21 0% 0% Lighting System Second Fix (Wires)
A29790 Conductors and cables 5 22-May-21 26-May-21 22-May-21 26-May-21 0% 0% Conductors and cables
A29780 Sockets & Switches 3 27-May-21 30-May-21 27-May-21 30-May-21 0% 0% Sockets & Switches
A29770 Power Installation 3 27-May-21 30-May-21 27-May-21 30-May-21 0% 0% Power Installation
A29750 Panel Boards 3 27-May-21 30-May-21 27-May-21 30-May-21 0% 0% Panel Boards
A29860 Lighting System Third Fix (Fixtures) 3 31-May-21 02-Jun-21 31-May-21 02-Jun-21 0% 0% Lighting System Third Fix (Fixtures)
Communications 18 13-May-21 02-Jun-21 13-May-21 02-Jun-21 0% 0% 02-Jun-21, Communications
A29820 Fire Alarm System First Fix 7 13-May-21 20-May-21 13-May-21 20-May-21 0% 0% Fire Alarm System First Fix
A29800 Telephone & Data Communication System First Fix 9 13-May-21 23-May-21 13-May-21 23-May-21 0% 0% Telephone & Data Communication System First Fix
A29870 Fire Alarm System Second Fix 5 22-May-21 26-May-21 22-May-21 26-May-21 0% 0% Fire Alarm System Second Fix
A29890 Telephone & Data Communication System Second Fix 3 24-May-21 26-May-21 24-May-21 26-May-21 0% 0% Telephone & Data Communication System Second Fix
A29810 Public Address system 3 27-May-21 30-May-21 27-May-21 30-May-21 0% 0% Public Address system
A29900 Telephone & Data Communication System Third Fix 3 31-May-21 02-Jun-21 31-May-21 02-Jun-21 0% 0% Telephone & Data Communication System Third Fix
A29880 Fire Alarm System Third Fix 3 31-May-21 02-Jun-21 31-May-21 02-Jun-21 0% 0% Fire Alarm System Third Fix
Water Tank & Pump Room (C) 121 21-Jan-21 10-Jun-21 21-Jan-21 10-Jun-21 0% 0% 10-Jun-21, Water Tank & Pump Room (C)
Civil Works 24 21-Jan-21 17-Feb-21 21-Jan-21 17-Feb-21 0% 0% 17-Feb-21, Civil Works
A30120 Test the filtration of the existing tank 5 21-Jan-21 26-Jan-21 21-Jan-21 26-Jan-21 0% 0% Test the filtration of the existing tank
A30240 Pump Room 14 27-Jan-21 11-Feb-21 27-Jan-21 11-Feb-21 0% 0% Pump Room

Actual Level of Effort Remaining Work Milestone Date Revision Checked Approved
Page 18 of 19
Actual Work Critical Remaining Work summary 11-Jun-20 UTS
UPDATED TIME SCHEDULE Al Ihsaa- Educational Complex in Al Jubail D.D 11-Jun-20

Activity ID Activity Name Original Duration BL1 Start BL1 Finish Start Finish Schedule % Performance %Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Complete Complete
A A A A A A A A A A A A A A
A30110 Cover & Ladder 5 13-Feb-21 17-Feb-21 13-Feb-21 17-Feb-21 0% 0% Cover & Ladder
Mechanical Works 35 18-Feb-21 30-Mar-21 18-Feb-21 30-Mar-21 0% 0% 30-Mar-21, Mechanical Works
A30090 Fire Pump 21 18-Feb-21 14-Mar-21 18-Feb-21 14-Mar-21 0% 0% Fire Pump
A30140 Water Transfer Pumps 14 15-Mar-21 30-Mar-21 15-Mar-21 30-Mar-21 0% 0% Water Transfer Pumps
Electrical Works 62 31-Mar-21 10-Jun-21 31-Mar-21 10-Jun-21 0% 0% 10-Jun-21, Electrical Works
A30260 Fire Alarm System First Fix 3 31-Mar-21 03-Apr-21 31-Mar-21 03-Apr-21 0% 0% Fire Alarm System First Fix
A30270 Fire Alarm System Second Fix 3 04-Apr-21 06-Apr-21 04-Apr-21 06-Apr-21 0% 0% Fire Alarm System Second Fix
A30150 Sockets & Switches 3 07-Apr-21 10-Apr-21 07-Apr-21 10-Apr-21 0% 0% Sockets & Switches
A30280 Fire Alarm System Third Fix 3 08-Jun-21 10-Jun-21 08-Jun-21 10-Jun-21 0% 0% Fire Alarm System Third Fix
Testing & Commissioning 13 07-Jul-21 21-Jul-21 07-Jul-21 21-Jul-21 0% 0% 21-Jul-21, Testing & Commissioning
A21010 Testing & Commissioning 13 07-Jul-21 21-Jul-21 07-Jul-21 21-Jul-21 0% 0% Testing & Commissioning
Hnading Over 7 28-Jul-21 04-Aug-21 28-Jul-21 04-Aug-21 0% 0% 04-Aug-21, Hnading Over
A4300 Handing Over 7 28-Jul-21 04-Aug-21 28-Jul-21 04-Aug-21 0% 0% Handing Over

Actual Level of Effort Remaining Work Milestone Date Revision Checked Approved
Page 19 of 19
Actual Work Critical Remaining Work summary 11-Jun-20 UTS

You might also like