PLANT FAMILIARIZATIONREPORT

INTRODUCTION OF THE PLANT:

Rihand Super Thermal Power Project is located in District Sonebhadra of Uttar Pradesh and
situated on the Southern bank of Rihand reservoir, a large artificial lake, popularly known as
“GovindVallabh Pant Sagar Lake”. This power station has been projected to have a capacity of 3000MW
in three stages, each consisting of 1000MW. The power station is supplying power to the states in
Northern Grid viz. Delhi, Uttar Pradesh, Punjab, Haryana, H.P., Rajasthan, J&K and the Union Territory
of Chandigarh. The raw material i.e. Coalis supplied through Northern Coal field( Amlori Mines)located
in Distt. Singrauli (MP), water from the Rihand reservoir and Oil (LDO) from IOCL terminals at
Bongaigaon/Haldia.

01. VITAL INSTALLATION OF PLANT FAMILARIZED WITH :

 Coal handling plant Stage –I/II/III including track hoppers.


 Crusher houseStage –I/II/III, Junction towers& Transfer points.
 Coal bunkers& coal mills.
 Main plant (boiler, turbo generator etc)
 Transformer Yards
 Water treatment plants
 Chlorination plants
 Hydrogen plants
 Fuel oil handling plant.
 HVDC
 Switchyard including sub-stations.
 Service Building, Admin Building & Township premises.

02. FIRE & EXPLOSION HAZARDS ASSOCIATED WITH THIS PLANT

FIRE HAZARDS:-
 Coal in coal handling plant and at conveyors
 Cables in cable galleries.
 Fuel oil handling in main plant.
 Transformer oil.
 Hydrogen plant
 MOT (Main Oil Tanks)
 Switch Yards
 CCR/ECR of different stages.
EXPLOSION HAZARDS:-
1) Hydrogen plant
2) Turbine Generator where Hydrogen is used of cooling of Gen. Winding.
3) Transformers
4) Boilers
5) Coal dust in mills and boilers.
RELEASE OF GASES:-
 Chlorine used in water treatment plant& Hydrogen used for cooling of Turbo Generators

03. COAL HANDLING EEQUIREMENTS:

6) Coal storage capacity = 10 Lacs MT


7) Coal consumption/day = 8,000 MT(Per unit)
8) No. of racks/day = 18-20 Racks
9) Capacity of a wagon = 60 MT each
10) No. of reclaimer = 03 Nos.
1
2

04. MAJOR FIRE FIGHTING VEHICLES AVAILABLE AT FIRE STATION :

SL NO Type of MAKE Qty.


Fire Tender (No.)
FOAM TENDER
01 UP-64-H-1064 LEYLAND-1613 01
02 UP -64-T -8064 LEYLAND-1613 01
WATER TENDER
UP-64-A-4899
03 UP64 AT- 1650 TATA-1210 01
04 Leyland-1613 01
05 DCP TENDER
UP-64AT-1652 Ashok Leyland 01
06 MINI TENDER
UP85-AT-0576 TATA-407 01
07 PORTABLE PUMP Tuhatsu (1800 LPM) 02
Sufficient Delivery hoses, Foam making/water Branches, BA Sets , PPE,s, portable extinguishers
etc. are available with fire tenders.