Project Planner Repair & Repainting Rental Factory Lot U1

Select a period to highlight at right. A legend describing the charting follows. Period Highlight: Actual (beyond plan) % Complete (beyond plan)

N PLAN ACTUAL ACTUAL PERCENT June


ACTIVITY PLAN START Reason
o DURATION START DURATION COMPLETE
19 20 21 22 23 24 25 26 27 28 29 30

1
Marka Parking 15% area parking car,motor,zebra cross,pedestrian
19 2 19 3
All Area 2nd Floor, Cutting Area Crack, Grouting with material Sika Grout, and
2
Repair & Repaint Office lt1 & 2 25%
20 11 20 11 Finishing Sealent Sika hyplex 104, cat with jotun
Chipping Area Damaged t=3cm, Instan Concrete K-500 Ex. SIKA Finishing
3
Repair Crack Floor Factory 25%
20 11 20 11 Epoxy Clear 600 micron

4
Replace Partisi Kitchen Set 10% Replace HPL and Repair Frame Inc. Accessories Finishing Painting Clear
21 2 21 3
5
Replace Partisi Door Toilet Man 10% Replace Cubicle Partition
21 2 21 3
6
General Cleaning 15% Cleaning Sanitary Toilet Male and Female 1st and 2nd Floor
28 2 28 2
100%