GP 44-70
GP 44-70
GP 44-70
GP 44-70
Applicability IMSL
Date 28 September 2007
GP 44-70
Foreword
This is the first issue of Engineering Technical Practice (ETP) IMSL GP 44-70. This Guidance on
Practice (GP) is based on parts of heritage documents as follows:
IMSL RPSE
RP 44-1 Overpressure Protection Systems.
Page 2 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
Table of Contents
Page
Foreword............................................................................................................................................2
Introduction.........................................................................................................................................5
1. Scope........................................................................................................................................6
2. Normative references................................................................................................................6
3. Terms and definitions................................................................................................................8
3.1. General..........................................................................................................................8
3.2. Terms.............................................................................................................................9
3.3. Definitions......................................................................................................................9
4. Symbols and abbreviations.......................................................................................................9
5. Overall philosophy...................................................................................................................10
5.1. General........................................................................................................................10
5.2. Reference to other codes.............................................................................................11
6. Documentation........................................................................................................................12
6.1. General........................................................................................................................12
6.2. Select stage – Early design of relief and overpressure protection systems................12
6.3. Define stage – Comprehensive relief and overpressure design basis.........................13
6.4. Execute Stage – Relief and overpressure system detailed development....................14
7. Design practice.......................................................................................................................20
7.1. General........................................................................................................................20
7.2. Relief limitation by design............................................................................................25
7.3. Pressure-limiting safety instrumented systems...........................................................26
7.4. Safety instrumented systems and reliability analysis...................................................29
7.5. Implication of changes in design conditions................................................................30
7.6. Emergency depressuring.............................................................................................30
7.7. Vacuum relief...............................................................................................................31
7.8. Cold service.................................................................................................................31
7.9. External fire condition..................................................................................................31
7.10. Thermal relief...............................................................................................................32
8. Relief design guidelines for let-down stations.........................................................................34
8.1. Definitions....................................................................................................................34
8.2. Let-down station relief design considerations..............................................................34
9. Design procedure for protection of equipment, tankage, and piping......................................38
9.1. General........................................................................................................................38
9.2. Shell-and-tube heat exchangers..................................................................................40
9.3. Air-cooled heat exchangers.........................................................................................43
9.4. Double pipe heat exchangers......................................................................................43
9.5. Plate-and-frame heat exchangers................................................................................44
Page 3 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
Page 4 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
Introduction
This Guidance on Practice (GP) provides guidance on overpressure protection systems that are within
its stated scope and is for use in determining the need for and design of specific overpressure
protection systems.
This GP refers to National and International Standards that are widely accepted. Codes and Standards
of the country in which the equipment is manufactured and/or operated should be considered and may
be accepted if they can be used to achieve equivalent safe and technical results to this GP. In any case,
statutory and local regulations must be complied with.
The value of this GP to its users is significantly enhanced by their regular participation in its
improvement and updating. For this reason, users are urged to inform IMSL of their experiences in all
aspects of its application.
Page 5 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
1. Scope
a. This GP provides guidance for the protection of pressured systems, up to the relief device
discharge flange, against overpressure to insure that plant equipment, facilities, and
pipelines comply with applicable codes, standards, and contract documents. This GP
provides a level of safety acceptable to IMSL in the design and operation of the following:
1. Processing plants, including refineries, gas installations, and chemical plants.
2. Steam generating plant and ancillary equipment.
3. Terminals, including jetty and loading facilities.
4. Petroleum production facilities, including well pads, crude oil & gas gathering
centres.
5. Main transmission pipelines, and associated equipment (as defined in clause 9.12.).
6. Storage installations.
7. Vacuum systems and systems relieving at a pressure less than 1 bar (ga) (14,5 psig).
b. It includes IMSL general requirements on the use of pressure-limiting instrumentation.
These are based broadly on:
1. Continuation of the use of pressure relief devices, wherever practicable, as the main
method of overpressure protection.
2. The use of pressure-limiting instrumentation (also known as safety instrumented
systems) as an initial method of overpressure protection in most cases, and as the sole
method in a limited number of cases.
c. It does not apply to pressure relief for systems in ships or road/rail tanks unless the system
is a special purpose-built facility that would normally be considered a processing plant.
d. This GP is applicable to new installations and to changes in overpressure protection
systems required as a result of changes in design conditions or modifications in existing
installations. The extent to which any part of the GP is applied retrospectively to an
existing system shall be subject to IMSL approval.
2. Normative references
The following normative documents contain requirements that, through reference in this text,
constitute requirements of this technical practice. For dated references, subsequent amendments to, or
revisions of, any of these publications do not apply. However, parties to agreements based on this
technical practice are encouraged to investigate the possibility of applying the most recent editions of
the normative documents indicated below. For undated references, the latest edition of the normative
document referred to applies.
The user should note there is some disagreement between the codes and standards listed in this
section. The user shall comply with the specific codes and standards applicable to the local facility and
specific equipment.
IMSL
GP 24-10 Guidance on Practice for Fire Protection – Onshore.
GP 30-75 Guidance on Practice for SIS - Management of the SIS Lifecycle.
GP 30-76 Guidance on Practice for Safety Instrumented Systems (SIS) –
Development of the Process Requirements Specification.
Page 6 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
Page 7 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
3.1. General
a. In this GP the term ‘approve’ or ‘approved’, as applied to IMSL , is used if IMSL does not
wish a design to proceed unless certain features have been agreed in writing with a
contractor or supplier. This does not imply that all details of a document have been
considered by IMSL and does not affect design responsibilities of the contractor or
supplier
b. Throughout this document, the words ‘will’, ‘may’, ‘should’, ‘shall’ and ‘must’, when used
in the context of actions by IMSL or others, have specific meanings. For purposes of this
GP, the following terms and definitions apply:
3.2. Terms
Will
used normally in connection with an action by IMSL , rather than by a contractor or supplier.
May
used if alternatives are equally acceptable.
Should
used if a provision is preferred.
Page 8 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
Shall
used if a provision is mandatory by IMSL .
Must
used only if a provision is a statutory requirement.
3.3. Definitions
The technical terms used in this GP have the meanings defined in API RP 521 or ISO 23251. The
following additional technical definitions also apply:
Disposal system
The purpose of a disposal system is to conduct the relieved fluid to a location where it can be safely
discharged. It may terminate in an atmospheric vent, combustion device such as a flare, or other
specialized treating equipment.
Heat-off
Stopping the heat input to a plant or section of a plant with either manual or automatic initiation.
Let-down station
A flow restriction where the upstream operating pressure is greater than the downstream design
pressure. It normally consists of an arrangement of valves and/or orifice plates.
Pressure-limiting instrumentation
Instrument systems that act to minimise the size or frequency of relief loads by automatically adjusting
process conditions when they tend towards a relief situation. One example of this is a safety
instrumented system (SIS) as described in clauses 7.3 and 7.4.
Reliability analysis
A mathematical technique for assessing in probabilistic terms the performance of a component, system
or plant.
Relief device
Any device (mechanical or instrumentation) that acts automatically and reliably to relieve material on
pressure rise. It normally refers to pressure relief valves and bursting discs; but explosion hatches,
water seals, buckling pin devices, and pressure/vacuum breather valves are among the devices that
meet this requirement.
For the purpose of this GP, the following symbols and abbreviations apply:
DN Nominal Diameter
Page 9 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
UK United Kingdom
5. Overall philosophy
5.1. General
a. This document defines IMSL ’s guideline for overpressure protection systems and
identifies related resources. This document’s objective is to assist in development of an
overpressure protection design that is safe, reliable, and cost effective. It is the obligation
of all parties to ensure the overpressure/relief system design accomplishes these goals.
b. As noted in API RP 521 and ISO 23251, this GP in particular shall be used in conjunction
with sound engineering judgement.
6. Documentation
6.1. General
a. For new and modified plant, the following documentation requirements shall apply.
Existing plant shall have their documentation upgraded to the level described in the
following clauses of this GP as soon as practicable.
b. Documentation for overpressure and relief systems shall be created in three sections or
phases. Each phase is further clarified in the following clauses.
Page 10 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
1. Early design concept (select project stage) with information submitted for IMSL
approval.
2. Complete relief and overpressure design basis (design and execute project stages)
with supporting calculations and system details.
3. A comprehensive relief and overpressure system summary for incorporation into the
plant operating procedures (during the project execute stage for use in the operate
stage) and to develop a permanent Relief and Overpressure database summary.
6.2. Select stage – Early design of relief and overpressure protection systems
a. At an early project stage, relief requirements shall be studied in sufficient depth to
establish the basic design philosophy. This shall then be considered in relation to proposed
siting constraints and relevant statutory requirements.
1. For new or significantly modified plant and process, an outline design philosophy and
pertinent data on which the design has been based shall be provided.
2. The preliminary design of an overpressure protection system shall be completed as
early as possible and should be reviewed independently in detail by IMSL .
3. The subsequent preliminary design for overpressure protection shall then be
developed, agreed, and finalised following discussion with IMSL .
b. The basic overpressure and relief protection philosophy should be fully developed before
the design specification stage of the Project Health, Safety, and Environmental Review
(PHSER). The preliminary design basis for any overpressure protection system shall be
submitted to IMSL with the following minimum information:
1. Conceptual design philosophy. (clause 6.4.2).
2. Codes and standards (both internal IMSL and external) being used for design.
3. A philosophy on safety instrumented systems and an outline of the SIS system
proposed with a supporting provisional integrity assessment (SIL). (clause 6.4.11).
4. Process flow diagrams or flowsheets showing relief devices and anticipated system
operating pressures (clause 6.4.3).
5. Rough sizing and type of disposal system.
c. IMSL may, at its discretion, call for additional back-up information such as calculations
and other details. Final versions of the above information shall be included in the relief and
overpressure protection design basis and shall be subject to IMSL approval.
Page 11 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
Page 12 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
b. A summary of relevant plant and process variables affecting overpressure and relief design
shall be distilled from clauses 6.4.2 through 6.4.11 and incorporated into an electronic
summary including, but not limited to:
1. Control valve trim size.
2. Valve Cv characteristics.
3. Pump impeller size.
4. Fluid suction pressure.
5. Fluid specific gravity.
6. Operating fluid levels.
7. Applicable scenarios including the relief load for each credible scenario.
8. Relief valve sizes.
9. Equipment or systems protected.
10. Summary of other relevant data impacting relief system design or capacity.
This Relief and Overpressure summary shall be produced and kept current by each facility
as part of their MOC process.
6.4.3. List of relieving devices, data sheets, and associated block valves
a. A complete set of final process specifications (data sheets only) listing relief valves and
rupture disks (i.e., bursting disks) shall be provided. In addition, the list shall include
thermal relief valves, rupture/buckling pins, conservation vents, vacuum relief valves, and
other mechanical devices used for both overpressure and underpressure protection. The
relief device list shall include the following information:
1. Tag No.
2. Manufacturer.
Page 13 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
Page 14 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
Page 15 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
utility failure and fire cases. Electronic files should be provided to IMSL in either Visual
Flare or FlareNet.
Page 16 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
2. The relief loads that could arise from these failures shall be determined. If relief loads
exceed design capability, it may be possible to re-assign system outputs to reduce the
relief load.
3. In all cases a table (clause 6.4.4) shall be provided showing relief loads associated
with the system outputs linked to the common cause failure being considered.
b. All items should be included, whether or not their failure can result in overpressure.
7. Design practice
7.1. General
a. A mechanical relieving device(s) or open vent should protect equipment subject to
overpressure. An instrumented HIPS may also be used for overpressure protection, subject
to clause 9.1b.
b. Relief devices or overpressure protection are set at the design pressure of the weakest
component in the system being protected. However, under some conditions the relief
device(s) are set at lower pressures than the process components and local codes may
permit setting multiple relief devices above the design pressure. (See clause 10.1)
c. Adequate consideration of the process relief and overpressure scenarios is a critically
important step and shall be developed during the design of relief and overpressure
protective systems; protection cannot be designed for an overpressure hazard that is not
clearly identified.
d. The following list identifies failures capable of creating potential overpressure. This list is
intended to identify some over-pressure scenarios, but it is not all-inclusive. This list shall
not preclude a detailed review of all other over-pressure possibilities. In all cases, potential
failures shall be carefully examined using a structured, documented process such as a PHA
or equivalent.
1. Power failure.
a) The power distribution system shall be analysed to determine which component
parts of the system could fail without loss of the whole system. These sub-
system failures should then be analysed for their relief implications.
b) Complete power system failure within a unit and the entire facility shall also be
evaluated.
2. Cooling or reflux system failures.
Partial cooling water failure shall not be assumed unless it can be shown that all
cooling water exchangers continue to receive water when part of the cooling water
pumping capacity is lost.
3. Steam failure.
4. Instrument air failure.
5. External fire or pool fire.
6. Individual valve failure, open or closed.
7. Inadvertent valve operation, control valve failure or valve opening from a higher
pressure source.
Page 17 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
Page 18 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
Page 19 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
b. To meet the reliability necessary for pressure protection, the HIPPS arrangement must
meet the required SIL. GP 30-75, GP 30-76, GP 30-80 and GP 30-81 shall be followed in
the application of HIPS or HIPPS. Also see ISO 23251 and API 521 for further
information on HIPPS.
c. A single process control instrument or single loop design by itself, with no redundancy or
an associated safety integrity level, in general shall not be considered to meet IMSL relief
requirements. In most cases redundant devices are required to achieve the required
performance.
d. A clear distinction shall be made in all documentation between “normal” pressure-limiting
instrumentation and safety instrumented systems providing final protection against loss of
containment. In order to take credit to mitigate an overpressure scenario, the safety
instrumented system shall be in operation during all operating modes (start-up, shutdown,
normal, etc.) when the overpressure scenario can occur.
e. This GP applies to any protective instrumentation (safety instrumented systems) that can
be considered as ‘pressure-limiting instrumentation’, i.e. acting to minimise or eliminate
the operation of pressure relief devices whether or not provided specifically for that
purpose.
f. Pressure-limiting instrumentation should be used, if practicable, subject to the need to
minimise the frequency and magnitude of spurious plant shutdowns. However, complete
relief system capacity shall be provided as the final protection for individual equipment
items if practicable (subject to 9.1.b). If not practicable, a safety-instrumented system with
suitable integrity may be used.
g. The reliability required of any safety instrumented system providing the final protection
against overpressurisation depends on the magnitude of the hazard involved and its
likelihood which is reflected in the integrity level established in accordance with
GP 30-76.
h. The set points of any pressure limiting safety instrumented system, preceded by alarms as
required, shall be below the lowest relief device set pressure in the system under
consideration, in order to be effective.
1. An increase in the vessel design pressure over that allowed by GP 46-01 may be
needed, but should not exceed guidelines in clause 10.1 or in applicable local codes
and national standards.
2. The design margin shall take account of the response of control systems and the
process dynamics.
i. The design margin should be defined to allow for:
1. The tolerance of the set pressure of the relief device under actual working conditions.
2. The setting of the trip switch or amplifier and its switching differential.
3. The setting of the pre-alarm and its switching differential.
4. The maximum working pressure under normal process conditions.
5. The time required for the safety instrumented system to fully complete its protective
function in relation to process dynamics.
j. Pressure-limiting instrumentation systems providing the final protection against
overpressurisation shall be designed to facilitate regular testing and strict control over
bypassing or deactivation, and shall be fully documented in accordance with GP 30-80.
1. Pressure-limiting and temperature-limiting instrumentation may, if appropriate,
include automatic actuation of the following:
a) Feed or pipeline transmission pump or compressor trips.
Page 20 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
Page 21 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
4. Changing pump impeller size, control valve trim size, or the removal or repositioning
of limit stops (clause 6.4.9).
Page 22 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
Page 23 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
8.1. Definitions
Page 24 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
8.2.1. General
In considering process systems in which fluids pass from a high pressure to a low pressure
system, the low pressure system must be protected from overpressure. Relief devices should be
sized to take into account the fluid conditions and all undesirable circumstances in operation of
the let-down station.
Page 25 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
1. If this occurrence could cause overfilling of the low pressure vessel, when starting
from normal operating levels, then full liquid relief capacity shall be considered from
the low pressure vessel.
2. It may be possible to reduce operating levels to prevent becoming overfilled. This can
take one of two forms:
a) Full liquid relief capacity shall be provided, together with suitable means of
disposing and holding a sufficient quantity of liquid (See GP 44-80).
b) A safety instrumented device of suitable integrity shall be provided to stop
further liquid inflow a sufficient time before the equipment space is filled.
b. Good engineering design utilizes normal process interventions to reduce demand
frequency on safety instrumented systems (SIS); however, SIS design must consider and
allow for the full range of potential process conditions including start up, restart, control
system trip recovery, or other non-routine operations.
Page 26 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
Page 27 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
9.1. General
a. Pressured systems in the plant or facility shall be designed to:
1. Identify primary causes of overpressure.
2. Assess the reliability of any means provided in the system to limit this pressure.
3. Specify to the vessel designer the resulting design case pressure relief device
requirement(s).
Either pressure relief devices of the specified requirement(s) or safety instrumented
systems of sufficient integrity shall be provided.
b. For protection of individual equipment items or sections of process plant, relief devices
shall be provided, taking no credit for provision of automatic pressure-limiting
instrumentation, except in special circumstances that shall be in accordance with GP 30-76
and GP 30-80. Examples of such circumstances are:
Page 28 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
Page 29 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
g. If there is only a single check valve, complete failure of the check valve shall be
considered. The reverse flow rate shall be based on the full orifice diameter within the
check valve, assuming complete failure.
h. The requirement for additional isolation to prevent ongoing leakage raises some practical
issues that shall be considered for the overall level of protection to be satisfactory. A
LOPA may help understand the issues involved and sensitivities of the key assumptions. If
a detailed consideration shows that a manual isolation is not a practical option,
consideration should be given to automatic isolation or an alternative means of protection.
1. Circumstances that require additional manual isolation shall be clearly identified and
agreed with operating personnel. This additional manual isolation shall be readily
identifiable in the field and the requirement for isolation shall be clearly identified in
operating procedures.
2. The system design shall ensure that it is safe for field personnel to make required
manual isolations – the rate of pressurization of the low pressure system shall be
sufficiently slow that a dangerous level of pressure is not reached within the timescale
for effective isolation.
3. Assessment of the time-scale for isolation shall take into account the likely
circumstances of the initiating event – e.g., a total power failure – and the alarm
loading and work load on field personnel at the time. The human factors aspects of
the situation shall be considered, including the potential for the isolation step to be
omitted.
4. Any manual isolation valve that is required to supplement the check valves should be
maintained in working order.
5. Any manual isolation valve shall be accessible in all foreseeable situations – e.g., if
the cause of the reverse flow was a fire that could lead to a pump being shut down,
then the isolating valve would need to be accessible unless the consequences of any
reverse flow were judged to be far less than the initiating event.
6. Consideration of the potential consequences of failure should be made – whilst
catastrophic failure of a vessel is always a very serious event, if the consequences are
particularly severe a higher standard may be warranted.
7. Consideration should be given to the implications of assumed leakage rates on the
inspection regime of the check valves, and whether simple visual inspection is
sufficient, or whether a higher standard of testing (e.g., periodic leak testing) is
required.
8. The orientation of the check valves shall ensure that the check valves can function
reliably – manufacturer’s recommendations shall be followed.
9.2.1. General
a. In exchanger systems consisting of more than one shell, both shell or tube sides
interconnected without intermediate isolating valves may be considered as single systems
for the purpose of overpressure protection design, unless severe fouling could occur. Both
shell and tube side of heat exchangers should be protected by pressure relieving devices in
accordance with requirements set forth in local codes such as ASME Code Section VIII,
European Pressure Equipment Directive (PED), PD 5500, etc.
b. Overpressure conditions to be considered shall include the possibilities set out in API
RP 521 or ISO 23251, and any other specific plant emergency condition.
1. In particular the blocked-in and burst tube conditions shall be allowed for, together
with any implications of more gradual tube leakage.
Page 30 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
Page 31 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
then a relief device should be fitted, but if a pressure leak can be accommodated in normal
flow, a relief device should not be automatically fitted. Accordingly, pressure relief for
tube failure may be omitted provided all of the following are true, however the possible
need for thermal relief should not be overlooked in any case:
1. The low-pressure side can absorb the tube break flow without causing other problems
upstream or downstream of the tube break.
2. The volumetric flow from the tube break is less than the normal volumetric flow
through the low-pressure side.
3. It is unlikely to close the low-pressure side discharge line during normal operation.
j. A coil fitted into a vessel shall also be considered for the burst tube condition, depending
on the design and construction of the coil.
Page 32 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
considered, but in most cases would constitute a partial failure (e.g., hole), rather than a
full-bore failure.
b. Regarding fire exposure, double-pipe heat exchangers are similar to piping (high surface
area per volume) and, as should be treated comparably to air-cooled heat exchangers.
Page 33 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
2. The set pressure shall correspond to the maximum allowable suction system pressure
or stationary seal pressure, whichever is less. For the seal, the exact set pressure
requires agreement with the pump manufacturer.
3. The discharge rate shall be the maximum estimated flow possible through the non-
return valve bypass or other pressurising line under the relieving condition.
Page 34 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
9.9. Furnaces
a. Pressure-relief devices should be located on furnace outlet, upstream of first block valve.
b. Pressure relief devices should only be installed at furnace inlet if there is the possibility of
the following:
1. Inside of pressure relief devices is subject to coking if located on the furnace outlet
and there is no steam or other purge available to keep pressure relief device inlet
clean.
2. Individual tubes can be blocked with coke.
c. A fuel shutdown system should be provided to prevent overheating and rupture of a tube if
a pressure-relief device located at the furnace inlet opens and causes inadequate flow
through tubes.
d. Failure of the process tubes should still be considered even if the fuel shutdown system
worked successfully because it may be possible for the residual sensible heat of refractory
to cause over-temperature failure of the process tubes after firing is stopped.
9.10. Boilers
a. Safety valves for ASME Section I Boilers should be set so the first valve to open is
downstream of superheater.
b. Safety valve(s) on steam drum should be set to open over as wide a range of pressure as
permissible with the first safety valve to open being the smallest size used.
c. Subsequent safety valves should be progressively larger.
d. Economizer/preheater safety valve should be set to open after all drum valves have
opened.
9.11. Compressors
a. Positive displacement and centrifugal compressors in which pressure during surge or
closed discharge can exceed MAWP of piping, equipment, or casing shall have a pressure-
relief device.
b. Compressor pressure-relief valves should discharge to a safe area such as a flare if
compressing hydrocarbons. If the pressure-relief valve discharges back to suction of the
compressor, an analysis should be performed to verify that temperature and pressure of
compressor suction and process fluid do not exceed their maximum safe operating limits.
c. Compressor pressure relief valve discharges shall be designed to prevent possible
compressor surge or system malfunction.
d. If positive displacement compressor suction piping can be overpressured due to internal
back-leakage through compressor discharge valves of discharge gas when machine is
shutdown, suction piping shall have a pressure relief device or the compressor inlet flange
and suction piping back to the first block valve shall be rated for the higher pressure.
e. Positive displacement compressors shall have a pressure relief device on discharge side
upstream of the first isolation valve.
f. Multistage positive displacement compressors shall have pressure relief devices for each
stage.
Page 35 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
9.12.1. General
a. For the purposes of this GP, main transmission pipelines and associated equipment shall be
defined as follows:
1. Oil or gas transmission pipelines both on land and offshore, but excluding processing
plant.
2. Departure and arrival terminals immediately associated with transmission pipelines
plus any intermediate stations as required. This includes pig launchers/receivers and
slug catchers, but not processing facilities associated with a terminal.
b. In main transmission pipelines and associated equipment, the provision of pressure relief
devices may not be acceptable or effective, apart from any provision for thermal
expansion.
c. When considering overpressure protection, all types of protective devices should be
considered, including overpressure controls, automatic shutdown equipment, and pressure
relief devices.
9.12.2. Surge
a. The maximum pressure in the system that can arise as the result of operating conditions
plus any surge pressure shall be evaluated and taken into consideration in the design, after
allowing for the effect of all practical methods for surge protection, e.g. expansion vessels,
slow-closing valves, etc. If the operating pressure plus the resultant surge pressure exceeds
that permitted by the appropriate code, then either overpressure devices or pressure-
limiting instrumentation shall be installed.
The manufacturer should be consulted for more precise data for specific types. The times
need to be correctly considered in the hydraulic surge analyses.
b. Surge pressures that are likely to be significant shall be determined and provided for in the
design, either by reducing the level of permitted operating pressure or by provision of
protective devices to keep the maximum pressure within that permissible.
Page 36 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
c. Facilities for depressuring shall be provided at compressor stations. Gas compressors shall
be fitted with a pressure-relieving system fully sized for the shut-in condition and installed
in the discharge line from each compressor.
d. Pressure-relieving systems, flares, and surge tanks shall be designed and located to meet
the requirements of GP 44-80.
9.14.1. General
Pressure-relieving arrangements for storage tanks to operate at or near atmospheric pressure
shall be in accordance with API Std 2000 and GP 58-10.
Page 37 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
d. If air is not to be tolerated within the tank, consideration should be given to designing the
tank to withstand full vacuum or providing an inert gas system to prevent vacuum during
normal and emergency conditions.
Page 38 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
10.1. General
a. Equipment, vessels, or process systems protected with more than one relief device for the
same overpressure contingency typically should have these relief devices with staggered
set pressures.
1. In some cases, a smaller relief valve with a lower set pressure for smaller and more
frequent upset should be considered in addition to the larger valve for the less
frequent, larger relief loads. Typically, a relief valve may be considered oversized
when the inlet flow is less than approximately 20-25% of the capacity.
2. One pressure relief device shall be set at or below the design pressure or maximum
allowable working pressure (MAWP) of the protected equipment.
3. Additional devices may be set at higher pressure (if allowed by local codes), but in no
case, except for fire, should the setting be more than 105% of the design pressure or
MAWP.
4. Only under fire conditions or other expected external heat input, could a supplemental
device be set as high as 110% of design pressure or MAWP.
b. Attention shall be given to relief situations that result in a wide range of relieving flow
rates under different upset conditions. In this case, consideration shall also be given to the
selection of two valves; a smaller pressure relief valve set at the equipment design pressure
to handle the upset conditions resulting in lower relieving rates, and a larger valve set at
105% of equipment design pressure for the largest relieving case or otherwise set as
permitted by code (the European Pressure Equipment Directive [PED] instructs EU
members that vessel design pressure should not be exceeded.).
c. Use of multiple pressure relief devices shall conform to the following:
1. Multiple pressure relief devices should be used if sufficient relief area cannot
practically be supplied by one relief device.
2. Consideration should be given to using multiple pressure relief devices, if a larger
size valve is being considered (e.g., Q, R or T size).
d. Similar considerations shall apply if a single large rupture disk is required for the
controlling scenario.
1. A parallel pressure relief valve set to open at lower pressure should be considered to
handle smaller upsets that do not require full rupture disk area but could occur more
frequently.
2. Depending on service, the pressure relief valve may require a rupture disk beneath it.
e. Relief valve set pressure corrections for temperature may be necessary for high
temperature systems.
1. Correction applied should be based on temperature at the valve when it is in the
closed position.
2. This temperature may not be the flowing process temperature even if the valve is
mounted directly on protected equipment but uninsulated.
3. Distance from process and effects of any thermal tracing shall be taken into account
when applying a thermal correction factor.
4. Once temperature is determined, manufacturer’s specific temperature correction
factor shall be applied.
5. Correction factor should be multiplied by set pressure to determine cold set pressure.
Page 39 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
f. The uses of pressure relief devices other than pressure relief valves, rupture disks, and
buckling pin type valves are not excluded, but shall be subject to approval by IMSL .
10.2.1. General
a. The selection of a pressure relief valve type is unique to each individual application;
however, general guidelines and experience can be given as follows.
b. Relief valve material shall be suitable for the inlet and outlet temperatures that result from
the extremes of operating and emergency conditions. This includes the effect of cooling as
a result of reducing pressure through the valve during relief; however it does not include
extreme conditions such as external fire or explosion in which relief valves would
subsequently be discarded.
c. Relief valves should follow API RP 520 or ISO 4126 guidelines and local or national
design standards if applicable such as PED, BSI, and ASME.
Page 40 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
valve set pressure, the particular valve manufacturer should be consulted for
sizing assistance and to assess the suitability of their valve in this application.
b) For a back pressure exceeding 55% of the valve set pressure, performance data
of the specific valve at the expected set pressure shall be obtained from the
manufacturer and be subject to IMSL approval.
2. The maximum pressure rating on the outlet side of the balanced valve (refer to API
Std 526).
e. Bonnet and bellows vents from balanced-type pressure relief valves shall be piped with
minimum restriction to a safe location, as approved by IMSL .
f. In bellows-type pressure relief valves, the bonnet shall be vented separately from the
discharge.
g. Bellows-type valves shall not be used in fouling conditions unless precautions are taken to
avoid or minimize bellows fouling or deposit build-up during relieving and normal
operation (e.g., due to leakage across the valve seat).
h. The auxiliary balancing piston type should be used for critical and fouling services as
specified by IMSL .
Page 41 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
10.3.1. General
a. The margins between normal operating and design pressures are generally larger for
rupture disks compared to relief valves and shall be accommodated in the design. Rupture
disks are also susceptible to opening due to short duration pressure transients particularly
common in liquid filled systems.
b. Rupture disks may be considered for slurry, corrosive and erosive services, or to minimize
leakage of valuable, hazardous, or toxic fluids. The use of a pressure relief valve combined
with an inlet rupture disk should be evaluated on a case-by-case basis if corrosive fluids
dictate the material of construction of the valve.
Page 42 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
1. Normal domed rupture disks (i.e., non-scored) may be operated at working pressures
only up to 70% of the bursting pressure.
2. Forward-acting scored rupture disks may be operated at 80-90% of the bursting
pressure.
3. Reverse-acting scored rupture disks may be operated at up to 90% in many
circumstances.
4. Use of a rupture disk at an operating working pressure exceeding 90% shall be
subject to approval by IMSL .
5. API RP 520 or ISO 4126 should be used for general guidance on the maximum
suitable operating pressures for the various types of bursting disks. However, in all
cases, the manufacturer’s information on the specific disk should be used.
e. Rupture disks may be used to shield inlet or outlet of the pressure relief valves provided
that:
1. Telltale device shall be used between disk and relief valve to identify disk leakage or
failure. This device in most installations includes a pressure gauge, an excess-flow
check valve, and a vent to atmosphere.
2. If leakage is not permitted to atmosphere, the vent should be routed to a closed
system operating near atmospheric pressure even under upset conditions.
3. Any back pressure in the closed system shall be considered in the rupture disk relief
burst pressure design.
4. Any leaking rupture disk beneath a pressure relief valve should be replaced
immediately.
5. If a rupture disk is used upstream of a pressure relief valve so that a lesser metallurgy
relief valve can be used (e.g., the use of a titanium rupture disk with a stainless steel
pressure relief valve instead of a titanium pressure relief valve) and if the pressure
relief valve vents into a common header, the design shall consider any corrosive or
fouling products from other locations that can degrade the pressure relief valve from
the outlet side.
f. If rupture disks are selected, the design shall ensure convenient and safe replacement of the
disks considering the layout and installation.
g. Low pressure (less than 1,0 bar (ga) [15 psig]) rupture disk designs that do not permit
affixing a tag should only be used if tag is firmly secured to installed disk assembly and
special provisions are made to ensure correct installation.
h. For slurry or any other service in which material could build up, consideration should be
given to providing a small gas or clean liquid purge flow across the process side of disk to
prevent possible obstruction in front of disk.
i. Pre-scored forward-acting design and pre-scored reverse-acting design are the preferred
choice for rupture disks.
j. Reverse-acting rupture disks that rely on a cutting assembly shall not be used.
Page 43 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
different from both the relieving temperature and the process operating temperature. To
prevent mismatch of temperature the following options shall be considered:
1. Heat tracing disk and holder to ensure it is always at a specified temperature. Design
burst temperature should be specified at this temperature.
2. Keeping disk temperature near ambient through remote disk location and/or
insulation removal. An average ambient temperature should be specified for design
burst temperature.
3. Locating disk near enough to process, so it is kept at operating temperature. Design
burst temperature should be specified at or near average operating temperature. The
temperature of the rupture disk shall be reconfirmed at the field.
4. Insulating rupture disk holder.
5. Jacketing rupture disk holder and applying heat through a temperature control system.
6. Using other engineered solutions that minimize the difference between operating and
set temperature.
7. Specify a disk material (e.g., Inconel 600 instead of 316 stainless steel) that is less
sensitive to temperature and still meets all other requirements.
Page 44 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
a. The calculation of required free area for relief valves and rupture disks should be in
accordance with the appropriate National Code. For example, TüV in Germany have their
own pressure relief valve sizing procedures which shall be used when applicable. In the
absence of such a Code they should be sized in accordance with the methods described in
ISO 4126 or API RP 520 Part I, or other appropriate sizing method.
b. In sizing relief devices, the set pressure and accumulation pressure shall be in accordance
with the applicable pressure vessel design code.
c. The design of pressure relief devices discharging to a closed relief system shall take into
account the maximum back pressure arising at the discharge of the device for the particular
overpressure case under consideration. Additionally, the mechanical design shall be
suitable for the maximum back pressure to which a device can be exposed as a result of
other devices relieving.
10.6.1. General
a. Pressure relief devices shall be installed in accordance with ISO 4126 or Part II of API
RP 520 as amplified and amended below.
b. Relief devices intended to relieve vapour should be connected to the highest point of the
equipment to be protected if possible. If this is not possible and there is the possibility of
liquid above the relief device inlet line, the relief device shall be sized for an equivalent
volumetric rate of liquid and means available to minimizing slugging.
c. If thermal cycling has been shown to be an issue, pressure relief valves should be located
such that the fluid temperature at the valve during normal plant operation is near ambient
conditions when the valve is inactive so as to minimize thermal cycling. The valves shall
be heat traced should it be deemed that ambient conditions affect its performance.
d. Pressure relief devices shall be isolated before hydro-test of piping or vessels, but included
in system tightness testing.
10.6.2. Preinstallation
10.6.2.1. General
a. Before installation, pressure-relief valves shall be stored in an upright position in a clean,
dry area and rupture disks shall be stored in a clean, dry area in their original shipping
containers.
b. Inlet and outlet of pressure-relief devices shall remain covered until time of installation.
c. Before installation or bench testing, pressure setting engraved on pressure-relief device
nameplates shall be verified as being the same as specified on data sheet and facility
pressure-relief device records.
d. Inlet piping and associated equipment shall be free of foreign matter. This includes pipe
scale, welding beads, or other objects that could cause damage or prevent pressure-relief
valves from reseating after operation.
Page 45 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
valves which do not have bellows shall have their bonnet vent connections plugged with a
metal plug.
Page 46 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
e. A valved and blanked/plugged drain connection of minimum size DN 20 (NPS 3/4) shall
be provided between the relief device and any upstream block valve. A similar vent
connection shall be provided between the relief device and any downstream block valve.
Page 47 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
f. If two or more pressure relief devices are placed on one connection, the cross-sectional
“nominal” area of this connection shall be at least equal to the combined “nominal” inlet
areas of the valves, and the normal pressure loss requirement shall apply for the combined
rated flow of the valves.
g. Modulating action relief valves can use the required relief load rate instead of the rated
capacity when determining inlet line pressure loss.
h. Inlet piping shall be heat traced if the fluids handled have pour or freezing points above the
lowest ambient temperature, or if fluids being handled become excessively viscous when
cold. The high viscosity shall be considered in pressure drop and relief device sizing.
i. Inlet piping shall not be susceptible to blockage in the event of failure of other equipment
such as level-control float balls and pieces of mesh blanket/pad.
j. Isolating valves shall be so selected as to minimise the pressure loss in the inlet line. For
ball valves in LPG service, the valves shall be full-bore, to help mitigate potential freezing
problems.
k. Relief valve discharge lines connected to a closed system shall enter the top of the header
or discharge piping system if practical.
l. Generally the isothermal flow method is used to calculate the pressure drop in outlet relief
piping for gas service. See ISO 23251 or API 521 for details. If the adiabatic method is
used in high pressure gas service, then the k value shall be calculated for gas conditions
that exist in the outlet relief piping.
m. Relief valve outlet piping where the velocity can exceed 0,5 Mach shall be evaluated for
potential acoustic fatigue and appropriate supports shall be provided.
Page 48 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
g. If a burst rupture disk is likely to discharge solid material such as polymer, arrangements
should be considered if appropriate to pass the discharge directly to a second vessel in
which the solid material may be retained, the gaseous element being discharged to
atmosphere, to treatment, or to flare, as appropriate.
a. Ensure that the contractor has produced an adequate relief and overpressure protection
design basis along with adequate documentation per clause 6 before commissioning a new
unit or starting up a modified unit.
b. Ensure that there is an adequate management system for translating the relief and
overpressure protective requirements into the plant operating procedures and to keep the
relief system design basis and/or plant procedures up-to-date when any pertinent
modification to equipment or throughput is made.
c. Ensure, before construction, that it is possible and convenient to operate the unit with the
requirements for:
1. Clearly identifying locked open or locked closed block valves.
2. Pressure-limiting safety instrumented systems, especially with respect to their
reliability, testing, prevention of bypassing, and maintenance.
3. Compliance with any statutory or local requirements for relief device maintenance.
4. Draining of heat exchangers upon blocking in while the unit is in operation.
5. Maintenance of heat resistant insulation in an adequate condition.
d. Ensuring relief and vent systems have been installed with the necessary valves, blinding
provisions, access, and other support infrastructure to safely isolate, drain liquids, and gas
free these systems during unit shutdowns or maintenance periods.
e. Ensure that there is an acceptable disposal route for hydrocarbon liquids from disposal
system knock out drums and water from knock out drums and water seal drums at all
times.
f. Institute and update as necessary a management system using the Relief and Overpressure
summary to ensure all parts of the overpressure protection system are in place, performing
to requirements and tested at the required frequency while the plant is operating. This shall
include:
1. Pressure-limiting safety instrumented systems at SIL 1 and higher integrity level are
clearly identified with their design details and/or critical set points summarized in the
Relief and Overpressure database summary.
2. Identifying relevant process equipment or components in the Relief and Overpressure
database such as: relief valve tag numbers, sizes, design capacity, and the equipment
or system a relief valve protects; control valves with trim sizes, bypasses, restriction
orifices, locked valves and other facility elements if they impact the overpressure
protection system design.
3. Fire-resistant insulation is verified and maintained in place.
4. Other critical items derived from clauses 6.4.2 through 6.4.11 are identified and
verified as being correctly installed and operational.
g. Develop a Register of Safety Critical Equipment for new plant and create the same from
existing data on all units before modifications are agreed, particularly for modifications to
the relief and overpressure system. The Register of Safety Critical Equipment on each site
Page 49 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
shall also be kept up to date to reflect any relief and overpressure system changes as part of
the plant modification/ MOC procedures.
h. Ensure relief devices on relief and overpressure systems which are designated by the site
as safety critical are included in the Register of Safety Critical Equipment with the
following minimum information:
1. A list of safety critical relief devices with their tag numbers.
2. Identification of other instruments or systems classified as being necessary for safety
critical overpressure or underpressure protection in the process being operated.
3. The inspection or testing interval for safety critical relief devices.
Page 50 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
Annex A
(Informative)
Regional annex on local regulation
This GP does not necessarily include the requirements of all local statutory regulations. However, the
UK and many other countries have such regulations affecting overpressure protection. The most
important examples are:
a. The provision of pressure relief devices in steam-raising and compressed air installations.
b. Such restrictions as may be imposed on atmospheric discharge.
c. The method of sizing pressure relief devices.
Page 51 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
Annex B-1
(Normative)
Operator intervention decision tree for liquid relief to closed system
with adequate liquid retention or for non-hazardous liquids
For potential liquid relief situations, operator intervention may be considered under certain conditions.
Outside the battery limit it is impractical to ignore operator intervention and allowing for such
intervention is worldwide practice, which is considered acceptable.
NOTES:
1. Relief is not needed unless there is a case in which the inflow is greater than the outflow and the source pressure is greater than
the design pressure of the equipment.
2. To prevent relief, an operator must have an adequate number of separate independent indicators such as level alarms, flow
variation alarm, etc. along with the time to react.
3. Design relief capacity depends on the length of time before a potential incident can occur. If the available time is less than
10 minutes, there is insufficient time to ensure operators can take corrective action and adequate relief capacity or a high
reliability trip is required.
4. If the available response time is greater than 30 minutes, it is unlikely operators would not take appropriate action. This relies on
operators being aware that a problem is occurring. Therefore, it is vital that instrumentation warning the operators that something
is amiss must be in service and fully operational before any equipment is commissioned or placed in operation.
5. If the time is between 10 minutes and 30 minutes (which encompasses most of IMSL ’s cases) the relief design for different
hazard rates depends on the level of indication.
Page 52 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
Annex B-2
(Normative)
Operator intervention decision tree for liquid relief without adequate
retention or for hazardous liquids
Page 53 of 54
28 September 2007 GP 44-70
Guidance on Practice for Overpressure Protection Systems
Bibliography
The following references are current at the time of publication, but are not maintained by IMSL, with
the exception of GP 48-03.
[2] GPSA Engineering Data Book This Gas Processors Suppliers Association (GPSA) manual has a
section titled “Relief Systems” which covers design and operation of pressure relieving systems for
gas processing plants.
[3] Relief Valve sizing and Simulation Tools Normally relief and flare systems have enough capacity
to handle small increases in flow rates from debottlenecking or minor process changes. If significant
flare/relief system changes are planned or for new facilities, a full flow analysis is required. Tools for
this include:
Visual Flare
FlareNet
Page 54 of 54