SOR.234.2-21-R.1, PITCH-UP Pipa 48 - 32 Indonesia Power
SOR.234.2-21-R.1, PITCH-UP Pipa 48 - 32 Indonesia Power
SOR.234.2-21-R.1, PITCH-UP Pipa 48 - 32 Indonesia Power
2. SAFETY GEARS
4. TRANSPORTASI
5. EQUIPMENT
- Excavator PC-200 = Sudah termasuk pada Estimasi Mob / Demob Loading Pipa
Project Mgr.
Name of Bid : PITCH - UP
Bid Value Rp. 753,690,000.00
Sheet : 1 of 2
1 MOBILIZATION / DEMOBILIZATION
2 PITCH - UP
2.1 - Tools & Equip. - Excavator = Sudah termasuk pada Estimasi Mob / Demob Loading Service
Sheet : 2 of 2
UNIT PRICE AMOUNT
NO DESCRIPTION QTY UoM
Rp. Rp.
- Manpower - Pipe Fitter - 1 1.00 Inch 37,300.00
TOTAL HARGA SATUAN PEKERJAAN PITCH-UP PIPA 48" & 32" / INCH 164,705.00
TOTAL BIAYA PITCH-UP PIPA 48 " ( QTY - 86 Jt = 4,128 Inch ) 4,128.00 Inch 164,705.00 679,902,240.00
TOTAL BIAYA PITCH-UP PIPA 32 " ( QTY - 14 Jt = 448 Inch ) 448.00 Inch 164,705.00 73,787,840.00
PEMBULATAN 753,690,000.00
Note : 1. Harga pekerjaan yang berlaku adalah Harga Satuan Pekerjaan Pangalengan, August 07, 2021
2. Termijn setiap 7 % Progres Volume Pekerjaan. PT. SRI MUKTI
Berita Acara Serah Terima Pekerjaan ( 100 % ) -
3.
dihitung sesuai volume actual hasil Inspect Bersama.
4. Invoice non Pajak kecuali pph.
Project Mgr.
PT.SRI MUKTI
BID PRICE - R1
PIPE LINE INSTALLATION SERVICES
SS-1 to WWQ Well Pad