Spindletop Energy

Folgers #228 Drilling


Work Performed 12/31/2021 06:00 - 1/1/2022 06:00
Report # 17 Report Date 1/1/2022
Well Folgers #228 Rig Energy Drilling #14 Days Since Spud
API # 42-123-31749 Rig Phone # AFE Amt / #
Field Coffee Valley RKB 20.5 ' Cum Cost
Location Section 002, T10S-R03W Ground Elevation 11.8 ' Daily Cost
County, State Dewitt, TX Water Depth Proposed (MD/TVD)
Permit # 251532 Present (MD/TVD)
Supervisors Eugene Troxell Daily Progress
Activity Summary Drill to 6148'. Circ. Sweep, Wiper trip to 3530'. Adjust brakes. TIH. Drill to 6148'. Change seat in mud pump #1.Drill to 7211.
Activity Planned Drill to 1800 hrs. CBU. Wiper trip to 6022'. Drilling ahead.
FROM TO HRS ACTIVITY DEPTH HOURLY COMMENTS
6:00 8:00 2.00 Drilling 6,148 ' Drilling and sliding to stay on directional plan from 6022 ft. to 6148 ft. For 126' ft. 165 SPM, 700 GPM, 3000 PSI, 70 RPM,

8:00 9:00 1.00 Circulating 6,148 ' Circulate 40 bbl hi vis sweep w/ LCM to surface at 6148 ft. Working and rotating pipe. 165 SPM, 700 GPM, 2800 PSI, 70 R

9:00 10:30 1.50 Tripping 6,148 ' Pump slug, Short trip from 6148 ft. to 3530 ft. 30-40k drag in spots. Work back down through spots and excessive drag go
10:30 11:00 0.50 Rig Service 6,148 ' Adjust brakes on drawworks, rig service.
11:00 12:30 1.50 Tripping 6,148 ' Trip back in hole from 3530 ft to 6148 ft. Hole taking proper fillups.
12:30 14:00 1.50 Drilling 6,294 ' Drilling and sliding to stay on directional plan from 6148 ft. to 6294 ft. For 146' ft. 165 SPM, 691 GPM, 3200 PSI, 70 RPM,
after short trip 70 units.
14:00 15:30 1.50 Rig Repairs 6,294 ' Change seat and valve on #1 mud pump. Discharge valve between pumps was leaking preventing pumping with #2 mud
on discharge valve.
15:30 6:00 14.50 Drilling 7,211 ' Drilling and sliding to stay on directional plan from 6294 ft. to 7211 ft. For 917' ft. 165 SPM, 691 GPM, 3200 PSI, 70 RPM,

Total Hrs: 24.00 Job Total Hrs: 408.00


Additional Notes
Casing Record
Type Size Weight Grade Thread Hole Size Top (MD) Btm (MD) Btm (TVD) TOC Cmt Sxs FIT/LOT
Conductor 20.000 '' 104.13 X-42 0' 187 ' 187 ' 0'
Surface 13.380 '' 61.00 J-55 0' 3,557 ' 3,557 ' 0' 2590 14.9 ppg FIT
Intermediate 9.630 '' 53.50 P-110 Planned
Liner 8.500 '' 29.70 EXP Planned
Liner 7.000 '' 29.00 HCP-110 Planned
Production 5.000 '' 18.00 HCP-110 Planned
Bit Record
# Size Make Model S/N Jets Dpth In Dpth Out Hours RPM ROP WOB Press. GPM Grade
1 17.500 '' Taurex GP-1P J44659 3 X 18, 1 X 16 25 ' 3,560 ' 39.0 80 91.2 20 1650 684 2,2,WT,A,E,I,NO,TD
2 12.250 '' Taurex HP-IPGC 1910829 3 X 18, 1 X 16 3,560 ' 31.0 171 180.0 30 3150 670

BOP Stack
Type Make Model Size WP TP Last BOP Test
Annular Hydril GK 13.625 '' 5,000 3,500 1/1/2020
Choke MAN 2.063 '' 5,000 5,000 1/1/2020
Pipe Rams LWS DBL 13.625 '' 5,000 5,000 1/1/2020
Drilling Parameters
Depth ROP RPM WOB B.G. Gas Torque Mud WT PU WT SO WT RT WT
6,980 ' 11 5.0 9.80 180 170 175 Clay, sand
Remarks
Mud Record
Type WBM

BHA Total Length 1,016.08 '


No. OD ID Description Length

Pump Data
Number 1 2
Mud Comp BCS Fluids 1 12 1/4 HA-IPGC 0.95 ' Stroke
Depth 7,015 ' 3X18,1X16
Liner Size
Time 12:00 AM 2 MUD MOTOR 28.42 ' 7:8X4.0,1.5 Pump Rate (GPM)
DEG,.166
Mud Weight In/Out 9.80/9.80
Viscosity 45.00
PV 10.00
YP 12.00
WL 10.00
HTHP
Cake 2.00
Solids
pH 9.20
Cl 4200.00
Gels 12.00 / 34.00 / 44.00
Mud Additives
3 11 3/4 STAB 7.53 '
4 UBHO 2.72 '
5 NMDC MWD COLLAR 28.64 '
6 NMDC 29.28 '
Health, Safety & Environment
Accidents Spills
POL 22
Temperature/Wind 41 °F - 4 mph NNE
Weather Clear
Waves
Efficiency % 95.00 95.00
SPM 82 83
Pressure 3,200 3,200
On Board Inventory
7 DP XO 3.02 ' Material 24 hr Usage Received On Hand
8 24 HWDP 730.97 ' Fuel - gal 1,794 6,734 11,886
9 DRILLING JARS 30.66 ' Barite - ton 693
10 5 JTS HWDP 153.89 ' Cement - sks 0
Additive Name QTY
Super seal 10
Caustic 6
Lime 4
Lig / nut plug 45
Folgers #228 Drilling Work Performed: 12/31/2021 06:00 - 1/1/2022 05:59 Repo
Intangible Costs
Cost Name Code Amount Cumulative Remarks
Mobilization 162-10 $117,045.00
Lump Sum 162-10.1 $117,045.00
Rig 162-11 $15,000.00 $148,751.00
Drilling Dayrate 162-11.1 $15,000.00 $148,751.00 Dayrate
Fluids 162-12 $5,769.00 $101,904.00
Mud' Materials, Chemicals & Additives 162-12.1 $964.00 $29,078.00

$330.00 Super seal


$472.00 Lig / nut plug
$162.00 Tax
Mud' Engineer 162-12.2 $2,000.00 $25,647.00 Mud engineer
Mud' Rentals 162-12.22 $105.00 $525.00 2 - bulk tanks and air pump
Solids Control Equipment 162-12.3 $2,700.00 $38,190.00 PMI Closed loop system, personnel
Other 162-12.5 $8,464.00
Rentals 162-13 $3,634.00 $65,097.00
HWDP 162-13.03 $420.00 $2,940.00 4-1/2" HWT DP (15 jts), (420/day while in hole)
BOP's/Manifold/Etc. 162-13.1 $510.00 $3,060.00 13 5/8" BOP single rental
Tester Personnel 162-13.12 $8,460.00
Communications 162-13.13 $225.00 $2,700.00 Rig phone system
Forklift 162-13.14 $150.00 $3,150.00 10k forklift
Surface rentals 162-13.16 $295.00 $4,415.00 200kw gen. for PMI Equip.
Test Plug/Wear Bushing 162-13.16.3 $105.00 $525.00 Wear bushing and retrieving tool
Trip Tank 162-13.16.4 $560.00
Pumps 162-13.16.5 $122.00 $1,304.00 3" diaphram pumps and hoses
Other 162-13.16.6 $8,627.00
Misc rentals 162-13.17 $230.00 $6,890.00 Light towers (4)
Trailers, sewer, water 162-13.18 $392.00 $6,457.00 4 trailers, water and sewer systems, trash bin (25/day)
Generators 162-13.19 $386.00 $7,334.00 2 generators for house trailers
Jars 162-13.5 $299.00 $2,093.00 Drilling Jars(299/day while in hole)
Data Monitoring System 162-13.7 $500.00 $6,000.00 Rig monitoring system
Inspection and Damages 162-13.8 $582.00
Cementing 162-16 $57,525.00
Cementing 162-16.1 $51,995.00
Float Equipment 162-16.2 $3,430.00
Centalizers 162-16.3 $2,100.00
Bits, Stabilizers, Other DH Equip 162-17 $18,950.00
Bits & Mills 162-17.1 $17,950.00
Stabilizers 162-17.2 $1,000.00
Tubular Services 162-18.1 $47,857.00
Casing Crews 162-18.1.1 $16,361.00
PU LD Machine 162-18.1.2 $5,862.00
Other 162-18.1.7 $25,634.00
Labor 162-21 $9,463.00
Roustabouts 162-21.3 $2,123.00
Wellhead 162-21.4 $5,780.00
SVC Personnel 162-21.5 $1,560.00
Supervision 162-22 $3,600.00 $55,600.00
Consultant 162-22.1 $2,800.00 $42,000.00 Ben Perry and Jeff Brousard
Engineering 162-22.4 $800.00 $13,600.00 Engineering services
Transportation 162-23 $2,925.00 $29,407.00
Trucking 162-23.1 $15,592.00
Other 162-23.7 $2,925.00 $13,815.00 Trucking for disposal of WBM/cuttings
Disposal 162-25 $9,710.00 $70,994.00
Cuttings 162-25.2 $9,710.00 $65,913.00
Other 162-25.3 $5,081.00
Directional Survey/Drilling 162-26 $9,350.00 $62,992.00
Operator 162-26.1 $9,350.00 $58,225.00 DDS Personnel/equipment
Gyros/Multishot 162-26.4 $4,767.00
Permits & Locations 162-360 $131,600.00
Location Construction 162-360.3 $131,600.00
Fuel, Electrcity, Water 162-370 $62,856.00
Fuel 162-370.1 $44,272.00
Water 162-370.2 $18,584.00
Contingency 162-999 $4,998.80 $98,004.00 10%
Total Intangible Costs: $54,986.80 $1,078,045.00
Tangible Costs
Cost Name Code Amount Cumulative Remarks
Casing 163-210 $124,357.00
Wellhead 163-230 $6,732.00
Trees 163-230.2 $6,732.00
Total Tangible Costs: $0.00 $131,089.00
Total Costs: $54,986.80 $1,209,134.00
Days Since Spud 10
AFE Amt / # $1,534,600 / D7384
Cum Cost $1,209,134
Daily Cost $54,987
Proposed (MD/TVD) 13,521 ' 13,500 '
Present (MD/TVD) 7,211 ' 7,193 '
Daily Progress 1,189 '

MENTS
65 SPM, 700 GPM, 3000 PSI, 70 RPM, 1200-3500 ft/lbs torque.

pe. 165 SPM, 700 GPM, 2800 PSI, 70 RPM, 1300 ft/lbs torque

n through spots and excessive drag gone.

65 SPM, 691 GPM, 3200 PSI, 70 RPM, 2000-5500 ft/lbs torque. Max gas

ng preventing pumping with #2 mud pump. Changed paddle and rubbers

65 SPM, 691 GPM, 3200 PSI, 70 RPM, 2000-5500 ft/lbs torque

Cmt Sxs FIT/LOT

2590 14.9 ppg FIT

GPM Grade
684 2,2,WT,A,E,I,NO,TD

BOP Test Next BOP Test


1/1/2020 1/21/2020
1/1/2020 1/21/2020
1/1/2020 1/21/2020

12.00 '' 12.00 ''


6.00 '' 6.00 ''
345.00 347.00
Report # 17

marks Vendors

Energy Drilling

BCS Fluids
BCS Fluids
BCS Fluids
Eagle Consultants
BCS Fluids
el PMI

while in hole) Knight Oil Tools


Patterson

Oilfield Instrumentation
Rusco Services
Jewel Rentals
Warrior Energy Services
Jewel Rentals

Jewel Rentals
ms, trash bin (25/day) Jewel Rentals
Jewel Rentals
e) Knight Oil Tools
Oilfield Instrumentation

Stokes & Sphieler


Eagle Consultants

ttings Omni Environmental Solutions

R 360

Downhole Drilling Services

marks Vendors

You might also like