MECHANICAL WORKS
GENERAL
ACTIVITY – 09 WORKING UNDER CRANE , LIFTING EQUIPMENTS
ACTIVITY – 10 LOADING UNLOADING ON TRUCK/TRAILOR etc…
ACTIVITY – 11 HANDLING OF GAS CYLENDORS
ACTIVITY – 12 SLIPS,TRIPS&FALL AT WORK PLACE
ACTIVITY- 13 FIRE PREVENTION AND PROTECTION
ACTIVITY- 14 EMERGENCY PREPAREDNESS
2
S. ACTIVITY HAZARD CONSEQUENCE PROBABILITY SEVIRITY RISK LEVEL RISK RATING CONTROL MEASURES
No. FACTOR FACTOR
ACTIVITY – PLACEMENT OF CRANE / HYDRA
MODERATE
Crane /Hydra
placement
1. Toppling of crane/hydra.
2. Failure of crane/hydra.
1. Person may sustain
severe injuries and prove
4 3 3 1. Soil condition is good & well leveled..
2. Compacted soil. .
1
fatal. 3. Ensure proper base plates or sol plates are provided
2. Persons working at lower under the jack.
level get injured. 4. Check over head clearance like live lines etc…
3. Property damage. 5. The out riggers are fully extended.
6. Not provide any other supports on jack.
7. Crane has a valued test certificate.
8. The operator had availed driving license.
9. No haudraulic leakages
10. Proper load chart is available
11. Proper PPEs are wearing all work force in
evolving this activity
12. Ensure that the crane had its SLI unit and
over hoist limit switch.
13. Competed riggers are trained & medically fit.
14. Keep fire extinguishers in crane.
15. Proper bed should made for movement of
crane
16.
Design scaffolding fo
10.
Scaffolding planks sh
S. ACTIVITY HAZARD CONSEQUEN PROBABILIT SEVIRITY RISK RISK RATING CONTROL MEASURES
No. CE Y FACTOR FACTOR LEVEL
ACTIVITY – 2 LIFTING ARRAINGEMENT
1 Lifting hook 1. Failure of hook. 1. Injury to eyes do to 3 5 High 3 1. Use proper PPE.
welding and 2. Electrocution. welding work. 2. Select proper size of plate for hook purpose.
sling 3. Cut injury. 2. Accident and injury 3. Proper ribs provided in hooks.
arraignments. 4. Scratch injury. 4. Know the accurate weight of the material should
5. Failure of slings. lift.
5. Calculate the CG of the material.
6. Choose the appropriate sling.
7. Mark the SWL of the sling.
8. Ensure the third party inspection certificates are
available for all lifting tools & tackles and its validity..
9. Check the all the tools before in use.
10. Check the welding of lifting hook.
11. If the work is above 1.8 mtr height wear double
lanyard safety harness.
1 Gas welding / 1. Welding radiates invisible 1. Radiation can damage eyes and 2 5 HIGH 4 1. Use specified shielding devices and other PPE of
cutting / heating. ultraviolet and infrared rays. skin. correct specifications.
2. Improper placement of 2. Explosion may occur. 2. Avoid throated tungsten electrodes for GTAW.
oxygen and acetylene cylinders. 3. May cause fire. 3. Move out any leaking cylinder.
3. Leakage /cuts in hoses. 4. Cylinder may burst. 4. Keep trolley for transportation of cylinders and
4. Opening - up of cylinder. chain them .
5. Welding of tanks, container 5. Use flashback arrestors.
or pipes storing flammable 6. Purge regulators immediately and then turn off.
liquids. 7. Never use grease or oil on oxygen line connections
and copper fittings on acetylene lines.
8. Inspect regularly gas carrying hoses.
9. Always use red hose for acetylene and other fuel
gases and blue for oxygen.
10. Always stand back from regulator while opening
the cylinder.
11. Turn valve slowly to avoid bursting.
12. Cover the lug terminals to prevent short circuiting .
13. Empty & purge them before welding.
14. Never attach the ground cable to tanks, container
or pipe storing flammable liquids.
15. Never use LPG for gas cutting.
Working at 1. Person can fall down. 1. May sustain sever injuries 2 5 HIGH 4 1. Provide guard rails/ barricade at the work place.
elevated 2. Material can fall down or prove 2. Use PPE like full body harness, life line, helmets,
places. fatal . safety shoes, etc.
2. May hit the scrap/ material 3. Obtain the permit before starting the work at height
stacked above 3m.
at the ground or in between. 4. Fall arrest and safety nets, etc, must be installed.
3. May hit the workers 5. Provide adequate working space (min.0.6m).
working at 6. Tie / weld working platform with fixed support .
lower levels and prove fatal. 7. Use roof top walk ladder while working on a
slopping roofs.
8. Avoid movement on beams.
9. Keep the work place neat and clean.
10. Remove the scrap immediately.
11. Do not throw or drop materials or equipment from
height. i.e. do not bomb materials.
12. All tools to be carried in a tool- kit Bag or on
working uniform.
13. Remove scrap from the planks.
14. Ensure wearing of helmet by the workers working
at lower levels.
1 Loading and 1. Loaded material due to fall. 1. Accident / injury 1 5 HIGH 4 1. Follow lifting procedure.
unloading of 2. Defective equipment. 2. Damage of materials. 2. Use correct equipment & lifting tackles.
materials on 3. Overloading 3.Damage to equipment. 3. Supervision by competent persons.
trucks / trailers. 4. Provide trained banks men/rigger.
5. Do not jump out from vehicle till clearance is
obtained.
6. Proper supervision.
7. Refer to load chart.
8. Use platform ladder for safe access.
9. Never deactivate or deenergise over riding devices
on lifting equipment.
2 Loading near 1. Live facilities / OH lines etc. 1. Fire 2 5 HIGH 4 1. Keep Safe distance from Live facilities.
live facilities 2. Electric shock.
3. Injury.
4. Property Damage
preparedness vehicle.
2) One dedicated person always present in this job.
2) Absence of the Rescue
3) First aid box facilities available at work spot.
person.
4) Ensure passage way always free from any
3) First Aid not available.
obstruct.
4) Access blocked by
5. Keep fire fighting equipments near to the work
material.