Bdp-Bcpa3 & BLQ3 - DPR 03-07-2017
Bdp-Bcpa3 & BLQ3 - DPR 03-07-2017
Bdp-Bcpa3 & BLQ3 - DPR 03-07-2017
ONGC
Contractor : M/s. L&T Hydrocarbon Engineering
PROJECT : Bassein Development Project
CA : M/S. ABSIV (INDIA) PVT.LTD. PRODUCTION DATE: 7/2/2017
TPI : M/S. VCS (INDIA) PVT.LTD. REPORTING DATE : 7/3/2017
ONGC/BDP/ABS/3607093/BCPA3& BLQ3/081
Location & Activity: BCPA3 & BLQ3 Platform - Green Field Hook up, Pre-commissioning & Commissioning Works
Barge: Hookup & Accommodation barge EASTWIND 365
SCOPE
Sr. no Description L-2 WTG Items/ Qty / No. Today's Progress Cumulative Progress Remarks
Unit Fit - up Welding NDT
0.00% 66.86%
0.00% 88.04%
ii Non - metallic 8 Joints / 126 Inch No. / Inch Dia. 126 Scope Completed
Dia
Total 39 Spools /190 Inch No. / Inch Dia. 0 190 Scope Completed
Dia
0.00% 100%
0.00% 43.24%
0.00% 100.00%
Total 68216 mtrs / 1583 0 Mtrs. & 0 Nos. 29908 Mtrs. & 240 Nos.
Nos
0.00% 29.50%
1.4.2 BLQ3 Platform 1.36% 0.000% 1.03%
0.00% 75.81%
Total 98502Mtrs / 935 Nos Mtrs / Nos. 0 Mtrs &0 Nos 105570 Mtrs. & 200 Nos.
0.00% 64.28%
Total 1287 Mtrs / 38 Nos Mtrs / Nos. 0 Mtrs & 10 Nos 1287 Mtrs & 27 Nos
0.00 85.53%
1.6 Architectural 1.60% 0.000% 0.800%
0.00 1.00
BLQ-3
(1) Installation of bed rails: 15 Nos completed.
2 (2) False floor tiles alignment & sticking of skirting in progress.
(3) Installation of supporting Hooks on the bed completed as per ONGC observation in all living rooms.
PRE-COMMISSIONING
(1) System conformity & continuous flow test of ODD System at BLQ3 completed.
3 (2) Loop Check completed for 26 Nos of addressable F&G smoke detectors in TG Module. All loop check for addressable F&G smoke detectors for TGBM & BLQ3 completed.
(3) Leak test of start up air system at BCPA3 in progress.
BLQ3
(1) Furniture installation to continue.
2
Area of Concern :
1) SAT Approved Procedures were not available at offshore for Life Boat David Load Test and STP Test. L&T Performed the Test and the acceptence subject to approval of Procedures.
2) During the SAT Test of Water Maker at BLQ3 Platform, Vibrations observed in HP Pump locations which needs to be rectified. Refer E-mail dated on 25.05.2017
3) Safety Surveyor is not availble at site from 01st June onwards and needs to be mobilized immediately
4) In order to avoid the corrosion during monsoon period, wherever the Parent Material Exposed to atmosphere needs to be painted immediately . Advised to L&T , to take needful action. Refer E-mail dated on 19.06.2017
5) Observations noticed in HVAC Package at BLQ3 Platform and needs to rectify the same. Refer E-mail dated on 21.06.2017
Note :
(a) Percentage progress break up (discipline wise) considered only if work fully completed. Regular cumulative progress is mentioned in appropriate columns.
(b) BCPA3 Hardcopy drawings yet to be submitted to ONGC TPI/CA.