Name of Utility shifting

Name of work From chainage To chainage


deportment

1 Utility shifting up to 33 kv 156+000 168+000 APSPDCL


2 Utility shifting up to 33 kv 168+000 180+000 TANGEDCO
3 Utility shifting up to 110 kv 178+100 178+350 TANTRANSCO
4
5 Utility shifting up to 765 kv 167+050 167+300 PGCIL(Powergrid)
6 Utility shifting up to 765 kv 169+700 169+950 PGCIL(Powergrid)
7 Utility shifting up to 765 kv 172+700 172+850 PGCIL(Powergrid)
8 Utility shifting up to 400 kv 174+650 174+750 PGCIL(Powergrid)
9 Utility shifting up to 400 kv 177+950 178+100 PGCIL(Powergrid)
10 Utility shifting up to 400 kv 179+650 180+000 PGCIL(Powergrid)
Utility shifting det
praposal
Date of Total
and
Last Site Visit Reqest by Approved Expenditure
Name of Division Interventions estimate
Date Authority for by Sanctioned (Rs
submitted
estimate in Cr)
date

Chittoor 05.03.2022 RO 3.602


Katpadi 18.10.2021 RO 3.531
Salem 12.05.2023 1.548

Southern Region -1
Southern Region -1 45.063
Southern Region -1
Southern Region -2
Southern Region -2 17.66
Southern Region -2
Utility shifting details

Date of Physical
Santion Deposit of
start Progress in
Approval Sanction Letter no. Supervision
(Utility % of Utility
Date Charges Rs
shifting) Shifting

22.03.2022 CGM/O&M/EE/C/F e-295365/ D. No 293/22 900,579


18.10.2021 870,170
09.08.2023 SE/O/TVLM/EA/AE-T/F.DCW NHAID 499/2023 377,457

16.09.2021 9,805,974

22.09.2023
Financial Total Date /Likely date
Utility Shifting
Progress in % Expenditure of Completion Pendency
Completed or Remarks
of Utility So Far (Rs in (Utility Shifting Reason
not
Shifting Cr) work)

completed
completed
Under progress

Under progress
Under progress
Under progress
Under progress
Under progress
Under progress