P166 NSE TS MS MEP MECH 00001 02 Raft Piping Drainage System - B
P166 NSE TS MS MEP MECH 00001 02 Raft Piping Drainage System - B
P166 NSE TS MS MEP MECH 00001 02 Raft Piping Drainage System - B
RELATED TO:
MEP
CIVIL ARCH STRUCT A/C ELECT PLUMB GENERAL
CONTRACTOR:
SUBMITTED BY: Eng. Mohamed Omar SIGNATURE: DATE: 30-Dec-2023
Project Manager
CONSULTANT:
RECEIVED BY: SIGNATURE: DATE:
APPROVED AS NOTED B
ACTION
REVISED AND RESUBMIT C
REJECTED D
CONSULTANTS COMMENTS:
Refer to the review comments noted on the attached Comment Sheet.
CONSULTANT:
RESPONSE BY: Eng. Hamdy Alqatrany SIGNATURE: DATE: 08-Jan-2024
Resident Engineer
CLIENT COMMENTS:
CLIENT:
RESPONSE BY: SIGNATURE: DATE:
CONTRACTOR:
RESPONSE RECEIVED BY: SIGNATURE: DATE:
NOTE: APPROVAL / COMMENTS DO NOT RELIEVE THE CONTRACTOR FROM HIS CONTRACTUAL OBLIGATIONS.
DISTRIBUTION:
Engineer’s Comments Sheet
Date : 08/Jan/2024
Reference : P166-NSE-TS-MS-MEP-MECH-00001-02
Status : Approved as noted
Mech:
Only for the raft area , all other areas to be provided for check.
Provide mockup.
Pipes during casting to be under pressure to detect if any leak occurring.
Pipes to be fixed properly.
Coordinate with all other services.
MIR, installation approval, testing to be done before casting.
Page 1 of 1
CLIENT CONSULTANT CONTRACTOR
COMPLIANCE STATEMENT
Document Description: Method Statements of Raft Piping - Drainage System
Submittal Ref: P166-NSE-TS-MS-MEP-MECH-00001 Rev.02
MECH:
The Contractor reply /proposal is inaccurate since the submittal subject is for
the U/G piping which includes the external MH, GT, FCo, concrete
1 Noted , Title changed to MOS of Raft Piping- Drainage System
incasement..etc while the Contractor replies consider the raft only. Either
update the subject or update the content of the submittal as commented.
CLIENT CONSULTANT CONTRACTOR
RELATED TO:
MEP
CIVIL ARCH STRUCT A/C ELECT PLUMB GENERAL
CONTRACTOR:
SUBMITTED BY: Eng. Mohamed Omar SIGNATURE: DATE: 21-Dec-2023
Project Manager
CONSULTANT:
RECEIVED BY: SIGNATURE: DATE:
APPROVED AS NOTED B
ACTION
REVISED AND RESUBMIT C
REJECTED D
CONSULTANTS COMMENTS:
Refer to the review comments noted on the attached Comment sheet
CONSULTANT:
RESPONSE BY: Eng. Hamdy Alqatrany SIGNATURE: DATE: 28-Dec-2023
Resident Engineer
CLIENT COMMENTS:
CLIENT:
RESPONSE BY: SIGNATURE: DATE:
CONTRACTOR:
RESPONSE RECEIVED BY: SIGNATURE: DATE:
NOTE: APPROVAL / COMMENTS DO NOT RELIEVE THE CONTRACTOR FROM HIS CONTRACTUAL OBLIGATIONS.
DISTRIBUTION:
Engineer’s Comments Sheet
Date : 28/Dec/2023
Reference : P166-NSE-TS-MS-MEP-MECH-00001-01
Status : Revise & Resubmit
The Contractor reply /proposal is inaccurate since the submittal subject is for
the U/G piping which includes the external MH, GT, FCo, concrete
incasement..etc while the Contractor replies consider the raft only. Either
update the subject or update the content of the submittal as commented.
Page 1 of 1
CLIENT CONSULTANT CONTRACTOR
COMPLIANCE STATEMENT
MECH:
NSE Structural Engineer submitted the details of embedded piping. Raft thickens's
Pipes should run in the raft as per the common practice, however subject to incresed from 400mm to 700mm to reduce the piping below raft. However this
1
Structure Engineer, details to be submitted in detail. submission is the methodology of pipe installation in Raft to proceed with work.
Final approval subjected to work inspection approval.
The tile coordination to be approved and FD location and wc type to be confirmed
2 There is no tile or WC in basement. Please refer to the Basement layout.
before the final pipe locations.
Raft thickness inceased to 700mm to reduce the piping below raft and wherever
3 Provide deatails of concrete encasement. the pipe goes below raft shall be protected with trench & adequate
reinforcement as shown in the drawing. Refre drainage approved drawings.
There is no Manhole in the basement. Refer to basement drainage L/L drawing.
Catch Basin, Gully trap, Sump pit & sand trap, trench grating only available in
4 Provide manhole pipe method statement. basement. Drainage Manholes are in the basement H/L. Moreover M.H
construction MOS will be submitted separately prior to commence M.H
construction work.
During casting, pipes should be under metered pressure to indictae any leakage or
5 Noted. Compliance subjected to work inspection approval at site
broken pipe.
HSE:
The Contractor shall submit a complete and sufficient Risk Assesment with
1 Comply. Refer to attached Risk assessment.
quantitative matrices for all stages of activities.
2 HSE precautions must not be ignored. Noted. Necessary precautions will be taken prior to commence the work at site.
CLIENT CONSULTANT CONTRACTOR
RELATED TO:
MEP
CIVIL ARCH STRUCT A/C ELECT PLUMB GENERAL
CONTRACTOR:
SUBMITTED BY: Eng. Mohamed Omar SIGNATURE: DATE: 4-Nov-2023
Project Manager
CONSULTANT:
RECEIVED BY: SIGNATURE: DATE:
APPROVED AS NOTED B
ACTION
REVISED AND RESUBMIT C
REJECTED D
CONSULTANTS COMMENTS:
Refer to the review comments noted on the attached Comment Sheet.
- Submission Ref No. should reflect on the attached method statement.
CONSULTANT:
RESPONSE BY: Eng. Hamdy Alqatrany SIGNATURE: DATE: 29-Nov-2023
Resident Engineer
CLIENT COMMENTS:
CLIENT:
RESPONSE BY: SIGNATURE: DATE:
CONTRACTOR:
RESPONSE RECEIVED BY: SIGNATURE: DATE:
NOTE: APPROVAL / COMMENTS DO NOT RELIEVE THE CONTRACTOR FROM HIS CONTRACTUAL OBLIGATIONS.
DISTRIBUTION:
Engineer’s Comments Sheet
Date : 29/Nov/2023
Reference : P166-NSE-TS-MS-MEP-MECH-00001
Status : Revise & Resubmit
Mech:
∧ Pipes should run in the raft as per the common practice, however subject to Structure
Engineer, details to be submitted in detail.
∧ The tile coordination to be approved and FD location and wc type to be confirmed
before the final pipe locations.
∧ Provide details of concrete encasement.
∧ Provide manhole pipe method statement.
∧ During casting , pipes should be under metered pressure to indicate any leakage or
broken pipe.
HSE:
The Contractor shall submit a complete and sufficient Risk Assessment with quantitative
matrices for all stages of activities.
HSE precautions must not be ignored.
Hamdy Al-Qatrany
Resident Engineer
Page 1 of 1
“Method of Statements for
Raft Piping - Drainage
System ”
SPOTS
ELECTROMECHANICAL INSTALLATION OF RAFT PIPING - Date Rev.
WORKS L.L.C
DRAINAGE SYSTEM 29-12-2023 02
PROJECT TITLE:
PROJECT NO:
P-166
Document Title: Method Statement for Installation of Raft piping- Drainage System.
Page 1 of 14
Reference
SPOTS
ELECTROMECHANICAL INSTALLATION OF RAFT PIPING - Date Rev.
WORKS L.L.C
DRAINAGE SYSTEM 29-12-2023 02
CONTENTS
5.1 Materials
5.2 Tools
5.3 Clearance & NOCs
5.4 Preparation
5.5 Commencement
5.6 QA/QC Assurance
5.5.1 IT Plan
5.5.2 Calibration
5.5.3 Tolerance as specified.
5.5.4 Hold Point
5.5.5 Witness Points
5.5.6 Inspection Points
5.5.7 Test Regime
7.0 Responsibility
Page 2 of 14
Reference
SPOTS
ELECTROMECHANICAL INSTALLATION OF RAFT PIPING - Date Rev.
WORKS L.L.C
DRAINAGE SYSTEM 29-12-2023 02
This document defines the methods to be used to ensure that the works to be conducted at
site are in compliance with the approved designs and approved materials.
The method of statement describes the procedure for installation of Underground Drainage
piping system.
This document applies to the inward site inspection, installation, and inspection methods to
be adopted for the Underground drainage piping system.
1. Delivery and inspection of Drainage and Vent Piping materials upon delivery at site.
4. Delivery and inspection of Drainage and Vent Piping materials upon delivery at working
area.
Page 3 of 14
Reference
SPOTS
ELECTROMECHANICAL INSTALLATION OF RAFT PIPING - Date Rev.
WORKS L.L.C
DRAINAGE SYSTEM 29-12-2023 02
5.1 Material:
1. The raceway system material such as Drainage pipes should be according to the site
requirement and in accordance with the approved shop drawing/design drawing It should
be noted that the materials used in this work area are of valuable nature and that they
shall be stores in a secure location, and access to these materials shall be strictly
controlled.
2. All materials delivered to the site will be first to be inspected by the store in-charge / site
in-charge. All materials should be check in accordance with the site requirement,
approved design, and material qualification. It must also be free from any damage caused
during the delivery to site. Delivery documentation shall be checked for completeness.
Defective or damage materials shall either be returned to the supplier’s facility or stored
on site at a suitable quarantine location.
5.2 Tools:
2. Water level, level bar, File, Hole saw cutter and marker.
4. Electric Drill
7. Step ladder
Page 4 of 14
Reference
SPOTS
ELECTROMECHANICAL INSTALLATION OF RAFT PIPING - Date Rev.
WORKS L.L.C
DRAINAGE SYSTEM 29-12-2023 02
Not Applicable
5.4 Preparation:
1. Prior to installation of drainage and vent piping works, the supervisor and foreman will
verify and ensure that all the safety requirements have been complied with and are in
place.
2. The supervisor will verify that all relevant approved latest revisions of shop drawings,
technical submittals, inspection and test plans are in the workplace for installation
reference. This also includes installation procedures / method statement.
3. The supervisor and foreman will inspect all the materials delivered to the workplace and
ensure that these are the required materials and also for damage or defect. Materials
found not to be as per requirement or with damage or defect will be set aside. These will
be properly labeled and returned to the warehouse. These will also be reported in a Non-
Conformance Report to the QA/QC Engineer.
4. The supervisor and foreman will orient and familiarize all the plumbers and labors
involved in the installations regarding the relevant approved shop drawings, technical
submittals, installation procedures and details, acceptance criteria and safety
requirements.
5. The supervisor and foreman will examine surfaces to receive drainage and vent pipe works
for compliance with installation tolerances and other required conditions, as described in
the installation requirement. Installation will not proceed until unsatisfactory conditions
have been corrected.
5.5 Commencement:
1. All delivered material shall be inspected upon arrival at site / working area.
2. The delivered material shall be in accordance with the approved design and approved
shop drawing / Approved Material submittal.
3. The material should no defect or damage when delivered on site.
4. All delivered material that does not conform to the approved submittal and does not
conform on the mentioned above shall be returned to the point of supply or stored on the
Page 5 of 14
Reference
SPOTS
ELECTROMECHANICAL INSTALLATION OF RAFT PIPING - Date Rev.
WORKS L.L.C
DRAINAGE SYSTEM 29-12-2023 02
site at a suitable quarantine store. An NCR shall be raised for such non-conformance.
Noncompliance material to be sent outside the site.
1. Determine the position of the pipe as per approved shop drawing with the help of
surveyor coordinates for catch basins & other drain points. Pipe invert level, to be marked
out along the route of the pipe at intervals not exceeding 6 meters and at every branch,
changes in direction together with positions of floor drains and drain points.
2. Positions of the floor drains, cleanouts, vents, and drain points to be clearly marked and
identified by way of marker posts from main contractor’s surveyor reference provided on
site.
3. Each drain run prior to installation will be marked out with string between points of
changes in direction and held tight to prevent sagging. This line will be on the crown of the
pipe or if not possible to one side and will allow the pipe to be installed in a straight line to
the correct slope.
4. Measure length of pipe required and cut to suit ensuring a square cut. De-burr pipe and
chamfer ends. An allowance of 5-10mm for expansion to be made for each joint of pipe
run.
5. Lay pipes in aligned with the marker strings.
1. Measure depth of the socket and mark with pencil on spigot end of pipe.
3. Push spigot end of pipe into uPVC ring socket to full depth, ensuring that the ring seal is in
Place correctly and then pull back by 5-10mm to allow for expansion.
5. At the head of each drain branch, ensure that the floor drain or drain point is level with the
marker port reference and that the fitting is square.
6. On completion of each drain section, check and adjust if necessary to ensure that the pipe
Is in line with the marker string and all inverts are correct.
7. For pipe work that will be cast within the concrete slab, the pipe is to be restrained and
Supported by bent rebar rods with tie wires fixed around the pipe to prevent movement.
During testing and pouring concrete.
Page 6 of 14
Reference
SPOTS
ELECTROMECHANICAL INSTALLATION OF RAFT PIPING - Date Rev.
WORKS L.L.C
DRAINAGE SYSTEM 29-12-2023 02
8. Where the Raft thickness less than 500 mm and the slope ratio of pipe goes beyond the
raft depth compacted trench with Steel reinforcement to be provided to ensure the slope
of pipe maintained without affecting the substructure of the building.
8. During concrete pour, minimum one senior representative from main contractor & MEP
Contractor to be present to supervise the work. Proper care should be taken to avoid.
Contact from the mechanical vibrator to the pipe to avoid pipe breakage. In event of pipe
damage during casting that section of pipe will be removed immediately and
replaced and water will be filled to check for any leaks. Casting will proceed to other areas.
Till the pipe has rectified.
9. Pipes shall be laid to uniform slope as per approved shop drawing & DM standards.
10. All works open ends to be covered with temporary fabricated end caps / plugs.
1. All work shall be inspected for quality workmanship and conformance to specification prior to
offering for inspection.
2. Notice of inspection shall be advised to main contractor and to the consultant for their
discretionary attendance and witnessing. Notice shall be advised at least 24 hours prior to
date of inspection.
3. Water gravity leak test is conducted to ensure and prove the tightness of the joints and
ensure there are no leaks in the piping system.
4. The water pressure test can be applied to the entire system or in sections. All opening in the
piping will be tightly closed by end caps/plugs or by suitable means and the system filled with
water to the point of overflow from the highest point.
5. No section of the system shall be tested to less than 1.5meter head of water.
6. The water shall be kept in the system or in the portion under test for at least 4 hours during
inspection. The water level will be marked on the pipe at the start and before the end of the
test.
7. While the system is under test, a careful inspection shall be made on all the pipes and joints. If
any leaks in joints or evidence of defective fittings or pipe is revealed the defective fittings /
pipe shall be replaced with new.
8. After rectification the test will be carried out for minimum of 4 hrs.
9. Testing will be witnessed by main contractor / consultant to their satisfaction and
documentation will be maintained by the consultant and main contractor signing off the
inspection request.
10. Only after approval of testing, the pipe would be allowed to cast within the raft slab.
11. Temporarily seal the pipe opening using plastic or wooden disc with packing taps to avoid
ingress of debris and mortar during concrete pouring.
Page 7 of 14
Reference
SPOTS
ELECTROMECHANICAL INSTALLATION OF RAFT PIPING - Date Rev.
WORKS L.L.C
DRAINAGE SYSTEM 29-12-2023 02
1. Select the spirit level that will rest against the drainage pipe you are measuring without
contacting fitting or other obstacles. The level must rest only on the pipe.
2. Set the spirit level on the top of the pipe or hold it against the bottom. Note the position of
the spirit level’s bubble, it should not be centered. Life the end of the spirit level until the
bubble is centered.
3. Measuring the distance between the end of spirit level and the pipe. The distance is the slop
of the pipe along the length of spirit level.
4. Verify the slope is in the correct direction. The pipe must slope downward from the source of
the waste towards the main sewer or manhole.
10 For subsequent inspection procedures, see the Project Quality Control Plan.
1. Measure depth of the socket and mark with pencil on spigot end of pipe
3. Push spigot end of pipe into uPVC ring socket to full depth, ensuring that the ring seal is in
place correctly and then pull back by a distance of 12mm to allow for expansion.
5. At the head of each drain branch, ensure that the floor drain or drain point is level with the
marker port reference and that the fitting is square.
6. On completion of each drain section, check and adjust if necessary to ensure that the pipe
is in line with the marker string and all inverts are correct.
1. Select the spirit level that will rest against the drainage pipe you are measuring without
contacting fittings or other obstacles. The level must rest only on the pipe.
2. Set the spirit level on the top of the pipe or hold it against the bottom. Note the position of
the spirit level’s bubble, it should not be centered. Lift the end of the spirit level until the
bubble is centered.
Page 8 of 14
Reference
SPOTS
ELECTROMECHANICAL INSTALLATION OF RAFT PIPING - Date Rev.
WORKS L.L.C
DRAINAGE SYSTEM 29-12-2023 02
3. Measured the distance between the end of the spirit level and the pipe. The distance is the
slope of the pipe along the length of the spirit level. The standard slope for most soil and
waste pipe is 1 percent downward in direction of flow.
4. Verify the slope is in the correct direction. The pipe must slope downward from the source
of the water or waste toward the main sewer or catch basin.
1. All materials used on the project shall be brand new and of high quality. Obtain approval of
all manufacturers from the Consultant and the Owner.
2. "New" is defined as newly manufactured, "state of the art," tested and proven item of
equipment. Items which have been held in stock for any extended period of time by either the
Manufacturer or the Supplier will be rejected.
5.6.1 IT PLAN:
5.6.2 CALIBRATION:
1. The Tools & Equipment Maintenance In-charge shall maintain the “Calibration Schedule”,
which shall record the dates of required calibration checks.
3. The Tools & Equipment Maintenance In-charge shall ensure that all items appearing in the
calibration schedule are checked, and if appropriate re-calibrated by the dates stipulated in
the schedule.
4. The Tools & Equipment Maintenance In-charge shall give adequate advance notice to sites
and individuals of the dates by which their items of equipment must be returned for
calibration checks.
5. The Tools & Equipment Maintenance In-charge may, at his discretion, either perform such
calibration checks as may be required himself or send the item of equipment to an external
agency for checking, in line with the policies of Purchase Department.
1. A physical dimension,
Page 9 of 14
Reference
SPOTS
ELECTROMECHANICAL INSTALLATION OF RAFT PIPING - Date Rev.
WORKS L.L.C
DRAINAGE SYSTEM 29-12-2023 02
Dimensions, properties, or conditions may vary within certain practical limits without
significantly affecting functioning of equipment or a process. Tolerances are specified to
allow reasonable leeway for imperfections and inherent variability without compromising
performance.
The Site Store In-charge shall clearly mark and label those items which are pending for
inspection/verification as “Hold for Inspection”.
The Site Store In-charge shall ensure that all items are stored in a suitable manner to prevent
deterioration and damage.
Items received from any source not suitable for intended use are held pending their disposal
or return to supplier, shall be marked and labeled "Rejected Items".
The Project Manager/In-charge shall be responsible for monitoring and inspecting the quality
of the installation throughout the course of the contract.
1. The QA/QC Engineer shall evidence the inspection of the works in progress by preparing for
each completed stage or deemed appropriate area, on the “Inspection Request”.
2. The “Inspection Request” shall define the stage of works or area completed and shall
further summarize the various installations inspected and found to be acceptable by the
company.
Page 10 of 14
Reference
SPOTS
ELECTROMECHANICAL INSTALLATION OF RAFT PIPING - Date Rev.
WORKS L.L.C
DRAINAGE SYSTEM 29-12-2023 02
in which our works are deemed to be completed and which may be released for following
trades.
4. The QA/QC Engineer shall ensure that the “Sanitary ware Handing Over Form” is prepared
for each area in which the installation of sanitary ware is completed and ready to be
handed over to the main contractor or client’s authorized representative.
5. The QA/QC Engineer shall obtain such signatures as may be contractually required from
the main contractor and/or client’s authorized representative on the “Sanitary ware
handing over Form”.
1. The QA/QC Engineer shall ensure that the applicable tests are conducted, at appropriate
stages, during the course of the project and the results are recorded on the following
forms:
a) Foul and Surface Water Drainage
b) Gravity Test Report
2. Test reports shall accompany, as appropriate, by explanatory notes in the form of check
lists, guidelines, method statements or technical procedures, to ensure the correct
method of conducting the test.
3. The above test reports shall reflect the name and signature of the person conducting the
test together with the unique reference number of the instrument used to perform the
test and shall be passed to the QA/QC Engineer for his approval signature confirming the
test results obtained.
4. The QA/QC Engineer shall obtain such approvals of tests so conducted as may be
contractually required from the main contractor and/or consultant’s engineer.
1. INSPECTION:
a) The QA/QC Engineer shall, at the time of completing the installation, inspect the
works so completed and produce a list of any defects (snag list) that he may
recognize as requiring rectification.
b) The QA/QC Engineer shall ensure that all such defects are rectified in a timely
manner.
c) The list of defects produced by the QA/QC Engineer shall constitute evidence of the
inspection of the completed installation.
Page 11 of 14
Reference
SPOTS
ELECTROMECHANICAL INSTALLATION OF RAFT PIPING - Date Rev.
WORKS L.L.C
DRAINAGE SYSTEM 29-12-2023 02
2. The QA/QC Engineer shall respond in a timely manner to any preliminary snag lists that
may be issued by the Client’s authorized representative prior to his final inspection of the
installed works.
4. The QA/QC Engineer shall ensure that all defects advised by the client’s authorized
representative, when conducting his final inspection of the installed works, are rectified in
a timely manner.
5. Unless specified by the contract agreement, the company shall obtain such local authority
approvals, as may be required, for the following:
a) Plumbing Services
b) Fire Fighting / Fire Alarm
c) Drainage
d) Water
6. The QA/QC Engineer shall ensure that all defects advised by the relevant local authority
when inspecting the installed works are rectified in a timely manner.
2. All personal protective equipment shall be used as appropriate according to the nature of
the job.
3. Housekeeping shall be of good standard and all cut pipes and debris shall be removed.
7.0 Responsibility.
The Project Manager is the overall responsible person for the process of implementation of
the works. The Project Engineer will be responsible for all construction activities at the site
and will directly supervise through erection supervisor/skilled foremen at the work site. The
Site Engineer will be responsible for arranging and controlling the inspection and testing
activities.
Furthermore, it is the responsibility of each individual employed in the project to take due
care to ensure their own personal safety and that of their work colleagues.
Page 12 of 14
Reference
SPOTS
ELECTROMECHANICAL INSTALLATION OF RAFT PIPING - Date Rev.
WORKS L.L.C
DRAINAGE SYSTEM 29-12-2023 02
1. To ensure that completed system are inspected, commissioned (in accordance with
relevant commissioning and completion plans) and operating in a safe manner in
accordance with the contract and manufacturers specified requirements (All relevant
documentation included) and then formally handed over to client or authorized
representative.
2. Protection of work till project handing over.
8.0.2 Procedure
Inspections & Defect Lists (Snag List)
(a) At the outset of the contract agree the basis on which the works will be inspected
(In accordance with ITPs and specification requirements).
(b) Carry out pre-commissioning checks.
(c) Non-compliances identified while carrying out site inspections, testing and/or
commissioning are recorded on the relevant inspection test reports.
(3) Commissioning
(a) Prepare and issue to the commissioning Engineer, before starting commissioning
work, a schedule of items to be checked; tested and/or commissioned, together with
the relevant drawings and documents. Use authorised and calibrated test instruments,
copies of the calibration certificates should be attached to the commissioning
documents as required.
(b) Issue an Inspection Test Request in advance of Commissioning to enable the Main
Contractor and/or the Consultant to witness the Commissioning.
(c) Use a Check sheet to record details of any installation/plant/equipment failures.
(a) Collate the results recorded while the commissioning done, include any specialist
supplier reports.
(b) Include commissioning documentation in the Operating & Maintenance Manuals
for handover to Client or his representative. Where it is not appropriate to include
them in the Manual forward the commissioning results later for inclusion with the
other records.
Page 13 of 14
Reference
SPOTS
ELECTROMECHANICAL INSTALLATION OF RAFT PIPING - Date Rev.
WORKS L.L.C
DRAINAGE SYSTEM 29-12-2023 02
(c) The person responsible for Commissioning will produce a commissioning Plan to be
issued and approved prior to commissioning commencing.
(d) Instruction & Demonstration
(e) Where required use the commissioning period to instruct the client or
representative, on the use and maintenance of services provided. This must
include information, instruction and training in the safe operation and
maintenance of the systems and equipment. Whilst the Supplier’s specialist.
(f) Commissioning engineer is doing his/her work, arrange for him/her to
demonstrate the operation and maintenance of the equipment to the client or his
representative.
(g) Arrange a handover meeting with the client to ensure that they are satisfied that
all defects are closed out and that the installation functions safely & correctly. At
this meeting, or as required by the specification; issue the appropriate number of
Operating & Maintenance Manuals and Record Drawings. The ‘Handover’ is
deemed to be the date from when the client has beneficial use of the installation,
unless there has been earlier partial hand-over/s.
(c) Asset Register will be produced which will record such data as:
Asset Type, TAG Code, System
Supplier Code, Manufacture Code, Model and Origin
Product Code, Quantity
Drawing, Photograph number Serial Number, Bar Code
Nominal Capacity, Date Commissioned
Life Span, Warranty
Location, O&M Manual Reference
Spares Register
***************************
Page 14 of 14
Page no. : 1 of 4
Date of Issue : 20/12/2023
Revision : 00
RISK ASSESSMENT Document ref : P166-NSE-TS-MS-MEP-
MECH-00001
Project :P-166
Installation of Under Ground PVC Pipes and RA No. P166-NSE-TS-MS-MEP-MECH-00001
ACTIVITY:
Fittings in Raft DATE 20/12/2023
PROPOSED (B+G+7
FLOORS+ROOF) HOTEL
LOCATION: Basement Raft PROJECT:
APARTMENT BULDING ON
PLOT NO. AFCH014
EQUIPMENT TO BE USED SUBSTANCES TO BE USED REVISION STATUS
1. Hand Saw REVISION NUMBER REVISED DATE
2. Measuring Tape
Rev. 00 20/12/2023
3. Chalk Line & Powder
4. Wire Cutter N/A
5. Glue
6. Lubricant
7. Spirit Level
POTENTIAL HAZARDS / CONDITIONS CONSIDERED (TICK BOX) PERSONS AT RISK (TICK BOX)
SAFE WORK PLACE PROPER BARRICADE AND WARNING SIGN IN THE AFFECTED AREA
H (HIGH-Potential to cause death or permanent injury) M (MEDIUM – Potential to cause loss time injury) L (LOW – An injury treatable with First Aid)
1. IMPROBABLE. 1. NEGLIGIBLE. 4 4 8 12 16 20
HIGH = 15 – 25
2. REMOTE. 2. MINOR. 3 3 6 9 12 15
3. PROBABLE 3. REPORTABLE. MEDIUM = 07 – 14
2 2 4 6 8 10
4. OCCASIONAL. 4. SERIOUS. LOW = 01 - 06 1 1 2 3 4 5
5. FREQUENT 5. CATASTROPHIC.
1 2 3 4 5
SEVERITY (S)
NOTE: 1. Risk assessment must be addressed to workers by work in charge before starting job.
2. Risk assessment is a continuous process hence to be reviewed depending on activity & risk involved
Page no. : 2 of 4
Date of Issue : 20/12/2023
Revision : 00
RISK ASSESSMENT Document ref : P166-NSE-TS-MS-
MEP-MECH-00001
Project :P-166
ACTIVITY: P166-NSE-TS-MS-MEP-MECH-00001
1. All the workers must have helmets, hand gloves and safety shoes.
2. The employees must be made aware of the requirements of this assessment.
3. Lift area to be demarcated to restrict access.
4. Ensure safe slinging and ringing practices.
Lifting Operation
5. Do not stand beneath the load. Foreman,
(Overloading and overturning
2 Broken limbs, Fatality 20 H 6. Lifting plan to be made prior to lifting operation. Engineer & 4
of equipment’s / materials, Fall
7. Coordinate with the main contractor for proper lifting operation. Safety Officer
of Load)
8. Only certified operator and bankman will do the operation.
9. Ensure all lifting equipment to be regularly monitored or checked by assigned
personnel.
1. Employees are made aware of the risks associated with manual handling and the
required kinetic lifting techniques during toolbox talks and awareness campaigns.
Musculoskeletal 2. A Toolbox Talk Training should be conducted before manual handling operation.
injuries from 3. All person should allow only to lift / carry the materials or equipment as per their
Workers &
3 Manual Handling torque/sudden 12 M capacity. 3
movement of hand 4. Lifting plan to be made prior to manual lifting operation.
Foreman
tools and lifting 5. Mechanization should be done to minimize exposure.
6. Use safe lifting practices, keep the weight as close to you as possible, involve extra
people for as needed.
7. Carry out housekeeping before the manual lifting.
1. Proper machine maintenance.
2. Implement an existing energy control program or develop a site-specific program that
addresses how employees will be protected from unexpected start-up and/or
Fire or explosion risk release of stored energy during servicing and maintaining machines and equipment.
& Fatality 3. Control procedures will include the following:
Vibration of machine a.) Shutoff machines and equipment using established procedures.
Foreman,
Unexpected Start-up of equipment during use b.) Ensure that each authorized employee places a lockout or tagout device on each
4 20 H Engineer & 4
electrical tools can affect fingers, energy isolating device.
arms and hand in c.) Relieve, disconnect, or restrain all potentially stored hazardous or residual energy. Safety Officer
long term to disability d.) Verify isolation using test procedures before beginning work.
cuts of body parts e.) Ensure that locks and tags are only removed by the authorized employee.
f.) Prior to returning machine or equipment to normal operation, replace and reactivate
all safeguards and remove all locks and tags.
ASSESSED BY
REV. No:02
(NAME): SPOTS ELECTROMECHANICAL WORKS L.L.C SIGNATURE:
APPROVED BY
REV. DATE:29/12/2023
(NAME): JOUZY CONSULTING ENGINEERS SIGNATURE: