A. SUB- STRUCTURE
1. EXCAVATION AND EARTH WORK
1.1 Clear site and remove top soil to an average depth of 20
cm from natural ground level M2 20.25 45.00 911.25
1.3 Pit Excavation to adepth of 120cm starting from
reduced ground level in normal soil M3 21.60 300.00 6,480.00
1.5 Pit Excavation to adepth of 120cm -220cm starting
from reduced ground level M3 18.00 600.00 10,800.00
1.5 Pit Excavation to adepth of 220cm -300cm starting
from reduced ground level M3 45.00 800 36,000.00
1.8 Back fill with good dry filling normal soil ,compact well
in layers not exceeding 20cm thickness . Material from
site M3 27.00 400.00 10,800.00
1.9 Cart away surplus excavated material and deposit at a
distance not less than 1 km from the site. M3 57.60 250.00 14,400.00
1.1 0 25 cm thick basaltic or equivalent stone hard core Well
rolled compacted and blinded with crushed stone. M2 10.00 350.00 3,500.00
Total carried to summary 82,891.25
2. MASONRY WORK
A. SUB- STRUCTURE
1. EXCAVATION AND EARTH WORK
1.1 Site clearing and removing of the top 20cm thick soil. m2
1.2 Bulk excavation in black cotton soil to an average depth of
50cm from NGL to reduced level . m3 447.50 45.00 -
1.3 Isolated footing excavation work to adepth of not exceeding
120cm from the natural ground level. m3
1.4 Isolated footing excavation in black cotton soil for