SATIP-W-016-01 Rev.4
SATIP-W-016-01 Rev.4
SATIP-W-016-01 Rev.4
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
1.0 DOCUMENT REVIEW SPECIAL PROCESS (WELDING) REQUIRES BEST QUALITY PRACTICE, CPI & EFFICIENT METHODS IN PROCEDURES. PROPOSE BEST METHODS.
Page 1 of 4
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Welding of Special Corrosion Resistant Matl's (Incl. Duplex SS) SATIP-W-016-01 31-Aug-11 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
Verify NDE Method Application and *Refer to the respective NDE SATIP
3.9 Evaluation, Documentation & See Remarks See Remarks W/RH* W/R* (SATIP-NDE-UT-01, LPT-01, MPT-01, RT-01, etc):
Reporting of Results* *Per NDE Special Process Control Procedure
Page 2 of 4
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Welding of Special Corrosion Resistant Matl's (Incl. Duplex SS) SATIP-W-016-01 31-Aug-11 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
GENERAL NOTES
NOTICE (SAEP-1160, Section 9.2): Use of Welding and NDT SAICS 9.2.1 One SAIC per day per activity is required for production welding on a daily or continual basis, e.g., fit-up, in-process, and final
inspection. Applicable weld numbers must be entered in the Remarks Box on the appropriate SAIC. 9.2.2 Special welding activities such as branch connections, tie-ins, sleeve installation, hot-tap welding,
and temperature tie-ins will require a separate IR per weld per activity in accordance with the applicable SATIP. 9.2.3 NDT subcontractors must complete NDT Checklists on a daily basis per above but not as an
IR with the exception of the start of NDT activities. START OF NEW WELDING ACTIVITIES IN NEW AREAS REQUIRES NOTIFICATION.
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels
1 of Saudi Aramco participation based upon the Contractor’s performance.
Page 3 of 4
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Welding of Special Corrosion Resistant Matl's (Incl. Duplex SS) SATIP-W-016-01 31-Aug-11 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
1.0
2 DOCUMENTQA/QC
Surveillance: REVIEW SPECIAL
organization to PROCESS (WELDING)
monitor work in progressREQUIRES BEST
without notice QUALITY
from PRACTICE,
Construction CPI & EFFICIENT METHODS IN PROCEDURES. PROPOSE BEST METHODS.
Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative
3 is not present.
4 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection
Page 4 of 4