Mine Layout
Mine Layout
Mine Layout
Mine Layout
1. Introduction
The classic procedure for designing a mine starts by determining the mining method(s) and
probable optimum mining rate (discussed in other chapters). This chapter is principally devoted
to the next step – determining initial mine layout or “conceptual mine design.” The procedure is
also considered initial mine planning.
If the mining method is open pit, the layout starts with the basic design of the open pit itself.
This includes pit layouts in intervals up to the final design (ultimate pit). With the pit established,
the infrastructure is planned, including surface haul roads, stockpiles, dumps, tailings
impoundment, utility corridors, and surface plant layout. The mine layout for an open pit mine
might have to be modified if underground mining is contemplated when the pit is exhausted.
If the plan includes underground mining, planning starts with locating and sizing pre-production
and on-going development requirements. The initial planning includes determining level
intervals, haulage ways, primary access (shaft, ramp or adit), and other major entries. The
design of major entries requires considering the requirements for ore handling, waste rock
handling, primary ventilation circuit, backfill, transfer, materials handling, access for personnel,
refuge stations, and escape route(s). Once the underground mine concept is established, the
surface infrastructure is designed, including access roads, dumps, tailings impoundment, utility
corridors, maintenance facilities, explosives storage, and surface plant layout.
While the procedures outlined above may appear to be sequential, they are actually iterative to
the extent that the process can become tedious. The practical solution for this dilemma is to
conduct the exercise employing short-cut methods based on the following activities.
• Comparisons
• Intuitive reasoning
• Rules of thumb
• Tricks of the trade
Comparisons
Comparisons refer to the study of comparable well-engineered projects. In some cases, the
layout of another mine may be accepted as a starting model.
Intuitive Reasoning
Intuitive reasoning by the team participants is knowledge-based and relies on rational
perception, first-hand mining experience, and good judgment.
Rules of Thumb
Rules of thumb may be applied to break circular references by providing benchmarks and
starting points. Rules are also useful in identifying significant planning problems at an early
stage.
2. Rules of Thumb
Pit Layout
• The overall slope (including berms, access roads, and haul roads) of large open pits in good
ground will eventually approach the natural angle of repose of broken wall rock (i.e. 38
degrees), except for the last few cuts, which may be steeper. Source: Jack de la Vergne
• When hard laterites are mined in an open pit, safe pit slopes may be steeper than calculated
by conventional practice (as steep as 50 degrees between haul roads). Source: Companhia
Vale do Rio Doce
• For haul roads in general, 10% is the maximum safe sustained grade. For particular
conditions found at larger operations, the grade has often been determined at 8%. It is usually
safe to exceed the maximum sustained grade over a short distance. Source: USBM
• The maximum safe grade over a short distance is generally accepted to be 15%. It may be
12% at larger operations. Source: Kaufman and Ault
• The maximum safe operating speed on a downhill grade is decreased by 2 km/h for each 1%
increase in gradient. Source: Jack de la Vergne
• Each lane of travel should be wide enough to provide clearance left and right of the widest
haul truck in use equal to half the width of the vehicle. For single lane traffic (one-way), the
travel portion of the haul road is twice the width of the design vehicle. For double lane (twoway),
the width of roadway required is 3½ times the width of the widest vehicle. Source: Association
of American State Highway Officials (AASHO)
• A crushed rock safety berm on a haulage road should be at least as high as the rolling radius
of the vehicle tire. A boulder-faced berm should be of height approximately equal to the height
of the tire of the haulage vehicle. Source: Kaufman and Ault
Crown Pillar
• A crown pillar of ore beneath the open pit is usually left in place while underground mining
proceeds. The height of the crown pillar in good ground is typically made equal to the maximum
width of stopes to be mined immediately beneath. When the overburden is too deep, the ore
body is not mined by open pit, but a crown pillar is left in place of height the same as if it were.
If the outcrop of the ore body is badly weathered (“oxidized”) or the ore body is cut by major
faults, under a body of water or a muskeg swamp - the height of the crown pillar is increased to
account for the increased risk. Source: Ron Haflidson and others
Mine Entries
• Small sized deposits may be most economically served by ramp and truck haulage to a
vertical depth of as much as 500m (1,600 feet). Source: Ernie Yuskiw
• A medium-sized deposit, say 4 million (short) tons, may be most economically served by ramp
and truck haulage to a vertical depth of 250m (800 feet). Source: Ernie Yuskiw
• In good ground, at production rates less than one million tons per year, truck haulage on a
decline (ramp) is a viable alternative to shaft hoisting to depths of at least 300m. Source: G.G.
Northcote
• Shallow ore bodies mined at over 5,000 tpd are more economically served by belt conveyor
transport in a decline entry than haul trucks in a ramp entry. Source: Al Fernie
• As a rule, a belt conveyor operation is more economical than rail or truck transport when the
conveying distance exceeds one kilometer (3,281 feet). Source: Heinz Altoff
Shafts
• The normal location of the production shaft is near the center of gravity of the shape (in plan
view) of the ore body, but offset by 200 feet or more. Source: Alan O’Hara
• The first lift for a near vertical ore body should be approximately 2,000 feet. If the ore body
outcrops, the shaft will then be approximately 2,500 feet deep to allow for gravity feed and
crown pillar. If the outcrop has been or is planned to be open cut, the measurement should be
made from the top of the crown pillar. If the ore body does not outcrop, the measurement is
taken from its apex. Source: Ron Haflidson
• The depth of shaft should allow access to 1,800 days mining of ore reserves. Source: Alan
O’Hara
• For a deep ore body, the production and ventilation shafts are sunk simultaneously and
positioned within 100m or so of each other. Source: D.F.H. Graves
Underground Layout
• Footwall drifts for blasthole mining should be offset from the ore by at least 15m (50 feet) in
good ground. Deeper in the mine, the offset should be increased to 23m (75 feet) and for
mining at great depth it should be not less than 30m (100 feet). Source: Jack de la Vergne
• Ore passes should be spaced at intervals not exceeding 500 feet (and waste passes not more
than 750 feet) along the footwall drift, when using LHD extraction. Source: Jack de la Vergne
• The maximum economical tramming distance for a 5 cubic yard capacity LHD is 500 feet, for
an 8 cubic yard LHD it is 800 feet. Source: Len Kitchener
• The amount of pre-production stope development required to bring a mine into production is
equal to that required for 125 days of mining. Source: Alan O’Hara
Another advantage to the ramp or adit entry is direct access by mobile equipment when
trackless mining is to be employed. For a typical shaft, the equipment must be dismantled and
reassembled underground. The set-up time required to initiate ramp driving is usually shorter
than for a shaft. One to three months may be required to provide access and collar a ramp
portal, while the collar, hoist, and headframe required for a shaft may take six months of site
work.
For medium sized ore bodies, ramp haulage may still be the best choice where the ore body is
relatively flat lying. In this case, the ramp may have to be enlarged to accommodate larger
trucks. In some cases, it may be practical to provide twin ramp entries to handle two-way traffic.
Belt Conveyor
For large flat-lying ore bodies, a belt conveyor is typically the most economical method of
hoisting ore. The legs of the conveyor are put into a ramp that has been driven straight (i.e. a
“decline”) for each leg of the proposed conveyor way. If the soil overburden is very deep, or
deep and water bearing, a ramp or decline may not be a practical method due to the
extraordinary cost of excavating and constructing a portal. If the ground (rock) beneath the
overburden is not competent or is heavily water bearing, a ramp or decline access may be
impractical due to the driving time and cost.
Shaft System
For large steeply dipping ore bodies, a shaft system is usually best. In this scenario, it may be
advisable to have a ramp entry as well to accelerate the pre-production schedule and later to
provide service access to the mine.
The following flow chart (Figure 4-1) summarizes rules of thumb for bringing ore to surface from
an underground mine. The flow chart is only a guideline. For example, one underground mine
employed truck haulage (for a very small rich ore body) to a vertical depth of 700m before the
operation was abandoned.
Figure 4-1 Moving Ore to Surface
Main Entry
The foregoing strategy determines a main entry to the underground on the basis of ore
transport. In many cases, this entry also serves for personnel and materials transfer, particularly
at small operations. Consideration should be given to a separate entry for man and materials
handling when it can be afforded. For example, some mines use the production shaft for
ore/waste hoisting, main exhaust, and alternate escape while a second shaft provides cage
service in the main fresh air entry.
gambrenk at 12:10 PM
Share
‹ Home ›
View web version
About Me
gambrenk
View my complete profile
Powered by Blogger.