1.7 Bus Bar System & Single Line Diagram
1.7 Bus Bar System & Single Line Diagram
1.7 Bus Bar System & Single Line Diagram
• The electrical elements are represented by graphical symbols and their main
electrical characteristics are shown on the drawing.
• IEC Standard 60617 suggests graphical symbols to use for the elaboration of a
single line diagram.
• IEEE std C37.2 is also used for the device function number and contact
designation for metering and protection diagrams.
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
Busbar Systems in Substations
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
a) Single Bus
Single busbar system is simplest
switching scheme
• Lowest cost;
• Small land area;
• Easily expandable;
• Simple in concept and operation and
for the application of protective
relaying.
Disadvantage
• Arrangement having a low reliability;
• Loss of entire substation caused by a
bus fault;
• Involve fairly extensive outages for
busbar and busbar disconnector
maintenance.
Single busbar system is very little used
in the main HV grid, however common in
rural distribution systems.
Figure 1 Typical single Bus arrangement is shown
in Fig.1.
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
b) Single Bus with Transfer Bus
• Reasonable in cost
• Fairly small land area
• Easily expandable
Disadvantage
• Additional circuit breaker
needed for bus tie;
• Protection and relaying becoming
complicated;
• Main Bus fault causes loss of
the entire substation.
• the substation operation cannot
be sectionalized.
This bus arrangement has been
extensively used in 132 kV
Substations.
Figure 2 Typical Single Bus with Transfer
Bus arrangement is shown in Fig.2.
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
c) Double Bus Double Busbar System
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
e) Double Bus Double Breaker
Disadvantage
High cost – 2 breakers per
circuit
Figure 5
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
f) Ring bus
• Flexible operation;
• High reliability;
• Double feed to each circuit;
• No main bus;
• Isolation of bus section and
circuit breakers for maintenance
without circuit disruption.
Disadvantage
• During fault, splitting of ring
may leave undesirable circuit
combination;
• Limited number of circuit
positions and limited extension
possibilities .
Figure 6
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
Breaker and Half System
g) Breaker-and-a-Half In this scheme, three circuit breakers
are used for controlling two circuits
which are connected between two bus
bars. Normally, both the bus bars are
in service.
•Flexible operation and high
reliability;
•Isolation of either bus without
service disruption;
•Isolation of any breaker for
maintenance without service
disruption;
•Double feed to each circuit;
•Bus fault does not interrupt service
to any circuits;
•More complicated relaying;
This scheme has been used in the 400
kV substations.
Suitable for substations handling
Figure 7 large amount of power.
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
Following table contains unavailability and relative cost
and reliability values of the busbar systems as well as
summarized the flexibility (load re-arrangements) and
extension possibilities of the systems:
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
Service continuity
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
Service continuity
Category 1
No outage necessary within the substation for either
maintenance or fault
Category 2
Short outage (4 hours) necessary to transfer the load to
an alternative circuit for maintenance or fault
Category 3
Loss of circuit or section until the repair is completed
Category 4
Loss of substation
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
Analysis of service continuity
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
• SUBSTATION TYPES
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
Technology: AC and DC
AC Substations
Distribution
• Step-down HV to MV
Transmission
• Step-up MV to HV/EHV ( generating station )
• Step-down EHV to HV, EHV to MV
• Switching, HV, EHV
• Interconnection, generally HV or EHV
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
DC Substations
Converters stations
Transmission of energy from one station to the other
Rectifiers
Inverters
Network Interconnection
Back-to-back
DC line link
Submarine Cable Transmission
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
AC Substations
AIS = AIR INSULATED SUBSTATION
-INDOOR
-OUTDOOR BOX TYPE
-OUTDOOR OPEN STRUCTURE
-OUTDOOR LOW PROFILE
-METAL ENCLOSED INDOOR/OUTDOOR
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023
Prefabricated MV Substation
Substation Erection, Construction, Operation Maintenance & Testing and Commissioning Training © CHMC, 2023