Biil of Quantity (Boq)
Biil of Quantity (Boq)
Biil of Quantity (Boq)
Rate/Unit in Amount in
Sl. No. Description Qty Unit
Rs. Rs.
1 Dismantling of 60 feet lattices mast/communication 02 Nos. 21600.00 43200.00
Tower
2 Erection/ Installation of 60 feet lattices mast/ 02 Nos. 21600.00 43200.00
communication tower
3 Supply of 01 Block tower (10 feet) with 50 mm GI 02 Nos. 15000.00 30000.00
pipe Including flinch in both side, painting etc
complete
4 Supply of 01 Block tower (04 feet) with 50 mm GI 02 Nos. 6000.00 12000.00
pipe Including flinch in both side, painting etc
complete
5 Foundation for lattices mast / Communication 3.20 Cum 5320.00 17024.00
tower providing and laying in position reinforced
cement concrete 1:2:4 ( 1 cement: 2 coarse sand: 4
stone aggregate 20mm nominal size) in foundation
of pump, Dg set etc. including form work etc as
required (excluding reinforcement)
6 Transportation charge of lattices mast/ 02 Nos. 2200.00 4400.00
communication Tower
7 Installation, commissioning and configure of 02 job 10000.00 20000.00
wireless radiolink and IP camera
TOTAL ESTIMATED COST IN Rs. 169824.00
Note: Bidders are requested to quote their rate in figure & words both.
G.M./Staff Officer(E&M)
Magadh-Amrapali Area
I AGREE TO EXECUTE THE WORK at …………..%(in words …………….%) ABOVE / BELOW THE
ESTIMATED COST.
SIGNATURE OF BIDDER