1.0 PURPOSE
The purpose the production process which affect quality and ensure that these
processes are carried out under controlled conditions.
2.0 SCOPE
3.0 RESPONSIBILITY
4.0 PROCEDURE
4.1.1 The production processes that affect quality will be identified as simple
process/vital process/special process, based on its impact on final product.
4.1.3 Vital process is defined as a process which is complex and need extra care in
tool setting are whose outputs directly affect the final product quality.
4.1.4 Special process is defined as a process whose result could not be fully verified
by subsequent inspection and processing deficiencies may be apparent only
after the completion of the process.
Date : Date :
Quality System Procedure Doc. No.: SAPL-III /QSP/0704
SAPL-III Revision No. 01
Process Control Date 23.09.2015
Page No 2 to 4
4.1.5 Process flow diagram, Process control charts and/or Process control plans will
be prepared which includes type of process, machineries and equipments
required, process control parameters, product characteristics and specifications,
method of inspection, inspection frequency, sample size, records, responsibility
and reaction plan for out of control situations.
4.1.8 Control Plans are developed at the component level for Pre-Launch and
Production taking Manufacturing Process FMEA outputs.
4.1.9 Control Plans are reviewed and updated, when any change occurs that could
affect product, manufacturing process, measurement, logistics, supply sources
or FMEA.
4.2.1 Monthly production schedule will be prepared by AGM, based on, the
customer schedule, stock in transit and stock in plant and the same will be
notified to stores, purchase and production department.
4.2.2 Apart From Above All Daily Production Plan Will be Prepared Based on Customers
Requirements for the Day
4.2.3. Material Planning sheet will be prepared by Stores Supervisor as per the
monthly production schedule and stock in stores, for facilitating the necessary
purchase activities.
4.2.4 Daily Production & Delivery Will be Reviewed in the Daily Meeting & Counter
measures Will be Taken as up to Meet Customer Volumes
4.3.1 To carry out process in controlled conditions, process drawings and/or work
standards instructions will be displayed near the workstations. QSP for work
standards addressed for preparation of work standards .Wherever required,
Reviewed by: Approved by :
Date : Date :
Quality System Procedure Doc. No.: SAPL-III /QSP/0704
SAPL-III Revision No. 01
Process Control Date 23.09.2015
Page No 3 to 4
4.3.3 All production machines, dies and equipments will be properly maintained in
accordance with procedure No.SAPL-III/QSP/0705 & SAPL-III/QSP/0709.
(Maintenance Procedures)
4.3.5 Process studies on all new manufacturing processes to verify process capability
The results of process studies are recorded along with specifications, which
include:
4.4.1 Special processes will be qualified prior to accepting the process for regular
production and such records will be maintained. All special processes will be
carried by qualified PERSONNEL.
4.4.2 Process will be monitored as per the relevant Process Control Plans and/or
Process Control Charts and the operating parameters will be recorded in
"Quality Check Sheet for Special Process".
4.4.3 All the processes are validated once in a year. The records are maintained in
the "Process Validation Report"
Date : Date :
Quality System Procedure Doc. No.: SAPL-III /QSP/0704
SAPL-III Revision No. 01
Process Control Date 23.09.2015
Page No 4 to 4
4.5.1 The Entire Work Place will be Maintained Clearly Basic 5S Principles 1. Sort
2.Set in order 3.Shine 4. Standardize 5.Sustain will be Followed 5S
Improvement activities will be carried out .Ensure Employee Safety
Preservation of RM & Products maintain a neat and clean Environment and to
Identify ok & NG parts easily
4.5.2 Nursery Training Will be Provided to Employee .5S audit will be Conducted
by Every Month .5S activities will be audited as per the Check Sheet & Result
one Monitored in the Check sheet Itself
4.5.3 Minimum Grading Required is “B” How Ever efforts will be Made to Achieve
“A” Grade and Sustain
6.0 RECORDS
Date : Date :