Time Line Relocate RBC

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

AGUSTUS SEPTEMBER

MAN POWER /
NO WORK ITEM VOLUME SATUAN WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 5 WEEK 6 WEEK 7 WEEK 8 WEEK 9 REMAKS
STATUS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

I. CIVIL ACTIVITY
A1 CONCRETE WORK
1 Box Sludge 1.2 M3 COMPLETE
2 Precast Cover Intake Pond 10.27 M3 TASK FORCE
Control Box

A2 DISMANTLE & INSTALL PLUMBING


TASK FORCE /
1 Install Line Plumbing At Intake Pond 120 M' INPROGRES 70%

2 Install Line Plumbing From outlet Intake 55 M' TASK FORCE /


pond to Concrete Slab RBC COMPLETE

Dismantle Plumbing System At Existing


3 RBC (Rotating Biological Contractor) 30 M' TASK FORCE

Tie In Line Black Water From Contractor TASK FORCE /


INPROGRESS
4 Camp Block F, A & B, Messhall, Mushola & 30 M' COMPLETE MANUAL
Drilling Camp to New Intake pond DIGGING

Reintsall Plumbing System At Existing RBC


5 30 M' TASK FORCE
After Relocate

A3 FABRIACTE, DISMANTLE & INSTALL STEEL


STRUCTURE
1 Fabricate & Install For Roof Box Sludge 133.26 KG TASK FORCE

Fabricate & install Screen At Intake Pond


2 No.1 (Inlet Black Water From Contractor 191.27 KG TASK FORCE
Camp Block F, A & B, Messhall, Mushola &
Drilling Camp )
Fabricate & Install Pipe Support for Line FUNCTION TEST
3 36.62 KG TASK FORCE
Plumbing From Intake Pond To RBC
4 Dismantle Roofing Eksisting RBC 172 KG TASK FORCE
5 Dismantle Disk Bank RBC 300 KG TASK FORCE

Dismantel Handrail & Gratting Platform


6 506.76 KG TASK FORCE
RBC

7 Dismantle Cantilever Platform Around RBC 266.74 KG TASK FORCE

8 Dismantle Stair RBC 169.32 KG TASK FORCE


9 Reinstall Roofing Eksisting RBC 172 KG TASK FORCE
10 Reinstall Disk Bank RBC 300 KG TASK FORCE

11 Reinstall Handrail & Gratting Platform RBC 506.76 KG TASK FORCE

12 Reinstall Cantilever Platform Around RBC 266.74 KG TASK FORCE


13 Reinstall Stair RBC 169.32 KG TASK FORCE

II. LIFTING & VACUM TRUCK


1 Dewatering RBC 57 M3 VACUM TRUCK

Support Activity Civil For Dismantle Facility


2 At RBC 1 TRIP CRANE & TMC
NEED SUPPORT :
1. LIFTING PLAN & PTW
Support Loading & Unloading RBC From
3 Drilling Camp To Block F Contractor Camp 1 TRIP CRANE & TMC 2. QC CONTROL FOR LIFTING LUG
3. SUPPORT HDE FOR ACCESS & COMPACTING AREA FOR CRANE
4 Setup RBC At Concrete Slab RBC 1 TRIP CRANE & TMC

Support Activity Civil For Reinstall Facility


5 At RBC 1 TRIP CRANE

III. WATER TANK TRUCK


1 Commisioning test pipe 57 M3 VACUM TRUCK

III. MATERIAL BY NMK


1 PVC Pipe 4 Inch 40 EA ONSITE 20 EA
2 PVC Elbow, Tee & Shock 4 inch 51 EA ONSITE 40 EA

NOT YET / WAITING


3 Dry Mix 520 SAK COST PROPOSAL

4 Brick Stone 370 EA COMPLETE


5 Cement PC @ 50 KG 10 ZAK COMPLETE
6 Wood Kaso 5/5 & 5/7 0.35 M3 COMPLETE
7 Playwood 25 SHEET COMPLETE
NOT YET/ USE
8 Steel Structure Angle 75x75 2 EA MATERIAL STOCK
MEDCO

Prepared by Checked by Checked & Review by


PT. Nira Murni Konstruksi PT. Nira Murni Konstruksi MedcoEnergi

Almirah R M Bagus P / M Razali Eko Gede S


SS Civil Engineer Planner SS Civil / Str. Inspector
MAN AUGUST SEPTEMBER
NO WORK ITEM VOLUME SATUAN POWER / WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 5 WEEK 1 WEEK 2 WEEK 3
STATUS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

I. CIVIL ACTIVITY
A1 CONCRETE WORK
1 Box Sludge 1.2 M3 COMPLETE
2 Precast Cover Intake Pond 10.27 M3 TASK FORCE
3 Control Box for pump 1 M3 TASK FORCE

A2 DISMANTLE & INSTALL PLUMBING


Install Line Plumbing From outlet
1 Intake pond to Concrete Slab RBC 55 M' COMPLETE

TASK FORCE /
2 Install Line Plumbing At Intake Pond 120 M' INPROGRES
70%

Tie In Line Black Water From TASK FORCE /


Contractor Camp Block F, A & B, INPROGRESS
3 30 M' COMPLETE
Messhall, Mushola & Drilling Camp to MANUAL
New Intake pond DIGGING

Dismantle Plumbing System At Existing


4 RBC (Rotating Biological Contractor) 30 M' TASK FORCE

Reintsall Plumbing System At Existing


5 RBC After Relocate 30 M' TASK FORCE

Cut off line existing to septic tank

FABRICATE, DISMANTLE & INSTALL


A3 STEEL STRUCTURE

1 Fabricate & Install For Roof Box Sludge 133.26 KG COMPLETE

Fabricate & install Screen At Intake


Pond No.1 (Inlet Black Water From
2 Contractor Camp Block F, A & B, 191.27 KG COMPLETE

Messhall, Mushola & Drilling Camp )

Fabricate & Install Pipe Support for


3 Line Plumbing From Intake Pond To 36.62 KG COMPLETE
RBC
4 Dismantle Roofing Eksisting RBC 172 KG TASK FORCE
5 Dismantle Disk Bank RBC 300 KG TASK FORCE

Dismantel Handrail & Gratting Platform FUNCTION TEST


6 506.76 KG TASK FORCE
RBC
Dismantle Cantilever Platform Around
7 266.74 KG TASK FORCE
RBC
8 Dismantle Stair RBC 169.32 KG TASK FORCE
9 Reinstall Roofing Eksisting RBC 172 KG TASK FORCE
10 Reinstall Disk Bank RBC 300 KG TASK FORCE

Reinstall Handrail & Gratting Platform


11 506.76 KG TASK FORCE
RBC
Reinstall Cantilever Platform Around
12 RBC 266.74 KG TASK FORCE

13 Reinstall Stair RBC 169.32 KG TASK FORCE

II. LIFTING & VACUM TRUCK


1 Dewatering RBC 57 M3 VACUM TRUCK

Support Activity Civil For Dismantle


2 Facility At RBC 1 TRIP CRANE & TMC

Support Loading & Unloading RBC


3 From Drilling Camp To Block F 1 TRIP CRANE & TMC
Contractor Camp
4 Setup RBC At Concrete Slab RBC 1 TRIP CRANE & TMC

Support Activity Civil For Reinstall


5 1 TRIP CRANE
Facility At RBC

III. WATER TANK TRUCK


1 Commisioning test pipe 57 M3 VACUM TRUCK

IV. ELECTRIC
Dismantle equipment RBC existing

V. SCAFOLDING
Dismantle RBC existing

Prepared by Checked by Checked & Review by


PT. Nira Murni Konstruksi PT. Nira Murni Konstruksi MedcoEnergi

Almirah R M Bagus P / M Razali Eko Gede S


SS Civil Engineer Planner SS Civil / Str. Inspector