Vol. III (C)
Vol. III (C)
Vol. III (C)
THIS PAGE IS A RECORD OF ALL SPECIFICATION REVISIONS. NORMALLY, REVISED SHEETS ONLY ATTACHED
EACH TIME THE SPECIFICATION IS CHANGED ONLY THE NEW OR REVISED ENTIRE SPECIFICATION RE-ISSUED
PAGES ARE ISSUED. ENTIRE SPECIFICATION REVISED
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. TABLE OF CONTENT
CAIRO - EGYPT 000010 - 2874 0
CONTENTS
VOLUME I
GENERAL REQUIREMENTS
VOLUME II
DIVISION 0: INFORMATION
VOLUME III
Divisions 03 Concrete
Divisions 04 Masonry
Divisions 05 Metals
Divisions 08 Openings
Divisions 09 Finishes
Division 10 Specialties
101405 Signage
101453 Traffic Signage
102113 Toilet Compartments
102600 Wall And Door Protection
102800 Toilet and Bath Accessories
Divisions 11 Equipment
VOLUME III
210548 Vibration And Seismic Controls For Fire-Suppression Piping And Equipment
211000 Water-Based Fire-Suppression Systems
211339 Foam-Water Systems
212100 Carbon Dioxide Fire Extinguishing Systems
212200 Clean-Agent Fire Extinguishing Systems
213113 Electrical-Drive, Centrifugal Fire Pumps
213400 Pressure-Maintenance Pumps
Division 22 Plumbing
VOLUME III
Division 26 Electrical
Division 27 Communications
Division 31 Earthwork
Division 33 Utilities
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. CONMEN WORK RESULT FOR
CAIRO – EGYPT ELECTRICAL WORK 260500 - 2874 0
SECTION 260500
Page
PART 1 GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Submittals 4
1.4 Quality Assurance 7
1.5 Coordination 10
1.6 Delivery, Storage And Handling 10
1.7 Project Conditions 11
1.8 Warranty 12
PART 2 PRODUCTS 12
2.1 Manufacturers 12
2.2 Materials 12
2.3 Performance And Design Requirements 13
2.4 Accessories 14
2.5 Fabrication 14
2.6 Selection Of Equipment Supplier 14
PART 3 EXECUTION 14
3.1 Workmanship 14
3.2 Acceptable Installers 15
3.3 Preparation 15
3.4 Installation 15
3.5 Construction 17
3.6 Field Quality Control 17
3.7 Protection 17
PART 1 GENERAL
1.2 SUMMARY
A This section covers the furnishing of labor, materials and equipment under other
sections of this Contract; installation of all equipment, as may be furnished by the
Owner; and furnishing and installation of all additional equipment and materials
needed for the electrical requirements of this Contract.
C Work shall include furnishing all labor, materials, tools, equipment and services to
construct and install, test and commission the complete electrical system as
indicated on the drawings, specified herein and subject to the requirements of the
Conditions of Contract.
D For any deviations from the contract drawings pertaining to the ratings of electrical
equipment, due to the use of codes and standards of the country in which the
equipment is manufactured, it shall be the responsibility of the Contractor to verify
E Contract Provision: The Contractor will be required to make provision for the
following and his prices shall be deemed to include for any cost arising there from:
F The General and Special Provisions shall apply to all works under this Section.
I Alternate proposal shall only be permitted if equal to or better and only if with
considerable savings to the Owner than what is specified herein and when deemed
by the Owner as of absolute necessity. Contractor may proceed only upon
concurrence by the Engineer and upon approval of all redesign details, which may
have direct or indirect impact on other disciplines. No additional cost will be
provided for changes in the work.
J Redesign or altered drawings, reviewed by the Engineer, shall not relieve the
Contractor of any or all of his contractual obligations and responsibilities with the
Owner for proper and complete installation and operation of all materials and
equipment, including related accessories as required or detailed on the Contract.
1.3 SUBMITTALS
A Tendering Submittals: Contractor to fill-in the ECG compliance data sheet (when
attached to a section) and stamp it by the proposed supplier and by the proposed
electrical sub-contractor (or himself if no Sub-contractor).
B If the Contractor is assuming two suppliers for one material item in his bid, two data
sheets should then be filled and stamped, as mentioned, for the same item.
C Shop Drawings: Unless otherwise permitted by the Engineer all shop drawings shall
be prepared on A0 at least scale 1:50 sheet and drawn to a suitable metric scale for
plans and layout. Shop drawings shall be submitted for installations and layout of but
not limited to the following:
F Working Drawings and Data: The Contractor shall submit for approval number of
specified in general condition copies of prints of working drawing and detail drawings
of the entire installation.
G The working drawings shall be submitted early enough to get the approval as
specified in general conditions prior to any construction and not before getting the
approval of the Engineer for the equipment shown on the working drawings. This
should be coordinated to conform to the general program and schedules of work for
all trades.
O Samples of conduit, fittings, wires, cables, switches, lighting fixtures, track lights,
receptacles, telephone, outlets and instruments, speakers, pushbuttons, and any
other small items used in the job shall be submitted by the Contractor as specified
hereinabove, labeled and to be kept in a locked room under the control of the
Engineer. Samples shall not be used in the installation.
P Manuals: Complete operations and maintenance data for all equipment furnished
under Division 26, Electrical, shall be submitted in accordance with the requirements
set forth at the Conditions of Contract. The manuals shall be prepared specifically for
this installation and shall include all required catalog cuts, drawings, equipment lists,
descriptions, complete parts lists address of vendors of relevant equipment etc., that
are required to instruct operating and maintenance personnel unfamiliar with such
equipment.
Q Operation and Maintenance Manual: Submit at least four (4) copies of manuals as
required for systems and equipment indicated in the technical sections and shall be
in the English language. Furnish three copies, bound in hardback binders or an
approved equivalent. Furnish one complete manual prior to performance of systems
or equivalent tests, and furnish the remaining manuals prior to contract completion.
Inscribe the following identification on the cover the words: “OPERATION AND
MAINTENANCE MANUAL”, name and location of the system, equipment, building,
name of Contractor, and contract number. Include in the manual the names,
addresses, and telephone numbers of each sub-contractor installing the system or
equipment and the local representatives for the system or equipment.
R Include a table of contents and assemble the manual to conform to the table of
contents, with tab sheets placed before instructions covering the subject. The
instructions shall be legible and easily read, with large sheets of drawings folded in.
The manual shall include:
1. Internal and interconnecting wiring and control diagrams with data to explain
detailed operation and control of the system or equipment
2. A control sequence describing start-up, operation and shutdown
3. Description of the function of each principal item of equipment
4. Installation and maintenance instructions
5. Safety precautions.
6. Diagrams and illustrations.
7. Testing methods.
8. Performance data.
A Reference Standards
D BS (UK) CENELEC (EUR), VDE (Germany), and NEC (USA) shall be considered with
regards to all matters that are not covered by IEC recommendations and ISO
documents.
G The use of IEC recommendations and accepted European practice and philosophy is
governed by the fact that all major production and process equipment shall be
manufactured in Europe.
H The equipment for each classified area shall be certified for the applicable zone or
better.
1. PTB Germany
2. BASEFA England
K Safety and Health Regulations: The requirements of the Egypt Industrial Safety and
Health Regulations and subsequent amendments are considered part of these
Contract Documents and shall be enforced during the installation and operations of
the Works. All applicable Local and/or International Standards shall be deemed as
minimum requirements under the Industrial Safety and Health Regulations. Where
higher standards are required, they shall be complied with.
L The Contractor shall be responsible for ensuring that all items of electrical systems
comply with the requirements of these Governing Standards; that the manufacturers
comply with all the necessary instructions and that these instructions are included in
the operating and maintenance instructions when submitted.
M The Contractor shall be responsible for providing all electrical equipment with the
necessary, warnings signs and instructions. These shall cover maintenance, working,
operating and access or egress. All electrical equipment rooms shall have a notice
permanently secured to all doors stating "No Admittance to Unauthorized
Personnel". Where the noise level is in excess of 80 dBA, there shall be installed a
warning notice on all doors in accordance with the Governing Standards for reducing
the exposure of noise to operating personnel.
O Factory Tests and Inspection: The Owner reserves the right to witness factory testing
and inspection of any equipment furnished under these Division 26, Electrical
specifications. The Contractor shall furnish the Engineer with any sketches, test
setups, and instrumentation and shall notify the Engineer at least 20 days in advance
of the time each shop test will be made.
P Inspection of the Works: The Engineer shall perform inspections of the work as he
requires from time to time, and shall witness the tests performed by the Contractor
as specified in Quality Control paragraphs of this section. Any work not acceptable to
the Engineer shall be removed and redone at the Contractor's expense.
R The study shall include, but not be limited to, the following:
S The coordination study shall be bound in a standard paper size report. The study
shall be provided in accordance with the requirements set forth at the Conditions of
Contract. Final selection of all protective device settings or sizes shall be subject to
review and acceptance by the Engineer.
T Standardization: All materials and equipment supplied under this section of the
works shall wherever possible be standardized and of metric uniform design to
facilitate maintenance and operation and to limit storage of spare parts and tools.
All materials of the same kind of service shall be identical and made by the same
manufacturer.
U All components of the same size and rating used in the works shall wherever
practicable be interchangeable with one another. All circuit breakers, fuses,
contactors, relays, etc., shall be of the same make and design unless particular
location and duty make such standardization impracticable.
V Derating: All ratings given in the Contract Documents are standard ratings.
W For components and accessories for which no specific ratings or sizes are indicated,
the Contractor shall select rating and sizes that will be suitable for the site conditions.
Twenty percent (20%) shall be minimum derating factor for such items.
Y Spare Capacity: Spare capacity shall be provided to allow for future expansion and
future loads. Where required in the contract drawings, there shall be spares for
conduits, spare space for installing future equipment, and spare circuits at
panelboards and switchgears. If during the field-testing prior to handing over the
Works, the required spare capacity is not available, the Contractor shall replace or
add to any component or equipment to the system at no cost to the Owner.
1.5 COORDINATION
A The drawings indicate the extent and general location and arrangement of electrical
equipment, conduit and wiring, poles, manholes, trenches, etc. All works shall be
carefully laid out in advance, coordinating electrical features with architectural,
structural and mechanical features of construction. Any conflicts which occur
necessitating departures from the drawings shall be submitted in the form of details
of departures and reasons therefore as soon as practicable for written approval.
B Where any of the electrical work may interfere with the work of other trades, assist
in working out space conditions to make a satisfactory adjustment. If requested by
the Engineer, the Contractor shall prepare, scaled working drawings and sections,
which clearly show how the work is to be installed in relation to the work of other
trades.
C Supervision: The Contractor shall provide competent supervision on the site at all
times to layout, check, coordinate and supervise the installation of all electrical work.
Where required, vendor’s representative for the equipment to also supervise the
work at site where deemed required by the Engineer. The Contractor shall plan the
installation of all electrical work, giving consideration to the work of other trades.
A Delivery: The equipment furnished under this section shall be prepared for
shipment, delivered, stored, and handled.
B Deliver electrical materials and equipment in original cartons or containers with seals
intact as applicable. Unless otherwise specified, deliver conductors in sealed cartons
or on sealed reels, ends of reeled conductor’s factory sealed. Deliver large multi-
component assemblies in sections that facilitate field handling and installation.
C Handling: All exothermal welding materials and molds shall be stored and protected
against absorption of moisture. Welding charges, which show signs of moisture
absorption during storage or during installation, shall be discarded and replaced.
D All grounding, insulating and electrolyte materials shall be protected from degrading
by any cause and from loss by any cause.
E Handle materials and equipment in accordance with best industry practices and
manufacturer's recommendations. Lift large or heavy items only at the points
designed by the manufacturer. Use padded slings and hooks for lifting as necessary
to prevent damage.
F The contractor shall inform the Engineer by the receiving of equipment to inspect
before installation.
G Store materials and equipment on the ground and under cover. Prevent corrosion,
contamination or deterioration. Unless the equipment item is specifically designed
for outdoor exposure in a non-operating mode, all items shall be stored in a
protected area.
A Environmental Requirements: All equipment and materials shall be suitable for use
in an ambient temperature range from 5°C to 40C. Equipment and materials shall be
sized so that their ratings will not be exceeded nor their functional use degraded in
any way under these ambient conditions. Motor starters and other thermally-
sensitive equipment that is installed outdoors where exposed to sunlight shall be
provided with a sun screen or other provisions to avoid false tripping or damage due
to solar energy. Moreover, equipment shall be protected against corrosion, and
blowing sand and dirt.
B All services installed below grade on corrosive soil due to presence of moisture, salts,
acids and other substances that would cause corrosion, shall be protected with
acceptable treatment or encasement. Materials such as grounding cables, mats and
plates where meant to have electrical contact with earth shall be made of materials
resistant to corrosion while maintaining good electrical conductivity. Other means
such as grounding pits with provision for replaceable ground rods will be considered
where deemed necessary.
C All electrical equipment shall be rated for an ambient temperature of 45°C outside
and 40°C inside the building. The ground temperature at 75cm depth varies from
15°C in winter to 35°C in summer. It is the responsibility of the Contractor to take
into account the effects of any severe and arduous conditions in the design and
utilization of all electrical equipment.
E Where a conduit enters through a concrete floor, the curved portion shall not be
visible above the finished floor and the entire conduit below the floor slab shall be
encased in a concrete envelope having a wall thickness of not less than 76 mm. Ends
of the underground conduit shall be protected by suitable caps until connections are
made.
F Electric Utility Service: The service feeders shall be at 22kV-380/220 volts, 3-phase,
4-wire, 50 Hertz unless otherwise specified.
1.8 WARRANTY
PART 2 PRODUCTS
2.1 MANUFACTURERS
2.2 MATERIALS
A The materials used in all systems shall be new, unused and as herein specified. All
materials where not specified shall be of the very best of their respective kinds in
accordance with the industry standard to which they are made.
C Standard catalog items and IEC sizes, ratings, capacities, and voltages shall be given
preference.
D Prohibited Materials: Aluminum conduits, fittings, supports and conductors are not
acceptable unless specially approved for each use, or location, and Manufacturer
Standards.
G Equipment located in damp or wet locations shall meet exterior requirements. Refer
to environment conditions (Item 1.7 above).
I Ratings: The required output ratings of all electric equipment shall be referred to a
continuous duty at a coolant temperature of 40C, Class F, for insulation and Class B
for temperature rise unless particularly specified elsewhere.
K Common Requirements for Packaged Equipment: Where two or more units of the
same class of material or equipment are required, the Contractor shall provide
products of a single manufacturer.
M Deviations in quality or quantity that are not listed or inspected shall in no way
relieve the Contractor from responsibility.
B Design Criteria: The criteria for this project shall be taken as:
2.4 ACCESSORIES
B Danger Signs: Provide danger signs on all electrical panelboards, switchboard, main
distribution panelboard, and other live energized equipment.
C All nameplates, signs and other notices shall conform to the requirements of IEEE, or
IEC Standards and shall be engraved (of durable quality) in both Arabic and English.
2.5 FABRICATION
A Surface Preparation: Remove all casting projections, weld flux or splatter, by hand
scraping, hand impact tools, etc., follow by wire brushing or power grinding. Sharp
corners or sheared edges shall be dulled and radiused with power grinder to improve
paint adherence.
B Exposed grooved surfaces shall be finished smooth by filling and thoroughly cleaned
as required to provide a smooth uniform surface for painting.
C Shop Painting: Unless otherwise specified, all iron and steel surfaces, except copper
and stainless steel shall be shop primed with a vinyl primer and then given two or
more shop coats of vinyl base light gray enamel finish. The shop coating, including
primer, shall have a dry film thickness of at least 0.155 mm.
A The supplier of each equipment shall have a local representative or in the area
nearby. It shall be easy to get spare parts for all the equipment. The Owner’s
representative reserves the right to specify make and type to be supplied.
PART 3 EXECUTION
3.1 WORKMANSHIP
A Regulations for Electrical Installations: The Contractor shall plan methods of wiring
and installation of components into the Works in compliance with all regulations,
requirements and recommendations of the Governing Standards, and shall comply
with all local codes and ordinances. The Contractor shall be responsible for the full
compliance with the requirements of the applicable Standards and IEC 60364
"Electrical Installations in Buildings", throughout the installation of the Works
including any temporary works required.
B An installation or part thereof complying with the herein specified standards is one in
which:
C The Contractor shall ensure that his employees are familiar with requirements of the
herein specified Governing Standards and the requirements of the "Industrial Safety
and Health" Regulations.
3.3 PREPARATION
A Before installing any materials, the Contractor shall make certain that there are
accepted shop drawings available in his files for the material being installed. All
electrical equipment furnished in this and other sections of the specification shall be
connected according to the schematic diagrams indicated on the drawings or on the
accepted drawings furnished by the Manufacturer of the equipment.
3.4 INSTALLATION
A Setting of Equipment: All equipment shall be installed level and plumb. Sheet metal
junction boxes, equipment enclosures, sheet metal raceways, etc., mounted on
water-bearing or earth-bearing walls, shall be separated from the wall by corrosion-
resistant spacers not less than 6mm.
C Repair of Existing Works: The work shall be carefully laid out in advance and where
cutting, channeling, chasing, or drilling of floors, walls, partitions, ceilings or other
surfaces necessary for the proper installation of supports or/and anchorage for
electrical works. This work shall be carefully done and any damage to building, piping
or equipment shall be repaired by skilled personnel of the trade involved, at the
satisfaction of and at no additional cost to the Owner.
D Thermal Expansion: Conduits and raceways crossing expansion joints or areas subject
to difference in temperatures shall be provided with approved factory-made fittings
to compensate for mechanical stress on raceways.
E Use of Different Materials: All metallic frames, structures and raceways used for
electrical installations shall be made of the same materials. Where deemed as of
absolute necessity, only approved compatible transition joints shall be used while
maintaining the cross-section of the Conduit System.
F Ducts: All ducts and conduit system shall be of the same materials. Where deemed
of absolute necessity, only approved compatible transition joints shall be used while
maintaining the cross-section of the Conduit System.
G Wiring: Install wiring for control systems, power feeder and branch circuits, lighting
branch circuits, communication and auxiliary systems such as fire alarm and security,
in separate raceways unless otherwise indicated. Install power system wiring for
“Emergency”, “Life Safety”, ”Critical”, systems in separate raceways.
H Wet, Damp, or Dry Location Work: Provide products as appropriate for wet, damp,
or dry location as defined by IEC.
J Fire and Smoke Barrier Penetrations: Install fire stopping to raceways, boxes and
electrical equipment installed in or penetrating fire – rated or smoked barrier
assemblies, in a manner which maintains the fire resistance rating or barrier intent.
A Sleeves and Forms: The Contractor shall provide and place all sleeves for conduits
penetrating floors, walls, partitions, etc. Locate all necessary slots for electrical work
and form before concrete is poured.
B Where exact locations are required by equipment for stubbing-up and terminating
conduit concealed in floor slabs, the Contractor shall request shop drawings,
equipment location drawings, foundation drawings, and any other data required by
him to locate the concealed conduit before the floor slab is poured.
C Where such data is not available in time to avoid delay in scheduled floor slab pours,
the Engineer may elect to allow the installation of such conduit to be exposed. No
additional compensation for such change will be allowed.
D All openings, sleeves, penetration, and slots shall be sealed as specified herein.
A Field Service: All roughing in works for embedded items shall be subject to
inspection to the Engineer and cleared prior to concrete pouring, closing of
shuttering or closure of walls, ceiling and floors where electrical service shall be
concealed or embedded. The Engineer has the authority to stop any electrical work
found to be non-compliant with the project specification.
B Field Tests: In conjunction with the coordination study, the Contractor shall test and
calibrate all protective devices in accordance with the manufacturer's specification
prior to making the proper device setting before the initial energization of the
conductors and equipment. Field setting of adjustable protective devices shall be
indicated on electrical drawings that show the proper wiring of the protective devices
and the rating and wiring on non adjustable devices.
C The Contractor shall provide all test equipment and personnel and submit written
copies of all test results. As an exception to requirements that may be stated
elsewhere in the contract, the Engineer shall be given 15 working days notice prior to
each test.
3.7 PROTECTION
A Care of Equipment: During construction, all electrical equipment and cable insulation
shall be protected against absorption of moisture, and metallic components shall be
protected against corrosion by strip heaters, lamps, or other suitable means. This
protection shall be provided immediately upon receipt of the equipment and
maintained continuous until the equipment is put into operation.
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. MEDIUM VOLTAGE CABLES
CAIRO - EGYPT 260513 - 2874 0
SECTION 260513
Page
PART 1 GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Submittals 2
1.4 Quality Assurance 3
1.5 Design Criteria 4
1.6 Shipment 4
1.7 Delivery, Storage And Handling 5
PART 2 PRODUCTS 5
2.1 Manufacturers 5
2.2 Construction Of Cables 5
2.3 Identification Of The Cable Phases And Marking 7
2.4 Multiple-Conductor Unarmoured Cables 7
2.5 Multiple-Conductor, Armoured Cables 7
2.6 Cable Supports And Fittings 7
2.7 Splice Kits 8
2.8 Solid Terminations 8
2.9 Cable Cleats 8
PART 3 EXECUTION 9
3.1 Installation 9
3.2 Inspection And Testing 12
3.3 Guarantee Tables 12
3.4 Field Testing 15
PART 1 GENERAL
1.2 SUMMARY
A This section covers the furnishing medium voltage cables, including armored and
unarmored single and multiple conductor power cables.
1.3 SUBMITTALS
A Submit the following in accordance with the requirements set forth at the Conditions
of Contract.
B Tendering Submittals: Contractor to fill-in the ECG compliance data sheet (when
attached to a section) and stamp it by the proposed supplier and by the proposed
electrical sub-contractor (or himself if no sub-contractor).
C If the Contractor is assuming two suppliers for one material item in his bid, two data
sheets should then be filled and stamped, as mentioned, for the same item.
E Each sample shall show full data embossed on the sheath and shall be prepared for
easy investigation and measuring purposes.
H Reports: Test Reports for the following shall be in accordance with the paragraph
entitled, "Field Testing," of this section.
1. Conductor Resistance
2. Thickness of Armour
3. Ionization
4. High-Voltage
5. Flammability
6. Mechanical Integrity
7. Bending Test
8. High-Voltage Time Test
9. Dielectric Power Loss
10. Power-Factor Tests
11. Qualifications of Cable Splices
12. Dielectric Pothead Tests
A. Reference Standards
1. Governing Standards:
B. Installer’s Qualifications: The Contractor shall submit data showing that he has
successfully installed systems of the same type and design as specified herein, or
that the Contractor has a firm contractual agreement with a subcontractor having
not less than five years’ experience in the design and installation of such systems.
Data shall include names and location of at least two installations of such systems,
he or his referenced sub-contractors has installed. The references shall indicate type
and design of each system and certification that each system has been performed
satisfactorily in the manner intended for not less than three years.
B The cable shall be rated for 90°C continuous temperature, 130°C maximum
emergency temperature and 250°C short circuit temperature
1.6 SHIPMENT
A Cable shall be shipped on reels such that the cable will be protected from mechanical
injury. Each end of each length of cable shall be hermetically sealed and securely
attached to the reel.
B Minimum reel drum diameter shall be 14 times the overall diameter of the cable. A
pulling eye shall be installed by the manufacturer for each length of cable supplied
for installation in ducts, manholes, and utility trenches.
A Delivery: All cables shall be delivered to site with seals intact and bearing the
Manufacturer's label indicating classification, size, description, length and grade. All
labels shall be retained and kept in a logbook to be available for inspection by the
Owner’s Representative.
B Storage: Cables shall be stored at normal temperatures and out of direct sunlight.
Cables not on purpose-built cable reels shall be coiled neatly, allowing for any
limitations of bend radius and protected against mechanical damage. Cable ends
shall be sealed to prevent ingress of moisture.
C Care shall be taken to ensure that all cables are adequately protected while stored
on site prior to erection. No damaged cable shall be used.
D Handling: Whenever possible, cranes shall be used with suitable spindle through the
center of the reel. In the absence of hosting equipment, temporary ramp shall be
provided to move cable reels to and from storage area. Cable reels that have been
dropped will be subject to rejection by the Owner’s Representative, because of
flatting of the cable inner layers. Drums shall be rolled in the direction of indicating
arrows.
PART 2 PRODUCTS
2.1 MANUFACTURERS
A Medium voltage Cable 18/30 (36) kV Stranded compacted circular plain Aluminum
conductor, XLPE insulated in compliance with IEC 60502. The resistance of each
conductor shall be according to IEC 60228.
B Conductors: The cable shall have single conductor of plain aluminum Class 2, of
concentric strand wires. The conductor shall be of compacted circular shape.
F Copper Sheath: On each core insulation screening flat copper tape shall be applied
helically and overlapped comply with IEC 60502-2 standard. The number of copper
tapes and their percentage overlap for each core shall be selected in such a way to
obtain the specified effective cross section area of copper screen per phase.
1. The effective cross section area of copper screen per phase shall be not less
than the following:
G Filling and Inner Covering: The three cores shall be assembled together, the
interstice filled with non-hygroscopic; non–conductive material, which may be
extruded or not so, that the completed cable assembly is of substantial circular
cross-section.
H The inner covering wrapping the three cores together shall be of extruded corrosion
resistant material.
I The material is used for the filler and inner covering shall be suitable for the cable
operating temperature. The thickness of the inner covering shall be in accordance
with the attached table of dimensions.
J Metallic Armour: The metallic armor is of double tape type and shall be of steel. The
tapes shall be hot or cold rolled of commercial quality. The armor shall be applied
helically in two layers so that the outer type is approximately central over the gap of
the inner tape. The gap between adjacent turns of each tape shall not exceed 50% of
the tape width. Special consideration shall be given to the possibility of corrosion,
not only for mechanical safety, but also for electrical safety. It shall be applied on an
inner covering in accordance with IEC 60502 standard.
K The material and dimensions of the steel tapes shall be in accordance with IEC 60502
standard.
L The tape armour shall be helically applied in two layers so that the outer tape is
approximately central to cover the gap of the inner tape. The gap between adjacent
turns of each tape shall not exceed 50% of the width of the tape.
M Outer Jacket: The cable shall have an over sheath of extruded PVC st-2. The over
sheath shall be non-hygroscopic, sunlight resistant and suitable for soil conditions in
Egypt.
A Identification for phases shall be carried using colored plastic ribbon between the
semi-conducting layer and copper screen (RED, YELLOW, BLUE).
B The cable shall be marked throughout its length with the following items:
1. Voltage Rating
2. Size
3. Number of Conductors
4. Manufacturer’s Name
5. Cumulative Length
6. Year of Manufacture.
7. Compliance Standards
C Intervals of marking shall not exceed one meter and each mark shall serially indicate
the length of the cable remaining.
A Cable supports, related fittings, and accessories for use in corrosive underground
locations, such as manholes, shall be provided with a factory applied coating of
polyvinyl chloride of at least 0.51 millimeter thick. Polyvinyl chloride (PVC) coated
items shall have a uniform thickness and be free of blisters, breaks, and holidays.
PVC compound shall conform to IEC.
A Approved connectors shall be provided for splices and terminal connections of all
aluminum conductors. The connector shall fit the conductor to which it shall be
connected, and the assembly shall have joint contact surfaces not less than 50%. (As
recommended in writing by the splicing kit manufacturer for specific sizes, ratings
and configuration of cable conductor and splices specified). Include all components
required for complete splice with detail instruction. Comply with IEC Code.
A Termination for medium voltage cable shall be in the switchgear or cable entrance
Compartment of transformers. Type of termination fitting shall be as required to
match conductor to equipment, built–up insulation and heat shrink stress cone as
manufactured by Raychem (or approved equal) for the type of cable specified.
A Cable Cleats shall be design and tested as per IEC 61914 and used to securing the
cables when installed at intervals along the length of the cables
B Where trays are not required metal rack with one or more pairs of cleats shall be
used to suit the formation of the cables.
D Where single core cables in trefoil or quadrature formation are not secured in cleats,
binders of approved material and construction shall be fitted around the formation
to prevent the cables separating under fault conditions. The binders shall consist of a
nonferrous strap secured around the cables by means of a bolted connection. The
spacing of binders shall be approved by the Engineer. Single core and multicore
cables shall be clamped to the racks with smooth finish split packing pieces of non-
inflammable material or cleats with bores of the correct size for the cable diameters.
3.1 INSTALLATION
B Cable shall be installed in underground duct banks; in conduit above and below
grade; inside buildings; by open wire method; on insulator hooks; on racks; in wall
and ceiling mounted cable trays and manholes; and by direct burial.
D Cables shall be secured with PVC coated, metallic or non-metallic cable clamps,
straps, hangers, or other approved supporting devices, ceilings, and in cable trays
mounted vertically, where tray bottom is in a vertical plane. When field cuts or other
damage occurs to the PVC coating, a liquid PVC patch shall be applied to maintain
the integrity of the coating. After the installation is complete, an inspection shall be
performed to ensure the absence of voids, pinholes, or cuts.
E Contractor shall ensure that all cable trays are properly secured and supported prior
to installing new armored cable. Contractor shall add new permanent and/or
temporary tray support devices as required to preclude cable tray failure during
cable pulling or after cable is installed.
H Protection During Splicing Operations: Blowers shall be provided to force fresh air
into manholes or confined areas where free movement or circulation of air is
obstructed. Waterproof protective coverings shall be available on the work site to
provide protection against moisture while a splice is being made. Pumps shall be
used to keep manholes dry during splicing operations. Under no conditions shall a
splice or termination be made with the interior of a cable exposed to moisture. A
manhole ring at least 150 millimeters above ground shall be used around the
manhole entrance to keep surface water from entering the manhole. Unused ducts
shall be plugged and water seepage through ducts in use shall be stopped before the
splice is started.
I Duct Cleaning: Ducts shall be thoroughly cleaned before installation of power cables.
A standard flexible mandrel shall be pulled through each duct to loosen particles of
earth, sand, or foreign material in the line. Mandrel length shall be not less than 300
J Pulling Cables in Ducts and Manholes: Medium-voltage cables shall be pulled into
ducts with equipment designed for this purpose, including power-driven winch,
cable-feeding flexible tube guide, cable grips, and lubricants. A sufficient number of
trained personnel and equipment shall be employed to ensure the careful and
proper installation of the cable.
K Cable reel shall be set up at the side of the manhole and above the duct, allowing the
cable to enter through the opening without reverse bending. Flexible tube guide
shall be installed through the opening in a manner that will prevent the cable from
rubbing on the edges of any structural member.
L Cable shall be unreeled from the top of the reel. Payout shall be carefully controlled.
Cable to be pulled shall be attached through a swivel to the main pulling wire by
means of a pulling eye or suitable cable grip permitted only on cables less than 60
meter long and less than 50 millimeter in diameter.
M Woven-wire cable grips shall be used to grip the cable end when pulling small cables
and short straight lengths of heavier cables.
N Pulling eyes shall be attached to the cable conductors to prevent damage to the
cable structure.
O Pulling eyes and cable grips shall be used together for PVC sheathed cables to
prevent damage to the cable structure.
P
P Minimum bending radius shall be in accordance with NEC article 300.34 and IEEE
1185 as the following:
R Cables shall be pulled into ducts at a speed not to exceed 0.25 meter per second and
not in excess of maximum permissible pulling tension specified by the cable
manufacturer. Cable pulling using a vehicle shall not be permitted. Pulling operations
shall be stopped immediately with any indication of binding or obstruction and shall
not be resumed until such difficulty is corrected. Sufficient slack shall be provided
for free movement of cable due to expansion or contraction.
T Cables cut in the field shall have the cut ends immediately sealed to prevent
entrance of moisture. Unarmored cables shall be sealed with rubber tape wrapped
down to 75 millimeter from the cable end. Rubber tape shall be cover-wrapped with
polyvinyl chloride tape. Armored cables shall be sealed with wiping metal making a
firm bond with the end of the sheath or with a disk of lead fitted over the end and
wiped to the sheath.
U Direct Buried Installation: Cable direct buried, unless otherwise specified furnish a
bed of soft clean sand 100 mm depth at the bottom of trench, and the same over
cable. Install concrete tiles to the whole route of the cable with 50 mm thickness
and covering at least 200 mm over the outer edge of the cable from both sides.
V Then storing in backfilling with selected soil and reach to 95% compaction minimum.
Before reaching to the finished grade level by 300 mm, install warning tape, in both
English and Arabic, to cover the whole routes indicating “DANGER ELECTRICAL
CABLES”.
W In road crossing, install UPVC pipe embedded in concrete encasement and install
warning tape and install spare pipes not less than 25 % of the same size.
Z Use kits, which are compatible with conductor size, material and type and according
to the manufacturer’s recommendations.
AA Install terminations at ends of conductors and seal multi–conductor cable ends with
standard kits and glands.
A ENGINEER reserves its right to carry out inspection during fabrication stages and to
witness the testing of cables.
A The tenderer shall thoroughly fill in the attached guarantee tables (technical
particulars and performance) for guidance.
B The cable length on each reel shall be as long as possible to minimize the number of
joints and as shown in the attached tables.
C All cable ends shall be firmly secured to the reel and shall be covered by heat-
shrinkable end caps.
D The cable drum shall be covered with wooden slabs of suitable thickness.
E All cables shall be supplied on reels whose size is not to exceed 2.6 m diameter and
1.6 m width including protruded bolt length. The reels may be returnable as per
agreement between the tenderer and ENGINEER.
G Important Note
The factory laboratory must be equipped with all modern instruments and
equipment required to perform all routine and special tests of IEC 60502 with
the accuracies mentioned in IEC 60502
1. Offers from tenderers having no such laboratories shall not be considered
2. Dimensions shall be measured by digital and microscopic instruments.
18/30 kV XLPE
Item
3*240 mm
Minimum thickness of conductor screening 0.8 mm
Nominal thickness of XLPE insulation 8 mm
Minimum thickness of insulation screening 1 mm
Nominal thickness of Armor tapes 0.8 mm
Nominal thickness of extruded PVC over sheath 4.1mm
The cable length on each reel shall be not more than 800 meters
2. The thickness of insulation at any place, may however be less than the
specified nominal value provided that the difference does not exceed 0.1 mm
+ 10% of the specified nominal value.
3. The dimension of the armour shall not fall below the specified nominal value
by more than 10%.
4. The measured smallest thickness of the PVC over sheath, at any point shall not
fall below 80% of the specified nominal value by more than 0.2 mm.
5. Guarantee Table (Similar data fills on typical manufacturer data sheets shall be
also accepted.
a. Technical Particulars
Maker’s Name:
1) Thickness of tape
2) Width of the tape
3) Percentage overlap of tape
4) Number of tapes
5) Effective cross-sectional area of screen per phase
I Performance
a. Conductor: KA
a. Continuous: °C
b. Emergency: °C
c. Short Circuit: °C
K We certify that the above mentioned data are guaranteed for the offered cable.
B The power frequency routine test voltage shall be 3.5 U0 values of single phase test
voltage for the standard rated voltage according to IEC 60502 and as given in the
following table:
C The partial discharge test shall be carried out in accordance with IEC 60885-3, except
that the sensitivity as defined in IEC 60885-3 and shall be 10 Pico-coulombs (P.C) or
better. The partial discharge test voltage shall be raised gradually to and held at 2 U0
for 10 seconds and then slowly reduced to 1.5 U0.
G Each power cable shall first be given a full dielectric-absorption test. Test shall be
applied for a long enough time to fully charge the cable. Readings shall be recorded
H Upon successful completion of the dielectric absorption test, the cable shall be
subjected to a direct-current high-potential test for 5 minutes with test voltages
applied in accordance with IEC for cross-linked, polyethylene-insulated cable.
I Leakage current readings shall be recorded every 30 seconds during the first 2
minutes and every minute thereafter for the remainder of the test. When the
leakage current continues to increase after the first minute, the test shall be
immediately terminated and steps taken to find and correct the fault. When a
second test becomes necessary, this test procedure shall be repeated.
J Upon satisfactory completion of the high-potential test, the cable shall be given a
second dielectric-absorption test as before.
K Results of the second dielectric-absorption test shall agree with the first test and
shall indicate no evidence of permanent injury to the cable caused by the high-
potential test.
L Test data shall be recorded and shall include identification of cable and location,
mega ohm readings versus time, leakage current readings versus time, and cable
temperature versus time.
M Final acceptance shall depend upon the satisfactory performance of the cable under
test. No cable shall be energized until recorded test data have been accepted by the
Electrical Distribution Company and approved by the Engineer’s Representative.
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. LOW-VOLTAGE ELECTRICAL POWER
CAIRO - EGYPT CONDUCTORS AND CABLES 260519 – 2874 0
SECTION 260519
PART 1 GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Submittals 2
1.4 Quality Assurance 3
1.5 Delivery, Storage, And Handling 4
1.6 Coordination 5
PART 2 PRODUCTS 5
2.1 Manufacturers 5
2.2 Lv Wires And Cables 450/750 V Grade 5
2.3 Lv Cables 600/1000 (1200) V Grade 6
2.4 Control And Signal Cables 6
2.5 Connectors (Lv Power) 7
2.6 Performance And Design Requirements 8
PART 3 EXECUTION 11
3.1 Inspection 11
3.2 Preparation 11
3.3 Installation 13
PART 1 GENERAL
A. Drawings and general provisions of the Contract, including General and Supplemen-
tary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This section covers the furnishing and installation of all insulated wires and cables in-
cluding control / (for power) cables voltages 600 volts nominal or lower; except wire
and cable for special applications, such as low-level circuits for analog signals, data
and supervisory control, Communication and Telemetering Systems.
1.3 SUBMITTALS
A. Submit the following in accordance with the requirements set forth at the Conditions
of Contract.
a. Exact routing layouts, sections and profiles of trays, feeder, sub feeder
cables and branch circuits, with indication of any equipment to show
and verify coordination between various trades.
b. Details of supports and fixings for buses, trays and cables.
c. Details of connections to transformers, switchboards, panelboards etc.
Low-Voltage Electrical Power Conductors and Cables Section 260519
Urbanium New Administrative Building (Prj. 2874) Page 2 of 14
d. Details of terminations, splices and tapings where permitted, glands and
bushings at enclosures.
e. Number and size of conductors in conduit for all branch circuits in
accordance with final conduit routing.
f. Cable sizing calculations.
g. Cable schedule.
h. Cable termination schedule.
B. Standards: Wires and cables are to comply with IEC or other equally approved stand-
ards and are to bear the mark of identification of the Standards to which they are
manufactured. Wires and cables not having this identification will be rejected.
A. Deliver wires and cables properly packaged in factory packed or fabricated contain-
ers, wound on factory reels.
8. Store wires and cables in dry areas, and protect from weather, fumes, water, debris,
etc.
B. Handle wire and cable carefully to avoid abrading, puncturing and tearing wire and
cable insulation and sheathing. Ensure that dielectric resistance integrity of
wires/cables is maintained.
C. Before dispatch, the manufacturer shall cap the ends of all cables so as to form a seal
to prevent the ingress of water during transportation, storage and installation. The
cable shall be supplied on stout wooden drums, which shall be designed so as to pro-
tect the cable from damage.
D. The lagging batten shall be secured at least with 2 nails of each end in addition to
steel bonding straps. No drum shall contain more than 1 length of the cable.
E. The cable shall be tightly wrapped on the cable drum and no turn shall be left loose.
Both ends of the cable shall be adequately secured to the cable drum. Inner end of
the cable shall be suitably fixed / gripped to the cable drum so that it will not come
out during cable laying operation. The cable shall be wrapped on drums of suitable
diameter such that the radius of bend of the innermost layers is not less than the
minimum radius of bend stipulated in relevant BS/IEC for installation of the cable.
F. No space shall exist between the adjacent layers of the cable and between the drum
flange and the cable.
G. Cable shall be wrapped with black polyethylene sheet inside the wood covering of
the drum.
H. Central lifting hole of the cable drum shall be provided with a steel pipe. The pipe
shall be welded with steel plates at both ends and these plates shall be duly secured
to the flanges of the cable drum with suitable size bolts. The pipe and the welded
end plates shall be of robust design to withstand the weight of the cable drum during
unrolling.
I. Each drum shall bear a distinguishing number on the outside of the flanges and par-
ticulars of the cable, i.e. voltage, length, conductor size, cable type and gross weight
shall also be clearly visible. The direction for rolling shall be indicated by an arrow.
J. Immediately after the Works tests, both ends of every length of metal sheathed ca-
ble shall be sealed by means of a metal cap fitted over the end and plumbed to the
sheath. All cables shall be sealed by enclosing the ends in approved caps, which shall
be tight fitting and adequately secured to prevent ingress of moisture.
K. The ends of factory lengths of cable shall be marked "A" and "Z", "A" being the end at
which the sequence of core numbers is clockwise and "Z" the end at which the se-
quence is anti-clockwise. The words "Running End "A"" or "Running End "Z"" shall be
marked on the flange and the direction for rolling shall be indicated by an arrow. The
method of drum marking shall be to the Purchaser's approval.
M. Cable drums shall be non-returnable and shall be made of timber, pressure impreg-
nated against fungal and insect attack or made of steel suitably protected against
corrosion. They shall be arranged to take a round spindle and be lagged with strong
closely-fitting battens of minimum 38 mm thickness.
N. All cables and accessories shall be carefully packed for transport and storage on Site
in such a manner that they are fully protected against all climatic conditions, particu-
lar attention being paid to the possibility of deterioration during transport to the Site
by sea or overland and to the conditions prevailing on the Site.
O. Wooden drums shall be suitably constructed to avoid problems due to shrinkage, rot
and attack by insects.
P. Drums, carts, cases, etc., for maintenance spares shall be non-returnable. Cable
maintenance lengths and spare lengths shall be wound onto steel drums inspected
and tested by the Engineer before they are handed over to the Purchaser's stores.
Particulars of the cable (as stated above) shall be clearly marked.
1.6 COORDINATION
B. Revise locations and elevations from those indicated, as required to suit field condi-
tions and as approved by Engineer.
C. Ensure that cable twists, and crossings are avoided and sufficient bending radius is
maintained as per regulation.
PART 2 PRODUCTS
2.1 MANUFACTURERS
A Single Core PVC Insulated Cables and Wires 450/750 V grade: single conductor cables
for wiring in conduit are to have soft annealed copper stranded conductors unless
otherwise indicated in the drawings, insulated with flame retardant, moisture and
heat resistant PVC according to IEC 60227 or BS 6004, suitable for wet locations and
for conductor temperature of 70 deg. C.
B Single Core PVC Insulated Cables and wires with Flexible Copper Conductors 450/750
V grade: Soft annealed Copper fine wires, bunched together in subunits or stranded
bunched groups into a main unit, twisted and Sheathed which forms the flexible
Low-Voltage Electrical Power Conductors and Cables Section 260519
Urbanium New Administrative Building (Prj. 2874) Page 5 of 14
conductor. According to IEC 60227 or BS 6004. Shall be used where particular
flexibility is required for Electrical Panels connection and electrical apparatus they
can be laid in groups around steel sheets. Conductor temperature of 70 deg. C.
A Single Core PVC Insulated Cables (0.6/1 kV): Single-core circular stranded annealed,
copper conductors as indicated in the drawings, compacted, suitable filler and
sheathed with PVC according to IEC 60502, suitable for outdoor and indoor
installations in damp and wet locations. Conductor temperatures of 70 deg. C and
PVC over-sheath.
B Single Core XLPE Insulated Feeder Cables (0.6/1 kV): Single-core circular stranded,
annealed copper conductors as indicated in the drawings, compacted, insulated with
cross-linked polyethylene (XLPE), according to IEC 60502 or BS 7889 suitable for wet
locations and conductor temperatures of 90 deg. C.
C Multi-Core PVC Insulated Cables (0.6/1 kV): soft annealed, copper conductors as per
indicated in the drawings, compacted, suitable filler and sheathed with PVC
according to IEC 60502, flame retardant, moisture and heat resistant, suitable for
outdoor and indoor installations in damp and wet locations. Conductor temperatures
of 70 deg. C.
D Multi-Core XLPE Insulated Feeder Cables (0.6/1 kV): annealed copper conductors as
indicated in the drawings, compacted, XLPE insulated, for conductor temperature of
90 deg. C, laid up and bedded with suitable non-hygroscopic material compatible
with the insulation and PVC over-sheathed, color black according to IEC 60502 or BS
5467.
E Armored Multi-Core cables are to have single layer of steel wire or steel tape applied
helically over extruded PVC bedding (which may be an integral part of filling) and
over-sheathed with PVC, color black. PVC over-sheaths are to be type ST2 according
to IEC 60502. Armored cables shall be used where mechanical damages are expected.
G Fire Resistance cable (0.6/1 KV): Plain annealed copper conductors class 2 according
to IEC 60228, with primary insulation of fire resistant MICA tape and secondary
insulation of 90°C. cross-linked polyethylene insulation, extruded LSHF bedding
compound and galvanized steel wires and robust LSHF sheath. Cable is to be rated at
600/1000 V, certified from a third party lab to passed the fire resistance tests
according to BS 6387 and Flame retardant tests according to IEC 60332-1 and 60332-
3. with Category CWZ according to BS 6387. Category C subject to fire at 950°C for 3
hours, category W (Resistance to fire with water) subject to fire at 650°C for 15
minutes, then at 650°C with water spray for a further 15 minutes and category Z
(Resistance to fire with mechanical shock) subject to fire at 950°C with mechanical
shock for 15 minutes.
A Multi-Core XLPE Insulated Control Cables: 0.6/1 kV rating, solid 1.5 mm2, 2.5 mm2 or
stranded 4 mm2 plain circular copper conductors, with heat resistive PVC/A to IEC
60502-1, rated for 90 deg. C, of 7, 12, 19, 24, 30 or 37 cores. Cores are to be laid up
together and filled with non-hygroscopic material, and covered with copper wire or
tape screen and over sheathed with flame retardant PVC/ST1, to form compact and
circular cable for use in switchgear, control gear and generally for control of power
and lighting systems. Armored cable is to have extruded PVC bedding which may be
an integral part of the filling, galvanized steel wire armoring, and over-sheath of
flame retardant PVC/ST1 to IEC 60502-1 and IEC 60332-1, color black. Core
identification is to be white printed numbers 1, 2, 3 etc. over black insulation.
B Cables are to be certified to have passed IEC 60331 fire resistance and IEC 60332-1 &
3 flame retardant and reduced flame propagation to category CWZ of BS 6387.
C PE insulated control and signal cables, for use on data systems, are to be generally
300 V rating, polyethylene insulated, color-coded, tinned copper conductors (0.6-mm
diameter), twisted together into pairs. Multi-pair core assembly is to be covered with
binder tape, spirally wound 0.075-mm bare copper shielding tape and provided with
drain wire and overall PVC sheath.
D Control and signal cables, enclosed in conduit and raceways with power cables, are
to be insulated for same voltage grade.
E Multi core PVC insulated cables (300/500 V) annealed copper conductors, solid
conductors, up to 4 mm2 unless otherwise indicated, insulated with moisture and
heat resistant PVC/C to IEC 60227 and with over sheath of flame redundant PVC type
ST1 to IEC 60227 and IEC 60332-1.
A Connector - Type A-1: Pressure indent type, for terminating or making T-taps and
splices on conductors 10 mm2 and smaller. Connector is to be non-ferrous copper
alloy applied to conductor by mechanical crimping pressure, with vinyl insulating
sleeves or phenolic insulating covers.
B Connector - Type A-2: Bolted pressure split type for terminating or making T-taps and
splices on conductors 16 mm2 and larger. Connector is to be cast non-ferrous copper
alloy applied to conductor by clamping with minimum of two screws and provided
with phenolic insulating cover.
Low-Voltage Electrical Power Conductors and Cables Section 260519
Urbanium New Administrative Building (Prj. 2874) Page 7 of 14
C Connector - Type B-1: Pre-insulated, spring type, for branch circuit and fixture wiring.
Connector is to be steel encased spring with shell, insulated with vinyl cap and skirt,
type Scotchlok brand, as manufactured by Minnesota Mining & Mfg. Co. or 3M or
other equal and approved.
A Cable Design Criteria: All cables shall conform to the applicable provisions of the IEC
and local standard.
B Each type of cable used throughout the installation shall be supplied by one
manufacturer only.
C Cable Types: The following types of wiring systems shall be used for power circuits
and controls.
D The armour of single-core cables for use on a.c. systems shall consist of non-
magnetic material, unless a special construction is chosen.
E Cable Sizing and Selection: The applicable IEC or local regulations for Electrical
Installations shall be used as the basis for sizing cables and conductors.
F Minimum wire size shall be 4 mm2 for power circuits; 6 mm2 for current transformer
secondary circuits; 3 mm2 for potential transformer, digital signal, relaying, and
control circuits; 1.5 mm2 for annunciator circuits, analog signal and alarm circuits.
G Voltage drop on distribution cables for final branch circuit shall not exceed 5 percent.
H No cable shall be loaded to more than 80 percent of its current carrying capacity
after application of all the appropriate derating factors.
I The spacing of cables shall be as determined in the calculation of the derating factors
for the current carrying capacity of cables.
J When required, control cables shall be selected taking into account of the following:
K Cable sizes shall not be less than the minimum size specified herein. Minimum
cables sizes for circuits outgoing from main switchboards, distribution panel board,
and main distribution boards shall be in accordance with the schedule set forth in
Table No. 1, indicating the nominal cross section area of PVC type cables.
M Cables for motors above 2 kW, shall be sized to conform to the Governing Standards,
so that the current ratings are not less than 125 percent of the full load current of the
motor and that the cable is not smaller than
a. Voltage rating
b. Size
c. Number of conductors
d. Manufacturer’s name
O Cables in Conduits and Trunking: All cables for lighting, small power, control and
auxiliary services, including low and extra low voltage services, shall be multistranded
single core (except for metal conduits shall be multicore) PVC, butyl, or silicone
insulated as required for 450/750 Volt grade as set forth in IEC and local specification
having stranded copper conductors. The minimum cable size shall be 1.5 mm2.
Q Marker sleeves shall be fitted to each end of cables and at suitable distances along its
length. Sleeves and markers shall be of the proprietary type manufactured for the
particular applications, and they shall be of the correct size to ensure a tight fit on
the cable. Where cables changed direction, or are routed through conduits, cables
identification sleeves shall be fitted.
R Cables shall be contained within a protective enclosure of a size not less than that
complying with IEC or local standards throughout its whole length.
S Cables installed in conduits, trunking shall be so grouped that the cables of all
phases, neutral and earth, are drawn into the same conduit. The lead and return
conductors shall always be drawn into the same conduit. Not less than three single
core cables shall be enclosed in any one conduit or trunking compartment.
T The grouping of cables fed from different distribution units shall not be permitted.
Also the grouping of cables of different service systems shall not be permitted.
U Where cables are installed in trunking, they shall be grouped in their respective
circuits or services and taped or bound by means of nylon cable straps at one-meter
intervals for purpose of identification.
V Flexible Cables: The use and type of flexible cables or cords shall suit the applications.
W Cables shall be butyl, silicone, PVC or impregnated glass fiber insulated as required
for the particular application. The cables shall be suitably sized, with a rating not less
than the protective device of the particular circuit, unless exempted by the
Governing Standards and, shall not be less than 0.75 mm² with a voltage rating of
300/500 volts.
X Flexible cables and cores shall be used for pendant luminaires, adjustable lamps,
portable appliances and certain items of special equipment such as air conditioning
terminal units.
Y The cables shall have the correct number of cores necessary for the particular
application and a strain cord shall be included where necessary to obviate any excess
weight being carried on the conductors. The grounding conductors shall be of
sufficient length to ensure that undue stress is not placed upon it.
Z No flexible cable, other than that enclosed in conduits, shall be in excess of two
meters in length.
AA Heat Resistant Cables: Where indicated, flexible cables for use with heating
appliances or luminaires shall be heat resistant of at least 105°C.
BB Cable Support Systems: For above ground installations the method of fixing
PVC/XLPE insulated and PVC sheathed cables shall be either laid on cable trays or
ladder rack or clipped to the building structure by suitable cable clamp. All single
core unsheathed cables shall be run in a non-metal conduit or trunking system.
DD In the case of vertical cables, the clamps shall be so designed and of sufficient
number to grip the cable firmly to prevent creeping. No cable runs shall be without
fittings. All cable hangers and racks shall be submitted for inspection by the Owner’s
Representative prior to the installation of cables. Where cable routes are subject to
numerous changes in level and direction additional cable hangers shall be provided.
PART 3 EXECUTION
3.1 INSPECTION
A. The outside of each cable reel shall be carefully inspected and protruding nails, fas-
tenings, or other objects which might damage the cable shall be removed. A thor-
ough visual inspection for flaws, breaks, or abrasions in the cable sheath shall be
made as the cable leaves the reel, and the pulling speed shall be slow enough to
permit this inspection. Damage to the sheath or finish of the cable shall be sufficient
cause for rejecting the cable. Cable damaged in any way during installation shall be
replaced by and at the expense of the Contractor.
3.2 PREPARATION
A. Cable Protection: Cables shall be carefully handled during installation to avoid dam-
age of any kind. They shall be unreeled or uncoiled slowly in order to prevent dam-
age to the insulation or sheath due to sudden bending. Repeated bending shall be
avoided. Sharp links shall be avoided in unreeling, uncoiling and pulling.
B. The pulling of cables into conduits or ducts shall be carried out with all possible care.
The cable reels or coils shall be positioned so that the cable may be trained into the
conduit or duct as directly as possible, with the minimum of changes of direction or
of bending. The cable end shall be provided with a suitable protector to guard
against damage to the insulation or sheath. Where several cables are contained in
one conduit or duct, all cables shall be pulled-in together.
C. The pulling tension shall not exceed the maximum tension as recommended by the
cable manufacturer.
D. Long lengths of cable shall be laid using an adequate number of drum jacks, rollers
and other handling accessories. Make-shift-arrangements will not be acceptable.
Care shall be taken to break the rotation of the reel and cables shall not be dragged
over loose earth, concrete or any surface detrimental to the insulation. Cables shall
not be stretched but shall be adequately supported on rollers or manhandled into
position.
E. Before cables are pulled through ducts, the ducts shall be checked for cleanliness and
smoothness. Where ducting is longer than two meters, a cable wire mesh cable
stocking shall be used to attach the cable to the draw-in rope.
F. The minimum bending radii shall be not less than that recommended but the cable
manufacturer and contra twisting shall be avoided.
Low-Voltage Electrical Power Conductors and Cables Section 260519
Urbanium New Administrative Building (Prj. 2874) Page 11 of 14
G. Spacing between cables shall be suitable for the derating factors applied to the cable
installation design.
H. Cables shall be installed using the loop-in principle, unless otherwise specified no
straight through or tee joints will be permitted.
I. Cable Routing: The general route of all cables shall be indicated on the drawings
and/or as directed by the Owner’s Representative if there are no drawings. The Con-
tractor shall include for all deviations required by the building structure and other
services. The final routes of all cables shall be submitted to the Owner’s Representa-
tive before any work in connection with the cable installation is commenced.
K. Where cables are situated below floor level in sub-stations and switch rooms, they
shall be run either in formed concrete open ducts, PVC or under fire resisting access
flooring. No cables shall be buried directly in concrete flooring or foundations.
L. Where cables pass through holes in panels or other metalwork, they shall be pro-
tected by rubber grommets, compression glands or their equivalent.
M. Where cables are run vertically heavy gauge sheet metal guards shall be supplied and
fixed where there is a possibility that the cable could sustain mechanical damage.
O. Before commencing any part of the works, the Contractor shall submit for engineer
study and approval, drawings indicating conduit, trunking, ladders, trays and duct
sizes together with the proposed layout of the system.
P. Whenever cables have to pass through walls or slabs, special fire insulation should be
applied. The insulation shall have the same fire class as the wall or slab penetration.
Q. Both high, medium, low voltage and intrinsically safe cables shall be on separate ca-
ble runs.
R. All cable runs shall have minimum 30% spare space after all cables is installed.
S. Cable runs, supports and all its splices shall be conductive and be well earthed.
T. The main runs for cables between buildings shall be on the edge of the road, outside
the water ditch. If cables have to cross roads or concrete covers the cables must be
run in a drained cast ditch of concrete. The ditch must have covers that are to move.
U. Segregation: Cables of different voltages and duties shall be segregated and particu-
lar attention shall be paid to the avoidance of induced 'spikes' or ' electrical noise' on
adjacent circuits due to high currents and/or switches surges.
V. Grounding: All metal work which cannot be insulated as defined in the Governing
Standards and is associated with cable runs shall be bonded to earth or to the cable
armoring where this latter methods is approved.
Low-Voltage Electrical Power Conductors and Cables Section 260519
Urbanium New Administrative Building (Prj. 2874) Page 12 of 14
W. Where steel tape armored cables are specified and the resistance of the armoring is
unsatisfactory, a supplementary earth (ground) cable shall be run with the affected
cable. This cable shall be sized to ensure compliance with the wiring regulations for
earthing.
3.3 INSTALLATION
A. Cable Installation: Cable shall be installed in accordance with IEC standards and local
code.
B. If single core cables are used they must not be installed separately through openings
of magnetic materials. They must be installed in 3 phase grouping to avoid current
heating”.
C. Cables for intrinsically safe circuits shall be routed on separate cable ladder or trays
or separated clearly from other cables. The tray shall be marked with a light blue
color.
D. Cable entries into all equipment shall be from below. When an entry has to be hori-
zontal a drip loop shall be performed in the cable immediately behind the cable
gland. Entries from above shall be avoided if possible, except for distribution board
in electrical rooms, top entry is allowed.
E. Cables shall not be buried in solid or hard setting building finishes unless prior ap-
proval has been given by the Owner’s Representative. The Contractor shall ensure
that cables when run in building finishes are immediately protected against mechani-
cal or any other damage. The Contractor shall also be in attendance when finishes
are applied and shall ensure that no damage or displacement occurs.
F. Cables shall be installed parallel to the building lines and shall not be run diagonally
in floor or ceiling finishes.
G. Single cable passing through walls and floors shall be protected by means of tubular
PVC or steel sleeves of sufficient size to give minimum 13 mm clearance all round the
cable. Sleeves passing through floors shall extend above the floor level a minimum
of 40 mm.
H. Where passing through walls the sleeve shall finish flush with the finished surface.
All sleeves shall be tightly packed with suitable fire resistant materials of an approved
type. All cables rising from floor level to equipment or in other locations where acci-
dental damage may occur shall be protected.
I. Cables shall be straightened and dressed neatly on the runs by approved methods.
All bends shall have an inside radius of not less than that recommended by the cable
manufacturer and in no case shall it be smaller than the bending radii shown in the
appropriate standards.
K. Cables shall be tagged at both ends, inside each panel, and every 15 m of the run.
Tag shall be metal type and shall read both the cable size and the target panels or
loads (From/To).
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP GROUNDING AND BONDING FOR
CAIRO - EGYPT ELECTRICAL SYSTEMS 260526- 2874 0
SECTION 260526
Page
PART 1 - GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Definitions 2
1.4 Submittals 3
1.5 Quality Assurance 5
PART 2 - PRODUCTS 5
2.1 Conductors 5
2.2 Connectors And Earthing Accessories 6
2.3 Earthing Electrodes 6
2.4 Soil Survey And Calculations 7
2.5 Fault Current And Duration 8
2.6 System Design 8
PART 3 - EXECUTION 12
3.1 Applications 12
3.2 Equipment Grounding 12
3.3 Installation 14
3.4 Connections 16
3.5 Field Quality Control 17
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including General and Supplemen-
tary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes complete installations to earth every source of energy and to
provide protective earthing and equipotential bonding, based on the TN-S system ar-
rangement, including:
C. In addition to, the common ground bonding for lightning protection system.
1.3 DEFINITIONS
A. The words "earth" and "earthing" as used herein are synonymous with the words
"ground" and "grounding" and may be used interchangeably within this specification.
C. Earth: Conductive mass of the Earth whose electric potential at any point is conven-
tionally taken as zero.
D. Earth Electrode: Conductor or group of conductors in initial contact with, and provid-
ing electrical connection to, Earth.
E. Exposed Conductive Part: Any part which can be readily touched and which is not a
live part, but which may become live under fault conditions.
F. Extraneous Conductive Part: Any conductive part not forming part of the electrical in-
stallation such as structural metalwork of a building, metallic gas pipes, water pipes,
heating tubes etc. and non-electrical apparatus electrically connected to them i.e. ra-
diators, cooking ranges, metal sinks etc. and non-insulating floors and walls.
G. Protective Conductor: Conductor used for some measure of protection against elec-
tric shock and intended for connecting together any of the following parts:
H. Main Earthing Terminal or Bar: The terminal or bar provided for the connection of
protective conductors, including equipotential bonding and functional earthing con-
ductors if any to the means of earthing.
1.4 SUBMITTALS
A. Product Data and Sample: Submit for each type of product indicated including manu-
facturer’s catalogue sheets with catalogue numbers marked for the items furnished,
which shall include:
B. Qualification data for firms and persons specified in "Quality Assurance" Article to
demonstrate their capabilities and experience. Include lists of completed projects
C. Field inspection reports indicating compliance with specified requirement and submit
written test reports to include the following:
1. Test procedures used and test conditions (Method statements for testing of
the earthing system for each building/structure and the measurement of soil
resistivity).
2. Test results that comply with requirements.
3. Results of failed tests and corrective action taken to achieve test results that
comply with requirements.
E. Shop Drawings: Submit drawings for approval including, but not limited to, the fol-
lowing:
F. As-Built Drawings: Scaled drawings, showing actual layout and specification of all
components of earthing system include the number of rods driven and their depths
at each location, indicate nature of soil, special earthing arrangements, date and par-
ticulars of additives to soil or in bore-holes if used, test conditions such as weather
and other phenomena that may effect on the tests and results obtained.
G. Compliance Sheet: Contractor to fill-in the compliance data sheet (when attached to
a section) and stamp it by the proposed supplier and by the proposed electrical sub-
contractor (or himself if no sub-contractor). If the Contractor is assuming two suppli-
ers for one material item in his bid, two data sheets should then be filled and
stamped, as mentioned, for the same item.
H. Operation and Maintenance Data: For grounding to include the following in emer-
gency, operation, and maintenance manuals:
PART 2 - PRODUCTS
2.1 CONDUCTORS
A. Insulated Conductors: Copper wire or cable PVC insulated in green and/or green-
yellow color for 380 V unless otherwise required by applicable Code and indicated on
the drawings.
1. Stranded Conductors: Soft drawn annealed bare copper with 98% conductivity
and shall conform ASTM B3 and/or BS EN 60228 and/or IEC 60228.The cross
section shall be 120 mm2 unless otherwise indicated on the drawings.
2. Flexible braided cable strap: Copper, 250 mm by 35 mm thick ground post
clamps. Clamps shall be of the anti-electrolysis type.
3. Grounding plates: Copper, minimum 600 mm by 600 mm by 3 mm thick.
C. All conductor fittings shall be manufactured from high strength copper alloys with
phosphor bronze nuts, bolts, washers and screws. All fittings shall be designed for the
specific application and shall not be permanently deformed when correctly installed.
D. Protective Bonding Conductors: Bare copper strip conductor, annealed stranded cop-
per cable or flexible strap (flexible braid) of cross-sectional area as mentioned in item
2.7 (b)-12.
D. When the reinforcing in concrete is used as a part of the earthing system the fittings
used to provide a connection point at the surface of the concrete shall be exothermi-
cally welded to a reinforcing bar. This fitting shall be provided with a bolted connec-
tion for an earthing conductor. The main bars in the reinforcing shall be welded to-
gether at intervals to ensure electrical continuity throughout the reinforcing.
E. No connections shall be made to reinforcing bars and other steelwork, which do not
form part of the earthing system and are completely encased in concrete.
A. Earth Electrode: The earth electrodes shall comprise a system of bare conductors
forming a loop/ring buried near the surface of the ground supplemented, by one or
more of the following electrodes:
B. Ground/Earth Rods: Copper-clad steel rods and shall not less than 20mm in diameter
by not less than 3000 mm in length per section and shall conform to the require-
ments of NFPA 70 and UL 467 and/or BS. Ground rods must be clean and smooth and
have a cone-shaped point on the first section and be die-stamped near the top.
C. Reinforcing Steel:
D. Earth Pit: Precast, square or circular section concrete hand-hole (minimum 450 mm
internal diameter), with concrete cover, with ultra-heavy-duty cover for areas where
heavy vehicles cross and extending to about 150 mm below top of earth rod. Earth
pit is to be provided for each earth rod where connected to an earthing conductor.
Cover is to have inset brass plate with inscription 'Earth Pit No. # & Earth pit ID - Do
Not Remove'.
E. Earth pit with Sealing Kit: shall be installed within the building itself. The pit shall be
provided with a suitable sealing mechanism around the earth electrode.
The pit shall be of high performance lightweight polymer, corrosion resistance pres-
sure tested, compliant to BS EN 62305-3 standard and tested according to BS EN
50164-5. The sealing mechanism shall consist of high density polyethylene molding
flange and housing to accommodate the sealing kit and protective tube for the earth
rod.
F. Power Systems (transformer, medium voltage switchgear, generator, and main dis-
tribution board) Main Earthing Bar: Consisting of hard drawn annealed copper bar
conforming to ASTM B3, 50 x 6 mm. Earth bar is to be labeled 'Main Earth Bar' and is
to be drilled, for connection of conductors, at a spacing not less than 75 mm, and is
to be supplied with copper alloy bolts, nuts and washers and wall mounting insula-
tors.
G. Telecommunication Systems Main Earthing Bar: similar to above but with minimum
dimensions 100 x 6 mm for the main grounding busbar of the main telecommunica-
tion room, and 50 x6 mm for equipment rooms grounding busbars.
H. Disconnecting links shall comprise a high conductivity copper PVC insulated link sup-
ported on two insulators mounted on a galvanized steel base for bolting to the sup-
porting structure. The two conductors shall be in direct contact with the link and shall
not be disturbed by the removal of the link. Links for mounting at ground level shall
be mounted on bolts embedded in a concrete base.
I. Disconnecting links mounted at ground level and the connections at the earth rods
shall be enclosed in concrete inspection pits, with concrete lids, installed flush with
the ground level.
J. Testing joints (Test links): Copper or copper alloy, with bolted end connections, dis-
connect able by use of a tool, and suitably sized for earthing conductors or earth bar
connection. Links are to be fixed to porcelain or other approved insulating supports.
Contact surfaces are to be tinned.
A. The Contractor shall carry out an earth resistivity survey on each site and report in
B. The value of resistivity’s to be used in the design of the earthing system shall be sub-
ject to the Engineer’s approval.
C. The surveys shall show the variation of resistivity across the site and with the depth
below the site. The Contractor shall consider if there is a need to model the resistivity
in two layers and if there is any advantage in the use of long rods. The surveys shall
also determine the depth and nature of any underlying rock, which may limit the
depth for driving earth rods or if boring will be necessary for installing earth rods.
D. The weather conditions prior to and at the time of the surveys shall be recorded in
the report and an assessment made of the seasonal variations in resistivity based on
meteorological data for the area. The program for the project should, as far as possi-
ble, time the resistivity surveys to take place during a dry season.
E. The report should also state if there are any indications that the ground is corrosive
to copper or if there is any risk of galvanic corrosion on other metal structures in the
neighborhood.
F. The report shall be approved by the Engineer before proceeding with the design of
the earthing system.
G. The calculations shall be submitted for approval prior to commencing the design of
the earthing systems.
A. The earthing system design calculation by the Contractor shall be based on earth
fault withstand current.
B. The estimated maximum duration of the fault current shall not be less than 1.0 sec-
onds for the 11 KV system.
A. Design Calculations:
1. The design of the earth electrode systems shall be based on the approved
earth resistivity data and the system’s fault currents and their duration.
2. The design calculations shall be submitted to the approval of the Engineer and
shall be based on the methods given in the standards listed. The calculations
shall include the following parameters: -
B. General Requirements
13. Main Equipotential Bonding: Main incoming and outgoing water pipes and any
other metallic service pipes are to be connected by main equipotential bond-
ing conductors to main earth terminal or bar. Bonding connections are to be as
short as practicable between point of entry/exit of services and main earthing
bar. Where meters are installed, bonding is to be made on the premise side of
the meter. Cross-sections of conductors are not to be less than half that of the
earthing conductor connected thereto, and minimum 6 mm2.
14. Identification: Connection of every earthing conductor to earthing electrode
and every bonding conductor to extraneous conducting parts is to be labeled in
accordance with the Regulations, as follows:
1. Patient care areas shall be provided with retardant ground (earthing) path. Re-
tardant ground paths will be provided via equipment ground conductors and
raceway systems.
2. The equipment ground busses in different panel-boards serving the same pa-
tient care areas will be bonded together.
3. Provide an equipotential grounding system in each operating room. All metal
objects likely to become energized in the OR room shall be grounded via a ded-
icated, insulated grounding conductor to the room ground bus.
4. Room ground bus shall consist of an isolated ground bar mounted in a re-
cessed metal junction box with stainless steel cover
5. Each patient room shall include two Patient Equipment Grounding Points on
both sides of bed installed in the bed head unit. Each Patient Equipment
Grounding Point shall include one grounding jack.
3.1 APPLICATIONS
A. Conductors: Install solid conductor for 10mm2 and smaller, and stranded conductors
for 16 mm2 and larger, unless otherwise indicated on the drawings.
1. Bury at least 600 mm below grade at a distance not less than 1000mm and not
more than 3000 mm from the edge of walkways and not more than three me-
ters from the structure.
2. Duct-Bank Grounding Conductor: Bury 300 mm above duct bank when indi-
cated as part of duct-bank installation.
D. Grounding Resistance: The completed installation when a ground loop is not used
shall have a maximum total resistance to ground using the fall-of-potential method
described in IEEE 81 or equivalent method as per BS and/or IEC of 5 ohms, under
normally dry conditions. Use a ground loop when two of any three (3) ground rods,
driven not less than three meters into the ground, a minimum of three meters apart
and equally spaced around the perimeter, give a combined value exceeding 50 ohms
immediately after having been driven.
F. Make connections between ground conductors and grounds or ground loop and be-
tween ground loop and grounds electrically continuous. Where so indicated, provide
an alternate method for grounding electrodes in shallow soil by digging trenches ra-
dially from the building. A 120 mm2 bare copper cable (or as shown on the drawings)
arranged in a star pattern with the structure at the center for radial systems shall be
installed.
1. Ring Main Unit is to have a separate main earthing bar connected to RMU
room earth bar by two insulated earthing conductors, one at each end of bar,
via testing joints. Earthing Conductors is to be minimum not less than 120mm2
1. Generator room is to have a separate main earthing bar, to which the genera-
tor neutral (star point) is to be connected by insulated earthing conductor
through the neutral earthing link or device. Neutral earthing conductor is to be
suitably sized to carry maximum earth fault current for time it takes the system
protection to operate with final conductor temperature not exceeding 160
deg. C, but not less than 120 mm2 for LV generator ratings below 500 kVA and
300 mm2 for higher LV generators’ ratings.
2. Generator earthing terminal is to be connected to the generator room main
earthing bar by insulated copper conductor of cross section not less than 120
mm2 unless otherwise indicated on the drawings.
3. Automatic Transfer Switch (ATS) and Control Gear: Earthing terminals or bars
of switchgear and control gear are to be connected by separate protective
conductors to respective normal and emergency main distribution board earth
bars.
4. Extraneous conductive parts including steel frames, battery racks, day-tank,
pumps and piping are to be connected by bare copper earthing conductors to
main earth bar in compliance with bonding regulations.
E. Road Lighting
1. Earthing Cables: separate protective earthing cables for lighting column circuits
are to be run with power circuit, terminated at LV supply position in lighting
control panel and looped into column earthing terminals. The last column is to
be bonded via an earthing bolt to a single 16 mm diameter copper covered
steel rod, 2.4 m long, driven into ground adjacent to column. Bonding is to be
16 mm2 stranded bare copper conductor.
2. Connections between rods and earthing conductors are to be made by the cad
weld process producing a fused joint. Bolted connections may be used for con-
nection to removable items of equipment only.
1. Clean earth grounding or low noise earth shall be provided as required, to en-
sure that the level of induced or conducted interference from external sources,
including the facility power grounding system, does not produce incidence of
malfunction of the equipment, which is unacceptable for the operating system.
2. Clean earth grounding system shall not be connected to any other earthing or
grounding system.
3. Clean earth grounding cables shall not be run parallel with other grounding ca-
bles or power cables.
4. Clean earth grounding system shall comply with IEC 60950 and BS EN 50310.
5. Clean earth grounding pits shall be separated from other earthing pits by a dis-
tance of at least 1800mm.
6. In general clean earth grounding shall be provided for data system, telephony
and other communication systems, and UPS unless otherwise recommended
and required by systems providers.
7. Clean earth grounds shall have an earth impedance of less than 0.5 ohm unless
otherwise indicated.
3.3 INSTALLATION
A. Coordination: All works below grade shall be thoroughly coordinated with all under-
ground services and structures. Grounding and bonding works must, in all circum-
B. Continuity: Ensure that complete earthing system is electrically continuous and me-
chanically secure.
C. Grounding Conductors: Route along shortest and straightest paths possible, unless
otherwise indicated or required by Code. Avoid obstructing access or placing con-
ductors where they may be subjected to strain, impact, or damage.
D. Common Ground Bonding with Lightning Protection System: Comply with code when
interconnecting with lightning protection system. Bond electrical power system
ground directly to lightning protection system grounding conductor at closest point
to electrical service grounding electrode. Use bonding conductor sized same as sys-
tem grounding electrode conductor, and install in conduit.
E. Ground Rods: Drive rods until tops are 50 mm below finished floor or final grade, un-
less otherwise indicated.
F. Test Pits: Install at least one test pit for each service, unless otherwise indicated on
the drawings. Set top of test pit flush with finished grade or floor.
G. Bonding Straps and Jumpers: Install in locations accessible for inspection and
maintenance, except where routed through short lengths of conduit.
1. Bonding to Structure: Bond straps directly to basic structure, taking care not to
penetrate any adjacent parts.
2. Bonding to Equipment Mounted on Vibration Isolation Hangers and Supports:
Install so vibration is not transmitted to rigidly mounted equipment.
3. Use exothermic-welded connectors for outdoor locations, but if a disconnect-
H. Bonding shall be provided where necessary to assure electrical continuity and the ca-
pacity to conduct safely any fault current likely to be imposed. Non-current-carrying
metal parts of service equipment shall be effectively bonded together.
J. Care shall be taken to ensure good ground continuity, in particular between the con-
duit system and equipment frames and enclosures. Where necessary, jumper wires
shall be installed.
L. Bonding Interior Metal Ducts: Bond metal air ducts to equipment grounding conduc-
tors of associated fans, blowers, electric heaters, and air cleaners. Install bonding
jumper to bond across flexible duct connections to achieve continuity.
M. Grounding for Steel Building Structure: Install a driven ground rod at base of each
corner column and at intermediate exterior columns at distances not more than 18 m
apart unless otherwise indicated on the drawings or required by the codes.
3.4 CONNECTIONS
C. Where earth connections between dissimilar metals must be made, use bimetallic fit-
tings and protect by coating with moisture resisting bituminous paint or compound,
or by wrapping with protective tape to exclude moisture.
E. Tighten screws and bolts for grounding and bonding connectors and terminals ac-
cording to manufacturer's published torque-tightening values. If manufacturer's
torque values are not indicated, use those specified in applicable Standards.
F. Connection of earthing conductors to ground pit earth rods, shall utilize multiple
connectors as required. More than one cable shall not be connected through one
connector clamp unless specifically permitted.
A. Testing Agency: Owner or his representative will engage a qualified testing and in-
specting agency to perform field tests and inspections and prepare test reports.
B. Perform the following tests in addition to the tests required by IEC and/or BS and in-
spections and prepare test reports:
1. After installing grounding system but before permanent electrical circuits have
been energized, test for compliance with specifications and drawings require-
ments.
2. Test completed grounding system at each location where a maximum ground-
resistance level is specified, at service disconnect enclosure grounding termi-
nal. Make tests at ground rods before any conductors are connected.
a. Measure ground resistance not less than two full days after last
trace of precipitation and without soil being moistened by any
means other than natural drainage or seepage and without chemi-
cal treatment or other artificial means of reducing natural ground
resistance.
C. Report measured ground resistances that exceed the maximum ground resistance
value required.
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. RACEWAY AND BOXES FOR ELECTRICAL
CAIRO - EGYPT SYSTEMS 260533 – 2874 0
SECTION 260533
Page
PART 1 GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Submittals 2
1.4 Quality Assurance 2
1.5 Coordination 3
PART 2 PRODUCTS 3
2.1 Manufacturers 3
2.2 General 3
2.3 Application Considerations 3
2.4 Electrical Metalic Tubing 4
2.5 Flexible Metal Conduit 4
2.6 Rigid Heavy Gauge Pvc Conduit 4
2.7 Under Groung Upvc Conduits 5
2.8 Flexible Pvc Conduit 5
2.9 Steel Conduit Accessories 5
2.10 Wiring And Cable Trunking 6
2.11 Weatherproof Wiring And Cable Trunking 6
2.12 Outlet Boxes, General 7
2.13 Metallic Outlet Boxes 7
2.14 Moulded Plastic Outlet Boxes 7
2.15 Floor Outlet Box 8
PART 3 EXECUTION 8
3.1 Examination 8
3.2 Equipment Installation Requirements 8
3.3 Installation And Wiring 8
3.4 Outlet Boxes 10
3.5 Junction, Pull 11
3.6 Grounding And Bonding 11
3.7 Connections 11
3.8 Protection 11
3.9 Cleaning 12
PART 1 GENERAL
A. Drawings and general provisions of the Contract, including General and Supplemen-
tary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This section covers raceways, fittings, boxes, enclosures, and cabinets for electrical
wiring:
1. Raceways include all types of conduits, trunking and duct bank systems, such
as Electrical Metal Tubing (EMT), Rigid PVC Conduit, Flexible Conduit, wire
ways, Surface Raceways, galvanized trunking, rigid PVC trunking, etc.
2. Boxes, enclosures, and cabinets include the following devices: floor boxes,
pulling and junction boxes, cabinets and hinged cover enclosures.
1.3 SUBMITTALS
C. Shop Drawings showing components and wiring as to ensure clearances and access
provisions. Refer to cable sections (260513, 260519) for more details on cable laying,
segregation and bundling inside raceways, trunking and trays.
E. Samples.
A. Products specified in this section should comply with IEC & local Egyptian regulations
for components and installation.
1.5 COORDINATION
A. Coordinate layout and installation of raceways and boxes with other construction el-
ements to ensure adequate heady room, working clearance, and access.
PART 2 PRODUCTS
2.1 MANUFACTURERS
2.2 GENERAL
A. Materials and equipment to be provided shall be new and essentially the standard
catalogued products of a manufacturer regularly engaged in the manufacture of the
products.
A. The specified products for raceways, boxes, and cabinets shall be used as suitable to
the environment. The following table shall be a general guide and shows a complete
list of environments and permissible products.
B. Legend:
A. Electrical Metallic Tubing (EMT): Welded steel, non-threaded type galvanized exter-
nally and protected internally with corrosion resistant enamel, according to U.S. Fed-
eral Specifications, UL 797 and ANSI C80.3.
B. EMT Fittings: Generally, thread less pressure type, galvanized or cadmium plated
malleable cast iron. Fittings used in corrosive atmospheres are to be specially treat-
ed. Factory made bends are to be provided where site bending is not possible.
A. Material: Steel, cold rolled and annealed, non-threaded type, formed from continu-
ous length of helically wound and interlocked strip steel, with fused zinc coating on
inside and outside, and to IEC 61386-1, BS EN 50086-1.
C. Fittings: Generally Thread less, hinged clamp type, galvanized or cadmium plated
malleable cast iron. Fittings used in corrosive atmospheres are to be specially treat-
ed.
D. Straight Connectors: One-piece body, female end, having hinged clamp and deep
slotted machine screws for securing to conduit, male end having thread and locknut.
A. Material: Rigid un-plasticized polyvinyl chloride with high impact and high tempera-
A. UPVC conduits with diameter greater than 32 mm used for electrical low voltage and
medium voltage Cables ducts shall comply with DIN Standard 8061/8062 or BS 3506.
B. Conduits installed in concrete encased duct bank shall be UPVC Class-2 (4 bar) ac-
cording to DIN standard, unless otherwise indicated.
C. Conduits installed direct-buried duct in non-traffic areas shall be UPVC Class-3 (6 bar)
according to DIN standard, unless otherwise indicated
D. Conduits installed direct-buried duct in traffic area shall be UPVC Class-4 (10 bar) ac-
cording to DIN standard, unless otherwise indicated.
A. Sleeves Through Outside Walls: Cast iron, with end and intermediate integral flanges,
and internal diameter larger than diameter of through-conduit. Length is to corre-
spond to wall thickness. Space between sleeve and conduit is to be packed with
backer rod/oakum to within 50 mm of both faces of wall, remainder of sleeve packed
with plastic compound or lead, held in place by heavy escutcheon plates bolted at
both ends to flanged ends of sleeve. Alternatively, sleeves are to be O.Z/Gedney,
Type WSK or other equal and approved, with cable or conduit bolted pressure sealing
components.
B. Supports and Hangers: Galvanized malleable cast iron straps or structural steel sec-
tions with hot dip galvanized bolts and nuts.
D. Expansion Joint for Exposed Steel Conduits - Type B: Sleeve with fittings to permit
telescoping of one conduit into sleeve. Movable conduit is to be fitted with water-
tight bushing. Joint is to be weatherproof, of galvanized malleable iron or steel.
Bonding jumper with earth clamp is to electrically connect both sides of joint. Expan-
sion fitting is to be O.Z/Gedney, Type DXX or other equal and approved.
E. Expansion Joint for Exposed Steel Conduits - Type C: PVC sheathed flexible steel con-
duit terminating in pull boxes and securely fixed on each side of structural expansion
joint. Bonding jumper is to electrically connect both sides of joint.
F. Tags: 50 mm diameter steel with indented lettering, rust inhibiting treatment and
baked enamel finish.
A. Components are to include wire way base, clip-on covers, couplings, end plates, wall
flanges, panel to trunking rubber grommets, elbows, tees, adaptor plates and neces-
sary hangers, supports and accessories.
C. PVC Trunking: To BS 4678 part 4 high impact, heavy duty, self-extinguishing, rigid PVC
with grooved double locking action of the clip-on cover. Design is to be approved by
Engineer before ordering materials. Trunking is to be capable of receiving functional
slot-in hangers and demountable separators to segregate wiring systems as needed.
A. Type: Hot-dip galvanized sheet steel trunking of 1.5 mm thickness (minimum) with 1
mm thick cover to BS EN 50085-1 and BS EN 50085-2 for trunking and BS EN ISO 1461
for galvanizing.
B. Construction: Trunking is to have outwardly turned flanges to receive cover, and in-
ternal sleeve coupling between sections, permitting cutting of trunking on site.
C. Gaskets: Neoprene bonded cork gaskets are to be fitted throughout, between any
two attached surfaces.
A. Surface or recessed boxes are to be suitable for type of related conduit or cable sys-
tem. Shapes and sizes of boxes are to be of compatible standards as switches and
socket outlets specified under Division 26 Section "Wiring Devices", and lighting fix-
tures selected and of various types and mounting methods required.
B. Unused openings in outlet boxes are to be closed with molded caps or knock-out
closers manufactured for the purpose.
A. Recessed and Concealed Boxes: Galvanized pressed steel, with knock-outs for easy
field installation. Special boxes are to be punched as required on Site.
B. Exposed Surface Mounted Boxes: Galvanized cast iron with threaded hubs.
C. Outdoor Surface or Recessed Boxes: Galvanized cast iron with threaded hubs and
PVC gaskets to ensure water tightness and with stainless steel or non-ferrous, corro-
sion resistant screws.
D. Floor Boxes - Type A: Watertight, cast iron or cast metal alloy with corrosion resistant
finish, adjustable mounting, standard duty, round or square, factory drilled and
tapped for required conduit sizes, and with brass cover and flange with brushed fin-
ish free from markings other than required for mounting screws.
E. Floor Boxes - Type B: non-standard size, flush floor mounted, cast metal alloy, with
watertight neoprene gasket and hinged cover for each service. Box to be ready with
factory drilled and tapped conduit entries and adjustable mounting fittings. Metal
barriers are to separate services for power and low current.
F. Flame-Proof Boxes: Malleable iron or cast iron, with gas threaded hubs, special co-
vers with silicon rubber gaskets, gas tight, and water-tight. Boxes are to comply with
the Regulations for explosive areas.
A. Type: Boxes and covers used with PVC conduit systems are to be heavy gauge pres-
sure molded plastic, minimum 2 mm thick, self extinguishing, with softening point
not less than 85 deg. C. Boxes are to have provision for securely terminating conduits
and are to be manufacturer's standard for required application.
B. Fittings: Boxes are to have brass inset threads to receive cover screws and for mount-
ing devices or accessories, push-fit brass earth terminals, and steel insert clips to
A. Floor service waterproof boxes shall be a steel recessed floor box with four wiring
compartments. Fully adjustable mounting hardware with degree of protection not
less than IP 44.
B. Wiring compartments shall be interconnected within the box with removable divid-
ers. Each floor box shall use flush activation. The cover shall be suitable for the appli-
cation, specifically a flush access hatch with carpet trim or flush furniture partition
feed. The exact type of cover for each box will be determined by the owner in con-
junction with the interior finishes.
C. Boxes with no connections shall be equipped with the flush access hatch. The covers
shall not be installed until the floor coverings or tile is installed. The boxes shall be
protected from damage during construction.
E. Install two brackets for mounting receptacles with provision for snap-in connector
modules unless indicated otherwise on the drawings.
PART 3 EXECUTION
3.1 EXAMINATION
A. Examine surfaces to install raceways, boxes enclosures and cabinets for compliance
with installation tolerances and other conditions affecting performance of the race-
way system. The Contractor shall not proceed with installation until unsatisfactory
conditions have been corrected.
A. General: Provide all the equipment installation and wiring installation, including
connections as indicated, specified and required. Assure proper fits for all equip-
ment and materials in the space as shown on the Drawings. Conduits installed un-
derground shall be provided with preformed long radius PVC elbows encased in con-
crete. Liquid-tight lengths of flexible conduit shall be used for connections to all mo-
tors and equipment subject to vibration. Maximum conduit fill shall not exceed 40%.
A. Conduits shall be concealed either within false ceiling plenums or embedded in slabs,
B. A minimum clearance of 300 mm shall be maintained for conduits that are installed
in the vicinity of uninsulated hot pipes or hot surfaces.
C. Sleeves and inserts shall be furnished and installed as required for electrical work.
Open conduit ends shall be carefully closed during construction to prevent foreign
materials from entering the conduit.
D. Conduit buried in concrete shall have 35 mm depth of cover over its entire length.
Conduit shall not be installed in plastering layers.
E. A draw in (Pull) box shall be provided in all conduit runs exceeding 10 m or contain-
ing more than two right angled bends. Any unused opening shall be plugged.
F. The length of thread (for galvanized steel conduits) at the ends shall suit the length
of the internal thread of the fitting or accessory. Excess length shall not be allowed.
G. Fixings for surface mounted conduit boxes, accessory boxes and saddles to concrete,
brick, building blocks and similar materials shall be by means of cadmium-plated
steel screws and raw plugs.
H. The ends of conduits shall be cut straight and the length of screw thread (for the gal-
vanized steel conduits) shall be sufficient only to allow the ends of the conduit to
butt solidly in all couplings and against the shoulders provided in conduit boxes.
I. The ends of galvanized conduits shall be carefully reamer to remove all burrs or
sharp edges after the screw threads have been cut. All dirt, paint or oil on the
screwed threads of the conduit and accessories shall be carefully removed immedi-
ately prior to erection.
J. The number of running joints in conduit shall be kept to a minimum and where in-
stalled locknuts shall be used to secure the sockets.
K. Where space permits their use, plain bends are preferred than elbows. Maximum
number of bends is 3 as total.
M. All joints in an assembly of conduit shall be painted after assembly with two coats of
moisture resisting paint. Arrangements shall be made, where necessary to prevent
the collection of moisture in conduit fittings.
N. Runs terminating in flexible conduit shall have the latter fitted with special adaptors
in accordance with the Manufacturer's recommendations to ensure a weatherproof
connection and where applicable, earth continuity.
O. Where equipment is provided with a plain entry only, the conduit shall be fixed by
means of flanged couplings, lead washers and male brass brush.
Q. Deep boxes or extension rings on standard circular conduit boxes shall be used
where necessary in order to bring the front face of each box flush with the surface of
the ceilings.
R. Nails shall not be used for fastening the boxes installed in concrete slabs.
S. The box shall be so constructed as to prevent contact between the conductors in the
box and the supporting screws.
T. Flush-mounted boxes shall be cast in concrete walls or grouted into hollow masonry
walls. Metal boxes threaded to raceways in exposed installations shall be separately
supported. Boxes installed in concealed conduit or raceway systems shall be set
flush with the finished surfaces. The location of all boxes shall be easily accessible
and any interference with mechanical equipment or structural features shall be relo-
cated as directed by the Engineer.
U. All circuit wires shall be tagged to indicate clearly the circuit number and panel des-
ignation at each pull box or access point. Circuit wires in excess of 600 V shall have
voltage identification.
V. Device plates shall be installed with all four edges in continuous contact with finished
wall surfaces without the use of mats or similar devices. Device plates shall be in-
stalled vertically with an alignment tolerance of 2 mm.
B. Outlet boxes for similar equipment shall be mounted at uniform heights within the
same or similar areas. Without any restrictions by Drawings or instructions on Site,
and except where they are located 250 mm above work benches or positioned to suit
a particular piece of equipment, switches and socket outlets shall be mounted at
1.25 m and 300 mm from finished floor level, respectively.
C. All outlet boxes shall be securely fastened. Exposed outlet boxes shall be attached to
permanent inserts or lead anchors with machine screws.
D. All unused openings in outlet boxes shall be closed with knockout closers manufac-
tured for such purpose.
E. Blank plates for wall outlets shall be attached by a bridge with slots for horizontal
and vertical adjustment.
A. Junction and pull boxes shall be located where required to facilitate pulling of wires.
B. Boxes of adequate capacity shall be provided at every junction of the conduit system
and as required by the "IEE Building Regulations".
D. Concealed surfaces of hot dip galvanized steel junction, pull boxes shall be given a
heavy field application of emulsified asphalt prior to installation.
A. Grounding type insulated bushings shall be provided on steel conduits at all distribu-
tion boards. The grounding bushings shall be bonded together and to the equipment
enclosure or, where provided, to the equipment ground bus. This type of installation
shall also be used at pull boxes to ensure ground continuity.
B. Effectiveness of grounding shall not be dependent upon the continuity of the metal
and a separate earth conductor shall run throughout the conduit for this purpose.
D. Sizes of installed earthing conductor shall not be less than those indicated in relevant
regulations, codes of practice etc.
3.7 CONNECTIONS
A. All conduit connections shall be made up tight to provide good electrical conductivity
throughout the entire length of the conduit run including flexible conduits.
3.8 PROTECTION
A. The contractor shall exercise the necessary precautions to prevent the lodgment of
dirt, plaster or trash in conduit, fittings and boxes during the course of installation. A
run of conduit, which has become clogged, shall be entirely freed of these accumula-
tions or shall be replaced. Open conduit ends shall be carefully closed during con-
struction to prevent foreign materials entering the conduit. Conduits, which have
3.9 CLEANING
A. Upon completion of installation of system including outlet fittings and devices, in-
spect exposed finished and remove burrs, dirt and construction debris and repair
damage finish including clips, scratches and abrasions.
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. CABLE TRAYS FOR ELECTRICAL SYSTEMS
CAIRO - EGYPT 260536 – 2874 0
SECTION 260536
Page
PART 1 - GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Submittals 2
1.4 Quality Assurance 3
1.5 Sequencing And Scheduling 3
1.6 Delivery,Storage And Handlines 3
PART 2 - PRODCUTS 3
2.1 Materials And Finishes 3
2.2 Sizes And Configurations 4
2.3 Cable Tray Accessories 4
2.4 Fire Stopping 5
2.5 Wiring Signs 5
2.6 Perforation Engineering 5
2.7 Cable Saddles 5
2.8 End Caps 5
2.9 Source Quality Control 5
PART 3 - EXECUTION 5
3.1 General 5
3.2 Installation 6
3.3 Grounding 7
3.4 Warning Signs 7
3.5 Field Quality Control 7
3.6 Cleaning 7
3.7 Protection 7
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including General and Supplemen-
tary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section covers cable trays and accessories as required by the contract.
B. Related Sections.
1.3 SUBMITTALS
C. Shop Drawings: To scale 1:50 detailing the installation of main cable trays, including
plans, sections, and attachment to other construction elements, to show the sup-
porting intervals and inside clearances as suitable to actual assigned cables and
weights as per selected manufacturer’s recommendations.
D. In general:
1. Where multi-core cables are installed in ventilated cable trays, the sum of the
diameters of all cables installed shall not exceed 90 percent of the cable tray
width and the cables shall be installed spaced in a single layer.
E. Coordination Drawings: Floor plans drawn to accurate scale. Show accurately scaled
cable tray layout and relationships between components and adjacent structural and
mechanical elements.
A. All cable tray and components shall be the product of a single manufacturer.
A. Contractor should coordinate layout and installation of cable trays with other trades
and installation. Revise location and elevations as required to suit field condition and
as approved by the Engineer.
A. Store indoors to prevent water or other foreign materials from staining or adhering
to cable tray.
PART 2 - PRODCUTS
A. Cable trays, fittings and accessories shall be post fabricated heavy gauge hot-dip gal-
vanized, manufactured from mild steel sheets of thickness not less than 2 mm for
above 400 mm width. Trays shall not present sharp edges, burrs or projections inju-
rious to the insulation or jackets of cables. Fixing brackets shall be hot-dip galva-
nized.
B. All cable tray sections shall be close return flange type, legibly and durably marked to
show the manufacturer name or logo.
C. Successful manufacturer shall have his logo engraved or bossed to the tray and a
strengthen means along the tray width by forming smooth left and right corrugation
in its base (not just 4 shape).
A. Sizes and configuration shall be as per table below and comply with IEC Code. Cable
trays shall carry the installed cable weight with an allowance for future cable load of
about 25% of the existing cable plus the weight of a tradesman standing at mid-span
on tray (about 80 kg) at the expected locations.
B. Ladder-Type Trays:
1. Width:
a. 100 mm
b. 150 mm
c. 200 mm
d. 300 mm
e. 400 mm
f. 600 mm
g. 800 mm
h. 900 mm
i. 1000 mm
C. Perforated-Type Trays:
1. Width:
a. 100 mm
b. 150 mm
c. 200 mm
d. 300 mm
e. 400 mm
f. 600 mm
g. 800 mm
h. 900 mm
i. 1000 mm
A. Cable tray fittings, bends, tips, etc., shall be supplied by the same cable tray manufac-
turer and from the same material and finishing as cable trays. Site fabricated acces-
sories shall not be accepted.
B. In selecting materials for use as fire stops, some important factors such as gas tight-
ness, poisonous gases or fumes developed during installation or during a fire, and
heat dissipation are to be considered. Spray coating of fire resisting material (30 min.
retarding) shall be applied on cables for at least 1.5 meter on both sides of the fire
stop barrier.
A. All visible cable trays shall have approved durable type conspicuously located warn-
ing signs reading "WARNING! NOT TO BE USED AS WALKWAY, LADDER, OR SUPPORT
FOR LADDERS OR PERSONNEL", and shall be readable at 8-meter distance. All warn-
ing signs shall be in Arabic / English. Sign's lettering shall be black on yellow back-
ground and 40 mm high.
A. The perforation details shall provide both adequate heat dissipation and adequate
strength or rigidity to the bottom and sides of cable trays.
A. Cable installed on trays shall be secured by means of PVC covered metal saddles.
Cable should be clamped to the tray at 3m intervals horizontally or 0.9m vertically.
A. Plastic end caps for cable trays and tray support shall be provided, to avoid personnel
injury.
PART 3 - EXECUTION
3.1 GENERAL
A. Provide cable trays with the indicated types and sizes as per the approved shop
3.2 INSTALLATION
A. General: Cable trays shall be installed (level and plumb) as indicated and according
to manufacturer's written instructions and reference standard. Cable tray shall be
supported at not more than 1.5 m intervals, and/or in accordance with Manufactur-
er's instructions and Engineer's approval. Supports for horizontal elbow trays fittings
shall be placed within 0.2 m of each fitting extremity. Remove burrs and sharp edges
of cable trays. Unless otherwise indicated, cable tray supports shall be securely fas-
tened to the building structure.
B. Installation Requirements:
1. Supports shall be designed to carry the greater of the calculated loads with an
allowance for future load about 25% of the existing weight plus a tradesman
standing at mid span on tray about 80 kg at the expected locations
2. Make connections to equipment with flanges fittings fastened to the tray and
to the equipment. Support the tray independently of fitting. Do not carry
the weight of the tray on the equipment enclosure.
3. Provide adequate supports for cables leaving or entering the tray individually
to prevent stress on cables.
4. Install expansion connectors in cable tray runs that exceed 30 m. Space con-
nectors and set gaps according to IEC.
5. Change in direction, elevation and cable tray connection shall be in accordance
with manufacturer's instruction and by standard fittings, of same manufactur-
er.
6. Locate cable tray above piping except as required for tray accessibility and
3.3 GROUNDING
A. After installation of cable trays is completed, install warning signs in a visible location
on or near cable tray according to the engineer instructions.
3.6 CLEANING
3.7 PROTECTION
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. IDENTIFICATION FOR ELECTRICAL
CAIRO - EGYPT SYSTEMS 260553 - 2874 0
SECTION 260553
Page
PART 1 - GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Submittals 2
1.4 Quality Assurance 2
1.5 Coordination 3
PART 2 - PRDOCUTS 3
2.1 Power Raceway Identification Materials 3
2.2 Power and Control Cable Identification Materials 4
2.3 Conductor Identification Materials 4
2.4 Underground-Line Warning Tape 5
2.5 Warning Labels and Signs 5
2.6 Instruction Signs 5
2.7 Equipment Identification Labels 6
2.8 Cable Ties 6
2.9 Miscellaneous Identification Products 6
PART 3 - EXECUTION 7
3.1 Installation 7
3.2 Identification Schedule 7
PART 1 - GENERAL
1.2 SUMMARY
A. Section Includes:
G. Instruction signs.
1.3 SUBMITTALS
A. Product Data: Submit product data for each electrical identification product
indicated.
B. Samples: Submit sample for each type of label and sign to illustrate size, colors,
lettering style, mounting provisions, and graphic features of identification products.
1.5 COORDINATION
PART 2 - PRDOCUTS
A. Comply with IEC and/or BS for minimum size of letters for legend and for minimum
length of color field for each raceway size.
1. Tape and Stencil for Raceways Carrying Circuits More Than 600 V: 100 mm
wide black stripes on 250mm centers diagonally over orange background that
extends full length of raceway or duct and is 300 mm wide. Stop stripes at
legends.
F. Metal Tags: Aluminum, 50 by 50 by 1.3 mm, with stamped legend, punched for use
with self-locking cable tie fastener.
A. Comply with IEC and/or BS for minimum size of letters for legend and for minimum
length of color field for each raceway and cable size.
B. Field –applied color coding method shall be used in addition to the factory code for
all the electrical cables and wires according to cover the following.
1. Color-Coding Conductor Tape: Colored, self-adhesive vinyl tape not less than
0.08 mm thick by 25 to 50 mm wide.
A. Tape:
D. Warning label and sign shall include for example, but are not limited to, the following
legends in English and Arabic languages:
A. Engraved, laminated acrylic or melamine plastic, minimum 1.6 mm thick for signs up
to 129 sq. cm and 3.2 mm thick for larger sizes.
A. According to the location of the installations and Engineer instructions one of the
following cables ties shall used.
B. General-Purpose Cable Ties: Fungus inert, self extinguishing, one piece, self locking,
Type 6/6 nylon.
C. UV-Stabilized Cable Ties: Fungus inert, designed for continuous exposure to exterior
sunlight, self extinguishing, one piece, self locking, Type 6/6 nylon.
D. Plenum-Rated Cable Ties: Self extinguishing, UV stabilized, one piece, self locking.
A. Paint: Comply with requirements in Division 09 painting Sections for paint materials
and application requirements. Select paint system applicable for surface material
and location (exterior or interior).
3.1 INSTALLATION
B. Location: Install identification materials and devices at locations for most convenient
viewing without interference with operation and maintenance of equipment.
C. Apply identification devices to surfaces that require finish after completing finish
work.
E. Attach signs and plastic labels that are not self-adhesive type with mechanical
fasteners appropriate to the location and substrate.
F. System Identification Color-Coding Bands for Raceways and Cables: Each color-
coding band shall completely encircle cable or conduit. Place adjacent bands of two-
color markings in contact, side by side. Locate bands at changes in direction, at
penetrations of walls and floors, at 15-m maximum intervals in straight runs, and at
7.6-m maximum intervals in congested areas.
G. Aluminum Wraparound Marker Labels and Metal Tags: Secure tight to surface of
conductor or cable at a location with high visibility and accessibility.
H. Cable Ties: For attaching tags. Use general-purpose type, except as listed below:
A. Concealed Raceways, Duct Banks, More Than 600 V, within Buildings: Tape and
stencil 100-mm wide black stripes on 250-mm centers over orange background that
extends full length of raceway or duct and is 300 mm wide. Stencil legend "DANGER
CONCEALED HIGH VOLTAGE WIRING" with 75-mm high black letters on 500-mm
centers. Stop stripes at legends. Apply to the following finished surfaces:
1. Floor surface directly above conduits running beneath and within 300 mm of a
floor that is in contact with earth or is framed above unexcavated space.
B. Accessible Raceways, and Cables, More Than 600 V: Install labels at 3-m maximum
intervals.
C. Accessible Raceways and Cables, 600 V or Less, for Service, Feeder, and Branch
Circuits More Install labels at 3-m maximum intervals.
D. Accessible Raceways and Cables within Buildings: Identify the covers of each junction
and pull box of the following systems with self-adhesive vinyl labels with the wiring
system legend and system voltage. System legends shall be as follows:
1. Emergency Power.
2. Power.
3. UPS.
G. Install instructional sign including the color-code for grounded and ungrounded
conductors using adhesive-film-type labels.
H. Conductors to Be Extended in the Future: Attach marker tape to conductors and list
source.
K. Warning Labels for Indoor Cabinets, Boxes, and Enclosures for Power and Lighting :
Self-adhesive warning labels or Baked-enamel warning signs according to the
Engineer instructions.
M. Emergency Operating Instruction Signs: Install instruction signs with white legend on
a red background with minimum 10-mm high letters for emergency instructions at
equipment used for power transfer, load shedding and other emergency operations.
1. Labeling Instructions:
2. Equipment to Be Labeled:
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. MEDIUM-VOLTAGE DRY TYPE
CAIRO - EGYPT TRANSFORMER 261202 – 2874 0
SECTION 261202
Page
PART 1 - GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Related Sections 2
1.4 Submittals 2
1.5 Warranty 3
1.6 Quality Assurance 3
1.7 Delivery, Storage, And Handling 3
1.8 Coordination 4
PART 2 - PRODUCTS 4
2.1 Dry-Type Distribution And Power Transformers 4
2.2 Identification Devices 6
2.3 Source Quality Control 7
PART 3 - EXECUTION 7
3.1 Examination 7
3.2 Installation 8
3.3 Identification 8
3.4 Connections 8
3.5 Field Quality Control 8
3.6 System Validation 9
PART 1 - GENERAL
1.2 SUMMARY
A. This Section includes the Dry type transformers with medium-voltage primary 24kV
and secondary no-load low- voltage at principle tap is 400 V, 50 HZ and according to
IEC 60076-11.
B. The Contractor is responsible to supply and install the transformer (s) according to
the latest requirements of the Electrical Distribution Company. This shall require
from the contractor’s manufacturer to obtain the approval (before delivering) for the
type, voltage, losses, etc. from Electrical Distribution Company. Any additional
requirements shall be considered without any extra cost to the Contract even if these
requirements are not clearly mentioned in these specifications.
C. The contractor is responsible to supply and install the transformer (s) with the rating
indicated on the drawings at the ambient conditions mentioned in the specifications
without applying any derating factors.
A. The following sections include, but not limited to, requirements which relate to work
of this section:
1.4 SUBMITTALS
C. Coordination Drawings: Floor plans, drawn to scale, on which the following items are
shown and coordinated with each other, based on input from installers of the items
1.5 WARRANTY
A. The Maintenance Period for the equipment and appurtenances shall begin when the
performance test on the equipment and appurtenances has been successfully
completed and preliminary accepted as stipulated in the Conditions of Contract.
B. Reference Standards
1. IEC 60076-1
2. IEC 60076-3: Part 3: Insulation levels, dielectric tests
3. IEC 60076-10: Part 10: Determination of sound levels
4. IEC 60076-11: Part 11: Dry Type Transformer
5. IEC 60076-12: Part 12: loading guide for Dry Type Transformer
6. IEC 60085 Thermal evaluation and classification of electrical insulation.
7. IEC 60137 Bushings for alternating voltages above 1000V
8. IEC 60364: Electrical Installations.
A. Store transformers protected from weather and so condensation will not form on or
in units. Provide temporary heating according to manufacturer's written instructions.
1.8 COORDINATION
A. Coordinate size and location of concrete bases. Cast anchor-bolt inserts into bases.
Concrete, reinforcement, and formwork requirements are specified in Division 03.
PART 2 - PRODUCTS
B. Primary Connection: Fully enclosed cable end box on high voltage side.
F. Average winding Temperature Rise above ambient temperature at rated current: 100°C
K. Climate Class: C1
L. Environmental Class: E2
M. Fire Class: F1
Q. Core: The cores of the transformer shall be built-up from best quality, low losses,
high permeability cooled rolled grain-oriented stress relieved steel laminations non-
aging silicon steel, insulated on both sides as per Electrical Distribution Company
requirements.
R. Windings: HV and LV Windings shall be of Aluminum conductors with low losses and
then cast separately in molds as per Electricity Company requirements according to
transformer rating. Conductors insulated with high dielectric strength tapes having
very good temperature stability and be firmly braced so as not be loosen due to short
circuit.
T. Transformer Losses: The maximum acceptable values for transformer losses shall be
according to the following tables:
V. Permissible Overload: 10% for 1 hour without undue heating and without any forced
cooling fans support.
Y. in case of installing any equipment within the transformer room a wire mesh gate
access shall be installed to make a separation between the transformer and any live
equipment) and according to engineer approval.
Z. Accessories:
A. Reference Standards:
D. Prior to shipment the Contractor should submit all test certificates mentioned in item
A and B for review and approval.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Inspect each transformer and related accessories for damage, defects and
completeness before installing.
B. Examine areas and conditions for compliance with requirements for medium-voltage
transformers.
D. Examine walls, floors, roofs, and concrete bases for suitable mounting conditions
where transformers will be installed.
3.2 INSTALLATION
3.3 IDENTIFICATION
A. Identify field-installed wiring and components and provide warning signs as specified
in Division 26 Section "Identification for Electrical Systems."
3.4 CONNECTIONS
B. Perform the following field tests and inspections and prepare test reports:
B. Simulate malfunctions to sound alarms. Check all systems thoroughly for correct
operation. Test equipment for this function shall be furnished by the Contractor.
C. Immediately correct all defects and malfunctions disclosed by tests. Use new parts
and materials as required and approved and retest. Provide a report certifying
completion and validation of each system.
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. RING MAIN UNIT
CAIRO - EGYPT 261301 - 2874 0
SECTION 261301
Page
PART 1 GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Submittals 2
1.4 Quality Assurance 3
1.5 Coordination 3
1.6 Delivery, Storage And Handling 4
1.7 Warranty 5
1.8 Instructions And Training On Operation And Maintenance 5
PART 2 PRODUCTS 5
2.1 Manufacturers 5
2.2 Performance And Design Requirement 5
2.3 Components 5
2.4 Accessories 10
2.5 Fabrication 10
2.6 Voltage Presence Indicators (Vpi) 10
2.7 Fault Passage Indicator 11
PART 3 EXECUTION 11
3.1 Installation 11
3.2 Field Quality Control 11
PART 1 GENERAL
1.2 SUMMARY
A This section covers Ring Main Unit which shall be furnished and installed as specified
herein and as indicated on the drawings.
B Equipment furnished and installed under this section shall be fabricated, assembled,
erected, and placed in proper operating condition in full conformity with the
drawings, specifications, engineering data, instructions, and recommendations of the
equipment manufacturer unless exceptions are noted by the Engineer.
C During tendering, the Contractor shall select one of the manufacturers whose is
capable of delivering Ring Main Unit which fulfill the requirement of electrical
distribution company (EDC) and had previous approvals of similar types. By this
awareness the manufacture shall give the correct quotation for the required
Equipment including EDC requirements during tendering.
D Before delivery, the Contractor is responsible to obtain the approval for the
manufacturer, type, voltage, protection devices, meters, etc. from the electrical
distribution company whose additional requirements shall be considered even if
these requirements are not clearly mentioned in these specifications.
1.3 SUBMITTALS
A Drawings and Data: Complete drawings, details, and specifications covering the
equipment furnished under this section shall be submitted.
B Complete and accurate drawings of the equipment, including plan, front, and
sectional or side views, and base plans showing anchor bolt locations and base
details, shall be provided.
C Within 90 days after the Notice to Proceed, the Contractor shall furnish outline
drawings and dimensional data which fully describe the projected floor space
required for the equipment; the absolute minimum working space required at the
front, rear, and sides of the equipment; the equipment height; and the equipment
weight.
1. 62271-200 A/C Metal Enclosed Switchgear and Control Gear for Rated
Voltages Above 1 kV and up to and Including 52 kV
2. 62271-102: Alternating current and earthing switches
3. 62271-103: Switches for rated voltage above 1 KV up to and including 52 KV.
4. 62271-1: Common Specifications for HV Switchgear & Control Gear Standards
5. 62271-105: Alternating current switch-fuse combination).
6. 60255: Measuring relays and Protection equipment’s
7. 60529: Degree of Protection
C Manufacturer’s Experience: Each Ring Main Unit (RMU) shall be a product of RMU
manufacturer who has designed, fabricated, and furnished equipment of the type
and size specified which has been successfully installed for a period of not less than
five or ten years.
D Shop Tests: All standard factory tests, including quality control tests, shall be
performed on the RMU. Four certified copies of test results shall be submitted to
the Owner Representative before the equipment is shipped.
1.5 COORDINATION
A All equipment specified under this section shall be furnished by or through a single
manufacturer who shall be responsible for the design, coordination, testing, and
satisfactory performance of all the components.
F Protective relay coordination curves for each relay provided as a part of the unit
substation assembly.
G Protective fuse curves for each current-limiting fuse provided as a part of the RMU
assembly.
H Within 28 days after the return of the initial equipment shop drawing submittal, the
equipment manufacturer shall provide the above information to the Contractor in
accordance with Section 260500, Electrical Materials and Method.
A Delivery Schedule: Delivery schedule of the RMU shall be coordinated with the
Engineer and the Contractor. A copy of all correspondence and memoranda
regarding delivery of each RMU beyond point of manufacture to the construction
sites shall be submitted as required at the Conditions of Contract.
D In additions to the protection specified for prolonged storage, the packaging of spare
parts (If Any) shall be prepared for export packing and shall be suitable for long-term
storage in a damp location. Each spare item shall be packed separately and shall be
completely identified on the outside of the container.
A The Maintenance Period for the equipment and appurtenances shall begin when the
performance test on the equipment and appurtenances has been successfully
completed and preliminary accepted as stipulated in the Conditions of Contract.
A Contractor shall provide instructions and training for the staff to be assigned in the
operation and maintenance of the equipment specified under this section. Training
and instructions shall be in accordance with the requirements set forth at the
Conditions of Contract.
PART 2 PRODUCTS
2.1 MANUFACTURERS
A System Characteristics: The system will be rated at (24) KV, 3-Phase, 50 Hz. The
approximate fault current shall be 750 MVA unless otherwise as shown on the
drawing.
B Station Criteria:
a. Two incoming with SF6 Load break switches with earthing switch
mechanically interlocked. With rating as indicated in the drawings.
b. One outgoing with SF6/Vacuum Circuit breaker for feeding the
transformers with rating as indicated in the drawings.
b. Earth leakage indicator with Ferranti C.T.
c. Complete with bus bars and supporting insulators
d. Metering cell ready to install all meters required by Electrical
Distribution Company (EDC).
2.3 COMPONENTS
A RMU Enclosure: Enclosure shall be made of steel sheet 2.5 mm thick before paint
and treated against rust and provided with priming, intermediate and finishing coats
of electrostatic painting powder from inside and outside.
E All bus bars shall be electrical copper, Air insulated, mounted on support insulators
enough to withstand mechanical forces which may happen due to short circuit 20 kA
R.M.S for 3 sec.
F Each switch compartment shall be equipped with suitable clamp or any other mean
for supporting and fixing the cable or end box.
G Each switch board shall be supplied with a detachable insulated operating handle ≥
650 mm.
I Detailed drawings and technical specifications shall be attached with the offer.
1. Load break switch and its mechanically interlocked earthing switch shall be SF6
insulation.
2. Shall be maintenance -free, the position of the power contacts and earthing
contacts shall be clearly visible on the front of the switchboard. The position
indicator shall provide positive contact indication.
3. The switches shall have 3 positions, open-disconnected, closed and earthed,
and will be constructed in such a way that natural interlocking prevents
unauthorized operations.
4. The switches shall be fully mounted and inspected in the factory.
5. Manual opening and closing will be driven by a fast-acting mechanism,
independent of operator action.
K Circuit-breakers:
13. Circuit breaker shall be rated at 750 MVA at 22kV rating nominal 3-phase class
with a normal continuous current rating as sown on Drawing’s bus. Breaker
shall be rated at least 20 kA RMS symmetrical at 22 KV and shall have a closing
and latching capability of 62.5 kA. Rates shall be referred to withstand short
circuit for three (3) seconds. Operating cycle shall be as a follow (0-0.3 sec-
CO-15 secs-CO). Automatic reclosure shall not be required.
N Specifications and tests shall comply with IEC 62271 for cable switch disconnectors
(L.B.S.).
P The earthing switch shall be manual operated with mechanical lock which prevents
its switching while the main switch is on.
R The rated short-time withstand current of the earthing switch shall be at least equal
to that assigned to the disconnectors (L.B.S.)
S The peak withstand current of the earthing switch shall be at least equal to that
assigned to the disconnectors (L.B.S.)
T Cable L.B.S. shall also fulfill the conditions for isolating distance acc. To IEC 62271-
102 prescribed for isolators.
U At the side of the fused switch compartment shall be the outlet of 3 single or multi
core XLPE cables. That side shall be equipped with an insulating backelite plate with
three holes to pass the XLPE cables outside to the transformer. The level of this
backelite plate shall be ≥ 200 mm over the bottom, from outside, the place of the
backelite plate shall have a cover of the same sheet steel bolted with detachable
bolts. Depth of cover ≥ 22 cm.
V Contractor shall submit type tests certificates for the offered equipment’s according
to IEC.
W Routine tests shall be in accordance with IEC and shall be attended by Employer’s
representative(s).
X Earth Fault Indicators: 220 V, 50Hz, Automatic reset type complete with Ferranti
current transformer which will be erected around the cable sheath, according to the
specification.
Y Current Limiting Fuses: (22) according to project KV H.R.C. FUSES (if required)
AA A powder filled fuse-link shall not emit flame or powder although a minor emission
of flame from a striker is permissible, provided this does not cause breakdown or
significant electrical leakage to earth.
BB After the fuse has operated, the components of the fuse apart from these intended
to be replaced after each operation shall be in the original state. It shall be possible
to remove the fuse-link in one piece after operation.
Ring Main Unit Section 261301
Urbanium New Administrative Building (Prj. 2874) Sheet 8 of 12
CC Strikers shall comply with the requirements specified in Sub-clause 18.3 of IEC
60282-1.
EE After operation, the fuse shall be capable of withstanding the power frequency
recovery voltage across its terminals.
FF Fuse Ratings:
GG Features Required:
1. The fuse links shall have the dimensions as per attached spec.
2. The fuse link contacts shall be silver plated.
3. The fuse link body shall be of porcelain.
4. On each fuse link the badge of the Employer shall be printed.
5. Each fuse link shall be equipped with a striker which complies with Sub-clause
18.13 of IEC 62271
1. Current Transformers (CT's): Class 0.5 for metering and class 5P10 for
protection n10.
2. Potential Transformers (PT's): Class 0.5 for metering (first core) and class 3P
for protection (second core).
JJ All potential transformers shall be provided with current limiting fuses. Voltage
rating for the secondary winding shall be of ratios:
KK The thermal rating of the transformers shall be sufficient to provide the total current
required to operate the burdens on the secondaries without exceeding the rating of
transformer as indicated on nameplate. PT's (1 per phase) shall be installed either as
a unit drawout assembly or with an isolating switch in a separate compartment so
that the transformers, primary fuses and secondary circuits may be inspected and
tested in a completely de-energized condition.
LL CT's shall have mechanical and thermal rating equal to the rating of the LBS.
Secondary rating shall be 5 amperes and primary ratings shall be as shown on one-
Ring Main Unit Section 261301
Urbanium New Administrative Building (Prj. 2874) Sheet 9 of 12
line diagram. Transformer shall be capable of carrying 120 percent of rated current
for one hour. Ground current sensing transformers shall have a one ampere
secondary current.
MM Control switches shall be the rotary enclosed type with positive means for
maintaining contact position.
2.4 ACCESSORIES
A Signage: Each RMU shall have engraved laminated nameplates screwed to the doors
of each individual compartment and wiring diagrams pasted inside each door.
B Each RMU shall be furnished with a sign marked “DANGER - HIGH VOLTAGE”. Letters
shall not be less than 25mm high, 6 mm stroke. Signs shall be laminated plastic, red
letters with a white background.
C All compartments with voltages from sources outside of the compartment shall have
a sign on the compartment door marked “CAUTION - THIS UNIT CONTAINS A
VOLTAGE FROM A SOURCE OUTSIDE OF THIS UNIT”. Letters shall be black on a high
visibility yellow background. Signs shall be adhesive backed vinyl approximately
75mm by 125mm.
D All nameplates and signage shall be printed in both English and Arabic.
2.5 FABRICATION
A Surface Preparation: Remove all casing projections, weld flux, or splatter by hand
scraping, hand impact tools, etc., followed by wire brushing or power grinding.
Sharp corners or sheared edges shall be dulled and radiused with power grinder to
improve paint adherence.
B Exposed grooved surfaces shall be finished smooth by filling and thoroughly cleaned
as required to provide a smooth uniform surface for painting.
C Shop Painting: Unless galvanized surfaces are provided, all ferrous metal surfaces
shall be painted with a prime coat and given two or more finish coats of paint.
A Each RMU function shall be equipped with a Voltage Presence Indicator (VPI) on the
front cover to indicate whether there is voltage in the cables.
C Cable connection bushings shall be equipped with capacitive dividers that will supply
low voltage power to the voltage presence lamps.
D The lamps shall be of high performance LED technology to insure high visibility and
long life duration. Three voltage sensing inlets shall be provided on each function to
allow checking the phase concordance.
Ring Main Unit Section 261301
Urbanium New Administrative Building (Prj. 2874) Sheet 10 of 12
E It shall be possible to replace the voltage presence indicator while unit remains
energized, guaranteeing the safety of people.
A Each of the two Incoming Load break switches shall be equipped with a fault Passage
indicator
B The voltage signal shall be taken from the Voltage Presence Indicator (VPI)
connected to capacitive divider in each load break switch cable bushing.
C The voltage detection device shall display the MV network voltage. It is not allowed
to use a voltage measuring tool to calibrate the device.
D The fault passage indicator function is used to detect and localize the faulty part of
the network.
E It shall indicate short circuit and earth faults with a high performance red LED on the
front panel.
F It shall indicate permanently the load currents of each phase and memories the maxi
meters of each phase.
H In order to guarantee a fault validation on cable with low load value, a validation by
voltage presence shall be provided.
PART 3 EXECUTION
3.1 INSTALLATION
A The RMU base assembly comprises the preformed concrete sump to which are fixed
2 opposing sheet steel support trays. The steel support trays, which overhang the
concrete sump, serve to support and secure RMU together with the external
extremities of the cable entry compartments.
A Test and Checks: The following minimum test and checks shall be performed before
energizing the substation.
B Megger terminals and buses for grounds after disconnecting devices sensitive to
megger voltage.
Ring Main Unit Section 261301
Urbanium New Administrative Building (Prj. 2874) Sheet 11 of 12
C Remove all current transformer shunts after completing secondary circuit.
G Tests Certificate
1. Type test certificates shall be submitted with the offer (if not before
submission) including:
H OWNER may require its representative(s) to attend some or all of the routine tests
acc. to same above IEC publications.
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. LOW VOLTAGE SWITCHBOARDS
CAIRO - EGYPT 262413- 2874 0
SECTION 262413
Page
PART 1 GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Submittals 2
1.4 Warranty 4
1.5 Quality Assurance 4
1.6 Delivery, Storage And Handling 4
PART 2 PRODUCTS 4
2.1 Manufacturers 4
2.2 General 5
2.3 Connection To Building Management System (Bms) 7
2.4 Communication 7
2.5 Switchgear 7
2.6 Incoming Supply And Outgoing Circuits 9
2.7 Circuit Breakers 9
2.8 Power Air Circuit Breakers (Pacbs) 11
2.9 Instrumentation And Controls 13
2.10 Mcc Special Requirements 14
2.11 Surge Protection Device (Spd) 14
2.12 Factory Testing 14
PART 3 EXECUTION 15
3.1 Inspection 15
3.2 Preparation 15
3.3 Electrical Work 15
3.4 Mounting 15
3.5 Installation Supervision 15
3.6 Field Testing 16
3.7 System Validation 16
PART 1 GENERAL
A. Drawings and General Provisions of the Contract, including General Conditions, Con-
ditions of Particular Application and Division-1 Specification Sections, apply to work
of this Section.
1.2 SUMMARY
A. This section covers low voltage metal enclosed switchgear as indicated on the Draw-
ings and required by the Contract and shall include the following items:
1. Switchboard
2. Distribution Boards
3. Branch Circuit Panelboards
B. Related Sections
1. The following sections of work contain requirements that relate to this Sec-
tion:
a. Division 25 Section “Building Management System”
b. Division 26 Section “Basic Electrical Materials and Methods “
c. Division 26 Section “Grounding and Bonding “
d. Division 26 Section “Package Engine Generator “
e. Division 26 Section “Power Factor Correction Equipment “
f. Division 26 Section “Panelboards “
1.3 SUBMITTALS
A. Submit the following in accordance with the Conditions of the Contract and Division-
1 Specification Sections.
Studies:
5. Provide thermal stress limitation checks for all breakers and cables as per
Test Programs:
C. Equipment Data: The equipment data to be provided by the Contractor prior to or-
dering any material covered by this Section shall include but not be limited to:
1. Plans, front, rear and side elevations, with indication of all face-mounted
equipment exact dimensions and weights.
2. Drawings of arrangement of equipment inside the board.
3. One line schematic diagram of circuits.
4. Control circuit diagram, showing all auxiliary contacts remote control, if any,
and remote indication.
5. Indication of arrangement of main incoming feeders and outgoing feeders
(bus-bars or cables).
E. The Contractor shall submit the Main Distribution Boards (MDB) according to the lat-
est requirements of the Egyptian distribution Company (EDC) for approval before
manufacturing.
Any additional requirements shall be considered without any extra cost to the Con-
tract even if these requirements are not clearly mentioned in these specifications.
EDC shall witness the factory testing for the MDB and approved before shipment to
site.
A. Contractor shall agree to repair or replace the equipment that does not comply with
the requirements or fails in work.
A. Reference Standards
1. The work and equipment of this section shall be designed, manufactured and
design verification in accordance with the International Electro-Technical
Commission (IEC) or other approved equivalent International Standards.
2. International Electro-Technical Commission IEC 61439.
A. Shipments shall be securely packed for delivery and transit, protected against exces-
sive heat and humidity and waterproofed for protection against water damage.
When material must be bundled due to excessive size each bundle shall have a tag,
made of metal, securely tied on with heavy gauge wire. Purchaser's markings shall
be die-stamped on the tag.
B. Equipment, relays, and other components with moving or fragile parts shall be
properly blocked, tied or packed to prevent damage.
C. Any component shipped separately shall be clearly marked with description, use and
installation instructions.
D. All packages shall be marked with equipment tag number for identification when
shipped and when received at site.
F. Each shipping unit shall be equipped with shipping angles or lifting lugs for handling
by crane.
PART 2 PRODUCTS
2.1 MANUFACTURERS
A. Materials and equipment shall be new and completely assembled, wired and tested
at the factory requiring only field installation and connection of power and control
circuits to place the equipment in service, except for multi-unit switchgear which
could be divided into shipping section after being completed and tested at the facto-
ry.
E. Index of protection for all Switchboards according to IEC 60529 unless otherwise in-
dicated on the drawings and schedules shall be as follow:
F. Switchgear shall be metal enclosed, form (2b) type as per IEC 61439, complete with
stationary structure, have complete bussing and front access apparatus described
herein.
G. Provide a dead hanged front panel behind the door of a distribution board, to allow
safe operation. This front panel shall carry the required tags of equipment to show
function of each breaker inside or any push-button, etc.
H. The Contractor shall make sure that the space for each switchboard is available in ac-
cordance with the requirements for the installation and operation and maintenance
of the equipment as specified and supplied by the Manufacturer, and as per IEC
60364, 61439. Any inaccuracy in the building shall be corrected as required and di-
rected by the Engineer, and at no extra charge to the Employer.
I. Ratings are shown on the one-line diagrams and the panel details and should be
checked based on the actual loads at no extra cost to the Employer.
J. The switchgear shall contain equipment with ratings as indicated on the one line dia-
gram, panel details, and in this Specification.
L. All ratings shown on the one line diagrams are the required operational equipment
ratings at the ambient temperature. It shall be the Contractor's responsibility to en-
sure that the equipment furnished satisfy the ratings shown without any extra cost
to the Employer.
M. The Contractor shall assume all responsibility for mechanical and electrical coordina-
tion of equipment and devices required by the Drawings and Specifications.
O. The prospected short circuit current (Isc) value indicated at each bus-bar on drawings
shall represent the maximum 3-phase symmetrical R.M.S. kA, and it is the rating that
all switchboard components (i.g. bus, bars, bolts, circuit breakers, etc. shall with-
stand.
P. Buses shall be 99.9% electrolytic copper of sufficient size to limit temperature rise to
values according to IEC 61439.
S. Forced Ventilation should be used according to design guide of the original equip-
ment manufacturer in order to maintain the internal temperature within the design
limit.
T. The phase arrangement on 3-phases buses shall be R.S.T from front to back, left to
right, or top to bottom from the front of the switchboard.
U. All switchboard components shall be of the same manufacturer and must be tested
according to IEC standards. The assembly must be design verification and fully coor-
dinated.
V. All switchboard doors shall have a key lock and indicating lamp for ON/OFF-READY, in
addition to the necessary equipment for security identification.
W. All indicating lamps used in the switchboards should be semi-conductor LED diodes.
Use of neon or incandescent indicating lamps is not acceptable.
X. All indicating lamps and pushbuttons should be chromatid metallic base and body.
Y. All panel access doors shall be provided with a master key for maintenance and op-
eration.
Z. Main circuit breakers of the MDB shall be provided with smart interface module SIM
for the circuit breakers as indicated on the drawings .
AA. The panel shall be designed to permit continuous operation of all components
mounted therein with panel ambient temperatures of up to 40C for indoor installa-
tion and 45C for outdoor installation.
BB. Digital power meters for Main switch boards shall be provided as indicated in single
line drawings
A. coordinate with the Building Management System (BMS) supplier and provide all
necessary interface devices using smart panel communication concept as shown in
drawings and BMS schedules.
2.4 COMMUNICATION
As Indicating in the drawings, the switchboard shall be equipped with a Smart inter-
face module that makes it possible to:
1. Monitor modular protection, control units and trip units natively and provide
the centralized management system (BMS, supervisor, management software,
etc.) with information on their status and measurements.
2. Transmit orders from the centralized power manager system to the switch-
board control units
3. Transmit real time measurements, status, and trips with Modbus TCP/IP pro-
tocol to a management software database.it shall have embedded Ethernet
port and the data to be ready to be processed and displayed on its embedded
web server.
2.5 SWITCHGEAR
A. Apparatus: All auxiliary equipment, transition sections, bus duct, and other neces-
sary components required for complete installation and proper operation, under TN-
S distribution system, although not specifically listed herein, shall be furnished and
included in the switchgear assembly.
B. All circuit breakers of the same type and rating shall be completely inter-changeable
between compartments and between units at different locations on the site.
C. All doors, panels and cubicles in general, shall be sealed with neoprene or equivalent
gaskets. Enclosure shall be dust and vermin proof. Provide a directory of circuits on
inside cable compartment.
D. Fuses (if applicable) shall be of the same manufacturer, dual elements current limit-
G. All live conductors behind doors should be protected against accidental contact by
use of transparent plexi-glass sheet marked with an electrical shock warning label.
H. Fuses or miniature circuit breakers shall be provided so that relays, controls and in-
struments may be isolated whilst other essential circuits are kept energized. Accord-
ingly the control circuit should be divided into two separate circuits (indicators cir-
cuit) and (circuit breakers control circuit).
I. Supply of any control shall be via a suitably sized control transformer (at least three
times the VA rating of all connected devices). Control circuits which are fed directly
from the busbar will not be accepted. The control transformer shall be protected at
its primary and secondary sides by HRC fuses of suitable size.
J. Main Bus: The main bus shall be made of 99.9% pure copper and shall be continuous
current ratings as indicated on the Drawings or shall be of equal rating to the maxi-
mum setting of the protective device on the incoming side whichever is greater.
K. All bus-bars shall be fully rated and extend with the same size along the entire length
of the switchgear assembly.
L. Short-circuit Duty: Bus bars are to carry at least 125% of the maximum short-circuit
level at point of application for one second, without showing any signs of degrada-
tion.
M. All horizontal bussing shall have provisions for future extension on either end.
N. All main bus connections shall be tight, corrosion-free and with sufficient bolts to
withstand the symmetrical fault currents indicated on the Drawings.
O. The bus-bar supports shall be formed of high strength, low moisture absorbing, high
impact material with ample creepage distance between bus-bars. Bus-bars shall be
braced to withstand the symmetrical fault currents indicated. All busbar bracing ma-
terials should be of a non-magnetic material.
P. All bus-bars and tap connections shall be connected in such a manner that initial con-
tact pressure remains substantially undiminished at bus temperatures ranging from
indicated rated ambient to rated full load temperatures, to maintain minimum con-
tact resistance for the full service life of the equipment.
Q. Vertical Bus: All vertical bus-bars shall be of same material of main bus and shall
have sufficient capacity to supply all installed circuit breakers and each vertical sec-
tion shall have full height and depth, fire stop barriers of approved fire resistant ma-
terial.
R. Vertical bus compartment shall be completely enclosed and isolated from other
components.
T. Neutral Bus: Neutral buses shall be sized for the same capacity of the main bus and
shall be of copper.
U. The neutral bus shall be separate and isolated from the ground bus and completely
insulated from ground. A removable bus link shall be provided for grounding the
neutral bus as shown on Drawings.
W. Ground Bus: A solid copper ground bus shall extend along the full length of the
switchgear and rigidly bolted to the switchgear lower part compartments, frame and
all sections of structure.
A. Source: Incoming supply shall be 380 volts, 3-phase, 5 wire, 50 Hz, with symmetrical
fault current level available at the incoming line terminals as indicated on Drawings.
B. The connections from the incoming line terminals to the main bus shall have the
same capacity as the main horizontal bus.
D. If the incoming power supply is shown as cables a removable metallic gland plate
with thickness of not less than 5 mm shall be fixed to the top or bottom or both sides
of the panel depending on the direction of the cables. A non-ferrous material must
be used in case of single core conductors. Pressure lugs shall be provided for the
termination of cables, whose sizes are as shown on the one line diagrams.
E. Outgoing Circuit by Cables: All outgoing feeder sizes shown on Drawings are consid-
ered a minimum and the Contractor shall adjust without any additional cost to con-
form to the IEC 60364 Regulations after final equipment selection, same gland plates
mentioned above will be applicable.
A. Main incoming, bus tie circuit breakers shall be four-pole, single-throw, motorized
circuit breaker with continuous current ratings as shown on the one-line diagram and
wiring schedules.
B. All breakers above or equal to 1600A must be air-type and as indicated in the draw-
ings.
C. As a general rule All breakers above 1600A must be electrically motorized unless
otherwise indicated on drawings
D. Unless otherwise indicated all incoming and coupler breakers must be withdrawable
E. All automatic source change over (ATS) schemes must have mechanical interlocks in
addition to electrical interlocks.
F. Three (3) phase outgoing circuit breakers shall be Three (3) pole molded case, Three
(3) pole miniature circuit breakers or combined with residual current devices four (4)
pole as shown in the single line diagram or in panel schedules.
G. All four (4) pole circuit breakers must have neutral protection accordingly their trip
units should be able to sense the current on all four (4) poles. The trip unit should al-
low a separate setting for the neutral pole to select one of three settings (neutral
unprotected), (neutral protected at 50% phase current) and (neutral protected at
100% of phase current).
H. Circuit breakers shall be selected in line with this specification at the point of applica-
tion in accordance with the drawings, allocated spaces and the "Regulations" as ap-
plicable and shall be suitably graded for 660 volt line service.
I. Circuit breakers serving as generator incoming must be fitted with a generator class
trip unit capable of achieving low settings suitable to generator applications.
K. Each pole of the circuit-breaker shall have an inverse-time delay over current protec-
tion for small overloads and an instantaneous magnetic overcurrent trip element for
operation under short circuit conditions. All poles shall be constructed to open, trip
or close simultaneously.
L. Circuit breakers shall be provided with quick-make, quick break switching mechanism
and positive trip-free operation so that contacts cannot be held closed against excess
currents under manual or automatic operation. Contacts shall be non-welding silver
alloy and shall be adequately protected with effective arc-quenching devices.
M. The service short-circuits breaking capacity of the molded case circuit breaker which
is 100% of ultimate short current shall be in accordance with IEC 60947-2 and shall
be equal to the same value of short circuit level (Isc) indicated on Drawings. Switch-
board and components withstanding rating shall be equal to this short circuit level
also.
N. The miniature circuit breakers shall be rated 10 kA breaking capacity as minimum un-
less otherwise specified, with terminals capacity up to 25 mm2.
O. All miniature circuit breakers should have protection shoulders against accidental
contact with their terminals.
P. When tripped by either the thermal or magnetic elements, the handle shall automat-
R. Non-interchangeable trip breakers shall have their covers sealed and breakers with
interchangeable trips shall have the trip unit sealed to prevent tampering.
S. All incoming and outgoing circuit breakers in the same switchboard shall be totally
selective at the prospected short circuit level.
T. Molded case circuit breakers shall have trip units that achieve full selective system
for overload, short circuit and instantaneous protection.
U. Circuit breakers of rating 250 Ampere and above shall have electronic trip unit.
W. Combination of circuit breakers and ground fault circuit interrupters shall be used
wherever specified with a fault indicator lamp. It shall be instantaneous trip with a10
mA, 30 mA and 100 mA sensitivity setting unless otherwise indicated.
X. All circuit breakers shall be derated according to climatic conditions and operating
temperature as per manufacturer standards.
A. Type: Encased in high strength, high temperature resistant, molded plastic insulating
materials, for normal operation at maximum temperature within enclosure at point
of application, tested to approve standards, manually operated for normal functions,
and automatically tripped under over-current conditions. Trip power is to be derived
from main power circuit, with sufficient tripping energy to reliably trip circuit break-
er. Fixed mounted circuit breaker is to be rear connected.
C. Control Power: For electrically charged circuit breaker and/or for shunt trip device,
where required, control power is to be obtained from in-built MDB control power
transformer connected and fused on line-side of circuit breaker. Where shunt trip
D. Rating: 4-pole, unless otherwise shown on the drawings. 750 V rated insulation volt-
age class, with continuous current rating (frame size) as per the approved design and
calculations, ranging between 1600 A and 5000 A (1600, 2000, 2500, 3000, 4000 and
5000 A), fully rated (100%) for service under worst site conditions. Breakers are to be
rated for a symmetrical RMS service short-circuit breaking capacity as per the ap-
proved design and calculations, to IEC 60947-2 sequence II (rated service short-circuit
breaking capacity) at specified voltage and frequency, meeting IEC60947-2, sequence
I, II, III and IV tests (for circuit breakers of utilization category B), tested in an enclo-
sure substantially the same as the enclosure in which they are to be installed.
E. Trip Unit: Totally enclosed, programmable, solid state device, interchangeable for
compatible frame sizes, pluggable into front of circuit breaker, tamper-proof and
with transparent, sealable cover. Trip unit is to measure sinusoidal and non–
sinusoidal current wave forms (fundamental to thirteenth harmonic) by continuously
sampling each phase throughout every cycle. Trip unit is to be direct acting trip de-
vice, current transformer operated, with flux transfer shunt trip that requires no ex-
ternal power. It is to have adjustable current setting (0.5 - 1.0 times trip unit rating)
with adjustable long-time delay, short-time pick-up and short-time delay, earth-fault
pick-up and time delay instantaneous over current pickup. Current setting range is to
be by means of replaceable trip-units within the maximum frame size rating. Once
removed, circuit breaker is to remain in the trip-free position. Short time delay is to
be adjustable in steps, with pre-settable or adjustable time band having maximum
delay of 0.3 to 0.5 seconds. Instantaneous trip is to be adjustable in steps at least 2 –
13 times the trip Unit rating. Over-ride protection is to allow full sensitivity up to in-
terrupting capacity of Circuit Breaker.
G. Trip Unit Status Display: Shall indicate in words the status of normal breaker opera-
tion, long time over current pick up, instantaneous time over current trip, short time
over current trip, ground fault trip. Unit shall have integral resettable counter to
count long time, short time, instantaneous and ground fault trips.
H. Position Indicators: Positive with trip indication target. Target indicator is to be me-
chanical and is to give indication even when control power has been lost.
I. Neutral Current Transformer: Provide on the neutral conductor of each main, tie or
outgoing circuit having earth fault protection. Rating and characteristics of the neu-
tral current transformer are to be suitable for proper operation of the earth fault
protection system.
K. Auxiliary Contacts: Include N.O. and N.C. contacts on switchgear as required for re-
mote monitoring and control, plus 2 N.O. and 2 N.C. spare contacts.
L. Electrical Interlock: If electrical interlock is required between power air circuit break-
ers (as shown on the drawings), the mechanical closing button of the circuit breaker
is to be disabled in the connect position and an additional electrical push button is to
be provided for the closing of the circuit breaker through the breaker’s shunt close
coil. The electrical interlock is to be provided on both shunt trip and close coils of the
circuit breaker in order to perform simultaneous tripping and inhibit closing functions
on the interlocked breaker.
A. All instruments, relays and components as contained in the one-line diagrams speci-
fied herein or required by manufacturer’s standard practices, shall be provided.
B. Control switches, if any, shall be the rotary enclosed rear-mounting type with posi-
tive means for maintaining contact position.
C. Ammeters mounted in the main incoming sections shall be moving-iron type having a
measuring range and shall be capable of withstanding twice the rated current for one
second without damage.
E. A voltmeter selector switch shall be mounted in the main incoming panel and shall
be of the rotary type with cam operated contacts. It shall have (7) positions "OFF",
R-S, S-T, T-R, R-N, S-N and T-N.
F. Current transformers (CTS) shall be of accuracy class 0.5 for measurements and shall
comply with IEC Recommendations 60185.
G. Test block with socket and plugs shall be provided for testing all instruments and
CT's.
A. Frequency Converters: A quite large amount of the installed motors may be driven
by Frequency Converters.
B. If the total amount of Converters has any impact or not on the electrical supply sys-
tem must be considered and investigated. The Converters shall not have impact on
other electrical consumers in the network. It could be that special requirements for
electrical components must be considered. These are components as Circuit Break-
ers and Capacitor Banks.
C. As a rule shall be used on each Converter. Please follow the recommendation given
by the brand.
D. Cables shall be used. The earthing of the screen must be done with special
clamps/terminal made for screened cables. The motor cables shall not be laid to-
gether with instrument cables.
A. Surge protection device – shall be provided at the incoming supply side of main low
voltage panel, as shown on the drawings. The Contractor should select the proper
type recommended by the supplier and submit to the Engineer for approval support-
ed by calculations.
A. The switchgear shall be factory assembled and tested before shipping. Test reports
shall be furnished by the Contractor.
B. All components shall be thoroughly inspected and tested to ensure alignment and
adequacy of all functions.
3.1 INSPECTION
A. Inspect each switchgear assembly and related accessories for damage, defects, com-
pleteness and correct operation before installing. Inspect previously installed related
work and verify that it is ready for installation of instruments and equipment.
3.2 PREPARATION
A. Ensure that installation areas are clean and that construction operations are com-
pleted prior to installing equipment. Maintain the areas in a broom-clean condition
during installation operations.
A. The Contractor shall perform all interconnecting wiring and grounding as indicated,
specified and required and shall include cables, conductors, terminals, connectors,
wire markers, conduits, conduit fittings, supports, hardware and all other required
materials.
B. Provide the electrical materials and complete all the required electrical installations
in accordance with the requirements specified in Section 260500 and as required by
Drawings.
3.4 MOUNTING
A. The switchboards and panelboards (both surface and flush types) shall be installed so
that the height of the top edge will not exceed 1.80 m from the finished floor. Direc-
tories shall be typewritten in English and Arabic to indicate load served by each cir-
cuit, and shall be mounted in a holder behind protective coating. Contractor shall
follow manufacturer's installation instructions.
B. For free stand panelboard either steel or concrete base should be made without any
extra cost to Employer.
C. Contractor shall submit to the Engineer for approval, an elevation mounting detail
and plan for each distribution board specially those mounted inside vertical service
ducts, also showing cable risers and racking to a scale of 1:10 or 1:50 before installa-
tion.
A. Furnish the service of engineer especially trained and experienced in the installation
of the equipment to (1) supervise the installation in accordance with the approved
material and equipment manuals and (2) inspect, check, adjust as necessary in ac-
cordance with the Specifications herein, until the installation and operation are ac-
ceptable. Include all costs for services in the Contract Price.
A. Contractor shall prepare in full details and submit for approval, post installation, test
procedures attached with test forms for all L.V. panels.
C. The tests shall be both electrical and mechanical to demonstrate satisfactory opera-
tion. Where protection relays or adjustable overcurrent trips are incorporated, pri-
mary/secondary injection tests shall be carried out to demonstrate the correct set-
ting of the protection device and its satisfactory operation. Test Certificates shall be
issued by the Contractor when primary injection tests are carried out.
D. The whole of the switchgear and control center shall be tested as integral units based
on the completeness of the circuits in the final manufactured form within the Manu-
facturer's works. Witnessed tests shall comprise Routine Tests in accordance with
IEC 61439 with the following:
1. Primary injection tests to ensure correct ratio and polarity of CT's and to
demonstrate the correct operation of current operated protection relays and
direct acting coils over their full range of settings.
2. Operation and through current stability tests on balanced earth fault protec-
tion relays by primary current injection.
3. Correct operation of sequencing and control circuits indications and alarms at
normal operating voltages by operation of local control switches and simula-
tion of operation of remote control circuits and all protection devices.
4. Circuit breakers shall be subject to routine tests together with checking of all
mechanical and electrical interlocks.
5. Type test certificates and performance test data for identical panel types shall
be made available.
6. Measure phase-to-phase and phase-to-ground insulations to meet manufac-
turer's specified minimum resistance.
7. Check electrical continuity of circuits and for short circuits.
8. Coordinate tests with tests of generator and run them concurrently.
9. Demonstrate interlocking and operational functions for at least 3 times.
A. Provide the services of trained and field experienced Engineer(s) to validate each
Switchgear System to verify that each system is operational and performing its in-
tended function as specified and detailed in the approved Post-Installation Test Pro-
cedures. Validate each system by simulating inputs.
B. Immediately correct any and all defects and malfunctions disclosed by tests. Use
new parts and materials as required and approved and retest. Provide a report certi-
fying completion of validation of each system.
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. PANELBOARDS
CAIRO - EGYPT 262416 – 2874 0
SECTION 262416
PANELBOARDS
Page
PART 1 GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Submittals 2
1.4 Quality Assurance 3
1.5 Coordination 3
1.6 Warranty 3
1.7 Factory Acceptance Test 3
1.8 Schedules 4
PART 2 PRODUCTS 4
2.1 Manufacturers 4
2.2 General Requirements 4
2.3 Panelboard Enclosures 5
2.4 Busbars 6
2.5 Molded Case Circuit Breakers (Mccbs) 7
2.6 Miniature Circuit Breakers (Mcbs) 9
2.7 Distribution Panelboards (Dp) 9
2.8 Final Branch Circuit, Power And Sub-Distribution Panelboards -
Generally 10
2.9 Final Branch Circuit, Power And Subdistribution Panelboards - Type
Mccb 10
2.10 Final Branch Panelboards - Type Mcb 11
2.11 Distribution Board For Outdoor Lighting 12
2.12 Lighting Control Panel 12
PART 3 EXECUTION 12
3.1 Installation 12
3.2 Identification 13
3.3 Connections 14
3.4 Field Quality Control 14
PART 1 GENERAL
1.2 SUMMARY
A. This section covers low voltage panel boards as indicated on the drawings and
required by the contract and shall include the following items:
1.3 SUBMITTALS
A. Equipment Data: Submit data for approval including, but not limited to, the
following:
D. Shop and Construction Drawings: Submit drawings for approval including, but not
limited to, the following:
1. Exact composition of each panel board, indicating Bus bar rating, frame
F. Panel board Schedules: For installation in panel boards submit final versions after
load balancing.
G. Panel board Schedules: For installation in panel boards. Submit final versions
after load balancing. As-Built (Record) Drawings before energization.
A. Comply with:
1.5 COORDINATION
A. Coordinate layout and installation of panel boards and components with other
construction that penetrates walls or is supported by them, including electrical
and other types of equipment, raceways, piping, and encumbrances to
workspace clearance requirements.
1.6 WARRANTY
A. Contractor shall agree to repair or replace the equipment that does not comply
with the requirements or fails in work.
A. Contractor shall submit manufacturer's type test certificates and routine test
records in accordance with the IEC 61439.
A. Schedules shall show the designation and required type of panel board using the
following criteria:
PART 2 PRODUCTS
2.1 MANUFACTURERS
C. Panel boards are to be totally enclosed, dead front type and to be factory
designed and assembled.
J. Molded case circuit breakers shall have trip units that achieve full selective
system for overload, short circuit and instantaneous protection.
K. Circuit breakers are to be non-fused type and all MCCBs, MCSs and MCBs shall be
clearly marked indelibly with manufacturer’s name, ratings, product number and
serial number.
L. Circuit Breaker Arrangement: Panel boards are to have one main incoming circuit
breaker or switch and the required number of branch circuit breakers, including
spare circuit breakers and spaces for future expansion. Three-phase panel boards
are to be designed for sequence phase connection of branch circuit devices.
M. In the event of an insulation fault, the fault current shall be limited to a safe
value and shall not result in a loss of power.
A. Type: General purpose type, suitable for relevant ambient conditions, flush or
surface mounted, comprising box, trim, or trim and door to approved
manufacturer's standards and sizes.
B. Construction: Box, trim and doors where required, are to be sheet steel of
gauges in accordance with the standards. Welded joints are to be galvanized
after manufacture. Gutter spaces are to conform to the standards, adequate for
the utilized cables/wires subject to the engineers’ approval and in no case less
than 100 mm on all sides. Enclosure is to have pre-designed angles or threaded
end studs to support and adjust mounting of interior panel board assembly.
C. Trims are to cover and overlap front shield, covering all terminals and bus
compartments, to form a dead front panel. Trims are to be fixed to cabinet/box
by quarter-turn clamps engaging flange of box (use of screws engaging holes in
flange of box is not acceptable). Screws where used are to be oval-head,
countersunk and flush. Trims for flush mounted panel boards are to overlap box
and front shields by at least 20 mm. Trims for surface mounted panel boards are
to be exactly sized to form flush fit to box.
D. Doors are to have concealed hinges integral with trim, and flush combination
cylinder lock and catch. Doors over 1000 mm high are to have vault-type handle
and multiple point latch mechanism. Locks are to be keyed alike.
E. Finish: Inner and outer surfaces of cabinet/boxes, trims, doors etc. Are to be
cleaned, phosphatized, chrome passivated and treated electrostatically with final
thermosetting epoxy powder modified by polyester resins providing high
resistance to mechanical injury, heat, acid and alkali solvents, grease, aging and
corrosion and of standard gray color to the approval of Engineer.
2.4 BUSBARS
A. Type: One piece, 99% pure electrolytic copper, based on total maximum
operating temperature of 90 deg C at any point of the bus, at full continuous
rating. Bolted or clamped contact surfaces are to have maximum current density
not exceeding requirements of the approved standards. Aluminum is not to be
used for bus bars or panel board parts.
C. Rating: Bus bar rating is to be at least equal to main-circuit breaker frame size.
Where no main circuit breaker is required, bus bars are to have main lugs or
disconnect switch, with nominal rating equal to 1.25 times the upstream circuit
breaker trip rating.
D. Short-circuit Duty: Bus bars are to carry at least 125% of the maximum short-
circuit level at point of application for one second, without showing any signs of
degradation.
F. Neutral bar is to be solid and fully insulated from cabinet or box. One solder-less
box type set-screw connector is to be provided for neutral wire of each branch
circuit and one bolted clamp-type connector or anti-turn lug with set-screw for
main incoming neutral wire. Neutral is to be fully sized and rated as for phase bus
bars.
G. Earthing bar is to be copper, brazed to panel board cabinet, with bolted pressure
connector for main conductor and one set-screw-type tunnel terminal for each
outgoing conductor, to provide secure and reliable contact with all metal parts
and enclosure.
B. Circuit Breaker Trip Units: Unless otherwise specified, molded case circuit
breakers of final branch circuit panel boards (LPs), power panel boards (PPs ) and
sub distribution panel boards (SDPs) are to be thermal magnetic type, while
molded case circuit breakers of distribution panel boards (DPs) are to be thermal
magnetic for frame sizes up to 160 amperes and electronic type for higher frame
sizes.
C. Thermal magnetic circuit breaker trip units: are to have bi-metallic inverse time
delay over- current element for small overloads and instantaneous magnetic
over-current trip element for operation under short-circuit conditions on each
pole. Circuit breakers rated 150/160 A are to have adjustable instantaneous trips.
E. Electronic trips units, applicable to circuit breakers 250 A frame size and larger,
are to be solid state with long time delay settings between 0.5 and 1.0 times
maximum trip rating, short time delay range of 3 to 10 times maximum trip
rating with a maximum clearing time of 0.2 seconds, and instantaneous
protection adjustable from 5 to 10 times continuous rating. Solid state trip units
are to be insensitive to changes in ambient temperature between -20 and +55
deg C. Earth fault protection is to be built into trip unit where specified, and is to
be suitable for connection to external current sensor. Push-to-trip button is to be
provided on cover for testing the trip unit. Short time over current protection is
only required for circuit breakers 630A and above.
G. Trip current rating (amps) indicates nominal maximum rating at which overload
element is set to operate.
H. MCCBs for LPs, PPs, SDPs and DPs Type 2: Comply with IEC 60947-2 test
sequences I, II, utilization category A, and are to have rated ultimate short circuit
breaking capacities (sequence III) to meet the electrical requirements at the
I. MCCBs for DP Type 1: MCCBs rated 630 A and above are to have utilization
category B (with an intended short time withstand capability), and are to have
rated service short circuit breaking capacities (sequence II) with suitably selected
frame sizes and trip ranges to meet the electrical requirements at the
distribution panel board, with declared ratings as percentage (100%, 75% or 50%)
of the ultimate ratings as quoted by the circuit breaker manufacturer marked on
the circuit breaker rating plate. MCCBs below 630A are to have utilization
category A with rated ultimate short circuit breaking capacity (sequence III) to
meet the electrical requirements at the panel boards locations with preferred
ratings in accordance with the below tables.
N. Residual current operated earth leakage trip devices (RCDs) are provided as add-
on or built-in earth leakage accessories, where required. Protection against earth
fault current, in addition to over-current and short-circuit protection, is to be in
accordance with the Regulations. Trip current sensitivity on breakers for branch
circuits is to be as per the local Regulations. Circuit breakers are to include
current transformer with tripping coil assembly, test button and trip free
mechanism to ensure circuit breaker cannot be held closed against earth faults.
O. Current Limiting Circuit Breakers: Molded case type without fusible elements.
When operating within current limiting range, the I2t of let-through current is to
be less than 1/2 cycle wave of symmetrical protective short-circuit current as
compatible with breaker construction.
P. Current limiting circuit breakers are to have, on each pole, adjustable inverse
time-delay over-current characteristics for overload protection and
instantaneous trip for short-circuit protection. Operation of main contacts is to
be based on Electro-magnetic repulsion forces between contacts created by fault
current. Ratings are specified at rated voltage for an rms value of prospective
short-circuit current.
D. MCBs and combination devices are to be modular, of unified profile and suitable
for mounting either to a standard din rail, or a plug-in system.
F. Ratings: Preferred rated currents are to be 6, 10, 15, 20, 25, 30, 40, 50, 60, 80,
100 and 125 A, calibrated at 40deg.c, available as 1, 2, 3 and 4-pole circuit
breakers. De-rating above 40 deg C is not to exceed 1% per deg C and loading is
not to exceed 70% of circuit breaker rating.
G. Residual current devices for earth leakage protective circuit breakers are to be
add-on devices, or built-in and integral with the standard circuit breaker. Non-
adjustable sensitivities of 30 mA, 100 mA and 300 mA are to be available for all
ratings of 2-pole and 4-pole circuit breakers.
H. Auxiliaries are to include alarm switch, auxiliary switch, shunt trip, under voltage
trip and similar units which are to be modular additions to the circuit breakers.
A. DP Type 1: Form 2b to IEC 61439-1, and have a minimum rated insulation voltage
of 750V free standing, with doors, suitable for ratings of main breaker, bus bars
ranging, 3-phase, 4-wire (or 3-wire where specifically indicated), suitably and
orderly arranged for any selected combination of branch MCCBs.
D. Molded insulators are to have minimum temperature rating of 130 deg C and
insulation grade of 3.5 kV for one minute.
E. Circuit breakers are to be mounted in twin arrangement (except for larger circuit
breakers) and bolted rigidly to copper cross and center bus connectors.
B. Branch circuit breakers are to be 1, 2 or 3-pole, rated 100 A frame size, with trip
ratings between 15 A and 100 A, and compatible ICs, selected from normal (N),
high-break (H) or current-limiting (L) range.
D. Short-circuit Rating: Panel boards may only have integrated equipment (series)
short-circuit ratings in accordance with paragraph F of Article 2.2 "GENERAL
REQUIREMENTS" hereof.
D. SPN type panel boards are to be suitable for 240 V maximum service voltage,
single-phase and neutral, with MCBs on branch circuits and main incoming.
E. SPN type main circuit breaker is to be double-pole MCB, with or without earth
leakage device (RCD), as shown on the Schedules.
F. Single-pole and double-pole MCBs for 240 V service, are to have trip ratings
between 6A and 125A, with ICs as required in the Schedules.
G. TPN type panel boards are to be suitable for up to 415 V A.C. maximum service
voltage, 3- phase and neutral, with MCBs on branch circuits and 3 or 4-pole MCB
or MCCB main incoming.
H. Triple-pole branch circuit breakers are to have trip ratings between 6A and 125A,
with IC as required in the Schedules.
I. TPN type panel board main circuit breakers are to be MCB or MCCB, 125A
continuous current rating, with trip range from 25 A to 125A, or 250 A MCCB
with trip range 70 A to 250 A, normal (N) or high-break (H) duty with/without
RCD.
J. Short-circuit Rating: TPN panel boards may only have integrated equipment
(series) short-circuit ratings in accordance with clause paragraph F of Article 2.2
A. When the photoelectric lighting control and timer unit switches on the triple pole
contactor, the outgoing phase lighting circuits shall be energized.
B. Provide with bush button and indication lamp only devices as scheduled, matching
the IEC type specified for the enclosure.
PART 3 EXECUTION
3.1 INSTALLATION
A. Fixing Generally:
B. Panel board Interiors: Do not install in cabinets until all conduit connections to
cabinet have been completed.
C. Wiring inside Panel boards: Neatly arranged, accessible and strapped to prevent
tension on circuit breaker terminals. Tap-off connections are to be split and
bolted type, fully insulated.
D. Trim: Fix plumb and square prior to painting. Fix trim for flush mounted cabinets
flush with wall surface finish.
F. Mounting Heights: Top of trim 1880 mm above finished floor, unless otherwise
indicated.
G. Mounting: Plumb and rigid without distortion of box. Mount recessed panel
boards with fronts uniformly flush with wall finish.
J. Provision for Future Circuits at Flush Panel boards: as approved by the engineer,
stub four empty conduits from panel board into accessible ceiling space or space
designated to be ceiling space in the future. Stub four empty conduits into raised
floor space or below slab not on grade.
K. Provide panel board key on a stainless steel chain alongside the panel, fixed
securely to the adjoining wall.
3.2 IDENTIFICATION
B. Panel board Nameplates: Label each panel board with engraved metal or
laminated-plastic nameplate mounted with corrosion-resistant screws.
3.3 CONNECTIONS
A. Generally: Carry out all tests, required by the governing codes and by the
Engineer, on Panel boards after installation, to verify compliance with the
specifications and standards. Inspect conditions within panel boards and verify
insulation conditions by use of a megger.
B. Inspect conditions within panel boards and verify insulation conditions by use of
a calibrated megger.
D. Routine tests on site are to be carried out, in accordance with the Standards, on
all panel boards assembled from standardized components of the manufacturer
outside the works of the manufacturer.
E. Testing: After installing panel boards and after electrical circuitry has been
energized, demonstrate product capability and compliance with requirements.
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. MOTOR CONTROL CENTERS
CAIRO - EGYPT 262419 – 2874 0
SECTION 262419
PART 1 - GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Submittals 2
1.4 Quality Assurance 3
1.5 Delivery, Storage, And Handling 3
1.6 Coordination 3
1.7 Factory Acceptance Test 4
1.8 Coordination 4
PART 2 - PRODUCTS 4
2.1 Approved Manufacturers 4
2.2 Variable Speed Drives (Vsds) 4
2.3 Starters 8
2.4 Combination Starters Switch Disconnectors 10
2.5 Push Buttons 10
2.6 Relays 10
2.7 Motor Control Center 11
2.8 Control Switches 13
PART 3 - EXECUTIONS 14
3.1 Applications 14
3.2 Installation 14
3.3 Identification 15
3.4 Control Wiring Installation 15
3.5 Earthing 16
3.6 Connections 16
3.7 Field Quality Control 16
3.8 Cleaning 17
3.9 Demonstration 17
PART 1 - GENERAL
1.2 SUMMARY
A. This Section includes variable speed drives, motor control centers and panels for use
on AC circuits.
1.3 SUBMITTALS
A. Technical Data: Include dimensions, ratings and data on features and components &
enclosures. Type test certifications are also to be included as required.
C. It should be noted that other comments like “noted “ or “partial compliance” are
unacceptable and will be interpreted as a non-compliance.
D. Shop and Installation Drawings: Submit for each motor control center prior to
ordering materials and equipment specified in this Section. Include dimensioned
plans, elevations, and component lists. Show ratings, including short time and short-
circuit ratings, and horizontal and vertical bus ampacities.
F. Submit certified protection relay coordination settings for review, along with certified
“As- built” connection drawings, before energization of equipment.
A. Source Limitations: Obtain motor control devices, variable speed drives and
enclosures/panels, through one source from a single manufacturer. MCC to be
approved by EDC and manufacturer to be listed in EDC's vender list.
C. All products shall be sourced either directly from the manufacturer or from the
manufacturer’s authorized dealer/agent.
A. Deliver in shipping splits of lengths that can be moved past obstructions in delivery
path as indicated.
1.6 COORDINATION
A. Coordinate features of controllers and accessory devices with pilot devices and
control circuits to which they connect.
B. Coordinate features, accessories, and functions of each motor controller with the
ratings and characteristics of the supply circuit, the motor, the required control
Motor Control Centers Section 262419
Urbanium New Administrative Building (Prj. 2874) Page 3 of 17
sequence, and the duty cycle of the motor and load.
A. Contractor shall submit manufacturer's type test certificates and routine test records
in accordance with the IEC 61439-1 & IEC 61439-2
1.8 COORDINATION
A. Coordinate features of controllers and accessory devices with pilot devices and
control circuits to which they connect.
B. Coordinate features, accessories, and functions of each motor controller with the
ratings and characteristics of the supply circuit, the motor, the required control
sequence, and the duty cycle of the motor and load.
PART 2 - PRODUCTS
A. General:
1. This part of the Specification describes the general requirements for the
variable speed drives, the VSDs. The nominal values, the standard documents
and the drive's minimum performance are defined in this part. The VSD does
not include motors in this specification. The Specification uses the term motor
unit which means a combination of the VSD and the motor.
2. If the Project specific part of the Specification is in contradiction with the other
parts of the document, the Project specific document shall apply.
3. Requirements for the Manufacturer:
5. General requirements:
a) The VSD shall be of the modern design, yet user friendly and be simple
to install commission and maintain. The VSD shall be able to start and
control the speed of a standard squirrel cage induction AC motor. The
VSDs shall be CE marked. The VSDs have to be built to comply with the
IEC standards.
b) The materials used in the VSD as a complete unit shall be recyclable,
non-toxic and flame retardant.
c) The VSD shall be a digitally controlled drive, using, at least, the pulse
width modulation (PWM) with flux vector control, a direct torque
control (DTC), or equivalent. It shall have IGBT's in the inverter section of
the throughout the power range, and it shall have the following
minimum specifications.
6. Operating conditions:
8. Main Protections: Over current, short circuit, input/output phase loss, motor
overload and under load, over/under-voltage, over speed, over temperature,
motor stall, other internal fault.
9. The VSD shall be able to give a 100 percent output current continuously in the
above-specified conditions. In order to ensure that the drive can provide the
required output current in the specified ambient conditions, the manufacturer
shall inform of the required de rating, if the ambient temperature given in the
Project specific Specification is higher than 50 deg. C or if the installation
altitude is more than 1000 m above the sea level. The de rating factor shall be
specified so that neither the lifetime of the VSD nor the unit's performance,
overload ability included, nor the reliability of the VSD shall suffer.
10. Storage conditions (in the protective package):
a) Power loss ride-through: The drive shall have a power loss ride-through
capability. This means that the drive controls should stay alive during a
power loss by means of the energy stored in the load. The ride through
time shall be the longer the higher the kinetic energy of the load is. The
motor shall be magnetized as long as there is kinetic energy in the
system.
b) Flux Optimization: The VSD shall have a built-in automatic flux
optimization function. The flux optimization function minimizes the sum
of the magnetizing current and the load current so that the drive can still
follow the given reference. This feature reduces energy consumption
Motor Control Centers Section 262419
Urbanium New Administrative Building (Prj. 2874) Page 6 of 17
and motor noise when driving at less than the nominal load.
c) Critical speed jump-over: The VSD shall have programmable skip speeds
to jump over critical resonance speeds. If the speed reference is in the
critical speed area, it is ignored and the latest speed reference is
maintained. 3 programmable critical speeds at least shall be available.
d) Current/speed limiting: In case the acceleration or deceleration ramps
are too fast for the drive capacity, the drive shall be able to
automatically reduce the ramp to prevent tripping. Also, in case of
transient overloads the drive shall automatically reduce speed to
prevent an over current trip, if the drive capacity is not sufficient to
handle the load.
e) PID-controller the drive shall have a built-in PID-controller for control of
the customer process.
f) Restart in the event of a fault trip due to over voltage, over current or
loss of analog signal, the VSD shall be programmable to attempt an
automatic restart. For safety reasons, the maximum number of attempts
shall be five (selectable) within a short time. If the fault does not clear
after the attempts, the drive shall lock out.
14. Documents:
2.3 STARTERS
B. Motor Data: Obtain from equipment supplier before ordering any motor starter, or
check motor nameplate for full load current rating and allowable temperature rise in
order to select proper overload thermal element for motor starter.
D. Control voltage for starters and control circuits is not to exceed 110 V.
F. Control Circuit Protection: Use high rupturing capacity fuses or circuit breakers.
G. Auxiliary supply for controls other than from main power circuit, to be effectively
isolated by auxiliary contacts on main isolator.
I. Starter type A for single phase motors not exceeding ½ HP to be surface or flush
mounted, manual 2 pole toggle type, for non-reversing across the line starting, fitted
with 1 overload element.
L. Starter type D for 3 phase motors over 50 HP to be soft starter or variable frequency
drive as applicable, with 3 pole overload relay and low voltage protection, unless
otherwise required by local regulations. Harmonics produced by such starters shall
be certified to be within the relevant IEC limits.
O. Contactors: Comply with IEC 60947-4, utilization category AC3 or AC4 as applicable,
and be 3 phase, 4 pole, magnetic type, 600 V rating, capable of interrupting at least
ten times rated current inductive or non-inductive loads under normal service
conditions and are to have replaceable main arcing contacts and arc quenching
devices. Contactors are to withstand, without welding or burning of contacts, an
inrush current of 20 times normal rating for 4 seconds upon closing and are to be
capable of closing on the heaviest short circuit of the system and withstand the short
circuit for period required by upstream short circuit protective device to operate. 3
N.O. (normally open) and 3 N.C. (normally closed) spare contacts are to be provided
on each contactor.
P. Contactors shall be of robust design and shall comply with BS EN 60947: Part 4-1.
They shall operate without undue noise or vibration. Where 2 or more contactors are
contained in the same cubicle, they shall be separated by barriers. All secondary
wiring shall be so arranged and protected as to prevent its being damaged by arcing.
R. Adjustable acceleration rate control utilizing voltage or current ramp, and adjustable
starting torque control with up to 500 percent current limitation for 20 seconds.
T. LED indicators showing motor and control status, including the following conditions:
B. Switch Disconnectors Operating Mechanism: Quick make, quick break, with external
operating handle mechanically interlocked with enclosure cover necessitating
disconnecting switch to be in OFF position for access to inside of enclosure. Means
are to be provided for by-passing interlocks. Position of isolating switch to be clearly
indicated on cover.
C. Short circuit protection gear to be HRC fused cartridges or molded case circuit
breakers of appropriate current rupturing capacity. Switch disconnectors are not
required if circuit breakers are used for the short circuit protection. In this case the
circuit breaker will perform the disconnection function.
B. Lock keys shall be suitably attached within easy access on a stainless steel chain fixed
to immovable surface with anchor-bolts.
C. All push buttons shall be of the non-retaining type with body of stainless steel and
button made of non-hygroscopic materials, non-swelling and fitted to avoid any
possibility of sticking.
2.6 RELAYS
C. Outdoor MCC: Electro galvanized sheet steel with metal parts of the housing are to
be cleaned, primed with rust inhibiting and waterproofing primer and finished with
corrosion and weather-resistant enamel and final coat of air drying enamel.
Alternative finish may be used subject to approval of the Employer/Engineer before
manufacturing.
H. Bus bars to be adequately isolated and braced to sustain maximum possible short
circuit current which may be encountered at the proposed location. Type test
certification required by ASTA or KEMA.
J. Spare Positions: Fully equipped cells, ready for connection to motors, are to be
provided in adequate number.
K. Space Positions: if required to be fully equipped cells ready to receive control unit are
to be provided in adequate number.
M. Incoming line connections to be made with solder less terminal 4 bolt type clamps.
N. Mounting plates for the draw-out feeders shall be painted galvanized sheet steel and
of minimum 2m thickness, with necessary “lock-in-place” fixtures made of metal.
Draw-out shall imply no requirement of any cable disconnection requirements for
either power or control.
O. Control wiring and BMS wiring shall not be routed through power areas within the
BMS.
P. All terminal blocks for control and BMS wiring shall be of 500V insulation class, DIN
rail mounted and manufactured from non-toxic, color coded non-inflammable, self-
extinguishing material and shall contain nickel plated electrolytic copper terminals.
The terminal contacts shall be suitable to meet the “pull-out” forces as per IEC
60947-7-1. All terminals shall be clearly identified in respect of service usage,
designation and number.
Q. All internal wiring and cabling shall be terminated with tinned copper lugs.
R. Current transformers provided in the MCC shall conform to IEC 60185, class H
Motor Control Centers Section 262419
Urbanium New Administrative Building (Prj. 2874) Page 12 of 17
insulation, 0.2 accuracy class as per IEC and secondary 5A, of suitable VA rating. The
Current transformers shall have type test certification from an internationally
accredited testing laboratory and shall be subject to 100 % routine tests as per the
IEC.
S. Certified and stamped Schematic and wiring diagrams to be firmly fixed within motor
control center, showing each component and cross- referenced with component
labels.
A. Float Switch: Level operated, stainless steel, heavy duty, bracket mounted type,
suitable for application in open tanks, complete with 178 mm spun copper float,
brass rod, two stops, floor mounting stand, lever and counterweight. Switch to have
oil tight and dust tight enclosure and 2 pole double throw silver contacts that open
on liquid rise.
B. Pressure Switch: Industrial, heavy-duty bellows actuated type, suitable for water
service, with contacts to close on falling pressure. Range to be 0.1 to 8 kg/cm².
Switch to be good for 1720 kPa operating pressure and to have 6 mm pipe tap
bottom connection. It is to have oil tight and dust tight enclosure, single pole double
throw contacts and setting adjustment.
C. Low Suction Pressure Switch: Industrial, sensitive, low range, diaphragm actuated
type, suitable for water service, with range of 2 to 20 kPa of falling pressure, preset
at factory to 3 kPa. Switch to be good for 690 kPa operating pressure and to have 6
mm pipe tap bottom connection. It is to have oil tight and dust tight enclosure,
single pole double throw contacts, range adjustment knob, sealing cap and range
locking nut.
D. Control Switches shall be operated by shrouded push buttons or have handles of the
spade type. Control, reversing, selector and test switches shall be mounted,
constructed and wired so as to facilitate the maintenance of contacts without the
necessity for disconnecting wiring. Control switches shall carry KEMA or ASTA or UL
certification.
F. Control switches for use in direct control schemes shall be rated for the substation
battery voltage.
G. All control switches shall be provided with identification labels, including labels to
give clear indication to the direction of each operation, for example, "open", "close",
"raise", "lower", etc.
Motor Control Centers Section 262419
Urbanium New Administrative Building (Prj. 2874) Page 13 of 17
PART 3 - EXECUTIONS
3.1 APPLICATIONS
D. Emergency disconnect switches or push buttons (as applicable) for all motors, within
3 meters of the equipment that it is meant to protect, located at a logically
convenient position where it is clearly identifiable.
3.2 INSTALLATION
B. Anchor each motor control center assembly to steel-channel sills 100 mm high,
arranged and sized according to manufacturer's written instructions. Attach by tack
welding or bolting. Level and grout sills flush with motor control center mounting
surface.
C. Fuses: Install correctly rated and clearly labeled fuses in each fusible switch as
indicated.
D. Power and Control Wiring: Run in separate conduits unless otherwise specified.
E. Rigid conduits are not to terminate in nor be fastened to a motor frame or base.
H. Flexible Conduits: Do not use in place of rigid conduits except at motor connections,
unless otherwise specified.
Motor Control Centers Section 262419
Urbanium New Administrative Building (Prj. 2874) Page 14 of 17
I. Support conduit with conduit supports in an adequate approved manner.
J. Conduits are not to cross pipe or vent shafts, ducts or openings. They are to be run a
minimum 100 mm away from pipes of non-electrical services.
K. Conduits: Install so that moisture can drain to lowest point. Provide screw plug at all
low points for draining.
L. Keys for MCCs and other panels to be provided on stainless steel chain alongside the
panel, fixed securely to immovable surface with anchor bolt.
M. All installations shall particularly comply with requirements of IEC 60204- “Safety of
machinery-Electrical equipment of machines”. Contractor is required to submit
specific certification to this effect before power energization.
3.3 IDENTIFICATION
C. Starters: Fix certified, detailed wiring diagram inside enclosure cover to clearly
indicate circuits.
D. Starters: Identify control and power wires either by distinctive colored insulation,
engraved tags or other approved method.
B. Protect circuits with high rupturing capacity fuses or circuit breakers. Auxiliary supply
for controls other than from main power circuit, to be effectively isolated by auxiliary
contacts on main isolator.
C. Provide bus bar mounted fuses where direct control connections are required.
E. Connect selector switches to bypass only the manual and automatic control devices
that have no safety functions when switch is in the hand position.
Motor Control Centers Section 262419
Urbanium New Administrative Building (Prj. 2874) Page 15 of 17
F. Connect selector switches with motor control circuit in both hand and automatic
positions for safety-type control devices such as low- and high-pressure cutouts,
high-temperature cutouts, and motor-overload protectors.
3.5 EARTHING
C. All MCCs shall be provided with a second earthing connection through the local
common earth bar located in the respective electrical/mechanical room.
3.6 CONNECTIONS
A. Tighten motor control center bus joint, electrical connector, and terminal bolts with a
torque-wrench, according to manufacturer's published torque-tightening values.
B. Ensure all covers and doors are in proper alignment and all equipment handles
functioning properly.
C. Testing: After installing motor control center and after electrical circuitry has been
energized, demonstrate product capability and compliance with requirements, as per
approved method statement.
E. Remove and replace malfunctioning units with new units, and retest.
F. Submit settings along with justification to support them both at overload and short
circuit.
G. Circuit Breakers: Coordinate earth fault detection and interruption with those of
Motor Control Centers Section 262419
Urbanium New Administrative Building (Prj. 2874) Page 16 of 17
main incoming breaker on main distribution panel, and submit settings.
H. Pressure Switches: Test after installation to ensure dependable operation and correct
setting.
3.8 CLEANING
A. Inspect interior and exterior of motor control centers before energization and
vacuum clean all dust and debris. Remove paint splatters and other spots, dirt, and
debris. Touch up scratches and mars of finish to match original finish. Clean devices
internally, using methods and materials recommended by manufacturer.
3.9 DEMONSTRATION
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. ENCLOSED BUS ASSEMBLIES
CAIRO - EGYPT 262500 - 2874 0
SECTION 262500
Page
PART 1 GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Submittals 2
1.4 Quality Assurance 3
1.5 Delivery, Storage And Handling 3
1.6 Project Conditions 3
1.7 Warranty 3
PART 2 PRODUCTS 4
2.1 Manufacturers 4
2.2 Enclosed Bus Assemblies 4
2.3 Supports And Accessories 6
2.4 Fire Stopping 7
PART 3 EXECUTION 7
3.1 Inspection 7
3.2 Installation 7
3.3 Field quality control 8
PART 1 GENERAL
1.2 SUMMARY
C Related Sections
1.3 SUBMITTALS
A General: Submit the following according to the Conditions of the Contract and
Division 1 Specification Sections.
B Product data for each component. Include electrical ratings, dimensions, mounting
position, mounting method, vertical supports, materials, fire stops, and weather
stops.
D Coordination drawings include floor plans and sections drawn to accurate scale.
Submit shop drawings. Show bus assemblies layout and relationships between
components and adjacent structural and mechanical elements. Show support
locations, type of support, and weight on each support. Indicate and certify field
measurements.
F Field test reports indicate and interpreting test results relative to compliance with
specified requirements.
B Reference standard:
A Field Measurements: Don’t take measures from electrical drawings. Verify existing
dimensions by field measurements. Verify clearances and locate obstructions within
manufacturing and installation tolerances of busway.
1.7 WARRANTY
A The Maintenance Period for the equipment and appurtenances shall begin when the
performance test on the equipment and appurtenances has been successfully
completed and preliminary accepted as stipulated in the Conditions of Contract.
2.1 MANUFACTURERS
D Feeder type Bus way: shall be indoor type for non-tapped straight runs and direct
connections between equipment, as applicable, complete with manufacturer's
recommended fittings and accessories where indicated and as required for a
complete, functioning and safe installation. The busway must comply with IEC
standards.
E The Feeder type bus-way shall be designed and constructed for a rated voltage of
1000 V three-phase, 50 Hz, with four conductors where the size of the neutral
conductor is 100% of the phase conductor as follow [L1, L2, L3 + 100%N] +50%
integrated housing ground, with earthed neutral (i.e. TN-S system grounding) and
having a source fault level for 1.0 second at operating voltage 380V as indicated in
the drawings.
G The busbar insulation and insulating supporting supports will be made from
insulation possessing flame retardant and self-extinguishing, die-electric and non-
hygroscopic properties.
H The bus shall carry its rated current continuously, without exceeding the
temperature rise of 55°C over an outside ambient of 40°C.
I The joints shall be designed to provide optimum electrical contact and mechanical
strength.
J Busbars: Busbars shall be generally comply with IEC 61439-1 and IEC 61439-6.
L The temperature rise values for Bus Duct shall not exceed the limit as per IEC 61439-
6 and as specified.
M Hot Spot Temperature Rise not in excess of 55 deg C above an ambient temperature
of 40 deg C at any point in the bus bar when bus bar is operated at continuously
rated load current and system frequency.
N Each busbar except the earth shall be totally enclosed in insulating material.
Insulated and anti-tracking supports for the busbar shall be provided at regular
spaced intervals of 300/600 mm. The supports shall be suitable for use of the busbar
trunking in any position. In vertical positions the supports shall be capable of holding
the vertical thrust of the busbars.
O Bus bar is to be specially built and assembled to provide low reactance and very low
voltage drop.
P Where straight length of busbar trunking are installed in excess of 40 meters thermal
expansion joints shall be fitted in the busbar run, in accordance with the
Manufacturer’s recommendations.
S The joints for splicing adjacent sections together will be tin plated and enclosed by
either insulation bolts or approved taped insulation paint film.
T The joints shall provide optimum electrical contact and mechanical strength. Not
require special tools or bus connectors to join busway sections and shall not require
maintenance after installation.
U Joints shall be properly clean and free from contamination before joint.
V Joints in busbars shall not cause any loss in mechanical strength, electrical
continuity, current carrying capacity and short circuit capacity of the busbars
compared with an un-joined part.
W Joints shall be properly aligned before the final tightening of all joint bolts.
Bolts shall not be over or loosely tightened. Bolt tightening shall be done as specified
by the manufacturer or in accordance with the manufacturer’s special procedure.
X The metal housing surfaces will be chemically cleaned and treated to provide a bond
between the primer light gray paint and the metal surface paint film.
Z After assembly, all conductor joints shall be accessible by the removal of covers in
the enclosure. Such covers shall be weather-proof by neoprene gaskets or other
suitable means.
AA The preliminary layout will be furnished as a part of the material requisition. The
complete installation shall coordinate throughout and shall consist of standard
sections and special section and fittings provided to suit the installation. All material
and installation shall comply with the applicable standard.
BB Enclosure: The bus assemblies casing shall be manufactured and enclosed in 2.5 mm
thickness extruded aluminum with a sandwich configuration to prevent air
circulation inside the casing and to allow excellent heat dissipation performance and
provide minimum hysteresis and eddy current losses. The casing shall be totally
enclosed, non-ventilated and to be bonderized inside and outside and finished with
gray baked electrostatic paint. Joints between sections are to have special insulation,
flanged and pressure bolted, easily dismantled and giving equally strong mechanical
connection to bus bar sections. Any one section of the bus way is to be removable
without disturbing adjacent sections.
CC The enclosure shall be mechanically and electrically continuous and provide a degree
of protection not less than IP 54 as per IEC standards.
EE The busbar enclosure shall be designed and constructed suitable for mounting in
horizontal flat or edgewise position and in the vertical plane. Fixing points shall be at
any position in the run, with the supported spans recommended by the
manufacturer.
A. Spring Mounted Vertical Riser Supports: adjustable for leveling and spring tension
and arranged to permit relative movement between floor and bus bar.
C. Expansion Section: capacity and conductor provisions same as adjacent bus bar
section. Arranged to absorb expansion and contraction of bus bars and housing.
B. Wall and Floor Flanges: sheet steel, 2 mm (12-gage) minimum thickness close fitting
to bus bar arranged to close the wall or floor opening at the bus bar penetration.
C. Fire Barrier: Where busbar trunking passes through wall or slab a proper fire barrier
made of non-hygroscopic material having a fire-resistance period of not less than
that of the corresponding wall or slab shall be provided.
D. Fire resisting barriers shall be fitted in enclosure where it passes through fire
compartment walls and floors. In vertical runs of enclosure, irrespective of fire
resisting barriers at floor levels, where the floor to ceiling height exceeds 3 meters,
an additional barrier shall be fitted in the trunking mid-way between floor and
ceiling.
PART 3 EXECUTION
3.1 INSPECTION
A Examine conditions under which busbar trunking are to be installed. Notify Engineer
in writing of conditions detrimental to proper completion of the work. Do not
proceed with the work until unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A The bus assemblies shall be installed so that the maximum unsupported span does
not exceed 3 meters. Any fixings used shall be of mild steel angle or channel finished
to the same standard as the trunking and shall not cause any long term corrosion or
electrolytic action.
B Where any cutting or damage is caused during erection, the burrs and rough edges
shall be removed, and the finish made good. Any corrosion, which has occurred,
shall be removed and the area treated with a rust-proof agent. The finish shall then
be made good by the application of either a zinc rich epoxy primer or equal
alternative, and for Class 2 finishes shall be followed by coat of color matching paint.
C Runs of enclosure shall not be used to support other equipment or services nor shall
any cables be installed in the enclosure unless the trunking is specially designed for
these purposes.
D Where bus assemblies enclosure passes through fire barriers, walls, floors and
ceilings, fire resting barriers shall be fitted in the trunking and the hole surrounding
the trunking shall be made good to the full thickness with resisting material to
E In vertical runs of assemblies thrust supports shall be fitted either at each floor level
or at 3 meters spacing whichever is of lesser dimensions.
F Incoming cables and all outline shall be supported to avoid appreciable mechanical
loads being imposed on the busbar trunking.
A Prior to installing, test for electrical continuity of bonding, and earthing connections
is to demonstrate compliance with grounding requirements.
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. WIRING DEVICES AND
CAIRO - EGYPT DISCONNECTORS 262726 – 2874 0
SECTION 262726
Page
PART 1 GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Submittal 2
1.4 Quality Assurance 2
PART 2 PRODUCTS 3
2.1 Manufacturers 3
2.2 Wiring Devices 3
2.3 Motor Circuit Protectors And Switches 6
2.4 Touch-Up Paint 7
PART 3 EXECUTION 8
3.1 Installation 8
3.2 Grounding 8
3.3 Field Quality Control 9
PART 1 GENERAL
1.2 SUMMARY
A. This Section shall cover various types of receptacles, connectors, switches and finish
plates.
B. Related Sections
1.3 SUBMITTAL
A. Submit the following according to the Conditions of the Contract and Division 1
Specification Sections:
B. Product Data: Data shall be submitted for each product specified in this section, with
catalog clippings and manufacturer’s technical specifications.
C. Samples: Provide three (3) samples for each device, which shall be used, and for all
relevant accessories (cover, plates). Color selection and technical features shall be
complied with the requirements of codes, interior decoration and Owner’s representative
acceptance.
D. Operation and Maintenance Data: Provide operation and maintenance data for materials
and products specified in this section.
E. Field Quality Control: Submit for Engineer’s approval quality control plan.
1. IEC 60669-1: Switches for Domestic and Similar Purpose (for Fixed or Portable
Mounting).
2. IEC 60947-3: switches, disconnectors and fuse combination unit.
PART 2 PRODUCTS
2.1 MANUFACTURERS
A. General: Wiring devices shall comply fully with the relevant Local, and International
Standards.
B. All wiring devices must be suitable for 3-wire systems for single phase and 5-wire
systems for three phase i.e. earthing terminal must be provided in sockets plugs, lighting
switches, power socket, etc.
C. Boxes and Fittings: Boxes shall be provided with means to terminate conduits securely.
1. For heavy-molded rigid PVC boxes shall be provided with brass insert threads
and fixed lugs to receive cover screws or galvanized steel with suitable marked
earth terminal for exposed and outdoor use.
2. For more details on boxes and fittings, refer to Section 260533.
E. Various samples shall be submitted for approval and/or selection by the Engineer.
1. Fixing screws shall be chromium plated, polished. Screw head shall suit the
plates.
2. Combination (multi-gang) plates shall be provided for grouped outlets and
devices as detailed on the Architectural or Electrical Drawings. Color shall be
selected by the Engineer for different typical areas without any cost
implication to the Contract.
F. Convenience Socket Outlets: The Contractor shall supply a unified standard type socket
outlet for the whole project.
1. Socket outlets shall be rated 16 Amp and 250 Volts with two rounded poles
plus side earth and 20 mm spacing. The earth terminal of each socket shall be
effectively connected with the earth continuity conductor, phase and neutral
conductors to the respective terminals.
2. Socket outlets shall have a molded plastic or porcelain base and be designed
to fit the appropriate plate as required or as approved, before execution, by
the Engineer.
3. Contacts shall be self-adjusted and have a non-expanding size limiting entry, to
prevent permanent distortion.
4. Where duplex socket outlets are shown on Drawings, two of this type of
socket shall be mounted under one common plate.
5. Weatherproof socket outlets shall be mounted in the box specified with a
gasketed, weatherproof cast-metal cover plate, with individual cap over each
socket outlet opening and stainless steel mounting screws. Caps shall be
tightly closed with stainless steel springs when the socket outlet is not in use.
6. Where indicated on Drawings, receptacles shall be served by ground fault
circuit interrupters for personnel protection.
7. Application: Outlets for internal use shall generally be of the insulated pattern
ivory finish, or as specified in Volume 5 interior and furniture works. Color is
to be selected by Engineer. In utility and workshop areas metal clad enclosures
and finishes shall be used.
8. Outlets for exterior use shall be weatherproof pattern enclosed in Glass-fibre
Reinforced Plastic (GRP) or galvanized metal boxes.
9. Terminals for 250 V outlets shall each be capable of receiving and satisfactorily
connecting two (2) conductors (solid or stranded), each of 4 mm2 minimum.
10. Contact pressure with conductors shall preferably be by clamp plate rather
than by pinch screw.
11. Socket outlets for flush fitting shall be mounted in appropriate recessed box.
12. Socket outlets and their enclosures shall be complete with necessary terminals
for the connection of circuit protective conductors as required by the IEE
Regulations and IEC latest edition.
13. Boxes providing enclosure and/or mounting for socket outlets shall be PVC if
concealed, or galvanized steel if exposed complete with conduit entries.
G. Industrial Power Outlets: Industrial pattern socket outlets shall comply with IEC 60309-2.
Unless specifically detailed, single phase or 3 phase with neutral and earth 250 or 415 V
sockets shall be fitted flush or surface mounted. Rating of power socket and number of
poles shall be according to the drawings and/or data sheets.
H. Lighting Switches
1. Internal Lighting Switches: Internal lighting switches shall comply with IEC
60669 and shall be complete with box, cover plate and fixing screws. At multi-
switch positions, the switches shall be contained in multi-gang boxes.
2. Wall mounted switches shall be suitable for use at a system voltage of 220 V
and continuously rated at 10 A. Each switch terminals shall be capable of
terminating two (2) conductors (solid or stranded), each of 3 mm2 minimum.
3. Generally where a number of switches are mounted adjacent to each other,
they shall be grouped in one box and share a common switch plate, except
those fed from different supply panels or different phases.
4. Switches shall not disconnect the grounded conductor of a circuit. A switch in
a wet location or outside of a building shall be enclosed in a weatherproof
enclosure.
5. Switches for internal use shall generally be of the insulated, ivory finish
pattern unless otherwise specified. In utility and workshop areas, metal clad
enclosures and finish shall be used. Lighting switches shall be mounted in a
galvanized metal or PVC box with conduit entry facilities suitable for flush or
surface mountings as appropriate. In all cases, a sample shall be approved by
the Engineer.
6. Lighting switches for external use and wet areas shall be weatherproof and
shall be enclosed in Plastic Glass-fibre Reinforced (GRP) or galvanized metal
boxes.
7. Lighting switches shall be provided with all necessary terminals to allow
connection of circuit protective conductors as required by the 16th edition of
the IEE Regulations or IEC latest edition.
8. Multi Pole Switches: Multi pole switches shall conform to the requirements of
IEC 60669 Standard where used for the connection of fixed appliances.
9. Switches shall be installed as shown on Drawings, and for height refer to
general notes.
10. All units shall be of similar style and finish to those specified for lighting
switches and socket outlets.
11. Primary connection terminals shall be capable of receiving and satisfactorily
connecting the following stranded conductors:
10 A 3(1 x 3) mm2
20 A 3(1 x 4) mm2
25 A 3(1 x 6) mm2
A. Motor Circuit Protector: Molded case, magnetic break type with adjustable instantaneous
setting suitable for motor protection.
B. Motor Circuit Protectors are to be in compliance with IEC 60947-2, utilization category A,
sequence II (service capacity) for motor control centers and sequence III (ultimate
capacity) for motor control panels and combination starters unless otherwise indicated on
the Drawings.
D. All motors shall be provided with a safety disconnect switch, 1000 V insulation class,
category AC23, non-fused, single throw, safety type, housed in separate metallic
enclosure IP 55 with arc quenching devices on each pole, and provided with padlock.
E. When located outdoors, the switch disconnector enclosures shall be provided with U.V
resistant paint finish.
F. Switch disconnector handle and indicator markings shall be Red/yellow and is to have
provision for bypassing interlock by authorized and trained technicians. Position of handle
is to be positive and clearly indicated on cover. Locking of operating handle is to be
possible in open and closed positions. Where safety disconnect switch ratings are required
to be in excess of 250 Amps, provide “Emergency” push button stations wired directly for
trip.
G. Switch disconnectors shall comply with IEC 60664 and IEC 60947 and shall carry KEMA or
ASTA or UL certification. They shall be manufactured to environmentally friendly and
recyclable materials.
I. Control switches for electrically operated circuit breakers and motor operated
disconnectors shall be discrepancy type and arranged to operate clockwise when closing
the devices and anti-clockwise when opening them. There should be marking for
discrepancy indications. They shall be designed to prevent accidental operation, which
shall be effected by 2 independent movements.
J. The contacts of all switches and push buttons shall be strong and to have a positive wiping
action when operated.
K. All safety switches and emergency push buttons shall be clearly labeled as per
specification 260553
A. The surface of all wiring devices shall be of the manufacturer's finish according to location
and the Engineer’s approval.
3.1 INSTALLATION
A. General: Flush-mounted boxes shall be cast in concrete walls and grouted into brick
walls. Metal boxes threaded to raceways in exposed installations shall be separately
supported.
B. Boxes installed in concealed conduits or raceway systems shall be set flush with the
finished surfaces. The location of all boxes shall be easily accessible and any interference
with mechanical equipment or structural features shall be relocated as directed by the
Engineer without any additional cost.
C. Receptacles: The receptacles shall be located and installed as shown on the Drawings.
The location shall be easily accessible. Receptacles shall be so installed that the neutral
pin is always on the left side when viewed facing the installation.
D. Switches: Local wall switches near doors, shall be located at free side of doors as finally
hung, whether so indicated on Drawings or not.
E. A junction box shall be placed in the back of each wall mounted switch or socket outlet.
F. If thickness of wall does not permit such an installation, adjacent position shall be
accepted.
G. The switches shall be installed as shown on the approved Drawings. Where more than
one switch is shown for one indoor outlet box, the switches shall be installed under one
plate. Toggle switches for lighting, except for 2-way and 3-way switches shall be installed
so that the contacts are closed when the handle is in the up position.
H. Switches shall be mounted with the longer dimension vertical and operating handle in an
upward position when in the "ON" position.
I. Single pole switches shall switch the (phase) wire circuit. Neutral wire shall not run
through switches.
K. Device Plates: Device plates shall be installed with all four edges in continuous contact
with finished wall surfaces without the use of mats or similar devices. Device plates shall
be installed vertically with an alignment tolerance of 0.16 mm (1/16 inches).
L. Mounting Height: The mounting height of wall-mounted outlet and switch boxes shall be
as specified and approved by the Engineer and measured between the bottom of the box
and the finished floor.
3.2 GROUNDING
A. Provide checking, adjusting and testing operations on the wiring devices installation
including the following:
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. ENGINE GENERATORS
CAIRO - EGYPT 263213 – 2874 0
SECTION 263213
ENGINE GENERATORS
Page
PART 1 GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Submittals 2
1.4 Quality Assurance 4
1.5 Coordination 4
1.6 Project Conditions 4
1.7 Delivery, Storage And Handling 4
1.8 Spare Parts 5
1.9 Instructions And Training On Operation & Maintenance 5
1.10 Project Conditions 5
1.11 Coordination 6
1.12 Warranty 6
1.13 Maintenance Service 6
PART 2 PRODUCTS 6
2.1 Engine-Generator Set 6
2.2 Engine 8
2.3 Fuel Oil Storage 11
2.4 Control And Monitoring 11
2.5 Generator Overcurrent And Fault Protection 12
2.6 Generator, Exciter, And Voltage Regulator 13
2.7 Vibration Isolation Devices 13
2.8 Finishes 14
2.9 Source Quality Control 14
PART 3 EXECUTION 14
3.1 Examination 14
3.2 Installation 15
3.3 Field Quality Control 15
3.4 Grounding 15
3.5 Connections 15
3.6 Identification 16
3.7 Demonstration 16
PART 1 GENERAL
A. Drawings and general provisions of the Contract, including General and Supplemen-
tary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This section covers the equipment, installation and testing of diesel engine and driv-
en electric generator units. The engine generator unit/s shall be installed as indicated
on the drawings.
1.3 SUBMITTALS
A. Drawings and Data: Complete descriptive and engineering data shall be submitted.
These data shall consist of drawings and photographs in sufficient detail that the con-
struction of the equipment is indicated, together with details, specifications, perfor-
mance curves, installation drawings, schematics, and wiring diagrams; and founda-
tion drawing showing location detail and size of anchor bolts. Data submitted shall
include the following:
1. Engine Data.
a. Manufacturer.
b. Model.
c. Number of cylinders.
d. RPM.
e. Bore x stroke.
f. Rated capacity kW.
g. BMEP at rated kW (including any parasitic loads and Gen. efficiency).
2. Generator Data.
a. Manufacturer.
b. Model.
c. Rated kVA.
d. Rated kW at 0.8 PF.
e. Voltage.
f. Temperature rise above 50 C ambient for Stator and Field.
g. Class of insulation.
a. Full load.
b. 3/4 load.
c. 1/2 load.
d. 1/4 load.
B. Test Reports: Copies of the manufacturer’s certified shop test record of the complete
engine driven generator. The engine-generator log test sheets and a performance re-
view report shall be signed by the engine tester and certified by the manufacturer.
The report shall include brief outlines of all test procedures and shall compare actual
test results to the requirements of these specifications by means of calculations,
graphs, or charts.
C. Submit name and address of nearest factory authorized service and parts facility.
D. Operations and Maintenance Manuals/Charts and Spare Parts Data: Complete opera-
tions and maintenance manuals/Charts including spare parts data and wiring dia-
grams of all equipment furnished under this section.
E. Exhaust Pipe calculations to ensure the back pressure limits is within the manufac-
turer limit.
A. References Standards.
1.5 COORDINATION
A. All equipment specified in this section shall be furnished through a single manufac-
turer who shall be responsible for the design, manufacture coordination, and proper
installation and operation of the entire system and as mentioned in section division
26 Section “Basic Electric materials & methods “.
A. Power Supply: The power supply for the engine-generator accessories will be
380Y/220 Volts AC, 50 Hz, three-phase, 5-wire or as may be required by manufactur-
ers standard.
A. Manufacturer Date: The required manufacturing date of the package engine genera-
tor (s) shall be 6 – 8 months before the delivering date.
C. Packaging: In addition to the protection specified for prolonged storage, the packag-
ing of spare units and spare parts shall be similar to export packing and shall be suit-
able for long-term storage in a damp location. Each spare item shall be packed sepa-
rately and shall be completely identified on the outside of the container.
A. A list of all spare parts recommend by the manufacturer for 1000 operating hours
and required for adjustment, operation, and maintenance of the equipment shall be
submitted in accordance with the requirements set forth at the Conditions of Con-
tract.
B. In addition, all special tools required for adjustment, operation, and maintenance of
the equipment. plus the following spare parts shall be furnished with each unit:
A. Contractor shall provide instructions and training for the staff to be assigned in the
operation and maintenance of the equipment specified under this section. Training
and instructions shall be in accordance with the requirements set forth at the Condi-
tions of Contract.
1.11 COORDINATION
A. Coordinate size and location of concrete bases for package engine generators. Cast
anchor-bolt inserts into bases. Concrete, reinforcement, and formwork requirements
are specified in Division 03.
1.12 WARRANTY
PART 2 PRODUCTS
E. Steady state voltage, Steady state frequency, Voltage recover time, frequency recov-
er time, Maximum voltage Dip, Maximum frequency Dip shall comply with ISO 8528-
5 for performance class G2.
G. Noise reduction is to be achieved by silencer, sound attenuators for air inlet and out-
lets and sound absorbing wall lining. Achieve an overall Noise Rating of 85 dBA at 1 m
outside the room in any direction in accordance with ISO standards. Coordinate with
the Architectural works for the needed provisions and installations.
1. Over sizing generator compared with the rated power output of the engine
is permissible to meet specified performance.
10. Start Time: Comply with NFPA 110, Type 10, system requirements.
C. Maximum Piston Speed for Four-Cycle Engines: 2250 fpm (11.4 m/s).
1. Main Fuel Pump: Mounted on engine. Pump ensures adequate primary fuel
flow under starting and load conditions.
2. Relief-Bypass Valve: Automatically regulates pressure in fuel line and returns
excess fuel to source.
G. Comply with NFPA 110 requirements for Level 1 equipment for heater capacity.
I. Cooling System: Closed loop, liquid cooled, with radiator factory mounted on en-
gine-generator-set mounting frame and integral engine-driven coolant pump.
K. Exhaust System: The engine-generator installation shall include a critical exhaust silencer,
exhaust piping, expansion joints, stainless steel rain cap, hangers, and accessories as re-
quired for a complete operating system. Exhaust piping and insulation shall be terminat-
ed with a single pipe flange connection.
1. Hangs and supports shall be provided for the silencer and exhaust piping
such that essentially no load is transmitted to the engine exhaust connec-
tion.
2. The exhaust silencer shall be a chamber type, attenuated for low noise
emission, all welded steel construction, with suitable bracket supports for
vertical or horizontal mounting. The silencer shall be reinforced to be able
to withstand a horizontal force of not less than 2224 N at the inlet connec-
tion. The silencer size shall be such that the silencer produces half the
maximum allowable back pressure at future operating conditions with inlet
and outlet flanged connections. The silencer shall be suitable for critical
type silencing.
3. Noise level required is 85 dB (A) at one meter from air intake and outlet
louvers or as required in the drawings and bill of quantities.
5. The expansion joint in the vertical riser immediately above the engine ex-
haust connection shall be bellows type, fabricated of all stainless steel with
a flange on one end and a butt weld connection on the other end and shall
be designed for 6 mm lateral offset, and vibration isolation.
6. A stainless steel rain cap shall be furnished and installed on the exhaust
stack to prevent the entry of dust and rain.
7. Insulation: for exhaust silencer and all interior exhaust piping is to be 100
mm thick Calcium silicate molded block type of rigid hydrous calcium sili-
cate with thermal conductivity of 0.060 W/M-K. Outer covering shall be
aluminum jacket, 0.4 mm inches thick, and type 3003 or 5005 alloys with 4
mm corrugations. Jacket shall have a factory applied vapor barrier on the
inside with aluminum straps over transverse joints. Adjacent section cor-
rugations shall overlap.
B. Day Tank: Comply with UL 142, freestanding, factory-fabricated fuel tank assem-
bly, with integral, float-controlled transfer pump and the following features:
1. AC voltmeter.
2. AC ammeter.
3. AC frequency meter.
4. DC voltmeter (alternator battery charging).
5. Engine-coolant temperature gage.
6. Engine lubricating-oil pressure gage.
7. Running-time meter.
8. Ammeter-voltmeter, phase-selector switch (es).
9. Generator-voltage adjusting rheostat.
10. Fuel tank derangement alarm.
11. Fuel tank high-level shutdown of fuel supply alarm.
D. Supporting Items: Include sensors, transducers, terminals, relays, and other de-
vices and include wiring required to support specified items. Locate sensors and
other supporting items on engine or generator, unless otherwise required.
B. Ground-Fault Indication: Comply with NFPA 70, "Emergency System" signals for
ground- fault. Integrate ground-fault alarm indication with other generator-set
alarm indications.
B. Drive: Generator shaft shall be directly connected to engine shaft. Exciter shall be
rotated integrally with generator rotor.
C. Electrical Insulation: Insulation class H for stator and rotor and temperature rise
class H.
E. Construction shall prevent mechanical, electrical, and thermal damage due to vi-
bration, over speed up to 125 percent of rating, and heat during operation at 110
percent of rated capacity.
I. Windings: Two-thirds pitch stator winding and fully linked amortisseur winding.
2.8 FINISHES
A. Prototype Testing: Factory test engine-generator set using same engine model,
constructed of identical or equivalent components and equipped with identical
or equivalent accessories.
1. Tests: Comply with NFPA 110, Level 1 Energy Converters and with IEEE 115.
1. Test components and accessories furnished with installed unit that are not
identical to those on tested prototype to demonstrate compatibility and
reliability.
2. Full load run.
3. Maximum power.
4. Voltage regulation.
5. Transient and steady-state governing.
6. Single-step load pickup.
7. Safety shutdown.
8. Provide 14 days' advance notice of tests and opportunity for observation of
tests by Owner's representative.
9. Report factory test results within 10 days of completion of test.
PART 3 EXECUTION
3.1 EXAMINATION
A. Examine areas, equipment bases, and conditions, with Installer present, for com-
pliance with requirements for installation and other conditions affecting pack-
aged engine-generator performance.
3.2 INSTALLATION
A. Field Supervision and Tests: The Contractor shall include a minimum of three 8
hour working days allowance for the services of a competent manufacturer's
technical representative to check the installation, make all necessary adjust-
ments and, in the presence of the Engineer, perform acceptance tests on the en-
gine-generator unit to determine whether the equipment conforms to specified
requirements for load capacity and starting duty.
B. As part of the field test, each of the automatic shutdown devices shall be made
to be operated and the respective values recorded at which the devices actually
stopped the engine. Any adjustments required shall be made in the devices to
make the operating values correspond to those recommended by the engine
manufacturer.
C. Before running the field test, submit a copy of the proposed log sheet on which
shall be recorded the load and all corresponding temperatures and pressures as
well as the total quantity of fuel consumed during the test. The test shall consist
of operations under a load bank at the specified power rating for four continuous
hours.
D. Readings shall be taken and recorded at 15-minute intervals over the four-hour
test period.
E. The Contractor shall furnish the fuel, lubricants, load bank, instruments and all
other devices necessary for the tests.
3.4 GROUNDING
3.5 CONNECTIONS
E. Connect fuel piping to engines with a gate valve and union and flexible connect-
or.
1. Diesel storage tanks, tank accessories, piping, valves, and specialties for
fuel systems are specified in Division 23 Section “Facility Fuel-Oil Piping”.
3.6 IDENTIFICATION
3.7 DEMONSTRATION
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. STATIC UNINTERRUPTIBLE POWER
CAIRO - EGYPT SUPPLY 263353 – 2874 0
SECTION 263353
PART 1 GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Definitions 2
1.4 Submittals 3
1.5 Quality Assurance 3
1.6 Project Conditions 5
1.7 Warranty 5
1.8 Extra Materials 5
PART 2 PRODUCTS 5
2.1 Manufacturers 5
2.2 Description 5
2.3 System Operation 6
2.4 System Characteristics 8
2.5 Ups Systems 11
2.6 Rectifier Charger 12
2.7 Inverter 12
2.8 Automatic Static Bybass Transfer Switch 13
2.9 Maintenance By-Pass Switching 13
2.10 Battery 13
2.11 Controls And Indicators 14
2.12 Rack Mounted U.P.S 16
PART 3 EXECUTION 16
3.1 Examination 16
3.2 Installation 17
3.3 Grounding 17
3.4 Identification 17
3.5 Battery Equalization 17
3.6 Field Quality Control 17
3.7 Demonstration 18
PART 4 SCHEDULES 18
PART 1 GENERAL
1.2 SUMMARY
A. This Section includes, on-line, static-type, continuous duty, solid state, double
conversion uninterruptible power supply (UPS) system installation and static transfer
switch, comprising the following:
1.3 DEFINITIONS
A. Product Data: Submit full technical data of equipment for approval including:
1. Plans, front and side elevations, physical data (dimensions and weights),
installation and arrangement details for the UPS and batteries, power wiring
diagram, control / signal wiring diagram, ratings of each piece of equipment,
cabling, grounding etc.
D. Qualification Data: For firms and persons specified in "Quality Assurance" Article.
F. System is to undergo a functional and load test program approved by the Engineer,
and is to undergo a minimum 24 hours 'burn-in' test.
G. Final test procedures for each equipment shall include a check of performance
specification before and after the 24 hours 'burn-in' test.
H. Field Test Reports: Indicate test results compared with specified performance
requirements, and check the controls and indicators after installation.
1. All materials and parts comprising the UPS shall match the project
specifications and local codes.
2. All components shall be stored, installed, sealed and dust covered in a proper
way matches the manufacture recommendations ensuring maximum
reliability. The manufacturer is to conduct inspection on incoming parts,
modular assemblies, and final products.
3. The manufacture or his representatives (agent) is responsible for installation,
regular and emergency maintenance and providing spare parts of all units and
components.
4. Failure to satisfy Engineer may disqualify a manufacturer.
IEEE 485 IEEE Recommended Practice for Sizing Lead-Acid Batteries for
Stationary Applications”
1.7 WARRANTY
A. Provide list of manufacturer's spare parts for five years’ operation together with
current prices.
PART 2 PRODUCTS
2.1 MANUFACTURERS
2.2 DESCRIPTION
A. System: UPS system is to be online, continuous duty, double conversion and class
VFI-SS-111 according to IEC 62040-3.
C. General: System is to be interposed between normal A.C. power supply and critical
load, to secure a minimum period of continuity of no-break battery back-up for the
durations shown on drawings, in case of failure of normal A.C. supply and maintain
output voltage, frequency and phase deviation within specified tolerances.
D. System is to be 100% fully rated, for number and capacity as shown on drawings;
which implies complete UPS unit(s). UPS is to be maintained (continuously supplying
load through the inverter), with automatic no-break transfer to or retransfer from
alternate source (bypass) in case of failure or overload on rectifier- battery-inverter
system. System is to employ decentralized bypass technique so that each UPS unit is
to be provided with its own static bypass transfer switch. Each UPS unit is to be
provided with its own master controller. Master and slave configuration is not
acceptable.
E. Normal A.C. power supply will be available from one protected source fed from
either normal A.C. network or from A.C. Characteristics of output of generator set
(when provided) and UPS system are to be coordinated for best results. Study and
advice on special requirements of generator characteristic output and stability.
F. UPS Bypass and Output Neutral shall be designed to continuously carry twice the full
load phase current.
G. System overall efficiency is not to be less than [94] % at full load and [95] % at half
load.
H. Noise level of complete assembly is not to exceed [65] dB(A) at 1.0 m distance
anywhere within UPS room.
I. Surge suppression: Protect internal UPS components from surge that enter at each
AC power input connection
1. Normal Conditions:
B. Load is supplied with power flowing from the normal power input terminals, through
the rectifier-charger and inverter, with the battery connected in parallel with the
rectifier-charger output. Upon loss of normal a.c. supply, battery is to continue
supply of no-break power to inverters, which then free-run on self- generated UPS
frequency reference.
3. Over-temperature is sensed.
4. Retransfer to Inverter:
1. Turning the inverter off causes the static bypass transfer switch to transfer the
load directly to the normal ac supply circuit without disturbance or
interruption.
2. Turning the inverter on causes the static bypass transfer switch to transfer the
load to the inverter.
E. Full Isolation: Load is supplied, bypassing the UPS. Normal UPS ac input circuit,
static bypass transfer switch, and UPS load terminals are completely disconnected
from external circuits.
F. Maintenance Bypass: Load is supplied, bypassing the UPS. UPS ac supply terminals
are energized to permit operational checking, but system load terminals are isolated
from the load.
G. Normal: Normal UPS ac supply terminals are energized and the load is supplied
through either the static bypass transfer switch and the UPS rectifier-charger and
inverter, or the battery and the inverter.
H. Environmental Conditions:
A. Rectifier/Charger Input:
1. Nominal net system power output rating in kVA: as shown on drawings with
load power factor 0.9 lag.
D. Battery
A. Materials and Parts: Electronic devices are to be solid state, hermetically sealed.
Indicator lights are to be twin LED type, those denoting blown fuse conditions are to
be seen by operator without removing panels or opening cabinet doors.
D. Coordinate this article with "Basic Battery Monitoring" Article if battery monitoring is
included. Coordinate with Division 26 Section "Electrical Power Monitoring and
Control."
1. Connectors and network interface units or modems for data transmission via
RS-232 link or USB
2. BMS Port: Each unit shall be equipped with an RS 485 serial port
communication board capable of implementing the lon, backnet, Modbus,
OPC as specified in BMS System.
3. Data Port: Each unit shall be equipped with an SNMP communication board
for connection to an Ethernet network.
4. Software designed for control and monitoring of UPS functions and to provide
on-screen explanations, interpretations, diagnosis, action guidance, and
instructions for use of monitoring indications and development of meaningful
reports. Permit storage and analysis of power-line transient records. Designs
for Windows applications, software, and computer are not included in this
Section.
5. Software and Hardware: Compatible with that specified in Division 26 Section
"Electrical Power Monitoring and Control."
G. Suitable casters and leveling pads shall be included to suite installing the equipment
directly on floor.
I. Ventilation: units shall be provided with forced-air, cooling system in each UPS
module to ensure components operate within environmental ratings suitable for
best performance. Air is to enter from air inlets near to the bottom of cabinet
through input filters, and discharge from outlets near to the top. Redundant fans or
blowers are to be provided for ventilating each enclosure to keep on the same
performance in case of one fan failure. Inlet air temperature shall be monitored and
displayed to initiate alarm if maximum working temperature is exceeded.
A. Rectifier/charger unit is to be Insulated Gate Bipolar Transistor (IGBT) type for UPS
ratings 200 kVA and below; and IGBT or 12 pulse type with filter (to reduce feedback
current harmonics to specified values) for ratings above 200 kVA.
B. The unit is to have mainline circuit breaker, EMI transient suppressor network, I/O
filters , control circuitry providing constant V/I electronic current limiters and is to
be automatic with soft start-up (walk-in) feature over a period of approximately 15
seconds.
E. Rectifier charger shall be automatically turned off without opening the circuit
breaker in case of sensing high DC voltage, AC over/ under voltage of (10%), loss of
phase in input and loss of normal AC input.
F. Using IGBT with vector control design to suit power output requirements and
protect against primary power surges, lightning transients, under-voltage and over-
voltage conditions. Output is to be passed through LC filters to D.C. bus.
2.7 INVERTER
A. Inverter is to employ IGBT technology in three leg, vector control or high frequency
switching and real time control technique, and complete with filters. Inverter start-
up is to be automatic, to reach full voltage within milliseconds and deliver power to
the load during less than one (1) seconds. Inverter is to start at any load including
short-circuit.
E. Inverter shall shut down if the battery reaches the low DC shut down level, and shall
be automatically restarts and returns to normal when AC power return.
A. Static bypass switch continuously rated at (125% FL), hybrid type (make-before-
break), consists of one pair of silicon controlled rectifiers (SCR’s) per phase, each pair
connected in parallel with logic thyristor assembly isolatable or completely
removable for maintenance.
B. Test position is to permit testing of static switch while load is being fed from bypass
power circuit.
2.10 BATTERY
A. High rate discharge, valve-regulated, premium, maintenance free, sealed lead- acid
(gas recombination) type cells; with automatically re-closing explosion proof safety
vents.
E. Enclosures of welded construction and formed from heavy gauge steel with added
supports to retain cabinet square-ness and integrity during harsh shipping and
handling conditions.
F. Adjustable battery rails or trays are to be provided to allow for multiple battery
configurations and facilitate battery upgrades in the future, Cabling is to be routed
down the sides of the cabinet, away from the front of the batteries allowing full
access for easy maintenance, series wiring is to be routed efficiently and neatly with
G. A load rated circuit breaker for over current protection and isolating the battery
from the UPS module for maintenance purposes shall be furnished; fused switches
shall not be acceptable. The battery circuit breaker shall be installed inside the
battery enclosure when the matching cabinet is provided. Remote tripping and
position indicating shall be included as required by the UPS module.
H. Battery calculations are to be carried out by UPS supplier and submitted for
approval, based on the following:
A. Mimic Panel: UPS assembly is to include a mimic diagram with digital and LED
displays, indicating instruments and control devices, in true relative positions.
B. Minimum displays, indicating devices, and controls include those in lists below.
Provide sensors, transducers, terminals, relays, and wiring required to support listed
items. Alarms include audible signals and visual displays.
a. Normal operation.
b. Load-on bypass.
c. Load-on battery.
d. Inverter off.
e. Alarm condition.
4. Remote panel control and indicators are to include at least the following:
a. Inverter on-off.
b. UPS start.
C. Dry-form "C" contacts shall be available for remote indication of the following
conditions:
1. UPS on battery.
2. UPS on-line.
3. UPS load-on bypass.
4. UPS in alarm condition.
5. UPS off (maintenance bypass closed).
D. Emergency Power off Switch: Capable of local operation and operation by means of
activation by external dry contacts.
B. This unit shall allow manual transfer of connected equipment to utility power via a
maintenance bypass switch, permitting scheduled maintenance or UPS replacement
without disrupting data center power.
C. The UPS shall include data line surge protection, transient voltage surge protection,
and optional communications for shutdown and reporting. The UPS with minimum 8
output receptacles. A rack mounting rail kit is included as standard.
D. Optional telescoping rack rails mount to the sides of the UPS for easy installation
into a rack enclosure. A standard tower support base ships with the UPS.
PART 3 EXECUTION
3.1 EXAMINATION
A. Installation conditions which may affect the UPS performance shall be examined by
engineer before installation, Proceed with installation only after unsatisfactory
conditions have been corrected.
A. Equipment Bases: Ensure that concrete bases and foundations provided for
installation of equipment are constructed in accordance with approved shop and
construction drawings and equipment manufacturers' drawings and that holes for
fixing bolts and provisions for passage of cables etc. are provided as required.
B. For supported equipment, install epoxy-coated anchor bolts that extend through
concrete base and anchor into structural concrete floor.
3.3 GROUNDING
3.4 IDENTIFICATION
2. Test manual and automatic operational features and system protective and
alarm functions.
3. Test communication of status and alarms to remote monitoring equipment.
D. The UPS system will be considered defective if it does not pass tests and inspections.
E. Record of Tests and Inspections: Maintain and submit documentation of tests and
inspections, including references to manufacturers' written instructions and other
test and inspection criteria. Include results of tests, inspections, and retests.
3.7 DEMONSTRATION
PART 4 SCHEDULES
A. Provide UPS rated as shown on the drawings and each for minutes shown on the
drawings. Quantities as shown on the drawings and Bill of quantities.
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. LOW VOLTAGE POWER FACTOR
CAIRO - EGYPT CORRECTION EQUIPMENT 263533- 2874 0
SECTION 263533
PART 1 GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Submittals 2
1.4 Quality Assurance 2
1.5 Standard Products 3
1.6 Extra Materials 3
1.7 Substitution of Materials And Methods 3
1.8 Safety Signs 3
1.9 Warranty and Product Quality 3
PART 2 PRODUCTS 3
2.1 Manufacturers 3
2.2 General Description 3
2.3 System Configuration 4
2.4 Fault Current Considerations 5
2.5 Performance Requirements 6
2.6 Withstanding Transients 6
PART 3 EXECUTION 6
3.1 Inspection 6
3.2 Installation 6
3.3 Field Quality Control 7
3.4 Maintenance 7
PART 1 GENERAL
1.2 SUMMARY
A. This section specifies capacitor-type power factor correction equipment for use in
electrical power systems rated 600 Volts and less.
1.3 SUBMITTALS
A. Product Data: For products specified, include data on features, components, ratings and
performance.
B. Drawings: Include dimensioned plan, elevation views of enclosure and details of control
panels.
C. Special Studies: For the effect of the following systems (actual selected sizes of the
project) on the capacitors:
1. Motors.
2. Generators.
D. Three (3) complete original sets of operation and maintenance manuals. Each set shall
include:
B. Standard catalogue items and IEC (or NEMA) sizes, ratings, capacities and voltages shall
be given preference.
C. Products and Manufacturer shall be nationally “listed”, “labeled” and “approved” from
local concerned authority.
A. All access panels to the electrical equipment shall have appropriate warning labels.
A. One year warranty after the date of Substantial Completion, for the power factor
correction equipment shall be provided, for the materials and manufacturing quality
control.
B. Contractor shall agree to repair or replace the equipment that does not comply with the
requirements or fails in work.
PART 2 PRODUCTS
2.1 MANUFACTURERS
A. The system shall consist of a power factor correction unit(s) installed in its own enclosure
to achieve at least 0.93 power factor correction, IP 42 , for indoor installation, and shall be
an integral part of low voltage panel board. System includes a separately mounted
Low Voltage Power Factor Correction Equipment Section 263533
Urbanium New Administrative Building (Prj. 2874) Sheet 3 of 7
current transformer sensing current in the power circuit being corrected and providing
input to the system controls. Capacitor shall be of the dry type and shall be capable of
withstanding twice its rated voltage for 10 seconds at rated frequency between terminals
and container. Capacitor shall also withstand 3 kV for 10 seconds, capacitor losses shall be
less than 0.5 W/KVAR.
A. The basic types of power factor correction equipment used to incorporate the capacitor
cells may include:
A. Air-Core Type inductors and power bus-work in the power factor correction units shall
withstand the mechanical forces that occur when the prospected short circuit currents
flow.
B. These currents shall be limited by the appropriate protective means, and the bracing of
these components shall withstand the peak asymmetrical symmetrical short-circuit
current (S.C.C.) of the system.
C. The switching device should be over sized (as mentioned below) to exceed the capacitor
nominal current as follows:
A. The controls shall continuously sense the power factor on the circuit being corrected and
when it differs from the target settings for more than 10 seconds, system shall bring the
corrected circuit power factor closer to the target setting.
B. The supply cables and the control and protection devices of selected capacitor bank
ratings shall be oversized to at least (1.3 x 1.15 = 1.5) times their current rating (other
than installation derating requirements)
A. The construction of the system should give excellent withstanding capability to current
transients resulting from frequent switching of the stages of a multi stage capacitor bank.
PART 3 EXECUTION
3.1 INSPECTION
A. Examine conditions under which centralized automatic power factor capacitor assemblies
are to be installed. Notify Engineer in writing of conditions detrimental to proper
completion of the work. Do not proceed with work until unsatisfactory conditions have
been corrected.
3.2 INSTALLATION
C. Mount the switchboard assembly on flush steel aligning channels elevated above floor
level by a concrete pad and as noted on Drawings. Provide aligning shims to achieve level
installation where channels cannot be provided.
D. Ensure that centralized automatic power factor capacitor assemblies are shipped in
sections which can be fitted through the available structures and openings available.
E. Bond together the centralized automatic power factor capacitor assemblies structure,
sections and all conduits terminating at the same with a 120 mm2 bare copper earth
(ground) cable, and connect to the switchboard earth (ground) bus and to the earthing
(grounding) grid as required. Provide conduits terminating at centralized automatic
power factor capacitor assemblies with earthing (grounding) Wedges of the required size.
G. Provide 6.35 mm minimum thick x 60 cm wide insulation material (on ground) in front of
centralized automatic power factor capacitor assemblies and rear of freestanding
equipment and extend 30 cm beyond ends.
J. Provide control fuses, with five spare fuses for each rating.
A. Upon completion of installation of equipment and after circuitry has been energized, test
equipment to demonstrate compliance with requirements. When possible, field-correct
malfunctioning units, then retest to demonstrate compliance.
1. Perform insulating resistance test on each pole, phase-to-phase and phase-to- earth
for one (1) minute. Minimum test voltage to be 1000 Volts D.C. with a minimum
resistance of 100 mega ohms.
2. Check centralized automatic power factor capacitor assemblies for continuity and for
short circuits.
3. Notify Engineer of any abnormalities.
3.4 MAINTENANCE
A. All maintenance and inspection on the capacitor assembly shall be done with the system
disconnect device in the open position.
B. Maintenance and inspections (before handing over of the installation) should be limited
to 15 minutes or less so not to affect utility billing.
C. An annual inspection of the capacitor cell (before the handing over of the installation)
shall be done to identify failing capacitor cells (a bulged cover is the symptom to watch
for).
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. AUTOMATIC TRANSFER SWITCHES
CAIRO - EGYPT 263600 - 2874 0
SECTION 263600
Page
PART 1 GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Submittals 2
1.4 Quality Assurance 3
1.5 Warranty 3
1.6 Delivery, Storage And Handling 4
1.7 Instructions And Training On Operation And Maintenance 4
PART 2 PRODUCTS 4
2.1 Manufacturers 4
2.2 Change Over Switch 4
2.3 Enclosure 6
2.4 Testing 6
PART 3 EXECUTION 7
3.1 Installation 7
3.2 Operational Testing 7
PART 1 GENERAL
A. Drawings and general provisions of the Contract, including General Conditions, Conditions
of Particular Application and Division-1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This section covers the furnishing, the installing, and the placing in operation of the
Automatic Transfer Switch.
1.3 SUBMITTALS
A. Drawings and Data: One line diagram of transfer switch (change over switch) assembly
and elementary or schematic and wiring diagram of the unit in plastic lamination
permanently secured to the inside of the front enclosure door. An interface equipment
connection diagram showing all conduits and wiring between the transfer switch all other
related equipment. The one-line diagram shall show interlocking provisions and
cautionary notes, if any.
1. It shall also general arrangement and complete dimensional layout of the equipment.
2. Above drawings shall show components description, technical ratings of equipment
and materials.
3. Single Line Diagram: Show connections between transfer switch, power sources
B. Certificates: Test certificates shall be executed and submitted prior to final inspection and
acceptance in accordance with the requirements of IEC standards. The certified tests
reports shall show date, time and duration of the overload, endurance and temperature
tests, and that the unit under test was not de-energized during the test sequence. Three
certified copies of each test certificate shall be submitted to the Owner’s Representative.
C. Test Plan: Test plan and test procedures for the acceptance tests. The test plan and test
procedures shall explain in detail, step-by-step actions and expected results to
demonstrate compliance with the requirements specified. The procedure shall also
explain methods for simulating the necessary conditions of operation to demonstrate
system performance.
D. Acceptance Tests: Test reports in booklet form showing all field tests are performed to
adjust each component and to prove compliance with the specified performance criteria,
upon completion and testing of the installed system. The reports shall include the
manufacturer, model number, and serial number of test equipment used in each test.
Each report shall indicate the final position of controls and operating mode of the system.
B. Source Limitations: Obtain transfer switch and related control panels through one source
from a single manufacturer.
C. Installer’s Qualifications: Contractor shall submit data showing that he has successfully
installed systems of the same type and design as specified herein, or that the Contractor
has a firm contractual agreement with a subcontractor having not less than ten years
experience in the design and installations of such system. Data shall include names and
location of at least two installation he or his referenced subcontractors has installed such
systems. The references shall indicate type and design of each system and certification
that each systems has performed satisfactorily in the manner intended for not less than
three years.
1.5 WARRANTY
A. Contractor shall agree to repair or replace the equipment that does not comply with
the requirements or fails in work.
B. In addition to the protection specified for prolonged storage, the packaging of spare parts
(If Any) shall be prepared for export packing and shall be suitable for long-term storage in
a damp location. Each spare item shall be packed separately and shall be completely
identified on the outside of the container.
C. Instructions for the servicing of equipment while in long-term or prolonged storage shall
accompany each item of equipment. An enclosed instruction with each package shall be
noted on the exterior of the package and shall be in the Arabic and English languages.
D. Verification of Dimensions: The Contractor shall become familiar with the details of the
work and working conditions, shall verify dimensions in the field, and shall advise the
Owner’s Representative of any discrepancies before performing the work.
E. Spare Parts: All lists of all spare parts required for adjustment, operation, and
maintenance of the equipment for a period of three years from the date of the certificate
of completion shall be provided in accordance with the requirements of Section 01605,
General Equipment Stipulations.
A. Contractor shall provide instructions and training for the staff to be assigned in the
operation and maintenance of the equipment specified under this section. Training and
instructions shall be in accordance with the requirements set forth at the Conditions of
Contract.
PART 2 PRODUCTS
2.1 MANUFACTURERS
A. Shall be electrically operated, mechanically held, fully protected, complete with voltage
B. Shall be suitable for use in emergency or standby systems described in NFPA 70. Transfer
switch shall comply with IEC Standard. Test certificate and test reports are shall be
provided.
C. Transfer Switch shall have a continuous phase or main current rating equal to or exceed
the rating shown but, in no case, less than 125 percent of the full load rating of the
emergency power source, 380 Volts, 4P, 50 Hz and symmetrical interrupting capacity as
per final short circuit calculation approved by the engineer.
D. Override Time Delay: Time delay to override monitored source deviation shall be
adjustable from 0.5 to 6 seconds and factory set at 1 second. The device shall detect and
respond to a sustained voltage drop of 30 percent of nominal voltage between any two
of the normal supply conductors, and initiate transfer action to the emergency source
and start the engine-driven generator set after the set time period. The pickup voltage
shall be adjustable between 90 to 100 percent of nominal and factory set 90 percent. The
dropout voltage shall be adjustable from 65 to 70 percent of the pickup value, and factory
set at 70 percent of nominal voltage.
E. Transfer Time Delay: Time delay before transfer to the emergency power source shall be
adjustable from 0.2 to 120 seconds and factory set at 10 seconds. The device shall
monitor the frequency and voltage of the emergency power source and transfer when
frequency and voltage is stabilized at or above 90 percent of rated values. The pickup
voltage shall be adjustable from 85 to 100 percent of nominal, and factory set at 90
percent. The pickup frequency shall be adjustable from 90 to 100 percent of nominal and
factory set at 90 percent.
F. Return Time Delay: Time delay before return transfer to the normal power source shall
be adjustable from 2 to 30 minutes and factory set at 30 minutes. The time delay shall be
automatically defeated upon loss or sustained under voltage of the emergency power
source, provided that the normal supply has been restored.
G. Auxiliary Contacts: Two normally opened and two normally closed auxiliary switches shall
operate when the transfer switch is connected with the normal power source, and two
normally opened and two normally closed switches shall operate when the transfer
switch is connected with the emergency power source.
H. Control Panel: The transfer switch shall be equipped with a microprocessor based control
panel. This panel will perform the operational and display functions of the transfer switch.
The panel digital display shall be accessible without opening the door of enclosure.
I. Supplemental Features: The transfer switch shall also be furnished with the following:
K. Green Indicating Lights: A green indicating light shall supervise the normal power source
and shall have a nameplate engraved NORMAL.
L. Red Indicating Lights: A red indicating light shall supervise the emergency power source
and shall have a nameplate engraved EMERGENCY.
2.3 ENCLOSURE
B. Wiring shall be color coded or the wires shall be permanently tagged near the terminal
at each end with the wire number shown on approved detail drawings.
D. Finishing: Painting required for surfaces not otherwise specified and finish painting of
items only primed at the factory shall be as Manufacturer’s recommendations.
2.4 TESTING
B. Factory Testing: In addition to other factory tests, each completely assembled transfer
switch unit shall be subjected to dielectric and operational tests, and withstand tests.
D. Dielectric Tests: Tests shall be performed in accordance with NEMA ICS 1. Wiring of each
control panel shall be subjected to voltage surge tests as stipulated in IEEE C37.90.1.
Impulse withstand rating tests shall be performed in accordance with the requirements of
NEMA ICS 1.
E. Operational Tests: Tests shall be performed and shall demonstrate that the operational
sequence of each transfer switch unit conforms to the requirements of the specifications
with regard to operating transfer time, voltage, frequency, and timing intervals.
PART 3 EXECUTION
3.1 INSTALLATION
A. The transfer switch shall be installed as indicated and in accordance with approved
Manufacturer's instructions.
A. Following completion of the installation of each of the transfer switch, the Contractor
shall perform operational tests in accordance with the written instructions of the
manufacturer after having made proper adjustments and settings to demonstrate that
each of the transfer switch functions satisfactorily and as specified. The Contractor shall
advise the Owner’s Representative not less than 5 work days prior to the scheduled date
or dates for operational testing, and shall provide certified field test reports to the
Owner’s Representative within 2 calendar weeks following successful completion of the
operational tests. The test reports shall describe all adjustments and settings made and
all operational tests performed.
1. Contractor shall provide instructions and training for the staff to be assigned in the
operation and maintenance of the equipment specified under this section. Training
and instructions shall be in accordance with the requirements set forth at the
Conditions of Contract.
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. LIGHTNING PROTECTION FOR
CAIRO - EGYPT STRUCTURES 264113 – 2874 0
SECTION 264113
Page
PART 1 GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Submittals 2
1.4 Quality Assurance 3
1.5 Coordination 3
PART 2 - PRODUCTS 3
2.1 Lightning Protection System Components 3
2.2 Design Criteria 4
PART 3 - EXECUTION 6
3.1 Installation 6
3.2 Corrosion Protection 7
3.3 Field Quality Control 8
3.4 Testing 8
3.5 Personnel Training 8
PART 1 GENERAL
1.2 SUMMARY
A. This Section includes lightning protection for buildings and building site components
.including but not limited to
B. The words "earth" and "earthing" as used herein are synonymous with the words
"ground" and "grounding" and may be used interchangeably within this specification.
1.3 SUBMITTALS
A. Product Data: During the time of the contract and as required by the Contract
program, submit to the Engineer three (3) copies of descriptive literature, technical
data, and maintenance recommendations (from the equipment Manufacturer),
catalogues etc for air terminals, fasteners, test links, connectors, wall inserts , bolts ,
earth point , rods and any accessories forming part of the lightning protection
system.
C. Qualification data for firms and persons specified in "Quality Assurance" Article to
demonstrate their capabilities and experience. Include lists of completed projects
with project names and its locations, Engineer/Consultant and Owner. The firm
should have at least two years of success full installation experience.
D. Retain first paragraph below for air terminals mounted on single-ply membrane
E. Certification, signed by Contractor, that roof adhesive for air terminals is approved
by manufacturers of both the terminal assembly and the single-ply membrane
roofing material.
H. As-Built Drawings: Indicate nature of soil, special earthing arrangements, date and
particulars of additives to soil or in bore-holes if used, test conditions and results
obtained.
1. Local Codes.
2. Code of practice for protection of structures against lightning: BS EN 62305.
1.5 COORDINATION
B. Coordinate installation of air terminals attached to roof systems with roofing work as
necessary to interface installation of lightning protection system with other works.
PART 2 - PRODUCTS
C. Roof Main Conductors: Bare annealed copper strips of cross sectional area 25 mm x
3 mm. any location where the tape is in view of general public, PVC covered tape
(color to the approval of the Engineer) shall be used.
D. Ground Rod: Solid copper clad steel minimum 20 mm diameter x minimum 3.6 m
length (in 1200 mm sections).
G. Accessories: Supports, joints, fasteners, clamps, bonds, test links, etc., are to be
copper or copper alloy and specially manufactured for the purpose. Clamps and
connectors are to be specifically designed and sized for clamping and connecting to
the various shapes and surfaces of bonded metalwork. Provide bimetallic connectors
between different materials. Galvanized or plated steel nails, screws and bolts will
not be accepted on copper installations.
H. Flexible Bonding Straps: Flexible annealed copper braid, 20 x 3 mm, suitable for
bonding flat surfaces, cut to length required and with drilled flat terminals for bolted
connections. Provide special bimetallic alloy terminals for joining to aluminum
conductive parts.
J. Test Links: Two-bolt split-coupling, copper alloy, made to join two ends of down
conductor specified. Plate indicating position and number of electrodes is to be fitted
above each test link.
A. Provide horizontal conductors around periphery (or parapet), and along inner edges
of roofs that are higher than adjacent parts, unless they fall in zone of protection of a
B. Space the down conductors at 10m or 15m or 20m according to relevant class of
lightning protection system. Every down conductor is to:
1. Have test link above earth for testing earth termination network.
2. Be protected against corrosion.
3. Terminate in an earth electrode (horizontal or vertical as per design require-
ments).
4. Be insulated and installed in PVC conduit from test link to electrode connec-
tion point (to reduce potential gradient at earth level which otherwise would
be lethal to humans or animals).
F. Provide bonding between the earth termination network of the lightning protection
system and earth networks of all other services to ensure a common earthing
system. The resistance to ground should, in this case be the lowest value needed for
any of the individual services. Combined resistance to ground of whole network is
not to exceed 10 Ohm.
G. Interconnect and bury ground electrode conductors at least 0.6 m below ground
surface and minimum 1.0 m from building foundations.
3. Unless otherwise indicated, following are typical applications for using various
types of SPDs
PART 3 - EXECUTION
3.1 INSTALLATION
A. Install conductors with direct paths from air terminals to ground connections. Avoid
sharp bends and narrow loops.
F. Delete two paragraphs and associated subparagraphs below if NFPA 780 compliance
is specified; retain if specifying bonding requirements that exceed minimum UL 96A
requirements. See Editing Instruction No. 3 in the Evaluations. Coordinate with
Drawings for counterpoise requirements, if any.
H. Down conductors are to follow most direct path between air terminals and earth pit,
avoiding sharp bends and narrow loops. Where necessary, the formation of loops in
down conductors shall not violate the code restrictions in terms of the gap formed
across the loop.
J. Clean and treat contact surfaces with non-corrosive compound. Protect joints
between dissimilar metals from moisture by inert, tenacious material, and with
overlapping joints not less than 30 mm long. Provide as few joints and bonds as
possible and make mechanically and electrically effective by clamping, bolting or
exothermic welding. Cross-sectional areas of joints and bonds are not to be less than
that of main conductor.
L. Extend 150 mm below top of earth rod inside the inspection/earth pits. Cover earth
rod connector with suitable protective compound, which can be easily removed for
inspection. Connector is not to be covered with backfill material and is to remain
clean.
A. Do not combine materials that can form an electrolytic couple that will accelerate
corrosion in the presence of moisture unless moisture is permanently excluded from
junction of such materials.
3.4 TESTING
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. LIGHTING
CAIRO - EGYPT 265100 - 2874 0
SECTION 265100
LIGHTING
Page
PART 1 GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Submittals 2
1.4 Quality Assurance 4
1.5 Delivery, Storage And Handling 4
PART 2 PRODUCTS 4
2.1 Manufacturers 4
2.2 General 5
2.3 Lighting Fittings, General 6
2.4 Led (Light Emitting Diode) Lighting Fixtures 7
2.5 Lamps 8
2.6 Drivers 9
2.7 Emergency Lighting Power Unit 9
2.8 Exit Signs 11
2.9 Lamps 11
2.10 Landscape Lighting 11
PART 3 EXECUTION 11
3.1 General 11
3.2 Inspection 11
3.3 Installation 12
3.4 Installation Supervision 13
PART 1 GENERAL
1.2 SUMMARY
A This section covers partially the work of indoor lighting and ancillary fittings and the
work of outdoors lighting as required by the Contract and includes the following
items:
B Indoor lighting and ancillary fittings of service areas in all project locations are
covered under this section.
C Extent of lighting work and ancillary fittings covered by this section are indicated on
Drawings.
D Related Sections
E The following sections include requirements, which relate to work of this section:
1.3 SUBMITTALS
a. LED module Data: Trade, model, origin, type, wattage, lumen, color
rendering, color temperature, lifetime and efficacy.
b. Driver Data: Trade, model, origin, type, P.F, ignition time, approval
B Detail layout shop drawings are coordinated with all other trades (architectural,
HVAC, fire alarm, firefighting, etc.) These drawings shall identify, but not limited to,
the following:
C Product Certificates.
1. Test report for LED of the luminaire according to IES LM-80, measuring the
lumen depreciation of solid-state lighting sources, such as LED packages,
modules and arrays.
2. Test report for luminaire according to IES LM-79, Electrical and Photometric
tests.
3. Test Report for luminaire according to LM82, Characterization of LED Light
Engines and LED Lamps for Electrical and Photometric Properties as a Function
of Temperature
4. Thermal management test report, in situ temperature measurement testing
(ISTMT) according to TM-21-11.
1. Submit sample for each type of lighting fixture specified in the lighting fixtures
schedule for approval.
2. Spare parts data
3. Detailed painting procedure to meet requirements
E Calculations as per proposed Vendor’s software to verify the design, layout, furniture
and code lux values.
A Reference Standards: The work to be performed under this section shall be in strict
compliance with the applicable regulations and standards.
D In case of conflict among the referenced standards and codes, the more stringent
provision will govern.
E In case of conflict among the specifications, drawings and BOQ, the more stringent
provision will govern.
A Materials and products shall be securely packed for delivery, with waterproofed type
providing protection against excessive heat, humidity and water damages.
PART 2 PRODUCTS
2.1 MANUFACTURERS
2.2 GENERAL
A Provide all new lighting fittings, wall brackets, lamps, poles, auxiliary lighting units
and other fixtures and materials, including proper space, and complete the interior
lighting installations as shown on Drawings, specified and required.
C Luminaires have been selected to provide the illumination levels in accordance with
Lighting Handbook, IES. If the space envelope and/or furniture layout of any facility
is changed from Drawings, the Contractor shall adjust the lighting layout for that
space to maintain these standards.
F The Contractors shall produce upon request, the photometric data for any luminaire
specified or supplied.
G All luminaries shall be provided with a lamp compatible with the control gear used.
I All flexible cords shall be anchored at both ends such that the cord is free from
strain.
J Any plastics used in the luminaire shall be light and UV stable and shall be suitable
for their application.
K All sheet steel components shall be suitably pre-treated and electrostatically spray-
painted using acrylic polyester or epoxy powders.
M Louvers shall be restrained to prevent them from failing out of the body of the
luminaire under normal conditions and when relamping. Metal louvers shall be
earthed to the body of the luminaire or the earth terminal.
N Diffusers shall be restrained to prevent them from falling out of the body of the
luminaries under normal conditions and when relamping.
P All lights have on their packaging a description of what they are and a position
number which matches that in the project manual.
R If the supplier or contractor should have doubts about the quality of any materials,
construction, equipment or installations from other companies particularly with
regard to accident, prevention, and if these things will affect what is defined in the
project manual, he shall immediately report this in writing.
T When submitting the tender, the bidder shall provide the following technical
specifications
U For the prototypes and the series lights in the form of a report:
V The lights shall be examined before delivered to ensure they are capable of the
required performance;
W After the award of the contract this shall be verified by laboratory testing. The client
reserves the right to have these tests carried out by an institution of his own
choosing
X For all areas, luminance calculations and luminance distribution graphs conforming
to the applicable statutory requirements shall be presented and must be approved
(horizontal and vertical).
B Wiring: Connection to the Main Circuit Wiring Shall Be 3-Wire of A Minimum Core
Size of 3 Mm2, Earthing Shall Be Connected. The Wiring from Ceiling Rose Shall Be
Heat Resisting.
C The Contractor shall not order any lighting fitting until final approval of the type,
color and surface finish has been given by the Engineer.
D Lamps and Lamp-holders: Lamps shall be provided for each lighting fitting. Service
bases wattage and mounting shall be compatible with the fitting specified. Lamps
operating voltage shall be single phase, 220 V, 50 Hz.
A Provide LED lighting fixtures shall be in accordance with the Fixture Schedule.
B LED lighting fixtures and drivers shall be from the same manufacture and shall be
tested and certified as whole Luminaire.
F Ingress protection for indoor, and outdoor luminaires shall be as indicated on the
drawings.
G The LED luminaire shall be designed and suitably rated to ensure correct operation
and continuous trouble free service under the prevailing climatic conditions. The
luminaire shall be designed to withstand the effects of direct sun exposure during
the day and dusty weather conditions including the occasional sand storm. The
luminaire manufacturer shall guarantee the performance and life time claims of;
lumen maintenance and luminaire life of the luminaire under the stated climatic
conditions.
I LED fixtures shall be modular backlight and allow for separate replacement of LED
lamps and drivers. User serviceable LED lamps and drivers shall be replaceable from
the room side.
J The classification of the risk group shall meet the requirements of IEC 62471 and The
LED binning shall be as defined by ANSI in the C78.377 standard - MacAdam color
ellipse.
K Housing:
1. Reflectors and lenses must be designed so that they do not affect neither the
electrical (e.g. risk of short circuits in misplaced metal reflectors) nor the
mechanical stability of the LED (eg. by damaging the LED components).
2. Optical components, each according to the product and the field of
implementation, must be protected against damage by radiation (clouding of
the lens), mechanical stress, etc.
3. Solder Connections must be produced according to the data sheet and shall
not affect the function of the LED.
M Binning:
1. In the manufacturing process the LEDs and their component features are
subject to a relatively large dispersion in different areas. The selection of the
LEDs according to different finely scaled classes is called "binning".
2. A detailed list of the binnings and the associated data and diagrams of a LED
must be provided by the manufacturer in order to understand the
photometric and electro technical measurement values.
N Luminaires must be tested to IES LM-79, IES LM-80 and IES LM-82 standards, with
the results provided as required in the Submittals paragraph of this specification.
2.5 LAMPS
B LED lamps shall have a color temperature as indicating in the lighting schedule for
indoor installation and outdoor installation or as indicated in the drawings, a CRI of
80 minimum, and a lumen maintenance L70 rating of 50,000 hours minimum.
C LED lamps shall comply with NEMA SSL 4 “SSL Retrofit Lamps: Suggested Minimum
Performance Requirements”.
D Adequate spacing shall be left between wall and bracket-mounted lighting bulbs.
E The fixed wiring to a fitting shall terminate adjacent to the fitting in a conduit box.
Final connection to the fitting being carried out silicon rubber insulated pull through
flexible conduit.
F Final connections between fixed wiring systems and lighting fittings shall in all cases
be carried out in heat resisting flexible cables. Under no circumstances shall cables
insulated with general purpose PVC be used for final connections to any lighting
fittings.
G The flexible cables used for final connections shall be type selected for temperature
duty and current/mass supported in accordance with IEC Regulations, except that no
cable shall be less than 2.5 mm2 cross section.
C LED driver shall be Class2 comply with UL1310 Standard for Safety which requires
the output voltage to pose no risk of fire or electric shock which makes secondary
circuit protection unnecessary.
E Drivers shall have a total individual Luminaire Harmonic Distortion (THD) of ≤20% in
accordance with ANSI C82.77
G Drivers shall be rated for the ambient temperature from -20°C to +50°C
I Electromagnetic Compliance of drivers shall comply with FCC Title 47 Part 15 Class A
M Drivers shall be Suitable for emergency lighting system with central battery
according to IEC 61347-2-13.
N Drivers shall comply with the requirements of IEC 61000-4-5 for surge immunity, 4 kv
for outdoor lighting.
O Individually fused drivers shall have their fuses accessible from outside of the fixture
chassis.
P Luminaires shall be equipped with an LED driver(s) that accepts the voltage as
indicated on the "Luminaire (Lighting Fixture) Schedule". Individual driver(s) shall be
replaceable.
C All “Exit” signs and fire safety signs shall be of the pictogram type utilizing the
pictograms as give in IEC or DIN/VDE Standards. Where wording is incorporated on
the signs it shall be in accordance with IEC or DIN/VDE Standards.
E Exit Signs shall be connected to BMS as indicated in the drawings and BMS Schedules
F Exit sign shall be interface with BMS where the following critical status and alarms
for each exist signs shall be sent to BMS for remote monitoring via volt-free contacts
or serial interface over standard protocol communication as approved
1. On/Off status
2. Auto/Manual and trip status.
3. On/off control
4. Battery status
B Lamps: LEDs, 70,000 hours minimum rated lamp life at 50°C ambient
E Manufacturer shall provide data to demonstrate the hour lumen depreciation factor
at the minimum 50°C temperature. The method of calculation of lumen depreciation
for more than 70,000 hrs. shall be reviewed by the Engineer and declared consistent
with their data by the LED chip manufacturer.
E Garden Lighting fixture shall be with electrostatic painting with body of the
Aluminum – die cast, ingress protection IP65
F All fixtures installed in the Landscape Lighting System shall be suitable for outdoor
installation.
PART 3 EXECUTION
3.1 GENERAL
3.2 INSPECTION
A Inspect each assembly and related accessories for damage, defects and
B At early stage of the construction, inspect a sample area to verify that the Lux level is
as per approved calculation
3.3 INSTALLATION
A Where a conduit wiring system is specified for the wiring to totally enclose lighting
fittings such as bulkhead fittings etc., and the wiring passes through the fittings or
the fittings are mounted directly to a conduit box housing, the circuit wiring shall be
carried out in silicone rubber insulated cable enclosed in a separate conduit.
C Adequate spacing shall be left between wall and bracket-mounted lighting bulbs.
D The fixed wiring to a fitting shall terminate adjacent to the fitting in a conduit box.
Final connection to the fitting being carried out silicon rubber insulated pull through
flexible conduit.
E Final connections between fixed wiring systems and lighting fittings shall in all cases
be carried out in heat resisting flexible cables.
F Under no circumstances shall cables insulated with general purpose PVC be used for
final connections to any lighting fittings.
G The flexible cables used for final connections shall be type selected for temperature
duty and current/mass supported in accordance with IEC Regulations, except that no
cable shall be less than 2.5 mm2 cross section.
J The luminaire has to be mounted at the wall with a gap of 5mm below the bottom
edge of the wall.
K For maintenance it must be able to change the LED modules in the luminaire as easy
as possible without any additional maintenance tools. Therefore it is designed that
the LED modules can be taken off for easy maintenance.
L The luminaire housing is mounted at the wall with three distance cylinder. These
mounting cylinders are very important because the walls are not always straight.
Therefore it is necessary to have a gap Between the wall and luminaire. The final
length of the distance cylinder in the construction drawing of the manufacturer has
to be approved by the architect and lighting consultant.
M The distance from the LED-module to the light output holes (Φ10mm) in the
N Final details and developments have to be done by the luminaire manufacturer and
to be approved by the client and the lighting specialist.
O Any design / construction drawings have to be coordinated and agreed with the
lighting specialist, engineer and client.
P Mounting and the electrical connection must be independently coordinated with the
responsible trades (electrical, ceiling, static etc) and lighting specialist, engineer and
client.
Q The operating devices for normal and emergency operation are located in the
luminaire housing. For each luminaire it is necessary to have operating devices for
normal and emergency operation as described under point 1.3.
R All required connection cables between the LED module and operating devices have
to be delivered with the luminaire and connected via appropriate plugs and have to
be pre wired and connected ready for installation.
S The luminaire manufacturer has to coordinate the control cable type from the
operating devices to the nearest electrical room with the lighting control system
supplier.
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. EXTERIOR LIGHTING
CAIRO - EGYPT 265600 – 2874 0
SECTION 265600
EXTERIOR LIGHTING
Page
PART 1 - GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Definitions 2
1.4 Structural Analysis Criteria For Pole Selection 2
1.5 Submittals 3
1.6 Informational Submittals 3
1.7 Quality Assurance 4
1.8 Delivery, Storage, And Handling 4
1.9 Warranty 5
PART 2 - PRODUCTS 5
2.1 Manufacturers 5
2.2 General 5
2.3 Street Lighting Luminaire 6
2.4 Optional Photoelectric Relay 8
2.5 Required Data In Catalog 8
2.6 Luminaire Support Components 8
2.7 Lighting Poles 9
2.8 Decorative Poles 9
PART 3 - EXECUTION 9
3.1 General 9
3.2 Inspection 10
3.3 Pole Installation 10
3.4 Grounding 11
3.5 Field Quality Control 11
PART 1 - GENERAL
1.2 SUMMARY
1.3 DEFINITIONS
D. Pole: Luminaire support structure, including tower used for large area illumination.
A. Dead Load: Weight of luminaire and its horizontal and vertical supports, lowering
devices, and supporting structure, applied as stated in AASHTO LTS-4.
B. Wind Load: Pressure of wind on pole and luminaire, calculated and applied as per
IEC 2006 Edition -Exposure C, basic wind speed go mph
A. Product Data: For each luminaire, pole, and support component, arranged in order
of lighting unit designation. Include data on features, accessories, finishes, and the
following:
6. Photoelectric relays.
7. Ballasts, including energy-efficiency data.
8. Lamps, including life, output, and energy-efficiency data.
9. Materials, dimensions, and finishes of poles.
10. Means of attaching luminaires to supports, and indication that attachment is
suitable for components involved.
11. Anchor bolts for poles.
12. Manufactured pole foundations.
C. Shop Drawings: Include plans, elevations, sections, details, and attachments to other
work.
D. Samples: For products designated for sample submission in the Exterior Lighting
Device Schedule. Each Sample shall include lamps and ballasts.
A. Store poles on decay-resistant-treated skids at least 12 inches (300 mm) above grade
and vegetation. Support poles to prevent distortion and arrange to provide free air
circulation.
B. Handle wood poles so they will not be damaged. Do not use pointed tools that can
indent pole surface more than 1/4 inch (6 mm) deep. Do not apply tools to section of
pole to be installed below ground line.
1. Warranty Period for Luminaries: Five years from date of Substantial Comple-
tion.
2. Warranty Period for Metal Corrosion: Five years from date of Substantial
Completion.
3. Warranty Period for Color Retention: Five years from date of Substantial Com-
pletion.
4. Warranty Period for Poles: Repair or replace lighting poles and standards that
fail in finish, materials, and workmanship within manufacturer's standard war-
ranty period, but not less than three years from date of Substantial Comple-
tion.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
2.2 GENERAL
A. Comply with UL 1572, UL 1598 and listed for installation in wet locations. Comply
with IESNA RP-8 for parameters of lateral lighting distribution patterns and shall
meet ambient conditions of 50ºC, 90% humidity.
D. Housing: Rigidly formed, weather and light-tight enclosure with integral control
gear.
E. Doors, Frames and Accessibility: Easily accessible and usable, self blocking, smooth,
free of light leakage, permits relamping without use of tools and without risk of
accidental falling of parts. Removable doors for cleaning or replacing lens. Designed
to disconnect ballast when door opens. Easy access to lamp, gear tray, tilt
adjustment and lamp adjustment.
F. Plastic Parts: High resistance to yellowing and other changes due to aging, exposure
K. Seal Gasket: Use heat and aging-resistant, removable non glued, silicon resilient
gaskets to seal and cushion lenses and refractors in luminaire doors.
M. Luminaire Wiring: Use 105ºC moisture and heat-resistant silicon rubber wires,
A. General:
1. Luminaires must be tested to IES LM-79 and IES LM-80 standards, with the re-
sults provided as required in the Submittals paragraph of this specification.
2. IES LM-79 : Electrical and Photometric Measurements of Solid-State Lighting
Products
3. IES LM-80 : Measuring Lumen Maintenance of LED Light Source
4. Luminaire drive current value must be identical to that provided by test data
for luminaire.
5. LED components and sub components shall meet the new standard IES LM-84,
IES LM-85, IES TM-26 and IES TM-28.
1. Exterior LED luminaires supplied shall be complete with the proper Reflectors,
diffusers, house side shields, louvers, glassware, gaskets, pole arms, Collars,
shims, wiring, control, conduit, hardware, drivers, photo controls, and Other
appropriate devices, parts and accessories to be properly installed for an exte-
rior weatherproof lighting installation.
1. Poles for LED luminaires shall be as indicated on the Drawings with factory fin-
ish as shown in the "Luminaire (Lighting Fixture) Schedule". Poles shall be fac-
tory wrapped with heavy weatherproof paper for protection during handling
and shipping.
2. Contractor shall furnish hot-dipped galvanized anchor bolts, templates, ground
rods, conduit elbows, and base information, etc., for the installation of con-
crete bases as detailed on the Drawings.
3. Poles shall be of the height and with brackets, etc. as indicated in the drawings
"Luminaire (Lighting Fixture) Schedule".
E. ILLUMINATION
1. Illumination values for roadways and sidewalks shall be set to achieve the rec-
ommended values of standard:
F. FOUNDATIONS
A. UL listed, factory mounted to the luminaire, single throw, designed and factory set to
turn the light unit on at 15 to 30 lux and OFF at 50 to 100 lux with 15-sec. minimum
time delay.
C. Polar diagrams
F. Ballast losses
G. Inlet diameter
E. Anchor Bolts Nuts, and washers: Hot-dip galvanized after fabrication unless stainless
steel items are indicated.
G. Pole/Support Structure Bases: Anchor type with hold-down or anchor bolts, leveling
nuts, and bolt covers. The design strength of concrete for pole foundation shall be
3000-psig (20.7 M Pa), 28-day compressive strength.
B. Pole of area lighting shall withstand the weight of 4 luminaires (explosion proof type)
plus one person in operation and the resultant moment of these weights at the
indicated height and wind.
C. Pole Earthing: Provide a 12 mm welded threaded lug, for steel poles, accessible
through hand hole and listed for copper conductor connection.
D. Pole Finish: Grind welds and polish surfaces to a smooth, even finish.
A. Pole Material:
B. Mounting Provisions:
C. Fixture Brackets:
PART 3 - EXECUTION
3.1 GENERAL
A. Inspect each assembly and related accessories for damage, defects and
completeness prior to installation.
A. Alignment: Align pole foundations and poles for optimum directional alignment of
luminaires and their mounting provisions on the pole.
D. Foundation-Mounted Poles: Mount pole with leveling nuts, and tighten top nuts to
torque level recommended by pole manufacturer.
1. Use anchor bolts and nuts selected to resist seismic forces defined for the ap-
plication and approved by manufacturer.
2. Grout void between pole base and foundation. Use non shrink or expanding
concrete grout firmly packed to fill space.
3. Install base covers unless otherwise required.
4. Use a short piece of 1/2-inch- (13-mm-) diameter pipe to make a drain hole
through grout. Arrange to drain condensation from interior of pole.
E. Embedded Poles with Tamped Earth Backfill: Set poles to depth below finished
grade, but not less than one-sixth of pole height.
1. Dig holes large enough to permit use of tampers in the full depth of hole.
2. Backfill in 6-inch (150-mm) layers and thoroughly tamp each layer so compac-
tion of backfill is equal to or greater than that of undisturbed earth.
F. Embedded Poles with Concrete Backfill: Set poles in augered holes to depth below
finished grade, but not less than one-sixth of pole height.
1. Make holes 6 inches (150 mm) in diameter larger than pole diameter.
2. Fill augered hole around pole with air-entrained concrete having a minimum
compressive strength of 3000 psi (20 MPa) at 28 days, and finish in a dome
above finished grade.
3. Use a short piece of 1/2-inch- (13-mm-) diameter pipe to make a drain hole
through concrete dome. Arrange to drain condensation from interior of pole.
4. Cure concrete a minimum of 72 hours before performing work on pole.
H. Raise and set poles using web fabric slings (not chain or cable).
3.4 GROUNDING
A. Inspect each installed fixture for damage. Replace damaged fixtures and
components.
C. Illumination Tests:
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. STRUCTURED CABLING SYSTEM
CAIRO - EGYPT 271000 – 2874 0
SECTION 271000
Page
PART 1 INTRODUCTION 2
1.1 SCOPE 2
1.2 Related Documents 3
1.3 System Description 3
1.4 External Links /Connectivity 5
1.5 Interface Requirements With Bms 6
1.6 References And Compliance 6
1.7 Abbreviations & Definitions: 7
1.8 Quality Assurance 7
1.9 Delivery, Storage And Handling 8
1.10 Contractor Responsibility & Submittals 9
PART 2 PRODUCTS 15
2.1 General 15
2.2 Products Minimum Technical Requirement 15
PART 3 INSTALLATION 19
3.1 Installation Of Basic Wiring System Materials 19
3.2 Grounding: 20
3.3 System Labelling 21
3.4 Field Quality Control 21
3.5 Coordination With Other Divisions 21
PART 1 INTRODUCTION
1.1 SCOPE
A This document provides the minimum technical specifications / requirements for the
structured cabling system that shall be installed in the project as indicated in
drawings and relevant documents.
B The WORK of this Part is integral with the whole of the Project Documentation and is
not intended to be interpreted outside that context.
C This Part of the WORK shall be read and executed in conjunction and coordination
with all other Sections of this Specification and other Services/Trade Contractors.
F The contractor is fully responsible to achieve the design intent indicated in the design
package including drawings, specifications and BOQs.
A Contractor must refer to all other related packages for coordination purposes. For
any missing information or contradicting information, contractor must submit RFI
(Request for information) to the design Engineer. No action or interpretation of the
design documents shall be considered valid for construction until it is approved by
the design Engineer through a reply to the RFI.
A The work to be carried out under this section shall comprise the supply, installation,
testing, commissioning and setting to work all items that are necessary for a
complete structured cabling system as per specifications and drawings. Contractor
shall develop a comprehensive structured cabling system including, but not limited to
the items indicated throughout the design package including specification , drawings
and BOQ
C At this point that the performance requirements in this specification are subject to
change due to market updates. Therefore it is the Contractor’s responsibility to
ensure that Hardware and Operating System (where applicable) information is
updated at time of hardware selection or installation.
E The Service level agreement (SLA) is considered integral part of this specification.
F The structured cabling system shall comply with EIA/TIA and IEC standards.
G All telecommunication systems shall be IP based including Voice, Video (IPTV &CCTV)
and all low current systems controllers with Ethernet interface.
H Structured cabling system shall be provided to serve IP-based systems but not limited
to the following:
1. Administration LAN.
2. Security LAN.
3. Wireless network.
4. IP Telephony.
5. IP-CCTV.
6. IPTV.
7. Access Control System.
8. Building management system.
I The network shall support 1GbE/ 10GbE Gigabit Ethernet for the project (data
services and fast internet connectivity).
K All application servers (operator and hospitality) and software applications shall be
provided by the client.
L All the incoming public network service cables shall be terminated at entrance facility
room.
N IT Rooms/closets:
1. The Telecom Rooms will house all horizontal Category 6A cabling along with
the fiber optic backbone cabling and the active network equipment. All of the
Telecom Rooms are being designed to meet the following requirements where
ever possible:
I. Backbone Connections.
II. Horizontal Cabling connections
1. Fiber optic cables shall be used to provide backbone cable links between the
Data center and each IT rooms/closets located in the project.
1. The horizontal cabling in the project will be balanced twisted pair category 6A
cabling (F/UTP).
2. The horizontal category 6A cabling will support but not be limited to the
following applications where applicable:
1. Wiring and network cabinets will all be 600mm x 800mm and 42U high if floor
mounted or where is a small amount of horizontal cabling wall mounted
600mm x 600mm and 12 high.
A Contractor must follow all Monitor and control points indicated in the I/O Schedules
attached to the Building management system specifications
A All works shall be performed in strict accordance with the drawings, specifications
and stipulations of the Local Building and safety Codes, TIA/EIA the National Fire
Protection Association (NFPA), International Electrical Commission (IEC) and other
related international standards
1. Contractor is required to comply with the approved vendor list. Any deviation
must be documented and approved by the design engineer through the official
approval procedure updated at the time of the project.
2. The Supplier/Installer/Manufacturer must be registered with ECG through the
ECG Official procedure prior to submitting the technical material submittal.
D TRAINING:
E Warranty: Provide warranty for the system for at least 25 years starting from the first
day of system handing over to the operation team. SLA (Service level agreement)
shall be submitted and approved by the operator.
F Licenses: The systems shall be provided with all necessary licenses and allow for any
future upgrade software /firmware. Online notifications should be included to allow
for any software versions upgrades according to service level agreement with project
operator.
G Source Limitations for the System and Components: Obtain all system components
from single source from single manufacturer. Any deviation must be supported with
documented reasons which shall be assessed and approved by the Engineer.
A Deliver products in factory containers. Store in clean, dry, closed space in original
containers. Protect products from fumes. Handle very carefully to avoid shocks or
damage.
C Inspection shall be performed in two stages, first time upon receiving the equipment,
devices and cables on site before storing and second time after installation according
to installation phases.
A General: Submit the necessary complete sets of documentation indicating type, size,
rating, style, catalogue number, Manufacturers names, and/or catalogue data sheets
for all items to ensure compliance with specifications. This documentation shall be
subject to the approval of the Engineer and no equipment shall be ordered without
his approval for all equipment and devices, which are shown on documents
(drawings, specs …etc). Any document submitted by the Contractor during the tender
stage shall not be considered as technical submittal, it shall be used only to approve
the manufacturer name. During technical submittal stage, Contractor shall submit all
required technical document for study and approval.
B For any missing or mismatch between various drawings sets in all disciplines,
contractor must issue RFI (Request for Information) to the Design Engineer to provide
the proper corrective action.
C Shop Drawings: Submit shop drawings & Composite drawings showing equipment,
device locations, labeling, part number and connecting wiring of the systems,
including riser diagrams. Shop drawings shall include, but not be limited to the
following:
1. Complete pin to pin one-line riser diagram(s) showing all approved equipment,
size, type and number of all conductors, interconnection between the system
and all other related systems.
2. Installation details for all system components. Installation details drawings
shall show all accessories used in installation such as back boxes, glands,
washers, etc.
3. Complete Grounding details as per system manufacturer requirements.
Indicating connections with dedicated grounding system including connections
with telecommunication grounding bus bars as part of overall grounding and
bonding system including telecom main grounding bus bar.
4. Exact location of every single component of the system in coordination with all
other works (Electromechanical, Arch., and Civil).
5. Colored Composite drawings for all MEP systems showing all coordinated MEP
works
D Material Submittal: shall include, but not be limited to, the following:
1. Contractor and System integrator shall stamp and approve the system material
submittal prior to submitting to the Engineer.
2. Pin to pin connection diagram
3. Complete one-line riser diagram(s) showing all equipment and the size,
connections, type and number of all equipment
4. Include programming and installation manuals
5. Complete sequence of operations and functions of the system
6. Complete system wiring diagrams for components and interfaces to
equipment supplied by others
7. A listing of the manufacturer's authorized, local representative responsible for
installation, coordination and service
8. Compliance sheet item by item providing a comparison between each item
specifies each item submitted. Contractor must indicate clearly any deviations
from design & items specifications-if exists-indicating the reason of deviation.
Such deviations must be approved by the Design Engineer.
9. Detailed Technical Data sheets with highlighted part numbers must be
submitted.
10. [All System cables must be approved by system manufacturer .Contractor
must provide a letter from the manufacturing approving the cables connected
to the manufacturer devices/equipment]
11. BOQ in ECG Format complete with quantities and products part numbers.
12. The submitted BOQ must be mapped to ECG BOQ .i.e Each item in ECG BOQ
should be followed by The equivalent manufacturer Part numbers fulfilling the
requirements of ECG BOQ item .this shall include all hardware and software
licenses and services that fulfill the ECG Item requirements.
13. Compliance Response on this specification document (in every page in this
specifications document) with project approved vendor list. Any deviations
from the project approved vendor list must be approved by the Design
Engineer.
14. All Specifications and BOQs must be stamped by the contractor declaring fully
compliance.
F Maintenance Data: Submit maintenance data and parts lists for each type of the
installed system including furnished specialties and accessories. Include this data,
product data, and shop drawings in maintenance manual; in accordance with
requirements of other relevant documentation.
G Instruction Manuals: The Contractor shall provide with the assistance of the
equipment manufacturer and its authorized, local representative. In addition, one
approved copy of the system submittal, complete operating instructions; pertinent
system orientation documents and system service.
I System Initial Configurations: Contractor must perform all necessary system software
configurations-as required- based on the project operator/client requirements.
Detailed configuration plan must be submitted for the client approval prior to
configuration.
1. Provide calculations to provide filling ratio of cable trays and conduits. The
filling ratio shall not exceed 40% of cable trays/conduits cross sectional area.
2. Provide Optical Power budget calculations for all fiber cable links.
K System supplier & Installer qualifications documents: System supplier & Installer
should submit the required certifications indicating that the system supplier and
installer company is certified from system manufacturer to perform all system
supplying, installations, testing and commissioning supported by system installers
CVs and related manufacturer certifications. The system supplier should be involved
in a strong relationship with system manufacturer with proven reference of similar
projects. The system supplier & installer should submit reference of similar projects
and abide by all requirements in project documents (specifications, drawings, BOQ,
and method of measurements)
N Finalized Reflected ceiling drawings: illustrating all works in the ceilings after
finalizing the coordination process.
I. Wire map
II. Cable length
III. Delay skew
IV. Propagation delay
V. NEXT
VI. Attenuation
VII. Return loss
VIII. ACR
IX. ELFEXT
X. Power sum NEXT
XI. Power sum ACR
XII. Power sum ELFEXT
I. Date of Calibration
II. Cable ID
III. Date/time
IV. Selected testing limits
V. Cable type
VI. Operator name
VII. Software version
VIII. Limits version
IX. Used NVP (Nominal Velocity of Propagation)
I. Date of Calibration
II. Cabling link
III. Test wavelengths
IV. Fiber identification.
P Close out documents :Required documents shall include but not limited to the
following :
1. As built drawings: During the construction of the system, the Contractor shall
put in writing all his remarks, during the progress of work, concerning any
suggested alterations from the shop drawings in wiring routes, locations of
equipment or devices which arise from coordination between the system and
other activities on related shop drawing plans. As built drawings and
documents shall include updating for all of the drawings, documents,
calculations, data sheets..etc previously submitted in shop drawing stage to
reflect what is exactly executed on site.
2. During executing the work and preparing the drawings, no execution of
alterations shall be allowed before receiving a written approval from the
Engineer.
3. All alterations shall be registered and filled by the Contractor and extra copies
shall be submitted to the involved parties (Engineer, Project Manager, Site,
etc.).
4. Complete as-built draft set of Drawings and equipment schedules shall be
prepared fifteen (15) days after completion of work for the engineer’s
approval. The as built draft shall include all previously approved alterations
and technical data sheets of installed equipment, devices…..etc. Final originals
and copies of the as-built Drawings shall be submitted in accordance with
Contract documents.
5. As built documents shall also include: Operation and maintenance manuals
including; updated data sheets for installed equipments, operation
instructions, programming procedures Electronic circuits for every device and
equipment, troubleshooting repair guide, and the required spare parts list for
5 years of operation, along with the circuit diagram. Selected spare parts shall
be provided without any extra cost.
Q EXTRA MATERIALS
2.1 GENERAL
B The above components shall be provided with the appropriate numbers and
capacities to serve the whole project and achieve the design intent. The locations of
various system components are shown on the drawings. Other components and
accessories deemed necessary and essential for system operation and integration
which are not shown on drawings are deemed essential and integral part of the
design intent which should be included in the contractor submitted solution to
achieve end to end fully functional integrated system.
C All notes on the drawings are integral part of the contract document and must be
read in conjunction with all design package documents (specification ,BOQs...etc)
D The following general requirements shall be fulfilled in the provided system. Bidders
shall state clearly any deviations/omissions or additions from the desired
specifications, drawings and BOQs. Such deviations-If Exist- must be assessed and
approved by the Design Engineer.
Patch cords Cat 6A [ 1 meter] [LSZH] Stranded type for rack patching.
Patch cords Cat 6A [ 3 meters] [LSZH] Stranded type for work area patch-
ing.
Management panel
RJ45 Cat 6A Jacks/Outlets Including Cables, [coordination for first fix includ-
ing conduits, pull boxes] Face plates, Modular Jacks, Patch Cords and all
needed fixation accessories including the below general requirements:
IT Rack / Cabinets:
Contractor shall provide detailed cable tray sizing calculations & routing ac-
cording to number of entire cables and coordination with all other utilities in
corridors with filling ratio not exceed 40%.
PART 3 INSTALLATION
C Identify system components, wiring, cabling, boxes, panels and terminals. Comply
with requirements for system identification according to project operator
requirements.
D System labeling scheme must be submitted to the End user project operator for
approval. Operator teams labeling requirements should be considered.
G All System Cables should be LSZH produce no toxic gases in case of fire.
H Cables should be listed for the system specific application and installation
requirements
I All wires and cables shall be listed and/or approved by a recognized testing agency &
System manufacturer through official letter supported with all necessary calculations,
documentations and testing certificates.
J Embedded conduits shall be PVC and all exposed conduits shall be EMT conduit
K All wiring shall be color coded and cabled. Junction boxes shall be color coded and
include wiring identification numbering.
L Wires and cables shall provide sufficient resistance to the spread of fire and generate
no hazardous smoke to human life.
M Wiring System shall include all indoor and outdoor cables necessary for complete
system installations.
3.2 GROUNDING:
A System labelling scheme must be submitted to the End user for approval. Operator
teams labelling requirements should be considered.
E The system will be considered defective if it does not pass tests and inspections.
G Maintenance Test and Inspection: Perform tests and inspections listed for weekly,
monthly, quarterly, and semi-annual periods. Use forms developed for initial tests
and inspections.
H Annual Test and Inspection: One year after date of Substantial Completion, test the
system complying with visual and testing inspection requirements. Use forms
developed for initial tests and inspections.
J System manufacturer and his authorized, local representative shall provide, in depth,
system service on site training to selected Employer’s personnel for two weeks.
A Contractor shall coordinate to provide the necessary required power (DC &A) for all
equipment after determining the manufacturer equipment exact part number and
hence submit any necessary modifications (if needed) according to selected
equipment manufacturer instructions.
B The System supplier shall be responsible for coordination and exchange information
with the Suppliers of other systems and equipment which shall communicate with, in
order to achieve the required specified functions and achieve the AHJ requirements,
operator requirements and related international codes and standards. Contractor
Structured Cabling System Section 271000
Urbanium New Administrative Building (Prj. 2874) Page 21 of 22
must coordinate with all other MEP disciplines to perform all manual override and
systems reset and return to normal operation, a detailed document shall be
submitted for the engineer’s approval. This process is valid in all stages of the project
D LAN Coordination
1. All equipment, Racks, panels and cable shields must be bonded with access to
an approved ground connection (clean earth) using TGB "Telecommunication
Grounding” according to TIA-607-C.
END OF SECTION-271000
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. DATA NETWORK ACTIVE EQUIPMENT
CAIRO - EGYPT 272000 - 2874 0
SECTION 272000
Page
PART 1 INTRODUCTION 2
1.1 SCOPE 2
1.2 Related Documents 3
1.3 System Description 3
1.4 System Architecture 4
1.5 Data Communications Wireless Access Points 5
1.6 Encompassing Design 7
1.7 External Links /Connectivity 7
1.8 Interface Requirements With Bms 7
1.9 References And Compliance 7
1.10 Abbreviations & Definitions: 8
1.11 Quality Assurance 8
1.12 Delivery, Storage And Handling 9
1.13 Contractor Responsibility & Submittals 10
PART 2 PRODUCTS 15
2.1 General 15
2.2 Products Minimum Technical Requirement 15
PART 3 INSTALLATION 22
3.1 Installation Of Basic Wiring System Materials 22
3.2 Grounding: 23
3.3 System Labelling 23
3.4 Field Quality Control 23
3.5 Coordination With Other Divisions 24
PART 1 INTRODUCTION
1.1 SCOPE
A This document provides the minimum technical specifications / requirements for the
data network active equipment system that shall be installed in the project as
indicated in drawings and relevant documents.
B The WORK of this Part is integral with the whole of the Project Documentation and is
not intended to be interpreted outside that context.
C This Part of the WORK shall be read and executed in conjunction and coordination
with all other Sections of this Specification and other Services/Trade Contractors.
D This section applies to the data network active equipment system, as indicated on
accompanying layout drawings and as required by this specification.
F The contractor is fully responsible to achieve the design intent indicated in the design
package including drawings, specifications and BOQs.
A Contractor must refer to all other related packages for coordination purposes. For
any missing information or contradicting information, contractor must submit RFI
(Request for information) to the design Engineer. No action or interpretation of the
design documents shall be considered valid for construction until it is approved by
the design Engineer through a reply to the RFI.
A The work to be carried out under this section shall comprise the supply, installation,
testing, commissioning and setting to work all items that are necessary for a
complete data network active equipment system as per specifications and drawings.
Contractor shall develop a comprehensive data network active equipment system
including, but not limited to the items indicated throughout the design package
including specification , drawings and BOQ
C At this point that the performance requirements in this specification are subject to
change due to market updates. Therefore it is the Contractor’s responsibility to
ensure that Hardware and Operating System (where applicable) information is
updated at time of hardware selection or installation.
E The Service level agreement (SLA) is considered integral part of this specification.
F The LAN will perform all switching and routing functions for voice, video and data
services serving the buildings in scope. The network shall serve all IP based services
such as VOIP, IP CCTV and IPTV...etc.
G Various network traffic will be managed using various techniques such as using
Virtual LANs to segregate various traffics. The network shall provide the required
control to prioritize traffic as required using various queuing techniques according to
networking related standards.
H The Data Network will perform all switching and routing functions for voice, video,
data services & applications. The network shall serve all IP based services that run on
the facility network.
I The Local Area Networks shall be based on a multilayer, fault tolerant, campus wide
TCP/IP network. Multilayer access switches shall be utilized at the network access to
connect the IP devices for the facility network. The access switches shall be stackable
24/48-port 10/100/1000 Base-T POE+ (Power over Ethernet 802.3at). All connections
J The network must support and include all features that provide fundamental
switching, and advanced switching capabilities such as PIM , BGP,OSFP.
K The network must support and include Network segmentation capabilities through
VXLAN.
L The network must support and include Automation, telemetry and visibility and
provide high availability and resiliency.
M The Switches shall provide very fast switching, intelligent high performance platform
for deploying numerous concurrent intelligent services without degrading the overall
performance of the network.
N The network must support and include IOT integration and secured using MACsec.
A The LAN shall be based on a collapsed core design consisting of three layers:
1. Core layer.
2. Distribution layer.
3. Access layer.
B Core Layer:
1. The core will be located at the heart of the network and shall provide very fast
switching, intelligent high performance platform for deploying numerous
concurrent intelligent services without degrading the overall performance of
the network.
2. Core Switches will be located at the center of the network and shall provide
very fast switching, intelligent high performance platform for deploying
numerous concurrent intelligent services without degrading the overall
performance of the network. The core switches shall perform various functions
using various service modules for WAN interfaces, security firewalls…etc.
separate core switches shall be used for each network.
C Distribution Layer:
1. Distribution switches will be located at the Main Telecom rooms (MTR) in the
ground floor of each building; they will connect access switches with the core
switches to give access to the project network. Each distribution switch shall
be connected to core switches via two uplinks.
D Access Layer:
1. Multiple access switches shall be provided for each Equipment Room. The
edge switches shall be capable of being stacked to provide inter-switch
1. Each server cabinet in the data center room shall be connected to the modular
core switches in the data center room via CAT6A copper cables & OM4 Multi-
mode fiber optic cables as indicated on riser diagram [End Of Row / Middle Of
Row – EOR/ MOR].
F The LAN shall be resilient and redundant with automatic fail-over to insure that
performance and high-availability objectives are met without manual intervention.
Recovery mechanisms must be deployed as part of the network implementation and
must be tuned to achieve less than 1 second recovery time. All switches shall be
interconnected and configured as indicated on network riser diagrams and plans
taking into consideration all required redundancy features on both software and
hardware levels.
G All network equipment shall be both IPV4 and IPV6 capable. Contractor, if directed by
the Engineer, shall implement IPV6 with backward compatibility to IPV4.
Notwithstanding, the contractor shall define all IP addresses static ranges and
dynamic ranges as well as subnets and subnet masks.
A The contractor shall supply, install, test and commission a fully functional Wireless
LAN system as detailed within this specification and drawings, including but not
limited to:
1. WLAN Controllers
2. WLAN Management System integrated with the network overall unified
management platform
3. WLAN indoor Access Points
4. External antennas.
5. Mounting hardware for the Wireless Access Points and antennas.
C Site Surveys
1. The Contractor shall complete site surveys at the appropriate time to ensure
their design for quantity and location of Access Points achieves the desired
coverage before any installation commences.
D The following minimum requirements shall be followed for the wireless network:
2. Offices
1. Mobility shall be inherently provided to allow users to access the WLAN from
multiple specific locations.
2. In the areas of coverage roaming shall be enabled to allow users to move
seamlessly through the WLAN whilst unnoticeable transition of AP association
takes place.
3. The network shall be scalable with regard to roaming to ensure that as the
network grows roaming is still possible seamlessly across all WLAN areas.
4. The WLAN shall provide Layer 2 and Layer 3 roaming ability.
5. The WiFi network shall allow for VOIP to run on the wireless network and
ensure service continuity throughout the project areas.
Data Network Active Equipment System Section 272000
Urbanium New Administrative Building (Prj. 2874) Page 6 of 24
1.6 ENCOMPASSING DESIGN
A The contractor shall develop a fully working design for the LAN cognizant of all the
systems to be supported, as well as adopting good engineering practice for future
expansion to ensure that emerging technologies can be supported / adopted for use
on the network in the near future.
B The contractor shall review the system specifications for the listed systems and
ensure that the particular requirements for each of the systems are incorporated into
the design of LAN.
A Contractor must follow all Monitor and control points indicated in the I/O Schedules
attached to the Building management system specifications
A All works shall be performed in strict accordance with the drawings, specifications
and stipulations of the Local Building and safety Codes, TIA/EIA the National Fire
Protection Association (NFPA), International Electrical Commission (IEC) and other
related international standards
1. Ethernet
2. Fast Ethernet
3. IEEE 802.3ad Gigabit-Ethernet channeling
4. IEEE 802.1q VLAN Ethernet
5. IEEE 802.1p Class of Service (CoS)
6. IEEE 802.1d Spanning-Tree Protocol
7. IEEE 802.1w Rapid Spanning-Tree Protocol
8. IEEE 802.3af Power over Ethernet
9. IEEE 802.3ad Gigabit-Ethernet channeling
10. IEEE 802.1q VLAN Ethernet
11. IEEE 802.1p Class of Service (CoS)
12. IEEE 802.1d Spanning-Tree Protocol
13. IEEE 802.1s Multiple Spanning-Tree Protocol (Layer 2 load sharing on
redundant links)
14. IEEE 802.1w Rapid Spanning-Tree Protocol
15. IEEE 802.3af Power over Ethernet
16. IEEE 802.1x network security standards.
17. IEEE 802.11 ac- Wi-Fi
18. BICSI TDMM Manual Latest edition
19. Equal codes and standard could be accepted, which should be listed in detail
as an alternative. Such alternative standards shall be indicated in detail
together with their equivalent IEC, NFPA and UL. A copy of the approved
1. Contractor is required to comply with the approved vendor list. Any deviation
must be documented and approved by the design engineer through the official
approval procedure updated at the time of the project.
2. The Supplier/Installer/Manufacturer must be registered with ECG through the
ECG Official procedure prior to submitting the technical material submittal.
3. The Contractor must follow the approved vendor list for the project. Approved
equal manufacturers must be submitted to the Design Engineer for Approval
through the official registration procedure.
4. Supplier /Installer must submit Official letter from the manufacturer indicating
the level of partnership and support level given to the system
supplier/installer.
5. Supplier/Installer must submit detailed reference list indicating similar projects
installations indicating, location P/N and Quantities of installed items.
Data Network Active Equipment System Section 272000
Urbanium New Administrative Building (Prj. 2874) Page 8 of 24
D TRAINING:
E Warranty: Provide warranty for the system for at least 3 years starting from the first
day of system handing over to the operation team. SLA (Service level agreement)
shall be submitted and approved by the operator.
F Licenses: The systems shall be provided with all necessary licenses and allow for any
future upgrade software /firmware. Online notifications should be included to allow
for any software versions upgrades according to service level agreement with project
operator.
G Source Limitations for the System and Components: Obtain all system components
from single source from single manufacturer. Any deviation must be supported with
documented reasons which shall be assessed and approved by the Engineer.
A Deliver products in factory containers. Store in clean, dry, closed space in original
containers. Protect products from fumes. Handle very carefully to avoid shocks or
damage.
C Inspection shall be performed in two stages, first time upon receiving the equipment,
devices and cables on site before storing and second time after installation according
to installation phases.
A General: Submit the necessary complete sets of documentation indicating type, size,
rating, style, catalogue number, Manufacturers names, and/or catalogue data sheets
for all items to ensure compliance with specifications. This documentation shall be
subject to the approval of the Engineer and no equipment shall be ordered without
his approval for all equipment and devices, which are shown on documents
(drawings, specs …etc). Any document submitted by the Contractor during the tender
stage shall not be considered as technical submittal, it shall be used only to approve
the manufacturer name. During technical submittal stage, Contractor shall submit all
required technical document for study and approval.
B For any missing or mismatch between various drawings sets in all disciplines,
contractor must issue RFI (Request for Information) to the Design Engineer to provide
the proper corrective action.
C Shop Drawings: Submit shop drawings & Composite drawings showing equipment,
device locations, labeling, part number and connecting wiring of the systems,
including riser diagrams. Shop drawings shall include, but not be limited to the
following:
1. Complete pin to pin one-line riser diagram(s) showing all approved equipment,
size, type and number of all conductors, interconnection between the system
and all other related systems.
2. Installation details for all system components. Installation details drawings
shall show all accessories used in installation such as back boxes, glands,
washers, etc.
3. Complete Grounding details as per system manufacturer requirements.
Indicating connections with dedicated grounding system including connections
with telecommunication grounding bus bars as part of overall grounding and
bonding system including telecom main grounding bus bar.
4. Exact location of every single component of the system in coordination with all
other works (Electromechanical, Arch., and Civil).
5. Colored Composite drawings for all MEP systems showing all coordinated MEP
works
6. Signature of all involved contractor engineers representing different disciplines
(Electromechanical, Arch, and Civil etc.) to confirm their approval of such
locations, installations and coordination.
7. Complete sequence of operations and functions of the system.
8. All drawings and technical material submittals should be submitted in both
softcopy and hardcopy formats .No of copies shall be according to contract
documents requirements (at least three copies shall be submitted)
1. Contractor and System integrator shall stamp and approve the system material
submittal prior to submitting to the Engineer.
2. Pin to pin connection diagram
3. Complete one-line riser diagram(s) showing all equipment and the size,
connections, type and number of all equipment
4. Include programming and installation manuals
5. Complete sequence of operations and functions of the system
6. Complete system wiring diagrams for components and interfaces to
equipment supplied by others
7. A listing of the manufacturer's authorized, local representative responsible for
installation, coordination and service
8. Compliance sheet item by item providing a comparison between each item
specifies each item submitted. Contractor must indicate clearly any deviations
from design & items specifications-if exists-indicating the reason of deviation.
Such deviations must be approved by the Design Engineer.
9. Detailed Technical Data sheets with highlighted part numbers must be
submitted.
10. [All System cables must be approved by system manufacturer .Contractor
must provide a letter from the manufacturing approving the cables connected
to the manufacturer devices/equipment]
11. BOQ in ECG Format complete with quantities and products part numbers.
12. The submitted BOQ must be mapped to ECG BOQ .i.e Each item in ECG BOQ
should be followed by The equivalent manufacturer Part numbers fulfilling the
requirements of ECG BOQ item .this shall include all hardware and software
licenses and services that fulfill the ECG Item requirements.
13. Compliance Response on this specification document (in every page in this
specifications document) with project approved vendor list. Any deviations
from the project approved vendor list must be approved by the Design
Engineer.
14. All Specifications and BOQs must be stamped by the contractor declaring fully
compliance.
F Maintenance Data: Submit maintenance data and parts lists for each type of the
installed system including furnished specialties and accessories. Include this data,
product data, and shop drawings in maintenance manual; in accordance with
requirements of other relevant documentation.
G Instruction Manuals: The Contractor shall provide with the assistance of the
equipment manufacturer and its authorized, local representative. In addition, one
approved copy of the system submittal, complete operating instructions; pertinent
system orientation documents and system service.
I System Initial Configurations: Contractor must perform all necessary system software
configurations-as required- based on the project operator/client requirements.
Detailed configuration plan must be submitted for the client approval prior to
configuration.
K System supplier & Installer qualifications documents: System supplier & Installer
should submit the required certifications indicating that the system supplier and
installer company is certified from system manufacturer to perform all system
supplying, installations, testing and commissioning supported by system installers
CVs and related manufacturer certifications. The system supplier should be involved
in a strong relationship with system manufacturer with proven reference of similar
projects. The system supplier & installer should submit reference of similar projects
and abide by all requirements in project documents (specifications, drawings ,BOQ,
and method of measurements)
N Finalized Reflected ceiling drawings: illustrating all works in the ceilings after
finalizing the coordination process.
P Close out documents :Required documents shall include but not limited to the
following :
R EXTRA MATERIALS
PART 2 PRODUCTS
2.1 GENERAL
A The data network active equipment system will be composed of the following items :
B The above components shall be provided with the appropriate numbers and
capacities to serve the whole project and achieve the design intent. The locations of
various system components are shown on the drawings. Other components and
accessories deemed necessary and essential for system operation and integration
which are not shown on drawings are deemed essential and integral part of the
design intent which should be included in the contractor submitted solution to
achieve end to end fully functional integrated system.
C All notes on the drawings are integral part of the contract document and must be
read in conjunction with all design package documents (specification ,BOQs...etc)
D The following general requirements shall be fulfilled in the provided system. Bidders
shall state clearly any deviations/omissions or additions from the desired
specifications, drawings and BOQs. Such deviations-If Exist- must be assessed and
approved by the Design Engineer.
Contractor
Must fill
LAN-SWITCHING NETWORK MINIMUM REQUIREMENTS this col-
umn with
comply /
Chassis
Minimum number of slots:4
Line cards slots: 4
Switch fabric module slots: Two Management modules / supervisors
In addition to maximum number of supported fabric modules are included to provide the switch
maximum switching capacity.
Power supply & redundant power supply: Included (Maximum number of power modules must
be supplied)
Fan tray: Included (Maximum number of Fan tray modules must be supplied)
Power Supplies
Redundant power supply Included: YES (in all slots)
Power supply slot: 3 slots
Hot swappable: YES
Fans
Fan tray / Module: Included (Maximum capacity)
Air Flow: Front to Back
Performance
Fabric Switching capacity: At least 1 Tbps per line card
Forwarding rate /Throughput: At least 1 Bpps per line card
Supported Standards:
802.3az (Energy efficiency)
IEEE 802.1s (Multiple STP)
IEEE 802.1w (Rapid STP)
IEEE 802.11ac (Wi Fi)
IEEE 802.1x (Security)
IEEE 802.3ad (Link Aggregation)
IEEE 802.1D Spanning Tree Protocol
IEEE 802.1p CoS prioritization
IEEE 802.1Q VLAN
IEEE 802.3z 1000BASE-X specification
OSPF
BGP
PIM
IPv6 Routing
Intermediate System-to-Intermediate System (IS-IS) Protocol
Policy-Based Routing
VXLAN
BGP eVPN control plane
Locator/ID Separation Protocol (LISP)
Multiprotocol Label Switching (MPLS)
Layer 3 Virtual Private Network (VPN)
Layer 2 Ethernet over MPLS (EoMPLS)
Layer 2 Virtual Private LAN Services (VPLS)
Switching Capacity: NGFW Firewall throughput (With IPS & Application visibility): 10 Gbps
Concurrent session: 1.5 Million
New sessions per second: 56,000
Hard drive capacity maximum capacity
2x10GE SFP+ Ports c/w 10G-SR Transceivers & 18xGE RJ45 Ports.
Expansion slots for future network modules accepting [ 1/10G ] [Network module not included]
Licenses for Threat defense/prevention, Malware and URL for 3 Years
[Power supply] [and Redundant power supply is included]
Fan tray / Module [Maximum No of fans Included]
[Console cables] [Power cords] [Grounding Kit]
Service Is included for all Firewalls
Switching Capacity: NGFW Firewall throughput (With IPS & Application visibility): 5 Gbps
Concurrent session: 700,000
New sessions per second: 35,000
Hard drive capacity maximum capacity
5xGE RJ45 Ports.
Expansion slots for future network modules accepting [ 1/10G ] [Network module not included]
Licenses for Threat defense/prevention, Malware and URL for 3 Years
[Power supply] [and Redundant power supply is included]
Fan tray / Module [Maximum No of fans Included]
[Console cables] [Power cords] [Grounding Kit]
Service Is included for all Firewalls
Interfaces: 2X 10 GE Ports
Max Access point No: 1024
Throughput: 20 Gbps
Max No of access Users: 10,000
Including console cables, power cords, grounding kit
Redundant hot swappable power supply Included
Protocols:
802.11a/b/g/n/ac/ac wave2,
4x4 MIMO with min. three spatial streams and shall be utilized to provide the required coverage
Support Quality of Service and include security policies supporting WEP, WPA, 802.1X support
Allowing detecting wireless security threats, interference and combating rogue access, Band
steering, Load balancing
AP must support full RF Interference detection & avoidance techniques
Note:
Contractor shall add/Adjust all necessary access points including all accessories and connections to
ensure full Wi-Fi coverage.
The NMS shall be suitable to support all the LAN hardware/Software using Software defined
networking technologies including but not limited to:
LAN switches
Routers
Wireless LAN controllers
Wireless access points
IP telephony server/appliances
IP gateways
Integration with the server management platform
Should provide graphical interface for the while network and distribute configuration as re-
quired.
Warranty 3 years starting from system final testing and commissioning and final acceptace tests
for the whole system including Service Level Agreement [SLA] covering:
-Telephone tech support [8 hours x 5 days]
-Software updates
-Site visit including overall system check and provide maintenance report every 3 Monthes
-Critical Spare Parts Necessary for full system operation Next Business day site delivery
Software Licenses Subscriptions that require renewal after three years to maintain full system op-
Data Network Active Equipment System Section 272000
Urbanium New Administrative Building (Prj. 2874) Page 21 of 24
eration
Contractor must state in THE OPPOSITE CELL the details of such licesnes [if applicable] indicating
features that will be lost in case subscription is not renewed. if such licenses are not applicable con-
tractor shall type [NOT APPLICABLE] ##
PART 3 INSTALLATION
C Identify system components, wiring, cabling, boxes, panels and terminals. Comply
with requirements for system identification according to project operator
requirements.
D System labeling scheme must be submitted to the End user project operator for
approval. Operator teams labeling requirements should be considered.
G All System Cables should be LSZH produce no toxic gases in case of fire.
H Cables should be listed for the system specific application and installation
requirements
I All wires and cables shall be listed and/or approved by a recognized testing agency &
System manufacturer through official letter supported with all necessary calculations,
documentations and testing certificates.
J Embedded conduits shall be PVC and all exposed conduits shall be EMT conduit
K All wiring shall be color coded and cabled. Junction boxes shall be color coded and
include wiring identification numbering.
L Wires and cables shall provide sufficient resistance to the spread of fire and generate
no hazardous smoke to human life.
Data Network Active Equipment System Section 272000
Urbanium New Administrative Building (Prj. 2874) Page 22 of 24
M Wiring System shall include all indoor and outdoor cables necessary for complete
system installations.
3.2 GROUNDING:
A System labelling scheme must be submitted to the End user for approval. Operator
teams labelling requirements should be considered.
E The system will be considered defective if it does not pass tests and inspections.
G Maintenance Test and Inspection: Perform tests and inspections listed for weekly,
monthly, quarterly, and semi-annual periods. Use forms developed for initial tests
and inspections.
H Annual Test and Inspection: One year after date of Substantial Completion, test the
system complying with visual and testing inspection requirements. Use forms
developed for initial tests and inspections.
J System manufacturer and his authorized, local representative shall provide, in depth,
system service on site training to selected Employer’s personnel for two weeks.
A Contractor shall coordinate to provide the necessary required power (DC &A) for all
equipment after determining the manufacturer equipment exact part number and
hence submit any necessary modifications (if needed) according to selected
equipment manufacturer instructions.
B The System supplier shall be responsible for coordination and exchange information
with the Suppliers of other systems and equipment which shall communicate with, in
order to achieve the required specified functions and achieve the AHJ requirements,
operator requirements and related international codes and standards. Contractor
must coordinate with all other MEP disciplines to perform all manual override and
systems reset and return to normal operation, a detailed document shall be
submitted for the engineer’s approval. This process is valid in all stages of the project
END OF SECTION-272000
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. MASTER ANTENNA TELEVISION
CAIRO - EGYPT SYSTEM 274133 - 2874 0
SECTION 274133
Page
PART 1 INTRODUCTION 2
1.1 SCOPE 2
1.2 Related Documents 2
1.3 System Description 3
1.4 External Links /Connectivity 3
1.5 References And Compliance 4
1.6 Abbreviations & Definitions 4
1.7 Quality Assurance 4
1.8 Delivery, Storage And Handling 6
1.9 Contractor Responsibility & Submittals 6
PART 2 PRODUCTS 11
2.1 General 11
2.2 Products Minimum Technical Requirement 11
PART 3 INSTALLATION 13
3.1 Installation Of Basic Wiring System Materials 13
3.2 Grounding: 14
3.3 System Labelling 14
3.4 Field Quality Control 14
3.5 Coordination With Other Divisions 15
PART 1 INTRODUCTION
1.1 SCOPE
A This document provides the minimum technical specifications / requirements for the
Master Antenna Television system that shall be installed in the project as indicated in
drawings and relevant documents.
B The WORK of this Part is integral with the whole of the Project Documentation and is
not intended to be interpreted outside that context.
C This Part of the WORK shall be read and executed in conjunction and coordination
with all other Sections of this Specification and other Services/Trade Contractors.
F The contractor is fully responsible to achieve the design intent indicated in the design
package including drawings, specifications and BOQs.
1. Dish Antenna.
2. VHF/UHF antenna.
3. Quattro Low Noise Block (LNB).
4. IF Multi-Switch
5. TV Box
6. RG6 Coaxial Cable
7. RG11 Coaxial Cable
A Contractor must refer to all other related packages for coordination purposes. For
any missing information or contradicting information, contractor must submit RFI
(Request for information) to the design Engineer. No action or interpretation of the
A The work to be carried out under this section shall comprise the supply, installation,
testing, commissioning and setting to work all items that are necessary for a
complete Master Antenna Television system as per specifications and drawings.
Contractor shall develop a comprehensive Master Antenna Television system
including, but not limited to the items indicated throughout the design package
including specification , drawings and BOQ
C At this point that the performance requirements in this specification are subject to
change due to market updates. Therefore it is the Contractor’s responsibility to
ensure that Hardware and Operating System (where applicable) information is
updated at time of hardware selection or installation.
E The Service level agreement (SLA) is considered integral part of this specification.
F Master Antenna Television Network (MATV) shall be provided for the project by
installing satellite antenna dish farm on the roof top of the building.
G The system will be based on receiving the 4 universal satellite bands [i.e. Ku band;
H/H, H/L, V/H, V/L] via quarto type LNB and distribute them to cascaded IF multi
switch network as indicated on drawings.
I Each tenant will get his own IF-receiver [intermediate frequency RX; 850 MHz – 2150
MHz] allowing to receive & modulate all satellite band channels & terrestrial
channels to be selected and viewed on the LED TV screens.
A All works shall be performed in strict accordance with the drawings, specifications
and stipulations of the Local Building and safety Codes, TIA/EIA the National Fire
Protection Association (NFPA), International Electrical Commission (IEC) and other
related international standards
1. Contractor is required to comply with the approved vendor list. Any deviation
must be documented and approved by the design engineer through the official
approval procedure updated at the time of the project.
2. The Supplier/Installer/Manufacturer must be registered with ECG through the
ECG Official procedure prior to submitting the technical material submittal.
3. The Contractor must follow the approved vendor list for the project. Approved
equal manufacturers must be submitted to the Design Engineer for Approval
through the official registration procedure.
4. Supplier /Installer must submit Official letter from the manufacturer indicating
the level of partnership and support level given to the system
supplier/installer.
5. Supplier/Installer must submit detailed reference list indicating similar projects
installations indicating, location P/N and Quantities of installed items.
D TRAINING:
E Warranty: Provide warranty for the system for at least 3 years starting from the first
day of system handing over to the operation team. SLA (Service level agreement)
shall be submitted and approved by the operator.
F Licenses: The systems shall be provided with all necessary licenses and allow for any
future upgrade software /firmware. Online notifications should be included to allow
for any software versions upgrades according to service level agreement with project
operator.
G Source Limitations for the System and Components: Obtain all system components
from single source from single manufacturer. Any deviation must be supported with
documented reasons which shall be assessed and approved by the Engineer.
Master Antenna Television System Section 274133
Urbanium New Administrative Building (Prj. 2874) Page 5 of 15
H Electrical Components, Devices, and Accessories: Listed and labeled as defined in
related international codes and standards, by a qualified testing agency approved by
the Engineer, and marked for intended location and application.
A Deliver products in factory containers. Store in clean, dry, closed space in original
containers. Protect products from fumes. Handle very carefully to avoid shocks or
damage.
C Inspection shall be performed in two stages, first time upon receiving the equipment,
devices and cables on site before storing and second time after installation according
to installation phases.
A General: Submit the necessary complete sets of documentation indicating type, size,
rating, style, catalogue number, Manufacturers names, and/or catalogue data sheets
for all items to ensure compliance with specifications. This documentation shall be
subject to the approval of the Engineer and no equipment shall be ordered without
his approval for all equipment and devices, which are shown on documents
(drawings, specs …etc). Any document submitted by the Contractor during the tender
stage shall not be considered as technical submittal, it shall be used only to approve
the manufacturer name. During technical submittal stage, Contractor shall submit all
required technical document for study and approval.
B For any missing or mismatch between various drawings sets in all disciplines,
contractor must issue RFI (Request for Information) to the Design Engineer to provide
the proper corrective action.
C Shop Drawings: Submit shop drawings & Composite drawings showing equipment,
device locations, labeling, part number and connecting wiring of the systems,
including riser diagrams. Shop drawings shall include, but not be limited to the
following:
1. Complete pin to pin one-line riser diagram(s) showing all approved equipment,
size, type and number of all conductors, interconnection between the system
and all other related systems.
D Material Submittal: shall include, but not be limited to, the following:
1. Contractor and System integrator shall stamp and approve the system material
submittal prior to submitting to the Engineer.
2. Pin to pin connection diagram
3. Complete one-line riser diagram(s) showing all equipment and the size,
connections, type and number of all equipment
4. Include programming and installation manuals
5. Complete sequence of operations and functions of the system
6. Complete system wiring diagrams for components and interfaces to
equipment supplied by others
7. A listing of the manufacturer's authorized, local representative responsible for
installation, coordination and service
8. Compliance sheet item by item providing a comparison between each item
specifies each item submitted. Contractor must indicate clearly any deviations
from design & items specifications-if exists-indicating the reason of deviation.
Such deviations must be approved by the Design Engineer.
9. Detailed Technical Data sheets with highlighted part numbers must be
submitted.
10. [All System cables must be approved by system manufacturer .Contractor
must provide a letter from the manufacturing approving the cables connected
to the manufacturer devices/equipment]
11. BOQ in ECG Format complete with quantities and products part numbers.
12. The submitted BOQ must be mapped to ECG BOQ .i.e Each item in ECG BOQ
should be followed by The equivalent manufacturer Part numbers fulfilling the
requirements of ECG BOQ item .this shall include all hardware and software
licenses and services that fulfill the ECG Item requirements.
13. Compliance Response on this specification document (in every page in this
specifications document) with project approved vendor list. Any deviations
from the project approved vendor list must be approved by the Design
Engineer.
F Maintenance Data: Submit maintenance data and parts lists for each type of the
installed system including furnished specialties and accessories. Include this data,
product data, and shop drawings in maintenance manual; in accordance with
requirements of other relevant documentation.
G Instruction Manuals: The Contractor shall provide with the assistance of the
equipment manufacturer and its authorized, local representative. In addition, one
I System Initial Configurations: Contractor must perform all necessary system software
configurations-as required- based on the project operator/client requirements.
Detailed configuration plan must be submitted for the client approval prior to
configuration.
1. Head End signal strength calculations should be provided for all TV outlet.
K System supplier & Installer qualifications documents: System supplier & Installer
should submit the required certifications indicating that the system supplier and
installer company is certified from system manufacturer to perform all system
supplying, installations, testing and commissioning supported by system installers
CVs and related manufacturer certifications. The system supplier should be involved
in a strong relationship with system manufacturer with proven reference of similar
projects. The system supplier & installer should submit reference of similar projects
and abide by all requirements in project documents (specifications, drawings ,BOQ,
and method of measurements)
N Finalized Reflected ceiling drawings: illustrating all works in the ceilings after
finalizing the coordination process.
P Close out documents :Required documents shall include but not limited to the
following :
1. As built drawings: During the construction of the system, the Contractor shall
put in writing all his remarks, during the progress of work, concerning any
suggested alterations from the shop drawings in wiring routes, locations of
equipment or devices which arise from coordination between the system and
other activities on related shop drawing plans. As built drawings and
documents shall include updating for all of the drawings, documents,
calculations, data sheets..etc previously submitted in shop drawing stage to
reflect what is exactly executed on site.
2. During executing the work and preparing the drawings, no execution of
alterations shall be allowed before receiving a written approval from the
Engineer.
3. All alterations shall be registered and filled by the Contractor and extra copies
shall be submitted to the involved parties (Engineer, Project Manager, Site,
etc.).
4. Complete as-built draft set of Drawings and equipment schedules shall be
prepared fifteen (15) days after completion of work for the engineer’s
approval. The as built draft shall include all previously approved alterations
and technical data sheets of installed equipment, devices…..etc. Final originals
and copies of the as-built Drawings shall be submitted in accordance with
Contract documents.
5. As built documents shall also include: Operation and maintenance manuals
including; updated data sheets for installed equipment, operation instructions,
programming procedures Electronic circuits for every device and equipment,
troubleshooting repair guide, and the required spare parts list for 5 years of
operation, along with the circuit diagram. Selected spare parts shall be
provided without any extra cost.
Q EXTRA MATERIALS
2.1 GENERAL
A The Master Antenna Television system will be composed of the following items :
1. Dish Antenna.
2. VHF/UHF antenna.
3. Quattro Low Noise Block (LNB).
4. IF Multi-Switch
5. TV Box
6. RG6 Coaxial Cable
7. RG11 Coaxial Cable
B The above components shall be provided with the appropriate numbers and
capacities to serve the whole project and achieve the design intent. The locations of
various system components are shown on the drawings. Other components and
accessories deemed necessary and essential for system operation and integration
which are not shown on drawings are deemed essential and integral part of the
design intent which should be included in the contractor submitted solution to
achieve end to end fully functional integrated system.
C All notes on the drawings are integral part of the contract document and must be
read in conjunction with all design package documents (specification ,BOQs...etc)
D The following general requirements shall be fulfilled in the provided system. Bidders
shall state clearly any deviations/omissions or additions from the desired
specifications, drawings and BOQs. Such deviations-If Exist- must be assessed and
approved by the Design Engineer.
Dish Antenna
Element type used for receiving VHF & UHF local chan-
nels
VHF range: 174 - 230 MHz
UHF range: 470 - 862 MHz
Maximum Gain: 7dB (VHF) & 13dB(UHF)
Back/Front ratio: 20/20 (VHF/UHF)
Half power beam horizontal: 49°/38° (VHF/UHF)
IF Multi-Switch
Cascaded type
Input [SAT+TERR]: 8+1
Frequency Range TERR: 5-862 MHZ
Frequency Range SAT: 950-2400 MHZ
Through Loss TERR: 5.5 dB
Through Loss SAT: 1.3 – 3.4 dB
Subscriber Output: 24
Gain TERR: 14dB [for active multi-switch]
Gain SAT: 15 dB [for active multi-switch]
TV Box
TV metal enclosure
Including 4 port BNC types adaptor connector
RJ6 Coaxial cable In/Out
PART 3 INSTALLATION
C Identify system components, wiring, cabling, boxes, panels and terminals. Comply
with requirements for system identification according to project operator
requirements.
D System labeling scheme must be submitted to the End user project operator for
approval. Operator teams labeling requirements should be considered.
G All System Cables should be LSZH produce no toxic gases in case of fire.
H Cables should be listed for the system specific application and installation
requirements
I All wires and cables shall be listed and/or approved by a recognized testing agency &
System manufacturer through official letter supported with all necessary calculations,
documentations and testing certificates.
J Embedded conduits shall be PVC and all exposed conduits shall be EMT conduit
K All wiring shall be color coded and cabled. Junction boxes shall be color coded and
include wiring identification numbering.
L Wires and cables shall provide sufficient resistance to the spread of fire and generate
no hazardous smoke to human life.
M Wiring System shall include all indoor and outdoor cables necessary for complete
system installations.
3.2 GROUNDING:
A System labelling scheme must be submitted to the End user for approval. Operator
teams labelling requirements should be considered.
E The system will be considered defective if it does not pass tests and inspections.
G Maintenance Test and Inspection: Perform tests and inspections listed for weekly,
monthly, quarterly, and semi-annual periods. Use forms developed for initial tests
and inspections.
H Annual Test and Inspection: One year after date of Substantial Completion, test the
system complying with visual and testing inspection requirements. Use forms
developed for initial tests and inspections.
J System manufacturer and his authorized, local representative shall provide, in depth,
system service on site training to selected Employer’s personnel for two weeks.
A Contractor shall coordinate to provide the necessary required power (DC &A) for all
equipment after determining the manufacturer equipment exact part number and
hence submit any necessary modifications (if needed) according to selected
equipment manufacturer instructions.
B The System supplier shall be responsible for coordination and exchange information
with the Suppliers of other systems and equipment which shall communicate with, in
order to achieve the required specified functions and achieve the AHJ requirements,
operator requirements and related international codes and standards. Contractor
must coordinate with all other MEP disciplines to perform all manual override and
systems reset and return to normal operation, a detailed document shall be
submitted for the engineer’s approval. This process is valid in all stages of the project
END OF SECTION-274133
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. PUBLIC ADDRESS SYSTEM
CAIRO - EGYPT 275116 – 2874 0
SECTION 275116
Page
PART 1 INTRODUCTION 2
1.1 SCOPE 2
1.2 Related Documents 3
1.3 System Description 3
1.4 External Links /Connectivity 4
1.5 Interface Requirements With Bms 4
1.6 References And Compliance 4
1.7 Abbreviations & Definitions: 5
1.8 Quality Assurance 5
1.9 Delivery, Storage And Handling 7
1.10 Contractor Responsibility & Submittals 7
PART 2 PRODUCTS 12
2.1 General 12
2.2 Products Minimum Technical Requirement 12
PART 3 INSTALLATION 17
3.1 Installation Of Basic Wiring System Materials 17
3.2 Grounding: 18
3.3 System Labelling 18
3.4 Field Quality Control 18
3.5 Coordination With Other Divisions 18
PART 1 INTRODUCTION
1.1 SCOPE
A This document provides the minimum technical specifications / requirements for the
public address system that shall be installed in the project as indicated in drawings
and relevant documents.
B The WORK of this Part is integral with the whole of the Project Documentation and is
not intended to be interpreted outside that context.
C This Part of the WORK shall be read and executed in conjunction and coordination
with all other Sections of this Specification and other Services/Trade Contractors.
F The contractor is fully responsible to achieve the design intent indicated in the design
package including drawings, specifications and BOQs.
A Contractor must refer to all other related packages for coordination purposes. For
any missing information or contradicting information, contractor must submit RFI
(Request for information) to the design Engineer. No action or interpretation of the
design documents shall be considered valid for construction until it is approved by
the design Engineer through a reply to the RFI.
A The work to be carried out under this section shall comprise the supply, installation,
testing, commissioning and setting to work all items that are necessary for a
complete public address system as per specifications and drawings. Contractor shall
develop a comprehensive public address system including, but not limited to the
items indicated throughout the design package including specification , drawings and
BOQ
C At this point that the performance requirements in this specification are subject to
change due to market updates. Therefore it is the Contractor’s responsibility to
ensure that Hardware and Operating System (where applicable) information is
updated at time of hardware selection or installation.
E The Service level agreement (SLA) is considered integral part of this specification.
F The public address System shall be used to provide background music, public
announcements and voice evacuation.
G The system will be centralized where the main rack will be located. Remote
equipment will be interconnected to the central equipment to accommodate
centralizing the audio sources and to permit centralized master control of all PA
systems.
H The system design shall incorporate multiple loudspeaker circuits grouped into zones
such that volume levels can be accurately set between different areas and different
themed music content can be used to differentiate areas.
I The public Address system will be independent of the Fire Alarm system and an
interface will be provided between the PA system and the fire alarm system, in order
to mute any sound program and start the evacuation message in the event of an
alarm condition. Local civil defense codes and regulations shall take precedence.
J The Interface equipment shall be included in the public address & sound Systems to
communicate with the Fire Alarm system for receiving STOP signal in case of fire.
L The objective in design of the PA system is to provide the operator with the following
facilities and features:
1. Main Entrance
2. Reception
3. Lobbies & Lounges
4. Public Circulation Areas & Waiting rooms.
N Zoning:
1. The PA system will be configured into logical zones based on the building
layout and fire zones.
2. Zone wires for speakers should not exceed the maximum tolerable power
losses required by manufacturers and related codes.
3. Each alarm Zone shall be fed from and audio amplifier independently.
O All system PA speakers used for evacuation shall be fire rated type complete with fire
dome back boxes and all used sound cables shall be LSZH flame retardant type that
produce no toxic gases in case of fire as required by codes/standards.
A [The PA matrix and amplifiers shall be interfaced with the BMS for alarm and fault
statuses.]
B Contractor must follow all Monitor and control points indicated in the I/O Schedules
attached to the Building management system specifications
A All works shall be performed in strict accordance with the drawings, specifications
and stipulations of the Local Building and safety Codes, TIA/EIA the National Fire
Protection Association (NFPA), International Electrical Commission (IEC) and other
related international standards
D TRAINING:
E Warranty: Provide warranty for the system for at least 3 years starting from the first
day of system handing over to the operation team. SLA (Service level agreement)
shall be submitted and approved by the operator.
F Licenses: The systems shall be provided with all necessary licenses and allow for any
future upgrade software /firmware. Online notifications should be included to allow
for any software versions upgrades according to service level agreement with project
operator.
G Source Limitations for the System and Components: Obtain all system components
from single source from single manufacturer. Any deviation must be supported with
documented reasons which shall be assessed and approved by the Engineer.
A Deliver products in factory containers. Store in clean, dry, closed space in original
containers. Protect products from fumes. Handle very carefully to avoid shocks or
damage.
C Inspection shall be performed in two stages, first time upon receiving the equipment,
devices and cables on site before storing and second time after installation according
to installation phases.
A General: Submit the necessary complete sets of documentation indicating type, size,
rating, style, catalogue number, Manufacturers names, and/or catalogue data sheets
for all items to ensure compliance with specifications. This documentation shall be
subject to the approval of the Engineer and no equipment shall be ordered without
his approval for all equipment and devices, which are shown on documents
(drawings, specs …etc). Any document submitted by the Contractor during the tender
stage shall not be considered as technical submittal, it shall be used only to approve
the manufacturer name. During technical submittal stage, Contractor shall submit all
required technical document for study and approval.
B For any missing or mismatch between various drawings sets in all disciplines,
contractor must issue RFI (Request for Information) to the Design Engineer to provide
the proper corrective action.
C Shop Drawings: Submit shop drawings & Composite drawings showing equipment,
device locations, labeling, part number and connecting wiring of the systems,
including riser diagrams. Shop drawings shall include, but not be limited to the
following:
1. Complete pin to pin one-line riser diagram(s) showing all approved equipment,
size, type and number of all conductors, interconnection between the system
and all other related systems.
2. Installation details for all system components. Installation details drawings
shall show all accessories used in installation such as back boxes, glands,
washers, etc.
3. Complete Grounding details as per system manufacturer requirements.
Indicating connections with dedicated grounding system including connections
D Material Submittal: shall include, but not be limited to, the following:
1. Contractor and System integrator shall stamp and approve the system material
submittal prior to submitting to the Engineer.
2. Pin to pin connection diagram
3. Complete one-line riser diagram(s) showing all equipment and the size,
connections, type and number of all equipment
4. Include programming and installation manuals
5. Complete sequence of operations and functions of the system
6. Complete system wiring diagrams for components and interfaces to
equipment supplied by others
7. A listing of the manufacturer's authorized, local representative responsible for
installation, coordination and service
8. Compliance sheet item by item providing a comparison between each item
specifies each item submitted. Contractor must indicate clearly any deviations
from design & items specifications-if exists-indicating the reason of deviation.
Such deviations must be approved by the Design Engineer.
9. Detailed Technical Data sheets with highlighted part numbers must be
submitted.
10. [All System cables must be approved by system manufacturer. Contractor
must provide a letter from the manufacturing approving the cables connected
to the manufacturer devices/equipment]
11. BOQ in ECG Format complete with quantities and products part numbers.
12. The submitted BOQ must be mapped to ECG BOQ .i.e Each item in ECG BOQ
should be followed by The equivalent manufacturer Part numbers fulfilling the
requirements of ECG BOQ item .this shall include all hardware and software
licenses and services that fulfill the ECG Item requirements.
13. Compliance Response on this specification document (in every page in this
specifications document) with project approved vendor list. Any deviations
from the project approved vendor list must be approved by the Design
Engineer.
14. All Specifications and BOQs must be stamped by the contractor declaring fully
compliance.
F Maintenance Data: Submit maintenance data and parts lists for each type of the
installed system including furnished specialties and accessories. Include this data,
product data, and shop drawings in maintenance manual; in accordance with
requirements of other relevant documentation.
G Instruction Manuals: The Contractor shall provide with the assistance of the
equipment manufacturer and its authorized, local representative. In addition, one
approved copy of the system submittal, complete operating instructions; pertinent
system orientation documents and system service.
I System Initial Configurations: Contractor must perform all necessary system software
configurations-as required- based on the project operator/client requirements.
1. Sound and noise levels provided in these specifications are for GUIDANCE and
the Contractor is responsible for measuring the noise level in all the public
areas and re-adjusts the type, power, distribution of the loud speakers and its
sound levels accordingly.
2. The contractor shall carry out an acoustic modeling and simulation to confirm
the sound level throughout the building before finalizing the speaker locations
and shall get approval from the engineer/Client before ordering the
equipment.
3. Locations of speakers indicated on the drawing are not final. The specialist
sub-Contractor shall carry out acoustic modeling and simulate to find the final-
position of the speakers in coordination with the client. Each zone shall be
individually configurable for all channels / audio sources.
4. Amplifier sizing, SPL and intelligibility calculations should be provided.
K System supplier & Installer qualifications documents: System supplier & Installer
should submit the required certifications indicating that the system supplier and
installer company is certified from system manufacturer to perform all system
supplying, installations, testing and commissioning supported by system installers
CVs and related manufacturer certifications. The system supplier should be involved
in a strong relationship with system manufacturer with proven reference of similar
projects. The system supplier & installer should submit reference of similar projects
and abide by all requirements in project documents (specifications, drawings ,BOQ,
and method of measurements)
N Finalized Reflected ceiling drawings: illustrating all works in the ceilings after
finalizing the coordination process.
P Close out documents :Required documents shall include but not limited to the
following :
1. As built drawings: During the construction of the system, the Contractor shall
put in writing all his remarks, during the progress of work, concerning any
suggested alterations from the shop drawings in wiring routes, locations of
equipment or devices which arise from coordination between the system and
other activities on related shop drawing plans. As built drawings and
documents shall include updating for all of the drawings, documents,
calculations, data sheets..etc previously submitted in shop drawing stage to
reflect what is exactly executed on site.
2. During executing the work and preparing the drawings, no execution of
alterations shall be allowed before receiving a written approval from the
Engineer.
3. All alterations shall be registered and filled by the Contractor and extra copies
shall be submitted to the involved parties (Engineer, Project Manager, Site,
etc.).
4. Complete as-built draft set of Drawings and equipment schedules shall be
prepared fifteen (15) days after completion of work for the engineer’s
approval. The as built draft shall include all previously approved alterations
and technical data sheets of installed equipment, devices…..etc. Final originals
and copies of the as-built Drawings shall be submitted in accordance with
Contract documents.
5. As built documents shall also include: Operation and maintenance manuals
including; updated data sheets for installed equipments, operation
instructions, programming procedures Electronic circuits for every device and
equipment, troubleshooting repair guide, and the required spare parts list for
5 years of operation, along with the circuit diagram. Selected spare parts shall
be provided without any extra cost.
Q EXTRA MATERIALS
PART 2 PRODUCTS
2.1 GENERAL
B The above components shall be provided with the appropriate numbers and
capacities to serve the whole project and achieve the design intent. The locations of
various system components are shown on the drawings. Other components and
accessories deemed necessary and essential for system operation and integration
which are not shown on drawings are deemed essential and integral part of the
design intent which should be included in the contractor submitted solution to
achieve end to end fully functional integrated system.
C All notes on the drawings are integral part of the contract document and must be
read in conjunction with all design package documents (specification ,BOQs...etc)
D The following general requirements shall be fulfilled in the provided system. Bidders
shall state clearly any deviations/omissions or additions from the desired
specifications, drawings and BOQs. Such deviations-If Exist- must be assessed and
approved by the Design Engineer.
Volume Control:
Transformer Attenuator
Power tapping: 10,20,35,50,100 W R.M.S
Rated voltage: 70/100 volt
Steps: 6 steps
C Identify system components, wiring, cabling, boxes, panels and terminals. Comply
with requirements for system identification according to project operator
requirements.
D System labeling scheme must be submitted to the End user project operator for
approval. Operator teams labeling requirements should be considered.
G All System Cables should be LSZH produce no toxic gases in case of fire.
H Cables should be listed for the system specific application and installation
requirements
I All wires and cables shall be listed and/or approved by a recognized testing agency &
System manufacturer through official letter supported with all necessary calculations,
documentations and testing certificates.
J Embedded conduits shall be PVC and all exposed conduits shall be EMT conduit
K All wiring shall be color coded and cabled. Junction boxes shall be color coded and
include wiring identification numbering.
L Wires and cables shall provide sufficient resistance to the spread of fire and generate
no hazardous smoke to human life.
M Wiring System shall include all indoor and outdoor cables necessary for complete
system installations.
A System labelling scheme must be submitted to the End user for approval. Operator
teams labelling requirements should be considered.
E The system will be considered defective if it does not pass tests and inspections.
G Maintenance Test and Inspection: Perform tests and inspections listed for weekly,
monthly, quarterly, and semi-annual periods. Use forms developed for initial tests
and inspections.
H Annual Test and Inspection: One year after date of Substantial Completion, test the
system complying with visual and testing inspection requirements. Use forms
developed for initial tests and inspections.
J System manufacturer and his authorized, local representative shall provide, in depth,
system service on site training to selected Employer’s personnel for two weeks.
A Contractor shall coordinate to provide the necessary required power (DC &A) for all
equipment after determining the manufacturer equipment exact part number and
B The System supplier shall be responsible for coordination and exchange information
with the Suppliers of other systems and equipment which shall communicate with, in
order to achieve the required specified functions and achieve the AHJ requirements,
operator requirements and related international codes and standards. Contractor
must coordinate with all other MEP disciplines to perform all manual override and
systems reset and return to normal operation, a detailed document shall be
submitted for the engineer’s approval. This process is valid in all stages of the project
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. ACCESS CONTROL SYSTEM (ACS)
CAIRO - EGYPT 281300 – 2874 0
SECTION 281300
Page
PART 1 INTRODUCTION 2
1.1 SCOPE 2
1.2 Related Documents 3
1.3 System Description 3
1.4 External Links /Connectivity 4
1.5 Interface Requirements With Bms 4
1.6 References And Compliance 4
1.7 Abbreviations & Definitions: 5
1.8 Quality Assurance 5
1.9 Delivery, Storage And Handling 7
1.10 Contractor Responsibility & Submittals 7
PART 2 PRODUCTS 11
2.1 General 11
2.2 Products Minimum Technical Requirement 12
PART 3 INSTALLATION 17
3.1 Installation Of Basic Wiring System Materials 17
3.2 Grounding: 18
3.3 System Labelling 18
3.4 Field Quality Control 18
3.5 Coordination With Other Divisions 19
PART 1 INTRODUCTION
1.1 SCOPE
A This document provides the minimum technical specifications / requirements for the
access control and integrated security management System that shall be installed in
the project as indicated in drawings and relevant documents.
B The WORK of this Part is integral with the whole of the Project Documentation and is
not intended to be interpreted outside that context.
C This Part of the WORK shall be read and executed in conjunction and coordination
with all other Sections of this Specification and other Services/Trade Contractors.
D This section applies to the access control and integrated security management
System, as indicated on accompanying layout drawings and as required by this
specification.
F The contractor is fully responsible to achieve the design intent indicated in the design
package including drawings, specifications and BOQs.
A Contractor must refer to all other related packages for coordination purposes. For
any missing information or contradicting information, contractor must submit RFI
(Request for information) to the design Engineer. No action or interpretation of the
design documents shall be considered valid for construction until it is approved by
the design Engineer through a reply to the RFI.
A The work to be carried out under this section shall comprise the supply, installation,
testing, commissioning and setting to work all items that are necessary for a
complete access control and integrated security management System as per
specifications and drawings. Contractor shall develop a comprehensive access control
and integrated security management System including, but not limited to the items
indicated throughout the design package including specification , drawings and BOQ
C At this point that the performance requirements in this specification are subject to
change due to market updates. Therefore it is the Contractor’s responsibility to
ensure that Hardware and Operating System (where applicable) information is
updated at time of hardware selection or installation.
E The Service level agreement (SLA) is considered integral part of this specification.
F The Access Control system is security system, which shall control access to the
building and to certain areas, as well as giving an alarm in case of unauthorized
activities in order to achieve maximum-security in the project.
H The criteria of the system shall be based on using proximity card readers for control
access.
I The system shall be capable of saving events for extended periods of time and shall
be extendable for future extension of the project.
J Readers shall cover all service rooms (Elec. Room, Control Room, IT Rooms, etc.) and
all other areas as required by the client.
K The Access Control System shall interface with the Fire Alarm System, CCTV System
and Building Management System (BMS).
M Intelligent Door control equipment shall be used to communicate with the computer
digitally in order to relay the captured data and to control the door lock. Every door
controller shall have its own battery and power supply to feed the internal
electronics and the electronic lock as well. Door controllers shall achieve the door
capacities shown in the drawings.
N The door controller shall be provided with all necessary I/O Extension modules to
provide all necessary hardwired interfaces with other devices/systems.
Q The operation of the electronic access control system shall be in compliance with the
applicable fire and building codes.
A [The Access control server shall be software interfaced with BMS in order to report
all system status and alarms]
B Contractor must follow all Monitor and control points indicated in the I/O Schedules
attached to the Building management system specifications
A All works shall be performed in strict accordance with the drawings, specifications
and stipulations of the Local Building and safety Codes, TIA/EIA the National Fire
Protection Association (NFPA), International Electrical Commission (IEC) and other
related international standards
D TRAINING:
E Warranty: Provide warranty for the system for at least 3 Years starting from the first
day of system handing over to the operation team. SLA (Service level agreement)
shall be submitted and approved by the operator.
F Licenses: The systems shall be provided with all necessary licenses and allow for any
future upgrade software /firmware. Online notifications should be included to allow
for any software versions upgrades according to service level agreement with project
operator.
G Source Limitations for the System and Components: Obtain all system components
from single source from single manufacturer. Any deviation must be supported with
documented reasons which shall be assessed and approved by the Engineer.
A Deliver products in factory containers. Store in clean, dry, closed space in original
containers. Protect products from fumes. Handle very carefully to avoid shocks or
damage.
C Inspection shall be performed in two stages, first time upon receiving the equipment,
devices and cables on site before storing and second time after installation according
to installation phases.
A General: Submit the necessary complete sets of documentation indicating type, size,
rating, style, catalogue number, Manufacturers names, and/or catalogue data sheets
for all items to ensure compliance with specifications. This documentation shall be
subject to the approval of the Engineer and no equipment shall be ordered without
his approval for all equipment and devices, which are shown on documents
(drawings, specs …etc). Any document submitted by the Contractor during the tender
stage shall not be considered as technical submittal, it shall be used only to approve
the manufacturer name. During technical submittal stage, Contractor shall submit all
required technical document for study and approval.
B For any missing or mismatch between various drawings sets in all disciplines,
contractor must issue RFI (Request for Information) to the Design Engineer to provide
the proper corrective action.
C Shop Drawings: Submit shop drawings & Composite drawings showing equipment,
device locations, labeling, part number and connecting wiring of the systems,
including riser diagrams. Shop drawings shall include, but not be limited to the
following:
1. Complete pin to pin one-line riser diagram(s) showing all approved equipment,
size, type and number of all conductors, interconnection between the system
and all other related systems.
2. Installation details for all system components. Installation details drawings
shall show all accessories used in installation such as back boxes, glands,
washers, etc.
3. Complete Grounding details as per system manufacturer requirements.
Indicating connections with dedicated grounding system including connections
D Material Submittal: shall include, but not be limited to, the following:
1. Contractor and System integrator shall stamp and approve the system material
submittal prior to submitting to the Engineer.
2. Pin to pin connection diagram
3. Complete one-line riser diagram(s) showing all equipment and the size,
connections, type and number of all equipment
4. Include programming and installation manuals
5. Complete sequence of operations and functions of the system
6. Complete system wiring diagrams for components and interfaces to
equipment supplied by others
7. A listing of the manufacturer's authorized, local representative responsible for
installation, coordination and service
8. Compliance sheet item by item providing a comparison between each item
specifies each item submitted. Contractor must indicate clearly any deviations
from design & items specifications-if exists-indicating the reason of deviation.
Such deviations must be approved by the Design Engineer.
9. Detailed Technical Data sheets with highlighted part numbers must be
submitted.
10. [All System cables must be approved by system manufacturer .Contractor
must provide a letter from the manufacturing approving the cables connected
to the manufacturer devices/equipment]
11. BOQ in ECG Format complete with quantities and products part numbers.
12. The submitted BOQ must be mapped to ECG BOQ .i.e Each item in ECG BOQ
should be followed by The equivalent manufacturer Part numbers fulfilling the
requirements of ECG BOQ item .this shall include all hardware and software
licenses and services that fulfill the ECG Item requirements.
13. Compliance Response on this specification document (in every page in this
specifications document) with project approved vendor list. Any deviations
from the project approved vendor list must be approved by the Design
Engineer.
14. All Specifications and BOQs must be stamped by the contractor declaring fully
compliance.
F Maintenance Data: Submit maintenance data and parts lists for each type of the
installed system including furnished specialties and accessories. Include this data,
product data, and shop drawings in maintenance manual; in accordance with
requirements of other relevant documentation.
G Instruction Manuals: The Contractor shall provide with the assistance of the
equipment manufacturer and its authorized, local representative. In addition, one
approved copy of the system submittal, complete operating instructions; pertinent
system orientation documents and system service.
I System Initial Configurations: Contractor must perform all necessary system software
configurations-as required- based on the project operator/client requirements.
K System supplier & Installer qualifications documents: System supplier & Installer
should submit the required certifications indicating that the system supplier and
installer company is certified from system manufacturer to perform all system
supplying, installations, testing and commissioning supported by system installers
CVs and related manufacturer certifications. The system supplier should be involved
in a strong relationship with system manufacturer with proven reference of similar
projects. The system supplier & installer should submit reference of similar projects
and abide by all requirements in project documents (specifications, drawings ,BOQ,
and method of measurements)
N Finalized Reflected ceiling drawings: illustrating all works in the ceilings after
finalizing the coordination process.
1. As built drawings: During the construction of the system, the Contractor shall
put in writing all his remarks, during the progress of work, concerning any
suggested alterations from the shop drawings in wiring routes, locations of
equipment or devices which arise from coordination between the system and
other activities on related shop drawing plans. As built drawings and
documents shall include updating for all of the drawings, documents,
calculations, data sheets,...etc previously submitted in shop drawing stage to
reflect what is exactly executed on site.
2. During executing the work and preparing the drawings, no execution of
alterations shall be allowed before receiving a written approval from the
Engineer.
3. All alterations shall be registered and filled by the Contractor and extra copies
shall be submitted to the involved parties (Engineer, Project Manager, Site,
etc.).
4. Complete as-built draft set of Drawings and equipment schedules shall be
prepared fifteen (15) days after completion of work for the engineer’s
approval. The as built draft shall include all previously approved alterations
and technical data sheets of installed equipment, devices…..etc. Final originals
and copies of the as-built Drawings shall be submitted in accordance with
Contract documents.
5. As built documents shall also include: Operation and maintenance manuals
including; updated data sheets for installed equipments, operation
instructions, programming procedures Electronic circuits for every device and
equipment, troubleshooting repair guide, and the required spare parts list for
5 years of operation, along with the circuit diagram. Selected spare parts shall
be provided without any extra cost.
Q EXTRA MATERIALS
PART 2 PRODUCTS
2.1 GENERAL
A The access control and integrated security management System will be composed of
the following items:
Access Control System (ACS) Section 281300
Urbanium New Administrative Building (Prj. 2874) Page 11 of 19
1. Access Control Server
2. Access Control Workstation
3. A4 Laser Printer
4. Card Issuing Printer
5. Intelligent Door Controller
6. Smart proximity Card Reader
7. Fingerprint Reader with Keypad for time attendance
8. Door Sensor
9. Magnetic Door Lock
10. Request to exit button
11. Emergency break glass
12. Proximity Cards
B The above components shall be provided with the appropriate numbers and
capacities to serve the whole project and achieve the design intent. The locations of
various system components are shown on the drawings. Other components and
accessories deemed necessary and essential for system operation and integration
which are not shown on drawings are deemed essential and integral part of the
design intent which should be included in the contractor submitted solution to
achieve end to end fully functional integrated system.
C All notes on the drawings are integral part of the contract document and must be
read in conjunction with all design package documents (specification ,BOQs...etc)
D The following general requirements shall be fulfilled in the provided system. Bidders
shall state clearly any deviations/omissions or additions from the desired
specifications, drawings and BOQs. Such deviations-If Exist- must be assessed and
approved by the Design Engineer.
Door Sensor
Magnetic Lock
Proximity Cards:
PART 3 INSTALLATION
C Identify system components, wiring, cabling, boxes, panels and terminals. Comply
with requirements for system identification according to project operator
requirements.
D System labeling scheme must be submitted to the End user project operator for
approval. Operator teams labeling requirements should be considered.
G All System Cables should be LSZH produce no toxic gases in case of fire.
H Cables should be listed for the system specific application and installation
requirements
I All wires and cables shall be listed and/or approved by a recognized testing agency &
System manufacturer through official letter supported with all necessary calculations,
documentations and testing certificates.
J Embedded conduits shall be PVC and all exposed conduits shall be EMT conduit
K All wiring shall be color coded and cabled. Junction boxes shall be color coded and
include wiring identification numbering.
M Wiring System shall include all indoor and outdoor cables necessary for complete
system installations.
3.2 GROUNDING:
A System labelling scheme must be submitted to the End user for approval. Operator
teams labelling requirements should be considered.
E The system will be considered defective if it does not pass tests and inspections.
G Maintenance Test and Inspection: Perform tests and inspections listed for weekly,
monthly, quarterly, and semi-annual periods. Use forms developed for initial tests
and inspections.
H Annual Test and Inspection: One year after date of Substantial Completion, test the
system complying with visual and testing inspection requirements. Use forms
developed for initial tests and inspections.
J System manufacturer and his authorized, local representative shall provide, in depth,
system service on site training to selected Employer’s personnel for two weeks.
Access Control System (ACS) Section 281300
Urbanium New Administrative Building (Prj. 2874) Page 18 of 19
3.5 COORDINATION WITH OTHER DIVISIONS
A Contractor shall coordinate to provide the necessary required power (DC &A) for all
equipment after determining the manufacturer equipment exact part number and
hence submit any necessary modifications (if needed) according to selected
equipment manufacturer instructions.
B The System supplier shall be responsible for coordination and exchange information
with the Suppliers of other systems and equipment which shall communicate with, in
order to achieve the required specified functions and achieve the AHJ requirements,
operator requirements and related international codes and standards. Contractor
must coordinate with all other MEP disciplines to perform all manual override and
systems reset and return to normal operation, a detailed document shall be
submitted for the engineer’s approval. This process is valid in all stages of the project
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. PARKING MANAGEMENT SYSTEM
CAIRO - EGYPT 281303 - 2874 0
SECTION 281303
Page
PART 1 INTRODUCTION 2
1.1 SCOPE 2
1.2 Related Documents 2
1.3 System Description 3
1.4 External Links /Connectivity 4
1.5 Interface Requirements With Bms 4
1.6 References And Compliance 4
1.7 Abbreviations & Definitions: 4
1.8 Quality Assurance 5
1.9 Delivery, Storage And Handling 6
1.10 Contractor Responsibility & Submittals 7
PART 2 PRODUCTS 11
2.1 General 11
2.2 Products Minimum Technical Requirement 12
PART 3 INSTALLATION 15
3.1 Installation Of Basic Wiring System Materials 15
3.2 Grounding: 16
3.3 System Labelling 17
3.4 Field Quality Control 17
3.5 Coordination With Other Divisions 17
PART 1 INTRODUCTION
1.1 SCOPE
A This document provides the minimum technical specifications / requirements for the
Parking Management System that shall be installed in the project as indicated in
drawings and relevant documents.
B The WORK of this Part is integral with the whole of the Project Documentation and is
not intended to be interpreted outside that context.
C This Part of the WORK shall be read and executed in conjunction and coordination
with all other Sections of this Specification and other Services/Trade Contractors.
F The contractor is fully responsible to achieve the design intent indicated in the design
package including drawings, specifications and BOQs.
A Contractor must refer to all other related packages for coordination purposes. For
any missing information or contradicting information, contractor must submit RFI
(Request for information) to the design Engineer. No action or interpretation of the
A The work to be carried out under this section shall comprise the supply, installation,
testing, commissioning and setting to work all items that are necessary for a
complete Parking Management System as per specifications and drawings.
Contractor shall develop a comprehensive Parking Management System including,
but not limited to the items indicated throughout the design package including
specification, drawings and BOQ
C At this point that the performance requirements in this specification are subject to
change due to market updates. Therefore, it is the Contractor’s responsibility to
ensure that Hardware and Operating System (where applicable) information is
updated at time of hardware selection or installation.
E The Service level agreement (SLA) is considered integral part of this specification.
F The Parking Management System shall be provided for the project to provide
convenient & comfortable parking solution for the project.
G The system shall be designed only to alert the users if there is available parking
space/lot in the overall parking floors in the project or at any dedicated parking floor
inside the building.
H System architecture will be based on main parking management server located inside
server room and parking area controller located inside IT rooms which shall be
connected to the system server via TCP/IP network.
I The parking area controller is used for counting all vehicles entrance and exit the
facility parking, counting the number of vehicles entrance/exit and provide the
available free parking lots floor by floor on the main sign LED display located at main
entrances.
J The number of vehicles entrance or exit the project parking shall be detected via
means of underground loop detector located at each main entrance and exit lane
connected to the parking area controller along with ultrasonic directional sensor
positioned at all ramps transition from floor to another floor which will be connected
to its corresponding parking controller, providing at end that all vehicles entrance,
exit or moved from parking floor to another floor are detected and counted on the
main sign display.
L Parking system shall include also parking arm barrier and entrance/exit terminal unit
including long range RFID card reader located at all entrance/exit parking lanes
facilitating the employees and/or visitor entrance and exit to the project parking via
means of EFID tags/ car badges.
A The Parking Management System server shall be software interfaced with BMS in
order to report all system status and alarms]
B Contractor must follow all Monitor and control points indicated in the I/O Schedules
attached to the Building management system specifications
A All works shall be performed in strict accordance with the drawings, specifications
and stipulations of the Local Building and safety Codes, TIA/EIA the National Fire
Protection Association (NFPA), International Electrical Commission (IEC) and other
related international standards
1. Contractor is required to comply with the approved vendor list. Any deviation
must be documented and approved by the design engineer through the official
approval procedure updated at the time of the project.
2. The Supplier/Installer/Manufacturer must be registered with ECG through the
ECG Official procedure prior to submitting the technical material submittal.
3. The Contractor must follow the approved vendor list for the project. Approved
equal manufacturers must be submitted to the Design Engineer for Approval
through the official registration procedure.
4. Supplier /Installer must submit Official letter from the manufacturer indicating
the level of partnership and support level given to the system
supplier/installer.
5. Supplier/Installer must submit detailed reference list indicating similar projects
installations indicating, location P/N and Quantities of installed items.
Parking Management System (PMS) Section 281300
Urbanium New Administrative Building (Prj. 2874) Page 5 of 18
D TRAINING:
E Warranty: Provide warranty for the system for at least 3 Years starting from the first
day of system handing over to the operation team. SLA (Service level agreement)
shall be submitted and approved by the operator.
F Licenses: The systems shall be provided with all necessary licenses and allow for any
future upgrade software /firmware. Online notifications should be included to allow
for any software versions upgrades according to service level agreement with project
operator.
G Source Limitations for the System and Components: Obtain all system components
from single source from single manufacturer. Any deviation must be supported with
documented reasons which shall be assessed and approved by the Engineer.
A Deliver products in factory containers. Store in clean, dry, closed space in original
containers. Protect products from fumes. Handle very carefully to avoid shocks or
damage.
C Inspection shall be performed in two stages, first time upon receiving the equipment,
devices and cables on site before storing and second time after installation according
to installation phases.
A General: Submit the necessary complete sets of documentation indicating type, size,
rating, style, catalogue number, Manufacturers names, and/or catalogue data sheets
for all items to ensure compliance with specifications. This documentation shall be
subject to the approval of the Engineer and no equipment shall be ordered without
his approval for all equipment and devices, which are shown on documents
(drawings, specs …etc). Any document submitted by the Contractor during the tender
stage shall not be considered as technical submittal, it shall be used only to approve
the manufacturer name. During technical submittal stage, Contractor shall submit all
required technical document for study and approval.
B For any missing or mismatch between various drawings sets in all disciplines,
contractor must issue RFI (Request for Information) to the Design Engineer to provide
the proper corrective action.
C Shop Drawings: Submit shop drawings & Composite drawings showing equipment,
device locations, labeling, part number and connecting wiring of the systems,
including riser diagrams. Shop drawings shall include, but not be limited to the
following:
1. Complete pin to pin one-line riser diagram(s) showing all approved equipment,
size, type and number of all conductors, interconnection between the system
and all other related systems.
2. Installation details for all system components. Installation details drawings
shall show all accessories used in installation such as back boxes, glands,
washers, etc.
3. Complete Grounding details as per system manufacturer requirements.
Indicating connections with dedicated grounding system including connections
with telecommunication grounding bus bars as part of overall grounding and
bonding system including telecom main grounding bus bar.
4. Exact location of every single component of the system in coordination with all
other works (Electromechanical, Arch., and Civil).
5. Colored Composite drawings for all MEP systems showing all coordinated MEP
works
6. Signature of all involved contractor engineers representing different disciplines
(Electromechanical, Arch, and Civil etc.) to confirm their approval of such
locations, installations and coordination.
7. Complete sequence of operations and functions of the system.
8. All drawings and technical material submittals should be submitted in both
softcopy and hardcopy formats .No of copies shall be according to contract
documents requirements (at least three copies shall be submitted)
D Material Submittal: shall include, but not be limited to, the following:
F Maintenance Data: Submit maintenance data and parts lists for each type of the
installed system including furnished specialties and accessories. Include this data,
product data, and shop drawings in maintenance manual; in accordance with
requirements of other relevant documentation.
G Instruction Manuals: The Contractor shall provide with the assistance of the
equipment manufacturer and its authorized, local representative. In addition, one
approved copy of the system submittal, complete operating instructions; pertinent
system orientation documents and system service.
I System Initial Configurations: Contractor must perform all necessary system software
configurations-as required- based on the project operator/client requirements.
Detailed configuration plan must be submitted for the client approval prior to
configuration.
K System supplier & Installer qualifications documents: System supplier & Installer
should submit the required certifications indicating that the system supplier and
installer company is certified from system manufacturer to perform all system
Parking Management System (PMS) Section 281300
Urbanium New Administrative Building (Prj. 2874) Page 9 of 18
supplying, installations, testing and commissioning supported by system installers
CVs and related manufacturer certifications. The system supplier should be involved
in a strong relationship with system manufacturer with proven reference of similar
projects. The system supplier & installer should submit reference of similar projects
and abide by all requirements in project documents (specifications, drawings ,BOQ,
and method of measurements)
N Finalized Reflected ceiling drawings: illustrating all works in the ceilings after
finalizing the coordination process.
P Close out documents :Required documents shall include but not limited to the
following:
1. As built drawings: During the construction of the system, the Contractor shall
put in writing all his remarks, during the progress of work, concerning any
suggested alterations from the shop drawings in wiring routes, locations of
equipment or devices which arise from coordination between the system and
other activities on related shop drawing plans. As built drawings and
documents shall include updating for all of the drawings, documents,
calculations, data sheets,...etc previously submitted in shop drawing stage to
reflect what is exactly executed on site.
2. During executing the work and preparing the drawings, no execution of
alterations shall be allowed before receiving a written approval from the
Engineer.
Q EXTRA MATERIALS
PART 2 PRODUCTS
2.1 GENERAL
B The above components shall be provided with the appropriate numbers and
capacities to serve the whole project and achieve the design intent. The locations of
various system components are shown on the drawings. Other components and
accessories deemed necessary and essential for system operation and integration
which are not shown on drawings are deemed essential and integral part of the
Parking Management System (PMS) Section 281300
Urbanium New Administrative Building (Prj. 2874) Page 11 of 18
design intent which should be included in the contractor submitted solution to
achieve end to end fully functional integrated system.
C All notes on the drawings are integral part of the contract document and must be
read in conjunction with all design package documents (specification ,BOQs...etc)
D The following general requirements shall be fulfilled in the provided system. Bidders
shall state clearly any deviations/omissions or additions from the desired
specifications, drawings and BOQs. Such deviations-If Exist- must be assessed and
approved by the Design Engineer.
Exit Terminal Unit c/w receipt checker & Long Range Card Reader [LCR]
Barrier Controller
Specifications:
PART 3 INSTALLATION
C Identify system components, wiring, cabling, boxes, panels and terminals. Comply
with requirements for system identification according to project operator
requirements.
D System labeling scheme must be submitted to the End user project operator for
approval. Operator teams labeling requirements should be considered.
G All System Cables should be LSZH produce no toxic gases in case of fire.
H Cables should be listed for the system specific application and installation
requirements
I All wires and cables shall be listed and/or approved by a recognized testing agency &
System manufacturer through official letter supported with all necessary calculations,
documentations and testing certificates.
J Embedded conduits shall be PVC and all exposed conduits shall be EMT conduit
K All wiring shall be color coded and cabled. Junction boxes shall be color coded and
include wiring identification numbering.
L Wires and cables shall provide sufficient resistance to the spread of fire and generate
no hazardous smoke to human life.
M Wiring System shall include all indoor and outdoor cables necessary for complete
system installations.
3.2 GROUNDING:
A System labelling scheme must be submitted to the End user for approval. Operator
teams labelling requirements should be considered.
E The system will be considered defective if it does not pass tests and inspections.
G Maintenance Test and Inspection: Perform tests and inspections listed for weekly,
monthly, quarterly, and semi-annual periods. Use forms developed for initial tests
and inspections.
H Annual Test and Inspection: One year after date of Substantial Completion, test the
system complying with visual and testing inspection requirements. Use forms
developed for initial tests and inspections.
J System manufacturer and his authorized, local representative shall provide, in depth,
system service on site training to selected Employer’s personnel for two weeks.
A Contractor shall coordinate to provide the necessary required power (DC &A) for all
equipment after determining the manufacturer equipment exact part number and
hence submit any necessary modifications (if needed) according to selected
equipment manufacturer instructions.
B The System supplier shall be responsible for coordination and exchange information
with the Suppliers of other systems and equipment which shall communicate with, in
order to achieve the required specified functions and achieve the AHJ requirements,
operator requirements and related international codes and standards. Contractor
Parking Management System (PMS) Section 281300
Urbanium New Administrative Building (Prj. 2874) Page 17 of 18
must coordinate with all other MEP disciplines to perform all manual override and
systems reset and return to normal operation, a detailed document shall be
submitted for the engineer’s approval. This process is valid in all stages of the project
END OF SECTION-281303
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. IP-CLOSED CIRCUIT TELEVISION
CAIRO - EGYPT SYSTEM 282300 – 2874 0
SECTION 282300
Page
PART 1 INTRODUCTION 2
1.1 SCOPE 2
1.2 Related Documents 2
1.3 System Description 3
1.4 External Links /Connectivity 5
1.5 Interface Requirements With Bms 5
1.6 References And Compliance 5
1.7 Abbreviations & Definitions: 5
1.8 Quality Assurance 6
1.9 Delivery, Storage And Handling 7
1.10 Contractor Responsibility & Submittals 8
PART 2 PRODUCTS 12
2.1 General 12
2.2 Products Minimum Technical Requirement 13
PART 3 INSTALLATION 18
3.1 Installation Of Basic Wiring System Materials 18
3.2 Grounding: 19
3.3 System Labelling 19
3.4 Field Quality Control 19
3.5 Coordination With Other Divisions 20
PART 1 INTRODUCTION
1.1 SCOPE
A This document provides the minimum technical specifications / requirements for the
IP-Closed circuit television system that shall be installed in the project as indicated in
drawings and relevant documents.
B The WORK of this Part is integral with the whole of the Project Documentation and is
not intended to be interpreted outside that context.
C This Part of the WORK shall be read and executed in conjunction and coordination
with all other Sections of this Specification and other Services/Trade Contractors.
F The contractor is fully responsible to achieve the design intent indicated in the design
package including drawings, specifications and BOQs.
A Contractor must refer to all other related packages for coordination purposes. For
any missing information or contradicting information, contractor must submit RFI
A The work to be carried out under this section shall comprise the supply, installation,
testing, commissioning and setting to work all items that are necessary for a
complete IP-Closed circuit television system as per specifications and drawings.
Contractor shall develop a comprehensive IP-Closed circuit television system
including, but not limited to the items indicated throughout the design package
including specification , drawings and BOQ
C At this point that the performance requirements in this specification are subject to
change due to market updates. Therefore it is the Contractor’s responsibility to
ensure that Hardware and Operating System (where applicable) information is
updated at time of hardware selection or installation.
E The Service level agreement (SLA) is considered integral part of this specification.
F The IPCCTV System shall be enterprise IP video security solution that provides
seamless management of digital video, audio and data through CCTV cameras across
the IP network enabling viewing and control of images from different points on the
network moreover Automatic digital recording of live video scenes shall provide user
activated, event activated, scheduled recording and video motion detection
activation including related data at locations need this function. The system is
intended for Security automated visual surveillance, alarm notification, recording
video and data for areas under observation.
G The system shall be based on digital high performance IP cameras transmitting digital
IP video signal to Digital Video management System and workstation to achieve
viewing and control of any camera image from different points at the Local Area
Network and via TCP/IP internet protocol. Signals coming from cameras shall be
routed to data switch connected to LAN backbone and stored on the network video
recorders also encoding algorithms schemes that secure no visible degradation from
PAL quality video.
H The cameras at far locations out of LAN 90 meter limiting distance, fiber optic
connections, media convertors,…etc. shall be provided wherever the cable length is
longer than 90m.
I The IP CCTV system shall display automatically, the alarm related live video scenes
and data of the detected events on selected workstations, as programmed and
J The IPCCTV system shall combine state-of-the art modular design and powerful user
programmable software together with versatile and flexible hardware options to
make it easy to integrate and extend the CCTV system and to be interfaced with
other security systems.
K The system shall be only programmed and configured by the authorized security
officials from the main IP CCTV workstation. Authorization to access the system
resources shall be made in levels (Administrator, Manager…etc.) as programmed.
L The system shall be supplied from the UPS source to ensure uninterrupted operation
in case of supply failure.
M The IP CCTV system shall utilize indoor/outdoor color TCP/IP network based digital
cameras. Cameras shall be controlled remotely for focus adjustment and camera
on/off. This shall be done using the appropriate software modules that run under the
management main software platform of the ISMS (Integrated Security Management
System) system and drive the cameras as configured by the ISMS server.
N The IP CCTV system shall display automatically, the alarm related live video scenes
and data of the detected events on selected workstations, as programmed and
configured. It shall activate recording. It shall also allow viewing real time live video
pictures.
O Network video recording hard drives of ample capacity shall record live video of all
cameras for archiving purposes. Various recording techniques according to
manufacturer specific solution shall be accepted according to manufacturer standard
range of products. Alarm events shall be recorded together with related data. It shall
include large amount of disk space to record for four weeks.
Q Contractor shall coordinate to determine the camera lens to achieve the required
field of view according to the camera locations.
R Surveillance – Power
S Surveillance – Transmission
1. The IPCCTV System shall utilize digital video transmission to allow IP Video
over standard Ethernet hardware. IP Video technology with Power over
Ethernet (PoE) that provides power and signal on same cable.
2. Route of fiber optic cables and scope of work from CCTV server to plot limit
with existing infrastructure services to be considered at different design stages.
A The CCTV server and network video recording systems shall be monitored by the
BMS in order to report all alarm and fault statuses.
B Contractor must follow all Monitor and control points indicated in the I/O Schedules
attached to the Building management system specifications
A All works shall be performed in strict accordance with the drawings, specifications
and stipulations of the Local Building and safety Codes, TIA/EIA the National Fire
Protection Association (NFPA), International Electrical Commission (IEC) and other
related international standards
1. Contractor is required to comply with the approved vendor list. Any deviation
must be documented and approved by the design engineer through the official
approval procedure updated at the time of the project.
2. The Supplier/Installer/Manufacturer must be registered with ECG through the
ECG Official procedure prior to submitting the technical material submittal.
3. The Contractor must follow the approved vendor list for the project. Approved
equal manufacturers must be submitted to the Design Engineer for Approval
through the official registration procedure.
4. Supplier /Installer must submit Official letter from the manufacturer indicating
the level of partnership and support level given to the system
supplier/installer.
5. Supplier/Installer must submit detailed reference list indicating similar projects
installations indicating, location P/N and Quantities of installed items.
D TRAINING:
E Warranty: Provide warranty for the system for at least 3 Years starting from the first
day of system handing over to the operation team. SLA (Service level agreement)
shall be submitted and approved by the operator.
F Licenses: The systems shall be provided with all necessary licenses and allow for any
future upgrade software /firmware. Online notifications should be included to allow
for any software versions upgrades according to service level agreement with project
operator.
G Source Limitations for the System and Components: Obtain all system components
from single source from single manufacturer. Any deviation must be supported with
documented reasons which shall be assessed and approved by the Engineer.
A Deliver products in factory containers. Store in clean, dry, closed space in original
containers. Protect products from fumes. Handle very carefully to avoid shocks or
damage.
C Inspection shall be performed in two stages, first time upon receiving the equipment,
devices and cables on site before storing and second time after installation according
to installation phases.
A General: Submit the necessary complete sets of documentation indicating type, size,
rating, style, catalogue number, Manufacturers names, and/or catalogue data sheets
for all items to ensure compliance with specifications. This documentation shall be
subject to the approval of the Engineer and no equipment shall be ordered without
his approval for all equipment and devices, which are shown on documents
(drawings, specs …etc). Any document submitted by the Contractor during the tender
stage shall not be considered as technical submittal, it shall be used only to approve
the manufacturer name. During technical submittal stage, Contractor shall submit all
required technical document for study and approval.
B For any missing or mismatch between various drawings sets in all disciplines,
contractor must issue RFI (Request for Information) to the Design Engineer to provide
the proper corrective action.
C Shop Drawings: Submit shop drawings & Composite drawings showing equipment,
device locations, labeling, part number and connecting wiring of the systems,
including riser diagrams. Shop drawings shall include, but not be limited to the
following:
1. Complete pin to pin one-line riser diagram(s) showing all approved equipment,
size, type and number of all conductors, interconnection between the system
and all other related systems.
2. Installation details for all system components. Installation details drawings
shall show all accessories used in installation such as back boxes, glands,
washers, etc.
3. Complete Grounding details as per system manufacturer requirements.
Indicating connections with dedicated grounding system including connections
with telecommunication grounding bus bars as part of overall grounding and
bonding system including telecom main grounding bus bar.
4. Exact location of every single component of the system in coordination with all
other works (Electromechanical, Arch., and Civil).
5. Colored Composite drawings for all MEP systems showing all coordinated MEP
works
6. Signature of all involved contractor engineers representing different disciplines
(Electromechanical, Arch, and Civil etc.) to confirm their approval of such
locations, installations and coordination.
7. Complete sequence of operations and functions of the system.
8. All drawings and technical material submittals should be submitted in both
softcopy and hardcopy formats .No of copies shall be according to contract
documents requirements (at least three copies shall be submitted)
9. Camera FOV and coverage pattern should be indicated on all floor plans for
each camera.
D Material Submittal: shall include, but not be limited to, the following:
F Maintenance Data: Submit maintenance data and parts lists for each type of the
installed system including furnished specialties and accessories. Include this data,
product data, and shop drawings in maintenance manual; in accordance with
requirements of other relevant documentation.
G Instruction Manuals: The Contractor shall provide with the assistance of the
equipment manufacturer and its authorized, local representative. In addition, one
approved copy of the system submittal, complete operating instructions; pertinent
system orientation documents and system service.
I System Initial Configurations: Contractor must perform all necessary system software
configurations-as required- based on the project operator/client requirements.
Detailed configuration plan must be submitted for the client approval prior to
configuration.
K System supplier & Installer qualifications documents: System supplier & Installer
should submit the required certifications indicating that the system supplier and
installer company is certified from system manufacturer to perform all system
supplying, installations, testing and commissioning supported by system installers
CVs and related manufacturer certifications. The system supplier should be involved
in a strong relationship with system manufacturer with proven reference of similar
projects. The system supplier & installer should submit reference of similar projects
and abide by all requirements in project documents (specifications, drawings ,BOQ,
and method of measurements)
N Finalized Reflected ceiling drawings: illustrating all works in the ceilings after
finalizing the coordination process.
P Close out documents :Required documents shall include but not limited to the
following :
Q EXTRA MATERIALS
PART 2 PRODUCTS
2.1 GENERAL
A The IP-Closed circuit television system will be composed of the following items :
B The above components shall be provided with the appropriate numbers and
capacities to serve the whole project and achieve the design intent. The locations of
various system components are shown on the drawings. Other components and
accessories deemed necessary and essential for system operation and integration
which are not shown on drawings are deemed essential and integral part of the
design intent which should be included in the contractor submitted solution to
achieve end to end fully functional integrated system.
C All notes on the drawings are integral part of the contract document and must be
read in conjunction with all design package documents (specification ,BOQs...etc)
D The following general requirements shall be fulfilled in the provided system. Bidders
shall state clearly any deviations/omissions or additions from the desired
specifications, drawings and BOQs. Such deviations-If Exist- must be assessed and
approved by the Design Engineer.
IP-CCTV Workstation
LED Screen
PART 3 INSTALLATION
C Identify system components, wiring, cabling, boxes, panels and terminals. Comply
with requirements for system identification according to project operator
requirements.
D System labeling scheme must be submitted to the End user project operator for
approval. Operator teams labeling requirements should be considered.
G All System Cables should be LSZH produce no toxic gases in case of fire.
H Cables should be listed for the system specific application and installation
requirements
I All wires and cables shall be listed and/or approved by a recognized testing agency &
System manufacturer through official letter supported with all necessary calculations,
documentations and testing certificates.
J Embedded conduits shall be PVC and all exposed conduits shall be EMT conduit
K All wiring shall be color coded and cabled. Junction boxes shall be color coded and
include wiring identification numbering.
L Wires and cables shall provide sufficient resistance to the spread of fire and generate
no hazardous smoke to human life.
M Wiring System shall include all indoor and outdoor cables necessary for complete
system installations.
3.2 GROUNDING:
A System labelling scheme must be submitted to the End user for approval. Operator
teams labelling requirements should be considered.
G Maintenance Test and Inspection: Perform tests and inspections listed for weekly,
monthly, quarterly, and semi-annual periods. Use forms developed for initial tests
and inspections.
H Annual Test and Inspection: One year after date of Substantial Completion, test the
system complying with visual and testing inspection requirements. Use forms
developed for initial tests and inspections.
J System manufacturer and his authorized, local representative shall provide, in depth,
system service on site training to selected Employer’s personnel for two weeks.
A Contractor shall coordinate to provide the necessary required power (DC &A) for all
equipment after determining the manufacturer equipment exact part number and
hence submit any necessary modifications (if needed) according to selected
equipment manufacturer instructions.
B The System supplier shall be responsible for coordination and exchange information
with the Suppliers of other systems and equipment which shall communicate with, in
order to achieve the required specified functions and achieve the AHJ requirements,
operator requirements and related international codes and standards. Contractor
must coordinate with all other MEP disciplines to perform all manual override and
systems reset and return to normal operation, a detailed document shall be
submitted for the engineer’s approval. This process is valid in all stages of the project
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. INTELLIGENT ADDRESSABLE FIRE
CAIRO - EGYPT ALARM SYSTEM 283100 - 2874 0
SECTION 283100
Page
PART 1 INTRODUCTION 2
1.1 SCOPE 2
1.2 Related Documents 3
1.3 System Description 3
1.4 External Links /Connectivity 5
1.5 Interface Requirements With Bms 5
1.6 Sequence Of Operation 6
1.7 References And Compliance 7
1.8 Abbreviations & Definitions 8
1.9 Quality Assurance 8
1.10 Delivery, Storage And Handling 10
1.11 Contractor Responsibility & Submittals 10
PART 2 PRODUCTS 15
2.1 General 15
2.2 Products Minimum Technical Requirement 16
PART 3 INSTALLATION 22
3.1 Installation Of Basic Wiring System Materials 22
3.2 Grounding: 23
3.3 System Labelling 23
3.4 Field Quality Control 23
3.5 Coordination With Other Divisions 24
PART 1 INTRODUCTION
1.1 SCOPE
A This document provides the minimum technical specifications / requirements for the
intelligent addressable fire alarm system that shall be installed in the project as
indicated in drawings and relevant documents.
B The WORK of this Part is integral with the whole of the Project Documentation and is
not intended to be interpreted outside that context.
C This Part of the WORK shall be read and executed in conjunction and coordination
with all other Sections of this Specification and other Services/Trade Contractors.
D This section applies to the intelligent addressable fire alarm system, as indicated on
accompanying layout drawings and as required by this specification.
F The contractor is fully responsible to achieve the design intent indicated in the design
package including drawings, specifications and BOQs.
A Contractor must refer to all other related packages for coordination purposes. For
any missing information or contradicting information, contractor must submit RFI
(Request for information) to the design Engineer. No action or interpretation of the
design documents shall be considered valid for construction until it is approved by
the design Engineer through a reply to the RFI.
A The work to be carried out under this section shall comprise the supply, installation,
testing, commissioning and setting to work all items that are necessary for a
complete intelligent addressable fire alarm system as per specifications and
drawings. Contractor shall develop a comprehensive intelligent addressable fire
alarm System including, but not limited to the items indicated throughout the design
package including specification, drawings and BOQ
C At this point that the performance requirements in this specification are subject to
change due to market updates. Therefore, it is the Contractor’s responsibility to
ensure that Hardware and Operating System (where applicable) information is
updated at time of hardware selection or installation.
E The Service level agreement (SLA) is considered integral part of this specification.
G The system shall be a fully intelligent microprocessor based system that can
supervise space status and self-adjust its sensitivity in analogue form according to the
environmental conditions of the place and to address electronically every part of the
system to report its status, and to easily identify the source of fire.
I The Fire Alarm System shall be used to detect early start of fire and initiate the
appropriate annunciation, alarm, interlocking and counter measures commands as
described in this section.
J The Fire Alarm System shall supervise all the functions of the equipment and devices
including the connected safety related systems such as firefighting, smoke purge, etc.
K Fire alarm system shall be a fully addressable loop powered system. All fire alarm
devices should be loop powered for direct connection to the 2 core detection loop.
L All fire alarm devices should have built in short circuit line isolator provided as an
integral component to protect the system.
M Detectors on a remote location such as above false ceiling should be provided with
individual LED unit sited on a visible location by means of 2 core wire connection.
N The maximum covered area of one loop should not exceed manufacturer’s
requirements.
O All addressable fire alarm panels shall have alpha numeric display.
P Audible warning devices used for fire alarm system should have similar sound and be
distinct from any other audible alarm use for other purpose except in noisy areas
where high performance sounder is required.
Q The notification appliances including alarm sirens and strobe lights shall be located as
required to achieve acceptable audibility in all areas of the building.
R All FACPs serving different areas shall be connected to MFACPs by way of ring
networking cable. All message from panels should be transmitted in both directions
on the ring structure. Any wire-break or short circuit on the ring shall not affect data
transmission. The network shall be configured so that single panel, group of panels or
all panels on the network operate the same site configured cause and effect fire plan.
The network shall also be configured to allow master control from any one of the
control panels on the network.
S The contractor shall ensure that the fire sounder achieving 15 dB above ambient
noise in all areas & new redistribution of the bells will be approved accordingly.
T Fire extinguishing control panels (CP) shall be provided with built in programmable
relays.
U MFACP system shall be interfaced with access control system, public address system,
elevator control panel, firefighting and fire suppression system, HAVC, mechanical
systems and BMS system.
V Communication loop between MFACP and Satellite FAPs must be via SMFO cables or
as per system manufacturer specific communication requirements. Contractor shall
provide main fire alarm control panel & satellite panels with required fiber optic
A The Main Fire Alarm Panel shall have a data port to enable the transfer of
information to the Management level Network of the BMS. The communication shall
be uni-directional from the Main Fire Alarm Panel to the Management Level Network
only.
B The start and end of any message shall be uniquely identified and the message shall
indicate time, date, and zone of incidence, also indicating whether the fire alarm
system return to normal of fire alarm fault. In the event of a fire, the fire alarm
system shall communicate a list of all equipment shut down and start by fire alarm
system.
C There shall be no transfer of data from the Management Level Network of BMS to
the Fire Alarm System.
D The Fire Alarm System shall automatically shut down all terminal that serve the zone
of incidence in the event of a fire alarm and the BMS shall automatically restart
equipment following a return to normal message from the fire alarm system.
F The Fire Alarm System shall be fully interfaced with the Building Management System
(BMS) by means of software to monitor various points in the system. The BMS shall
receive all events, actions and reports from the MFACP through the appropriate
protocol. The protocol converter and software shall be included with MFACP, so as to
be fully compatible with the BMS. All addressing information must be transferred
between the systems and shown on Both Graphical interfaces showing the building
layout indicating the exact location of the monitored and controlled points alarms
and operation.
G Contractor must follow all Monitor and control points indicated in the I/O Schedules
attached to the Building management system specifications.
A The system shall be interfaced with the following systems to achieve the integration
sequence of operation indicated below:
a. Manual stations.
b. Heat detectors.
c. Multi detectors.
d. Duct smoke detectors.
e. Verified automatic alarm operation of multi detectors.
f. Monitor Modules over any other System.
A All works shall be performed in strict accordance with the drawings, specifications
and stipulations of the Local Building and safety Codes, TIA/EIA the National Fire
Protection Association (NFPA), International Electrical Commission (IEC) and other
related international standards
1. Contractor is required to comply with the approved vendor list. Any deviation
must be documented and approved by the design engineer through the official
approval procedure updated at the time of the project.
2. The Supplier/Installer/Manufacturer must be registered with ECG through the
ECG Official procedure prior to submitting the technical material submittal.
3. The Contractor must follow the approved vendor list for the project. Approved
equal manufacturers must be submitted to the Design Engineer for Approval
through the official registration procedure.
4. Supplier /Installer must submit Official letter from the manufacturer indicating
the level of partnership and support level given to the system
supplier/installer.
5. Supplier/Installer must submit detailed reference list indicating similar projects
installations indicating, location P/N and Quantities of installed items.
D TRAINING:
E Warranty: Provide warranty for the system for at least 3 Years starting from the first
day of system handing over to the operation team. SLA (Service level agreement)
shall be submitted and approved by the operator.
F Licenses: The systems shall be provided with all necessary licenses and allow for any
future upgrade software /firmware. Online notifications should be included to allow
for any software versions upgrades according to service level agreement with project
operator.
A Deliver products in factory containers. Store in clean, dry, closed space in original
containers. Protect products from fumes. Handle very carefully to avoid shocks or
damage.
C Inspection shall be performed in two stages, first time upon receiving the equipment,
devices and cables on site before storing and second time after installation according
to installation phases.
A General: Submit the necessary complete sets of documentation indicating type, size,
rating, style, catalogue number, Manufacturers names, and/or catalogue data sheets
for all items to ensure compliance with specifications. This documentation shall be
subject to the approval of the Engineer and no equipment shall be ordered without
his approval for all equipment and devices, which are shown on documents
(drawings, specs …etc). Any document submitted by the Contractor during the tender
stage shall not be considered as technical submittal, it shall be used only to approve
the manufacturer name. During technical submittal stage, Contractor shall submit all
required technical document for study and approval.
B For any missing or mismatch between various drawings sets in all disciplines,
contractor must issue RFI (Request for Information) to the Design Engineer to provide
the proper corrective action.
C Shop Drawings: Submit shop drawings & Composite drawings showing equipment,
device locations, labeling, part number and connecting wiring of the systems,
including riser diagrams. Shop drawings shall include, but not be limited to the
following:
D Material Submittal: shall include, but not be limited to, the following:
1. Contractor and System integrator shall stamp and approve the system material
submittal prior to submitting to the Engineer.
2. Pin to pin connection diagram
3. Complete one-line riser diagram(s) showing all equipment and the size,
connections, type and number of all equipment
4. Include programming and installation manuals
5. Complete sequence of operations and functions of the system
6. Complete system wiring diagrams for components and interfaces to
equipment supplied by others
7. A listing of the manufacturer's authorized, local representative responsible for
installation, coordination and service
8. Compliance sheet item by item providing a comparison between each item
specifies each item submitted. Contractor must indicate clearly any deviations
from design & items specifications-if exists-indicating the reason of deviation.
Such deviations must be approved by the Design Engineer.
9. Detailed Technical Data sheets with highlighted part numbers must be
submitted.
10. [All System cables must be approved by system manufacturer. Contractor
must provide a letter from the manufacturing approving the cables connected
to the manufacturer devices/equipment]
11. BOQ in ECG Format complete with quantities and products part numbers.
12. The submitted BOQ must be mapped to ECG BOQ. i.e. Each item in ECG BOQ
should be followed by The equivalent manufacturer Part numbers fulfilling the
requirements of ECG BOQ item. this shall include all hardware and software
licenses and services that fulfill the ECG Item requirements.
13. Compliance Response on this specification document (in every page in this
specifications document) with project approved vendor list. Any deviations
F Maintenance Data: Submit maintenance data and parts lists for each type of the
installed system including furnished specialties and accessories. Include this data,
product data, and shop drawings in maintenance manual; in accordance with
requirements of other relevant documentation.
I System Initial Configurations: Contractor must perform all necessary system software
configurations-as required- based on the project operator/client requirements.
Detailed configuration plan must be submitted for the client approval prior to
configuration.
K System supplier & Installer qualifications documents: System supplier & Installer
should submit the required certifications indicating that the system supplier and
installer company is certified from system manufacturer to perform all system
supplying, installations, testing and commissioning supported by system installers
CVs and related manufacturer certifications. The system supplier should be involved
in a strong relationship with system manufacturer with proven reference of similar
projects. The system supplier & installer should submit reference of similar projects
and abide by all requirements in project documents (specifications, drawings, BOQ,
and method of measurements)
N Finalized Reflected ceiling drawings: illustrating all works in the ceilings after
finalizing the coordination process.
P Close out documents: Required documents shall include but not limited to the
following:
1. As built drawings: During the construction of the system, the Contractor shall
put in writing all his remarks, during the progress of work, concerning any
suggested alterations from the shop drawings in wiring routes, locations of
equipment or devices which arise from coordination between the system and
other activities on related shop drawing plans. As built drawings and
documents shall include updating for all of the drawings, documents,
calculations, data sheets… etc. previously submitted in shop drawing stage to
reflect what is exactly executed on site.
2. During executing the work and preparing the drawings, no execution of
alterations shall be allowed before receiving a written approval from the
Engineer.
3. All alterations shall be registered and filled by the Contractor and extra copies
shall be submitted to the involved parties (Engineer, Project Manager, Site,
etc.).
4. Complete as-built draft set of Drawings and equipment schedules shall be
prepared fifteen (15) days after completion of work for the engineer’s
approval. The as built draft shall include all previously approved alterations
and technical data sheets of installed equipment, devices…. etc. Final originals
and copies of the as-built Drawings shall be submitted in accordance with
Contract documents.
5. As built documents shall also include: Operation and maintenance manuals
including; updated data sheets for installed equipment, operation instructions,
programming procedures Electronic circuits for every device and equipment,
troubleshooting repair guide, and the required spare parts list for 5 years of
operation, along with the circuit diagram. Selected spare parts shall be
provided without any extra cost.
Q EXTRA MATERIALS
PART 2 PRODUCTS
2.1 GENERAL
A The intelligent addressable fire alarm system will be composed of the following
items:
B The above components shall be provided with the appropriate numbers and
capacities to serve the whole project and achieve the design intent. The locations of
various system components are shown on the drawings. Other components and
accessories deemed necessary and essential for system operation and integration
which are not shown on drawings are deemed essential and integral part of the
design intent which should be included in the contractor submitted solution to
achieve end to end fully functional integrated system.
C All notes on the drawings are integral part of the contract document and must be
read in conjunction with all design package documents (specification, BOQs...etc)
D The following general requirements shall be fulfilled in the provided system. Bidders
shall state clearly any deviations/omissions or additions from the desired
specifications, drawings and BOQs. Such deviations-If Exist- must be assessed and
approved by the Design Engineer.
Intelligent Addressable
Loops as per drawings [loop must have 20% spare]
Interface communication cards
Listed for smoke control, [UL 864] [Or equivalent Standards]
[Modular] [Microprocessor based] [LED display]
[RJ45 Ethernet Network interface] [RS 484] [RS323] [FO
communication]
[UL Listed Backup battery 24 Hour in standby mode and 15
Min in system full alarm mode] [Battery charger] [Battery
monitoring system-provide battery status and alarm].
I/O points on the panel for hardwired interfaces.
Not less than 5000 Events in memory
Grounding kit
Power supply panels
Repeater Panel
Event Printer
Addressable.
Double actions
Tamper resistant
Reset Key lock
LED Indicator
Built-in Fault isolation module.
Operable part of a manually actuated alarm initiating de-
vice shall be ranging from 1.10m to 1.40 m from the fin-
ished floor as per local fire alarm code.
Manual fire alarm boxes shall be located within 5ft
(1.5m) of each exit doorway on each floor.
Strobe light
Siren
Siren -Outdoor
Addressable
Two (2) state alarm or supervisory signals.
Built-in Fault isolation module
LED indicator
Addressable.
Interfacing circuits.
Built-in Fault isolation module
Addressable
Operate audible and visible signal appliances.
Built-in Fault isolation module
PART 3 INSTALLATION
C Identify system components, wiring, cabling, boxes, panels and terminals. Comply
with requirements for system identification according to project operator
requirements.
D System labeling scheme must be submitted to the End user project operator for
approval. Operator teams labeling requirements should be considered.
G All System Cables should be LSZH produce no toxic gases in case of fire.
H Cables should be listed for the system specific application and installation
requirements
I All wires and cables shall be listed and/or approved by a recognized testing agency &
System manufacturer through official letter supported with all necessary calculations,
documentations and testing certificates.
J Embedded conduits shall be PVC and all exposed conduits shall be EMT conduit
K All wiring shall be color coded and cabled. Junction boxes shall be color coded and
include wiring identification numbering.
L Wires and cables shall provide sufficient resistance to the spread of fire and generate
no hazardous smoke to human life.
M Wiring System shall include all indoor and outdoor cables necessary for complete
system installations.
3.2 GROUNDING:
A System labelling scheme must be submitted to the End user for approval. Operator
teams labelling requirements should be considered.
G Maintenance Test and Inspection: Perform tests and inspections listed for weekly,
monthly, quarterly, and semi-annual periods. Use forms developed for initial tests
and inspections.
H Annual Test and Inspection: One year after date of Substantial Completion, test the
system complying with visual and testing inspection requirements. Use forms
developed for initial tests and inspections.
J System manufacturer and his authorized, local representative shall provide, in depth,
system service on site training to selected Employer’s personnel for two weeks.
A Contractor shall coordinate to provide the necessary required power (DC &A) for all
equipment after determining the manufacturer equipment exact part number and
hence submit any necessary modifications (if needed) according to selected
equipment manufacturer instructions.
B The System supplier shall be responsible for coordination and exchange information
with the Suppliers of other systems and equipment which shall communicate with, in
order to achieve the required specified functions and achieve the AHJ requirements,
operator requirements and related international codes and standards. Contractor
must coordinate with all other MEP disciplines to perform all manual override and
systems reset and return to normal operation, a detailed document shall be
submitted for the engineer’s approval. This process is valid in all stages of the project
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. DISABLED ALARM SYSTEM
CAIRO - EGYPT 283101 - 2874 0
SECTION 283101
Page
PART 1 INTRODUCTION 2
1.1 SCOPE 2
1.2 Related Documents 2
1.3 System Description 3
1.4 External Links /Connectivity 4
1.5 Interface Requirements With Bms 4
1.6 References And Compliance 4
1.7 Abbreviations & Definitions 5
1.8 Quality Assurance 5
1.9 Delivery, Storage And Handling 6
1.10 Contractor Responsibility & Submittals 7
PART 2 PRODUCTS 11
2.1 General 11
2.2 Products Minimum Technical Requirement 12
PART 3 INSTALLATION 13
3.1 Installation Of Basic Wiring System Materials 13
3.2 Grounding: 14
3.3 System Labelling 14
3.4 Field Quality Control 14
3.5 Coordination With Other Divisions 15
PART 1 INTRODUCTION
1.1 SCOPE
A This document provides the minimum technical specifications / requirements for the
Disabled Persons Emergency Call System that shall be installed in the project as
indicated in drawings and relevant documents.
B The WORK of this Part is integral with the whole of the Project Documentation and is
not intended to be interpreted outside that context.
C This Part of the WORK shall be read and executed in conjunction and coordination
with all other Sections of this Specification and other Services/Trade Contractors.
D This section applies to the Disabled Persons Emergency Call System, as indicated on
accompanying layout drawings and as required by this specification.
F The contractor is fully responsible to achieve the design intent indicated in the design
package including drawings, specifications and BOQs.
A Contractor must refer to all other related packages for coordination purposes. For
any missing information or contradicting information, contractor must submit RFI
(Request for information) to the design Engineer. No action or interpretation of the
design documents shall be considered valid for construction until it is approved by
the design Engineer through a reply to the RFI.
A The work to be carried out under this section shall comprise the supply, installation,
testing, commissioning and setting to work all items that are necessary for a
complete Disabled Persons Emergency Call System as per specifications and
drawings. Contractor shall develop a comprehensive Disabled Persons Emergency
Call System including, but not limited to the items indicated throughout the design
package including specification , drawings and BOQ
C At this point that the performance requirements in this specification are subject to
change due to market updates. Therefore it is the Contractor’s responsibility to
ensure that Hardware and Operating System (where applicable) information is
updated at time of hardware selection or installation.
E The Service level agreement (SLA) is considered integral part of this specification.
F The Disabled Emergency Call Systems are facilities that shall be used by disabled
persons in emergency cases.
G A Disabled Toilet Emergency Call System shall be used inside all Disabled Toilets.
H Pulling a pull cord by a disabled person shall initiate an alarm led in the main control
panel and a led in the remote alarm indicator located outside the toilet.
I Upon dealing with the emergency case, a reset button inside the toilet can reset the
system to its normal operation.
L The emergency call system shall be electrically supervised so that loss of AC power
will result in an audible and visual trouble indication at the control panel.
M The system shall be equipped with secondary power, or terminals or leads for the
connection of secondary power (batteries).
N The capacity of the secondary power (batteries) shall be sufficient to operate the
system at 10% of its maximum signaling capacity for the time specified in the
manufacturer’s installation instructions.
P With secondary power connected, neither loss nor restoration of the primary voltage
source shall cause the indication of an off-normal condition.
Q There shall be no loss of emergency call signals while a signaling unit is energized by a
secondary power source.
R A trouble signal shall be distinguishable from all emergency call signals and shall be
indicated by operation of a sounding appliance.
S Momentary power failures and subsequent power restorations shall not render the
equipment inoperative for any of its functions.
B Contractor must follow all Monitor and control points indicated in the I/O Schedules
attached to the Building management system specifications
A All works shall be performed in strict accordance with the drawings, specifications
and stipulations of the Local Building and safety Codes, TIA/EIA the National Fire
Protection Association (NFPA), International Electrical Commission (IEC) and other
related international standards
1. Contractor is required to comply with the approved vendor list. Any deviation
must be documented and approved by the design engineer through the official
approval procedure updated at the time of the project.
2. The Supplier/Installer/Manufacturer must be registered with ECG through the
ECG Official procedure prior to submitting the technical material submittal.
3. The Contractor must follow the approved vendor list for the project. Approved
equal manufacturers must be submitted to the Design Engineer for Approval
through the official registration procedure.
4. Supplier /Installer must submit Official letter from the manufacturer indicating
the level of partnership and support level given to the system
supplier/installer.
5. Supplier/Installer must submit detailed reference list indicating similar projects
installations indicating, location P/N and Quantities of installed items .
D TRAINING:
E Warranty: Provide warranty for the system for at least 3 Years starting from the first
day of system handing over to the operation team. SLA (Service level agreement)
shall be submitted and approved by the operator.
F Licenses: The systems shall be provided with all necessary licenses and allow for any
future upgrade software /firmware. Online notifications should be included to allow
for any software versions upgrades according to service level agreement with project
operator.
G Source Limitations for the System and Components: Obtain all system components
from single source from single manufacturer. Any deviation must be supported with
documented reasons which shall be assessed and approved by the Engineer.
A Deliver products in factory containers. Store in clean, dry, closed space in original
containers. Protect products from fumes. Handle very carefully to avoid shocks or
damage.
C Inspection shall be performed in two stages, first time upon receiving the equipment,
devices and cables on site before storing and second time after installation according
to installation phases.
A General: Submit the necessary complete sets of documentation indicating type, size,
rating, style, catalogue number, Manufacturers names, and/or catalogue data sheets
for all items to ensure compliance with specifications. This documentation shall be
subject to the approval of the Engineer and no equipment shall be ordered without
his approval for all equipment and devices, which are shown on documents
(drawings, specs …etc). Any document submitted by the Contractor during the tender
stage shall not be considered as technical submittal, it shall be used only to approve
the manufacturer name. During technical submittal stage, Contractor shall submit all
required technical document for study and approval.
B For any missing or mismatch between various drawings sets in all disciplines,
contractor must issue RFI (Request for Information) to the Design Engineer to provide
the proper corrective action.
C Shop Drawings: Submit shop drawings & Composite drawings showing equipment,
device locations, labeling, part number and connecting wiring of the systems,
including riser diagrams. Shop drawings shall include, but not be limited to the
following:
1. Complete pin to pin one-line riser diagram(s) showing all approved equipment,
size, type and number of all conductors, interconnection between the system
and all other related systems.
2. Installation details for all system components. Installation details drawings
shall show all accessories used in installation such as back boxes, glands,
washers, etc.
3. Complete Grounding details as per system manufacturer requirements.
Indicating connections with dedicated grounding system including connections
with telecommunication grounding bus bars as part of overall grounding and
bonding system including telecom main grounding bus bar.
4. Exact location of every single component of the system in coordination with all
other works (Electromechanical, Arch., and Civil).
5. Colored Composite drawings for all MEP systems showing all coordinated MEP
works
6. Signature of all involved contractor engineers representing different disciplines
(Electromechanical, Arch, and Civil etc.) to confirm their approval of such
locations, installations and coordination.
7. Complete sequence of operations and functions of the system.
8. All drawings and technical material submittals should be submitted in both
softcopy and hardcopy formats .No of copies shall be according to contract
documents requirements (at least three copies shall be submitted)
D Material Submittal: shall include, but not be limited to, the following:
1. Contractor and System integrator shall stamp and approve the system material
submittal prior to submitting to the Engineer.
2. Pin to pin connection diagram
3. Complete one-line riser diagram(s) showing all equipment and the size,
connections, type and number of all equipment
4. Include programming and installation manuals
Disabled Alarm System
Urbanium New Administrative Building (Prj. 2874) Section 283101
Page 7 of 15
5. Complete sequence of operations and functions of the system
6. Complete system wiring diagrams for components and interfaces to
equipment supplied by others
7. A listing of the manufacturer's authorized, local representative responsible for
installation, coordination and service
8. Compliance sheet item by item providing a comparison between each item
specifies each item submitted. Contractor must indicate clearly any deviations
from design & items specifications-if exists-indicating the reason of deviation.
Such deviations must be approved by the Design Engineer.
9. Detailed Technical Data sheets with highlighted part numbers must be
submitted.
10. [All System cables must be approved by system manufacturer .Contractor
must provide a letter from the manufacturing approving the cables connected
to the manufacturer devices/equipment]
11. BOQ in ECG Format complete with quantities and products part numbers.
12. The submitted BOQ must be mapped to ECG BOQ .i.e Each item in ECG BOQ
should be followed by The equivalent manufacturer Part numbers fulfilling the
requirements of ECG BOQ item .this shall include all hardware and software
licenses and services that fulfill the ECG Item requirements.
13. Compliance Response on this specification document (in every page in this
specifications document) with project approved vendor list . Any deviations
from the project approved vendor list must be approved by the Design
Engineer.
14. All Specifications and BOQs must be stamped by the contractor declaring fully
compliance.
F Maintenance Data: Submit maintenance data and parts lists for each type of the
installed system including furnished specialties and accessories. Include this data,
product data, and shop drawings in maintenance manual; in accordance with
requirements of other relevant documentation.
G Instruction Manuals: The Contractor shall provide with the assistance of the
equipment manufacturer and its authorized, local representative. In addition, one
approved copy of the system submittal, complete operating instructions; pertinent
system orientation documents and system service.
I System Initial Configurations: Contractor must perform all necessary system software
configurations-as required- based on the project operator/client requirements.
Detailed configuration plan must be submitted for the client approval prior to
configuration.
1. Provide calculations to support the size of the backup batteries for the
emergency power supply.
2. Provide calculation of the DC lines to indicate the no. of audible alarms and
visual strobe lights per each circuit.
K System supplier & Installer qualifications documents: System supplier & Installer
should submit the required certifications indicating that the system supplier and
installer company is certified from system manufacturer to perform all system
supplying, installations, testing and commissioning supported by system installers
CVs and related manufacturer certifications. The system supplier should be involved
in a strong relationship with system manufacturer with proven reference of similar
projects. The system supplier & installer should submit reference of similar projects
N Finalized Reflected ceiling drawings: illustrating all works in the ceilings after
finalizing the coordination process.
P Close out documents: Required documents shall include but not limited to the
following :
1. As built drawings: During the construction of the system, the Contractor shall
put in writing all his remarks, during the progress of work, concerning any
suggested alterations from the shop drawings in wiring routes, locations of
equipment or devices which arise from coordination between the system and
other activities on related shop drawing plans. As built drawings and
documents shall include updating for all of the drawings, documents,
calculations, data sheets..etc previously submitted in shop drawing stage to
reflect what is exactly executed on site.
2. During executing the work and preparing the drawings, no execution of
alterations shall be allowed before receiving a written approval from the
Engineer.
3. All alterations shall be registered and filled by the Contractor and extra copies
shall be submitted to the involved parties (Engineer, Project Manager, Site,
etc.).
4. Complete as-built draft set of Drawings and equipment schedules shall be
prepared fifteen (15) days after completion of work for the engineer’s
Disabled Alarm System
Urbanium New Administrative Building (Prj. 2874) Section 283101
Page 10 of 15
approval. The as built draft shall include all previously approved alterations
and technical data sheets of installed equipment, devices…..etc. Final originals
and copies of the as-built Drawings shall be submitted in accordance with
Contract documents.
5. As built documents shall also include: Operation and maintenance manuals
including; updated data sheets for installed equipments, operation
instructions, programming procedures Electronic circuits for every device and
equipment, troubleshooting repair guide, and the required spare parts list for
5 years of operation, along with the circuit diagram. Selected spare parts shall
be provided without any extra cost.
Q EXTRA MATERIALS
PART 2 PRODUCTS
2.1 GENERAL
A The Disabled Persons Emergency Call System will be composed of the following
items:
B The above components shall be provided with the appropriate numbers and
capacities to serve the whole project and achieve the design intent. The locations of
various system components are shown on the drawings. Other components and
accessories deemed necessary and essential for system operation and integration
which are not shown on drawings are deemed essential and integral part of the
design intent which should be included in the contractor submitted solution to
achieve end to end fully functional integrated system.
C All notes on the drawings are integral part of the contract document and must be
read in conjunction with all design package documents (specification ,BOQs...etc)
Floor Controller
PART 3 INSTALLATION
C Identify system components, wiring, cabling, boxes, panels and terminals. Comply
with requirements for system identification according to project operator
requirements.
D System labeling scheme must be submitted to the End user project operator for
approval. Operator teams labeling requirements should be considered.
G All System Cables should be LSZH produce no toxic gases in case of fire.
H Cables should be listed for the system specific application and installation
requirements
I All wires and cables shall be listed and/or approved by a recognized testing agency &
System manufacturer through official letter supported with all necessary calculations,
documentations and testing certificates.
J Embedded conduits shall be PVC and all exposed conduits shall be EMT conduit
Disabled Alarm System
Urbanium New Administrative Building (Prj. 2874) Section 283101
Page 13 of 15
K All wiring shall be color coded and cabled. Junction boxes shall be color coded and
include wiring identification numbering.
L Wires and cables shall provide sufficient resistance to the spread of fire and generate
no hazardous smoke to human life.
M Wiring System shall include all indoor and outdoor cables necessary for complete
system installations.
3.2 GROUNDING:
A System labelling scheme must be submitted to the End user for approval. Operator
teams labelling requirements should be considered.
E The system will be considered defective if it does not pass tests and inspections.
G Maintenance Test and Inspection: Perform tests and inspections listed for weekly,
monthly, quarterly, and semi-annual periods. Use forms developed for initial tests
and inspections.
H Annual Test and Inspection: One year after date of Substantial Completion, test the
system complying with visual and testing inspection requirements. Use forms
developed for initial tests and inspections.
A Contractor shall coordinate to provide the necessary required power (DC &A) for all
equipment after determining the manufacturer equipment exact part number and
hence submit any necessary modifications (if needed) according to selected
equipment manufacturer instructions.
B The System supplier shall be responsible for coordination and exchange information
with the Suppliers of other systems and equipment which shall communicate with, in
order to achieve the required specified functions and achieve the AHJ requirements,
operator requirements and related international codes and standards. Contractor
must coordinate with all other MEP disciplines to perform all manual override and
systems reset and return to normal operation, a detailed document shall be
submitted for the engineer’s approval. This process is valid in all stages of the project
END OF SECTION-283101
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. WATER LEAK DETECTION SYSTEM
CAIRO - EGYPT 283600 – 2874 0
SECTION 283600
Page
PART 1 INTRODUCTION 2
1.1 SCOPE 2
1.2 Related Documents 2
1.3 System Description 3
1.4 External Links /Connectivity 4
1.5 Interface Requirements With Bms 4
1.6 References And Compliance 4
1.7 Abbreviations & Definitions: 4
1.8 Quality Assurance 5
1.9 Delivery, Storage And Handling 6
1.10 Contractor Responsibility & Submittals 6
PART 2 PRODUCTS 11
2.1 General 11
2.2 Products Minimum Technical Requirement 11
PART 3 INSTALLATION 13
3.1 Installation Of Basic Wiring System Materials 13
3.2 Grounding: 14
3.3 System Labelling 14
3.4 Field Quality Control 14
3.5 Coordination With Other Divisions 15
PART 1 INTRODUCTION
1.1 SCOPE
A This document provides the minimum technical specifications / requirements for the
Water Leak detection system that shall be installed in the project as indicated in
drawings and relevant documents.
B The WORK of this Part is integral with the whole of the Project Documentation and is
not intended to be interpreted outside that context.
C This Part of the WORK shall be read and executed in conjunction and coordination
with all other Sections of this Specification and other Services/Trade Contractors.
F The contractor is fully responsible to achieve the design intent indicated in the design
package including drawings, specifications and BOQs.
A Contractor must refer to all other related packages for coordination purposes. For
any missing information or contradicting information, contractor must submit RFI
(Request for information) to the design Engineer. No action or interpretation of the
design documents shall be considered valid for construction until it is approved by
the design Engineer through a reply to the RFI.
A The work to be carried out under this section shall comprise the supply, installation,
testing, commissioning and setting to work all items that are necessary for a
complete Water Leak detection system as per specifications and drawings.
Contractor shall develop a comprehensive Water Leak detection system including,
but not limited to the items indicated throughout the design package including
specification , drawings and BOQ
C At this point that the performance requirements in this specification are subject to
change due to market updates. Therefore it is the Contractor’s responsibility to
ensure that Hardware and Operating System (where applicable) information is
updated at time of hardware selection or installation.
E The Service level agreement (SLA) is considered integral part of this specification.
F Leak detection system should be provided to notify building operators in the event of
a water/fuel leak.
G Water leak detection system shall be installed under raised floor of the server room
and under CRAC units or at any other areas as indicated on drawings.
H Fuel leakage detection system shall be installed inside generator rooms of the data
center.
I The Water leak detection system shall detect and report the presence and exact
location of water and other liquids.
J The system shall points the location of the leak when a conductive liquid comes in
contact with the water leak detection sensor cable.
K In the event of a leak the system shall sound and the exact location (distance from
the panel) of the leak shall be shown on the liquid crystal display (LCD).
L The system shall have the capability to eliminate high humidity false alarms that can
occur.
M The system shall continuously monitor the Leak Detection Sensor Cable and the
following trouble signals in the system shall activate local audiovisual alarm together
with visual display of the nature of the trouble in the water leakage detection panel:
N The system shall be consists of leakage detection control panel and Sensor Cable.
O The contractor is responsible for selecting the sensor cable length and to make sure
that the sensor length shall fit the room dimensions in order to have full coverage
areas.
P The system shall be interfaced with BMS systems to report the alarms and take the
proper actions.
A Contractor must follow all Monitor and control points indicated in the I/O Schedules
attached to the Building management system specifications
A All works shall be performed in strict accordance with the drawings, specifications
and stipulations of the Local Building and safety Codes, TIA/EIA the National Fire
Protection Association (NFPA), International Electrical Commission (IEC) and other
related international standards
1. Contractor is required to comply with the approved vendor list. Any deviation
must be documented and approved by the design engineer through the official
approval procedure updated at the time of the project.
2. The Supplier/Installer/Manufacturer must be registered with ECG through the
ECG Official procedure prior to submitting the technical material submittal.
3. The Contractor must follow the approved vendor list for the project. Approved
equal manufacturers must be submitted to the Design Engineer for Approval
through the official registration procedure.
4. Supplier /Installer must submit Official letter from the manufacturer indicating
the level of partnership and support level given to the system
supplier/installer.
5. Supplier/Installer must submit detailed reference list indicating similar projects
installations indicating, location P/N and Quantities of installed items.
D TRAINING:
E Warranty: Provide warranty for the system for at least 3 Years starting from the first
day of system handing over to the operation team. SLA (Service level agreement)
shall be submitted and approved by the operator.
F Licenses: The systems shall be provided with all necessary licenses and allow for any
future upgrade software /firmware. Online notifications should be included to allow
for any software versions upgrades according to service level agreement with project
operator.
G Source Limitations for the System and Components: Obtain all system components
from single source from single manufacturer. Any deviation must be supported with
documented reasons which shall be assessed and approved by the Engineer.
A Deliver products in factory containers. Store in clean, dry, closed space in original
containers. Protect products from fumes. Handle very carefully to avoid shocks or
damage.
C Inspection shall be performed in two stages, first time upon receiving the equipment,
devices and cables on site before storing and second time after installation according
to installation phases.
A General: Submit the necessary complete sets of documentation indicating type, size,
rating, style, catalogue number, Manufacturers names, and/or catalogue data sheets
for all items to ensure compliance with specifications. This documentation shall be
subject to the approval of the Engineer and no equipment shall be ordered without
his approval for all equipment and devices, which are shown on documents
(drawings, specs …etc). Any document submitted by the Contractor during the tender
stage shall not be considered as technical submittal, it shall be used only to approve
B For any missing or mismatch between various drawings sets in all disciplines,
contractor must issue RFI (Request for Information) to the Design Engineer to provide
the proper corrective action.
C Shop Drawings: Submit shop drawings & Composite drawings showing equipment,
device locations, labeling, part number and connecting wiring of the systems,
including riser diagrams. Shop drawings shall include, but not be limited to the
following:
1. Complete pin to pin one-line riser diagram(s) showing all approved equipment,
size, type and number of all conductors, interconnection between the system
and all other related systems.
2. Installation details for all system components. Installation details drawings
shall show all accessories used in installation such as back boxes, glands,
washers, etc.
3. Complete Grounding details as per system manufacturer requirements.
Indicating connections with dedicated grounding system including connections
with telecommunication grounding bus bars as part of overall grounding and
bonding system including telecom main grounding bus bar.
4. Exact location of every single component of the system in coordination with all
other works (Electromechanical, Arch., and Civil).
5. Colored Composite drawings for all MEP systems showing all coordinated MEP
works
6. Signature of all involved contractor engineers representing different disciplines
(Electromechanical, Arch, and Civil etc.) to confirm their approval of such
locations, installations and coordination.
7. Complete sequence of operations and functions of the system.
8. All drawings and technical material submittals should be submitted in both
softcopy and hardcopy formats .No of copies shall be according to contract
documents requirements (at least three copies shall be submitted)
9. Complete room coverage layout showing sensor cable routing and all related
equipment exact locations (i.e. HVAC CRAC units, fuel tanks, generator,…etc.
D Material Submittal: shall include, but not be limited to, the following:
1. Contractor and System integrator shall stamp and approve the system material
submittal prior to submitting to the Engineer.
2. Pin to pin connection diagram
3. Complete one-line riser diagram(s) showing all equipment and the size,
connections, type and number of all equipment
4. Include programming and installation manuals
5. Complete sequence of operations and functions of the system
6. Complete system wiring diagrams for components and interfaces to
equipment supplied by others
7. A listing of the manufacturer's authorized, local representative responsible for
installation, coordination and service
8. Compliance sheet item by item providing a comparison between each item
specifies each item submitted. Contractor must indicate clearly any deviations
F Maintenance Data: Submit maintenance data and parts lists for each type of the
installed system including furnished specialties and accessories. Include this data,
product data, and shop drawings in maintenance manual; in accordance with
requirements of other relevant documentation.
G Instruction Manuals: The Contractor shall provide with the assistance of the
equipment manufacturer and its authorized, local representative. In addition, one
approved copy of the system submittal, complete operating instructions; pertinent
system orientation documents and system service.
I System Initial Configurations: Contractor must perform all necessary system software
configurations-as required- based on the project operator/client requirements.
Detailed configuration plan must be submitted for the client approval prior to
configuration.
K System supplier & Installer qualifications documents: System supplier & Installer
should submit the required certifications indicating that the system supplier and
installer company is certified from system manufacturer to perform all system
supplying, installations, testing and commissioning supported by system installers
CVs and related manufacturer certifications. The system supplier should be involved
in a strong relationship with system manufacturer with proven reference of similar
projects. The system supplier & installer should submit reference of similar projects
and abide by all requirements in project documents (specifications, drawings ,BOQ,
and method of measurements)
P Close out documents :Required documents shall include but not limited to the
following :
1. As built drawings: During the construction of the system, the Contractor shall
put in writing all his remarks, during the progress of work, concerning any
suggested alterations from the shop drawings in wiring routes, locations of
equipment or devices which arise from coordination between the system and
other activities on related shop drawing plans. As built drawings and
documents shall include updating for all of the drawings, documents,
calculations, data sheets..etc previously submitted in shop drawing stage to
reflect what is exactly executed on site.
2. During executing the work and preparing the drawings, no execution of
alterations shall be allowed before receiving a written approval from the
Engineer.
3. All alterations shall be registered and filled by the Contractor and extra copies
shall be submitted to the involved parties (Engineer, Project Manager, Site,
etc.).
4. Complete as-built draft set of Drawings and equipment schedules shall be
prepared fifteen (15) days after completion of work for the engineer’s
approval. The as built draft shall include all previously approved alterations
and technical data sheets of installed equipment, devices…..etc. Final originals
and copies of the as-built Drawings shall be submitted in accordance with
Contract documents.
5. As built documents shall also include: Operation and maintenance manuals
including; updated data sheets for installed equipments, operation
instructions, programming procedures Electronic circuits for every device and
equipment, troubleshooting repair guide, and the required spare parts list for
5 years of operation, along with the circuit diagram. Selected spare parts shall
be provided without any extra cost.
PART 2 PRODUCTS
2.1 GENERAL
A The Water leak detection system will be composed of the following items:
B he above components shall be provided with the appropriate numbers and capacities
to serve the whole project and achieve the design intent. The locations of various
system components are shown on the drawings. Other components and accessories
deemed necessary and essential for system operation and integration which are not
shown on drawings are deemed essential and integral part of the design intent which
should be included in the contractor submitted solution to achieve end to end fully
functional integrated system.
C All notes on the drawings are integral part of the contract document and must be
read in conjunction with all design package documents (specification ,BOQs...etc)
D The following general requirements shall be fulfilled in the provided system. Bidders
shall state clearly any deviations/omissions or additions from the desired
specifications, drawings and BOQs. Such deviations-If Exist- must be assessed and
approved by the Design Engineer.
Sensor Cable
PART 3 INSTALLATION
C Identify system components, wiring, cabling, boxes, panels and terminals. Comply
with requirements for system identification according to project operator
requirements.
D System labeling scheme must be submitted to the End user project operator for
approval. Operator teams labeling requirements should be considered.
G All System Cables should be LSZH produce no toxic gases in case of fire.
H Cables should be listed for the system specific application and installation
requirements
I All wires and cables shall be listed and/or approved by a recognized testing agency &
System manufacturer through official letter supported with all necessary calculations,
documentations and testing certificates.
K All wiring shall be color coded and cabled. Junction boxes shall be color coded and
include wiring identification numbering.
L Wires and cables shall provide sufficient resistance to the spread of fire and generate
no hazardous smoke to human life.
M Wiring System shall include all indoor and outdoor cables necessary for complete
system installations.
3.2 GROUNDING:
A System labelling scheme must be submitted to the End user for approval. Operator
teams labelling requirements should be considered.
E The system will be considered defective if it does not pass tests and inspections.
G Maintenance Test and Inspection: Perform tests and inspections listed for weekly,
monthly, quarterly, and semi-annual periods. Use forms developed for initial tests
and inspections.
H Annual Test and Inspection: One year after date of Substantial Completion, test the
system complying with visual and testing inspection requirements. Use forms
developed for initial tests and inspections.
J System manufacturer and his authorized, local representative shall provide, in depth,
system service on site training to selected Employer’s personnel for two weeks.
A Contractor shall coordinate to provide the necessary required power (DC &A) for all
equipment after determining the manufacturer equipment exact part number and
hence submit any necessary modifications (if needed) according to selected
equipment manufacturer instructions.
B The System supplier shall be responsible for coordination and exchange information
with the Suppliers of other systems and equipment which shall communicate with, in
order to achieve the required specified functions and achieve the AHJ requirements,
operator requirements and related international codes and standards. Contractor
must coordinate with all other MEP disciplines to perform all manual override and
systems reset and return to normal operation, a detailed document shall be
submitted for the engineer’s approval. This process is valid in all stages of the project
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. EARTHWORK
CAIRO - EGYPT 312000 – 2874 1
SECTION 312000
EARTHWORK
Page
PART 1 GENERAL 2
PART 3 EXECUTION 10
PART 1 GENERAL
A. Drawings and general provisions of the Contract, including Contract Conditions and
Division 1 Specification Sections, apply to work of this section.
1.2 SUMMARY
A. Earth works including cut, fill and backfilling and grading works shall be performed in
compliance with Drawings, tests and the requirements of the project, and the
specifications of the American Society of Testing and Materials (ASTM) as noted
below:
ASTM No.
ASTM C131 Standard Test Method for Resistance to Degradation of Small Size
Coarse Aggregate by Abrasion and impact in the Los Angeles
Machine.
ASTM C136 Sieve Analysis of Fine and Coarse Aggregates
ASTM C142 Clay Lumps and Friable Particles in Aggregates
ASTM D421 Practice for Dry Preparation of Soil Samples for Particle Size Analysis
and Determination of Soil Constants
ASTM D422 Particle Size Analysis of Soils
ASTM D427 Shrinkage Factors of Soils
ASTM D512 Chloride Ion in Water
ASTM D516 Sulfate Ion in Water
ASTM D638 Tensile Properties of Plastics
ASTM D698 Moisture Density Relation of Soils and Soil Aggregate Mixtures
ASTM D854 Specific Gravity of Soils
ASTM D1293 pH of Water
ASTM D1556 Density of Soil in Place by the Sand-Cone Method
Earthwork Section 312000
Urbanium Office Building (Prj. 2874) Page 2 of 17
ASTM D1557 Moisture Density Relations of Soils and Soil Aggregate Mixtures Using
10 lb. (4.54 kg) Hammer and 18 in (457 mm) Drop
ASTM D1586 Penetration Test and Split-Barrel Sampling of Soils
ASTM D1883 Standard Test Method for California Bearing Ratio of Laboratory
Compacted Soils
ASTM D2167 Density and Unit Weight of Soil In-Place by the Rubber Balloon
Method
ASTM D2487 Classification of Soils for Engineering Purposes
ASTM D2488 Description and Identification of Soils (Visual-Manual Procedure)
ASTM D2922 Density of Soil and Soil-Aggregate in Place by Nuclear Methods
(Shallow Depth)
ASTM D2940 Graded Aggregate Material for Bases or Sub-bases for Highways or
Airports
ASTM D3776 Standard Test MG7000 for Mass per Unit Area (Weight) of woven
fabric
ASTM D3786 Hydraulic Bursting Strength of Knitted Goods and Nonwoven Fabrics-
Diaphragm Bursting Strength Tester Method
ASTM D4253 Maximum Index Density of Soils Using a Vibratory Table
ASTM D4254 Minimum Index Density of Soils and Calculation of Relative Density
ASTM D4318 Standard Test Method for Liquid Limit, Plastic Limit, and Plasticity
Index of Soils
ASTM D4491 Standard Test Method for Water Permeability of Geotextiles by
Permittivity
ASTM D4632 Standard Test Method for Grab Breaking Load and Elongation of
Geotextiles
ASTM D4718 Correction of Unit Weight and Water Content for Soils Containing
Oversize Particles
ASTM D5030 Density of Soil and Rock in Place by the Water Replacement Method
in a Test Pit
1.5 SUBMITTALS
A. Submit the following in accordance with Conditions of the Contract and Division-1
Specification Sections:
1. 2 kg samples sealed in airtight containers, of each proposed fill and backfill soil
material from on-site or borrow sources
2. 300 mm long of each type of plastic warning tape
3. 300 x 300 mm samples of drainage fabric
G. Detailed design of temporary side slopes and side support system (if any) for
approval.
1.6 DEFINITIONS
A. Borrow soil: Satisfactory soil imported from off-site for use as fill or backfill.
D. Rock Fill: Material composed of hard, sound, durable rock with only a small amount
of fine particles used for filling or back filling
E. Sub-base Course: Course placed between the subgrade and base course for hot-mix
asphalt pavement, or course placed between the subgrade and a cement concrete
pavement or a cement concrete or hot-mix asphalt walk.
F. Retain definitions that remain after this Section has been edited. Revise to suit office
or local earthwork practices.
G. Base Course: Course placed between the sub-base course and hot-mix asphalt
paving.
H. Bedding Course: Course placed over the excavated subgrade in a trench before
laying pipe.
I. Revise heading in first paragraph below to read "Capillary Water Barrier" or a similar
title if required.
J. Drainage Course: Course supporting the slab-on-grade that also minimizes upward
capillary flow of pore water.
B. A geotechnical report has been prepared for this project and is available. The
opinions expressed in this report, the design and drawings are those of the
geotechnical engineer and represent interpretations of the subsoil conditions, tests,
and results of analyses conducted by the geotechnical engineer.
C. The Contractor shall carry out his own site investigations and shall inform and satisfy
himself as to the character, quality and distribution of all material to be excavated,
filled, spoiled and borrowed. The Contractor shall be fully responsible for asserting
necessary information concerning permanent water-table, period of rainfall and all
matters affecting the excavation and foundation work.
D. The contractor is responsible to verify the required different levels before starting
construction works.
E. Before starting any construction works compacting the top surface is required to
assure the quality of compaction.
F. Topographic Survey: Do not assume accuracy of the existing benchmark, and run a
closing survey of the existing project area and take cross-sectional elevations and
levels of the works on the Site and submit the result to the Engineer for approval, as
quantities of excavation, earthwork etc., shall be measured from these levels as
agreed and signed by the Engineer.
A. Blasting and use of explosives is prohibited. Do not bring explosives onto Site or use
in work.
A. The methods of excavation which the Contractor desires to use shall be at the sole
discretion of the Contractor.
B. The Contractor shall perform all excavation and backfilling as required for all works
under this Contract. Excavations shall be carried out in all materials, by whatever
means necessary and shall be performed accurately to the lines, levels and grades
shown on Drawings.
C. Except where indicated on the Drawings to remain undisturbed, the Contractor shall
remove all unaccepted topsoil, plants, roots, vegetation, rubbish, rock, etc., from
areas lying within limits of structures and from area to receive fill, embankment,
surfacing, road construction, concrete or other constructions.
E. In the event of a fall occurring in any excavation the Contractor shall carry out at his
own expense and to the satisfaction of the Engineer any re-excavation reinstatement
or repairs which may become necessary as the result of such fall. Any voids caused
by a fall shall be filled and consolidated as directed by the Engineer.
F. Protection of Persons and Properties: The Contractor shall erect temporary fencing
or barricade open excavations occurring as part of this work and post with warning
lamps and take all necessary steps to prevent any entry of public to the vicinity of
open excavation. He shall protect structures and utilities from damage caused by
settlement, lateral movement, undermining, washout and other hazards created by
earthwork operations.
G. The Contractor shall restore and repair any damage or defects caused to adjacent
structures, utilities or properties without responsibilities or extra charge to the
Employer.
PART 2 PRODUCTS
A. General: Provide borrow soil materials when sufficient satisfactory soil materials are
not available from excavations.
B. Topsoil: Natural and cultivated surface-soil layer containing organic matter and sand,
silt and clay particles, friable, pervious, and black or darker shade of brown, gray or
red than underlying subsoil, reasonably free of subsoil, clay lumps, gravel, and other
objects more than (50mm) in diameter, and free of subsoil and weeds, roots, toxic
materials, or other non-soil materials.
D. Structural fill shall be used underneath the structures and under slab on grade.
E. The source of the Engineering fill shall be provided by the Contractor and approved
by the Engineer. The Contractor shall provide samples at specified intervals to
monitor the material, and to the Engineer satisfaction.
F. Engineering fill shall be used underneath the structures, roads, shoulders and paved
areas and under slab on grade as specified in the geotechnical report.
Table 1
Table 2
Selected Fill
1. For depth from 3.0 m to 10.0 m (under buildings area) with max. Fines
percentage 20% and min. compaction percentage 85% (as stated in table 3).
2. For depth from 2.0 m to 10.0 m (under roads and parking area) with max. Fines
percentage 25% and min. compaction percentage 85%.
3. Landscape area and non-loaded area (non-structural fill) with max. Fines
percentage 25%, min. compaction percentage 85% and the maximum
thickness for each layer is 700 mm.
I. Maximum dry density and optimum moisture content shall be determined based on
Modified Proctor Test according to ASTM D 1557.
J. Backfilling material uses under buildings specifications and criteria are stated in the
following table:
Table 3
Table 4
L. Backfilling material uses under roads and parking areas specifications and criteria are
stated in the following table:
M. Bedding for Underground Utility Installation: Bedding shall be granular, well graded,
with all material passing 12.5 mm (1/2 inch) mesh screen and at least 90 percent
retained on 75 µm (No. 200) sieve as determined in accordance with ASTM D 422.
N. Trench Backfill (Within the Pipe Zone): Trench backfill shall contain no rocks or
stones larger than 25 mm in the greatest dimension and shall be free of vegetation,
trash, chunks of highly plastic clay, or other unsatisfactory- material. Trench backfill
placed under roadways or structures shall meet the requirements of engineering fill.
A. Acid- and alkali-resistant polyethylene film warning tape for marking and identifying
underground utilities 150 mm wide and 4 mils thick, continuously inscribed with a
description of the utility; colored as follows:
A. Water used for soil compaction shall be clean and free from unusual proportions of
dissolved salt, organic matters and industrial contamination oils, acids or other
deleterious matter.
B. Water shall not contain chemical salts including sulfates (SO3) and chlorides (Cl) in a
percentage that shall increase the overall salts percentage for filling materials more
than 0.35%.
C. For the water used in compaction process, water sample from wells and/or any
source shall be tested to satisfy the previous limits.
2.4 EQUIPMENT
A. Use types of equipment that are most suitable for the work and of numbers, sizes
and capacities that can perform earthwork as specified within the time schedule.
Equipment for earthwork shall be operated in strict accordance to manufacturer's
instructions and recommendations and shall be always maintained by the Contractor
in such condition that they shall deliver manufacturer's rated capacities.
PART 3 EXECUTION
A. Should the Contractor through negligence or other fault excavate or fill beyond the
designated lines, he shall replace/remove such excavation/fill in an approved manner
and condition at his own expense with satisfactory soil materials and thoroughly
compact to a density equal to adjacent original ground.
B. Do not neglect to check for underground services, which may not initially appear to
be of interest. Protect utilities, structures, improvements, pavement from damage
caused by settlement due to lateral movement created by earthwork operations.
B. Survey points, benchmarks, boundary stones and the like shall be removed only with
the engineer’s written consent.
C. Removed boundary stones and marking shall be stored according to the engineer
instructions.
E. For all fill and cut over 1 m in height, sturdy stakes shall be placed at any changes of
direction of the ground but in all cases at intervals not greater than 30 m as directed
by the engineer.
F. Permanent slope (if any) to be kept in the sand it shall be stabilized by one of the
following means:
G. The quantity, type and capacity of the equipment provided, the work method
envisaged transportation and distribution of the excavated materials, location of
stock-piles, main storage areas as well as the approximate number of laborers, etc.
and the working schedule and any amendment to it during the construction period
shall require the engineer’s period approved.
L. The Contractor shall make his own estimate of the kind and extent of the various
materials and presence or absence of water which shall be encountered in the
excavation.
M. The final 150 mm depth of all excavations shall be taken out manually or otherwise if
accepted by the Engineer and the bottom levelled and rammed immediately prior to
placing structures.
O. Stockpile soil materials suitable for backfill at sufficient distance away from edge of
excavation and neatly pile in stock piles in a manner that shall not overload or cause
collapse of excavation sides. All unsuitable and surplus excavated materials shall be
immediately removed from site, loaded and transported to dumps approved by local
authorities.
P. Extend excavations a sufficient distance from structures for placing and removing
concrete formwork, for installing services and other construction, for inspection.
R. No back-throwing whatever shall be allowed and all materials shall be brought to the
surface and formed in heaps clear of excavation.
T. Over Excavation: If somewhere and for any reason excavations are executed beyond
the established lines and without the engineer’s previous approval, the Contractor
shall backfill with lean concrete or other approved materials, the volume
corresponding to the over excavation.
W. The excavation shall at all times be well drained, kept free from storm water,
percolating water or subsoil water.
X. The Contractor shall make good at his own expense any damage that may result from
his failure to keep the excavation free from water.
3.2 EXCAVATION FOR STRUCTURES
A. Excavation Limits for Structures: Banks shall be either shored or sloped at a safe
angle according to conditions and to the approval of the Engineer. If necessary
extend a reasonable sufficient distance from footing and foundations to permit
placing and removal of concrete form work, shoring, installation of services and other
constructions, for performing all works in the excavation and for inspection. No
compensation shall be paid to the Contractor in respect to excavation or backfilling of
extended distances.
B. If any part of an excavated area is in error or excavated wider than required, the
excess excavated distance shall be backfilled as directed by the Engineer and
compacted at the Contractor's charge.
A. When excavation has reached required subgrade elevations, the Engineer shall
inspect soil materials at these elevations for suitability as a foundation level for the
related construction, and he may instruct the Contractor to test the bearing capacity
of the soil at this level. Should the bottoms of excavation be found to be unsuitable
as bearing surfaces as a result of such tests, the Engineer may decide to continue
excavation until suitable bearing materials are encountered and replace with
compacted backfill. Additional excavation and replacement material shall be paid for,
according to Contract.
B. Excavated materials shall not be piled up along sides of excavations in a manner that
will overload or cause collapse of excavation sides.
C. Sub-soil from the excavation shall be selected for suitability for backfilling and
compaction, shall be free from any organic materials and shall not have big lumps. It
shall be placed directly in its final position or stacked on site as directed by the
Engineer in the vicinity of the work and those unsuitable for fill shall be removed
from site to a tip provided by the Contractor. All other filling materials shall be
imported.
D. Cleaning, grubling and removal of trash and debris from excavation shall be done
before backfilling works.
F. Compaction areas shall be kept separate and no layer shall be covered by another
until the proper density is obtained.
I. The soil used in backfilling shall be mixed with sufficient water to provide a moisture
content within a range of 2% from the optimum value. The mixing process shall be
completed out of backfill area then soil shall be spread in loose lifts and compacted
at designated locations. The moisture content shall be uniform throughout the
compacted layer. If the field quality testing as specified in Clause 3.9 revealed
moisture content out of the previously specified range, the soil shall be removed,
remixed and compacted again.
J. The Engineer, at his own discretion, may allow greater lift thickness not exceeding
350 mm thick if proper density and uniformity is obtained. Effective spreading
equipment shall be used on each lift to obtain uniform thickness prior to compacting.
As the compaction of each layer progresses, continuous levelling and manipulating
shall be required to assure uniform density. Water shall be added in order to obtain
the correct water content and the required density on stocked soil outside the
excavation. Construction equipment shall be routed uniformly over the entire
surface both in width and longitudinal extent of each layer before the next lift is
started. At the start of the work a field test shall be performed in the Site over an
adequate area not less than 100 m2 to determine the allowable thickness of layers
K. Pipes and reinforced concrete foundation members such as tie-beams laid on natural
ground shall be protected with a minimum of 1000 mm of tamped fill over the top
surface or according to Drawings before heavy equipment is allowed to pass over.
L. Backfill excavations shall start as promptly as work permits, but not until completion
of the following:
M. Pipes and reinforced concrete foundation members such as tie beams laid on natural
ground shall be protected with a minimum of 1000 mm of tamped fill over the top
surface or according to Drawings before heavy equipment are allowed to pass over.
R. After installation of pipes and cables according to specifications and all related tests
are performed and approved by Engineer.
A. Unless otherwise indicated on Drawings, the subgrade under footings and tie-beams
shall be prepared in the following sequence:
1. Excavate under footing and tie-beams down to the required depth from
existing ground surface.
2. Clean bottom of excavation from the loose surface soil skin and compact the
soil using suitable compaction equipment.
3.5 BACKFILLING AROUND FOUNDATIONS
A. Use selected fill materials as specified in Clause 2.1 and compact mechanically or by
manual tamping to 90% of maximum dry density according to ASTM D 1556 at
optimum moisture content during excavation.
A. Allow testing agency to inspect and test each subgrade and each fill layer.
B. Compaction and field density tests of in-place soil or the fill shall be made at each
location directed by the Engineer at the rate of one (1) test every 250 m2 for each
compacted layer according to ASTM D1556.
C. One plate loading test/1000 m2, with minimum of two tests for each plot, shall be
carried out at foundation level of natural granular soil or the top of the replacement
layer (if existing), or as directed by the Engineer.
In case of the existence of replacement soil with thickness equal to or bigger than
1.50 m, then the same number of tests shall be carried out at the middle of the layer
The test shall be carried out dry and soaked to check the soil collapsibility as per the
Egyptian code and shall satisfy the following:
1. The steel plate diameter at least 450 mm.
2. The stress of the test should be not less than three times the net allowable
bearing capacity at the foundation level.
3. The submergence is to occur at stress equals the net allowable bearing
capacity at the foundation level.
4. The value of deformation modulus, Es should be not less than 500 Kg/cm2
D. Field density tests shall be performed in accordance with AASHTO T-191 (sand cone
method). The Contractor shall perform the following tests at locations as directed by
the Engineer:
1. Laboratory test for Maximum Dry Density (MDD), Optimum moisture content,
for each layer.
2. Field density and California Bearing Ratio (CBR), for each layer as required by
the Engineer.
3. The areas shall be rejected if the resulting test results do not satisfy specified
requirements.
4. The Contractor shall be responsible for making good all settlement of filling
that may occur at/to the end of the Defect Liability Period.
A. Unless otherwise specified, all and any kind of works, materials, services, safety
measures, etc. as well as, and if so requested by the Engineer, all tests and samples
required for the completion of the work shall be for the responsibility of the
Contractor. The auxiliary works comprises, but not limited to the following:
A. The tolerance limits for the permanent finished earthworks will be as follows:
A. The top surface area shall be of dense and level without any protruding rock
fragments in excess of 50 mm, recesses of soft spots to the satisfaction of the
engineer.
A. Remove, only by night, surplus satisfactory soil and waste material including
unsatisfactory soil, trash, debris, and legally dispose of it off to the public disposal
areas.
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. AGGREGATE BASE COURSE
CAIRO - EGYPT 321123 – 2874 0
SECTION 321123
Page
PART 1 GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Reference Standard 2
1.4 Submittals 3
1.5 Quality Control 3
1.6 Project Conditions 4
PART 2 PRODUCTS 4
2.1 Materials 4
2.2 Equipment 5
2.3 Operation 7
PART 3 EXECUTION 7
3.1 Preparation Of Subgrade 7
3.2 Application Of Base Course 8
3.3 Protection And Maintenance 10
PART 1 GENERAL
1.2 SUMMARY
A. This section covers the work of a crushed aggregate base layer (course) as required
by the Contract.
1. The base course shall consist of placing and compacting crushed aggregates
on a prepared subgrade in accordance with the technical specifications and in
conformity with the lines, grades, thickness and typical cross sections shown
on Drawings.
2. Extent of base layer (course) work is shown on Drawings.
B. Related Sections
A. Works shall be performed in strict accordance with the stipulations of the Egyptian
standard specifications (ES), the specifications of the American Association of State
Highway and Transportation Officials (AASHTO),the American Society for Testing and
Materials (ASTM), or other equivalent standards and sound practice..
Sampling of Aggregate T2 D 75
B. In the event of conflict between various codes and standards, the most stringent
conditions shall apply.
1.4 SUBMITTALS
C. Testing: Materials and installed work may require testing or retesting at any time
during the progress of the works. Tests, including retesting of rejected materials or
installed work, shall be done at the Contractor's expense.
D. All sampling and testing shall be performed by site testing laboratory or an approved
independent laboratory according to “Quality Control”.
E. The following tests should be carried out unless otherwise directed by the Engineer
and at frequencies laid down by the Engineer.
F. Minimum test requirement for aggregate base course: One sample every 1,000 m3
or part thereof as directed by the engineer shall be tested for grading plasticity
index, sand equivalent, maximum dry density, C.B.R. and loss by abrasion. Three in-
situ density tests shall be made per unit (900m2) of aggregate base course laid or as
directed by the engineer.
A. Traffic Control: Maintain access for vehicular and pedestrian traffic as required for
other construction activities.
PART 2 PRODUCTS
2.1 MATERIALS
A. General: Use locally available materials and gradations which exhibit a satisfactory
record of previous installations and which shall after addition of water and
compaction form a uniform and homogeneous section conforming with this
specification.
B. Borrow pits and quarries shall be cleared and grubbed in accordance with the
requirements and approved before crushing operations started.
C. Base Course Granular: Base course aggregate shall consist of well graded coarse,
fine aggregates and filler from clean crushed rock or crushed aggregates stone.
TABLE 1
GRADING FOR BASE COURSE AGGREGATE
(PERCENTAGE BY WEIGHT)
AASHTO T 88 - 57
Percentage Passing
by Weight (%)
F. The fraction passing the No. 200 sieve shall be not more than one half the fraction
passing the No. 40 sieve.
G. The fraction passing the No. 40 sieve shall have a liquid limit not exceeding 25 and a
plasticity index not exceeding 6.
H. The mixture shall have a soaked California Bearing Ratio CBR of not less than 80%
(with zero swelling).
2.2 EQUIPMENT
A. The Contractor shall use types of earth moving compaction equipment that are most
suitable for the work and of numbers, sizes and capacities that can perform the work
of the base course as determined in the time schedule and they shall include:
B. Tamping Rollers: A tamping roller unit shall consist of two watertight metal drums
mounted in frames in such manner as to be fully oscillating, together with a tractor
having sufficient weight and power under actual working conditions to pull the roller
drums at a minimum speed of 5 km/hour.
C. The drums shall be not less than 1.00 m in diameter and not less than 1.00 m in
length, measured at the drum's surface and shall be studded with tamping feet
projecting not less than 18 cm from the face of the drums. The distance between
circumferential rows of tamper feet shall be such that the diagonal distance from
any foot to the nearest foot in each adjacent row shall be not more than 30 cm,
measured center-to-center of feet at the surface of the drums. The cross sectional
area of the face of each tamper foot, measured perpendicular to the axis of the stud,
shall be not less than 30 cm2 not more than 55 cm2.
D. The weight of the tamping-roller unit shall be such as to exert a minimum pressure
of 18 kg/ cm2 on the ground area in contact with the tamping feet and the roller
shall be so designed that the weight may be increased to exert a pressure up to 36
kg/ cm2 on the ground area in contact with the tamping feet. The ground pressure
shall be determined by dividing the total weight of the roller unit, not including the
weight of the tractor, by the total cross sectional area of the tamping feet in one row
of tamping feet parallel to the axis of the roller.
F. Maximum speed of these rollers under working conditions shall not exceed 5
km/hour.
I. The rolling width of the unit shall be not less than 1.50 m exclusive of the power
unit. The roller shall be so constructed that the contact pressure is adjustable
between 3 and 8 kg/cm2, and uniformly distributed on all of the tires; the tyres shall
be inflated to maintain the air pressure in the several tires within a total tolerance of
1 kg/cm2. The roller shall be so constructed that the total weight of the roller can be
varied to produce an operating weight of between 500 and 2000 kg per tyre, the
actual operating weight of the rollers shall be as ordered by the Engineer.
K. Water Sprayer: Shall be truck mounted, equipped with a pump, with a separate
power unit including a spray bar.
L. The design of the spraying equipment shall be such as water shall be applied and
added to soils at uniform and controlled rated to provide the optimum, moisture
content.
2.3 OPERATION
PART 3 EXECUTION
A. The work shall be performed after the earthwork and sub-grade have been
substantially completed and tested.
B. Immediately before placing base course, subgrade shall be rolled with pneumatic
tyred roller of sufficient weight or heavy smooth wheel roller, to satisfy the
adequate levels shown on Drawings and to detect soft spots.
C. For vehicle areas compact with a roller weighing not less than 8 to 10 tons. For
pedestrian areas compact with a roller weighing not less than 2.5 tons.
D. After the subgrade has been constructed, prepared and substantially completed, and
if after compaction any soft spots are found the full width shall be conditioned by
removing any soft or other unstable material that was not compacted properly or
serve the intended purpose. The resulting areas and all other low sections, holes, or
depressions shall be brought to grade with suitable selected material.
E. Compaction soil test shall be made to determine the maximum dry density and
optimum moisture content of soil.
A. Contractor shall make the survey required for the reference grade, he shall erect a
reference straight line parallel to the centerline of the road, and operate the
compacting equipment to conform the straight line.
B. Elevation control point stakes for the crushed aggregates course shall be set at
maximum spacing of 50 m.
C. Sufficient uniform material mixture shall be spread on the road surface by a motor
grader and well mixed with water with the specified equipment to reach the
maximum density after compaction and so that the surface of the compaction is just
above the specified grade.
D. Placing: The wet granular base material shall be spread in layers on the prepared
subgrade and compacted to grade and cross section shown on the Drawings. When
more than one layer is required, each layer shall be shaped and compacted before
the succeeding layer is placed.
E. The placing of material shall begin at the point designated by the Engineer. Placing
shall be from spreader boxes or from vehicles especially equipped to distribute the
material in a uniform layer of windrow on the existing surface for immediate
spreading by a motor grader.
F. The layer or windrow shall be of such size that when spread and compacted, making
allowance for any blending material that is to be added on the road, the layer shall
have the required thickness of 150 mm after compaction.
G. Slope base course to the required crown elevations and cross slope grade.
H. When hauling is done over previously placed material, hauling equipment shall be
routed as uniformly as possible over the entire area of previously constructed layers.
I. Adding Blending Material: When additional fine aggregate or filler is required and it
is to be blended with the material on the road, the blending material shall be
uniformly placed with spreader boxes or other approved devices.
J. Mixing and Spreading: After layer of base course material has been placed and
blending material added when required, it shall be thoroughly mixed to its full depth
by means of power graders, travelling mixers, or other mixing equipment.
K. During the mixing, water shall be added in the amount necessary to provide the
optimum moisture content for compacting as specified in Item 3.2.M. When
uniformly mixed, the mixture shall be graded smoothly to a uniform thickness, to the
cross section shown on the Drawings.
M. Compaction: Immediately following the spreading and water addition compact with
a pneumatic-tire roller and for the final grading and smoothing, the layer shall be
N. Rolling shall progress gradually from the sides to the center parallel with the
centerline of the road, and shall continue until the entire surface has been rolled.
P. The amount of rolling and tamping as required above is estimated as the minimum
necessary for adequate compaction. During the progress of the work, the Engineer
may make density tests in accordance with AASHTO T-147, modified to include only
materials passing a 19 mm sieve, and if the density is less than 100 percent of the
maximum density as determined by AASHTO T 180 Method C, the Contractor shall
perform additional rolling tamping as may be necessary to obtain that density.
Other types of field density tests may be used for control purposes after density
value corresponding to those obtained by AASHTO T 147 have been established.
Q. The Engineer may permit compaction with types of equipment other than those
specified above, provided he determines that use of the alternative equipment will
consistently produce densities of not less than 100 percent according to the
modified AASHTO Designation T180.
R. California Bearing Ratio (CBR) shall not be less than 80%, (with zero swelling)
according to AASHTO Designation T 193.
S. Thickness Requirements: The thickness of the completed base shall not vary more
than 20.0 mm from the thickness shown on the Drawings for roads and parking
areas.
T. Immediately after final compaction of the base, the thickness shall be measured at
one or more points in each 150 m length of base. Measurements shall be made by
means of test holes or other approved methods. The points for measurement shall
be selected by the Engineer at random locations within each 150 m section in such a
manner as to avoid any regular pattern. Various points on the cross section shall be
covered. Whenever a measurement indicates a variation from the thickness shown
on the Drawings of more than the allowable tolerance, additional measurement shall
be taken at intervals of approximately 50 m length. Any area not within the
allowable tolerance shall be corrected by removal or adding base course material as
necessary and shaping and compacting as specified.
U. The cutting of test holes and refilling with materials properly compacted shall be
done by the Contractor under the Engineer's supervision.
V. The levelling of the finished course shall be performed by the Contractor in a grid as
indicated by the Engineer. The Contractor shall submit all levels in due time to the
X. When tested by a crown template, conforming to the typical cross section shown on
the Drawings and a 3 m straight edge applied at right angles and parallel,
respectively, to the centerline of the road, the variation of the surface from each
testing edge between any two contacts with the surface shall at no point exceed the
requirements of Sub Clause 3.2.5.
A. Protection: Work on the base course shall not be carried out when the subgrade is
too wet.
B. Hauling equipment may be routed over completed portions of the base course,
provided no damage results and provided that such equipment is routed over the
full width of the base course to avoid rutting or uneven compaction.
C. The Engineer shall have full and specific authority to stop all hauling over completed
or partially completed base course when, in his opinion, such hauling is causing
damage.
D. Any damage resulting to the base course from routing equipment over the base
course shall be repaired by the Contractor at his own expense.
E. Maintenance: Following the completion of the base course the Contractor shall
perform all maintenance work necessary to keep the base course in a condition
satisfactory for priming. The base course shall be properly drained at all times.
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. UNIT PAVING
CAIRO - EGYPT 321400 - 2874 0
SECTION 321400
UNIT PAVING
Page
PART 1 GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Submittals 2
1.4 Quality Assurance 2
1.5 Delivery, Storage, And Handling 3
PART 2 PRODUCTS 3
2.1 Concrete Pavers 3
2.2 Accessories 4
2.3 Aggregate Setting-Bed Materials 4
2.4 Mortar Setting-Bed Materials 4
2.5 Mortar Mixes 5
PART 3 EXECUTION 5
3.1 Examination 5
3.2 Preparation 5
3.3 Installation, General 6
3.4 Ungrouted Mortarless Concrete Paver Applications 6
3.5 Mortar Setting-Bed Applications 7
3.6 Repair, Pointing, Cleaning, And Protection 8
PART 1 GENERAL
A. Drawings and general provisions of the Contract, including General and Supplemen-
tary Conditions and Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
1.3 SUBMITTALS
1. Full-size units of each type of unit paver indicated. Assemble not less than five
Samples of each type of unit on suitable backing.
2. Joint materials.
A. Source Limitations: Obtain each type of unit paver, joint material, and setting mate-
rial from one source with resources to provide materials and products of consistent
quality in appearance and physical properties.
A. Store pavers on elevated platforms in a dry location. If units are not stored in an en-
closed location, cover tops and sides of stacks with waterproof sheeting, securely
tied.
B. Store cementitious materials on elevated platforms, under cover, and in a dry loca-
tion. Do not use cementitious materials that have become damp.
C. Store aggregates where grading and other required characteristics can be maintained
and contamination avoided.
PART 2 PRODUCTS
A. Concrete Pavers: Solid interlocking paving units complying with ES 269, made from
normal-weight aggregates.
E. Compressive Strength:
2.2 ACCESSORIES
A. Precast Concrete Curbs: Made from normal-weight with a compressive strength not
less than 34 MPa and water absorption not more than 5 percent, in shapes and sizes
indicated.
B. Compressible Foam Filler: Preformed strips complying with ASTM D 1056, Grade 2A1.
C. Sand for Leveling Course: Shall be fine, sharp, clean masonry sand complying with
E.S. No. 1108 passing Sieve No. 16 and no more than 10% shall pass Sieve No. 200
and containing not more than 3% silt plus clay by weight.
D. Sand for Joints: ASTM C 144 except use aggregate graded with 100 percent passing
the No. 8 sieve and 95 percent, the No. 16 sieve.
B. Hydrated Lime: Do not add lime to the mix. Use of approved liquid-type mortar ad-
mixtures that replaces performance of lime is permitted.
E. Water: Potable.
A. General: Comply with referenced standards and with manufacturers' written instruc-
tions for mix proportions, mixing equipment, mixer speeds, mixing containers, mixing
times, and other procedures needed to produce setting-bed and joint materials of
uniform quality and with optimum performance characteristics. Discard mortars if it
have reached its initial set before being used.
C. Mortar for pointing shall be composed of 400 kg cement to 1 m3 sand. Combine and
thoroughly mix cementitious materials, water and fine aggregates in a mechanical
batch mixer, comply with standards as applicable, for mixing time and water content
unless otherwise indicated
D. Cement-Paste Bond Coat: Mix bond coat to a consistency similar to that of thick
cream and consisting of either neat cement and water or cement, sand, and water.
PART 3 EXECUTION
3.1 EXAMINATION
A. Examine areas indicated to receive paving, with Installer present, for compliance
with requirements for installation tolerances and other conditions affecting perfor-
mance.
1. Proceed with installation only after unsatisfactory conditions have been cor-
rected.
2. Where pavers are to be installed over waterproofing, examine waterproofing
installation, with waterproofing Installer present, for protection from paving
operations. Examine areas where waterproofing system is turned up or
flashed against vertical surfaces and horizontal waterproofing. Proceed with
installation only after protection is in place.
3.2 PREPARATION
A. Remove substances from substrates that could impair mortar bond, including curing
and sealing compounds, form oil, and laitance.
B. Clean concrete substrates to remove dirt, dust, debris, and loose particles.
A. Do not use unit pavers with chips, cracks, voids, discolorations, and other defects
that might be visible or cause staining in finished work.
B. Mix pavers from several pallets or cubes, as they are placed, to produce uniform
blend of colors and textures.
C. Cut unit pavers with motor-driven masonry saw or block splitter equipment to pro-
vide clean, sharp, unchipped edges. Cut units to provide pattern indicated and to fit
adjoining work neatly. Use full units without cutting where possible. Hammer cut-
ting is not acceptable.
E. Pavers over Waterproofing: Exercise care in placing pavers and setting materials
over waterproofing so protection materials are not displaced and waterproofing is
not punctured or otherwise damaged. Carefully replace protection materials that
become displaced and arrange for repair of damaged waterproofing before covering
with paving.
F. Expansion and Control Joints: Provide for sealant-filled joints at locations and of
widths indicated on approved shop drawings. Provide joint filler as backing for seal-
ant-filled joints where indicated. Install joint filler before setting pavers. Sealant ma-
terials and installation are specified in Division 7 Section "Joint Sealants."
G. Expansion and Control Joints: Provide joint filler at locations and of widths indicated.
Install joint filler before setting pavers. Make top of joint filler flush with top of pav-
ers.
H. Provide steps made of pavers as indicated. Install paver steps before installing adja-
cent pavers.
1. Where pavers set in mortar bed are indicated for steps constructed adjacent
to pavers set in aggregate setting bed, install steps and allow mortar to cure
before placing aggregate setting bed and remainder of pavers. Cut off mortar
bed at a steep angle so it will not interfere with aggregate setting bed.
B. Place aggregate subbase and base over compacted subgrade. Provide compacted
thickness indicated. Compact subbase and base to 100 percent of ASTM D 1557
maximum laboratory density and screed to depth required to allow setting of pavers.
D. Place aggregate subbase and base, compact to 100 percent of ASTM D 1557 maxi-
mum laboratory density, and screed to depth indicated.
E. Place drainage geotextile over compacted base course, overlapping ends and edges
at least 300 mm.
F. Place leveling course and screed to a thickness of 25 to 38 mm, unless otherwise in-
dicted, taking care that moisture content remains constant and density is loose and
constant until pavers are set and compacted.
G. Treat leveling base with soil sterilizer to prohibit growth of grass and weeds.
H. Set pavers with a minimum joint width of 1.5 mm and a maximum of 3.0 mm being
careful not to disturb leveling base. If pavers have spacer bars, then place pavers
hand tight against spacer bars. Use string lines to keep straight lines. Select units
from 4 or more cubes to blend color and texture variations. Fill gaps between units
that exceed 5.0 mm with pieces cut to fit from full-size unit pavers.
1. When installation is performed with mechanical equipment, use only unit pav-
ers with spacer bars on sides of each unit.
I. Spread dry sand and fill joints immediately after vibrating pavers into leveling course.
Vibrate pavers and add sand until joints are completely filled, then remove excess
sand. Leave a slight surplus of sand on the surface for joint filling.
J. Do not allow traffic on installed concrete pavers until sand has been vibrated into
joints.
A. Saturate concrete subbase with clean water several hours before placing setting bed.
Remove surface water about one hour before placing setting bed.
B. Apply cement-paste bond coat over surface of concrete subbase about 15 minutes
before placing setting bed. Limit area of bond coat to avoid its drying out before
placing setting bed. Do not exceed 1.5-mm thickness for bond coat.
C. Apply mortar bed over bond coat immediately after applying bond coat. Spread and
screed setting bed to uniform thickness at subgrade elevations required for accurate
setting of pavers to finished grades indicated.
D. Mix and place only that amount of mortar bed that can be covered with curbs before
initial set. Cut back, bevel edge, remove, and discard setting-bed material that has
reached initial set before placing curbs.
E. Place curbs before initial set of cement occurs. Immediately before placing curbs on
F. Tamp or beat curbs with a wooden block or rubber mallet to obtain full contact with
setting bed and to bring finished surfaces within indicated tolerances. Set each unit
in a single operation before initial set of mortar; do not return to areas already set
and disturb units for purposes of realigning finished surfaces or adjusting joints.
A. Remove and replace unit pavers that are loose, chipped, broken, stained, or other-
wise damaged or if units do not match adjoining units as intended. Provide new
units to match adjoining units and install in same manner as original units, with same
joint treatment to eliminate evidence of replacement.
B. Pointing: During tooling of joints, enlarge voids or holes and completely fill with
mortar. Point up joints at sealant joints to provide a neat, uniform appearance,
properly prepared for sealant application.
C. Cleaning: Remove excess from exposed paver surfaces; wash and scrub clean.
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. CONCRETE CURBS
CAIRO - EGYPT 321613 - 2874 0
SECTION 321613.26
CONCRETE CURB
Page
PART 1 - GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Submittals 2
1.4 Quality Assurance 2
1.5 Delivery, Storage And Handling 3
PART 2 - PRODUCTS 3
2.1 Materials, General 3
2.2 Precast Concrete Curbs 3
2.3 Mortar And Grout Mixtures 3
2.4 Mortar Mixing And Pointing 3
2.5 Cast-In-Place Concrete Curbs 3
2.6 Joints 4
PART 3 - EXECUTION 4
3.1 Examination 4
3.2 Preparation Of Ground Surface 4
3.3 Laying Precast Curbs 4
3.4 Cleaning 4
3.5 Tolerances 5
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
B. Related Sections:
1.2 SUMMARY
A. This section covers the contractor works as required for the followings:
1.3 SUBMITTALS
B. Representative samples of all materials to be used in the work in full size units of each
type.
C. Shop drawings showing patterns, colors and full range of variations expected
A. Reference Standards: Works shall be performed in strict accordance with the stipulations of
the Egyptian Standard Specifications (ES) last edition, the American Society of testing and
materials (ASTM) and the American Association of State Highway and Transportation Officials
(AASHTO).
1. E.S. No.
2. AASHTO No.
3. ASTM No.
PART 2 - PRODUCTS
B. Materials for mortar shall be ordinary Portland cement to ASTM C150 and aggregates
to ASTM C 144.
A. The curbs shall not present defects such as cracks, distortion or stripping with the di-
mensions, section size, length and shape shown on the drawings with fair and smooth
finishing.
B. Compressive strength of concrete after 28 days shall not be less than 210kg/cm2.
A. Provide natural color Portland cement in combination with sand and filler materials to
produce joints. Mortar and Grouting shall be 400 kg cement to 1 m3 sand.
1. For joints narrower than 6 mm use aggregate graded with 100% passing the No.
8 sieve and 95% the No. 16 sieve.
2. For pointing mortar use aggregate graded with 100% passing the No.16 sieve.
A. Combine and thoroughly mix the cementations materials, water and aggregates in a
mechanical batch mixer as applicable for mixing time and water content.
B. The thickness of the joint between two (2) units of curbs shall be fixed to 5 mm in no
case it shall exceed 10 mm. The joints shall be flat and smoothed with the trowel.
A. Forms: Forms shall be made to the required shape according to Drawings, of metal hav-
ing a thickness of not less than 4 mm and shall be furnished in sections of not less than
3.0 m in length.
2.6 JOINTS
A. Joints should be constructed with the dimensions and in the places shown in the details
drawings.
B. If the joints are made to be separate from the concrete pavement, or connected with
an elastic binder or wearing surfaces, a metallic mould could be put in the joint’s loca-
tion after the curb has been completely spread with a depth not less than 30mm
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine exposed sub-grades and sub-base surfaces for compliance with requirements
for dimensional, grading, and elevation tolerances.
B. Following, an appropriate sand base in thickness indicated shall be spread and com-
pacted to 95% relative density by tamping with plate vibrator and screed to depth re-
quired to allow setting of pavers units.
A. Curbs shall be bed in plain concrete Type C as per Division 3 Section “Cast-In-Place Con-
crete” hunched half way up back. Joint with mortar as specified herein before as the
work proceeds neatly flush pointed. Lay curbs to lines shown on Drawings with top sur-
face flush and level. Form curves with straight pieces with angling the joints.
C. The curbs should be constructed to be one piece with the concrete pavement, the con-
crete should be poured and compacted then shaped with a steel tool according to the
cross-section shown in the details drawings.
3.4 CLEANING
A. After grouting has sufficiently set or hardened, curb surface shall be cleaned and traces
of cement or dust accumulations and foreign matter shall be completely removed.
B. Repair or remove and replace curbs which may damage during paving works on the
contractor responsibilities.
A. The finished work shall be true to line grade and levels within 5mm and shall present a
smooth appearance free from kinks and distortions visible to the eye.
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. PAINTED ROADWAY MARKING
CAIRO - EGYPT 321723 - 2874 0
SECTION 321723
Page
PART 1 GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Submittals 2
1.4 Reference Standards 2
1.5 Quality Assurance 3
1.6 Delivery, Storage And Handling 3
PART 2 PRODUCTS 3
2.1 Paints 3
2.2 Glass Beads (Ballotini) 4
2.3 Paint Equipment 4
PART 3 EXECUTION 5
3.1 General 5
3.2 Application 5
3.3 Cleaning 5
PART 1 GENERAL
1.2 SUMMARY
A. This section covers the Roadway Marking Paint works as required by the contract
for:
1. Marking of the centerline, edge line& Lanes separators, Stop line, etc.
2. Parking bays.
3. Pedestrian Crossings.
4. Ground marking shapes (Traffic Arrows, Give way, etc.).
5. Chevrons at merging or diverging of roads.
C. Related Sections:
1.3 SUBMITTALS
B. Representative samples of all materials to be used in the work for each color,
texture
C. Shop drawings showing patterns, colors and full range of variations expected
E.S. No.
A. In the event of conflict between various codes and standards, the most stringent
conditions shall apply.
A. Tests: Use standard test with manufacturer to determine if painting materials will
obtain optimum adhesion with asphalt, and shall be nonstinging to asphalt paving
surface or materials constituting the paving. Schedule for sufficient time for testing
and analysis of results to prevent delaying the work.
B. Mock-up: Prior to proceed with the roadway marking work, construct mock-ups for
each form and pattern required to demonstrate aesthetic effects as well as qualities
of materials and execution. Paint mock-ups using material indicated for final unit of
work including same base construction special features as indicated.
A. Deliver pavement marking materials to project site in original package with seals
unbroken and bearing manufacturer's labels containing brand name, type of
materials and date of manufacture.
B. Containers shall be made of a material which does not contaminate the contents,
and shall protect the contents from contamination.
C. Store pavement marking materials in a clean, dry, protected location and within
temperature range required by manufacturer. Protect stored materials from direct
sunlight.
PART 2 PRODUCTS
2.1 PAINTS
1. Aggregate 40 parts
2. Ballotini 20 parts
3. Pigment and Extender 20 parts
4. Binder 20 parts
C. The grading of the various ingredients shall be such that the final product when in a
molten state can be sprayed on the road surface at approximately 1.5 mm thickness.
D. Alkyd-resin type, ready mixed complying with AASHTO M-248 Type N Factory mixed
quick drying and non-bleeding.
F. Latex, water-base emulsion, ready-mix. The minimum drying time of 2 hours shall
be allowed.
A. Where specifying reflective feature add glass beads (sphere) to the paint.
C. The ballotini sprayed on the surface of the line shall conform to the same limits of
color and roundness. Consumption shall be up to 6 kg per 10 liters of paint.
A. The mechanical marker shall be an approved mobile atomizing spray type marking
machine for the application of the required paint, either hand-propelled or machine-
propelled, capable of applying paint in single, double and dashed lines.
3.1 GENERAL
A. Allow paving to cure for 30 days before starting pavement marking paint.
3.2 APPLICATION
A. Do not apply pavement marking paint until layout, colors and placement have been
verified with Engineer.
B. Proceed with pavement marking only on dry, clean surfaces, entirely free from dirt,
mud, grease, oil, etc., and at a minimum ambient or surface temperature of 10 C
and not exceeding 35C for oil based materials.
C. Sweep broom, blow and clean surface to eliminate loose materials and dust.
D. Sand blasting or high pressure water shall be used to remove curing compound, or
old paint.
E. Apply paint with an approved mechanical pressure spray unit equipment to produce
uniform straight edges with the general alignment of the carriage way.
G. The finished lines shall be free from "raggednesses" on sides and ends.
I. In addition to the ballotini included in the mix, an additional quantity of glass beads
shall be sprayed on the wet spray plastic line at the time of application. The rate of
application shall be about 0.5 kg/m2. The upper surfaces of the lines shall be level,
uniform and free from streaks.
3.3 CLEANING
A. All marking paint shall be protected from damage until the paint is dry. Paint shall
be protected from all traffic, vehicle and pedestrian. All paints shall be maintained to
the Engineer's satisfaction.
END OF SECTION 32 17 23
THIS PAGE IS A RECORD OF ALL SPECIFICATION REVISIONS. NORMALLY, REVISED SHEETS ONLY ATTACHED
EACH TIME THE SPECIFICATION IS CHANGED ONLY THE NEW OR ENTIRE SPECIFICATION RE-ISSUED
REVISED PAGES ARE ISSUED. ENTIRE SPECIFICATION REVISED
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. WATER SUPPLY, IRRIGATION MAIN
CAIRO - EGYPT AND FIREFIGHTING NETWORKS 331000 - 2874 0
SECTION 331000
PAGE
PART 1 GENERAL 2
1.1 Related Documents 2
1.2 Description Of Work 2
1.3 Reference Standards 2
1.4 Submittals 5
1.5 Quality Control 7
1.6 Quality Assurance 8
1.7 Delivery, Handling And Storage 11
PART 2 PRODUCTS 14
2.1 Warning Tapes 14
2.2 Geo-Textile 15
2.3 Pipes, Fittings And Accessories 16
2.4 Valve Features, General 23
2.5 Irrigation Equipment And Accessories 40
PART 3 EXECUTION 45
3.1 General 45
3.2 Pipes 46
PART 1 GENERAL
A Drawings and general provisions of the Contract, including General and Supplemen-
tary Conditions and Division 01 Specification Sections, apply to this Section.
A This section covers water pressure pipes, valves as indicated on the drawings and
specified here in addition to all types of Potable water structure such as valve cham-
bers as required by the Contract. Extent of these structures is indicated on Drawings.
B This section covers fire pressure pipes, valves as indicated on the drawings and speci-
fied here in after in addition to all types of Fire water structure such as valve cham-
bers as required by the Contract. Extent of these structures is indicated on Drawings.
C This section covers Irrigation pressure pipes, valves as indicated on the drawings and
specified here in after in addition to all types of irrigation water equipment’s and
structure such as valve chambers as required by the Contract. Extent of these struc-
tures is indicated on Drawings.
A The work shall be performed in strict accordance with the stipulations of the British
Standard Specifications (BS), American Standards (ASTM) as noted herein below or
other equivalent approved Standards and Sound Practice.
D American Society for Testing and Materials & American Water Works Association
(ASTM & AWWA No.)
1.4 SUBMITTALS
A Submit the following in accordance with Conditions of the Contract and Division-1
Specification Sections:
1. Pipes
b. Original catalogue
c. Material Certificates of compliance.
d. Materials Sample.
e. Method statement of pipelines construction.
f. Shop drawings.
g. Record drawings.
h. Maintenance data.
i. Certificates of origin.
2. Valves
3. Valve Chambers
4. Certifications:
A Testing
A General
1. Codes and Standards. Reference to the standards of any technical society, or-
ganization, or association, or to codes of local authorities, shall mean the latest
standard, code, specification, or tentative standard adopted and published at
the date of taking tender, unless specifically stated otherwise.
2. In the absence of a specified referenced code or standard, the Contractor may
propose other recognized international codes and standards, and in such a
case the Contractor shall demonstrate to the satisfaction of the Engineer, suit-
ability and equivalence of the substitute codes and standards as well as pro-
vide proof of previous successful use.
3. Work specified by reference to the published standard or specification of a
government agency, technical association, trade association, professional soci-
ety or institute, testing agency, or other organization shall conform or surpass
the minimum standards of quality for materials and workmanship established
by the designated standard or specification.
4. Where the specific date or issue of the standard is not included with the refer-
ence to the standard, the latest edition, including all amendments published
and available on the first published date of the Invitation to Tender, shall ap-
ply.
5. Where two or more standards are specified to establish quality, the product
and workmanship shall conform to or surpass the requirements of both. In
case of conflict between referenced standards, the more stringent shall apply.
6. Where both a standard and a brand name are specified for a product in the
Contract Documents, the proprietary product named shall conform to or sur-
pass the requirements of the specified reference standard.
7. The listing of a trade name in the Contract Documents shall not be construed
as warranting that such product conforms to the respective reference stand-
ard.
8. Copies of applicable referenced standards have not been bound in this Con-
tract Document. Where copies of standards are needed by the Contractor for
superintendence and quality control of the work, Contractor shall obtain a
copy or copies directly from the publication source and maintain in an orderly
manner at the jobsite, available to the Contractor's personnel, subcontractors,
Employer, and Engineer.
9. Contractors shall clearly identify and submit for approval any requests to use
products conforming to printed standards or publications with a different pub-
lication date from that effective under the Contract. Clearly indicate the
changes in product or workmanship quality involved in the proposed change, if
any, and reasons for the request.
D Inspection:
1. All pipes, Valves, Irrigation equipment’s and fittings shall be subject to inspec-
tion at the place of manufacture, in accordance with the provisions of the ref-
erenced standards.
2. The Contractor shall give appropriate written notice to the Engineer not less
than 28 days before offsite inspection services are required, and shall provide
for the producer, manufacturer, or fabricator to furnish safe access and proper
facilities and to cooperate with inspecting personnel in the performance of
their duties.
E Tests:
1. All materials used in the manufacture of the pipes, fittings and specials shall be
tested in accordance with requirements as applicable.
F Test Costs:
G Plant Access:
1. During the manufacture of the pipe, valves, irrigation equipment’s and fittings,
the ENGINEER shall be given access to all areas where manufacturing and test-
ing is in process and shall be permitted to make all inspections necessary to
confirm compliance with the Specifications.
1. Upon request the CONTRACTOR shall submit affidavits of compliance from the
MANUFACTURER for the following:
a. Ductile Iron
b. HDPE
c. Valves
I Warranty:
A Vendor Documentation
1. Each pipe, fitting and special appurtenance shall be marked with permanent
identification which shall include but not necessarily limited to the following:
a. Nominal diameter
b. Name or trade mark of manufacturer
c. Serial number
d. Class of pipe, pressure rating in compliance with referenced standards
e. Date of manufacture
f. Type of service
g. Details on fittings such as angle of change and taper
h. Clearly marked on the inside and outside to indicate the top of the pipe
when laid.
i. Certificate from Manufacturer
j. Certificate from PE 100 + Association
k. Local agent name and address.
2. Each Valve shall furnish following vendor data as a minimum, with the bid:
B Delivery
1. The acceptability of the pipes and fittings on delivery to the Site will be based
on the results of tests carried out by one or more of the following:
2. The Engineer shall be permitted at all reasonable times to visit places of manu-
facture to witness tests.
3. The Engineer may require checking dimensional accuracy of pipes and fittings
at the place of manufacture, the cost of such verification shall be borne by the
Contractor.
2. During transport
a. Pipes and fittings shall be well secured and adequately supported along
their length
b. Bolsters and binding of approved type shall be used
c. Nesting of pipes (placing a smaller pipe inside a larger) may be permitted
for pipes of certain materials and size provided that methods state-
ments demonstrate that effective precautions will be taken to protect
all pipe surfaces and coatings from damage
d. No pipe shall overhang the end of a vehicle
e. Pipes and fittings of plastic materials shall be covered.
1) Approved hooks, of the type having a plate curved to fit the curva-
ture of the inside of the pipe, on ends of sections
2) Fabric slings not less than 250 mm wide
3) Other methods approved for the pipe used
c. Use of w ire rope, chains and fork lift trucks will not be permitted
d. For strings of pipe longer than the standard length precautions shall be
taken to avoid curvature and longitudinal stress in excess of allowable
limits
e. Pipes and fittings of plastic materials
1) Packing list.
2) General arrangement and catalogues.
3) Operation and maintenance manual as applicable.
4) Installation instructions
4. All pipes, valves, fittings and materials shall be stored in accordance with the
manufacturer’s recommendations and the following:
a. Pipes may be stored in the open on a flat level area and raised above the
ground on timber bearers so that the lowest point of any pipe or fitting
is not less than 150 mm above the ground
b. Timber bearers not less than 200 mm wide and 75 mm thick to be pro-
vide d at 4 m intervals maximum
c. If on pallets or crated, on the pallets or in their crates until required
d. If not on pallets or not crated, stacked one above the other as follows:
e. If spigot and socket, stacked so that successive pipe layers have sockets
protruding at opposite ends of the stack
f. With pipes of different sizes and thick ness stacked separately
g. With maximum height of stacked pipes not exceeding 2m, or that rec-
ommended by the supplier if less than 2 m.
h. Pipes and fittings of plastic materials shall be:
1) Under cover
2) Rubber ring gaskets shall
3) Stored in their original packing
4) Not be exposed to sunlight
5) Protected from exposure to greases and oils
6) Gasket lubricants shall be stored so as to prevent damage to the con-
Water Supply, Irrigation Main and Firefighting Networks Section 331000
Urbanium New Administrative Building (Prj. 2874) Page 13 of 72
tainer.
j. Pipes and fittings shall be protected in storage to the approval of the En-
gineer by means of an impermeable membrane which shall cover the
pipes and fittings and separate them from the ground on which they are
supported. The membrane shall be strong and durable in the prevailing
climate conditions.
1) Valves should be stored in a location that protects the valve from any
pollution or contamination.
2) The valves must be stored in upright position and in an almost closed
position to prevent long-term compression of the wedge rubber.
3) The valve must be kept out of sunlight to prevent oxidation of the
rubber and coating. Valves stored in cold storage must be protected
against freezing.
4) Gate valves with PE pipe connection have to be stored and handled
carefully to avoid damage of the pipe.
5. The following procedures shall be followed for dealing with damaged pipes
and fittings:
PART 2 PRODUCTS
A Service protection tapes shall be installed above all sewage pipelines and pressure
mains constructed or exposed under this contract excluding individual service con-
nections.
1. The tape shall be 150 mm wide and 250 micron thick and produced as a strong
composite laminate consisting of : -
2. 30 Micron polyester film top layer
3. 12 Micron detectable aluminum foil in between
4. 208 Micron bottom layer polyethylene.
5. The thickness of the tape (250 micron / 1000 gauge) shall be measured in ac-
cordance with BS 2782 : Part 6. Method 630 A.
6. The following properties shall be demonstrated by appropriate tests :-
C Chemical resistance:-
1. The tape shall be remaining legible and colour fast in all soil conditions at PH
2.5 to 11.0, inclusive. The tape shall not show any adverse effect when in con-
tact with the sulphates, chlorides and other minerals present in sub soil and
water, oil, 5% Acetic Acid, 5% NaOH and Alcohol mix, if any.
1. Text in Arabic and English indicating the protected services lying below the
tape shall be permanent ink bonded to resist prolonged chemical attack by
corrosive acids and alkalis with the message repeated at a maximum interval of
two meters. Tapes shall be colour coded as follows, with black text as indi-
cated. The sign and styles of the text shall be approved by the Engineer.
a. Water : Blue
b. CAUTION : Water Pressure Mains Below
c. Fire : Blue
d. CAUTION : Fire Water Pressure Mains Below
e. Municipality logo shall be printed in black between the spaces of re-
peated messages.
2.2 GEO-TEXTILE
A General
B Pressure Pipelines
1. Materials used for the manufacture of polyethylene pipe and fittings shall be
made from a PE 3408 high density polyethylene resin compound meeting cell
classification 345434C per ASTM D3350; and meeting Type lll, Class C, Category
5, Grade P34 per ASTM D1238.
2. High Density Polyethylene (HDPE) pipe shall comply with AWWA Specifications
C906 / or Pipes and fittings shall be made of high density polyethylene (HDPE)
and shall comply with the requirements of ISO 4427 PE 100. The material shall
be produced by a member of the PE 100 + Association.
3. The material used for the manufacturer of pipes and fittings shall be in accord-
ance with Table 1 and Table 2 of clause 4.4 of ISO 4427-1
1. The minimum required strength (MRS) of the material compound shall be 10
MPa at 200 C. The design stress shall be 8 MPa. Lifecycle durability of 80 years
is to be confirmed.
2. If rework compounds are required, only those generated in the Manufacturer’s
Water Supply, Irrigation Main and Firefighting Networks Section 331000
Urbanium New Administrative Building (Prj. 2874) Page 17 of 72
own plant from resin compounds of the same class and type from the same
raw material supplier shall be used.
3. Dimensions and workmanship shall be as specified by ASTM F714 and ASTM
D3035. HDPE fittings and transitions shall meet ASTM D3261. HDPE pipe shall
have a minimum density of 0.955 grams per cubic centimeter. All HDPE pipe
and fittings shall have a Hydrostatic Design Basis (HDB) of 1,600 psi.
4. HDPE pipe and accessories shall be meeting the requirements of Standard Di-
mension Ration (SDR) 17 (PE 100) as MINIMUM STRENGTH as MINIMUM
STRENGTH for Potable Water and Irrigation Network
5. The pipe Manufacturer must certify compliance with the above requirements.
C Fittings
1. The PE pipe industry has worked diligently to make PE piping systems as com-
prehensive as possible. As such, various fittings are produced which increase
the overall use of the PE piping systems. PE fittings may be injection molded,
fabricated or thermoformed.
2. The following will briefly describe the operations of each technique.
3. Injection Molded Fittings
4. Fabricated Fittings
a. Fully pressure-rated, full bore fabricated fittings are available from select
fittings fabricators. Fabricated fittings are constructed by joining sections
of pipe, machined blocks, or molded fittings together to produce the de-
sired configuration.
b. Components can be joined by butt or socket heat fusion, electro-fusion,
hot gas welding or extrusion welding techniques. It is not recommended
to use either hot gas or extrusion welding for pressure service fittings
since the resultant joint strength is significantly less than that of the
other heat fusion joining methods.
c. Fabricated fittings designed for full pressure service are joined by heat
fusion and must be designed with additional material in regions of sharp
geometrical changes, regions that are subject to high localized stress.
Water Supply, Irrigation Main and Firefighting Networks Section 331000
Urbanium New Administrative Building (Prj. 2874) Page 18 of 72
The common commercial practice is to increase wall thickness in high-
stress areas by fabricating fittings from heavier wall pipe sections. The
increased wall thickness may be added to the OD, which provides for a
full-flow ID; or it may be added to the ID, which slightly restricts ID flow.
This is similar to molded fittings that are molded with a larger OD, heav-
ier body wall thickness. If heavy-wall pipe sections are not used, the
conventional practice is to reduce the pressure rating of the fitting. The
lowest-pressure-rated component in a pipeline determines the operat-
ing pressure of the piping system. Various manufacturers address this
reduction process in different manners. Reinforced over-wraps are
sometimes used to increase the pressure rating of a fitting. Encasement
in concrete, with steel reinforcement or rebar, is also used for the same
purpose. Contact the fitting manufacturer for specific recommendations.
d. Very large diameter fittings require special handling during shipping, un-
loading, and installation. Precautions should be taken to prevent bend-
ing moments that could stress the fitting during these periods. Consult
the fittings manufacturer for specifics. These fittings are sometimes
wrapped with a reinforcement material, such as fiberglass, for protec-
tion.
5. Thermoformed Fittings
D JOINTING
1. PE pipe or fittings are joined to each other by heat fusion or with mechanical
fittings. PE pipe may be joined to other pipe materials by means of compres-
sion fittings, flanges, or other qualified types of manufactured transition fit-
tings. There are many types and styles of fittings available from which the user
may choose. Each offers its particular advantages and limitations for each join-
ing situation the user may encounter. Contact with the various manufacturers
is advisable for guidance in proper applications and styles available for joining
as described herein below:-
a. There are three types of conventional heat fusion joints currently used
in the industry; Butt, Saddle, and Socket Fusion. Additionally, electro fu-
sion (EF) joining is available with special EF couplings and saddle fittings.
b. The principle of heat fusion is to heat two surfaces to a designated tem-
perature, then fuse them together by application of a sufficient force.
This force causes the melted materials to flow and mix, thereby resulting
in fusion. When fused according to the pipe and/or fitting manufactur-
ers’ procedures, the joint area becomes as strong as, or stronger than,
the pipe itself in both tensile and pressure properties and properly fused
joints are absolutely leak proof. As soon as the joint cools to near ambi-
ent temperature, it is ready for handling. The following sections of this
chapter provide a general procedural guideline for each of these heat
fusion methods.
3. Butt Fusion
a. The most widely used method for joining individual lengths of PE pipe
and pipe to PE fittings is by heat fusion of the pipe butt ends. This tech-
nique produces a permanent, economical and flow-efficient connection.
Quality butt fusion joints are produced by using trained operators and
quality butt fusion machines in good condition.
4. Saddle/Conventional Fusion
5. Socket Fusion
6. Mechanical Connections:
a. There are many styles and varieties of “Bolt Type” couplings available to
join PE to PE or other types of pipe such as PVC, steel and cast iron in
sizes from 1¼” IPS and larger. As with the mechanical compression fit-
tings, these couplings work on the general principle of compressing an
elastomeric gasket around each pipe end to be joined, to form a seal.
b. The gasket, when compressed against the outside of the pipe by tighten-
ing the bolts, produces a pressure seal. These couplings may or may not
incorporate a grip ring, as illustrated, that provides pullout resistance
sufficient to exceed the yield strength of the PE pipe. When PE pipe is
pressurized, it expands a little and shortens slightly due to Poisson’s ef-
fect. In a run of PE pipe, the cumulative shortening may be enough to
cause separation of unrestrained mechanical joints that are in-line with
the PE pipe. This can be a particular concern where transitioning from PE
pipe to Ductile Iron pipe. Joint separation can be prevented by installing
external joint restraints (gripping devices or flex restraints; Additional
restraint mechanisms are available to supplement the pull resistance of
these types of fittings if needed.
c. The fitting manufacturer can help guide the user with that information.
Use of a stiffener is needed in this fitting style to support the pipe under
the area of the seal ring and any gripping devices incorporated for
pullout resistance.
8. Flanged Connections
1. All valves supplied shall be suitable for use with water temperatures up to 50o
C and in climatic and soil conditions encountered in the project area. The nom-
inal working pressure shall be 16 bar or as mentioned in the tender
2. The CONTRACTOR shall provide valves of an approved type for installation and
shall be suitable for potable water service. Prior to internal coating on the
valves, a certificate of non-toxicity of paint materials shall be submitted to
ENGINEER for approval. The certificate shall be signed by an internationally
recognized authority.
3. The valves shall have flanged connections with the flanges drilled in accord-
ance with the standards and ratings indicated in the relevant Data Sheets. All
bolts, nuts and washers shall be hot dipped galvanized or cadmium plated.
4. The valves shall be designed for pressure caused by the unbalanced closed po-
sition, and be suitable for the specified working and hydrostatic test pressures.
5. All valves shall close clockwise and be equipped with an open / closed position
indicator.
6. Valves shall be suitable for continuous operation as well as for intermittent
operation. All ferrous parts of the valves shall be coated, except for the fin-
ished or bearing surfaces. The type of the internal and external coating shall be
as specified on the respective data sheets for each type of valve. Valves,
strainers and other devices mounted in underground pipelines shall be in-
stalled in reinforced concrete chambers complete with all accessories and pro-
tection systems as per the project specifications and drawings. Valves, strain-
ers and other devices shall be adequately supported independently of the
pipes to which they connect to prevent the pipe having to bear the weight of
the valve.
7. The valves shall be supplied complete with all the required joint accessories,
approved gaskets, bolts, nuts and washers etc. for both flanges of each valve.
All valves shall have the name of the manufacturer, working pressure, diame-
ter and cast number on the body. Face to face dimensions for flange valves
Water Supply, Irrigation Main and Firefighting Networks Section 331000
Urbanium New Administrative Building (Prj. 2874) Page 23 of 72
shall be as per BS 5163.
8. Unless otherwise detail or specified here-in, gate and butterfly valves shall be
supplied complete with extension spindles and appurtenances such that the
square nut operation is within 500 mm of the top of the chamber cover slab.
Where required, special couplings shall be incorporated to absorb the weight
of the extension spindle at no extra cost.
9. The dimensions of stem cap of all valves and square nut operator in case of ex-
tension spindles or without extension spindle shall be in accordance with BS
5163. All valves shall be supplied with stem (spindle) cap made from ductile
iron. The spindle cap shall be fixed with spindle by a nut bolt passing through it
so that spindle cap is tied with spindle. The manufacturer shall fix spindle cap
to spindle by a nut bolt before dispatching (not acceptable as loose items) .
10. All valves to be supplied shall correspond to internationally accepted standards
as applicable in the relevant parts of this document. Any other equivalent na-
tional or international standard shall be considered subject to submission of
acceptable comparison statement. The CONTRACTOR shall attach to his offer
the English text of Standards as applicable.
11. The valves must be accompanied with a certificate guaranteeing their water
tightness and satisfactory operation for a period of not less than 10 years.
12. Contractors shall provide Material Certificates issued by the Manufacturers in
accordance with the requirements of EN 10204
13. Contractor shall ensure that all material in contact with potable water shall not
adversely affect the potable water quality requirement of Regulation & Super-
vision Bureau Regulation which refers to WHO. Furthermore international re-
quirements on non-toxicity certification and coating protection shall be met.
14. All gate valves shall be designed to provide 100 % water tight shut off at all
specified pressures and suitable for installation of electrical actuators when
required.
15. Hand wheels shall be providing for all valves when installed above ground,
when operation is within reach. Valve installed out of reach above ground shall
be provided with chain drive or remote control drive as the case may be.
16. All Valves Working Pressure: 16 bars unless specified otherwise and Test pres-
sure: 1.5 x Design pressure.
a. General
b. Features:
a) Wedge shaped with guides and designed with a special rubber profile
ensuring low closing torques
b) Stainless steel stem with rolled threads providing high strength
c) Full circle thrust collar provides fixation of the stem and low free running
torques
c. Construction Material
Description Material
Stem Stainless steel min. 13% Cr
Wiper ring NBR rubber
O-ring NBR rubber
Bearing Polyamide
Bonnet Ductile iron, GJS-500 (GGG-50)
Thrust collar Dezincification resistant brass CZ132
Manchette EPDM rubber
Bonnet bolt Stainless steel A2, sealed with hot melt
Bonnet gasket EPDM rubber
Wedge Dezincification resistant brass
Body Ductile iron, (GGG-50)
2. Service Connection Valve, Tensile socket joints
a. General
1) Resilient seated service connection valves are designed with built-in safety in
every detail. The wedge is vulcanized with drinking water approved EPDM
rubber compound.
2) Service connection valve with tensile socket ends for drinking water and
neutral liquids to max. 70° C
3) Designed according to EN 1074 part 1 & 2
4) The epoxy resin coating is electrostatically applied (inside and outside) with
a minimum thickness of 300.
b. Construction Material
1. General
2. Material
a. General.
1) Materials shall comply with the requirements of the Safe Drinking Water Act
and other local requirements. it is the contractor and supplier’s
responsibility to verify the current requirements of local regulations. And
international regulations when reference is made to ANSI, ASTM, AWWA, BS
or other standards, it shall be understood that the latest revision thereof
shall apply. All materials used in valves produced according. to this standard
shall conform to the requirements stipulated in the following sections.
2) Mechanical and chemical properties. The requirements of ANSI, ASTM,
AWWA, BS or other standards to which reference is made in this
specification shall govern the mechanical and chemical characteristics of the
valve components. Whenever valve components are to be made in
b. Specification
c. Detailed Specification
i. The end flange of a tapping valve that forms a joint with the tapping
sleeve shall conform to the dimensions of MSS SP-60 in sizes 3inch. (75-
mm) through 12inch. (300-mm) NPS. For larger sizes, flange dimensions
shall be as per the manufacturer recommendation.
ii. The connecting end of the tapping valve mating with the tapping machine
must be parallel and concentric with the opposite flange and concentric
with the waterway to provide proper alignment for the tapping
operation. The end flange of a tapping valve that forms a joint with the
tapping machine shall conform to the dimensions of MSS SP-113.
i) Yokes on OS&Y valves. On OS&Y valves, the yoke on bonnets may be integral
or of bolted-on construction. If the yoke is not an integral part of the bonnet,
it shall be made of ductile iron. The design shall be such that a hand cannot
be jammed between a yoke and the hand wheel.
2) Gate
3) Guides
4) Bolting
a) Stems, stem nuts, and copper-alloy gates shall be made from a copper alloy
as indicated in ANSI/AWWA C509 Table 3.
i. Valve stems shall be made from copper alloys that have a yield strength
i. NRS valves
NRS valves. NRS valves shall be designed so that the seal above the stem
collar can be replaced with the valve under pressure in the fully open
position.
OS&Y valves. Design of the valve shall be such that the stuffing box can be
packed when the valve is in the fully open position and under pressure.
Caution. Stem seal or packing replacement under pressure is hazardous
and is not recommended.
a) Wrench nuts and hand wheels shall be made of ductile iron; the wrench nuts
shall be 115/16inch. (49.2-mm) square at the top, 2 inch. (50.8-mm) square
at the base, and 13/4inch. (44.5-mm) high. The outside diameter of hand
wheels shall not be less than indicated in ANSI/AWWA C509 Table 5. Nuts
shall have a flanged base on which shall be cast an arrow at least 2inch.
(50.8-mm) long showing the direction of opening. The word "OPEN," in 1/2
inch. (12.7-mm) or larger letters, shall be cast on the nut to indicate clearly
the direction to tum the wrench when opening the valve. Hand wheels shall
Water Supply, Irrigation Main and Firefighting Networks Section 331000
Urbanium New Administrative Building (Prj. 2874) Page 30 of 72
be of the spoke type only. Webbed or disc types are not permissible. An
arrow showing the direction to tum the hand wheel to open the valve, with
the word "OPEN" in 1/2 inch. (12.7-mm) or larger letters in a break in the
arrow shaft, shall be cast on the rim of the hand wheel so as to be readily
readable.
7) Gaskets
8) Gearing
1) The valves shall be of the resilient seated with non-rising stem in compliance
with AWWA C509 and C515, the pressure rating and the drilling of the
flanges shall be as per the Data Sheets and the BOQ.
2) The valves requirements shall apply for gate valves (isolation valves) which
Water Supply, Irrigation Main and Firefighting Networks Section 331000
Urbanium New Administrative Building (Prj. 2874) Page 31 of 72
shall be used for pipeline of size of DN 250 mm dia (inclusive) and smaller
unless specifically mentioned otherwise.
3) The valve shall have necessary provision to be coupled with an electrical
actuator if required at a later date.
4) Material. The body and bonnet shall be ductile iron
5) The wedge of the gate valve shall be fully encapsulated with an EPDM
rubber.
6) The valve shall be closed by clockwise movement
7) Gate valves shall be shall be of the double flange type with overall length
(flange to flange) complying with ASME B16.10 / ANSI B16.10, ISO 5752
Series 14 or series 15 standards
Material
Body Ductile Iron A536 65-45-12
Bonnet Bolt & Nuts Stainless Steel AISI 316
Bonnet O-Ring Nitrile ASTM D2000
Bonnet Ductile Iron A536 65-45-12
Ductile Iron, SBR Encapsulat- A536 65-45-12 + Rubber Encapsulation,
Wedge
ed SBR
Anti- friction Washer (2) Acetal
Stuffing Box w/dirt seal Ductile Iron A536 65-45-12
Guide Cap Bearings Acetal
Stem Nut Bronze ASTM B62
Hand wheel Ductile Iron A536 65-45-12
Wrench Nut Cap Screw Stainless Steel AISI 304
Stem Stainless Steel AISI 420
Wrench Nut Ductile Iron A536 65-45-12
Stuffing Box Seal Nitrile ASTM D2000
Wrench Nut Cap Screw Stainless Steel AISI 316
Stem O-Ring Nitrile ASTM D2000
Stuffing Box Bolts & Nuts Stainless Steel AISI 316
Pressure Rating
Potable Water PN 10
Irrigation PN 10
D Service Connection
1. General
2. Polyethylene Pipes
d. The pipes shall be supplied in coils of 150 m and shall be kept shaded at
all times. The coils shall be wrapped and shall not be exposed to direct
sunlight.
3. Saddle Straps
a. DI tapping saddles for service connections designed for long life Suitable for
tapping up to 2" diameter. The Saddles shall be suitable for making service
connections under pressure or dry using approved tapping machine into
HDPE or PVC pipes. The saddle shall be of two parts fitted with EPDM seal-
ing gasket, stainless steel nuts, bolts and washer to ISO 3506 and shall be
suitable for a working pressure of up to 16 bar.
b. Tapping saddle for PVC and PE pipes for water and wastewater treatment
to max. 70° C
h. SBR rubber lining covers the internal surface to avoid direct contact be-
tween the ductile iron saddle and the pipe surface.
i. The bolt holes are fully epoxy coated to protect against corrosion.
l. Material specification
1) Compression Fittings
a. Detectable warning tape shall be installed 250mm above the top of pol-
yethylene pipes over entire length of the house connection in green and
unpaved areas.
b. The tape shall be 250mm wide, blue coloured, plastic and aluminum
coated with the detection strip sealed at the edge. The tape shall have
the warning "CAUTION – WATER MAIN BELOW" in Arabic and English
printed on it.
E Accessories
b. Extension Spindle:
1) The extension spindle shall be in one piece i. e. the main spindle shall be ex-
tended without connecting coupling. Alternatively, extension spindle with con-
necting coupling shall be supplied.
2) The height of extension spindle shall be such that spindle cap is 300mm from
surface box. The size and material of extension spindle shall be as per manufac-
Water Supply, Irrigation Main and Firefighting Networks Section 331000
Urbanium New Administrative Building (Prj. 2874) Page 35 of 72
turer recommendation and to ensure by manufacturer / tenderer that it can
withstand heavy torque during operation. The connecting coupling joining to
main spindle and extension spindle shall be attached by nut bolt of stainless
steel grade 316 and passing through. The spindle cap on the extension spindle
shall be as per dimension shown in BS 5163. The spindle cap shall be attached to
extension spindle by nut bolt of stainless steel grade 316 and passing through
extensional spindle and cap. Round supporting plate shall be welded to exten-
sion spindle at 100 mm below spindle cap and dia. of round supporting plate
shall be 5 mm less than internal dia. of PVC pipe. This is required to keep exten-
sion spindle in the center of PVC pipe. Extension spindle, connecting coupling
and spindle cap shall be epoxy coated in blue color. The following marking shall
be provided on top of round plate: Name of Manufacturer, Contract No. and
Date of Manufacturing.
3) The PVC pipe piece shall be 100mm dia and class C/D/E. It shall have length of
1.3m for valve size 150mm dia. and below and 1.0 m for valve size above 150
mm dia. More length shall be provided if valve is laid deeper than normal depth.
PVC pipe piece shall be fitted over the neck of valve with watertight adaptor.
The top of PVC pipe shall be cut up to bottom of frame of manhole cover, at site.
4) Watertight adapter or any other suitable arrangement is to be given which shall
be used to connect the neck of valve and PVC pipe. It shall be watertight so that
groundwater cannot enter inside PVC pipe after fixing over the neck of valve.
a. Except as stated otherwise, all fastening steel bolts for connecting valve flanges
with pipeline flanges shall be of high tensile steel (400 N/mm²). The bolts, nuts
and washers shall be either cadmium plated or hot dipped galvanized steel as
indicated in the applicable data sheets or in the piping specification of the re-
spective project.
/ Or
b. Nuts & bolts with washers shall be of AISI type 316 Stainless Steel complying
with ASTM A276 or equivalent. The grade shall be embossed on bolts. They shall
be supplied with two stainless steel grade 316 standard washers. Unless other-
wise indicated on the drawings, all stainless steel (whether nut bolts or any oth-
er items) shall be Type 316 with a mill finish
a. Where flexible couplings are required, they shall be of the tied or restrained
type, flexible couplings or equal. The supplier shall follow the manufacturer’s
Recommendations as to the methods and equipment to be used in assembling
the joints. In particular, the supplier shall ensure that rubber rings are correctly
positioned and free of twists. The rubber rings and any recommended lubricants
should be obtained only from the coupling manufacturer.
b. Flexible couplings and flange adaptors shall be capable of withstanding the test
pressure appropriate to the pipes for which they are supplied.
c. Material Specification (at a glance):
d. Details of couplings for incorporation in the works shall be submitted to the En-
gineer for approval
e. Rating: Shall be as follows:
1) Pressure Rating is the same as the valve or the pipe connected to the stepped
coupling
2) Test pressure equals to 1.5 working pressure.
4. Dismantling Joints
a. Dismantling joints shall be installed at selected locations within the piping of the
pump station and in the valve chambers along the pipeline as shown on the de-
tailed drawing to facilitate future removal of valves and other equipment for
servicing/replacement.
b. Features
c. The dismantling joints shall be of the tied/restrained type having the following
specifications:
3) Flanged Spigot
Water Supply, Irrigation Main and Firefighting Networks Section 331000
Urbanium New Administrative Building (Prj. 2874) Page 37 of 72
a) Flange - Rolled Steel to BS EN 10025-2:
b) Spigot - Steel Tube to BS EN10255, or Steel Tube to BS EN10216-1, or Rolled
Steel to BS EN 10025-2
4) Gaskets, BS EN681-1
5) Steel Tie Rods & Nuts
7) Studs/Nuts/Washers
1) Pressure Rating is the same as the valve or the pipe connected to the
Dismantling joints
2) Test pressure equals to 1.5 working pressure
5. Stepped Couplings
a. Stepped couplings shall be used to connect the spigot ends of two pipes of dif-
ferent nominal diameters.
b. A range of universal straight couplings, stepped couplings and flange adaptors
for ductile iron, steel, and uPVC, stepped couplings are easy to mount due to the
anti-friction coated bolts and nuts and the possibility of up to ±4° angular deflec-
tion. The stainless steel bolts and nuts and the high quality coating offer a dura-
ble corrosion protection.
Water Supply, Irrigation Main and Firefighting Networks Section 331000
Urbanium New Administrative Building (Prj. 2874) Page 38 of 72
c. Features
d. The Stepped Couplings shall be of the universal straight couplings type having
the following specifications:
1) Pressure Rating is the same as the valve or the pipe connected to the
stepped coupling
2) Test pressure equals to 1.5 working pressure.
a. The sealing mechanism shall be by rubber ring set in a locating groove around
the branch opening and held firmly against the mainline pipe by the pressure of
the opposite bolted half or alternatively by full length rubber gaskets along the
mating halves and at the separate end flanges. The rubber gaskets shall be
EPDM to ISO 4633 suitable for drinking water. The bolts, nuts, washers shall be
stainless steel 316. The split tees shall be coated with nontoxic fusion bonded
epoxy powder or a Nylon based polyimide 11 coating system with normal dry
film thickness of 300 microns and a minimum DFT of 250 microns.
a. Thrust/anchor flanges shall be used where D.I. pipes or fittings are cast into the
chamber wall and shall be designed to restrain the connecting valves or other
equipment installed inside the chamber. Thrust/anchor flanges shall be integral-
ly cast or factory welded on to the pipe piece. Bolted or screwed on thrust
flanges are not acceptable. The coating to the thrust/anchor flange shall be simi-
lar to that of the pipe/fitting. The position of the thrust/anchor flange shall be as
shown on the drawings or determined on site.
b. Rating: Shall be as follows:
1) Pressure Rating is the same as the valve or the pipe connected to the
stepped coupling
1. The electric remote control valve shall be a normally closed 24 VAC 50/60 Hz
(cycles/sec) solenoid actuated globe pattern design capable of having a flow
rate and pressure as indicated on the drawings. The valve pressure rating shall
not be less than 200 psi (13,8 Bars).
2. The valve body shall be constructed of heavy-duty glass-filled UV-resistant ny-
lon and have stainless steel studs and flange nuts; diaphragm shall be of nylon
reinforced nitrile rubber.
3. The valve shall have both internal and external manual open/close control (in-
ternal and external bleed) for manually opening and closing the valve without
electrically energizing the solenoid. The valve's internal bleed shall prevent
flooding of the valve box.
4. The valve shall house a fully-encapsulated, one-piece solenoid. The solenoid
shall have a captured plunger with a removable retainer for easy servicing and
a leverage handle for easy turning. This 24 VAC 50/60 Hz solenoid shall open
with 19.6 VAC minimum at 200 PSI (13,8 Bars). At 24 VAC, average inrush cur-
rent shall not exceed .41 amps. Average holding current shall not exceed 0.28
amps.
5. The valve shall have a brass flow control stem for accurate manual regulation
and/or shut-off of outlet flow. The valve must open or close in less than 1 mi-
nute at 200 PSI (13,8 Bars) and less than 30 seconds at 20 PSI (1,4 Bars).
6. The PESB valve shall have a self-cleaning stainless steel screen designed for use
in dirty water applications.
7. The valve construction shall be such as to provide for all internal parts to be
removable from the top of the valve without disturbing the valve installation.
8. Pressure Regulating Modules When so indicated on the design, the 1", 1 1/2",
and 2" electric remote control plastic valves shall have a pressure regulating
module capable of regulating outlet pressure between 1,04 and 6,90 Bar +/-
0,21 Bar. The pressure regulator module shall have an adjusting knob for set-
ting pressure and Schrader valve connection for monitoring pressure. The
pressure shall be adjustable from the pressure regulator when the valve is in-
ternally manually bled or electrically activated.
1. The quick coupling valve shall be a one-piece type capable of having a dis-
charge rate of 7 m3/Hr. with a pressure loss not to exceed 1.15 bars.
2. The valve body shall be constructed of red brass. The cover shall be a durable,
protective self-closing rubber cover. When so specified, the cover shall be a
locking rubber cover (LRC).
3. The valve shall be opened and closed by a brass key of the same manufacturer
having a 1" (FNPT) outlet. The valve throat shall have a key-way with detent
positions for regulating water flow.
4. Reinforced Rubber Hoses: According to BS 5119 rubber, vinyl or other high
tensile thermoplastic material reinforced with woven fabric, with quick cou-
plings to match the hose taps. Hose to be flexible, of such construction as to
prevent snaking and allow easy coiling.
Water Supply, Irrigation Main and Firefighting Networks Section 331000
Urbanium New Administrative Building (Prj. 2874) Page 40 of 72
5. The hoses should be made of reinforced fabric to be continuous nylon or poly-
ester fibers; inner and outer liners to be high tensile thermoplastic of high re-
sistance to heat and sun and abrasion when dragged over concrete.
6. End connections shall be of brass, factory installed on hose and watertight.
7. Head End: quick coupling, water tight swivel female thread or socket snap-on-
type to fit the water tap outlet.
8. Tail end: male threaded with all brass hand-trigger type discharge nozzles with
adjustable pattern and flow to complete shut off. Springs to be of stainless
steel.
9. The hose is to maintain its flexibility and pressure requirements between 2 and
60 deg. C. Hose is to withstand pressure of 6 bars when discharge nozzle is
closed, and comply with the requirements of ASTM D3901-85 as appropriate
for the materials selected.
10. Hose is to have an inside diameter of 25 mm and a length of 30 m excluding
end fittings.
1. Valve boxes shall be used as durable, rigid enclosures for valves or other irriga-
tion system components requiring subsurface protection for installation or
maintenance.
2. The valve box shall be made of structural foam HDPE resin that is resistant to
UV light, weather, moisture, and chemical action of soils.
3. The standard rectangular body shall have knock-outs molded into the sides
that can be readily removed. The knock-outs shall remain an integral part of
the body unless removed to run pipes or wires through the valve box.
4. The valve box shall have corrugated sides. Rectangular valve boxes shall have
a grooved feature on one side, just below the lid at the top of the box, for in-
serting a shovel blade or other prying tool to provide easy lid removal. This is
useful following compaction of the surrounding soil or after the eventual ac-
cumulation of thatch over the valve box.
5. Extension models shall have vertical ribs inside that make them capable of be-
ing mounted directly over the top of another box.
6. Boxes shall have a stepped feature on the bottom that securely interlocks two
boxes together when mated bottom-to-bottom for use in a deep installation.
7. There shall be no hole in the valve box lid unless the bolt-hole knock-out is
removed in order to use the locking bolt. Lids shall have beveled edges to min-
imize potential damage from lawn equipment. Lids shall be clearly marked
with the words “Irrigation Control Valve” molded onto the top. Lids shall have
a marking area measuring at least 6” by 2” that is suitable for branding or oth-
er means of identification.
b. Standard 200 mesh (75 micron) filter screen constructed of durable pol-
yester fabric attached to propylene frame. Screen is serviceable for
cleaning purposes by unscrewing cap from filter body and removing fil-
ter element.
1. The sprinkler body, stem, nozzle and screen shall be constructed of heavy-
duty, ultra-violet resistant plastic. It shall have a heavy-duty stainless steel re-
tract spring for positive pop-down and a ratcheting system for easy alignment
of the pattern. The sprinkler shall have a soft elastomer pressure-activated co-
molded wiper seal for cleaning debris from the pop-up stem as it retracts into
the case to prevent the sprinkler from sticking up.
2. The sprinkler shall have a plastic variable arc nozzle with an adjusting screw
capable of regulating the radius and flow. The sprinkler shall be capable of
housing filter screens under the nozzle.
F BUBBLERS
1. Adjustable Bubblers for Trees and Palms: The bubbler shall be of adjustable
flow and radius type by turning outer cap.
2. The bubbler shall have Four convenient installation connections available for
design flexibility: 10-32 self-tapping thread, 1⁄2" FPT, 1⁄4" barb, and 5" spike.
3. The bubbler shall be capable of covering a 0.38 (meter) at 2.0 (Bars) with a dis-
charge rate of 132.5 (l/h).
G MULTI-OUTLETS
2. These emitters are also available in both barbed and 1/2” female pipe thread
inlet.
3. The outlets are easily opened by removing the tip with cutting pliers. For une-
ven terrain, long laterals, pipe friction loss and mainline variations, the pres-
Water Supply, Irrigation Main and Firefighting Networks Section 331000
Urbanium New Administrative Building (Prj. 2874) Page 42 of 72
sure compensating design assures a high level of uniformity.
1. P.E Drip-In Lines for Ground Covers and Vines: tubing; brown in color, con-
forming to an outside diameter (O.D.) of 0.634 inches (16 mm) and an inside
diameter (I.D.) of 0.536 inches (13,6 mm) and wall thickness of 0.049 inches
(1,2 mm)
4. Consistent flow rate from each installed inline emitter when emitter inlet
pressure is supplied between recommended operating range of 8.5 to 60 PSI
(0,7 to 4,1 bar)
5. Required filtration for drip line tubing and emitters is 120 mesh (125 micron)
6. P.E Tubing: Extruded from virgin linear low density polyethylene resin, free of
splits and kinks, resistant to stress, cracking and rolling, suitable for use above
or below ground, specifically manufactured for receiving drip irrigation emit-
ters, maximum working pressure of 4 bars.
7. The fittings for laterals are to be durable with minimum flow resistance, com-
pression type couplings. Connection to manifold to be achieved using com-
pression fittings or insert barbs with external retaining clamps or collars. Fit-
tings to attach to the manifold by solvent cement for HDPE manifold and by
threaded connection or rubber grommet for polyethylene. Ends of laterals to
be folded over and held in place by a slide collar.
I Program Controllers
1. The irrigation system Controller shall be of a hybrid type that combines elec-
tro-mechanical and microelectronic circuitry capable of fully automatic or
manual operation. The controller shall be housed in a wall-mountable, weath-
er-resistant plastic cabinet with a key-locking cabinet door suitable for either
indoor or outdoor installation.
6. The controller shall have a 365-day calendar with Permanent Day Off feature
that allows a day(s) of the week to be turned off on any user selected program
day cycle. (Custom, Even, Odd, Odd31, & Cyclical). Days set to Permanent Day
Off shall override the normal repeating schedule and not water on the speci-
fied day(s) of the week.
7. The controller shall also have a Calendar Day Off feature allowing the user to
select up to 5 dates up to 365-days in the future when the controller shall not
start programs. The controller shall incorporate a Rain Delay feature allowing
the user to set the number of days the controller should remain off before au-
tomatically returning to the auto mode.
8. The controller shall have Cycle+Soak water management software which is ca-
pable of operating each station for a maximum cycle time and a minimum soak
time to reduce water run-off. The maximum cycle time shall not be extended
by Seasonal Adjustment.
10. The controller shall offer Water Windows for each program. This function sets
the allowed start and stop time where watering is allowed. If the watering
cannot be completed by the time the Water Window closes, the stations with
remaining run time are paused and watering automatically resumes when the
Water Window opens the next time.
11. The controller shall have an alarm indicator light on the front panel visible
through the outer door with the door closed and locked. The alarm light shall
prompt the user to select the alarm soft key to review the alarm condition(s).
2. Scope:
3. Construction:
f. Listing for valve wire: All wire listed for use in the USA shall be tested
physically and electrically in accordance with UL Standards 493 and
83. These wires will carry a 600V rating.
g. Dual rated wire, listed for use in the USA and Canada, shall be tested
physically and electrically in accordance with UL Standards 493 & 83,
and CSA Rule C22.2 No. 35. These wires will carry a 30V rating.
4. Splicing Recommendations:
PART 3 EXECUTION
3.1 GENERAL
A All pipe work, fittings are to be installed in strict accordance with the manufacturer
instructions and in accordance with this specification. The excavation, pipe bedding
and back filling shall comply with Section 3200 “Earthwork”
A Excavation
1. The Engineer shall provide the Contractor with benchmark, base line and
points of reference to be used by the Contractor in laying out the work. From
the benchmark, base line and points of reference the Contractor shall do his
own layout. The Contractor shall notify the Engineer if for any reason these
benchmarks, base line and pints of reference are disturbed, lost or destroyed.
The Contractor shall be charged the cost necessary to replace and relocate all
bench marks, base line and points of reference so disturbed, lost or destroyed.
2. The Contractor shall be responsible for true and proper laying out of the work
and for the correctness of position, levels, dimensions and alignment of all
parts of the work and for the provision of all necessary survey instruments,
equipment, labor, stakes, templates, batter boards, material and supplies nec-
essary for the laying out of the work and maintenance thereof.
3. If at any time during the progress of the work any error shall appear or arise in
the position, levels, dimensions or alignment of any part of the work the Con-
tractor shall, at his own expense, rectify such error to the satisfaction of the
Engineer.
4. The checking of any layout or of any line or level by the Engineer shall in no
way relieve the Contractor of his responsibility for the correctness thereof.
C Pipe Distribution
1. Distribute material on the job no faster than it can be used to good advantage.
Unload pipe, which cannot be physically lifted by workers from the trucks, by a
forklift or other approved means. Do not drop pipe of any size from the bed of
week’s supply of material in advance of laying, unless otherwise approved by
the Engineer.
1. Inspect all pipe and fittings prior to lowering into trench to ensure no cracked,
broken or otherwise defective materials are being used. Clean ends of pipe
thoroughly. Remove foreign matter and dirt from inside of pipe and keep clean
during and after laying.
2. Pipe and accessories that are chipped, cracked or contain other imperfection
or do not meet the test requirements shall be marked with a permanent mark-
ing as rejected and shall be promptly removed from the Site.
3. Use proper implements, tools and facilities for the safe and proper protection
of the work. Lower pipe into the trench in such a manner as to avoid any phys-
ical damage to it. Remove all damaged pipe from the Site. Do not drop or
dump pipe into trench under any circumstances.
1. Warning tapes shall be laid above all utility pipes. Tapes shall be durable and
Water Supply, Irrigation Main and Firefighting Networks Section 331000
Urbanium New Administrative Building (Prj. 2874) Page 47 of 72
detectable by electro-magnetic means using low output generator equipment.
They shall remain legible and color fast in all soil conditions at pH values of 2.5
to 11.0 inclusive.
2. Warning tapes shall be placed in compacted backfill material, approximately
300 mm below finish grade and as indicated on drawings.
3. The tapes shall be flexible and subject to the Engineer’s approval. Width of the
tape shall be at least 6” (150 mm).
4. Tapes shall have different colors for different utilities and with black text in Ar-
abic and English as “CAUTION WATER PRESSURE MAIN BELOW” for water
mains, etc. The text on the tape shall be permanent ink bounded to resist pro-
longed chemical attack by corrosive acids and alkaline with message repeated
at a maximum interval of two (2) meters.
5. The tape shall be laid continuous over pipelines and at joints there shall be a
minimum of one (1) meter overlapping. Tape shall be terminated inside valve
boxes to allow clipping of detector equipment to the tape.
6. Warning tape shall not be separately measured or paid for, but shall be con-
sidered as a subsidiary obligation under the respective items included in the
Bill of Quantities.
F Geotextiles
1. Store and handle geotextiles in accordance with ASTM D 4873. Place and in-
stall in accordance with manufacturer’s written instructions and as follows, to
the approval of the Engineer
G Soil Tests
1. During buried pipe installation, work should be checked throughout the con-
struction period by an inspector who is thoroughly familiar with the jobsite,
contract specifications, materials, and installation procedures. Inspections
should reasonably ensure that signify cant factors such as trench depth, grade,
pipe foundation (if required), quality and compaction of embedment backfill,
and safety are in compliance with contract specifications and other require-
ments. To evaluate soil stability, density and compaction, appropriate ASTM
tests may be required in the contract specifications.
I INSPECTION
J Pipe Cutting
1. Where pipes are required to be cut on the Site the cutting shall be done by the
Contractor in accordance with the manufacturer’s recommendations and in a
manner approved by the Engineer.
2. The pipe and methods of jointing shall be such that the locations of fittings and
lengths of pipe can be adjusted to suit Site conditions.
3. Cutting of reinforced concrete pipes will not be allowed. Special lengths of
pipes shall be manufactured for closures as required. Other pipes such as GRP,
ductile iron, vitrified clay, MDPE, HDPE, PVC-U and cast iron pipes shall only be
cut if approved by the Engineer.
4. The cutting of vitrified clay pipes, MDPE, HDPE, PVC-U, and ductile iron pipes
for inserting specials, fittings or closure pieces shall be carried out as follows:
a. Heat fusion joining may be performed in any season and in hot or cold
conditions. During inclement weather, a temporary shelter should be
set-up around the joining operation to shield heat fusion operations
from rain, frozen precipitation, and high wind conditions. Wind chill can
reduce heating plate temperature or chill melted component ends be-
fore joining. If fusion joining operations cannot be protected against
dust contamination during severe windblown dust conditions, joining
may need to be temporarily suspended until conditions improve.
b. Most heat fusion equipment is electrically powered, but is not explosion
proof. The fusion equipment manufacturer’s instructions should be ob-
served at all times and especially when heat fusion is to be performed in
an atmosphere that may be volatile, such as coal or grain dust or in are-
as where gas or gas fumes may be present.
c. When installing large diameter PE pipe in a butt fusion machine, do not
bend the pipe against an open fusion machine collet or clamp. The pipe
may suddenly slip out of the open clamp, and cause injury or damage.
1) Damage Inspections
1. The CONTRACTOR shall make the under pressure tapping for the connection to
the main water pipeline, install the polyethylene service connection pipe in-
cluding all auxiliary fittings from the tapping point up to the consumer water
entry point.
2. Saddle straps shall be installed on to the main water pipeline. The tapping to
the pipeline shall be done though the saddle strap using tapping machine ap-
proved by the ENGINEER.
3. Install Gate valves for service connection to allow for the isolation of the con-
sumer connection. The valve shall directly installed to the BSP Saddle thread-
ed, the polyethylene pipe shall connected to the socket end of the pipe and
shall be laid from the socket end up to the consumer entry point.
4. The polyethylene pipe shall be laid from the ferrule up to the consumer entry
point.
Water Supply, Irrigation Main and Firefighting Networks Section 331000
Urbanium New Administrative Building (Prj. 2874) Page 54 of 72
5. Connectors, bends, adapters shall be provided as necessary. The polyethylene
pipe shall be installed in uPVC protection pipe class 10 for protection and ease
of maintenance. The uPVC pipe shall be 110 mm diameter for ½ " and ¾ " pol-
yethylene pipes and 160 mm diameter for 1", 1 ½ " and 2" polyethylene pipes.
The uPVC protection pipe shall be provided at all green and unpaved areas. In
sidewalk and paved area the uPVC protection pipe shall be encased in rein-
forced concrete. Warning tape shall be provided over the polyethylene pipe /
uPVC protection pipe in green and unpaved areas.
6. For future consumers the polyethylene service connection pipe shall be termi-
nated and plugged within the consumer limits.
1. The Engineer will issue to the Contractor detailed instructions regarding each
interconnection that has to be made to the existing mains and service pipes.
Cutting into an existing main or service pipe and effecting the interconnection
shall only be made in the presence of a representative from the Employer's
Maintenance Section at the time specified by the Employer.
2. Cutting into the existing main or service pipe and installation of the intercon-
necting pipe work shall be carried out efficiently and rapidly so as to reduce to
a minimum the interruption of the public water supply. It may be necessary to
undertake such work at night, when water demands are reduced and/or to
schedule such work to be performed during the winter.
3. Existing mains and service pipes shall only be cut using special equipment ap-
proved by the Engineer. The cut shall be perpendicular to the centerline of the
pipe and special care shall be taken with respect to the location of the cut to
ensure that the new pipe work shown on the Drawings may be installed. The
Contractor shall agree with the Engineer the length of existing pipe work to be
removed.
4. The Contractor shall take every care to avoid any dirt or extraneous material
entering the existing main or service pipe.
5. The Contractor shall have available at the site of the connection an efficient
dewatering pump before commencing any cut into the existing main or service
pipe in order that the excavation remains dry at all times and to reduce the risk
of dirty or contaminated water entering the existing distribution system. The
work shall be carried out in a clean and efficient manner. The Contractor shall
provide at the site of the connection sufficient quantities of clean water con-
taining 10 ppm chlorine in solution. Every item of new pipe work to be in-
stalled shall be submerged in the chlorine solution for at least 15 minutes im-
mediately before being installed in the permanent works.
6. The Employer may put the interconnection into use as soon as possible after
its installation and will carry out an inspection to detect any evidence of leak-
age; any remedial work necessary to eliminate leakage shall be carried out by
the Contractor. No pipe work shall be covered or backfilled until the Engineer
is totally satisfied that the interconnection is free of all leakage.
1. Cleaning
b. Swabbing
1) One of the following methods shall be used to swab the pipeline. En-
gineer shall instruct the Contractor as to which method is to be uti-
lized.
a) Hydraulic Swabbing
b) A foam plastic cylinder swab, inserted into the pipeline and driven
by hydraulic pressure through the pipeline. The dimensions of the
swab shall be as follows:
c. Scouring
2. Testing
a. General
1) After being vented, the pipework shall be slowly filled with water and
subjected to the required test pressure.
2) Where there are significant differences between the ambient temper-
ature and the water temperature, there shall be an initial period of 30
min before the commencement of the test period, to permit tempera-
ture equilibrium after the test pressure has been applied.
3) There shall be no visible leakage of water and the test pressure shall
be maintained for a test period of one (1) hour.
1) After being vented, the pipework shall be slowly filled with water and
shall be subjected to the required procedures of test procedure A or
test procedure B. The selection of test procedure shall be agreed by
the Engineer.
a) Test Procedure A
b) Test Procedure B
1) PVC Pipes
2) PE Pipes
1) For every test and visual inspection, record the following information
and provide copies to the Engineer as required:
f. Subsequent Failure
g. Final Inspection
1) Facilitate the final inspection of the pipe system and ensure access to
the work by the Engineer. Notify the Engineer when any portion of the
work is ready for final inspection and witness the inspection.
2) The Engineer reserves the right to employ any means to accomplish
the final inspection including the use of television inspection equip-
ment.
3) The Contractor shall provide necessary lamps, ropes, bulkheads, plugs,
temporary pumping, ventilation equipment, ladders and other equip-
ment to allow the Engineer to properly and safely inspect the work.
3. Disinfection
a. General
a) Tablet Method:
b) Continuous-Feed Method:
i. Place calcium hypochlorite granules in pipe sections during
installation to provide a strong chlorine concentration in
the first flow of flushing.
ii. The flushing velocity shall be not less than 0,76 m/s.
iii. After flushing, the system, or a part of the system or a pipe
section shall be slowly filled with potable water and chlo-
rinated at a constant rate of chlorine such that the water
will have not less than 25 mg/liter free chlorine. Below table
gives the amount of chlorine required for each 30 m of pipe
section of various diameters. Solutions of 1% chlorine may
be prepared with sodium hypochlorite or calcium hypo-
chlorite. The latter solution requires 450 grams of calcium
hypochlorite in 30 liters of water.
iv. Chlorine Required to Produce 25-mg/Liter Concentration in
30 m of pipe
c) Slug Method:
O BACKFILLING
1) Cohesive soils shall be placed in layers not greater than 150mm thick
(compacted thickness) and compacted such that throughout each layer
placed the dry density is not less than 95% of the in situ dry density of
the soil prior to excavation when tested in accordance with relevant BS
specification.
2) The placement moisture of the soil shall be within the range 2% below
to 1% above the natural in situ moisture content of the soil before ex-
cavation. It is to be noted that the cohesive soils or hard materials
from excavations shall be broken down to suitable sizes to be used for,
backfilling, of the top two layers for stability or as per Engineer’s in-
structions at no extra cost.
b. Granular Soils
1) Granular soils shall be placed in layers not greater than 150mm thick
(compacted thickness) and compacted such that throughout each layer
placed the dry density is not less than 95% of that obtained in the vi-
brating hammer compaction test when the test is carried out on the
same soil at the same moisture content in accordance with relevant BS
specification.
2) Unless otherwise directed the moisture content shall be maintained
and if necessary adjusted by approved means to fall within the range
plus 1.5% to minus 3% of optimum moisture content determined in
the vibrating hammer compaction test.
3) For free draining granular soils that have no clearly defined optimum
moisture content, compaction shall be carried out to achieve a relative
density of not less than 95%. During compaction the soil shall be made
as wet as practicable.
c. Testing of Backfill
1) The Contractor shall provide at his own cost the services of approved
and backfilled soil properties and shall maintain with a copy to the En-
gineer, a daily log of tests carried out.
2) All back fills shall be carried out in layers of 150 mm thick. In-situ soil
compaction tests shall be carried out for pipe line trenches at the rate
of one test per 100mtrs of trench length for each layer of 150mm
thick, starting from 450 mm above the crown of the pipe. Deep test
shall not be carried out as the test location may not be representative.
Also, the Contractor shall continue backfilling the next upper layer only
if the test result for the previous layer is available and found to have
passed as per the requirements. In addition to the pipeline trench
backfilling and testing the chambers pits and pits forming at the sides
of the Thrust blocks shall backfilled in accordance with the relevant
specifications and tested for compaction for every 150 mm thick layers
of backfills. The initial layer to be tested shall be the excavated for-
mation level for the Thrust Block or chamber pits, which shall be tested
prior to placing the structure. The remaining in-situ soil compaction
tests to be carried out as the backfilling progresses layer by layer.
3) Where a land drain passes through an excavation the backfill shall first
be taken up to form a bed for replacement pipes. The severed drains
Water Supply, Irrigation Main and Firefighting Networks Section 331000
Urbanium New Administrative Building (Prj. 2874) Page 63 of 72
shall then be exposed at each side of the trench excavation. This new
drain shall be of similar pipes of the same diameter as those in the ex-
isting drain. Before any further backfilling is done the Contractor shall
notify the owner or occupier to enable him to see the reinstated land
drain. The replacement drain shall be surrounded with pipe bedding
material to a minimum thickness of 150mm before further backfilling.
P Valves
a. ENGINEER and/or third party Inspection Authority reserve the right for
stage inspection of material, manufacturing process, testing, etc. by
their authorized representatives. Such inspection shall not relieve the
CONTRACTOR of the responsibility for suitable design and workmanship.
b. Each individual component of the valve (body, disk, shaft etc.) shall be
subjected to heat treatments and tests (including NDT) as required by
the specific applicable material specification.
c. The material certificate indicating above details shall be inspected and
certified by ENGINEER's inspectors prior to starting shop tests of the
valve.
d. The Manufacturer/CONTRACTOR shall provide full assistance and co-
operation for any such inspection, when required by ENGINEER.
e. ENGINEER and/or Third Party Inspection Authority shall be informed of
all defects arising during manufacture and fabrication of the valves and
only the above shall authorize repair or rejection of faulty material or
workmanship.
f. The programme for the tests shall be prepared by the CONTRACTOR and
shall be subject to ENGINEER approval.
g. The below mentioned certificate requirements shall apply to the quality
Control Plan.
a) Functional tests
b) Strength test for the body
c) Leak test for the disk /seat
d) Rubber lining checks after vulcanization
e) Coating thickness checks (internally & externally)
f) Dimensional checks
a) Visual inspection
b) Adhesion test
c) Dielectric test
d) Shore D hardness test
e) Thickness test by electronic device
h. MANUFACTURER shall ensure that all the applicable codes and stand-
ards are available at their works for ENGINEER's reference during their
visit to manufacturer's works for shop inspection/tests.
i. Testing shall be carried out in accordance with applicable codes and
standards for the particular valves. Besides mechanical operation tests,
each valve shall be subjected to hydrostatic body pressure/leakage test
of 1.5 times the design pressure and a disc strength/ leakage test of 1.1
(hydrostatic) times the design pressure before leaving the manufactur-
er's works. Tests shall be witnessed by ENGINEER as specified and each
valve shall be accompanied by manufacturer's test certificates.
j. 5% of each size and type of valves supplied (butterfly, gate, non-return
and air valves) or a minimum of 1 No. of each size and type whichever is
greater shall be made available to ENGINEER witness testing. If the test
on any valve fails, the percentage of valves to be tested will be raised to
10%. Flow control valves, pressure sustaining valves, pressure reducing
valves & altitude valves shall be 100% witness tested by ENGINEER.
k. If any defect is detected during the tests before completion or during
the warranty period, the faulty equipment shall then be rectified imme-
diately by the VENDOR/CONTRACTOR at his expense. If the fault cannot
be rectified, the VENDOR/CONTRACTOR must then replace the defective
equipment which must also be proven to be free from defect.
2. Installation, General
a. Locate valves for easy access and provide separate support where nec-
essary.
b. Install valves in horizontal piping with stem at or above the center of the
pipe.
c. Install valves in a position to allow full stem movement.
d. Support piping systems and align components to minimize bending at
the valve connections
e. Place the valve on firm footing in the trench to prevent settling.
f. Install the valve in alignment with the pipe to prohibit excessive strain
on the connection to the pipe. Preventing any strain on the connection
is critical in flanged installations. Flange fracture can result from unequal
strains set up by improper makeup and tightening of the joints.
Water Supply, Irrigation Main and Firefighting Networks Section 331000
Urbanium New Administrative Building (Prj. 2874) Page 65 of 72
1) Support and align valves.
2) Clean dirt and grit particles from all parts.
3) Insert bolts and nuts and tighten by hand.
4) Tighten bolts and nuts by using the crossover method. Tighten the
bolts and nuts across the connection from each other in order un-
til the joint is uniformly tight (do not tighten the bolts and nuts in
rotation). This crossover method will load both pipe and valve
evenly and eliminate any concentrated stresses.
g. Install valves in the closed position to prevent any foreign material from
entering the valve.
h. Install swing check valves for proper direction of flow with hinge pin lev-
el.
i. Locate flow meter as recommended by manufacturer with respect to
other piping components to ensure flow meter will meet specified accu-
racy.
j. Flanged Connections: Align flange surfaces parallel. Assemble joints by
sequencing bolt tightening to make initial contact of flanges and gaskets
as flat and parallel as possible. Use suitable lubricants on bolt threads.
Tighten bolts gradually and uniformly using a torque wrench.
k. All exposed bolts nuts shall be heavily coated with 2 coats of bituminous
paint.
l. All valves shall be equipped with dismantling joint to enable removal and
installation of flanged valves as shown on Drawings. Install buried gate
valve complete with valve box and install valves inside valve chambers
complete with hand wheels/or spindle with valve box
m. Wrap buried valves, flanged joints, mechanical joints, flanged pipe
spools with thrust collars, and adapters with polyethylene material,
complete the wrap prior to placing concrete anchor blocks. Repair poly-
ethylene material damaged during construction.
n. Provide a valve box or vault for each valve used in a buried-service appli-
cation. The valve box should be installed so as not to transmit shock
loads or stress to the valve or valve actuator. When valves with exposed
gearing or operating mechanisms are installed belowground, a vault
must be provided to allow pipe clearance and prevent settling on the
pipe.
o. If groundwater or surface water enters the vault, the vault floor should
include a recessed drainage area and a pump to remove water from the
vault.
p. Center the valve box over the operating nut of the valve. The box cover
should be flush with the surface of the finished area. The operating nut
should be accessible from the top opening of the vault with a valve key.
Valve box should be installed in a manner that will not exert force creat-
ed from street traffic to the valve.
q. If installing a larger valve that uses smaller bypass valves, install a second
valve box over the bypass valve operating nut.
r. If the valves must be buried in an unusually deep trench, install a riser
on the stem to permit a normal key to be used, or make a notation in
the valve records that a long key will be required for operation.
Underground Installation
1. Valves in water-distribution lines shall, where practical, be located in easily ac-
cessible areas.
2. During installation, there is the possibility of foreign materials inadvertently en-
tering the valve. Foreign material can damage internal working parts during op-
eration of the gate valve. For this reason, gate valves should be installed in the
closed position. Each valve should be placed on firm footing in the ‘trench to
prevent settling and excessive strain on the connection to the pipe. Piping sys-
tems should be supported and aligned to avoid damage to the valve.
3. A valve box or vault should be provided for each valve used in a buried service
application. The valve box should be installed so as not to transmit shock loads
or stress to the valve. The valve box should be centered over the operating nut
of the valve with the box cover flush with the surface of the finished area or
such other level as directed by the engineer. Valve boxes should be designed so
that a traffic load on the top of the box is not transmitted to the valve.
4. Valves buried in unusually deep trenches should have special provisions for op-
erating the valve. Either a riser on the stem to permit use of a normal key or a
notation on valve records that a long key will be required.
5. When valves with exposed gearing or operating mechanisms are installed be-
lowground, a vault designed to allow pipe clearance and prevent settling on the
pipe should be provided. The operating nut should be accessible from the top
opening of the chamber with a valve key. The size of the chamber should pro-
vide for easy removal of the valve bonnet and internal parts of the valve for pur-
poses of repair. Consideration should be given to the possible entry of ground-
water or surface and to the need to provide for the disposal thereof.
General
1. Remove nut/washers from the extreme ends of the fittings and loosen nuts
behind flange.
2. Collapse dismantling joint and push tie rods through until flush with flange
that is to be mated with.
3. Assemble dismantling joint, together with gaskets/tie rods between flanges
of pipeline and valve.
4. Tighten up first flange joint to recommended torque.
5. Expand dismantling joint to required length and centralize tie rods, tighten
the tie rods to recommended torque.
6. Tighten the gland ring nuts to the recommended torque, it is essential that
the nuts are tightened in the correct sequence to ensure that the compres-
sion of the sealing element is consistent around its circumference.
7. Typical tightening sequence for the seal housing center flange.
a. Firstly, tighten all the gland seal nuts to the initial torque
b. On the second pass tighten the nuts to the mid-range torque.
c. Tighten for the final torque on the third pass.
SITE TESTS
General
After installation and before pressurization, inspect all pressure-containing bolting (bon-
net, seal-plate, bypass, and end connections) for adequate tightness to prevent leakage.
After installation and before commissioning, the CONTRACTOR shall carry out site tests,
to be witnessed by ENGINEER representatives as well as valves manufacturer's repre-
sentative.
Inspect all tapped and plugged openings of the valve interior for adequate tightness.
Proper inspection at this time will minimize the possibility of leaks once the piping sys-
tem is pressurized.
The test pressure should not exceed the rated valve pressure when resilient-seated gate
valves or butterfly valves are used to isolate a test section.
Examine valve interior through the end ports, for cleanliness, freedom from foreign mat-
ter and corrosion. Remove special packing materials such as blocks used to prevent disc
movement during shipping and handling. Actuate valve through an open-close and
close-open cycle. Examine functionally significant features such as guides and seats
made accessible by such actuation. Following examination, return the valve closure
member to the shipping position.
Examine mating flange faces for conditions which might cause leakage. Check bolting
for proper size, length and material. Check gasket material for proper size, material
composition suitable for service and freedom from defects and damage.
When metal-seated gate valves are being used as closure pieces for a test, the test pres-
sure should not exceed twice the rated valve pressure. Metal seated valves have an al-
Water Supply, Irrigation Main and Firefighting Networks Section 331000
Urbanium New Administrative Building (Prj. 2874) Page 68 of 72
lowable leakage, and this should be determined before the test. For tests at pressures
greater than the rated valve pressure, the test setup should include a reduction of the
line pressure to the rated valve pressure (independent of the valve) on completion of
the test. The valve can then be opened enough to release trapped pressure and equalize
it with the line pressure. The valve should not be opened or closed at differential pres-
sures above its rated working pressure.
Any problems/defects detected during these tests shall be promptly remedied / rectified
by the CONTRACTOR/Manufacturer at no additional cost to ENGINEER.
Replace defective valves with new valves.
When installation is complete, installers should make complete records of the installa-
tion on a permanent record that will serve as a reference during maintenance and re-
pair.
Test certificates shall be issued immediately after site testing and copies of the same
should be incorporated in the O&M manuals.
Q Irrigation:
1. General
2. Pipes
3. Cleaning
a. Flush dirt and debris from piping before installing sprinklers and other
devices.
4. System Components
d. Connections
7. Start-up Service
a. Verify that controllers are installed and connected according to the Con-
tract Documents.
b. Verify that electrical wiring installation complies with manufacturer's
submittal and installation requirements in electrical Division.
c. Complete start-up checks according to manufacturer's written instruc-
tions.
8. Adjusting
9. Demonstration
THIS PAGE IS A RECORD OF ALL SPECIFICATION REVISIONS. NORMALLY, REVISED SHEETS ONLY ATTACHED
EACH TIME THE SPECIFICATION IS CHANGED ONLY THE NEW OR REVISED ENTIRE SPECIFICATION RE-ISSUED
PAGES ARE ISSUED. ENTIRE SPECIFICATION REVISED
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. SEWAGE COLLECTION NETWORKS
CAIRO - EGYPT 333000 – 2874 0
SECTION 333000
PART 1 GENERAL 2
1.1 Related Documents 2
1.2 Description Of Work 2
1.3 Reference Standard 2
1.4 Submittal 4
1.5 Related Sections 6
1.6 Quality Control 6
1.7 Delivery Storage And Handling 7
PART 2 PRODUCTS 7
2.1 Warning Tapes 7
2.2 High Density Polyethylene Liner (Hdpe) 9
2.3 Geotextile 10
2.4 Oil-Water-Debris Separator 10
2.5 Reliner Inside Drop System 12
2.6 Pipes, Fittings And Accessories 13
2.7 Draiange Structure 19
PART 3 EXECUTION 29
3.1 Specialists, Inspection And Testing 29
3.2 Soil Corrosivity Study 30
3.3 Earth Work 30
3.4 Pipe Laying 39
3.5 Drainage Structure 50
PART 1 GENERAL
1.4 SUBMITTAL
A. Submit the following in accordance with Conditions of the Contract and Division-1
Specification Sections:
1. Pipes
a. In order to verify compliance with the specification the Contractor shall submit
information for all products and materials used in the Works to the Engineer for
approval sufficiently in advance of their use in accordance with the Contract
programme allowing for ordering and approval times. Information to be
submitted for each proposed production shall comprise but not necessarily be
limited to:
b. Should any details of the pipes and fittings be altered in any way during
manufacture from those proposed and approved by the Engineer, submit for the
Engineer's approval the revised details and test results.
2. Drainage Structure
3. Method of Statement
a. The Contractor shall submit method statements to the Engineer for approval 4
weeks in advance of commencing the site activity. These shall comprise but not
necessarily be limited to:
Earthwork Section
Cast-in-Place Concrete Section
Unit Masonry Assemblies Section
Metal Fabrications Section
Corrosion Protection and Odor Control Section
1.6 QUALITY CONTROL
A. Prior to dispatch of any product and/or material from source the Contractor shall
notify the Engineer in writing in sufficient time to allow the Engineer the
opportunity to inspect and test the product and/or material prior to delivery in.
B. Products and materials shall be from a manufacture/supplier who operates a
quality system which is registered to ISO 9000 series or approved equal.
C. To allow the Engineer to inspect the works the Contractor shall give the Engineer
a minimum of 24 hours’ notice of carrying out the following activities on site:
a. Any products damaged during delivery, storage and handling shall be marked by
the Contractor and set aside.
b. Proposals for repair of any damaged products shall be submitted in writing to
the Engineer for approval.
c. Any damaged products deemed unsuitable for repair by the Engineer shall be
removed from site and replaced.
PART 2 PRODUCTS
A Service protection tapes shall be installed above all sewage pipelines and
pressure mains constructed or exposed under this contract excluding individual
service connections.
D The thickness of the tape (250 micron / 1000 gauge) shall be measured in
accordance with BS 2782: Part 6. Method 630 A.
E The following properties shall be demonstrated by appropriate tests :-
1) MD : 450%
2) TD : 550%
2. Chemical resistance:
a. The tape shall be remaining legible and colour fast in all soil conditions at PH 2.5
– 11.0, inclusive. The tape shall not show any adverse effect when in contact
with the sulphates, chlorides and other minerals present in sub soil and water,
oil, 5% Acetic Acid, 5% NaOH and Alcohol mix, if any.
1. Text in Arabic and English indicating the protected services lying below the tape
shall be permanent ink bonded to resist prolonged chemical attack by corrosive
acids and alkalis with the message repeated at a maximum interval of two
meters. Tapes shall be color coded as follows, with black text as indicated. The
sign and styles of the text shall be approved by the Engineer
a. Sewage: Yellow
A General
B Properties
2
Property Unit Test Method Minimum
1
Thickness mm avg. ASTM D5199 1.52 (60 mil)
1
Thickness mm min. ASTM D5199 1.37 (54 mil)
Density g/cc min. ASTM D1505 0.940
Tensile Properties-Minimum Average Roll Values 1
ASTM D638
(Each Direction)
MPa 15.2 (2200 psi)
Yield Strength min.
N/cm 231 (132 lb/in)
MPa 10.3 (1500 psi)
Break Strength min.
N/cm 158 (90 lb/in)
Elongation at Yield % min. 13
Elongation at Break % min. 150
N/cm 1313 (750 lb/in)
Tear Resistance Puncture min. ASTM D1004
N 200 (45 lbs)
N/cm 3152 (1800 lb/in)
Resistance min. ASTM D4833
N 480 (108 lbs)
Law Temperature C max. ASTM D746 (-60)
ASTM D1204 +2.0
Dimensional Stability % max.
1 hour @ 1080
C Other Materials
2.3 GEOTEXTILE
A GENERAL
a. Easy to install
b. Easy to clean
c. Low head loss with high flow abilities
d. Reduces pipe cleaning maintenance
e. Highly corrosion resistant
f. Lightweight high-strength construction
g. Converts existing sump structures into oil—debris trap
h. Prevents siphoning of trapped contaminants
1. The SNOUT is hand fabricated from marine grade fiberglass. The attachment
hardware is stainless steel, the anti-siphon device is schedule 40 PVC and the
access hatch is ABS plastic. These materials have proven to be extremely
durable and maintenance free.
2. The SNOUT is adaptable to any type catch basin construction and is available in
flat or rounded back styles.
C Technical Data
2. SNOUT composite components are hand and chopper gun laminations of these
of Unsaturated Polyester Resin Reinforced Laminates, with the following
physical properties: -
D Specification
A. Product Description
B. Advantages
1. Reduce maintenance
2. Eliminate confined space entry
3. Speed Inspection
4. Simplify cleaning
5. Reduce turbulence and odor
6. Solids and liquids remain together
7. Erosion of structure eliminated
8. High corrosion resistance
9. Allow workers entering structure without risk of effluent contact
C. Technical Data
5. All new and/or existing manhole structures employing inside drop connections
for services and collector sewers shall use the RELINER® Inside Drop Bowl
components, Bowl size shall be determined by incoming pipe sizes and flow
rates. The bowl shall be installed as per manufacturer's instructions using
stainless steel fasteners. The drop pipe of SDR 35, Schedule 40 or other shall be
securely attached to the manhole wall using stainless steel RELINER Adjustable
Clamping Brackets and stainless steel fasteners. Bracket interval shall be 4 feet
maximum (minimum of 2 brackets). The connection of Drop Bowl to drop pipe
shall be by flexible external pipe coupler. The turn-out at the base end of the
drop pipe shall be accomplished with an appropriately angled PVC pipe elbow
(45 degree recommended).
A. General
1. The material from which the pipes, fittings and valves are made shall be an
unplasticized poly (vinyl chloride) compound or formulation. This compound or
formulation shall consist of PVC-U resin/powder, to which shall be added those
additives which are needed to facilitate the manufacture of pipes and fittings
conforming to BS EN 1401-1:2009 as applicable.
B. Raw Material
a. The composition of the CaCO3, before coating if any, shall conform to the
following:
C. Pipe Material
D. Fitting Material
E. Compound Characteristics
F. Ring Stiffness
2. Consequently, fittings are classified with the corresponding pipe stiffness. The
actual value of stiffness of the fittings can be determined in accordance with
ISO 13967 [7].
3. Fittings according to this standard, because of their geometry, have a stiffness
greater than the stiffness of the corresponding pipe. Therefore, the following
applies:
a. Fittings marked with SDR 41 may be used with pipes up to SN 8 (SDR 34) ;
b. Fittings of DN ≥ 400 marked with SDR 51 may be used with pipes up to SN 4
(SDR 41).
G. Creep Ratio
1. The creep ratio for pipes and fittings conforming to BS EN 1401-1:2009, when
determined in accordance with EN ISO 9967 [8], is less than 2. For fittings the
full cylindrical length of the socket or spigot is used as a test piece and the pre-
load force, F0, is decreased relative to the actual length of the test piece.
H. Chemical Resistance
I. Abrasion Resistance
J. Hydraulic Roughness
L. General Characteristics
a. The internal and external surfaces of pipes and fittings shall be smooth, clean
and free from grooving, blistering, impurities and pores and any other surface
irregularity
b. Pipe ends shall be cleanly cut and the ends of pipes and fittings shall be square
to their axis.
2. Color, the pipes and the fittings shall be colored through the wall. The color
should preferably be orange-brown (approximately RAL 8023 1)) or dusty grey
(approximately RAL 7037 1)). Other colors may be used.
M. Geometrical Characteristic
1. Pipe
2. Fittings
a. Outside diameters, the mean outside diameter, dem, of the spigot shall conform
to Table 3 BS EN 1401-1:2009
b. Design lengths (Z), the Z-length(s) of fittings shall be given by the manufacturer.
c. Wall thicknesses, minimum wall thickness, emin, of the body or the spigot of a
fitting shall conform to Table 4 BS EN 1401-1:2009, except that a reduction of 5
% resulting from core shifting is permitted. In such a case, the average of two
a. Elastomeric ring seal sockets and spigots Diameters and lengths: - the diameters
and lengths of elastomeric ring seal sockets and spigots shall conform to Table 5
BS EN 1401-1:2009. Different designs of elastomeric ring seal sockets and
spigots are permitted, provided the joints conform to the requirements given in
Table 15 BS EN 1401-1:2009.
b. Wall thicknesses of sockets, the wall thicknesses of sockets, except the socket
mouth, shall conform to Table 6 BS EN 1401-1:2009
c. Dimensions for "O-ring type" sockets, the dimensions of "O-ring type" sockets
with a nominal diameter, shall conform to Table 7 BS EN 1401-1:2009
N. Mechanical Characteristics
O. Physical Characteristics
P. Types of Fittings
a. Bends
b. Couplers and slip couplers
c. Reducers
d. Branches and reducing branches
e. Saddle branches
f. Plugs
Q. Sealing Rings
1. Sealing ring shall have no detrimental effects on the properties of the pipe and
the fitting and shall not cause the test assembly to fail to conform to Table 15
BS EN 1401-1:2009
2. Materials for sealing rings shall conform to EN 681-1 or EN 681-2, as applicable.
R. Adhesives
S. Classification of PIPES:
A. Fine Aggregate
1. The grading of fine aggregate shall be within the limits of Table (5) BS 882.
2. Fine aggregate shall be of such uniformity that the fineness modulus as defined
in AASHTO M6 or (ASTM C125) shall not vary more than 0.20 either way from
the fineness modulus of the representative samples used in the mix design.
3. The sand equivalent for fine aggregate (AASHTO T176) shall be a minimum of
70.
4. The water absorption of fine aggregates (ASTM C128) or (AASHTO T84) shall not
exceed 2 percent.
B. Coarse Aggregate
C. Cement
D. Water
E. Concrete:
F. Concrete Blocks
1. Concrete blocks shall be hard, durable, sound, clean, well defined edges and free
from cracks, flaws or other defects. They shall comply with the requirements of
ASTM C140.
2. All mortar shall consist of one-part masonry cement to three parts loose sand
complying with the following requirements.
a. Sand complying with ASTM C144, grading and coloring suitable for type of
masonry and as approved by the Engineer.
b. Sulphate Resisting Portland Cement shall comply with the requirements of BS
4027 or ASTM C150 type V.
c. Water Complying with water for Concrete Mixes and curing, of the
Specifications Section “Concrete and Reinforced Concrete”
G. Reinforcing
1. General
2. Materials
b. Cast Iron:
c. Steel:
3. Plastics encapsulation
A. All manhole drop connections shall be outside drop. Outside drops shall be
provided with same pipe material as sewer main as indicated in the standard
drawings.
B. Pipes and fittings (Elbow, Tee, and Y connection) shall be provided with same
pipe material as sewer main as indicated in the standard drawings
A. Manholes, Ductile iron kitemarked to BS EN124 solid top circular hinged access
cover and frame , opposite cover parts block at 90, the covers are removable
from the frame horizontally or vertically after removing the metal safety pins.
Circular frame over all flanged with anchoring holes that can be used to fix the
frame.
B. Inspection/Drainage/sedimentation chamber, ductile iron kitemarked to BS
EN124 solid top rectangular access cover and frame, the covers are removable
from the frame horizontally or vertically after removing the metal safety pins.
Rectangular frame over all flanged with anchoring holes that can be used to fix
the frame.
1. Warm applied black bitumen coat (paint) to BS 3416 and special coats for
protecting covers.
2. All covers shall be non-rock preventing noise and vibration.
3. Clear opening dimensions shall be as indicated on drawings.
4. All covers, frames and supporting metal work shall be designed for loading to BS
5400-2.
5. One prying and lifting bar of approved design shall be provided with each 20
covers supplied with a minimum of one for each type of cover.
6. Covers shall be sampled at random by the Engineer and load tested under his
supervision according to BS EN 124 procedures. The sampling and testing rate
shall be 2%.
7. Each cover should be badged with:
e. All castings shall be inspected for defects. Castings with unacceptable defects
shall be rejected.
f. Minor blowholes and surface imperfections shall be filled in and repaired with
approved two component epoxy amine solvent free filler.
g. All castings shall be degreased, grit blasted to SA 2.5, near white metal
condition, primed with a metallic zinc primer and then coated with a black two
PROTECTIVE COATING:
GROUT
1. Non shrink cementations grouts shall meet or exceed the requirements of ASTM
C1107 Grades B or C and CRD-C 621. Grouts shall be Portland cement based,
contain a pre- proportioned blend of selected aggregates and shrinkage
compensating agents and shall require only the addition of water. Non shrink
cementations grouts shall not contain expansive cement or metallic particles.
The grouts shall exhibit no shrinkage when tested in conformity with ASTM
C827.
GRP PRODUCTS
A. Raw Materials
2. Materials used in the manufacture of GRP products shall be new stock and of
the best quality.
3. Materials shall be free from all defects and imperfections that might affect the
performance of the finished product.
4. Resins shall comply with the relevant provisions of BS 3532 Type B, unless
otherwise approved by the Engineer. Vinylester resins shall have an elongation
at break of 3 to 6%.
5. Glass shall comply with the relevant provisions of the following standards unless
otherwise approved by the Engineer. Surface tissues shall also comply with one
of the following standards:
6. All glass shall be ECR or other corrosion resistant glass, unless otherwise
approved by the Engineer.
7. Roving size shall not exceed 2400 Tex.
8. Chopped strand mat shall not exceed 450g/m².
9. Sand aggregate used for non-slip surfaces shall be a clean graded silica sand,
nominal size 3mm.
10. General properties of GRP products shall be as follows: -
11. The frequency of testing of GRP products for dimensional accuracy, the
properties given above and the load and deformation criteria given below shall
be as agreed with the Engineer.
12. GRP products exposed to a sewage environment shall be corrosion resistant to
raw sewage and associated gases.
13. GRP products exposed to weather shall contain an ultraviolet inhibitor and shall
additionally receive a 500 microns’ thick gel coat to shield the exposed surface
from ultra violet light.
1. The sealing plate thickness shall be a minimum of 7mm and shall be designed to
support a minimum load of 7.5kN/m².
2. The sealing plate shall be manufactured from the required number of layers of
chopped strand mat 450g/m², “Advantex” powder bound corrosion resistance
or equivalent approved, impregnated with isophthalic or vinylester resin of
approved type. Resin to glass ratio shall be 75% to 25% by weight with a
tolerance of ± 5%. Fillers and aggregates shall not be used. The underside of the
plate shall be protected with a resin rich vinylester liner 1.5mm thick reinforced
with one layer of “C” glass tissue and two layers of chopped strand mat
300g/m².
3. The sealing plate shall be in the form of a plug with a flange to prevent the plate
dropping through the access opening.
4. The sealing plate shall incorporate a peripheral retained rubber ring such that
when the cover is closed a gas tight seal is formed. The rubber ring shall be
made from nitrile rubber, EPDM formulation, in compliance with BS EN 681 and
with joints vulcanised and not glued.
5. The plate shall be designed such that a gas tight seal is obtained without the use
of bolts.
6. The sealing plates shall have two securely laminated GRP lifting handles.
7. Cuts and/or drilled faces shall be sealed with resin only.
8. GRP sealing plates shall be seated on the lips of the frames without causing any
reduction to the dimensions of the specified openings
1. GRP ladders shall be of an approved pattern, dimension and duty to suit the
location and shall be installed as shown on the drawings.
2. GRP ladders shall be hand laminated mouldings composed of seven layers of
chopped strand mat 450g/m² and one layer of glass surface veil 30g/m,
“Advantex” powder bound corrosion resistance or equivalent approved,
impregnated with vinylester resin of approved type. Resin to glass ratio shall be
75% to 25% by weight with a tolerance of ± 5%. Fillers and aggregates shall not
be used.
3. Hardwood stiffeners are to be provided inside both the rungs and the rails as a
former, and shall be fully encased in the GRP laminate which shall have a
minimum thickness of 5mm and there shall be no sharp edges.
4. The structural components shall possess Class I fire retardance, with an ASTM
E84 maximum flame spread rating of 25.
5. Fixing brackets shall be GRP integrally moulded into the ladder laminations and
they shall be not more than 500mm apart. The fixing brackets shall be designed
to be anchored securely in concrete having a roughened surface to provide a
good bond and shall project a minimum of 100mm into the concrete.
6. The rungs shall be 250mm apart with the upper faces finished to a non-slip
surface.
7. Intermediate landing shall be provided where the rise exceeds 6m.
8. Nuts and bolts shall not be used either in the construction, assembly or fixing of
the ladder.
9. Each rung shall be able to withstand a point load of 5000N when applied at the
center of the rung and when applied close to one end.
10. When supported horizontally over a span of 1m with the climbing face
uppermost and with a load of 1000N applied at the center of the span there
shall not be a deflection greater than 10mm at the point of application of the
load and there shall be no permanent deformation after removal of the load.
The loads shall remain in place for 24hours after which the ladder shall be
inspected for defects.
11. Each ladder fixing shall be capable of withstanding shear and pullout loads of
5000N.
12. GRP safety cages shall be as shown on the drawings and shall be manufactured
in the same manner as GRP ladders but without the hardwood core.
13. Safety cages shall be provided where the distance between the ladder landings
exceeds 4.5m.
14. Safety cages shall be constructed of three flat vertical members supported by
flat hoops with diameter of 750mm. The hoops shall be at a maximum of
700mm centers and the first hoop shall be 2.4m above ground or platform level.
15. Each hoop shall be able to withstand a tangential point load of 740N and a
vertical point load of 1200N applied at any point on the hoop. The maximum
allowable deflection at the point of application of the load shall not exceed
25mm and there shall be no permanent deformation of the hoops after removal
of the load after 24 hrs.
E. GRP Liners
F. GRAB Handles
1. Grab handles shall be constructed from 20mm diameter formed mild steel bars
and coated with a vinylester resin rich GRP laminate. Handles shall have 150mm
x 150mm square openings in their final position.
STEEL PRODUCTS
A. Material
1. Steel, hand railing, ladders, stairs and flooring shall comply with the following:
1) Threads BS 1387
2) Hot rolled sections BS 4: Part 1 Hot
3. Aluminum, hand railing, ladders, stairs and flooring shall comply with the
following:
a. Bolts, nuts, screws, washers and rivets, shall comply with the and following:
2) ISO metric black cup and countersunk head bolts and BS 4933
screws with hexagon nuts
b. The length of bolts shall be such that the threaded portion of each bolt projects
through the nut by at least one thread and by not more than four threads.
c. Rag, indented bolts, expansion bolts and resin bonded bolts shall be of a
proprietary type approved by the Engineer and shall be capable of withstanding
the design working load.
d. Hot dip galvanized bolts, nuts, screws, washers and rivets shall be used with hot
dip galvanized hand railing, ladders, stairs and flooring. Aluminum bolts, nuts,
screws, washers and rivets shall be used with aluminum hand railing, ladders,
stairs and flooring. Stainless steel bolts, nuts, screws, washers and rivets shall be
used with other types of hand railing, ladders, stairs and flooring. Bolts, nuts,
screws and washers shall be insulated from aluminum by non-metallic washers
and sleeves.
e. The length of bolts shall be such that the threaded portion of each bolt projects
through the nut by at least one thread and by not more than four threads.
B. Designed by Contractor
1. General
a. Steelwork for hand railing, ladders, stairs and flooring shall be fabricated in
accordance with BS 5950: Part 2.
2. Galvanizing to steel
a. All steel that is to be galvanized shall be hot dip galvanized in accordance with
BS EN ISO 1461:1999.
b. Galvanizing to steel shall be applied after welding, drilling and cutting are
complete.
3. Welding steel
a. Welds to steel for hand railing, ladders, stairs and flooring shall be full depth
fillet welds. The welded surface shall be clean and flush before application of
the protective coating.
b. Steel shall not be welded after hot dip galvanizing unless permitted by the
Engineer and if permitted, the welded areas shall be free from scale and slag
and shall be treated with appropriate coating system approved by the Engineer,
which is compatible with the protective system of the parent material.
4. Fabrication
a. Hand railing
b. ladders
c. Stairs
d. Flooring
1) The shape of each panel of flooring shall be such that the panel can be easily
removed. The mass of each panel shall not exceed 40 kg. Where intermediate
supports are provided to support flooring they shall be capable of being
removed to provide the specified clear opening.
2) Curbs shall be provided in concrete surfaces for flooring.
3) Cut-outs in flooring shall be neatly shaped and shall be provided with toe plates.
Cut-outs in open mesh flooring shall be trimmed with edge bars welded to the
bearing bars. The clearance between the edge of cut-outs and the component
passing through the cut-out shall not exceed 30 mm.
4) The bearing bars in open mesh flooring shall be welded to the nosing bars. The
transverse bars shall be riveted or welded to the bearing bars. Panels of open
mesh flooring shall be secured with adjustable fixing clips.
5) Chequer plate flooring shall have a non-slip pattern of a type approved by the
Engineer and shall be provided with lifting holes. The flooring shall be secured to
curbs by countersunk screws.
e. Toe plates
1) Toe plates shall be fixed to handrail standards by brackets and shall be bolted or
welded to stairs and flooring.
f. Safety Chains
1) Pipes over DN600mm should be provided with safety chains for placing at the
mouth of the outgoing sewer, BS EN 752-3:1997
2) Safety chains shall comply with BS 4942 and shall be capable of withstanding a
breaking force of 30 kN and a proof force of 15 kN.
3) Steel safety chains shall be 8 mm nominal size, Grade M4 non-calibrated chain
Type 1 and shall be hot-dip galvanized.
4) The links of stainless steel safety chains shall be welded and shall have an
internal length exceeding 45 mm and an internal width of between 12 mm and
18 mm. Fins caused by welding shall be removed.
5) Hot dip galvanized hooks on chains shall be fitted with a sprung securing device.
PART 3 EXECUTION
A. The Employer may employ the services of a specialist firm to assist the Engineer
A. Where designated in the Project Specification, the Contractor shall carry out a
soil corrosivity study along the route of proposed ferrous pipelines as directed
by the Engineer and mark the results on the pipeline layout plans.
B. Soil resistivities shall be undertaken using a low resistance, null -balance earth
tester and a four pin array, or any other equipment approved by the Engineer.
Readings shall be recorded in ohm-cm and shall be taken at 1.0 m incremental
depths to a depth 1 m below the pipeline invert levels. Readings shall be taken
at a spacing along the route of the proposed pipelines as required to reflect the
changing soil conditions, but in no case shall the spacing exceed 500 m.
C. Soil samples shall be taken as directed by the Engineer along the route of the
proposed pipelines at a maximum spacing of 500 m. Soil samples shall be
tested for sulphates, sulphides, chlorides, pH, moisture content, and
carbonates.
3.3 EARTH WORK
EXCAVATION
A. General
1. The requirements of “Earthwork” Section shall be applied, except as otherwise
specified in this Clause.
2. The trenches shall be excavated to the required line and level as shown on the
drawings or as approved by ENGINEER, and shall, at all times, be drained and
braced to ensure safe and efficient pipe laying. In locations where services,
ruins, or other structures are near the pipeline route, only hand excavation will
be permitted.
E. Support of Trenches
1. Fix timbering, steel sheeting, shuttering and sheet piling for the support of
excavation in accordance with BS 6031 taking into account the nature of the
ground to be excavated, the level of water table at the site and the proximity of
buildings and roads.
2. Where the depth of trenches exceeds 1.2m do the following.
3. Do not remove temporary works supporting the excavations until in the opinion
of the Engineer the permanent work is sufficiently advanced to permit such
removal. Execute removal of temporary works under the personal supervision
of a competent foreman. Any advice, permission, acceptance or instruction
given by the Engineer relative to such support or its removal will not relieve the
Contractor from his responsibilities under the Contract.
4. Remove all temporary works supporting the trenches during backfilling, unless
previous acceptance has been obtained from the Engineer.
BACKFILLING
A. Backfill trenches to contours and elevations with fill materials as specified in this
specification and accepted by the Engineer.
B. In the case of trenches other than in roads and tiled/paved areas backfill the
trench excavation with approved material in layers not exceeding 250mm to
obtain minimum 90% compaction of the relevant maximum dry density of the
material in accordance with BS 1377 Part 9.
C. Backfill trenches in roads and paved/tiled areas, including areas designated as
future roads and paved/tiled areas as directed by the Engineer, in accordance
with the Abu Dhabi Municipality specification for backfilling of trenches and
excavations in asphalt roads, tiled/paved parking areas and sidewalks.
D. Employ a placement method that does not disturb or damage foundation
perimeter drainage and utilities in trench.
E. Maintain optimum moisture content of fill materials to attain required
compaction density.
F. Where concrete slab protection to pipelines is required extend such protection
to a minimum of 200mm onto undisturbed ground on either side of the pipe
trench to the details shown on the drawings. Place a compressible layer of
expanded polystyrene of width equal to the diameter of the pipe directly above
the pipe and immediately below the slab for the full length of the pipe. Take
care that the compressible layer is not disturbed when the slab is placed.
G. Remove surplus fill materials from site.
H. Leave fill material stockpile areas completely free of excess fill materials.
I. The finished level shall be within plus or minus 25mm of the specified level.
J. All trenches shall be marked with a high quality acid and alkali - resistant red
non bio-degradable plastic tape with a minimum width of 150 mm placed during
backfilling 300 mm below finished surface or as directed by the Engineer.
K. All tapes shall be clearly marked in black lettering with “SEWAGE WATER” All
non-ferrous pipelines shall have marker tape with tracer wire.
A. Upon completion of the work of this section, all rubbish debris and excess or
waste material shall be removed from the site.
B. All areas subject to vehicular traffic during construction shall be reinstated to
their original condition.
3.4 PIPE LAYING
STRINGING OF PIPES
A. Inspect all pipe and fittings prior to lowering into trench to ensure no cracked,
broken or otherwise defective materials are being used. Clean ends of pipe
thoroughly. Remove foreign matter and dirt from inside of pipe and keep clean
A. Pipes and fittings including any sheathing, shall be inspected by the Contractor
immediately before and after installation, and damage or other imperfection
shall be repaired by the Contractor as directed by the Engineer before
installation and in accordance with the following:
1. Without relieving the Contractor of any of his obligations, the Engineer may
inspect and test the pipe and appurtenances by any appropriate means, and
damage discovered by such inspection shall be repaired by the Contractor
2. The Contractor shall remove from Site any pipe or appurtenance which in the
opinion of the Engineer is so damaged as to be unfit for incorporation in the
Works. The obtaining of replacements for damaged pipes and fittings to the
approval of the Engineer shall be an obligation of the Contractor.
A. General
1. All operations involving the laying, bedding, jointing, backfilling etc. of pipes of
plastic materials shall be strictly in accordance with the manufacturer’s
recommendations subject to the approval of the Engineer.
2. The pipes shall be laid and bedded in granular bedding material except where
concrete bedding or protection is required. The granular material shall extend
from not less than l50 millimeters beneath the pipes to l50 millimeters above
the crown of the pipes or as approved by the Engineer. Subsequent filling of the
pipe trench shall be carried out as detailed in this Section of the Specification.
3. Except as otherwise specified in this Clause, pipe bedding shall conform to the
requirements specified in EARTHWORK sections. The Contractor shall, after
excavating the trench and preparing the proper bedding, furnish all necessary
facilities for properly lowering and placing sections of the pipe in the trench
without damage and shall properly install the pipe.
4. Each pipe shall be carefully lowered onto its prepared bed by means of
appropriate slings and tackle. A recess shall be left in the prepared bed to
permit the sling to be withdrawn. If the prepared bed is damaged, the pipe shall
be raised and the bed made good before pipe laying is continued.
5. No pipe shall be rolled into place for lowering into the trench except over
suitable timber planking free from roughness likely to damage any coatings.
6. The section of pipe shall be fitted together correctly and shall be laid true to line
and grade in accordance with the bench marks established by the Contractor.
The bench marks shall be approved by the Engineer.
7. The full length of the barrel of the pipe shall have a uniform bearing upon the
bedding material and if the pipe has a projecting socket, suitable excavation
shall be made to receive the socket which shall not bear on the subgrade.
B. Joints
1. Push fit Joints
a. Immediately before assembling each joint incorporating a rubber ring seal, the
rubber shall be inspected for cracks, every part of the ring being deformed by
hand to about l50 mm radius. If under this deformation any cracks are either
revealed or initiated the ring shall be rejected, cut through completely to
prevent inadvertent use, and the matter reported forthwith to the Engineer. If
more than three successive rings inspected in this way are rejected the
2. Mechanical Joints
a. For the purpose of reducing the angular deflections at pipe joints, and for
closure sections, the Contractor will be permitted to install pipe sections of less
than standard length. Closing lengths and short sections of pipes of all types
shall be fabricated and installed by the Contractor as found necessary at Site.
Where closing pieces are required, the Contractor shall make all necessary
measurements and shall be responsible for the correctness thereof. The
Contractor shall be responsible for taking the measurements required to
determine the lengths of cut portions of pipes for insertion as closing lengths in
pipelines.
C. Cutting of Pipes
1. Where pipes are required to be cut on the Site the cutting shall be done by the
Contractor in accordance with the manufacturer’s recommendations and in a
manner approved by the Engineer.
2. The pipe and methods of jointing shall be such that the locations of fittings and
lengths of pipe can be adjusted to suit Site conditions.
3. Cutting of reinforced concrete pipes will not be allowed. Special lengths of
pipes shall be manufactured for closures as required. Other pipes such as GRP,
ductile iron and cast iron pipes shall only be cut if approved by the Engineer.
4. The cutting of ductile iron pipes for inserting specials, fittings or closure pieces
shall be carried out as follows:
A. General
1. All pipe and fittings shall be thoroughly cleaned before laying, shall be kept
clean until they are used in the work, and when laid, shall conform to the lines
and grades required. PVC pipe and fittings shall be installed in accordance with
requirements of the manufacturer except as otherwise provided herein. As
soon as the excavation is complete to normal grade of the bottom of the
trench, sand shall be placed as shown on the drawings, compacted and graded
to provide firm, uniform and continuous support for the pipe. Bell holes shall
be excavated so that only the barrel of the pipe bears upon the bedding. The
pipe shall be laid accurately to the lines and grades indicated on the Drawings.
Blocking under the pipe will not be permitted. Sand shall be placed evenly on
each side of the pipe to mid-diameter and hand tools shall be used to force the
sand bedding material under the haunches of the pipe and into the bell holes to
give firm continuous support for the pipe. Sand shall then be placed to 300
mm above the top of the pipe. The initial 900 mm of backfill above the
bedding material shall be placed in 300 mm layers and carefully compacted.
Generally, the compaction shall be done evenly on each side of the pipe and
compaction equipment shall not be operated directly over the pipe until
sufficient backfill has been placed to ensure that such compaction equipment
will not have a damaging effect on the pipe. Equipment used in compacting the
initial 900mm of backfill shall be approved by the pipe manufacturer's
representative prior to use.
2. All pipes shall be sound and clean before laying. When laying is not in progress,
including lunchtime, the open ends of the pipe shall be closed by watertight
plug or other approved means. Good alignment shall be preserved in laying.
The deflection at joints shall not exceed that recommended by manufacturer.
3. When cutting pipe is required, the cutting shall be done by machine, leaving a
smooth cut at right angles to the axis of the pipe. Cut ends of pipe to be used
with a bell shall be beveled to conform to the manufactured spigot end.
4. The Contractor shall construct anchor and thrust blocks at every bend and
junction on pressure pipelines and where otherwise shown on the Contract
Drawings or instructed by the Engineer. Each thrust block shall to have a
sufficient bearing area and shall be placed to safely transmit thrust to the
surrounding original ground. If soft, spongy, unstable or similar material is
encountered upon which the thrust block is to bear this unsuitable material
shall be removed and replaced with Grade 20 SRC mass concrete as directed by
1. The joint is engineered to provide problem-free service for the life of the pipe,
but proper procedures must be followed to ensure its effectiveness:
a. Clean the gasket area. Remove sand, dirt, grease, and debris. Do not remove
gaskets from bells, removal could cause improper reinstallation.
b. Check the gasket. Make sure the gasket is seated uniformly in the groove by
running your finger around the inner edge of the gasket.
c. Clean the spigot. Use a rag to wipe the spigot clean.
d. Lower the pipe into the trench. Lower carefully to avoid getting dirt into the
bell or spigot.
e. Lubricate. Apply lubricant to the bevel of the spigot end and approximately
midway back to the stop line. A thin layer of lubricant may be applied to the
face of the gasket, but be careful not to get lubricant behind or under the
gasket.
f. Keep lubricated areas clean. If dirt or sand adhere to lubricated areas, clean
and re-lubricate.
g. Assemble pipe. Insert the spigot end into the bell until it contacts the gasket
uniformly. Straight alignment is essential for ease of assembly. Apply steady
pressure by hand or by mechanical means (bar and block, come along,
hydraulic jack) until the spigot slips through the gasket. Insert the pipe until the
stop line is flush with the bell end. For some job conditions and sizes of pipe,
use of heavy equipment (such as a backhoe bucket) may be necessary for
assembling the pipe. When this equipment is used, extra care must be taken
because the installer loses the “feel” of the assembly. Conditions such as
improper spigot alignment, rolled gaskets, or over insertion (over belling) could
go unnoticed during assembly because of the large force generated by the
equipment.
a. Position the spigot carefully in the bell to ensure straight alignment both
horizontally and vertically.
b. Exercise caution to prevent damage of the bell lip due to rough contact by the
equipment.
c. Be careful that the action of the equipment does not move the pipe out of
f. If the pipe must be field-cut, mark the entire circumference of the pipe to
ensure a square cut. The pipe can be cut with a hacksaw, handsaw, or portable
power saw with a steel blade or abrasive disc.
g. Bevel the cut end using a pipe beveling tool or a portable sander or abrasive
disc. Round off any sharp edges on the leading edge of the bevel with a pocket
knife or a file. Mark cut end with an insertion line similar to uncut pipe.
h. Bevel requirements may vary with different joint types:
1) Joint Bevel
2) PVC pipe Bell Same as factory bevel
3) PVC push-on fitting Same as factory bevel
4) Other pipe bell/push on fitting Shorter bevel length
5) Mechanical joint fitting No bevel
A. Warning tapes shall be laid above all utility pipes. Tapes shall be durable and
detectable by electro-magnetic means using low output generator equipment.
They shall remain legible and color fast in all soil conditions at pH values of 2.5
to 11.0 inclusive.
B. Warning tapes shall be placed in compacted backfill material, approximately
300 mm below finish grade and as indicated on drawings.
C. The tapes shall be flexible and subject to the Engineer’s approval. Width of the
tape shall be at least 6” (150 mm).
D. Tapes shall have different colors for different utilities and with black text in
Arabic and English as “CAUTION WATER PRESSURE MAIN BELOW” for water
mains, etc. The text on the tape shall be permanent ink bounded to resist
prolonged chemical attack by corrosive acids and alkaline with message
repeated at a maximum interval of two (2) meters.
A. General
1. The Contractor shall submit for the Engineer’s approval details of his proposed
methods and program for testing (including details of test equipment) and shall
arrange for all test to be witnessed by the Engineer or other person appointed
by the Engineer. Test equipment shall be approved by the Engineer and
calibration certificates when requested by the Engineer shall be submitted.
The Contractor shall provide all equipment necessary for carrying out testing
B. Inspection of Sewers:
1. Inspect and obtain the Resident Engineer's approval. Thoroughly flush out
before inspection. Lamp test between structures and show full bore indicating
sewer is true to line and grade. Lip at joints on the inside of gravity sewer lines
is not acceptable.
C. Television Inspection:
1. The video inspection shall be conducted and paid for by the contractor. The
Contractor shall video inspect all sections of lines from manhole to manhole or
other structures. Video inspection shall not be done until the pipe is laid and
has passed the required leakage test and deflection test.
2. Preparation for Video Inspection: After cleaning of the line and just prior to
performing the video inspection, water will be introduced in the upstream
manhole until observed at the most downstream manhole to be videoed. This
shall ensure that any area where ponding is possible will be filled with water.
a. The video cameras and video cassette's recorder shall record VHS format in
color. Lighting and camera quality shall be suitable to allow a clear, in-focus
picture for the entire inside periphery of pipelines. To ensure peak picture
quality throughout all conditions encountered during the survey, a variable
intensity control of the camera lights shall be located at a studio. The replay of
the recorded video information shall be free of electrical interference and shall
provide a clear stable image.
b. The camera monitor shall be located within a studio which will allow seating of
two authorized viewing personnel in addition to the operating technician.
Simultaneously displayed on the monitor as part of the video presentation shall
be a continuous forward readout of the camera distance from the start of each
4. Operations:
a. The operating technician shall have control of the movement of the television
camera at all times. The travel speed of the camera shall be variable but
uniform, and shall not exceed 45 feet per minute while viewing. Any means of
propelling the camera through the sewer lines which would produce
nonuniform or jerky movements will not be acceptable. The television system
shall be capable of doing increments of 900 feet (274 m) with one setup. As
directed by the Engineer, the camera shall be stopped to view and analyze
conditions that appear unusual or uncommon. The operating technicians shall
at all times be able to move the camera through the lines in either direction
without the loss of quality in the video presentation on the monitor.
b. Footage shall appear on the screen as well as the picture of the interior of the
pipe and shall become a part of the video cassette record.
5. Inspection Records:
a. In addition to the video cassette tape, a certified inspection report detailing the
physical condition of each of the sewer mains scheduled for inspection shall be
submitted to the Engineer. Each main shall be reported individually providing
the following information:
1) The log shall contain the project name, inspector's name, date of inspection,
client's name, pipe size, type of pipe, and tape footage reference number.
2) Location of sewer main - the street name where the main is located together
with the upstream and downstream cross streets, where applicable.
3) The direction of flow and the direction of the camera shall be indicated as well
as the section length.
4) Reach shall be defined by the manhole and cleanout numbers and line
designations which appear on the drawings and in the below stated lines to be
cleaned and televised.
5) Defective or abnormal segments of each reach shall be defined by the beginning
and end stations when stationing is used, or footage from the center of the
manhole immediately upstream of any particular reach if reach is defined by
code numbers. The type of defect or abnormality shall be accurately described
indicating the degree of severity using a systematic rating system. Infiltrations,
6. Acceptance:
a. Any of the following observations shall be considered defects that will require
corrections prior to acceptance.
1) Ponding greater than 10 percent of the nominal pipe inside diameter or over 25
feet in length will be cause for rejection of the pipe segment.
2) Joint separations - over 3/4 inch (18 mm).
3) Offset joints.
4) Chips in pipe ends - none more than 1/4 inch (6 mm) deep;
5) Cracked or damaged pipe or evidence of the presence of an external object
bearing upon the pipe (rocks, roots, etc.).
6) Infiltration.
7) Debris or other foreign objects.
8) Other obvious deficiencies when compared to Approved Plans and
Specifications and Standard Drawings.
D. Air Test:
1. The Contractor shall plug all pipe outlets with suitable plugs, and brace each
plug securely where needed
2. Air shall be pumped in slowly to the pipe until a pressure of 100 mm water
gauge is indicated on a manometer connected to the system. After the internal
pressure of 100 mm water gauge is obtained, 5 min shall be allowed for the air
temperature to stabilize within the pipe
3. Air may be added to restore the pressure to 100 mm water gauge. During a
further period of 5 min, the pressure shall not fall below 75 mm water gauge
without further pumping.
E. Water Test:
1. All the joints of the pipeline shall be able to withstand a pressure of a minimum
5 m head of water, above the crown of pipe at the highest point of pipeline
without leakage. A layer of embedding soil equal to the diameter of pipe shall
be laid over the pipe to prevent the lifting of pipe while applying test pressure.
However, all the joints shall be left open for the purpose of inspection for
leakage if any. All branches and open ends shall be closed with stoppers,
secured with longitudinal braces/ thrust block, before testing begins
F. Infiltration Test:
1. The upper ends of the sewer and service connections shall be closed
sufficiently to prevent the entry of water and pumping of groundwater shall be
discontinued until the groundwater surface reaches its natural level before
beginning the infiltration test
2. The dewatering system shall be stopped, but not be removed until the
infiltration test has been successfully completed or as otherwise permitted by
the Engineer
3. The infiltration shall not exceed 6 liters per millimeter diameter per kilo meter
per day of the portion of sewer being tested, including the length of service
connection entering that section
4. The total length tested in one section shall not exceed 400 m in length. This
length is dependent upon the type of deflection measuring equipment
proposed by the Contractor if flexible pipes are used
5. No gravity pipeline will be accepted if the total infiltration exceeds the above
mentioned limit and joints will not be accepted if during an internal inspection,
any infiltration is visible.
GENERAL
A. The Employer may employ the services of a specialist firm to assist the Engineer
as he may require in any matter concerning Drainage Structure including the
inspection of materials and workmanship and the witnessing of tests at any
stage during the execution and maintenance of the Works.
B. Such independent tests may be carried out at any stage during the execution
and maintenance of the Works, but they shall not relieve the Contractor of his
obligations under the Contract.
C. To the extent ordered by the Engineer, the Contractor shall provide labour,
plant, tools and materials (but not special testing equipment) for direct
assistance to the specialist firm in their inspection and independent testing and
for any further work, investigations, and repairs which the Engineer considers
necessary as a result of such inspection or testing.
D. The provision of labour, plant and materials as aforesaid shall be an obligation
of the Contractor where in the Engineer’s opinion the inspection test or further
investigation shows that materials and workmanship provided by the Contractor
do not comply with the designated requirements.
DRAINAGE STRUCTURE
CAST IN SITU
a. Select Drop Bowl of size appropriate to flow rate and pipe diameter, a pipe
downsize is possible in most applications.
b. Trim incoming pipe so that only 2" maximum protrudes into manhole, for
improved flow control, cut a "V" shaped notch at bottom edge of incoming pipe.
c. Center Drop Bowl directly under incoming pipe, allow approximately 1"
clearance between pipe and bowl.
d. Attach Drop Bowl to manhole wall with 3/8" diameter stainless steel anchors
(between 4 & 6 expansion anchors) / or (3” Wedge Anchors) according to
manufacture installation instruction.
e. Cut and mount PVC drop pipe of diameter appropriate to Drop Bowl size and
flow, using RELINER adjustable stainless steel clamping brackets. Use a
minimum of 2 brackets with a maximum spacing of 4 feet (RELINER clamping
brackets will adjust to allow drop pipe to maintain correct stand off from wall).
e. Attach the vent pipe adapter in the pre-drilled hole in the top of the SNOUT
using the 2 flat O-ring gaskets and PVC lock-nut supplied in the kit. Install with
female slip adapter up and a washer on each side of the SNOUT shell. Tighten
lock-nut hand tight.
f. Remove backing and with firm pressure, attach gasket strip(s) to back of flange
and trim excess.
g. Attach the SNOUT to the catch basin wall with 3/8" diameter stainless steel
bolts in lead expansion anchors. Do not over tighten; 10-15 foot-pounds should
be sufficient.
h. Cut the anti-siphon vent stack to length and attach to hood at slip adapter with
PVC cement.
i. Attach 90 degree fitting to vent stack with PVC cement. Ensure that fitting
opening is accessible for maintenance and inspection.
A. Benching and channels shall be made to conform accurately to the pipe grades
and openings, and shall be brought together smoothly and in alignment with the
pipe at the ends of curved benching’s, with well-rounded junctions, thoroughly
clean the walls and base slab and apply a bonding agent prior to pouring
concrete of benching. Main drain channel shall be formed of Class C 30
reinforced concrete benching at inverts designated on Drawings at bottom of
manholes. Top surface of benching shall get 12 mm thick corrosion resistant
screed with non-skid finish and shall be given steep slopes towards the drain
channel. Remove all sharp edges or rough sections, which tend to obstruct flow
1. When both the incoming and outgoing pipes are the same diameter, set the top
of bench at same as the top of pipe.
2. When the incoming and outgoing pipes have different diameters, set the top of
bench at the top of pipe elevation of the highest pipe within the manhole,
except when a manhole drop connection is designed. When a Sewer Service
(House) Connection SHC entering the manhole is significantly higher than the
mainline sewer, the bench on the side where the SHC enters may be elevated,
and the bench on the opposite side may match the top of the mainline sewer
for more convenient access.
3. If the HGL in the manhole is higher than the top of pipe within the manhole, set
the top of the bench at an elevation of 3-inch above the HGL.
4. If the top of bench needs to be higher than the incoming or outgoing pipes, the
top of bench elevation must be shown at the manhole on the profile.
A. The backdrop lower connection to manhole shall be fixed and cast along with
the manhole base.
B. While casting manhole shaft, a plywood box frame shall be fixed at the
backdrop upper connection level.
C. Backdrop construction shall start after finishing shaft construction; as per the
following steps:
D. An opening in the shaft liner, with a size as per backdrop pipe size shall be
prepared at the backdrop higher connection point.
E. The backdrop pipe shall be fixed and connected, by lamination.
F. Due to practicality, back drop concrete is done after shaft.
G. Shutter shall be fixed around the pipe as per the required size and concrete will
A. General
1. Chamber covers shall be ductile iron and comply with EN 124. Production
facilities shall be quality assessed in accordance with ISO 9000 or EN 29002 BS
5750).
2. The Contractor shall supply one pair of manhole keys or prying and lifting bar, as
appropriate with each 30 covers provided with a minimum of one tool for each
type cover. Keys and prying and lifting bars shall be of approved appropriate
design to match the different cover configurations. Keyways in chamber covers
shall be of the closed type.
3. Install frames and covers on top of drainage structure to positively prevent all
infiltration of surface or ground water into manholes. Frames shall be set in a
bed of mortar with the mortar carried over the flange of the ring. Set frames so
tops of covers are flush with surface of adjoining finish pavement surface.
Elsewhere set 50 mm above ground surface, unless otherwise shown or
directed.
4. The covers in paved areas shall be accurately set on precast concrete brickwork
to the level and slopes of the roads or pavements, to adjust cover level as
required.
5. The covers in landscape area areas shall be accurately set on precast concrete
brickwork to the level above the landscape by at least 100 mm above the
landscape level.
B. Installation
1. Ensure the Clear Area of the access cover or gully grating frame component is
the same or larger than the chamber top opening but does not result in any
cover or grating support ribs fouling on the chamber top. An exception may be
made when;
j. Proprietary Packing Pieces can be stacked to form a suitable Clear Area opening
within the overall depth available and/or
k. where the product’s cover-to-frame seating positions are located well-away
from the frame Clear Area opening and sit over the intended chamber wall, slab
or proprietary Packing arrangement.
2. Where available, ensure an area 50mm (min) greater than the frame size around
the chamber top opening is clean, dry and clear of any loose debris, but not
smooth, if this area is not already of sufficient surface texture to mechanically
‘key’ with the foundation mortar; abrade the surface locally, to achieve this aim.
A. Steps shall be cast into the walls of base, risers and conical top sections, and
shall be aligned vertically and spaced so as to be on equal centers in the
assembled manhole at a maximum distance apart of 12 inches (305 mm). Steps
shall be located a minimum of 6 inches (152 mm) from the ends of base, riser,
and top sections, and shall be securely embedded in manhole sections by
mortar or cast in place polypropylene inserts.
BACKFILLING
A. Visual Inspection
1. All work constructed will be subject to visual inspection for faults, defects, or
deviations from the Plans and any such deviation or omission will be corrected
at once. All tests will be made by the Contractor who will provide necessary
equipment for testing and lamping the manhole or structure in the presence of
and under the supervision and instructions of the Engineer. Lamp tests will be
observed first hand by the Engineer. All defects found will be corrected before
conducting leakage tests. Repair methods must be approved by the Engineer.
B. Leakage Testing
1. Temporary Plugs: Temporary plugs for testing shall consist of a watertight plug
and timber bulkhead or may be a steel plug at the contractor option.
Temporary plugs shall be removable without damage to pipe stub outs and shall
be capable of withstanding all internal pressures, external loads and external
pressures without leakage.
2. All drainage structure shall be visually inspected for leakage during hydrostatic
tests and before the backfilling of the chamber is complete. Any leakage of
water through the drainage structure walls or joints shall be caused for the
chamber to be rejected and replaced or repaired to the Engineer’s satisfaction.
3. To test the drainage structure hydrostatically the Contractor shall fill the
chamber with water after plugging, to the bottom of the frame.
4. After 6 hours the water shall be again brought to the bottom of the frame. The
quantity of refilled water shall be measured and considered to be the leakage.
C. Vacuum Testing:
1. All drainage structure shall be subjected to a vacuum test. The Contractor will
furnish all necessary equipment and labor needed for conducting the tests.
2. The Contractor shall have the option to test drainage structure prior to
backfilling. Preparation and testing of manholes shall be as follows:
SPECIFICATION REV.
ECG ENGINEERING CONSULTANTS GROUP S.A. OVERHEAD TRAVELING CRANE SYSTEM
CAIRO - EGYPT 412215.10 - 2874 0
SECTION 412215.10
Page
PART 1 GENERAL 2
1.1 Related Documents 2
1.2 Summary 2
1.3 Quality Assurance 2
1.4 Submittals 2
1.5 Quality Assurance 3
1.6 Coordination 3
1.7 Warranty 3
PART 2 PRODUCTS 3
2.1 General 3
2.2 Constituents Of The Overhead Crane 4
2.3 Materials 5
2.4 Technical Specification 5
PART 3 EXECUTION 5
3.1 Installation 5
3.2 Field Quality Control 6
3.3 Unauthorized Use By Contractor 6
PART 1 GENERAL
1.2 SUMMARY
A Reference Standards: All materials used in the work shall be performed in strict
accordance with specifications, drawings and the general equipment stipulations of
the international standards as noted herein below:
NFPA
National Fire Protection Association Standards NFPA 70
1.4 SUBMITTALS
A Product Data: Submit product data for the crane unit, sizes, performances,
operations, safety features, controls, finishes and similar information according to
indicated capacity. Indicate any variations from specified requirements.
B Shop Drawings: Submit shop drawings including dimensioned drawings for the
cranes, showing plans, elevations, sections and large-scale details indicating
fabricated steel girders coordination with building structure and relationship with
other constructions, activities, indicate any variations from specified requirements
A Provide certification that manufacturer and installer are regularly engaged in the
production and erection of components and equipment of this type and whose
equipment have been satisfactorily used in similar service for not less than 5 years.
1.6 COORDINATION
A Contractor shall furnish inserts and anchorages which must be built into other work
for installation of Overhead Traveling Crane’s and related work; coordinate delivery
with other work to avoid delay.
B All equipment and accessories furnished and installed under this section shall be
fabricated, assembled, erected and placed in proper operating condition in full
conformity with drawings, specifications, instructions and recommendations of the
equipment manufacturer.
1.7 WARRANTY
PART 2 PRODUCTS
2.1 GENERAL
A Provide motorized operated hoist and trolley and carriage for provided cranes.
B Ball or roller bearings shall be employed, and the load hook shall revolve on a ball
swivel. A load chain collection box shall be incorporated on the crane.
D The hoisting gear shall be such that one man is capable of easily raising the
maximum load. There shall be included for each item of lifting equipment:
F Complete operating and installation include hoist and trolley, carriage fasteners,
inserts, ropes, end stop, cable and track.
B Bridge Crane: double beam bridge crane assembly including bridge girder beams,
track and trolley for hoist support.
1. The bridge shall be double I-beam section or flat flanged type rigidly fixed.
The bridge shall be constructed to accommodate a top running or underhung
hoist and trolley.
C Track: Includes but not limited to rails, inserts, end stops fastenings, etc., required
for construction of the track.
1. Steel design and fabrication shall comply with applicable portions of the
specifications of the American Institute of Steel Construction. Loadings,
impact allowances, and allowable stresses shall be in accordance with the
governing standards. Deflection of the main girder shall not exceed 1/800 of
the span with the maximum load at any point.
D Wheels: Trolley wheels for I-beam section shall be made of rolled, forged, or cast
steel. Trolley side plates shall be cut from hot rolled steel plate and extend past the
wheels to provide bumper protection on all four wheels trolley. Axles shall be
heated treated alloy steel rigidly supported in the trolley side plates. Wheel bearings
shall be permanently shielded, lifetime-lubricated ball or tapered roller type,
antifriction type, adequate for radial and end thrust landing.
E The load chain anchorage associated fittings and framework at the slack end shall be
at least equal in strength to 2.5 times the maximum tension in the load chain when
the working load limit is being lifted. Any links used for connecting the load chain to
a terminal fitting shall be of the material specified for the chain and heat treated to
provide mechanical properties and strength equivalent to those of the load chain.
The hook shall be made from high grade forged steel and provided with a safety
latch. The safe working load shall be marked on the hook in kilograms.
F Longitudinal motions shall be provided on the crane and shall be such that operation
is speedy without impairing safety in working. They shall be operated by means of
hand chains which shall extend to within 600 mm of the operating floor. The
hoisting and lowering chains shall be of the same length. The hook and load chain
shall be such that the hook shall reach to the lowest floor or duct level.
G An extending, portable aluminum ladder shall be provided for access to the crane for
maintenance, etc..
I Bumpers and Stops: Bumpers and stops for the trolley shall meet the requirements
of the governing standards.
2.3 MATERIALS
A Trolley Materials:
1. Hoist capacity (kg), span, hook lifting range as per indicated in drawings.
PART 3 EXECUTION
3.1 INSTALLATION
A Equipment and accessories installed under this section shall be assembled, erected,
and placed in proper operating condition in full conformity with drawings,
specifications, engineering data, instructions, and recommendations of the
equipment manufacturer unless exceptions are noted by the Engineer.
B Beam Hoist: The beam and trolley and hoist shall be erected by workmen regularly
engaged in crane erecting and acceptable to the crane manufacturer. The
orientation of installation of the hoist and trolley on the beam shall be as directed by
the Engineer.
B The Contractor shall make all adjustments to the equipment as directed by the
technical representative.
C Operational Tests: After installation the Contractor shall conduct operational tests as
required to demonstrate that the crane shall operate in accordance with the
requirements of these specifications.
D Prior to acceptance of the crane, the Contractor shall clean and lubricate the
equipment and make all final adjustments necessary to ensure operation
satisfactory.
A Contractor shall not use the Crane provided to install other equipment in the
performance of his work under this contract.