Our Ref: B4239 02 December 2021

STADSIG ESTATE WELLINGTON


AESTHETIC APPROVAL - BUILDING PLAN SUBMISSION PROCEDURE

In accordance with the approved Building Guidelines for the Development, Building Plans for all
dwelling units are to be submitted to the Control Architect (CA) appointed by the Stadsig Estate
Home Owners Association (SEHOA) for aesthetic approval, as per the requirements and
procedures set out under Clause 6: Membership of the Association and Clause 12: Building,
Architectural and Design Requirements of the SEHOA Constitution.

1.0 One (1x) colour electronic copy (PDF) or hardcopy of the building plans must be submitted
to the CA for aesthetic approval prior to Local Authority submission.

2.0 A non-refundable scrutiny fee as set out below will be payable.

3.0 Completed Plan Submission Form (p. 2 & 3) and proof of payment as set out below to be
emailed to den@dmp.co.za BEFORE any plans can be scrutinized.

4.0 Upon receipt of 3.0 the CA will proceed to scrutinize the plans. These plans will be returned
within a period of 10 working days calculated from the Wednesday following the date the
plans have been submitted. The CA will advise on any changes on the design or layout
known in writing to be implemented to obtain aesthetic approval. The comments will be
forwarded to the appointed correspondent by email.

5.0 The plans with changes required (as referred to in 4.0) will have to be re-submitted for scrutiny
to obtain aesthetic approval. No additional fees will be payable should only 1x re-submission
be required.

6.0 Any further re-submissions in addition to 5.0 will incur additional costs (refer fees for re-
submissions below).

7.0 When aesthetic approval is obtained the plans will be stamped accordingly & said plans
may then be submitted to the Local Authority for Building Plan Approval.

17 Market St • P.O. Box 371 • Stellenbosch 7599 • SOUTH AFRICA


Tel: +27 (0)21 887 0124 • Fax: +27 (0)21 886 5393 • email: info@dmp.co.za • website: www.dmp.co.za

Dennis Moss Planners & Architects (Pty) Ltd. Reg. No. 2003/007711/07
Directors: DF Moss, URP (SA) BA M (URP) M SAPI • GC de Klerk, URP (SA) B Econ M (URP) M SAPI • M Le Roux-Cloete, Pr Arch, BAS, B Arch (UCT), MIArch, CIA • JMH Lackay, Pr S Arch, T MIArch
Associates: WJ Tijmens, Ing (NED) FILASA (Landscape Architect) • SW vd Merwe, Pr Sci Nat, NHD (Nature Conservation) SACNASP
AESTHETIC APPROVAL - PLAN SUBMISSION FORM

ERF NR: _________________ ERF SIZE: _____________

OWNER: _____________________________________________________________________

ADDRESS: ___________________________________________________________________

__________________________________________________________________

TEL NR: ____________________ E-MAIL ADDRESS: ________________________________

DESIGN ARCHITECT/TECHNOLOGIST: _____________________________________________

ADDRESS: ___________________________________________________________________

__________________________________________________________________

SACAP REG. NR: ______________________________________________________________

TEL. NR: ________________ E-MAIL ADDRESS: ____________________________________

SEND CORRESPONDENCE TO (E-MAIL): _________________________________________

DECLARATION

I, the undersigned _____________________________________________________

in my capacity as appointed design architect/technologist herewith declare that the information


given on my drawing/s are correct and complete, and certify that all elements of the design
submitted, conform with the Stadsig Estate Building Guidelines in every respect and acknowledge that
should they not, I may be held responsible for additional costs that may occur, in order to comply.

SIGNATURE: ______________________ Date: ______________


(ARCHITECT/TECHNOLOGIST)

SIGNATURE: ______________________ Date: ______________

2
SCRUTINY FEES – AESTHETIC APPROVAL IN TERMS OF ARCHITECTURAL GUIDELINES

A. New Dwellings R 2 500

B. Additions & Alterations to Existing Dwellings & As-Builts R 2 500

C. Additional Extra over Fee applicable following a 3rd submission R 1 000


of same plan for Aesthetic Approval. At the discretion of the Control
Architect, minor Alterations and Additions to Existing Dwellings & same on As-Builts
may be charged at this reduced Fee.

NOTE – Above scrutiny fees include 15% VAT. Scrutiny fees may be revised periodically as deemed
necessary.

BANKING DETAILS

1. Name: DENNIS MOSS PLANNERS & ARCHITECTS (PTY) LTD

2. Bank: NEDBANK BUSINESS SOUTHERN PENINSULA


(Branch code, 123209)

3. Account Number: 1232-104191

4. Reference for Payment: Use project number B4239 and


Erf number as reference, e.g.
B4239_Erfxxx

Email proof of payment to: den@dmp.co.za

POWER OF ATTORNEY

I/We the (Registered Owner)

__ _________________________________________________________________

ID: _______________________

the undersigned, hereby nominate/appoint:

_________________________________________________________________

with the power of substitution to be my/our legal agent in my/our name/place and stead to apply for
aesthetic approval on Stadsig Estate, Erf: __________________and in general to effect the application and
do whatever I/we would do if I/we were present in person and be acting in that capacity. I/we hereby
ratify, allow and confirm everything my agent may do or may permit to be done legally in terms of this
Power of Attorney:

Signature: ________________________ Date: _____________