Application - Halfway River Temporary Access Bridges Revised Design For 19.7A Crossing
Application - Halfway River Temporary Access Bridges Revised Design For 19.7A Crossing
Application - Halfway River Temporary Access Bridges Revised Design For 19.7A Crossing
Notice of Work
For Canadian Navigable Waters Act
July 8, 2020
Submitted to:
Transport Canada
Navigation Protection Program
Suite 1100 - 1166 W Pender Street
Vancouver, BC V6E 2R9
Submitted by:
BC Hydro and Power Authority
Site C Clean Energy Project
9th Floor – 1111 West Georgia Street.
Vancouver BC V6E 4M3
Site C Clean Energy Project – Halfway River Temporary Access Bridges
Revised Design for Crossing 19.7A
TABLE OF CONTENTS
List of Tables ........................................................................................................................................ i
List of Attachments ............................................................................................................................. i
1 INTRODUCTION ..................................................................................................................... 2
2 HALFWAY RIVER TEMPORARY Crossings – RESERVOIR CLEARING ........................... 2
3 PUBLIC BOATER ACCESS ................................................................................................... 4
List of Tables
Table 1: Location, dimensions and land descriptions for revised Halfway River
crossings at 19.7A ......................................................................................................3
List of Attachments
Attachment B Design Drawings, Plan and Profile Views of Revised Temporary Access Crossings
at 19.7A over Halfway River
1 INTRODUCTION
The Canadian Navigable Waters Act (CNWA) came into force on August 28, 2019. The CNWA includes a
Schedule of navigable waters requiring regulatory approval for works that risk a substantial interference
with navigation. Works required for construction and operation of the Site C Clean Energy Project (the
Project) that occur on, over, under or through navigable waterways, as defined by the CNWA, must be
permitted.
The Halfway River is a Peace River tributary near Hudson’s Hope, BC and is not named in the CNWA
schedule of navigable waters. As such, this application is being submitted as a Notice of Work for the
construction of five (5) temporary bridge and causeway crossings over Halfway River. These five
crossings replace the design for one bridge crossing at 19.7A that was submitted in a previous Notice of
Work (Registry #1493).
This Notice of Work application is specifically for the final upstream mainstem crossing which includes a
combination of five (5) structures over the Halfway River. This multi-crossing design replaces the one
crossing at 19.7A, that was submitted in a previous Notice of Work (Registry #1493) and incorporates the
access that was originally planned as a non-obstructive causeway along the northern bank of the river.
The previous design at crossing 19.7A was for a causeway and bridge with a causeway length of 105m,
and a bridge length of 36.576 m.
A map showing the revised multi-crossing locations at 19.7A is provided in Attachment A. The crossings
span portions of the Halfway River that are Crown Land and are within the Occupant Licence to Cut
(OLTC 19) area held by BC Hydro. The dimensions and approximate location of each crossing at site
19.7A are provided in Table 1.
July 8, 2020 2
Site C Clean Energy Project – Halfway River Temporary Access Bridges
Revised Design for Crossing 19.7A
Table 1. Location, dimensions and land descriptions for revised Halfway River crossings at 19.7A
Halfway
River
Mainstem Bridge
Latitude Longitude Land Description of River Crossing
Crossing Length (m)
19.7A Bridge
ID
1 30.480 56.242011 -121.547452 Theoretical Unsurveyed Crown land North
2 24.385 56.241527 -121.547467 1/2 of Section 34 Township 83 Range 23
3 24.385 56.241127 -121.548261 West of The 6th Meridian Peace River
4 18.288 56.239539 -121.552287 District; and
5 60.960 56.241587 -121.546293 Crown Foreshore, bed of the Halfway
(2 x 30.480 m River and the Halfway River located within
bridges) the North 1/2 of Section 34 Township 83
Range 23 West of The 6th Meridian Peace
River District.
• Bridge 1 to Bridge 2: 47 m
• Bridge 2 to Bridge 3: 42 m
• Bridge 4: No causeway
Under high flow, non-frozen conditions, the causeways and bridge approaches would be constructed from
local river bed materials and supplemented with imported granular material and riprap rock. Five bridge
crossings using six spans (two spans combined into a single structure and supported with a lock block
pier) are planned for managing higher river flows.
Under low flow and/or frozen conditions, a combination of snow and granular material may be used to
develop the access and approaches. Two bridge crossings (Bridges 1 & 5) using three spans (two spans
combined into a single structure and supported with a lock block pier) in combination with three sets of 2-
800 mm steel culverts (in place of high flow bridges) are planned for low river conditions. Where no flow
July 8, 2020 3
Site C Clean Energy Project – Halfway River Temporary Access Bridges
Revised Design for Crossing 19.7A
exists (western backchannel), under frozen conditions the planned culverts may be reduced in size and
number.
A centre pier to support the two-bridge span configuration (Bridge 5), over the widest section of the
channel, would be constructed out of concrete lock blocks. During higher flows, a riprap base may be
required to provide a platform, outside of the river flow, for the lock blocks. The riprap base will be capped
with granular material to ensure the platform is level and can be compacted to provide stability for the
structures.
Riprap specifications have been developed using the estimated flows level and associated scour potential.
The granular material requirements and riprap specifications for each crossing are summarized in the IFC
drawings in Attachment B.
Crossings would be removed in April 2021 and boating access would be reinstated on or before May 1,
2021. The Halfway River boat launch would remain open during this period.
Communication to boaters ahead of river closures would be done in accordance with the Site C Boater
Communication Protocol (Site C Construction Safety Management Plan, Section 5.3.4.2). Signs that are
visible to boaters would be placed upstream of the crossing location to alert them to the upcoming
blockage and potential hazard. Downstream of the crossing, the river would be signed to alert
approaching boaters.
July 8, 2020 4
Site C Clean Energy Project – Halfway River Temporary Access Bridges
Revised Design for Crossing 19.7A
Attachment A – Maps
July 8, 2020 5
Projection: UTM Zone 10, NAD83 Drawing No.: Site C Clean Energy Project Produced by:
Geographic Center of Map: Mapsheet Reference: 94A.013, 023 OLTC19-N11-00004B-01 Middle Reservoir
E: 591,850 Longitude: 121°31'6.43"W Location: Halfway River Revision: 0 OLTC19 - Halfway River
N: 6,232,557 Latitude: 56°13'44.48"N No. Revisions Made Chkd Appd Date Resource District: Peace Date: 26Jun20 Trilogy Crossing Location Map
6236000 588000 590000 592000 594000 596000
6236000
6234000
19.2E
(MR14)
!
D
19.2B
(MR11)
!
D 19.2A
19.2C (MR10)
(MR12) !
D
!
D
19.7A 19.2D
(MR51) (MR13)
19.7A ! D !
D
(MR50)
!
D
6234000
19.3A
Halfw (MR9)
ay R !
D
iver
6232000
Halfway River
Fording Trail
6232000
29
y
Features Hw
r
OLTC19 Boundary
R ive
Primary Access Road a ce
Pe
6230000
Existing Trail
Proposed Access
D
! Crossing ID
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
Projection: UTM Zone 10, NAD83 Drawing No.: Site C Clean Energy Project Produced by:
!
!
!
!
!
!
Geographic Center of Map: Mapsheet Reference: 94A.023 OLTC19-N11-00005B-01 Middle Reservoir
!
!
!
!
!
E: 589,934 Longitude: 121°32'56.08"W Location: Halfway River Revision: 0 OLTC19 - Halfway River
!
N: 6,233,842 Latitude: 56°14'27.34"N No. Revisions Made Chkd Appd Date Resource District: Peace Date: 26Jun20 Trilogy Crossing ID: 19.7A Location Map
!
!
!
!
!
589500 589750 590000 590250
!
!
!
!
!
!
!
!
!
!
!
!
!
³
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
10+741
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
6234000
6234000
!
!
!
!
!
!
!
!
!
!
WP2
!
!
!
!
10+782
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
! !
#
!
!
!
!
!
!
B
!
WP1 !
!
!
10+788
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
B
!
!
!
#
!
Bridge ID: 1
! !
! !
! !
!
#
!
!
!
!
!
!
WP5-7 (2 x 30.480m)
!
!
!
!
!
19.7A
!
!
!
!
!
(MR51)
!
!
!
!
!
!
!
!
!
!
!
B
!
!
!
! !
! !
!
! !
B
!
!
! !
!
!
!
D
! !
! !
!
! !
!
!
WP8
! !
!
!
!
B
!
!
! !
!
!
! !
!
!
! !
!
B
!
!
!
!
!
!
WP5
!
!
!
!
!
!
!
!
B
!
!
!
!
!
!
! !
!
!
!
!
!
!
WP10 (1 x 24.385m)
!
!
! !
!
!
!
! !
!
!
WP9
!
!
!
WP6
!
!
B
!
!
! !
!
!
!
!
!
!
!
!
!
! !
!
!
Bridge ID: 2
!
! !
!
!
WP7
!
! !
!
WP8 (1 x 24.385m)
#
!
!
!
!
B
!
!
!
!
!
! !
!
!
!
!
WP10
!
!
!
! ! !
!
! !
!
!
! !
! !
!
! !
!
! !
WP11
!
! !
!
! !
!
! !
!
!
!
! !
!
!
! !
!
!
!
!
!
!
! !
!
!
!
!
!
!
! !
!
!
!
!
!
!
! !
!
!
!
!
!
!
!
!
!
!
19.7A
!
!
!
!
!
!
!
(MR50)
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
D
!
!
!
!
6233750
6233750
!
!
!
!
!
!
!
!
!
!
!
Bridge ID: 4 !
!
!
!
!
!
!
!
WP14 (1 x 18.288m)
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
Features
!
!
11+279
!
!
!
!
!
!
!
!
!
! !
!
!
! ! !
!
!
!
! !
R
! !
!
B
!
!
!
! !
!
!
! !
!
!
VE
OLTC19 Boundary
!
!
B
!
!
!
! !
!
! !
! !
!
!
!
!
! !
! ! !
!
!
RI
!
!
!
!
! !
!
!
D
!
!
Crossing ID
!
!
! ! !
!
!
!
!
!
#
AY
! !
!
!
!
!
!
!
!
!
Distance Markers
W
!
#
WP14
!
LF
!
!
!
!
WP15
!
!
B
! Bridge Span Markers
!
!
!
HA
!
!
!
!
!
Temporary Access
!
!
!
! ! ! ! ! !
!
!
! ! ! ! ! !
!
!
Temporary Access
!
!
!
!
!
!
!
! ! ! ! ! !
!
! ! ! ! ! !
!
!
!
!
!
!
!
Temporary Bridge
!
!
!
! ! ! ! ! !
!
!
! ! ! ! ! !
!
!
!
!
Skid Trail
!
! ! ! ! ! !
!
!
!
!
! ! ! ! ! !
!
!
!
!
!
Fording Trail
!
! ! ! ! ! !
!
!
! ! ! ! ! ! !
!
!
!
Causeway
!
! ! ! ! ! ! !
!
!
!
!
!
! ! ! ! ! !
!
!
!
!
!
!
!
0 12.5 25 50 75 100
!
!
!
!
!
!
!
!
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User Community
!
!
!
1: 2 500
!
Meters
! !
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
Site C Clean Energy Project – Halfway River Temporary Access Bridges
Revised Design for Crossing 19.7A
Attachment B
Design Drawings, Plan and Profile Views of Revised Temporary Access Crossings at
19.7A over Halfway River
July 8, 2020 6
HALFWAY RIVER
OLTC 19 - 7A