Nothing Special   »   [go: up one dir, main page]

Application - Halfway River Temporary Access Bridges Revised Design For 19.7A Crossing

Download as pdf or txt
Download as pdf or txt
You are on page 1of 36

SITE C CLEAN ENERGY PROJECT

Component Application Package –


Halfway River Temporary Access Bridges
Revised Design for Crossing 19.7A

Notice of Work
For Canadian Navigable Waters Act

July 8, 2020

Submitted to:
Transport Canada
Navigation Protection Program
Suite 1100 - 1166 W Pender Street
Vancouver, BC V6E 2R9

Submitted by:
BC Hydro and Power Authority
Site C Clean Energy Project
9th Floor – 1111 West Georgia Street.
Vancouver BC V6E 4M3
Site C Clean Energy Project – Halfway River Temporary Access Bridges
Revised Design for Crossing 19.7A

TABLE OF CONTENTS
List of Tables ........................................................................................................................................ i
List of Attachments ............................................................................................................................. i
1 INTRODUCTION ..................................................................................................................... 2
2 HALFWAY RIVER TEMPORARY Crossings – RESERVOIR CLEARING ........................... 2
3 PUBLIC BOATER ACCESS ................................................................................................... 4

List of Tables

Table 1: Location, dimensions and land descriptions for revised Halfway River
crossings at 19.7A ......................................................................................................3

List of Attachments

Attachment A Overview Map of Halfway River Temporary Access Crossings


Map of Revised Multi-crossing Bridge Locations at 19.7A
Map of Halfway River Blockage Extent

Attachment B Design Drawings, Plan and Profile Views of Revised Temporary Access Crossings
at 19.7A over Halfway River

July 8, 2020 Revision 0


Site C Clean Energy Project – Halfway River Temporary Access Bridges
Revised Design for Crossing 19.7A

1 INTRODUCTION
The Canadian Navigable Waters Act (CNWA) came into force on August 28, 2019. The CNWA includes a
Schedule of navigable waters requiring regulatory approval for works that risk a substantial interference
with navigation. Works required for construction and operation of the Site C Clean Energy Project (the
Project) that occur on, over, under or through navigable waterways, as defined by the CNWA, must be
permitted.

The Halfway River is a Peace River tributary near Hudson’s Hope, BC and is not named in the CNWA
schedule of navigable waters. As such, this application is being submitted as a Notice of Work for the
construction of five (5) temporary bridge and causeway crossings over Halfway River. These five
crossings replace the design for one bridge crossing at 19.7A that was submitted in a previous Notice of
Work (Registry #1493).

2 HALFWAY RIVER TEMPORARY CROSSINGS – RESERVOIR


CLEARING
Site C Reservoir clearing in forest areas of the lower Halfway River catchment requires machine access
to both banks of the river. The available road networks do not provide access to areas that require
clearing ahead of reservoir filling, hence new roads and access routes are proposed. Within this new road
network, six (6) mainstem bridge crossings are required, each being accessed using constructed
causeway approaches. These mainstem crossings are shown in the overview map in Attachment A.

This Notice of Work application is specifically for the final upstream mainstem crossing which includes a
combination of five (5) structures over the Halfway River. This multi-crossing design replaces the one
crossing at 19.7A, that was submitted in a previous Notice of Work (Registry #1493) and incorporates the
access that was originally planned as a non-obstructive causeway along the northern bank of the river.
The previous design at crossing 19.7A was for a causeway and bridge with a causeway length of 105m,
and a bridge length of 36.576 m.

A map showing the revised multi-crossing locations at 19.7A is provided in Attachment A. The crossings
span portions of the Halfway River that are Crown Land and are within the Occupant Licence to Cut
(OLTC 19) area held by BC Hydro. The dimensions and approximate location of each crossing at site
19.7A are provided in Table 1.

July 8, 2020 2
Site C Clean Energy Project – Halfway River Temporary Access Bridges
Revised Design for Crossing 19.7A

Table 1. Location, dimensions and land descriptions for revised Halfway River crossings at 19.7A
Halfway
River
Mainstem Bridge
Latitude Longitude Land Description of River Crossing
Crossing Length (m)
19.7A Bridge
ID
1 30.480 56.242011 -121.547452 Theoretical Unsurveyed Crown land North
2 24.385 56.241527 -121.547467 1/2 of Section 34 Township 83 Range 23
3 24.385 56.241127 -121.548261 West of The 6th Meridian Peace River
4 18.288 56.239539 -121.552287 District; and
5 60.960 56.241587 -121.546293 Crown Foreshore, bed of the Halfway
(2 x 30.480 m River and the Halfway River located within
bridges) the North 1/2 of Section 34 Township 83
Range 23 West of The 6th Meridian Peace
River District.

The approximate causeways lengths are as follows:

• Northern bank of river to Bridge 1: 11 m

• Bridge 1 to Bridge 2: 47 m

• Bridge 2 to Bridge 3: 42 m

• Bridge 3 to Bridge 4: 290 m

• Bridge 4: No causeway

• Between Bridge 1 and Bridge 5: 52 m

2.1 REVISED DESIGN OF MULTI-CROSSING 19.7A


Two options for this crossing location are provided to address high and low flow river conditions. The
general arrangement, dimensions and specifications for each of the five bridges under both conditions, is
provided in the drawing package in Attachment B. Each bridge has been designed by an engineering
professional. Each crossing would have the capacity to pass the daily average flow estimated for the
seasonal (September - April), 1 in 10-year return period (124 m3/s).

Under high flow, non-frozen conditions, the causeways and bridge approaches would be constructed from
local river bed materials and supplemented with imported granular material and riprap rock. Five bridge
crossings using six spans (two spans combined into a single structure and supported with a lock block
pier) are planned for managing higher river flows.

Under low flow and/or frozen conditions, a combination of snow and granular material may be used to
develop the access and approaches. Two bridge crossings (Bridges 1 & 5) using three spans (two spans
combined into a single structure and supported with a lock block pier) in combination with three sets of 2-
800 mm steel culverts (in place of high flow bridges) are planned for low river conditions. Where no flow

July 8, 2020 3
Site C Clean Energy Project – Halfway River Temporary Access Bridges
Revised Design for Crossing 19.7A

exists (western backchannel), under frozen conditions the planned culverts may be reduced in size and
number.

A centre pier to support the two-bridge span configuration (Bridge 5), over the widest section of the
channel, would be constructed out of concrete lock blocks. During higher flows, a riprap base may be
required to provide a platform, outside of the river flow, for the lock blocks. The riprap base will be capped
with granular material to ensure the platform is level and can be compacted to provide stability for the
structures.

Riprap specifications have been developed using the estimated flows level and associated scour potential.
The granular material requirements and riprap specifications for each crossing are summarized in the IFC
drawings in Attachment B.

2.2 CONSTRUCTION SEQUENCE AND SCHEDULE


The contractor is expected to begin constructing the Hwy 29 temporary access crossings in early
September, starting at the downstream end (Site ID 19.3A) and moving upstream after each crossing is
built. Construction of the multi-crossing at 19.7A is planned to begin late November 2020.
Minor changes to location and bridge sizing may be required in order to field fit each crossing to site
conditions that exist during construction. These changes may be required due to the dynamic changes in
gravel bar and channel locations that occur frequently in this drainage.
Decommission of the crossings will involve bridge deck, abutment and pier removal such that navigation
access can be reinstated by May 1, 2021. Causeway materials will remain in place, unless minor
openings are required for fish migration. The future Site C reservoir would cover the causeway materials
after reservoir filling is completed in 2024, and each causeway would be shown in the future reservoir
maps.

3 PUBLIC BOATER ACCESS


Construction of temporary crossings in the Halfway River channel is expected to block boater access to
lower portions of the Halfway River between September 1, 2020 and April 30, 2021. A map showing the
river blockage extent has been included in Attachment A.

Crossings would be removed in April 2021 and boating access would be reinstated on or before May 1,
2021. The Halfway River boat launch would remain open during this period.

Communication to boaters ahead of river closures would be done in accordance with the Site C Boater
Communication Protocol (Site C Construction Safety Management Plan, Section 5.3.4.2). Signs that are
visible to boaters would be placed upstream of the crossing location to alert them to the upcoming
blockage and potential hazard. Downstream of the crossing, the river would be signed to alert
approaching boaters.

July 8, 2020 4
Site C Clean Energy Project – Halfway River Temporary Access Bridges
Revised Design for Crossing 19.7A

Attachment A – Maps

Overview Map of Halfway River Temporary Access Crossings


Map of Revised Multi-crossing Bridge Locations at 19.7A
Map of Halfway River Blockage Extent

July 8, 2020 5
Projection: UTM Zone 10, NAD83 Drawing No.: Site C Clean Energy Project Produced by:
Geographic Center of Map: Mapsheet Reference: 94A.013, 023 OLTC19-N11-00004B-01 Middle Reservoir
E: 591,850 Longitude: 121°31'6.43"W Location: Halfway River Revision: 0 OLTC19 - Halfway River
N: 6,232,557 Latitude: 56°13'44.48"N No. Revisions Made Chkd Appd Date Resource District: Peace Date: 26Jun20 Trilogy Crossing Location Map
6236000 588000 590000 592000 594000 596000
6236000

6234000
19.2E
(MR14)
!
D
19.2B
(MR11)
!
D 19.2A
19.2C (MR10)
(MR12) !
D
!
D

19.7A 19.2D
(MR51) (MR13)
19.7A ! D !
D
(MR50)
!
D
6234000

19.3A
Halfw (MR9)
ay R !
D
iver

6232000
Halfway River
Fording Trail
6232000

29
y
Features Hw
r
OLTC19 Boundary
R ive
Primary Access Road a ce
Pe

6230000
Existing Trail
Proposed Access

D
! Crossing ID

0 125 250 500 750 1,000

Meters 1:25 000


Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User Community

588000 6230000 590000 592000 594000 596000


!
!

!
!

!
!

!
!

!
!

!
!

!
!

!
!

!
!
!

!
!

!
!

Projection: UTM Zone 10, NAD83 Drawing No.: Site C Clean Energy Project Produced by:

!
!

!
!

!
!
Geographic Center of Map: Mapsheet Reference: 94A.023 OLTC19-N11-00005B-01 Middle Reservoir

!
!

!
!

!
E: 589,934 Longitude: 121°32'56.08"W Location: Halfway River Revision: 0 OLTC19 - Halfway River

!
N: 6,233,842 Latitude: 56°14'27.34"N No. Revisions Made Chkd Appd Date Resource District: Peace Date: 26Jun20 Trilogy Crossing ID: 19.7A Location Map

!
!

!
!

!
589500 589750 590000 590250

!
!
!

!
!

!
!

!
!

!
!

!
!
³

!
!

!
!

!
!

!
!

!
!

!
!
!

!
!

!
!

!
!

!
!

!
!

!
!

!
!

!
!

!
!

!
!

!
!
!

!
!

!
!
!

!
!

!
10+741

!
!
!

!
!
!

!
!
!

!
!

!
!
!

!
!

!
!
6234000

6234000
!

!
!

!
!
!

!
!
!

!
WP2

!
!
!

!
10+782

!
!

!
!
!

!
!
!

!
!

!
!

!
!

!
!

! !

#
!
!
!
!
!
!

B
!

WP1 !
!

!
10+788
!

!
!

!
!

!
!

!
!

!
!

!
!
!
!

B
!

!
!

#
!

Bridge ID: 1
! !

! !
! !
!

#
!

WP1 (1 x 30.480m) Bridge ID: 5


!

!
!
!
!

!
WP5-7 (2 x 30.480m)

!
!
!

!
!

19.7A
!
!
!

!
!

(MR51)
!
!

!
!

!
!
!
!

!
!
!

B
!
!
!
! !
! !
!

! !

B
!

!
! !
!
!

!
D
! !

! !

!
! !
!
!

WP8
! !
!

!
!

B
!

!
! !
!
!
! !
!
!
! !

!
B
!
!

!
!

!
!

WP5
!
!

!
!

!
!

!
!

Bridge ID: 3 10+960


!

B
!

!
!

!
!
!
! !
!
!
!
!
!
!

WP10 (1 x 24.385m)
!
!

! !
!
!
!
! !
!
!

WP9
!
!
!

WP6
!
!

B
!

!
! !

!
!
!
!
!
!
!

!
!
! !
!
!

Bridge ID: 2
!

! !
!
!

WP7
!

! !
!

WP8 (1 x 24.385m)

#
!
!
!

!
B
!
!

!
!

!
! !

!
!

!
!

WP10
!
!
!

! ! !
!
! !
!
!

! !

! !
!
! !
!
! !

WP11
!
! !
!
! !
!
! !
!

!
!
! !

!
!
! !
!
!

!
!
!
!

! !
!
!
!

!
!
!

! !

!
!
!
!
!

!
! !

!
!
!
!
!
!
!

!
!

!
19.7A
!

!
!

!
!
!
!

(MR50)
!

!
!

!
!

!
!
!

!
!

!
!
!

!
!

!
!

!
!

!
D
!
!
!

!
6233750

6233750
!
!
!

!
!

!
!

!
!

!
!

Bridge ID: 4 !
!

!
!
!

!
!

!
WP14 (1 x 18.288m)
!

!
!
!

!
!

!
!

!
!

!
!

!
!
!

!
!
!
!

!
!

!
!
!

!
!
!
!
!
!

!
!
!

!
!

!
!

!
!

!
!

!
!

!
Features

!
!

11+279
!

!
!

!
!
!
!

!
!
! !
!

!
! ! !
!
!

!
! !

R
! !
!

B
!

!
!
! !
!

!
! !

!
!

VE
OLTC19 Boundary

!
!
B
!

!
!
! !

!
! !
! !
!
!
!
!
! !

! ! !
!
!

RI
!
!

!
!
! !
!

!
D
!

!
Crossing ID
!

!
! ! !

!
!
!

!
!
#

AY
! !
!
!

!
!
!

!
!

!
Distance Markers
W

!
#

WP14

!
LF
!

!
!

!
WP15

!
!

B
! Bridge Span Markers

!
!

!
HA

!
!
!
!

!
Temporary Access
!

!
!

! ! ! ! ! !

!
!

! ! ! ! ! !

!
!
Temporary Access

!
!

!
!

!
!
!

! ! ! ! ! !
!

(Winter Access Construction)


!

! ! ! ! ! !

!
!

!
!
!

!
!

Temporary Bridge
!

!
!

! ! ! ! ! !
!

!
! ! ! ! ! !

!
!

!
!
Skid Trail
!

! ! ! ! ! !
!

!
!

!
! ! ! ! ! !
!

!
!

!
!
Fording Trail
!

! ! ! ! ! !
!

!
! ! ! ! ! ! !
!

!
!

Causeway
!

! ! ! ! ! ! !
!

!
!
!

!
! ! ! ! ! !
!

!
!

!
!

!
!

0 12.5 25 50 75 100
!
!

!
!

!
!

!
!

Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User Community
!

!
!

1: 2 500
!

Meters
! !
!
!

!
!

!
!

!
!

!
!
!

!
!
!

589500 589750 590000 590250


!

!
!

!
!
!

!
!
!

!
!

!
!
!

!
!

!
!

!
!
!

!
!

!
!

!
!

!
!

!
!

!
!

!
!

!
!

!
!
!

!
!

!
!

!
!

!
!
!

!
!

!
Site C Clean Energy Project – Halfway River Temporary Access Bridges
Revised Design for Crossing 19.7A

Attachment B

Design Drawings, Plan and Profile Views of Revised Temporary Access Crossings at
19.7A over Halfway River

July 8, 2020 6
HALFWAY RIVER
OLTC 19 - 7A

HALFWAY RIVER CROSSINGS (MIN. CL-625)


BRIDGE DETAILS

PROPOSED SET OF PLANS FOR


LOW-FLOW OPTION

PROPOSED#2 SET OF PLANS FOR


ULTRA LOW-FLOW OPTION
(ALMOST NO FLOW PRESENT IN
CULVERT CHANNELS AT TIME OF
CONSTRUCTION)
N
N
N
N
N
N
N
N
N
N
N
N

You might also like