ITML Pour Card
ITML Pour Card
ITML Pour Card
PROJECTS LIMITED
Concrete Pour Card
Project Name: Pour location:
Pour Type:
Design Strength: MPa @ 28 days Supplier:
PRE-RELEASE CHECKS
ITEM ITMPL HDC DATE
Safety & Access acceptable Y N
Clean out complete Y N
Dewatering complete N/A Y N
Waterproofing installed N/A Y N
Waterstops installed N/A Y N
Formwork acceptable N/A Y N
Reinforcement acceptable N/A Y N
Reinforcement coverage acceptable N/A Y N
Concrete embeds in place N/A Y N
Construction joint(s) in place N/A Y N
CONCRETE POUR
ITEM ITMPL HDC DATE
Concrete Supplier(s)
Concrete placed per project specs Y N
Concrete consolidated appropriately Y N
Roughened surface for bond N/A Y N
Slurry / bonding agent utilized N/A Y N
Concrete Slump measured N/A mm
Volume of concrete poured m3
Concrete sampling performed N/A Y N
FINAL ACCEPTANCE
ITEM ITMPL HDC DATE