C&G Cosntruction
C&G Cosntruction
C&G Cosntruction
Form must be well balanced with materials, craftsmanship and structural method to enhance
environmental blend.
Factors affecting the choice or form of construction
i. Invention of new material
ii. Functional requirement
iii. The client taste
iv. Scarcity of materials
v. Rising cost or scarcity of labour.
Process of construction
There are two major process used for constructing a building and they are;
1. Design process: this process involves the determining of the size and shape of the
building and the allocation of space in the building.
2. Production process: this concern with the nature and sequence of building operations
and it is this that determines the method which can be adopted in in carrying out the
operation.
Exercise
1. With a neat sketch, explain the use of ten building tools. Including builder square,
corner profile and gauge rod.
2. List and explain the uses of five plants used in construction work.
3. Explain the following terms.
i. DPC
ii. Over site concrete
iii. Gable roof
iv. Lintel
v. Dwarf wall.
Site preparation
Before a building is erected the piece of land that is to be used is called the site. This site is to
be prepared before setting out for foundation.
Therefore; site preparation is the process of clearing, uprooting, gruping trees and unwanted
element from the ground. This can be done by the use of cutlass, shovel, spade, pickaxe,
bulldozer, etc.
There are two categories of tools used in site preparation and these are;
1. Mechanical tools: - such as bulldozer, tractor shovels, graders, chain saw, excavators
etc.
2. Hand tool: - cutlass, wheel barrow, head pan, hoe, auger, auger, axe, rake etc.
Setting out
Setting out is the process of transferring the building plan (foundation plan) in full scale to the
ground by the use of lines and pegs.
To set out a building requires the knowledge of building drawing and the ability to read
drawings accurately.
A building is set out in order to clearly define the outline of the excavation and the center line
of the walls, so that construction can be carried out exactly according to the plan. The center
line method of setting out is generally preferred and adopted.
1. From the plan (fig 1), the center line of the walls are calculated. Then the center lines of the
rooms are set out by setting perpendiculars in the ratio 3:4:5. Suppose the corner points are a,
b, c, d, e, f and g which are marked by pegs with nails on top.
2. The setting of the corner point is checked according to diagonals ac, bd, cf and eg.
3. During excavation, the center points a, b, c, d, e, f, g may be removed. Therefore the center
lines are extended and the center points are marked about 2m away from the outer edge of
excavation. Thus the points A1, A2, B1, B2 and likewise, are marked outside the trench. Centre
line is shown clearly by stretching thread or rope. The center points fixed 2m away from the
excavation are marked with sit out pegs.
4. From the plan details, the width of excavation to be done is also marked by thread with pegs
at appropriate positions.
5. The excavation width is then marked by lime or by with furrow with spade.
6. If the plan is much too complicated and follows a zigzag pattern, then the center pegs are
kept at suitable positions according to site conditions.
All setting out operations are carried out from information given on drawings produced by a building
designer, architect or construction company. On larger sites the site engineer carries out the setting out
of buildings and associated roads. It is however also quite common for the site supervisor to set out
individual plots on a housing estate. Drawings should be produced to BS 1192 ‘Recommendations for
Drawing Office Practice.
Drawings must be approved by the local authority for the area in which the building is being
constructed. On approval of the drawings for Planning Permission (Planning Department), and Building
Regulations (Building Control), the setting out can safely commence.
The following information relevant to setting out must be shown on drawings submitted for local
authority approval:
• Position of proposed buildings in relation to existing boundaries or roads.
• Position and levels of new roads and drains.
• Levels of new buildings at foundations, floors etc.
The site plan will show exactly where the building is to be situated on the land. This is often drawn to a
scale of 1:200 or 1:500.
Often the two front corners of the building are dimensioned from existing set features on the site such
as boundary walls or intersections, gate posts etc., allowing initial positioning of the base (or ‘frontage’)
line of the building.
The building layout or general location plan, often produced to a scale of 1:50, will contain the
dimensions of the building, including the internal room sizes.
Dimensions on drawings
When setting out, measurements have to be made on site from dimensions ‘taken off’ from a drawing.
Dimensions on construction drawings are most commonly stated in millimeters, although sometimes
meters may be used.
Measurements made on site from drawing dimensions should be regularly checked for accuracy. An
accuracy of 1:1000, i.e. 1mm in every 1 metre, should be achieved for general construction work.
NOTE!
All information to be used for setting out any building must be checked before setting out
commences.
NB: All information to be used for setting out any building must be checked before setting out
commences.
1. Running dimensions
All dimensions along a line are stated as a distance from a single point, e.g. the corner of a building.
This is the most accurate method because errors in individual measurements will not accumulate along
a line of dimensions, when used for setting out a building.
2. Separate dimensions
All dimensions are stated separately and are not able to be checked. This is not recommended for
setting out purposes.
By checking that individual dimensions tally up to the overall dimension, the reader becomes
confident that the dimensions are correct.
Before any setting out commences, it is good practice to remove turf and vegetable soil from
the area on which the building will stand. The reasons for this are:
• Setting out markings will be clearly visible and distinct on soil but not on grass.
• ‘Topsoil’ is unsuitable to build on as it has a low bearing capacity.
• The soil may also allow plant growth to continue, even when covered by a building, and this could
result in timber decay.
The Building Regulations require the vegetable soil to be removed from the building area. This is either
stored in convenient on-site ‘spoil heaps’, or removed from the site totally if no storage room is
available (and if it is not to be reused for landscaping).
Engineer’s drawings are more to technical drawing that was an outcome from the design
procedure.
In this chapter, students will be introduce with structural system of a building that are
designed by civil engineer as for building is one of the field that need the expertise of a civil
engineer.
Building superstructure
The superstructure system is the vertical extensions of building physical structure above the
foundations
Columns
Beams
Load bearing walls
Slab
Columns
Columns are rigid, relatively slender structural members design to support axial compressive
loads applied to the ends of the members.
Beams
Beams are rigid structural members designed to carry and transfer loads across space to
supports elements mostly a columns
Building substructure
The substructure is the underlying structure forming the foundation of the building. This
systems a later to be discuss in geotechnical engineering drawing. That’s in drawing building
plans section. This comprises of the foundation footing, earth filling, hardcore, oversight-
concrete and floor screeding.
Other structure details of building are referred to as the basic elements of building.
Elements of building
1. Foundation: Foundation is the most important part of the building. Building activity starts
with digging the ground for foundation and then building it. It is the lowest part of the building.
It transfers the load of the building to the ground. Its main functions and requirements are:
(a) Distribute the load from the structure to soil evenly and safely.
(b) To anchor the building to the ground so that under lateral loads building will not move.
(c) It prevents the building from overturning due to lateral forces.
(d) It gives level surface for the construction of super structure.
2. Plinth: The portion of the wall between the ground level and the ground floor level is called
plinth. It is usually of stone masonry. If the foundation is on piles, a plinth beam is cast to
support wall above floor level.
At the top of plinth a damp proof course is provided. It is usually 75 mm thick plain
concrete course.
The function of the plinth is to keep the ground floor above ground level, free of dampness. Its
height is not less than 450 mm. It is required that plinth level is at least 150 mm above the road
level, so that connections to underground drainage system can be made.
3. Walls and Columns: The function of walls and columns is to transfer the load of the structure
vertically downwards to the foundation. Apart from this, wall performs the following functions:
(a) It encloses building area into different compartments and provides privacy.
(b) It provides safety from burglary and insects.
(c) It keeps the building warm in winter and cool in summer.
4. Sills, Lintels and Chejjas: A window frame should not be directly placed over masonry. It is
placed over 50 mm to 75 mm thick plain concrete course provided over the masonry. This course
is called as sill. Lintels are the R.C.C. or stone beams provided over the door and window
openings to transfer the load transversely so as to see that door or window frame is not stressed
unduly. The width of lintels is equal to the width of wall while thickness to be provided depend
upon the opening size.
Chejjas is the projection given outside the wall to protect doors and windows from the rain. They
are usually made with R.C.C. In low cost houses stone slabs are provided as chejjas. The
projection of
chejjas varies from 600 mm to 800 mm. Sometimes drops are also provided to chejjas to improve
aesthetic look and also to get additional protection from sun and rain.
5. Doors and Windows: The function of a door is to give access to different rooms in the
building and to deny the access whenever necessary. Number of doors should be minimum
possible.
The size of the door should be of such dimension as will facilitate the movement of the largest
object likely to use the door.
Windows are provided to get light and ventilation in the building. They are located at a height of
6. Floors: Floors are the important component of a building. They give working/useful area for
the occupants. The ground floor is prepared by filling brick bats, waste stones, gravel and well
compacted with not less than 100 mm sand layer on its top. A lean concrete of 1: 4: 8, 100 mm
thick is laid. On this a damp proof course may be provided. Then floor finishing is done as per
the requirement of the owner.
Cheapest floor finish for a moderate house is with 20 to 25 mm rich mortar course finished with
red oxide. The costliest floor finish is mosaic or marble finishing.
Other floors are usually of R.C.C. finished as per the requirements of the owner.
7. Roof: Roof is the top most portion of the building which provide top cover to the building. It
should be leak proof.
Sloping roof like tiled and A.C. sheet give leak proof cover easily. But they do not give provision
for the construction of additional floor. Tiled roof give good thermal protection.
Flat roofs give provision for additional floors. Terrace adds to the comfort of occupants. Water
tanks can be easily placed over the flat roofs.
8. Step, Stairs and Lifts: Steps give convenient access from ground level to ground floor level.
They are required at doors in the outer wall. 250 to 300 mm wide and 150 mm rise is ideal size
for
steps. In no case the size of two consecutive steps be different. Number of steps required depends
upon
the difference in the levels of the ground and the floor. Stairs give access from floor to floor.
They
should consists of steps of uniform sizes.
In all public buildings lifts are to be provided for the conveniences of old and disabled persons.
In hostels G + 3 floors can be built without lifts, but in residential flats maximum floors
permitted
without lifts is only G + 2. Lift is to be located near the entrance. Size of the lift is decided by the
number of users in peak hours. Lifts are available with capacity 4 to 20 persons.
9. Finishing: Bottom portion of slab (ceiling), walls and top of floor need smooth finishing
with plaster. Then they are provided with white wash, distemper or paints or tiles. The function
of
finishing work is:
(a) Give protective cover
(b) Improve aesthetic view
(c) Rectify defective workmanship
(d) Finishing work for plinth consists in pointing while for floor it consists in polishing.
10. Building Services: Water supply, sanitation and drainage works, electric supply work and
construction of cupboards and show cases constitute major building services.
For storing water from municipal supply or from tanker a sump is built in the house property
FOUNDATION
Foundation is the lowest part of thye wall of a building, its that part of the structure which has
direct contact with the ground to which the load are transmitted.
It is the base of which a building rest, it may be founded of stone, concrete or steel but the
most common material ii mordern construction is concrete.
Concrete is a mixture of cement, sand and aggrete (granit, gravel etc.)
Purpose /function of foundation.
The function of foundation is to safely transfer the load of a building to the soil. In such a way
that settlement is limited and failure of the under soil is avioded. From this brief defination
foundation can not be designed without the engineers having fair knowledge of the soil on
which the foundation is rested and this esssence of soil investigation.
Which ever foundation chosen, it should be very strong so as not to
1. Break on or under load.
2. Be destroyed by the roots of trees.
3. Be affected by the present of water.
Types of foundation
There are different types of foundation namely;
1. stirp foundation: is a continous deposite of concrete in the foundation trench on which
the walls is of tghe building are constructed. It is the commest ofn foundation.
As the name implies continous. Strip of mass concrete or reinforced concrete or stone
laid on the ground level and along the position of the bad load, walls only. This type of
foundation areb suitable for boundaries walls, domestic buildings of not more than
three stories and retaing walls. They are not suitable on made up ground, very sofy slay
soil or peat. A strip foundation may be stepped in sloppy ground to save excessive
digging atb the higher ground. Strip foundation is generally composed of plain concrete
offer to a mix of 1:3:6 of volume (i.e 1 part of cement, 3 part of sand and 6 part of
concrete), with a thickness been not less than projection of the foundation in no casev
les than 150mm.
Wall
Concrete
Strip foundation is used for simple buildings on firm ground and on wet ground reinforced strip
foundation can be used.
Pad foundation: is a reinforced concrete base on which concrete columns are constructed. Pad
foundation could be isolated pad or reinforced strip foundation. It may be rectangular, circular
or square in section. It is used for storey buildings. The most common types are square, they
are may be of mass or reinforced concrete pad are reserved for the large types of structures.
Pad is used to support isolated loads, such as load in column, piers and heavy machinery in
factories. The thickness must not be less than the projection from the column, unless
reinforced and must be in no case less than 150mm. the size of the foundation can be reduced
by providing steel reinforce towards the bottom of the foundation running in both direction.
Sanding
End bearing pile: the shaft passes through soft deposit and the base or point rest on the bed
rock or penetrate dense sand or gravel and the pile act as a column.
Friction pile: is embedded in coarse soil and obtain its support mainly by adhesion or skin
friction of the soil or the surface of the shaft.
Types of walls.
I. External wall/load bearing wall/enclosing wall: support load from floor to roof. They are load
bearing walls. They resist side pressure from wind and sometimes from stored materials or
objects within the building.
II. Internal wall/dividing wall/non-loading bearing wall: are non-load bearing walls. They divide
space.
The primary function of a wall is to enclose and divide space. Walls are to provide adequate
Wall finishes
A wall finish may consist of painting, plastering, rendering, pointing the joint, Tyrolean application or dry
lining with blaster board.
Plastering: is the application of wet mix of fine cement and sand to the internal surfaces of a wall.
Although, in some cases only cementing materials is used without the addition of sand. Plastering is
primarily intended to provide a flat even surface to the wall.
Rendering: is the application cementing material and sand or without sand on the external surface of
the wall. Rendering is intended primarily to prevent the penetration of water into the wall.
Pointing: is the name given to the method of finish or the joint receives after the wall has been built.
There are three types of pointing, each of which is carried out after the joint has been racked out and
thoroughly cleaned.
Types of pointing
I. Flush pointing
II. Wheather pointing
III. Tuck pointing
Jointing: is the treatment of the joint as the building of the wall proceeds.
1. Wheather joint
2. Struck
3. Half turn recessed joint
4. Square joint
5. Vee - joint
Types of pointing.
a. Flushed pointing: is used to obtain a generally sand faced effect to concrete block wall.
Flush pointing
Coping is one of the method use at the termination of block wall. These are features at the top of free
standing walls, including parapets, given Wheather protection and at the same time providing a
decorative finished. Coping may be of stone, concrete, brick or metal, they protect the sides of the wall
and are lead to a slope so as to throw water clear. Concrete coping has a throating under each side
projection and a D.P.C to prevent moisture from penetrating through the joints. (D.P.C meaning damp
proof course).
Types of coping
1) Feather edge
2) Saddle back
3) Segmental
4) Buck on edge
1) 2)
Throating
Stairs
Stairs consist of a series of steps with accompanied hand rail, stair case or staring lands and balustrades
and other components art in one or more successive flight of stairs. The space occupied by stir case
stands a stir well, with the vertical distance between the floors served by a stair case describe is the lift.
Types
1. Straight flight: is the simplest form of stair. All the steps leads in the same direction from floor to
floor with or without a landing.
2. Half turn: is stair which rises to half space landing between floors, turn 180°, and the second
flight rising the opposite direction to the one below.
Landing
3. Quarter turn stair: has a quarter which turn through 90° and continue to the next floor.
Up
Quarter turn
4. Geometric: can be similar to the open newel stair expect instead of quarter space landing, it has
a series of winder arranged in a spiral form. A form of geometrical stair which has no well is
known as a spiral stair.
Winders
Stair case is constructed in a building to facilitate the movement of people, equipment and machinery
from one floor to another.
Stair cases are constructed with different stair case is a structural member of a building. The first case is
to see that they are of equal height because they prompt accident.
Parts of stair
1. Riser
2. Balustrade
3. Landing
4. Newel post
5. String
6. Pitch
7. Going
8. Nosing
9. Tread
The floor height of a building is 2400mm and the total going is 3750. Calculate the number of riser and
treads required for the stair ways. If a straight flight is to be use the riser is 150mm and the going is
250mm.
Note:
2G + G = 550
2400 riser
Floors
Floors are generally designed to satisfy a number of functional requirement, such as stated below;
Functions of a floor.
Types
1. Solid floor (ground floor)r: over-site concrete (German floor). Over-site are supported with DPC
which is Damp roof course. This is the type of floor that has direct contact with the ground.
Damp prove course is a layer of barrier of concrete to prevent ground moisture for penetrating the
building.
Floor finishes
1. Screeding: is a mixture of cement, sand and water in the other to give a level floor surface.
2. PVC tiles, Quarry (clay) tiles
3. Terrazzo
4. Wood block
5. Marble.
1. Maintaince
2. Non-slip
3. Ease of cleaning
4. Wear
5. Economical
Quarry tiles are mostly use in the bathroom, swimming pool etc.
Function of screeding
1. The floor height of a building is 2100mm and the total going is 4750. Calculate the number of
riser and treads required for the stair ways. If a straight flight is to be use the riser is 250mm and
the going is 400mm.
2. The floor height of a building is 10700mm and the total going is 7500. Calculate the number of
riser and treads required for the stair ways. If a straight flight is to be use the riser is 150mm and
the going is 250mm.