Flett Handouts
Flett Handouts
Flett Handouts
Presentation Contents
1 2
3 4
1/10
1
Project Organisation Role of the Contractor’s Checking Engineer
Korean Expressway
IBC – 51% AMEC and 49% the
City of Incheon Joint Venture INPUTS
Corporation (KEC) SCJV – Samsung, Daelim, Daewoo,
Hanjin, Hanwha, Kumho and GS • Independent Design Check of the Permanent Works
Incheon Bridge • Independent Design Review of the Temporary Works
Company Ltd AMEC
(Concessionaire) (Project
• Review Technical Notes produced by others
Management)
Samsung • Provide Technical Assistance to the Contractor
Construction Contractors Design Supervisor
Joint Venture Designers (DS)
(SCJV) Seoyeong-Chodai-Cowi Yooshin-Mott MacDonald DELIVERABLES
(Design and
Build Contractor) Construction • Design Check Certificates (DCC) for permanent works
Supervisor (CS)
Halcrow (lead) Yooshin • Design Review Certificates (DRC) for temporary works
Contractors
Checking Arup Contractual Relationship • Design Review Certificates (DRC) for technical reports
Engineer Line of Communication
Dasan
5 6
Role of the Contractor’s Checking Engineer Role of the Contractor’s Checking Engineer
Halcrow (lead) Arup Dasan
General CCE Management, Technical Technical Advice, Construction Alignment, Expansion Joints, • Design Standards
Advice, Construction Advice, Advice, Seismic survey and Barriers, Surfacing, Drainage,
Seismic survey and hazard hazard, Pile load test Lighting
• 2 key documents
Cable Stayed Bridge Analysis (Support), Analysis, Deck, Aerodynamics
Geotechnics, Substructure,
Pylons, Aerodynamics
• Project Performance Requirements (PPR)
Viaduct Analysis, Geotechnics,
Substructure, Superstructure
- Written by the Ministry of Construction and Transportation
• Concessionaire’s Supplementary Requirements (CSR)
Approach Bridge Analysis, Geotechnics,
Substructure, Superstructure - Written by Incheon Bridge Company Ltd (IBC)
Ship Impact Protection Layout, finite element • AASHTO LRFD (3rd Edition) & Korean Bridge Design Standards
modelling, model test
• Interpretation of LRFD required – new document
Scour Protection Scour protection design, model
test • CCE produced many Technical Notes
7 8
2/10
2
Role of the Contractor’s Checking Engineer Role of the Contractor’s Checking Engineer
• Approach Bridge Design Check
• Cable Stayed Bridge Design Check • 145m long spans by balanced cantilever construction
• Built in pier tops – no bearings apart from end spans
• 1480m long with 800m main span
• Design tools – LARSA, stage construction & time dependent effects
• 33.4m wide steel orthotropic deck
• REPUTE – non-linear analysis of pile groups in multiple soil strata
• Pylon – reinforced concrete hollow section in diamond configuration
• Camber curves checked for casting yard segment alignment
• Design tools – TDV RM2000, Oasys GSA, LARSA
• Sub-structure certified for construction before deck checked
• Fast track design & check – 12 weeks to start of piling
• Interaction with the Designer – agree loads before detailing re-bar • Low Level Viaduct Design Check
• Wind buffeting analysis, response spectrum seismic analysis • 50m spans built by the span-by-span method
• pre-tensioned 1400 tonne units erected by floating crane
• Majority of sub-structure on pile bents
• Represented the majority of the crossing
9 10
Role of the Contractor’s Checking Engineer Role of the Contractor’s Checking Engineer
11 12
3/10
3
Pile Cage Prefabrication
• Pile reinforcement cages
fabricated in 12m lengths
• Link reinforcement rolled onto
the pile cage
• Up to 3.0m diameter piles
Construction Yard Activities • Accurate assembly allows the
used of threaded couplers to
join cages
13 14
15 16
4/10
4
Site Construction Yard
Reinforcement storage Approach Bridge deck Deep Water Piles
precast segment
Concrete batching cutting and bending fabrication
plant
Site offices and staff
accommodation
17 18
19 20
5/10
5
Viaduct Deck
Pilecaps • 1500t viaduct deck units
brought out to deep water
using 3000t floating crane
• Temporary enclosure for pilecap
concreting and curing • Loaded onto multi-wheel
carrier
• Low level viaducts consist of pile bent
and in-situ cross beam below deck • Multi-wheel carrier moves
level deck unit out to launching
girder operating in shallow
water area inaccessible to
floating crane
• Units lifted onto bearings
using launching gantry
21 22
23 24
6/10
6
Viaduct Deck
Approach Bridge Balanced Cantilevers
25 26
27 28
7/10
7
Approach Bridge Balanced Cantilevers Approach Bridge Balanced Cantilevers
29 30
31 32
8/10
8
Approach Bridge Balanced Cantilevers Approach Bridge Balanced Cantilevers
33 34
35 36
9/10
9
Pylon Construction Pylon Construction
37 38
10/10
10