Basic Knowledge in Construction Management
Basic Knowledge in Construction Management
Basic Knowledge in Construction Management
in
Construction Management
Objective
responsibility
Construction Management Approach
(International Construction Industry)
Client
Construction
Management
Service
Contract Design
Designer Consultant
Contract Complete
Agreement Work
Contractor
Construction Management Approach
(Local Construction Industry)
Client
Design
Tender
DOH
Committee,
Designer
Internal QC,
Complete
Third party QC,
Contract
Agreement Work etc
Contractor
Quality Management System
within budget
SAFETY
Maintenance
• Preventive
• Routine Maintenance • Project Appraisal
• Corrective • Project Priority
• Periodic Maintenance
• Special Maintenance and
Rehabilitation
• Preliminary Design
• Emergent Maintenance
• Detail Design
• EIA, IEE, EMP (if required)
Budget Approval
Financing Scheme
Operation
• Traffic Management Construction
• Road Safety Management • Land Acquisition
• Law Enforcement (Speed, Access Control, ROW) • Procurement
• Roadway Inventory Management • Construction
How to prepare / implement our projects?
Planning Construction
Assistant Director/
Project Manager
Deputy Director
QC Engineer QC Engineer
SUBMISSIONS FROM THE
CONTRACTOR
Submission to the PM
Submittals DOH
All submittals required/implied in The
the Specifications Project Director
Contractor
Program
Guarantee
Project Engineer
TO
CC
RESPONSES BY PROJECT
ENGINEER
Basic Response to Submittals in Contract
Comment/Instruction/Approval by
Conditions
the Project Manager on:
TO
CC
Basic Response to Submittals in Contract
Conditions
Comment/Instruction/Approval by
Project Engineer on:
The
Proposal of Material Source DOH Contractor
Equipment Plan
Project Director
Traffic Management Plan
Mobilization Schedule
QC Engineer
TO
CC
Submittals in
Quality Control Report
The Contractor
DOH
Note:
Project Director
Contractor shall submit M/S.
DOH shall issue ITP & Check
NCR
form. Project Manager
QC Engineer shall report
Monthly QC report and shall
submit daily result to Project Project Engineer
Engineer and contractor. If
has non complyed the QC Engineer
te
ica
Project Director
ti f
er
tc
approval, if
en
approved
ym
needed
pa
ll
Bi
Project Manager
im
Cl a
comments
၁။အရည်အေသွးစစ်ေဆးမ]ေကာ်မတီ
QC Engineer
ေထာက်ခံချက်
၂။QC Report
Letter Numbering on JICA Loan
• From CSC
(1) Loan No.
– P17CS/DOH/Lxxxx (2) Originator
(1) (2) (3) (4) (3) Outgoing Entity
(4) Serial Number
• From DOH
– P17DOH/CS/xxxx
(1) (2) (3) (4)
• The Contractor
– TGO-01-Co.,Ltd/PM or PE/MS/2020-21/xxxx
Categorization of Documents Control