SP 1173
SP 1173
SP 1173
Document ID SP-1173
Security Unrestricted
Version 3.0
Keywords: This document is the property of Petroleum Development Oman, LLC. Neither the whole nor any part
of this document may be disclosed to others or reproduced, stored in a retrieval system, or transmitted in any form
by any means (electronic, mechanical, reprographic recording or otherwise) without prior written consent of the
owner.
Revision:3.0
Petroleum Development Oman LLC Effective:February, 2021
i DOCUMENT AUTHORISATION
Document Authorisation
ii REVISION HISTORY
The following is a brief summary of the recent revisions to this document. Details of all revisions prior to these are
held by the issuing department.
The related CMS Documents can be retrieved from the Corporate Management Portal (CMS).
TABLE OF CONTENTS
Introduction
i) DISTRIBUTION , INTENDED USE AND REGULATORY CONSIDERATIONS
Unless otherwise authorised by PDO, the distribution of this SP is restricted to Contractors and
Manufacturers/Suppliers nominated by PDO. Any authorized access to this SP does not constitute an
authorization to any documents, data or information to which the SP refers.
This specification is a revision of the Specification of the same number dated December 2019.
This specification is an amendment / supplementation of International Assosciation of Oil and Gas
Producers( IOGP) specification S-705 Version 1.0 published in June 2020.
The clauses of IOGP S-705 not supplemented or amended in this specification shall be considered
valid and applicable.
This specification shall be applied as a standalone document as modified in this SP and shall not be
read with any of the following documents:
IOGP S-705D: Data sheet for Welding of Pressure Containing Equipment and Piping;
IOGP S-705Q:Quality Requirments for Welding of Pressure Containing Equipment and Piping;
IOGP S-705L: Information Requirements for Welding of Pressure Containing Equipment and Piping.
1. Scope
1.1 Modify the clause as the following
b) Refer to Tank specification SP 2187 for storage tanks for Welding requirements.
2. Normative References
Add to the clause 2.0 as the following:
ASTM Standards
Standard Test Methods for Detecting Susceptibility to Intergranular Corrosion in Wrought, ASTM G 28
Nickel-Rich, Chromium-Bearing Alloys
Standard Test Methods for Pitting and Crevice Corrosion resistance of Stainless Steels and ASTM G48
related Alloys by the Use of Ferric Chloride Solution
Standard Practice for Cleaning, Descaling, and Passivation of Stainless Steel Parts, ASTM A 380
Equipment, and Systems
Material verification programme for new and existing alloy piping systems. API 578
5 Welding processes
5.1 Acceptable Welding Processes
Modify the Notes of Table 7 as the following
Replace Note 3 as the following
SMAW is not permitted for root pass in single sided welds where root pass is not removed.
Add Note 5 as the following
GMAW shall be applied only as mechanised or automatic process. GMAW welds shall be inspected by
UT. Semi automated GMAW shall not be used except for weld overlay clad restoration.
Add Note 7 as the following
GTAW shall be used for root run of small bore piping upto dia 3 inch ( DN 75) and for sour service piping
applications.
Add Note e) , When PWHT applied, attachment welds and branch welds shall be included.
PWHT for Piping Fabrication of Carbon Steel weldments shall be carried out as the following
Material Service Nominal PWHT requirement
thickness
of weld
Carbon (Sour) ≤20 mm PWHT is required, unless following conditions are met
steel piping Wet
1) WPS PQR is qualified on actual or higher thickness and with
weldments H2S
highest CE ( +0.03).
2) Preheat of 100 Deg. C shall be applied for thickness ≥ 12.7mm
>20 mm Mandatory PWHT
Butt Welds - Visual,MT/ PT, RT (and UT ,If any pass is welded with GMAW or FCAW process).
Fillet Welds- Visual, MT / PT.
Any weld, which fails to meet the acceptance criteria specified in applicable construction code, shall not be
permitted for further laboratory testing.
Each PQR shall include Hardness survey as per clause 11.5.4 and Macrotest as per clause 11.7.
PQRs for CRA materials shall include metallogrphic evaluation.
PQRs for piping application shall be carried out using piping components, in production welding position or
in 6G position.
For piping systems in high wet H2S / sour service, the Welding Procedure Qualification shall be carried out
on the same P-No. and Group-No. or same group and subgroup as used in production welding.
11.2.6 Tube ID shall be inspected as per clause 7.8.4. Unacceptable discolouration shall treated as per
ASTM A 380.
11.3 Additional Procedure Qualification Requirements for Duplex and Superduplex Stainless Steels
11.3.6 Corrosion and Impact Testing
11.3 6.2 Corrosion Test
12 Other Items
12.3 Weldoverlay and Clad Restoration( Back cladding)
Replace the clause as the following
12.3.1 Weld overlays shall be as per ASME Sec IX, Section 11 and as modified in Annex B.
12.6 Hardness testing – Production Testing
12.6.1 Replace the clause as the following
Hardness testing shall be carried out on 10% Production welds of CS sour service and for DSS welds.
If weld overlay is applied to restore the clad area of weld joints between clad components, at least one deposit
analysis per welding procedure per longseam and cicumferential seam in the vessel shall be performed.
If weld overlay is applied to the surface of equipment shells/dished end , deposit analyses shall be the greater
number of samples of the following:
( a) at least two analyses per 10 m2 (100 ft2) of overlay or fraction thereof;
( b) one analysis from each end of the shell/dish at locations that are diametrically opposed.
If weld overlay is applied to the surface of equipment components, deposit analyses shall be provided as
follows:
( a) one analysis for each welding procedure used;
(b) one analysis for each piece of equipment manufactured.
( c) at least one analysis for the smallest component welded with each procedure;
(c) at least one analysis for the largest component welded with each procedure.
If weld overlay is applied for surface repair of clad components or for restoration of surfaces where cladding
has been removed (other than weld seams), at least one deposit analysis shall be provided for each WPS.
B.7.1.1 End preparation for field joints of piping requiring PWHT,may be buttered ,then subjected to
PWHT,machines while during shop fabrication. The field joint shall be qualified without PWHT.