CIS4603 - Resource MGMT - Case2 - Answers
CIS4603 - Resource MGMT - Case2 - Answers
CIS4603 - Resource MGMT - Case2 - Answers
Instructions:
Work in groups of 2 to 3 students in each group. Your task is to read the case, develop a resource break
down structure, and create a time based cost baseline for the project.
Case:
Salem is the project manager for a Hardware upgrade project for a university. The project duration is 12
months. The project has two main deliverables, the hardware and the hardware installation and
configuration.
- 4 servers each server is 12,000, the servers need to be bought by the fourth month in the project.
- 60 desktop computers, each is for 4,000. 30 computers need to be bought in the 3rd month and 30
computers in the 6th month.
- 20 laptops each for 4,000. These need to be available in the 10th month.
- 5 printers , each for 1,000, these need to be available in the 9th month.
- Two full time technicians each at 10,000/month for 12 months
- 50% of a Security specialist at 30,000/month for 4 months, for the last 4 months.
- 30% of an AVA specialist at 20,000/month for 3 months, for the last 3 months.
1.1.2 120,00
Desktop 60 4,000 240,000 120,000 0
Contingency Reserve 69,100 2000 2000 14000 6800 2000 14000 2000 2000 4000 12100 4100 4100
Totals
22,000 22,00 154,000 74,800 22,000 154,00 22,000 22,000 44,000 133,100 45,10 45,100
Dr. Rula Kayyali 3 July 2020
760,100 0 0 0