COMMISSIONING CHECK LIST ‐ EARTHING 
PROJECT NAME :
MAIN CONTRACTOR DATE OF TEST
MEP CONTRACTOR EQUIPMENT EARTHING SYSTEM
CONSULTANT DOCUMENT REF. -
Earth Pit Ref.No Panel Ref:
GENERAL
REMARKS
SR.NO. DESCRIPTION
YES NO N/A

1 Ensure the materials used are as per the approved submittals

2 Ensure that the shop drawings used are approved by certain authorities.

3 Ensure that all located earth pit as per approved shop drawing

4 Ensure that earth rod is fixed properly

5 Ensure that the conductor loop from earth pit to another is installed.

6 Check the copper conductor is connected with earth electrode at earth pit.

7 Ensure that all bolts are tightened.

8 Ensure concrete inspection pit with cover is provided


Ensure that the transformer body earthing is terminated on the main earth bar
9
installed at the sub station
Ensure that earth bar of right size is installed in a proper location in the
10
electrical room
11 Ensure that earth conductor from L.V Switch gear is connected to earth bar
Ensure that the earth continuity conductor for the incoming/outgoing cables
12 and earth ring of the cable glands are terminated on earth bar/earth terminals of
the respective panels/DB's/Equipment/trunking etc..
13 Ensure all contact surfaces of connections are thorougly cleaned and tightned.

14 Ensure that test link is provided and all connections are tightned.
Check the continuty of earth cables from respective main earth busbar to earth
15
pits..
16 Ensure that earth pits and earth cables are labelled properly.

REMARKS / COMMENTS

Tested By M/s. ABL Verified By M/s. Al Ali Const.& Development


NAME:
SIGN:
DATE:
Witnessed By M/s. Atkins Approved By M/s. Hilton
NAME:
SIGN:
DATE: