Riser & I-Tube Clamp Installation Procedure
Riser & I-Tube Clamp Installation Procedure
Riser & I-Tube Clamp Installation Procedure
PROCEDURE
Client : ONGC
Date: 18.8.2011
Rev.: 0
TABLE OF CONTENTS
1. INTRODUCTION ............................................................................................................................................... 3
1.1 General...................................................................................................................................................... 3
2. REFERENCES, DEFINITIONS AND ABBREVIATIONS.................................................................................. 5
2.1 REFERENCES .......................................................................................................................................... 5
2.1.1 General Documents .................................................................................................................................. 5
2.1.2 Company Specifications, Codes and Standards................................................................................... 5
2.1.3 Project Documents .................................................................................................................................... 5
2.2 DEFINITIONS ............................................................................................................................................ 5
2.3 ABBREVIATIONS ..................................................................................................................................... 5
3. RESPONSIBILITY ............................................................................................................................................. 6
3.1 BARGE SUPERINTENDENT .................................................................................................................... 6
3.2 CHIEF ENGINEER .................................................................................................................................... 6
3.3 FIELD ENGINEER..................................................................................................................................... 6
3.4 BARGE FOREMAN................................................................................................................................... 6
3.5 ANCHOR FOREMAN ................................................................................................................................ 7
3.6 HSE OFFICER ........................................................................................................................................... 7
3.7 Diving Supervisor .................................................................................................................................... 7
4. DESCRIPTION .................................................................................................................................................. 8
4.1 Pre-installation checks............................................................................................................................ 8
4.2 MARKING CLAMPS POSITIONS ........................................................................................................... 10
4.3 REMOVAL OF ANODES & MARINE GROWTH .................................................................................... 10
4.4 INSTALLATION OF CLAMPS ................................................................................................................ 10
4.5 ALIGNMENT CHECK OF RISER/I-TUBE CLAMPS .............................................................................. 11
4.6 INSTALLATION OF HANG-Off CLAMP ................................................................................................ 11
1. INTRODUCTION
1.1 General
Oil and Natural Gas Corporation Limited, herein after, called as ‘Company’ is engaged in exploration &
exploitation of Mumbai High Field located about 160 km. West-North-West of Mumbai and Bassein Field
located about 80 km West-North West of Mumbai which are in the Arabian Sea on the continental shelf of
Western India. The fields are well developed, with an extensive infrastructure of wellhead platforms,
process platforms and pipelines.
ONGCL, Client has awarded the B-SERIES AND N-15 & N-16 PIPELINE PROJECT to VML-VMML
Consortium. The said project has been awarded as an EPC Contract with a scope of work appended below:
a. PIPE LAYING:
TOTAL LENGTH OF PIPELINE TO BE LAID IS 106.19 KM WHICH CONSISTS OF 14 SEGMENTS OF
PIPE LINES AS DETAILED BELOW:
• Five (5) nos. Gas Lift Lines out of which 3 line are rigid (MNP - N15, N15- N14, NV- N16), & the
balance 2 lines are flexible (N3 -WI2 & N1-WI5).
• Eight (8) nos. Well Fluid Lines (B188-B48, B105-B48, B48-B46, B46-MNP, N15-MNP, N16-MNP,
WI2-N3 & WI5-N1) – Rigid.
• One (1) no. Water Injection Line (N14- N18) – Flexible.
b. TIE-INS:
• Hook-up of Pipelines @ Process/ Well Platforms (either with the pre-installed risers, or the ones to
be installed by contractor during this project)
• Total tie-ins = 17 nos.
c. RISERS:
• Five (5) nos. Risers at NV, N1, N3, WI-2 & WI-5 Platforms.
d. I/J TUBES:
• Six (6) nos. I/J tubes to be installed at N14, N18, N1, N3, WI-2 & WI-5 Platforms.
e. TOPSIDE MODIFICATIONS:
• TOPSIDE MODIFICATION OF EXISTING WELL PLATFORM NV & NW.
• Installation of Lift gas launcher, associated piping & instrumentation, new stand-alone pneumatic
shutdown panel & extension of existing fire water sprinkler network, etc…
• Procurement of loose items for NV & NW Platforms.
• Hook ups at N14, N18, N1, N3, WI-2 & WI-5 platforms topside.
CONSORTIUM OF
VALENTINE MARITIME LIMITED & VALENTINE
MARITIME MAURITIUS LIMITED
RISER AND I-TUBE CLAMP INSTALLATION
PROCEDURE
f. B-SERIES AND N-15 & N-16 P/L Project has the following completion dates (as defined in NOA):
SCHEDULED COMPLETION
1) Segments: Completion Date :10.03.2012
• B-48 to B-46.
• B-46 to MNP.
2) Segments:
• B-188 to B-48 Completion Date: :10.04.2012
• B-105 to B-48.
3) Segments:
• N-15 to MNP. Completion Date: 15.05.2011
• N-16 to MNP.
• MNP to N-15.
• N-15 to N-14 (GL).
• NV to N-16.
• N-14 to N-18.
• WI-2 to N-3 (WF)
• WI-5 to N-1 (WF)
• N-3 to WI-2 (GL)
• N-1 to WI-5 (GL)
• Associated top side Modification at NV Platform.
4) Completion of Project in all respects Completion Date: 15.05.2011
(including handing over of loose materials for NV & NW)
2.1 REFERENCES
2.2 DEFINITIONS
Company/Client ONGCL
Contractor VML-VMML Consortium
Sub-Contractor Dunnimaa
Vendor Any organization selected & awarded by VMSL to supply Project Material
and/or Equipment.
2.3 ABBREVIATIONS
HSE Health, Safety and Environment
KP Kilometer Point
PPE Personnel Protective Equipment
TBA To Be Advised
VML-VMML Valentine Maritime Limited - Valentine Maritime (Mauritius) Limited.
CONSORTIUM OF
VALENTINE MARITIME LIMITED & VALENTINE
MARITIME MAURITIUS LIMITED
RISER AND I-TUBE CLAMP INSTALLATION
PROCEDURE
3. RESPONSIBILITY
This procedure shall be followed by all concerned onboard all marine units involved in Field Joint Coating
Operations. Specific responsibilities are as follows:
4. DESCRIPTION
4.1 Pre-installation checks
a) The standoff distance for the “hanger” and “fixed” clamps has to be checked on deck by measuring
the distance between the centre of brace clamp and the centre of the riser/I-tube clamp.
This distance is referred to as “K” in the drawings. The value of “K” is provided in series of drawings
showing the location of riser/I-tube and riser/I-tube clamps (see Appendix A).
All the measurements of “K” should be verified on deck and passed to the field engineer to compare
and check the variations with the drawings; and if variations are found, the decision might be taken
to modify clamps prior to any installation commencement.
b) Internal diameter of brace clamp should be measured and compared with the jacket braces
diameter (TABLE 1) to make sure there is no variation.
c) Diameter of riser/I-tube clamp should be measured and compared with riser/I-tube outer diameter
to make sure there is no variation
d) Testing bolts and nuts threads.
e) Any obstructions underwater, like for instance anodes, should be removed temporarily and then re-
instated afterwards.
Elevation OD of brace
Jacket Clamp No/type
(m) clamp
WI2-FC-A5 -40.000 610
WI2-AC-A6 -53.000 660
WI5-HC-A1 +6.700 610
WI5-AC-A2 +4.128 610
WI5-AC-A3 -7.000 508
WI5
WI5-AC-A4 -22.000 610
WI5-FC-A5 -37.000 610
WI5-AC-A6 -54.000 610
APPENDIX A
DRAWINGS
-+
-+ -+ TAUT
WIRE STD. PIPE
II SCHEMATICI
NOTES:
1. ALL DIMENSIONS ARE IN MM. UNLESS OTHERWISE SPECIFIED.
..
..II1f\1
.,.
OIL AND NATURAL GAS
~ CORPORATION LIMITED
onGt:
B46 SEruES, N15 & N16 PIPELINES
AND MODIFICATION PROmCT
CONSORTIUM OF
VALENTINE MARITIME LIMITED & VALENTINE
MARITIME MAURITIUS LIMITED
RISER AND I-TUBE CLAMP INSTALLATION
PROCEDURE
APPENDIX B
GUIDELINES FOR CLAMP INSTALLATION AT SOME SELECTED PLATFORMS
CONSORTIUM OF
VALENTINE MARITIME LIMITED & VALENTINE
MARITIME MAURITIUS LIMITED
RISER AND I-TUBE CLAMP INSTALLATION
PROCEDURE
B.0 INTRODUCTION
This appendix presents step-by-step procedure for clamp installation at selected platforms to give
barge crew some common guidelines for clamp installation of the whole project
Thorough study of this appendix will give tips for other platforms which is not mentioned herein
below.
B.1 RISER CLAMPS AT NV
1. Hanger clamp at elevation +6.7 m and subsea clamp at elevation -57.193 m shall be used for
marking the location by which taut wire will be passing.
2. At +6.7 m brace, a horizontal distance of 1228 mm will be measured from the inner side of the
jacket leg B2 along the brace to mark the location of the (center of the) hanger clamp; this
distance consists of:
• 1000 mm (distance from WP)
• plus the horizontal projection of the jacket leg from the WP to top brace, which can be
obtained by dividing the vertical projection over 8 (jacket batter)
3. The brace at -57.193 will be marked by the same fashion, so the distance will be:
8.525 𝑚𝑚 + 57.193 𝑚𝑚
1.0 𝑚𝑚 + = 9.215 𝑚𝑚
8
4. Taut wire will be erected from top brace to seabed passing through the two mark places as
mentioned above.
FIGURE 1
1000 mm 228 mm
5. As a check, diver shall measure the distances between intersection points of the taut wire with
the jacket braces and the jacket leg. These measurements should match the dimensions
calculated as above in step 2 and 3; if they are matching then diver can proceed with marking.
6. Diver to mark the locations where the taut wire and predefined jacket braces are intersecting.
7. For the clamp at elevation +1.6, riggers will be involved in marking. A distance will be measured
from the upper end of the diagonal brace at elevation +6.7 to tentatively mark the location of the
clamp; this distance is calculated to be 5.974 m (FIGURE 2); to get this distance, engineer will
CONSORTIUM OF
VALENTINE MARITIME LIMITED & VALENTINE
MARITIME MAURITIUS LIMITED
RISER AND I-TUBE CLAMP INSTALLATION
PROCEDURE
FIGURE 2
1. Hanger clamp at elevation +6.7 m and subsea clamp at elevation -40.0 m shall be used for
marking the location by which taut wire will be passing.
2. At +6.7 m brace, a horizontal distance of 2928 mm will be measured from the inner side of the
jacket leg A2 along the brace to mark the location of the hanger clamp; this distance (as in the
NV platform case) consists of :
• 2700 mm (distance for WP)
CONSORTIUM OF
VALENTINE MARITIME LIMITED & VALENTINE
MARITIME MAURITIUS LIMITED
RISER AND I-TUBE CLAMP INSTALLATION
PROCEDURE
• plus the horizontal projection of the jacket leg from the WP to top brace, which can be
obtained by dividing the vertical projection over 8 (jacket batter)
3. The brace at -40.0 will be marked by the same fashion, so the distance will be:
8.525 𝑚𝑚 + 40.0 𝑚𝑚
2.7 𝑚𝑚 + = 8.766 𝑚𝑚
8
4. Taut wire will be erected from top brace to seabed passing through the two mark places as
mentioned above.
5. As a check, diver shall measure the distances between intersection points of the taut wire with
the jacket braces and the jacket leg. These measurements should match the dimensions
calculated as above in step 2 and 3; if they are matching then diver can proceed with marking.
6. Diver to mark the locations where the taut wire and predefined jacket braces are intersecting.
7. For the clamp at elevation -53.0 m, diver will mark the clamp location at the diagonal brace
where the water depth is 53.0 m; and this will be tentative location as this marking is likely to
involve many inaccuracies.