Sample KRA Directory
Sample KRA Directory
Sample KRA Directory
INDEX
Sl. No. Position ( E7 ) Page No.
1 Head, HVDC Station 3
2 Head, Finance, RHQ 5
3 Head, O& M and construction Sub-station 7
4 Head, Law, RHQ 11
5 Head, Construction, RHQ 12
6 Head, HR, RHQ 14
7 Head, contracts and Materials 17
8 Head, Commercial, RHQ 19
9 Head, RE & ST 20
10 Head MIS, e-billing and ERP 21
11 Head, Employee Development Centre 22
12 Head, Regional Testing and Development Centre 23
13 Head, Telecom (Marketing and BD), region 24
14 Head, O&M and Construction of Lines 25
15 Head, Regional Engineering 28
16 Head, Internal Audit, Region 29
17 Head, QA&I – Regional Inspection 30
18 Head, safety, Region 32
19 Head, Telecom (O&M), Region 33
20 Head, Project Environment and Social Management 34
(PESM)
21 Head, IT, CC 35
22 Head, LD & C, CC 36
23 Head, Vigilance, CC 37
24 Head, QA&I, CC 38
25 Head, CP, CC 39
26 Head, Commercial, CC 40
27 Head, Engg, CC 41
28 Common KRAs across Positions and functions 42
HR Appraisal Page 1
POWERGRID:SAMPLE KRA DIRECTORY
INDEX
Sl. No. Position (E2-E6) Page No.
29 Regional S/S O&M 43
30 Regional TL O&M 44
31 Regional S/S Construction 45
32 Regional HR 46
33 Regional T/L Construction 47
34 Regional PESM 48
35 Regional Finance 49
36 Regional C&M 50
37 Regional Engineering Dept 51
38 Corporate HR 52
39 Corporate Finance 53
40 Corporate Asset Management 54
41 Corporate HRD 55
42 Corporate Engineering 56
43 Corporate Vigilance Dept. (Engg.) 57
44 Corporate CSR 59
45 Corporate LD& C 60
46 Corporate BDD 61
47 Corporate Commercial Dept. 62
HR Appraisal Page 2
POWERGRID:SAMPLE KRA DIRECTORY
8 Self-development
20. Undertake Finance for non-Finance course Date
(completion by date)
9 Employee Development
21. Average No. of person days of training
22. Multi skill ( No. of operation engineers inducted Percentage
into all maintenance works)
23. Interactive in-house trainings ( No. per year)
10 Employee Welfare
24. No. of family events in the year
HR Appraisal Page 3
POWERGRID:SAMPLE KRA DIRECTORY
11 Knowledge Management
26. No. of Papers/studies from the station at
international level seminars/ publications
27. No. of Papers/studies from the station at national
level
28. No. of Knowledge sharing and technology Percentage
upgrade sessions
29. No. of seminars conducted at the station on
technical areas
30. Technology transfer from the international
partners (No of areas of self-sufficiency in
maintenance from the predefined list)
12 Social welfare/ CSR
31. Budget in Rs. Lakhs
32. Construction of road in village ( Km) Percentage
33. No. of schools renovated
13 Individual efforts towards self/peer based learning, Percentage 5
Contribution in knowledge management/knowledge
sharing, subordinate development, contribution in
workgroup activities, etc.
HR Appraisal Page 4
POWERGRID:SAMPLE KRA DIRECTORY
2 Financial Concurrence
7. Submission to Concurrence/ Return (in days) Percentage
8. % of cases returned (Max)
3 Financial statements
9. Timeliness of submission(in days)
a. Audits(deviation from CC schedule / plan)
b. CERC Certificates
c. Quarterly Results( by the date in the
following month as per CC schedule)
d. Annual Results ( by the date in the
following month as per CC schedule) Percentage
10. Accuracy and Quality of statements 1-5 (Rating by
CC Poor/ Fair/ Good/V Good/ excellent)
11. MIS (incl. O&M expenditure, Construction, taxes
w.r.t. to Budget) as per schedule- % deviation
HR Appraisal Page 5
POWERGRID:SAMPLE KRA DIRECTORY
% of payments as e-payments
7 Audits
17. Coordination with External Auditors 1-5 (Poor/
Fair/ Good/V Good/ excellent)
18. Completion of internal audit/ Govt audit (within
days ) Percentage
19. Observations on Audits NC/ Half Margin/ Audit
Para
20. Time to resolve observations (in days)
a. Major
b. Minor
9 Knowledge Management
21. No. of Knowledge sharing sessions Percentage
22. No. of seminars conducted at the station on Direct
taxation
10 Self-development
23. Undertake Certification in GAAP laws (completion Percentage
by date)
11 Employee Development
24. Average No. of person days of training
25. Multi skill ( No. of cases from Bills/ Percentage
bills/Establishment)
26. Training of F&A execs in IFRS (By date )
12 Banking and cash
27. Max number of days when minimum balance was Percentage
not maintained in the year
13 Individual efforts towards self/peer based learning, Percentage 5
Contribution in knowledge management/knowledge
sharing, subordinate development, contribution in
workgroup activities, etc.
HR Appraisal Page 6
POWERGRID:SAMPLE KRA DIRECTORY
3 Maintenance Excellence
1. Outages (Maximum no of Forced Tripping)
2. Auto Reclosure success rate (%)
3. Maintenance
a. % adherence to the AMP
b. Finalisation of AMP by date
HR Appraisal Page 7
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 8
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 9
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 10
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 11
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 12
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 13
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 14
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 15
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 16
POWERGRID:SAMPLE KRA DIRECTORY
3 Operational Excellence
10. Contract Closure during the year(% of
Matured Contracts )
11. Post award contract services
Time taken in days to process LD
proposals
Time taken to release CPG/ Security
deposit
Time taken to process first PV bills
i. Checking and verification Number of
(days) days/
ii. Processing
Time taken to finalise new items Percentage
Processing of time extension proposals
Processing of amendments
12. Liquidation of surplus inventory (start to
finish in days )
13. Scrap disposal (start to finish in days )
14. Getting and uploading of BOQ for e-billing
(days)
15. Release of EMD for unsuccessful bidders as
per tender (days)
16. Processing of recovery proposal within days
of contract work completion
17. Vetting of B.G.
18. Issue of Excise Duty Exemption certificates
/Project Authority Certificate
19. Processing of site proposal for RHQ proposals
HR Appraisal Page 17
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 18
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 19
POWERGRID:SAMPLE KRA DIRECTORY
2 Sub-transmission Commissioning
7. Budget utilization Date
8. Completion (By date)
3 Relationship with SEB / DM/ SP/Railways/
contractors/REC/ Power departmet
9. No. of meetings per month with Contractors/ PRM
per month Date
10. Minimum Meetings frequency with other
stakeholders per quarter
11. Railway Clearance ( By date)
4 No. of packages closed out of 8 Percentage
5 Contractor Payments (response time for verification for Number
bills in days) of Days
6 Knowledge management (No. of published Articles in
national level journals on Rural electrification- some Percentage
learnings and best practices )
7 Systems and processes-Automated system for project Date
monitoring (completion by date)
8 Self development- Undertake a course on project Date
management (completion by date)
9 MIS-Updation frequency on Web-based monitoring tool Percentage
(Times per quarter )
10 Individual efforts towards self/peer based learning, Percentage 5
Contribution in knowledge management/knowledge
sharing, subordinate development, contribution in
workgroup activities, etc.
HR Appraisal Page 20
POWERGRID:SAMPLE KRA DIRECTORY
4 MIS
7. Rating by Appraiser on the timeliness and quality Percentage
of MIS
HR Appraisal Page 21
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 22
POWERGRID:SAMPLE KRA DIRECTORY
4 Safety
Accidents Percentage
Awareness Programs
5 Employee Engagement Percentage
Family meets (No.)
6 Employee Development
Training programs (No.) Percentage
7 Knowledge management
No. of studies/ papers from the RTDC Percentage
published
8 Technological Up gradation
Procurement and commissioning of ….. testing Date
equipment ( By date)
9 Systems and processes
Development and approval of protocol and SOP Date
for ….test(By date)
10 Accreditation of the EDC by external agencies as
per predefined Plan(By date) Date
HR Appraisal Page 23
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 24
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 25
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 26
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 27
POWERGRID:SAMPLE KRA DIRECTORY
2 Contract Closing
4. Reconciliation proposal to be cleared by Engineering
(Days) Number
5. Recovery/ LOA deviation/Billing Break up/ BOQ of days
Proposal approval (Days)
HR Appraisal Page 28
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 29
POWERGRID:SAMPLE KRA DIRECTORY
3 Vendor satisfaction
Av. Rating on quality demanding, fair and hassle free
relationship with Power Grid on 1-5 scale Percentage
4 User satisfaction
Av. Rating on value adding and hassle free services
on 1-5 scale Percentage
HR Appraisal Page 30
POWERGRID:SAMPLE KRA DIRECTORY
9 Quality assurance
3. Pre dispatch inspection for L1 items (Intimation
to completion in days ) Number of
4. Inspection of materials at manufacturers works days
(Intimation to completion in days )
5. No. of FQA audit per site per month
HR Appraisal Page 31
POWERGRID:SAMPLE KRA DIRECTORY
2 Preventive Parameters
1. % of persons certified through safety trainings
2. No. of trainings programmes
a. Civil Works safety training
b. Erection safety
c. Stringing Percentage
d. O&M safety including safety
3. No. of Safety Audits
4. Person days of Safety trainings (no.)
5. Qualified Safety Engineers at site
6. % of eligible employees provided with
e. Safety Shoes
f. Safety belts
g. Helmets
h. Others (Gloves, Goggles etc.)
3 PPE procurement Percentage
HR Appraisal Page 32
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 33
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 34
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 35
POWERGRID:SAMPLE KRA DIRECTORY
5 Support to others
13. BDD for offer submission (Extent of value
add as per BDD on a scale of 1-5)
14. Cost Engg (Extent of value add as per Cost Percentage
engg. on a scale of 1-5)
HR Appraisal Page 36
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 37
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 38
POWERGRID:SAMPLE KRA DIRECTORY
5 ECM
Agenda (by date) Date
ATR (frequency)
6 External agency Coordination
MoP references Percentage
PQs
Liaison with MoP, MoF, CEA
7 Reporting
QPR Externally aided projects Percentage
QPR NTPC
8 Individual efforts towards self/peer based learning, Percentage 5
Contribution in knowledge management/knowledge
sharing, subordinate development, contribution in
workgroup activities, etc.
HR Appraisal Page 39
POWERGRID:SAMPLE KRA DIRECTORY
3 Agreements
Signing BPTA with beneficiaries Percentage
Signing of IA with generators
4 Filling of appeals in tribunals Percentage
HR Appraisal Page 40
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 41
POWERGRID:SAMPLE KRA DIRECTORY
Note: If the special projects are not there in the assessment Percentage
period, this weight will be shifted equitably to other
parameters.
10 Individual efforts towards self/peer based learning, 5
Contribution in knowledge management/knowledge
sharing, subordinate development, contribution in
workgroup activities, etc.
HR Appraisal Page 42
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 43
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 44
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 45
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 46
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 47
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 48
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 49
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 50
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 51
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 52
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 53
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 54
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 55
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 56
POWERGRID:SAMPLE KRA DIRECTORY
5 MIS
17. Monthly, Quarterly and Half year
reports to CC (Timeliness and Percentage
comprehensiveness.)- Rating by
Corporate Vigilance on 1-5 Scale
6 Self development
HR Appraisal Page 57
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 58
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 59
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 60
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 61
POWERGRID:SAMPLE KRA DIRECTORY
HR Appraisal Page 62