Nothing Special   »   [go: up one dir, main page]

Transport Impact Assessment: South West Amhara Iaip & RTC Facilities, Ethiopia

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 35

TRANSPORT IMPACT ASSESSMENT

SOUTH WEST AMHARA IAIP & RTC


FACILITIES, ETHIOPIA
Report Produced by:
WSP in collaboration with Zereu Girmay Environment Consultancy (ZGEC)

DRAFT
Date: December 2017
TRANSPORT IMPACT
ASSESSMENT
SOUTH WEST AMHARA IAIP &
RTC FACILITIES, ETHIOPIA
REPORT PRODUCED BY:
WSP IN COLLABORATION WITH ZEREU GIRMAY
ENVIRONMENT CONSULTANCY (ZGEC)

REPORT (DRAFT)

PROJECT NO.: 23669


DATE: NOVEMBER 2017
APPENDIX

TABLE OF CONTENTS

1 INTRODUCTION..........................................1
1.1 Background............................................................. 1

1.2 Scope of work.......................................................... 1

2 FINDINGS OF THE SCOPING REPORT...3


2.1 Air quality................................................................3

2.2 Noise........................................................................3

2.3 Traffic.......................................................................3

3 PROJECT DETIALS...................................5
3.1 Type & Extent of the developments......................5
3.1.1 Bure IAIP............................................................................. 5
3.1.2 Motta RTC........................................................................... 5

3.2 Phasing of the development..................................5

3.3 Approval of Submissions......................................5

4 LIAISON & DATA COLLECTION................6


4.1 Liaison.....................................................................6

4.2 Site Visits................................................................6

4.3 Data sources...........................................................6

4.4 Latent Developments.............................................6

4.5 Road Network & Master Planning.........................6

5 SITE LOCATION & SURROUNDING ROAD


NETWORK..................................................7
5.1 Bure IAIP..................................................................7
5.1.1 Site Location....................................................................... 7
5.1.2 Road network description................................................... 9

5.2 Motta RTC.............................................................. 10


5.2.1 Site Location..................................................................... 10
5.2.2 Road network description................................................... 11

6 GENERAL TRAFFIC INFORMATION.......13


6.1 Development Access............................................ 13

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
APPENDIX

6.2 Parking Provision.................................................. 13

6.3 Public & Non-Motorised Transport assessment 13


6.3.1 Bure IAIP........................................................................... 13
6.3.2 Motta RTC......................................................................... 13

7 TRAFFIC FLOWS & TRIP GENERATION 14


7.1 Existing Traffic Flows........................................... 14

7.2 Latent Traffic......................................................... 14

7.3 Development Traffic Generation..........................14

7.4 Capacity Analysis................................................. 15

8 TRAFFIC IMPACT ASSESSMENT...........16


8.1 IMPACT DESCRIPTION AND DEFINITION...........16
8.1.1 Impact Definition............................................................... 16
8.1.2 Description of Impacts....................................................... 16
8.1.3 Nature of Impact................................................................ 16
8.1.4 Type of Impact.................................................................. 16
8.1.5 scale of Impact.................................................................. 17
8.1.6 Duration of Impact............................................................. 17
8.1.7 probability.......................................................................... 17
8.1.8 Severity.............................................................................. 17
8.1.9 Evaluation of Significance of Impact................................. 19
8.1.10 Categories of impact significance..................................... 20

8.2 Traffic Impact Assessment per facility................21


8.2.1 Bure IAIP........................................................................... 21
8.2.2 Motta RTC......................................................................... 22

9 CONCLUSIONS &
RECOMMENDATIONS............................23

10 BIBLIOGRAPHY.......................................25

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
APPENDIX

TABLES
TABLE 2-1 POTENTIAL CONSTRUCTION
AND OPERATION RISKS
ASSOCIATED WITH TRAFFIC.....3
TABLE 8-1 PROBABILITY RATING OF
IMPACT....................................... 17
TABLE 8-2 DEFINITIONS OF SEVERITY
USED IN THE ESIA FOR
ENVIRONMENTAL
RECEPTORS.............................. 17
TABLE 8-3 DEFINITIONS OF SEVERITY
USED IN THE ESIA FOR SOCIO-
ECONOMIC RECEPTORS.........19
TABLE 8-4 SIGNIFICANCE MATRIX
NEGATIVE IMPACTS................20
TABLE 8-5 SIGNIFICANCE MATRIX
POSITIVE IMPACTS..................20
TABLE 8-6: IMPACT ASSESSMENT OF
TRAFFIC – BURE IAIP................21

FIGURES
FIGURE 5-1 BURE IAIP SITE LOCATION........7
FIGURE 5-2 BURE IAIP LAYOUT.....................8
FIGURE 5-3: PHOTO SHOWING THE FEDERAL
HIGHWAY NO. A3_5 AT THE
PROPOSED IAIP ENTRANCE
(SOUTH DIRECTION)..................9
FIGURE 5-4: PHOTO SHOWING THE FEDERAL
HIGHWAY NO. A3_5 AT THE
PROPOSED IAIP ENTRANCE
(NORTH DIRECTION)..................9
FIGURE 5-5 MOTTA RTC SITE LOCATION. . .10
FIGURE 5-6 MOTTA RTC LAYOUT................10
FIGURE 5-7 IMAGE OF CURRENT ACCESS
ROAD.......................................... 12
FIGURE 5-8 IMAGE FEDERAL HIGHWAY
NO.B_31...................................... 12
FIGURE 6-1 PROPOSED ADDITIONAL
VEHICLE AND NMT ACCESS....13
FIGURE 7-1 PROPOSED TYPICAL IAIP MAIN
ACCESS CONFIGURATION.......15

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
APPENDIX

1 INTRODUCTION
1.1 BACKGROUND
The United Nations Office for Project Services (UNOPS) has appointed WSP, in collaboration with
Zereu Girmay Environmental Consultancy (ZGEC) to undertake the required Environmental and
Social Impact Assessment (ESIA) of the proposed Bure Integrated Agri Industrial Park (IAIP) and
the accompanying Motta Rural Transformation Centre (RTC). The facilities will be located in the
South West Amhara Region of Ethiopia.
The objective of the ESIA is to obtain environmental certification for the proposed development from
the Ministry of Environment, Forestry and Climate Change (MEFCC). The ESIA is to be undertaken
in line with the African Development Bank (AfDB) standards and local Ethiopian legislation.
The potential traffic impacts of the proposed Project and the need for a specialist Traffic Impact
Assessment (TIA) was identified in the ESIA Scoping Report for the proposed Amhara IAIP and
RTC ESIA.

1.2 SCOPE OF WORK


The TIA consist of the following two components:
— Traffic Impact: input to ESIA Scoping Report.
— Traffic Impact Assessment: this report.
The TIA assesses the expected traffic related impacts of the proposed facilities during the operation
phase only. The construction phase traffic impact was only briefly noted due to the volume of
construction related traffic (material deliveries, personnel, etc.) that cannot be determined at this
stage. The proposed IAIP and associated RTC are intended to be long term operational facilities (i.e.
are not intended to be decommissioned in the near future). As such the potential traffic impact of the
decommissioning phase was also not considered further.
The following documents were reviewed to inform the Scope of Work of the TIA, namely:
— African Development Bank’s IESIA Guidelines, Safeguards and Sustainability Series, Volume 2,
Issue 1-3, dated December 2015.
— Ethiopian Roads Authority: on-line information.
Limited requirements are stated in these documents with regards to the scope of work for a TIA
for these type of developments. Therefore, the scope was informed by the requirements of the
South Africa Committee of Transport Officials, South African Traffic Impact and Site Traffic
Assessment Manual, TMH16, Vol. 1, Version 1, August 2012. Also refer to Section 2.3.
The scope covers inter alia the following:
— Description of the extent of the development, including location and land-use/s.
— Description of the phased development of the facility (if applicable).
— Record of liaison.
— Record of site visits.
— Description of the local and potentially affected road network, including planning and comment on
the road condition, where information is available.
— Description of latent developments in the vicinity of the facility that may also have an impact on
the local road network, where information is available.
— Assessment of the required site access and parking requirements.
— Assessment of expected trip generation (operational phase).

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
Page 1
APPENDIX

— Capacity analysis of affected local intersections (operational phase only).


— Assessment of public transport and non-motorised transport requirements.
— Recommendations and conclusions with regards to the required transportation upgrades and/or
mitigating measures.

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
Page 2
APPENDIX

2 FINDINGS OF THE SCOPING


REPORT
The Scoping report identified various traffic related potential impacts on the study area of the IAIP
and RTC. These are briefly discussed below.

2.1 AIR QUALITY


— Dust and vehicle tailpipe emissions caused by vehicle movements on the access roads and the
internal roads on each site during the construction and operational phases.
— Air quality may be affected due to these activities, and may impact the surrounding residential
receptors.
— The Scoping report recommended an Air Quality Impact Assessment and GHG emissions
monitoring and reporting studies should be undertaken in the ESIA Phase.
— The transport related air quality impacts will be assessed in the Air Quality Assessment and GHG
Emissions assessment, and was therefore not assessed further in this study.

2.2 NOISE
— Noise levels are expected to increase due to increased vehicle movements on the access roads
and the internal roads on each site during the construction and operational phases.
— Increased noise emissions may impact the surrounding noise sensitive receptors.
— The Scoping report recommended a Noise Impact Assessment should be undertaken in the ESIA
Phase.
— The transport related noise impact will be assessed in the Noise Impact Assessment, and was
therefore not assessed further in this study.

2.3 TRAFFIC
— The expected produce through-put and related vehicle volumes for deliveries and distribution to
and from the IAIP and the RTC is not known. However, the interaction between community
members using these routes with the increased Project traffic from the construction phase
onwards, may increase the risk of traffic accidents.
— A breakdown of potential construction phase and operational phase traffic related impacts and
ratings are provided in Table 2-1.
Table 2-1 Potential construction and operation risks associated with traffic

DESCRIPTION PROBABILITY CONSEQUENCE RISK LEVEL


Increased vehicle volumes on the local roads
may impact on the safety of the community in
the area, especially vulnerable non-motorised 3 2 Medium
transport users (pedestrians, cyclists, etc.)
(construction)
Increased vehicle volumes on the local roads
may impact on the safety of the community in
the area, especially vulnerable non-motorised 4 3 High
transport users (pedestrians, cyclists, etc.)
(operational)

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
Page 3
APPENDIX

— The Scoping report recommended that a Traffic Study should be undertaken in the ESIA Phase.
— It is recommended that investigations are made into the existing weekday traffic volumes on the
access road to the IAIP and the local roads in the vicinity of the developments. The estimated
vehicle volumes are to take cognisance of the produce deliveries and distribution, as well as
staff trips to and from the facilities.

The ESIA listed the following requirements for the TIA:


— Assess the volume of increased traffic that will result from the proposed IAIP and RTC sites.
— Whether the existing infrastructure will be able to handle the resultant volumes (i.e. whether
design amendments to the federal highways need to be made to facilitate trucks accessing
or departing the sites).
— Determine the possible impact the increased volumes will have on safety of the community in the
area.
— Identification of mitigation measures in light of any significant negative impacts identified.

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
Page 4
APPENDIX

3 PROJECT DETIALS
3.1 TYPE & EXTENT OF THE DEVELOPMENTS

3.1.1 BURE IAIP


The proposed Bure IAIP falls under the jurisdiction of Bure Town as it is located approximately 4 km
south east of the town in the South West Amhara Region. The site abuts the federal highway No. A3
which connects Addis Ababa and Bahir Dar which are approximately 400 km south and 150 km
north respectively. The site is part of the industrial master plan of Bure, which renders the advantage
of utilising the industrial infrastructure such as power, water, stormwater systems and road networks.
The site is geographically located between 1182481.036 N to 1184267.076 N, and 288737.915 E to
292314.594 E (UTM Coordinates) in the West Gojjam Zone of South West Amhara.
The proposed Bure IAIP is a pilot facility with a site area of 260.56 hectares (ha) out of a total 1,000
ha of land that has been identified for potential use. Based on the success of the project the IAIP will
be expanded within the remainder of the earmarked land. Note, this report only pertains to the
assessment of the 260.56 ha pilot development. Future expansion of the IAIP will require separate
environmental and social assessments to be undertaken. The growing area to be serviced by the
IAIP is approximately 398,059 ha with the main farming activities in the area consisting of maize,
sesame, potato, live animal (cattle, goat, sheep) dairy and meat, poultry and honey.
The predominant land uses on the site include farming (pastoral and crops) and residential
activities. As per the land tenure of Ethiopia the land is owned by the government. The western and
eastern portions of the site are utilised by the government for crops with the central portion being
leased to private individuals for residential and farming purposes.

3.1.2 MOTTA RTC


The proposed Motta RTC site is located directly east of the town of Motta, 120 km south west of
Bahir Dar, and 100 km west of the Bure IAIP. The proposed site falls under the jurisdiction of Motta
town, in the Hulet Ej Enese Woreda which is located in the Misraq Gojam Zone of the South West
Amhara Region. The proposed RTC is located in close proximity to the federal highway no. A3, that
links Dejen with Bahir Dar. The site is geographically located between 1224437.024 N to
1224883.549 N and 378948.322 E to 379342.918 E (UTM coordinates), with an elevation of
approximately 2,487 m above sea level.

3.2 PHASING OF THE DEVELOPMENT


The implementation planning of the facility is as follows:
— Commencement of construction: 2017
— Construction period: 24 months
— Commencement of operational phase: 2020
— Operational lifespan: long-term

3.3 APPROVAL OF SUBMISSIONS


This report will be subject to approval from the relevant roads authorities, and will be submitted as
part of the ESIA process.

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
Page 5
APPENDIX

4 LIAISON & DATA COLLECTION


4.1 LIAISON
Refer to the full ESIA Report (Section 7), for the detailed Stakeholder Engagement activities.

4.2 SITE VISITS


Site visits were undertaken during August and September 2017 to assess the proposed site
access, access roads and to undertake high-level traffic counts.

4.3 DATA SOURCES


The following project specific data sources were assessed:
— Preliminary Scoping Report for the proposed Amhara IAIP and RTC Environmental and Social
impact Assessment, undertaken by WSP in June 2017.
— Mahindra Consulting Engineers, Amhara Design and Detailed Engineering Documents and
Drawings, June 2017.
— Scoping Report for the proposed Bure IAIP and Motta RTC ESIA, undertaken by WSP, November
2017.
— Mahindra, Integrated Agro Industrial Park – Bure, Development Control Regulation, Release 1,
October 2017.

4.4 LATENT DEVELOPMENTS


There are no known large-scale latent developments in the vicinity of the sites, therefore
no Cumulative Transport Impacts are expected on the local road networks.
— No structure plans were available for the study areas, except for a high-level plan of Bure Town.

4.5 ROAD NETWORK & MASTER PLANNING


There are no known new or additional local roads or federal highways planned in the vicinity of
the sites or the study areas.

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
Page 6
APPENDIX

5 SITE LOCATION &


SURROUNDING ROAD NETWORK
5.1 BURE IAIP

5.1.1 SITE LOCATION


The proposed Bure IAIP is located approximately 4 km south east of Bure in the South West Amhara
Region. The site abuts the federal highway No. A3_5, Section 504/1, which connects Addis Ababa
and Bahir Dar which are approximately 400 km south and 150 km north respectively. The site is
geographically located between 1182481.036 N to 1184267.076 N, and 288737.915 E to
292314.594 E (UTM Coordinates) in the West Gojam Zone of South West Amhara.
Refer to Figure 5-1 for the locality of the development, Figure 5-2 for the proposed layout.
Figure 5-1 Bure IAIP site location

FEDERAL HIGHWAY NO. A3

Source: GoogleMaps

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
Page 7
APPENDIX

Figure 5-2 Bure IAIP Layout

Source: Mahindra Consulting Engineers

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
Page 8
APPENDIX

5.1.2 ROAD NETWORK DESCRIPTION


The local road network primarily consist of Federal Highway No. A3_5, Section 504/1, which connects
Addis Ababa and Bahir Dar which are approximately 400 km south and 150 km north respectively.
The highway is a single carriageway surfaced road, with 1 lane per direction in the vicinity of the
future access.
The road is suitable to provide vehicle access and connectivity to the development, pending the
provision of a suitable local access that takes cognisance of vehicle and Non-motorised transport
(NMT) safety. Refer to Figure 5-3 and Figure 5-4 for images of the Federal Highway No. A3_5 at
the proposed IAIP access.
Important note, the condition of the road was not assessed, therefore sections of this or other access
roads to the IAIP may currently be in a poor condition, dangerous or partially impassable, for example
the roadway width is reduced. The additional traffic due to the IAIP could therefore increase the road
safety risks and accident potential in these areas.
Figure 5-3: Photo showing the Federal Highway No. A3_5 at the proposed IAIP entrance (south
direction).

Source: ESIA team site investigations

Figure 5-4: Photo showing the Federal Highway No. A3_5 at the proposed IAIP entrance (north
direction).

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
Page 9
APPENDIX

Source: ESIA team site investigations

5.2 MOTTA RTC

5.2.1 SITE LOCATION


The proposed Motta RTC site is located directly adjacent and to the east of the town of Motta, 120 km
south west of Bahir Dar, and 100 km west of the Bure IAIP. The proposed RTC is located in close
proximity to the federal highway no. B_31, which links Dejen with Bahir Dar. The site is
geographically located between 1224437.024 N to 1224883.549 N and 378948.322 E to 379342.918
E (UTM coordinates), with an elevation of approximately 2,487 m above sea level.
Refer to Figure 5-5 for the locality of the development and Figure 5-6 for the proposed internal layout.
Figure 5-5 Motta RTC site location

FEDERAL HIGHWAY NO. B_31

Source: GoogleMaps
Figure 5-6 Motta RTC Layout

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
Page 10
APPENDIX

Source: Mahindra Consulting Engineers

5.2.2 ROAD NETWORK DESCRIPTION


The proposed RTC is located close to federal highway no.B_31. Entrance to the RTC is to be
obtained from the south-west corner of the site via a secondary road leading off the highway, and will
exit the RTC at the south-east corner. Two additional entry and exit points are identified for future
expansion along the northern boundary of the site.
The highway is suitable to provide vehicle access and connectivity to the development, pending the
provision of a suitable and safe direct access off the highway and an upgraded access road. The
access locations off the highway must take cognisance of vehicle and Non-motorised transport (NMT)
safety. Note that NMT movement are very prevalent along the access road, with developments
directly adjacent to it. Access must be maintained to these properties, refer to Figure 5-7 for an image
of the current access road to the highway. Figure 5-8 shows the existing federal highway no. B_31 at
the RTC site.
Important note, the condition of the highway was not assessed, therefore sections of this or other
access roads to the RTC may currently be in a poor condition, dangerous or partially impassable, for
example the roadway width is reduced. The additional traffic due to the RTC could therefore increase
the road safety risks and accident potential in these areas.

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
Page 11
APPENDIX

Figure 5-7 Image of current access road

Source: ESIA team site investigations


Figure 5-8 Image federal highway no.B_31

Source: ESIA team site investigations

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
Page 12
APPENDIX

6 GENERAL TRAFFIC INFORMATION


6.1 DEVELOPMENT ACCESS
The vehicle accesses to the IAIP and the RTC must be designed to the relevant National
standards, namely the Ethiopia Road Authority design standards. Also refer to Section 8.2.

6.2 PARKING PROVISION


All parking provision will be provided on-site, and parking on individual erven will be subject to the
Development Control Regulations of the sites. The parking provision will be in-line with the zoning of
each internal erf of the IAIP and RTC.

6.3 PUBLIC & NON-MOTORISED


TRANSPORT ASSESSMENT

6.3.1 BURE IAIP


The town of Bure is located near the site, therefore public transport may not be required to transport
workers to the site. Small scale services like minibuses may however be required to transport
workers from further afield. The type and extent of the services cannot be assess at this stage, and
may have to be provided in incremental stage as the number of workers on-site increases.
— A suitable public transport stop should be provided on-site, to ensure safety of passengers waiting
for transport.
— Due to the location of the site close to a residential area (town), non-motorised transport may be
present along the federal highway.
— An additional NMT access should be provided off the roundabout located on the north-western
edge of the site. This will allow a shorter and more direct access to the site from the town, and
will also decrease NMT and public transport movements along the federal highway to the main
access. See Figure 6-1 for the proposed location of the NMT access, and also refer to Section
8.2. Also refer to Section 7.4 with regards to an additional vehicle access.

6.3.2 MOTTA RTC


The town of Motta Bure is located directly adjacent to the RTC, therefore public transport may not
be required to transport workers to the site. Small scale services like minibuses may however
transport workers. The he type and extent of the services cannot be assess at this stage, and may
have to be provided in incremental stage as the number of workers on-site increases.
— A suitable public transport stop should be provided on-site, to ensure safety of passengers waiting
for transport.
— Due to the location of the site directly adjacent to the town, non-motorised transport may be
present along the access road and federal highway. Refer to Section 8.2.
— It is recommended that NMT facilities (sidewalks) be provided along the access road between the
RTC and the federal highway.

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
Page 13
APPENDIX

Figure 6-1 Proposed additional vehicle and NMT access

Proposed Additional
Access Point

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
Page 13
APPENDIX

7 TRAFFIC FLOWS &


TRIP GENERATION
7.1 EXISTING TRAFFIC FLOWS
Sample traffic counts were undertaken by Mahindra along Federal Highway No. A3 near the proposed
IAIP access. The traffic flow was approximately 632 veh/hr, of which 478 veh/hr was local traffic
(three wheel rickshaw taxis that travel back and forth along the highway). The remaining 144 veh/hr
was other traffic.
Traffic counts are not available for Federal Highway No. B_31 close to the RTC.

7.2 LATENT TRAFFIC


There are no known large-scale latent development in the vicinity of the sites that will
general additional traffic in future. Also refer to Section 4.4.

7.3 DEVELOPMENT TRAFFIC GENERATION


Mahindra calculated the expected trip generation of the site to determine the pavement structure
requirements for the design life of the facilities. The method to calculate the Average Annual Daily
Traffic (AADT) was as per the Ethiopian Roads Authority Manual for agri-processing and non-agri
processing areas.

BURE IAIP – 5,864 AADT (VEH/DAY) FOR THE FULLY DEVELOPED SITE

— Approximately 5,891 vehicles In + Out at the access.


— During an 8-hour work day, and allowing an additional 2 hours for arrival and departure, the
average vehicle volume is approximately 587 veh (In + Out) per hour. This is a high volume, and
capacity issues are expected.
— The workday AM and PM peak hour vehicle volumes were estimated as 30% per peak of the
AADT. The AM and PM peak volumes will therefore be approximately 1,759 veh/hr (In + Out) at
the access. This is a high volume, and capacity issues are expected.
— Note that the traffic generation estimates seems excessive for the type and extent of the
development due to the following reasons:
o Land-uses such as raw material storage is not expected to attract large numbers of workers.
o The estimates equal 25,796 persons on-site daily.
o No provision is made for NMT trips to the site for workers or shoppers. The proximity of the
IAIP to the town should generate a percentage of NMT users. All trips are stated as vehicle
trips (buses, cars, etc).
Mahindra has subsequently stated that they confirm their trip generation calculations.

MOTTA RTC – 126 VEH/DAY FOR THE FULLY DEVELOPED SITE

— Approximately 126 vehicles In + Out per day at the access.


— This is a very low volume, and no traffic safety or capacity issues are expected.

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
Page 14
APPENDIX

7.4 CAPACITY ANALYSIS


BURE IAIP
A capacity analysis of the access intersection is necessary due to the expected high peak hour
volumes to and from the site and moderate volumes along the federal highway.
It is recommended that due to the high traffic volumes at the IAIP access, the typical access
configuration should be as follows, refer to Figure 7-1. The additional turning lanes on the access
road to the site will improve the operation and safety of the intersection. Note, the configuration must
be approved by the roads authority.
If the full trip generation is considered, this intersection configuration will not provide sufficient
capacity. The provision of a large scale intersection, signalisation or grade separation may not be
feasible. It is therefore recommended that a second vehicle and pedestrian access be provided to the
IAIP via the adjacent road network to the north-west of the site. Refer to Figure 6-1.
Figure 7-1 Proposed typical IAIP main access configuration

MOTTA RTC

A capacity analysis of the access road intersection with the Federal Highway is not necessary due
to the low peak hour trip generation.

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
Page 15
APPENDIX

8 TRAFFIC IMPACT ASSESSMENT


8.1 IMPACT DESCRIPTION AND DEFINITION

8.1.1 IMPACT DEFINITION


Environmental impacts from planned and non-planned activities during all phases of the Project are
assessed on the basis of detailed knowledge and industry experience of these activities. For the
purpose of this ESIA an environmental or socio-economic impact is defined as:
“Any change to the environment, whether adverse or beneficial, wholly or partially resulting from
an organisation’s activities or services.” (ISO 14001)
Prediction of impacts is an objective exercise to determine what is likely to happen to the environment as a
consequence of the Project and its associated activities. From the potentially significant interactions
identified in scoping, the impacts to the various resources/receptors are elaborated and evaluated. The
diverse range of potential impacts considered in the impact assessment process typically results in a wide
range of prediction methods being used, including quantitative and semi quantitative techniques, for
example noise impacts on sensitive surrounding community receptors, and qualitative techniques for
assessing certain socio-economic impacts on communities.

8.1.2 DESCRIPTION OF IMPACTS


Environmental impacts arise as a result of Project activities either interacting with environmental or
social receptors directly, or causing changes to the existing environment such that an indirect
effect occurs.
Environmental and social impacts from a planned event are those resulting from the routine and
intended construction or operations/activities associated with the IAIP and RTC facilities (e.g.
regular truck movements to and from the facilities transferring produce to market). Environmental
and social impacts from unplanned events occur as a result of incidents or ‘upset conditions’.
Typical examples of impacts occurring from unplanned events include (but are not limited to) spills,
leaks, odours and fires.

8.1.3 NATURE OF IMPACT


The nature of an impact is defined as the type of change from baseline conditions. The nature of
an impact is described as being either positive (+ve) or negative (-ve).

8.1.4 TYPE OF IMPACT


Impact type indicates the relationship of the impact to the Project activity in terms of cause and effect,
as either:
— Direct impact resulting from the direct interaction between a project activity and the receiving
environment; or
— Indirect impact which include secondary or induced impacts caused by a change in the Project
environment (e.g. employment opportunities created by the supply chain requirements);or
— Cumulative impact; where a Project impact acts together with other impacts (including those
from concurrent or planned future third party activities) to affect the same resources and/or
receptors as the Project.

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
Page 16
APPENDIX

8.1.5 SCALE OF IMPACT


Impact extent relates to the geographic reach of the impact and is described as:
— Local impact would affect local resources or receptors and would be restricted to a single
community (i.e. impacts in the footprint of Project activities and the immediate adjacent area);
— Regional impact would affect regional resources or receptors and would be experienced at a
regional scale;
— Trans-boundary impact would be those that are experienced in one country as a result of
activities in another.

8.1.6 DURATION OF IMPACT


Impact duration refers to the time period over which a resource or receptor will be affected,
and includes:
— Temporary impacts would be of a very short duration, are reversible and intermittent or
occasional in nature. The resource or receptor would return to the previous state when the effect
ceases or after a short period of recovery;
— Short-term impacts would last for a short duration (2 to 5 years) and are usually limited to the
construction period. The impact would cease when the effect ceases following a short period
of recovery;
— Medium-term impacts would last for over five years but less than fifteen years (5 to 15 years).
The impact would cease following rehabilitation and a period of recovery;
— Long-term impacts would continue for an extended period of time (e.g. beyond 15 years), or
cause a more permanent change in the affected receptor or resource that endures
substantially beyond the Project lifetime.

8.1.7 PROBABILITY
The probability of an event occurring and creating an impact on a given receptor is designated using
a qualitative scale from 1 to 4, the higher values being more probable that an impact will occur, see
Table 8-1 below.
Table 8-1 Probability rating of impact
RATING DESCRIPTION
SCALE

1 Unlikely - very improbable, never heard of in the industry, or an event with a short
duration (probably will not happen).

2 Low probability - incident has occurred in the industry and so therefore could occur, or an
event lasting up to a day (some possibility, but low likelihood).

3 Medium Probability - incident has (or is) expected to occur during the project or is very likely to,
or an event which may occur up to 1 month (distinct possibility).

4 High probability - incident is expected to happen frequently a year or is almost certain to happen,
or an event which is expected to occur multiple times (most likely).

8.1.8 SEVERITY
The severity of an impact, on a given receptor is designated using a rating scale from 1 to 4 and
defined in Table 8-2 (Environmental Severity) and Table 8-3 (Socio-economic Severity) below,
the high values denoting a more severe impact.
Table 8-2 Definitions of Severity used in the ESIA for Environmental Receptors

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
Page 17
APPENDIX

CATEGORY ENVIRONMENTAL RECEPTORS – PHYSICAL AND BIOLOGICAL

Negative Positive

4 - High Major, long term national, international or Baseline will be significantly improved by the
transboundary effects. project.
Deterioration/improvements of the existing Results in changes / increase in the abundance
habitat or ecosystem baseline conditions is and biodiversity of populations.
significant. Exceed national and international regulatory
Rehabilitation is required or the baseline will not standards in protection and creation of natural
recover. habitats.
Results in changes / reduction in the
abundance and biodiversity of populations
which may or may not recover.
Such impacts are a major non-compliance with
national and international regulatory standards
and may result in immediate intervention by
governmental bodies and stakeholders.

3 - Medium Moderate, medium term deterioration / impact Moderate, medium term rehabilitation of
on the ecosystem on a local / national level, ecosystems or national significance, leading to
leading to observable and measurable observable and measurable changes.
changes. Moderate deterioration/improvements and
Moderate deterioration / improvements and changes / increase in the abundance and
changes / reduction in the abundance and biodiversity of the area with moderate recovery
biodiversity of the area with moderate recovery periods to baseline conditions.
periods to baseline conditions. Conformance with national and international
Non-conformance with national and regulatory standards.
international regulatory standards which may
result in the intervention by governmental
bodies and stakeholders.

2 - Low An effect will be experienced but they will be An effect will be experienced but they will be
minor, short term and local, leading to minor, short term and local, leading to
observable and measurablechanges observableandmeasurable changes
recoverable within short durations. recoverable within short durations.
Potential non-conformance with regulatory Partial conformance with regulatory standards.
standards. Unlikely to result in concerns being Meets governmental and stakeholder
raised by governmental bodies or requirements.
stakeholders. Minor improvements to ambient environmental
Minor deterioration of ambient environmental conditions.
conditions and recovery requires little or no
intervention.

1 - Very Low Deemed ‘imperceptible’ or indistinguishable Deemed ‘imperceptible’ or indistinguishable


from natural background conditions. from natural background conditions.

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
Page 18
APPENDIX

Table 8-3 Definitions of Severity used in the ESIA for Socio-Economic Receptors

SOCIO ECONOMIC RECEPTORS


CATEGORY
NEGATIVE POSITIVE
4 - High Highly significant, loss or major damage with Retention of all cultural and heritage resources
medium to long term effect on cultural and/or of value on site.
natural resources of national and regional Highly significant positive impacts on the
importance which are essentialfor
communities’ livelihood. national and international community
(regional, i.e. neighbouring countries). Those
Highly significant negative impacts on the affected will be able to adapt to changes with
national and international community some difficulty/ease, and will only be able to
(regional, i.e. neighbouring countries). Those maintain pre-impact livelihoods with a degree
affected will be able to adapt to changes with of support.
some difficulty/ease, and will only be able to Project meeting and exceeding Government
maintain pre-impact livelihoods with a degree
of support. policies and plans.
Immediate intervention by governmental National and International media and
bodies requiring rapid implementation of community support.
response measures.
National and International media and
community concerns and ongoing long term
complaints.

3 - Medium Moderate damage to archaeological, cultural Retention of cultural heritage resources (of
or key natural resources of local or national value) where possible and appropriate
importance. recording of resources that cannot be
Moderate negative impacts on the regional or retained.
national population. Vulnerable groups Moderate positive impacts on the regional or
significantly affected. Changes affecting national population. Vulnerable groups
livelihoods, amenity values, convenience and significantly affected. Changes affecting
quality of life of study population. livelihoods, amenity values, convenience and
National and potentially international media quality of life of study population;
and community concerns and ongoing long National media and community support.
term complaints.

2 - Low An effect will be experienced but they will be An effect will be experienced but they will be
Minor, short term effects recoverable within Minor, short term effects of short durations.
short durations. Meets governmental and stakeholder
Unlikely to result in concerns being raised by requirements.
governmental bodies or stakeholders. Measurable positive impacts that are
Measurable negative impacts that are intermittent or effect a small minority of the
intermittent or effect a small minority of the local population and / or vulnerable groups.
local population and / or vulnerable groups.
May result in concerns from local
communities.

1 - Very Low Deemed ‘imperceptible’ or indistinguishable Deemed ‘imperceptible’ or indistinguishable to


from natural background conditions. No public current social norms and variations.
interest. No public interest.

8.1.9 EVALUATION OF SIGNIFICANCE OF IMPACT


Based on the above methodology, the impacts resulting from the project are classified within
this ESIA as either positive or negative with a specific severity rating.

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
Page 19
APPENDIX

All environmental and social impacts have been identified based on the information summarised in
this ESIA and their significance is assessed and classified by combining the probability and
severity scores as shown in Table 8-4, which relates to negative impacts, or Table 8-5 which
relates to positive impacts below.
In assessing whether an impact is significant, reference has been made, where appropriate, to
criteria on which the evaluation is based. These may include legislative requirements, policy
guidance or accepted practice and past experience.
Table 8-4 Significance Matrix Negative Impacts
PROBABILITY RATING

SIGNIFICANCE Very low Low Medium High

1 2 3 4

Very low 1 Negligible Minor Minor Minor


Rating

Low 2 Minor Minor Moderate Moderate


Severity

Medium 3
Minor Moderate Moderate Major

High 4 Minor Moderate Major Major

Table 8-5 Significance Matrix Positive Impacts

PROBABILITY RATING

SIGNIFICANCE Very low Low Medium High

1 2 3 4

Very low 1 Negligible Minor Minor Minor


Severity Rating

Low 2 Minor Minor Moderate Moderate

Medium 3 Minor Moderate Moderate Major

High 4 Minor Moderate Major Major

8.1.10 CATEGORIES OF IMPACT SIGNIFICANCE


The different significance categories reflected by the colour scheme used in the above matrix
and within this ESIA reflect the following:
Negligible - no additional action is required and the impact is already reduced to as low
as reasonably practicable (ALARP);

Minor - where the level of risk is broadly acceptable and generic control measures are already
assumed in a design process but, where appropriate, require continuous improvement.

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
Page 20
APPENDIX

Moderate - where the level of risk is tolerable but control measures are required to reduce
the risk as far as is practicable (i.e. tolerable if as low as reasonably practicable (ALARP)).

Major - changes to the project are required which requires a re-assessment of applicable
mitigation and / or reconsideration of alternatives and options by the project design team.

8.2 TRAFFIC IMPACT ASSESSMENT PER FACILITY


The scoping report identified the following construction and operational phase traffic impacts:
— The expected produce through-put and related vehicle volumes for deliveries and distribution to
and from the IAIP and the RTC is not known. However, the interaction between community
members using these routes with the increased Project traffic from the construction phase
onwards, may increase the risk of traffic accidents.

8.2.1 BURE IAIP


A breakdown of the construction, operational and decommissioning phase traffic related impacts
and ratings are provided in Table 8-6.
Table 8-6: Impact assessment of traffic – Bure IAIP
WITHOUT MITIGATION WITH MITIGATION
Severity

Severity
Probability

Significanc

Probability

Significanc
IMPACT DESCRIPTION
e

e
Construction
Increased vehicle/vehicle & vehicle/NMT 2 2 Minor 1 3 Minor
accident risks on the local road network

Operation

Increased vehicle/vehicle & vehicle/NMT 2 3 Moderate 1 3 Minor


accident risks on the local road network

Decommissioning

Increased vehicle/vehicle & vehicle/NMT 2 2 Minor 1 3 Minor


accident risks on the local road network

MITIGATION MEASURES - CONSTRUCTION

It is not possible to determine the construction traffic volumes or types at this stage. However, it
should be noted that the volumes are expected to be less than the operational phase, and that the
impact will be for a shorter period, namely the construction phase of 2 years.
It is recommended that due to the higher traffic volumes to and from the IAIP during operation,, and the
single access, that the access configuration should include the following, also refer to Figure 7-1:
— Access with 2 lanes In and 2 lanes Out.
— Main road with short (80 m) right-turn In lane
— Main road with short (80 m) left-turn In lane
— Additional road signage & markings along the main road at all the accesses
— Street lighting along the main road along the full length of the property frontage

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
Page 21
APPENDIX

The additional turning lanes on the main will improve the operation and safety of the intersection.
Note, the configuration must be approved by the roads authority.
It is recommended that a second vehicle and pedestrian access be provided to the IAIP via
the adjacent road network to the north-west of the site.
These upgrades should be implemented for the construction phase to ensure safe access to
all construction vehicles, and the future operation phase traffic.

MITIGATION MEASURES - OPERATION


The mitigation measures (intersection upgrades, etc.) will be in place from the Construction phase.
It is also recommended that the trip generation of the IAIP be monitored annually during the
operational phase to ensure that the access intersections operate safely and with sufficient
capacity and acceptable levels of service. Note that through traffic on the access road must also
not be obstructed. If the intersection performance deteriorates to unacceptable levels in future,
additional intersection upgrades should be implemented.

MITIGATION MEASURES - DECOMMISSIONING

None – the mitigation measures (intersection upgrades, etc.) will be in place from the
Construction and Operation phase.

8.2.2 MOTTA RTC


The very low traffic volumes to and from the RTC does not justify additional turning lanes at
the access intersections, therefore no intersection upgrades are recommended.

MITIGATION MEASURES – CONSTRUCTION, OPERATION & DECOMMISSIONING


The required road signs, road markings and street lighting should be implemented at the accesses
to ensure good intersection operation and safety.
It is also recommended that the trip generation of the RTC be monitored annually to ensure that the
access intersections operate safely and with sufficient capacity and acceptable levels of service. Note
that through traffic on the access road must also not be obstructed. If the intersection performance
deteriorates to unacceptable levels in future, additional intersection upgrades should be implemented.

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
Page 22
APPENDIX

9 CONCLUSIONS &
RECOMMENDATIONS
Based on this report, the following key conclusions are relevant:
— The proposed Bure IAIP and Motta RTC will have traffic and safety impacts on the local road
networks and residents within in each study area.
— The condition of the main roads to the IAIP and RTC was not assessed, therefore sections of this or
other access roads may be in a poor condition, dangerous or partially impassable, for example the
roadway width is reduced. The additional traffic due to the IAIP and RTC could therefore increase the
road safety risks and accident potential along these sections outside the study area.
— There are no known large-scale latent developments in the vicinity of this development, therefore
no Cumulative Transport Impacts are expected on the local road network.
— All parking provision will be provided on-site, and parking on individual erven will be subject to the
Development Control Regulations of the sites. The parking provision will be in-line with the
zoning of each internal erf of the IAIP and RTC.
— Bure IAIP - There are residential areas in the vicinity of the IAIP. Public transport may still be
required due to the large number of workers that will be employed on the IAIP. The type and
extent of the services cannot be assess at this stage, and may have to be provided in
incremental stage as the number of workers on-site increases.
o A suitable public transport stop should be provided on-site, to ensure safety of
passengers waiting for transport.
o Due to the location of the site, non-motorised transport will be present along the
federal highway to the site.
o An additional NMT access should be provided off the roundabout located on the north-
western edge of the site. This will allow a shorter and more direct access to the site from
the town, and will also decrease NMT and public transport movements along the federal
highway to the main access. See Figure 6-1 for the proposed location of the NMT access,
and also refer to Section 8.2.
— Motta RTC – Located directly adjacent to residential areas of the town of Motta. Public transport
may therefore not be required to transport workers to the site.
o A suitable public transport stop should be provided on-site, to ensure safety of
passengers waiting for transport.
o Due to the location of the site directly adjacent to the town, non-motorised transport is
present along the access road and federal highway.
o It is recommended that NMT facilities (sidewalks) be provided along the access
road between the RTC and the federal highway.
— Construction phase traffic at the IAIP and RTC was not assessed, as the vehicle volumes cannot
be determined. The impact will also only be short-term (2 years).
— Operational phase traffic impacts:
o Bure IAIP - It is recommended that due to the higher traffic volumes to and from the IAIP
and the single vehicle access, that the configuration of the access should have multiple
lanes and turning lanes on the main This will assist to improve safety and operation of the
access. The required road signs, road markings and street lighting should also be
implemented at the access.
o It is recommended that the trip generation of the IAIP be monitored annually to ensure that
the access intersections operate safely and with sufficient capacity and acceptable levels of
service. Note that through traffic on the access road must also not be obstructed. If the
intersection performance deteriorates to unacceptable levels in future, additional
intersection upgrades should be implemented.

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
Page 23
APPENDIX

o It is recommended that a second vehicle and pedestrian access be provided to the IAIP
via the adjacent road network to the north-west of the site.
o Motta RTC - The very low traffic volumes to and from the RTC does not justify additional turning
lanes at the access intersections, and no intersection upgrades are recommended. Mitigation
measures in the form of the required road signs, road markings and street lighting should be
implemented at the accesses to ensure good intersection operation and safety.
o It is recommended that the trip generation of the RTC be monitored annually to ensure that
the access intersections operate safely and with sufficient capacity and acceptable levels of
service. Note that through traffic on the access road must also not be obstructed. If the
intersection performance deteriorates to unacceptable levels in future, additional
intersection upgrades should be implemented.

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
Page 24
APPENDIX

10 BIBLIOGRAPHY
— WSP, Preliminary Scoping Report for the proposed Amhara IAIP and RTC Environmental and
Social impact Assessment, June 2017.
— Mahindra Consulting Engineers, Amhara Design and Detailed Engineering Documents and
Drawings, 2017.
— African Development Bank, IESIA Guidelines, Safeguards and Sustainability Series, Volume 2,
Issue 1, December 2015.
— African Development Bank, IESIA Guidelines, Safeguards and Sustainability Series, Volume 2,
Issue 2, December 2015.
— African Development Bank, IESIA Guidelines, Safeguards and Sustainability Series, Volume 2,
Issue 3, December 2015.
— Ethiopian Roads Authority: www.era.gov.et
— South Africa Committee of Transport Officials TMH 17 South African Trip Data Manual, Version
1.01, September 2013.
— South Africa Committee of Transport Officials, South African Traffic Impact and Site Traffic
Assessment Manual, TMH16, Vol. 1, Version 1, August 2012.

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
Page 25
APPENDIX

A IMPACT SIGNIFICANCE
MATRIX

SOUTH WEST AMHARA IAIP & RTC FACILITIES, ETHIOPIA December 2017
DRAFT
APPENDIX

IMPACT SIGNIFICANCE MATRIX

CONSTRUCTION

OPERATION

DECOMMISSIONING

You might also like