Wavin QuickStream PE Installation Manual
Wavin QuickStream PE Installation Manual
Wavin QuickStream PE Installation Manual
J35 X719
June 2008
These include:
Rainwater infiltration
Wavin and Wavin QuickStream are registered trademarks of the Wavin Group. Wavin operates a programme of continuous
product development, and therefore reserves the right to modify or amend the specification of their products without notice.
THE POWER OF PERFORMANCE
All information in this publication is given in good faith, and believed to be correct at the time of going to press.
However, no responsibility can be accepted for any errors, omissions or incorrect assumptions. Users should satisfy
themselves that products are suitable for the purpose and application intended.
06/2008 08-171
Contents
1.1 Full-bore flow system A specially designed roof outlet with an The combination of elimination of air in
air baffle and anti vortex vane only allows the pipework and the increased flow
Wavin QuickStream is a siphonic roof the intake of water and prevents the velocities, result in a considerable
drainage system. Whereas in conventional ingress of air, so allowing full-bore flow to increase in discharge capacity, leading
gravity roof drainage systems gravity is be achieved (see figures 1 & 2). to a significant reduction of the pipe
the only driving force for discharge, in At full-bore flow, the difference in height dimensions.
siphonic systems a gravity induced between the roof outlets and the
vacuum will boost the drainage function. rainwater discharge level is utilised to
This is achieved by preventing air being gain the energy that will increase the flow
sucked into the roof outlets during heavy velocity of the water in the pipework.
rainfall.
Figure 11. Install eccentric reducers in a vertical pipe with the level side facing the wall.
Installation of eccentric reducers and In some countries, it is common practice 2.9 Fix roof outlets and
or increasers in vertical pipes should be to provide each 5-meter pipe-length in pipe system according
positioned with the level side facing the the vertical downpipe with an expansion to Wavin’s instructions
wall. This allows for ease of installation, joint, while in other countries no expansion One of the key elements in a Wavin
particular when fixing rails and clamps joints are used and fixing clamps are QuickStream system is the roof outlet.
are used. Furthermore, it is more effective directly installed to the wall. It is not good Detailed points of attention are presented
during priming of the system (see figure 11). practice to install an expansion joint in in chapter 5. Improper or incomplete
horizontal collector pipes. In those cases installation might cause condensation
2.8 Only install explansion where expansion joints are applied, and/or leakages. In most Wavin
joints where provided appropriate fixing is required. Guidance is QuickStream systems, long horizontal
in the design given in paragraph 7.3. pipes will be installed below the roof. For
Once installed, the Wavin QuickStream this part of the installation please follow
system is subjected to temperature Wavin does not in general advise the Wavin’s installation recommendations
changes and dynamic loads. Any practice of absorbing axial displacements mentioned in chapter 7. Wavin has
oscillation or vibration, originating from by expansion loops or flexible legs in a developed special brackets for an easy
partly filled pipes, must be effectively Wavin QuickStream PE system, unless and secure installation of the horizontal
damped. Wherever possible it is strongly provided in the design proposal. collector pipes.
recommended to make all joints tensile
resistant.
2.10 Do not connect gravity 2.11 Connect to a gravity 2.12 Use prescribed pipe
pipelines to the Wavin system of sufficient materials and pipe
QuickStream system capacity classes
Any open (gravity) connection to a Wavin In order to prevent future flooding in case As Wavin QuickStream siphonic systems
QuickStream system will allow the intake the design rainfall actually takes place, the are subjected to both under- and over
of air and thus can severely impair the installer should verify that the discharge pressures, as well as axial loadings, only
siphonic function. Therefore, such system, being either an open channel or Wavin’s recommended and quoted
connections cannot be allowed in the ventilated sewerage system, is capable of pipework materials, fixing materials and
design. Also, attention should be paid on discharging the design quantity. In case ancillaries should be used. In case of
not allowing extensions at a later date. the existing discharge system has a limited deviations, advice must be sought from
Extensions to the building will require its capacity, contact should be sought with Wavin’s technical team.
own dedicated rainwater discharge the project manager or local authorities.
system. Guidance on maximum discharge
capacities is presented in Chapter 9.
4.1 General installation 4.2 Sequence of installation Pipe sections located in either floor
recommendations In most cases the horizontal collector pipe and/or walls must be pressure tested
Until the Wavin QuickStream system is will be installed underneath the roof. In this prior to the casting of concrete. In order
required to deal with any water discharges, situation the following sequence is advised: to prevent any ingress of mortar into the
it is recommended to close the roof outlets Installation of the emergency overflow system, these pipe sections must be
on the roof. Otherwise, contamination of systems to prevent potential problems capped-off thoroughly. Open pipe ends
various kinds could penetrate into the of water on the roof and inside the must be well protected against possible
pipe system. Once the installation of the building. damage by using PE caps.
roofing materials has been completed Installation of the Wavin QuickStream
and the whole roof is cleared from loose roof outlets in the roof construction at
rubble, the plugs can be removed from the positions according to the design.
the roof outlets. Follow the installation instructions as
supplied with each product.
It is strictly prohibited to sweep dirt from Plug off the outlet to prevent
the roof into the roof outlets. Particular contamination of the system and
caution must be applied to remove all the water entering the system during the
cement waste. Once mixed with water construction works.
cement could set permanently in the Installation of the roofing material and
pipework, thereby severely reducing the fixing the outlet in the roofing material.
discharge capacity. Installation of the hanging rails and
brackets according to the design
If it is suspected that the system has (see chapter 7).
become contaminated during the building Installation of the horizontal collector
process, it is strongly recommended to pipe and the roof outlet connecting
clean the system before completion. pipes and then the vertical pipework
top-down according to the supplied
drawings. Use fix point brackets
where indicated in the design.
Check the bracketing system for
fixing and/or sliding.
Install discharge points.
Check if discharge can take place
unhindered and with sufficient
capacity (see table in chapter 9).
Commission pipework by pressure
testing (see chapter 10).
Clean roof surface.
Un-plug Wavin QuickStream roof
outlets.
Dismantle temporary emergency
overflows.
Figure 15. Location of the roof outlet at least 0.5 m from the eaves (0-3 degrees slope).
5.1 General installation Each delivery of roof outlets is provided Clamping type roof outlet
recommendations for with detailed installation instructions If required, the roof outlet can be
roof outlets related to type and size. Below the most fixed into the roof by using 4 screws
One of the key components in a siphonic important general steps are noted. or nails. The sealing with the roof
roof drainage system are the roof outlets. membrane is achieved by pressing
The roof outlets should be located exactly Check the correct position of the flat the membrane between the clamping
according to Wavin’s supplied Roof sealing ring at the end of the screw ring and the sump pan. Carefully
Outlet Plan. thread of the roof outlet connector. check on correct positioning of the
All roof outlets need to be placed at the Screw the roof outlet connector to sealing rings (if present) and the
lowest points of the roof but at least 0.5 the threaded outlet. Firmly tightening absence of dirt in the sealing area.
meters from the eaves. If the eave roof by hand will be sufficient to achieve If a joint of two roof membranes is
level is lower than the level of the roof a watertight connection. In case located at the position of the roof
outlets the roof surface between the roof de-icing heating is required, place the outlet, a square piece of roof
outlets and the eaves needs to be filled-up heating element prior to screwing on membrane of size 0.6 to 1 m should
to realise a slope of 0 to 3 degrees the roof outlet connector. The Wavin first be clamped into the outlet. At the
toward the outlets. All low points of the QSPE 75 roof outlet has a 75 mm location of the outlet a piece of the
roof must have an outlet. outlet pipe so no additional roof outlet roof membrane smaller than the
connector is required. square fixed into the roof outlet needs
All Wavin QuickStream roof outlets have Cut a piece from the insulation where to be cut out. Finally the roof
air baffles to prevent air entrainment into the roof outlet will be positioned (note: membrane fixed in the outlet can be
the pipe system. Any removal of baffles size of insulation blocks might differ!). fixed to the roof membrane positioned
or cleaning caps will reduce the drainage Use the insulation block as a gauge. on the roof.
capacity tremendously. Place the insulation block in the free Bitumen type roof outlet
In case insulation is required, either space made in the roof insulation. Place the roof outlet on the bitumen
existing insulation of the roof can be used The insulation block may be positioned sub-layer if present. If required, the
or special insulation blocks that can be about 10 mm lower than the roof outlet can be fixed to the roof by
sourced from Wavin. surrounding insulation but in any case using 4 screws or nails. Degrease
In specific climatic situations, it may be not higher. If required some insulation the stainless steel parts using an
required to install additional de-icing material may be added below the appropriate solvent. Heat weld the
heating on the roof outlet (see paragraph insulation block to achieve the right bitumen top layer to the stainless
5.6) height. steel plate of the roof outlet. Take
In all cases, movement and vibrations Dismantle the top part (clamping care to use sufficient heat to establish
must be prevented from being transferred ring / leaf separator) and store all a bond between the top layer and the
to the tail pipes of the roof outlets by dismantled parts properly for later sub layer via the holes in the plate of
effective fixing. Guidance is given in reassembly. the roof outlet.
chapter 7. Install the roof outlet.
Figure 17. Figure roof outlet in slope of the roof and placed at an insulation block.
5.3 Types of roof outlets Type 3: Gutter type A wide range of accessories is available
Wavin QuickStream roof outlets are These outlets are designed for installation for specific situations like:
available in different materials. in metal gutters. Sealing is performed by Foamed polystyrene insulation blocks
Additionally there are three different EPDM rubber gaskets, on both surfaces Moisture barriers
constructions for sealing to different of the gutter compressed between the De-icing electric heating elements
roofing materials and gutters. backing flange and the outlet part. Straight threaded roof outlet
Upon request, a gutter type outlet can be connectors and 90 degree bended
Type 1: Clamping type supplied with a contact sheet of the connectors.
Compressing the roofing membrane same metal as the gutter, so that the
between two flanges performs the outlet can be welded / soldered into the Detailed assembling instructions are
sealing. This outlet type can be directly gutter. supplied with each Wavin QuickStream
installed on the most common roofing outlet.
membranes such as PVC, EPDM and
bitumen.
Diameter range
Roof outlet type vertical tail pipe
Siluminium /
QS 75 stainless 21/2” A A A 40 mm 90 mm
steel
Plastic /
QSMP 75 stainless 21/2” A A A 40 mm 90 mm
steel
QSPE 75 Plastics / PE PE 75 mm A A A 40 mm 90 mm
Figure 22. Installation example Wavin QSPE 75 with a stainless steel contact sheet on a bitumen roof.
Figure 24. Installation example Wavin QS 75 clamp version for PVC, EPDM or bitumen
roof membranes.
Figure 28. Installation example Wavin QS 75 gutter version with backing flange and EPDM gaskets.
If possible deform the gutter around the outlet downwards by 3 to 4 mm.
Figure 30. Installation example Wavin QSMP 75 clamp version for PVC, EPDM or
bitumen roof membranes.
Figure 31. Installation example Wavin QSMP 75 heat welded bitumen roof foil.
Figure 33. Installation example Wavin QSMP 75 gutter version with backing flange and EPDM gaskets. If possible, deform the gutter
around the outlet downwards by 3 to 4 mm.
transferred to these parts of the roof Each heating element consumes 3 Watt
Figure 34 and 35. Moisture barriers. construction. For parking decks a similar in stand-by mode and takes 18 Watt
construction can be supplied. Please when heating. Voltage is single phase
consult Wavin for further details. 230 VAC.
5.5 Wavin QuickStream
outlets on green roofs 5.6 De-icing electrical
and parking decks heating elements
Wavin has developed special perforated Wavin QuickStream roof outlets can be
shafts DN 315 wrapped with geotextile provided with an automatic electric heating
that can be placed around standard system. A heating system prevents
(QuickStream) roof outlets. The shaft can blockage of the outlet in case of ice-rain,
be easily cut to the required height with a freezing melt water or snow.
minimum height of 200 mm. The cover A built in temperature probe will
should be positioned not higher than the automatically switch-on the heating plate
adjacent surface. Depending on the load when ambient temperature drops below
situation, various covers with gratings can + 4 °C. Figure 37. Heating element.
be supplied. The maximum load on the The heating element (see figure 37) is
shaft should not exceed 15000 N. Prior placed between the external surface of
to installation, the installer needs to check the sump pan and the thermal insulation
whether the roof construction and the pack. See also chapter 8.3; “Thermal
roof foil can withstand the loads to be insulation”.
6.1 Cutting polyethylene The butt-welding procedure 4. Check temperature heater plate
pipes incorporates the following 15 steps: on 210 ºC.
Best practice in cutting PE pipes is to use 1. Check environmental conditions.
a rotary pipe cutter designed for plastic When the outside temperature is below
pipes. In case a saw is used, ensure that 5 ºC and/or during rainy and windy
the cut is square to the pipe axis. This conditions, special precautionary
can easily be achieved by using a pipe measure have to be taken to ensure
clamp as sawing guide. Always remove dry and sufficiently warm welding
burrs and flashes! conditions.
7. Trim both pipe-ends using the 10. Reduce force until nearly zero, 14. Inspect weld bead for evenness.
planer. assuring contact with heater plate Uneven weld beads indicate incorrect
Keep planer running while slowly so that heat is soaked into both alignment or out of roundness. Large
reducing pressure. Do not stop pipe ends. weld beads could be caused by either
planer when still in contact with pipe too high a heater temperature and/or
ends in order to prevent uneven 11. Maintain heat soaking till a bead is too high a welding force. A small
surfaces. formed of approximate 1 mm for weld bead could be caused by a too
diameters 40 up to 200 and 1.5mm low a heater temperature and/or too
for diameters 250 and 315mm. low a welding force. In both cases
Use the figures mentioned in table 2 the weld should be rejected due to
as guidance for the heat soaking reduced strength.
duration.
Figure 43. Table 2. Guidance of the heat soaking duration (in seconds) for butt-welding.
Figure 47.
Table 2a. Guidance of the minimum cooling time (in seconds) for butt-welding at 20º C.
Figure 45.
6.4 Electrofusion welding 4. Always cut pipe-ends square! 6. Chafe pipe ends over its insertion
Electrofusion sockets are provided with If this is not the case, melt cannot be depth using a clean emery cloth
an electric resistance wiring embedded in kept encapsulated between pipe end (-lint) of a roughness 40 or lower or
the internal surface. When connected to and socket, resulting in a loss of a dedicated PE pipe scraper.
an electric power source, heat is supplied melt-pressure! Best practice is to use
directly in the fusion zones. During the a rotary pipe cutter (see photo). The
melting of polyethylene, its volume pipe ends are then square and free
increases. This expansion creates the from burrs. If a saw is used, it is
necessary welding pressure. The Wavin advised to use a spare clamp as a
welding equipment automatically doses the sawing guide. Such cut pipe ends
exact required energy for making a good must be de-burred before inserting
joint. There are two welding machines: the pipe end in the electrofusion
one for the sizes 40-160 and one for the socket.
dimensions 200, 250 and 315 mm.
Figure 51. Chafe pipe end with emery lint
In order to meet the four basic of roughness 40 or lower.
requirements for making a sound
joint, special attention should be paid
on the following 12 points:
1. Check environmental conditions.
When the outside temperature is
below 5 ºC and/or during rainy and
windy conditions special precautionary
measure have to be taken to secure Figure 49. Preferably use a pipe clamp.
dry and sufficient warm welding Figure 52. Clean pipe end with
conditions. 5. Clean and de-burr pipe ends PE cleaner.
7. Always insert pipe ends till the 9. In case pipe ends are too oval, 11. Inspect welded joint for correct
internal register in the socket, so re-rounding is required by using a alignment, insertion depths and
that full insertion is reached. temporary pipe clamp, fixed close weld indicators.
Mark the insertion depth on the pipe to the socket. The weld indicators indicate that the
ends so that any slippage can be This temporary clamp can be joint has been energized; they are not
detected in time. In case the internal removed after elapsed cooling time. linked to weld quality, as quality is
register (pipe stops) have been cut only reached by following above
away so that the electrofusion socket steps and requirements.
can be used as a sliding socket,
correct marking of the insertion depth
is essential. Improperly inserted pipe
ends also lead to a loss of melt
pressure.
6.5 Installation of For a good functioning of the expansion 4. Apply silicone oil on rubber seal
expansion joints joints, follow these instructions: and sparsely on spigot end.
Expansion joints are push-fit sockets with 1. Prepare positions of fix- and
a rubber seal. sliding brackets.
Expansion and contraction in the pipe Expansion sockets must always be
system is absorbed by axial displacements configured as a fixed-point. That
in the sockets. Normally expansion joints means that all other fixing points
are mostly located in the vertical must be sliding brackets
downpipes. In special circumstances, if (see figure 87).
no other options remain to absorb
thermally induced displacements, 2. Chamfer pipe end.
expansion joints can be positioned in Chamfer angle should be
horizontal collector pipes. approximately 15° and chamfering Figure 63.
length should be minimum 4 mm.
Figure 64.
Figure 65.
Figure 60. Installation of an expansion joint. Figure 62. 6. Check depth of insertion.
Pipe diameter
≤ 50 63 75 90 110 125 160 200 250 315
Ambient temperature Insertion depth in [mm] for pipe length of 6 meter
- 10° C 65 70 70 80 85 90 100 140 140 140
0° C 75 80 80 90 95 100 110 150 150 150
+ 10° C 85 90 90 100 105 110 120 160 160 160
+ 20° C 95 100 100 110 115 120 130 170 170 170
+ 30° C 105 110 110 120 125 130 140 180 180 180
Table 3. Insertion depth of pipes into an expansion socket, max. pipe length 6 meter.
7.1 Fixing the horizontal QuickStream rail connectors that can ded to the roof construction at a maxi-
collector pipe transfer thermally induced axial loads mum distance of 2 meters between the
A controlled absorption of thermal axial from one rail to the next one. The rail suspension elements, taking into account
pipe stresses in rigid suspension systems connector for the rail 30 x 45 mm can the weight of a fully filled pipe, the weight
by making use of galvanised steel rails is also be used for connecting a 30 x 30 of the suspension rail and the load ability
most commonly applied in PE siphonic mm rail to a 30 x 45 mm rail. of the roof construction.
rainwater discharge systems. It is not possible to make a connection
The benefits are ease of installation and between a 30 x 45 mm rail and a 41 x 62 4. Anchoring of the steel rails.
no unexpected displacements. The mm rail, or between a 30 x 30 mm rail All rails can be suspended relatively easily
thermally induced axial loads are and a 41 x 62 mm rail. In cases where it using threaded rods to the roof. The
completely absorbed by the suspension is not possible to use a rail connector, length of the threaded rods is of no
and bracketing system. Once the then the extreme brackets on each rail importance as these only bear the
suspension rails have been installed, pipe must be of the fixed type. This is only the weight of the pipe, pipe clamps and rail
segments can then easily be placed in case at bends and at a diameter change construction. Wavin recommends
the brackets. In-lays can be placed in the between 315 mm and 250 mm pipe size. anchoring the steel rails to the roof every
brackets to create a strong and cost 12 meters and at every change of
effective fix of the pipework against axial 2. Install the bottom side of all types direction. The anchors need to be fixed
displacement. of rail on the same level. to the wall structure or alternatively
The bottom side of the different types of installed lateral to the rails and approx.
All Wavin QuickStream brackets are rail always needs to be installed on the 45º to the roof.
designed to enable fast and easy placing same level. Special attention to the height
of pipe segments and additional closing of the rail needs to be paid when 5. Check weight limitations, which
of the brackets. See picture 68-82. installation of the rail is started at the can be suspended to the (roof)
upstream side of the horizontal collector construction.
Installation of the steel rails pipe and when the pipe size at the Care should be taken that the roof
The Wavin QuickStream system downstream side of the horizontal constructions have sufficient strength to
compromises three types of suspension collector pipe is larger than 160 mm. In bear the whole piping construction. The
rails: this situation, the 30 x 30 rail needs to be total weight per meter of a fully filled pipe
1. Wavin QuickStream rail 30 x 30 mm installed 15 or 30 mm lower to allow a and the suspension system can be taken
for pipes 40 – 160 mm bottom level connection to a 30 x 45 or a from table 4.
2. Wavin QuickStream rail 30 x 45 mm 41 x 62 mm rail. When the rail is fixed at When the rail system is suspended every
for pipe 200 – 250 mm the top side to e.g. steel beams, a 30 x 2 meters, the design strength of each
3. Wavin QuickStream rail 41 x 62 mm 15 or a 30 x 30 rail can be fixed between suspension point to the roof should be at
for pipe diameter 315 mm the 30 x 30 rail and the steel beam to least 2 times the total weight/m
adjust the height of the 30 x 30 rail to the according to table 4. The weight of
Special attention needs to be paid to height of the 30 x 45 or 41 x 62 mm rail. insulation blankets can be found in
the following 5 points: chapter 8.4.
3. Maximum intermediate distances
1. Wavin rail connectors. of the suspension elements.
The suspension rails must be mutually All Wavin QuickStream rail types 30 x 30,
connected with the specific Wavin 30 x 45 and 41 x 62 should be suspen-
Weight/m [kg/m] 3.4 4.2 4.7 5.4 6.7 8.8 12.1 15.0 23.3 35.8 54.6 86.9
Table 4. Weight of the pipe including suspension and 100% filled with water.
Installation of the brackets Fix the next rail to the rail connector and 4. Click fixed-point inlay in the bracket
To avoid potential sagging of the pipes, fasten the 4 screws (it is not required to and insert the pipe.
the horizontal maximum supporting / place the rails against the previous one).
bracketing distances from table 5 should Click one stainless steel inlay into the back
be applied in a Wavin QuickStream PE part of the bracket
pipe system.
Figure 66.
Fix the bracket to the rail by clicking the Click the front part of the bracket into the
front part into the rail and fasten the screw. hook and fasten the screw.
Figure 67.
Figure 74.
Figure 68.
Location of the fixed-points The photos below show the installation of 2. Fasten the screws.
As a minimum, a fixed-point bracket the sliding bracket.
must be placed on the largest side of Click the front part of the bracket into the
every increaser / reducer. If a Tee piece 1. Click the sliding bracket on the rail hook and fasten the bottom screw.
is located at an increaser, then the and put in the pipe.
fixed-point brackets can be situated
directly next to the Tee piece. Click the sliding bracket at the right
Fixed-point brackets should also be location on the rail (see table bracketing
installed directly before and after a change distances).
in direction, e.g. at a bend and at each
interruption of the rails. The maximum
distance between two fixed-point brackets
may not exceed 10 meters. The fixed
points need to be located within a maxi- Figure 80.
mum distance of 0.3 meters from a sus-
pesion element. Fasten the upper screw.
Figure 78.
Figure 81.
Figure 79.
Figure 82.
Figure 85. Install horizontal support brackets if the horizontal distance between roof
outlet and collector pipe is 0.8 to 1.2 meters.
100 1/ 1/
2” 2” 1” 1” 1” 1” 1”
Table 6. Minimum diameter of the threaded metal pipes for the fixed-points.
Table 7. Maximum bracketing distance (in meters) for the vertical downpipe.
100 1/ 1/ ” 1/
2” 2 2” 1” 1” 1” 1”
Table 8. Minimum diameter of the threaded metal pipes for fixed-points when using expansion sockets.
Table 9. Maximum bracketing distance (in meters) for the vertical downpipe.
8. Special constructions
8.3 Thermal insulation With one layer the sound level can be
In humid environments there can be the reduced between 15 and 22 dB, depen-
need to insulate the pipe system to ding on the type of installation and the
prevent condensation and subsequent location of the measurement.
water dripping from it. Condensation can
happen when the relative humidity is Installation of acoustic insulation
above 40%. Commonly the temperature sheets
in the top of buildings is rather high. The material is very flexible and is easy to
To prevent condensation on the pipe apply.
surface, it is necessary to use sufficient The Wavin acoustic insulation sheets can
insulation thickness and a vapour sealed be easily cut to size and shape with a
foil on the outside. The thickness of the knife or industrial scissors.
insulation sheet depends on the ambient
temperature, the humidity and of course Cut to required shape.
the medium temperature. Be aware that Fix to pipe and fittings using double
a high ambient temperature is more sided Wavin adhesive tape or a con-
critical for condensation than a low tact cement/glue. The layer with the
ambient temperature. A risk assessment high specific gravity needs to be
by the designer shall reveal the need for located on the outside.
thermal insulation. For most situations, a It is of utmost importance to avoid
15 mm thick insulation sheet can be gaps.
taken as a guideline. Close seams with 50 mm wide
adhesive tape.
8.4 Acoustic plus thermal
insulation
9.1 Discharge systems and storm water or combined sewer systems Wavin engineers have adapted the last
capacity a lower rain intensity is usually used pipe length to the appropriate diameter to
The discharge should be above water compared to the calculation for the reduce the flow speed. In any case the
level in gravity discharge systems of rainwater system of a building. When the adjacent gravity discharge system must
sufficient capacity. To guarantee the discharge of the Wavin QuickStream be able to cope with the design flow of
evacuation of air in the pipework and that system is in the building, the overflow the Wavin QuickStream roof drainage
the attainment of siphonic action is not relief chamber should be installed outside system. The provided design of each
retarded, the discharge point should be the building in the gravity system. If the Wavin QuickStream system indicates the
installed at a higher level than the water discharge of the Wavin QuickStream maximum discharge flow. It is the
in the gravity drainage system. It is always system has been extended to outside the responsibility of the contractor to
recommended to install an overflow relief building, Wavin can supply a special investigate if the existing ventilated
chamber. This inspection chamber overflow relief chamber with an inlet drainage system has sufficient capacity.
should have a cover with an open grating connection to the Wavin QuickStream As guidance table 10 presents the
to allow water overflow when the gravity system and a bigger outlet diameter maximum flow in [l/s] of 100% filled pipes
system is not able to cope with the connection towards the gravity sewer. dependending on the gradient. For a
discharge capacity of the siphonic system. If the discharge takes place directly in ventilated drainage system, a larger pipe
For the calculation of the capacity of open water or in a sewer system, the diameter should be selected.
Table 10. Maximum flow in [l/s] of 100% filled pipes at various gradients of drainage pipes.
Note: Above table is based on a friction factor kb = 0.40 suitable for plastic pipes and a water temperature of 10°C. The Du reflects a
PVC SDR34 pipe class. Other pipe materials such as concrete might have a higher friction factor and consequently the above
table cannot be used for these materials.
Commissioning Maintenance
As a Wavin QuickStream roof drainage Inspect in spring en autumn
system operates at both over and under Roof drainage systems will mostly be
pressures, it is necessary to carry out a inspected in spring and autumn. The
leak tightness test: best moment is directly after the trees
have dropped their seeds and after
Close the discharge of each Wavin leaf fall. In geographical areas having
QuickStream system and fill-up the predictable rainy seasons, inspection
system with water to roof level. and maintenance should performed
Check all connections for leakages. just before rainy season starts.
Unplug the discharge on completion
of the inspection. Clean roof en gutters
Roof and gutters must be cleared of
If the building is over 40 meters high, deposits, whereby it is not allowed to
the pipe system needs to be split-up in flush the dirt through the Wavin
sections not higher than 40 meter. QuickStream roof outlets.
Recommendations
If the emergency overflows have been
discharging during a rainfall, the roof
outlets need to be inspected for
obstructions. It is recommended to
record details of any such incidents
and the measures taken to rectify the
situation.
June 2008
These include:
Rainwater infiltration
Wavin and Wavin QuickStream are registered trademarks of the Wavin Group. Wavin operates a programme of continuous
product development, and therefore reserves the right to modify or amend the specification of their products without notice.
THE POWER OF PERFORMANCE
All information in this publication is given in good faith, and believed to be correct at the time of going to press.
However, no responsibility can be accepted for any errors, omissions or incorrect assumptions. Users should satisfy
themselves that products are suitable for the purpose and application intended.
06/2008 08-171