Insepction & Test Chart For Engine Room High Pressure Co System New Installation
Insepction & Test Chart For Engine Room High Pressure Co System New Installation
Insepction & Test Chart For Engine Room High Pressure Co System New Installation
PERFORMANCE
CHECK POINT CARRIED NOT
OUT APPLICABLE
01) Complete installation as per the
approved drawing
02) Manifold leak test, at 7 Bar with
main valve closed for 02 minutes
03) Down stream pipe leak test at 7 Bar
with nozzle ends blanked (for 02
Minutes)
04) Time delay and cylinder actuator
operation test (operating all actuators
after 30 seconds) from Control
Station I
05) Pilot discharge line leak test at 7 bar
for 2 minutes from Control Station I
06) Distribution Main Valve function test
(Main Valve for Engine Room / Pump
Room & SCR Room) from Control
Station I
07) Function test for audible & visual
alarms, ventilation & blower shutdown
test from Control Station I
08) Time delay and cylinder actuator
operation test (operating all actuators
after 30 seconds) from Control
Station II
09) Pilot discharge line leak test at 7 bar
for 2 minutes from Control Station II
10) Distribution Main Valve function test
(Main Valve for Engine Room / Pump
Room & SCR Room) from Control
Station II
PERFORMANCE
CHECK POINT CARRIED NOT
OUT APPLICABLE
11) Function test for audible & visual
alarms, ventilation & blower shutdown test
from Control Station II
12) CO 2 Operating Instructions &
evacuation sign board checked
13) Reset the system
REMARKS: …………………………………………………………………………………….
……………………………………………………………………………………
RIG REPRESENTATIVE
NAME : _________________
TITLE : __________________
DATE : __________________