National Cancer Institute Egypt Resources Calculation Sheet
National Cancer Institute Egypt Resources Calculation Sheet
National Cancer Institute Egypt Resources Calculation Sheet
Cancer Institute Egypt
Resources Calculation Sheet
Excavation 2 750 45 8 M3
1 Excavation Crew 2 Labors
Backfilling 2 250 14 9 M3
4 Concrete Placing Crew 2 Skilled + 2 Helper Concrete Works & Flooring Works 1 2,400 307 8 M2
12 Marble Crew 1 Skilled + 1 Helper Marble Works (Floors & Walls) 2 12,700 320 20 M2
13 Tiles Placing Crew 1 Skilled + 1 Helper Ceramic / Porcelain Works 2 5,820 168 17 M2
17 Wooden Works Crew 2 Skilled + 2 Helper Wooden Works (Doors) 2 513 91 3 Door
24 Firefighting Crew 1 Skilled + 1 Helper Firefighting Works (1st Fix) 4 4,922 210 6 M
25 Electrician Crew 1 Skilled + 1 Helper Electrical Works (1st Fix) 5 6,783 294 5 Point
26 Light Current Crew 1 Skilled + 1 Helper LC Works (1st Fix) 3 2,200 210 3 Point
27 Data Crew 1 Skilled + 1 Helper Data Works (1st Fix) 4 832 120 2 Point
29 Medical Gas Crew 1 Skilled + 1 Helper Medical Gas Works (1st Fix) 4 8820 394 6 M
National Cancer Institute Egypt
Resources Calculation Sheet
30 Plumbing Crew 1 Skilled + 1 Helper Plumbing Works (1st Fix) 3 7,470 300 8 M