J PLUS ASIA DEVELOPMENT CORPORATION Vs UTILITY ASSURANCE CORPORATION
J PLUS ASIA DEVELOPMENT CORPORATION Vs UTILITY ASSURANCE CORPORATION
J PLUS ASIA DEVELOPMENT CORPORATION Vs UTILITY ASSURANCE CORPORATION
CORPORATION
GR No. 199650, June 26, 2013
FACTS:
Shierly C. Ba-ad
JD 2A
CIAC_____________________________________________________
Petitioner prayed that Mabunay and respondent surety be
ordered to pay the unliquidated damages and the
unrecouped down payment or overpayment paid to Mabunay
Mabunay in his Answer, claimed that the delays were caused
by the retrofitting and other revision works ordered by Joo Han
Lee and the termination of the contract by the petitioner was
premature as the 365 days period of completion started only
on May 2, 2008, thus giving him until April 20,2009. UTASSCO on
the other hand, claimed that petitioner has no cause of action
against them. They argued that the performance bond merely
guaranteed the 20% down payment which was already
exhausted. UTASSCO, otherwise, filed a cross-claim against
Mabunay for the Indemnity Agreement which Mabunay
undertook to indemnify respondent for whatever amounts it
may be adjudged liable to pay petitioner under the surety
bond
CIAC RULING - Respondents Mabunay and UTASSCO were
ordered to jointly and severally pay the unliquidated damages
and the unrecouped down payment. It being understood that
UTASSCO‟s liability shall not exceed P8.4 million. CIAC also
ordered Mabunay to indemnify UTASSCO of the amounts
UTASSCO will have paid to claimant under the decision.
CA_____________________________________________________
The CA assailed CIAC decision that the specific condition in the
Performance Bond did not clearly state the limitation of the
surety‟s liability, thus, should be construed in favour of the
petitioner
However, the CA reversed the CIAC‟s ruling that Mabunay had
incurred delay which entitle petitioner to the stipulated
liquidated damages and unrecouped down payment. It held
that it is only from December 24,2008 (completion date) that
default should be reckoned with because the Construction
Agreement provided only for delay in the completion of the
project and not delay on a monthly basis using the work
schedule as reference point. Hence, petitioner‟s termination of
the contract was premature and obligation was not yet
demandable.
Shierly C. Ba-ad
JD 2A
ISSUES
RULING
Shierly C. Ba-ad
JD 2A
Whether or not, the Court of Appeals erred in deciding the case
upon an issue not raised or litigated before the CIAC.
Shierly C. Ba-ad
JD 2A
Whether or not respondent surety bond, UTASSCO, is
liable for the breach committed by Mabunay
Shierly C. Ba-ad
JD 2A