Guidelines Norms For Grant of Permission Amendments Reg DT On 28th January 2021
Guidelines Norms For Grant of Permission Amendments Reg DT On 28th January 2021
Guidelines Norms For Grant of Permission Amendments Reg DT On 28th January 2021
Government of India
Ministry of Road Transport a Highways
san (paB) Section
Transport Bhawan, 1, Parliament Street, New Delhi- 110001
Subject: Guidelines / Norms for grant of permission for construction of access to Fuel
Stations, Wayside Amenities, Connecting Roads, Other Properties, Rest Area Complexes a
such other facilities - amendments reg.
Sir,
The Ministry of Road Transport and Highways (MoRTH) has issued Guidelines / Norms
regarding grant of permission for construction of access to Fuel Stations, Wayside Amenities,
Connecting Roads, Other Properties, Rest Area Complexes & such other facilities vide circular
No. RW/NH-33032/01 /2017-S&R(R) dated 26.06.2020.
3. The matter has been examined in this Ministry and it has been decided by competent
authority to provide reliefs by amendment in the Revised Guidelines / Norms dated
26.06.2020 to the extent as below:
a. For the applications of access permissions submitted on online portal of MoRTHfor the
retail outlets allotted by Petroleum companies, plots acquired by applicants in urban
areas as per earlier guidelines (prior to 26.06.2020) i.e. of 20mx20m, the NOCsmay
be granted as per revised guidelines dated 26.06.2020 with relaxation for plot size of
20mx20m (instead of desired plot size of 30mx30m).
b. Processing fee may be waived off and access permission allowed for the cases where
due to change in National Highways configuration (widening, alignment change etc.),
the existing retail outlet locations have to be closed as the location becomes in non-
compliance with the access permission norms and the retail outlet owner/operator is
seeking permission for an alternate location complying with revised access permission
norms dated 26.06.2020.
Page 1 of 2
c. In case of any conflict on ground needing any relaxation in MoRTH revised guidelines
dated 26.06.2020, the relaxation may be granted with the approval of Minister(RT8:H).
4. This circular issues with the approval of the competent authority.
Copy to:
Page 2 of 2