Nothing Special   »   [go: up one dir, main page]

0% found this document useful (0 votes)
501 views3 pages

Revenue Recognition: Long Term Construction

Download as docx, pdf, or txt
Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1/ 3

REVENUE RECOGNITION: LONG TERM CONSTRUCTION

Question 12: XIII - Computation of CIP, net and Progress Billings


On January 1, 2005, Cleveland Enterprises obtained a contract to construct a building. It was
estimated at the beginning of the contract that it would take three years to complete the project at an
expected cost of P200,000. The contract price was P250,000. The following information describes the
status of the job at the close of production each year:

  20x4 20x5 20x6


Actual costs incurred P110,000 P120,000 P15,000
Estimated costs to complete 100,000 20,000 0
Billings on contract 125,000 125,000 0
Collections on contract 120,000 120,000 10,000

Required: Compute the items listed below for each year assuming (round all percentages decimals)
1. The use of the overtime/percentage-of-completion cost-to-cost method, and
2. The point-in-time/cost recovery (zero-profit) method

Percentage-of-Completion Method (Cost-to-Cost Approach)


  20x4 20x5 20x6
Revenue recognized during the year (1) (6) (11)
Gross profit recognized during the year (2) (7) (12)
Balance in the construction in progress (CIP) account (3) (8) 0
at December 31 after closing entries)
Balance in the progress billing account at December 31 (4) (9) 0
(after closing entries)
The balance in CIP, net or Progress Billings, net (5) (10) 0
 

Cost Recovery Method


20x4 20x5 20x6
Revenue recognized during the year (13) (18) (23)
Gross profit recognized during the year (14) (19) (24)
Balance in the construction in progress (CIP) account
(15) (20) 0
at December 31 after closing entries)
Balance in the progress billing account at December
(16) (21) 0
31 (after closing entries)
The balance in CIP, net or Progress Billings, net (17) (22) 0
 

Question 13: XIV - Computation of CIP, net and Progress Billings


On January 1, 20x4, Edwards Inc. obtained a contract to construct a building. It was estimated at the
beginning of the contract that it would take 3 years to complete the project at an expected cost
P200.000. The contract price was P250,000. The following information describes the status of the job
at the close of production each year:
20x4 20x5 20x6
Actual costs incurred P150,000 P100,000 P15,000
Estimated costs to complete 90,000 20,000 0

Billings on contract 110,000 120,000 20,000


Collections on contract 100,000 120,000 30,000

Required: Compute the items listed below for each year assuming (round all percentages to two
decimals)
1. The use of the overtime/percentage-of-completion cost-to-cost method, and
2. The point-in-time/cost recovery (zero-profit) method

  20x4 20x5 20x6


Revenue recognized during the year (1) (6) (11)
Gross profit recognized during the year (2) (7) (12)
Balance in the construction in progress (CIP) account at
(3) (8) (13)
December 31 after closing entries)
Balance in the progress billing account at December 31
(4) (9) (14)
(after closing entries)
The balance in CIP, net or Progress Billings, net (5) (10) (15)
 
Percentage-of-Completion Method (Cost-to-Cost Approach)
  20x4 20x5 20x6
Revenue recognized during the year (1) (6) (11)
Gross profit recognized during the year (2) (7) (12)
Balance in the construction in progress (CIP) (3) (8) 0
account at December 31 after closing entries)
Balance in the progress billing account at (4) (9) 0
December 31 (after closing entries)
The balance in CIP, net or Progress Billings, net (5) (10) 0
 

Cost Recovery Method


  20x4 20x5 20x6
Revenue recognized during the year (13) (18) (23)
Gross profit recognized during the year (14) (19) (24)
Balance in the construction in progress (CIP) (15) (20) 0
account at December 31 after closing entries)
Balance in the progress billing account at December (16) (21) 0
31 (after closing entries)
The balance in CIP, net or Progress Billings, net (17) (22) 0

You might also like