Sl. No. Description Previous Day Present Day Cumulative Quantity Plate Thickness

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

Package Name: CP-08, Supplying,fabrication & Laying of clear water transmission main from Harohalli to Vajarahalli.

DAILY PROGRESS REPORT ON FABRICATION YARD DATE:28.01.2021


MS PIPELINE WORKS
Previous Day Present Day Cumulative Quantity
Plate
Sl. No. Description
Thickness Numbers Meters Numbers Meters Numbers Meters

20 1075 2630 28 70.0 1103 2700.0


1 Edge cutting (Nos)
18 290 725 0 0.0 290 725.0
20 1047 2630 25 62.5 1072 2692.5
2 Rolling (Nos)
18 290 725 0 0.0 290 725.0
20 349 2617.5 6 45.0 355 2662.5
3 Fit up (Meters)
18 96 720 0 0.0 96 720.0

20 349 2617.5 2 15.0 351 2632.5


4 SAW Welding (Meters)
18 96 720 0 0.0 96 720.0

20 345 2587.5 0 0.0 345 2587.5


5 Radiography test (Meters)
18 95 712.5 0 0.0 95 712.5

20 340 2550 0 0.0 340 2550.0


6 Hydraulic test (Meters)
18 93 697.5 0 0.0 93 697.5

20 107 802.5 0 0.0 107 802.5


7 Copper slag Blasting
18 0 0 0 0.0 0 0.0

20 86 645 5 37.5 91 682.5


8 Epoxy coating (Meters)
18 0 0 0 0.0 0 0.0

20 115 825 3 22.5 118 847.5


9 Wrapping of welded mesh (Meters)
18 0 0 0 0.0 0 0.0

20 104 750 7 52.5 111 802.5


10 Guniting
18 0 0 0 0.0 0 0.0

20 53 375 6 45.0 59 420.0


11 Laying
18 0 0 0 0.0 0 0.0
SPML ONTB BWSSB
Package Name: CP-08, Supplying,fabrication & Laying of clear water transmission main
from Harohalli to Vajarahalli.

DAILY PROGRESS REPORT ON LAYING SITE DATE :28-01-2021


MS PIPELINE LAYING DETAILS

CHAINAGE IN MTRS LAYING DETAILS ( IN NOS)


SL.NO CONTRACTOR NAME TOTAL MTRS REMARKS
AS ON
FROM TO TODAY TOTAL
YESTRDAY
1 UBEN PROJECTS 585 832.5 247.5 32 1 33 Work in Progress
2 MAHENDRA REDDY KOKU 1300 1442.5 142.5 16 3 19 Work in Progress
3 BEM ENTERPRISES 4830 4875 45 5 1 6 Work in Progress
4 RGN ENTERPRISES 5800 5807.5 7.5 0 1 1 Work in Progress
4 442.5
TOTAL 442.5 53 6 59