Revision No.: 0 Revision Date: 12 Dec 2020 Project: Wilmont's Pharmacy Drone Project - Project Gantt Chart
Revision No.: 0 Revision Date: 12 Dec 2020 Project: Wilmont's Pharmacy Drone Project - Project Gantt Chart
Revision No.: 0 Revision Date: 12 Dec 2020 Project: Wilmont's Pharmacy Drone Project - Project Gantt Chart
Revision No.: 0
Revision Date: 12 Dec 2020
Weeks
Activity Duration (Wks) Start Time (Wk) Finish Time (Wk) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
1.1 Initiating 0
1.1.1 Develop Scope and Plan
1.1.1.1 Develop project charter 1 0 1
1.1.1.2 Develop project scope 1 1 2
1.1.2 Engage Stakeholders
1.1.2.1 Develop stakeholders register 1 2 3
1.1.2.2 Establish communication channels 1 3 4
1.1.3 Raise Funds
1.1.3.1 Prepare a budget plan 1 2 3
1.1.3.2 Discuss constraints and exclusions 1 4 5
1.2 Planning
1.2.1 System Design
1.2.1.1 Customize bagging system and clamps 2 5 7
1.2.1.2 Customize system interfaces 1 5 6
1.2.2 Cost Estimate
1.2.2.1 Drone and all related piloting cost 1 5 6
1.2.2.2 Project teams and outsourcing cost 1 5 6
1.2.3 Approvals
1.2.3.1 Develop WBS and risk assessment matrix 2 7 9
1.2.3.2 Negotiate the contract 2 9 11
1.3 Construction
1.3.1 Purchase Materials
1.3.1.1 Purchase 4 drones and spare parts 16 11 27
1.3.1.2 Labor Cost 6 11 17
1.3.2 Customize System and interfaces
1.3.2.1 Develop UI/UX as required 10 17 27
1.3.2.2 Develop information security system 16 17 33
1.3.3 Engage Specialist 12 11 23
1.3.4 Complete Assembly and Integration
1.3.4.1 Assembly and painting 2 27 29
1.3.4.2 Integration of systems and interfaces 8 33 41
1.4 Testing
1.4.1 Component/System Testing
1.4.1.1 Component Testing 9 40 49
1.4.1.2 System Testing 10 41 51
1.4.2 Track Testing
1.4.2.1 Variable testing environment (conditions) 4 51 55
1.4.2.2 Distance travel testing 3 55 58