General Specifications: Detail A
General Specifications: Detail A
General Specifications: Detail A
ALL DESIGNS AND INSTALLATIONS SHALL BE IN COMPLIANCE WITH ICAO ANNEX 14 ON AERODROME DESIGN
AND OPERATIONS, AND GUIDED BY PHILIPPINE ELECTRONICS CODE (R.A. 9292) ON TELECOMMUNICATIONS
ELECTRONIC SAFETY & SECURITY FACILITIES DISTRIBUTION SYSTEM
1) ALL DIMENSIONS ARE IN METERS (m) UNLESS OTHERWISE NOTED
2) ALL INSTALLATIONS SHALL BE IN ACCORDANCE WITH NFPA 72-2010 STANDARD REQUIREMENT
3) UNLESS OTHERWISE INDICATED IN THE DRAWINGS, MINIMUM SIZE OF CONDUIT SHALL BE 20mm DIA.
4) CONDUITS SHALL HAVE PROTECTIVE BUSHING PLACED AT ALL CONNECTION POINT TO PREVENT DAMAGE TO CABLES
5) ALL CONDUIT RUNS SHALL NOT EXCEED 3O METERS OR TWO (2) 90 DEGREES BENDS. OTHERWISE, PULLBOXES ARE
REQUIRED.
6) ALL CEILING MOUNTED DEVICES SHALL BE INSTALLED WITH MINIMUM OF 20 mm DIA. FLEXIBLE CONDUIT
7) AT A MINIMUM, SPACING BETWEEN ELECTRICAL LIGHTS SHALL BE 300mm AND 910mm FROM HVAC SUPPLY
DIFFUSER
8) ALL DEVICES, EQUIPMENT, MATERIALS SPECIFICATION & REQUIREMENTS SHALL BE READ IN CONJUNCTION TO
PROJECT SPECIFICATION & ELECTRONICS SAFETY OR SECURITY.
9) INTERCOM WIRING SHALL COMPLY TO THE REQUIREMENTS FOR RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS.
10) FOR WIRING WITHIN ENCLOSURES: CONDUCTORS SHOULD BE BUNDLE LACED, AND TRAINED TO TERMINAL POINTS
WITH NO EXCESS AND WITHOUT EXCEEDING MANUFACTURER'S LIMITATION ON BENDING RADII.
11) CABLE DUCTING SHALL BE ALLOCATED FOR SPECIALIZED COMMUNICATIONS EQUIPMENT TO INCLUDE THE FOLLOWING:
INSTALL A FULL-HEIGHT (FLOOR TO CEILING) CABLE LADDER IN THE VERTICAL COMMUNICATIONS RISER.
11.5 0.56 M2 MINIMUM COMMUNICATIONS SPACE UNDER THE FIRST FLOOR BENEATH COMMUNICATIONS
DUCT RISER WITH MANHOLE ACCESS PORT FROM THE FIRST FLOOR.
FRONT VIEW
13.) ALL COMMUNICATION SYSTEMS SHALL BE EQUIPPED WITH UPS TO ACT AS POWER SUPPLY DURING POWER FAILURE SECTION
INTERVALS AS PER ICAO RECOMMENDATION 8.1.3 ANNEX 14
SECTION
2012
MSV PROPOSED 18 STOREY CLARK AIR TRAFFIC
CONSTRUCTION & SUPPLIES
U5-4E VIVIDA NORTH OMEGA AVE., COR ROLEX ST. CONTROL TOWER BUILDING FACILITY GENERAL NOTES 1
1
0001301 JANUARY 20, 2020
FAIRVIEW QUEZON CITY, PHILIPPINES
www.msvconstruction.com.ph PAM-6762535B 290-101-859-000 CLARK INTERNATIONAL AIRPORT
CITY OF SAN FERNANDO