Rfi Master Summary
Rfi Master Summary
Rfi Master Summary
S.No RFI Reference No. RFI No Description of Activity From To Side IPC PNC TPF Remarks
Request for: Inspection Inspection
1 NMSCEW/P-IV/STR/2019/001 1 Confirmation for SBC at founding level of LP6 at Viaduct No.195+900 Km 195+900 LHS 16-Mar-19 10:00 AM
2 NMSCEW/P-IV/STR/2019/002 2 Confirmation for SBC at founding level of RP6 at Viaduct No. 196+568 Km 196+568 RHS 16-Mar-19 11:30 AM
3 NMSCEW/P-IV/STR/2019/003 3 Confirmation for SBC at founding level of RP7 at Viaduct No. 196+568 Km 196+568 RHS 16-Mar-19 12:15 PM
4 NMSCEW/P-IV/STR/2019/004 4 Checking level for excavated bed for at LP- 12 Viaduct Km 169+800 LHS 17-Mar-19 12:00 AM IPC-02 DONE
5 NMSCEW/P-IV/STR/2019/004/c 004/c Checking level for excavated bed for at LP- 13 Viaduct Km 169+800 LHS 17-Mar-19 IPC-02 DONE AE
6 NMSCEW/P-IV/STR/2019/005 5 Checking of PCC at P13 and P12 Km 169+800 BHS 18-Mar-19 2:20 PM NR
7 NMSCEW/P-IV/STR/2019/004/a 004/a Checking of layout & level at RP-13 Viaduct Km 169+800 RHS 18-Mar-19 IPC-02 DONE
8 NMSCEW/P-IV/STR/2019/004/b 004/b Checking level for excavated bed for at RP-13 Viaduct Km 169+800 RHS 18-Mar-19 IPC-02 DONE AE
9 NMSCEW/P-IV/STR/2019/006 6 Layout & level checking for box culvert. Box culvert Km 163+993 Km 00+000 BHS 19-Mar-19 10:00 AM IPC-11 DONE
10 NMSCEW/P-IV/STR/2019/007 7 Layout & level checking for box culvert. Km 165+510 BHS 19-Mar-19 11:00 AM DONE
11 NMSCEW/P-IV/STR/2019/008 8 Structural Excavation for box culvert Box culvert Km 163+993 Km 00+000 BHS 19-Mar-19 11:30 AM IPC-11 DONE
12 NMSCEW/P-IV/STR/2019/009 9 Structural Excavation for box culvert Km 165+510 BHS 19-Mar-19 11:50 AM NR
13 NMSCEW/P-IV/STR/2019/010 10 SPT test LP-2 for confirmation SBC at founding level of viaduct Km 200+920 LHS 19-Mar-19 12:30 PM
14 NMSCEW/P-IV/STR/2019/011 11 SPT test RP-3 for confirmation SBC at founding level of viaduct Km 202+190 RHS 19-Mar-19 2:20 PM
15 NMSCEW/P-IV/STR/2019/012 12 Checking of PCC at P13 Km 169+800 RHS 19-Mar-19 9:00 AM
16 NMSCEW/P-IV/STR/2019/013 13 Checking of layout & level at P12 Km 169+800 LHS 19-Mar-19 9:30 AM NR
17 NMSCEW/P-IV/STR/2019/014 14 Checking of layout & level at P12 Viaduct Km 169+800 RHS 19-Mar-19 9:30 AM NR
18 NMSCEW/P-IV/STR/2019/015 15 Checking of PCC at P12 Km 169+800 LHS 19-Mar-19 10:30 AM NR
19 NMSCEW/P-IV/STR/2019/016 16 Checking of PCC at P12 Viaduct Km 169+800 RHS 19-Mar-19 10:30 AM NR
20 NMSCEW/P-IV/STR/2019/012/b 012/b Checking top Level & Laying concrete PCC for RP-13 Viaduct Km 169+800 RHS 19-Mar-19 IPC-02 DONE AE
21 NMSCEW/P-IV/STR/2019/017 17 Layout & level checking & structural excavation for box culvert. Box Culvert Km 186+352 BHS 20-Mar-19 10:00 AM IPC-05 DONE AE
22 NMSCEW/P-IV/STR/2019/018 18 Excavation for box culvert Km 186+352 BHS 20-Mar-19 11:30 AM NR
23 NMSCEW/P-IV/STR/2019/019 19 Checking of layout & level for foundation at P9 Km 196+560 RHS 20-Mar-19 12:30 PM
24 NMSCEW/P-IV/STR/2019/020 20 Checking of foundation PCC at P9 Km 196+560 RHS 20-Mar-19 2:00 PM
25 NMSCEW/P-IV/STR/2019/021 21 Checking top Level & Laying concrete PCC for LP- 12 Viaduct Km 169+800 LHS 20-Mar-19 12:00 AM IPC-02 DONE AE
26 NMSCEW/P-IV/STR/2019/022 22 Checking of foundation PCC at P12 Km 169+800 LHS 20-Mar-19 3:30 PM NR
27 NMSCEW/P-IV/STR/2019/023 23 Checking of layout & level for foundation at P13 Km 169+800 LHS 22-Mar-19 9:00 AM
28 NMSCEW/P-IV/STR/2019/024 24 Checking of PCC at P13 Km 169+800 LHS 22-Mar-19 10:00 AM NR
29 NMSCEW/P-IV/STR/2019/025 25 Inspection for concreating M15 for PCC box culvert Km 163+993 BHS 22-Mar-19 11:00 AM NR
30 NMSCEW/P-IV/STR/2019/026 26 Blank RFI Blank RFI
31 NMSCEW/P-IV/STR/2019/023/A 023/A Checking of layout & level at RP-03 Viaduct Km 169+800 RHS 22-Mar-19 IPC-02 DONE
32 NMSCEW/P-IV/STR/2019/027 27 Checking of layout and level at P 1 Km 169+800 LHS 25-Mar-19 9:00 AM NR
33 NMSCEW/P-IV/STR/2019/028 28 Checking of layout and level at P 2 Viaduct Km 169+800 RHS 25-Mar-19 9:30 AM NR
34 NMSCEW/P-IV/STR/2019/029 29 Checking level for excavated bed for at RP-03 Viaduct Km 169+800 RHS 25-Mar-19 12:00 AM IPC-02 DONE
35 NMSCEW/P-IV/STR/2019/030 30 Checking level for excavated bed for at LP-03 Viaduct Km 169+800 LHS 25-Mar-19 12:00 AM IPC-02 DONE AE
36 NMSCEW/P-IV/STR/2019/031 31 Checking of PCC at P1 Km 169+800 LHS 25-Mar-19 11:00 AM NR
37 NMSCEW/P-IV/STR/2019/032 32 Checking of PCC at P2 Viaduct Km 169+800 RHS 25-Mar-19 11:30 AM NR
38 NMSCEW/P-IV/STR/2019/033 33 Checking of PCC at P3 Km 169+800 RHS 25-Mar-19 12:00 PM NR
39 NMSCEW/P-IV/STR/2019/034 34 Checking of PCC at P3 Km 169+800 LHS 25-Mar-19 12:30 PM NR
40 NMSCEW/P-IV/STR/2019/035 35 Checking of SPT TEST at P8 Km 169+800 LHS 25-Mar-19 9:00 AM NR
41 NMSCEW/P-IV/STR/2019/036 36 Checking of layout and level. PUP Km 184+190 BHS 25-Mar-19 12:00 AM IPC-03 DONE AE
42 NMSCEW/P-IV/STR/2019/037 37 Layout & level checking for PUP PUP Km 183+290 BHS 25-Mar-19 10:00 AM IPC-04 DONE
43 NMSCEW/P-IV/STR/2019/038 38 Checking level for excavated bed. PUP Km 184+190 BHS 25-Mar-19 12:00 AM IPC-03 DONE AE
44 NMSCEW/P-IV/STR/2019/039 39 Structural Excavation for PUP PUP Km 183+290 BHS 25-Mar-19 12:30 PM IPC-04 DONE
45 NMSCEW/P-IV/STR/2019/040 40 Checking of layout and level at P 4 foundation Km 202+190 RHS 25-Mar-19 9:15 AM
46 NMSCEW/P-IV/STR/2019/041 41 Checking of PCC at P4 foundation Km 202+190 RHS 25-Mar-19 9:45 AM
47 NMSCEW/P-IV/STR/2019/042 42 Checking of layout and level at P 3 foundation Km 200+920 RHS 25-Mar-19 10:15 AM
48 NMSCEW/P-IV/STR/2019/043 43 Checking of PCC at P3 foundation Km 200+920 RHS 25-Mar-19 11:45 AM
49 NMSCEW/P-IV/STR/2019/044 44 Checking of layout and level at LP1 foundation Km 200+920 LHS 25-Mar-19 12:45 PM
50 NMSCEW/P-IV/STR/2019/045 45 Checking of layout and level at RP1 foundation Km 200+920 RHS 25-Mar-19 2:10 PM
51 NMSCEW/P-IV/STR/2019/046 46 Checking of layout and level at RP 9 foundation Viaduct Km 196+560 RHS 25-Mar-19 2:30 PM IPC-04 DONE AE
52 NMSCEW/P-IV/STR/2019/047 47 Checking of layout and level at LP 6 foundation Km 196+560 LHS 25-Mar-19 3:00 PM
53 NMSCEW/P-IV/STR/2019/048 48 Checking of PCC at P9 foundation Km 196+560 RHS 25-Mar-19 3:30 PM
54 NMSCEW/P-IV/STR/2019/049 49 Checking of PCC at LP6 foundation Km 196+560 LHS 25-Mar-19 4:00 PM
55 NMSCEW/P-IV/STR/2019/050 50 Layout & level checking for box culvert. BOX CULVERT Km 164+156 Km 00+000 BHS 25-Mar-19 10:20 AM IPC-10 DONE
56 NMSCEW/P-IV/STR/2019/051 51 Structural Excavation for box culvert BOX CULVERT Km 164+156 Km 00+000 BHS 25-Mar-19 11:05 AM IPC-10 DONE
57 NMSCEW/P-IV/STR/2019/029/A 029/A Checking of layout & level at LP-03 Viaduct Km 169+800 LHS 25-Mar-19 IPC-02 DONE
58 NMSCEW/P-IV/STR/2019/053 53 Checking of layout and level. PUP Km 186+000 BHS 26-Mar-19 12:00 AM IPC-03 DONE AE
59 NMSCEW/P-IV/STR/2019/054 54 Checking of layout and level. PUP Km 185+235 BHS 26-Mar-19 12:00 AM IPC-03 DONE AE
60 NMSCEW/P-IV/STR/2019/055 55 Structural Excavation for PUP PUP Km 185+235 BHS 26-Mar-19 11:30 AM IPC-03 DONE
61 NMSCEW/P-IV/STR/2019/056 56 Structural Excavation for PUP Km 186+000 BHS 26-Mar-19 12:00 PM NR
62 NMSCEW/P-IV/STR/2019/057 57 Layout & level checking for PUP PUP Km 177+810 BHS 26-Mar-19 9:30 AM IPC-03 DONE
63 NMSCEW/P-IV/STR/2019/058 58 Layout & level checking & structural excavation for LVUP LVUP Km 178+323 BHS 26-Mar-19 11:00 AM IPC-08 DONE
64 NMSCEW/P-IV/STR/2019/059 59 Layout & level checking for PUP Km 178+910 BHS 26-Mar-19 2:10 PM NR
65 NMSCEW/P-IV/STR/2019/060 60 Checking of layout and level at P3 Km 169+800 LHS 26-Mar-19 3:00 PM NR
66 NMSCEW/P-IV/STR/2019/061 61 Checking of PCC at P3 Km 169+800 LHS 26-Mar-19 4:00 PM NR
67 NMSCEW/P-IV/STR/2019/062 62 Checking PCC for box culvert concreting of M10 Box culvert Km 163+993 Km 00+000 BHS 27-Mar-19 9:30 AM IPC-11 DONE
68 NMSCEW/P-IV/STR/2019/063 63 Layout & level checking for CUP CUP Km 205+430 Km 00+000 BHS 27-Mar-19 10:00 AM IPC-03 DONE AE
69 NMSCEW/P-IV/STR/2019/064 64 Structural Excavation for CUP CUP Km 205+430 Km 00+000 BHS 27-Mar-19 10:30 AM IPC-03 DONE AE
70 NMSCEW/P-IV/STR/2019/065 65 Layout & level checking for CUP Km 206+980 BHS 27-Mar-19 10:50 AM NA
71 NMSCEW/P-IV/STR/2019/066 66 Structural Excavation for CUP Km 206+980 BHS 27-Mar-19 11:20 AM NA
72 NMSCEW/P-IV/STR/2019/067 67 Checking of layout and level at RP 1 Km 195+900 RHS 27-Mar-19 9:00 AM
73 NMSCEW/P-IV/STR/2019/068 68 Checking of foundation Excavation for RP1 Km 195+900 RHS 27-Mar-19 9:45 AM
74 NMSCEW/P-IV/STR/2019/069 69 Checking of PCC at RP1 Km 195+900 RHS 27-Mar-19 12:00 PM
75 NMSCEW/P-IV/STR/2019/070 70 Checking of layout and level at RP 2 Km 195+900 RHS 27-Mar-19 2:50 PM
76 NMSCEW/P-IV/STR/2019/071 71 Checking of foundation Excavation for RP2 Km 195+900 RHS 27-Mar-19 3:30 PM
77 NMSCEW/P-IV/STR/2019/072 72 Checking of PCC at RP2 Km 195+900 RHS 27-Mar-19 4:20 PM
78 NMSCEW/P-IV/STR/2019/073 73 Checking of layout and level at L P 4 foundation Viaduct Km 202+190 LHS 27-Mar-19 11:50 AM IPC-04 DONE AE
79 NMSCEW/P-IV/STR/2019/074 74 Checking of foundation Excavation for LP4 Viaduct Km 202+190 LHS 27-Mar-19 12:15 PM IPC-04 DONE AE
80 NMSCEW/P-IV/STR/2019/075 75 Checking of PCC at LP4 foundation Viaduct Km 202+190 LHS 27-Mar-19 12:45 PM IPC-04 DONE
81 NMSCEW/P-IV/STR/2019/076 76 Checking of foundation excavation at P4 Km 202+190 RHS 27-Mar-19 2:10 PM
82 NMSCEW/P-IV/STR/2019/077 77 Checking of foundation Excavation for LP6 Km 196+560 LHS 28-Mar-19 9:50 AM
83 NMSCEW/P-IV/STR/2019/078 78 Checking of foundation Excavation for RP9 Viaduct Km 196+560 RHS 28-Mar-19 10:15 AM IPC-04 DONE AE
84 NMSCEW/P-IV/STR/2019/079 79 Checking of foundation Excavation for LP4 Km 169+800 LHS 28-Mar-19 11:20 AM NR
85 NMSCEW/P-IV/STR/2019/080 80 Checking of foundation Excavation for RP4 Km 169+800 RHS 28-Mar-19 12:00 PM NR
86 NMSCEW/P-IV/STR/2019/081 81 Checking of foundation Excavation for RP3 Km 169+800 RHS 28-Mar-19 12:30 PM NR
87 NMSCEW/P-IV/STR/2019/082 82 Checking of layout and level for PUP Km 203+560 BHS 28-Mar-19 9:30 AM NA
88 NMSCEW/P-IV/STR/2019/083 83 Checking Structural Excavation for PUP Km 203+560 BHS 28-Mar-19 10:00 AM NA
89 NMSCEW/P-IV/STR/2019/084 84 Checking of layout and level for PUP PUP Km 204+470 Km 00+000 BHS 28-Mar-19 10:40 AM IPC-03 DONE
90 NMSCEW/P-IV/STR/2019/085 85 Checking Structural Excavation for PUP Km 204+470 BHS 28-Mar-19 12:00 AM DONE
91 NMSCEW/P-IV/STR/2019/086 86 Checking of PCC for PUP Km 205+430 BHS 28-Mar-19 11:45 AM DONE
92 NMSCEW/P-IV/STR/2019/087 87 GSB filling at PCC level due to removal of black cotton soil for PUP Km 184+190 BHS 28-Mar-19 11:00 AM NR
93 NMSCEW/P-IV/STR/2019/088 88 Checking layout of Box Culvert Km 204+945 BHS 29-Mar-19 10:00 AM DONE
94 NMSCEW/P-IV/STR/2019/089 89 Checking Excavation of Box Culvert Km 204+945 BHS 29-Mar-19 11:00 AM DONE
95 NMSCEW/P-IV/STR/2019/090 90 Checking Excavation level & laying of concrete for PCC of PUP PUP Km 205+430 Km 00+000 RHS 29-Mar-19 12:00 PM IPC-03 DONE AE
96 NMSCEW/P-IV/STR/2019/091 91 Checking Excavation of PUP Km 205+430 LHS 29-Mar-19 2:20 PM DONE
97 NMSCEW/P-IV/STR/2019/092 92 Checking level for excavated bed PUP Km 183+290 BHS 30-Mar-19 10:30 AM IPC-04 DONE
98 NMSCEW/P-IV/STR/2019/093 93 Checking level for excavated bed. PUP Km 185+235 BHS 30-Mar-19 12:00 AM IPC-03 DONE AE
99 NMSCEW/P-IV/STR/2019/094 94 Laying of PCC with top level checking PUP Km 183+290 BHS 30-Mar-19 2:20 PM NR
100 NMSCEW/P-IV/STR/2019/095 95 Laying of PCC with top level checking PUP Km 185+235 BHS 30-Mar-19 4:00 PM NR
101 NMSCEW/P-IV/STR/2019/096 96 Checking level for excavated bed PUP Km 205+430 Km 00+000 LHS 30-Mar-19 10:00 AM IPC-03 DONE AE
102 NMSCEW/P-IV/STR/2019/097 97 Laying of PCC with top level checking PUP Km 205+430 LHS 30-Mar-19 11:00 AM DONE
103 NMSCEW/P-IV/STR/2019/098 98 Layout for Box culvert with OGL recording BOX CULVERT Km 204+920 BHS 30-Mar-19 12:30 PM IPC-05 DONE
104 NMSCEW/P-IV/STR/2019/099 99 Layout for Box culvert with OGL recording BOX CULVERT Km 206+843 BHS 30-Mar-19 3:00 PM DONE
105 NMSCEW/P-IV/STR/2019/100 100 Laying of PCC with top level checking PUP Km 183+290 BHS 30-Mar-19 5:00 PM NR
106 NMSCEW/P-IV/STR/2019/101 101 Checking level for excavated bed BOX CULVERT Km 164+156 BHS 30-Mar-19 2:00 PM NR
107 NMSCEW/P-IV/STR/2019/102 102 Laying of PCC with top level checking BOX CULVERT Km 164+156 BHS 30-Mar-19 3:00 PM NR
108 NMSCEW/P-IV/STR/2019/103 103 Laying of PCC with top level checking PUP Km 205+430 Km 00+000 LHS 1-Apr-19 9:30 AM IPC-03 DONE AE
109 NMSCEW/P-IV/STR/2019/104 104 Layout of Box culvert with OGL recording Box Culvert Km 204+409 Km 00+000 BHS 1-Apr-19 10:30 AM IPC-09 DONE
110 NMSCEW/P-IV/STR/2019/105 105 Laying of PCC with top level checking Box Culvert Km 204+409 Km 00+000 BHS 1-Apr-19 11:45 AM IPC-09 DONE AE
111 NMSCEW/P-IV/STR/2019/106 106 Laying of PCC with top level checking PUP Km 183+290 BHS 1-Apr-19 2:00 PM IPC-04 DONE
112 NMSCEW/P-IV/STR/2019/107 107 Checking level for excavated bed PUP Km 186+000 BHS 2-Apr-19 9:30 AM IPC-03 DONE
113 NMSCEW/P-IV/STR/2019/108 108 Laying and top level checking concrete PCC PUP Km 186+000 BHS 2-Apr-19 12:00 AM IPC-03 DONE
114 NMSCEW/P-IV/STR/2019/109 109 Checking of layout and level. PUP Km 171+110 RHS 2-Apr-19 12:00 AM IPC-03 DONE AE
115 NMSCEW/P-IV/STR/2019/110 110 Checking level for excavated bed. PUP Km 171+110 RHS 2-Apr-19 12:00 AM IPC-03 DONE AE
116 NMSCEW/P-IV/STR/2019/111 111 Checking of layout and level. PUP Km 172+190 BHS 2-Apr-19 12:00 AM IPC-03 DONE AE
117 NMSCEW/P-IV/STR/2019/112 112 Checking level for excavated bed. PUP Km 172+190 BHS 2-Apr-19 12:00 AM IPC-03 DONE
118 NMSCEW/P-IV/STR/2019/113 113 Laying and top level checking concrete PCC PUP Km 172+190 BHS 2-Apr-19 12:00 AM IPC-03 DONE AE
119 NMSCEW/P-IV/STR/2019/114 114 Layout of Box culvert with OGL recording BOX CULVERT Km 164+746 BHS 3-Apr-19 12:10 PM NR
120 NMSCEW/P-IV/STR/2019/115 115 Checking level for excavated bed BOX CULVERT Km 165+510 BHS 3-Apr-19 12:15 PM DONE
121 NMSCEW/P-IV/STR/2019/116 116 Laying and top level checking of M10 concrete for PCC BOX CULVERT Km 165+510 BHS 3-Apr-19 12:30 PM NR
122 NMSCEW/P-IV/STR/2019/117 117 Laying and top level checking of M10 concrete for PCC PUP Km 171+110 BHS 3-Apr-19 12:45 PM NR
123 NMSCEW/P-IV/STR/2019/118 118 Laying and top level checking of M10 concrete for PCC PUP Km 172+190 BHS 3-Apr-19 2:30 PM NR
124 NMSCEW/P-IV/STR/2019/119 119 Laying and top level checking concrete PCC PUP Km 185+235 BHS 3-Apr-19 12:00 AM IPC-03 DONE AE
125 NMSCEW/P-IV/STR/2019/120 120 Laying and top level checking of M10 concrete for PCC PUP Km 184+190 BHS 3-Apr-19 3:00 PM NR
126 NMSCEW/P-IV/STR/2019/121 121 Layout and OGL recording PUP Km 187+835 BHS 3-Apr-19 11:20 AM IPC-05 DONE AE
127 NMSCEW/P-IV/STR/2019/122 122 Checking level for excavated bed PUP Km 187+835 BHS 3-Apr-19 12:00 PM NR
128 NMSCEW/P-IV/STR/2019/123 123 Checking for reinforcement & shuttering of B/C Precast unit type-1 at Casting Yard BOX CULVERT Km 163+993 BHS 3-Apr-19 11:30 AM NR
129 NMSCEW/P-IV/STR/2019/124 124 Checking for concreting Grade M-30 of B/C Precast unit type-1 at Casting Yard BOX CULVERT Km 163+993 BHS 3-Apr-19 11:45 AM NR
130 NMSCEW/P-IV/STR/2019/125 125 Checking level & Layout for excavated bed BOX CULVERT Km 204+409 BHS 3-Apr-19 3:15 PM
131 NMSCEW/P-IV/STR/2019/126 126 Laying and top level checking of M10 concrete for PCC BOX CULVERT Km 204+409 BHS 3-Apr-19 3:30 PM
132 NMSCEW/P-IV/STR/2019/127 127 Laying and top level checking of M10 concrete for PCC BOX CULVERT Km 164+156 Km 00+000 BHS 4-Apr-19 10:00 AM IPC-10 DONE AE
133 NMSCEW/P-IV/STR/2019/128 128 Laying and top level checking concrete PCC PUP Km 171+110 RHS 4-Apr-19 12:00 AM IPC-03 DONE AE
134 NMSCEW/P-IV/STR/2019/129 129 Laying and top level checking of M10 concrete for PCC BOX CULVERT Km 164+156 BHS 4-Apr-19 10:30 AM NR
135 NMSCEW/P-IV/STR/2019/130 130 Checking of layout and level for PUP PUP Km 204+470 LHS 4-Apr-19 11:00 AM DONE
136 NMSCEW/P-IV/STR/2019/131 131 Checking level for excavated bed PUP Km 187+835 BHS 4-Apr-19 10:00 AM NR
137 NMSCEW/P-IV/STR/2019/132 132 Laying and top level checking of M10 concrete for PCC BOX CULVERT Km 186+352 BHS 4-Apr-19 12:00 PM NR
138 NMSCEW/P-IV/STR/2019/133 133 Laying and top level checking of M10 concrete for PCC PUP Km 184+190 BHS 4-Apr-19 3:00 PM NR
139 NMSCEW/P-IV/STR/2019/134 134 Checking of layout and level for B/C BOX CULVERT Km 204+920 BHS 4-Apr-19 9:00 AM NA
140 NMSCEW/P-IV/STR/2019/135 135 Checking of layout and level for PUP PUP Km 204+470 LHS 5-Apr-19 10:00 AM DONE
141 NMSCEW/P-IV/STR/2019/136 136 Checking of layout and level for B/C BOX CULVERT Km 164+756 BHS 5-Apr-19 10:00 AM DONE
142 NMSCEW/P-IV/STR/2019/137 137 Laying and top level checking of M10 concrete for PCC BOX CULVERT Km 164+756 BHS 5-Apr-19 11:00 AM NR
143 NMSCEW/P-IV/STR/2019/138 138 Checking level & Layout for excavated bed PUP Km 174+095 BHS 5-Apr-19 10:30 AM NR
144 NMSCEW/P-IV/STR/2019/139 139 Laying and top level checking of M10 concrete for PCC PUP Km 174+095 BHS 5-Apr-19 10:45 AM NR
145 NMSCEW/P-IV/STR/2019/140 140 Checking level & Layout for excavated bed PUP Km 187+835 BHS 5-Apr-19 10:00 AM IPC-05 DONE AE
146 NMSCEW/P-IV/STR/2019/141 141 Laying and top level checking of M10 concrete for PCC BOX CULVERT Km 186+352 BHS 5-Apr-19 9:00 AM IPC-05 DONE AE
147 NMSCEW/P-IV/STR/2019/142 142 Laying and top level checking of M10 concrete for PCC PUP Km 184+190 BHS 5-Apr-19 3:00 PM NR
148 NMSCEW/P-IV/STR/2019/143 143 Checking of layout and level for B/C BOX CULVERT Km 204+920 BHS 5-Apr-19 10:00 AM IPC-05 DONE AE
149 NMSCEW/P-IV/STR/2019/144 144 Laying and top level checking of M10 concrete for PCC PUP Km 204+470 Km 00+000 BHS 5-Apr-19 11:00 AM IPC-03 DONE
150 NMSCEW/P-IV/STR/2019/145 145 Checking of layout and level for PUP PUP Km 204+470 Km 00+000 RHS 5-Apr-19 10:10 AM IPC-03 DONE
151 NMSCEW/P-IV/STR/2019/146 146 Checking of layout and level for B/C BOX CULVERT Km 204+920 BHS 5-Apr-19 11:15 AM NA
152 NMSCEW/P-IV/STR/2019/147 147 Checking for reinforcement & shuttering of B/C Precast unit type-1 at Casting Yard - 02 Nos BOX CULVERT Km 164+156 BHS 5-Apr-19 11:00 AM NR
153 NMSCEW/P-IV/STR/2019/148 148 Checking level for excavated bed BOX CULVERT Km 164+756 BHS 6-Apr-19 10:00 AM DONE
154 NMSCEW/P-IV/STR/2019/149 149 Laying and top level checking of M10 concrete for PCC BOX CULVERT Km 164+756 BHS 6-Apr-19 10:30 AM DONE
155 NMSCEW/P-IV/STR/2019/150 150 Checking of layout and level for B/C BOX CULVERT Km 163+570 Km 00+000 BHS 6-Apr-19 11:00 AM IPC-10 DONE
156 NMSCEW/P-IV/STR/2019/151 151 Checking level for excavated bed BOX CULVERT Km 163+570 BHS 6-Apr-19 11:40 AM NR
157 NMSCEW/P-IV/STR/2019/152 152 Checking of layout and level for PUP PUP Km 188+575 BHS 6-Apr-19 12:30 PM NR
158 NMSCEW/P-IV/STR/2019/153 153 Checking level for excavated bed PUP Km 188+575 BHS 6-Apr-19 2:10 PM NR
Checking for reinforcement & shuttering of B/C Precast unit type-1 (cushion 2 to 4 mtr) at
159 NMSCEW/P-IV/STR/2019/154 154 BOX CULVERT Km 164+156 BHS 6-Apr-19 9:00 AM DONE
Casting Yard
Checking - 02 Nos grade M30 of B/C Precast unit type-1 (cushion 2 to 4 mtr) at Casting
for Concreting
160 NMSCEW/P-IV/STR/2019/155 155 BOX CULVERT Km 164+156 BHS 6-Apr-19 11:00 AM DONE
Yard - 02 Nos
161 NMSCEW/P-IV/STR/2019/156 156 Checking of layout and level for PUP PUP Km 174+095 BHS 6-Apr-19 2:50 PM IPC-04 DONE
162 NMSCEW/P-IV/STR/2019/157 157 Checking level for excavated bed PUP Km 174+095 BHS 6-Apr-19 3:30 PM IPC-04 DONE
163 NMSCEW/P-IV/STR/2019/158 158 Laying and top level checking concrete for PCC PUP Km 174+095 BHS 6-Apr-19 4:10 PM NR
164 NMSCEW/P-IV/STR/2019/159 159 Laying and top level checking concrete for PCC BOX CULVERT Km 204+920 BHS 6-Apr-19 5:00 PM IPC-05 DONE
165 NMSCEW/P-IV/STR/2019/160 160 Laying and top level checking concrete for PCC PUP Km 187+835 BHS 6-Apr-19 2:00 PM NR
166 NMSCEW/P-IV/STR/2019/161 161 Laying and top level checking of M10 concrete for PCC PUP Km 187+835 BHS 7-Apr-19 8:00 AM IPC-05 DONE
167 NMSCEW/P-IV/STR/2019/162 162 Laying and top level checking of M10 concrete for PCC PUP Km 184+190 BHS 7-Apr-19 10:00 AM NR
168 NMSCEW/P-IV/STR/2019/163 163 Checking of layout and level for PUP PUP Km 174+095 BHS 7-Apr-19 11:30 AM NR
169 NMSCEW/P-IV/STR/2019/164 164 Checking level for excavated bed PUP Km 174+095 BHS 7-Apr-19 12:00 PM NR
170 NMSCEW/P-IV/STR/2019/165 165 Laying and top level checking concrete for PCC PUP Km 174+095 BHS 7-Apr-19 2:20 PM IPC-04 DONE
171 NMSCEW/P-IV/STR/2019/166 166 Checking of layout and level for B/C BOX CULVERT Km 184+490 BHS 7-Apr-19 9:00 AM NR
172 NMSCEW/P-IV/STR/2019/167 167 Checking level for excavated bed BOX CULVERT Km 184+490 BHS 7-Apr-19 10:30 AM NR
173 NMSCEW/P-IV/STR/2019/168 168 Checking of layout and level for B/C BOX CULVERT Km 183+326 BHS 7-Apr-19 9:30 AM NR
174 NMSCEW/P-IV/STR/2019/169 169 Checking level for excavated bed BOX CULVERT Km 183+326 BHS 7-Apr-19 11:00 AM NR
175 NMSCEW/P-IV/STR/2019/170 170 Checking level for excavated bed BOX CULVERT Km 163+570 Km 00+000 BHS 8-Apr-19 10:00 AM IPC-10 DONE
176 NMSCEW/P-IV/STR/2019/171 171 Laying and top level checking of M10 concrete for PCC BOX CULVERT Km 163+570 Km 00+000 BHS 8-Apr-19 12:00 PM IPC-10 DONE
177 NMSCEW/P-IV/STR/2019/172 172 Checking of layout and level for B/C BOX CULVERT Km 206+490 BHS 8-Apr-19 11:30 AM NA
178 NMSCEW/P-IV/STR/2019/173 173 Laying and top level checking of M10 concrete for PCC PUP Km 187+835 BHS 8-Apr-19 11:30 AM NR SPOT RFI
179 NMSCEW/P-IV/STR/2019/174 174 Checking of layout and level for B/C BOX CULVERT Km 166+440 BHS 9-Apr-19 11:00 AM DONE
180 NMSCEW/P-IV/STR/2019/175 175 Checking of layout and level for LVUP LVUP Km 173+400 BHS 9-Apr-19 9:00 AM NR
181 NMSCEW/P-IV/STR/2019/176 176 Checking level for excavated bed LVUP Km 173+400 BHS 9-Apr-19 12:00 PM NR
182 NMSCEW/P-IV/STR/2019/177 177 Laying and top level checking of concrete for PCC LVUP Km 173+400 BHS 9-Apr-19 2:30 PM NR
183 NMSCEW/P-IV/STR/2019/178 178 Checking of layout and level for B/C BOX CULVERT Km 203+886 BHS 9-Apr-19 4:00 PM NA
184 NMSCEW/P-IV/STR/2019/179 179 Checking of layout and level for B/C BOX CULVERT Km 200+286 BHS 9-Apr-19 3:00 PM
Checking reinforcement for precaste box culvert 3m x 3m ,(Cushion 2m to 4m) at camp -2
185 NMSCEW/P-IV/STR/2019/180 180 BOX CULVERT Km 200+200 LHS 9-Apr-19 4:30 PM
location
186 NMSCEW/P-IV/STR/2019/181 181 Checking of layout and level for B/C,Checking for top level for PCC Box Culvert Km 206+490 Km 00+000 BHS 9-Apr-19 12:00 AM IPC-09 DONE
187 NMSCEW/P-IV/STR/2019/182 182 Checking level for excavated bed BOX CULVERT Km 184+490 BHS 9-Apr-19 10:10 AM NR
188 NMSCEW/P-IV/STR/2019/183 183 Laying and top level checking of M10 concrete for PCC PUP Km 184+190 BHS 9-Apr-19 12:30 PM NR
189 NMSCEW/P-IV/STR/2019/184 184 Checking of layout and level. PUP Km 188+575 BHS 9-Apr-19 12:00 AM IPC-03 DONE AE
190 NMSCEW/P-IV/STR/2019/185 185 Checking level for excavated bed. PUP Km 188+575 BHS 9-Apr-19 12:00 AM IPC-03 DONE AE
191 NMSCEW/P-IV/STR/2019/186 186 Laying and top level checking concrete PCC PUP Km 188+575 BHS 9-Apr-19 12:00 AM IPC-03 DONE
192 NMSCEW/P-IV/STR/2019/187 187 Laying and top level checking of M10 concrete for PCC BOX CULVERT Km 165+510 BHS 10-Apr-19 10:00 AM DONE
193 NMSCEW/P-IV/STR/2019/188 188 Checking of layout and level for PUP PUP Km 188+575 RHS 10-Apr-19 9:00 AM NR
194 NMSCEW/P-IV/STR/2019/189 189 Checking level for excavated bed PUP Km 188+575 RHS 10-Apr-19 10:30 AM NR
195 NMSCEW/P-IV/STR/2019/190 190 Laying and top level checking of M10 concrete for PCC PUP Km 188+575 RHS 10-Apr-19 12:00 PM DONE
196 NMSCEW/P-IV/STR/2019/191 191 Checking of layout and level for PUP PUP Km 189+000 BHS 10-Apr-19 9:45 AM IPC-05 DONE
197 NMSCEW/P-IV/STR/2019/192 192 Checking level for excavated bed PUP Km 189+000 BHS 10-Apr-19 2:20 PM IPC-05 DONE
198 NMSCEW/P-IV/STR/2019/193 193 Laying and top level checking of M10 concrete for PCC PUP Km 188+575 BHS 10-Apr-19 3:30 PM DONE
199 NMSCEW/P-IV/STR/2019/194 194 Laying and top level checking of concrete for PCC BOX CULVERT Km 203+886 BHS 10-Apr-19 11:00 AM DONE
200 NMSCEW/P-IV/STR/2019/195 195 Checking of layout and level for B/C BOX CULVERT Km 200+286 BHS 10-Apr-19 12:45 PM NA
201 NMSCEW/P-IV/STR/2019/196 196 Checking level for excavated bed BOX CULVERT Km 184+490 BHS 10-Apr-19 11:30 AM NR
202 NMSCEW/P-IV/STR/2019/197 197 Laying and top level checking of M10 concrete for PCC PUP Km 184+190 BHS 10-Apr-19 2:50 PM NR
203 NMSCEW/P-IV/STR/2019/198 198 Checking of layout & level & excavated bed for PUP PUP Km 165+790 BHS 11-Apr-19 10:00 AM IPC-08 DONE AE
204 NMSCEW/P-IV/STR/2019/199 199 Checking of layout and level for LVUP LVUP Km 173+400 BHS 11-Apr-19 9:00 AM NR
205 NMSCEW/P-IV/STR/2019/200 200 Checking level for excavated bed LVUP Km 173+400 BHS 11-Apr-19 11:30 AM NR
206 NMSCEW/P-IV/STR/2019/201 201 Laying and top level checking of concrete for PCC LVUP Km 173+400 BHS 11-Apr-19 2:20 PM NR
Checking concrete Pouring for precast box culvert 3m x 3m (cusion 2m to 4m)at casting yard
207 NMSCEW/P-IV/STR/2019/202 202 BOX CULVERT Km 200+200 LHS 11-Apr-19 10:30 AM DONE
of camp-2
208 NMSCEW/P-IV/STR/2019/203 203 Laying and top level checking of M10 concrete for PCC PUP Km 184+190 BHS 11-Apr-19 11:00 AM NR
209 NMSCEW/P-IV/STR/2019/204 204 Checking bottom slab reinforcement and shuttering of PUP PUP Km 183+290 LHS 11-Apr-19 12:00 PM NR
210 NMSCEW/P-IV/STR/2019/205 205 Laying and top level checking of M30 concrete for Raft PUP Km 183+290 LHS 11-Apr-19 12:30 PM NR
Checking reinforcement and shuttering for precast Box Culvert (3x3) unit type 1 (cushion 2-
211 NMSCEW/P-IV/STR/2019/206 206 BOX CULVERT Km 175+500 LHS 11-Apr-19 11:30 AM DONE
4m) for Ch Pouring
Checking 164+156 Concrete
at precast Grade
yard. UNIT NO-3
=(M-30) for & 4, location
Precast camp-1(3×3) Unit type-1
Box Culvert
212 NMSCEW/P-IV/STR/2019/207 207 BOX CULVERT Km 175+500 LHS 11-Apr-19 3:00 PM DONE
(Cushion 2 to 4 m) for Ch 164+156 at precast yard Unit No. - 3 & 4, location camp-1
213 NMSCEW/P-IV/STR/2019/208 208 Laying and top level checking of concrete for PCC at P10 Viaduct Km 196+560 RHS 11-Apr-19 9:30 AM IPC-04 DONE
214 NMSCEW/P-IV/STR/2019/208A 208A Checking level for excavated bed at RP10 Viaduct Km 196+560 RHS 13-Apr-19 11:00 AM IPC-04 DONE
215 NMSCEW/P-IV/STR/2019/209 209 Checking of layout and level for B/C BOX CULVERT Km 200+286 BHS 11-Apr-19 11:10 AM NA
216 NMSCEW/P-IV/STR/2019/210 210 Laying and top level checking of M10 concrete PCC for 3mx3m B/C BOX CULVERT Km 200+286 BHS 11-Apr-19 2:00 PM NA
217 NMSCEW/P-IV/STR/2019/211 211 Laying and top level checking of concrete for PCC at RP9 Viaduct Km 196+560 RHS 12-Apr-19 12:30 PM IPC-04 DONE AE
218 NMSCEW/P-IV/STR/2019/212 212 Checking of layout and level at P3 FLYOVER Km 169+800 RHS 12-Apr-19 2:30 PM
219 NMSCEW/P-IV/STR/2019/213 213 Checking of layout and level at P3 FLYOVER Km 169+800 LHS 12-Apr-19 3:00 PM NR
220 NMSCEW/P-IV/STR/2019/214 214 Checking of layout & level at LP- 13 Viaduct Km 169+800 LHS 12-Apr-19 12:00 AM IPC-02 DONE AE
221 NMSCEW/P-IV/STR/2019/215 215 Checking level for excavated bed at P3 FLYOVER Km 169+800 RHS 12-Apr-19 4:00 PM NR
222 NMSCEW/P-IV/STR/2019/216 216 Checking level for excavated bed at P3 FLYOVER Km 169+800 LHS 12-Apr-19 4:30 PM NR
223 NMSCEW/P-IV/STR/2019/217 217 Checking level for excavated bed at P13 FLYOVER Km 169+800 LHS 12-Apr-19 5:00 PM DONE
224 NMSCEW/P-IV/STR/2019/218 218 Laying and top level checking of concrete for PCC at P3 FLYOVER Km 169+800 RHS 12-Apr-19 5:30 PM NR
225 NMSCEW/P-IV/STR/2019/219 219 Laying and top level checking of concrete for PCC at P3 FLYOVER Km 169+800 LHS 12-Apr-19 6:00 PM NR
226 NMSCEW/P-IV/STR/2019/220 220 Checking top Level & Laying concrete PCC for LP- 13 Viaduct Km 169+800 LHS 12-Apr-19 12:00 AM IPC-02 DONE AE
227 NMSCEW/P-IV/STR/2019/221 221 Checking of layout and level for LVUP LVUP Km 173+400 BHS 12-Apr-19 9.30 AM IPC-05 DONE AE
228 NMSCEW/P-IV/STR/2019/222 222 Checking level for excavated bed LVUP Km 173+400 BHS 12-Apr-19 10.30 AM IPC-05 DONE AE
229 NMSCEW/P-IV/STR/2019/223 223 Laying and top level checking of concrete for PCC LVUP Km 173+400 RHS 12-Apr-19 11:30 AM NR
230 NMSCEW/P-IV/STR/2019/224 224 Checking of layout and level for PUP CUP Km 208+930 LHS 12-Apr-19 4:15 PM IPC-04 DONE AE
231 NMSCEW/P-IV/STR/2019/225 225 Laying and top level checking concrete PCC PUP Km 184+190 BHS 12-Apr-19 12:00 AM IPC-03 DONE
232 NMSCEW/P-IV/STR/2019/226 226 Checking bottom slab reinforcement and shuttering PUP Km 183+290 LHS 12-Apr-19 9:30 AM NR
233 NMSCEW/P-IV/STR/2019/227 227 Laying and top level checking of M30 concrete for Raft PUP Km 183+290 LHS 12-Apr-19 10:20 AM NR
234 NMSCEW/P-IV/STR/2019/228 228 Laying and top level checking of M10 concrete for PCC PUP Km 189+000 BHS 12-Apr-19 9:00 AM NR
235 NMSCEW/P-IV/STR/2019/229 229 Laying and top level checking of M10 concrete for PCC BOX CULVERT Km 200+286 BHS 12-Apr-19 9:50 AM DONE
236 NMSCEW/P-IV/STR/2019/212/A 212/A Checking of layout & level at RP-04 Viaduct Km 169+800 RHS 12-Apr-19 IPC-02 DONE
237 NMSCEW/P-IV/STR/2019/230 230 Laying and top level checking of concrete for PCC at P10 Viaduct Km 196+560 RHS 13-Apr-19 10:30 AM IPC-04 DONE AE
238 NMSCEW/P-IV/STR/2019/231 231 Laying and top level checking of concrete for PCC at RP3 Viaduct Km 195+900 RHS 13-Apr-19 3:00 PM IPC-04 DONE
239 NMSCEW/P-IV/STR/2019/231A 231A Checking of Layout & Level for RP3 Viaduct Km 195+900 RHS 13-Apr-19 10:10Am IPC-04 DONE
240 NMSCEW/P-IV/STR/2019/232 232 Laying and top level checking of concrete for PCC at RP4 FLYOVER Km 169+800 RHS 13-Apr-19 9:00 AM
Checking of reinforcement for box culvert 3m x 3m (cusing 2m to 4m)seg.no.2 at camp:2
241 NMSCEW/P-IV/STR/2019/233 233 BOX CULVERT Km 200+200 LHS 13-Apr-19 11:00 AM DONE
casting yard
242 NMSCEW/P-IV/STR/2019/234 234 Laying and top level checking of concrete PCC CUP Km 208+930 BHS 13-Apr-19 8:00 AM IPC-04 DONE AE
243 NMSCEW/P-IV/STR/2019/235 235 Checking of layout and level for PUP PUP Km 199+060 LHS 13-Apr-19 9:30 AM IPC-04 DONE
244 NMSCEW/P-IV/STR/2019/236 236 Checking of layout and level for PUP PUP Km 190+650 BHS 13-Apr-19 8:50 AM IPC-05 DONE
245 NMSCEW/P-IV/STR/2019/237 237 Laying and top level checking of M10 concrete for PCC PUP Km 189+000 BHS 13-Apr-19 11:30 AM IPC-05 DONE
246 NMSCEW/P-IV/STR/2019/238 238 Checking level for excavated bed PUP Km 165+790 BHS 13-Apr-19 10:00 AM REPEATED
247 NMSCEW/P-IV/STR/2019/239 239 Laying and top level checking of concrete PCC PUP Km 165+790 BHS 13-Apr-19 10:45 AM IPC-08 DONE AE
248 NMSCEW/P-IV/STR/2019/240 240 Checking of layout and level PUP Km 165+300 BHS 13-Apr-19 12:00 PM IPC-05 DONE AE
Checking reinforcement and shuttering for precast Box Culvert (3x3) unit type 1 (cushion 2-
249 NMSCEW/P-IV/STR/2019/241 241 Checking BOX CULVERT Km 175+500 LHS 13-Apr-19 2:00 PM DONE
4m) for Chfor Concreting
164+156 Gradeyard.
at precast =(M-30) forNO-5
UNIT Precast
& 6Box Culvert (3×3) Unit type-1
250 NMSCEW/P-IV/STR/2019/242 242 (Cushion 2 to 4 m) for Ch 164+156 at precast yard. BOX CULVERT Km 175+500 LHS 13-Apr-19 3:00 PM DONE
251 NMSCEW/P-IV/STR/2019/243 243 Unit No. - of
Checking 5& 6 and level
layout PUP Km 208+930 RHS 13-Apr-19 4:00 PM
252 NMSCEW/P-IV/STR/2019/232/A 232/A Checking top Level & Laying concrete PCC for RP-03 Viaduct Km 169+800 RHS 13-Apr-19 IPC-02 DONE AE
253 NMSCEW/P-IV/STR/2019/244 244 Laying and top level checking of concrete for PCC PUP Km 190+650 BHS 14-Apr-19 2:00 PM IPC-05 DONE
254 NMSCEW/P-IV/STR/2019/245 245 Checking bottom slab reinforcement and shuttering of PUP PUP Km 183+290 LHS 14-Apr-19 9:30 AM NR
255 NMSCEW/P-IV/STR/2019/246 246 Laying and top level checking of M30 concrete for Raft PUP Km 183+290 LHS 14-Apr-19 10:20 AM NR
256 NMSCEW/P-IV/STR/2019/247 247 Laying and top level checking of concrete PCC PUP Km 199+060 LHS 15-Apr-19 8:00 AM IPC-04 DONE AE
257 NMSCEW/P-IV/STR/2019/248 248 Checking of layout and level for B/C BOX CULVERT Km 203+886 BHS 15-Apr-19 4:00 PM DONE
Checking reinforcement and shuttering for precast Box Culvert (3x3) unit type 1 (cushion 2-
258 NMSCEW/P-IV/STR/2019/249 249 BOX CULVERT Km 175+500 LHS 16-Apr-19 10:45 AM DONE
4m) for Chfor
Checking 164+156 at precast
Concreting Gradeyard. UNIT
=(M-30) forNO-6 & 7Box Culvert (3×3) Unit type-1 (Cushion 2
Precast
259 NMSCEW/P-IV/STR/2019/250 250 BOX CULVERT Km 175+500 LHS 16-Apr-19 11:30 AM DONE
to 4 m) for Ch 164+156 at precast yard, Unit No. - 6 & 7
260 NMSCEW/P-IV/STR/2019/251 251 Checking level for excavated bed PUP Km 165+300 BHS 16-Apr-19 10:00 AM IPC-05 DONE AE
261 NMSCEW/P-IV/STR/2019/252 252 Laying and top level checking of M10 concrete for PCC PUP Km 165+300 BHS 16-Apr-19 10:30 AM IPC-05 DONE AE
262 NMSCEW/P-IV/STR/2019/254 254 Laying and top level checking of M30 concrete for Raft PUP Km 172+190 LHS 16-Apr-19 12:30 PM NR
263 NMSCEW/P-IV/STR/2019/255 255 Laying and top level checking of M10 concrete for PCC PUP Km 190+650 BHS 16-Apr-19 9:00 AM IPC-05 DONE
264 NMSCEW/P-IV/STR/2019/256 256 Laying and top level checking of M10 concrete for PCC BOX CULVERT Km 203+886 BHS 16-Apr-19 4:30 PM IPC-05 DONE AE
265 NMSCEW/P-IV/STR/2019/257 257 Checking excavation of layout and level at LP3 FLYOVER Km 169+800 LHS 16-Apr-19 2:00 AM NR
266 NMSCEW/P-IV/STR/2019/258 258 Checking level for excavated bed for at RP-04 Viaduct Km 169+800 RHS 16-Apr-19 12:00 AM IPC-02 DONE AE
267 NMSCEW/P-IV/STR/2019/259 259 Checking top Level & Laying concrete PCC for LP-03 Viaduct Km 169+800 LHS 16-Apr-19 12:00 AM IPC-02 DONE
268 NMSCEW/P-IV/STR/2019/260 260 Laying and top level checking concrete PCC at RP4 FLYOVER Km 169+800 RHS 16-Apr-19 3:00 PM NR
269 NMSCEW/P-IV/STR/2019/261 261 Checking Reinforcement & shuttering at RP13 for raft FLYOVER Km 169+800 RHS 16-Apr-19 3:15 PM NR
270 NMSCEW/P-IV/STR/2019/262 262 Checking Reinforcement & shuttering at LP12 for raft FLYOVER Km 169+800 LHS 16-Apr-19 4:00 PM NR
271 NMSCEW/P-IV/STR/2019/263 263 .Checking of layout and level at RP8 FLYOVER Km 196+560 BHS 16-Apr-19 8:50 AM
272 NMSCEW/P-IV/STR/2019/264 264 Checking level for excavated bed at RP8 FLYOVER Km 196+560 BHS 16-Apr-19 9:25 AM
273 NMSCEW/P-IV/STR/2019/265 265 Laying and top level checking concrete PCC at RP8 FLYOVER Km 196+560 BHS 16-Apr-19 11:00 AM
274 NMSCEW/P-IV/STR/2019/266 266 .Checking of layout and level at LP5 Viaduct Km 196+560 BHS 16-Apr-19 9:15 AM IPC-04 DONE AE
275 NMSCEW/P-IV/STR/2019/267 267 Checking level for excavated bed at LP5 Viaduct Km 196+560 BHS 16-Apr-19 9:40 AM IPC-04 DONE AE
276 NMSCEW/P-IV/STR/2019/268 268 Laying and top level checking concrete PCC at LP5 Viaduct Km 196+560 BHS 16-Apr-19 10:15 AM IPC-04 DONE AE
277 NMSCEW/P-IV/STR/2019/253 253 Checking of reinforcement and shuttering of raft. PUP Km 172+190 LHS 17-Apr-19 12:00 AM IPC-03 DONE
Checking reinforcement and shuttering for precast Box Culvert (3x3) unit type 1 (cushion 2-
278 NMSCEW/P-IV/STR/2019/269 269 BOX CULVERT Km 175+500 LHS 17-Apr-19 9:30 AM DONE
4m) for Ch 164+156 at precast yard. Camp-1, UNIT NO-08
Checking for Concreting Grade =(M-30) for Precast Box Culvert (3×3) Unit type-1 (Cushion 2
279 NMSCEW/P-IV/STR/2019/270 270 BOX CULVERT Km 175+500 LHS 17-Apr-19 10:00 AM DONE
to 4 m) for Ch 164+156 at precast yard, Camp-1 Unit No. - 08
280 NMSCEW/P-IV/STR/2019/271 271 Checking Reinforcement & shuttering for raft PUP Km 205+430 Km 00+000 LHS 17-Apr-19 3:00 PM IPC-03 DONE AE
281 NMSCEW/P-IV/STR/2019/272 272 Checking of reinforcement and shuttering for RP-13 Viaduct Km 169+800 RHS 17-Apr-19 12:00 AM IPC-02 DONE AE
282 NMSCEW/P-IV/STR/2019/273 273 .Checking of layout and level at RP4 FLYOVER Km 169+800 RHS 17-Apr-19 3:00 PM REPEATED
283 NMSCEW/P-IV/STR/2019/274 274 Checking level for excavated bed at RP4 FLYOVER Km 169+800 RHS 17-Apr-19 4:00 PM NR
284 NMSCEW/P-IV/STR/2019/275 275 Checking top Level & Laying concrete PCC for RP-04 Viaduct Km 169+800 RHS 17-Apr-19 12:00 AM IPC-02 DONE
285 NMSCEW/P-IV/STR/2019/276 276 Checking of layout & level at LP-04 Viaduct Km 169+800 LHS 17-Apr-19 12:00 AM IPC-02 DONE AE
286 NMSCEW/P-IV/STR/2019/277 277 Checking level for excavated bed at LP4 FLYOVER Km 169+800 LHS 17-Apr-19 3:30 PM NR
287 NMSCEW/P-IV/STR/2019/278 278 Laying and top level checking concrete PCC at LP4 FLYOVER Km 169+800 LHS 17-Apr-19 5:30 PM NR
288 NMSCEW/P-IV/STR/2019/279 279 .Checking of layout and level at LP5 FLYOVER Km 195+900 LHS 17-Apr-19 11:00 AM
289 NMSCEW/P-IV/STR/2019/280 280 Checking level for excavated bed at LP5 FLYOVER Km 195+900 LHS 17-Apr-19 12:00 PM
290 NMSCEW/P-IV/STR/2019/281 281 Laying and top level checking concrete PCC at LP5 FLYOVER Km 195+900 LHS 17-Apr-19 12:45 PM
291 NMSCEW/P-IV/STR/2019/282 282 Checking of layout and level PUP Km 164+380 Km 00+000 BHS 17-Apr-19 11:30 AM IPC-09 DONE
292 NMSCEW/P-IV/STR/2019/301 301 Checking of top level and Pouring of concrete for Raft PUP Km 172+190 LHS 17-Apr-19 12:00 AM IPC-03 DONE
293 NMSCEW/P-IV/STR/2019/316/A 316/A Checking top Level & Laying concrete PCC for LP-04 Viaduct Km 169+800 LHS 17-Apr-19 IPC-02 DONE AE
294 NMSCEW/P-IV/STR/2019/283 283 Checking of layout and level at RP4 FLYOVER Km 169+800 RHS 18-Apr-19 9:00 AM NR
295 NMSCEW/P-IV/STR/2019/284 284 Checking level for excavated bed at RP4 FLYOVER Km 169+800 RHS 18-Apr-19 9:20 AM NR
296 NMSCEW/P-IV/STR/2019/285 285 Laying and top level checking concrete PCC at RP4 FLYOVER Km 169+800 RHS 18-Apr-19 9:45 AM NR
297 NMSCEW/P-IV/STR/2019/286 286 Checking of layout and level at LP4 FLYOVER Km 169+800 LHS 18-Apr-19 10:05 AM NR
298 NMSCEW/P-IV/STR/2019/287 287 Checking level for excavated bed for at LP-04 Viaduct Km 169+800 LHS 18-Apr-19 12:00 AM IPC-02 DONE AE
299 NMSCEW/P-IV/STR/2019/288 288 Laying and top level checking concrete PCC at LP4 FLYOVER Km 169+800 LHS 18-Apr-19 10:28 AM NR
300 NMSCEW/P-IV/STR/2019/289 289 Checking of layout and level at LP5 FLYOVER Km 195+900 LHS 18-Apr-19 10:35 AM
301 NMSCEW/P-IV/STR/2019/290 290 Checking level for excavated bed at LP5 FLYOVER Km 195+900 LHS 18-Apr-19 10:55 AM
302 NMSCEW/P-IV/STR/2019/291 291 Laying and top level checking concrete PCC at LP5 FLYOVER Km 195+900 LHS 18-Apr-19 11:15 AM
303 NMSCEW/P-IV/STR/2019/292 292 Checking of layout and level at RP7 Viaduct Km 196+560 RHS 18-Apr-19 11:35 AM IPC-04 DONE AE
304 NMSCEW/P-IV/STR/2019/293 293 Checking level for excavated bed at RP7 Viaduct Km 196+560 RHS 18-Apr-19 11:45 AM IPC-04 DONE AE
305 NMSCEW/P-IV/STR/2019/294 294 Laying and top level checking concrete PCC at RP7 Viaduct Km 196+560 RHS 18-Apr-19 11:55 AM IPC-04 DONE AE
306 NMSCEW/P-IV/STR/2019/295 295 Checking of layout and level at RP8 FLYOVER Km 196+560 RHS 18-Apr-19 12:30 PM IPC-05 DONE
307 NMSCEW/P-IV/STR/2019/296 296 Checking level for excavated bed at RP8 FLYOVER Km 196+560 RHS 18-Apr-19 3:30 PM IPC-05 DONE
308 NMSCEW/P-IV/STR/2019/297 297 Laying and top level checking concrete PCC at RP8 FLYOVER Km 196+560 RHS 18-Apr-19 4:30 PM IPC-05 DONE
checking of reinforcement and shuttering for precast Box Culvert (3x3) unit type 1 (cushion 2-
309 NMSCEW/P-IV/STR/2019/298 298 Box culvert Km 175+500 LHS 18-Apr-19 5:30 PM DONE
4m) for Chfor
Checking 164+156 at precast
Concreting Gradeyard campfor
=(M-30) 1, UNIT
PrecastNO-09
Box Culvert (3×3) Unit type-1 (Cushion 2
310 NMSCEW/P-IV/STR/2019/299 299 Box culvert Km 175+500 LHS 18-Apr-19 5:50 PM DONE
to 4 m) for Ch 164+156 at precast yard, Camp-1 Unit No. - 09
311 NMSCEW/P-IV/STR/2019/300 300 checking of bottom haunch reinforcement & shuttering PUP Km 172+190 LHS 18-Apr-19 6:20 PM NR
312 NMSCEW/P-IV/STR/2019/302 302 checking of concrete for raft at pup PUP Km 205+430 Km 00+000 LHS 18-Apr-19 9:00 AM IPC-03 DONE AE
313 NMSCEW/P-IV/STR/2019/303 303 checking of layout & level for box culvert Box culvert Km 208+675 BHS 18-Apr-19 10:00 AM DONE
314 NMSCEW/P-IV/STR/2019/304 304 checking of layout & level & Structural Excavation for box culvert Box culvert Km 190+750 Km 00+000 BHS 18-Apr-19 9:00 AM IPC-11 Approved
315 NMSCEW/P-IV/STR/2019/305 305 Laying and top level checking concrete PCC M10 PUP Km 190+650 RHS 18-Apr-19 9:30 AM DONE
checking of Pouring of concrete for precast box culvert 3m x 3m (cusion 2m to 4m)segment
316 NMSCEW/P-IV/STR/2019/306 306 box culvert Km 200+200 LHS 19-Apr-19 9:00 AM DONE
no.2 at casting yard of camp-2
317 NMSCEW/P-IV/STR/2019/307 307 Checking of pcc at Box culvert box culvert Km 208+675 BHS 19-Apr-19 9:20 AM DONE
318 NMSCEW/P-IV/STR/2019/308 308 Checking of reinforcement and shuttering of raft. PUP Km 184+190 LHS 19-Apr-19 12:00 AM IPC-03 DONE
319 NMSCEW/P-IV/STR/2019/309 309 Checking of top level and Pouring of concrete for Raft PUP Km 184+190 LHS 19-Apr-19 12:00 AM IPC-03 DONE
checking of reinforcement and shuttering for precast Box Culvert (3x3) unit type 1 (cushion 2-
320 NMSCEW/P-IV/STR/2019/310 310 Box Culvert Km 175+500 LHS 19-Apr-19 10:00 AM DONE
4m) for Ch 164+156 at precast yard camp 1, Segment NO-09,10&11
Checking for Concreting Grade =(M-30) for Precast Box Culvert (3×3) Unit type-1 (Cushion 2
321 NMSCEW/P-IV/STR/2019/311 311 Box Culvert Km 175+500 LHS 19-Apr-19 10:20 AM DONE
to 4 m) for Ch 164+156 at precast yard, Camp-1, Segment No. - 10&11
322 NMSCEW/P-IV/STR/2019/312 312 Checking of layout and level at RP4 Flyover Km 169+800 RHS 19-Apr-19 11:00 AM NR
323 NMSCEW/P-IV/STR/2019/313 313 Checking level for excavated bed for at RP-05 Viaduct Km 169+800 RHS 19-Apr-19 12:00 AM IPC-02 DONE AE
324 NMSCEW/P-IV/STR/2019/314 314 Checking level for excavated bed at RP4 Flyover Km 169+800 RHS 19-Apr-19 11:45 AM NR
325 NMSCEW/P-IV/STR/2019/315 315 Checking level for excavated bed at RP4 Flyover Km 169+800 RHS 19-Apr-19 12:20 PM NR
326 NMSCEW/P-IV/STR/2019/316 316 Laying and top level checking concrete PCC at RP4 Flyover Km 169+800 RHS 19-Apr-19 12:45 PM
327 NMSCEW/P-IV/STR/2019/317 317 Laying and top level checking concrete PCC at RP5 Flyover Km 169+800 RHS 19-Apr-19 2:02 PM NR
328 NMSCEW/P-IV/STR/2019/318 318 Checking of layout and level at LP5 Flyover Km 195+900 LHS 19-Apr-19 2:22 PM
329 NMSCEW/P-IV/STR/2019/319 319 Checking of layout and level at LP2 Flyover Km 195+900 LHS 19-Apr-19 2:36 PM IPC-08 DONE
330 NMSCEW/P-IV/STR/2019/320 320 Checking of layout and level at RP8 Flyover Km 195+900 RHS 19-Apr-19 2:50 PM
331 NMSCEW/P-IV/STR/2019/321 321 Checking level for excavated bed at LP5 Flyover Km 195+900 LHS 19-Apr-19 3:00 PM
332 NMSCEW/P-IV/STR/2019/322 322 Checking level for excavated bed at LP2 Flyover Km 195+900 LHS 19-Apr-19 3:20 PM IPC-08 DONE
333 NMSCEW/P-IV/STR/2019/323 323 Checking level for excavated bed at RP8 Flyover Km 195+900 RHS 19-Apr-19 3:35 PM
334 NMSCEW/P-IV/STR/2019/324 324 Checking level for excavated bed at RP8 Flyover Km 195+900 RHS 19-Apr-19 3:50 PM
335 NMSCEW/P-IV/STR/2019/325 325 Laying and top level checking concrete PCC at LP5 Flyover Km 195+900 LHS 19-Apr-19 4:10 PM
336 NMSCEW/P-IV/STR/2019/326 326 Laying and top level checking concrete PCC at LP2 Flyover Km 195+900 LHS 19-Apr-19 4:25 PM IPC-08 DONE
337 NMSCEW/P-IV/STR/2019/327 327 Checking level for excavated bed at box culvert box culvert Km 166+440 BHS 19-Apr-19 4:30 PM DONE
338 NMSCEW/P-IV/STR/2019/328 328 Laying and top level checking concrete PCC at box culvert box culvert Km 166+440 BHS 19-Apr-19 5:30 PM DONE
checking of reinforcement & shuttering precast box culvert 3m x 3m (cusion 2m to
339 NMSCEW/P-IV/STR/2019/329 329 box culvert Km 200+200 LHS 19-Apr-19 5:50 PM DONE
4m)segment no.3 at of
checking of Pouring casting yardfor
concrete of precast
camp-2box culvert 3m x 3m (cusion 2m to 4m)segment
340 NMSCEW/P-IV/STR/2019/330 330 box culvert Km 200+200 LHS 19-Apr-19 6:15 PM DONE
no.3 at casting yard of camp-2
341 NMSCEW/P-IV/STR/2019/331 331 Checking of reinforcement and shuttering of raft. PUP Km 172+190 RHS 20-Apr-19 12:00 AM IPC-03 DONE AE
342 NMSCEW/P-IV/STR/2019/332 332 Checking of top level and Pouring of concrete for Raft PUP Km 172+190 RHS 20-Apr-19 12:00 AM IPC-03 DONE AE
343 NMSCEW/P-IV/STR/2019/333 333 Checking of layout,level and Top Level PCCat box culvert box culvert Km 200+460 BHS 20-Apr-19 11:00 AM IPC-05 DONE
checking of reinforcement and shuttering for precast Box Culvert (3x3) (cushion 2-4m) at
344 NMSCEW/P-IV/STR/2019/334 334 box culvert Km 200+200 LHS 20-Apr-19 2:50 PM DONE
precast yard
Checking of camp 2, Segment
shuttering NO-04
& pouring Concreting Grade =(M-30) for Precast Box Culvert (3×3)
345 NMSCEW/P-IV/STR/2019/335 335 box culvert Km 200+200 LHS 20-Apr-19 3:10 PM DONE
(Cushion
checking of2 to 4 m) at precast
reinforcement andyard, Camp-2,
shuttering for Segment No.Culvert
precast Box - 04 (3x3) (cushion 2-4m) at
346 NMSCEW/P-IV/STR/2019/336 336 box culvert Km 175+500 LHS 20-Apr-19 4:10 PM DONE
precast yard
Checking of camp 1, UNIT
shuttering NO- 11 Concreting
& pouring & 12 Grade =(M-30) for Precast Box Culvert (3×3)
347 NMSCEW/P-IV/STR/2019/337 337 box culvert Km 175+500 LHS 20-Apr-19 5:00 PM DONE
(Cushion of
checking 2 to 4 m) at precast
reinforcement andyard, Camp-1,
shuttering for Segment No.Culvert
precast Box - 11 & (3x3)
12 (cushion 2-4m) at
348 NMSCEW/P-IV/STR/2019/338 338 box culvert Km 200+200 LHS 20-Apr-19 6:20 PM DONE
precast yard camp 2, Segment NO-01
Checking of shuttering & pouring Concreting Grade =(M-30) for Precast Box Culvert (3×3)
349 NMSCEW/P-IV/STR/2019/339 339 box culvert Km 200+200 LHS 20-Apr-19 7:25 PM DONE
(Cushion 2 to 4 m) at precast yard, Camp-2, Segment No. - 01
350 NMSCEW/P-IV/STR/2019/340 340 Checking of layout & level at RP-05 Viaduct Km 169+800 RHS 20-Apr-19 12:00 AM IPC-02 DONE AE
351 NMSCEW/P-IV/STR/2019/341 341 Checking level for excavated bed at RP5 Viaduct Km 169+800 RHS 20-Apr-19 10:10 AM NR
352 NMSCEW/P-IV/STR/2019/342 342 Checking top Level & Laying concrete PCC for RP-05 Viaduct Km 169+800 RHS 20-Apr-19 12:00 AM IPC-02 DONE AE
353 NMSCEW/P-IV/STR/2019/343 343 Checking of layout and level at LP3 Viaduct Km 196+560 Km 00+000 LHS 20-Apr-19 2:00 PM IPC-11 Approved
354 NMSCEW/P-IV/STR/2019/344 344 Checking level for excavated bed at LP3 Viaduct Km 196+560 Km 00+000 LHS 20-Apr-19 2:10 PM IPC-11 Approved
355 NMSCEW/P-IV/STR/2019/345 345 checking Laying and top level concrete PCC at LP3 Viaduct Km 196+560 Km 00+000 LHS 20-Apr-19 2:30 PM IPC-11 Approved
356 NMSCEW/P-IV/STR/2019/346 346 Checking of layout and level at LP4 Viaduct Km 196+560 LHS 20-Apr-19 2:45 PM IPC-08 DONE AE
357 NMSCEW/P-IV/STR/2019/347 347 Checking level for excavated bed at LP4 Viaduct Km 196+560 LHS 20-Apr-19 2:50 PM IPC-08 DONE AE
358 NMSCEW/P-IV/STR/2019/348 348 checking Laying and top level concrete PCC at LP4 Viaduct Km 196+560 LHS 20-Apr-19 2:59 PM IPC-08 DONE AE
359 NMSCEW/P-IV/STR/2019/349 349 checking of reinforcement & shuttering at RP9 Viaduct Km 196+560 RHS 20-Apr-19 3:29 PM
360 NMSCEW/P-IV/STR/2019/350 350 Pouring and top level checking of concrete for Raft at RP9 Viaduct Km 196+560 RHS 20-Apr-19 4:29 PM
361 NMSCEW/P-IV/STR/2019/351 351 Checking of reinforcement and shuttering for LP- 12 Viaduct Km 169+800 LHS 20-Apr-19 12:00 AM IPC-02 DONE AE
362 NMSCEW/P-IV/STR/2019/352 352 Checking top level & Pouring concrete for LP- 12 Viaduct Km 169+800 LHS 20-Apr-19 12:00 AM IPC-02 DONE AE
363 NMSCEW/P-IV/STR/2019/351/A 351/A Checking of reinforcement and shuttering for RP-04 Viaduct Km 169+800 RHS 20-Apr-19 IPC-02 DONE
364 NMSCEW/P-IV/STR/2019/352/A 352/A Checking top level & Pouring concrete for RP-04 Viaduct Km 169+800 RHS 20-Apr-19 IPC-02 DONE
365 NMSCEW/P-IV/STR/2019/353 353 Checking of layout and level at PUP PUP Km 168+380 BHS 21-Apr-19 9:30 AM DONE
366 NMSCEW/P-IV/STR/2019/354 354 Checking level for excavated bed at PUP PUP Km 168+380 BHS 21-Apr-19 10:00 AM DONE
367 NMSCEW/P-IV/STR/2019/357 357 Laying and top level checking concrete PCC at PUP PUP Km 177+810 BHS 21-Apr-19 11:30 AM NR
368 NMSCEW/P-IV/STR/2019/358 358 checking of reinforcement and shuttering of bottom haunch at PUP PUP Km 172+190 LHS 21-Apr-19 11:50 AM NR
369 NMSCEW/P-IV/STR/2019/359 359 checking of top level and Pouring of concrete of bottom haunch at PUP PUP Km 172+190 LHS 21-Apr-19 12:30 PM NR
370 NMSCEW/P-IV/STR/2019/360 360 Checking of layout and level at LP3 Viaduct Km 195+900 LHS 21-Apr-19 10:20 AM IPC-08 DONE
371 NMSCEW/P-IV/STR/2019/361 361 Checking level for excavated bed at LP3 Viaduct Km 195+900 LHS 21-Apr-19 11:15 AM IPC-08 DONE
372 NMSCEW/P-IV/STR/2019/362 362 Laying and top level checking concrete PCC at LP3 Viaduct Km 195+900 LHS 21-Apr-19 12:00 PM IPC-08 DONE
373 NMSCEW/P-IV/STR/2019/363 363 Checking of layout and level at RP-01 Viaduct Km 196+560 RHS 21-Apr-19 9:45 AM IPC-08 DONE
374 NMSCEW/P-IV/STR/2019/364 364 Checking level for excavated bed at RP-01 Viaduct Km 196+560 RHS 21-Apr-19 11:45 AM IPC-08 DONE
375 NMSCEW/P-IV/STR/2019/365 365 Laying and top level checking concrete PCC at RP-01 Viaduct Km 196+560 RHS 21-Apr-19 2:20 PM IPC-08 DONE
376 NMSCEW/P-IV/STR/2019/355 355 Checking of reinforcement and shuttering of raft. PUP Km 171+110 RHS 22-Apr-19 12:00 AM IPC-03 DONE AE
377 NMSCEW/P-IV/STR/2019/356 356 Checking of top level and Pouring of concrete for Raft PUP Km 171+110 RHS 22-Apr-19 12:00 AM IPC-03 DONE AE
378 NMSCEW/P-IV/STR/2019/366 366 checking of layout & level of precast box culvert (3×3) Box culvert Km 188+726 BHS 22-Apr-19 9:45 AM NR
379 NMSCEW/P-IV/STR/2019/367 367 checking of reinforcement and shuttering of bottom at PUP PUP Km 186+000 RHS 22-Apr-19 9:30 AM NR
380 NMSCEW/P-IV/STR/2019/368 368 Pouring and top level checking of concrete for Raft at PUP PUP Km 186+000 RHS 22-Apr-19 10:00 AM NA
381 NMSCEW/P-IV/STR/2019/369 369 Laying and top level checking of M10 concrete for PCC of Precast box culvert (3×3) Box culvert Km 190+750 BHS 22-Apr-19 10:15 AM
checking of reinforcement and shuttering for precast Box Culvert (3x3) (cushion 2-4m) at
382 NMSCEW/P-IV/STR/2019/370 370 Box culvert Km 175+500 LHS 22-Apr-19 10:30 AM DONE
precast yard
Checking of camp 1, Segment
shuttering no- 13,14
& pouring & 15 Grade =(M-30) for Precast Box Culvert (3×3)
Concreting
383 NMSCEW/P-IV/STR/2019/371 371 Box culvert Km 175+500 LHS 22-Apr-19 11:00 AM DONE
(Cushion 2 to 4 m) at precast yard, Camp-1, Segment No. - 13,14 &15
384 NMSCEW/P-IV/STR/2019/372 372 Checking of layout & level at LP- 05 Viaduct Km 169+800 LHS 22-Apr-19 12:00 AM IPC-03 DONE AE
385 NMSCEW/P-IV/STR/2019/373 373 Checking level for excavated bed for at LP- 05 Viaduct Km 169+800 LHS 22-Apr-19 12:00 AM IPC-03 DONE AE
386 NMSCEW/P-IV/STR/2019/374 374 Checking top Level & Laying concrete PCC for LP- 05 Viaduct Km 169+800 LHS 22-Apr-19 12:00 AM IPC-03 DONE AE
387 NMSCEW/P-IV/STR/2019/375 375 checking of layout & level at LP6 Viaduct Km 169+800 LHS 22-Apr-19 2:20 PM NR
388 NMSCEW/P-IV/STR/2019/376 376 Checking level for excavated bed at LP6 Viaduct Km 169+800 LHS 22-Apr-19 3:00 PM NR
389 NMSCEW/P-IV/STR/2019/377 377 checking Laying and top level concrete PCC at LP6 Viaduct Km 169+800 LHS 22-Apr-19 4:00 PM NR
checking of reinforcement and shuttering of precast Box Culvert (3x3) (cushion 2-4m) for
390 NMSCEW/P-IV/STR/2019/378 378 Box culvert Km 175+500 LHS 22-Apr-19 2:20 PM NR SPOT RFI
the ch 164+156 BHS at precast yard camp 1 , Segment no- 12
Checking of shuttering & pouring Concreting Grade =(M-30) of Precast Box Culvert (3×3)
391 NMSCEW/P-IV/STR/2019/379 379 Box culvert Km 175+500 LHS 22-Apr-19 3:00 PM NR SPOT RFI
(Cushion of
checking 2 to 4 m) for the and
reinforcement ch 164+156 BHS
shuttering for at precast
precast yard,
Box Camp-1,
Culvert (3x3)Segment No.
(cushion - 12 at
2-4m)
392 NMSCEW/P-IV/STR/2019/380 380 Box culvert Km 200+200 LHS 22-Apr-19 10:30 AM DONE SPOT RFI
precast yard
Checking of camp 2, Segment
shuttering no- 02
& pouring Concreting Grade =(M-30) for Precast Box Culvert (3×3)
393 NMSCEW/P-IV/STR/2019/381 381 Box culvert Km 200+200 LHS 22-Apr-19 11:00 AM DONE SPOT RFI
(Cushion 2 to 4 m) at precast yard, Camp-2, Segment No. - 02
394 NMSCEW/P-IV/STR/2019/382 382 checking of layout & level at Minor bridge Minor Bridge Km 208+455 BHS 23-Apr-19 10:00 AM DONE
395 NMSCEW/P-IV/STR/2019/383 383 Checking level for excavated bed at Minor bridge Minor Bridge Km 208+455 BHS 23-Apr-19 11:25 AM DONE
396 NMSCEW/P-IV/STR/2019/384 384 Laying and top level checking concrete PCC at Minor bridge Minor Bridge Km 208+455 BHS 23-Apr-19 2:30 PM DONE
397 NMSCEW/P-IV/STR/2019/385 385 checking of layout & level at PUP PUP Km 191+740 BHS 23-Apr-19 11:00 AM IPC-04 DONE AE
398 NMSCEW/P-IV/STR/2019/386 386 Checking level for excavated bed at PUP PUP Km 191+740 BHS 23-Apr-19 11:25 AM IPC-04 DONE AE
399 NMSCEW/P-IV/STR/2019/387 387 Laying and top level checking concrete PCC at PUP PUP Km 191+740 BHS 23-Apr-19 12:40 PM IPC-04 DONE AE
400 NMSCEW/P-IV/STR/2019/388 388 Checking level for excavated bed at PUP PUP Km 164+380 Km 00+000 BHS 23-Apr-19 2:00 PM IPC-09 DONE AE
401 NMSCEW/P-IV/STR/2019/389 389 checking Laying and top level concrete M10 PCC at PUP PUP Km 164+380 Km 00+000 BHS 23-Apr-19 2:30 PM IPC-09 DONE AE
402 NMSCEW/P-IV/STR/2019/390 390 Laying and top level checking concrete PCC PUP Km 177+810 LHS 23-Apr-19 12:00 AM IPC-03 DONE
403 NMSCEW/P-IV/STR/2019/391 391 checking Laying and top level concrete PCC at LVUP LVUP Km 173+400 BHS 23-Apr-19 4.00 PM IPC-05 DONE AE
404 NMSCEW/P-IV/STR/2019/394 394 checking of layout & level and Structural Excavation of box culvert (3×3) Box culvert Km 191+870 Km 00+000 BHS 23-Apr-19 9:00 AM IPC-11 Approved
405 NMSCEW/P-IV/STR/2019/395 395 checking Laying and top level concrete M10 PCC at box culvert (3×3) B.C. Km 188+726 BHS 23-Apr-19 10:30 AM DONE
406 NMSCEW/P-IV/STR/2019/396 396 Checking layout & level for excavated bed at RP1 VIADUCT Km 195+900 RHS 23-Apr-19 11:00 AM
407 NMSCEW/P-IV/STR/2019/397 397 Laying and top level checking concrete PCC at RP1 VIADUCT Km 195+900 RHS 23-Apr-19 12:30 PM
408 NMSCEW/P-IV/STR/2019/398 398 checking of reinforcement & shuttering raft at RP3 VIADUCT Km 195+900 RHS 23-Apr-19 2:00 AM IPC-04 DONE AE
409 NMSCEW/P-IV/STR/2019/399 399 checking Laying and top level concrete raft at RP3 VIADUCT Km 195+900 RHS 23-Apr-19 2:30 AM IPC-04 DONE AE
410 NMSCEW/P-IV/STR/2019/400 400 Checking layout & level for excavated bed at LP6 VIADUCT Km 196+560 LHS 23-Apr-19 9:30 AM
411 NMSCEW/P-IV/STR/2019/401 401 Laying and top level checking concrete PCC at LP6 VIADUCT Km 196+560 LHS 23-Apr-19 9:50 AM
412 NMSCEW/P-IV/STR/2019/402 402 checking of reinforcement & shuttering raft at RP9 Viaduct Km 196+560 LHS 23-Apr-19 10:40 AM IPC-04 DONE
413 NMSCEW/P-IV/STR/2019/403 403 checking Laying and top level concrete raft at RP9 Viaduct Km 196+560 LHS 23-Apr-19 11:20 AM IPC-04 DONE AE
414 NMSCEW/P-IV/STR/2019/404 404 Checking layout & level for excavated bed at LP6 VIADUCT Km 169+800 LHS 23-Apr-19 10:00 AM NR
415 NMSCEW/P-IV/STR/2019/405 405 Checking of layout & level at RP-06 Viaduct Km 169+800 RHS 23-Apr-19 12:00 AM IPC-03 DONE
416 NMSCEW/P-IV/STR/2019/406 406 Laying and top level checking concrete PCC at LP6 VIADUCT Km 169+800 LHS 23-Apr-19 11:00 AM NR
417 NMSCEW/P-IV/STR/2019/407 407 Laying and top level checking concrete PCC at RP6 VIADUCT Km 169+800 RHS 23-Apr-19 11:30 AM NR
418 NMSCEW/P-IV/STR/2019/408 408 Checking of reinforcement and shuttering of raft. PUP Km 184+190 RHS 23-Apr-19 12:00 AM IPC-03 DONE
419 NMSCEW/P-IV/STR/2019/409 409 Checking of top level and Pouring of concrete for Raft PUP Km 184+190 RHS 23-Apr-19 12:00 AM IPC-03 DONE
checking of reinforcement and shuttering for precast Box Culvert (3x3) unit type 1 (cushion 2-
420 NMSCEW/P-IV/STR/2019/410 410 B.C. Km 175+500 LHS 23-Apr-19 5:30 PM DONE
4m) at precast
Checking yard campGrade
for Concreting 1, Segment NO-14&
=(M-30) 15 Box Culvert (3×3) Unit type-1 (Cushion 2
for Precast
421 NMSCEW/P-IV/STR/2019/411 411 B.C. Km 175+500 LHS 23-Apr-19 6:30 PM DONE
to 4 m) at precast yard, Camp-1, Segment No. - 14 & 15
422 NMSCEW/P-IV/STR/2019/392 392 checking of A1 & A2 reinforcement and shuttering of bottom haunch. PUP Km 172+190 LHS 24-Apr-19 12:00 AM IPC-03 DONE
423 NMSCEW/P-IV/STR/2019/393 393 A1 & A2 bottom hauch pouring of concrete PUP Km 172+190 LHS 24-Apr-19 12:00 AM IPC-03 DONE
424 NMSCEW/P-IV/STR/2019/412 412 checking of reinforcement of raft at PUP PUP Km 205+430 Km 00+000 RHS 24-Apr-19 4:00 PM IPC-03 DONE AE
425 NMSCEW/P-IV/STR/2019/413 413 Checking layout & level for excavated bed at RP1 Viaduct Km 195+900 RHS 24-Apr-19 11:00 AM IPC-04 DONE AE
426 NMSCEW/P-IV/STR/2019/414 414 Laying and top level checking concrete PCC at RP1 VIADUCT Km 195+900 RHS 24-Apr-19 12:30 PM
427 NMSCEW/P-IV/STR/2019/415 415 checking of reinforcement of raft at RP3 VIADUCT Km 195+900 RHS 24-Apr-19 10:00 AM
428 NMSCEW/P-IV/STR/2019/416 416 Laying and top level checking concrete of raft at RP3 VIADUCT Km 195+900 RHS 24-Apr-19 2:30 PM
429 NMSCEW/P-IV/STR/2019/417 417 Checking level for excavated bed for at RP-06 Viaduct Km 169+800 RHS 24-Apr-19 12:00 AM IPC-03 DONE AE
430 NMSCEW/P-IV/STR/2019/418 418 Checking top Level & Laying concrete PCC for RP-06 Viaduct Km 169+800 RHS 24-Apr-19 12:00 AM IPC-03 DONE AE
431 NMSCEW/P-IV/STR/2019/419 419 Checking layout & level for excavated bed at RP6 BC Km 193+940 RHS 24-Apr-19 12:30 PM DONE
432 NMSCEW/P-IV/STR/2019/420 420 checking of reinforcement and shuttering for bottom slab at pup PUP Km 186+000 RHS 24-Apr-19 4:30 PM NR
433 NMSCEW/P-IV/STR/2019/421 421 checking Laying and top level concrete raft at pup PUP Km 186+000 RHS 24-Apr-19 5:00 PM NR
checking of reinforcement and shuttering for precast Box Culvert (3x3) unit type 1 (cushion 2-
434 NMSCEW/P-IV/STR/2019/422 422 Box Culvert Km 175+500 LHS 24-Apr-19 6:20 PM NR
4m) at precast
Checking yard camp
for shuttering & 1, Segment
pouring NO-16 &Grade
Concreting 17 =(M-30) for Precast Box Culvert (3×3)
435 NMSCEW/P-IV/STR/2019/423 423 Box Culvert Km 175+500 LHS 24-Apr-19 7:00 PM NR
Unit type-1 (Cushion 2 to 4 m) at precast yard, Camp-1, Segment No. - 16 & 17
436 NMSCEW/P-IV/STR/2019/052 52 Checking level for excavated bed. PUP Km 177+810 BHS 25-Apr-19 12:00 AM IPC-03 DONE AE
437 NMSCEW/P-IV/STR/2019/424 424 Checking Of Layout & Level for Box culvert Box Culvert Km 168+330 BHS 25-Apr-19 9:00 AM DONE
438 NMSCEW/P-IV/STR/2019/425 425 Checking Of Excavation for Box Culvert Box Culvert Km 168+330 BHS 25-Apr-19 9:40 AM NR
Checking reinforcement for precaste box culvert 3m x 3m ,(cusion upto 2m ) for (ch.200+286)
439 NMSCEW/P-IV/STR/2019/426 426 Box Culvert Km 200+200 LHS 25-Apr-19 10:30 AM DONE
at casting yard
Checking of camp
concrete -2 location
Pouring Segment
for precast box No. 3,4 3m
culvert &5 x 3m (cusion upto 2m ) for (ch.
440 NMSCEW/P-IV/STR/2019/427 427 Box Culvert Km 200+200 LHS 25-Apr-19 11:50 AM DONE
200+286) at casting yard of camp-2 Segment No. 3,4 &5
441 NMSCEW/P-IV/STR/2019/428 428 Checking of layout and level for precast Box Culvert ( 3 x 3 ) Ch. 192+575 Box Culvert Km 192+575 BHS 25-Apr-19 2:20 PM DONE
442 NMSCEW/P-IV/STR/2019/429 429 Checking top Level & Laying concrete M10 PCC for Box Culvert ( 3 x 3 ) ch.190+750 Box Culvert Km 190+750 Km 00+000 BHS 25-Apr-19 2:50 PM IPC-11 Approved
443 NMSCEW/P-IV/STR/2019/430 430 Checking top Level & Laying concrete PCC for PUP PUP Km 177+810 RHS 25-Apr-19 3:30 PM IPC-04 DONE
444 NMSCEW/P-IV/STR/2019/433 433 Checking of layout and level for LVUP LVUP Km 169+291 BHS 25-Apr-19 11:00 AM IPC-08 DONE
445 NMSCEW/P-IV/STR/2019/434 434 Checking level for excavated bed for LVUP LVUP Km 169+291 BHS 25-Apr-19 11:30 AM IPC-08 DONE AE
446 NMSCEW/P-IV/STR/2019/435 435 Checking of layout and level for PUP PUP Km 193+880 BHS 25-Apr-19 11:10 AM IPC-04 DONE AE
447 NMSCEW/P-IV/STR/2019/436 436 Checking top Level & Laying concrete PCC for PUP PUP Km 193+880 BHS 25-Apr-19 12:10 PM NA
448 NMSCEW/P-IV/STR/2019/437 437 checking of pouring raft concrete for PUP PUP Km 205+430 Km 00+000 RHS 25-Apr-19 8:00 AM IPC-03 DONE AE
449 NMSCEW/P-IV/STR/2019/438 438 checking of reinforcement and shuttering for bottom haunch & bottom slab PUP Km 186+000 RHS 25-Apr-19 10:00 AM IPC-04 DONE
450 NMSCEW/P-IV/STR/2019/439 439 Checking top Level & Laying M30 raft & bottom haunch concrete for PUP PUP Km 186+000 RHS 25-Apr-19 11:50 AM IPC-04 DONE
451 NMSCEW/P-IV/STR/2019/440 440 checking of bottom haunch reinforcement & shuttering PUP Km 184+190 LHS 25-Apr-19 4:00 PM NR
452 NMSCEW/P-IV/STR/2019/441 441 Checking top Level & Laying M30 haunch concrete for PUP PUP Km 184+190 LHS 25-Apr-19 4:30 PM NR
453 NMSCEW/P-IV/STR/2019/442 442 Checking of layout & level at LP-06 Viaduct Km 169+800 LHS 25-Apr-19 12:00 AM IPC-03 DONE AE
454 NMSCEW/P-IV/STR/2019/443 443 Checking top Level & Laying concrete PCC for LP-06 Viaduct Km 169+800 LHS 25-Apr-19 12:00 AM IPC-03 DONE
455 NMSCEW/P-IV/STR/2019/444 444 Checking of reinforcement and shuttering for LP- 13 Viaduct Km 169+800 LHS 25-Apr-19 12:00 AM IPC-02 DONE AE
456 NMSCEW/P-IV/STR/2019/445 445 Checking top level & Pouring concrete for LP- 13 Viaduct Km 169+800 LHS 25-Apr-19 12:00 AM IPC-02 DONE AE
457 NMSCEW/P-IV/STR/2019/446 446 Checking Of Layout & Level for LP 1 VIADUCT Km 169+800 LHS 25-Apr-19 2:00 PM NR
458 NMSCEW/P-IV/STR/2019/447 447 Checking level for excavated bed for at LP 1 VIADUCT Km 169+800 LHS 25-Apr-19 2:50 PM NR
459 NMSCEW/P-IV/STR/2019/448 448 Checking top Level & Laying concrete PCC for LP 1 VIADUCT Km 169+800 LHS 25-Apr-19 3:40 PM NR
460 NMSCEW/P-IV/STR/2019/442a 442a Checking level for excavated bed for at LP-06 Viaduct Km 169+800 LHS 25-Apr-19 IPC-03 DONE
461 NMSCEW/P-IV/STR/2019/444/A 444/A Checking of reinforcement and shuttering for LP-04 Viaduct Km 169+800 LHS 25-Apr-19 IPC-02 DONE
462 NMSCEW/P-IV/STR/2019/445/A 445/A Checking top level & Pouring concrete for LP-04 Viaduct Km 169+800 LHS 25-Apr-19 IPC-02 DONE
463 NMSCEW/P-IV/STR/2019/431 431 checking of A1 & A2 reinforcement and shuttering of bottom haunch. PUP Km 172+190 RHS 26-Apr-19 12:00 AM IPC-03 DONE
464 NMSCEW/P-IV/STR/2019/432 432 A1 & A2 bottom hauch pouring of concrete PUP Km 172+190 RHS 26-Apr-19 12:00 AM IPC-03 DONE
465 NMSCEW/P-IV/STR/2019/449 449 Checking level for excavated bed for Box Culvert BOX CULVERT Km 168+330 BHS 26-Apr-19 8:16 AM DONE
466 NMSCEW/P-IV/STR/2019/450 450 Checking top Level & Laying concrete M10 PCC for Box Culvert BOX CULVERT Km 168+330 BHS 26-Apr-19 8:44 AM DONE
467 NMSCEW/P-IV/STR/2019/451 451 checking of Layout reinforcement and shuttering for RP13 pier starter VIADUCT Km 169+800 RHS 26-Apr-19 9:04 AM NR
468 NMSCEW/P-IV/STR/2019/452 452 checking of Layout reinforcement and shuttering for LP12 pier starter VIADUCT Km 169+800 LHS 26-Apr-19 9:14 AM NR
469 NMSCEW/P-IV/STR/2019/453 453 Checking top level & Laying concrete for RP13 pier starter VIADUCT Km 169+800 RHS 26-Apr-19 10:24 AM NR
470 NMSCEW/P-IV/STR/2019/454 454 Checking top level & Laying concrete for LP12 pier starter VIADUCT Km 169+800 LHS 26-Apr-19 11:26 AM NR
471 NMSCEW/P-IV/STR/2019/455 455 Checking Of Layout & Level for RP7 VIADUCT Km 169+800 RHS 26-Apr-19 12:16 PM NR
472 NMSCEW/P-IV/STR/2019/456 456 Checking level for excavated bed for at RP7 VIADUCT Km 169+800 RHS 26-Apr-19 12:40 PM NR
473 NMSCEW/P-IV/STR/2019/457 457 Checking top Level & Laying concrete PCC for RP7 VIADUCT Km 169+800 RHS 26-Apr-19 2:26 PM NR
474 NMSCEW/P-IV/STR/2019/458 458 Checking Of Layout & Level for LP1 VIADUCT Km 195+900 LHS 26-Apr-19 2:36 PM IPC-08 DONE
475 NMSCEW/P-IV/STR/2019/459 459 Checking level for excavated bed for at LP 1 VIADUCT Km 195+900 LHS 26-Apr-19 2:50 PM IPC-08 DONE
476 NMSCEW/P-IV/STR/2019/460 460 Checking top Level & Laying concrete PCC for LP1 VIADUCT Km 195+900 LHS 26-Apr-19 3:12 PM IPC-08 DONE
477 NMSCEW/P-IV/STR/2019/461 461 Checking Of Layout & Level for RP2 VIADUCT Km 195+900 Km 00+000 RHS 26-Apr-19 3:42 PM IPC-10 DONE
478 NMSCEW/P-IV/STR/2019/462 462 Checking level for excavated bed for PCC at RP2 VIADUCT Km 195+900 Km 00+000 RHS 26-Apr-19 4:02 PM IPC-10 DONE
479 NMSCEW/P-IV/STR/2019/463 463 Checking top Level & Laying concrete PCC for RP2 VIADUCT Km 195+900 Km 00+000 RHS 26-Apr-19 4:32 PM IPC-10 DONE
480 NMSCEW/P-IV/STR/2019/464 464 checking of Layout reinforcement and shuttering of pier starter of RP 3 VIADUCT Km 195+900 RHS 26-Apr-19 4:45 PM
481 NMSCEW/P-IV/STR/2019/465 465 Checking top Level & Laying concrete for RP3 pier starter VIADUCT Km 195+900 RHS 26-Apr-19 5:05 PM
482 NMSCEW/P-IV/STR/2019/466 466 checking of Layout reinforcement and shuttering for RP 9 pier starter VIADUCT Km 196+560 RHS 26-Apr-19 5:35 PM
483 NMSCEW/P-IV/STR/2019/467 467 Checking top Level & Laying concrete PCC for RP9 VIADUCT Km 196+560 RHS 26-Apr-19 5:58 PM
484 NMSCEW/P-IV/STR/2019/468 468 Checking top Level & Laying concrete M10 PCC for Box Culvert BOX CULVERT Km 191+870 Km 00+000 BHS 26-Apr-19 8:00 AM IPC-11 Approved
Checking of reinforcement for precast Box Culvert (3x3) (cushion 2-4m) at precast yard camp
485 NMSCEW/P-IV/STR/2019/469 469 BOX CULVERT Km 175+500 LHS 26-Apr-19 8:40 AM DONE
-1 Segment
Checking forNO-16,17&18
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
486 NMSCEW/P-IV/STR/2019/470 470 BOX CULVERT Km 175+500 LHS 26-Apr-19 9:32 AM DONE
(3×3) (Cushion 2 to 4 m) at precast yard camp-1Segment no.-16,17&18
487 NMSCEW/P-IV/STR/2019/471 471 checking of bottom haunch reinforcement & shuttering PUP Km 205+430 Km 00+000 LHS 27-Apr-19 9:00 AM IPC-03 DONE
488 NMSCEW/P-IV/STR/2019/472 472 Checking top Level & Laying M30 bottom haunch concrete pouring for PUP PUP Km 205+430 Km 00+000 LHS 27-Apr-19 10:00 AM IPC-03 DONE AE
489 NMSCEW/P-IV/STR/2019/473 473 Checking of layout and level for B/C BOX CULVERT Km 209+470 BHS 27-Apr-19 9:30 AM
490 NMSCEW/P-IV/STR/2019/474 474 Checking level for excavated bed BOX CULVERT Km 209+470 BHS 27-Apr-19 10:30 AM
491 NMSCEW/P-IV/STR/2019/475 475 Laying and top level checking of M10 concrete for PCC BOX CULVERT Km 209+470 BHS 27-Apr-19 11:30 AM
492 NMSCEW/P-IV/STR/2019/476 476 checking of A1 & A2 reinforcement and shuttering of bottom haunch. PUP Km 184+190 LHS 27-Apr-19 12:00 AM IPC-03 DONE
493 NMSCEW/P-IV/STR/2019/477 477 A1 & A2 bottom hauch pouring of concrete PUP Km 184+190 LHS 27-Apr-19 12:00 AM IPC-03 DONE
494 NMSCEW/P-IV/STR/2019/478 478 Checking of layout and level for LP1 VIADUCT Km 195+900 LHS 27-Apr-19 10:28 AM
495 NMSCEW/P-IV/STR/2019/479 479 Checking level for excavated bed for LP1 VIADUCT Km 195+900 LHS 27-Apr-19 10:35 AM
496 NMSCEW/P-IV/STR/2019/480 480 Laying and top level checking of concrete for PCC for LP1 VIADUCT Km 195+900 LHS 27-Apr-19 11:23 AM
497 NMSCEW/P-IV/STR/2019/481 481 checking of Layout reinforcement and shuttering for RP3 pier starter VIADUCT Km 195+900 RHS 27-Apr-19 12:02 PM IPC-14
498 NMSCEW/P-IV/STR/2019/482 482 Checking top level & Laying concrete for RP3 pier starter VIADUCT Km 195+900 RHS 27-Apr-19 12:30 PM IPC-14
499 NMSCEW/P-IV/STR/2019/483 483 checking of Layout reinforcement and shuttering for RP9 pier starter VIADUCT Km 195+900 RHS 27-Apr-19 2:05 PM
500 NMSCEW/P-IV/STR/2019/484 484 Checking top level & Laying concrete for RP9 pier starter VIADUCT Km 195+900 RHS 27-Apr-19 2:25 PM
501 NMSCEW/P-IV/STR/2019/485 485 Checking of layout and level for LP3 VIADUCT Km 195+900 LHS 27-Apr-19 2:50 PM
502 NMSCEW/P-IV/STR/2019/486 486 Checking level for excavated bed for LP3 VIADUCT Km 195+900 LHS 27-Apr-19 3:20 PM
503 NMSCEW/P-IV/STR/2019/487 487 Laying and top level checking of concrete for PCC for LP3 VIADUCT Km 195+900 LHS 27-Apr-19 3:35 PM
504 NMSCEW/P-IV/STR/2019/488 488 Checking of layout & level at RP-07 Viaduct Km 169+800 RHS 27-Apr-19 12:00 AM IPC-03 DONE AE
505 NMSCEW/P-IV/STR/2019/489 489 Checking level for excavated bed for at RP-07 Viaduct Km 169+800 RHS 27-Apr-19 12:00 AM IPC-03 DONE AE
506 NMSCEW/P-IV/STR/2019/490 490 Checking top Level & Laying concrete PCC for RP-07 Viaduct Km 169+800 RHS 27-Apr-19 12:00 AM IPC-03 DONE AE
507 NMSCEW/P-IV/STR/2019/491 491 Checking of layout and level for RP8 Viaduct Km 169+800 RHS 27-Apr-19 12:05 PM IPC-04 DONE
508 NMSCEW/P-IV/STR/2019/492 492 Checking level for excavated bed for RP8 Viaduct Km 169+800 RHS 27-Apr-19 12:25 PM IPC-04 DONE
509 NMSCEW/P-IV/STR/2019/493 493 Laying and top level checking of concrete for PCC for RP8 Viaduct Km 169+800 RHS 27-Apr-19 1:00 PM IPC-04 DONE
510 NMSCEW/P-IV/STR/2019/494 494 checking of Layout reinforcement and shuttering for RP13 pier starter VIADUCT Km 169+800 RHS 27-Apr-19 1:10 PM NR
511 NMSCEW/P-IV/STR/2019/495 495 checking of Layout reinforcement and shuttering for LP12 pier starter VIADUCT Km 169+800 RHS 27-Apr-19 2:02 PM NR
512 NMSCEW/P-IV/STR/2019/496 496 Checking top level & Laying concrete for RP13 pier starter VIADUCT Km 169+800 RHS 27-Apr-19 3:25 PM NR
513 NMSCEW/P-IV/STR/2019/497 497 Checking top level & Laying concrete for LP12 pier starter VIADUCT Km 169+800 RHS 27-Apr-19 4:00 PM NR
Checking reinforcement for precast Box Culvert (3x3) (cushion 2-4m) at precast yard camp -1
514 NMSCEW/P-IV/STR/2019/498 498 BOX CULVERT Km 175+500 LHS 27-Apr-19 4:10 PM DONE
,Segment NO-19&20&21
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
515 NMSCEW/P-IV/STR/2019/499 499 BOX CULVERT Km 175+500 LHS 27-Apr-19 4:20 PM DONE
(3×3) ,(Cushion 2 to 4 m) at precast yard camp-1,Segment no.-19&20&21
516 NMSCEW/P-IV/STR/2019/500 500 checking of reinforcement and shuttering for raft PUP Km 190+650 LHS 28-Apr-19 12:05 PM DONE
517 NMSCEW/P-IV/STR/2019/501 501 checking top level and pouring concrete(M30) for raft PUP Km 190+650 LHS 28-Apr-19 2:08 PM DONE
518 NMSCEW/P-IV/STR/2019/502 502 checking of bottom haunch reinforcement & shuttering PUP Km 205+430 Km 00+000 RHS 28-Apr-19 8:00 AM IPC-03 DONE AE
519 NMSCEW/P-IV/STR/2019/503 503 Checking top Level & Pouring M30 haunch concrete for PUP PUP Km 205+430 Km 00+000 RHS 28-Apr-19 9:00 AM IPC-03 DONE AE
520 NMSCEW/P-IV/STR/2019/504 504 checking of reinforcement and shuttering for raft LVUP Km 173+400 LHS 29-Apr-19 4:30 PM NR
521 NMSCEW/P-IV/STR/2019/505 505 checking top level and pouring concrete(M30) for raft LVUP Km 173+400 LHS 29-Apr-19 5:00 PM NR
522 NMSCEW/P-IV/STR/2019/506 506 checking of A1 & A2 reinforcement and shuttering of bottom haunch. PUP Km 171+110 RHS 29-Apr-19 12:00 AM IPC-03 DONE
523 NMSCEW/P-IV/STR/2019/507 507 A1 & A2 bottom hauch pouring of concrete PUP Km 171+110 RHS 29-Apr-19 12:00 AM IPC-03 DONE
524 NMSCEW/P-IV/STR/2019/508 508 Checking top level & laying M10 concrete for PCC BOX CULVERT Km 192+575 BHS 29-Apr-19 10:00 AM NA
525 NMSCEW/P-IV/STR/2019/509 509 Checking of layout and level for PUP PUP Km 203+560 RHS 29-Apr-19 2:00 PM IPC-04 DONE AE
526 NMSCEW/P-IV/STR/2019/510 510 Checking level for excavated bed for PUP PUP Km 203+560 RHS 29-Apr-19 3:00 PM IPC-04 DONE AE
527 NMSCEW/P-IV/STR/2019/511 511 Checking top Level & Laying concrete PCC for PUP PUP Km 203+560 RHS 29-Apr-19 5:45 PM IPC-04 DONE AE
Checking reinforcement for precast Box Culvert (3x3) (cushion 2-4m) at precast yard camp
528 NMSCEW/P-IV/STR/2019/512 512 BOX CULVERT Km 175+500 LHS 29-Apr-19 3:00 PM NR
-1 ,Segment
Checking for NO 21&22& Pouring of Concreting Grade =(M-30) for Precast Box Culvert
shuttering
529 NMSCEW/P-IV/STR/2019/513 513 BOX CULVERT Km 175+500 LHS 29-Apr-19 5:42 PM NR
(3×3),(Cushion 2 to 4 m) at precast yard camp-1,Segment 21&22
530 NMSCEW/P-IV/STR/2019/514 514 Checking Of Layout & Level for LP3 VIADUCT Km 196+560 LHS 29-Apr-19 10:10 AM
531 NMSCEW/P-IV/STR/2019/515 515 Checking level for excavated bed for at LP 3 Viaduct Km 196+560 LHS 29-Apr-19 10:40 AM IPC-04 DONE AE
532 NMSCEW/P-IV/STR/2019/516 516 Checking top Level & Laying concrete PCC for LP1 Viaduct Km 196+560 LHS 29-Apr-19 11:30 AM IPC-04 DONE AE
533 NMSCEW/P-IV/STR/2019/517 517 Checking Of Layout & Level for LP6 VIADUCT Km 196+560 LHS 29-Apr-19 11:00 AM
534 NMSCEW/P-IV/STR/2019/518 518 Checking level for excavated bed for at LP 6 VIADUCT Km 196+560 LHS 29-Apr-19 11:45 AM
535 NMSCEW/P-IV/STR/2019/519 519 Checking top Level & Laying concrete PCC for LP6 VIADUCT Km 196+560 LHS 29-Apr-19 4:50 PM
536 NMSCEW/P-IV/STR/2019/520 520 Checking Of Layout & Level for RP9 VIADUCT Km 195+900 RHS 29-Apr-19 2:30 PM IPC-08 DONE
537 NMSCEW/P-IV/STR/2019/521 521 Checking level for excavated bed for at RP9 VIADUCT Km 195+900 RHS 29-Apr-19 3:00 PM IPC-08 DONE
538 NMSCEW/P-IV/STR/2019/522 522 Checking top Level & Laying concrete PCC for RP9 VIADUCT Km 195+900 RHS 29-Apr-19 5:10 PM
539 NMSCEW/P-IV/STR/2019/523 523 Checking annular filling arround foundation of M15 concrete at RP13 VIADUCT Km 169+800 RHS 29-Apr-19 9:30 AM NR
540 NMSCEW/P-IV/STR/2019/524 524 Checking annular filling arround foundation of M15 concrete at LP12 VIADUCT Km 169+800 LHS 29-Apr-19 11:10 AM NR
541 NMSCEW/P-IV/STR/2019/525 525 Checking of reinforcement and shuttering for pier shaft starter at LP12. VIADUCT Km 169+800 LHS 29-Apr-19 2:20 PM NR
542 NMSCEW/P-IV/STR/2019/526 526 Checking of reinforcement and shuttering for pier shaft starter at RP13 VIADUCT Km 169+800 RHS 29-Apr-19 2:45 PM NR
543 NMSCEW/P-IV/STR/2019/527 527 Checking top level & Laying concrete for LP12 pier saft starter VIADUCT Km 169+800 LHS 29-Apr-19 4:22 PM NR
544 NMSCEW/P-IV/STR/2019/528 528 Checking top level & Laying concrete for RP13 pier saft starter VIADUCT Km 169+800 RHS 29-Apr-19 5:11 PM NR
545 NMSCEW/P-IV/STR/2019/529 529 Checking of layout & level at LP- 07 Viaduct Km 169+800 LHS 29-Apr-19 12:00 AM IPC-03 DONE
546 NMSCEW/P-IV/STR/2019/530 530 Checking level for excavated bed for at LP- 07 Viaduct Km 169+800 LHS 29-Apr-19 12:00 AM IPC-03 DONE
547 NMSCEW/P-IV/STR/2019/531 531 Checking top Level & Laying concrete PCC for LP- 07 Viaduct Km 169+800 LHS 29-Apr-19 12:00 AM IPC-03 DONE
548 NMSCEW/P-IV/STR/2019/532 532 Checking Of Layout & Level for LP8 Viaduct Km 169+800 LHS 29-Apr-19 9:15 AM IPC-04 DONE
549 NMSCEW/P-IV/STR/2019/533 533 Checking level for excavated bed for at LP 8 Viaduct Km 169+800 LHS 29-Apr-19 9:42 AM IPC-04 DONE
550 NMSCEW/P-IV/STR/2019/534 534 Checking top Level & Laying concrete PCC for LP8 Viaduct Km 169+800 LHS 29-Apr-19 10:28 AM IPC-04 DONE
551 NMSCEW/P-IV/STR/2019/535 535 Checking annular filling arround raft of M15 concrete at RP3 VIADUCT Km 195+900 RHS 29-Apr-19 2:20 PM
552 NMSCEW/P-IV/STR/2019/536 536 Checking level for excavated bed at PUP PUP Km 168+380 BHS 30-Apr-19 10:00 AM REPEATED
553 NMSCEW/P-IV/STR/2019/537 537 Checking top level & laying M10 concrete for PCC PUP Km 168+380 BHS 30-Apr-19 10:30 AM DONE
Checking reinforcement for precast Box Culvert (3x3) (cushion upto 2m) at precast yard camp
554 NMSCEW/P-IV/STR/2019/538 538 BOX CULVERT Km 200+200 LHS 30-Apr-19 9:30 AM DONE
-2 for ch 200+286,
Checking Segment
for shuttering No-6,7,8
& Pouring of Concreting Grade =(M-30) for Precast Box Culvert
555 NMSCEW/P-IV/STR/2019/539 539 BOX CULVERT Km 200+200 LHS 30-Apr-19 11:00 AM DONE
(3×3),(cushion upto 2m) for
Checking reinforcement at precast
precastyard
Boxcamp -2 (2x2)
Culvert for ch(cushion
200+286,2mSegment No-6,7,8
to 4m) at precast yard
556 NMSCEW/P-IV/STR/2019/540 540 BOX CULVERT Km 200+200 LHS 30-Apr-19 9:45 AM DONE
camp -2 , Segment
Checking No-1& Pouring of Concreting Grade =(M-30) for Precast Box Culvert
for shuttering
557 NMSCEW/P-IV/STR/2019/541 541 BOX CULVERT Km 200+200 LHS 30-Apr-19 10:45 AM DONE
(2x2) (cushion 2m to 4m) at precast yard camp -2 , Segment No-1
558 NMSCEW/P-IV/STR/2019/542 542 Checking of layout and level for PUP PUP Km 193+880 BHS 30-Apr-19 9:00 AM IPC-04 DONE AE
559 NMSCEW/P-IV/STR/2019/543 543 Checking level for excavated bed at PUP PUP Km 193+880 BHS 30-Apr-19 10:10 AM IPC-04 DONE AE
560 NMSCEW/P-IV/STR/2019/544 544 Checking top level & laying M10 concrete for PCC PUP Km 193+880 BHS 30-Apr-19 10:50 AM IPC-04 DONE AE
561 NMSCEW/P-IV/STR/2019/545 545 Checking top level & laying M10 concrete for PCC BOX CULVERT Km 192+575 BHS 30-Apr-19 9:35 AM NA
562 NMSCEW/P-IV/STR/2019/546 546 checking of bottom haunch reinforcement & shuttering PUP Km 190+650 LHS 30-Apr-19 4:30 PM IPC-05 DONE
563 NMSCEW/P-IV/STR/2019/547 547 Checking top Level & Pouring M30 concrete at bottom haunch for PUP PUP Km 190+650 LHS 30-Apr-19 4:45 PM IPC-05 DONE
564 NMSCEW/P-IV/STR/2019/548 548 checking of reinforcement and shuttering for raft LVUP Km 173+400 LHS 30-Apr-19 10:15 AM IPC-05 DONE AE
565 NMSCEW/P-IV/STR/2019/549 549 checking top level and pouring concrete(M30) for raft LVUP Km 173+400 LHS 30-Apr-19 11:30 AM IPC-05 DONE AE
Checking reinforcement for precast Box Culvert (3x3) (cushion 2-4m) at precast yard camp
566 NMSCEW/P-IV/STR/2019/550 550 BOX CULVERT Km 175+500 LHS 30-Apr-19 4:00 PM DONE
-1 ,Segment
Checking for No- 21,22 &2
shuttering 3
& Pouring of Concreting Grade =(M-30) for Precast Box Culvert
567 NMSCEW/P-IV/STR/2019/551 551 BOX CULVERT Km 175+500 LHS 30-Apr-19 5:00 PM DONE
(3×3) (Cushion 2 to 4 m) at precast yard camp-1,Segment No- 21,22 &2 3
568 NMSCEW/P-IV/STR/2019/552 552 Checking of reinforcement and shuttering for pier shaft starter at LP12. VIADUCT Km 169+800 LHS 30-Apr-19 11:30 AM NR SPOT RFI
569 NMSCEW/P-IV/STR/2019/553 553 Checking of reinforcement and shuttering for pier shaft starter at RP13 VIADUCT Km 169+800 RHS 30-Apr-19 11:32 AM NR SPOT RFI
570 NMSCEW/P-IV/STR/2019/554 554 Checking top level & Laying concrete for LP12 pier saft starter VIADUCT Km 169+800 LHS 30-Apr-19 12:00 PM NR SPOT RFI
571 NMSCEW/P-IV/STR/2019/555 555 Checking top level & Laying concrete for RP13 pier saft starter VIADUCT Km 169+800 RHS 30-Apr-19 12:08 PM NR SPOT RFI
572 NMSCEW/P-IV/STR/2019/556 556 Checking of layout and level for RP12 Viaduct Km 169+800 RHS 30-Apr-19 11:45 AM IPC-04 DONE SPOT RFI
573 NMSCEW/P-IV/STR/2019/557 557 Checking level for excavated bed for RP12 Viaduct Km 169+800 RHS 30-Apr-19 11:55 AM IPC-04 DONE SPOT RFI
574 NMSCEW/P-IV/STR/2019/558 558 Laying and top level checking of concrete for PCC for RP12 Viaduct Km 169+800 RHS 30-Apr-19 12:15 PM IPC-04 DONE SPOT RFI
575 NMSCEW/P-IV/STR/2019/559 559 Checking of reinforcement and shuttering for RP-03 Viaduct Km 169+800 RHS 30-Apr-19 12:00 AM IPC-02 DONE
576 NMSCEW/P-IV/STR/2019/560 560 Checking top level & Pouring concrete for RP-03 Viaduct Km 169+800 RHS 30-Apr-19 12:00 AM IPC-02 DONE
577 NMSCEW/P-IV/STR/2019/561 561 Checking of layout and level & structural excavation for VUP VUP Km 176+614 BHS 30-Apr-19 10:00 AM IPC-08 DONE AE SPOT RFI
578 NMSCEW/P-IV/STR/2019/559/A 559/A Checking of reinforcement and shuttering for LP-03 Viaduct Km 169+800 LHS 30-Apr-19 IPC-02 DONE
579 NMSCEW/P-IV/STR/2019/559/B 559/B Checking of reinforcement and shuttering for RP-05 Viaduct Km 169+800 RHS 30-Apr-19 IPC-02 DONE
580 NMSCEW/P-IV/STR/2019/560/A 560/A Checking top level & Pouring concrete for LP-03 Viaduct Km 169+800 LHS 30-Apr-19 IPC-02 DONE
581 NMSCEW/P-IV/STR/2019/560/B 560/B Checking top level & Pouring concrete for RP-05 Viaduct Km 169+800 RHS 30-Apr-19 IPC-02 DONE
582 NMSCEW/P-IV/STR/2019/561-A 561-A Checking of layout and level for VUP VUP Km 176+614 BHS 30-Apr-19 10:00 AM SPOT RFI
583 NMSCEW/P-IV/STR/2019/561-B 561-B Checking level for excavated bed for VUP VUP Km 176+614 BHS 30-Apr-19 11:32 AM SPOT RFI
584 NMSCEW/P-IV/STR/2019/562 562 Checking of reinforcement and shuttering for raft at PUP PUP Km 177+810 LHS 1-May-19 11:30 AM NR
585 NMSCEW/P-IV/STR/2019/563 563 Checking top level and Pouring of concrete for raft at PUP PUP Km 177+810 LHS 1-May-19 4:30 PM NR
586 NMSCEW/P-IV/STR/2019/564 564 Checking of reinforcement and shuttering for raft at PUP PUP Km 186+000 LHS 1-May-19 5:00 PM NR
587 NMSCEW/P-IV/STR/2019/565 565 Checking top level and Pouring of concrete for raft at PUP PUP Km 186+000 RHS 1-May-19 5:30 PM NR
588 NMSCEW/P-IV/STR/2019/566 566 Checking of 1st Lift of wall no. 1st at PUP PUP Km 205+430 LHS 1-May-19 8:00 AM DONE
589 NMSCEW/P-IV/STR/2019/567 567 Checking of layout and level for PUP PUP Km 212+080 Km 00+000 RHS 2-May-19 8:55 AM IPC-10 DONE AE
590 NMSCEW/P-IV/STR/2019/568 568 Checking level for excavated bed for PUP PUP Km 212+080 Km 00+000 RHS 2-May-19 9:00 AM IPC-10 DONE AE
591 NMSCEW/P-IV/STR/2019/569 569 Checking top level & laying M10 concrete for PCC at PUP PUP Km 212+080 Km 00+000 RHS 2-May-19 10:00 AM IPC-10 DONE
592 NMSCEW/P-IV/STR/2019/570 570 checking of A1 & A2 reinforcement and shuttering of bottom haunch. PUP Km 184+190 RHS 1-May-19 12:00 AM IPC-03 DONE
593 NMSCEW/P-IV/STR/2019/571 571 A1 & A2 bottom hauch pouring of concrete PUP Km 184+190 RHS 1-May-19 12:00 AM IPC-03 DONE
checking of reinforcement and shuttering for precast Box Culvert (3x3) (cushion up to 2m) for
594 NMSCEW/P-IV/STR/2019/572 572 Box Culvert Km 200+200 LHS 1-May-19 11:52 AM DONE
(ch-200+286) at precast &
Checking for shuttering yard camp of
Pouring 2, Segment NO-
Concreting 09 &=(M-30)
Grade 10 for Precast Box Culvert
595 NMSCEW/P-IV/STR/2019/573 573 Box Culvert Km 200+200 LHS 1-May-19 12:08 PM DONE
(3×3),(Cushion up to 2m) for (ch.200+286) at precast yard camp-1,Segment 09&10
596 NMSCEW/P-IV/STR/2019/574 574 Checking of layout and level for RP- 01 VIADUCT Km 169+800 RHS 1-May-19 10:50 AM NR
597 NMSCEW/P-IV/STR/2019/575 575 Checking level for excavated bed for RP -01 VIADUCT Km 169+800 RHS 1-May-19 11:20 AM NR
598 NMSCEW/P-IV/STR/2019/576 576 Checking top Level & Laying concrete PCC for RP-01 VIADUCT Km 169+800 RHS 1-May-19 12:50 PM NR
599 NMSCEW/P-IV/STR/2019/577 577 Checking top level & Pouring of concrete for LP12 pier saft starter VIADUCT Km 169+800 RHS 1-May-19 2:20 PM NR
600 NMSCEW/P-IV/STR/2019/578 578 Checking top level & Pouring of concrete for LP13 pier saft starter VIADUCT Km 169+800 RHS 1-May-19 2:30 PM NR
601 NMSCEW/P-IV/STR/2019/579 579 Laying and top level checking of concrete for PCC for RP-01 VIADUCT Km 169+800 RHS 1-May-19 11:08 AM NR
602 NMSCEW/P-IV/STR/2019/580 580 Laying and top level checking of concrete for PCC for RP-09 VIADUCT Km 195+900 RHS 1-May-19 10:05 AM IPC-08 DONE
Checking reinforcement for precast Box Culvert (3x3) (cushion upto 2m) for (ch.200+286)at
603 NMSCEW/P-IV/STR/2019/581 581 Box culvert Km 200+200 LHS 2-May-19 9:30 AM DONE
precast
Checkingyard
forcamp -2. Segment
shuttering & PouringNO-11.
of Concreting Grade =(M-30) for Precast Box Culvert
604 NMSCEW/P-IV/STR/2019/582 582 Box culvert Km 200+200 LHS 2-May-19 9:50 AM DONE
(3×3) ,(Cushion upto 2m) for (ch.200+286) at precast yard camp-2.,Segment no.-11.
605 NMSCEW/P-IV/STR/2019/583 583 Checking of reinforcement and shuttering of raft. PUP Km 186+000 LHS 2-May-19 12:00 AM IPC-03 DONE AE
606 NMSCEW/P-IV/STR/2019/584 584 Checking of top level and Pouring of concrete for Raft PUP Km 186+000 LHS 2-May-19 12:00 AM IPC-03 DONE AE
607 NMSCEW/P-IV/STR/2019/585 585 Checking of reinforcement and shuttering of raft. PUP Km 177+810 LHS 2-May-19 12:00 AM IPC-03 DONE
608 NMSCEW/P-IV/STR/2019/586 586 Checking of top level and Pouring of concrete for Raft PUP Km 177+810 LHS 2-May-19 12:00 AM IPC-03 DONE
609 NMSCEW/P-IV/STR/2019/587 587 Checking of layout and level for B/C Box culvert Km 193+484 BHS 2-May-19 10:00 AM DONE
610 NMSCEW/P-IV/STR/2019/588 588 Checking level for excavated bed Box culvert Km 193+484 BHS 2-May-19 12:15 PM DONE
611 NMSCEW/P-IV/STR/2019/589 589 Checking top level and laying of M10 concrete for PCC Box culvert Km 193+484 BHS 2-May-19 12:45 PM DONE
612 NMSCEW/P-IV/STR/2019/590 590 Checking of layout and level for B/C Box culvert Km 192+575 Km 00+000 BHS 2-May-19 11:10 AM IPC-11 Approved AE
613 NMSCEW/P-IV/STR/2019/591 591 Checking level for excavated bed Box culvert Km 192+575 Km 00+000 BHS 2-May-19 12:20 PM IPC-11 Approved AE
614 NMSCEW/P-IV/STR/2019/592 592 Checking top level and laying of M10 concrete for PCC Box culvert Km 192+575 Km 00+000 BHS 2-May-19 12:50 PM IPC-11 Approved AE
615 NMSCEW/P-IV/STR/2019/593 593 Checking of layout and level for B/C Box culvert Km 198+128 Km 00+000 BHS 2-May-19 12:35 PM IPC-11 Approved
616 NMSCEW/P-IV/STR/2019/594 594 Checking level for excavated bed Box culvert Km 198+128 Km 00+000 BHS 2-May-19 2:20 PM IPC-11 Approved
617 NMSCEW/P-IV/STR/2019/595 595 Checking top level and laying of M10 concrete for PCC Box culvert Km 198+128 Km 00+000 BHS 2-May-19 3:00 PM IPC-11 Approved
Checking reinforcement for precast Box Culvert (3x3) (cushion 2-4m) at precast yard camp -1
618 NMSCEW/P-IV/STR/2019/596 596 Box culvert Km 175+500 LHS 2-May-19 10:30 AM DONE
Segment NO
Checking 24&25&26
for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
619 NMSCEW/P-IV/STR/2019/597 597 Box culvert Km 175+500 LHS 2-May-19 10:45 AM DONE
(3×3) ,(Cushion 2 to 4 m) at precast yard camp-1,Segment 24&25&26
620 NMSCEW/P-IV/STR/2019/598 598 Checking of reinforcement and shuttering for pier at RP3 VIADUCT Km 195+990 RHS 2-May-19 3:08 PM
621 NMSCEW/P-IV/STR/2019/599 599 Checking top level & Laying concrete for RP 3 pier VIADUCT Km 195+990 RHS 2-May-19 3:22 PM
622 NMSCEW/P-IV/STR/2019/600 600 Checking of Layout & Level for RP1 Viaduct Km 195+990 RHS 2-May-19 2:10 PM IPC-04 DONE AE
623 NMSCEW/P-IV/STR/2019/601 601 Checking level for excavated bed for at RP1 Viaduct Km 195+990 RHS 2-May-19 3:00 PM IPC-04 DONE
624 NMSCEW/P-IV/STR/2019/602 602 Checking top Level & Laying concrete PCC for RP1 Viaduct Km 195+990 RHS 2-May-19 4:05 PM IPC-04 DONE AE
625 NMSCEW/P-IV/STR/2019/603 603 Checking top level & Laying concrete for LP12 pier saft starter VIADUCT Km 169+800 LHS 2-May-19 9:00 AM NR
626 NMSCEW/P-IV/STR/2019/604 604 Checking top level & Laying concrete for RP13 pier saft starter VIADUCT Km 169+800 RHS 2-May-19 9:15 AM NR
627 NMSCEW/P-IV/STR/2019/605 605 Checking of layout & level at RP-01 Viaduct Km 169+800 RHS 2-May-19 12:00 AM IPC-03 DONE
628 NMSCEW/P-IV/STR/2019/606 606 Checking level for excavated bed for at RP-01 Viaduct Km 169+800 RHS 2-May-19 12:00 AM IPC-03 DONE
629 NMSCEW/P-IV/STR/2019/607 607 Checking top Level & Laying concrete PCC for RP-01 Viaduct Km 169+800 RHS 2-May-19 12:00 AM IPC-03 DONE AE
630 NMSCEW/P-IV/STR/2019/608 608 Checking of layout and level for LP1 Viaduct Km 202+190 LHS 2-May-19 3:30 PM IPC-04 DONE AE
631 NMSCEW/P-IV/STR/2019/609 609 Checking level for excavated bed for LP1 Viaduct Km 202+190 LHS 2-May-19 3:47 PM IPC-04 DONE AE
632 NMSCEW/P-IV/STR/2019/610 610 Laying and top level checking of concrete for PCC for LP1 Viaduct Km 202+190 LHS 2-May-19 5:00 PM IPC-04 DONE AE
633 NMSCEW/P-IV/STR/2019/611 611 Checking for reinforcement & shuttering of first lift of A1 +A2 wall PUP Km 184+190 LHS 2-May-19 12:00 AM IPC-03 DONE AE
634 NMSCEW/P-IV/STR/2019/612 612 Checking Top level and pouring concrete first lift for A1 +A2 wall PUP Km 184+190 LHS 2-May-19 12:00 AM IPC-03 DONE AE
635 NMSCEW/P-IV/STR/2019/613 613 Checking of reinforcement and shuttering for pier at RP3 VIADUCT Km 195+990 RHS 3-May-19 3:00 PM
636 NMSCEW/P-IV/STR/2019/614 614 Checking top level & Laying concrete for RP 3 pier VIADUCT Km 195+990 RHS 3-May-19 3:15 PM
637 NMSCEW/P-IV/STR/2019/615 615 Checking of Layout & Level for LP5 VIADUCT Km 195+990 LHS 3-May-19 12:00 PM
638 NMSCEW/P-IV/STR/2019/616 616 Checking level for excavated bed for at LP5 VIADUCT Km 195+990 LHS 3-May-19 12:45 PM
639 NMSCEW/P-IV/STR/2019/617 617 Checking top Level & Laying concrete PCC for LP5 VIADUCT Km 195+990 LHS 3-May-19 2:20 PM
640 NMSCEW/P-IV/STR/2019/618 618 Checking of Layout & Level for RP2 VIADUCT Km 196+560 RHS 3-May-19 2:00 PM
641 NMSCEW/P-IV/STR/2019/619 619 Checking level for excavated bed for at RP2 VIADUCT Km 196+560 RHS 3-May-19 2:45 PM
642 NMSCEW/P-IV/STR/2019/620 620 Checking top Level & Laying concrete PCC for RP2 VIADUCT Km 196+560 RHS 3-May-19 3:00 PM
643 NMSCEW/P-IV/STR/2019/621 621 Checking of Layout & Level for RP2 VIADUCT Km 202+190 RHS 3-May-19 3:15 PM
644 NMSCEW/P-IV/STR/2019/622 622 Checking level for excavated bed for at RP2 VIADUCT Km 202+190 RHS 3-May-19 3:40 PM
645 NMSCEW/P-IV/STR/2019/623 623 Checking top Level & Laying concrete PCC for RP2 VIADUCT Km 202+190 RHS 3-May-19 4:00 PM
646 NMSCEW/P-IV/STR/2019/624 624 Checking of reinforcement and shuttering for raft at PUP PUP Km 177+810 LHS 3-May-19 10:30 AM NR
647 NMSCEW/P-IV/STR/2019/625 625 Checking top level and Pouring of concrete for raft at PUP PUP Km 177+810 LHS 3-May-19 11:00 AM NR
648 NMSCEW/P-IV/STR/2019/626 626 Checking of Layout & Level for PUP PUP Km 212+080 Km 00+000 LHS 3-May-19 9:00 AM IPC-10 DONE
649 NMSCEW/P-IV/STR/2019/627 627 Checking level for excavated bed for for PUP PUP Km 212+080 LHS 3-May-19 9:45 AM DONE
650 NMSCEW/P-IV/STR/2019/628 628 Checking top Level & Laying concrete PCC for PUP PUP Km 212+080 Km 00+000 LHS 3-May-19 11:15 AM IPC-10 DONE
651 NMSCEW/P-IV/STR/2019/629 629 Checking top level & Pouring concrete for LP12 pier saft starter VIADUCT Km 169+800 LHS 3-May-19 10:00 AM NR
652 NMSCEW/P-IV/STR/2019/630 630 Checking top level & Pouring concrete for RP13 pier saft starter VIADUCT Km 169+800 RHS 3-May-19 10:15 AM NR
653 NMSCEW/P-IV/STR/2019/631 631 Checking of layout and level for RP- 09 Viaduct Km 169+800 RHS 3-May-19 10:50 AM NR
654 NMSCEW/P-IV/STR/2019/632 632 Checking level for excavated bed for RP -09 Viaduct Km 169+800 RHS 3-May-19 11:30 AM NR
655 NMSCEW/P-IV/STR/2019/633 633 Laying and top level checking of concrete for PCC for RP-09 Viaduct Km 169+800 RHS 3-May-19 12:15 PM NR
656 NMSCEW/P-IV/STR/2019/634 634 Checking of reinforcement and shuttering for raft at LP3 VIADUCT Km 169+800 LHS 3-May-19 4:20 PM NR
657 NMSCEW/P-IV/STR/2019/635 635 Checking top level and Pouring of concrete for raft at LP3 VIADUCT Km 169+800 LHS 3-May-19 5:00 PM NR
Checking reinforcement for precast Box Culvert (3x3) (cushion upto 2m) for (ch.200+286)at
658 NMSCEW/P-IV/STR/2019/636 636 Box Culvert Km 200+200 LHS 3-May-19 2:15 PM DONE
precast yard
Checking forcamp -2. Segment
shuttering & PouringNO-12.
of Concreting Grade =(M-30) for Precast Box Culvert
659 NMSCEW/P-IV/STR/2019/637 637 Box Culvert Km 200+200 LHS 3-May-19 2:40 PM DONE
(3×3) ,(Cushion
Checking upto 2m)for
reinforcement forprecast
(ch.200+286) at precast
Box Culvert (3x3) yard camp-2,Segment
(cushion no.-12.
2-4m) at precast yard camp
660 NMSCEW/P-IV/STR/2019/638 638 Box culvert Km 175+500 LHS 3-May-19 3:35 PM NR
-1, Segment
Checking for No-25,26
shuttering&&27 Pouring of Concreting Grade =(M-30) for Precast Box Culvert
661 NMSCEW/P-IV/STR/2019/639 639 Box culvert Km 175+500 LHS 3-May-19 4:22 PM NR
(3×3) ,(Cushion 2 to 4 m) at precast yard camp-1,Segment No-25,26 & 27
662 NMSCEW/P-IV/STR/2019/640 640 Checking level for excavated bed for Lvup LVUP Km 169+291 LHS 3-May-19 11:10 AM REPEATED
663 NMSCEW/P-IV/STR/2019/641 641 Checking top level & laying M10 concrete for PCC at Lvup LVUP Km 169+291 BHS 3-May-19 11:25 AM IPC-08 DONE
664 NMSCEW/P-IV/STR/2019/642 642 Checking of reinforcement & shuttering 1st lift for wall2 PUP Km 205+430 Km 00+000 LHS 4-May-19 11:00 AM IPC-03 DONE AE
665 NMSCEW/P-IV/STR/2019/643 643 Checking level and pouring concrete(M30) 1st lift for wall2 PUP Km 205+430 Km 00+000 LHS 4-May-19 11:15 AM IPC-03 DONE AE
666 NMSCEW/P-IV/STR/2019/644 644 Checking of layout and level for B/C Box culvert Km 193+940 BHS 4-May-19 2:00 PM NA
667 NMSCEW/P-IV/STR/2019/645 645 Checking level for excavated bed Box culvert Km 193+940 BHS 4-May-19 2:50 PM NA
668 NMSCEW/P-IV/STR/2019/646 646 Checking top level and laying of M10 concrete for PCC Box culvert Km 193+940 BHS 4-May-19 4:00 PM NA
669 NMSCEW/P-IV/STR/2019/647 647 Checking for reinforcement & shuttering of first lift of A1 &A2 wall PUP Km 184+190 LHS 4-May-19 12:00 AM DONE
670 NMSCEW/P-IV/STR/2019/648 648 Checking level and pouring Concrete for first lift of A1 &A2 wall PUP Km 184+190 LHS 4-May-19 12:00 AM DONE
671 NMSCEW/P-IV/STR/2019/649 649 Checking of reinforcement and shuttering for pier at RP3 VIADUCT Km 195+990 RHS 4-May-19 3:00 PM
672 NMSCEW/P-IV/STR/2019/650 650 Checking top level & Laying concrete for RP 3 pier VIADUCT Km 195+990 RHS 4-May-19 3:15 PM
673 NMSCEW/P-IV/STR/2019/651 651 Checking of Layout & Level for LP9 VIADUCT Km 195+990 LHS 4-May-19 2:30 PM
674 NMSCEW/P-IV/STR/2019/652 652 Checking level for excavated bed for at LP9 VIADUCT Km 195+990 LHS 4-May-19 3:30 PM
675 NMSCEW/P-IV/STR/2019/653 653 Checking top Level & Laying concrete PCC for LP9 VIADUCT Km 195+990 LHS 4-May-19 4:30 PM
676 NMSCEW/P-IV/STR/2019/654 654 Checking of Layout & Level for RP2 VIADUCT Km 196+560 RHS 4-May-19 12:00 PM IPC-08 DONE AE
677 NMSCEW/P-IV/STR/2019/655 655 Checking level for excavated bed for at RP2 VIADUCT Km 196+560 RHS 4-May-19 12:45 PM IPC-08 DONE AE
678 NMSCEW/P-IV/STR/2019/656 656 Checking top Level & Laying concrete PCC for RP2 VIADUCT Km 196+560 RHS 4-May-19 2:15 PM IPC-08 DONE AE
679 NMSCEW/P-IV/STR/2019/657 657 Checking of Layout & Level for RP2 VIADUCT Km 202+190 RHS 4-May-19 10:00 AM
680 NMSCEW/P-IV/STR/2019/658 658 Checking level for excavated bed for at RP2 VIADUCT Km 202+190 RHS 4-May-19 10:15 AM
681 NMSCEW/P-IV/STR/2019/659 659 Checking top Level & Laying concrete PCC for RP2 VIADUCT Km 202+190 RHS 4-May-19 11:30 AM
682 NMSCEW/P-IV/STR/2019/660 660 Checking of Layout & Level for LP5 Viaduct Km 195+990 LHS 4-May-19 11:45 AM IPC-04 DONE AE
683 NMSCEW/P-IV/STR/2019/661 661 Checking level for excavated bed for at LP5 Viaduct Km 195+990 LHS 4-May-19 12:15 PM IPC-04 DONE AE
684 NMSCEW/P-IV/STR/2019/662 662 Checking top Level & Laying concrete PCC for LP5 Viaduct Km 195+990 LHS 4-May-19 12:30 PM IPC-04 DONE AE
Checking reinforcement for precast Box Culvert (3x3) (cushion upto 2m) for (ch.200+286)at
685 NMSCEW/P-IV/STR/2019/663 663 Box Culvert Km 200+200 LHS 4-May-19 9:00 AM DONE
precast yard
Checking forcamp -2. Segment
shuttering No-12&13
& Pouring of Concreting Grade =(M-30) for Precast Box Culvert
686 NMSCEW/P-IV/STR/2019/664 664 Box Culvert Km 200+200 LHS 4-May-19 9:30 AM DONE
(3×3) ,(Cushion
Checking upto 2m)for
reinforcement forprecast
(ch.200+286) at precast
Box Culvert (3x3) yard camp-2,
(cushion Segment
2-4m) No-12&13
at precast yard camp
687 NMSCEW/P-IV/STR/2019/665 665 Box culvert Km 175+500 LHS 4-May-19 3:10 PM DONE
-1, Segment
Checking for No,26 ,27 &
shuttering & 28
Pouring of Concreting Grade =(M-30) for Precast Box Culvert
688 NMSCEW/P-IV/STR/2019/666 666 Box culvert Km 175+500 LHS 4-May-19 4:50 PM DONE
(3×3) ,(Cushion 2 to 4 m) at precast yard camp-1, Segment No,26 ,27 & 28
689 NMSCEW/P-IV/STR/2019/667 667 Checking of Layout & Level for LP6 VIADUCT Km 196+560 LHS 4-May-19 12:10 PM
690 NMSCEW/P-IV/STR/2019/668 668 Checking level for excavated bed for at LP6 VIADUCT Km 196+560 LHS 4-May-19 12:50 PM
691 NMSCEW/P-IV/STR/2019/669 669 Checking top Level & Laying concrete PCC for LP6 VIADUCT Km 196+560 LHS 4-May-19 2:37 PM
692 NMSCEW/P-IV/STR/2019/670 670 Checking top level & Pouring concrete for LP12 pier saft starter VIADUCT Km 169+800 LHS 4-May-19 9:15 AM NR
693 NMSCEW/P-IV/STR/2019/671 671 Checking top level & Pouring concrete for RP13 pier saft starter VIADUCT Km 169+800 RHS 4-May-19 9:45 AM NR
694 NMSCEW/P-IV/STR/2019/672 672 Checking of layout and level for RP- 09 Viaduct Km 169+800 RHS 4-May-19 4:10 PM IPC-04 DONE
695 NMSCEW/P-IV/STR/2019/673 673 Checking level for excavated bed for RP -09 Viaduct Km 169+800 RHS 4-May-19 5:10 PM IPC-04 DONE
696 NMSCEW/P-IV/STR/2019/674 674 Laying and top level checking of concrete for PCC for RP-09 Viaduct Km 169+800 RHS 4-May-19 5:40 PM IPC-04 DONE
697 NMSCEW/P-IV/STR/2019/675 675 Checking of reinforcement and shuttering of raft. PUP Km 185+235 RHS 5-May-19 12:00 AM IPC-03 DONE AE
698 NMSCEW/P-IV/STR/2019/676 676 Checking of top level and Pouring of concrete for Raft PUP Km 185+235 RHS 5-May-19 12:00 AM IPC-03 DONE AE
699 NMSCEW/P-IV/STR/2019/677 677 Checking top level & Pouring concrete for LP12 pier saft starter VIADUCT Km 169+800 Km 00+000 LHS 5-May-19 9:30 AM IPC-09 DONE SPOT RFI
700 NMSCEW/P-IV/STR/2019/678 678 Checking top level & Pouring concrete for RP13 pier saft starter VIADUCT Km 169+800 Km 00+000 RHS 5-May-19 9:45 AM IPC-09 DONE SPOT RFI
701 NMSCEW/P-IV/STR/2019/679 679 Checking of reinforcement and shuttering for pier at RP3 VIADUCT Km 195+990 RHS 6-May-19 10:00 AM IPC-14
702 NMSCEW/P-IV/STR/2019/680 680 Checking top level & Laying concrete for RP 3 pier VIADUCT Km 195+990 RHS 6-May-19 10:15 AM IPC-14
703 NMSCEW/P-IV/STR/2019/681 681 Checking of Layout & Level for LP9 VIADUCT Km 195+990 LHS 6-May-19 10:30 AM
704 NMSCEW/P-IV/STR/2019/682 682 Checking level for excavated bed for at LP9 VIADUCT Km 195+990 LHS 6-May-19 11:00 AM
705 NMSCEW/P-IV/STR/2019/683 683 Checking top Level & Laying concrete PCC for LP9 VIADUCT Km 195+990 LHS 6-May-19 11:15 AM
706 NMSCEW/P-IV/STR/2019/684 684 Checking of Layout & Level for LP2 VIADUCT Km 196+560 LHS 6-May-19 12:15 PM
707 NMSCEW/P-IV/STR/2019/685 685 Checking level for excavated bed for at LP2 VIADUCT Km 196+560 LHS 6-May-19 12:45 PM
708 NMSCEW/P-IV/STR/2019/686 686 Checking top Level & Laying concrete PCC for LP2 VIADUCT Km 196+560 LHS 6-May-19 2:00 PM
709 NMSCEW/P-IV/STR/2019/687 687 Checking of layout and level for B/C Box culvert Km 212+170 BHS 6-May-19 9:00 AM NA
710 NMSCEW/P-IV/STR/2019/688 688 Checking level for excavated bed Box culvert Km 212+170 BHS 6-May-19 9:30 AM NA
711 NMSCEW/P-IV/STR/2019/689 689 Checking top level and laying of M10 concrete for PCC Box culvert Km 212+170 BHS 6-May-19 10:45 AM NA
712 NMSCEW/P-IV/STR/2019/690 690 Checking of reinforcement and shuttering for raft at PUP PUP Km 177+810 RHS 6-May-19 12:30 PM NR
713 NMSCEW/P-IV/STR/2019/691 691 Checking top level and Pouring of concrete for raft at PUP PUP Km 177+810 RHS 6-May-19 4:30 PM NR
714 NMSCEW/P-IV/STR/2019/692 692 Checking of reinforcement & shuttering 1st lift for A1 wall PUP Km 171+110 RHS 6-May-19 10:22 AM NR
715 NMSCEW/P-IV/STR/2019/693 693 Checking of reinforcement & shuttering 1st lift for A2 wall PUP Km 171+110 RHS 6-May-19 10:50 AM NR
716 NMSCEW/P-IV/STR/2019/694 694 Checking level and pouring concrete(M30) 1st lift for A1 wall PUP Km 171+110 RHS 6-May-19 11:50 AM NR
717 NMSCEW/P-IV/STR/2019/695 695 Checking level and pouring concrete(M30) 1st lift for A2 wall PUP Km 171+110 RHS 6-May-19 12:39 PM NR
718 NMSCEW/P-IV/STR/2019/696 696 Checking top level and laying of M10 concrete for PCC VUP Km 176+614 LHS 6-May-19 2:15 PM IPC-08 DONE
Checking reinforcement for precast Box Culvert (3x3) (cushion 2-4m) at precast yard camp
719 NMSCEW/P-IV/STR/2019/697 697 Box culvert Km 175+500 LHS 6-May-19 3:30 PM NR
-1, Segment
Checking for No,28 ,29 &
shuttering & 30
Pouring of Concreting Grade =(M-30) for Precast Box Culvert
720 NMSCEW/P-IV/STR/2019/698 698 Box culvert Km 175+500 LHS 6-May-19 4:00 PM NR
(3×3) ,(Cushion 2 to 4 m) at precast yard camp-1, Segment No,28 ,29 & 30
721 NMSCEW/P-IV/STR/2019/699 699 Checking of layout and level at RP 10 Viaduct Km 169+800 BHS 6-May-19 10:05 AM IPC-04 DONE
722 NMSCEW/P-IV/STR/2019/700 700 Checking level for excavated bed at RP10 Viaduct Km 169+800 BHS 6-May-19 10:22 AM IPC-04 DONE
723 NMSCEW/P-IV/STR/2019/701 701 Checking top level and laying of M10 concrete for PCC at RP 10 Viaduct Km 169+800 BHS 6-May-19 12:02 PM IPC-04 DONE
724 NMSCEW/P-IV/STR/2019/702 702 Checking of layout and level at RP 11 Viaduct Km 169+800 BHS 6-May-19 11:05 AM NR
725 NMSCEW/P-IV/STR/2019/703 703 Checking level for excavated bed at RP11 Viaduct Km 169+800 BHS 6-May-19 11:27 AM NR
726 NMSCEW/P-IV/STR/2019/704 704 Checking top level and laying of M10 concrete for PCC at RP 11 Viaduct Km 169+800 BHS 6-May-19 3:06 PM NR
Checking reinforcement for precast Box Culvert (3x3) (cushion upto 2m) for (ch.200+286)at
727 NMSCEW/P-IV/STR/2019/705 705 Box Culvert Km 200+200 LHS 6-May-19 3:16 PM DONE SPOT RFI
precast yard
Checking forcamp -2. Segment
shuttering NO-14&15.
& Pouring of Concreting Grade =(M-30) for Precast Box Culvert
728 NMSCEW/P-IV/STR/2019/706 706 Box Culvert Km 200+200 LHS 6-May-19 4:05 PM DONE SPOT RFI
(3×3) ,(Cushion upto 2m) for (ch.200+286) at precast yard camp-2,Segment no.-14&15.
729 NMSCEW/P-IV/STR/2019/707 707 Checking of reinforcement and shuttering for raft at PUP PUP Km 177+810 RHS 7-May-19 12:30 PM NR
730 NMSCEW/P-IV/STR/2019/708 708 Checking top level and Pouring of concrete for raft at PUP PUP Km 177+810 RHS 7-May-19 4:30 PM NR
731 NMSCEW/P-IV/STR/2019/709 709 Checking of reinforcement & shuttering 1st lift for A1 wall PUP Km 171+110 RHS 7-May-19 11:00 AM NR
732 NMSCEW/P-IV/STR/2019/710 710 Checking of reinforcement & shuttering 1st lift for A2 wall PUP Km 171+110 RHS 7-May-19 11:15 AM NR
733 NMSCEW/P-IV/STR/2019/711 711 Checking level and pouring concrete(M30) 1st lift for A1 wall PUP Km 171+110 RHS 7-May-19 4:00 PM NR
734 NMSCEW/P-IV/STR/2019/712 712 Checking level and pouring concrete(M30) 1st lift for A2 wall PUP Km 171+110 RHS 7-May-19 4:15 PM NR
735 NMSCEW/P-IV/STR/2019/713 713 Checking of reinforcement & shuttering 2nd lift for W1 wall PUP Km 205+430 Km 00+000 LHS 7-May-19 8:00 AM IPC-03 DONE AE
736 NMSCEW/P-IV/STR/2019/714 714 Checking level and pouring concrete(M30) 2nd lift for W1 wall PUP Km 205+430 Km 00+000 LHS 7-May-19 8:30 AM IPC-03 DONE AE
737 NMSCEW/P-IV/STR/2019/715 715 Checking level for excavated bed for LVUP LVUP Km 169+291 RHS 7-May-19 2:30 PM REPEATED
738 NMSCEW/P-IV/STR/2019/716 716 Checking top Level & Laying concrete PCC (M10) LVUP LVUP Km 169+291 Km 00+000 RHS 7-May-19 3:00 PM IPC-10 DONE
739 NMSCEW/P-IV/STR/2019/717 717 checking of bottom haunch reinforcement & shuttering PUP Km 177+810 LHS 7-May-19 11:30 AM NR
740 NMSCEW/P-IV/STR/2019/718 718 Checking top Level & Laying M30 bottom haunch concrete pouring for PUP PUP Km 177+810 LHS 7-May-19 5:00 PM NR
Checking reinforcement for precast Box Culvert (3x3) (cushion upto 2m) for (ch.200+286)at
741 NMSCEW/P-IV/STR/2019/719 719 Box Culvert Km 200+200 LHS 7-May-19 3:30 PM NR
precast yard
Checking forcamp -2. Segment
shuttering NO-16.
& Pouring of Concreting Grade =(M-30) for Precast Box Culvert
742 NMSCEW/P-IV/STR/2019/720 720 Box Culvert Km 200+200 LHS 7-May-19 3:45 PM NR
(3×3) ,(Cushion upto 2m) for (ch.200+286) at precast yard camp-2,Segment no.-16.
743 NMSCEW/P-IV/STR/2019/721 721 checking of reinforcement and shuttering for bottom slab CUP Km 188+575 LHS 7-May-19 4:30 PM NR
744 NMSCEW/P-IV/STR/2019/722 722 Checking top Level & Pouring M30 concrete for bottom slab CUP Km 188+575 LHS 7-May-19 5:00 PM NR
745 NMSCEW/P-IV/STR/2019/723 723 Checking of Layout & Level for LP6 Viaduct Km 195+990 LHS 7-May-19 10:01 AM IPC-04 DONE AE
746 NMSCEW/P-IV/STR/2019/724 724 Checking level for excavated bed for at LP6 Viaduct Km 195+990 LHS 7-May-19 10:31 AM IPC-04 DONE
747 NMSCEW/P-IV/STR/2019/725 725 Checking top Level & Laying concrete PCC for LP6 Viaduct Km 195+990 LHS 7-May-19 10:46 AM IPC-04 DONE
748 NMSCEW/P-IV/STR/2019/726 726 Checking of Layout & Level for RP6 Viaduct Km 196+560 RHS 7-May-19 2:00 PM IPC-04 DONE AE
749 NMSCEW/P-IV/STR/2019/727 727 Checking level for excavated bed for at RP6 Viaduct Km 196+560 RHS 7-May-19 2:32 PM IPC-04 DONE AE
750 NMSCEW/P-IV/STR/2019/728 728 Checking top Level & Laying concrete PCC for RP6 Viaduct Km 196+560 RHS 7-May-19 2:55 PM IPC-04 DONE AE
751 NMSCEW/P-IV/STR/2019/729 729 Checking of Layout & Level for L11 Viaduct Km 169+800 LHS 7-May-19 11::05 NR
752 NMSCEW/P-IV/STR/2019/730 730 Checking level for excavated bed for at LP11 Viaduct Km 169+800 LHS 7-May-19 11:35 AM NR
753 NMSCEW/P-IV/STR/2019/731 731 Checking top Level & Laying concrete PCC for LP11 Viaduct Km 169+800 LHS 7-May-19 12:11 PM NR
754 NMSCEW/P-IV/STR/2019/732 732 Checking of Layout & Level for RP11 Viaduct Km 169+800 RHS 7-May-19 12:50 PM IPC-04 DONE
755 NMSCEW/P-IV/STR/2019/733 733 Checking level for excavated bed for at RP11 Viaduct Km 169+800 RHS 7-May-19 2:22 PM IPC-04 DONE
756 NMSCEW/P-IV/STR/2019/734 734 Checking top Level & Laying concrete PCC for RP11 Viaduct Km 169+800 RHS 7-May-19 3:12 PM IPC-04 DONE
757 NMSCEW/P-IV/STR/2019/735 735 Checking of reinforcement and shuttering for raft at LP4 VIADUCT Km 169+800 LHS 7-May-19 3:45 PM NR
758 NMSCEW/P-IV/STR/2019/736 736 Checking top level and Pouring of concrete for raft at LP4 VIADUCT Km 169+800 LHS 7-May-19 4:36 PM NR
Checking reinforcement for precast Box Culvert (3x3) (cushion 2-4m) at precast yard camp
759 NMSCEW/P-IV/STR/2019/737 737 Box culvert Km 175+500 LHS 7-May-19 3:39 PM DONE
-1, Segment
Checking for No,28 ,29 &
shuttering & 30
Pouring of Concreting Grade =(M-30) for Precast Box Culvert
760 NMSCEW/P-IV/STR/2019/738 738 Box culvert Km 175+500 LHS 7-May-19 4:21 PM DONE
(3×3) ,(Cushion 2 to 4 m) at precast yard camp-1, Segment No,28 ,29 & 30
761 NMSCEW/P-IV/STR/2019/739 739 Checking of reinforcement & shuttering 1st lift for A1 wall PUP Km 172+190 LHS 8-May-19 8:00 AM DONE
762 NMSCEW/P-IV/STR/2019/740 740 Checking level and pouring concrete(M30) 1st lift for A1 wall PUP Km 172+190 LHS 8-May-19 4:20 PM DONE
763 NMSCEW/P-IV/STR/2019/741 741 Checking of Layout & Level for box culvert BOX CULVERT Km 212+170 BHS 8-May-19 10:00 AM
764 NMSCEW/P-IV/STR/2019/742 742 Checking top Level & Laying concrete PCC for box culvert BOX CULVERT Km 212+170 BHS 8-May-19 11:30 AM
765 NMSCEW/P-IV/STR/2019/743 743 Checking level for excavated bed for at LP9 VIADUCT Km 195+900 LHS 8-May-19 10:15 AM IPC-08 DONE
766 NMSCEW/P-IV/STR/2019/744 744 Checking of Layout & Level for LP9 VIADUCT Km 195+900 LHS 8-May-19 10:40 AM IPC-08 DONE
767 NMSCEW/P-IV/STR/2019/745 745 Checking top Level & Laying concrete PCC for LP9 VIADUCT Km 195+900 LHS 8-May-19 11:18 AM IPC-08 DONE
768 NMSCEW/P-IV/STR/2019/746 746 Checking level for excavated bed for at RP6 VIADUCT Km 195+900 RHS 8-May-19 2:18 PM
769 NMSCEW/P-IV/STR/2019/747 747 Checking of Layout & Level for RP6 VIADUCT Km 195+900 RHS 8-May-19 2:27 PM
770 NMSCEW/P-IV/STR/2019/748 748 Checking top Level & Laying concrete PCC for RP6 VIADUCT Km 195+900 RHS 8-May-19 2:40 PM
771 NMSCEW/P-IV/STR/2019/749 749 Checking level for excavated bed for at RP4 Viaduct Km 202+190 RHS 8-May-19 3:20 PM IPC-04 DONE
772 NMSCEW/P-IV/STR/2019/750 750 Checking of Layout & Level for RP4 Viaduct Km 202+190 RHS 8-May-19 3:40 PM IPC-04 DONE
773 NMSCEW/P-IV/STR/2019/751 751 Checking top Level & Laying concrete PCC for RP4 Viaduct Km 202+190 RHS 8-May-19 4:00 PM IPC-04 DONE AE
774 NMSCEW/P-IV/STR/2019/752 752 checking of A1 & A2 reinforcement and shuttering of bottom haunch. PUP Km 185+235 RHS 8-May-19 12:00 AM IPC-03 DONE
775 NMSCEW/P-IV/STR/2019/753 753 A1 & A2 bottom hauch pouring of concrete PUP Km 185+235 RHS 8-May-19 12:00 AM IPC-03 DONE
776 NMSCEW/P-IV/STR/2019/754 754 Checking of reinforcement and shuttering of raft. PUP Km 188+575 LHS 8-May-19 12:00 AM IPC-03 DONE
777 NMSCEW/P-IV/STR/2019/755 755 Checking of top level and Pouring of concrete for Raft PUP Km 188+575 LHS 8-May-19 12:00 AM IPC-03 DONE
778 NMSCEW/P-IV/STR/2019/756 756 Checking for reinforcement & shuttering of second lift of A1 &A2 wall PUP Km 184+190 LHS 8-May-19 12:00 AM IPC-03 DONE
779 NMSCEW/P-IV/STR/2019/757 757 Checking Top level and pouring concrete second lift for wall A1 & A2 PUP Km 184+190 LHS 8-May-19 12:00 AM IPC-03 DONE
checking for reinforcement for precast Box Culvert (3x3) (cushion 2-4m) at precast yard camp
780 NMSCEW/P-IV/STR/2019/758 758 BOX CULVERT Km 175+500 LHS 8-May-19 6:38 PM NR
-1 Segment
Checking forNO 31&32 & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
shuttering
781 NMSCEW/P-IV/STR/2019/759 759 BOX CULVERT Km 175+500 LHS 8-May-19 6:50 PM NR
(3×3) (Cushion 2 to 4 m) at precast yard camp-1 Segment 31&32
782 NMSCEW/P-IV/STR/2019/760 760 Checking level for excavated bed for at LP 11 Viaduct Km 169+800 LHS 8-May-19 12:12 PM IPC-04 DONE
783 NMSCEW/P-IV/STR/2019/761 761 Checking of Layout & Level for LP 11 Viaduct Km 169+800 LHS 8-May-19 2:16 PM IPC-04 DONE
784 NMSCEW/P-IV/STR/2019/762 762 Checking top Level & Laying concrete PCC for LP 11 Viaduct Km 169+800 LHS 8-May-19 2:25 PM IPC-04 DONE
NSPECTION for reinforcement for precast Box Culvert (3x3) (cushion upto 2m) for
785 NMSCEW/P-IV/STR/2019/763 763 BOX CULVERT Km 200+200 LHS 8-May-19 2:48 PM
(ch.200+286)at
Checking precast yard
for shuttering camp -2.
& Pouring of Segment
ConcretingNO-16
Grade =(M-30) for Precast Box Culvert
786 NMSCEW/P-IV/STR/2019/764 764 BOX CULVERT Km 200+200 LHS 8-May-19 4:08 PM
(3×3) (Cushion
Checking upto 2m) for
reinforcement for precast
(ch.200+286) at precast
Box Culvert (3x3)yard camp-2.Segment
(cushion 2 to 4m) for no.-16.
(ch.193+484)at
787 NMSCEW/P-IV/STR/2019/765 765 BOX CULVERT Km 200+200 LHS 8-May-19 10:12 AM NR SPOT RFI
precast yard
Checking forcamp -2. Segment
shuttering NO-05.
& Pouring of Concreting Grade =(M-30) for Precast Box Culvert
788 NMSCEW/P-IV/STR/2019/766 766 BOX CULVERT Km 200+200 LHS 8-May-19 11:32 AM NR SPOT RFI
(3×3) ,(Cushion 2 to 4m) for (ch.193+484) at precast yard camp-2,Segment no.-05.
789 NMSCEW/P-IV/STR/2019/767 767 Checking of reinforcement & shuttering 2nd lift for wall no. 2 PUP Km 205+430 Km 00+000 LHS 9-May-19 8:00 AM IPC-03 DONE AE
790 NMSCEW/P-IV/STR/2019/768 768 Checking level and pouring concrete(M30) 2nd lift for wall no. 2 PUP Km 205+430 Km 00+000 LHS 9-May-19 8:30 AM IPC-03 DONE
Checking for reinforcement for precast Box Culvert (3x3) (cushion upto 2m) for
791 NMSCEW/P-IV/STR/2019/769 769 Box Culvert Km 200+200 LHS 9-May-19 9:30 AM DONE
(ch.200+286)at
Checking precast yard
for shuttering camp -2.
& Pouring of Segment
ConcretingNO-16
Grade =(M-30) for Precast Box Culvert
792 NMSCEW/P-IV/STR/2019/770 770 Box Culvert Km 200+200 LHS 9-May-19 9:50 AM DONE
(3×3) (Cushion
Checking upto 2m) forfor
for reinforcement (ch.200+286) at precast
precast Box Culvert yard(cushion
(3x3) camp-2.Segment no.-16
2 to 4m) for
793 NMSCEW/P-IV/STR/2019/771 771 Box Culvert Km 200+200 LHS 9-May-19 10:20 AM DONE
(ch.193+484)at
Checking precast yard
for shuttering camp -2.
& Pouring of Segment
ConcretingNO-05
Grade =(M-30) for Precast Box Culvert
794 NMSCEW/P-IV/STR/2019/772 772 Box Culvert Km 200+200 LHS 9-May-19 10:40 AM DONE
(3×3) (Cushion 2 to 4m) for (ch.193+484) at precast yard camp-2.Segment no.-05
795 NMSCEW/P-IV/STR/2019/773 773 Checking level for excavated bed for at RP 5 VIADUCT Km 196+560 RHS 9-May-19 2:12 PM
796 NMSCEW/P-IV/STR/2019/774 774 Checking of Layout & Level for RP 5 VIADUCT Km 196+560 RHS 9-May-19 2:25 PM
797 NMSCEW/P-IV/STR/2019/775 775 Checking top Level & Laying concrete PCC for RP 5 VIADUCT Km 196+560 RHS 9-May-19 2:45 PM
798 NMSCEW/P-IV/STR/2019/776 776 Checking level for excavated bed for at RP 1 Viaduct Km 202+190 RHS 9-May-19 11:00 AM IPC-04 DONE AE
799 NMSCEW/P-IV/STR/2019/777 777 Checking of Layout & Level for RP 1 Viaduct Km 202+190 RHS 9-May-19 11:20 AM IPC-04 DONE AE
800 NMSCEW/P-IV/STR/2019/778 778 Checking top Level & Laying concrete PCC for RP 1 Viaduct Km 202+190 RHS 9-May-19 11:55 AM IPC-04 DONE AE
801 NMSCEW/P-IV/STR/2019/779 779 Checking level for excavated bed for at LP 10 Viaduct Km 169+800 LHS 9-May-19 3:00 PM IPC-04 DONE
802 NMSCEW/P-IV/STR/2019/780 780 Checking of Layout & Level for LP 10 Viaduct Km 169+800 LHS 9-May-19 3:20 PM IPC-04 DONE
803 NMSCEW/P-IV/STR/2019/781 781 Checking top Level & Laying concrete PCC for LP 10 Viaduct Km 169+800 LHS 9-May-19 3:45 PM IPC-04 DONE
804 NMSCEW/P-IV/STR/2019/782 782 Checking level for excavated bed for at LP 4 VIADUCT Km 200+920 LHS 9-May-19 4:15 PM IPC-08 DONE AE
805 NMSCEW/P-IV/STR/2019/783 783 Checking of Layout & Level for LP 4 VIADUCT Km 200+920 LHS 9-May-19 4:38 PM IPC-08 DONE AE
806 NMSCEW/P-IV/STR/2019/784 784 Checking top Level & Laying concrete PCC for LP 4 VIADUCT Km 200+920 LHS 9-May-19 4:50 PM IPC-08 DONE AE
807 NMSCEW/P-IV/STR/2019/785 785 Checking level for excavated bed for at LP 3 VIADUCT Km 200+920 LHS 9-May-19 5:08 PM IPC-08 DONE
808 NMSCEW/P-IV/STR/2019/786 786 Checking of Layout & Level for LP 3 VIADUCT Km 200+920 LHS 9-May-19 5:30 PM IPC-08 DONE
809 NMSCEW/P-IV/STR/2019/787 787 Checking top Level & Laying concrete PCC for LP 3 VIADUCT Km 200+920 LHS 9-May-19 10:38 AM IPC-08 DONE
810 NMSCEW/P-IV/STR/2019/788 788 Checking level for excavated bed for at RP 4 VIADUCT Km 200+920 RHS 9-May-19 10:46 AM IPC-08 DONE AE
811 NMSCEW/P-IV/STR/2019/789 789 Checking of Layout & Level for RP 4 VIADUCT Km 200+920 RHS 9-May-19 12:42 PM IPC-08 DONE AE
812 NMSCEW/P-IV/STR/2019/790 790 Checking top Level & Laying concrete PCC for RP 4 VIADUCT Km 200+920 RHS 9-May-19 2:33 PM IPC-08 DONE AE
Checkingfor reinforcement for precast Box Culvert (3x3) (cushion 2-4m) at precast yard camp
813 NMSCEW/P-IV/STR/2019/791 791 Box Culvert Km 175+500 LHS 9-May-19 2:48 PM DONE
-1 Segment
Checking forNO 31&32 & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
shuttering
814 NMSCEW/P-IV/STR/2019/792 792 Box Culvert Km 175+500 LHS 9-May-19 3:12 PM DONE
(3×3) (Cushion 2 to 4 m) at precast yard camp-1 Segment 31&32
815 NMSCEW/P-IV/STR/2019/793 793 Checking of reinforcement for precast Box culvert(2*2) (cushion-0to2m) segment no 1,2,3,4 Box Culvert Km 175+500 LHS 9-May-19 3:48 PM DONE
816 NMSCEW/P-IV/STR/2019/795 795 Checking level and pouring Concrete for first lift of A1 & A2 wall PUP Km 172+190 LHS 10-May-19 12:00 AM IPC-03 DONE
817 NMSCEW/P-IV/STR/2019/796 796 checking of A1 & A2 reinforcement and shuttering of bottom haunch. PUP Km 177+810 LHS 10-May-19 12:00 AM IPC-03 DONE
818 NMSCEW/P-IV/STR/2019/797 797 A1 & A2 bottom hauch pouring of concrete PUP Km 177+810 LHS 10-May-19 12:00 AM NR
Checking for reinforcement for precast Box Culvert (3x3) (cushion upto 2m) for
819 NMSCEW/P-IV/STR/2019/802 802 BOX CULVERT Km 200+286 BHS 10-May-19 10:50 AM DONE
(ch.200+286)at
Checking precast yard
for shuttering camp -2.
& Pouring of Segment
ConcretingNO-17
Grade&18.
=(M-30) for Precast Box Culvert
820 NMSCEW/P-IV/STR/2019/803 803 BOX CULVERT Km 200+286 BHS 10-May-19 11:10 AM DONE
(3×3) (Cushion
Checking upto 2m)&for
for shuttering (ch.200+286)
Pouring at precast
of Concreting Gradeyard camp-2.Segment
=(M-30) no.-17&18.
for Precast Box Culvert
821 NMSCEW/P-IV/STR/2019/804 804 BOX CULVERT Km 175+500 LHS 10-May-19 11:30 AM NR
(3×3) (Cushion 2 to 4 m) at precast yard camp-1 Segment 32
822 NMSCEW/P-IV/STR/2019/805 805 Checking of reinforcement, shuttering at precast yard camp-1 precast Box culvert (2*2) (cu BOX CULVERT Km 176+250 BHS 10-May-19 11:50 AM IPC-05 DONE
823 NMSCEW/P-IV/STR/2019/806 806 Checking level for excavated bed at LP 9 Viaduct Km 169+800 LHS 10-May-19 2:00 PM IPC-04 DONE
824 NMSCEW/P-IV/STR/2019/807 807 Checking of layout and level at LP 9 Viaduct Km 169+800 LHS 10-May-19 2:30 PM IPC-04 DONE
825 NMSCEW/P-IV/STR/2019/808 808 Checking top level and laying of concrete for PCC at LP 9 Viaduct Km 169+800 LHS 10-May-19 3:00 PM IPC-04 DONE
826 NMSCEW/P-IV/STR/2019/809 809 Checking of reinforcement and shuttering for LP 13 pier shaft starter VIADUCT Km 169+800 LHS 10-May-19 3:30 PM NR
827 NMSCEW/P-IV/STR/2019/810 810 Checking top level & Pouring concrete for LP13 pier saft starter VIADUCT Km 169+800 LHS 10-May-19 4:00 PM NR
828 NMSCEW/P-IV/STR/2019/811 811 Checking of reinforcement and shuttering for RP 4 for raft Viaduct Km 169+800 RHS 10-May-19 4:30 PM NR
829 NMSCEW/P-IV/STR/2019/812 812 Checking top level & Pouring concrete for RP 4 for raft Viaduct Km 169+800 RHS 10-May-19 5:00 PM NR
830 NMSCEW/P-IV/STR/2019/813 813 Checking of layout and level for RP (1st lift) pier VIADUCT Km 196+560 RHS 10-May-19 5:30 PM
831 NMSCEW/P-IV/STR/2019/814 814 Checking of reinforcement and shuttering for RP-09 (1st lift) pier VIADUCT Km 196+560 Km 00+000 RHS 10-May-19 6:00 PM IPC-09 DONE
832 NMSCEW/P-IV/STR/2019/815 815 Checking top level & Pouring concrete for RP-09 (1st lift) pier VIADUCT Km 196+560 Km 00+000 RHS 10-May-19 6:30 PM IPC-09 DONE
833 NMSCEW/P-IV/STR/2019/816 816 Checking level for excavated bed at RP 5 VIADUCT Km 196+560 RHS 10-May-19 11:05 AM
834 NMSCEW/P-IV/STR/2019/817 817 Checking of layout and level at RP 5 VIADUCT Km 196+560 RHS 10-May-19 11:33 AM
835 NMSCEW/P-IV/STR/2019/818 818 Checking top level and laying of concrete for PCC at RP 5 VIADUCT Km 196+560 RHS 10-May-19 11:45 AM
836 NMSCEW/P-IV/STR/2019/819 819 Checking level for excavated bed at RP 6 VIADUCT Km 195+900 RHS 10-May-19 3:02 PM
837 NMSCEW/P-IV/STR/2019/820 820 Checking of layout and level at RP 6 VIADUCT Km 195+900 RHS 10-May-19 3:33 PM
838 NMSCEW/P-IV/STR/2019/821 821 Checking top level and laying of concrete for PCC at RP 6 VIADUCT Km 195+900 RHS 10-May-19 3:58 PM
839 NMSCEW/P-IV/STR/2019/794 794 Checking for reinforcement & shuttering of first lift of A1 & A2wall PUP Km 172+190 LHS 11-May-19 12:00 AM IPC-03 DONE
840 NMSCEW/P-IV/STR/2019/798 798 Checking for reinforcement & shuttering of first lift of A1 wall PUP Km 171+110 RHS 11-May-19 12:00 AM IPC-03 DONE AE
841 NMSCEW/P-IV/STR/2019/799 799 Checking for reinforcement & shuttering of first lift of A2 wall PUP Km 171+110 RHS 11-May-19 12:00 AM IPC-03 DONE AE
842 NMSCEW/P-IV/STR/2019/800 800 Checking level and pouring Concrete for first lift of A1 wall PUP Km 171+110 RHS 11-May-19 12:00 AM IPC-03 DONE AE
843 NMSCEW/P-IV/STR/2019/801 801 Checking level and pouring Concrete for first lift of A2 wall PUP Km 171+110 RHS 11-May-19 12:00 AM IPC-03 DONE AE
844 NMSCEW/P-IV/STR/2019/822 822 Checking of reinforcement and shuttering for raft at LVUP LVUP Km 173+400 RHS 11-May-19 4:15 PM IPC-05 DONE AE
845 NMSCEW/P-IV/STR/2019/823 823 Checking top level and Pouring of concrete for raft at LVUP LVUP Km 173+400 RHS 11-May-19 4:36 PM IPC-05 DONE AE
846 NMSCEW/P-IV/STR/2019/824 824 Checking of reinforcement & shuttering 1st lift for wall no. 2 PUP Km 205+430 Km 00+000 RHS 11-May-19 11:00 AM IPC-03 DONE AE
847 NMSCEW/P-IV/STR/2019/825 825 Checking top level and Pouring of concrete 1st lift for wall no. 2 PUP Km 205+430 Km 00+000 RHS 11-May-19 12:00 PM IPC-03 DONE AE
848 NMSCEW/P-IV/STR/2019/826 826 Checking level for excavated bed for PUP PUP Km 199+060 RHS 11-May-19 9:00 AM IPC-04 DONE
849 NMSCEW/P-IV/STR/2019/827 827 Checking of layout and level for PUP PUP Km 199+060 RHS 11-May-19 9:30 AM IPC-04 DONE
850 NMSCEW/P-IV/STR/2019/828 828 Checking top Level & Laying concrete PCC for PUP PUP Km 199+060 RHS 11-May-19 10:00 AM IPC-04 DONE
851 NMSCEW/P-IV/STR/2019/829 829 checking of bottom slab reinforcement & shuttering for CUP CUP Km 185+235 LHS 11-May-19 4:30 PM NR
852 NMSCEW/P-IV/STR/2019/830 830 Checking top Level & Laying M30 bottom slab concrete pouring for CUP CUP Km 185+235 LHS 11-May-19 5:00 PM NR
853 NMSCEW/P-IV/STR/2019/831 831 checking of A1 & A2 reinforcement and shuttering of bottom haunch. PUP Km 188+575 LHS 11-May-19 12:00 AM IPC-03 DONE
854 NMSCEW/P-IV/STR/2019/832 832 A1 & A2 bottom hauch pouring of concrete PUP Km 188+575 LHS 11-May-19 12:00 AM IPC-03 DONE
checking for reinforcement for precast Box Culvert (2x2) (cushion 2-4m) at precast yard camp
855 NMSCEW/P-IV/STR/2019/833 833 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert Box Culvert Km 175+500 LHS 11-May-19 8:30 AM DONE
-1 Segment NO 1 & 2 And (cushion 0 to 2m) Segment NO 3 & 4
856 NMSCEW/P-IV/STR/2019/834 834 (2×2) (Cushion 2 to 4 m) at precast yard camp-1 Segment 1&2 And (cushion 0 to 2m) Box Culvert Km 175+500 LHS 11-May-19 9:30 AM NR
857 NMSCEW/P-IV/STR/2019/835 835 Segment NO 3 & 4
Checking of reinforcement and shuttering for raft at LP5 VIADUCT Km 196+560 LHS 11-May-19 3:00 PM
858 NMSCEW/P-IV/STR/2019/836 836 Checking top level and Pouring of concrete for raft at LP5 VIADUCT Km 196+560 LHS 11-May-19 4:30 PM
859 NMSCEW/P-IV/STR/2019/837 837 Checking level for excavated bed for at LP 2 Viaduct Km 169+800 LHS 11-May-19 2:00 PM NR
860 NMSCEW/P-IV/STR/2019/838 838 Checking of Layout & Level for LP 2 Viaduct Km 169+800 LHS 11-May-19 2:30 PM NR
861 NMSCEW/P-IV/STR/2019/839 839 Checking top Level & Laying concrete PCC for LP 2 Viaduct Km 169+800 LHS 11-May-19 3:58 PM NR
862 NMSCEW/P-IV/STR/2019/840 840 Checking of reinforcement and shuttering for raft at RP 4 Viaduct Km 169+800 RHS 11-May-19 9:00 AM NR
863 NMSCEW/P-IV/STR/2019/841 841 Checking top level and Pouring of concrete for raft at RP 4 Viaduct Km 169+800 RHS 11-May-19 11:32 AM NR
864 NMSCEW/P-IV/STR/2019/834/B 834/B Checking for shuttering & Pouring of Concreting Grade (M-30) for Precast Box Culvert (2×2 Box Culvert Km 176+250 BHS 11-May-19 9:30 AM IPC-05 DONE
865 NMSCEW/P-IV/STR/2019/842 842 checking of bottom haunch reinforcement & shuttering PUP Km 177+810 LHS 12-May-19 8:50 AM NR
866 NMSCEW/P-IV/STR/2019/843 843 A1 & A2 bottom hauch pouring of concrete PUP Km 177+810 LHS 12-May-19 12:00 AM IPC-03 DONE
867 NMSCEW/P-IV/STR/2019/844 844 Checking of reinforcement & shuttering 1st lift for wall no. 1 PUP Km 205+430 Km 00+000 RHS 12-May-19 9:30 AM IPC-03 DONE AE
868 NMSCEW/P-IV/STR/2019/845 845 Checking top level and Pouring of concrete 1st lift for wall no. 1 PUP Km 205+430 Km 00+000 RHS 12-May-19 10:40 AM IPC-03 DONE AE
Checking of reinforcement for Precast Box Culvert (2×2) at precast yard camp-1Segment
869 NMSCEW/P-IV/STR/2019/846 846 BOX CULVERT Km 175+500 LHS 12-May-19 11:40 AM
-1,2,3 (cushion
Checking 2-4m) And
of shuttering and segment-5, 6 (cushion
pouring of concrete 1-2m) =(M-30) at precast yard camp-1
forGrade
870 NMSCEW/P-IV/STR/2019/847 847 BOX CULVERT Km 175+500 LHS 12-May-19 2:30 PM
precast Box culvert (2*2)Segment -1,2,3(cushion 2-4m) And segment-5, 6 (cushion 1-2m)
871 NMSCEW/P-IV/STR/2019/848 848 Checking of Layout & Level for LP 2 Viaduct Km 169+800 LHS 12-May-19 3:00 PM NR
872 NMSCEW/P-IV/STR/2019/849 849 Checking level for excavated bed for at LP 2 Viaduct Km 169+800 LHS 12-May-19 3:30 PM NR
873 NMSCEW/P-IV/STR/2019/850 850 Checking top Level & Laying concrete PCC for LP 2 Viaduct Km 169+800 LHS 12-May-19 3:50 PM NR
874 NMSCEW/P-IV/STR/2019/851 851 Checking of reinforcement and shuttering for raft at RP 4 Viaduct Km 169+800 RHS 12-May-19 4:20 PM NR
875 NMSCEW/P-IV/STR/2019/852 852 Checking top level and Pouring of concrete for raft at RP 4 Viaduct Km 169+800 RHS 12-May-19 4:40 PM NR
876 NMSCEW/P-IV/STR/2019/846/A 846/A Checking of reinforcement for Precast Box Culvert (2×2) at precast yard camp-1Segment -5, BOX CULVERT Km 163+830 BHS 12-May-19 11:40 AM IPC-05 DONE
877 NMSCEW/P-IV/STR/2019/847/A 847/A Checking of shuttering and pouring of concrete forGrade =(M-30) at precast yard camp-1 prec BOX CULVERT Km 163+830 BHS 12-May-19 2:30 PM IPC-05 DONE
878 NMSCEW/P-IV/STR/2019/853 853 Checking of reinforcement and shuttering for raft at PUP PUP Km 174+095 LHS 13-May-19 4:28 PM NR
879 NMSCEW/P-IV/STR/2019/854 854 Checking top level and Pouring of concrete for raft at PUP PUP Km 174+095 LHS 13-May-19 5:36 PM NR
880 NMSCEW/P-IV/STR/2019/855 855 Checking of reinforcement and shuttering for raft at PUP PUP Km 204+470 Km 00+000 LHS 13-May-19 12:10 PM IPC-03 DONE
881 NMSCEW/P-IV/STR/2019/856 856 Checking top level and Pouring of concrete for raft at PUP PUP Km 204+470 Km 00+000 LHS 13-May-19 2:02 PM IPC-03 DONE
882 NMSCEW/P-IV/STR/2019/857 857 Checking of reinforcement and shuttering for raft at LP 5 Viaduct Km 196+560 LHS 13-May-19 12:45 PM IPC-04 DONE
883 NMSCEW/P-IV/STR/2019/858 858 Checking top level and Pouring of concrete for raft at LP 5 Viaduct Km 196+560 LHS 13-May-19 2:05 PM IPC-04 DONE
884 NMSCEW/P-IV/STR/2019/859 859 Checking of Layout & Level for RP 5 VIADUCT Km 196+560 RHS 13-May-19 2:32 PM
885 NMSCEW/P-IV/STR/2019/860 860 Checking level for excavated bed for RP 5 VIADUCT Km 196+560 RHS 13-May-19 2:40 PM
886 NMSCEW/P-IV/STR/2019/861 861 Checking top Level & Laying concrete PCC for RP 5 VIADUCT Km 196+560 RHS 13-May-19 2:58 PM
887 NMSCEW/P-IV/STR/2019/862 862 Checking of Layout & Level for LP 4 VIADUCT Km 195+900 LHS 13-May-19 10:01 AM
888 NMSCEW/P-IV/STR/2019/863 863 Checking level for excavated bed for LP 4 VIADUCT Km 195+900 LHS 13-May-19 10:21 AM
889 NMSCEW/P-IV/STR/2019/864 864 Checking top Level & Laying concrete PCC for LP 4 VIADUCT Km 195+900 LHS 13-May-19 10:38 AM
890 NMSCEW/P-IV/STR/2019/865 865 Checking of Layout & Level for RP 3 VIADUCT Km 200+920 RHS 13-May-19 10:50 AM IPC-08 DONE AE
891 NMSCEW/P-IV/STR/2019/866 866 Checking level for excavated bed for RP 3 VIADUCT Km 200+920 RHS 13-May-19 11:20 AM IPC-08 DONE AE
892 NMSCEW/P-IV/STR/2019/867 867 Checking top Level & Laying concrete PCC for RP 3 VIADUCT Km 200+920 RHS 13-May-19 11:40 AM IPC-08 DONE AE
893 NMSCEW/P-IV/STR/2019/868 868 Checking of Layout & Level for LP 2 VIADUCT Km 200+920 LHS 13-May-19 11:57 AM
894 NMSCEW/P-IV/STR/2019/869 869 Checking level for excavated bed for LP 2 VIADUCT Km 200+920 LHS 13-May-19 12:12 PM
895 NMSCEW/P-IV/STR/2019/870 870 Checking top Level & Laying concrete PCC for LP 2 VIADUCT Km 200+920 LHS 13-May-19 2:18 PM
896 NMSCEW/P-IV/STR/2019/871 871 Checking of Layout & Level for LP 5 Viaduct Km 202+190 LHS 13-May-19 9:18 AM IPC-04 DONE AE
897 NMSCEW/P-IV/STR/2019/872 872 Checking level for excavated bed for LP 5 Viaduct Km 202+190 LHS 13-May-19 9:32 AM IPC-04 DONE AE
898 NMSCEW/P-IV/STR/2019/873 873 Checking top Level & Laying concrete PCC for LP 5 Viaduct Km 202+190 LHS 13-May-19 9:50 AM IPC-04 DONE AE
899 NMSCEW/P-IV/STR/2019/874 874 Checking of Layout & Level for RP 5 Viaduct Km 202+190 RHS 13-May-19 10:26 AM IPC-04 DONE
900 NMSCEW/P-IV/STR/2019/875 875 Checking level for excavated bed for RP 5 Viaduct Km 202+190 RHS 13-May-19 10:47 AM IPC-04 DONE
901 NMSCEW/P-IV/STR/2019/876 876 Checking top Level & Laying concrete PCC for RP 5 Viaduct Km 202+190 RHS 13-May-19 11:11 AM IPC-04 DONE AE
902 NMSCEW/P-IV/STR/2019/877 877 Checking of Layout & Level for LP 1 VIADUCT Km 169+800 LHS 13-May-19 2:08 PM NR
903 NMSCEW/P-IV/STR/2019/878 878 Checking level for excavated bed for LP 1 VIADUCT Km 169+800 LHS 13-May-19 2:22 PM NR
904 NMSCEW/P-IV/STR/2019/879 879 Checking top Level & Laying concrete PCC for LP 1 VIADUCT Km 169+800 LHS 13-May-19 3:23 PM NR
905 NMSCEW/P-IV/STR/2019/880 880 Checking of reinforcement and shuttering at LP 13 for pier shaft starter VIADUCT Km 169+800 Km 00+000 LHS 13-May-19 5:03 PM IPC-09 DONE
906 NMSCEW/P-IV/STR/2019/881 881 Checking of reinforcement and shuttering at RP 3 for pier shaft starter VIADUCT Km 169+800 Km 00+000 RHS 13-May-19 5:38 PM IPC-09 DONE
907 NMSCEW/P-IV/STR/2019/882 882 Checking top level & Laying concrete at LP 13 for pier shaft starter VIADUCT Km 169+800 Km 00+000 LHS 13-May-19 6:18 PM IPC-09 DONE
908 NMSCEW/P-IV/STR/2019/883 883 Checking top level & Laying concrete at RP 3 for pier shaft starter VIADUCT Km 169+800 Km 00+000 RHS 13-May-19 6:38 PM IPC-09 DONE
909 NMSCEW/P-IV/STR/2019/884 884 Checking of Layout & Level for LP 2 Viaduct Km 169+800 LHS 13-May-19 6:50 PM IPC-04 DONE
910 NMSCEW/P-IV/STR/2019/885 885 Checking level for excavated bed for LP 2 Viaduct Km 169+800 LHS 13-May-19 7:20 PM IPC-04 DONE
911 NMSCEW/P-IV/STR/2019/886 886 Checking top Level & Laying concrete PCC for LP 2 Viaduct Km 169+800 LHS 13-May-19 7:35 PM IPC-04 DONE
Checking for
Checking reinforcement
shuttering &for precastofBox
Pouring Culvert (3x3)
Concreting Grade(cushion
=(M-30)upto 2m) forBox
for Precast (ch.200+286)at
Culvert
912 NMSCEW/P-IV/STR/2019/887 887 Box culvert Km 200+200 LHS 13-May-19 2:30 PM DONE
precast yard camp -2. Segment NO-19&20.
(3×3)
913 NMSCEW/P-IV/STR/2019/888 888 Box culvert Km 200+200 LHS 13-May-19 2:50 PM DONE
(Cushion upto
Checking for 2m) for
reinforcement (ch.200+286)
forPouring
precastof
Boxat precast yard
Culvert (3x3) camp-2.
914 NMSCEW/P-IV/STR/2019/889 889 Checking
Segment shuttering &
no.-19&20. Concreting Grade(cushion
=(M-30)2 for
to 4m) for (ch.193+484)at
Precast Box Culvert Box culvert Km 200+200 LHS 13-May-19 3:30 PM DONE
precast yard
(3×3) camp -2. Segment NO-06.
915 NMSCEW/P-IV/STR/2019/890 890 Box culvert Km 200+200 LHS 13-May-19 4:22 PM DONE
(Cushion 2 to 4m) for (ch.193+484) at precast yard camp-2.
916 NMSCEW/P-IV/STR/2019/891 891 Checkingno.-06.
Segment of reinforcement and shuttering for raft & bottom haunch at CUP CUP Km 185+235 LHS 13-May-19 10:30 AM IPC-04 DONE
917 NMSCEW/P-IV/STR/2019/892 892 Checking top level and Pouring of concrete (M30) for raft & bottom haunch at CUP CUP Km 185+235 LHS 13-May-19 11:00 AM IPC-04 DONE
918 NMSCEW/P-IV/STR/2019/893 893 Checking of reinforcement and shuttering for raft at CUP CUP Km 177+810 RHS 13-May-19 11:30 AM IPC-04 DONE
919 NMSCEW/P-IV/STR/2019/894 894 Checking top level and Pouring of concrete (M30) for raft at CUP CUP Km 177+810 RHS 13-May-19 4:30 PM IPC-04 DONE
920 NMSCEW/P-IV/STR/2019/895 895 Checking of Layout & Level Box Culvert Km 192+039 BHS 14-May-19 9:00 AM DONE
921 NMSCEW/P-IV/STR/2019/896 896 Checking level for excavated bed Box Culvert Km 192+039 BHS 14-May-19 10:00 AM DONE
922 NMSCEW/P-IV/STR/2019/897 897 Checking top Level & Laying concrete PCC Box Culvert Km 192+039 BHS 14-May-19 11:00 AM DONE
923 NMSCEW/P-IV/STR/2019/898 898 checking of bottom haunch reinforcement & shuttering A1 & A2 LVUP Km 173+400 LHS 14-May-19 11:30 AM NR
924 NMSCEW/P-IV/STR/2019/899 899 Checking top Level & Laying M30 bottom haunch concrete pouring A1 & A2 LVUP Km 173+400 LHS 14-May-19 4:30 PM NR
Checking reinforcement for precast Box Culvert (3x3) (cushion 2 to 4m) for (ch.193+484)at
925 NMSCEW/P-IV/STR/2019/900 900 Box Culvert Km 200+200 LHS 14-May-19 3:00 PM NR
precast yard
Checking forcamp -2. Segment
shuttering NO-07
& Pouring & 08.
of Concreting Grade =(M-30) for Precast Box Culvert
926 NMSCEW/P-IV/STR/2019/901 901 Box Culvert Km 200+200 LHS 14-May-19 3:30 PM NR
(3×3) ,(Cushion 2 to 4m) for (ch.193+484) at precast yard camp-2.,Segment no.-07 & 08.
927 NMSCEW/P-IV/STR/2019/902 902 Checking reinforcement, shuttering for final lift at wall A1 & A2 PUP Km 184+190 LHS 14-May-19 12:00 AM IPC-03 DONE
928 NMSCEW/P-IV/STR/2019/903 903 Checking concrete pouring. for final lift at wall A1 & A2 PUP Km 184+190 LHS 14-May-19 12:00 AM IPC-03 DONE
929 NMSCEW/P-IV/STR/2019/904 904 Checking of reinforcement & shuttering for 2nd lift for A1 & A2 wall CUP Km 184+190 RHS 14-May-19 5:00 PM NR
930 NMSCEW/P-IV/STR/2019/905 905 Checking level and pouring concrete(M30) for 2nd lift for A1 & A2 wall CUP Km 184+190 RHS 14-May-19 5:30 PM NR
Checking of reinforcement for Precast Box Culvert (2×2) at precast yard camp-1,Segment
931 NMSCEW/P-IV/STR/2019/906 906 Box Culvert Km 175+000 LHS 14-May-19 4:00 PM IPC-08 DONE AE 3, 4, 5
-3,4,5(cushion
Checking 2-4m) and pouring of concrete forGrade =(M-30) at precast yard camp-1
of shuttering
932 NMSCEW/P-IV/STR/2019/907 907 Box Culvert Km 175+000 LHS 14-May-19 4:45 PM IPC-08 DONE AE 3, 4, 5
precast Box culvert (2*2)Segment -3,4,5(cushion 2-4m
933 NMSCEW/P-IV/STR/2019/908 908 Checking of Layout & Level at LP1 Viaduct Km 169+800 LHS 14-May-19 2:00 PM NR
934 NMSCEW/P-IV/STR/2019/909 909 Checking level for excavated bed at LP1 Viaduct Km 169+800 LHS 14-May-19 2:20 PM NR
935 NMSCEW/P-IV/STR/2019/910 910 Checking top Level & Laying concrete PCC at LP1 Viaduct Km 169+800 LHS 14-May-19 3:02 PM NR
936 NMSCEW/P-IV/STR/2019/911 911 checking of bottom haunch reinforcement & shuttering A1 & A2 LVUP Km 173+400 LHS 15-May-19 11:30 AM NR
937 NMSCEW/P-IV/STR/2019/912 912 Checking top Level & Laying M30 bottom haunch concrete pouring A1 & A2 LVUP Km 173+400 LHS 15-May-19 4:30 PM NR
938 NMSCEW/P-IV/STR/2019/913 913 Checking of reinforcement and shuttering for raft at PUP PUP Km 174+095 LHS 15-May-19 4:00 PM IPC-04 DONE
939 NMSCEW/P-IV/STR/2019/914 914 Checking top level and Pouring of concrete (M30) for raft at PUP PUP Km 174+095 LHS 15-May-19 5:00 PM IPC-04 DONE
940 NMSCEW/P-IV/STR/2019/915 915 Checking for reinforcement & shuttering of first lift of A1 &A2 wall PUP Km 177+810 LHS 15-May-19 12:00 AM NR
941 NMSCEW/P-IV/STR/2019/916 916 Checking level and pouring concrete(M30) for 1st lift for A1 & A2 wall PUP Km 177+810 LHS 15-May-19 5:30 PM NR
Checking reinforcement for precast Box Culvert (3x3) (cushion 2 to 4m) for (ch.193+484)at
942 NMSCEW/P-IV/STR/2019/917 917 Box culvert Km 200+200 LHS 15-May-19 3:15 PM DONE
precast
Checkingyard
forcamp -2. Segment
shuttering & Pouring NO-07 & 08.
of Concreting Grade =(M-30) for Precast Box Culvert
943 NMSCEW/P-IV/STR/2019/918 918 Box culvert Km 200+200 LHS 15-May-19 3:30 PM DONE
(3×3) ,(Cushion 2 to 4m) for (ch.193+484) at precast yard camp-2,Segment no.-07 & 08.
944 NMSCEW/P-IV/STR/2019/919 919 Checking of reinforcement & shuttering for 2nd lift for W2 wall PUP Km 205+430 Km 00+000 RHS 15-May-19 9:00 AM IPC-03 DONE AE
945 NMSCEW/P-IV/STR/2019/920 920 Checking reinforcement
Checking level and pouring concrete(M30)
for precast Box Culvertfor 2nd(cushion
(2x2) lift for 2W2 wall for (ch.188+390)at
to 4m) PUP Km 205+430 Km 00+000 RHS 15-May-19 10:00 AM IPC-03 DONE AE
946 NMSCEW/P-IV/STR/2019/921 921 precast yard camp -2. Segment NO-02 & 03. Box culvert Km 200+200 LHS 15-May-19 3:40 PM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
947 NMSCEW/P-IV/STR/2019/922 922 Box culvert Km 200+200 LHS 15-May-19 3:50 PM DONE
(2×2) ,(Cushion 2 to 4m) for (ch.188+390) at precast yard camp-2.,Segment
Checking of reinforcement for Precast Box Culvert (2×2) at precast yard camp-1 no.-02 & 03. 2-
,(cushion
948 NMSCEW/P-IV/STR/2019/923 923 Box culvert Km 175+500 LHS 15-May-19 2:20 PM IPC-08 DONE AE 6, 7, 8
4m) And segment-6,7,8
Checking of shuttering and pouring of concrete forGrade =(M-30) at precast yard camp-1 for
949 NMSCEW/P-IV/STR/2019/924 924 Box culvert Km 175+500 LHS 15-May-19 3:35 PM DONE
precast Box culvert (2*2) (cushion 2-4m) And segment- 6,7
950 NMSCEW/P-IV/STR/2019/925 925 Checking of reinforcement for Precast Box Culvert (2×2) at precast yard camp-1 ,(cushion Box culvert Km 163+830 BHS 15-May-19 4:46 PM IPC-05 DONE
951 NMSCEW/P-IV/STR/2019/926 926 Checking of shuttering and pouring of concrete forGrade =(M-30) at precast yard camp-1 for Box culvert Km 163+830 BHS 15-May-19 5:22 PM IPC-05 DONE AE
952 NMSCEW/P-IV/STR/2019/927 927 Checking of Layout & Level for LP 4 VIADUCT Km 195+900 LHS 15-May-19 10:00 AM
953 NMSCEW/P-IV/STR/2019/928 928 Checking level for excavated bed for at LP 4 VIADUCT Km 195+900 LHS 15-May-19 10:30 AM
954 NMSCEW/P-IV/STR/2019/929 929 Checking top Level & Laying concrete PCC for LP 4 VIADUCT Km 195+900 LHS 15-May-19 10:45 AM
955 NMSCEW/P-IV/STR/2019/930 930 Checking of reinforcement and shuttering for raft at LP5 VIADUCT Km 195+900 LHS 15-May-19 11:00 AM
956 NMSCEW/P-IV/STR/2019/931 931 Checking top level and Pouring of concrete (M30) for raft at LP5 VIADUCT Km 195+900 LHS 15-May-19 12:00 PM
957 NMSCEW/P-IV/STR/2019/932 932 Checking of Layout & Level for LP 1 VIADUCT Km 169+800 LHS 15-May-19 2:00 PM NR
958 NMSCEW/P-IV/STR/2019/933 933 Checking level for excavated bed for at LP 1 VIADUCT Km 169+800 LHS 15-May-19 2:15 PM NR
959 NMSCEW/P-IV/STR/2019/934 934 Checking top Level & Laying concrete PCC for LP 1 VIADUCT Km 169+800 LHS 15-May-19 3:00 PM NR
960 NMSCEW/P-IV/STR/2019/935 935 Checking of reinforcement and shuttering for raft at RP5 VIADUCT Km 169+800 RHS 15-May-19 9:30 AM NR
961 NMSCEW/P-IV/STR/2019/936 936 Checking top level and Pouring of concrete (M30) for raft at RP5 VIADUCT Km 169+800 RHS 15-May-19 10:00 AM NR
962 NMSCEW/P-IV/STR/2019/937 937 Checking for reinforcement & shuttering of first lift of A1 &A2 wall PUP Km 177+810 LHS 16-May-19 12:00 AM IPC-03 DONE
963 NMSCEW/P-IV/STR/2019/938 938 Checking level and pouring Concrete for first lift of A1 &A2 wall PUP Km 177+810 LHS 16-May-19 12:00 AM IPC-03 DONE
964 NMSCEW/P-IV/STR/2019/939 939 Checking of reinforcement and shuttering for raft at PUP PUP Km 171+110 LHS 16-May-19 11:30 AM IPC-04 DONE
965 NMSCEW/P-IV/STR/2019/940 940 Checking top level and Pouring of concrete (M30) for raft at PUP PUP Km 171+110 LHS 16-May-19 4:30 PM IPC-04 DONE
Checking for reinforcement for precast Box Culvert (3x3) (cushion 2 to 4m) for
966 NMSCEW/P-IV/STR/2019/941 941 BOX CULVERT Km 200+200 LHS 16-May-19 9:25 AM DONE
(ch.193+484)at
Checking precast yard
for shuttering camp -2.
& Pouring of Segment
ConcretingNO-09.
Grade =(M-30) for Precast Box Culvert
967 NMSCEW/P-IV/STR/2019/942 942 BOX CULVERT Km 200+200 LHS 16-May-19 10:55 AM DONE
(3×3) (Cushion 2 to 4m) for (ch.193+484) at precast yard camp-2 Segment no.-09.
968 NMSCEW/P-IV/STR/2019/943 943 Checking of Layout & Level for LP 4 VIADUCT Km 195+900 LHS 16-May-19 2:02 PM IPC-08 DONE AE
969 NMSCEW/P-IV/STR/2019/944 944 Checking level for excavated bed for at LP 4 VIADUCT Km 195+900 LHS 16-May-19 2:30 PM IPC-08 DONE
970 NMSCEW/P-IV/STR/2019/945 945 Checking top Level & Laying concrete PCC for LP 4 VIADUCT Km 195+900 LHS 16-May-19 3:00 PM IPC-08 DONE AE
971 NMSCEW/P-IV/STR/2019/946 946 Checking of reinforcement & shuttering for 2nd lift for A1 & A2 wall CUP Km 184+190 RHS 16-May-19 9:30 AM NR
972 NMSCEW/P-IV/STR/2019/947 947 Checking level and pouring concrete(M30) for 2nd lift for A1 & A2 wall CUP Km 184+190 RHS 16-May-19 10:15 AM NR
973 NMSCEW/P-IV/STR/2019/948 948 Checking for reinforcement & shuttering of first lift of A1 &A2 wall PUP Km 188+575 LHS 16-May-19 12:00 AM IPC-03 DONE
974 NMSCEW/P-IV/STR/2019/949 949 Checking level and pouring Concrete for first lift of A1 &A2 wall PUP Km 188+575 LHS 16-May-19 12:00 AM IPC-03 DONE
Checking of reinforcement for Precast Box Culvert (2×2) at precast yard camp-1 ,(cushion 2-
975 NMSCEW/P-IV/STR/2019/950 950 Box culvert Km 175+500 LHS 16-May-19 3:10 PM DONE
4m) And segment-9
Checking & 10
of shuttering and pouring of concrete forGrade =(M-30) at precast yard camp-1 for
976 NMSCEW/P-IV/STR/2019/951 951 Box culvert Km 175+500 LHS 16-May-19 3:30 PM IPC-08 DONE AE 8
precast Box culvert (2*2) (cushion 2-4m) And segment- 7 & 8
977 NMSCEW/P-IV/STR/2019/952 952 Checking of reinforcement for Precast Box Culvert (2×2) at precast yard camp-1 ,(cushion 0 Box culvert Km 163+830 BHS 16-May-19 3:58 PM IPC-05 DONE
978 NMSCEW/P-IV/STR/2019/953 953 Checking of shuttering and pouring of concrete forGrade =(M-30) at precast yard camp-1 for Box culvert Km 163+830 BHS 16-May-19 4:20 PM IPC-05 DONE
979 NMSCEW/P-IV/STR/2019/954 954 Checking of layout & level at LP-01 Viaduct Km 169+800 LHS 16-May-19 12:00 AM IPC-03 DONE
980 NMSCEW/P-IV/STR/2019/955 955 Checking level for excavated bed for at LP-01 Viaduct Km 169+800 LHS 16-May-19 12:00 AM IPC-03 DONE
981 NMSCEW/P-IV/STR/2019/956 956 Checking top Level & Laying concrete PCC for LP-01 Viaduct Km 169+800 LHS 16-May-19 12:00 AM IPC-03 DONE
982 NMSCEW/P-IV/STR/2019/957 957 Checking of Layout & Level for LP 7 Viaduct Km 202+190 LHS 16-May-19 11:00 AM IPC-04 DONE
983 NMSCEW/P-IV/STR/2019/958 958 Checking level for excavated bed for at LP 7 Viaduct Km 202+190 LHS 16-May-19 11:20 AM IPC-04 DONE
984 NMSCEW/P-IV/STR/2019/959 959 Checking top Level & Laying concrete PCC for LP 7 Viaduct Km 202+190 LHS 16-May-19 11:38 AM IPC-04 DONE AE
985 NMSCEW/P-IV/STR/2019/960 960 Checking of Layout & Level for PUP PUP Km 203+560 LHS 17-May-19 10:00 AM IPC-04 DONE AE
986 NMSCEW/P-IV/STR/2019/961 961 Checking level for excavated bed for at PUP PUP Km 203+560 LHS 17-May-19 10:10 AM IPC-04 DONE AE
987 NMSCEW/P-IV/STR/2019/962 962 Checking top Level & Laying concrete PCC for PUP PUP Km 203+560 LHS 17-May-19 10:35 AM IPC-04 DONE AE
988 NMSCEW/P-IV/STR/2019/963 963 Checking of reinforcement & shuttering 2ndt lift for wall no. 1 PUP Km 205+430 Km 00+000 RHS 17-May-19 11:00 AM IPC-03 DONE AE
989 NMSCEW/P-IV/STR/2019/964 964 Checking top level and Pouring of concrete 2nd lift for wall no. 1 PUP Km 205+430 Km 00+000 RHS 17-May-19 2:00 PM IPC-03 DONE AE
990 NMSCEW/P-IV/STR/2019/965 965 Checking for reinforcement & shuttering of second lift of A1 wall PUP Km 171+110 RHS 17-May-19 12:00 AM IPC-03 DONE
991 NMSCEW/P-IV/STR/2019/966 966 Checking for reinforcement & shuttering of second lift of A2 wall PUP Km 171+110 RHS 17-May-19 12:00 AM IPC-03 DONE
992 NMSCEW/P-IV/STR/2019/967 967 Checking Top level and pouring concrete second lift for wall A1 PUP Km 171+110 RHS 17-May-19 12:00 AM IPC-03 DONE
993 NMSCEW/P-IV/STR/2019/968 968 Checking level and pouring Concrete for second lift of A2 wall PUP Km 171+110 RHS 17-May-19 12:00 AM IPC-03 DONE
994 NMSCEW/P-IV/STR/2019/969 969 Checking for reinforcement & shuttering of first lift of A1 wall PUP Km 172+190 RHS 17-May-19 12:00 AM IPC-03 DONE
995 NMSCEW/P-IV/STR/2019/970 970 Checking for reinforcement & shuttering of first lift of A2 wall PUP Km 172+190 RHS 17-May-19 12:00 AM IPC-03 DONE
996 NMSCEW/P-IV/STR/2019/971 971 Checking level and pouring Concrete for first lift of A1 wall PUP Km 172+190 RHS 17-May-19 12:00 AM IPC-03 DONE
997 NMSCEW/P-IV/STR/2019/972 972 Checking level and pouring Concrete for first lift of A2 wall PUP Km 172+190 RHS 17-May-19 12:00 AM IPC-03 DONE
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
998 NMSCEW/P-IV/STR/2019/973 973 BOX CULVERT Km 200+200 LHS 17-May-19 5:08 PM NR
-2. Segment
Checking for NO-04 & 05
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
999 NMSCEW/P-IV/STR/2019/974 974 BOX CULVERT Km 200+200 LHS 17-May-19 5:39 PM NR
(2×2) ,(Cushion 2 to 4m) at precast yard camp-2,Segment no.-04 & 05.
1000 NMSCEW/P-IV/STR/2019/975 975 Checking of Layout & Level for RP 2 Viaduct Km 169+800 RHS 17-May-19 4:00 PM NR
1001 NMSCEW/P-IV/STR/2019/976 976 Checking level for excavated bed for at RP 2 Viaduct Km 169+800 RHS 17-May-19 4:15 PM NR
1002 NMSCEW/P-IV/STR/2019/977 977 Checking top Level & Laying concrete PCC for RP 2 Viaduct Km 169+800 RHS 17-May-19 5:00 PM NR
Checking of reinforcement for Precast Box Culvert (2×2) at precast yard camp-1 ,(cushion 2-
1003 NMSCEW/P-IV/STR/2019/978 978 Box culvert Km 175+500 LHS 17-May-19 9:00 AM IPC-08 DONE AE 9, 10, 11
4m) And segment-9,10
Checking & 11pouring of concrete forGrade =(M-30) at precast yard camp-1 for
of shuttering and
1004 NMSCEW/P-IV/STR/2019/979 979 Box culvert Km 175+500 LHS 17-May-19 9:40 AM IPC-08 DONE AE 9, 10
precast Box culvert (2*2) (cushion 2-4m) And segment- 9,10 & 11
1005 NMSCEW/P-IV/STR/2019/980 980 Checking of reinforcement for Precast Box Culvert (2×2) at precast yard camp-1 ,(cushion Box culvert Km 163+830 BHS 17-May-19 10:18 AM IPC-05 DONE AE
1006 NMSCEW/P-IV/STR/2019/981 981 Checking of shuttering and pouring of concrete forGrade =(M-30) at precast yard camp-1 for Box culvert Km 163+830 BHS 17-May-19 11:22 AM IPC-05 DONE AE
1007 NMSCEW/P-IV/STR/2019/982 982 Checking of reinforcement and shuttering for raft at LP5 VIADUCT Km 195+900 LHS 17-May-19 2:00 PM
1008 NMSCEW/P-IV/STR/2019/983 983 Checking top level and Pouring of concrete (M30) for raft at LP5 VIADUCT Km 195+900 LHS 17-May-19 2:28 PM
1009 NMSCEW/P-IV/STR/2019/984 984 Checking of Layout & Level for LP 2 VIADUCT Km 200+920 LHS 17-May-19 2:32 PM IPC-08 DONE
1010 NMSCEW/P-IV/STR/2019/985 985 Checking level for excavated bed for at LP 2 VIADUCT Km 200+920 LHS 17-May-19 2:40 PM IPC-08 DONE
1011 NMSCEW/P-IV/STR/2019/986 986 Checking top Level & Laying concrete PCC for LP 2 VIADUCT Km 200+920 LHS 17-May-19 3:22 PM IPC-08 DONE
1012 NMSCEW/P-IV/STR/2019/987 987 Checking of Layout & Level for LP 5 VIADUCT Km 200+920 LHS 17-May-19 8:00 AM
1013 NMSCEW/P-IV/STR/2019/988 988 Checking level for excavated bed for at LP 5 VIADUCT Km 200+920 LHS 17-May-19 8:15 AM
1014 NMSCEW/P-IV/STR/2019/989 989 Checking top Level & Laying concrete PCC for LP 5 VIADUCT Km 200+920 LHS 17-May-19 8:42 AM
1015 NMSCEW/P-IV/STR/2019/990 990 Checking of Layout & Level for LP 6 VIADUCT Km 196+560 LHS 17-May-19 12:08 PM IPC-08 DONE
1016 NMSCEW/P-IV/STR/2019/991 991 Checking level for excavated bed for at LP 6 VIADUCT Km 196+560 LHS 17-May-19 12:31 PM IPC-08 DONE
1017 NMSCEW/P-IV/STR/2019/992 992 Checking top Level & Laying concrete PCC for LP 6 VIADUCT Km 196+560 LHS 17-May-19 12:55 PM IPC-08 DONE
Checking for reinforcement for precast Box Culvert (3x3) (cushion 2 to 4m) at precast yard
1018 NMSCEW/P-IV/STR/2019/993 993 BOX CULVERT Km 200+200 LHS 17-May-19 3:00 PM SPOT RFI
camp -2. Segment
Checking NO-10,11.
for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1019 NMSCEW/P-IV/STR/2019/994 994 BOX CULVERT Km 200+200 LHS 17-May-19 3:00 PM SPOT RFI
(3×3) (Cushion 2 to 4m) at precast yard camp-2. Segment no.-10,11.
1020 NMSCEW/P-IV/STR/2019/995 995 Checking of reinforcement and shuttering for raft at PUP PUP Km 204+470 Km 00+000 RHS 18-May-19 8:00 AM IPC-03 DONE
1021 NMSCEW/P-IV/STR/2019/996 996 Checking top level and Pouring of concrete (M30) for raft at PUP PUP Km 204+470 Km 00+000 RHS 18-May-19 9:00 AM IPC-03 DONE
1022 NMSCEW/P-IV/STR/2019/997 997 Checking for reinforcement & shuttering of second lift of A2 wall PUP Km 184+190 RHS 18-May-19 12:00 AM IPC-03 DONE
1023 NMSCEW/P-IV/STR/2019/998 998 Checking Top level and pouring concrete second lift for A2 wall PUP Km 184+190 RHS 18-May-19 12:00 AM IPC-03 DONE
1024 NMSCEW/P-IV/STR/2019/999 999 Checking of reinforcement & shuttering 1st lift for wall A1 & A2 CUP Km 188+575 LHS 18-May-19 10:50 AM NR
1025 NMSCEW/P-IV/STR/2019/1000 1000 Checking top level and Pouring of concrete 1st lift for wall A1 & A2 CUP Km 188+575 LHS 18-May-19 11:30 AM NR
1026 NMSCEW/P-IV/STR/2019/1001 1001 Checking of reinforcement & shuttering 1st lift for wall A1 & A2 CUP Km 185+235 RHS 18-May-19 2:00 PM NR
1027 NMSCEW/P-IV/STR/2019/1002 1002 Checking top level and Pouring of concrete 1st lift for wall A1 & A2 CUP Km 185+235 RHS 18-May-19 2:30 PM NR
1028 NMSCEW/P-IV/STR/2019/1003 1003 Checking for reinforcement & shuttering of second lift of A1 wall PUP Km 172+190 LHS 18-May-19 12:00 AM NR
1029 NMSCEW/P-IV/STR/2019/1004 1004 Checking for reinforcement & shuttering of second lift of A2 wall PUP Km 172+190 LHS 18-May-19 12:00 AM NR
1030 NMSCEW/P-IV/STR/2019/1005 1005 Checking Top level and pouring concrete second lift for wall A1 PUP Km 172+190 LHS 18-May-19 12:00 AM NR
1031 NMSCEW/P-IV/STR/2019/1006 1006 Checking Top level and pouring concrete second lift for wall A2 PUP Km 172+190 LHS 18-May-19 12:00 AM NR
1032 NMSCEW/P-IV/STR/2019/1007 1007 Checking for level & layout of raft shuttering at LP-05 Viaduct Km 195+900 LHS 18-May-19 10:30 AM IPC-04 DONE AE
1033 NMSCEW/P-IV/STR/2019/1008 1008 Checking top level and Pouring of concrete (M30) for raft at LP5 VIADUCT Km 195+900 LHS 18-May-19 9:25 AM IPC-04 DONE
1034 NMSCEW/P-IV/STR/2019/1009 1009 Checking of Layout & Level for LP 5 VIADUCT Km 200+920 LHS 18-May-19 2:10 PM
1035 NMSCEW/P-IV/STR/2019/1010 1010 Checking level for excavated bed for at LP 5 VIADUCT Km 200+920 LHS 18-May-19 2:30 PM
1036 NMSCEW/P-IV/STR/2019/1011 1011 Checking top Level & Laying concrete PCC for LP 5 VIADUCT Km 200+920 LHS 18-May-19 3:35 PM
1037 NMSCEW/P-IV/STR/2019/1012 1012 Checking of Layout & Level for RP 7 VIADUCT Km 202+190 RHS 18-May-19 11:40 AM
1038 NMSCEW/P-IV/STR/2019/1013 1013 Checking level for excavated bed for at RP 7 VIADUCT Km 202+190 RHS 18-May-19 11:55 AM
1039 NMSCEW/P-IV/STR/2019/1014 1014 Checking top Level & Laying concrete PCC for RP 7 VIADUCT Km 202+190 RHS 18-May-19 12:32 PM
1040 NMSCEW/P-IV/STR/2019/1015 1015 Checking of Layout & Level for RP 2 Viaduct Km 169+800 RHS 18-May-19 3:05 PM NR
1041 NMSCEW/P-IV/STR/2019/1016 1016 Checking level for excavated bed for at RP 2 Viaduct Km 169+800 RHS 18-May-19 3:25 PM NR
1042 NMSCEW/P-IV/STR/2019/1017 1017 Checking top Level & Laying concrete PCC for RP 2 Viaduct Km 169+800 RHS 18-May-19 3:55 PM NR
1043 NMSCEW/P-IV/STR/2019/1018 1018 Checking of reinforcement and shuttering for raft at RP 6 Viaduct Km 169+800 RHS 18-May-19 4:10 PM NR
1044 NMSCEW/P-IV/STR/2019/1019 1019 Checking top level and Pouring of concrete (M30) for raft at RP 6 Viaduct Km 169+800 RHS 18-May-19 5:00 PM NR
Checking of reinforcement for Precast Box Culvert (2×2) at precast yard camp-1 ,(cushion 2-
1045 NMSCEW/P-IV/STR/2019/1020 1020 Box Culvert Km 175+500 LHS 18-May-19 11:50 AM IPC-08 DONE AE 11, 12, 13
4m) And segment-11,
Checking of shuttering12
and& pouring
13 of concrete forGrade =(M-30) at precast yard camp-1 for
1046 NMSCEW/P-IV/STR/2019/1021 1021 Box Culvert Km 175+500 LHS 18-May-19 2:02 PM IPC-08 DONE AE 11, 12
precast Box culvert (2*2) (cushion 2-4m) And segment- 11,12 & 13
1047 NMSCEW/P-IV/STR/2019/1022 1022 Checking of reinforcement for Precast Box Culvert (2×2) at precast yard camp-1 (cushion Box Culvert Km 176+250 BHS 18-May-19 12:25 PM IPC-05 DONE
1048 NMSCEW/P-IV/STR/2019/1023 1023 Checking of shuttering and pouring of concrete forGrade =(M-30) at precast yard camp-1 for Box Culvert Km 176+250 BHS 18-May-19 2:55 PM IPC-05 DONE
1049 NMSCEW/P-IV/STR/2019/1024 1024 Checking of reinforcement and shuttering for raft at RP 6 VIADUCT Km 196+560 RHS 18-May-19 6:17 PM
1050 NMSCEW/P-IV/STR/2019/1025 1025 Checking top level and Pouring of concrete (M35) for raft at RP 6 VIADUCT Km 196+560 RHS 18-May-19 6:43 PM
1051 NMSCEW/P-IV/STR/2019/1026 1026 Checking bottom haunch reinforcement & shuttering for wall A1 & A2 LVUP Km 173+400 LHS 19-May-19 9:30 AM NR
1052 NMSCEW/P-IV/STR/2019/1027 1027 Checking top Level & concrete pouring of bottom haunch for wall A1 & A2 LVUP Km 173+400 LHS 19-May-19 10:30 AM NR
Checking reinforcement for precast Box Culvert (3x3) (cushion 2 to 4m) at precast yard camp
1053 NMSCEW/P-IV/STR/2019/1028 1028 Box culvert Km 200+200 LHS 19-May-19 3:00 PM DONE
-2. Segment
Checking for NO-11.
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1054 NMSCEW/P-IV/STR/2019/1029 1029 Checking reinforcement Box culvert Km 200+200 LHS 19-May-19 3:30 PM DONE
(3×3) ,(Cushion 2 to 4m)for precast yard
at precast Box Culvert (2x2) (cushion
camp-2.,Segment 2 to 4m) at precast yard camp
no.-11.
1055 NMSCEW/P-IV/STR/2019/1030 1030 -2. Segment NO-04. Box culvert Km 200+200 LHS 19-May-19 3:15 PM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1056 NMSCEW/P-IV/STR/2019/1031 1031 Box culvert Km 200+200 LHS 19-May-19 4:00 PM DONE
(2×2),(Cushion 2 to 4m) at precast yard camp-2.,Segment no.-04 &05.
1057 NMSCEW/P-IV/STR/2019/1032 1032 Checking of Layout & Level for RP2 Viaduct Km 169+800 RHS 19-May-19 11:00 AM NR
1058 NMSCEW/P-IV/STR/2019/1033 1033 Checking level for excavated bed for at RP2 Viaduct Km 169+800 RHS 19-May-19 11:15 AM NR
1059 NMSCEW/P-IV/STR/2019/1034 1034 Checking top Level & Laying concrete PCC for RP2 Viaduct Km 169+800 RHS 19-May-19 12:00 PM NR
1060 NMSCEW/P-IV/STR/2019/1035 1035 Checking for reinforcement & shuttering of second lift of A1 &A2 wall PUP Km 177+810 LHS 20-May-19 12:00 AM IPC-03 DONE
1061 NMSCEW/P-IV/STR/2019/1036 1036 Checking Top level and pouring concrete second lift for wall A1 & A2 PUP Km 177+810 LHS 20-May-19 12:00 AM IPC-03 DONE
1062 NMSCEW/P-IV/STR/2019/1037 1037 Checking bottom haunch reinforcement & shuttering for wall A1 & A2 PUP Km 174+095 LHS 20-May-19 11:30 AM NR
1063 NMSCEW/P-IV/STR/2019/1038 1038 Checking reinforcement
Checking top Level & concrete pouring
for precast of bottom
Box Culvert (2x2)haunch
(cushionfor wall
2 to 4m)A1 & A2 yard camp
at precast PUP Km 174+095 LHS 20-May-19 12:00 PM NR
1064 NMSCEW/P-IV/STR/2019/1039 1039 -2. Segment NO-06,07,08 & 09. Box culvert Km 200+200 LHS 20-May-19 12:40 PM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1065 NMSCEW/P-IV/STR/2019/1040 1040 Box culvert Km 200+200 LHS 20-May-19 2:20 PM DONE
(2×2),(Cushion 2 to 4m) at precast yard camp-2.,Segment no.-06,07,08 & 09.
1066 NMSCEW/P-IV/STR/2019/1041 1041 Checking of reinforcement and shuttering for raft at RP 6 VIADUCT Km 196+560 RHS 20-May-19 9:00 AM
1067 NMSCEW/P-IV/STR/2019/1042 1042 Checking top level and Pouring of concrete for raft at RP 6 VIADUCT Km 196+560 RHS 20-May-19 10:20 AM
1068 NMSCEW/P-IV/STR/2019/1043 1043 Checking of Layout & Level for RA 1 Viaduct Km 169+800 RHS 20-May-19 2:40 PM NR
1069 NMSCEW/P-IV/STR/2019/1044 1044 Checking level for excavated bed for at RA 1 Viaduct Km 169+800 RHS 20-May-19 3:15 PM NR
1070 NMSCEW/P-IV/STR/2019/1045 1045 Checking top Level & Laying concrete PCC for RA 1 Viaduct Km 169+800 RHS 20-May-19 3:45 PM NR
1071 NMSCEW/P-IV/STR/2019/1046 1046 Checking of reinforcement and shuttering at RP 12 for pier shaft 1st Lift VIADUCT Km 169+800 RHS 20-May-19 4:10 PM NR
1072 NMSCEW/P-IV/STR/2019/1047 1047 Checking top level & Laying concrete at RP 12 for pier shaft 1st Lift VIADUCT Km 169+800 RHS 20-May-19 4:30 PM NR
1073 NMSCEW/P-IV/STR/2019/1048 1048 Checking of Layout & Level for LA 2 Viaduct Km 169+800 LHS 20-May-19 3:30 PM NR
1074 NMSCEW/P-IV/STR/2019/1049 1049 Checking level for excavated bed for at LA 2 Viaduct Km 169+800 LHS 20-May-19 3:40 PM NR
1075 NMSCEW/P-IV/STR/2019/1050 1050 Checking top Level & Laying concrete PCC for LA 2 Viaduct Km 169+800 LHS 20-May-19 4:39 PM NR
1076 NMSCEW/P-IV/STR/2019/1051 1051 Checking of reinforcement and shuttering for RP-06 Viaduct Km 169+800 RHS 20-May-19 12:00 AM IPC-03 DONE AE
1077 NMSCEW/P-IV/STR/2019/1052 1052 Checking top level & Pouring concrete for RP-06 Viaduct Km 169+800 RHS 20-May-19 12:00 AM IPC-03 DONE AE
1078 NMSCEW/P-IV/STR/2019/1053 1053 Checking of Layout & Level for RP 2 Viaduct Km 169+800 RHS 20-May-19 10:55 AM NR
1079 NMSCEW/P-IV/STR/2019/1054 1054 Checking level for excavated bed for at RP 2 Viaduct Km 169+800 RHS 20-May-19 11:20 AM NR
1080 NMSCEW/P-IV/STR/2019/1055 1055 Checking top Level & Laying concrete PCC for LA 2 Viaduct Km 169+800 RHS 20-May-19 11:40 AM NR
1081 NMSCEW/P-IV/STR/2019/1056 1056 checking of bottom haunch reinforcement & shuttering at PUP PUP Km 204+470 Km 00+000 LHS 20-May-19 8:00 AM IPC-03 DONE
1082 NMSCEW/P-IV/STR/2019/1057 1057 Checking top Level & Laying bottom haunch concrete pouring at PUP PUP Km 204+470 Km 00+000 LHS 20-May-19 9:20 AM IPC-03 DONE
Checking of reinforcement for Precast Box Culvert (2×2)at Precast yard Camp-1 Segment no:-
1083 NMSCEW/P-IV/STR/2019/1058 1058 Box culvert Km 175+500 LHS 20-May-19 12:00 PM NR
13,14 & 15of( shuttering
Checking Cushion- 2and
to 4pouring
M) of concrete for grade M-30 at Precast Yard camp-1 Precast
1084 NMSCEW/P-IV/STR/2019/1059 1059 Box culvert Km 175+500 LHS 20-May-19 4:35 PM NR
Box Culvert
Checking (2×2),Segmentfor
of reinforcement no:- 13,14 Box
Precast 15 (Cushion-2 to 4 M)
Culvert (2×2)at Precast yard Camp-1,Segment no:-
1085 NMSCEW/P-IV/STR/2019/1060 1060 Box culvert Km 175+500 LHS 20-May-19 12:15 PM NR
15 & 16 (Cushion-
Checking 0 to and
of shuttering 2 M)pouring of concrete for grade M-30 at Precast Yard camp-1 Precast
1086 NMSCEW/P-IV/STR/2019/1061 1061 Box culvert Km 175+500 LHS 20-May-19 4:40 PM NR
Box Culvert (2×2),Segment no:- 15 & 16 (Cushion- 0 to 2 M)
1087 NMSCEW/P-IV/STR/2019/1062 1062 Checking for reinforcement & shuttering of second lift of A1 &A2 wall PUP Km 172+190 LHS 20-May-19 12:00 AM IPC-03 DONE
1088 NMSCEW/P-IV/STR/2019/1063 1063 Checking Top level and pouring concrete second lift for wall A1 & A2 PUP Km 172+190 LHS 20-May-19 12:00 AM IPC-03 DONE
1089 NMSCEW/P-IV/STR/2019/1064 1064 Checking for reinforcement & shuttering of second lift of A1 wall PUP Km 184+190 RHS 20-May-19 12:00 AM IPC-03 DONE
1090 NMSCEW/P-IV/STR/2019/1065 1065 Checking Top level and pouring concrete second lift for A1 wall PUP Km 184+190 RHS 20-May-19 12:00 AM IPC-03 DONE
1091 NMSCEW/P-IV/STR/2019/1066 1066 Checking for reinforcement & shuttering of first lift of A1 &A2 wall PUP Km 185+235 RHS 20-May-19 12:00 AM IPC-03 DONE AE
1092 NMSCEW/P-IV/STR/2019/1067 1067 Checking level and pouring Concrete for first lift of A1 &A2 wall PUP Km 185+235 RHS 20-May-19 12:00 AM IPC-03 DONE AE
1093 NMSCEW/P-IV/STR/2019/1068 1068 Checking of Layout & Level for PUP PUP Km 211+210 BHS 21-May-19 9:00 AM DONE
1094 NMSCEW/P-IV/STR/2019/1069 1069 Checking level for excavated bed for PUP PUP Km 211+210 BHS 21-May-19 10:00 AM DONE
1095 NMSCEW/P-IV/STR/2019/1070 1070 Checking top Level & Laying concrete PCC for PUP PUP Km 211+210 BHS 21-May-19 11:00 AM DONE
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
1096 NMSCEW/P-IV/STR/2019/1071 1071 Box culvert Km 200+200 LHS 21-May-19 3:30 PM DONE
-2. Segment
Checking for NO-10,11.
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1097 NMSCEW/P-IV/STR/2019/1072 1072 Box culvert Km 200+200 LHS 21-May-19 4:00 PM DONE
(2×2) ,(Cushion 2 to 4m) at precast yard camp-2,Segment no.-10,11.
1098 NMSCEW/P-IV/STR/2019/1073 1073 Checking layout ,level and structural excavation Utility duct Km 162+930 LHS 21-May-19 5:00 PM DONE
1099 NMSCEW/P-IV/STR/2019/1074 1074 Checking bottom haunch reinforcement & shuttering for wall A1 & A2 LVUP Km 173+400 LHS 21-May-19 3:00 PM IPC-05 DONE
1100 NMSCEW/P-IV/STR/2019/1075 1075 Checking top Level & concrete pouring(M35) of bottom haunch for wall A1 & A2 LVUP Km 173+400 LHS 21-May-19 3:34 PM IPC-05 DONE
1101 NMSCEW/P-IV/STR/2019/1076 1076 Checking bottom haunch reinforcement & shuttering for wall A1 & A2 PUP Km 174+095 LHS 21-May-19 5:10 PM NR
1102 NMSCEW/P-IV/STR/2019/1077 1077 Checking top Level & concrete pouring(M30) of bottom haunch for wall A1 & A2 PUP Km 174+095 LHS 21-May-19 5:30 PM NR
1103 NMSCEW/P-IV/STR/2019/1078 1078 Checking for reinforcement & shuttering of second lift of A1 wall PUP Km 188+575 LHS 21-May-19 12:00 AM IPC-03 DONE
1104 NMSCEW/P-IV/STR/2019/1079 1079 Checking Top level and pouring concrete second lift of A1 PUP Km 188+575 LHS 21-May-19 12:00 AM IPC-03 DONE
Checking of reinforcement for Precast Box Culvert (2×2)at Precast yard Camp-1 Segment no:-
1105 NMSCEW/P-IV/STR/2019/1080 1080 Box culvert Km 175+500 LHS 21-May-19 12:00 PM IPC-08 DONE AE 13, 14, 15
13,14 & 15of( shuttering
Checking Cushion- 2and
to 4pouring
M) of concrete for grade M-30 at Precast Yard camp-1 Precast
1106 NMSCEW/P-IV/STR/2019/1081 1081 Box culvert Km 175+500 LHS 21-May-19 4:35 PM IPC-08 DONE AE 13, 14
Box Culvert (2×2),Segment no:- 13,14 15 (Cushion-2 to 4 M)
1107 NMSCEW/P-IV/STR/2019/1082 1082 Checking of reinforcement for Precast Box Culvert (2×2)at Precast yard Camp-1,Segment no:- Box culvert Km 163+830 BHS 21-May-19 12:15 PM IPC-05 DONE
1108 NMSCEW/P-IV/STR/2019/1083 1083 Checking of shuttering and pouring of concrete for grade M-30 at Precast Yard camp-1 Preca Box culvert Km 163+830 BHS 21-May-19 4:40 PM IPC-05 DONE
1109 NMSCEW/P-IV/STR/2019/1084 1084 Checking of annular filling at LP5 Viaduct Km 196+560 LHS 21-May-19 10:05 AM
1110 NMSCEW/P-IV/STR/2019/1085 1085 Checking of Layout & Level for LA 2 Viaduct Km 169+800 LHS 21-May-19 10:15 AM NR
1111 NMSCEW/P-IV/STR/2019/1086 1086 Checking level for excavated bed for at LA 2 Viaduct Km 169+800 LHS 21-May-19 10:35 AM NR
1112 NMSCEW/P-IV/STR/2019/1087 1087 Checking top Level & Laying concrete PCC for LA 2 Viaduct Km 169+800 LHS 21-May-19 2:05 PM NR
1113 NMSCEW/P-IV/STR/2019/1088 1088 Checking of Layout & Level for RA 2 Viaduct Km 169+800 Km 00+000 RHS 21-May-19 10:32 AM IPC-09 DONE MNB
1114 NMSCEW/P-IV/STR/2019/1089 1089 Checking level for excavated bed for at RA 2 Viaduct Km 169+800 Km 00+000 RHS 21-May-19 11:01 AM IPC-09 DONE MNB
1115 NMSCEW/P-IV/STR/2019/1090 1090 Checking top Level & Laying concrete PCC for RA 2 Viaduct Km 169+800 Km 00+000 RHS 21-May-19 3:32 PM IPC-09 DONE MNB
1116 NMSCEW/P-IV/STR/2019/1091 1091 Checking of reinforcement and shuttering for pier shaft stater at LP3 Viaduct Km 169+800 Km 00+000 LHS 21-May-19 9:46 AM IPC-09 DONE
1117 NMSCEW/P-IV/STR/2019/1092 1092 Checking top level & Pouring concrete for pier shaft stater at LP3 Viaduct Km 169+800 Km 00+000 LHS 21-May-19 11:32 AM IPC-09 DONE
1118 NMSCEW/P-IV/STR/2019/1093 1093 Checking of Layout & Level for RP7 Viaduct Km 200+190 RHS 21-May-19 3:08 PM IPC-04 DONE AE
1119 NMSCEW/P-IV/STR/2019/1094 1094 Checking level for excavated bed for at RP7 Viaduct Km 200+190 RHS 21-May-19 3:13 PM IPC-04 DONE AE
1120 NMSCEW/P-IV/STR/2019/1095 1095 Checking top Level & Laying concrete PCC for RP7 Viaduct Km 200+190 RHS 21-May-19 3:30 PM IPC-04 DONE AE
1121 NMSCEW/P-IV/STR/2019/1096 1096 Checking of Layout & Level for LP5 Viaduct Km 200+920 LHS 21-May-19 9:50 AM IPC-08 DONE AE
1122 NMSCEW/P-IV/STR/2019/1097 1097 Checking level for excavated bed for at LP5 Viaduct Km 200+920 LHS 21-May-19 10:12 AM IPC-08 DONE AE
1123 NMSCEW/P-IV/STR/2019/1098 1098 Checking top Level & Laying concrete PCC for LP5 Viaduct Km 200+920 LHS 21-May-19 10:36 AM IPC-08 DONE AE
1124 NMSCEW/P-IV/STR/2019/1099 1099 Checking for reinforcement & shuttering of second lift of A1 &A2 wall PUP Km 172+190 RHS 22-May-19 12:00 AM IPC-03 DONE
1125 NMSCEW/P-IV/STR/2019/1100 1100 Checking Top level and pouring concrete second lift for wall A1 & A2 PUP Km 172+190 RHS 22-May-19 12:00 AM IPC-03 DONE
1126 NMSCEW/P-IV/STR/2019/1101 1101 checking of A1 & A2 reinforcement and shuttering of bottom haunch. PUP Km 186+000 LHS 22-May-19 12:00 AM IPC-03 DONE
1127 NMSCEW/P-IV/STR/2019/1102 1102 A1 & A2 bottom hauch pouring of concrete PUP Km 186+000 LHS 22-May-19 12:00 AM IPC-03 DONE
1128 NMSCEW/P-IV/STR/2019/1103 1103 Checking for concreting(M15) of Lp5 foundation annular filling Viaduct Km 195+900 LHS 22-May-19 11:00 AM
1129 NMSCEW/P-IV/STR/2019/1104 1104 Checking of layout &level and structural excavation for RP1 Viaduct Km 200+920 RHS 22-May-19 2:00 PM IPC-08 DONE AE
1130 NMSCEW/P-IV/STR/2019/1105 1105 Checking top Level & Laying concrete PCC for RP1 Viaduct Km 200+920 RHS 22-May-19 2:30 PM IPC-08 DONE AE
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
1131 NMSCEW/P-IV/STR/2019/1106 1106 Box culvert Km 200+200 LHS 22-May-19 3:00 PM DONE
-2. Segment
Checking for NO-12,13.
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1132 NMSCEW/P-IV/STR/2019/1107 1107 Box culvert Km 200+200 LHS 22-May-19 3:30 PM DONE
(2×2) ,(Cushion 2 to 4m) at precast yard camp-2.,Segment no.-12,13.
1133 NMSCEW/P-IV/STR/2019/1108 1108 Checking of layout &level and structural excavation for LA2 Viaduct Km 169+800 Km 00+000 LHS 22-May-19 10:00 AM IPC-09 DONE MNB
1134 NMSCEW/P-IV/STR/2019/1109 1109 Checking top Level & Laying concrete PCC for LA2 Viaduct Km 169+800 Km 00+000 LHS 22-May-19 11:00 AM IPC-09 DONE MNB
1135 NMSCEW/P-IV/STR/2019/1110 1110 Checking of reinforcement and shuttering for raft at RP 7 Viaduct Km 169+800 RHS 22-May-19 10:05 AM NR
1136 NMSCEW/P-IV/STR/2019/1111 1111 Checking top level and Pouring of concrete(M35) for raft at RP 7 Viaduct Km 169+800 RHS 22-May-19 12:30 PM NR
1137 NMSCEW/P-IV/STR/2019/1112 1112 Checking of layout &level and structural excavation for RP2 Viaduct Km 169+800 RHS 22-May-19 9:30 AM NR
1138 NMSCEW/P-IV/STR/2019/1113 1113 Checking top
Checking Level & Laying
reinforcement concrete
for precast Box PCC for (2x2)
Culvert RP2 (cushion 0 to 2m) for Ch 163+830 at Viaduct Km 169+800 RHS 22-May-19 10:35 AM NR
1139 NMSCEW/P-IV/STR/2019/1114 1114 precast yard camp -1. Segment NO-17,18,19,20 Box culvert Km 175+500 LHS 22-May-19 10:20 AM IPC-08 DONE AE 17, 18, 19, 20
Checking for shuttering & Pouring of Concreting Grade (M-30) for Precast Box Culvert
1140 NMSCEW/P-IV/STR/2019/1115 1115 Box culvert Km 175+500 LHS 22-May-19 10:40 AM IPC-08 DONE 17, 18, 19, 20
(2×2) , (cushion
Checking 0 to 2m)for
reinforcement forprecast
Ch 163+830 at precast
Box Culvert (2x2)yard camp -1.
(cushion 2 toSegment NO-17,18,19,20
4m) at precast yard camp
1141 NMSCEW/P-IV/STR/2019/1116 1116 Box culvert Km 200+200 LHS 22-May-19 4:26 PM DONE
-2. Segment
Checking for NO-14.
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1142 NMSCEW/P-IV/STR/2019/1117 1117 Box culvert Km 200+200 LHS 22-May-19 5:20 PM DONE
(2×2) ,(Cushion 2 to 4m) at precast yard camp-2.,Segment no.-14.
1143 NMSCEW/P-IV/STR/2019/1118 1118 Checking for reinforcement & shuttering of second lift of A2 wall PUP Km 188+575 LHS 22-May-19 12:00 AM IPC-03 DONE
1144 NMSCEW/P-IV/STR/2019/1119 1119 Checking Top level and pouring concrete second lift of A2 PUP Km 188+575 LHS 22-May-19 12:00 AM IPC-03 DONE
1145 NMSCEW/P-IV/STR/2019/1120 1120 Checking of layout &level and structural excavation for LP6 Viaduct Km 202+190 LHS 23-May-19 11:00 AM
1146 NMSCEW/P-IV/STR/2019/1121 1121 Checking top Level & Laying concrete PCC for LP6 Viaduct Km 202+190 LHS 23-May-19 11:30 AM
1147 NMSCEW/P-IV/STR/2019/1122 1122 Checking of reinforcement and shuttering for raft at RP 10 Viaduct Km 196+560 RHS 23-May-19 10:00 AM IPC-04 DONE AE
1148 NMSCEW/P-IV/STR/2019/1123 1123 Checking and Pouring of concrete for raft at RP 10 Viaduct Km 196+560 RHS 23-May-19 10:30 AM IPC-04 DONE AE
1149 NMSCEW/P-IV/STR/2019/1124 1124 Checking top Level & Laying concrete(M-10) PCC for B/C Box culvert Km 171+334 BHS 23-May-19 8:30 AM NR
1150 NMSCEW/P-IV/STR/2019/1125 1125 Checking bottom haunch reinforcement & shuttering for wall A1 & A2 PUP Km 174+095 LHS 23-May-19 5:30 PM IPC-04 DONE
1151 NMSCEW/P-IV/STR/2019/1126 1126 Checking and concrete (M30) pouring in bottom haunch for wall A1 & A2 PUP Km 174+095 LHS 23-May-19 5:50 PM IPC-04 DONE
1152 NMSCEW/P-IV/STR/2019/1127 1127 Checking reinforcement ,shuttering and soffit levels for top haunch and top slab CUP Km 184+190 LHS 23-May-19 5:00 PM NR
1153 NMSCEW/P-IV/STR/2019/1128 1128 Checking and concrete (M30) pouring in top haunch with top slab CUP Km 184+190 LHS 23-May-19 5:15 PM NR
1154 NMSCEW/P-IV/STR/2019/1129 1129 Checking of reinforcement & shuttering for 1st lift W1 & W2 wall PUP Km 204+470 Km 00+000 LHS 23-May-19 9:00 AM IPC-03 DONE AE
1155 NMSCEW/P-IV/STR/2019/1130 1130 Checking and pouring concrete for 1st lift W1 & W2 wall PUP Km 204+470 Km 00+000 LHS 23-May-19 10:00 AM IPC-03 DONE AE
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
1156 NMSCEW/P-IV/STR/2019/1131 1131 Checking for NO-15,16.
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert Box culvert Km 200+200 LHS 23-May-19 3:00 PM DONE
-2. Segment
1157 NMSCEW/P-IV/STR/2019/1132 1132 (2×2),(Cushion 2 to 4m) at precast yard camp-2, Segment no.-15,16. Box culvert Km 200+200 LHS 23-May-19 3:30 PM DONE
1158 NMSCEW/P-IV/STR/2019/1133 1133 Checking level for excavated bed for at RP-02 Viaduct Km 169+800 RHS 23-May-19 12:00 AM IPC-03 DONE
1159 NMSCEW/P-IV/STR/2019/1134 1134 Checking top Level & Laying concrete PCC for RP-02 Viaduct Km 169+800 RHS 23-May-19 12:00 AM IPC-03 DONE AE
1160 NMSCEW/P-IV/STR/2019/1135 1135 Checking of reinforcement and shuttering for RP-07 Viaduct Km 169+800 RHS 23-May-19 12:00 AM IPC-03 DONE AE
1161 NMSCEW/P-IV/STR/2019/1136 1136 Checking top level & Pouring concrete for RP-07 Viaduct Km 169+800 RHS 23-May-19 12:00 AM IPC-03 DONE AE
1162 NMSCEW/P-IV/STR/2019/1137 1137 Checking of reinforcement and shuttering for pier shaft stater at RP4 Viaduct Km 169+800 RHS 23-May-19 11:22 AM IPC-08 DONE
1163 NMSCEW/P-IV/STR/2019/1138 1138 Checking and
Checking Pouring concrete
reinforcement for pier
for precast Boxshaft stater
Culvert at RP4
(2x2) (cushion 2m to 4m) for Ch 163+830 at Viaduct Km 169+800 RHS 23-May-19 3:15 PM IPC-08 DONE
1164 NMSCEW/P-IV/STR/2019/1139 1139 precast yard
Checking forcamp -1. Segment
shuttering & PouringNO-16,17,18,19,
of Concreting Grade (M-30) for Precast Box Culvert Box culvert Km 175+500 LHS 23-May-19 3:40 PM IPC-08 DONE AE 16, 17, 18, 19
1165 NMSCEW/P-IV/STR/2019/1140 1140 (2×2) , (cushion 2m to 4m) for Ch 163+830 at precast yard camp -1. Segment NO- Box culvert Km 175+500 LHS 23-May-19 4:20 PM NR
1166 NMSCEW/P-IV/STR/2019/1141 1141 16,17,18,19,
Checking of reinforcement and shuttering for raft CUP Km 208+930 LHS 24-May-19 9:00 AM IPC-04 DONE
1167 NMSCEW/P-IV/STR/2019/1142 1142 Checking reinforcement
Checking and Pouring offorconcrete
precastfor
Boxraft
Culvert (2x2) (cushion 2 to 4m) at precast yard camp CUP Km 208+930 LHS 24-May-19 10:00 AM IPC-04 DONE
1168 NMSCEW/P-IV/STR/2019/1143 1143 -2. Segment NO-17. Box culvert Km 200+200 LHS 24-May-19 3:00 PM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1169 NMSCEW/P-IV/STR/2019/1144 1144 Box culvert Km 200+200 LHS 24-May-19 3:30 PM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-2,Segment
Checking reinforcement ,shuttering and soffit levels for Final no.-17.
lift with top haunch and top slab
1170 NMSCEW/P-IV/STR/2019/1145 1145 PUP Km 171+110 RHS 24-May-19 10:05 AM NR
at wall A1and
Checking & A2
concrete (M30) pouring for Final lift with top haunch and top slab at wall A1
1171 NMSCEW/P-IV/STR/2019/1146 1146 PUP Km 171+110 RHS 24-May-19 4:00 PM NR
& A2
1172 NMSCEW/P-IV/STR/2019/1147 1147 Checking top Level & Laying concrete PCC VUP Km 176+614 Km 00+000 RHS 24-May-19 10:30 AM IPC-10 DONE
1173 NMSCEW/P-IV/STR/2019/1148 1148 Checking of layout, levels and structural excavation of BC Box culvert Km 178+014 BHS 24-May-19 4:50 PM IPC-08 DONE
1174 NMSCEW/P-IV/STR/2019/1149 1149 Checking and concrete (M30) pouring for Final lift at wall A1 & A2 CUP Km 184+190 RHS 24-May-19 5:20 PM NR
1175 NMSCEW/P-IV/STR/2019/1150 1150 Checking reinforcement, shuttering for top haunch and top slab at wall A1 & A2 PUP Km 184+190 LHS 24-May-19 12:00 AM IPC-03 DONE
1176 NMSCEW/P-IV/STR/2019/1151 1151 Checking & pouring
Checking for concrete
shuttering for top
& Pouring haunch & top
of Concreting Gradeslab(M-30)
at wallfor
A1Precast
& A2. Box Culvert PUP Km 184+190 LHS 24-May-19 12:00 AM IPC-03 DONE
1177 NMSCEW/P-IV/STR/2019/1152 1152 (2×2) , (cushion 2m to 4m) for Ch 168+020 at precast yard camp -1. Segment NO- Box culvert Km 175+500 LHS 24-May-19 9:30 AM IPC-08 DONE 16, 17, 18
1178 NMSCEW/P-IV/STR/2019/1153 1153 16,17,18,19,
Checking of reinforcement and shuttering for pier shaft at LP12 Viaduct Km 169+800 Km 00+000 LHS 24-May-19 3:05 PM IPC-09 DONE
1179 NMSCEW/P-IV/STR/2019/1154 1154 Checking and Pouring concrete for pier shaft at LP12 Viaduct Km 169+800 Km 00+000 LHS 24-May-19 4:05 PM IPC-09 DONE
1180 NMSCEW/P-IV/STR/2019/1155 1155 Checking of reinforcement and shuttering for pier shaft stater at LP4 Viaduct Km 169+800 LHS 24-May-19 10:15 AM IPC-08 DONE
1181 NMSCEW/P-IV/STR/2019/1156 1156 Checking and Pouring concrete for pier shaft stater at LP4 Viaduct Km 169+800 LHS 24-May-19 10:45 AM IPC-08 DONE
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
1182 NMSCEW/P-IV/STR/2019/1157 1157 Box culvert Km 200+200 LHS 25-May-19 9:30 AM DONE
-2. Segment
Checking for NO-18,19
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1183 NMSCEW/P-IV/STR/2019/1158 1158 Box culvert Km 200+200 LHS 25-May-19 10:30 AM DONE
(2×2),(Cushion 2 to 4m) for
Checking reinforcement at precast
precastyard
Boxcamp-2,Segment no.-18,19
Culvert (2x2) (cushion 2 to 4m) at precast yard camp
1184 NMSCEW/P-IV/STR/2019/1159 1159 Box culvert Km 200+200 LHS 25-May-19 3:00 PM DONE
-2. Segment
Checking for NO-20,21,22,23.
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1185 NMSCEW/P-IV/STR/2019/1160 1160 Box culvert Km 200+200 LHS 25-May-19 3:40 PM DONE
(2×2),(Cushion 2 to 4m) at precast yard camp-2,Segment no.-20,21,22,23.
1186 NMSCEW/P-IV/STR/2019/1161 1161 Checking of reinforcement and shuttering for raft at RP1 Viaduct Km 195+900 RHS 25-May-19 3:10 PM
1187 NMSCEW/P-IV/STR/2019/1162 1162 Checking and Pouring of concrete(M-35) for raft at RP1 Viaduct Km 195+900 RHS 25-May-19 3:30 PM
1188 NMSCEW/P-IV/STR/2019/1163 1163 Checking of layout &level and structural excavation for LP7 Viaduct Km 195+900 LHS 25-May-19 2:00 PM
1189 NMSCEW/P-IV/STR/2019/1164 1164 Checking top Level & Laying concrete PCC for LP7 Viaduct Km 195+900 LHS 25-May-19 2:20 PM
1190 NMSCEW/P-IV/STR/2019/1165 1165 Checking of reinforcement and shuttering for raft at LP1 Viaduct Km 202+190 LHS 25-May-19 11:00 AM IPC-04 DONE AE
1191 NMSCEW/P-IV/STR/2019/1166 1166 Checking and Pouring of concrete(M-35) for raft at LP1 Viaduct Km 202+190 LHS 25-May-19 11:30 AM IPC-04 DONE AE
1192 NMSCEW/P-IV/STR/2019/1167 1167 Checking of layout &level and structural excavation for LP6 Viaduct Km 202+190 LHS 25-May-19 9:00 AM IPC-04 DONE AE
1193 NMSCEW/P-IV/STR/2019/1167A 1167A Checking level for excavated bed for LP 6 Viaduct Km 202+190 LHS 25-May-19 9:40 AM IPC-04 DONE AE
1194 NMSCEW/P-IV/STR/2019/1168 1168 Checking top Level & Laying concrete PCC for LP6 Viaduct Km 202+190 LHS 25-May-19 9:40 AM IPC-04 DONE AE
1195 NMSCEW/P-IV/STR/2019/1169 1169 Checking top Level & Laying concrete (M-10) PCC for B/C Box culvert Km 178+014 BHS 25-May-19 4:30 PM IPC-08 DONE
1196 NMSCEW/P-IV/STR/2019/1170 1170 Checking of reinforcement and shuttering for raft at VUP VUP Km 176+614 LHS 25-May-19 6:00 PM IPC-08 DONE AE
1197 NMSCEW/P-IV/STR/2019/1171 1171 Checking and
Checking Pouring of concrete(M-35)
reinforcement for raft (2x2)
for precast Box Culvert at VUP (cushion 2m to 4m) for Ch 168+020 at VUP Km 176+614 LHS 25-May-19 6:30 PM IPC-08 DONE AE
1198 NMSCEW/P-IV/STR/2019/1172 1172 precast yard camp -1. Segment NO-20,21 Box culvert Km 175+500 LHS 25-May-19 10:40 AM IPC-08 DONE AE 20, 21
Checking for shuttering & Pouring of Concreting Grade (M-30) for Precast Box Culvert
1199 NMSCEW/P-IV/STR/2019/1173 1173 Box culvert Km 175+500 LHS 25-May-19 11:30 AM IPC-08 DONE AE 19, 20, 21
(2×2) , (cushion 2m to 4m) for Ch 168+020 at precast yard camp -1. Segment NO-19,20,21
1200 NMSCEW/P-IV/STR/2019/1174 1174 Checking reinforcement ,shuttering for Final lift at wall A1 & A2 CUP Km 184+190 RHS 25-May-19 10:30 AM NR
1201 NMSCEW/P-IV/STR/2019/1175 1175 Checking and concrete (M30) pouring for Final lift at wall A1 & A2 CUP Km 184+190 RHS 25-May-19 11:00 AM NR
1202 NMSCEW/P-IV/STR/2019/1176 1176 Checking of reinforcement and shuttering for LP-06 Viaduct Km 169+800 LHS 25-May-19 12:00 AM IPC-03 DONE
1203 NMSCEW/P-IV/STR/2019/1177 1177 Checking top level & Pouring concrete for LP-06 Viaduct Km 169+800 LHS 25-May-19 12:00 AM IPC-03 DONE
1204 NMSCEW/P-IV/STR/2019/1178 1178 Checking for concreting(M15) around of RP13 foundation annular filling Viaduct Km 169+800 RHS 25-May-19 9:38 AM NR
1205 NMSCEW/P-IV/STR/2019/1179 1179 Checking reinforcement, shuttering for final lift at wall A1 & A2 PUP Km 184+190 RHS 26-May-19 12:00 AM IPC-03 DONE
1206 NMSCEW/P-IV/STR/2019/1180 1180 Checking concrete pouring. for final lift at wall A1 & A2 PUP Km 184+190 RHS 26-May-19 12:00 AM IPC-03 DONE
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
1207 NMSCEW/P-IV/STR/2019/1181 1181 Box culvert Km 200+200 LHS 26-May-19 11:15 AM DONE
-2. Segment
Checking for NO-24.
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1208 NMSCEW/P-IV/STR/2019/1182 1182 Box culvert Km 200+200 LHS 26-May-19 11:30 AM DONE
(2×2)(Cushion 2 to 4m) at precast yard camp-2,Segment no.-24.
1209 NMSCEW/P-IV/STR/2019/1183 1183 Checking of reinforcement and shuttering for RP-02 Viaduct Km 169+800 RHS 26-May-19 12:00 AM IPC-03 DONE
1210 NMSCEW/P-IV/STR/2019/1184 1184 Checking of reinforcement and shuttering for RP-01 Viaduct Km 169+800 RHS 26-May-19 12:00 AM IPC-03 DONE
1211 NMSCEW/P-IV/STR/2019/1185 1185 Checking of layout &level and structural excavation Box culvert Km 198+128 BHS 26-May-19 8:00 AM
1212 NMSCEW/P-IV/STR/2019/1186 1186 Checking of layout &level and structural excavation Box culvert Km 200+286 BHS 26-May-19 8:12 AM
1213 NMSCEW/P-IV/STR/2019/1187 1187 Checking of reinforcement and shuttering for raft at RP1 Viaduct Km 195+900 RHS 26-May-19 10:00 AM
1214 NMSCEW/P-IV/STR/2019/1188 1188 Checking and Pouring of concrete for raft at RP1 Viaduct Km 195+900 RHS 26-May-19 10:45 AM
1215 NMSCEW/P-IV/STR/2019/1189 1189 Checking of layout &level and structural excavation for LP7 Viaduct Km 195+900 LHS 26-May-19 11:40 AM IPC-04 DONE AE
1216 NMSCEW/P-IV/STR/2019/1189A 1189A Checking level for excavated bed for at LP7 Viaduct Km 195+900 LHS 26-May-19 12:00 PM IPC-04 DONE
1217 NMSCEW/P-IV/STR/2019/1190 1190 Checking top Level & Laying concrete PCC for LP7 Viaduct Km 195+900 LHS 26-May-19 2:20 PM IPC-04 DONE AE
1218 NMSCEW/P-IV/STR/2019/1183a 1183a Checking top level & Pouring concrete for RP-02 Viaduct Km 169+800 RHS 26-May-19 IPC-03 DONE
1219 NMSCEW/P-IV/STR/2019/1184a 1184a Checking top level & Pouring concrete for RP-01 Viaduct Km 169+800 RHS 26-May-19 IPC-03 DONE
1220 NMSCEW/P-IV/STR/2019/1191 1191 Checking for concreting(M15) around of RP13 foundation annular filling Viaduct Km 169+800 RHS 27-May-19 9:30 AM DONE
1221 NMSCEW/P-IV/STR/2019/1192 1192 Checking for concreting(M15) around of LP13 foundation annular filling Viaduct Km 169+800 LHS 27-May-19 11:00 AM NR
1222 NMSCEW/P-IV/STR/2019/1193 1193 Checking of reinforcement and shuttering for pier stater at LP4 Viaduct Km 169+800 LHS 27-May-19 10:30 AM NR
1223 NMSCEW/P-IV/STR/2019/1194 1194 Checking layout ,level and structural excavation Box culvert Km 211+335 BHS 27-May-19 12:00 PM REPEATED
1224 NMSCEW/P-IV/STR/2019/1195 1195 Checking and concrete (M35) pouring for 1st Lift at Wall A1 & A2 of LVUP LVUP Km 173+400 LHS 27-May-19 12:50 PM IPC-05 DONE
1225 NMSCEW/P-IV/STR/2019/1196 1196 Checking and Pouring concrete for pier stater at LP4 Viaduct Km 169+800 LHS 27-May-19 12:00 PM NR
1226 NMSCEW/P-IV/STR/2019/1197 1197 Checking layout ,level and structural excavation Utility duct Km 163+830 BHS 27-May-19 11:00 AM IPC-05 DONE
1227 NMSCEW/P-IV/STR/2019/1198 1198 Checking layout ,level and structural excavation Box culvert Km 191+870 BHS 27-May-19 6:00 PM REPEATED
1228 NMSCEW/P-IV/STR/2019/1199 1199 Checking layout ,level and structural excavation Box culvert Km 198+128 BHS 27-May-19 6:22 PM REPEATED
1229 NMSCEW/P-IV/STR/2019/1200 1200 Checking top Level & Laying concrete(M-10) PCC Utility duct Km 162+930 BHS 27-May-19 11:30 AM DONE
1230 NMSCEW/P-IV/STR/2019/1201 1201 Checking of reinforcement and shuttering for raft at PUP PUP Km 174+095 RHS 27-May-19 5:00 PM NR
1231 NMSCEW/P-IV/STR/2019/1202 1202 Checking and
Checking Pouring of concrete(M-30)
reinforcement for raft (2x2)
for precast Box Culvert at PUP(cushion 0 to 2m) for Ch 163+830 at PUP Km 174+095 RHS 27-May-19 5:30 PM NR
1232 NMSCEW/P-IV/STR/2019/1203 1203 precast yard camp -1. Segment NO-21,22,23 Box culvert Km 175+500 LHS 27-May-19 11:05 AM IPC-08 DONE 21, 22, 23
Checking for shuttering & Pouring of Concreting Grade (M-30) for Precast Box Culvert
1233 NMSCEW/P-IV/STR/2019/1204 1204 Checking reinforcement Box culvert Km 175+500 LHS 27-May-19 11:33 AM IPC-08 DONE AE 21, 22, 23
(2×2) , (cushion 0 to 2m)for
forprecast Box Culvert
Ch 163+830 (2x2)
at precast (cushion
yard 2 toSegment
camp -1. 4m) at precast yard camp
NO-21,22,23
1234 NMSCEW/P-IV/STR/2019/1205 1205 -2. Segment NO-25,26,27. Box culvert Km 200+200 LHS 27-May-19 3:00 PM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1235 NMSCEW/P-IV/STR/2019/1206 1206 Box culvert Km 200+200 LHS 27-May-19 3:32 PM DONE
(2×2),(Cushion 2 to 4m) at precast yard camp-2,Segment no.-25,26,27.
1236 NMSCEW/P-IV/STR/2019/1207 1207 Checking layout ,level and structural excavation for B/C (3x3) Box culvert Km 211+470 BHS 27-May-19 12:30 PM DONE
1237 NMSCEW/P-IV/STR/2019/1208 1208 Checking top Level & Laying concrete PCC for B/C (3x3) Box culvert Km 211+470 BHS 27-May-19 2:30 PM DONE
1238 NMSCEW/P-IV/STR/2019/1209 1209 Checking of reinforcement & shuttering for bottom hunch of wall A1& A2 VUP Km 176+614 LHS 27-May-19 11:00 AM IPC-08 DONE
1239 NMSCEW/P-IV/STR/2019/1210 1210 Checking & pouring concrete(M30) for bottom hunch of wall A1& A2 VUP Km 176+614 LHS 27-May-19 11:35 AM IPC-08 DONE
1240 NMSCEW/P-IV/STR/2019/1211 1211 Checking of soffit level of CUP CUP Km 188+575 LHS 27-May-19 9:30 AM NR
1241 NMSCEW/P-IV/STR/2019/1195A 1195A Checking reinforcement ,shuttering for 1st Lift at Wall A1 of LVUP LVUP Km 173+400 LHS 27-May-19 12:50 PM IPC-05 DONE
1242 NMSCEW/P-IV/STR/2019/1212 1212 Checking of reinforcement and shuttering for raft at PUP CUP Km 208+930 RHS 28-May-19 2:30 PM IPC-04 DONE
1243 NMSCEW/P-IV/STR/2019/1213 1213 Checking and Pouring of concrete for raft at PUP CUP Km 208+930 RHS 28-May-19 3:00 PM IPC-04 DONE AE
1244 NMSCEW/P-IV/STR/2019/1214 1214 Checking of reinforcement & shuttering for 1st lift W1 & W2 wall PUP Km 204+470 Km 00+000 RHS 28-May-19 9:00 AM IPC-03 DONE
1245 NMSCEW/P-IV/STR/2019/1215 1215 Checking and pouring concrete for 1st lift W1 & W2 wall PUP Km 204+470 Km 00+000 RHS 28-May-19 10:00 AM IPC-03 DONE
1246 NMSCEW/P-IV/STR/2019/1216 1216 Checking reinforcement, shuttering for final lift with top haunch and top slab at wall A1 & A2 PUP Km 177+810 LHS 28-May-19 12:00 AM IPC-03 DONE
1247 NMSCEW/P-IV/STR/2019/1217 1217 Checking & pouring concrete for Final lift with top haunch & top slab at wall A1 & A2. PUP Km 177+810 LHS 28-May-19 12:00 AM IPC-03 DONE
1248 NMSCEW/P-IV/STR/2019/1218 1218 Checking layout ,level and structural excavation Box culvert Km 190+750 BHS 28-May-19 8:00 AM REPEATED
1249 NMSCEW/P-IV/STR/2019/1219 1219 Checking layout ,level and structural excavation Box culvert Km 191+870 BHS 28-May-19 8:30 AM REPEATED
1250 NMSCEW/P-IV/STR/2019/1220 1220 Checking of reinforcement and shuttering for raft & bottom haunch at PUP PUP Km 174+095 RHS 28-May-19 5:30 PM IPC-04 DONE
1251 NMSCEW/P-IV/STR/2019/1221 1221 Checking and Pouring of concrete(M-30) for raft & bottom haunch at PUP PUP Km 174+095 RHS 28-May-19 6:00 PM IPC-04 DONE
1252 NMSCEW/P-IV/STR/2019/1222 1222 Checking of reinforcement & shuttering for 2nd lift A1 & A2 wall CUP Km 185+235 RHS 28-May-19 4:40 PM NR
1253 NMSCEW/P-IV/STR/2019/1223 1223 Checking and pouring concrete(M-30) for 2nd lift A1 & A2 wall CUP Km 185+235 RHS 28-May-19 5:00 PM NR
1254 NMSCEW/P-IV/STR/2019/1224 1224 Checking reinforcement ,shuttering for top slab at PUP PUP Km 205+430 LHS 28-May-19 10:05 AM NR
1255 NMSCEW/P-IV/STR/2019/1225 1225 Checking layout ,level and structural excavation Box culvert Km 209+470 BHS 28-May-19 9:30 AM REPEATED
1256 NMSCEW/P-IV/STR/2019/1226 1226 Checking layout ,level and structural excavation Box culvert Km 210+285 BHS 28-May-19 10:42 AM REPEATED
1257 NMSCEW/P-IV/STR/2019/1227 1227 Checking of reinforcement and shuttering for pier shaft stater at RP5 Viaduct Km 169+800 RHS 28-May-19 11:00 AM IPC-08 DONE
1258 NMSCEW/P-IV/STR/2019/1228 1228 Checking and Pouring concrete for pier shaft stater at RP5 Viaduct Km 169+800 RHS 28-May-19 4:00 PM IPC-08 DONE
1259 NMSCEW/P-IV/STR/2019/1229 1229 Checking for concreting around of LP13 foundation annular filling Viaduct Km 169+800 LHS 28-May-19 11:00 AM DONE
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
1260 NMSCEW/P-IV/STR/2019/1230 1230 Box culvert Km 200+200 LHS 28-May-19 3:05 PM
-2. Segment
Checking for NO-28.
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1261 NMSCEW/P-IV/STR/2019/1231 1231 Box culvert Km 200+200 LHS 28-May-19 3:50 PM
(2×2) ,(Cushion
Checking 2 to 4m)for
reinforcement at precast
precast yard camp-2,Segment
Box Culvert no.-28. 168+020 (cushion 2 to 4m)
(2x2)for chainage
1262 NMSCEW/P-IV/STR/2019/1232 1232 Box culvert Km 175+500 LHS 28-May-19 3:34 PM IPC-08 DONE AE 22, 23
at precast yard
Checking camp -1. &
for shuttering Segment
PouringNO-22,23.
of Concreting Grade =(M-30) for Precast Box Culvert
1263 NMSCEW/P-IV/STR/2019/1233 1233 Box culvert Km 175+500 LHS 28-May-19 4:10 PM NR
(2×2) for chainage 168+020 (Cushion 2 to 4m) at precast yard camp-1,Segment no.-22,23.
1264 NMSCEW/P-IV/STR/2019/1234 1234 Checking of reinforcement and shuttering for raft at RP 5 Viaduct Km 202+190 RHS 28-May-19 3:00 PM IPC-04 DONE SPOT RFI
1265 NMSCEW/P-IV/STR/2019/1235 1235 Checking and Pouring of concrete(M-35) for raft at RP 5 Viaduct Km 202+190 RHS 28-May-19 4:00 PM IPC-04 DONE SPOT RFI
1266 NMSCEW/P-IV/STR/2019/1236 1236 Checking of reinforcement and shuttering for raft at PUP PUP Km 191+740 LHS 29-May-19 11:00 AM IPC-04 DONE
1267 NMSCEW/P-IV/STR/2019/1237 1237 Checking and Pouring of concrete for raft at PUP PUP Km 191+740 LHS 29-May-19 12:00 PM IPC-04 DONE
1268 NMSCEW/P-IV/STR/2019/1238 1238 Checking layout ,level and structural excavation Box culvert Km 200+286 BHS 29-May-19 9:00 AM
1269 NMSCEW/P-IV/STR/2019/1239 1239 Checking layout ,level and
Checking reinforcement for structural
precast Boxexcavation
Culvert (2x2) (cushion 2 to 4m) at precast yard camp Box culvert Km 204+409 BHS 29-May-19 9:30 AM REPEATED
1270 NMSCEW/P-IV/STR/2019/1240 1240 -2. Segment NO-29,30,31,32. Box culvert Km 200+200 LHS 29-May-19 4:00 PM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1271 NMSCEW/P-IV/STR/2019/1241 1241 Box culvert Km 200+200 LHS 29-May-19 4:30 PM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-2,Segment no.-29,30,31,32.
1272 NMSCEW/P-IV/STR/2019/1242 1242 Checking of reinforcement and shuttering for LP- 05 Viaduct Km 169+800 LHS 29-May-19 12:00 AM IPC-03 DONE
1273 NMSCEW/P-IV/STR/2019/1243 1243 Checking of reinforcement and shuttering for LP-01 Viaduct Km 169+800 LHS 29-May-19 12:00 AM IPC-03 DONE
1274 NMSCEW/P-IV/STR/2019/1244 1244 Checking layout ,level and structural excavation Utility duct Km 165+020 BHS 29-May-19 5:00 PM DONE
Checking reinforcement ,shuttering for Final lift with top haunch and top slab at wall A1 &
1275 NMSCEW/P-IV/STR/2019/1245 1245 CUP Km 188+575 LHS 29-May-19 5:10 PM NR
A2
Checking and concrete (M30) pouring for Final lift with top haunch and top slab at wall A1
1276 NMSCEW/P-IV/STR/2019/1246 1246 CUP Km 188+575 LHS 29-May-19 5:40 PM NR
& A2
Checking reinforcement ,shuttering for Final lift with top haunch and top slab at wall A1 &
1277 NMSCEW/P-IV/STR/2019/1247 1247 CUP Km 184+190 RHS 29-May-19 5:30 PM NR
A2
Checking and concrete (M30) pouring for Final lift with top haunch and top slab at wall A1
1278 NMSCEW/P-IV/STR/2019/1248 1248 CUP Km 184+190 RHS 29-May-19 5:50 PM NR
& A2
1279 NMSCEW/P-IV/STR/2019/1249 1249 Checking reinforcement ,shuttering for bottom slab CUP Km 189+000 LHS 29-May-19 4:15 PM NR
1280 NMSCEW/P-IV/STR/2019/1250 1250 Checking and concrete (M30) pouring for bottom slab CUP Km 189+000 LHS 29-May-19 4:45 PM NR
Checking reinforcement ,shuttering for Final lift with top haunch and top slab at wall A1 &
1281 NMSCEW/P-IV/STR/2019/1251 1251 PUP Km 172+190 LHS 29-May-19 5:20 PM NR
A2
Checking and concrete (M30) pouring for Final lift with top haunch and top slab at wall A1
1282 NMSCEW/P-IV/STR/2019/1252 1252 PUP Km 172+190 LHS 29-May-19 6:00 PM NR
& A2
1283 NMSCEW/P-IV/STR/2019/1253 1253 Checking of reinforcement & shuttering for 2nd lift A1 & A2 wall CUP Km 185+235 RHS 29-May-19 8:00 AM DONE
1284 NMSCEW/P-IV/STR/2019/1254 1254 Checking Top level and pouring concrete second lift for wall A1 & A2 PUP Km 185+235 RHS 29-May-19 12:00 AM IPC-03 DONE
1285 NMSCEW/P-IV/STR/2019/1255 1255 Checking of reinforcement and shuttering for raft at RP1 Viaduct Km 195+900 RHS 29-May-19 2:00 PM IPC-04 DONE
1286 NMSCEW/P-IV/STR/2019/1256 1256 Checking and Pouring of concrete for raft at RP1 Viaduct Km 195+900 RHS 29-May-19 2:30 PM IPC-04 DONE
1287 NMSCEW/P-IV/STR/2019/1257 1257 Checking layout ,level and structural excavation at RP4 Viaduct Km 195+900 RHS 29-May-19 12:00 PM
1288 NMSCEW/P-IV/STR/2019/1258 1258 Checking top Level & Laying concrete PCC at RP4 Viaduct Km 195+900 RHS 29-May-19 12:30 PM
1289 NMSCEW/P-IV/STR/2019/1259 1259 Checking of reinforcement and shuttering for LP- 07 Viaduct Km 169+800 LHS 29-May-19 12:00 AM IPC-03 DONE AE
1290 NMSCEW/P-IV/STR/2019/1260 1260 Checking top level & Pouring concrete for LP- 07 Viaduct Km 169+800 LHS 29-May-19 12:00 AM IPC-03 DONE AE
1291 NMSCEW/P-IV/STR/2019/1261 1261 Checking for concreting around of LP12 foundation annular filling Viaduct Km 169+800 LHS 29-May-19 11:10 AM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1292 NMSCEW/P-IV/STR/2019/1262 1262 Box culvert Km 175+500 LHS 29-May-19 3:50 PM IPC-08 DONE AE 22, 23
(2×2) for chainage 168+020 (Cushion 2 to 4m) at precast yard camp-1,Segment no.-22,23.
1293 NMSCEW/P-IV/STR/2019/1273 1273 Checking for reinforcement & shuttering of second lift of A1 &A2 wall PUP Km 185+235 RHS 29-May-19 12:00 AM IPC-03 DONE
1294 NMSCEW/P-IV/STR/2019/1242a 1242a Checking top level & Pouring concrete for LP- 05 Viaduct Km 169+800 LHS 29-May-19 IPC-03 DONE
1295 NMSCEW/P-IV/STR/2019/1243a 1243a Checking top level & Pouring concrete for LP-01 Viaduct Km 169+800 LHS 29-May-19 IPC-03 DONE
1296 NMSCEW/P-IV/STR/2019/1263 1263 Checking layout ,level and structural excavation Box culvert Km 193+484 Km 00+000 BHS 30-May-19 9:30 AM IPC-11 Approved AE
1297 NMSCEW/P-IV/STR/2019/1264 1264 Checking top Level & Laying concrete PCC at B/C Box culvert Km 193+484 Km 00+000 BHS 30-May-19 11:00 AM IPC-11 Approved
1298 NMSCEW/P-IV/STR/2019/1265 1265 Checking layout ,level and structural excavation Box culvert Km 204+409 BHS 30-May-19 10:22 AM
1299 NMSCEW/P-IV/STR/2019/1266 1266 Checking layout ,level and structural excavation at RP4 Viaduct Km 195+900 RHS 30-May-19 10:00 AM
1300 NMSCEW/P-IV/STR/2019/1267 1267 Checking top Level & Laying concrete PCC at RP4 Viaduct Km 195+900 RHS 30-May-19 10:50 AM IPC-04 DONE
1301 NMSCEW/P-IV/STR/2019/1268 1268 Checking layout ,level and structural excavation Box culvert Km 184+490 BHS 30-May-19 9:32 AM NR
1302 NMSCEW/P-IV/STR/2019/1269 1269 Checking layout ,level and structural excavation at RP5 Viaduct Km 196+560 RHS 30-May-19 10:30 AM IPC-08 DONE
1303 NMSCEW/P-IV/STR/2019/1270 1270 Checking top Level & Laying concrete PCC at RP5 Viaduct Km 196+560 RHS 30-May-19 11:30 AM IPC-08 DONE
1304 NMSCEW/P-IV/STR/2019/1271 1271 Checking reinforcement, shuttering for final lift with top haunch and top slab at wall A1 & A2 PUP Km 172+190 RHS 30-May-19 12:00 AM IPC-03 DONE
1305 NMSCEW/P-IV/STR/2019/1272 1272 Checking & pouring concrete for Final lift with top haunch & top slab at wall A1 & A2. PUP Km 172+190 RHS 30-May-19 12:00 AM IPC-03 DONE
1306 NMSCEW/P-IV/STR/2019/1274 1274 Checking and concrete (M30) pouring for for bottom haunch at wall A1 & A2 of pup PUP Km 174+095 RHS 30-May-19 9:00 AM NR
1307 NMSCEW/P-IV/STR/2019/1275 1275 Checking layout ,level and structural excavation Box culvert Km 183+326 BHS 30-May-19 8:35 AM NR
1308 NMSCEW/P-IV/STR/2019/1276 1276 Checking top Level & Laying concrete PCC at Utility duct Utility duct Km 163+830 BHS 30-May-19 11:30 AM IPC-05 DONE
1309 NMSCEW/P-IV/STR/2019/1277 1277 Checking of reinforcement and shuttering for bottom slab of CUP CUP Km 189+000 LHS 30-May-19 8:00 AM IPC-05 DONE
1310 NMSCEW/P-IV/STR/2019/1278 1278 Checking and Pouring of concrete(M-30) for bottom slab of CUP CUP Km 189+000 LHS 30-May-19 8:20 AM IPC-05 DONE
1311 NMSCEW/P-IV/STR/2019/1279 1279 Checking for reinforcement & shuttering of first lift of A1 &A2 wall PUP Km 186+000 LHS 30-May-19 12:00 AM IPC-03 DONE
1312 NMSCEW/P-IV/STR/2019/1280 1280 Checking level and pouring Concrete for first lift of A1 &A2 wall PUP Km 186+000 LHS 30-May-19 12:00 AM IPC-03 DONE
1313 NMSCEW/P-IV/STR/2019/1281 1281 Checking reinforcement, shuttering for top haunch and top slab at wall A1 & A2 PUP Km 184+190 RHS 30-May-19 12:00 AM IPC-03 DONE
1314 NMSCEW/P-IV/STR/2019/1282 1282 Checking & pouring concrete for top haunch & top slab at wall A1 & A2. PUP Km 184+190 RHS 30-May-19 12:00 AM IPC-03 DONE
1315 NMSCEW/P-IV/STR/2019/1283 1283 Checking reinforcement, shuttering for final lift with top haunch and top slab at wall A1 & A2 PUP Km 185+235 RHS 30-May-19 12:00 AM IPC-03 DONE
1316 NMSCEW/P-IV/STR/2019/1284 1284 Checking & pouring concrete for Final lift with top haunch & top slab at wall A1 & A2. PUP Km 185+235 RHS 30-May-19 12:00 AM IPC-03 DONE
1317 NMSCEW/P-IV/STR/2019/1285 1285 Checking layout ,level and structural excavation at LP1 Viaduct Km 200+980 LHS 30-May-19 3:00 PM
1318 NMSCEW/P-IV/STR/2019/1286 1286 Checking top Level & Laying concrete PCC at LP1 Viaduct Km 200+980 LHS 30-May-19 3:30 PM
1319 NMSCEW/P-IV/STR/2019/1287 1287 Checking layout ,level and structural excavation Box culvert Km 209+470 BHS 30-May-19 10:52 AM
1320 NMSCEW/P-IV/STR/2019/1288 1288 Checking of reinforcement & shuttering for 3rd lift W1 & W2 wall PUP Km 205+430 Km 00+000 LHS 30-May-19 9:15 AM IPC-03 DONE
1321 NMSCEW/P-IV/STR/2019/1289 1289 Checking reinforcement
Checking and pouring for
concrete
precastforBox
3rdCulvert
lift W1(2x2)
& W2 wall 2 to 4m) at precast yard camp
(cushion PUP Km 205+430 Km 00+000 LHS 30-May-19 9:45 AM IPC-03 DONE
1322 NMSCEW/P-IV/STR/2019/1290 1290 -2. Segment NO-33. Box culvert Km 200+200 LHS 30-May-19 3:50 PM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1323 NMSCEW/P-IV/STR/2019/1291 1291 Box culvert Km 200+200 LHS 30-May-19 5:46 PM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-2,Segment no.-33
1324 NMSCEW/P-IV/STR/2019/1292 1292 Checking of reinforcement and shuttering for raft PUP Km 203+560 RHS 30-May-19 4:01 PM IPC-04 DONE
1325 NMSCEW/P-IV/STR/2019/1293 1293 Checking and Pouring of concrete for raft PUP Km 203+560 RHS 30-May-19 5:02 PM IPC-04 DONE
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
1326 NMSCEW/P-IV/STR/2019/1294 1294 Box culvert Km 200+200 LHS 31-May-19 3:30 PM DONE
-2. Segment
Checking for NO-34,35.
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1327 NMSCEW/P-IV/STR/2019/1295 1295 Box culvert Km 200+200 LHS 31-May-19 4:25 PM DONE
(2×2),(Cushion 2 to 4m) at precast yard camp-2,Segment no.-34,35.
1328 NMSCEW/P-IV/STR/2019/1296 1296 Checking layout ,level and structural excavation at RP4 Viaduct Km 195+900 RHS 31-May-19 10:00 AM IPC-04 DONE
1329 NMSCEW/P-IV/STR/2019/1297 1297 Checking top Level & Laying concrete PCC at RP4 Viaduct Km 195+900 RHS 31-May-19 10:30 AM IPC-04 DONE
1330 NMSCEW/P-IV/STR/2019/1298 1298 Checking layout ,level and structural excavation at LP1 Viaduct Km 200+980 LHS 31-May-19 3:00 PM IPC-08 DONE
1331 NMSCEW/P-IV/STR/2019/1299 1299 Checking top Level & Laying concrete PCC at LP1 Viaduct Km 200+980 LHS 31-May-19 3:30 PM IPC-08 DONE
1332 NMSCEW/P-IV/STR/2019/1300 1300 Checking layout ,level and structural excavation Box culvert Km 171+334 BHS 31-May-19 9:30 AM IPC-08 DONE
1333 NMSCEW/P-IV/STR/2019/1301 1301 Checking top Level & Laying concrete PCC at B/C Box culvert Km 171+334 BHS 31-May-19 11:12 AM IPC-08 DONE
1334 NMSCEW/P-IV/STR/2019/1302 1302 Checking of reinforcement and shuttering for raft at RP4 Viaduct Km 202+190 RHS 31-May-19 5:00 PM IPC-04 DONE
1335 NMSCEW/P-IV/STR/2019/1303 1303 Checking and Pouring of concrete(M-35) for raft at RP4 Viaduct Km 202+190 RHS 31-May-19 6:00 PM IPC-04 DONE
1336 NMSCEW/P-IV/STR/2019/1304 1304 Checking of reinforcement & shuttering for 1st lift A1 & A2 wall PUP Km 174+095 LHS 31-May-19 6:00 PM NR
1337 NMSCEW/P-IV/STR/2019/1305 1305 Checking and pouring concrete(M-30) for 1st lift A1 & A2 wall PUP Km 174+095 LHS 31-May-19 6:30 PM NR
1338 NMSCEW/P-IV/STR/2019/1306 1306 Checking of reinforcement & shuttering for 1st lift A2 wall VUP Km 176+614 LHS 31-May-19 10:35 AM NR
1339 NMSCEW/P-IV/STR/2019/1307 1307 Checking and pouring concrete(M-35) for 1st lift A2 wall VUP Km 176+614 LHS 31-May-19 11:10 AM NR
1340 NMSCEW/P-IV/STR/2019/1308 1308 Checking layout ,level and structural excavation Box culvert Km 179+715 BHS 31-May-19 8:22 AM NR
1341 NMSCEW/P-IV/STR/2019/1309 1309 Checking layout ,level and structural excavation Box culvert Km 200+286 BHS 31-May-19 1:00 PM REPEATED
1342 NMSCEW/P-IV/STR/2019/1310 1310 Checking reinforcement, shuttering for final lift with top haunch and top slab at wall A1 & A2 PUP Km 188+575 LHS 31-May-19 12:00 AM IPC-03 DONE
1343 NMSCEW/P-IV/STR/2019/1311 1311 Checking & pouring concrete for top haunch & top slab at wall A1 & A2. PUP Km 188+575 LHS 31-May-19 12:00 AM IPC-03 DONE
1344 NMSCEW/P-IV/STR/2019/1312 1312 Checking of reinforcement & shuttering for 1st lift A1 & A2 wall CUP Km 186+000 LHS 31-May-19 4:40 PM NR
1345 NMSCEW/P-IV/STR/2019/1313 1313 Checking & pouring concrete for Final lift with top haunch & top slab at wall A1 & A2. PUP Km 171+110 RHS 31-May-19 12:00 AM IPC-03 DONE
1346 NMSCEW/P-IV/STR/2019/1314 1314 Checking and pouring concrete(M-30) for 1st lift A1 & A2 wall CUP Km 186+000 LHS 31-May-19 5:10 PM NR
1347 NMSCEW/P-IV/STR/2019/1315 1315 Checking top Level & Laying concrete(M-10) PCC at Utility duct Utility duct Km 165+020 BHS 31-May-19 10:18 AM DONE
1348 NMSCEW/P-IV/STR/2019/1316 1316 Checking layout ,level and structural excavation Utility duct Km 203+980 Km 00+000 BHS 31-May-19 5:21 PM IPC-09 DONE
1349 NMSCEW/P-IV/STR/2019/1317 1317 Checking reinforcement ,shuttering for top slab of pup PUP Km 205+430 LHS 31-May-19 11:32 AM IPC-04 DONE
1350 NMSCEW/P-IV/STR/2019/1318 1318 Checking reinforcement, shuttering for final lift with top haunch and top slab at wall A1 & A2 PUP Km 171+110 RHS 31-May-19 12:00 AM IPC-03 DONE
1351 NMSCEW/P-IV/STR/2019/1319 1319 Checking and concrete pouring for top slab of pup PUP Km 205+430 LHS 31-May-19 2:00 PM IPC-04 DONE
1352 NMSCEW/P-IV/STR/2019/1320 1320 Checking of reinforcement & shuttering for 1st lift W2 wall PUP Km 204+470 RHS 31-May-19 9:05 AM DONE
1353 NMSCEW/P-IV/STR/2019/1321 1321 Checking reinforcement, shuttering for final lift with top haunch and top slab at wall A1 & A2 PUP Km 172+190 LHS 31-May-19 12:00 AM IPC-03 DONE
1354 NMSCEW/P-IV/STR/2019/1322 1322 Checking & pouring concrete for Final lift with top haunch & top slab at wall A1 & A2. PUP Km 172+190 LHS 31-May-19 12:00 AM IPC-03 DONE
1355 NMSCEW/P-IV/STR/2019/1323 1323 Checking and concrete pouring for deck slab of cup CUP Km 172+190 LHS 31-May-19 5:52 PM
1356 NMSCEW/P-IV/STR/2019/1324 1324 Checking for reinforcement & shuttering of second lift of A1 &A2 wall PUP Km 186+000 LHS 31-May-19 12:00 AM IPC-03 DONE
1357 NMSCEW/P-IV/STR/2019/1325 1325 Checking for reinforcement & shuttering of final of A1 &A2 wall PUP Km 186+000 LHS 31-May-19 12:00 AM IPC-03 DONE
1358 NMSCEW/P-IV/STR/2019/1326 1326 Checking of reinforcement and shuttering for raft at LP5 Viaduct Km 169+800 LHS 31-May-19 4:12 PM NR SPOT RFI
1359 NMSCEW/P-IV/STR/2019/1327 1327 Checking and Pouring of concrete for raft at LP5 Viaduct Km 169+800 LHS 31-May-19 5:08 PM NR SPOT RFI
1360 NMSCEW/P-IV/STR/2019/1328 1328 Checking of reinforcement and shuttering for raft at LP1 Viaduct Km 169+800 LHS 31-May-19 5:22 PM NR SPOT RFI
1361 NMSCEW/P-IV/STR/2019/1329 1329 Checking and Pouring of concrete for raft at LP1 Viaduct Km 169+800 LHS 31-May-19 6:02 PM NR SPOT RFI
1362 NMSCEW/P-IV/STR/2019/1324A 1324A Checking Top level and pouring concrete second lift for wall A1 & A2 PUP Km 186+000 LHS 31-May-19 IPC-03 DONE
1363 NMSCEW/P-IV/STR/2019/1325A 1325A Checking Top level and pouring concrete final lift for wall A1 & A2 PUP Km 186+000 LHS 31-May-19 IPC-03 DONE
1364 NMSCEW/P-IV/STR/2019/1330 1330 Checking layout ,level and structural excavation at RP5 Viaduct Km 195+900 RHS 1-Jun-19 11:00 AM IPC-08 DONE
1365 NMSCEW/P-IV/STR/2019/1331 1331 Checking top Level & Laying concrete PCC at RP5 Viaduct Km 195+900 RHS 1-Jun-19 12:00 PM IPC-08 DONE
1366 NMSCEW/P-IV/STR/2019/1332 1332 Checking of reinforcement and shuttering for pier shaft 1st lift at RP3 Viaduct Km 169+800 RHS 1-Jun-19 3:00 PM NR
1367 NMSCEW/P-IV/STR/2019/1333 1333 Checking and Pouring concrete for pier shaft 1st lift at RP3 Viaduct Km 169+800 RHS 1-Jun-19 5:00 PM NR
1368 NMSCEW/P-IV/STR/2019/1334 1334 Checking layout ,level and structural excavation Utility duct Km 166+330 BHS 1-Jun-19 9:00 AM DONE
1369 NMSCEW/P-IV/STR/2019/1335 1335 Checking top Level & Laying concrete(M-10) PCC at Utility duct Utility duct Km 166+330 BHS 1-Jun-19 11:15 AM DONE
1370 NMSCEW/P-IV/STR/2019/1336 1336 Checking of reinforcement & shuttering for 1st lift A2 wall VUP Km 176+614 LHS 1-Jun-19 11:30 AM IPC-08 DONE
1371 NMSCEW/P-IV/STR/2019/1337 1337 Checking and pouring concrete(M-35) for 1st lift A2 wall VUP Km 176+614 LHS 1-Jun-19 11:50 AM IPC-08 DONE
Checking reinforcement ,shuttering for Final lift with top haunch at wall A1 & A2 and top
1372 NMSCEW/P-IV/STR/2019/1338 1338 CUP Km 188+575 LHS 1-Jun-19 4:00 PM NR
slab of cup
Checking and concrete (M30) pouring for Final lift with top haunch at wall A1 & A2 and top
1373 NMSCEW/P-IV/STR/2019/1339 1339 CUP Km 188+575 LHS 1-Jun-19 4:30 PM DONE
slab of cup
1374 NMSCEW/P-IV/STR/2019/1340 1340 Checking reinforcement ,shuttering for Final lifth at wall A1 & A2 of cup CUP Km 186+000 LHS 1-Jun-19 2:45 PM IPC-04 DONE
1375 NMSCEW/P-IV/STR/2019/1341 1341 Checking and concrete (M30) pouring for Final lifth at wall A1 & A2 of cup CUP Km 186+000 LHS 1-Jun-19 5:15 PM IPC-04 DONE
1376 NMSCEW/P-IV/STR/2019/1342 1342 Checking for concreting around of LP1 foundation annular filling Viaduct Km 202+190 LHS 1-Jun-19 10:00 AM
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
1377 NMSCEW/P-IV/STR/2019/1343 1343 Box culvert Km 200+200 LHS 1-Jun-19 3:00 PM DONE
-2. Segment
Checking for NO-36,37.
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1378 NMSCEW/P-IV/STR/2019/1344 1344 Checking reinforcement Box culvert Km 200+200 LHS 1-Jun-19 3:50 PM DONE
(2×2) ,(Cushion 2 to 4m)for precast yard
at precast Box Culvert (2x2) (cushion
camp-2,Segment 2 to 4m) at precast yard camp
no.-36,37.
1379 NMSCEW/P-IV/STR/2019/1345 1345 -2. Segment NO-38. Box culvert Km 200+200 LHS 2-Jun-19 3:30 PM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1380 NMSCEW/P-IV/STR/2019/1346 1346 Box culvert Km 200+200 LHS 2-Jun-19 4:00 PM DONE
(2×2) ,(Cushion 2 to 4m) at precast yard camp-2,Segment no.-38.
Checking reinforcement ,shuttering for Final lift with top haunch at wall A1 & A2 and top
1381 NMSCEW/P-IV/STR/2019/1347 1347 PUP Km 171+110 RHS 2-Jun-19 3:40 PM REPEATED
slab of pup
Checking and concrete (M30) pouring for Final lift with top haunch at wall A1 & A2 and top
1382 NMSCEW/P-IV/STR/2019/1348 1348 PUP Km 171+110 RHS 2-Jun-19 4:20 PM REPEATED
slab of pup
1383 NMSCEW/P-IV/STR/2019/1349 1349 Checking for concreting(M15) around of LP5 foundation annular filling Viaduct Km 195+900 LHS 2-Jun-19 9:30 AM
1384 NMSCEW/P-IV/STR/2019/1350 1350 Checking of reinforcement and shuttering for pier shaft 1st lift at RP3 Viaduct Km 169+800 RHS 2-Jun-19 9:00 AM NR
1385 NMSCEW/P-IV/STR/2019/1351 1351 Checking and Pouring concrete for pier shaft 1st lift at RP3 Viaduct Km 169+800 RHS 2-Jun-19 9:45 AM NR
Checking reinforcement ,shuttering for Final lift with top haunch at wall A1 & A2 and top
1386 NMSCEW/P-IV/STR/2019/1352 1352 PUP Km 172+190 LHS 3-Jun-19 6:00 PM NR
slab of pup
Checking and concrete (M30) pouring for Final lift with top haunch at wall A1 & A2 and top
1387 NMSCEW/P-IV/STR/2019/1353 1353 PUP Km 172+190 LHS 3-Jun-19 6:20 PM NR
slab of pup
1388 NMSCEW/P-IV/STR/2019/1354 1354 Checking of reinforcement & shuttering for 1st lift A1& A2 wall PUP Km 174+095 RHS 3-Jun-19 3:30 PM NR
1389 NMSCEW/P-IV/STR/2019/1355 1355 Checking and pouring concrete(M-30) for 1st lift A1& A2 wall PUP Km 174+095 RHS 3-Jun-19 3:50 PM NR
Checking reinforcement for precast Box Culvert (3x3)for chainage 164+156 (cushion 2 to 4m)
1390 NMSCEW/P-IV/STR/2019/1356 1356 Box culvert Km 175+500 LHS 3-Jun-19 9:30 AM IPC-08 DONE 32, 33, 34
at precast yard
Checking camp -1. &
for shuttering Segment
PouringNO-32,33,34.
of Concreting Grade =(M-30) for Precast Box Culvert
1391 NMSCEW/P-IV/STR/2019/1357 1357 Box culvert Km 175+500 LHS 3-Jun-19 11:05 AM NR
(3×3) for chainage
Checking 164+156
reinforcement (Cushion
for precast Box2 to 4m) at(2x2)
Culvert precast
foryard camp-1,Segment
chainage no.-32,33,34.
168+020 (Cushion 2 to
1392 NMSCEW/P-IV/STR/2019/1358 1358 Box culvert Km 175+500 LHS 3-Jun-19 10:10 AM IPC-08 DONE AE 24, 25, 8
4m) at precast
Checking yard camp&-1.
for shuttering Segment
Pouring NO-24,25,Grade
of Concreting 8 =(M-30) for Precast Box Culvert
1393 NMSCEW/P-IV/STR/2019/1359 1359 Box culvert Km 175+500 LHS 3-Jun-19 4:22 PM IPC-08 DONE AE 24, 25, 8
(2×2) for chainage 168+020 (Cushion 2 to 4m) at precast yard camp-1,Segment no.-24,25,8.
1394 NMSCEW/P-IV/STR/2019/1360 1360 Checking for
Checking reinforcement
shuttering &for precastofBox
Pouring Culvert (2x2)
Concreting Gradefor chainage
=(M-30) for 168+830 (Cushion
Precast Box Culvert0 to 2m Box culvert Km 179+390 BHS 3-Jun-19 11:25 AM IPC-05 DONE
1395 NMSCEW/P-IV/STR/2019/1361 1361 (2×2) for chainage 168+830 (Cushion 0 to 2m) at precast yard camp-1,Segment no.- Box culvert Km 175+500 LHS 3-Jun-19 5:50 PM NR
1396 NMSCEW/P-IV/STR/2019/1362 1362 23,24,25,26.
Checking layout ,level and structural excavation at RP11 Viaduct Km 202+190 Km 00+000 RHS 3-Jun-19 10:00 AM IPC-10 DONE
1397 NMSCEW/P-IV/STR/2019/1363 1363 Checking top Level & Laying concrete PCC at RP11 Viaduct Km 202+190 Km 00+000 RHS 3-Jun-19 10:30 AM IPC-10 DONE
1398 NMSCEW/P-IV/STR/2019/1364 1364 Checking of reinforcement and shuttering for raft at RP6 Viaduct Km 195+900 RHS 3-Jun-19 3:05 PM
1399 NMSCEW/P-IV/STR/2019/1365 1365 Checking and Pouring of concrete for raft at RP6 Viaduct Km 195+900 RHS 3-Jun-19 3:35 PM
1400 NMSCEW/P-IV/STR/2019/1366 1366 Checking of reinforcement and shuttering for pier shaft 1st lift at RP4 Viaduct Km 169+800 RHS 3-Jun-19 9:00 AM NR
1401 NMSCEW/P-IV/STR/2019/1367 1367 Checking and Pouring concrete for pier shaft 1st lift at RP4 Viaduct Km 169+800 RHS 3-Jun-19 9:30 AM NR
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
1402 NMSCEW/P-IV/STR/2019/1368 1368 Box culvert Km 200+200 LHS 3-Jun-19 3:25 PM
-2. Segment
Checking for NO-39,40,41.
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1403 NMSCEW/P-IV/STR/2019/1369 1369 Box culvert Km 200+200 LHS 3-Jun-19 4:21 PM
(2×2) ,(Cushion 2 to 4m) at precast yard camp-2,Segment no.-39,40,41.
1404 NMSCEW/P-IV/STR/2019/1370 1370 Checking of reinforcement and shuttering for pier shaft 1st lift at RP3 Viaduct Km 169+800 Km 00+000 RHS 3-Jun-19 9:00 AM IPC-09 DONE
1405 NMSCEW/P-IV/STR/2019/1371 1371 Checking and Pouring concrete for pier shaft 1st lift at RP3 Viaduct Km 169+800 Km 00+000 RHS 3-Jun-19 9:45 AM IPC-09 DONE AE
1406 NMSCEW/P-IV/STR/2019/1372 1372 Checking reinforcement ,shuttering for top slab of pup PUP Km 205+430 RHS 4-Jun-19 3:00 PM IPC-04 DONE
1407 NMSCEW/P-IV/STR/2019/1373 1373 Checking and concrete pouring for top slab of pup PUP Km 205+430 RHS 4-Jun-19 3:30 PM WRONG RFI
1408 NMSCEW/P-IV/STR/2019/1374 1374 Checking of reinforcement & shuttering for 3rd lift W1& W2 wall PUP Km 205+430 Km 00+000 RHS 4-Jun-19 3:45 PM IPC-03 DONE
1409 NMSCEW/P-IV/STR/2019/1375 1375 Checking and pouring concrete for 3rd lift W1& W2 wall PUP Km 205+430 Km 00+000 RHS 4-Jun-19 4:15 PM IPC-03 DONE
1410 NMSCEW/P-IV/STR/2019/1376 1376 Checking of reinforcement & shuttering for 2nd lift W1 wall PUP Km 204+470 RHS 4-Jun-19 2:00 PM DONE
1411 NMSCEW/P-IV/STR/2019/1377 1377 Checking and pouring concrete for 2nd lift W1 wall PUP Km 204+470 RHS 4-Jun-19 3:15 PM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1412 NMSCEW/P-IV/STR/2019/1378 1378 Box culvert Km 175+500 LHS 4-Jun-19 9:00 AM IPC-08 DONE 32, 33, 34
(3×3) for chainage 164+156 (Cushion 2 to 4m) at precast yard camp-1,Segment no.-32,33,34.
1413 NMSCEW/P-IV/STR/2019/1379 1379 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2×2 Box culvert Km 179+390 BHS 4-Jun-19 4:00 PM IPC-05 DONE
1414 NMSCEW/P-IV/STR/2019/1380 1380 Checking layout ,level and structural excavation at Utility duct Utility duct Km 166+710 BHS 4-Jun-19 10:30 AM DONE
1415 NMSCEW/P-IV/STR/2019/1381 1381 Checking top Level & Laying concrete PCC(M-10) at Utility duct Utility duct Km 166+710 BHS 4-Jun-19 12:32 PM DONE
1416 NMSCEW/P-IV/STR/2019/1382 1382 Checking of reinforcement and shuttering for raft at RP6 Viaduct Km 195+900 RHS 4-Jun-19 3:05 PM
1417 NMSCEW/P-IV/STR/2019/1383 1383 Checking and Pouring of concrete for raft at RP6 Viaduct Km 195+900 RHS 4-Jun-19 3:40 PM
1418 NMSCEW/P-IV/STR/2019/1384 1384 Checking layout ,level and structural excavation at RP6 Viaduct Km 195+900 RHS 4-Jun-19 10:02 AM IPC-04 DONE
1419 NMSCEW/P-IV/STR/2019/1384A 1384A Checking level for excavated bed for at RP6 Viaduct Km 195+900 RHS 4-Jun-19 10:02 AM IPC-04 DONE
1420 NMSCEW/P-IV/STR/2019/1385 1385 Checking top Level & Laying concrete PCC at RP6 Viaduct Km 195+900 RHS 4-Jun-19 10:32 AM IPC-04 DONE AE
1421 NMSCEW/P-IV/STR/2019/1386 1386 Checking layout ,level and structural excavation at RP6 Viaduct Km 202+190 RHS 4-Jun-19 10:46 AM
1422 NMSCEW/P-IV/STR/2019/1387 1387 Checking top Level & Laying concrete PCC at RP6 Viaduct Km 202+190 RHS 4-Jun-19 11:11 AM
1423 NMSCEW/P-IV/STR/2019/1388 1388 Checking layout ,level and structural excavation at LP2 Viaduct Km 196+560 LHS 4-Jun-19 10:15 AM
1424 NMSCEW/P-IV/STR/2019/1389 1389 Checking top Level & Laying concrete PCC at LP2 Viaduct Km 196+560 LHS 4-Jun-19 10:50 AM
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
1425 NMSCEW/P-IV/STR/2019/1390 1390 Box culvert Km 200+200 LHS 4-Jun-19 4:12 PM DONE
-2. Segment
Checking for NO-42,43.
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1426 NMSCEW/P-IV/STR/2019/1391 1391 Box culvert Km 200+200 LHS 4-Jun-19 5:32 PM DONE
(2×2) ,(Cushion
Checking 2 to 4m),shuttering
reinforcement at precast yard camp-2,Segment
for Final no.-42,43.
lift with top haunch at wall A1 & A2 and top
1427 NMSCEW/P-IV/STR/2019/1392 1392 PUP Km 172+190 LHS 4-Jun-19 6:00 PM REPEATED
slab of pup
Checking and concrete (M30) pouring for Final lift with top haunch at wall A1 & A2 and top
1428 NMSCEW/P-IV/STR/2019/1393 1393 PUP Km 172+190 LHS 4-Jun-19 6:20 PM REPEATED
slab of pup
1429 NMSCEW/P-IV/STR/2019/1394 1394 Checking of reinforcement & shuttering for 1st lift A1& A2 wall PUP Km 174+095 LHS 4-Jun-19 9:10 AM IPC-04 DONE
1430 NMSCEW/P-IV/STR/2019/1395 1395 Checking and pouring concrete(M-30) for 1st lift A1& A2 wall PUP Km 174+095 LHS 4-Jun-19 9:45 AM IPC-04 DONE
1431 NMSCEW/P-IV/STR/2019/1396 1396 Checking of reinforcement and shuttering for pier shaft 1st lift at RP4 Viaduct Km 169+800 RHS 4-Jun-19 4:02 PM IPC-08 DONE
1432 NMSCEW/P-IV/STR/2019/1397 1397 Checking and Pouring concrete for pier shaft 1st lift at RP4 Viaduct Km 169+800 RHS 4-Jun-19 5:01 PM IPC-08 DONE
1433 NMSCEW/P-IV/STR/2019/1398 1398 Checking of reinforcement and shuttering for raft at RP7 Viaduct Km 202+190 RHS 5-Jun-19 10:00 AM IPC-04 DONE AE
1434 NMSCEW/P-IV/STR/2019/1399 1399 Checking and Pouring of concrete(M-35) for raft at RP7 Viaduct Km 202+190 RHS 5-Jun-19 11:00 AM IPC-04 DONE AE
1435 NMSCEW/P-IV/STR/2019/1400 1400 Checking of reinforcement and shuttering for raft at LP1 Viaduct Km 169+800 LHS 5-Jun-19 4:00 PM NR
1436 NMSCEW/P-IV/STR/2019/1401 1401 Checking and Pouring of concrete for raft at LP1 Viaduct Km 169+800 LHS 5-Jun-19 5:00 PM NR
1437 NMSCEW/P-IV/STR/2019/1402 1402 Checking of reinforcement and shuttering for raft at LP6 Viaduct Km 195+900 LHS 5-Jun-19 10:15 AM
1438 NMSCEW/P-IV/STR/2019/1403 1403 Checking and Pouring of concrete(M-35) for raft at LP6 Viaduct Km 195+900 LHS 5-Jun-19 11:15 AM
1439 NMSCEW/P-IV/STR/2019/1404 1404 Checking layout ,level and structural excavation at RP7 Viaduct Km 195+900 RHS 5-Jun-19 10:30 AM IPC-04 DONE
1440 NMSCEW/P-IV/STR/2019/1404A 1404A Checking level for excavated bed for at RP7 Viaduct Km 195+900 RHS 5-Jun-19 10:30 AM IPC-04 DONE
1441 NMSCEW/P-IV/STR/2019/1405 1405 Checking top Level & Laying concrete PCC at RP7 Viaduct Km 195+900 RHS 5-Jun-19 11:30 AM IPC-04 DONE
1442 NMSCEW/P-IV/STR/2019/1406 1406 Checking layout ,level and structural excavation at LP2 Viaduct Km 196+560 LHS 5-Jun-19 11:45 AM
1443 NMSCEW/P-IV/STR/2019/1407 1407 Checking top Level & Laying concrete PCC at LP2 Viaduct Km 196+560 LHS 5-Jun-19 12:30 PM
1444 NMSCEW/P-IV/STR/2019/1408 1408 Checking layout ,level and structural excavation at Utility duct Utility duct Km 167+250 BHS 5-Jun-19 11:42 AM DONE
Checking reinforcement for precast Box Culvert (3x3)for chainage 164+156 (cushion 2 to 4m)
1445 NMSCEW/P-IV/STR/2019/1409 1409 Box culvert Km 175+500 LHS 5-Jun-19 9:30 AM IPC-08 DONE 35, 36
at precast yard
Checking camp -1. &
for shuttering Segment
PouringNO-35,36
of Concreting Grade =(M-30) for Precast Box Culvert
1446 NMSCEW/P-IV/STR/2019/1410 1410 Box culvert Km 175+500 LHS 5-Jun-19 11:05 AM IPC-08 DONE 35
(3×3) for chainage
Checking 164+156
reinforcement (Cushion
for precast Box2 to 4m) at(2x2)
Culvert precast
foryard camp-1,Segment
chainage no.-35,36
168+020 (Cushion 2 to
1447 NMSCEW/P-IV/STR/2019/1411 1411 Box culvert Km 175+500 LHS 5-Jun-19 10:10 AM IPC-08 DONE AE 27, 28, 29
4m) at precast
Checking yard camp&-1.
for shuttering Segment
Pouring NO-27,28,29
of Concreting Grade =(M-30) for Precast Box Culvert
1448 NMSCEW/P-IV/STR/2019/1412 1412 Box culvert Km 175+500 LHS 5-Jun-19 4:22 PM IPC-08 DONE AE 27, 28, 29
(2×2) for chainage 168+020 (Cushion
Checking reinforcement for precast Box 2 to 4m) at(2x2)
Culvert precast
foryard camp-1,Segment
chainage no.-27,28,29
168+830 (Cushion 0 to
1449 NMSCEW/P-IV/STR/2019/1413 1413 Box culvert Km 175+500 LHS 5-Jun-19 11:25 AM DONE
2m) at precast
Checking yard camp&-1.
for shuttering Segment
Pouring NO-27,28 Grade =(M-30) for Precast Box Culvert
of Concreting
1450 NMSCEW/P-IV/STR/2019/1414 1414 Box culvert Km 175+500 LHS 5-Jun-19 5:50 PM NR
(2×2) for chainage 168+830 (Cushion 0 to 2m) at precast yard camp-1,Segment no.-27,28
1451 NMSCEW/P-IV/STR/2019/1415 1415 Checking reinforcement ,shuttering for Final lift at wall A1 & A2 PUP Km 177+810 LHS 5-Jun-19 9:30 AM NR
1452 NMSCEW/P-IV/STR/2019/1416 1416 Checking and concrete (M30) pouring for Final lift at wall A1 & A2 PUP Km 177+810 LHS 5-Jun-19 10:06 AM NR
1453 NMSCEW/P-IV/STR/2019/1417 1417 Checking reinforcement ,shuttering for 1st lift at wall A1 & A2 PUP Km 174+095 RHS 5-Jun-19 4:05 PM NR
1454 NMSCEW/P-IV/STR/2019/1418 1418 Checking and concrete (M30) pouring for 1st lift at wall A1 & A2 PUP Km 174+095 RHS 5-Jun-19 4:42 PM NR
1455 NMSCEW/P-IV/STR/2019/1419 1419 Checking reinforcement ,shuttering for top haunch at wall A1 & A2 and top slab of pup PUP Km 177+810 LHS 5-Jun-19 5:01 PM NR
1456 NMSCEW/P-IV/STR/2019/1420 1420 Checking and concrete (M30) pouring for top haunch at wall A1 & A2 and top slab of pup PUP Km 177+810 LHS 5-Jun-19 5:50 PM NR
1457 NMSCEW/P-IV/STR/2019/1421 1421 Checking and concrete pouring for top slab of pup PUP Km 205+430 RHS 5-Jun-19 9:00 AM IPC-04 DONE
1458 NMSCEW/P-IV/STR/2019/1422 1422 Checking of reinforcement & shuttering for 1st lift W1 wall CUP Km 208+930 LHS 5-Jun-19 11:02 AM IPC-04 DONE
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
1459 NMSCEW/P-IV/STR/2019/1423 1423 Box culvert Km 200+200 LHS 5-Jun-19 3:30 PM DONE
-2. Segment
Checking for NO-44,45,46.
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1460 NMSCEW/P-IV/STR/2019/1424 1424 Box culvert Km 200+200 LHS 5-Jun-19 5:11 PM DONE
(2×2) ,(Cushion 2 to 4m) at precast yard camp-2,Segment no.-44,45,46.
1461 NMSCEW/P-IV/STR/2019/1422-A 1422-A Checking and concrete pouring or 1st lift W1 wall CUP Km 208+930 Km 00+000 LHS 5-Jun-19 2:00 PM IPC-04 DONE
1462 NMSCEW/P-IV/STR/2019/1425 1425 Checking of reinforcement and shuttering for raft at LP6 Viaduct Km 195+900 LHS 6-Jun-19 3:00 PM IPC-04 DONE AE
1463 NMSCEW/P-IV/STR/2019/1426 1426 Checking and Pouring of concrete for raft at LP6 Viaduct Km 195+900 LHS 6-Jun-19 3:30 PM IPC-04 DONE AE
1464 NMSCEW/P-IV/STR/2019/1427 1427 Checking layout ,level and structural excavation at LP2 Viaduct Km 196+560 LHS 6-Jun-19 11:00 AM
1465 NMSCEW/P-IV/STR/2019/1428 1428 Checking top Level & Laying concrete PCC at LP2 Viaduct Km 196+560 LHS 6-Jun-19 12:00 PM
1466 NMSCEW/P-IV/STR/2019/1429 1429 Checking layout ,level and structural excavation at RP2 Viaduct Km 202+190 RHS 6-Jun-19 2:00 PM IPC-04 DONE AE
1467 NMSCEW/P-IV/STR/2019/1429A 1429A Checking level for excavated bed for at RP 2 Viaduct Km 202+190 RHS 6-Jun-19 2:00 PM IPC-04 DONE AE
1468 NMSCEW/P-IV/STR/2019/1430 1430 Checking top Level & Laying concrete PCC at RP2 Viaduct Km 202+190 RHS 6-Jun-19 3:15 PM IPC-04 DONE
1469 NMSCEW/P-IV/STR/2019/1431 1431 Checking layout ,level and structural excavation at RP6 Viaduct Km 202+190 RHS 6-Jun-19 3:20 PM
1470 NMSCEW/P-IV/STR/2019/1432 1432 Checking top Level & Laying concrete PCC at RP6 Viaduct Km 202+190 RHS 6-Jun-19 4:10 PM
1471 NMSCEW/P-IV/STR/2019/1433 1433 Checking top Level & Laying concrete PCC(M-10) at Utility duct Utility duct Km 167+250 BHS 6-Jun-19 10:00 AM DONE
Checking reinforcement for precast Box Culvert (3x3)for chainage 164+156 (cushion 2 to 4m)
1472 NMSCEW/P-IV/STR/2019/1434 1434 Box culvert Km 175+500 LHS 6-Jun-19 9:35 AM IPC-08 DONE AE 36, 37, 38
at precast yard
Checking camp -1. &
for shuttering Segment
PouringNO-36,37,38
of Concreting Grade =(M-30) for Precast Box Culvert
1473 NMSCEW/P-IV/STR/2019/1435 1435 Box culvert Km 175+500 LHS 6-Jun-19 11:15 AM IPC-08 DONE AE 36, 37, 38
(3×3) for chainage 164+156 (Cushion 2 to 4m) at precast yard camp-1,Segment
Checking reinforcement for precast Box Culvert (2x2) for chainage 168+020 (Cushion 2 to no.-36,37,38
1474 NMSCEW/P-IV/STR/2019/1436 1436 Box culvert Km 175+500 LHS 6-Jun-19 10:15 AM IPC-08 DONE AE 26, 30
4m) at precast
Checking yard camp&-1.
for shuttering Segment
Pouring NO-26,30 Grade =(M-30) for Precast Box Culvert
of Concreting
1475 NMSCEW/P-IV/STR/2019/1437 1437 Box culvert Km 175+500 LHS 6-Jun-19 4:25 PM IPC-08 DONE AE 26, 30
(2×2) for chainage
Checking 168+020
reinforcement (Cushion
for precast Box2 to 4m) at(2x2)
Culvert precast
foryard camp-1,Segment
chainage no.-26,30
168+830 (Cushion 0 to
1476 NMSCEW/P-IV/STR/2019/1438 1438 Box culvert Km 175+500 LHS 6-Jun-19 11:46 AM IPC-08 DONE AE 29, 30
2m) at precast yard camp -1. Segment NO-29,30
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1477 NMSCEW/P-IV/STR/2019/1439 1439 Box culvert Km 175+500 LHS 6-Jun-19 5:55 PM IPC-08 DONE AE 29, 30
(2×2) for chainage 168+830 (Cushion 0 to 2m) at precast yard camp-1,Segment no.-29,30
1478 NMSCEW/P-IV/STR/2019/1440 1440 Checking reinforcement ,shuttering for 1st lift at wall A1 & A2 PUP Km 174+095 RHS 6-Jun-19 5:00 PM NR
1479 NMSCEW/P-IV/STR/2019/1441 1441 Checking and concrete (M30) pouring for 1st lift at wall A1 & A2 PUP Km 174+095 RHS 6-Jun-19 5:30 PM NR
1480 NMSCEW/P-IV/STR/2019/1442 1442 Checking of reinforcement and shuttering for raft at LP2 Viaduct Km 169+800 LHS 6-Jun-19 4:05 PM IPC-04 DONE
1481 NMSCEW/P-IV/STR/2019/1443 1443 Checking and Pouring of concrete for raft at LP2 Viaduct Km 169+800 LHS 6-Jun-19 5:05 PM IPC-04 DONE
1482 NMSCEW/P-IV/STR/2019/1444 1444 Checking reinforcement ,shuttering for Final lift at wall A1 & A2 of pup PUP Km 177+810 LHS 6-Jun-19 9:30 AM REPEATED
1483 NMSCEW/P-IV/STR/2019/1445 1445 Checking and concrete (M30) pouring for Final lift at wall A1 & A2 of pup PUP Km 177+810 LHS 6-Jun-19 10:01 AM REPEATED
1484 NMSCEW/P-IV/STR/2019/1446 1446 Checking reinforcement ,shuttering for top haunch at wall A1 & A2 and top slab of pup PUP Km 177+810 LHS 6-Jun-19 5:15 PM REPEATED
1485 NMSCEW/P-IV/STR/2019/1447 1447 Checking and concrete (M30) pouring for top haunch at wall A1 & A2 and top slab of pup PUP Km 177+810 LHS 6-Jun-19 5:28 PM REPEATED
1486 NMSCEW/P-IV/STR/2019/1448 1448 Checking reinforcement ,shuttering for 2nd Lift aW1 &W2 PUP Km 204+470 Km 00+000 RHS 7-Jun-19 8:00 AM IPC-03 DONE
1487 NMSCEW/P-IV/STR/2019/1449 1449 Checking and concrete pouring for 2nd Lift at W1 & W2 PUP Km 204+470 Km 00+000 RHS 7-Jun-19 8:30 AM IPC-03 DONE
1488 NMSCEW/P-IV/STR/2019/1450 1450 Checking reinforcement ,shuttering for 1st Lift at Wall No.-2 of pup CUP Km 208+930 LHS 7-Jun-19 2:00 PM IPC-04 DONE AE
1489 NMSCEW/P-IV/STR/2019/1451 1451 Checking and concrete pouring for 1st Lift at Wall No.-2 of pup CUP Km 208+930 LHS 7-Jun-19 3:00 PM IPC-04 DONE AE
1490 NMSCEW/P-IV/STR/2019/1452 1452 Checking reinforcement ,shuttering for 2nd Lift at Wall No.-1 of pup PUP Km 204+470 Km 00+000 LHS 7-Jun-19 10:00 AM IPC-03 DONE AE
1491 NMSCEW/P-IV/STR/2019/1453 1453 Checking and concrete pouring for 2nd Lift at Wall No.-1 of pup PUP Km 204+470 Km 00+000 LHS 7-Jun-19 11:00 AM IPC-03 DONE AE
1492 NMSCEW/P-IV/STR/2019/1454 1454 Checking reinforcement ,shuttering for 1st Lift at Wall A1 of vup VUP Km 176+614 LHS 7-Jun-19 10:30 AM NR
1493 NMSCEW/P-IV/STR/2019/1455 1455 Checking and concrete (M35) pouring for 1st Lift at Wall A1 of vup VUP Km 176+614 LHS 7-Jun-19 10:11 AM NR
1494 NMSCEW/P-IV/STR/2019/1456 1456 Checking reinforcement ,shuttering for Bottom Haunch A1 & A2 of LVUP LVUP Km 173+400 LHS 7-Jun-19 11:20 AM NR
1495 NMSCEW/P-IV/STR/2019/1457 1457 Checking and concrete (M35) pouring for Bottom Haunch A1 & A2 of LVUP LVUP Km 173+400 LHS 7-Jun-19 12:10 PM NR
1496 NMSCEW/P-IV/STR/2019/1458 1458 Checking layout ,level and structural excavation at RP6 Viaduct Km 202+190 RHS 7-Jun-19 4:00 PM
1497 NMSCEW/P-IV/STR/2019/1459 1459 Checking top Level & Laying concrete PCC at RP6 Viaduct Km 202+190 RHS 7-Jun-19 4:30 PM
1498 NMSCEW/P-IV/STR/2019/1460 1460 Checking of reinforcement and shuttering for raft at LP7 Viaduct Km 202+190 LHS 7-Jun-19 5:00 PM
1499 NMSCEW/P-IV/STR/2019/1461 1461 Checking and Pouring of concrete for raft at LP7 Viaduct Km 202+190 LHS 7-Jun-19 5:30 PM
1500 NMSCEW/P-IV/STR/2019/1462 1462 Checking layout ,level and structural excavation at LP2 Viaduct Km 196+560 LHS 7-Jun-19 11:06 AM
1501 NMSCEW/P-IV/STR/2019/1463 1463 Checking top Level & Laying concrete PCC at LP2 Viaduct Km 196+560 LHS 7-Jun-19 11:48 AM
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
1502 NMSCEW/P-IV/STR/2019/1464 1464 Box culvert Km 200+200 LHS 7-Jun-19 2:38 PM DONE
-2. Segment
Checking for NO-47,48.
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1503 NMSCEW/P-IV/STR/2019/1465 1465 Box culvert Km 200+200 LHS 7-Jun-19 3:25 PM DONE
(2×2) ,(Cushion 2 to 4m) at precast yard camp-2,Segment no.-47,48.
1504 NMSCEW/P-IV/STR/2019/1466 1466 Checking layout ,level and structural excavation for Box culvert Box culvert Km 198+478 Km 00+000 BHS 7-Jun-19 2:10 PM IPC-11 Approved
1505 NMSCEW/P-IV/STR/2019/1467 1467 Checking top Level & Laying concrete PCC for Box culvert Box culvert Km 198+478 Km 00+000 BHS 7-Jun-19 4:32 PM IPC-11 Approved
1506 NMSCEW/P-IV/STR/2019/1468 1468 Checking layout ,level and structural excavation for Box culvert Box culvert Km 211+335 BHS 7-Jun-19 3:18 PM DONE
1507 NMSCEW/P-IV/STR/2019/1469 1469 Checking top Level & Laying concrete PCC for Box culvert Box culvert Km 211+335 BHS 7-Jun-19 4:06 PM DONE
Checking reinforcement for precast Box Culvert (3x3) (cushion 0 to 2m) at precast yard camp
1508 NMSCEW/P-IV/STR/2019/1470 1470 Box culvert Km 200+200 LHS 7-Jun-19 3:14 PM DONE
-2. Segment
Checking for NO-21,22.
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1509 NMSCEW/P-IV/STR/2019/1471 1471 Box culvert Km 200+200 LHS 7-Jun-19 4:12 PM DONE
(3x3) ,(Cushion 0 to 2m) at precast yard camp-2,Segment no.-21,22.
1510 NMSCEW/P-IV/STR/2019/1472 1472 Checking of reinforcement and shuttering for raft at PUP PUP Km 203+560 LHS 8-Jun-19 4:00 PM IPC-04 DONE
1511 NMSCEW/P-IV/STR/2019/1473 1473 Checking and Pouring of concrete for raft at PUP PUP Km 203+560 LHS 8-Jun-19 5:00 PM IPC-04 DONE
1512 NMSCEW/P-IV/STR/2019/1474 1474 Checking layout ,level and structural excavation at LP2 Viaduct Km 196+560 LHS 8-Jun-19 11:00 AM IPC-05 DONE AE
1513 NMSCEW/P-IV/STR/2019/1475 1475 Checking top Level & Laying concrete PCC at LP2 Viaduct Km 196+560 LHS 8-Jun-19 12:00 PM IPC-05 DONE AE
1514 NMSCEW/P-IV/STR/2019/1476 1476 Checking of reinforcement and shuttering for raft at LP7 Viaduct Km 202+190 LHS 8-Jun-19 4:00 PM IPC-04 DONE AE
1515 NMSCEW/P-IV/STR/2019/1477 1477 Checking and Pouring of concrete(M-35) for raft at LP7 Viaduct Km 202+190 LHS 8-Jun-19 4:30 PM IPC-04 DONE AE
1516 NMSCEW/P-IV/STR/2019/1477A 1477A Checking of layout and level for LP2 Viaduct Km 202+190 LHS 8-Jun-19 10:00 AM IPC-04 DONE
1517 NMSCEW/P-IV/STR/2019/1477B 1477B Checking level for excavated bed for LP2 Viaduct Km 202+190 LHS 8-Jun-19 12:00 PM IPC-04 DONE
1518 NMSCEW/P-IV/STR/2019/1477C 1477C Laying and top level checking of concrete for PCC for LP2 Viaduct Km 202+190 LHS 8-Jun-19 4:10 PM IPC-04 DONE
1519 NMSCEW/P-IV/STR/2019/1478 1478 Checking of reinforcement & shuttering for bottom slab & haunch at CUP CUP Km 183+290 RHS 8-Jun-19 4:45 PM IPC-04 DONE
1520 NMSCEW/P-IV/STR/2019/1479 1479 Checking and pouring concrete(M-30) for bottom slab at CUP CUP Km 183+290 RHS 8-Jun-19 5:10 PM IPC-04 DONE
1521 NMSCEW/P-IV/STR/2019/1480 1480 Checking of reinforcement & shuttering for bottom slab at CUP CUP Km 188+575 RHS 8-Jun-19 6:00 PM NR
1522 NMSCEW/P-IV/STR/2019/1481 1481 Checking and
Checking pouring concrete(M-30)
reinforcement for precast Box for bottom
Culvert slab
(3x3) at CUP2m to 4m) for Ch 164+156 at
(cushion CUP Km 188+575 RHS 8-Jun-19 6:30 PM NR
1523 NMSCEW/P-IV/STR/2019/1482 1482 precast yard camp -1. Segment NO-39,40,41 Box culvert Km 175+500 LHS 8-Jun-19 9:15 AM IPC-08 DONE 39, 40, 41
Checking for shuttering & Pouring of Concreting Grade (M-30) for Precast Box Culvert
1524 NMSCEW/P-IV/STR/2019/1483 1483 Checking reinforcement Box culvert Km 175+500 LHS 8-Jun-19 9:30 AM IPC-08 DONE 39, 40
(3x3) , (cushion 2m to 4m)for forprecast Box Culvert
Ch 164+156 (2x2)
at precast (cushion
yard 2mSegment
camp -1. to 4m) for Ch 168+020
NO-39,40,41
1525 NMSCEW/P-IV/STR/2019/1484 1484 at precast yard camp -1. Segment NO-31,32 Box culvert Km 175+500 LHS 8-Jun-19 11:30 AM IPC-08 DONE AE 31, 32
Checking for shuttering & Pouring of Concreting Grade (M-30) for Precast Box Culvert
1526 NMSCEW/P-IV/STR/2019/1485 1485 Checking reinforcement Box culvert Km 175+500 LHS 8-Jun-19 4:15 PM IPC-08 DONE AE 31, 32
(2×2) , (cushion 2m to 4m)for forprecast Box Culvert
Ch 168+020 (2x2)yard
at precast (cushion
camp0-1.
to Segment
2m) for Ch 163+830 at
NO-31,32
1527 NMSCEW/P-IV/STR/2019/1486 1486 precast yard camp -1. Segment NO-31,32 Box culvert Km 175+500 LHS 8-Jun-19 12:30 PM IPC-08 DONE AE 31, 32
Checking for shuttering & Pouring of Concreting Grade (M-30) for Precast Box Culvert
1528 NMSCEW/P-IV/STR/2019/1487 1487 Box culvert Km 175+500 LHS 8-Jun-19 5:02 PM IPC-08 DONE AE 31, 32
(2×2) , (cushion 0 to 2m) for Ch 163+830 at precast yard camp -1. Segment NO-31,32
1529 NMSCEW/P-IV/STR/2019/1488 1488 Checking reinforcement ,shuttering for 1st Lift at Wall A1& A2 of Pup PUP Km 174+095 RHS 8-Jun-19 9:00 AM IPC-04 DONE
1530 NMSCEW/P-IV/STR/2019/1489 1489 Checking and concrete (M30) pouring for 1st Lift at Wall A1 & A2 of Pup PUP Km 174+095 RHS 8-Jun-19 9:40 AM IPC-04 DONE
1531 NMSCEW/P-IV/STR/2019/1490 1490 Checking reinforcement ,shuttering for 1st Lift at Wall A1 of LVUP LVUP Km 176+614 LHS 8-Jun-19 8:00 AM IPC-08 DONE
1532 NMSCEW/P-IV/STR/2019/1491 1491 Checking and concrete (M35) pouring for 1st Lift at Wall A1 of LVUP LVUP Km 176+614 LHS 8-Jun-19 8:30 AM IPC-08 DONE
1533 NMSCEW/P-IV/STR/2019/1492 1492 Checking reinforcement ,shuttering for bottom haunch A1 & A2 of LVUP LVUP Km 173+400 RHS 8-Jun-19 10:12 AM NR
1534 NMSCEW/P-IV/STR/2019/1493 1493 Checking and concrete (M35) pouring for bottom haunch A1 & A2 of LVUP LVUP Km 173+400 RHS 8-Jun-19 10:38 AM NR
1535 NMSCEW/P-IV/STR/2019/1494 1494 Checking layout ,level and structural excavation at Utility duct Utility duct Km 169+000 BHS 9-Jun-19 10:00 AM NR
1536 NMSCEW/P-IV/STR/2019/1495 1495 Checking reinforcement ,shuttering for 2nd Lift at Wall A2 of VUP VUP Km 176+614 LHS 9-Jun-19 10:30 AM NR
1537 NMSCEW/P-IV/STR/2019/1496 1496 Checking and concrete (M35) pouring for for 2nd Lift at Wall A2 of VUP VUP Km 176+614 LHS 9-Jun-19 10:50 AM NR
1538 NMSCEW/P-IV/STR/2019/1497 1497 Checking reinforcement ,shuttering for 2nd Lift at Wall A1& A2 of Pup PUP Km 174+095 RHS 9-Jun-19 2:30 PM NR
1539 NMSCEW/P-IV/STR/2019/1498 1498 Checking and concrete (M30) pouring for 2nd Lift at Wall A1 & A2 of Pup PUP Km 174+095 RHS 9-Jun-19 3:15 PM NR
1540 NMSCEW/P-IV/STR/2019/1499 1499 Checking reinforcement ,shuttering for top haunch at wall A1 & A2 and top slab of Cup CUP Km 184+235 RHS 9-Jun-19 4:30 PM REPEATED
1541 NMSCEW/P-IV/STR/2019/1500 1500 Checking and concrete (M30) pouring for top haunch at wall A1 & A2 and top slab of Cup CUP Km 184+235 RHS 9-Jun-19 5:00 PM REPEATED
1542 NMSCEW/P-IV/STR/2019/1501 1501 Checking of reinforcement & shuttering for bottom slab at CUP CUP Km 188+575 RHS 9-Jun-19 8:30 AM IPC-04 DONE
1543 NMSCEW/P-IV/STR/2019/1502 1502 Checking and pouring concrete(M-30) for bottom slab at CUP CUP Km 188+575 RHS 9-Jun-19 9:00 AM IPC-04 DONE
1544 NMSCEW/P-IV/STR/2019/1503 1503 Checking for concreting(M15) around of LP1 foundation annular filling Viaduct Km 169+800 LHS 9-Jun-19 10:10 AM NR
1545 NMSCEW/P-IV/STR/2019/1504 1504 Checking for concreting(M15) around of LP2 foundation annular filling Viaduct Km 169+800 LHS 9-Jun-19 10:40 AM NR
1546 NMSCEW/P-IV/STR/2019/1505 1505 Checking of reinforcement and shuttering for raft at PUP PUP Km 203+560 LHS 10-Jun-19 9:00 AM IPC-04 DONE
1547 NMSCEW/P-IV/STR/2019/1506 1506 Checking and Pouring of concrete for raft at PUP PUP Km 203+560 LHS 10-Jun-19 10:00 AM IPC-04 DONE
1548 NMSCEW/P-IV/STR/2019/1507 1507 Checking of reinforcement and shuttering for raft at PUP PUP Km 191+740 RHS 10-Jun-19 2:00 PM IPC-04 DONE AE
1549 NMSCEW/P-IV/STR/2019/1508 1508 Checking and Pouring of concrete for raft at PUP PUP Km 191+740 RHS 10-Jun-19 3:10 PM IPC-04 DONE AE
1550 NMSCEW/P-IV/STR/2019/1509 1509 Checking layout ,level and structural excavation for Box culvert Box culvert Km 198+478 BHS 10-Jun-19 4:20 PM WRONG RFI
1551 NMSCEW/P-IV/STR/2019/1510 1510 Checking top Level & Laying concrete PCC for Box culvert Box culvert Km 198+478 BHS 10-Jun-19 4:54 PM WRONG RFI
1552 NMSCEW/P-IV/STR/2019/1511 1511 Checking reinforcement ,shuttering for 2nd Lift at Wall A2 of VUP VUP Km 176+614 LHS 10-Jun-19 10:24 AM NR
1553 NMSCEW/P-IV/STR/2019/1512 1512 Checking and concrete (M35) pouring for 2nd Lift at Wall A2 of VUP VUP Km 176+614 LHS 10-Jun-19 10:55 AM NR
1554 NMSCEW/P-IV/STR/2019/1513 1513 Checking reinforcement ,shuttering for 2nd Lift at Wall A1 & A2 of VUP VUP Km 174+095 RHS 10-Jun-19 2:30 PM IPC-04 DONE
1555 NMSCEW/P-IV/STR/2019/1514 1514 Checking and concrete (M30) pouring for 2nd Lift at Wall A1 & A2 of VUP VUP Km 174+095 RHS 10-Jun-19 3:20 PM IPC-04 DONE
1556 NMSCEW/P-IV/STR/2019/1515 1515 Checking of reinforcement and shuttering for raft at RP6 Viaduct Km 196+560 RHS 10-Jun-19 3:40 PM
1557 NMSCEW/P-IV/STR/2019/1516 1516 Checking and Pouring of concrete for raft at RP6 Viaduct Km 196+560 RHS 10-Jun-19 4:20 PM IPC-04 DONE
1558 NMSCEW/P-IV/STR/2019/1517 1517 Checking of reinforcement and shuttering for raft at LP3 Viaduct Km 200+930 LHS 10-Jun-19 3:30 PM
1559 NMSCEW/P-IV/STR/2019/1518 1518 Checking and Pouring of concrete for raft at LP3 Viaduct Km 200+930 LHS 10-Jun-19 4:54 PM
1560 NMSCEW/P-IV/STR/2019/1519 1519 Checking layout ,level and structural excavation at LP8 Viaduct Km 195+900 LHS 10-Jun-19 11:00 AM IPC-08 DONE
1561 NMSCEW/P-IV/STR/2019/1520 1520 Checking top Level & Laying concrete PCC at LP8 Viaduct Km 195+900 LHS 10-Jun-19 11:40 AM IPC-08 DONE
Checking reinforcement for precast Box Culvert (3x3) (cushion 0 to 2m) at precast yard camp
1562 NMSCEW/P-IV/STR/2019/1521 1521 Box culvert Km 200+200 LHS 10-Jun-19 12:00 PM DONE
-2. Segment
Checking for NO-23,24
shuttering && 25..
Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1563 NMSCEW/P-IV/STR/2019/1522 1522 Box culvert Km 200+200 LHS 10-Jun-19 2:18 PM DONE
(3x3) ,(Cushion 0 to 2m) at precast yard camp-2,Segment no.-23,24 & 25.
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
1564 NMSCEW/P-IV/STR/2019/1523 1523 Box culvert Km 200+200 LHS 10-Jun-19 10:55 AM DONE
-2. Segment
Checking for NO-49,50.
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1565 NMSCEW/P-IV/STR/2019/1524 1524 Box culvert Km 200+200 LHS 10-Jun-19 2:48 PM DONE
(2×2) ,(Cushion 2 to 4m) at precast yard camp-2,Segment no.-49,50.
1566 NMSCEW/P-IV/STR/2019/1525 1525 Checking for concreting(M15) around of LP1 foundation annular filling Viaduct Km 169+800 LHS 10-Jun-19 10:11 AM DONE
1567 NMSCEW/P-IV/STR/2019/1526 1526 Checking for concreting(M15) around of LP2 foundation annular filling Viaduct Km 169+800 LHS 10-Jun-19 10:42 AM DONE
1568 NMSCEW/P-IV/STR/2019/1527 1527 Checking of reinforcement and shuttering for pier shaft stater at LP4,LP5,LP6,LP7 Viaduct Km 169+800 LHS 10-Jun-19 5:00 AM NR
1569 NMSCEW/P-IV/STR/2019/1528 1528 Checking of reinforcement and shuttering for pier shaft stater at RP6,RP7 Viaduct Km 169+800 RHS 10-Jun-19 5:10 AM NR
1570 NMSCEW/P-IV/STR/2019/1529 1529 Checking & Pouring concrete for pier shaft stater at LP4,LP5,LP6,LP7 Viaduct Km 169+800 LHS 10-Jun-19 5:40 PM NR
1571 NMSCEW/P-IV/STR/2019/1530 1530 Checking & Pouring concrete for pier shaft stater at RP6,RP7 Viaduct Km 169+800 LHS 10-Jun-19 6:00 PM NR
Checking for shuttering & Pouring of Concreting Grade (M-30) for Precast Box Culvert
1572 NMSCEW/P-IV/STR/2019/1531 1531 Checking reinforcement for precast Box Culvert (2x2) (cushion 2m to 4m) for Ch 168+020 Box culvert Km 175+500 LHS 10-Jun-19 10:00 AM IPC-08 DONE AE 41
(3x3) , (cushion 2m to 4m) for Ch 164+156 at precast yard camp -1. Segment NO-40,41
1573 NMSCEW/P-IV/STR/2019/1532 1532 at precast yard camp -1. Segment NO-33,34 Box culvert Km 175+500 LHS 10-Jun-19 4:05 PM IPC-08 DONE 33, 34
Checking for shuttering & Pouring of Concreting Grade (M-30) for Precast Box Culvert
1574 NMSCEW/P-IV/STR/2019/1533 1533 Box culvert Km 175+500 LHS 10-Jun-19 6:10 PM IPC-08 DONE 33, 34
(2×2) , (cushion 2m to 4m) for Ch 168+020 at precast yard camp -1. Segment NO-33,34
Checking reinforcement for precast Box Culvert (2x2) (cushion 0 to 2m) for Ch 163+830 at precast yard camp -1. Segment NO-33,34
1575 NMSCEW/P-IV/STR/2019/1534 1534 Box culvert Km 163+830 BHS 10-Jun-19 5:06 PM IPC-05 DONE
1576 NMSCEW/P-IV/STR/2019/1535 1535 Checking for shuttering & Pouring of Concreting Grade (M-30) for Precast Box Culvert (2×2) Box culvert Km 163+830 BHS 10-Jun-19 7:10 PM IPC-05 DONE
1577 NMSCEW/P-IV/STR/2019/1536 1536 Checking of reinforcement & shuttering for 2nd lift for W2 wall PUP Km 204+470 Km 00+000 LHS 11-Jun-19 8:00 AM IPC-03 DONE AE
1578 NMSCEW/P-IV/STR/2019/1537 1537 Checking and pouring concrete(M30) for 2nd lift for W2 wall PUP Km 204+470 Km 00+000 LHS 11-Jun-19 8:30 AM IPC-03 DONE AE
1579 NMSCEW/P-IV/STR/2019/1538 1538 Checking of reinforcement & shuttering for 1st lift for W2 wall CUP Km 208+930 RHS 11-Jun-19 8:15 AM IPC-04 DONE
1580 NMSCEW/P-IV/STR/2019/1539 1539 Checking and pouring concrete(M30) for 1st lift for W2 wall CUP Km 208+930 RHS 11-Jun-19 9:00 AM IPC-04 DONE
1581 NMSCEW/P-IV/STR/2019/1540 1540 Checking of reinforcement & shuttering for 2nd lift for W1 & W2 wall CUP Km 208+930 LHS 11-Jun-19 12:10 PM IPC-04 DONE
1582 NMSCEW/P-IV/STR/2019/1541 1541 Checking and pouring concrete(M30) for 2nd lift for W1 & W2 wall CUP Km 208+930 LHS 11-Jun-19 2:00 PM IPC-04 DONE
Checking for reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard
1583 NMSCEW/P-IV/STR/2019/1542 1542 Box culvert Km 200+200 LHS 11-Jun-19 10:00 AM DONE
camp -2. Segment NO-51.
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1584 NMSCEW/P-IV/STR/2019/1543 1543 Checking reinforcement Box culvert Km 200+200 LHS 11-Jun-19 3:00 PM DONE
(2×2) (Cushion 2 to 4m) for precastyard
at precast Boxcamp-2.,Segment
Culvert (3x3) (cushion
no.-51.2 to 4m) at precast yard camp
1585 NMSCEW/P-IV/STR/2019/1544 1544 -2. Segment NO-12. Box culvert Km 200+200 LHS 11-Jun-19 10:30 AM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1586 NMSCEW/P-IV/STR/2019/1545 1545 Box culvert Km 200+200 LHS 11-Jun-19 4:00 PM DONE
(3×3) (Cushion
Checking 2 to 4m) for
reinforcement at precast
precastyard
Boxcamp-2
Culvert,Segment no.-12.0 to 2m) at precast yard camp
(3x3) (cushion
1587 NMSCEW/P-IV/STR/2019/1546 1546 Box culvert Km 200+200 LHS 11-Jun-19 11:00 AM DONE
-2. Segment
Checking for NO-26.
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1588 NMSCEW/P-IV/STR/2019/1547 1547 Box culvert Km 200+200 LHS 11-Jun-19 5:30 PM DONE
(3×3) (Cushion 0 to 2m) at precast yard camp-2. Segment no.-26.
1589 NMSCEW/P-IV/STR/2019/1548 1548 Checking of reinforcement and shuttering for pier shaft stater at LP4,LP5,LP6,LP7 Viaduct Km 169+800 LHS 11-Jun-19 5:05 PM IPC-08 DONE
1590 NMSCEW/P-IV/STR/2019/1549 1549 Checking of reinforcement and shuttering for pier shaft stater at RP6,RP7 Viaduct Km 169+800 LHS 11-Jun-19 5:10 PM IPC-08 DONE
1591 NMSCEW/P-IV/STR/2019/1550 1550 Checking & Pouring concrete for pier shaft stater at LP4,LP5,LP6,LP7 Viaduct Km 169+800 LHS 11-Jun-19 6:00 PM IPC-08 DONE
1592 NMSCEW/P-IV/STR/2019/1551 1551 Checking & Pouring concrete for pier shaft stater at RP6,RP7 Viaduct Km 169+800 LHS 11-Jun-19 6:22 PM IPC-08 DONE
1593 NMSCEW/P-IV/STR/2019/1552 1552 Checking of reinforcement and shuttering for raft at LP11 Viaduct Km 169+800 LHS 11-Jun-19 9:05 AM IPC-04 DONE
1594 NMSCEW/P-IV/STR/2019/1553 1553 Checking and Pouring of concrete for raft at LP11 Viaduct Km 169+800 LHS 11-Jun-19 10:32 AM IPC-04 DONE
1595 NMSCEW/P-IV/STR/2019/1554 1554 Checking layout ,level and structural excavation at Utility duct Utility duct Km 169+000 BHS 11-Jun-19 10:05 AM DONE
1596 NMSCEW/P-IV/STR/2019/1555 1555 Checking top Level & Laying concrete(M-10) PCC at Utility duct Utility duct Km 169+000 BHS 11-Jun-19 10:50 AM DONE
1597 NMSCEW/P-IV/STR/2019/1556 1556 Checking bottom haunch reinforcement & shuttering for haunch A1 & A2 PUP Km 171+110 LHS 11-Jun-19 10.42 am IPC-04 DONE
1598 NMSCEW/P-IV/STR/2019/1557 1557 Checking top Level & concrete pouring(M30) of bottom haunch for wall A1 & A2 PUP Km 171+110 LHS 11-Jun-19 11.15 am IPC-04 DONE
1599 NMSCEW/P-IV/STR/2019/1558 1558 Checking reinforcement ,shuttering for 2nd Lift at Wall A2 of vup VUP Km 176+614 LHS 11-Jun-19 4:05 PM NR
1600 NMSCEW/P-IV/STR/2019/1559 1559 Checking and concrete (M35) pouring for 2nd Lift at Wall A2 of vup VUP Km 176+614 LHS 11-Jun-19 4:41 PM NR
1601 NMSCEW/P-IV/STR/2019/1560 1560 Checking of reinforcement and shuttering for raft at LP3 Viaduct Km 200+930 LHS 11-Jun-19 5:00 PM IPC-08 DONE
1602 NMSCEW/P-IV/STR/2019/1561 1561 Checking and Pouring of concrete for raft at LP3 Viaduct Km 200+930 LHS 11-Jun-19 5:15 PM IPC-08 DONE
1603 NMSCEW/P-IV/STR/2019/1562 1562 Checking layout ,level and structural excavation at RP6 Viaduct Km 202+190 RHS 12-Jun-19 10:00 AM
1604 NMSCEW/P-IV/STR/2019/1563 1563 Checking top Level & Laying concrete PCC at RP6 Viaduct Km 202+190 RHS 12-Jun-19 10:30 AM
1605 NMSCEW/P-IV/STR/2019/1564 1564 Checking layout ,level and structural excavation at RP3 Viaduct Km 196+560 RHS 12-Jun-19 11:00 AM
1606 NMSCEW/P-IV/STR/2019/1565 1565 Checking top Level & Laying concrete PCC at RP3 Viaduct Km 196+560 RHS 12-Jun-19 11:30 AM
1607 NMSCEW/P-IV/STR/2019/1566 1566 Checking of reinforcement and shuttering for raft at RP11 Viaduct Km 169+800 RHS 12-Jun-19 2:00 PM NR
1608 NMSCEW/P-IV/STR/2019/1567 1567 Checking and Pouring of concrete for raft at RP11 Viaduct Km 169+800 RHS 12-Jun-19 5:00 PM NR
1609 NMSCEW/P-IV/STR/2019/1568 1568 Checking for concreting(M15) around of RP1 foundation annular filling Viaduct Km 169+800 RHS 12-Jun-19 9:00 AM DONE
1610 NMSCEW/P-IV/STR/2019/1569 1569 Checking for concreting(M15) around of RP2 foundation annular filling Viaduct Km 169+800 RHS 12-Jun-19 9:30 AM DONE
1611 NMSCEW/P-IV/STR/2019/1570 1570 Checking top Level & Laying concrete PCC for LVUP LVUP Km 178+323 Km 00+000 LHS 12-Jun-19 10:20 AM IPC-09 DONE
1612 NMSCEW/P-IV/STR/2019/1571 1571 Checking layout ,level and structural excavation for LVUP LVUP Km 178+910 BHS 12-Jun-19 10:40 AM NR
1613 NMSCEW/P-IV/STR/2019/1572 1572 Checking reinforcement ,shuttering for 2nd Lift at Wall A2 of VUP VUP Km 176+614 LHS 12-Jun-19 12:00 PM IPC-08 DONE AE
1614 NMSCEW/P-IV/STR/2019/1573 1573 Checking and
Checking concrete pouring
reinforcement for 2nd
for precast BoxLift at Wall
Culvert A2(cushion
(3x3) of VUP 2m to 4m) at precast yard VUP Km 176+614 LHS 12-Jun-19 4:30 PM IPC-08 DONE AE
1615 NMSCEW/P-IV/STR/2019/1574 1574 camp -1. Segment NO-42,43,44 Box culvert Km 175+500 LHS 12-Jun-19 9:45 AM IPC-08 DONE AE 42, 43, 44
Checking for shuttering & Pouring of Concreting Grade (M-30) for Precast Box Culvert
1616 NMSCEW/P-IV/STR/2019/1575 1575 Checking reinforcement Box culvert Km 175+500 LHS 12-Jun-19 3:30 PM IPC-08 DONE AE 42, 43
(3x3) , (cushion 2m to 4m)foratprecast
precastBox
yardCulvert
camp -1. (2x2) (cushion
Segment 2m to 4m) for Ch 168+020
NO-42,43,44
1617 NMSCEW/P-IV/STR/2019/1576 1576 at precast yard camp -1. Segment NO-35,36,37,38 Box culvert Km 175+500 LHS 12-Jun-19 10:45 AM IPC-08 DONE 35, 36, 37, 38
Checking for shuttering & Pouring of Concreting Grade (M-30) for Precast Box Culvert
1618 NMSCEW/P-IV/STR/2019/1577 1577 Box culvert Km 175+500 LHS 12-Jun-19 4:38 PM IPC-08 DONE 35
(2×2) , (cushion
Checking 2m to 4m)for
reinforcement forprecast
Ch 168+020 at precast
Box Culvert (2x2)yard camp0-1.
(cushion to Segment NO-35,36,37
2m) for Ch 163+830 at precast yard camp -1. Segment NO-28,35,36
1619 NMSCEW/P-IV/STR/2019/1578 1578 Box culvert Km 163+830 BHS 12-Jun-19 11:46 AM IPC-05 DONE AE
1620 NMSCEW/P-IV/STR/2019/1579 1579 Checking reinforcement
Checking for shuttering &
forPouring
precast of
BoxConcreting
Culvert (2x2)Grade (M-30)2for
(cushion Precast
to 4m) Box Culvert
at precast (2×2) Box culvert
yard camp Km 163+830 BHS 12-Jun-19 5:50 PM IPC-05 DONE AE
1621 NMSCEW/P-IV/STR/2019/1580 1580 -2. Segment NO-52. Box culvert Km 200+200 LHS 12-Jun-19 10:11 AM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1622 NMSCEW/P-IV/STR/2019/1581 1581 Checking reinforcement Box culvert Km 200+200 LHS 12-Jun-19 10:44 AM DONE
(2×2),(Cushion 2 to 4m) for precastyard
at precast Boxcamp-2,Segment
Culvert (3x3) (cushion
no.-52.0 to 2m) at precast yard camp
1623 NMSCEW/P-IV/STR/2019/1582 1582 -2. Segment NO-27. Box culvert Km 200+200 LHS 12-Jun-19 4:46 PM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1624 NMSCEW/P-IV/STR/2019/1583 1583 Box culvert Km 200+200 LHS 12-Jun-19 6:00 PM DONE
(3×3) (Cushion 0 to 2m) at precast yard camp-2,Segment no.-27.
1625 NMSCEW/P-IV/STR/2019/1584 1584 Checking layout ,level and structural excavation at Utility duct Utility duct Km 168+020 Km 00+000 BHS 13-Jun-19 4:30 PM IPC-10 DONE
1626 NMSCEW/P-IV/STR/2019/1585 1585 Checking reinforcement ,shuttering for bottom slab CUP Km 183+290 LHS 13-Jun-19 4:40 PM DONE
1627 NMSCEW/P-IV/STR/2019/1586 1586 Checking and concrete (M30) pouring for bottom slab CUP Km 183+290 LHS 13-Jun-19 5:00 PM DONE
1628 NMSCEW/P-IV/STR/2019/1587 1587 Checking of reinforcement & shuttering for 1st lift A1 & A2 wall CUP Km 188+575 RHS 13-Jun-19 5:30 PM NR
1629 NMSCEW/P-IV/STR/2019/1588 1588 Checking and pouring concrete(M-30) for 1st lift A1 & A2 wall CUP Km 188+575 RHS 13-Jun-19 6:00 PM NR
1630 NMSCEW/P-IV/STR/2019/1589 1589 Checking of reinforcement and shuttering for raft at RP11 Viaduct Km 169+800 RHS 13-Jun-19 2:00 PM IPC-04 DONE
1631 NMSCEW/P-IV/STR/2019/1590 1590 Checking and Pouring of concrete(M-35) for raft at RP11 Viaduct Km 169+800 RHS 13-Jun-19 3:00 PM IPC-04 DONE
1632 NMSCEW/P-IV/STR/2019/1591 1591 Checking for concreting(M15) around of LP11 foundation annular filling Viaduct Km 169+800 LHS 13-Jun-19 9:00 AM NR
1633 NMSCEW/P-IV/STR/2019/1592 1592 Checking of reinforcement & shuttering for final lift A1 & A2 wall PUP Km 172+190 RHS 13-Jun-19 2:30 PM NR
1634 NMSCEW/P-IV/STR/2019/1593 1593 Checking and pouring concrete(M-30) for final lift A1 & A2 wall PUP Km 172+190 RHS 13-Jun-19 3:30 PM NR
1635 NMSCEW/P-IV/STR/2019/1594 1594 Checking reinforcement ,shuttering for top haunch at wall A1 & A2 and top slab of pup PUP Km 172+190 RHS 13-Jun-19 6:30 PM NR
1636 NMSCEW/P-IV/STR/2019/1595 1595 Checking and concrete (M30) pouring for top haunch at wall A1 & A2 and top slab of pup PUP Km 172+190 RHS 13-Jun-19 6:50 PM NR
1637 NMSCEW/P-IV/STR/2019/1596 1596 Checking top Level & Laying concrete PCC (M-10) for LVUP LVUP Km 178+323 RHS 13-Jun-19 4:00 PM NR
1638 NMSCEW/P-IV/STR/2019/1597 1597 Checking of reinforcement and shuttering for raft Box culvert Km 200+460 RHS 13-Jun-19 10:00 AM IPC-05 DONE
1639 NMSCEW/P-IV/STR/2019/1598 1598 Checking and Pouring of concrete for raft Box culvert Km 200+460 RHS 13-Jun-19 11:00 AM IPC-05 DONE
1640 NMSCEW/P-IV/STR/2019/1599 1599 Checking layout ,level and structural excavation at RP3 Viaduct Km 196+560 RHS 13-Jun-19 11:00 AM
1641 NMSCEW/P-IV/STR/2019/1600 1600 Checking top Level & Laying concrete PCC at RP3 Viaduct Km 196+560 RHS 13-Jun-19 11:30 AM
1642 NMSCEW/P-IV/STR/2019/1601 1601 Checking of layout and level for raft at LP4 Viaduct Km 202+190 LHS 13-Jun-19 3:05 PM IPC-04 DONE AE
1643 NMSCEW/P-IV/STR/2019/1602 1602 Checking of reinforcement and shuttering for raft at LP4 Viaduct Km 202+190 LHS 13-Jun-19 3:15 PM IPC-04 DONE AE
1644 NMSCEW/P-IV/STR/2019/1603 1603 Checking and Pouring of concrete(M-35) for raft at LP4 Viaduct Km 202+190 LHS 13-Jun-19 3:50 PM IPC-04 DONE AE
1645 NMSCEW/P-IV/STR/2019/1603A 1603A Checking of layout and level for LP3 Viaduct Km 202+190 LHS 13-Jun-19 10:00 AM IPC-04 DONE
1646 NMSCEW/P-IV/STR/2019/1603B 1603B Checking level for excavated bed for LP3 Viaduct Km 202+190 LHS 13-Jun-19 12:00 PM IPC-04 DONE
1647 NMSCEW/P-IV/STR/2019/1603C 1603C Laying and top level checking of concrete for PCC for LP3 Viaduct Km 202+190 LHS 13-Jun-19 4:10 PM IPC-04 DONE
1648 NMSCEW/P-IV/STR/2019/1604 1604 Checking of reinforcement & shuttering for 1st lift for W1 wall CUP Km 208+930 RHS 13-Jun-19 2:10 PM IPC-04 DONE AE
1649 NMSCEW/P-IV/STR/2019/1605 1605 Checking and pouring for
Checking reinforcement concrete
precastforBox
1stCulvert
lift for(3x3)
W1 wall
(cushion 0 to 2m) at precast yard camp CUP Km 208+930 RHS 13-Jun-19 2:52 PM IPC-04 DONE AE
1650 NMSCEW/P-IV/STR/2019/1606 1606 -2. Segment NO-28. Box culvert Km 200+200 LHS 13-Jun-19 3:16 PM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1651 NMSCEW/P-IV/STR/2019/1607 1607 Box culvert Km 200+200 LHS 13-Jun-19 4:48 PM DONE
(3×3) ,(Cushion 0 to 2m) at precast yard camp-2,Segment no.-28.
1652 NMSCEW/P-IV/STR/2019/1608 1608 Blank RFI Blank RFI
1653 NMSCEW/P-IV/STR/2019/1609 1609 Blank RFI Blank RFI
1654 NMSCEW/P-IV/STR/2019/1610 1610 Checking layout and level at RP7 Viaduct Km 195+900 RHS 14-Jun-19 3:00 PM
1655 NMSCEW/P-IV/STR/2019/1611 1611 Checking of reinforcement and shuttering for raft at RP7 Viaduct Km 195+900 RHS 14-Jun-19 3:15 PM IPC-04 DONE
1656 NMSCEW/P-IV/STR/2019/1612 1612 Checking and Pouring of concrete for raft at RP7 Viaduct Km 195+900 RHS 14-Jun-19 3:30 PM IPC-04 DONE
1657 NMSCEW/P-IV/STR/2019/1613 1613 Checking layout ,level and structural excavation at RP8 Viaduct Km 195+900 RHS 14-Jun-19 11:00 AM
1658 NMSCEW/P-IV/STR/2019/1614 1614 Checking top Level & Laying concrete PCC at RP8 Viaduct Km 195+900 RHS 14-Jun-19 11:30 AM
1659 NMSCEW/P-IV/STR/2019/1615 1615 Checking layout ,level at LP1 Viaduct Km 196+560 LHS 14-Jun-19 12:00 PM IPC-05 DONE
1660 NMSCEW/P-IV/STR/2019/1616 1616 Checking top Level & Laying concrete PCC at LP2 Viaduct Km 196+560 LHS 14-Jun-19 12:30 PM
1661 NMSCEW/P-IV/STR/2019/1617 1617 Checking layout and Level at RP6 Viaduct Km 202+560 RHS 14-Jun-19 11:30 AM
1662 NMSCEW/P-IV/STR/2019/1618 1618 Checking top Level & Laying concrete PCC at RP6 Viaduct Km 202+560 RHS 14-Jun-19 11:50 AM
1663 NMSCEW/P-IV/STR/2019/1619 1619 Checking reinforcement ,shuttering for Final lift at wall A1 & A2 of pup PUP Km 172+190 RHS 14-Jun-19 9:30 AM REPEATED
1664 NMSCEW/P-IV/STR/2019/1620 1620 Checking and concrete (M30) pouring for Final lift at wall A1 & A2 of pup PUP Km 172+190 RHS 14-Jun-19 9:45 AM REPEATED
1665 NMSCEW/P-IV/STR/2019/1621 1621 Checking reinforcement ,shuttering for top haunch at wall A1 & A2 and top slab of pup PUP Km 172+190 RHS 14-Jun-19 4:30 PM REPEATED
1666 NMSCEW/P-IV/STR/2019/1622 1622 Checking and concrete (M30) pouring for top haunch at wall A1 & A2 and top slab of pup PUP Km 172+190 RHS 14-Jun-19 5:00 PM REPEATED
1667 NMSCEW/P-IV/STR/2019/1623 1623 Checking top Level & Laying concrete PCC(M-10) for LVUP LVUP Km 178+323 RHS 14-Jun-19 4:00 PM NR
1668 NMSCEW/P-IV/STR/2019/1624 1624 Checking reinforcement ,shuttering for bottom haunch at wall A1 & A2 of pup PUP Km 177+810 RHS 14-Jun-19 11:15 AM NR
1669 NMSCEW/P-IV/STR/2019/1625 1625 Checking and concrete (M30) pouring for bottom haunch at wall A1 & A2 of pup PUP Km 177+810 RHS 14-Jun-19 11:40 AM NR
1670 NMSCEW/P-IV/STR/2019/1626 1626 Checking of reinforcement & shuttering for 1st lift A1 & A2 wall CUP Km 188+575 RHS 14-Jun-19 4:40 PM NR
1671 NMSCEW/P-IV/STR/2019/1627 1627 Checking and pouring concrete(M-30) for 1st lift A1 & A2 wall CUP Km 188+575 RHS 14-Jun-19 5:30 PM NR
1672 NMSCEW/P-IV/STR/2019/1628 1628 Checking of reinforcement & shuttering for 1st lift A1 & A2 wall CUP Km 186+000 RHS 14-Jun-19 5:45 PM NR
1673 NMSCEW/P-IV/STR/2019/1629 1629 Checking and pouring concrete(M-30) for 1st lift A1 & A2 wall CUP Km 186+000 RHS 14-Jun-19 6:10 PM NR
Checking reinforcement for precast Box Culvert (2x2) (cushion 0 to 2m) for Ch 163+830 at precast yard camp -1. Segment NO-37,38,39
1674 NMSCEW/P-IV/STR/2019/1630 1630 Box culvert Km 163+830 BHS 14-Jun-19 9:15 AM IPC-05 DONE
1675 NMSCEW/P-IV/STR/2019/1631 1631 Checking for shuttering & Pouring of Concreting Grade (M-30) for Precast Box Culvert (2×2) Box culvert Km 163+830 BHS 14-Jun-19 10:00 AM IPC-05 DONE
Checking for shuttering & Pouring of Concreting Grade (M-30) for Precast Box Culvert
1676 NMSCEW/P-IV/STR/2019/1632 1632 Box culvert Km 175+500 LHS 14-Jun-19 4:10 PM IPC-08 DONE AE 44
(3x3) , (cushion 2m to 4m) at precast yard camp -1. Segment NO-44
Checking for shuttering & Pouring of Concreting Grade (M-30) for Precast Box Culvert
1677 NMSCEW/P-IV/STR/2019/1633 1633 Box culvert Km 175+500 LHS 14-Jun-19 4:35 PM DONE
(2×2) , (cushion 2m to 4m) for Ch 168+020 at precast yard camp -1. Segment NO-36,37,38
1678 NMSCEW/P-IV/STR/2019/1634 1634 Checking reinforcement ,shuttering for raft with bottom haunch at wall A1 & A2 of pup PUP Km 165+300 RHS 14-Jun-19 11:45 AM NR
1679 NMSCEW/P-IV/STR/2019/1635 1635 Checking reinforcement
Checking and concrete pouring for raft
for precast Boxwith bottom
Culvert (2x2)haunch at wall
(cushion A1 &atA2
2 to 4m) of pupyard camp
precast PUP Km 165+300 RHS 14-Jun-19 12:20 PM NR
1680 NMSCEW/P-IV/STR/2019/1636 1636 -2. Segment NO-53,54,55. Box culvert Km 200+200 LHS 14-Jun-19 9:20 AM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1681 NMSCEW/P-IV/STR/2019/1637 1637 Box culvert Km 200+200 LHS 14-Jun-19 9:50 AM DONE
(2×2),(Cushion 2 to 4m) at precast yard camp-2,Segment no.-53,54,55.
Checking reinforcement for precast Box Culvert (3x3) (cushion 0 to 2m) at precast yard camp
1682 NMSCEW/P-IV/STR/2019/1638 1638 Box culvert Km 200+200 LHS 14-Jun-19 3:22 PM DONE
-2. Segment
Checking for NO-29,30,31.
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1683 NMSCEW/P-IV/STR/2019/1639 1639 Box culvert Km 200+200 LHS 14-Jun-19 4:05 PM DONE
(3×3) (Cushion 0 to 2m) at precast yard camp-2,Segment no.-29,30,31
1684 NMSCEW/P-IV/STR/2019/1640 1640 Checking of reinforcement and shuttering for raft at LP9 Viaduct Km 169+800 LHS 14-Jun-19 2:02 PM IPC-04 DONE
1685 NMSCEW/P-IV/STR/2019/1641 1641 Checking and Pouring of concrete for raft at LP9 Viaduct Km 169+800 LHS 14-Jun-19 5:05 PM IPC-04 DONE
1686 NMSCEW/P-IV/STR/2019/1642 1642 Checking for concreting(M15) around of LP11 foundation annular filling Viaduct Km 169+800 LHS 14-Jun-19 9:06 AM DONE
1687 NMSCEW/P-IV/STR/2019/1643 1643 Checking of reinforcement and shuttering for bottom slab CUP Km 183+290 LHS 14-Jun-19 9:30 AM IPC-04 DONE
1688 NMSCEW/P-IV/STR/2019/1644 1644 Checking and Pouring of concrete(M-30) for bottom slab CUP Km 183+290 LHS 14-Jun-19 9:45 AM IPC-04 DONE
1689 NMSCEW/P-IV/STR/2019/1645 1645 Checking of reinforcement & shuttering for 2nd lift for W2 wall CUP Km 208+930 RHS 15-Jun-19 8:00 AM IPC-04 DONE AE
1690 NMSCEW/P-IV/STR/2019/1646 1646 Checking and pouring concrete for 2nd lift for W2 wall CUP Km 208+930 RHS 15-Jun-19 8:30 AM IPC-04 DONE AE
1691 NMSCEW/P-IV/STR/2019/1647 1647 Checking of reinforcement & shuttering for 1st lift for W1 wall PUP Km 191+740 LHS 15-Jun-19 8:15 AM IPC-04 DONE AE
1692 NMSCEW/P-IV/STR/2019/1648 1648 Checking and pouring concrete for 1st lift for W1 wall PUP Km 191+740 LHS 15-Jun-19 8:45 AM IPC-04 DONE AE
1693 NMSCEW/P-IV/STR/2019/1649 1649 Checking of reinforcement and shuttering for raft at pup PUP Km 199+060 LHS 15-Jun-19 10:00 AM IPC-04 DONE
1694 NMSCEW/P-IV/STR/2019/1650 1650 Checking and Pouring offor
Checking reinforcement concrete
precastfor
Boxraft at pup(2x2) (cushion 2 to 4m) at precast yard camp
Culvert PUP Km 199+060 BHS 15-Jun-19 11:00 AM IPC-04 DONE
1695 NMSCEW/P-IV/STR/2019/1651 1651 -2. Segment NO-56,57,58. Box culvert Km 200+200 LHS 15-Jun-19 9:30 AM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1696 NMSCEW/P-IV/STR/2019/1652 1652 Box culvert Km 200+200 LHS 15-Jun-19 11:30 AM DONE
(2×2) (Cushion
Checking 2 to 4m) for
reinforcement at precast
precastyard
Boxcamp-2,Segment no.-56,57,58.
Culvert (3x3) (cushion 0 to 2m) at precast yard camp
1697 NMSCEW/P-IV/STR/2019/1653 1653 Box culvert Km 200+200 LHS 15-Jun-19 12:00 PM DONE
-2. Segment
Checking for NO-32,33.
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1698 NMSCEW/P-IV/STR/2019/1654 1654 Box culvert Km 200+200 LHS 15-Jun-19 4:00 PM DONE
(3×3) (Cushion 0 to 2m) at precast yard camp-2,Segment no.-32,33.
1699 NMSCEW/P-IV/STR/2019/1655 1655 Checking top Level & Laying concrete(M-10) PCC at Utility duct Utility duct Km 168+020 Km 00+000 BHS 15-Jun-19 2:00 PM IPC-10 DONE
1700 NMSCEW/P-IV/STR/2019/1656 1656 Checking reinforcement ,shuttering for raft with bottom haunch at wall A1 & A2 of pup PUP Km 165+300 RHS 16-Jun-19 10:30 AM IPC-05 DONE
1701 NMSCEW/P-IV/STR/2019/1657 1657 Checking and
Checking concrete pouring
reinforcement for raft
for precast Box with bottom
Culvert haunch
(3x3) at wall
(cushion 2mA1 & A2atofprecast
to 4m) pup yard PUP Km 165+300 RHS 16-Jun-19 11:15 AM IPC-05 DONE
1702 NMSCEW/P-IV/STR/2019/1658 1658 camp -1. Segment NO-45,46 Box culvert Km 175+500 LHS 15-Jun-19 9:47 AM IPC-08 DONE 45, 46
Checking for shuttering & Pouring of Concreting Grade (M-30) for Precast Box Culvert
1703 NMSCEW/P-IV/STR/2019/1659 1659 Checking reinforcement Box culvert Km 175+500 LHS 15-Jun-19 3:37 PM IPC-08 DONE 45, 46
(3x3) , (cushion 2m to 4m)foratprecast
precastBox
yardCulvert
camp -1. (2x2) (cushion
Segment 2m to 4m) for Ch 168+020
NO-45,46
1704 NMSCEW/P-IV/STR/2019/1660 1660 at precast yard camp -1. Segment NO-39,40 Box culvert Km 175+500 LHS 15-Jun-19 10:49 AM IPC-08 DONE AE 39, 40
Checking for shuttering & Pouring of Concreting Grade (M-30) for Precast Box Culvert
1705 NMSCEW/P-IV/STR/2019/1661 1661 Box culvert Km 175+500 LHS 15-Jun-19 4:58 PM IPC-08 DONE AE 39, 40
(2×2) , (cushion
Checking 2m to 4m)for
reinforcement forprecast
Ch 168+020 at precast
Box Culvert (2x2)yard camp0-1.
(cushion to Segment
2m) for ChNO-39,40
163+830 at precast yard camp -1. Segment NO-40
1706 NMSCEW/P-IV/STR/2019/1662 1662 Box culvert Km 163+830 BHS 15-Jun-19 11:49 AM IPC-05 DONE
1707 NMSCEW/P-IV/STR/2019/1663 1663 Checking for shuttering & Pouring of Concreting Grade (M-30) for Precast Box Culvert (2×2) Box culvert Km 163+830 BHS 15-Jun-19 5:55 PM IPC-05 DONE
1708 NMSCEW/P-IV/STR/2019/1664 1664 Checking reinforcement ,shuttering for 2nd Lift at Wall A1 & A2 of PUP PUP Km 174+095 LHS 15-Jun-19 9:05 AM IPC-04 DONE
1709 NMSCEW/P-IV/STR/2019/1665 1665 Checking and concrete (M30) pouring for 2nd Lift at Wall A1 & A2 of PUP PUP Km 174+095 LHS 15-Jun-19 9:45 AM IPC-04 DONE
1710 NMSCEW/P-IV/STR/2019/1666 1666 Checking reinforcement ,shuttering for 2nd Lift at Wall A1 of VUP VUP Km 176+614 LHS 15-Jun-19 3:32 PM IPC-08 DONE
1711 NMSCEW/P-IV/STR/2019/1667 1667 Checking and concrete (M35) pouring for 2nd Lift at Wall A1 of VUP VUP Km 176+614 LHS 15-Jun-19 4:11 PM IPC-08 DONE
1712 NMSCEW/P-IV/STR/2019/1668 1668 Checking reinforcement ,shuttering for 1st Lift at Wall A1 of LVUP LVUP Km 173+400 LHS 15-Jun-19 5:40 PM NR
1713 NMSCEW/P-IV/STR/2019/1669 1669 Checking and concrete (M35) pouring for 1st Lift at Wall A1 of LVUP LVUP Km 173+400 LHS 15-Jun-19 6:10 PM NR
1714 NMSCEW/P-IV/STR/2019/1670 1670 Checking of reinforcement and shuttering for raft at RP12 Viaduct Km 169+800 RHS 15-Jun-19 3:11 PM IPC-04 DONE
1715 NMSCEW/P-IV/STR/2019/1671 1671 Checking and Pouring of concrete for raft at RP12 Viaduct Km 169+800 RHS 15-Jun-19 5:22 PM IPC-04 DONE
1716 NMSCEW/P-IV/STR/2019/1672 1672 Checking layout ,level and structural excavation at RP8 Viaduct Km 195+900 RHS 15-Jun-19 11:07 AM IPC-04 DONE AE
1717 NMSCEW/P-IV/STR/2019/1672A 1672A Checking level for excavated bed for at RP8 Viaduct Km 195+900 RHS 15-Jun-19 11:07 AM IPC-04 DONE
1718 NMSCEW/P-IV/STR/2019/1673 1673 Checking top Level & Laying concrete PCC at RP8 Viaduct Km 195+900 RHS 15-Jun-19 11:32 AM IPC-04 DONE AE
1719 NMSCEW/P-IV/STR/2019/1674 1674 Checking structural excavation at LP1 Viaduct Km 196+560 LHS 15-Jun-19 12:09 PM IPC-05 DONE
1720 NMSCEW/P-IV/STR/2019/1675 1675 Checking top Level & Laying concrete PCC at LP2 Viaduct Km 196+560 LHS 15-Jun-19 12:47 PM
1721 NMSCEW/P-IV/STR/2019/1676 1676 Checking reinforcement ,shuttering for 1st Lift at Wall A1 & A2 of CUP CUP Km 188+575 RHS 15-Jun-19 10:32 AM IPC-04 DONE
1722 NMSCEW/P-IV/STR/2019/1677 1677 Checking and concrete (M30) pouring for 1st Lift at Wall A1 & A2 of CUP CUP Km 188+575 RHS 15-Jun-19 11:13 AM IPC-04 DONE
1723 NMSCEW/P-IV/STR/2019/1678 1678 Checking reinforcement ,shuttering for 1st Lift at Wall A1 & A2 of CUP CUP Km 186+000 RHS 15-Jun-19 5:18 PM IPC-04 DONE
1724 NMSCEW/P-IV/STR/2019/1679 1679 Checking reinforcement
Checking and concrete (M30) pouring
for precast Boxfor 1st Lift
Culvert at Wall
(2x2) A1 &
(cushion A24m)
2 to of CUP
at precast yard camp CUP Km 186+000 RHS 15-Jun-19 5:50 PM IPC-04 DONE
1725 NMSCEW/P-IV/STR/2019/1680 1680 -2. Segment NO-59,60. Box Culvert Km 200+200 LHS 16-Jun-19 3:00 PM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1726 NMSCEW/P-IV/STR/2019/1681 1681 Box Culvert Km 200+200 LHS 16-Jun-19 4:00 PM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-2,Segment no.-59,60.
1727 NMSCEW/P-IV/STR/2019/1682 1682 Checking for concreting around of RP10 foundation annular filling Viaduct Km 196+560 RHS 16-Jun-19 10:00 AM
1728 NMSCEW/P-IV/STR/2019/1683 1683 Checking top Level & Laying concrete PCC at LP1 Viaduct Km 196+560 LHS 16-Jun-19 9:00 AM IPC-05 DONE
1729 NMSCEW/P-IV/STR/2019/1684 1684 Checking of reinforcement & shuttering for 1st lift A1 & A2 wall PUP Km 171+110 LHS 16-Jun-19 4.30 pm IPC-04 DONE
1730 NMSCEW/P-IV/STR/2019/1685 1685 Checking and pouring concrete(M-30) for 1st lift A1 & A2 wall PUP Km 171+110 LHS 16-Jun-19 5.00 pm IPC-04 DONE
1731 NMSCEW/P-IV/STR/2019/1686 1686 Checking reinforcement ,shuttering for 1st Lift at Wall A1 & A2 of LVUP LVUP Km 173+400 LHS 16-Jun-19 5:15 PM REPEATED
1732 NMSCEW/P-IV/STR/2019/1687 1687 Checking and concrete (M35) pouring for 1st Lift at Wall A1 & A2 of LVUP LVUP Km 173+400 LHS 16-Jun-19 5:30 PM REPEATED
1733 NMSCEW/P-IV/STR/2019/1688 1688 Checking reinforcement ,shuttering for Bottom hunch at Wall A1 & A2 of LVUP LVUP Km 173+400 RHS 16-Jun-19 9:30 AM IPC-05 DONE
1734 NMSCEW/P-IV/STR/2019/1689 1689 Checking and concrete (M35) pouring for Bottom hunch at Wall A1 & A2 of LVUP LVUP Km 173+400 RHS 16-Jun-19 10:00 AM IPC-05 DONE
1735 NMSCEW/P-IV/STR/2019/1690 1690 Checking top Level & Laying concrete PCC at Lvup LVUP Km 178+323 RHS 16-Jun-19 6:00 PM IPC-08 DONE
1736 NMSCEW/P-IV/STR/2019/1691 1691 Checking layout ,level and structural excavation at vup VUP Km 179+993 BHS 16-Jun-19 11:00 AM NR
1737 NMSCEW/P-IV/STR/2019/1692 1692 Checking top Level & Laying concrete PCC at RP6 Viaduct Km 202+190 RHS 16-Jun-19 10:10 AM IPC-04 DONE AE
1738 NMSCEW/P-IV/STR/2019/1692A 1692A Checking of Layout & Level for RP6 Viaduct Km 202+190 RHS 16-Jun-19 10:00 AM IPC-04 DONE AE
1739 NMSCEW/P-IV/STR/2019/1692B 1692B Checking level for excavated bed for at RP 6 Viaduct Km 202+190 RHS 16-Jun-19 12:00 PM IPC-04 DONE AE
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
1740 NMSCEW/P-IV/STR/2019/1693 1693 Box Culvert Km 200+200 LHS 17-Jun-19 9:30 AM DONE
-2. Segment NO-61,62,63.
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1741 NMSCEW/P-IV/STR/2019/1694 1694 Checking for reinforcement for precast Box Culvert Km 200+200 LHS 17-Jun-19 10:00 AM DONE
(2×2) (Cushion 2 to 4m) at precast yardBox Culvert (3x3)no.-61,62,63.
camp-2,Segment (cushion 0 to 2m) at precast yard
1742 NMSCEW/P-IV/STR/2019/1695 1695 camp -2. Segment NO-34,35. Box Culvert Km 200+200 LHS 17-Jun-19 3:00 PM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1743 NMSCEW/P-IV/STR/2019/1696 1696 Checking reinforcement Box Culvert Km 200+200 LHS 17-Jun-19 4:00 PM DONE
(3×3) (Cushion 0 to 2m) atfor precast
precast Boxcamp-2,Segment
yard Culvert (3x3) (cushion 2m to 4m) at precast yard
no.-34,35.
1744 NMSCEW/P-IV/STR/2019/1697 1697 camp -1. Segment NO-47,48,49,50 Box culvert Km 175+500 LHS 17-Jun-19 9:47 AM IPC-08 DONE 47, 48, 49, 50
Checking for shuttering & Pouring of Concreting Grade (M-30) for Precast Box Culvert
1745 NMSCEW/P-IV/STR/2019/1698 1698 Box culvert Km 175+500 LHS 17-Jun-19 3:37 PM IPC-08 DONE 47
(3x3) , (cushion
Checking 2m to 4m)foratprecast
reinforcement precastBox
yardCulvert
camp -1. Segment
(2x2) NO-47,48
(cushion 0 to 2m) for Ch 163+830 at precast yard camp -1. Segment NO-41,42
1746 NMSCEW/P-IV/STR/2019/1699 1699 Box culvert Km 163+830 BHS 17-Jun-19 10:49 AM IPC-05 DONE
1747 NMSCEW/P-IV/STR/2019/1700 1700 Checking for shuttering & Pouring of Concreting Grade (M-30) for Precast Box Culvert (2×2) Box culvert Km 163+830 BHS 17-Jun-19 3:22 PM IPC-05 DONE
1748 NMSCEW/P-IV/STR/2019/1701 1701 Checking reinforcement ,shuttering for bottom slab Box culvert Km 187+835 RHS 17-Jun-19 5:00 PM IPC-05 DONE AE
1749 NMSCEW/P-IV/STR/2019/1702 1702 Checking and concrete (M30) pouring for bottom slab CUP Km 187+835 RHS 17-Jun-19 8:30 AM IPC-05 DONE AE
1750 NMSCEW/P-IV/STR/2019/1703 1703 Checking and concrete (M30) pouring for bottom slab CUP Km 187+835 RHS 17-Jun-19 9:00 AM IPC-05 DONE AE
1751 NMSCEW/P-IV/STR/2019/1704 1704 Checking of reinforcement & shuttering for 2nd lift A1 & A2 wall CUP Km 188+575 RHS 17-Jun-19 3:50 PM NR
1752 NMSCEW/P-IV/STR/2019/1705 1705 Checking and pouring concrete(M-30) for 2nd lift A1 & A2 wall CUP Km 188+575 RHS 17-Jun-19 4:20 PM NR
1753 NMSCEW/P-IV/STR/2019/1706 1706 Checking of reinforcement & shuttering for 1st lift A1 & A2 wall CUP Km 183+290 RHS 17-Jun-19 4:05 PM IPC-04 DONE
1754 NMSCEW/P-IV/STR/2019/1707 1707 Checking and pouring concrete(M-30) for 1st lift A1 & A2 wall CUP Km 183+290 RHS 17-Jun-19 5:22 PM IPC-04 DONE
1755 NMSCEW/P-IV/STR/2019/1708 1708 Checking of reinforcement and shuttering for raft VUP Km 176+614 Km 00+000 RHS 17-Jun-19 3:50 PM IPC-10 DONE
1756 NMSCEW/P-IV/STR/2019/1709 1709 Checking and Pouring of concrete(M-35) for raft VUP Km 176+614 Km 00+000 RHS 17-Jun-19 4:00 PM IPC-10 DONE
1757 NMSCEW/P-IV/STR/2019/1710 1710 Checking reinforcement ,shuttering for bottom haunch at wall A1 & A2 of pup PUP Km 177+810 RHS 17-Jun-19 9:32 AM IPC-04 DONE
1758 NMSCEW/P-IV/STR/2019/1711 1711 Checking and concrete(M-30) pouring for bottom haunch at wall A1 & A2 of pup PUP Km 177+810 RHS 17-Jun-19 10:12 AM IPC-04 DONE
1759 NMSCEW/P-IV/STR/2019/1712 1712 Checking layout ,level for raft at LP6 Viaduct Km 202+190 LHS 17-Jun-19 3:00 PM IPC-04 DONE
1760 NMSCEW/P-IV/STR/2019/1713 1713 Checking of reinforcement and shuttering for raft at LP6 Viaduct Km 202+190 LHS 17-Jun-19 3:10 PM
1761 NMSCEW/P-IV/STR/2019/1714 1714 Checking of reinforcement and shuttering for raft at LP10 Viaduct Km 169+800 LHS 17-Jun-19 3:40 PM IPC-04 DONE
1762 NMSCEW/P-IV/STR/2019/1714A 1714A Checking and Pouring of concrete for raft at LP6 Viaduct Km 202+190 LHS 17-Jun-19 3:40 PM IPC-04 DONE
1763 NMSCEW/P-IV/STR/2019/1715 1715 Checking and Pouring of concrete for raft at LP10 Viaduct Km 169+800 LHS 17-Jun-19 9:15 AM IPC-04 DONE
1764 NMSCEW/P-IV/STR/2019/1716 1716 Checking of reinforcement & shuttering of Raft PUP Km 193+880 RHS 17-Jun-19 10:18 AM IPC-04 DONE AE
1765 NMSCEW/P-IV/STR/2019/1717 1717 Checking of reinforcement & shuttering for raft PUP Km 193+880 LHS 17-Jun-19 11:12 AM IPC-08 DONE
1766 NMSCEW/P-IV/STR/2019/1718A 1718A Checking and Pouring of concrete for raft PUP Km 193+880 LHS 17-Jun-19 11:12 AM IPC-08 DONE
1767 1718 Checking and Pouring of concrete for raft PUP Km 193+880 RHS 17-Jun-19 11:12 AM IPC-04 DONE AE
1768 NMSCEW/P-IV/STR/2019/1719 1719 Checking of reinforcement & shuttering for 2nd lift for W1 wall CUP Km 208+930 RHS 17-Jun-19 8:02 AM IPC-04 DONE AE
1769 NMSCEW/P-IV/STR/2019/1720 1720 Checking and pouring concrete for 2nd lift for W1 wall PUP Km 208+930 RHS 17-Jun-19 8:42 AM
1770 NMSCEW/P-IV/STR/2019/1721 1721 Checking of reinforcement & shuttering for 3rd lift for W1 & W2 wall PUP Km 204+470 Km 00+000 RHS 18-Jun-19 11:00 AM IPC-03 DONE
1771 NMSCEW/P-IV/STR/2019/1722 1722 Checking and pouring concrete for 3rd lift for W1 & W2 wall PUP Km 204+470 Km 00+000 RHS 18-Jun-19 12:10 PM IPC-03 DONE AE
Checking for reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard
1772 NMSCEW/P-IV/STR/2019/1723 1723 Box Culvert Km 200+200 LHS 18-Jun-19 9:30 AM DONE
camp -2. Segment
Checking NO-64,65.
for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1773 NMSCEW/P-IV/STR/2019/1724 1724 Box Culvert Km 200+200 LHS 18-Jun-19 10:00 AM DONE
(2×2) (Cushion
Checking 2 to 4m) at precast
for reinforcement yardBox
for precast camp-2,Segment
Culvert (3x3)no.-64,65.
(cushion 0 to 2m) at precast yard
1774 NMSCEW/P-IV/STR/2019/1725 1725 Box Culvert Km 200+200 LHS 18-Jun-19 3:00 PM DONE
camp -2. Segment
Checking NO-36,37.
for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1775 NMSCEW/P-IV/STR/2019/1726 1726 Box Culvert Km 200+200 LHS 18-Jun-19 4:00 PM DONE
(3×3) (Cushion 0 to 2m) at precast yard camp-2,Segment no.-36,37
1776 NMSCEW/P-IV/STR/2019/1727 1727 Checking reinforcement ,shuttering for top slab PUP Km 204+470 RHS 18-Jun-19 11:30 AM IPC-04 DONE AE
1777 NMSCEW/P-IV/STR/2019/1728 1728 Checking of reinforcement & shuttering for 1st lift for W2 wall PUP Km 191+740 LHS 18-Jun-19 2:00 PM IPC-04 DONE AE
1778 NMSCEW/P-IV/STR/2019/1729 1729 Checking and pouring concrete for 1st lift for W2 wall PUP Km 191+740 LHS 18-Jun-19 3:30 PM IPC-04 DONE AE
1779 NMSCEW/P-IV/STR/2019/1730 1730 Checking of reinforcement and shuttering for pier shaft stater at LP1,LP2 Viaduct Km 169+800 Km 00+000 LHS 18-Jun-19 2:00 PM IPC-09 DONE
1780 NMSCEW/P-IV/STR/2019/1731 1731 Checking of reinforcement and shuttering for pier shaft stater at RP1,RP2 Viaduct Km 169+800 Km 00+000 RHS 18-Jun-19 2:30 PM IPC-09 DONE
1781 NMSCEW/P-IV/STR/2019/1732 1732 Checking and Pouring concrete for pier shaft stater at LP1,LP2 Viaduct Km 169+800 Km 00+000 LHS 18-Jun-19 3:45 PM IPC-09 DONE
1782 NMSCEW/P-IV/STR/2019/1733 1733 Checking and Pouring concrete for pier shaft stater at RP1,RP2 Viaduct Km 169+800 Km 00+000 RHS 18-Jun-19 4:15 PM IPC-09 DONE
1783 NMSCEW/P-IV/STR/2019/1734 1734 Checking of reinforcement & shuttering for 2nd lift for A1 & A2 wall CUP Km 188+575 RHS 18-Jun-19 4:30 PM IPC-04 DONE
1784 NMSCEW/P-IV/STR/2019/1735 1735 Checking and pouring concrete(M-30) for 2nd lift for A1 & A2 wall CUP Km 188+575 RHS 18-Jun-19 4:55 PM IPC-04 DONE
1785 NMSCEW/P-IV/STR/2019/1736 1736 Checking reinforcement ,shuttering for top haunch with top slab CUP Km 186+000 LHS 18-Jun-19 5:00 PM IPC-04 DONE
1786 NMSCEW/P-IV/STR/2019/1737 1737 Checking and concrete (M30) pouring in top haunch with top slab CUP Km 186+000 LHS 18-Jun-19 5:30 PM IPC-04 DONE
Checking reinforcement for precast Box Culvert (3x3)(cushion 2 to 4m) at precast yard camp
1787 NMSCEW/P-IV/STR/2019/1738 1738 Box culvert Km 175+500 LHS 18-Jun-19 9:15 AM IPC-08 DONE AE 49, 50
-1. Segment
Checking for NO-49,50
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1788 NMSCEW/P-IV/STR/2019/1739 1739 Box culvert Km 175+500 LHS 18-Jun-19 10:10 AM IPC-08 DONE AE 49, 50
(3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-49,50
Checking reinforcement for precast Box Culvert (2x2) (Cushion 2 to 4m) at precast yard camp
1789 NMSCEW/P-IV/STR/2019/1740 1740 Box culvert Km 175+500 LHS 18-Jun-19 12:20 PM IPC-08 DONE AE 41, 42
-1. Segment
Checking for NO-41,42
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1790 NMSCEW/P-IV/STR/2019/1741 1741 Box culvert Km 175+500 LHS 18-Jun-19 4:15 PM IPC-08 DONE AE 41, 42
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-41,42
1791 NMSCEW/P-IV/STR/2019/1742 1742 Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp Box culvert Km 163+830 BHS 18-Jun-19 12:50 PM IPC-05 DONE AE
1792 NMSCEW/P-IV/STR/2019/1743 1743 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2×2 Box culvert Km 163+830 BHS 18-Jun-19 5:23 PM IPC-05 DONE AE
1793 NMSCEW/P-IV/STR/2019/1744 1744 Checking layout ,level and structural excavation at Utility duct Utility duct Km 193+700 BHS 19-Jun-19 10:00 AM IPC-04 DONE
1794 NMSCEW/P-IV/STR/2019/1745 1745 Checking top Level & Laying concrete PCC(M-10) at Utility duct Utility duct Km 193+700 BHS 19-Jun-19 10:30 AM IPC-04 DONE
1795 NMSCEW/P-IV/STR/2019/1746 1746 Checking of reinforcement and shuttering for raft at RP1 Viaduct Km 202+190 RHS 19-Jun-19 3:00 PM IPC-04 DONE AE
1796 NMSCEW/P-IV/STR/2019/1747 1747 Checking and Pouring of concrete(M-35) for raft at RP1 Viaduct Km 202+190 RHS 19-Jun-19 3:15 PM IPC-04 DONE AE
1797 NMSCEW/P-IV/STR/2019/1748 1748 Checking layout ,level and structural excavation at LP8 Viaduct Km 202+190 LHS 19-Jun-19 2:00 PM IPC-08 DONE AE
1798 NMSCEW/P-IV/STR/2019/1749 1749 Checking top Level & Laying concrete PCC at LP8 Viaduct Km 202+190 LHS 19-Jun-19 2:30 PM IPC-08 DONE AE
1799 NMSCEW/P-IV/STR/2019/1750 1750 Checking reinforcement ,shuttering for 2nd Lift at Wall A1 & A2 of LVUP LVUP Km 173+400 LHS 19-Jun-19 6:00 PM NR
1800 NMSCEW/P-IV/STR/2019/1751 1751 Checking and concrete (M35) pouring for 2nd Lift at Wall A1 & A2 of LVUP LVUP Km 173+400 LHS 19-Jun-19 6:30 PM NR
1801 NMSCEW/P-IV/STR/2019/1752 1752 Checking reinforcement ,shuttering for 2nd Lift at Wall A1 & A2 of Cup CUP Km 186+000 RHS 19-Jun-19 11:00 AM IPC-04 DONE
1802 NMSCEW/P-IV/STR/2019/1753 1753 Checking and concrete (M30) pouring for 2nd Lift at Wall A1 & A2 of Cup CUP Km 186+000 RHS 19-Jun-19 11:30 AM IPC-04 DONE
1803 NMSCEW/P-IV/STR/2019/1754 1754 Checking reinforcement ,shuttering for 2nd Lift at Wall A1 & A2 of Cup CUP Km 183+290 RHS 19-Jun-19 4:30 PM NR
1804 NMSCEW/P-IV/STR/2019/1755 1755 Checking and concrete (M30) pouring for 2nd Lift at Wall A1 & A2 of Cup CUP Km 183+290 RHS 19-Jun-19 5:00 PM NR
1805 NMSCEW/P-IV/STR/2019/1756 1756 Checking layout ,level and structural excavation at RP4 Viaduct Km 196+560 RHS 19-Jun-19 10:10 AM IPC-05 DONE
1806 NMSCEW/P-IV/STR/2019/1757 1757 Checking for
Checking top reinforcement
Level & Layingfor concrete PCCCulvert
precast Box at RP4(2x2) (cushion 2 to 4m) at precast yard Viaduct Km 196+560 RHS 19-Jun-19 11:10 AM IPC-05 DONE
1807 NMSCEW/P-IV/STR/2019/1758 1758 camp -2. Segment
Checking NO-66,67,68.
for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert Box Culvert Km 200+200 LHS 19-Jun-19 9:30 AM DONE
1808 NMSCEW/P-IV/STR/2019/1759 1759 (2×2) (Cushion
Checking 2 to 4m) at precast
for reinforcement yardBox
for precast camp-2,Segment
Culvert (3x3)no.-66,67,68.
(cushion 0 to 2m) at precast yard Box Culvert Km 200+200 LHS 19-Jun-19 10:20 AM DONE
1809 NMSCEW/P-IV/STR/2019/1760 1760 camp -2. Segment NO-38,39. Box Culvert Km 200+200 LHS 19-Jun-19 3:30 PM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1810 NMSCEW/P-IV/STR/2019/1761 1761 Box Culvert Km 200+200 LHS 19-Jun-19 4:15 PM DONE
(3×3) (Cushion
Checking 0 to 2m) for
reinforcement at precast
precastyard
Boxcamp-2,Segment no.-38,39
Culvert (3x3)(cushion 2 to 4m) at precast yard camp
1811 NMSCEW/P-IV/STR/2019/1762 1762 Box culvert Km 175+500 LHS 19-Jun-19 9:17 AM IPC-08 DONE 48, 51
-1. Segment NO-48,51
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1812 NMSCEW/P-IV/STR/2019/1763 1763 Box culvert Km 175+500 LHS 19-Jun-19 10:11 AM IPC-08 DONE 48
(3×3) (Cushion
Checking 2 to 4m) for
reinforcement at precast
precastyard
Boxcamp-1,Segment no.-48,51
Culvert (2x2) (Cushion 2 to 4m) at precast yard camp
1813 NMSCEW/P-IV/STR/2019/1764 1764 Box culvert Km 175+500 LHS 19-Jun-19 12:22 PM IPC-08 DONE AE 38
-1. Segment NO-38,
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1814 NMSCEW/P-IV/STR/2019/1765 1765 Box culvert Km 175+500 LHS 19-Jun-19 4:19 PM IPC-08 DONE AE 38
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-38
1815 NMSCEW/P-IV/STR/2019/1766 1766 Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp Box culvert Km 163+830 BHS 19-Jun-19 12:52 PM IPC-05 DONE
1816 NMSCEW/P-IV/STR/2019/1767 1767 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2×2 Box culvert Km 163+830 BHS 19-Jun-19 5:24 PM IPC-05 DONE
1817 NMSCEW/P-IV/STR/2019/1768 1768 Checking of reinforcement and shuttering for raft at RP9 Viaduct Km 169+800 RHS 19-Jun-19 11:05 AM IPC-04 DONE
1818 NMSCEW/P-IV/STR/2019/1769 1769 Checking and Pouring of concrete for raft at RP9 Viaduct Km 169+800 RHS 19-Jun-19 2:12 PM IPC-04 DONE
1819 NMSCEW/P-IV/STR/2019/1770 1770 Checking of reinforcement and shuttering for raft at RP3 Viaduct Km 200+920 RHS 19-Jun-19 4:06 PM
1820 NMSCEW/P-IV/STR/2019/1771 1771 Checking and Pouring of concrete(M-35) for raft at RP3 Viaduct Km 200+920 RHS 19-Jun-19 5:23 PM
1821 NMSCEW/P-IV/STR/2019/1772 1772 Checking reinforcement ,shuttering for 1st Lift at Wall W2 PUP Km 203+560 RHS 19-Jun-19 9:03 AM IPC-04 DONE AE
1822 NMSCEW/P-IV/STR/2019/1773 1773 Checking and concrete pouring for 1st Lift at Wall W2 PUP Km 203+560 RHS 19-Jun-19 9:34 AM IPC-04 DONE AE
1823 NMSCEW/P-IV/STR/2019/1774 1774 Checking and concrete pouring for top slab PUP Km 204+470 RHS 19-Jun-19 3:03 PM IPC-04 DONE AE
1824 NMSCEW/P-IV/STR/2019/1775 1775 Checking layout ,level at LP10 Viaduct Km 202+190 RHS 20-Jun-19 10:00 AM IPC-08 DONE
1825 NMSCEW/P-IV/STR/2019/1776 1776 Checking top Level & Laying concrete PCC at LP10 Viaduct Km 202+190 RHS 20-Jun-19 10:30 AM IPC-08 DONE
1826 NMSCEW/P-IV/STR/2019/1777 1777 Checking layout ,level at RP3 Viaduct Km 202+190 RHS 20-Jun-19 2:30 PM IPC-08 DONE
1827 NMSCEW/P-IV/STR/2019/1778 1778 Checking top Level & Laying concrete PCC at RP3 Viaduct Km 202+190 RHS 20-Jun-19 3:00 PM IPC-08 DONE
1828 NMSCEW/P-IV/STR/2019/1779 1779 Checking of reinforcement and shuttering for raft at RP10 Viaduct Km 169+800 RHS 20-Jun-19 2:00 PM IPC-04 DONE
1829 NMSCEW/P-IV/STR/2019/1780 1780 Checking and Pouring of concrete for raft at RP10 Viaduct Km 169+800 RHS 20-Jun-19 4:00 PM IPC-04 DONE
1830 NMSCEW/P-IV/STR/2019/1781 1781 Checking reinforcement ,shuttering for 2nd Lift at Wall A1 & A2 of LVUP LVUP Km 173+400 LHS 20-Jun-19 9:00 AM IPC-05 DONE
1831 NMSCEW/P-IV/STR/2019/1782 1782 Checking and concrete (M35) pouring for 2nd Lift at Wall A1 & A2 of LVUP LVUP Km 173+400 LHS 20-Jun-19 9:30 AM IPC-05 DONE
1832 NMSCEW/P-IV/STR/2019/1783 1783 Checking reinforcement ,shuttering for 1st Lift at Wall A1 & A2 of LVUP LVUP Km 173+400 RHS 20-Jun-19 11:00 AM IPC-05 DONE AE
1833 NMSCEW/P-IV/STR/2019/1784 1784 Checking and concrete (M35) pouring for 1st Lift at Wall A1 & A2 of LVUP LVUP Km 173+400 RHS 20-Jun-19 12:00 PM IPC-05 DONE AE
1834 NMSCEW/P-IV/STR/2019/1785 1785 Checking reinforcement ,shuttering for 2nd Lift at Wall A1& A2 of Pup PUP Km 171+110 LHS 20-Jun-19 4.30 PM IPC-04 DONE
1835 NMSCEW/P-IV/STR/2019/1786 1786 Checking and concrete (M30) pouring for 2nd Lift at Wall A1 & A2 of Pup PUP Km 171+110 LHS 20-Jun-19 5.10 PM IPC-04 DONE
1836 NMSCEW/P-IV/STR/2019/1787 1787 Checking reinforcement ,shuttering for 2nd Lift at Wall A1 & A2 of Cup CUP Km 183+290 RHS 20-Jun-19 4:45 PM IPC-04 DONE
1837 NMSCEW/P-IV/STR/2019/1788 1788 Checking and concrete (M30) pouring for 2nd Lift at Wall A1 & A2 of Cup CUP Km 183+290 RHS 20-Jun-19 5:30 PM IPC-04 DONE
Checking reinforcement for precast Box Culvert (3x3)(cushion 2 to 4m) at precast yard camp
1838 NMSCEW/P-IV/STR/2019/1789 1789 Box culvert Km 175+500 LHS 20-Jun-19 9:17 AM IPC-08 DONE AE 52
-1. Segment
Checking for NO-52
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1839 NMSCEW/P-IV/STR/2019/1790 1790 Box culvert Km 175+500 LHS 20-Jun-19 10:11 AM IPC-08 DONE AE 51, 52
(3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-51,52
Checking reinforcement for precast Box Culvert (2x2) (Cushion 2 to 4m) at precast yard camp
1840 NMSCEW/P-IV/STR/2019/1791 1791 Box culvert Km 175+500 LHS 20-Jun-19 12:22 PM IPC-08 DONE AE 43
-1. Segment
Checking for NO-43
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1841 NMSCEW/P-IV/STR/2019/1792 1792 Box culvert Km 175+500 LHS 20-Jun-19 4:19 PM IPC-08 DONE AE 43
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-43
1842 NMSCEW/P-IV/STR/2019/1793 1793 Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp Box culvert Km 163+830 BHS 20-Jun-19 12:52 PM IPC-05 DONE
1843 NMSCEW/P-IV/STR/2019/1794 1794 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2×2 Box culvert Km 163+830 BHS 20-Jun-19 5:24 PM IPC-05 DONE
Checking for reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard
1844 NMSCEW/P-IV/STR/2019/1795 1795 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert Box culvert Km 200+200 LHS 20-Jun-19 9:32 AM DONE
camp -2. Segment NO-69,79,71.
1845 NMSCEW/P-IV/STR/2019/1796 1796 (2×2) (Cushion
Checking 2 to 4m) at precast
for reinforcement yardBox
for precast camp-2,Segment
Culvert (3x3)no.-69,70,71.
(cushion 0 to 2m) at precast yard Box culvert Km 200+200 LHS 20-Jun-19 10:35 AM DONE
1846 NMSCEW/P-IV/STR/2019/1797 1797 camp -2. Segment NO-40,41. Box culvert Km 200+200 LHS 20-Jun-19 3:22 PM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1847 NMSCEW/P-IV/STR/2019/1798 1798 Box culvert Km 200+200 LHS 20-Jun-19 4:23 PM DONE
(3×3) (Cushion 0 to 2m) at precast yard camp-2,Segment no.-40,41.
Checking for reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard
1848 NMSCEW/P-IV/STR/2019/1799 1799 Box Culvert Km 200+200 LHS 21-Jun-19 9:30 AM DONE
camp -2. Segment
Checking NO-72,73,74,75.
for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1849 NMSCEW/P-IV/STR/2019/1800 1800 Box Culvert Km 200+200 LHS 21-Jun-19 10:35 AM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-2,Segment no.-72,73,74,75.
1850 NMSCEW/P-IV/STR/2019/1801 1801 Checking for concreting(M15) around of RP12 foundation annular filling Viaduct Km 169+800 RHS 21-Jun-19 9:00 AM DONE
1851 NMSCEW/P-IV/STR/2019/1802 1802 Checking reinforcement ,shuttering for raft with bottom haunch at wall A1 & A2 of pup PUP Km 165+300 LHS 21-Jun-19 9:15 AM IPC-05 DONE AE
1852 NMSCEW/P-IV/STR/2019/1803 1803 Checking and concrete pouring for raft with bottom haunch at wall A1 & A2 of pup PUP Km 165+300 LHS 21-Jun-19 9:50 AM IPC-05 DONE AE
1853 NMSCEW/P-IV/STR/2019/1804 1804 Checking reinforcement ,shuttering for 3rd Lift at Wall A1 & A2 of VUP VUP Km 176+614 LHS 21-Jun-19 4:30 PM NR
1854 NMSCEW/P-IV/STR/2019/1805 1805 Checking and concrete (M35) pouring for 3rd Lift at Wall A1 & A2 of VUP VUP Km 176+614 LHS 21-Jun-19 5:00 PM NR
1855 NMSCEW/P-IV/STR/2019/1806 1806 Checking reinforcement ,shuttering for bottom haunch at wall A1 & A2 of VUP VUP Km 176+614 RHS 21-Jun-19 10:00 AM NR
1856 NMSCEW/P-IV/STR/2019/1807 1807 Checking and concrete(M-35) pouring for bottom haunch at wall A1 & A2 of VUP VUP Km 176+614 RHS 21-Jun-19 11:00 AM NR
1857 NMSCEW/P-IV/STR/2019/1808 1808 Checking reinforcement ,shuttering for final Lift at Wall A1 & A2 of PUP PUP Km 174+095 RHS 21-Jun-19 9:10 AM NR
1858 NMSCEW/P-IV/STR/2019/1809 1809 Checking and concrete (M30) pouring for final Lift at Wall A1 & A2 of PUP PUP Km 174+095 RHS 21-Jun-19 10:10 AM NR
1859 NMSCEW/P-IV/STR/2019/1810 1810 Checking reinforcement ,shuttering for top haunch with top slab of PUP PUP Km 174+095 RHS 21-Jun-19 6:00 PM NR
1860 NMSCEW/P-IV/STR/2019/1811 1811 Checking and concrete (M30) pouring in top haunch with top slab of PUP PUP Km 174+095 RHS 21-Jun-19 6:30 PM NR
Checking reinforcement for precast Box Culvert (3x3)(cushion 2 to 4m) at precast yard camp
1861 NMSCEW/P-IV/STR/2019/1812 1812 Box culvert Km 175+500 LHS 21-Jun-19 9:21 AM IPC-08 DONE AE 53, 54
-1. Segment NO-53,54
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1862 NMSCEW/P-IV/STR/2019/1813 1813 Box culvert Km 175+500 LHS 21-Jun-19 10:19 AM NR
(3×3) (Cushion
Checking 2 to 4m) for
reinforcement at precast
precastyard
Boxcamp-1,Segment no.-53,54
Culvert (2x2) (Cushion 2 to 4m) at precast yard camp
1863 NMSCEW/P-IV/STR/2019/1814 1814 Box culvert Km 175+500 LHS 21-Jun-19 12:23 PM IPC-08 DONE AE 44
-1. Segment
Checking for NO-44
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1864 NMSCEW/P-IV/STR/2019/1815 1815 Box culvert Km 175+500 LHS 21-Jun-19 4:21 PM NR
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-44
1865 NMSCEW/P-IV/STR/2019/1816 1816 Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp Box culvert Km 163+830 BHS 21-Jun-19 12:55 PM IPC-05 DONE
1866 NMSCEW/P-IV/STR/2019/1817 1817 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2×2 Box culvert Km 163+830 BHS 21-Jun-19 5:26 PM IPC-05 DONE
1867 NMSCEW/P-IV/STR/2019/1818 1818 Checking of reinforcement and shuttering for raft at LP7 Viaduct Km 195+900 LHS 21-Jun-19 10:01 AM IPC-04 DONE
1868 NMSCEW/P-IV/STR/2019/1819 1819 Checking and Pouring of concrete for raft at LP7 Viaduct Km 195+900 LHS 21-Jun-19 10:37 AM IPC-04 DONE
1869 NMSCEW/P-IV/STR/2019/1820 1820 Checking of reinforcement and shuttering for raft at RP6 Viaduct Km 195+900 RHS 21-Jun-19 11:15 AM
1870 NMSCEW/P-IV/STR/2019/1821 1821 Checking and Pouring of concrete for raft at RP6 Viaduct Km 195+900 RHS 21-Jun-19 11:32 AM
1871 NMSCEW/P-IV/STR/2019/1822 1822 Checking layout ,level at RP9 Viaduct Km 202+190 RHS 21-Jun-19 2:10 PM IPC-08 DONE
1872 NMSCEW/P-IV/STR/2019/1823 1823 Checking top Level & Laying concrete PCC at RP9 Viaduct Km 202+190 RHS 21-Jun-19 2:50 PM IPC-08 DONE AE
1873 NMSCEW/P-IV/STR/2019/1824 1824 Checking of reinforcement & shuttering for 2nd lift for W2 wall PUP Km 191+740 LHS 21-Jun-19 2:22 PM IPC-04 DONE AE
1874 NMSCEW/P-IV/STR/2019/1825 1825 Checking and pouring concrete(M30) for 2nd lift for W2 wall PUP Km 191+740 LHS 21-Jun-19 3:18 PM IPC-04 DONE AE
1875 NMSCEW/P-IV/STR/2019/1826 1826 Checking layout ,level for MNB MNB Km 199+360 BHS 21-Jun-19 2:50 PM DONE
1876 NMSCEW/P-IV/STR/2019/1827 1827 Checking top Level & Laying concrete PCC for MNB MNB Km 199+360 BHS 21-Jun-19 4:10 PM NR
1877 NMSCEW/P-IV/STR/2019/1828 1828 Checking reinforcement ,shuttering for final Lift at Wall A1 & A2 of Cup CUP Km 186+000 RHS 22-Jun-19 10.00 AM IPC-04 DONE
1878 NMSCEW/P-IV/STR/2019/1829 1829 Checking and concrete (M30) pouring for final Lift at Wall A1 & A2 of Cup CUP Km 186+000 RHS 22-Jun-19 11.00 AM IPC-04 DONE
1879 NMSCEW/P-IV/STR/2019/1830 1830 Checking of reinforcement , shuttering & top level of raft at LP 3 Viaduct Km 202+190 LHS 22-Jun-19 3:00 PM IPC-04 DONE
1880 NMSCEW/P-IV/STR/2019/1831 1831 Checking of pouring concrete at LP3 for raft Viaduct Km 202+190 LHS 22-Jun-19 3:30 PM IPC-04 DONE
1881 NMSCEW/P-IV/STR/2019/1832 1832 Checking of reinforcement , shuttering for raft at RP-06 Viaduct Km 195+900 LHS 22-Jun-19 9:30 AM
1882 NMSCEW/P-IV/STR/2019/1833 1833 Checking of pouring pcc at RP-06 Viaduct Km 195+900 RHS 22-Jun-19 10:00 AM
1883 NMSCEW/P-IV/STR/2019/1834 1834 Checking of reinforcement & shuttering for wall W1 1st lift PUP Km 203+560 RHS 22-Jun-19 2:00 PM IPC-04 DONE AE
1884 NMSCEW/P-IV/STR/2019/1835 1835 Checking for pouring of concrete for wall W1 1st lift PUP Km 203+560 RHS 22-Jun-19 4:00 PM IPC-04 DONE AE
1885 NMSCEW/P-IV/STR/2019/1836 1836 Checking of reinforcement & shuttering for wall W1 2nd lift PUP Km 191+740 LHS 22-Jun-19 2:00 PM IPC-04 DONE
1886 NMSCEW/P-IV/STR/2019/1837 1837 Checking for pouring of concrete for wall W1 2nd lift PUP Km 191+740 LHS 22-Jun-19 3:00 PM IPC-04 DONE
1887 NMSCEW/P-IV/STR/2019/1838 1838 Checking of reinforcement & shuttering for LP 8 raft Viaduct Km 169+800 LHS 22-Jun-19 4:00 PM IPC-04 DONE
1888 NMSCEW/P-IV/STR/2019/1839 1839 Checking for pouring of concrete at LP8 raft (M-35) PUP Km 169+800 LHS 22-Jun-19 5:00 PM IPC-04 DONE
1889 NMSCEW/P-IV/STR/2019/1840 1840 Checking of reinforcement & shuttering for wall 1sr lift of A1 CUP Km 183+290 LHS 22-Jun-19 12:00 PM IPC-04 DONE
1890 NMSCEW/P-IV/STR/2019/1841 1841 Checking of reinforcement & shuttering for wall 1sr lift of A2 CUP Km 183+290 LHS 22-Jun-19 12:00 PM IPC-04 DONE
1891 NMSCEW/P-IV/STR/2019/1842 1842 Checking of pouring of concrete for M-30 Grade concrete for wall 1sr lift of A1 CUP Km 183+290 LHS 22-Jun-19 12:00 PM IPC-04 DONE
1892 NMSCEW/P-IV/STR/2019/1843 1843 Checking of pouring of concrete for M-30 Grade concrete for wall 1sr lift of A2 CUP Km 183+290 LHS 22-Jun-19 12:00 PM IPC-04 DONE
1893 NMSCEW/P-IV/STR/2019/1844 1844 Checking for reinforcement & shuttering for wall final lift of A1 & A2 PUP Km 174+095 RHS 22-Jun-19 10:00 AM IPC-04 DONE
1894 NMSCEW/P-IV/STR/2019/1845 1845 Checking for pouring of concrete for M-30 Grade concrete for wall final lift of A1 & A2 PUP Km 174+095 RHS 22-Jun-19 10:30 AM IPC-04 DONE
1895 NMSCEW/P-IV/STR/2019/1846 1846 Checking for reinforcement & shuttering of top haunch & top slab A1 & A2 PUP Km 174+095 RHS 22-Jun-19 4:00 PM IPC-04 DONE
1896 NMSCEW/P-IV/STR/2019/1847 1847 Checking for pouring of concrete of top haunch & top slab A1 & A2 PUP Km 174+095 RHS 22-Jun-19 4:30 PM IPC-04 DONE
1897 NMSCEW/P-IV/STR/2019/1848 1848 Checking for reinforcement & shuttering for wall 1st lift of A1 & A2 PUP Km 177+810 RHS 22-Jun-19 5:00 PM NR
1898 NMSCEW/P-IV/STR/2019/1849 1849 Checking for pouring of concrete for M-30 Grade concrete for wall 1st lift of A1 & A2 PUP Km 177+810 RHS 22-Jun-19 5:00 PM NR
checking for reinforcement for precast Box Culvert (2x2) (cushion 2-4m) at precast yard camp
1899 NMSCEW/P-IV/STR/2019/1850 1850 BOX CULVERT Km 200+200 LHS 22-Jun-19 11:50 AM DONE
-2 Segment
Checking forNO 76,77,78
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1900 NMSCEW/P-IV/STR/2019/1851 1851 BOX CULVERT Km 200+200 LHS 22-Jun-19 12:10 PM DONE
(2×2) (Cushion
checking 2 to 4 m) atfor
for reinforcement precast yard
precast camp-2
Box CulvertSegment No 76,77,78
(3x3) (cushion 2-4m) at precast yard camp
1901 NMSCEW/P-IV/STR/2019/1852 1852 BOX CULVERT Km 200+200 LHS 22-Jun-19 12:20 PM DONE
-2 Segment
Checking forNO 13
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1902 NMSCEW/P-IV/STR/2019/1853 1853 BOX CULVERT Km 200+200 LHS 22-Jun-19 12:50 PM DONE
(3x3) (Cushion
checking 2 to 4 m) atfor
for reinforcement precast yard
precast camp-2
Box CulvertSegment No 13 2-4m) at precast yard camp
(3x3) (cushion
1903 NMSCEW/P-IV/STR/2019/1854 1854 BOX CULVERT Km 200+200 LHS 22-Jun-19 12:20 PM DONE
-2 Segment
Checking forNO 13
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1904 NMSCEW/P-IV/STR/2019/1855 1855 BOX CULVERT Km 200+200 LHS 22-Jun-19 12:50 PM DONE
(3x3) (Cushion
checking 2 to 4 m) atfor
for reinforcement precast yard
precast camp-2
Box CulvertSegment No 13 0-2m) at precast yard camp
(3x3) (cushion
1905 NMSCEW/P-IV/STR/2019/1856 1856 BOX CULVERT Km 200+200 LHS 22-Jun-19 2:00 PM DONE
-2 Segment
Checking forNO 42
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1906 NMSCEW/P-IV/STR/2019/1857 1857 BOX CULVERT Km 200+200 LHS 22-Jun-19 2:20 PM DONE
(3x3) (Cushion 0 to 2 m) at precast yard camp-2 Segment No 42
checking for reinforcement for precast Box Culvert (2x2) (cushion 2-4m) at precast yard camp
1907 NMSCEW/P-IV/STR/2019/1858 1858 BOX CULVERT Km 175+500 LHS 22-Jun-19 10:00 AM DONE
-1 Segment NO 45
1908 NMSCEW/P-IV/STR/2019/1859 1859 checking for reinforcement for precast Box Culvert (2x2) (cushion 0-2m) at precast yard cam BOX CULVERT Km 163+830 BHS 22-Jun-19 10:15 AM IPC-05 DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1909 NMSCEW/P-IV/STR/2019/1860 1860 BOX CULVERT Km 175+500 LHS 22-Jun-19 4:00 PM NR
(3x3) (Cushion 2 to 4 m) at precast yard camp-1 Segment No 53, 54
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1910 NMSCEW/P-IV/STR/2019/1861 1861 Box culvert Km 175+500 LHS 22-Jun-19 5:30 PM IPC-08 DONE AE 44, 45
(2x2) (Cushion 2 to 4 m) at precast yard camp-1 Segment No 44,45
1911 NMSCEW/P-IV/STR/2019/1862 1862 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2x2BOX CULVERT Km 163+830 BHS 22-Jun-19 6:00 PM IPC-05 DONE
1912 NMSCEW/P-IV/STR/2019/1863 1863 Checking of reinforcement & shuttering for wall 1st lift CUP Km 185+235 LHS 22-Jun-19 2:30 PM IPC-04 DONE
1913 NMSCEW/P-IV/STR/2019/1864 1864 Checking and pouring concrete(M30) for wall 1st lift CUP Km 185+235 LHS 22-Jun-19 2:45 PM IPC-04 DONE
checking for reinforcement for precast Box Culvert (2x2) (cushion 2-4m) at precast yard camp
1914 NMSCEW/P-IV/STR/2019/1865 1865 BOX CULVERT Km 200+200 LHS 23-Jun-19 10:00 AM DONE
-2 Segment
Checking forNO 79,80 & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
shuttering
1915 NMSCEW/P-IV/STR/2019/1866 1866 BOX CULVERT Km 200+200 LHS 23-Jun-19 10:10 AM DONE
(2x2) (Cushion 2 to 4 m) at precast yard camp-2 Segment No 79,80
1916 NMSCEW/P-IV/STR/2019/1867 1867 Checking of reinforcement and shuttering for pier shaft 2nd lift at RP 4 Viaduct Km 169+800 RHS 23-Jun-19 9:30 AM NR
1917 NMSCEW/P-IV/STR/2019/1868 1868 Checking for Pouring of concrete (M-45) for pier shaft 2nd lift at RP 4 Viaduct Km 169+800 RHS 23-Jun-19 10:00 AM NR
1918 NMSCEW/P-IV/STR/2019/1869 1869 Checking of reinforcement and shuttering for pier shaft 1st lift at RP 5 Viaduct Km 169+800 RHS 23-Jun-19 9:45 AM NR
1919 NMSCEW/P-IV/STR/2019/1870 1870 Checking for Pouring of concrete (M-45) for pier shaft 1st lift at RP 5 Viaduct Km 169+800 RHS 23-Jun-19 10:30 AM NR
1920 NMSCEW/P-IV/STR/2019/1871 1871 Checking for reinforcement ,shuttering for 3rd Lift at Wall A1 & A2 of VUP VUP Km 176+614 LHS 23-Jun-19 4:30 PM IPC-08 DONE
1921 NMSCEW/P-IV/STR/2019/1872 1872 Checking for pouring of concrete (M-35) for 3rd Lift at Wall A1 & A2 of VUP VUP Km 176+614 LHS 23-Jun-19 4:40 PM IPC-08 DONE
1922 NMSCEW/P-IV/STR/2019/1873 1873 Checking for reinforcement ,shuttering for bottom haunch at wall A1 & A2 of VUP VUP Km 176+614 Km 00+000 RHS 23-Jun-19 9:00 AM IPC-10 DONE
1923 NMSCEW/P-IV/STR/2019/1874 1874 Checking for pouring of concrete (M-35) for bottom haunch at wall A1 & A2 of VUP VUP Km 176+614 Km 00+000 RHS 23-Jun-19 9:20 AM IPC-10 DONE
1924 NMSCEW/P-IV/STR/2019/1875 1875 Checking of reinforcement and shuttering for raft at RP-06 Viaduct Km 195+900 RHS 23-Jun-19 8:00 AM IPC-04 DONE
1925 NMSCEW/P-IV/STR/2019/1876 1876 Checking for Pouring of concrete for raft at RP-06 Viaduct Km 195+900 RHS 23-Jun-19 8:30 AM IPC-04 DONE
1926 NMSCEW/P-IV/STR/2019/1877 1877 Layout & level checking for box culvert. Box culvert Km 167+696 LHS 23-Jun-19 11:00 AM NR
1927 NMSCEW/P-IV/STR/2019/1878 1878 Structural Excavation for box culvert Box culvert Km 167+696 LHS 23-Jun-19 11:30 AM NR
1928 NMSCEW/P-IV/STR/2019/1879 1879 Checking of PCC of box culvert Box culvert Km 167+696 LHS 23-Jun-19 3:00 PM NR
Checking for reinforcement of precaste box culvert (2x 2) ,(Cushion 2m to 4m) at precast yard
1929 NMSCEW/P-IV/STR/2019/1880 1880 BOX CULVERT Km 200+200 LHS 24-Jun-19 10:00 AM DONE
camp -2 location segment no-81,82,83,84
Checking for shuttering & pouring of concrete Grade(M-30) for precast box culvert (2 x 2)
1930 NMSCEW/P-IV/STR/2019/1881 1881 BOX CULVERT Km 200+200 LHS 24-Jun-19 10:20 AM DONE
(cusion 2mfor
Checking toreinforcement
4m)at casting ofyard of camp-2,segment
precaste no-81,82,83,84
box culvert (3x 3) ,(Cushion 0m to 2m) at precast yard
1931 NMSCEW/P-IV/STR/2019/1882 1882 BOX CULVERT Km 200+200 LHS 24-Jun-19 10:30 AM DONE
camp -2 location
Checking segment
for shuttering & no-43
pouring of concrete Grade(M-30) for precast box culvert (3 x 3)
1932 NMSCEW/P-IV/STR/2019/1883 1883 BOX CULVERT Km 200+200 LHS 24-Jun-19 10:40 AM DONE
(cusion 0m to 2m)at casting yard of camp-2,segment no-43
1933 NMSCEW/P-IV/STR/2019/1884 1884 Checking for reinforcement & shuttering of 1st Lift of wall W 1 at PUP PUP Km 191+740 RHS 24-Jun-19 11:00 AM DONE
1934 NMSCEW/P-IV/STR/2019/1885 1885 checking of reinforcement and shuttering for raft at RP8 Viaduct Km 169+800 RHS 24-Jun-19 11:30 AM IPC-04 DONE
1935 NMSCEW/P-IV/STR/2019/1886 1886 Checking for Pouring of concrete (M-35) for raft at RP8 Viaduct Km 169+800 RHS 24-Jun-19 3:00 PM IPC-04 DONE
1936 NMSCEW/P-IV/STR/2019/1887 1887 Checking of reinforcement and shuttering for raft at LVUP LVUP Km 178+323 LHS 24-Jun-19 6:00 PM NR
1937 NMSCEW/P-IV/STR/2019/1888 1888 Checking for Pouring of concrete (M-35) for raft at LVUP LVUP Km 178+323 LHS 24-Jun-19 6:20 PM NR
1938 NMSCEW/P-IV/STR/2019/1889 1889 Checking top level & laying M10 concrete for PCC at VUP VUP Km 179+983 LHS 24-Jun-19 10:00 AM NR
Checking for reinforcement of precaste box culvert (3x 3) ,(Cushion 2m to 4m) at precast yard
1939 NMSCEW/P-IV/STR/2019/1890 1890 Box culvert Km 175+500 LHS 24-Jun-19 10:30 AM IPC-08 DONE AE 55, 56
camp -1 location
Checking segment no-55,56
for reinforcement of precaste box culvert (2x 2) ,(Cushion 0m to 2m) at precast yard
1940 NMSCEW/P-IV/STR/2019/1891 1891 Box culvert Km 175+500 LHS 24-Jun-19 10:50 AM IPC-05 DONE 59, 60
camp -1 location segment no-51,52, 59, 60
Checking for reinforcement of precaste box culvert (2x 2) ,(Cushion 2m to 4m) at precast yard
1941 NMSCEW/P-IV/STR/2019/1892 1892 Box culvert Km 175+500 LHS 24-Jun-19 10:50 AM IPC-08 DONE 59
camp -1 location
Checking segment
for shuttering & no-46,47
pouring of concrete Grade(M-30) for precast box culvert (3 x 3)
1942 NMSCEW/P-IV/STR/2019/1893 1893 Box culvert Km 175+500 LHS 24-Jun-19 11:00 AM IPC-08 DONE AE 55, 56
(cusion 2m to 4m)at casting yard of camp-1,segment no-55,56
1943 NMSCEW/P-IV/STR/2019/1894 1894 Checking for shuttering & pouring of concrete Grade(M-30) for precast box culvert (2x 2) BOX CULVERT Km 163+830 BHS 24-Jun-19 11:20 AM IPC-05 DONE AE
Checking for shuttering & pouring of concrete Grade(M-30) for precast box culvert (2 x 2)
1944 NMSCEW/P-IV/STR/2019/1895 1895 Box culvert Km 175+500 LHS 24-Jun-19 11:30 AM IPC-08 DONE AE 46, 47
(cusion 2m to 4m)at casting yard of camp-1,segment no-46,47
1945 NMSCEW/P-IV/STR/2019/1896 1896 checking of reinforcement and shuttering for raft at RP-06 VIADUCT Km 195+900 RHS 24-Jun-19 8:00 AM
1946 NMSCEW/P-IV/STR/2019/1897 1897 Checking for Pouring of concrete for raft at RP-06 VIADUCT Km 195+900 RHS 24-Jun-19 8:30 AM
1947 NMSCEW/P-IV/STR/2019/1898 1898 Checking for level & layout structural excavation at RP3 VIADUCT Km 196+560 RHS 24-Jun-19 10:00 AM IPC-05 DONE
1948 NMSCEW/P-IV/STR/2019/1899 1899 Checking for Pouring of PCC at RP-03 VIADUCT Km 196+560 RHS 24-Jun-19 11:00 AM IPC-05 DONE AE
1949 NMSCEW/P-IV/STR/2019/1900 1900 Layout & level checking for box culvert. Km 167+696 LHS 24-Jun-19 11:00 AM NR
1950 NMSCEW/P-IV/STR/2019/1901 1901 Structural Excavation for box culvert Km 167+696 LHS 24-Jun-19 11:30 AM NR
1951 NMSCEW/P-IV/STR/2019/1902 1902 Checking of PCC of box culvert Km 167+696 LHS 24-Jun-19 3:00 PM NR
1952 NMSCEW/P-IV/STR/2019/1884/A 1884/A Checking for Pouring of concrete (M-35) for 1st Lift of wall W 1 at PUP PUP Km 191+740 RHS 24-Jun-19 11:30 AM
1953 NMSCEW/P-IV/STR/2019/1903 1903 Checking for reinforcement & shuttering for wall 1st lift of A1 & A2 PUP Km 177+810 RHS 25-Jun-19 10:00 AM IPC-04 DONE
1954 NMSCEW/P-IV/STR/2019/1904 1904 Checking for pouring of concrete for M-30 Grade concrete for wall 1st lift of A1 & A2 PUP Km 177+810 RHS 25-Jun-19 10:20 AM IPC-04 DONE
1955 NMSCEW/P-IV/STR/2019/1905 1905 Checking Layout , levels and structural excavations for VUP VUP Km 179+983 BHS 25-Jun-19 9:00 AM IPC-08 DONE
1956 NMSCEW/P-IV/STR/2019/1906 1906 Checking for reinforcement & shuttering for wall 2nd lift of A1 & A2 LVUP Km 173+400 RHS 25-Jun-19 4:20 PM NR
1957 NMSCEW/P-IV/STR/2019/1907 1907 Checking for pouring of concrete for M-35 Grade concrete for wall 2nd lift of A1 & A2 LVUP Km 173+400 RHS 25-Jun-19 4:30 PM NR
1958 NMSCEW/P-IV/STR/2019/1908 1908 Checking for reinforcement & shuttering for raft LVUP Km 178+323 Km 00+000 LHS 25-Jun-19 9:30 AM IPC-09 DONE AE
1959 NMSCEW/P-IV/STR/2019/1909 1909 Checking for pouring of concrete for M-30 Grade concrete for raft LVUP Km 178+323 Km 00+000 LHS 25-Jun-19 9:40 AM IPC-09 DONE AE
1960 NMSCEW/P-IV/STR/2019/1910 1910 Checking of reinforcement and shuttering for pier shaft 1ST LIFT at RP 5. VIADUCT Km 169+800 RHS 25-Jun-19 9:30 AM NR
1961 NMSCEW/P-IV/STR/2019/1911 1911 Checking for pouring of concrete for M-45 Grade concrete for pier shaft 1ST LIFT at RP 5. VIADUCT Km 169+800 RHS 25-Jun-19 10:00 AM NR
1962 NMSCEW/P-IV/STR/2019/1912 1912 Checking of reinforcement and shuttering for pier shaft 2nd LIFT at RP 4. VIADUCT Km 169+800 RHS 25-Jun-19 9:45 AM NR
1963 NMSCEW/P-IV/STR/2019/1913 1913 Checking for pouring of concrete for M-45 Grade concrete for pier shaft 2nd LIFT at RP 4. VIADUCT Km 169+800 RHS 25-Jun-19 10:30 AM NR
Checking reinforcement for precast Box Culvert (2x2) (cushion 2m to 4m) at precast yard
1964 NMSCEW/P-IV/STR/2019/1914 1914 BOX CULVERT Km 200+200 LHS 25-Jun-19 8:50 AM DONE
camp -2 , Segment
Checking No-85,86,87
for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1965 NMSCEW/P-IV/STR/2019/1915 1915 BOX CULVERT Km 200+200 LHS 25-Jun-19 9:00 AM DONE
(2X2) (Cushion 2 to 4 m) at precast yard camp-2,Segment No- 85,86 &87
Checking reinforcement for precast Box Culvert (3x3) (cushion 0m to 2m) at precast yard
1966 NMSCEW/P-IV/STR/2019/1916 1916 BOX CULVERT Km 200+200 LHS 25-Jun-19 9:10 AM DONE
camp -2 , Segment
Checking No-44,45
for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1967 NMSCEW/P-IV/STR/2019/1917 1917 BOX CULVERT Km 200+200 LHS 25-Jun-19 9:20 AM DONE
(3X3) (Cushion
Checking 0 to 2 m)foratprecast
reinforcement precastBox
yardCulvert
camp-2,Segment No- 2m
(3x3) (cushion 44,45
to 4m) at precast yard
1968 NMSCEW/P-IV/STR/2019/1918 1918 BOX CULVERT Km 200+200 LHS 25-Jun-19 8:40 AM DONE
camp -2 , Segment No-14
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1969 NMSCEW/P-IV/STR/2019/1919 1919 BOX CULVERT Km 200+200 LHS 25-Jun-19 9:00 AM DONE
(3X3) (Cushion 2 to 4 m) at precast yard camp-2,Segment No- 14
1970 NMSCEW/P-IV/STR/2019/1920 1920 Checking for reinforcement & shuttering for W2 1st lift PUP Km 191+740 RHS 25-Jun-19 3:00 PM IPC-04 DONE
1971 NMSCEW/P-IV/STR/2019/1921 1921 Checking for pouring of concrete for W2 1st lift PUP Km 191+740 RHS 25-Jun-19 4:00 PM IPC-04 DONE
1972 NMSCEW/P-IV/STR/2019/1922 1922 Checking for reinforcement & shuttering for W1 1st lift of Box Culvert B.C. Km 200+460 RHS 25-Jun-19 12:00 PM IPC-05 DONE
1973 NMSCEW/P-IV/STR/2019/1923 1923 Checking for pouring of concrete for W1 1st lift of Box Culvert B.C. Km 200+460 RHS 25-Jun-19 2:00 PM IPC-05 DONE
Checking reinforcement for precast Box Culvert (2x2) (cushion 2m to 4m) at precast yard
1974 NMSCEW/P-IV/STR/2019/1924 1924 Box culvert Km 175+500 LHS 25-Jun-19 8:40 AM IPC-08 DONE AE 48, 49
camp -1, Segment
Checking No-48,49
for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1975 NMSCEW/P-IV/STR/2019/1925 1925 Box culvert Km 175+500 LHS 25-Jun-19 9:00 AM IPC-08 DONE 53, 54
(3X3) (Cushion
Checking 2 to 4 m)
for shuttering at precast
& Pouring ofyard camp-1,Segment
Concreting No- 53,54
Grade =(M-30) for Precast Box Culvert
1976 NMSCEW/P-IV/STR/2019/1926 1926 Box culvert 175+500 LHS 25-Jun-19 9:15 AM IPC-08 DONE AE 59, 60
(2X2) (Cushion 0 to 2 m) at precast yard camp-1,Segment No- 59,60
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
1977 NMSCEW/P-IV/STR/2019/1927 1927 BOX CULVERT Km 175+500 LHS 25-Jun-19 9:30 AM NR
(2X2) (Cushion 2 to 4 m) at precast yard camp-1,Segment No- 48,49
1978 NMSCEW/P-IV/STR/2019/1928 1928 Layout & level checking for box culvert. Km 167+696 LHS 25-Jun-19 11:00 AM NR
1979 NMSCEW/P-IV/STR/2019/1929 1929 Structural Excavation for box culvert Km 167+696 LHS 25-Jun-19 11:30 AM NR
1980 NMSCEW/P-IV/STR/2019/1930 1930 Checking of PCC of box culvert Km 167+696 LHS 25-Jun-19 3:00 PM NR
1981 NMSCEW/P-IV/STR/2019/1931 1931 Checking of reinforcement and shuttering for top level of raft at LP-5 Viaduct Km 202+190 LHS 25-Jun-19 3:00 PM IPC-04 DONE AE
1982 NMSCEW/P-IV/STR/2019/1932 1932 Checking for pouring of concrete for M-35 Grade concrete of raft at LP-5 VIADUCT Km 202+190 LHS 25-Jun-19 3:30 PM IPC-04 DONE AE
1983 NMSCEW/P-IV/STR/2019/1933 1933 Checking layout ,level and structural excavation at utility duct Utility duct Km 207+210 BHS 26-Jun-19 8:00 AM DONE
1984 NMSCEW/P-IV/STR/2019/1934 1934 Checking top Level & Laying concrete PCC at Utility duct Utility duct Km 207+210 BHS 26-Jun-19 8:30 AM DONE
1985 NMSCEW/P-IV/STR/2019/1935 1935 Checking layout ,level and structural excavation at utility duct Utility duct Km 193+350 BHS 26-Jun-19 10:00 AM IPC-05 DONE
1986 NMSCEW/P-IV/STR/2019/1936 1936 Checking top Level & Laying concrete PCC at Utility duct Utility duct Km 193+350 BHS 26-Jun-19 11:45 AM IPC-05 DONE
1987 NMSCEW/P-IV/STR/2019/1937 1937 Checking for Level & Layout for PCC at (LP 8) Viaduct Km 202+190 LHS 26-Jun-19 10:00 AM
1988 NMSCEW/P-IV/STR/2019/1938 1938 Checking top Level & Laying concrete PCC at LP8 Viaduct Km 202+190 LHS 26-Jun-19 11:00 AM
1989 NMSCEW/P-IV/STR/2019/1939 1939 Checking of reinforcement & shuttering in bottom slab of PUP PUP Km 187+835 LHS 26-Jun-19 9:00 AM IPC-05 DONE AE
1990 NMSCEW/P-IV/STR/2019/1940 1940 Checking and pouring concrete(M-30) IN bottom slab of PUP PUP Km 187+835 LHS 26-Jun-19 9:30 AM IPC-05 DONE
1991 NMSCEW/P-IV/STR/2019/1941 1941 Checking of reinforcement & shuttering for wall 2nd lift A1 & A2 LVUP Km 173+400 RHS 26-Jun-19 9:45 AM NR
1992 NMSCEW/P-IV/STR/2019/1942 1942 Checking and pouring of concrete (M-35) for wall 2nd lift A1 & A2 LVUP Km 173+400 RHS 26-Jun-19 10:00 AM NR
1993 NMSCEW/P-IV/STR/2019/1943 1943 Checking of reinforcement & shuttering for wall final lift A1 & A2 PUP Km 174+095 LHS 26-Jun-19 11:00 AM IPC-04 DONE
1994 NMSCEW/P-IV/STR/2019/1944 1944 Checking and pouring of concrete (M-30) for wall final lift A1 & A2 PUP Km 174+095 LHS 26-Jun-19 11:15 AM IPC-04 DONE
1995 NMSCEW/P-IV/STR/2019/1945 1945 Checking for reinforcement & shuttering for top haunch at top slab PUP Km 174+095 LHS 26-Jun-19 6:00 PM IPC-04 DONE
1996 NMSCEW/P-IV/STR/2019/1946 1946 Checking and pouring of concrete (M-30) for top haunch at top slab PUP Km 174+095 LHS 26-Jun-19 6:20 PM IPC-04 DONE
1997 NMSCEW/P-IV/STR/2019/1947 1947 Checking top Level & Laying concrete PCC at VUP VUP Km 179+983 RHS 26-Jun-19 9:00 AM IPC-08 DONE
Checking reinforcement for precast Box Culvert (3x3) (cushion 2 to 4m) at precast yard camp
1998 NMSCEW/P-IV/STR/2019/1948 1948 Box culvert Km 175+500 LHS 26-Jun-19 8:30 AM IPC-08 DONE 57, 58
-1. Segment NO-57,58
1999 NMSCEW/P-IV/STR/2019/1949 1949 Checking reinforcement for precast Box Culvert (2x2) (cushion 0 to 2m) at precast yard cam Box culvert Km 163+830 BHS 26-Jun-19 9:30 AM IPC-05 DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2000 NMSCEW/P-IV/STR/2019/1950 1950 Box culvert Km 175+500 LHS 26-Jun-19 10:00 AM IPC-08 DONE 57
(3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-57,58
2001 NMSCEW/P-IV/STR/2019/1951 1951 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2×2 Box culvert Km 163+830 BHS 26-Jun-19 10:20 AM IPC-05 DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2002 NMSCEW/P-IV/STR/2019/1952 1952 Box culvert Km 175+500 LHS 26-Jun-19 10:30 AM IPC-08 DONE AE 48
(2×2) (Cushion
Checking 2 to 4m) for
reinforcement at precast
precastyard
Boxcamp-1,Segment no.-48,49
Culvert (2x2) (cushion 2 to 4m) at precast yard camp
2003 NMSCEW/P-IV/STR/2019/1953 1953 Box culvert Km 200+200 LHS 26-Jun-19 8:30 AM DONE
-2. Segment
Checking NO-88,89,90
reinforcement for precast Box Culvert (3x3) (cushion 0 to 2m) at precast yard camp
2004 NMSCEW/P-IV/STR/2019/1954 1954 Box culvert Km 200+200 LHS 26-Jun-19 9:30 AM DONE
-2 Segment
Checking forNO-46,47
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2005 NMSCEW/P-IV/STR/2019/1955 1955 Box culvert Km 200+200 LHS 26-Jun-19 8:40 AM DONE
(2×2) (Cushion
Checking 2 to 4m)&atPouring
for shuttering precast yard camp-2,Segment
of Concreting no.-88,89,90
Grade =(M-30) for Precast Box Culvert
2006 NMSCEW/P-IV/STR/2019/1956 1956 Box culvert Km 200+200 LHS 26-Jun-19 9:40 AM DONE
(3×3) (Cushion 0 to 2m) at precast yard camp-2,Segment no.-46,47
2007 NMSCEW/P-IV/STR/2019/1957 1957 Checking of reinforcement & shuttering for wall W2 2nd lift PUP Km 203+560 RHS 26-Jun-19 8:00 AM IPC-04 DONE
2008 NMSCEW/P-IV/STR/2019/1958 1958 Checking and pouring of concrete (M-30) for wall W2 2nd lift PUP Km 203+560 RHS 26-Jun-19 9:00 AM IPC-04 DONE AE
2009 NMSCEW/P-IV/STR/2019/1959 1959 Checking of reinforcement & shuttering for wall W2 nd lift PUP Km 191+740 RHS 26-Jun-19 2:00 PM IPC-04 DONE
2010 NMSCEW/P-IV/STR/2019/1960 1960 Checking and pouring of concrete (M-30) for wall W2 2nd lift PUP Km 191+740 RHS 26-Jun-19 3:00 PM IPC-04 DONE
2011 NMSCEW/P-IV/STR/2019/1961 1961 Checking of reinforcement & shuttering for wall 2ndt lift A1, A2 CUP Km 183+290 LHS 26-Jun-19 11.00 AM IPC-04 DONE
2012 NMSCEW/P-IV/STR/2019/1962 1962 Checking level and pouring concrete(M30) for wall 2nd lift of PUP A1, A2 CUP Km 183+290 LHS 26-Jun-19 11.30 AM IPC-04 DONE
2013 NMSCEW/P-IV/STR/2019/1963 1963 Checking of PCC of box culvert Km 167+696 LHS 26-Jun-19 3:00 PM NR
2014 NMSCEW/P-IV/STR/2019/1964 1964 Checking of reinforcement & shuttering for top level of raft at RP 8 Viaduct Km 195+900 RHS 26-Jun-19 3:00 PM IPC-04 DONE
2015 NMSCEW/P-IV/STR/2019/1965 1965 Checking and pouring of concrete (M-35) for top level of raft at RP 8 Viaduct Km 195+900 RHS 26-Jun-19 3:30 PM IPC-04 DONE
2016 NMSCEW/P-IV/STR/2019/1966 1966 Checking layout ,level and structural excavation at utility duct Utility duct Km 192+130 Km 00+000 BHS 27-Jun-19 10:00 AM IPC-11 Approved
2017 NMSCEW/P-IV/STR/2019/1967 1967 Checking top Level & Laying concrete PCC (M-10) at Utility duct Utility duct Km 192+130 Km 00+000 BHS 27-Jun-19 12:45 PM IPC-11 Approved
2018 NMSCEW/P-IV/STR/2019/1968 1968 Checking of reinforcement and shuttering for pier shaft 1st lift at RP5 VIADUCT Km 169+800 RHS 27-Jun-19 3:00 PM IPC-08 DONE
2019 NMSCEW/P-IV/STR/2019/1969 1969 Checking top level & Laying concrete (M-45) for pier shaft 1st lift at RP5 VIADUCT Km 169+800 RHS 27-Jun-19 4:30 PM IPC-08 DONE
2020 NMSCEW/P-IV/STR/2019/1970 1970 Checking of reinforcement & shuttering for wall final lift at A1 &A2 PUP Km 171+110 LHS 27-Jun-19 11:00 AM NR
2021 NMSCEW/P-IV/STR/2019/1971 1971 Checking level and pouring concrete(M30) for wall final lift at A1 &A2 PUP Km 171+110 LHS 27-Jun-19 11:20 AM NR
2022 NMSCEW/P-IV/STR/2019/1972 1972 Laying and top level checking of concrete for PCC for VUP VUP Km 179+983 Km 00+000 LHS 27-Jun-19 9:00 AM IPC-10 DONE
2023 NMSCEW/P-IV/STR/2019/1973 1973 checking of TOP haunch A1 &A2 reinforcement & shuttering for PUP PUP Km 171+110 LHS 27-Jun-19 5:30 PM NR
2024 NMSCEW/P-IV/STR/2019/1974 1974 checking of final lift wall & TOP slab reinforcement & shuttering for PUP PUP Km 171+110 LHS 27-Jun-19 5:40 PM IPC-04 DONE
2025 NMSCEW/P-IV/STR/2019/1975 1975 Checking top Level & Laying M30 concrete pouring at final lift, TOP haunch A1 &A2 and to PUP Km 171+110 LHS 27-Jun-19 5:50 PM IPC-04 DONE
2026 NMSCEW/P-IV/STR/2019/1976 1976 Checking top Level & Laying M30 concrete pouring at TOP slab for PUP PUP Km 171+110 LHS 27-Jun-19 6:00 PM NR
2027 NMSCEW/P-IV/STR/2019/1977 1977 Checking of reinforcement & shuttering for wall 2nd lift at A1 &A2 LVUP Km 173+400 RHS 27-Jun-19 6:00 PM NR
2028 NMSCEW/P-IV/STR/2019/1978 1978 Checking level and pouring concrete(M30) for wall 2nd lift at A1 &A2 LVUP Km 173+400 RHS 27-Jun-19 6:00 PM NR
2029 NMSCEW/P-IV/STR/2019/1979 1979 Checking reinforcement ,shuttering for 1st lift at wall A1 & A2 PUP Km 165+300 RHS 27-Jun-19 11:00 AM IPC-05 DONE
2030 NMSCEW/P-IV/STR/2019/1980 1980 Checking level and pouring concrete(M30) for wall 1st lift at A1 &A2 PUP Km 165+300 RHS 27-Jun-19 11:15 AM IPC-05 DONE
Checking reinforcement for precaste box culvert (2x2) ,(cusion 2 to 4m ) at casting yard of
2031 NMSCEW/P-IV/STR/2019/1981 1981 Box Culvert Km 200+200 LHS 27-Jun-19 8:20 AM DONE
camp -2 location
Checking Segment
for shuttering No. 91 Pouring (M-30) for precast box culvert (2x2) ,(cusion 2 to
&concrete
2032 NMSCEW/P-IV/STR/2019/1982 1982 Box Culvert Km 200+200 LHS 27-Jun-19 8:30 AM DONE
4m ) at casting
Checking yard of camp
reinforcement -2 location
for precaste box Segment No. 91
culvert (3x3) ,(cusion 0 to 2m ) at casting yard of
2033 NMSCEW/P-IV/STR/2019/1983 1983 Box Culvert Km 200+200 LHS 27-Jun-19 8:40 AM DONE
camp -2 location
Checking Segment&No.
for shuttering 48,49 Pouring (M-30) for precast box culvert (3x3) ,(cusion 0
concrete
2034 NMSCEW/P-IV/STR/2019/1984 1984 Box Culvert Km 200+200 LHS 27-Jun-19 8:50 AM DONE
to 2m ) at casting yard of camp -2 location Segment No. 48,49
2035 NMSCEW/P-IV/STR/2019/1985 1985 Checking for level & Layout for PCC at LA1 VIADUCT Km 202+190 LHS 27-Jun-19 10:00 AM IPC-08 DONE
2036 NMSCEW/P-IV/STR/2019/1986 1986 Checking for pouring of concrete for PCC at LA1 VIADUCT Km 202+190 LHS 27-Jun-19 11:00 AM IPC-08 DONE
2037 NMSCEW/P-IV/STR/2019/1987 1987 Checking for pouring of concrete for pier shaft starter of (LP-3) VIADUCT Km 202+190 LHS 27-Jun-19 2:00 PM
2038 NMSCEW/P-IV/STR/2019/1988 1988 Checking of reinforcement & shuttering for wall 2ndt lift A1, A2 CUP Km 185+235 LHS 27-Jun-19 9.00 AM IPC-04 DONE
2039 NMSCEW/P-IV/STR/2019/1989 1989 Checking level and pouring concrete(M30) for wall 2nd lift of PUP A1, A2 PUP Km 185+235 LHS 27-Jun-19 9:10 AM IPC-04 DONE
2040 NMSCEW/P-IV/STR/2019/1990 1990 Checking for layout & level FOR Box Culvert Box Culvert Km 182+350 BHS 27-Jun-19 11:00 AM NR
2041 NMSCEW/P-IV/STR/2019/1991 1991 Checking top Level & Laying concrete PCC (M-10) FOR Box Culvert Box Culvert Km 182+350 BHS 27-Jun-19 11:20 AM NR
Checking reinforcement for precaste box culvert (3x3) ,(cusion 2 to 4m ) at casting yard of
2042 NMSCEW/P-IV/STR/2019/1992 1992 Box Culvert Km 175+500 LHS 27-Jun-19 8:40 AM DONE
camp -1 location Segment No. 59
2043 NMSCEW/P-IV/STR/2019/1993 1993 Checking reinforcement for precaste box culvert (2x2) ,(cusion 0 to 2m ) at casting yard of Box Culvert Km 163+830 BHS 27-Jun-19 8:50 AM IPC-05 DONE
Checking reinforcement for precaste box culvert (2x2) ,(cusion 2 to 4m ) at casting yard of
2044 NMSCEW/P-IV/STR/2019/1994 1994 Box Culvert Km 175+500 LHS 27-Jun-19 9:00 AM IPC-08 DONE AE 50, 51
camp -1 location Segment No. 50,51
Checking for shuttering &concrete Pouring (M-30) for precast box culvert (3x3) ,(cusion 2 to
2045 NMSCEW/P-IV/STR/2019/1995 1995 Box Culvert Km 175+500 LHS 27-Jun-19 9:10 AM IPC-08 DONE 58
4m ) at casting
Checking yard of camp
for shuttering -1 location
&concrete Segment
Pouring (M-30)No.
for58,59
precast box culvert (2x2) ,(cusion 0 to
2046 NMSCEW/P-IV/STR/2019/1996 1996 Box Culvert Km 175+500 LHS 27-Jun-19 9:15 AM IPC-08 DONE 64, 65
2m ) at casting
Checking yard of camp
for shuttering -1 location
&concrete Segment
Pouring (M-30)No.
for64,65,66 &67culvert (2x2) ,(cusion 2 to
precast box
2047 NMSCEW/P-IV/STR/2019/1997 1997 Box Culvert Km 175+500 LHS 27-Jun-19 9:20 AM IPC-08 DONE AE 50
4m ) at casting yard of camp -1 location Segment No. 50,51
2048 NMSCEW/P-IV/STR/2019/1998 1998 Checking of reinforcement & shuttering for 2nd lift at A1 & A2 wall PUP Km 177+810 RHS 27-Jun-19 11.20 AM IPC-04 DONE
2049 NMSCEW/P-IV/STR/2019/1999 1999 Checking and pouring concrete(M-30) for 2nd lift at A1 & A2 wall PUP Km 177+810 RHS 27-Jun-19 11.59 AM IPC-04 DONE
2050 NMSCEW/P-IV/STR/2019/2000 2000 Checking of PCC of box culvert Km 167+696 LHS 27-Jun-19 3:00 PM NR
2051 NMSCEW/P-IV/STR/2019/2001 2001 Checking reinforcement ,shuttering for top Lift at Wall A1 & A2 of Cup CUP Km 183+290 RHS 27-Jun-19 2.00 pm IPC-04 DONE
2052 NMSCEW/P-IV/STR/2019/2002 2002 Checking level and pouring concrete(M30) for top lift of wall CUP Km 183+290 RHS 27-Jun-19 3:00 PM IPC-04 DONE
2053 NMSCEW/P-IV/STR/2019/2003 2003 Checking for level & Layout for PCC at LP9 VIADUCT Km 202+190 LHS 28-Jun-19 10:00 AM IPC-08 DONE AE
2054 NMSCEW/P-IV/STR/2019/2004 2004 Checking top level & pouring of concrete for PCC at LP9 VIADUCT Km 202+190 LHS 28-Jun-19 11:00 AM IPC-08 DONE AE
2055 NMSCEW/P-IV/STR/2019/2005 2005 Checking for pouring of concrete for pier shaft starter of LP3 VIADUCT Km 202+190 LHS 28-Jun-19 2:00 PM
2056 NMSCEW/P-IV/STR/2019/2006 2006 Checking for level & Layout for PCC at RA2 VIADUCT Km 196+560 RHS 28-Jun-19 10:30 AM IPC-08 DONE
2057 NMSCEW/P-IV/STR/2019/2007 2007 Checking top level & pouring of concrete for PCC at RA2 VIADUCT Km 196+560 RHS 28-Jun-19 11:30 AM IPC-08 DONE
2058 NMSCEW/P-IV/STR/2019/2008 2008 Layout & level checking for box culvert. BOX CULVERT Km 204+920 BHS 28-Jun-19 9:00 AM
2059 NMSCEW/P-IV/STR/2019/2009 2009 Structural Excavation for box culvert BOX CULVERT Km 204+920 BHS 28-Jun-19 9:30 AM
2060 NMSCEW/P-IV/STR/2019/2010 2010 Checking of PCC of box culvert BOX CULVERT Km 204+920 BHS 28-Jun-19 10:20 AM
2061 NMSCEW/P-IV/STR/2019/2011 2011 Checking of reinforcement & shuttering for final lift for A1 & A2 wall LVUP Km 173+400 LHS 28-Jun-19 10:40 AM NR
2062 NMSCEW/P-IV/STR/2019/2012 2012 Checking and pouring concrete(M-35) for final lift for A1 & A2 wall LVUP Km 173+400 LHS 28-Jun-19 11:10 AM NR
2063 NMSCEW/P-IV/STR/2019/2013 2013 Checking reinforcement ,shuttering for top haunch at wall A1 & A2 with top slab LVUP Km 173+400 LHS 28-Jun-19 5:20 PM NR
2064 NMSCEW/P-IV/STR/2019/2014 2014 Checking and concrete (M35) pouring in top haunch at wall A1 & A2 with top slab LVUP Km 173+400 LHS 28-Jun-19 5:50 PM NR
2065 NMSCEW/P-IV/STR/2019/2015 2015 Checking of reinforcement & shuttering for 2nd lift for A1 & A2 wall LVUP Km 173+400 RHS 28-Jun-19 10:50 AM IPC-05 DONE
2066 NMSCEW/P-IV/STR/2019/2016 2016 Checking and pouring concrete(M-35) for 2nd lift for A1 & A2 wall LVUP Km 173+400 RHS 28-Jun-19 12:00 PM IPC-05 DONE
2067 NMSCEW/P-IV/STR/2019/2017 2017 Checking of layout and level for raft of B/C BOX CULVERT Km 204+920 BHS 28-Jun-19 9:20 AM IPC-05 DONE
2068 NMSCEW/P-IV/STR/2019/2018 2018 Checking of layout level and Structural Excavation for box culvert Box culvert Km 182+350 BHS 28-Jun-19 12:22 PM IPC-08 DONE
2069 NMSCEW/P-IV/STR/2019/2019 2019 Checking of PCC of box culvert Box culvert Km 182+350 BHS 28-Jun-19 1:00 PM IPC-08 DONE
2070 NMSCEW/P-IV/STR/2019/2019A 2019A Checking of Layout & Level for LP3 Viaduct Km 202+190 LHS 28-Jun-19 1:00 PM IPC-04 DONE
2071 NMSCEW/P-IV/STR/2019/2019B 2019B Checking level for excavated bed for at LP3 Viaduct Km 202+190 LHS 28-Jun-19 5:00 PM IPC-04 DONE
2072 NMSCEW/P-IV/STR/2019/2019C 2019C Checking top Level & Laying concrete PCC for LP3 Viaduct Km 202+190 LHS 29-Jun-19 11:00Am IPC-04 DONE
Checking for reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard
2073 NMSCEW/P-IV/STR/2019/2020 2020 BOX CULVERT Km 200+200 LHS 28-Jun-19 9:33 AM DONE
camp -2. Segment
Checking NO-92,93,94.
for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2074 NMSCEW/P-IV/STR/2019/2021 2021 Checking for reinforcement for precast (cushion 0 to 2m) at precast yard BOX CULVERT Km 200+200 LHS 28-Jun-19 10:45 AM DONE
(2×2) (Cushion 2 to 4m) at precast yard Box Culvert (3x3)no-92,93,94.
camp-2.Segment
2075 NMSCEW/P-IV/STR/2019/2022 2022 camp -2. Segment NO-50,51,52. BOX CULVERT Km 200+200 LHS 28-Jun-19 4:00 PM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2076 NMSCEW/P-IV/STR/2019/2023 2023 BOX CULVERT Km 200+200 LHS 28-Jun-19 5:05 PM DONE
(3×3) (Cushion 0 to 2m) at precast yard camp-2,Segment no-50,51,52.
2077 NMSCEW/P-IV/STR/2019/2024 2024 Checking reinforcement ,shuttering for top haunch with top slab PUP Km 186+000 RHS 28-Jun-19 2:00 PM NR
2078 NMSCEW/P-IV/STR/2019/2025 2025 Checking and
Checking concrete (M30)
reinforcement pouring
for precast Boxfor top haunch
Culvert with top2m
(3x3) (cushion slab
to 4m) at precast yard PUP Km 186+000 RHS 28-Jun-19 3:02 PM NR
2079 NMSCEW/P-IV/STR/2019/2026 2026 camp -1. Segment NO-60,61 Box culvert Km 175+500 LHS 28-Jun-19 9:15 AM IPC-08 DONE AE 60, 61
Checking for shuttering & Pouring of Concreting Grade (M-30) for Precast Box Culvert
2080 NMSCEW/P-IV/STR/2019/2027 2027 Box culvert Km 175+500 LHS 28-Jun-19 9:43 AM IPC-08 DONE AE 60, 61
(3x3) , (cushion
Checking 2m to 4m)foratprecast
reinforcement precastBox
yardCulvert
camp -1. Segment
(2x2) NO-60,61
(cushion 2m to 4m) at precast yard
2081 NMSCEW/P-IV/STR/2019/2028 2028 Box culvert Km 175+500 LHS 28-Jun-19 3:00 PM DONE
camp -1. Segment
Checking NO-52
for shuttering & Pouring of Concreting Grade (M-30) for Precast Box Culvert
2082 NMSCEW/P-IV/STR/2019/2029 2029 Box culvert Km 175+500 LHS 28-Jun-19 4:10 PM DONE
(2×2) , (cushion 2m to 4m) ,at precast yard camp -1. Segment NO-49,52
2083 NMSCEW/P-IV/STR/2019/2030 2030 Checking for shuttering & Pouring of Concreting Grade (M-30) for Precast Box Culvert (2×2) Box culvert Km 163+830 BHS 28-Jun-19 5:50 PM IPC-05 DONE
2084 NMSCEW/P-IV/STR/2019/2031 2031 Checking of reinforcement and shuttering for pier shaft 2nd lift at RP4 Viaduct Km 169+800 RHS 28-Jun-19 10:05 AM NR
2085 NMSCEW/P-IV/STR/2019/2032 2032 Checking for Pouring of concrete for pier shaft 2nd lift at RP4 Viaduct Km 169+800 RHS 28-Jun-19 11:13 AM NR
2086 NMSCEW/P-IV/STR/2019/2033 2033 Checking of reinforcement & shuttering for 1st lift for W1 wall PUP Km 199+060 LHS 28-Jun-19 2:11 PM IPC-04 DONE
2087 NMSCEW/P-IV/STR/2019/2034 2034 Checking and pouring concrete for 1st lift for W1 wall PUP Km 199+060 LHS 28-Jun-19 3:11 PM IPC-04 DONE
2088 NMSCEW/P-IV/STR/2019/2035 2035 Checking of reinforcement & shuttering for raft for B/C BOX CULVERT Km 204+920 BHS 28-Jun-19 3:23 PM IPC-05 DONE
2089 NMSCEW/P-IV/STR/2019/2036 2036 Checking and pouring concrete for raft for B/C BOX CULVERT Km 204+920 BHS 28-Jun-19 3:46 PM IPC-05 DONE
2090 NMSCEW/P-IV/STR/2019/2037 2037 Checking of reinforcement & shuttering for 2nd lift for W1 wall PUP Km 191+740 RHS 28-Jun-19 4:09 PM IPC-04 DONE AE
2091 NMSCEW/P-IV/STR/2019/2038 2038 Checking and pouring concrete for 2nd lift for W1 wall PUP Km 191+740 RHS 28-Jun-19 5:09 PM IPC-04 DONE AE
2092 NMSCEW/P-IV/STR/2019/2039A 2039A Checking of reinforcement & shuttering for 1st lift for W2 wall PUP Km 193+880 LHS 29-Jun-19 2:00 PM IPC-08 DONE
2093 NMSCEW/P-IV/STR/2019/2039 2039 Checking of reinforcement & shuttering for 1st lift for W2 wall PUP Km 193+880 RHS 29-Jun-19 2:00 PM IPC-04 DONE AE
2094 NMSCEW/P-IV/STR/2019/2040A 2040A Checking and pouring concrete for 1st lift for W2 wall PUP Km 193+880 LHS 29-Jun-19 3:00 PM IPC-08 DONE
2095 NMSCEW/P-IV/STR/2019/2040 2040 Checking and pouring concrete for 1st lift for W2 wall PUP Km 193+880 RHS 29-Jun-19 3:00 PM IPC-04 DONE AE
2096 NMSCEW/P-IV/STR/2019/2041 2041 Checking of reinforcement & shuttering for 1st lift for W2 wall PUP Km 203+560 LHS 29-Jun-19 2:30 PM IPC-04 DONE
2097 NMSCEW/P-IV/STR/2019/2042 2042 Checking and pouring concrete for 1st lift for W2 wall PUP Km 203+560 LHS 29-Jun-19 3:30 PM IPC-04 DONE
2098 NMSCEW/P-IV/STR/2019/2043 2043 Layout & level checking for box culvert. Box culvert Km 162+832 BHS 29-Jun-19 9:00 AM NR
2099 NMSCEW/P-IV/STR/2019/2044 2044 Structural Excavation for box culvert Box culvert Km 162+832 BHS 29-Jun-19 9:30 AM NR
2100 NMSCEW/P-IV/STR/2019/2045 2045 conc in raft at RP8 Viaduct Km 195+900 RHS 29-Jun-19 10:20 AM IPC-04 DONE
2101 NMSCEW/P-IV/STR/2019/2046 2046 Checking of reinforcement & shuttering for top Slab PUP Km 204+470 LHS 29-Jun-19 3:15 PM IPC-04 DONE AE
2102 NMSCEW/P-IV/STR/2019/2047 2047 Checking Layout & level checking for top Slab PUP Km 204+470 LHS 29-Jun-19 3:35 PM IPC-04 DONE AE
2103 NMSCEW/P-IV/STR/2019/2048 2048 Checking and pouring concrete for top Slab PUP Km 204+470 LHS 29-Jun-19 5:05 PM IPC-04 DONE AE
2104 NMSCEW/P-IV/STR/2019/2049 2049 Checking of reinforcement & shuttering for top Slab CUP Km 208+930 LHS 29-Jun-19 4:15 PM IPC-04 DONE AE
2105 NMSCEW/P-IV/STR/2019/2050 2050 Checking Layout & level checking for top Slab CUP Km 208+930 LHS 29-Jun-19 4:20 PM IPC-04 DONE AE
2106 NMSCEW/P-IV/STR/2019/2051 2051 Checking and pouring concrete for top Slab CUP Km 208+930 BHS 29-Jun-19 6:00 PM IPC-04 DONE AE
2107 NMSCEW/P-IV/STR/2019/2052 2052 Checking of irrection and fixing segment of utility duct (2×2) Utility duct Km 163+830 BHS 29-Jun-19 10:00 AM IPC-05 DONE
2108 NMSCEW/P-IV/STR/2019/2053 2053 Checking of reinforcement & shuttering for final lift for A1 & A2 wall PUP Km 177+810 RHS 29-Jun-19 10:50 AM IPC-04 DONE
2109 NMSCEW/P-IV/STR/2019/2054 2054 Checking and pouring concrete(M-30) for final lift for A1 & A2 wall PUP Km 177+810 RHS 29-Jun-19 11:11 AM IPC-04 DONE
2110 NMSCEW/P-IV/STR/2019/2055 2055 Checking reinforcement ,shuttering for top haunch at wall A1 & A2 with top slab PUP Km 177+810 RHS 29-Jun-19 6:10 PM IPC-04 DONE
2111 NMSCEW/P-IV/STR/2019/2056 2056 Inspection of precast segment errection completion (2x2)of utility duct Utility duct Km 193+700 BHS 29-Jun-19 10:00 AM IPC-04 DONE AE
2112 NMSCEW/P-IV/STR/2019/2057 2057 Structural Excavation for box culvert Box culvert Km 209+470 BHS 29-Jun-19 10:00 AM WRONG RFI
2113 NMSCEW/P-IV/STR/2019/2058 2058 Checking of PCC of box culvert Box culvert Km 209+470 BHS 29-Jun-19 12:30 PM WRONG RFI
2114 NMSCEW/P-IV/STR/2019/2059 2059 Checking and concrete (M30) pouring in top haunch at wall A1 & A2 with top slab PUP Km 177+810 RHS 29-Jun-19 6:40 PM IPC-04 DONE
2115 NMSCEW/P-IV/STR/2019/2060 2060 Checking reinforcement ,shuttering for bottom haunch at wall A1 & A2 LVUP Km 178+323 Km 00+000 LHS 29-Jun-19 11:33 AM IPC-09 DONE
2116 NMSCEW/P-IV/STR/2019/2061 2061 Checking and concrete(M-35) pouring for bottom haunch at wall A1 & A2 LVUP Km 178+323 Km 00+000 LHS 29-Jun-19 12:10 PM IPC-09 DONE
2117 NMSCEW/P-IV/STR/2019/2062 2062 Checking of layout ,level and Structural Excavation for box culvert Box culvert Km 180+427 BHS 29-Jun-19 10:25 AM IPC-08 DONE
Checking of reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard
2118 NMSCEW/P-IV/STR/2019/2063 2063 Box culvert Km 200+200 LHS 29-Jun-19 9:50 AM DONE
camp -2. Segment
Checking NO-95,96,97,98.
for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2119 NMSCEW/P-IV/STR/2019/2064 2064 Checking of reinforcement for precast Box culvert Km 200+200 LHS 29-Jun-19 11:17 AM DONE
(2×2) (Cushion 2 to 4m) at precast yardBox Culvert (3x3) (cushion
camp-2.Segment 0 to 2m) at precast yard
no-95,96,97,98.
2120 NMSCEW/P-IV/STR/2019/2065 2065 camp -2. Segment NO-53,54,55. Box culvert Km 200+200 LHS 29-Jun-19 2:40 PM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2121 NMSCEW/P-IV/STR/2019/2066 2066 Box culvert Km 200+200 LHS 29-Jun-19 3:42 PM DONE
(3×3)(Cushion 0 to 2m) at precast yard camp-2,Segment no-53,54,55.
2122 NMSCEW/P-IV/STR/2019/2067 2067 Checking of reinforcement & shuttering for top haunch & top Slab CUP Km 183+290 RHS 29-Jun-19 4:02 PM IPC-04 DONE
2123 NMSCEW/P-IV/STR/2019/2068 2068 Checking and pouring concrete(M-30) for top haunch & top Slab CUP Km 183+290 RHS 29-Jun-19 4:39 PM IPC-04 DONE
2124 NMSCEW/P-IV/STR/2019/2069 2069 Checking of reinforcement and shuttering for raft at RP6 Viaduct Km 202+190 RHS 29-Jun-19 3:01 PM IPC-04 DONE AE
2125 NMSCEW/P-IV/STR/2019/2070 2070 Checking and Pouring of concrete(M-35) for raft at RP6 Viaduct Km 202+190 RHS 29-Jun-19 4:09 PM IPC-04 DONE AE
2126 NMSCEW/P-IV/STR/2019/2071 2071 Checking for level & Layout for PCC at LP8 Viaduct Km 202+190 LHS 29-Jun-19 11:08 AM
2127 NMSCEW/P-IV/STR/2019/2072 2072 Checking top level & pouring of concrete for PCC at LP8 Viaduct Km 202+190 LHS 29-Jun-19 12:08 PM
2128 NMSCEW/P-IV/STR/2019/2073 2073 Checking for level & Layout for pier shaft starter at LP3 Viaduct Km 202+190 LHS 29-Jun-19 10:13 AM
2129 NMSCEW/P-IV/STR/2019/2074 2074 Checking for pouring of concrete for pier shaft starter of LP3 Viaduct Km 202+190 LHS 29-Jun-19 11:19 AM
2130 NMSCEW/P-IV/STR/2019/2075 2075 Checking for level & Layout for PCC at RP5 Viaduct Km 200+920 RHS 29-Jun-19 10:18 AM IPC-08 DONE AE
2131 NMSCEW/P-IV/STR/2019/2076 2076 Checking top level & pouring of concrete for PCC at RP5 Viaduct Km 200+920 RHS 29-Jun-19 11:32 AM IPC-08 DONE AE
Checking reinforcement for precast Box Culvert (3x3)(cushion 2 to 4m) at precast yard camp
2132 NMSCEW/P-IV/STR/2019/2077 2077 Box culvert Km 175+500 LHS 29-Jun-19 9:21 AM IPC-08 DONE 59, 62, 63
-1. Segment
Checking for NO-59,62,63
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2133 NMSCEW/P-IV/STR/2019/2078 2078 Box culvert Km 175+500 LHS 29-Jun-19 10:19 AM IPC-08 DONE 59
(3×3) (Cushion
Checking 2 to 4m) for
reinforcement at precast
precastyard
Boxcamp-1,Segment no.-59,62,63
Culvert (2x2) (Cushion 2 to 4m) at precast yard camp
2134 NMSCEW/P-IV/STR/2019/2079 2079 Box culvert Km 175+500 LHS 29-Jun-19 12:23 PM IPC-08 DONE 53,54,55
-1. Segment
Checking for NO-53,54,55
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2135 NMSCEW/P-IV/STR/2019/2080 2080 Box culvert Km 175+500 LHS 29-Jun-19 4:21 PM IPC-08 DONE 53
(2×2) (Cushion
Checking 2 to 4m) for
reinforcement at precast
precastyard
Boxcamp-1,Segment no.-53,54,55
Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
2136 NMSCEW/P-IV/STR/2019/2081 2081 Box culvert Km 175+500 LHS 29-Jun-19 12:55 PM IPC-08 DONE AE 66, 67, 68
-1. Segment
Checking for NO-66,67,68
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2137 NMSCEW/P-IV/STR/2019/2082 2082 Box culvert Km 175+500 LHS 29-Jun-19 5:26 PM NR
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-66,67,68
2138 NMSCEW/P-IV/STR/2019/2083 2083 Checking of reinforcement and shuttering for pier shaft 2nd lift at RP4 Viaduct Km 169+800 RHS 29-Jun-19 10:06 AM IPC-08 DONE
2139 NMSCEW/P-IV/STR/2019/2084 2084 Checking for Pouring of concrete for pier shaft 2nd lift at RP4 Viaduct Km 169+800 RHS 29-Jun-19 11:16 AM IPC-08 DONE
2140 NMSCEW/P-IV/STR/2019/2085 2085 Checking reinforcement ,shuttering for top haunch with top slab PUP Km 188+575 RHS 29-Jun-19 2:06 PM NR
2141 NMSCEW/P-IV/STR/2019/2086 2086 Checking and concrete (M30) pouring for top haunch with top slab PUP Km 188+575 RHS 29-Jun-19 3:25 PM NR
2142 NMSCEW/P-IV/STR/2019/2087 2087 Checking of reinforcement & shuttering for 1st lift for W1 wall PUP Km 203+560 LHS 30-Jun-19 8:00 AM IPC-04 DONE AE
2143 NMSCEW/P-IV/STR/2019/2088 2088 Checking and pouring concrete for 1st lift for W1 wall PUP Km 203+560 LHS 30-Jun-19 9:05 AM IPC-04 DONE AE
2144 NMSCEW/P-IV/STR/2019/2089A 2089A Checking of reinforcement & shuttering for 1st lift for W1 wall PUP Km 193+800 LHS 30-Jun-19 2:00 PM IPC-08 DONE
2145 NMSCEW/P-IV/STR/2019/2089 2089 Checking of reinforcement & shuttering for 1st lift for W1 wall PUP Km 193+800 RHS 30-Jun-19 2:00 PM IPC-04 DONE AE
2146 NMSCEW/P-IV/STR/2019/2090A 2090A Checking and pouring concrete for 1st lift for W1 wall PUP Km 193+800 LHS 30-Jun-19 3:00 PM IPC-08 DONE
2147 NMSCEW/P-IV/STR/2019/2090 2090 Checking and pouring concrete for 1st lift for W1 wall PUP Km 193+800 RHS 30-Jun-19 3:00 PM IPC-04 DONE AE
2148 NMSCEW/P-IV/STR/2019/2091 2091 Layout & level checking for box culvert. Box culvert Km 216+950 BHS 30-Jun-19 9:00 AM WRONG RFI
2149 NMSCEW/P-IV/STR/2019/2092 2092 Structural Excavation for box culvert Box culvert Km 216+950 BHS 30-Jun-19 9:30 AM WRONG RFI
2150 NMSCEW/P-IV/STR/2019/2093 2093 Checking of PCC of box culvert Box culvert Km 216+950 BHS 30-Jun-19 10:20 AM WRONG RFI
2151 NMSCEW/P-IV/STR/2019/2094 2094 Checking of reinforcement & shuttering for 1st lift for W2 wall PUP Km 199+060 LHS 30-Jun-19 3:10 PM IPC-04 DONE
2152 NMSCEW/P-IV/STR/2019/2095 2095 Checking and pouring concrete for 1st lift for W2 wall PUP Km 199+060 LHS 30-Jun-19 4:00 PM IPC-04 DONE
2153 NMSCEW/P-IV/STR/2019/2096 2096 Checking Layout & level MNB Km 199+360 BHS 30-Jun-19 9:15 AM IPC-08 DONE
2154 NMSCEW/P-IV/STR/2019/2097 2097 Checking top level & pouring of concrete for PCC MNB Km 199+360 BHS 30-Jun-19 10:40 AM IPC-08 DONE
2155 NMSCEW/P-IV/STR/2019/2098 2098 Checking of reinforcement and shuttering for raft at RP7 Viaduct Km 196+560 RHS 30-Jun-19 10:11 AM IPC-04 DONE
2156 NMSCEW/P-IV/STR/2019/2099 2099 Checking Layout of raft RP7 Viaduct Km 196+560 RHS 30-Jun-19 11:23 AM
2157 NMSCEW/P-IV/STR/2019/2100 2100 Checking and Pouring of concrete(M-35) for raft at RP7 Viaduct Km 196+560 RHS 30-Jun-19 11:46 AM IPC-04 DONE
2158 NMSCEW/P-IV/STR/2019/2101 2101 Checking top level & pouring of concrete(M-10) for PCC at B/C Box culvert Km 180+427 BHS 30-Jun-19 9:31 AM IPC-08 DONE
2159 NMSCEW/P-IV/STR/2019/2102 2102 Checking of reinforcement & shuttering for 2nd lift at A1 & A2 wall PUP Km 177+810 RHS 30-Jun-19 11:20 AM NR
2160 NMSCEW/P-IV/STR/2019/2103 2103 Checking and pouring concrete(M-30) for 2nd lift at A1 & A2 wall PUP Km 177+810 RHS 30-Jun-19 11:59 AM NR
2161 NMSCEW/P-IV/STR/2019/2104 2104 Conc pouring in raft in RP4 Viaduct Km 195+990 RHS 30-Jun-19 9:15 AM IPC-04 DONE
2162 NMSCEW/P-IV/STR/2019/2105 2105 Conc pouring in raft in LP2 Viaduct Km 202+190 LHS 30-Jun-19 10:00 AM IPC-04 DONE
2163 NMSCEW/P-IV/STR/2019/2106 2106 Conc pouring in raft in LP3 Viaduct Km 202+190 LHS 30-Jun-19 12:30 PM IPC-04 DONE
2164 NMSCEW/P-IV/STR/2019/2107 2107 Checking of reinforcement & shuttering for 1st lift at A1 & A2 wall VUP Km 176+614 Km 00+000 RHS 30-Jun-19 5:26 PM IPC-10 DONE
2165 NMSCEW/P-IV/STR/2019/2108 2108 Checking and pouring concrete(M-30) for 1st lift at A1 & A2 wall VUP Km 176+614 Km 00+000 RHS 30-Jun-19 6:05 PM IPC-10 DONE
2166 NMSCEW/P-IV/STR/2019/2109 2109 Checking reinforcement ,shuttering for top haunch with top slab PUP Km 185+235 LHS 30-Jun-19 4:06 PM IPC-04 DONE
2167 NMSCEW/P-IV/STR/2019/2110 2110 Checking and concrete (M30) pouring for top haunch with top slab PUP Km 185+235 LHS 30-Jun-19 3:06 PM IPC-04 DONE
2168 NMSCEW/P-IV/STR/2019/2111 2111 Checking reinforcement ,shuttering for final lift, top haunch with top slab CUP Km 183+290 LHS 30-Jun-19 6:01 PM IPC-04 DONE
2169 NMSCEW/P-IV/STR/2019/2112 2112 Checking and concrete (M30) pouring for final lift, top haunch with top slab CUP Km 183+290 LHS 30-Jun-19 7:00 PM IPC-04 DONE
2170 NMSCEW/P-IV/STR/2019/2113 2113 Checking reinforcement ,shuttering for top slab PUP Km 186+000 RHS 30-Jun-19 4:09 PM IPC-04 DONE
2171 NMSCEW/P-IV/STR/2019/2114 2114 Checking and concrete (M30) pouring for top slab PUP Km 186+000 RHS 30-Jun-19 4:47 PM IPC-04 DONE
2172 NMSCEW/P-IV/STR/2019/2115 2115 Checking reinforcement ,shuttering for final lift, top haunch & top slab PUP Km 188+575 RHS 30-Jun-19 5:03 PM IPC-04 DONE
2173 NMSCEW/P-IV/STR/2019/2116 2116 Checking of
Checking andreinforcement
concrete (M30) pouring
for precast Boxfor final lift,
Culvert (2x2)top(cushion
haunch 2&totop slab
4m) at precast yard PUP Km 188+575 RHS 30-Jun-19 5:55 PM IPC-04 DONE
2174 NMSCEW/P-IV/STR/2019/2117 2117 camp -2. Segment NO-99,100 Box Culvert Km 200+200 LHS 1-Jul-19 10:00 AM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2175 NMSCEW/P-IV/STR/2019/2118 2118 Box Culvert Km 200+200 LHS 1-Jul-19 10:30 AM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-2,Segment no-99,100
2176 NMSCEW/P-IV/STR/2019/2119 2119 Checking of reinforcement & shuttering for 2nd lift for W2 wall PUP Km 191+740 RHS 1-Jul-19 11:00 AM IPC-05 DONE
2177 NMSCEW/P-IV/STR/2019/2120 2120 Checking and pouring concrete for 2nd lift for W2 wall PUP Km 191+740 RHS 1-Jul-19 11:30 AM IPC-05 DONE
2178 NMSCEW/P-IV/STR/2019/2121 2121 Checking for level & Layout for PCC at RA1 Viaduct Km 195+900 RHS 1-Jul-19 2:00 PM
2179 NMSCEW/P-IV/STR/2019/2122 2122 Checking top level & pouring of concrete for PCC at RA1 Viaduct Km 195+900 RHS 1-Jul-19 2:30 PM
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2180 NMSCEW/P-IV/STR/2019/2123 2123 Box culvert Km 175+500 LHS 1-Jul-19 10:19 AM NR
(3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-62,63
2181 NMSCEW/P-IV/STR/2019/2124 2124 Checking reinforcement for precast Box Culvert (2x2) (Cushion 2 to 4m) at precast yard cam Box culvert Km 176+250 BHS 1-Jul-19 12:23 PM IPC-05 DONE AE
2182 NMSCEW/P-IV/STR/2019/2125 2125 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2×2 Box culvert Km 176+250 BHS 1-Jul-19 4:21 PM IPC-05 DONE
2183 NMSCEW/P-IV/STR/2019/2126 2126 Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp Box culvert Km 179+390 BHS 1-Jul-19 12:55 PM IPC-05 DONE AE
2184 NMSCEW/P-IV/STR/2019/2127 2127 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2×2 Box culvert Km 179+390 BHS 1-Jul-19 5:26 PM IPC-05 DONE
2185 NMSCEW/P-IV/STR/2019/2128 2128 Checking reinforcement ,shuttering for 1st Lift at Wall A1 of CUP PUP Km 187+835 LHS 1-Jul-19 10:33 AM IPC-05 DONE
2186 NMSCEW/P-IV/STR/2019/2129 2129 Checking and concrete (M30) pouring for 1st Lift at Wall A1 & A2 of CUP PUP Km 187+835 LHS 1-Jul-19 2:05 PM IPC-05 DONE
2187 NMSCEW/P-IV/STR/2019/2130 2130 Checking layout ,level and structural excavation at Utility duct Utility duct Km 192+130 BHS 1-Jul-19 12:01 PM
2188 NMSCEW/P-IV/STR/2019/2131 2131 Checking top Level & Laying concrete(M-10) PCC at Utility duct Utility duct Km 192+130 BHS 1-Jul-19 1:00 PM
2189 NMSCEW/P-IV/STR/2019/2132 2132 Checking of reinforcement and shuttering for raft at RP3 Viaduct Km 200+920 RHS 1-Jul-19 2:00 PM IPC-08 DONE AE
2190 NMSCEW/P-IV/STR/2019/2133 2133 Checking Layout of raft RP3 Viaduct Km 200+920 RHS 1-Jul-19 2:15 PM IPC-08 DONE
2191 NMSCEW/P-IV/STR/2019/2134 2134 Checking and Pouring of concrete for raft at RP3 Viaduct Km 200+920 RHS 1-Jul-19 3:00 PM IPC-08 DONE AE
2192 NMSCEW/P-IV/STR/2019/2135 2135 Checking of reinforcement and shuttering for pier shaft starter at LP3,LP4,LP5 Viaduct Km 202+190 LHS 1-Jul-19 4:00 PM IPC-08 DONE
2193 NMSCEW/P-IV/STR/2019/2136 2136 Checking Layout for pier shaft starter at LP3,LP4,LP5 Viaduct Km 202+190 LHS 1-Jul-19 4:15 PM SPOT RFI
2194 NMSCEW/P-IV/STR/2019/2137 2137 Checking and Pouring of concrete(M-45) for pier shaft starter at LP3,LP4,LP5 Viaduct Km 202+190 LHS 1-Jul-19 5:02 PM IPC-08 DONE
2195 NMSCEW/P-IV/STR/2019/2138 2138 Checking of reinforcement & shuttering for 2nd lift at A1 & A2 wall PUP Km 165+300 RHS 2-Jul-19 10:00 AM IPC-05 DONE AE
2196 NMSCEW/P-IV/STR/2019/2139 2139 Checking and pouring concrete(M-30) for 2nd lift at A1 & A2 wall PUP Km 165+300 RHS 2-Jul-19 10:10 AM IPC-05 DONE AE
checking of reinforcement for precast Box Culvert (3x3) unit type 1 (cushion 0-2m) at precast
2197 NMSCEW/P-IV/STR/2019/2140 2140 Box Culvert Km 200+200 LHS 2-Jul-19 11:00 AM DONE
yard campfor
Checking 2, Segment
shutteringNO-56,57
& pouring of Concreting Grade =(M-30) for Precast Box Culvert
2198 NMSCEW/P-IV/STR/2019/2141 2141 Box Culvert Km 200+200 LHS 2-Jul-19 11:10 AM DONE
(3×3) (Cushion
checking 0 to 2 m) at for
of reinforcement precast yard,
precast BoxCamp-1,
CulvertSegment No. -56,57
(2x2) (cushion 2-4m) at precast yard
2199 NMSCEW/P-IV/STR/2019/2142 2142 Box Culvert Km 200+200 LHS 2-Jul-19 11:20 AM DONE
camp 2, Segment
Checking NO-101,102,103,104,105
for shuttering & pouring of Concreting Grade =(M-30) for Precast Box Culvert
2200 NMSCEW/P-IV/STR/2019/2143 2143 Box Culvert Km 200+200 LHS 2-Jul-19 11:30 AM DONE
(2×2) (Cushion
checking 2 to 4 m) at for
of reinforcement precast yard,
precast BoxCamp-2,
CulvertSegment No. -101,102,103,104,105
(3x3) (cushion 2-4m) at precast yard
2201 NMSCEW/P-IV/STR/2019/2144 2144 Box Culvert Km 200+200 LHS 2-Jul-19 11:40 AM DONE
camp 2, Segment
Checking NO-15& pouring of Concreting Grade =(M-30) for Precast Box Culvert
for shuttering
2202 NMSCEW/P-IV/STR/2019/2145 2145 Box Culvert Km 200+200 LHS 2-Jul-19 11:50 AM DONE
(3×3) (Cushion 2 to 4 m) at precast yard, Camp-2, Segment No. -15
2203 NMSCEW/P-IV/STR/2019/2146 2146 Checking of reinforcement and shuttering and top level of raft at LP-2 VIADUCT Km 202+190 LHS 2-Jul-19 3:00 PM IPC-04 DONE
2204 NMSCEW/P-IV/STR/2019/2147 2147 Checking top level & Laying concrete (M-35) for raft at LP-2 VIADUCT Km 202+190 LHS 2-Jul-19 4:00 PM IPC-04 DONE
2205 NMSCEW/P-IV/STR/2019/2148 2148 Checking of reinforcement & shuttering for wall W1 2nd lift PUP Km 203+560 RHS 2-Jul-19 9:00 AM IPC-05 DONE
2206 NMSCEW/P-IV/STR/2019/2149 2149 Checking and pouring concrete for wall W1 2nd lift PUP Km 203+560 RHS 2-Jul-19 9:15 AM IPC-05 DONE
checking of reinforcement for precast Box Culvert (2x2) (cushion 0-2m) at precast yard
2207 NMSCEW/P-IV/STR/2019/2150 2150 Box Culvert Km 175+200 LHS 2-Jul-19 9:00 AM IPC-08 DONE AE 72
camp 1, Segment
checking NO-72 for precast Box Culvert (2x2) (cushion 2-4m) at precast yard
of reinforcement
2208 NMSCEW/P-IV/STR/2019/2151 2151 Box Culvert Km 175+200 LHS 2-Jul-19 9:10 AM IPC-08 DONE AE 57, 58
camp 1, Segment
Checking NO-57,58
for shuttering & pouring of Concreting Grade =(M-30) for Precast Box Culvert
2209 NMSCEW/P-IV/STR/2019/2152 2152 Box Culvert Km 175+200 LHS 2-Jul-19 9:20 AM IPC-08 DONE AE 67, 68, 72
(2×2) (Cushion
Checking 0 to 2 m)&atpouring
for shuttering precast of
yard, Camp-1,Grade
Concreting Segment No. -67,68,72
=(M-30) for Precast Box Culvert
2210 NMSCEW/P-IV/STR/2019/2153 2153 Box Culvert Km 175+200 LHS 2-Jul-19 9:30 AM IPC-08 DONE AE 56, 57, 58
(2×2) (Cushion
Checking 2 to 4 m)&atpouring
for shuttering precast of
yard, Camp-1,Grade
Concreting Segment No. -56,57,58
=(M-30) for Precast Box Culvert
2211 NMSCEW/P-IV/STR/2019/2154 2154 Box Culvert Km 175+200 LHS 2-Jul-19 9:40 AM NR
(3×3) (Cushion 2 to 4 m) at precast yard, Camp-1, Segment No. -62
2212 NMSCEW/P-IV/STR/2019/2155 2155 checking for Layout , level & Structural excavation of Utility Duct. Utility Duct Km 190+200 Km 00+000 BHS 3-Jul-19 9:00 AM IPC-10 DONE
2213 NMSCEW/P-IV/STR/2019/2156 2156 Laying of PCC with top level checking Utility Duct Km 190+200 Km 00+000 BHS 3-Jul-19 10:00 AM IPC-10 DONE
2214 NMSCEW/P-IV/STR/2019/2157 2157 checking for Layout and level for RP-5 FOR VIADUCT Viaduct Km 200+920 RHS 3-Jul-19 10:00 AM
2215 NMSCEW/P-IV/STR/2019/2158 2158 Checking for Laying of PCC ar RP-5 of viaduct Viaduct Km 200+920 RHS 3-Jul-19 11:00 AM
2216 NMSCEW/P-IV/STR/2019/2159 2159 Checking for concreting(M15) around of RP7 foundation annular filling Viaduct Km 200+920 RHS 3-Jul-19 12:00 PM
Checking reinforcement for precast Box Culvert (2x2) (cushion 2m to 4m) at precast yard
2217 NMSCEW/P-IV/STR/2019/2160 2160 Checking for shuttering & Pouring of Concreting Grade (M-30) for Precast Box Culvert Box culvert Km 200+200 LHS 3-Jul-19 9:00 AM DONE
camp -2 Segment NO-106,107,108,109,110
2218 NMSCEW/P-IV/STR/2019/2161 2161 (2×2) , (cushion 2m to 4m) for Ch 168+020 at precast yard camp -2. Segment NO- Box culvert Km 200+200 LHS 3-Jul-19 9:15 AM DONE
Checking reinforcement for precast Box Culvert (3x3) (cushion 0m to 2m) at precast yard
106,107,108,109,110
2219 NMSCEW/P-IV/STR/2019/2162 2162 Box culvert Km 200+200 LHS 3-Jul-19 9:30 AM DONE
camp -2 Segment
Checking NO-58,59,60,61
for shuttering & Pouring of Concreting Grade (M-30) for Precast Box Culvert
2220 NMSCEW/P-IV/STR/2019/2163 2163 Box culvert Km 200+200 LHS 3-Jul-19 9:45 AM DONE
(3×3) , (cushion 0m to 2m) precast yard camp -2. Segment NO-58,59,60,61
2221 NMSCEW/P-IV/STR/2019/2164 2164 checking for Layout , level & Structural excavation of Box Culvert (2x2) Utility Duct Km 206+700 Km 00+000 BHS 3-Jul-19 9:00 AM IPC-11 Approved
2222 NMSCEW/P-IV/STR/2019/2165 2165 Laying of PCC with top level checking Utility Duct Km 206+700 Km 00+000 BHS 3-Jul-19 10:00 AM IPC-11 Approved
Checking reinforcement for precast Box Culvert (2x2) (cushion 0m to 2m) at precast yard
2223 NMSCEW/P-IV/STR/2019/2166 2166 Box culvert Km 175+500 LHS 3-Jul-19 9:15 AM IPC-08 DONE AE 73, 74, 75
camp -1 Segment NO-73,74,75
2224 NMSCEW/P-IV/STR/2019/2167 2167 Checking reinforcement for precast Box Culvert (2x2) (cushion 2m to 4m) at precast yard Box culvert Km 176+250 BHS 3-Jul-19 9:30 AM IPC-05 DONE AE
Checking reinforcement for precast Box Culvert (3x3) (cushion 2m to 4m) at precast yard
2225 NMSCEW/P-IV/STR/2019/2168 2168 Box culvert Km 175+500 LHS 3-Jul-19 9:40 AM IPC-08 DONE AE 63, 64
camp -1 Segment
Checking NO-63,64
for shuttering & Pouring of Concreting Grade (M-30) for Precast Box Culvert
2226 NMSCEW/P-IV/STR/2019/2169 2169 Box culvert Km 175+500 LHS 3-Jul-19 10:00 AM IPC-08 DONE AE 73, 74, 75
(2×2) , (cushion
Checking 0m to 2m)
for shuttering precast yard
& Pouring camp -1. Segment
of Concreting Grade (M-30) NO-73,74,75
for Precast Box Culvert
2227 NMSCEW/P-IV/STR/2019/2170 2170 Box culvert Km 175+500 LHS 3-Jul-19 10:15 AM DONE
(2×2) , (cushion
Checking 2m to 4m)
for shuttering precast yard
& Pouring camp -1. Segment
of Concreting Grade (M-30) NO-59,60,61
for Precast Box Culvert
2228 NMSCEW/P-IV/STR/2019/2171 2171 Box culvert Km 175+500 LHS 3-Jul-19 10:20 AM IPC-08 DONE AE 62, 63
(3×3) , (cushion 2m to 4m) precast yard camp -1. Segment NO-62,63,64
2229 NMSCEW/P-IV/STR/2019/2172 2172 checking for Layout and level for LP-8 FOR VIADUCT Viaduct Km 202+190 LHS 3-Jul-19 2:00 PM
2230 NMSCEW/P-IV/STR/2019/2173 2173 Checking for Laying of PCC ar LP-8 of viaduct Viaduct Km 202+190 LHS 3-Jul-19 3:00 PM
2231 NMSCEW/P-IV/STR/2019/2174 2174 Checking for concreting(M15) around of RP6 foundation annular filling Viaduct Km 195+900 RHS 3-Jul-19 12:00 PM
2232 NMSCEW/P-IV/STR/2019/2175 2175 Checking for concreting(M15) around of RP8 foundation annular filling Viaduct Km 195+900 RHS 3-Jul-19 12:15 PM
2233 NMSCEW/P-IV/STR/2019/2176 2176 Checking for concreting(M15) around of RP7 foundation annular filling Viaduct Km 202+190 RHS 3-Jul-19 12:00 PM
2234 NMSCEW/P-IV/STR/2019/2177 2177 Checking for concreting(M15) around of LP1 foundation annular filling Viaduct Km 202+190 LHS 3-Jul-19 12:15 PM
2235 NMSCEW/P-IV/STR/2019/2178 2178 Checking for concreting(M15) around of RP1 foundation annular filling Viaduct Km 202+190 RHS 3-Jul-19 12:00 PM
2236 NMSCEW/P-IV/STR/2019/2179 2179 checking for Layout , level & Structural excavation of Utility Duct. Utility Duct Km 188+390 BHS 4-Jul-19 12:00 PM DONE
2237 NMSCEW/P-IV/STR/2019/2180 2180 Laying of PCC with top level checking (M-10) Utility Duct Km 188+390 BHS 4-Jul-19 1:00 PM DONE
2238 NMSCEW/P-IV/STR/2019/2181 2181 Checking of reinforcement & shuttering for PUP first lift at A1 & A2 wall PUP Km 190+650 LHS 4-Jul-19 11:20 AM IPC-05 DONE
2239 NMSCEW/P-IV/STR/2019/2182 2182 Checking and pouring concrete(M-30) for PUP first lift at A1 & A2 wall PUP Km 190+650 LHS 4-Jul-19 11:30 AM IPC-05 DONE
2240 NMSCEW/P-IV/STR/2019/2183 2183 Checking reinforcement & shuttering for top haunch A1 &A2 and top slab PUP Km 174+095 LHS 4-Jul-19 5:30 PM NR
2241 NMSCEW/P-IV/STR/2019/2184 2184 Checking and concrete (M30) pouring for top haunch A1 &A2 and top slab PUP Km 174+095 LHS 4-Jul-19 5:40 PM NR
2242 NMSCEW/P-IV/STR/2019/2185 2185 checking for Layout and level of PCC at LP8 Viaduct Km 202+190 BHS 4-Jul-19 2:00 PM
2243 NMSCEW/P-IV/STR/2019/2186 2186 Laying of PCC with top level checking (M-10) Viaduct Km 202+190 BHS 4-Jul-19 3:00 PM
Checking reinforcement for precast Box Culvert (2x2) (cushion 0 to 2m) at precast yard camp
2244 NMSCEW/P-IV/STR/2019/2187 2187 Box culvert Km 175+500 LHS 4-Jul-19 9:00 AM IPC-08 DONE 76, 77, 78
-1 Segment NO-76,77,78
2245 NMSCEW/P-IV/STR/2019/2188 2188 Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard cam Box culvert Km 176+250 BHS 4-Jul-19 9:10 AM IPC-05 DONE
Checking reinforcement for precast Box Culvert (3x3) (cushion 2 to 4m) at precast yard camp
2246 NMSCEW/P-IV/STR/2019/2189 2189 Box culvert Km 175+500 LHS 4-Jul-19 9:20 AM IPC-08 DONE 65, 66, 67
-1 Segment
Checking forNO-65,66,67
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2247 NMSCEW/P-IV/STR/2019/2190 2190 Box culvert Km 175+500 LHS 4-Jul-19 9:30 AM IPC-08 DONE AE 76, 77
(2×2),(Cushion 0 to 2m) at precast yard camp-1,Segment no.-76,77,78
2248 NMSCEW/P-IV/STR/2019/2191 2191 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2×2 Box culvert Km 176+250 BHS 4-Jul-19 9:40 AM IPC-05 DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2249 NMSCEW/P-IV/STR/2019/2192 2192 Box culvert Km 175+500 LHS 4-Jul-19 9:50 AM IPC-08 DONE 65, 66
(3×3),(Cushion 2 to 4m) at precast yard camp-1,Segment no.-65,66,67
2250 NMSCEW/P-IV/STR/2019/2193 2193 Checking of reinforcement & shuttering for bottom raft of PUP PUP Km 190+650 RHS 4-Jul-19 11:00 AM IPC-05 DONE AE
2251 NMSCEW/P-IV/STR/2019/2194 2194 Checking and pouring concrete(M-30) for bottom raft of PUP PUP Km 190+650 RHS 4-Jul-19 11:30 AM IPC-05 DONE AE
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
2252 NMSCEW/P-IV/STR/2019/2195 2195 Box culvert Km 200+200 LHS 4-Jul-19 9:00 AM DONE
-2 Segment
Checking forNO-111,112,113,114,115,116,117
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2253 NMSCEW/P-IV/STR/2019/2196 2196 Box culvert Km 200+200 LHS 4-Jul-19 9:40 AM DONE
(2×2),(Cushion
Checking 2 to 4m) for
reinforcement at precast
precastyard
Boxcamp-2,Segment no.-111,112,113,114,115,116,117
Culvert (3x3) (cushion 0 to 2m) at precast yard camp
2254 NMSCEW/P-IV/STR/2019/2197 2197 Box culvert Km 200+200 LHS 4-Jul-19 9:45 AM DONE
-2 Segment NO-62,63
2255 NMSCEW/P-IV/STR/2019/2198 2198 Checking of reinforcement & shuttering of 2nd lift of PUP at wall A1 &A2 PUP Km 183+290 LHS 4-Jul-19 10:00 AM DONE
2256 NMSCEW/P-IV/STR/2019/2199 2199 Checking and pouring concrete(M-30) of 2nd lift of PUP at wall A1 &A2 PUP Km 183+290 LHS 4-Jul-19 10:15 AM NR
2257 NMSCEW/P-IV/STR/2019/2200 2200 Checking of reinforcement,shuttering & layout for pier shaft starter at LP7 Viaduct Km 195+900 Km 00+000 LHS 4-Jul-19 10:00 AM IPC-11 Approved
2258 NMSCEW/P-IV/STR/2019/2201 2201 Checking and Pouring concrete for pier shaft starter at LP7 Viaduct Km 195+900 Km 00+000 LHS 4-Jul-19 10:30 AM IPC-11 Approved
2259 NMSCEW/P-IV/STR/2019/2202 2202 Checking for Layout & level of box culvert Box Culvert Km 200+460 LHS 4-Jul-19 2:00 PM SPOT RFI
2260 NMSCEW/P-IV/STR/2019/2203 2203 Checking of raft reinforcement and shuttering of Box Culvert Box Culvert Km 200+460 LHS 4-Jul-19 2:20 PM SPOT RFI
2261 NMSCEW/P-IV/STR/2019/2204 2204 Checking fo raft concrete pouring of Box Culvert Box Culvert Km 200+460 LHS 4-Jul-19 3:00 PM SPOT RFI
2262 NMSCEW/P-IV/STR/2019/2205 2205 Checking for layout of PCC at LP-8 Viaduct Km 195+900 LHS 4-Jul-19 10:00 AM SPOT RFI
2263 NMSCEW/P-IV/STR/2019/2206 2206 Checking top level & pouring of concrete for PCC at LP8 Viaduct Km 195+900 LHS 4-Jul-19 10:30 AM SPOT RFI
2264 NMSCEW/P-IV/STR/2019/2207 2207 Checking for layout of PCC at RP-5 Viaduct Km 200+920 RHS 4-Jul-19 10:15 AM SPOT RFI
2265 NMSCEW/P-IV/STR/2019/2208 2208 Checking top level & pouring of concrete for PCC at RP5 Viaduct Km 200+920 RHS 4-Jul-19 10:45 AM SPOT RFI
2266 NMSCEW/P-IV/STR/2019/2209 2209 Checking layout ,level and structural excavation of utility duct Utility duct Km 180+300 BHS 5-Jul-19 9:00 AM NR
2267 NMSCEW/P-IV/STR/2019/2210 2210 Checking top Level & Laying concrete(M-10) PCC Utility duct Km 180+300 BHS 5-Jul-19 11:30 AM NR
2268 NMSCEW/P-IV/STR/2019/2211 2211 Checking reinforcement ,shuttering for 1st lift at wall A1 & A2 PUP Km 165+300 LHS 5-Jul-19 11:00 AM IPC-05 DONE AE
2269 NMSCEW/P-IV/STR/2019/2212 2212 Checking and concrete pouring for 1st lift at wall A1 & A2 PUP Km 165+300 LHS 5-Jul-19 11:20 AM IPC-05 DONE AE
2270 NMSCEW/P-IV/STR/2019/2213 2213 Checking of reinforcement and shuttering for raft at RP-04 Viaduct Km 195+900 RHS 5-Jul-19 10:00 AM IPC-04 DONE
2271 NMSCEW/P-IV/STR/2019/2214 2214 Checking for level & layout of raft shuttering at RP-04 Viaduct Km 195+900 RHS 5-Jul-19 10:30 AM IPC-04 DONE
2272 NMSCEW/P-IV/STR/2019/2215 2215 Checking and Pouring of concrete for raft at RP-04 Viaduct Km 195+900 RHS 5-Jul-19 10:40 AM
2273 NMSCEW/P-IV/STR/2019/2216 2216 Checking of reinforcement, shuttering & layout for pier shaft starter at Lp-4 Viaduct Km 202+190 LHS 5-Jul-19 11:00 AM
2274 NMSCEW/P-IV/STR/2019/2217 2217 Checking and Pouring concrete for pier shaft starter at LP-4 Viaduct Km 202+190 LHS 5-Jul-19 12:00 PM
2275 NMSCEW/P-IV/STR/2019/2218 2218 Checking for concreting(M15) around of RP-4 & RP-5 foundation annular filling Viaduct Km 202+190 RHS 5-Jul-19 2:30 PM
2276 NMSCEW/P-IV/STR/2019/2219 2219 Checking for layout & level for PCC at LP8 Viaduct Km 202+190 LHS 5-Jul-19 2:00 PM
2277 NMSCEW/P-IV/STR/2019/2220 2220 Checking top Level & Laying concrete PCC at LP8 Viaduct Km 202+190 LHS 5-Jul-19 3:00 PM
2278 NMSCEW/P-IV/STR/2019/2221 2221 Checking for Exacavtion of Median Drain Outlet Median drain Km 203+540 5-Jul-19 9:00 AM DONE
2279 NMSCEW/P-IV/STR/2019/2222 2222 Checking for level of PCC at Median Drain Outlet Median drain Km 203+540 5-Jul-19 9:30 AM DONE
2280 NMSCEW/P-IV/STR/2019/2223 2223 Checking for Exacavtion of Median Drain Outlet Median drain Km 203+650 5-Jul-19 9:00 AM DONE
2281 NMSCEW/P-IV/STR/2019/2224 2224 Checking for level of PCC at Medium Drain Outlet Median drain Km 203+650 5-Jul-19 9:30 AM DONE
2282 NMSCEW/P-IV/STR/2019/2225 2225 Checking for layout and level for PUP PUP Km 212+080 LHS 5-Jul-19 2:30 PM NR
2283 NMSCEW/P-IV/STR/2019/2226 2226 Checking for raft reinforcement & shuttering for PUP PUP Km 212+080 LHS 5-Jul-19 3:00 PM NR
2284 NMSCEW/P-IV/STR/2019/2227 2227 Checking and concrete pouring for PUP PUP Km 212+080 LHS 5-Jul-19 3:30 PM NR
2285 NMSCEW/P-IV/STR/2019/2228 2228 Checking for layout and level for Box culvert Box culvert Km 200+460 LHS 5-Jul-19 12:30 PM NR
2286 NMSCEW/P-IV/STR/2019/2229 2229 Checking for raft reinforcement & shuttering for box culvert Box culvert Km 200+460 LHS 5-Jul-19 1:00 PM NR
2287 NMSCEW/P-IV/STR/2019/2230 2230 Checking and concrete pouring for box culvert Box culvert Km 212+080 LHS 5-Jul-19 2:00 PM WRONG RFI
2288 NMSCEW/P-IV/STR/2019/2231 2231 Checking for layout and level for PUP PUP Km 199+060 RHS 5-Jul-19 10:30 AM IPC-05 DONE AE
2289 NMSCEW/P-IV/STR/2019/2232 2232 Checking for raft reinforcement & shuttering for PUP PUP Km 199+060 RHS 5-Jul-19 11:00 AM IPC-05 DONE AE
2290 NMSCEW/P-IV/STR/2019/2233 2233 Checking and concrete pouring for PUP
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp PUP Km 199+060 RHS 5-Jul-19 12:00 PM IPC-05 DONE AE
2291 NMSCEW/P-IV/STR/2019/2234 2234 -2. Segment NO-118,119,120,121,122. Box culvert Km 200+200 LHS 5-Jul-19 8:30 AM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2292 NMSCEW/P-IV/STR/2019/2235 2235 Checking reinforcement Box culvert Km 200+200 LHS 5-Jul-19 9:00 AM DONE
(2×2) (Cushion 2 to 4m) for precastyard
at precast Boxcamp-2
Culvert,Segment
(3x3) (cushion 2 to 4m) at precast yard camp
no.-118,119,120,121,122
2293 NMSCEW/P-IV/STR/2019/2236 2236 -2. Segment NO-16 Box culvert Km 200+200 LHS 5-Jul-19 9:30 AM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2294 NMSCEW/P-IV/STR/2019/2237 2237 Checking reinforcement Box culvert Km 200+200 LHS 5-Jul-19 10:00 AM DONE
(3×3) (Cushion 2 to 4m) for precastyard
at precast Boxcamp-2
Culvert,Segment
(3x3) (cushion
no.-160 to 2m) at precast yard camp
2295 NMSCEW/P-IV/STR/2019/2238 2238 -2. Segment NO-64 Box culvert Km 200+200 LHS 5-Jul-19 10:30 AM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2296 NMSCEW/P-IV/STR/2019/2239 2239 Box culvert Km 200+200 LHS 5-Jul-19 11:00 AM DONE
(3×3) (Cushion 0 to 2m) at precast yard camp-2 ,Segment no.-64
2297 NMSCEW/P-IV/STR/2019/2240 2240 Checking reinforcement ,shuttering for 4th lift at wall A1 & A2 of VUP PUP Km 176+614 LHS 5-Jul-19 5:30 PM NR
2298 NMSCEW/P-IV/STR/2019/2241 2241 Checking and concrete pouring (M-35) for 4th lift at wall A1 & A2 of VUP PUP Km 176+614 LHS 5-Jul-19 5:40 PM NR
Checking reinforcement for precast Box Culvert (2x2) (cushion 0 to 2m) at precast yard camp
2299 NMSCEW/P-IV/STR/2019/2242 2242 Box culvert Km 175+500 LHS 5-Jul-19 8:30 AM IPC-08 DONE AE 79, 80, 81
-1. Segment
Checking NO-79,80,81
reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
2300 NMSCEW/P-IV/STR/2019/2243 2243 Box culvert Km 175+500 LHS 5-Jul-19 8:30 AM DONE
-1. Segment NO- 65
Checking reinforcement for precast Box Culvert (3x3) (cushion 2 to 4m) at precast yard camp
2301 NMSCEW/P-IV/STR/2019/2244 2244 Box culvert Km 175+500 LHS 5-Jul-19 8:40 AM DONE
-1. Segment
Checking for NO- 79,80 & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
shuttering
2302 NMSCEW/P-IV/STR/2019/2245 2245 Box culvert Km 175+500 LHS 5-Jul-19 8:50 AM DONE
(2×2) (Cushion 0 to 2m) at precast yard camp-1 ,Segment no.-79,80,81
2303 NMSCEW/P-IV/STR/2019/2246 2246 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2×2 Box culvert Km 176+250 BHS 5-Jul-19 9:50 AM IPC-05 DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2304 NMSCEW/P-IV/STR/2019/2247 2247 Box culvert Km 175+500 LHS 5-Jul-19 10:50 AM NR
(3×3) (Cushion 2 to 4m) at precast yard camp-1 ,Segment no.-75,79,80
2305 NMSCEW/P-IV/STR/2019/2248 2248 Checking of reinforcement, shuttering & layout for pier shaft starter at Lp-4 Viaduct Km 202+190 LHS 6-Jul-19 11:00 AM
2306 NMSCEW/P-IV/STR/2019/2249 2249 Checking and Pouring concrete for pier shaft starter at LP-4 Viaduct Km 202+190 LHS 6-Jul-19 11:10 AM
2307 NMSCEW/P-IV/STR/2019/2250 2250 Checking of reinforcement, shuttering & layout for pier shaft starter at RP-4 Viaduct Km 202+190 RHS 6-Jul-19 12:00 PM
2308 NMSCEW/P-IV/STR/2019/2251 2251 Checking and Pouring concrete for pier shaft starter at RP-4 Viaduct Km 202+190 RHS 6-Jul-19 12:20 PM
2309 NMSCEW/P-IV/STR/2019/2252 2252 Checking reinforcement ,shuttering for Side wall A1 & A2 2nd lift PUP Km 190+650 LHS 6-Jul-19 10:00 AM IPC-05 DONE
2310 NMSCEW/P-IV/STR/2019/2253 2253 Checking and concrete (M30)
Checking reinforcement pouring
for precast Boxfor Side wall
Culvert (2x2)A1 & A2 2nd
(cushion 0 tolift
2m) at precast yard camp PUP Km 190+650 LHS 6-Jul-19 11:00 AM IPC-05 DONE
2311 NMSCEW/P-IV/STR/2019/2254 2254 -1. Segment NO-82 &83 Box culvert Km 175+500 LHS 6-Jul-19 8:30 AM IPC-08 DONE AE 82, 83
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp -1. Segment NO-66 & 67
2312 NMSCEW/P-IV/STR/2019/2255 2255 Box culvert Km 176+250 BHS 6-Jul-19 8:40 AM IPC-05 DONE
Checking reinforcement for precast Box Culvert (3x3) (cushion 2 to 4m) at precast yard camp
2313 NMSCEW/P-IV/STR/2019/2256 2256 Box culvert Km 175+500 LHS 6-Jul-19 8:50 AM IPC-08 DONE AE 68, 69
-1. Segment
Checking for NO-68 & 69
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2314 NMSCEW/P-IV/STR/2019/2257 2257 Box culvert Km 175+500 LHS 6-Jul-19 9:00 AM IPC-08 DONE AE 78, 82
(2×2) (Cushion 0 to 2m) at precast yard camp-1 ,Segment no.-78,82 & 83
2315 NMSCEW/P-IV/STR/2019/2258 2258 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2×2 Box culvert Km 176+250 BHS 6-Jul-19 9:15 AM IPC-05 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2316 NMSCEW/P-IV/STR/2019/2259 2259 Box culvert Km 175+500 LHS 6-Jul-19 9:30 AM IPC-08 DONE 67, 68, 69
(3×3) (Cushion
Checking 2 to 4m) for
reinforcement at precast
precastyard
Boxcamp-1
Culvert,Segment no.-67,68
(2x2) (cushion 2 to ,4m)
69 at precast yard camp
2317 NMSCEW/P-IV/STR/2019/2260 2260 Box culvert Km 200+200 LHS 6-Jul-19 8:30 AM DONE
-2. Segment NO-123,124,125,126,127
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2318 NMSCEW/P-IV/STR/2019/2261 2261 Box culvert Km 200+200 LHS 6-Jul-19 9:00 AM DONE
(2×2) (Cushion
Checking 2 to 4m) for
reinforcement at precast
precastyard
Boxcamp-2
Culvert,Segment no.-123,124,125,126,127
(3x3) (cushion 0 to 2m) at precast yard camp
2319 NMSCEW/P-IV/STR/2019/2262 2262 Box culvert Km 200+200 LHS 6-Jul-19 9:30 AM DONE
-2. Segment
Checking for NO-65
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2320 NMSCEW/P-IV/STR/2019/2263 2263 Box culvert Km 200+200 LHS 6-Jul-19 10:00 AM DONE
(3×3) (Cushion 0 to 2m) at precast yard camp-2 ,Segment no.-65
2321 NMSCEW/P-IV/STR/2019/2264 2264 Blank RFI Blank RFI
2322 NMSCEW/P-IV/STR/2019/2265 2265 Blank RFI Blank RFI
2323 NMSCEW/P-IV/STR/2019/2266 2266 Checking of reinforcement & shuttering for 2nd lift for A1 & A2 wall PUP Km 187+835 LHS 7-Jul-19 5:30 PM IPC-05 DONE
2324 NMSCEW/P-IV/STR/2019/2267 2267 Checking and pouring concrete(M-30) for 2nd lift for A1 & A2 wall PUP Km 187+835 LHS 7-Jul-19 5:40 PM IPC-05 DONE
2325 NMSCEW/P-IV/STR/2019/2268 2268 Checking of reinforcement, shuttering & layout for pier shaft starter at Lp-4 Viaduct Km 202+190 LHS 7-Jul-19 9:00 AM IPC-08 DONE
2326 NMSCEW/P-IV/STR/2019/2269 2269 Checking and Pouring concrete for pier shaft starter at LP-4 Viaduct Km 202+190 LHS 7-Jul-19 10:00 AM IPC-08 DONE
2327 NMSCEW/P-IV/STR/2019/2270 2270 Checking of reinforcement, shuttering & layout for pier shaft starter at RP-4 Viaduct Km 202+190 RHS 7-Jul-19 9:10 AM
2328 NMSCEW/P-IV/STR/2019/2271 2271 Checking and Pouring concrete for pier shaft starter at RP-4 Viaduct Km 202+190 RHS 7-Jul-19 10:10 AM
2329 NMSCEW/P-IV/STR/2019/2272 2272 Checking annular filling arround foundation of M15 concrete at RP7 VIADUCT Km 202+190 RHS 7-Jul-19 10:20 AM
2330 NMSCEW/P-IV/STR/2019/2273 2273 Checking annular filling arround foundation of M15 concrete at RP4 VIADUCT Km 202+190 RHS 7-Jul-19 10:30 AM
2331 NMSCEW/P-IV/STR/2019/2274 2274 Checking annular filling arround foundation of M15 concrete at RP5 VIADUCT Km 202+190 RHS 7-Jul-19 10:40 AM
2332 NMSCEW/P-IV/STR/2019/2275 2275 Checking annular filling arround foundation of M15 concrete at LP-07 VIADUCT Km 195+900 RHS 7-Jul-19 10:50 AM
2333 NMSCEW/P-IV/STR/2019/2276 2276 Checking annular filling arround foundation of M15 concrete at RP-04 VIADUCT Km 195+900 RHS 7-Jul-19 11:00 AM
2334 NMSCEW/P-IV/STR/2019/2277 2277 Checking for Layout & Level for Box Culvert Box culvert Km 200+460 LHS 7-Jul-19 12:30 PM IPC-05 DONE
2335 NMSCEW/P-IV/STR/2019/2278 2278 Checking of raft reinforcement for Box Culvert Box culvert Km 200+460 LHS 7-Jul-19 1:00 PM IPC-05 DONE
2336 NMSCEW/P-IV/STR/2019/2279 2279 Checking and Pouring concrete for Box Culvert Box culvert Km 200+460 LHS 7-Jul-19 2:00 PM IPC-05 DONE
2337 NMSCEW/P-IV/STR/2019/2280 2280 Checking for reinforcement & shuttering for wall W1 2nd lift of PUP PUP Km 203+560 LHS 7-Jul-19 8:00 AM IPC-05 DONE AE
2338 NMSCEW/P-IV/STR/2019/2281 2281 Checking and concrete pouring for wall W1 2nd lift of PUP PUP Km 203+560 LHS 7-Jul-19 9:00 AM IPC-05 DONE AE
2339 NMSCEW/P-IV/STR/2019/2282 2282 Checking Layout & Level for exacavation of Utility Duct Utility duct Km 190+910 Km 00+000 BHS 8-Jul-19 9:00 AM IPC-09 DONE
2340 NMSCEW/P-IV/STR/2019/2283 2283 Checking top Level & Laying concrete(M-10) PCC Utility duct 190+900 Km 00+000 BHS 8-Jul-19 10:00 AM IPC-09 DONE
Checking for reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard
2341 NMSCEW/P-IV/STR/2019/2284 2284 Box culvert Km 200+200 LHS 8-Jul-19 10:30 AM DONE
camp -2. Segment
Checking NO-128,129,130,131,132.
for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2342 NMSCEW/P-IV/STR/2019/2285 2285 Box culvert Km 200+200 LHS 8-Jul-19 2:30 PM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-2.Segment no-128,129,130,131,132
Checking for reinforcement for precast Box Culvert (3x3) (cushion 0 to 2m) at precast yard
2343 NMSCEW/P-IV/STR/2019/2286 2286 Box culvert Km 200+200 LHS 8-Jul-19 12:30 PM DONE
camp -2. Segment
Checking NO-66,67.
for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2344 NMSCEW/P-IV/STR/2019/2287 2287 Box culvert Km 200+200 LHS 8-Jul-19 4:00 PM DONE
(3×3)(Cushion
Checking 0 to 2m) at precast
for reinforcement yard Box
for precast camp-2. Segment
Culvert (3×3)no-66,67.
(cushion 2 to 4m) at precast yard
2345 NMSCEW/P-IV/STR/2019/2288 2288 Box culvert Km 200+200 LHS 8-Jul-19 11:15 AM DONE
camp -2. Segment NO-17.
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2346 NMSCEW/P-IV/STR/2019/2289 2289 Box culvert Km 200+200 LHS 8-Jul-19 3:15 PM DONE
(3×3) (Cushion 2 to 4m) at precast yard camp-2. Segment no-17.
2347 NMSCEW/P-IV/STR/2019/2290 2290 Checking for reinforcement & shuttering for wall W2 1st lift of box culvert Box culvert Km 200+460 LHS 8-Jul-19 9:48 AM IPC-05 DONE
2348 NMSCEW/P-IV/STR/2019/2291 2291 Checking and concrete pouring for wall W2 1st lift of box culvert Box culvert Km 200+460 LHS 8-Jul-19 3:05 PM IPC-05 DONE
2349 NMSCEW/P-IV/STR/2019/2292 2292 Checking for reinforcement & shuttering for wall W1 1st lift of box culvert Box culvert Km 204+920 RHS 8-Jul-19 2:05 PM IPC-05 DONE
2350 NMSCEW/P-IV/STR/2019/2293 2293 Checking and concrete pouring for wall W1 1st lift of box culvert Box culvert Km 204+920 RHS 8-Jul-19 3:48 PM IPC-05 DONE
2351 NMSCEW/P-IV/STR/2019/2294 2294 Checking of reinforcement & shuttering for Raft at LVUP LVUP Km 178+323 RHS 8-Jul-19 4:55 PM NR
2352 NMSCEW/P-IV/STR/2019/2295 2295 Checking and concrete pouring
Checking reinforcement (M30)
for precast Boxfor Raft at(2x2)
Culvert LVU(cushion 0 to 2m) at precast yard camp LVUP Km 178+323 RHS 8-Jul-19 5:35 PM NR
2353 NMSCEW/P-IV/STR/2019/2296 2296 -1. Segment NO-84 & 85. Box culvert Km 175+500 LHS 8-Jul-19 12:35 PM IPC-08 DONE AE 84, 85
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp -1. Segment NO-49,61,65
2354 NMSCEW/P-IV/STR/2019/2297 2297 Box culvert Km 176+250 BHS 8-Jul-19 2:18 PM IPC-05 DONE
Checking reinforcement for precast Box Culvert (3x3) (cushion 2 to 4m) at precast yard camp
2355 NMSCEW/P-IV/STR/2019/2298 2298 Box culvert Km 175+500 LHS 8-Jul-19 2:46 PM DONE
-1. Segment
Checking for NO-70,71
shuttering && 72.
Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2356 NMSCEW/P-IV/STR/2019/2299 2299 Box culvert Km 175+500 LHS 8-Jul-19 3:52 PM IPC-08 DONE 80, 81
(2×2) (Cushion 0 to 2m) at precast yard camp-1 ,Segment no.-80,81,84 & 85.
2357 NMSCEW/P-IV/STR/2019/2300 2300 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2×2 Box culvert Km 176+250 BHS 8-Jul-19 4:16 PM IPC-05 DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2358 NMSCEW/P-IV/STR/2019/2301 2301 Box culvert Km 175+500 LHS 8-Jul-19 4:36 PM NR
(3×3) (Cushion 2 to 4m) at precast yard camp-1 ,Segment no.-70,71 & 72.
2359 NMSCEW/P-IV/STR/2019/2302 2302 Checking for reinforcement & shuttering for wall 2nd lift A1 & A2 of PUP PUP Km 165+300 LHS 8-Jul-19 11:00 AM IPC-05 DONE AE
2360 NMSCEW/P-IV/STR/2019/2303 2303 Checking and concrete pouring for wall 2nd lift A1 & A2 of PUP PUP Km 165+300 LHS 8-Jul-19 11:40 AM IPC-05 DONE AE
2361 NMSCEW/P-IV/STR/2019/2304 2304 Checking annular filling arround foundation of M15 concrete at RP7 VIADUCT Km 202+190 RHS 8-Jul-19 8:10 AM
2362 NMSCEW/P-IV/STR/2019/2305 2305 Checking annular filling arround foundation of M15 concrete at RP4 VIADUCT Km 202+190 RHS 8-Jul-19 8:30 AM
2363 NMSCEW/P-IV/STR/2019/2306 2306 Checking annular filling arround foundation of M15 concrete at RP5 VIADUCT Km 202+190 RHS 8-Jul-19 8:50 AM
2364 NMSCEW/P-IV/STR/2019/2307 2307 Checking of reinforcement and shuttering for pier shaft 1st & final lift at RP13 Viaduct Km 169+800 Km 00+000 RHS 8-Jul-19 10:09 AM IPC-09 DONE AE
2365 NMSCEW/P-IV/STR/2019/2308 2308 Checking for Pouring of concretefor pier shaft 1st & final lift at RP13 Viaduct Km 169+800 Km 00+000 RHS 8-Jul-19 11:08 AM IPC-09 DONE AE
2366 NMSCEW/P-IV/STR/2019/2309 2309 Checking layout & level for raft PUP Km 212+080 Km 00+000 LHS 8-Jul-19 10:00 AM IPC-10 DONE AE SPOT RFI
2367 NMSCEW/P-IV/STR/2019/2310 2310 Checking of reinforcement & shuttering for Raft PUP Km 212+080 Km 00+000 LHS 8-Jul-19 10:30 AM IPC-10 DONE AE SPOT RFI
2368 NMSCEW/P-IV/STR/2019/2311 2311 Checking and concrete pouring for Raft PUP Km 212+080 Km 00+000 LHS 8-Jul-19 11:10 AM IPC-10 DONE AE SPOT RFI
2369 NMSCEW/P-IV/STR/2019/2312 2312 Checking of reinforcement & shuttering for Raft LVUP Km 178+323 RHS 9-Jul-19 4:30 PM IPC-08 DONE AE
2370 NMSCEW/P-IV/STR/2019/2313 2313 Checking and concrete(M-35) pouring for Raft LVUP Km 178+323 RHS 9-Jul-19 5:00 PM IPC-08 DONE AE
Checking reinforcement for precast Box Culvert (2x2) (cushion 2m to 4m) at precast yard camp -1. Segment NO-69.
2371 NMSCEW/P-IV/STR/2019/2314 2314 Checking reinforcement for precast Box Culvert (2x2) (cushion 0 to 2m) at precast yard camp Box culvert Km 176+250 BHS 9-Jul-19 9:30 AM IPC-05 DONE AE
2372 NMSCEW/P-IV/STR/2019/2315 2315 -1. Segment NO-86,87 Box culvert Km 175+500 LHS 9-Jul-19 2:00 PM IPC-08 DONE AE 86, 87
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2373 NMSCEW/P-IV/STR/2019/2316 2316 Box culvert Km 175+500 LHS 9-Jul-19 4:00 PM IPC-08 DONE AE 70, 71
(3×3) (Cushion 2 to 4m) at precast yard camp-1 ,Segment no.-70,71 & 72.
2374 NMSCEW/P-IV/STR/2019/2317 2317 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2×2 Box culvert Km 176+250 BHS 9-Jul-19 10:00 AM IPC-05 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2375 NMSCEW/P-IV/STR/2019/2318 2318 Box culvert Km 175+500 LHS 9-Jul-19 3:00 PM IPC-08 DONE AE 84, 85
(2×2) (Cushion 0 to 2m) at precast yard camp-1 ,Segment no.-84,85,86,87
2376 NMSCEW/P-IV/STR/2019/2319 2319 Checking for layout & level of excaveted bed for PCC at RP13 Viaduct Km 202+190 Km 00+000 RHS 9-Jul-19 2:00 PM IPC-10 DONE AE
2377 NMSCEW/P-IV/STR/2019/2320 2320 Checking top Level & Laying concrete PCC at RP13 Viaduct Km 202+190 Km 00+000 RHS 9-Jul-19 3:05 PM IPC-10 DONE AE
2378 NMSCEW/P-IV/STR/2019/2321 2321 Checking of reinforcement, shuttering for pier shaft 1st lift at LP3 Viaduct Km 202+190 LHS 9-Jul-19 3:30 PM
2379 NMSCEW/P-IV/STR/2019/2322 2322 Checking and Pouring concrete for pier shaft 1st lift at LP3 Viaduct Km 202+190 LHS 9-Jul-19 4:22 PM
2380 NMSCEW/P-IV/STR/2019/2323 2323 Checking of reinforcement & shuttering for Raft at RP2 Viaduct Km 202+190 RHS 9-Jul-19 4:10 PM IPC-04 DONE
2381 NMSCEW/P-IV/STR/2019/2324 2324 Checking layout & level for raft at RP2 Viaduct Km 202+190 RHS 9-Jul-19 4:40 PM
2382 NMSCEW/P-IV/STR/2019/2325 2325 Checking and concrete pouring for Raft at RP2 Viaduct Km 202+190 RHS 9-Jul-19 5:26 PM IPC-04 DONE
Checking of Line, level and layout of bed-1, bed-2, bed-3, bed-5 & bed-6 for Girder, casting
2383 NMSCEW/P-IV/STR/2019/2326 2326 Girder Km 200+200 LHS 9-Jul-19 10:00 AM
yard at Camp-2
2384 NMSCEW/P-IV/STR/2019/2327 2327 Checking of completion 3x3 Precast segment errection. Box culvert Km 200+286 BHS 9-Jul-19 10:30 AM DONE
2385 NMSCEW/P-IV/STR/2019/2328 2328 Checking of completion 2x2 Precast segment errection. Utility duct Km 193+709 BHS 9-Jul-19 11:45 AM DONE
Checking of reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard
2386 NMSCEW/P-IV/STR/2019/2329 2329 Box culvert Km 200+200 LHS 9-Jul-19 11:00 AM DONE
camp -2. Segment
Checking NO-133,134.
for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2387 NMSCEW/P-IV/STR/2019/2330 2330 Box culvert Km 200+200 LHS 9-Jul-19 11:45 AM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-2,Segment no-133,134.
2388 NMSCEW/P-IV/STR/2019/2331 2331 Checking of reinforcement, shuttering for pier shaft final lift at RP4 Viaduct Km 169+800 RHS 9-Jul-19 3:35 PM NR
2389 NMSCEW/P-IV/STR/2019/2332 2332 Checking and Pouring concrete for pier shaft final lift at RP4 Viaduct Km 169+800 RHS 9-Jul-19 4:15 PM NR
2390 NMSCEW/P-IV/STR/2019/2333 2333 Checking of reinforcement & shuttering for Raft at RA1 Viaduct Km 169+800 RHS 9-Jul-19 2:40 PM NR
2391 NMSCEW/P-IV/STR/2019/2334 2334 Checking
Checking ofof reinforcement
reinforcement for& shuttering
precast Box forCulvert
Raft at(2x2)
LA1(cushion 2 to 4m) at precast yard Viaduct Km 169+800 LHS 9-Jul-19 2:50 PM NR
2392 NMSCEW/P-IV/STR/2019/2335 2335 camp -2. Segment NO-135,136,137,138,139. Box culvert Km 200+200 LHS 10-Jul-19 9:30 AM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2393 NMSCEW/P-IV/STR/2019/2336 2336 Checking of reinforcement for precast Box culvert Km 200+200 LHS 10-Jul-19 10:30 AM DONE
(2×2) (Cushion 2 to 4m) at precast yardBox Culvert (3x3)no-135,136,137,138,139.
camp-2.Segment (cushion 0 to 2m) at precast yard
2394 NMSCEW/P-IV/STR/2019/2337 2337 camp -2. Segment NO-68. Box culvert Km 200+200 LHS 10-Jul-19 3:00 PM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2395 NMSCEW/P-IV/STR/2019/2338 2338 Box culvert Km 200+200 LHS 10-Jul-19 3:50 PM DONE
(3×3) (Cushion 0 to 2m) at precast yard camp-2.Segment no-68.
2396 NMSCEW/P-IV/STR/2019/2339 2339 Checking of reinforcement and shuttering for raft Box culvert Km 204+920 LHS 10-Jul-19 3:30 PM IPC-05 DONE
2397 NMSCEW/P-IV/STR/2019/2340 2340 Checkingof level & layout for raft Box culvert Km 204+920 LHS 10-Jul-19 3:40 PM IPC-05 DONE
2398 NMSCEW/P-IV/STR/2019/2341 2341 Checking and Pouring of concrete for raft Box culvert Km 204+920 LHS 10-Jul-19 4:00 PM IPC-05 DONE
2399 NMSCEW/P-IV/STR/2019/2342 2342 Checking reinforcement ,shuttering for 2nd lift at wall W2 PUP Km 203+560 LHS 10-Jul-19 12:10 PM IPC-05 DONE AE
2400 NMSCEW/P-IV/STR/2019/2343 2343 Checking and concrete pouring for 2nd lift at wall W2 PUP Km 203+560 LHS 10-Jul-19 12:30 PM IPC-05 DONE AE
2401 NMSCEW/P-IV/STR/2019/2344 2344 Checking of reinforcement and shuttering for raft PUP Km 193+880 RHS 10-Jul-19 11:00 AM IPC-05 DONE AE
2402 NMSCEW/P-IV/STR/2019/2345 2345 Checkingof level & layout for raft PUP Km 193+880 RHS 10-Jul-19 2:00 PM IPC-05 DONE AE
2403 NMSCEW/P-IV/STR/2019/2346 2346 Checking and Pouring of concrete for raft PUP Km 193+880 RHS 10-Jul-19 3:15 PM IPC-05 DONE AE
2404 NMSCEW/P-IV/STR/2019/2347 2347 Checking of reinforcement & shuttering for Raft at RA1 Viaduct Km 169+800 RHS 10-Jul-19 3:05 PM NR
2405 NMSCEW/P-IV/STR/2019/2348 2348 Checking of reinforcement & shuttering for Raft at LA1 Viaduct Km 169+800 LHS 10-Jul-19 3:25 PM NR
2406 NMSCEW/P-IV/STR/2019/2349 2349 Checking of reinforcement, shuttering for pier shaft final lift at RP4 Viaduct Km 169+800 RHS 10-Jul-19 10:05 AM IPC-08 DONE
2407 NMSCEW/P-IV/STR/2019/2350 2350 Checking and Pouring concrete for pier shaft final lift at RP4 Viaduct Km 169+800 RHS 10-Jul-19 2:23 PM IPC-08 DONE
2408 NMSCEW/P-IV/STR/2019/2351 2351 Checking for layout & level for PCC at RP13 Viaduct Km 202+190 RHS 10-Jul-19 2:05 PM
2409 NMSCEW/P-IV/STR/2019/2352 2352 Checking top Level & Laying concrete PCC at RP13 Viaduct Km 202+190 RHS 10-Jul-19 3:18 PM
2410 NMSCEW/P-IV/STR/2019/2353 2353 Checking of reinforcement, shuttering for pier shaft 1st lift at LP3 Viaduct Km 202+190 LHS 10-Jul-19 12:00 PM
2411 NMSCEW/P-IV/STR/2019/2354 2354 Checking and Pouring concrete for pier shaft 1st lift at LP3 Viaduct Km 202+190 LHS 10-Jul-19 12:32 PM
2412 NMSCEW/P-IV/STR/2019/2355 2355 Checking annular filling arround foundation of M15 concrete at RP2 Viaduct Km 202+190 RHS 10-Jul-19 4:38 PM
2413 NMSCEW/P-IV/STR/2019/2356 2356 Checking of reinforcement and shuttering for raft at RP5 Viaduct Km 195+900 RHS 10-Jul-19 4:02 PM IPC-08 DONE AE
2414 NMSCEW/P-IV/STR/2019/2357 2357 Checkingof level & layout for raft at RP5 Viaduct Km 195+900 RHS 10-Jul-19 4:29 PM IPC-08 DONE AE
2415 NMSCEW/P-IV/STR/2019/2358 2358 Checking and Pouring of concrete(M-35) for raft at RP5 Viaduct Km 195+900 RHS 10-Jul-19 4:55 PM IPC-08 DONE AE
2416 NMSCEW/P-IV/STR/2019/2359 2359 Checking of reinforcement and shuttering for raft at RP4 Viaduct Km 195+900 RHS 10-Jul-19 3:11 PM
2417 NMSCEW/P-IV/STR/2019/2360 2360 Checkingof level & layout for raft at RP4 Viaduct Km 195+900 RHS 10-Jul-19 3:22 PM
2418 NMSCEW/P-IV/STR/2019/2361 2361 Checking and Pouring of concrete(M-35) for raft at RP4 Viaduct Km 195+900 RHS 10-Jul-19 3:50 PM
2419 NMSCEW/P-IV/STR/2019/2362 2362 Checking of Line, level and layout of bed-5 & bed-6 for Girder, casting yard at Camp-2 Girder Km 200+200 LHS 10-Jul-19 11:09 AM
2420 NMSCEW/P-IV/STR/2019/2363 2363 Checking reinforcement ,shuttering for final lift at wall A1 & A2 PUP Km 171+110 LHS 10-Jul-19 10:32 AM NR
2421 NMSCEW/P-IV/STR/2019/2364 2364 Checking and concrete(M-30) pouring for final lift at wall A1 & A2 PUP Km 171+110 LHS 10-Jul-19 10:46 AM NR
2422 NMSCEW/P-IV/STR/2019/2365 2365 Checking reinforcement ,shuttering for 4th lift at wall A1 & A2 VUP Km 176+614 LHS 10-Jul-19 11:48 AM IPC-08 DONE
2423 NMSCEW/P-IV/STR/2019/2366 2366 Checking and concrete(M-35) pouring for 4th lift at wall A1 & A2 VUP Km 176+614 LHS 10-Jul-19 12:12 PM IPC-08 DONE
2424 NMSCEW/P-IV/STR/2019/2367 2367 Checking reinforcement ,shuttering for top haunch at wall A1 & A2 and top slab PUP Km 171+110 LHS 10-Jul-19 2:33 PM NR
2425 NMSCEW/P-IV/STR/2019/2368 2368 Checking and concrete (M30) pouring for top haunch at wall A1 & A2 and top slab PUP Km 171+110 LHS 10-Jul-19 2:51 PM NR
Checking reinforcement for precast Box Culvert (3x3)(cushion 2 to 4m) at precast yard camp
2426 NMSCEW/P-IV/STR/2019/2369 2369 Box culvert Km 175+500 LHS 10-Jul-19 9:17 AM IPC-08 DONE 73, 74, 75
-1. Segment
Checking for NO-73,74,75
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2427 NMSCEW/P-IV/STR/2019/2370 2370 Box culvert Km 175+500 LHS 10-Jul-19 10:11 AM IPC-08 DONE AE 73, 74, 75
(3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-73,74,75
2428 NMSCEW/P-IV/STR/2019/2371 2371 Checking reinforcement for precast Box Culvert (2x2) (Cushion 2 to 4m) at precast yard cam Box culvert Km 176+250 BHS 10-Jul-19 12:22 PM IPC-05 DONE
2429 NMSCEW/P-IV/STR/2019/2372 2372 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2×2 Box culvert Km 176+250 BHS 10-Jul-19 4:19 PM IPC-05 DONE
2430 NMSCEW/P-IV/STR/2019/2373 2373 Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp Box culvert Km 179+390 BHS 10-Jul-19 12:52 PM IPC-05 DONE AE
2431 NMSCEW/P-IV/STR/2019/2374 2374 Checking forreinforcement
Checking of shuttering & Pouring of Box
for precast Concreting
CulvertGrade
(2x2) =(M-30)
(cushion for
2 toPrecast Box Culvert
4m) at precast yard (2×2 Box culvert Km 179+390 BHS 10-Jul-19 5:24 PM IPC-05 DONE AE
2432 NMSCEW/P-IV/STR/2019/2375 2375 camp -2. Segment NO-140,141,142,143,144. Box culvert Km 200+200 LHS 11-Jul-19 9:30 AM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2433 NMSCEW/P-IV/STR/2019/2376 2376 Box culvert Km 200+200 LHS 11-Jul-19 10:00 AM DONE
(2×2) (Cushion
Checking 2 to 4m) at precast
of reinforcement yardBox
for precast camp-2,Segment no-140,141,142,143,144.
Culvert (3x3) (cushion 0 to 2m) at precast yard
2434 NMSCEW/P-IV/STR/2019/2377 2377 Box culvert Km 200+200 LHS 11-Jul-19 11:00 AM DONE
camp -2. Segment
Checking NO-69,70,71,72.
for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2435 NMSCEW/P-IV/STR/2019/2378 2378 Box culvert Km 200+200 LHS 11-Jul-19 12:00 PM DONE
(3×3) (Cushion 0 to 2m) at precast yard camp-2.Segment no-69,70,71,72.
Checking of reinforcement for precast Box Culvert (3×3) (cushion 2 to 4m) at precast yard
2436 NMSCEW/P-IV/STR/2019/2379 2379 Box culvert Km 200+200 LHS 11-Jul-19 2:30 PM DONE
camp -2. Segment
Checking NO-18.
for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2437 NMSCEW/P-IV/STR/2019/2380 2380 Box culvert Km 200+200 LHS 11-Jul-19 3:30 PM DONE
(3×3) (Cushion
Checking 2 to 4m)and
of Shuttering at precast yard camp-2.Segment
reinforcement for precast typeno-18.
RE Wall Panel Nos -A7
2438 NMSCEW/P-IV/STR/2019/2381 2381 RE Wall Panel Km 200+200 LHS 11-Jul-19 10:30 AM DONE
Checking Pouring of Concrete for precast type RE Wall Panel Nos -A7
2439 NMSCEW/P-IV/STR/2019/2382 2382 RE Wall Panel Km 200+200 LHS 11-Jul-19 11:30 AM DONE
2440 NMSCEW/P-IV/STR/2019/2383 2383 Checking for layout and level for top Slab Box culvert Km 200+460 RHS 11-Jul-19 2:09 PM IPC-05 DONE
2441 NMSCEW/P-IV/STR/2019/2384 2384 Checking reinforcement ,shuttering and Concrete Pouring for top Slab Box culvert Km 200+460 RHS 11-Jul-19 3:20 PM IPC-05 DONE
2442 NMSCEW/P-IV/STR/2019/2385 2385 Checking reinforcement ,shuttering for 3rd lift at wall A1 & A2 PUP Km 183+290 LHS 11-Jul-19 2:15 PM NR
2443 NMSCEW/P-IV/STR/2019/2386 2386 Checking and concrete pouring for 3rd lift at wall A1 & A2 PUP Km 183+290 LHS 11-Jul-19 3:40 PM NR
2444 NMSCEW/P-IV/STR/2019/2387 2387 Checking layout ,level and structural excavation at Utility duct Utility duct Km 179+390 BHS 11-Jul-19 9:12 AM IPC-05 DONE
2445 NMSCEW/P-IV/STR/2019/2388 2388 Checking top Level & Laying concrete(M-10) PCC at Utility duct Utility duct Km 179+390 BHS 11-Jul-19 2:45 PM NR
2446 NMSCEW/P-IV/STR/2019/2389 2389 Checking reinforcement ,shuttering for final lift at wall A1 & A2 PUP Km 171+110 LHS 11-Jul-19 10:32 AM NR
2447 NMSCEW/P-IV/STR/2019/2390 2390 Checking and concrete(M-30) pouring for final lift at wall A1 & A2 PUP Km 171+110 LHS 11-Jul-19 10:46 AM NR
2448 NMSCEW/P-IV/STR/2019/2391 2391 Checking reinforcement ,shuttering for top haunch at wall A1 & A2 and top slab PUP Km 171+110 LHS 11-Jul-19 12:20 PM NR
2449 NMSCEW/P-IV/STR/2019/2392 2392 Checking and concrete (M30) pouring for top haunch at wall A1 & A2 and top slab PUP Km 171+110 LHS 11-Jul-19 12:50 PM NR
Checking reinforcement for precast Box Culvert (3x3)(cushion 2 to 4m) at precast yard camp
2450 NMSCEW/P-IV/STR/2019/2393 2393 Box culvert Km 175+500 LHS 11-Jul-19 9:18 AM IPC-08 DONE AE 76, 77, 78
-1. Segment
Checking for NO-76,77,78
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2451 NMSCEW/P-IV/STR/2019/2394 2394 Box culvert Km 175+500 LHS 11-Jul-19 10:12 AM IPC-08 DONE 72, 76, 77, 78
(3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-72,76,77,78
2452 NMSCEW/P-IV/STR/2019/2395 2395 Checking reinforcement for precast Box Culvert (2x2) (Cushion 2 to 4m) at precast yard cam Box culvert Km 176+250 BHS 11-Jul-19 12:23 PM IPC-05 DONE AE
2453 NMSCEW/P-IV/STR/2019/2396 2396 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2×2 Box culvert Km 176+250 BHS 11-Jul-19 4:17 PM IPC-05 DONE
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
2454 NMSCEW/P-IV/STR/2019/2397 2397 Box culvert Km 175+500 LHS 11-Jul-19 12:53 PM IPC-08 DONE AE 92, 93
-1. Segment
Checking for NO-92,93
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2455 NMSCEW/P-IV/STR/2019/2398 2398 Box culvert Km 175+500 LHS 11-Jul-19 5:26 PM IPC-08 DONE 86, 87, 92, 93
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-86,87,92,93
2456 NMSCEW/P-IV/STR/2019/2399 2399 Checking annular filling arround foundation of M15 concrete at RP7 Viaduct Km 195+900 RHS 11-Jul-19 9:36 AM
2457 NMSCEW/P-IV/STR/2019/2400 2400 Checking of reinforcement and shuttering for raft at RP4 Viaduct Km 195+900 RHS 11-Jul-19 3:12 PM
2458 NMSCEW/P-IV/STR/2019/2401 2401 Checkingof level & layout for raft at RP4 Viaduct Km 195+900 RHS 11-Jul-19 3:32 PM
2459 NMSCEW/P-IV/STR/2019/2402 2402 Checking and Pouring of concrete(M-35) for raft at RP4 Viaduct Km 195+900 RHS 11-Jul-19 3:57 PM
2460 NMSCEW/P-IV/STR/2019/2403 2403 Checking of reinforcement, shuttering for pier shaft 1st lift at LP3 Viaduct Km 202+190 LHS 11-Jul-19 11:46 AM IPC-08 DONE
2461 NMSCEW/P-IV/STR/2019/2404 2404 Checking and Pouring concrete for pier shaft 1st lift at LP3 Viaduct Km 202+190 LHS 11-Jul-19 12:19 PM IPC-08 DONE
2462 NMSCEW/P-IV/STR/2019/2405 2405 Checking for layout & level for PCC at LA1 Viaduct Km 202+190 LHS 11-Jul-19 3:08 PM
2463 NMSCEW/P-IV/STR/2019/2406 2406 Checking top Level & Laying concrete PCC at LA1 Viaduct Km 202+190 LHS 11-Jul-19 3:27 PM
2464 NMSCEW/P-IV/STR/2019/2407 2407 Checking of Line, level and layout of bed-5 & bed-6 for Girder, casting yard at Camp-2 Girder Km 200+200 LHS 11-Jul-19 11:11 AM
2465 NMSCEW/P-IV/STR/2019/2408 2408 Checking of reinforcement and shuttering for raft at RA1 Viaduct Km 169+800 RHS 11-Jul-19 8:02 AM NR
2466 NMSCEW/P-IV/STR/2019/2409 2409 Checking of reinforcement and shuttering for raft at LA1 Viaduct Km 169+800 LHS 11-Jul-19 8:22 AM DONE
2467 NMSCEW/P-IV/STR/2019/2410 2410 Checking and Pouring of concrete for raft at LA1 Viaduct Km 169+800 RHS 11-Jul-19 10:03 AM DONE
2468 NMSCEW/P-IV/STR/2019/2411 2411 Checking reinforcement ,shuttering for 2nd lift at wall W2 PUP Km 199+060 LHS 11-Jul-19 2:01 PM SPOT RFI
2469 NMSCEW/P-IV/STR/2019/2412 2412 Checking and concrete pouring for 2nd lift at wall W2 PUP Km 199+060 LHS 11-Jul-19 3:03 PM SPOT RFI
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
2470 NMSCEW/P-IV/STR/2019/2413 2413 Box culvert Km 175+500 LHS 12-Jul-19 10:50 AM NR
-2. Segment
Checking for NO-145
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2471 NMSCEW/P-IV/STR/2019/2414 2414 Box culvert Km 175+500 LHS 12-Jul-19 11:00 AM NR
(2×2) (Cushion
Checking 2 to 4m)and
of Shuttering at precast yard camp-2,Segment
reinforcement for precast typeno.-145
RE Wall Panel Nos 7 (Type-A)
2472 NMSCEW/P-IV/STR/2019/2415 2415 RE Wall Panel Km 200+200 LHS 12-Jul-19 2:00 PM DONE
Checking Pouring of Concrete for precast type RE Wall Panel Nos -7 (Type-A)
2473 NMSCEW/P-IV/STR/2019/2416 2416 RE Wall Panel Km 200+200 LHS 12-Jul-19 3:10 PM DONE
2474 NMSCEW/P-IV/STR/2019/2417 2417 Checking top Level & Laying concrete(M-10) PCC at Utility duct (2x2) Utility duct Km 179+390 BHS 12-Jul-19 11:00 AM IPC-05 DONE
2475 NMSCEW/P-IV/STR/2019/2418 2418 Checking reinforcement ,shuttering for final lift at wall A1 & A2 VUP Km 173+400 LHS 12-Jul-19 11:00 AM IPC-05 DONE
2476 NMSCEW/P-IV/STR/2019/2419 2419 Checking and concrete(M-35) pouring for final lift at wall A1 & A2 VUP Km 173+400 LHS 12-Jul-19 11:10 AM IPC-05 DONE
2477 NMSCEW/P-IV/STR/2019/2420 2420 Checking reinforcement ,shuttering for top haunch at wall A1 & A2 and top slab LVUP Km 173+400 LHS 12-Jul-19 3:30 PM IPC-05 DONE
2478 NMSCEW/P-IV/STR/2019/2421 2421 Checking and concrete (M35) pouring for top haunch at wall A1 & A2 and top slab LVUP Km 173+400 LHS 12-Jul-19 3:40 PM IPC-05 DONE
2479 NMSCEW/P-IV/STR/2019/2422 2422 Checking of reinforcement, shuttering for top slab and top haunch A1 &A2 at PUP PUP Km 190+650 LHS 12-Jul-19 2:20 PM IPC-05 DONE
2480 NMSCEW/P-IV/STR/2019/2423 2423 Checking top level & Laying concrete (M-30) for top slab top haunch A1 &A2 at PUP PUP Km 190+650 LHS 12-Jul-19 2:30 PM IPC-05 DONE
2481 NMSCEW/P-IV/STR/2019/2424 2424 Checking Reinforcement & shuttering for raft at Box Culvert B.C. Km 203+886 RHS 12-Jul-19 2:00 PM IPC-05 DONE AE
2482 NMSCEW/P-IV/STR/2019/2425 2425 Checking for Layout & level at box culvert B.C. Km 203+886 RHS 12-Jul-19 1:45 PM IPC-05 DONE AE
2483 NMSCEW/P-IV/STR/2019/2426 2426 checking of pouring concrete for box culvert B.C. Km 203+886 RHS 12-Jul-19 2:30 PM IPC-05 DONE AE
2484 NMSCEW/P-IV/STR/2019/2427 2427 Checking for Layout & level of Minor Bridge Minor Bridge Km 193+135 BHS 12-Jul-19 11:00 AM DONE
2485 NMSCEW/P-IV/STR/2019/2428 2428 Laying and top level checking concrete PCC at Minor bridge Minor Bridge Km 193+135 BHS 12-Jul-19 12:00 PM DONE
2486 NMSCEW/P-IV/STR/2019/2429 2429 checking Laying and top level concrete PCC at LA-1 Viaduct Km 202+190 LHS 12-Jul-19 10:00 AM
2487 NMSCEW/P-IV/STR/2019/2430 2430 Checking top level & Laying concrete for LP-3 pier shaft 1-st lift VIADUCT Km 202+190 LHS 12-Jul-19 12:00 PM
2488 NMSCEW/P-IV/STR/2019/2431 2431 checking of Layout reinforcement and shuttering (150mm) for LP1 pier starter VIADUCT Km 202+190 LHS 12-Jul-19 3:00 PM
2489 NMSCEW/P-IV/STR/2019/2432 2432 checking of Layout reinforcement and shuttering (150mm )for LP2 pier starter VIADUCT Km 202+190 LHS 12-Jul-19 3:00 PM
2490 NMSCEW/P-IV/STR/2019/2433 2433 Checking top level & Laying concrete for LP 1 (150mm) pier starter VIADUCT Km 202+190 LHS 12-Jul-19 4:00 PM
2491 NMSCEW/P-IV/STR/2019/2434 2434 Checking top level & Laying concrete for LP2 (150mm) pier starter VIADUCT Km 202+190 LHS 12-Jul-19 4:10 PM
2492 NMSCEW/P-IV/STR/2019/2435 2435 Checking reinforcement ,shuttering for bottom slab of box culvert Box culvert Km 186+352 RHS 12-Jul-19 5:00 PM IPC-05 DONE
2493 NMSCEW/P-IV/STR/2019/2436 2436 Checking and concrete (M30) pouring for bottom slab of box culvert Box culvert Km 186+352 RHS 12-Jul-19 5:10 PM IPC-05 DONE
2494 NMSCEW/P-IV/STR/2019/2437 2437 Checking for Layout & level at PUP PUP Km 212+080 RHS 12-Jul-19 2:30 PM DONE
2495 NMSCEW/P-IV/STR/2019/2438 2438 checking for raft reinforcement and shuttering at PUP PUP Km 212+080 RHS 12-Jul-19 3:00 PM DONE
2496 NMSCEW/P-IV/STR/2019/2439 2439 Checking top Level & Laying raft concrete at PUP PUP Km 212+080 RHS 12-Jul-19 4:00 PM DONE
2497 NMSCEW/P-IV/STR/2019/2440 2440 Checking of reinforcement, shuttering and layout for pier shaft starter at RP8 Viaduct Km 195+900 RHS 12-Jul-19 10:30 AM SPOT RFI
2498 NMSCEW/P-IV/STR/2019/2441 2441 Checking and Pouring concrete for pier shaft starter at RP8 Viaduct Km 195+900 RHS 12-Jul-19 11:00 AM SPOT RFI
2499 NMSCEW/P-IV/STR/2019/2442 2442 Checking of reinforcement, shuttering and layout for raft at RP4 Viaduct Km 196+560 RHS 12-Jul-19 10:45 AM IPC-05 DONE AE
2500 NMSCEW/P-IV/STR/2019/2443 2443 Checking and Pouring concrete for raft at RP4 Viaduct Km 196+560 RHS 12-Jul-19 11:20 AM IPC-05 DONE AE
Checking of Shuttering and reinforcement for RE WALL PANEL precast TYPE -A
2501 NMSCEW/P-IV/STR/2019/2444 2444 RE Wall Panel Km 200+200 LHS 13-Jul-19 3:00 PM DONE
13 NOS. Pouring of Concrete for RE WALL PANEL precast TYPE -A
Checking
2502 NMSCEW/P-IV/STR/2019/2445 2445 Checking RE Wall Panel Km 200+200 LHS 13-Jul-19 4:00 PM DONE
13 NOS. of reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard
2503 NMSCEW/P-IV/STR/2019/2446 2446 camp -2. Segment NO-146,147,148,149,150. Box culvert Km 200+200 LHS 13-Jul-19 9:30 AM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2504 NMSCEW/P-IV/STR/2019/2447 2447 Checking of reinforcement for precast Box culvert Km 200+200 LHS 13-Jul-19 10:30 AM DONE
(2×2) (Cushion 2 to 4m) at precast yardBox Culvert (3x3) (cushion
camp-2,Segment 0 to 2m) at precast yard
no-146,147,148,149,150.
2505 NMSCEW/P-IV/STR/2019/2448 2448 camp -2. Segment NO-73,74,75. Box culvert Km 200+200 LHS 13-Jul-19 11:30 AM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2506 NMSCEW/P-IV/STR/2019/2449 2449 Checking of reinforcement for precast Box Culvert (3×3) (cushion 2 to 4m) at precast yard Box culvert Km 200+200 LHS 13-Jul-19 2:20 PM DONE
(3×3) (Cushion 0 to 2m) at precast yard camp-2,Segment no-73,74,75.
2507 NMSCEW/P-IV/STR/2019/2450 2450 camp -2. Segment NO-18. Box culvert Km 200+200 LHS 13-Jul-19 3:00 PM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2508 NMSCEW/P-IV/STR/2019/2451 2451 Box culvert Km 200+200 LHS 13-Jul-19 5:10 PM DONE
(3×3) (Cushion 2 to 4m) at precast yard camp-2,Segment no-18.
2509 NMSCEW/P-IV/STR/2019/2452 2452 Checking of Line, level and layout of bed-1 & bed-3 for Girder, casting yard at Camp-2 Girder Km 200+200 LHS 13-Jul-19 11:00 AM
2510 NMSCEW/P-IV/STR/2019/2453 2453 Checking for layout & level for PCC at RA1 Viaduct Km 195+900 RHS 13-Jul-19 10:00 AM
2511 NMSCEW/P-IV/STR/2019/2454 2454 Checking top Level & Laying concrete PCC at RA1 Viaduct Km 195+900 RHS 13-Jul-19 10:30 AM
2512 NMSCEW/P-IV/STR/2019/2455 2455 Checking of reinforcement, shuttering and layout for pier shaft starter at LP1 Viaduct Km 202+190 LHS 13-Jul-19 11:05 AM IPC-08 DONE
2513 NMSCEW/P-IV/STR/2019/2456 2456 Checking and Pouring concrete for pier shaft starter at LP1 Viaduct Km 202+190 LHS 13-Jul-19 12:05 PM
2514 NMSCEW/P-IV/STR/2019/2457 2457 Checking of reinforcement, shuttering and layout for raft at RP3 Viaduct Km 202+190 RHS 13-Jul-19 3:02 PM
2515 NMSCEW/P-IV/STR/2019/2458 2458 Checking and Pouring concrete for raft at RP3 Viaduct Km 202+190 RHS 13-Jul-19 4:05 PM
2516 NMSCEW/P-IV/STR/2019/2459 2459 Checking for layout & level for PCC at LP13 Viaduct Km 202+190 LHS 13-Jul-19 10:18 AM
2517 NMSCEW/P-IV/STR/2019/2460 2460 Checking top Level & Laying concrete PCC at LP13 Viaduct Km 202+190 LHS 13-Jul-19 10:50 AM
Checking reinforcement for precast Box Culvert (3x3)(cushion 2 to 4m) at precast yard camp
2518 NMSCEW/P-IV/STR/2019/2461 2461 Box culvert Km 175+500 LHS 13-Jul-19 9:18 AM IPC-08 DONE AE 79, 80, 81, 82, 83
-1. Segment
Checking for NO-79,80,81,82,83
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2519 NMSCEW/P-IV/STR/2019/2462 2462 Box culvert Km 175+500 LHS 13-Jul-19 10:12 AM IPC-08 DONE AE 79, 80, 81, 82, 83
(3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-79,80,81,82,83
2520 NMSCEW/P-IV/STR/2019/2463 2463 Checking reinforcement for precast Box Culvert (2x2) (Cushion 2 to 4m) at precast yard cam Box culvert Km 176+250 BHS 13-Jul-19 12:23 PM IPC-05 DONE AE
2521 NMSCEW/P-IV/STR/2019/2464 2464 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2×2 Box culvert Km 176+250 BHS 13-Jul-19 4:17 PM IPC-05 DONE
2522 NMSCEW/P-IV/STR/2019/2465 2465 Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp Box culvert Km 179+390 BHS 13-Jul-19 12:53 PM IPC-05 DONE
2523 NMSCEW/P-IV/STR/2019/2466 2466 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2×2 Box culvert Km 179+390 BHS 13-Jul-19 5:26 PM IPC-05 DONE
2524 NMSCEW/P-IV/STR/2019/2467 2467 Checking for layout & level for top Slab PUP Km 208+930 RHS 13-Jul-19 10:46 AM DONE
2525 NMSCEW/P-IV/STR/2019/2468 2468 Checking of reinforcement, shuttering for top Slab PUP Km 208+930 RHS 13-Jul-19 11:05 AM DONE
2526 NMSCEW/P-IV/STR/2019/2469 2469 Checking and Pouring concrete for top Slab PUP Km 208+930 RHS 13-Jul-19 11:46 AM DONE
2527 NMSCEW/P-IV/STR/2019/2470 2470 Checking of reinforcement, shuttering for raft RA1 Viaduct Km 169+800 RHS 13-Jul-19 8:00 AM DONE
2528 NMSCEW/P-IV/STR/2019/2471 2471 Checking and Pouring concrete for raft RA1 Viaduct Km 169+800 RHS 13-Jul-19 8:30 AM DONE
2529 NMSCEW/P-IV/STR/2019/2472 2472 Checking of reinforcement, shuttering for pier shaft 1st lift at RP7 Viaduct Km 169+800 RHS 13-Jul-19 11:21 AM NR
Checking of reinforcement for precast Box Culvert (3×3) (cushion 2 to 4m) at precast yard
2530 NMSCEW/P-IV/STR/2019/2473 2473 Box Culvert Km 200+200 LHS 14-Jul-19 9:30 AM DONE
camp -2. Segment
Checking NO-19.
for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2531 NMSCEW/P-IV/STR/2019/2474 2474 Box Culvert Km 200+200 LHS 14-Jul-19 10:30 AM DONE
(3×3) (Cushion 2 to 4m) at precast yard camp-2,Segment no-19.
2532 NMSCEW/P-IV/STR/2019/2475 2475 Checking reinforcement ,shuttering for 1st lift at wall W2 Box Culvert Km 204+920 RHS 14-Jul-19 8:00 AM IPC-05 DONE
2533 NMSCEW/P-IV/STR/2019/2476 2476 Checking and concrete pouring for 1st lift at wall W2 Box Culvert Km 204+920 RHS 14-Jul-19 8:30 AM IPC-05 DONE
2534 NMSCEW/P-IV/STR/2019/2477 2477 checking for reinforcement and shuttering for bottom slab & haunch of Box Culvert Box Culvert Km 182+350 RHS 14-Jul-19 4:00 PM IPC-08 DONE AE
2535 NMSCEW/P-IV/STR/2019/2478 2478 Checking top Level & Pouring M30 concrete for bottom slab & haunch of Box Culvert Box Culvert Km 182+350 RHS 14-Jul-19 4:30 PM IPC-08 DONE AE
2536 NMSCEW/P-IV/STR/2019/2479 2479 Checking reinforcement ,shuttering for 1st lift at wall A1 & A2 PUP Km 189+000 LHS 14-Jul-19 5:00 PM NR
2537 NMSCEW/P-IV/STR/2019/2480 2480 Checking and concrete(M-30) pouring for 1st lift at wall A1 & A2 PUP Km 189+000 LHS 14-Jul-19 5:30 PM NR
2538 NMSCEW/P-IV/STR/2019/2481 2481 Checking reinforcement ,shuttering for 3rd lift at wall A1 & A2 PUP Km 183+290 LHS 14-Jul-19 2:00 PM REPEATED
2539 NMSCEW/P-IV/STR/2019/2482 2482 Checking and concrete(M-30) pouring for 3rd lift at wall A1 & A2 PUP Km 183+290 LHS 14-Jul-19 2:30 PM REPEATED
2540 NMSCEW/P-IV/STR/2019/2483 2483 Checking annular filling arround foundation of M15 concrete at RP4 Viaduct Km 196+560 RHS 14-Jul-19 10:00 AM
2541 NMSCEW/P-IV/STR/2019/2484 2484 Checking of Line, level and layout of bed-7 for Girder, casting yard at Camp-2 Girder Km 200+200 LHS 14-Jul-19 11:10 AM
2542 NMSCEW/P-IV/STR/2019/2485 2485 Checking reinforcement ,shuttering for final lift at wall A1 & A2 PUP Km 177+810 RHS 14-Jul-19 11:33 AM NR
2543 NMSCEW/P-IV/STR/2019/2486 2486 Checking and concrete(M-30) pouring for final lift at wall A1 & A2 PUP Km 177+810 RHS 14-Jul-19 12:02 PM NR
2544 NMSCEW/P-IV/STR/2019/2487 2487 Checking reinforcement ,shuttering for top haunch at wall A1 & A2 and top slab PUP Km 177+810 RHS 14-Jul-19 4:10 PM NR
2545 NMSCEW/P-IV/STR/2019/2488 2488 Checking and concrete (M30) pouring for top haunch at wall A1 & A2 and top slab PUP Km 177+810 RHS 14-Jul-19 4:40 PM NR
2546 NMSCEW/P-IV/STR/2019/2489 2489 Checking of reinforcement, shuttering for raft wirh bottom haunch at wall A1 & A2 PUP Km 165+790 RHS 14-Jul-19 10:42 AM IPC-08 DONE
2547 NMSCEW/P-IV/STR/2019/2490 2490 Checking and Pouring concrete for raft wirh bottom haunch at wall A1 & A2 PUP Km 165+790 RHS 14-Jul-19 10:52 AM IPC-08 DONE
Checking of reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard
2548 NMSCEW/P-IV/STR/2019/2491 2491 Box Culvert Km 200+200 LHS 15-Jul-19 9:30 AM DONE
camp -2. Segment
Checking NO-151,152,153,154,155,156,157.
for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2549 NMSCEW/P-IV/STR/2019/2492 2492 Box Culvert Km 200+200 LHS 15-Jul-19 10:30 AM DONE
(2×2) (Cushion
Checking 2 to 4m) at precast
of reinforcement yardBox
for precast camp-2,Segment no-151,152,153,154,155,156,157.
Culvert (3x3) (cushion 0 to 2m) at precast yard
2550 NMSCEW/P-IV/STR/2019/2493 2493 Box Culvert Km 200+200 LHS 15-Jul-19 11:30 AM DONE
camp -2. Segment NO-76,77,78.
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2551 NMSCEW/P-IV/STR/2019/2494 2494 Checking of reinforcement for precast Box Culvert Km 200+200 LHS 15-Jul-19 12:30 PM DONE
(3×3) (Cushion 0 to 2m) at precast yardBox Culvert (3×3) no-76,77,78.
camp-2,Segment (cushion 2 to 4m) at precast yard
2552 NMSCEW/P-IV/STR/2019/2495 2495 camp -2. Segment NO-20. Box Culvert Km 200+200 LHS 15-Jul-19 3:00 PM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2553 NMSCEW/P-IV/STR/2019/2496 2496 Box Culvert Km 200+200 LHS 15-Jul-19 4:30 PM DONE
(3×3) (Cushion 2 to 4m) at precast yard camp-2,Segment no-20.
2554 NMSCEW/P-IV/STR/2019/2497 2497 Checking for layout & level for Raft PUP Km 212+080 Km 00+000 RHS 15-Jul-19 9:00 AM IPC-10 DONE
2555 NMSCEW/P-IV/STR/2019/2498 2498 Checking of reinforcement, shuttering for Raft PUP Km 212+080 Km 00+000 RHS 15-Jul-19 10:00 AM IPC-10 DONE
2556 NMSCEW/P-IV/STR/2019/2499 2499 Checking and Pouring concrete for Raft PUP Km 212+080 Km 00+000 RHS 15-Jul-19 11:00 AM IPC-10 DONE
2557 NMSCEW/P-IV/STR/2019/2500 2500 Checking for layout & level for PCC PUP Km 206+985 LHS 15-Jul-19 8:00 AM DONE
2558 NMSCEW/P-IV/STR/2019/2501 2501 Checking top Level & Laying concrete for PCC PUP Km 206+985 LHS 15-Jul-19 8:30 AM DONE
2559 NMSCEW/P-IV/STR/2019/2502 2502 Checking of Shuttering and reinforcement for 2nd lift for wall PUP Km 193+880 LHS 15-Jul-19 10:10 AM IPC-08 DONE A1 & A2
2560 NMSCEW/P-IV/STR/2019/2503 2503 Checking and Pouring concrete for 2nd lift for wall PUP Km 193+880 LHS 15-Jul-19 11:10 AM IPC-08 DONE A1 & A2
Checking reinforcement for precast Box Culvert (3x3)(cushion 2 to 4m) at precast yard camp
2561 NMSCEW/P-IV/STR/2019/2504 2504 Box culvert Km 175+500 LHS 15-Jul-19 9:18 AM IPC-08 DONE AE 84, 85, 86, 87, 88
-1. Segment
Checking for NO-84,85,86,87,88
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2562 NMSCEW/P-IV/STR/2019/2505 2505 Box culvert Km 175+500 LHS 15-Jul-19 10:12 AM IPC-08 DONE AE 84, 85, 86, 87
(3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-84,85,86,87,88
2563 NMSCEW/P-IV/STR/2019/2506 2506 Checking reinforcement for precast Box Culvert (2x2) (Cushion 2 to 4m) at precast yard cam Box culvert Km 176+250 BHS 15-Jul-19 12:23 PM IPC-05 DONE
2564 NMSCEW/P-IV/STR/2019/2507 2507 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2×2 Box culvert Km 176+250 BHS 15-Jul-19 4:17 PM IPC-05 DONE AE
2565 NMSCEW/P-IV/STR/2019/2508 2508 Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard cam Box culvert Km 179+390 BHS 15-Jul-19 12:53 PM IPC-05 DONE AE
2566 NMSCEW/P-IV/STR/2019/2509 2509 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2×2 Box culvert Km 179+390 BHS 15-Jul-19 5:26 PM IPC-05 DONE AE
2567 NMSCEW/P-IV/STR/2019/2510 2510 Checking of reinforcement, shuttering for raft LP8 Viaduct Km 195+900 LHS 15-Jul-19 3:00 PM IPC-08 DONE AE
2568 NMSCEW/P-IV/STR/2019/2511 2511 Checking and Pouring concrete(M-35) for raft RP5 Viaduct Km 195+900 RHS 15-Jul-19 3:33 PM
2569 NMSCEW/P-IV/STR/2019/2512 2512 Checking of reinforcement, shuttering and layout for pier shaft 1st lift at LP7 Viaduct Km 195+900 Km 00+000 LHS 15-Jul-19 4:05 PM IPC-11 Approved
2570 NMSCEW/P-IV/STR/2019/2513 2513 Checking of
Checking andShuttering
Pouring concrete for pier shaft
and reinforcement 1st WALL
for RE lift at LP7
PANEL precast TYPE -A Viaduct Km 195+900 Km 00+000 LHS 15-Jul-19 4:35 PM IPC-11 Approved
2571 NMSCEW/P-IV/STR/2019/2514 2514 32 NOS, TYPE -B 10 NOS, TYPE -Sta 2 NOS, TYPE -Stb 2 NOS, TYPE -Stc 2 NOS, RE Wall Panel Km 200+200 LHS 15-Jul-19 10:15 AM DONE
2572 NMSCEW/P-IV/STR/2019/2515 2515 TYPE -Stdof2reinforcement,
Checking NOS, TYPE -Ltc 1 NOS,for
shuttering TYPE -Ltd starter
pier shaft 2 NOS, at LP2 Viaduct Km 202+190 LHS 15-Jul-19 10:02 AM IPC-08 DONE
2573 NMSCEW/P-IV/STR/2019/2516 2516 Checking and Pouring concrete for pier shaft starter at LP2 Viaduct Km 202+190 LHS 15-Jul-19 11:19 AM IPC-08 DONE
2574 NMSCEW/P-IV/STR/2019/2517 2517 Checking and Pouring concrete for pier shaft starter at LP1 Viaduct Km 202+190 LHS 15-Jul-19 9:16 AM IPC-08 DONE
2575 NMSCEW/P-IV/STR/2019/2518 2518 Checking and Pouring concrete for raft RP3 Viaduct Km 202+190 RHS 15-Jul-19 11:26 AM
2576 NMSCEW/P-IV/STR/2019/2519 2519 Checking annular filling arround foundation of M15 concrete at LP6,LP7 Viaduct Km 202+190 LHS 15-Jul-19 12:07 PM
2577 NMSCEW/P-IV/STR/2019/2520 2520 Checking annular filling arround foundation of M15 concrete at LP3 Viaduct Km 200+920 LHS 15-Jul-19 10:18 AM
2578 NMSCEW/P-IV/STR/2019/2521 2521 Checking annular filling arround foundation of M15 concrete at RP3 Viaduct Km 200+920 RHS 15-Jul-19 10:50 AM
2579 NMSCEW/P-IV/STR/2019/2522 2522 Checking of reinforcement, shuttering and layout for pier shaft 1st lift at RP7 Viaduct Km 169+800 RHS 15-Jul-19 9:31 AM IPC-08 DONE AE
2580 NMSCEW/P-IV/STR/2019/2523 2523 Checking and Pouring concrete for pier shaft 1st lift at RP7 Viaduct Km 169+800 RHS 15-Jul-19 10:21 AM IPC-08 DONE
2581 NMSCEW/P-IV/STR/2019/2524 2524 Checking and concrete pouring for 1ST lift at wall W1 & W2 Viaduct Km 203+886 RHS 15-Jul-19 2:02 PM IPC-05 DONE
2582 NMSCEW/P-IV/STR/2019/2525 2525 Checking and
Checking and Pouring
Pouring concrete
concrete forfor RE
pierWALL
shaft 2nd and final
PANEL lift TYPE
precast at RP5-A Viaduct Km 169+800 RHS 15-Jul-19 3:22 PM NR
2583 NMSCEW/P-IV/STR/2019/2514-A 2514-A 32 NOS, TYPE -B 10 NOS, TYPE -Sta 2 NOS, TYPE -Stb 2 NOS, TYPE -Stc 2 NOS, RE Wall Panel Km 200+200 LHS 15-Jul-19 12:00 PM DONE
2584 NMSCEW/P-IV/STR/2019/2526 2526 TYPE -Stdreinforcement
Checking 2 NOS, TYPE -Ltc 1 NOS,
,shuttering for TYPE
2nd lift-Ltd 2 NOS,
at wall W1 PUP Km 193+880 RHS 16-Jul-19 9:00 AM IPC-05 DONE
2585 NMSCEW/P-IV/STR/2019/2527 2527 Checking and concrete pouring for 2nd lift at wall W1 PUP Km 193+880 RHS 16-Jul-19 10:00 AM IPC-05 DONE
2586 NMSCEW/P-IV/STR/2019/2528 2528 Checking reinforcement ,shuttering for 1st lift at wall W1 PUP Km 199+060 RHS 16-Jul-19 10:00 AM IPC-05 DONE
2587 NMSCEW/P-IV/STR/2019/2529 2529 Checking and concrete pouring for 1st lift at wall W1 PUP Km 199+060 RHS 16-Jul-19 12:00 PM IPC-05 DONE
2588 NMSCEW/P-IV/STR/2019/2530 2530 Checking reinforcement ,shuttering for 1st lift at wall W1 Box culvert Km 200+460 LHS 16-Jul-19 2:00 PM IPC-05 DONE
2589 NMSCEW/P-IV/STR/2019/2531 2531 Checking and concrete pouring for 1st lift at wall W1 Box culvert Km 200+460 LHS 16-Jul-19 3:00 PM IPC-05 DONE
2590 NMSCEW/P-IV/STR/2019/2532 2532 Checking and Pouring concrete for raft at LP8 Viaduct Km 195+900 LHS 16-Jul-19 10:35 AM IPC-08 DONE
2591 NMSCEW/P-IV/STR/2019/2533 2533 Checking for layout & level for PCC at LP13 Viaduct Km 202+190 LHS 16-Jul-19 3:05 PM IPC-08 DONE
2592 NMSCEW/P-IV/STR/2019/2534 2534 Checking top Level & Laying concrete PCC at LP13 Viaduct Km 202+190 LHS 16-Jul-19 4:06 PM IPC-08 DONE
2593 NMSCEW/P-IV/STR/2019/2535 2535 Checking of reinforcement of girder no- 1,2,3 & 4 Bed no-1,girder type-2 Girder Km 200+200 LHS 16-Jul-19 10:18 AM
2594 NMSCEW/P-IV/STR/2019/2536 2536 Checking of reinforcement, shuttering and layout for pier shaft 2nd and final lift at RP5 Viaduct Km 169+800 RHS 16-Jul-19 11:09 AM IPC-08 DONE
2595 NMSCEW/P-IV/STR/2019/2537 2537 Checking and Pouring concrete for pier shaft 2nd and final lift at RP5 Viaduct Km 169+800 RHS 16-Jul-19 11:39 AM IPC-08 DONE
2596 NMSCEW/P-IV/STR/2019/2538 2538 Checking of reinforcement & shuttering for 1st lift A1 & A2 wall PUP Km 189+000 LHS 16-Jul-19 9:02 AM IPC-05 DONE AE
2597 NMSCEW/P-IV/STR/2019/2539 2539 Checking and pouring concrete(M-30) for 1st lift A1 & A2 wall PUP Km 189+000 LHS 16-Jul-19 9:32 AM IPC-05 DONE AE
2598 NMSCEW/P-IV/STR/2019/2540 2540 Checking of reinforcement & shuttering for 1st lift A1 & A2 wall PUP Km 190+650 RHS 16-Jul-19 11:22 AM IPC-05 DONE AE
2599 NMSCEW/P-IV/STR/2019/2541 2541 Checking and pouring concrete(M-30) for 1st lift A1 & A2 wall PUP Km 190+650 RHS 16-Jul-19 11:46 AM IPC-05 DONE
Checking reinforcement for precast Box Culvert (3x3)(cushion 2 to 4m) at precast yard camp
2600 NMSCEW/P-IV/STR/2019/2542 2542 Box culvert Km 175+500 LHS 16-Jul-19 9:21 AM IPC-08 DONE AE 94, 95, 96, 97, 98
-1. Segment
Checking for NO-94, 95,&96,
shuttering 97, 98 of Concreting Grade =(M-30) for Precast Box Culvert
Pouring
2601 NMSCEW/P-IV/STR/2019/2543 2543 Box culvert Km 175+500 LHS 16-Jul-19 10:22 AM IPC-08 DONE 94, 95, 96, 97
(3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-94, 95, 96, 97, 98
2602 NMSCEW/P-IV/STR/2019/2544 2544 Checking reinforcement for precast Box Culvert (2x2) (Cushion 2 to 4m) at precast yard cam Box culvert Km 176+250 BHS 16-Jul-19 12:27 PM IPC-05 DONE
2603 NMSCEW/P-IV/STR/2019/2545 2545 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2×2 Box culvert Km 176+250 BHS 16-Jul-19 4:19 PM IPC-05 DONE
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
2604 NMSCEW/P-IV/STR/2019/2546 2546 Box culvert Km 175+500 LHS 16-Jul-19 12:55 PM IPC-08 DONE 106, 107, 108, 109
-1. Segment
Checking for NO-106,
shuttering107, 108, 109of Concreting Grade =(M-30) for Precast Box Culvert
& Pouring
2605 NMSCEW/P-IV/STR/2019/2547 2547 Box culvert Km 175+500 LHS 16-Jul-19 5:36 PM IPC-08 DONE 106
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-106, 107, 108, 109
2606 NMSCEW/P-IV/STR/2019/2548 2548 Checking reinforcement ,shuttering for top haunch at wall A1 & A2 and top slab LVUP Km 173+400 LHS 16-Jul-19 5:20 PM DONE
2607 NMSCEW/P-IV/STR/2019/2549 2549 Checking and concrete (M35) pouring for top haunch at wall A1 & A2 and top slab LVUP Km 173+400 LHS 16-Jul-19 5:50 PM DONE
2608 NMSCEW/P-IV/STR/2019/2550 2550 Checking of reinforcement & shuttering for 1st lift for A1 & A2 wall LVUP Km 178+323 Km 00+000 LHS 16-Jul-19 5:31 PM IPC-09 DONE
2609 NMSCEW/P-IV/STR/2019/2551 2551 Checking and pouring concrete(M-35) for 1st lift for A1 & A2 wall LVUP Km 178+323 Km 00+000 LHS 16-Jul-19 6:10 PM IPC-09 DONE
2610 NMSCEW/P-IV/STR/2019/2552 2552 Checking reinforcement ,shuttering for bottom haunch at wall A1 & A2 LVUP Km 178+323 RHS 16-Jul-19 11:11 AM IPC-08 DONE
2611 NMSCEW/P-IV/STR/2019/2553 2553 Checking
Checking ofandShuttering
concrete(M-35) pouring for for
and reinforcement bottom
RE WALLhaunchPANEL
at wall precast
A1 & A2 TYPE -A LVUP Km 178+323 RHS 16-Jul-19 11:39 AM IPC-08 DONE
2612 NMSCEW/P-IV/STR/2019/2554 2554 32 NOS, TYPE
Checking -B 10 concrete
and Pouring NOS, TYPE -StaWALL
for RE 2 NOS,PANEL
TYPE precast
-Stb 2 NOS,
TYPETYPE-A -Stc 2 NOS, RE Wall Panel Km 200+200 LHS 16-Jul-19 3:37 PM DONE
2613 NMSCEW/P-IV/STR/2019/2555 2555 TYPE
32 -Std
NOS, 2 NOS,
TYPE TYPE
-B 10 NOS, -Ltc 1 NOS,
TYPE -Sta TYPE
2 NOS, -Ltd
TYPE 2 NOS,
-Stb 2 NOS, TYPE -Stc 2 NOS, RE Wall Panel Km 200+200 LHS 16-Jul-19 4:10 PM DONE
2614 NMSCEW/P-IV/STR/2019/2556 2556 TYPE -Stdof2reinforcement,
Checking NOS, TYPE -Ltc 1 NOS,for
shuttering TYPE -Ltd 1st
pier shaft 2 NOS,
lift at LP3 Viaduct Km 169+800 Km 00+000 LHS 16-Jul-19 2:02 PM IPC-09 DONE
2615 NMSCEW/P-IV/STR/2019/2557 2557 Checking and Pouring concrete for pier shaft 1st lift at LP3 Viaduct Km 169+800 Km 00+000 LHS 16-Jul-19 3:09 PM IPC-09 DONE
2616 NMSCEW/P-IV/STR/2019/2558 2558 Checking layout ,level and structural excavation at Utility duct Utility duct Km 198+770 BHS 16-Jul-19 12:02 PM SPOT RFI
2617 NMSCEW/P-IV/STR/2019/2559 2559 Checking top Level & Laying concrete(M-10) PCC at Utility duct Utility duct Km 198+770 BHS 16-Jul-19 12:46 PM SPOT RFI
2618 NMSCEW/P-IV/STR/2019/2560 2560 Checking layout ,level and structural excavation at Utility duct Utility duct Km 178+370 BHS 17-Jul-19 9:00 AM NR
2619 NMSCEW/P-IV/STR/2019/2561 2561 Checking top Level & Laying concrete(M-10) PCC at Utility duct Utility duct Km 178+370 BHS 17-Jul-19 3:00 PM NR
2620 NMSCEW/P-IV/STR/2019/2562 2562 Checking reinforcement ,shuttering for 2nd lift at wall W1 PUP Km 199+060 RHS 17-Jul-19 2:00 PM IPC-05 DONE AE
2621 NMSCEW/P-IV/STR/2019/2563 2563 Checking and concrete pouring for 2nd lift at wall W1 PUP Km 199+060 RHS 17-Jul-19 3:15 PM IPC-05 DONE AE
2622 NMSCEW/P-IV/STR/2019/2564 2564 Checking layout and level & Structural Excavation for PCC at B/C Box culvert Km 201+280 Km 00+000 BHS 17-Jul-19 9:15 AM IPC-11 Approved
2623 NMSCEW/P-IV/STR/2019/2565 2565 Checking of
Checking topreinforcement
Level & Laying concrete
for precast BoxPCC at B/C
Culvert (2x2) (cushion 2 to 4m) at precast yard Box culvert Km 201+280 Km 00+000 BHS 17-Jul-19 10:00 AM IPC-11 Approved
2624 NMSCEW/P-IV/STR/2019/2566 2566 camp -2. Segment
Checking NO-158,159,160,161,162,163,164,165.
for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert Box culvert Km 200+200 LHS 17-Jul-19 9:30 AM DONE
2625 NMSCEW/P-IV/STR/2019/2567 2567 (2×2) (Cushion 2 to 4m) at precast yard camp-2,Segment no- Box culvert Km 200+200 LHS 17-Jul-19 10:30 AM DONE
Checking of reinforcement for precast Box Culvert (3×3) (cushion 2 to 4m) at precast yard
158,159,160,161,162,163,164,165.
2626 NMSCEW/P-IV/STR/2019/2568 2568 Box culvert Km 200+200 LHS 17-Jul-19 2:30 PM DONE
camp -2. Segment
Checking NO-21.
for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2627 NMSCEW/P-IV/STR/2019/2569 2569 Box culvert Km 200+200 LHS 17-Jul-19 3:45 PM DONE
(3×3) (Cushion 2 to 4m) at precast yard camp-2,Segment no-21.
2628 NMSCEW/P-IV/STR/2019/2570 2570 Checking of reinforcement, shuttering for pier shaft 1st lift at RP6 Viaduct Km 169+800 RHS 17-Jul-19 10:02 AM IPC-08 DONE AE
2629 NMSCEW/P-IV/STR/2019/2571 2571 Checking and Pouring concrete for pier shaft 1st lift at RP6 Viaduct Km 169+800 RHS 17-Jul-19 11:09 AM IPC-08 DONE AE
2630 NMSCEW/P-IV/STR/2019/2572 2572 Checking of reinforcement, shuttering for raft RP3 Viaduct Km 202+190 RHS 17-Jul-19 11:18 AM IPC-08 DONE
2631 NMSCEW/P-IV/STR/2019/2573 2573 Checking and Pouring concrete for raft RP3 Viaduct Km 202+190 RHS 17-Jul-19 12:12 PM IPC-08 DONE
2632 NMSCEW/P-IV/STR/2019/2574 2574 Checking for layout & level for PCC at LP13 Viaduct Km 202+190 LHS 17-Jul-19 10:16 AM
2633 NMSCEW/P-IV/STR/2019/2575 2575 Checking top Level & Laying concrete PCC at LP13 Viaduct Km 202+190 LHS 17-Jul-19 11:22 AM
2634 NMSCEW/P-IV/STR/2019/2576 2576 Checking annular filling arround foundation of M15 concrete at RP7 Viaduct Km 202+190 RHS 17-Jul-19 10:23 AM
2635 NMSCEW/P-IV/STR/2019/2577 2577 Checking of reinforcement, shuttering for pier shaft 1st lift at LP7 Viaduct Km 195+900 LHS 17-Jul-19 10:50 AM
2636 NMSCEW/P-IV/STR/2019/2578 2578 Checking and Pouring concrete for pier shaft 1st lift at LP7 Viaduct Km 195+900 LHS 17-Jul-19 11:13 AM
2637 NMSCEW/P-IV/STR/2019/2579 2579 Checking reinforcement ,shuttering for raft with bottom haunch at wall A1 & A2 LVUP Km 169+291 LHS 17-Jul-19 4:02 PM IPC-08 DONE AE
2638 NMSCEW/P-IV/STR/2019/2580 2580 Checking and concrete pouring for raft with bottom haunch at wall A1 & A2 LVUP Km 169+291 LHS 17-Jul-19 4:47 PM IPC-08 DONE AE
Checking reinforcement for precast Box Culvert (3x3)(cushion 2 to 4m) at precast yard camp
2639 NMSCEW/P-IV/STR/2019/2581 2581 Box culvert Km 175+500 LHS 17-Jul-19 9:26 AM IPC-08 DONE AE 89, 90, 91,92, 93
-1. Segment
Checking for NO-89,90,91,92,93
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2640 NMSCEW/P-IV/STR/2019/2582 2582 Box culvert Km 175+500 LHS 17-Jul-19 10:29 AM IPC-08 DONE AE 89, 90, 91,92, 93
(3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-89,90,91,92,93
2641 NMSCEW/P-IV/STR/2019/2583 2583 Checking reinforcement for precast Box Culvert (2x2) (Cushion 2 to 4m) at precast yard cam Box culvert Km 176+250 BHS 17-Jul-19 12:37 PM IPC-05 DONE
2642 NMSCEW/P-IV/STR/2019/2584 2584 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2×2 Box culvert Km 176+250 BHS 17-Jul-19 4:29 PM IPC-05 DONE
2643 NMSCEW/P-IV/STR/2019/2585 2585 Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard cam Box culvert Km 179+390 BHS 17-Jul-19 12:52 PM IPC-05 DONE
2644 NMSCEW/P-IV/STR/2019/2586 2586 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2×2 Box culvert Km 179+390 BHS 17-Jul-19 5:38 PM IPC-05 DONE
2645 NMSCEW/P-IV/STR/2019/2587 2587 Checking layout ,level and structural excavation Box culvert Km 180+922 Km 00+000 BHS 17-Jul-19 8:00 AM IPC-10 DONE
2646 NMSCEW/P-IV/STR/2019/2588 2588 Checking top Level & Laying concrete(M-15) PCC Box culvert Km 180+922 Km 00+000 BHS 17-Jul-19 8:50 AM IPC-10 DONE
2647 NMSCEW/P-IV/STR/2019/2589 2589 Checking reinforcement ,shuttering for top haunch at wall A1 & A2 and top slab PUP Km 183+290 LHS 17-Jul-19 4:03 PM NR
2648 NMSCEW/P-IV/STR/2019/2590 2590 Checking of
Checking andreinforcement
concrete (M30)for pouring
precast Boxfor top haunch
Culvert (2x2)at wall A1 &2 A2
(cushion andattop
to 4m) slab yard
precast PUP Km 183+290 LHS 17-Jul-19 5:15 PM NR
2649 NMSCEW/P-IV/STR/2019/2591 2591 camp -2. Segment NO-166,167,168,169,170,171. Box Culvert Km 200+200 LHS 18-Jul-19 9:30 AM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2650 NMSCEW/P-IV/STR/2019/2592 2592 Box Culvert Km 200+200 LHS 18-Jul-19 11:00 AM DONE
(2×2) (Cushion
Checking 2 to 4m) at precast
of reinforcement yardBox
for precast camp-2,Segment no-166,167,168,169,170,171.
Culvert (3x3) (cushion 0 to 2m) at precast yard
2651 NMSCEW/P-IV/STR/2019/2593 2593 Box Culvert Km 200+200 LHS 18-Jul-19 2:20 PM DONE
camp -2. Segment
Checking NO-79,80,81.
for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2652 NMSCEW/P-IV/STR/2019/2594 2594 Box Culvert Km 200+200 LHS 18-Jul-19 3:15 PM DONE
(3×3) (Cushion 0 to 2m) at precast yard camp-2,Segment no-79,80,81.
2653 NMSCEW/P-IV/STR/2019/2595 2595 Checking layout and level at Utility duct Utility duct Km 176+250 BHS 18-Jul-19 10:00 AM NR
2654 NMSCEW/P-IV/STR/2019/2596 2596 Checking for layout & level for PCC at RA1 Viaduct Km 195+900 RHS 18-Jul-19 10:10 AM IPC-08 DONE
2655 NMSCEW/P-IV/STR/2019/2597 2597 Checking top Level & Laying concrete PCC at RA1 Viaduct Km 195+900 RHS 18-Jul-19 10:50 AM IPC-08 DONE
2656 NMSCEW/P-IV/STR/2019/2598 2598 Checking annular filling arround foundation of M15 concrete at RP5 Viaduct Km 195+900 RHS 18-Jul-19 11:15 AM
2657 NMSCEW/P-IV/STR/2019/2599 2599 Checking of reinforcement, shuttering for pier shaft starter at LP8 Viaduct Km 195+900 LHS 18-Jul-19 11:45 AM IPC-14
2658 NMSCEW/P-IV/STR/2019/2600 2600 Checking and Pouring concrete for pier shaft starter at LP8 Viaduct Km 195+900 LHS 18-Jul-19 12:10 PM IPC-14
2659 NMSCEW/P-IV/STR/2019/2601 2601 Checking of reinforcement, shuttering for pier shaft 1st lift at LP4 Viaduct Km 202+190 LHS 18-Jul-19 11:01 AM
2660 NMSCEW/P-IV/STR/2019/2602 2602 Checking and Pouring concrete for pier shaft 1st lift at LP4 Viaduct Km 202+190 LHS 18-Jul-19 12:05 PM
2661 NMSCEW/P-IV/STR/2019/2603 2603 Checking for layout & level for PCC at LP12 Viaduct Km 202+190 Km 00+000 LHS 18-Jul-19 3:03 PM IPC-10 DONE
2662 NMSCEW/P-IV/STR/2019/2604 2604 Checking top Level & Laying concrete PCC at LP12 Viaduct Km 202+190 Km 00+000 LHS 18-Jul-19 4:00 PM IPC-10 DONE
2663 NMSCEW/P-IV/STR/2019/2605 2605 Checking annular filling arround foundation of M15 concrete at RP7 Viaduct Km 202+190 LHS 18-Jul-19 10:08 AM
2664 NMSCEW/P-IV/STR/2019/2606 2606 Checking reinforcement ,shuttering for 1st lift at wall W1 Box Culvert Km 204+920 LHS 18-Jul-19 11:12 AM IPC-05 DONE
2665 NMSCEW/P-IV/STR/2019/2607 2607 Checking and concrete pouring for 1st lift at wall W1 Box Culvert Km 204+920 LHS 18-Jul-19 11:36 AM IPC-05 DONE AE
2666 NMSCEW/P-IV/STR/2019/2608 2608 Checking for layout & level for PCC of U type retaining wall PUP Km 204+470 BHS 18-Jul-19 8:00 AM DONE
2667 NMSCEW/P-IV/STR/2019/2609 2609 Checking top Level & Laying concrete for PCC of U type retaining wall PUP Km 204+470 BHS 18-Jul-19 8:30 AM DONE
2668 NMSCEW/P-IV/STR/2019/2610 2610 Checking for layout & level for PCC of U type retaining wall PUP Km 205+430 BHS 18-Jul-19 2:02 PM DONE
2669 NMSCEW/P-IV/STR/2019/2611 2611 Checking top Level & Laying concrete for PCC of U type retaining wall PUP Km 205+430 BHS 18-Jul-19 2:31 PM DONE
2670 NMSCEW/P-IV/STR/2019/2612 2612 Checking layout ,level and structural excavation Box culvert Km 178+730 BHS 18-Jul-19 9:11 AM IPC-08 DONE
2671 NMSCEW/P-IV/STR/2019/2613 2613 Checking top Level & Laying concrete(M-10) PCC Box culvert Km 178+730 BHS 18-Jul-19 2:09 PM IPC-08 DONE
Checking reinforcement for precast Box Culvert (3x3)(cushion 2 to 4m) at precast yard camp
2672 NMSCEW/P-IV/STR/2019/2614 2614 Box culvert Km 175+500 LHS 18-Jul-19 9:36 AM IPC-08 DONE AE 99, 100 ,101
-1. Segment
Checking for NO-99,100,101
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2673 NMSCEW/P-IV/STR/2019/2615 2615 Box culvert Km 175+500 LHS 18-Jul-19 10:26 AM IPC-08 DONE AE 88, 98, 99
(3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-88,98,99,100,101
2674 NMSCEW/P-IV/STR/2019/2616 2616 Checking reinforcement for precast Box Culvert (2x2) (Cushion 2 to 4m) at precast yard cam Box culvert Km 176+250 BHS 18-Jul-19 12:36 PM IPC-05 DONE
2675 NMSCEW/P-IV/STR/2019/2617 2617 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2×2 Box culvert Km 176+250 BHS 18-Jul-19 4:27 PM IPC-05 DONE
2676 NMSCEW/P-IV/STR/2019/2618 2618 Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard cam Box culvert Km 179+390 BHS 18-Jul-19 12:50 PM IPC-05 DONE
2677 NMSCEW/P-IV/STR/2019/2619 2619 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2×2 Box culvert Km 179+390 BHS 18-Jul-19 5:39 PM IPC-05 DONE
2678 NMSCEW/P-IV/STR/2019/2620 2620 Checking reinforcement ,shuttering for Top Hanch & Top Slab PUP Km 183+290 LHS 18-Jul-19 2:00 AM REPEATED
2679 NMSCEW/P-IV/STR/2019/2621 2621 Checking and concrete pouring for Top Hanch & Top Slab PUP Km 183+290 LHS 18-Jul-19 3:30 AM DONE
2680 NMSCEW/P-IV/STR/2019/2622 2622 Checking for layout & level for Minor Bridge MNBR Km 193+135 BHS 18-Jul-19 12:00 PM DONE
2681 NMSCEW/P-IV/STR/2019/2623 2623 Checking top Level & Laying concrete PCC for Minor Bridge MNBR Km 193+135 BHS 18-Jul-19 1:00 AM
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
2682 NMSCEW/P-IV/STR/2019/2624 2624 Box culvert Km 200+200 LHS 19-Jul-19 9:36 AM DONE
-2 Segment
Checking forNO-172,173
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2683 NMSCEW/P-IV/STR/2019/2625 2625 Box culvert Km 200+200 LHS 19-Jul-19 9:50 AM DONE
(2×2) (Cushion
Checking 2 to 4m) for
reinforcement at precast
precastyard
Boxcamp-2,Segment no.-172,173
Culvert (3x3)(cushion 0 to 2m) at precast yard camp
2684 NMSCEW/P-IV/STR/2019/2626 2626 Box culvert Km 200+200 LHS 19-Jul-19 10:00 AM DONE
-2 Segment NO-82,83,84
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2685 NMSCEW/P-IV/STR/2019/2627 2627 Box culvert Km 200+200 LHS 19-Jul-19 10:10 AM DONE
(3×3) (Cushion
Checking 0 to 2m) for
reinforcement at precast
precastyard
Boxcamp-2,Segment no.-82,83,84
Culvert (3x3)(cushion 2 to 4m) at precast yard camp
2686 NMSCEW/P-IV/STR/2019/2628 2628 Box culvert Km 200+200 LHS 19-Jul-19 10:20 AM DONE
-2 Segment
Checking forNO-22
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2687 NMSCEW/P-IV/STR/2019/2629 2629 Box culvert Km 200+200 LHS 19-Jul-19 10:30 AM DONE
(3×3) (Cushion 2 to 4m) at precast yard camp-2,Segment no.-22
2688 NMSCEW/P-IV/STR/2019/2630 2630 Checking for layout and level for top Slab PUP Km 203+560 LHS 19-Jul-19 2:00 PM IPC-05 DONE
2689 NMSCEW/P-IV/STR/2019/2631 2631 Checking reinforcement ,shuttering and Concrete Pouring for top Slab PUP Km 203+560 LHS 19-Jul-19 3:00 PM IPC-05 DONE
2690 NMSCEW/P-IV/STR/2019/2632 2632 checking for reinforcement and shuttering for bottom slab & haunch of Box Culvert Box culvert Km 182+350 LHS 19-Jul-19 12:30 PM IPC-08 DONE
2691 NMSCEW/P-IV/STR/2019/2633 2633 Checking top Level & Pouring M30 concrete for bottom slab & haunch of Box Culvert Box culvert Km 182+350 LHS 19-Jul-19 12:40 PM IPC-08 DONE
2692 NMSCEW/P-IV/STR/2019/2634 2634 checking for reinforcement and shuttering for bottom slab of Box Culvert Box culvert Km 186+352 LHS 19-Jul-19 3:00 PM NR
2693 NMSCEW/P-IV/STR/2019/2635 2635 Checking top Level & Pouring M30 concrete for bottom slab of Box Culvert Box culvert Km 186+352 LHS 19-Jul-19 3:10 PM NR
2694 NMSCEW/P-IV/STR/2019/2636 2636 Checking for layout and level for top Slab Box culvert Km 200+460 LHS 19-Jul-19 2:00 PM IPC-05 DONE
2695 NMSCEW/P-IV/STR/2019/2637 2637 Checking reinforcement ,shuttering and Concrete Pouring for top Slab Box culvert Km 200+460 LHS 19-Jul-19 3:00 PM IPC-05 DONE
2696 NMSCEW/P-IV/STR/2019/2638 2638 Checking layout ,level and structural excavation for utilty duct (2x2) Utility duct Km 178+540 BHS 19-Jul-19 11:00 AM IPC-08 DONE
2697 NMSCEW/P-IV/STR/2019/2639 2639 Checking top Level & Laying concrete PCC (M-10) at Utility duct (2X2) Utility duct Km 178+540 BHS 19-Jul-19 4:00 PM IPC-08 DONE
2698 NMSCEW/P-IV/STR/2019/2640 2640 Checking for layout and structural excavation at A1 & A2 for retaining wall Retaining wall Km 171+110 BHS 19-Jul-19 11:00 AM DONE
2699 NMSCEW/P-IV/STR/2019/2641 2641 Checking top Level & Laying concrete PCC (M-10) at A1 & A2 for retaining wall Retaining wall Km 171+110 BHS 19-Jul-19 11:30 AM DONE
2700 NMSCEW/P-IV/STR/2019/2642 2642 checking for reinforcement and shuttering for bottom slab of Box Culvert Box culvert Km 182+350 LHS 19-Jul-19 12:30 PM REPEATED
2701 NMSCEW/P-IV/STR/2019/2643 2643 Checking top Level & Pouring M30 concrete for bottom slab of Box Culvert Box culvert Km 182+350 LHS 19-Jul-19 12:40 PM REPEATED
2702 NMSCEW/P-IV/STR/2019/2644 2644 Checkingof level & layout for top Slab Box culvert Km 203+886 RHS 19-Jul-19 3:00 PM IPC-05 DONE
2703 NMSCEW/P-IV/STR/2019/2645 2645 Checking of reinforcement and shuttering and Pouring for top slab Box culvert Km 203+886 RHS 19-Jul-19 3:10 PM IPC-05 DONE
Checking reinforcement for precast Box Culvert (3x3)(cushion 2 to 4m) at precast yard camp
2704 NMSCEW/P-IV/STR/2019/2646 2646 Box culvert Km 175+500 LHS 19-Jul-19 10:20 AM IPC-08 DONE 102, 103, 104, 105, 106
-1 Segment
Checking NO-102,103,104,105,106
reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
2705 NMSCEW/P-IV/STR/2019/2647 2647 Box culvert Km 175+500 LHS 19-Jul-19 10:30 AM DONE
-1 Segment
Checking NO-92,93,94for precast Box Culvert (2x2)(cushion 0 to 2m) at precast yard camp
reinforcement
2706 NMSCEW/P-IV/STR/2019/2648 2648 Box culvert Km 175+500 LHS 19-Jul-19 10:40 AM IPC-08 DONE 111, 112, 113, 114
-1 Segment
Checking forNO-111,112,113,114
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2707 NMSCEW/P-IV/STR/2019/2649 2649 Box culvert Km 175+500 LHS 19-Jul-19 10:50 AM IPC-08 DONE 102, 103, 104, 105, 106
(3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-102,103,104,105,106
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2708 NMSCEW/P-IV/STR/2019/2650 2650 Box culvert Km 175+500 LHS 19-Jul-19 11:00 AM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-92,93,94
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2709 NMSCEW/P-IV/STR/2019/2651 2651 Box culvert Km 175+500 LHS 19-Jul-19 11:20 AM IPC-08 DONE AE 111, 112, 113, 114
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-111,112,113,114
2710 NMSCEW/P-IV/STR/2019/2654 2654 Checking of reinforcement & shuttering for side wall A1 & A2 2nd lift PUP Km 190+650 RHS 19-Jul-19 4:00 PM NR
2711 NMSCEW/P-IV/STR/2019/2655 2655 Checking and pouring concrete for side wall A1 & A2 2nd lift PUP Km 190+650 RHS 19-Jul-19 4:40 PM NR
2712 NMSCEW/P-IV/STR/2019/2656 2656 Checking of reinforcement and shuttering & top level for raft at LP1 Viaduct Km 196+560 LHS 19-Jul-19 10:00 AM IPC-05 DONE AE
2713 NMSCEW/P-IV/STR/2019/2657 2657 Checking and Pouring of concrete for raft at LP1 (M-35) Viaduct Km 196+560 LHS 19-Jul-19 10:30 AM IPC-05 DONE AE
2714 NMSCEW/P-IV/STR/2019/2658 2658 Checking of reinforcement and shuttering of starter of LP-06 Viaduct Km 195+900 LHS 19-Jul-19 3:00 PM IPC-14
2715 NMSCEW/P-IV/STR/2019/2659 2659 Checking and Pouring of concrete of starter at LP-06 Viaduct Km 195+900 LHS 19-Jul-19 3:30 PM IPC-14
2716 NMSCEW/P-IV/STR/2019/2660 2660 Checking of reinforcement and shuttering for pier shaft 1st lift at LP-4 VIADUCT Km 202+190 LHS 19-Jul-19 9:00 AM IPC-08 DONE
2717 NMSCEW/P-IV/STR/2019/2661 2661 Checking top level & Laying concrete for LP-4 pier shaft 1st lift VIADUCT Km 202+190 LHS 19-Jul-19 9:30 AM IPC-08 DONE
2718 NMSCEW/P-IV/STR/2019/2662 2662 Checking of reinforcement and shuttering for pier shaft 1st lift at LP-5 VIADUCT Km 202+190 LHS 19-Jul-19 11:00 AM
2719 NMSCEW/P-IV/STR/2019/2663 2663 Checking top level & Laying concrete for LP-5 pier shaft 1st lift VIADUCT Km 202+190 LHS 19-Jul-19 12:00 PM
2720 NMSCEW/P-IV/STR/2019/2664 2664 Checking of reinforcement and shuttering for raft at Lp-10 VIADUCT Km 202+190 LHS 19-Jul-19 3:00 PM IPC-08 DONE
2721 NMSCEW/P-IV/STR/2019/2665 2665 Checking top level & Laying concrete raft at Lp-10 VIADUCT Km 202+190 LHS 19-Jul-19 4:00 PM IPC-08 DONE
2722 NMSCEW/P-IV/STR/2019/2666 2666 Checking of reinforcement and shuttering for pier shaft 1st lift at RP-1 VIADUCT Km 169+800 Km 00+000 RHS 19-Jul-19 2:00 PM IPC-09 DONE
2723 NMSCEW/P-IV/STR/2019/2667 2667 Checking top level & Laying concrete for pier shaft 1st lift at RP-1 VIADUCT Km 169+800 Km 00+000 RHS 19-Jul-19 2:30 PM IPC-09 DONE
2724 NMSCEW/P-IV/STR/2019/2668 2668 Checking of reinforcement and shuttering for pier shaft 1st lift at LP-1 VIADUCT Km 169+800 Km 00+000 LHS 19-Jul-19 3:00 PM IPC-09 DONE
2725 NMSCEW/P-IV/STR/2019/2669 2669 Checking top level & Laying concrete for pier shaft 1st lift at LP-1 VIADUCT Km 169+800 Km 00+000 LHS 19-Jul-19 4:00 PM IPC-09 DONE
2726 NMSCEW/P-IV/STR/2019/2670 2670 Checking of reinforcement and shuttering for bottom slab & haunch. VUP Km 179+983 RHS 19-Jul-19 4:00 PM IPC-08 DONE
2727 NMSCEW/P-IV/STR/2019/2671 2671 Checking top level & Laying concrete for Bottom Slab & haunch VUP Km 179+983 RHS 19-Jul-19 5:30 PM IPC-08 DONE
2728 NMSCEW/P-IV/STR/2019/2652 2652 Checking reinforcement ,shuttering for Side wall A1 & A2 2nd lift PUP Km 189+000 LHS 20-Jul-19 10:40 AM IPC-05 DONE AE
2729 NMSCEW/P-IV/STR/2019/2653 2653 Checking and concrete (M30) pouring for Side wall A1 & A2 2nd lift PUP Km 189+000 LHS 20-Jul-19 10:56 AM IPC-05 DONE AE
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
2730 NMSCEW/P-IV/STR/2019/2672 2672 Box culvert Km 200+200 LHS 20-Jul-19 9:20 AM DONE
-2 Segment
Checking forNO-174,175
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2731 NMSCEW/P-IV/STR/2019/2673 2673 Box culvert Km 200+200 LHS 20-Jul-19 9:55 AM DONE
(2×2) (Cushion
Checking 2 to 4m) for
reinforcement at precast
precastyard
Boxcamp-2,Segment no.-174,175
Culvert (3x3)(cushion 0 to 2m) at precast yard camp
2732 NMSCEW/P-IV/STR/2019/2674 2674 Box culvert Km 200+200 LHS 20-Jul-19 10:15 AM DONE
-2 Segment
Checking forNO-85,86
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2733 NMSCEW/P-IV/STR/2019/2675 2675 Box culvert Km 200+200 LHS 20-Jul-19 10:32 AM DONE
(3×3) (Cushion
Checking 0 to 2m) for
reinforcement at precast
precastyard
Boxcamp-2,Segment no.-85,86
Culvert (2x2)(cushion 2 to 4m) at precast yard camp
2734 NMSCEW/P-IV/STR/2019/2676 2676 Box culvert Km 200+200 20-Jul-19 12:00 AM DONE
-2 Segment NO-176,177,178,179,180,181,182
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
2735 NMSCEW/P-IV/STR/2019/2677 2677 Box culvert Km 200+200 LHS 20-Jul-19 10:20 AM DONE
-2 Segment NO-176,177,178,179,180,181,182
2736 NMSCEW/P-IV/STR/2019/2678 2678 Checking of reinforcement and shuttering for Top Slab PUP Km 191+740 LHS 20-Jul-19 3:00 PM IPC-05 DONE AE
2737 NMSCEW/P-IV/STR/2019/2679 2679 Checking top level & Laying concrete for Top Slab PUP Km 191+740 LHS 20-Jul-19 4:00 PM IPC-05 DONE AE
2738 NMSCEW/P-IV/STR/2019/2680 2680 Checking layout ,level and structural excavation at Utility duct Utility duct Km 176+250 BHS 19-Jul-19 12:00 PM IPC-05 DONE
2739 NMSCEW/P-IV/STR/2019/2681 2681 Checking top Level & Laying concrete(M-10) PCC at Utility duct Utility duct Km 176+250 BHS 20-Jul-19 12:15 PM NR
2740 NMSCEW/P-IV/STR/2019/2682 2682 Checking reinforcement ,shuttering for Side wall A1 & A2 2nd lift PUP Km 189+000 LHS 20-Jul-19 10:40 AM NR
2741 NMSCEW/P-IV/STR/2019/2683 2683 Checking and concrete (M30) pouring for Side wall A1 & A2 2nd lift PUP Km 189+000 LHS 20-Jul-19 10:56 AM NR
2742 NMSCEW/P-IV/STR/2019/2684 2684 Checking reinforcement ,shuttering for Side wall A1 & A2 2nd lift PUP Km 190+650 RHS 20-Jul-19 2:30 PM NR
2743 NMSCEW/P-IV/STR/2019/2685 2685 Checking and concrete (M30) pouring for Side wall A1 & A2 2nd lift PUP Km 190+650 RHS 20-Jul-19 3:40 PM NR
Checking reinforcement for precast Box Culvert (3x3)(cushion 2 to 4m) at precast yard camp
2744 NMSCEW/P-IV/STR/2019/2686 2686 Box culvert Km 175+500 LHS 20-Jul-19 4:20 PM IPC-08 DONE AE 107, 108, 109
-1. Segment
Checking for NO-107,108,109
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2745 NMSCEW/P-IV/STR/2019/2687 2687 Box culvert Km 175+500 LHS 20-Jul-19 4:36 PM IPC-08 DONE AE100, 101, 107, 108, 109
(3×3) (Cushion
Checking 2 to 4m)&atPouring
for shuttering precast yard camp-1,Segment
of Concreting no.-100,101,107,108,109
Grade =(M-30) for Precast Box Culvert
2746 NMSCEW/P-IV/STR/2019/2688 2688 Box culvert Km 175+500 LHS 20-Jul-19 4:50 PM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-81,82,85
2747 NMSCEW/P-IV/STR/2019/2689 2689 Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard cam Box culvert Km 179+390 BHS 20-Jul-19 5:20 PM IPC-05 DONE
2748 NMSCEW/P-IV/STR/2019/2690 2690 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2×2 Box culvert Km 179+390 BHS 20-Jul-19 5:32 PM IPC-05 DONE
2749 NMSCEW/P-IV/STR/2019/2691 2691 Checking reinforcement ,shuttering for Box Culvert Box culvert Km 186+352 LHS 20-Jul-19 3:06 PM IPC-05 DONE
2750 NMSCEW/P-IV/STR/2019/2692 2692 Checking and concrete (M30) pouring for Box Culvert Box culvert Km 186+352 LHS 20-Jul-19 3:26 PM IPC-05 DONE
2751 NMSCEW/P-IV/STR/2019/2693 2693 Checking of reinforcement, shuttering for pier shaft 1st lift at LP5 Viaduct Km 202+190 LHS 20-Jul-19 9:00 AM IPC-08 DONE
2752 NMSCEW/P-IV/STR/2019/2694 2694 Checking and Pouring concrete for pier shaft 1st lift at LP5 Viaduct Km 202+190 LHS 20-Jul-19 10:00 AM IPC-08 DONE
2753 NMSCEW/P-IV/STR/2019/2695 2695 Checking reinforcement ,shuttering for wall first lift A1 & A2 Box Culvert Box culvert Km 186+352 RHS 20-Jul-19 2:00 PM IPC-05 DONE
2754 NMSCEW/P-IV/STR/2019/2696 2696 Checking and pourimg for wall first lift A1 & A2 Box Culvert Box culvert Km 186+352 RHS 20-Jul-19 2:30 PM IPC-05 DONE
2755 NMSCEW/P-IV/STR/2019/2697 2697 Checking reinforcement ,shuttering for LVUP side wall A1 & A2 1st lift LVUP Km 178+323 RHS 21-Jul-19 4:00 PM IPC-08 DONE
2756 NMSCEW/P-IV/STR/2019/2698 2698 Checking and concrete pouring for LVUP side wall A1 & A2 1st lift LVUP Km 178+323 RHS 21-Jul-19 4:10 PM IPC-08 DONE
2757 NMSCEW/P-IV/STR/2019/2699 2699 Checking layout ,level and structural excavation for retaining wall at A-2 PUP Km 171+110 BHS 21-Jul-19 12:30 PM NR
2758 NMSCEW/P-IV/STR/2019/2700 2700 Checking top Level & Laying concrete PCC for retaining wall at A-2 PUP Km 171+110 BHS 21-Jul-19 12:40 PM DONE
2759 NMSCEW/P-IV/STR/2019/2701 2701 Checking reinforcement ,shuttering for PUP side wall A1 & A2 2nd lift PUP Km 189+000 LHS 21-Jul-19 10:30 AM NR
2760 NMSCEW/P-IV/STR/2019/2702 2702 Checking and concrete pouring (M-30) for PUP side wall A1 & A2 2nd lift PUP Km 189+000 LHS 21-Jul-19 11:00 AM NR
2761 NMSCEW/P-IV/STR/2019/2703 2703 Checking reinforcement ,shuttering for PUP side wall A1 & A2 2nd lift PUP Km 190+650 RHS 21-Jul-19 2:30 PM NR
2762 NMSCEW/P-IV/STR/2019/2704 2704 Checking and concrete pouring (M-30) for PUP side wall A1 & A2 2nd lift PUP Km 190+650 RHS 21-Jul-19 2:40 AM NR
2763 NMSCEW/P-IV/STR/2019/2705 2705 Checking reinforcement ,shuttering of RP-2 pier shaft 1st lift Viaduct Km 169+800 RHS 21-Jul-19 9:00 AM NR
2764 NMSCEW/P-IV/STR/2019/2706 2706 Checking and concrete pouring of RP-2 pier shaft 1st lift Viaduct Km 169+800 RHS 21-Jul-19 10:00 AM NR
2765 NMSCEW/P-IV/STR/2019/2707 2707 Checking reinforcement ,shuttering of top level of raft at LP-2 Viaduct Km 196+560 RHS 21-Jul-19 10:00 AM IPC-05 DONE AE
2766 NMSCEW/P-IV/STR/2019/2708 2708 Checking and concrete pouring (M-35) of raft at LP-2 Viaduct Km 196+560 RHS 21-Jul-19 10:30 AM IPC-05 DONE
2767 NMSCEW/P-IV/STR/2019/2709 2709 Checking of line,level and layout of bed-4 for casting yard Km 200+200 LHS 21-Jul-19 10:00 AM
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
2768 NMSCEW/P-IV/STR/2019/2710 2710 Box culvert Km 200+200 LHS 22-Jul-19 8:00 AM DONE
-2 Segment
Checking NO-183,184,185,186,187,188,189
reinforcement for precast Box Culvert (3x3)(cushion 0 to 2m) at precast yard camp
2769 NMSCEW/P-IV/STR/2019/2711 2711 Box culvert Km 200+200 LHS 22-Jul-19 9:00 AM DONE
-2 Segment
Checking forNO-87,88
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2770 NMSCEW/P-IV/STR/2019/2712 2712 Box culvert Km 200+200 LHS 22-Jul-19 11:55 AM DONE
(3×3) (Cushion 0 to 2m) for
Checking reinforcement at precast
precastyard
Boxcamp-2,Segment no.-87,88
Culvert (3x3)(cushion 2 to 4m) at precast yard camp
2771 NMSCEW/P-IV/STR/2019/2713 2713 Box culvert Km 200+200 LHS 22-Jul-19 9:35 AM DONE
-2 Segment
Checking forNO-23
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2772 NMSCEW/P-IV/STR/2019/2714 2714 Box culvert Km 200+200 LHS 22-Jul-19 1:30 PM DONE
(2x2) (Cushion
Checking 2 to 4m)&
for shuttering at Pouring
precast yard camp-2,Segment
of Concreting no.-183,184,185,186,187,188,189
Grade =(M-30) for Precast Box Culvert
2773 NMSCEW/P-IV/STR/2019/2715 2715 Box culvert Km 200+200 LHS 22-Jul-19 2:00 PM DONE
(3x3) (Cushion 2 to 4m) at precast yard camp-2,Segment no.-23
2774 NMSCEW/P-IV/STR/2019/2716 2716 Checking layout ,level and structural excavation at Utility duct Utility duct Km 208+560 Km 00+000 BHS 22-Jul-19 3:00 PM IPC-11 Approved
2775 NMSCEW/P-IV/STR/2019/2717 2717 Checking top Level & Laying concrete(M-10) PCC at Utility duct Utility duct Km 208+560 Km 00+000 BHS 22-Jul-19 3:30 PM IPC-11 Approved
2776 NMSCEW/P-IV/STR/2019/2718 2718 Checking layout ,level and structural excavation at Utility duct Utility duct Km 204+700 BHS 23-Jul-19 11:00 AM IPC-08 DONE
2777 NMSCEW/P-IV/STR/2019/2719 2719 Checking top Level & Laying concrete(M-10) PCC at Utility duct Utility duct Km 204+700 BHS 23-Jul-19 12:00 PM IPC-08 DONE
2778 NMSCEW/P-IV/STR/2019/6815 6815 Checking layout ,level and structural excavation at Utility duct Utility duct Km 198+770 BHS 23-Jul-19 11:00 AM IPC-08 DONE
2779 NMSCEW/P-IV/STR/2019/6816 6816 Checking top Level & Laying concrete(M-10) PCC at Utility duct Utility duct Km 198+770 BHS 23-Jul-19 12:00 PM IPC-08 DONE
Checking reinforcement for precast Box Culvert (3x3)(cushion 2 to 4m) at precast yard camp
2780 NMSCEW/P-IV/STR/2019/2720 2720 Box culvert Km 175+500 LHS 22-Jul-19 9:00 AM DONE
-1 Segment NO-110,111,112,113,114
2781 NMSCEW/P-IV/STR/2019/2721 2721 Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp Box culvert Km 176+250 BHS 22-Jul-19 9:10 AM IPC-05 DONE
2782 NMSCEW/P-IV/STR/2019/2722 2722 Checking reinforcement for precast Box Culvert (2x2)(cushion 0 to 2m) at precast yard cam Box culvert Km 179+390 BHS 22-Jul-19 9:20 AM IPC-05 DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2783 NMSCEW/P-IV/STR/2019/2723 2723 Box culvert Km 175+500 LHS 22-Jul-19 9:30 AM DONE
(3x3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-110,111,112,113,114
2784 NMSCEW/P-IV/STR/2019/2724 2724 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2x2 Box culvert Km 176+250 BHS 22-Jul-19 9:40 AM IPC-05 DONE
2785 NMSCEW/P-IV/STR/2019/2725 2725 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2x2 Box culvert Km 179+390 BHS 22-Jul-19 9:50 AM IPC-05 DONE
2786 NMSCEW/P-IV/STR/2019/2726 2726 Checking layout,level & structural excavation at A1 & A2 for retaining wall for PUP PUP Km 172+190 BHS 22-Jul-19 10:10 AM DONE
2787 NMSCEW/P-IV/STR/2019/2727 2727 Checking reinforcement ,shuttering for wall first lift A1 & A2 Box Culvert Box culvert Km 186+352 LHS 22-Jul-19 10:20 AM IPC-05 DONE
2788 NMSCEW/P-IV/STR/2019/2728 2728 checking for reinforcement & shuttering of bottom haunch at A1 &A2 for VUP VUP Km 179+983 RHS 22-Jul-19 4:00 PM NR
2789 NMSCEW/P-IV/STR/2019/2729 2729 Checking top Level & Laying concrete(M-35) RCC A1 & A2 for retaining wall for PUP VUP Km 179+983 RHS 22-Jul-19 4:10 PM NR
2790 NMSCEW/P-IV/STR/2019/2730 2730 Checking and pourimg for wall first lift A1 & A2 Box Culvert Box culvert Km 186+352 LHS 22-Jul-19 5:20 PM IPC-05 DONE
2791 NMSCEW/P-IV/STR/2019/2731 2731 Checking top Level & Laying concrete PCC (M-10) at Utility duct (2X2) Utility duct Km 176+250 BHS 22-Jul-19 5:40 PM IPC-05 DONE
2792 NMSCEW/P-IV/STR/2019/2732 2732 Checking for layout & level for PCC at LA1 Viaduct Km 195+900 LHS 22-Jul-19 1:20 PM
2793 NMSCEW/P-IV/STR/2019/2733 2733 Checking top Level & Laying concrete PCC at LA1 Viaduct Km 195+900 LHS 22-Jul-19 1:35 PM
2794 NMSCEW/P-IV/STR/2019/2734 2734 Checking of reinforcement, shuttering of LP-9 for raft Viaduct Km 202+190 LHS 22-Jul-19 1:55 PM IPC-08 DONE AE
2795 NMSCEW/P-IV/STR/2019/2735 2735 Checking and Pouring concrete of LP-9 for raft Viaduct Km 202+190 LHS 22-Jul-19 2:15 PM IPC-08 DONE AE
2796 NMSCEW/P-IV/STR/2019/2736 2736 Checking of reinforcement, shuttering of LP-6 for pier starter Viaduct Km 202+190 LHS 22-Jul-19 4:15 PM
2797 NMSCEW/P-IV/STR/2019/2737 2737 Checking and Pouring concrete of LP-6 for pier starter Viaduct Km 202+190 LHS 22-Jul-19 4:35 PM
2798 NMSCEW/P-IV/STR/2019/2738 2738 Checking of reinforcement, shuttering for pier shaft 1st lift at RP2 Viaduct Km 169+800 Km 00+000 RHS 22-Jul-19 9:15 AM IPC-09 DONE
2799 NMSCEW/P-IV/STR/2019/2739 2739 Checking and Pouring concrete for pier shaft 1st lift at RP2 Viaduct Km 169+800 Km 00+000 RHS 22-Jul-19 9:22 AM IPC-09 DONE
2800 NMSCEW/P-IV/STR/2019/2740 2740 Checking of reinforcement, shuttering for pier shaft 1st lift at LP4 Viaduct Km 169+800 LHS 22-Jul-19 10:22 AM IPC-08 DONE
2801 NMSCEW/P-IV/STR/2019/2741 2741 Checking and Pouring concrete for pier shaft 1st lift at LP4 Viaduct Km 169+800 LHS 22-Jul-19 4:12 PM IPC-08 DONE
2802 NMSCEW/P-IV/STR/2019/2742 2742 Checking of reinforcement, shuttering & top level of raft at LP-2 Viaduct Km 196+560 LHS 22-Jul-19 8:45 AM
2803 NMSCEW/P-IV/STR/2019/2743 2743 Checking and Pouring concrete (M-35) of raft at LP-2 Viaduct Km 196+560 LHS 22-Jul-19 9:00 AM
2804 NMSCEW/P-IV/STR/2019/2744 2744 Checking of reinforcement, shuttering of W2 1st lift at box culvert Box culvert Km 200+460 LHS 22-Jul-19 11:45 AM
2805 NMSCEW/P-IV/STR/2019/2745 2745 Checking and Pouring concrete of W2 1st lift at box culvert Box culvert Km 200+460 LHS 22-Jul-19 2:00 PM
2806 NMSCEW/P-IV/STR/2019/2746 2746 Checking reinforcement ,shuttering for Side wall A1 & A2 2nd lift PUP Km 189+000 LHS 22-Jul-19 11:58 AM REPEATED
2807 NMSCEW/P-IV/STR/2019/2747 2747 Checking and concrete (M30) pouring for Side wall A1 & A2 2nd lift PUP Km 189+000 LHS 22-Jul-19 2:35 PM REPEATED
2808 NMSCEW/P-IV/STR/2019/2748 2748 Checking reinforcement ,shuttering for Side wall A1 & A2 2nd lift PUP Km 190+650 RHS 22-Jul-19 2:40 PM IPC-05 DONE
2809 NMSCEW/P-IV/STR/2019/2749 2749 Checking and concrete (M30) pouring for Side wall A1 & A2 2nd lift PUP Km 190+650 RHS 22-Jul-19 3:25 PM IPC-05 DONE
2810 NMSCEW/P-IV/STR/2019/2750 2750 Checking layout ,level and structural excavation at Utility duct Utility duct Km 198+300 BHS 23-Jul-19 11:00 AM IPC-08 DONE
2811 NMSCEW/P-IV/STR/2019/2751 2751 Checking top Level & Laying concrete(M-10) PCC at Utility duct Utility duct Km 198+300 BHS 23-Jul-19 12:00 PM IPC-08 DONE
2812 NMSCEW/P-IV/STR/2019/2752 2752 Checking for layout and level for top Slab Box culvert Km 204+920 LHS 23-Jul-19 3:00 PM IPC-05 DONE
2813 NMSCEW/P-IV/STR/2019/2753 2753 Checking reinforcement ,shuttering and Concrete Pouring for top Slab Box culvert Km 204+920 LHS 23-Jul-19 3:30 PM IPC-05 DONE
2814 NMSCEW/P-IV/STR/2019/2753A 2753A Checking of layout level,Structural Excavation and pouring of concrete for PCC Utility duct Km 207+560 BHS 23-Jul-19 3:30 PM IPC-11 Approved
2815 NMSCEW/P-IV/STR/2019/2754 2754 Checking of reinforcement, shuttering of Wall W2 1st lift at PUP Box culvert Km 199+060 RHS 23-Jul-19 12:00 PM IPC-05 DONE AE
2816 NMSCEW/P-IV/STR/2019/2755 2755 Checking and Pouring concrete of W2 1st lift at PUP Box culvert Km 199+060 RHS 23-Jul-19 2:00 PM IPC-05 DONE AE
2817 NMSCEW/P-IV/STR/2019/2756 2756 Checking of reinforcement, shuttering of side wall A1&A2 2nd Lift at VUP VUP Km 176+614 Km 00+000 RHS 23-Jul-19 4:00 PM IPC-10 DONE
2818 NMSCEW/P-IV/STR/2019/2757 2757 Checking and Pouring concrete (M-35) of side wall A1&A2 2nd Lift at VUP VUP Km 176+614 Km 00+000 RHS 23-Jul-19 4:10 PM IPC-10 DONE
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
2819 NMSCEW/P-IV/STR/2019/2758 2758 Box culvert Km 200+200 LHS 23-Jul-19 8:30 AM DONE
-2 Segment
Checking forNO-190,191,192,193,194
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2820 NMSCEW/P-IV/STR/2019/2759 2759 Box culvert Km 200+200 LHS 23-Jul-19 8:40 AM DONE
(2x2) (Cushion
Checking 2 to 4m) for
reinforcement at precast
precastyard
Boxcamp-2,Segment no.-190,191,192,193,194
Culvert (3x3)(cushion 0 to 2m) at precast yard camp
2821 NMSCEW/P-IV/STR/2019/2760 2760 Box culvert Km 200+200 LHS 23-Jul-19 9:58 AM DONE
-2 Segment
Checking forNO-89,90.
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2822 NMSCEW/P-IV/STR/2019/2761 2761 Box culvert Km 200+200 LHS 23-Jul-19 10:48 AM DONE
(3×3) (Cushion
Checking 0 to 2m) for
reinforcement at precast
precastyard
Boxcamp-2,Segment no.-89,90.
Culvert (3x3)(cushion 2 to 2m) at precast yard camp
2823 NMSCEW/P-IV/STR/2019/2762 2762 Box culvert Km 200+200 LHS 23-Jul-19 2:20 PM DONE
-2 Segment
Checking forNO-24.
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2824 NMSCEW/P-IV/STR/2019/2763 2763 Box culvert Km 200+200 LHS 23-Jul-19 4:26 PM DONE
(3×3) (Cushion 2 to 2m) at precast yard camp-2,Segment no.-24.
2825 NMSCEW/P-IV/STR/2019/2764 2764 Checking layout ,level and structural excavation at Utility duct (2x2) Utility duct Km 177+300 BHS 23-Jul-19 11:30 AM IPC-08 DONE
2826 NMSCEW/P-IV/STR/2019/2765 2765 Checking top Level & Laying concrete(M-10) PCC at Utility duct (2x2) Utility duct Km 177+300 BHS 23-Jul-19 3:16 PM IPC-08 DONE
2827 NMSCEW/P-IV/STR/2019/2766 2766 Checking of reinforcement & shuttering for wall A1&A2 1st Lift at Box Culvert Box culvert Km 186+352 RHS 23-Jul-19 9:09 AM REPEATED
2828 NMSCEW/P-IV/STR/2019/2767 2767 Checking and pouring concrete for wall A1&A2 1st Lift at Box Culvert Box culvert Km 186+352 RHS 23-Jul-19 9:36 AM REPEATED
Checking reinforcement for precast Box Culvert (3x3)(cushion 2 to 4m) at precast yard camp
2829 NMSCEW/P-IV/STR/2019/2768 2768 Box culvert Km 175+500 LHS 23-Jul-19 9:50 AM DONE
-1. Segment
Checking for NO-115,116,117,118,119.
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2830 NMSCEW/P-IV/STR/2019/2769 2769 Box culvert Km 175+500 LHS 23-Jul-19 2:21 PM DONE
(3×3) (Cushion
Checking 2 to 4m)&atPouring
for shuttering precast yard camp-1,Segment
of Concreting no.-115,116,117,118,119.
Grade =(M-30) for Precast Box Culvert
2831 NMSCEW/P-IV/STR/2019/2770 2770 Box culvert Km 175+500 LHS 23-Jul-19 11:22 AM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-99,100,101.
2832 NMSCEW/P-IV/STR/2019/2771 2771 Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard cam Box culvert Km 179+390 BHS 23-Jul-19 12:28 PM IPC-05 DONE AE
2833 NMSCEW/P-IV/STR/2019/2772 2772 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2×2 Box culvert Km 179+390 BHS 23-Jul-19 3:25 PM IPC-05 DONE AE
2834 NMSCEW/P-IV/STR/2019/2773 2773 Checking for Raft Layout & level at box culvert Box culvert Km 203+886 LHS 23-Jul-19 3:35 PM IPC-05 DONE
2835 NMSCEW/P-IV/STR/2019/2774 2774 checking for raft reinforcement and shuttering at box culvert Box culvert Km 203+886 LHS 23-Jul-19 3:45 PM IPC-05 DONE
2836 NMSCEW/P-IV/STR/2019/2775 2775 Checking top Level & Laying raft concrete at box culvert Box culvert Km 203+886 LHS 23-Jul-19 4:16 PM IPC-05 DONE
2837 NMSCEW/P-IV/STR/2019/2776 2776 Checking of reinforcement and shuttering for raft at Lp-4 VIADUCT Km 195+900 LHS 23-Jul-19 10:16 AM IPC-08 DONE AE
2838 NMSCEW/P-IV/STR/2019/2777 2777 Checking top level & Laying concrete raft at Lp-4 VIADUCT Km 195+900 LHS 23-Jul-19 10:52 AM IPC-08 DONE AE
2839 NMSCEW/P-IV/STR/2019/2778 2778 Checking of reinforcement and shuttering for pier shaft 1st lift at LP-2 VIADUCT Km 169+800 Km 00+000 LHS 23-Jul-19 9:32 AM IPC-09 DONE
2840 NMSCEW/P-IV/STR/2019/2779 2779 Checking top level & Laying concrete for pier shaft 1st lift at LP-2 VIADUCT Km 169+800 Km 00+000 LHS 23-Jul-19 10:00 AM IPC-09 DONE
2841 NMSCEW/P-IV/STR/2019/2780 2780 Checking of reinforcement and shuttering for pier shaft 1st lift at LP-6 VIADUCT Km 169+800 LHS 23-Jul-19 11:20 AM IPC-08 DONE
2842 NMSCEW/P-IV/STR/2019/2781 2781 Checking top level & Laying concrete for pier shaft 1st lift at LP-6 VIADUCT Km 169+800 LHS 23-Jul-19 2:20 PM IPC-08 DONE
2843 NMSCEW/P-IV/STR/2019/2782 2782 Checking of reinforcement and shuttering for pier shaft 1st lift & Final lift at RP-7 VIADUCT Km 169+800 LHS 23-Jul-19 3:16 PM IPC-08 DONE
2844 NMSCEW/P-IV/STR/2019/2783 2783 Checking top level & Laying concrete for pier shaft 1st lift & Final lift at RP-7 VIADUCT Km 169+800 LHS 23-Jul-19 4:22 PM IPC-08 DONE
2845 NMSCEW/P-IV/STR/2019/2784 2784 Checking of reinforcement and shuttering for raft at RP-3 VIADUCT Km 196+560 RHS 23-Jul-19 5:22 PM
2846 NMSCEW/P-IV/STR/2019/2785 2785 Checking top level & Laying concrete(M35) raft at RP-3 VIADUCT Km 196+560 RHS 23-Jul-19 6:10 PM
2847 NMSCEW/P-IV/STR/2019/2786 2786 Checking of reinforcement and shuttering for pier shaft Final lift at LP-3 VIADUCT Km 202+190 LHS 23-Jul-19 11:00 AM
2848 NMSCEW/P-IV/STR/2019/2787 2787 Checking top level & Laying concrete for pier shaft Final lift at LP-3 VIADUCT Km 202+190 LHS 23-Jul-19 12:10 PM
2849 NMSCEW/P-IV/STR/2019/2788 2788 Checking of reinforcement and shuttering for pier starter at LP-6 VIADUCT Km 202+190 LHS 23-Jul-19 2:00 PM
2850 NMSCEW/P-IV/STR/2019/2789 2789 Checking top level & Laying concrete for pier starter at LP-6 VIADUCT Km 202+190 LHS 23-Jul-19 3:20 PM
2851 NMSCEW/P-IV/STR/2019/2790 2790 Checking of annular filling at RP-6 Viaduct Km 202+190 RHS 23-Jul-19 3:30 PM
2852 NMSCEW/P-IV/STR/2019/2791 2791 Checking reinforcement ,shuttering for 1st Lift at Wall A1 of CUP PUP Km 187+835 RHS 23-Jul-19 12:55 AM IPC-05 DONE
2853 NMSCEW/P-IV/STR/2019/2792 2792 Checking and concrete (M30) pouring for 1st Lift at Wall A1 & A2 of CUP PUP Km 187+835 RHS 23-Jul-19 1:00 AM IPC-05 DONE
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
2854 NMSCEW/P-IV/STR/2019/2793 2793 Box culvert Km 200+200 LHS 24-Jul-19 9:00 AM DONE
-2 Segment
Checking forNO-195,196,197,198,199,200,201
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2855 NMSCEW/P-IV/STR/2019/2794 2794 Box culvert Km 200+200 LHS 24-Jul-19 9:30 AM DONE
(2x2) (Cushion
Checking 2 to 4m) for
reinforcement at precast
precastyard
Boxcamp-2,Segment no.-195,196,197,198,199,200,201
Culvert (3x3)(cushion 0 to 2m) at precast yard camp
2856 NMSCEW/P-IV/STR/2019/2795 2795 Box culvert Km 200+200 LHS 24-Jul-19 9:40 AM DONE
-2 Segment
Checking forNO-91,92
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2857 NMSCEW/P-IV/STR/2019/2796 2796 Box culvert Km 200+200 LHS 24-Jul-19 9:30 AM DONE
(3x3) (Cushion 0 to 2m) at precast yard camp-2,Segment no.-91,92
2858 NMSCEW/P-IV/STR/2019/2797 2797 Checking reinforcement & shuttering for wall W2 2nd lift at PUP PUP Km 193+880 RHS 24-Jul-19 9:00 AM IPC-05 DONE AE
2859 NMSCEW/P-IV/STR/2019/2798 2798 Checking and concrete pouring for wall W2 2nd lift at PUP PUP Km 193+880 RHS 24-Jul-19 10:00 AM IPC-05 DONE AE
2860 NMSCEW/P-IV/STR/2019/2799 2799 Checking of reinforcement ,shuttering & top level of raft at RP-3 VIADUCT Km 196+560 RHS 24-Jul-19 11:00 AM
2861 NMSCEW/P-IV/STR/2019/2800 2800 Checking top level & Laying concrete for raft at RP-3 VIADUCT Km 196+560 RHS 24-Jul-19 11:30 AM
2862 NMSCEW/P-IV/STR/2019/2801 2801 Checking of reinforcement ,shuttering of final lift wall A1 & A2 PUP Km 165+300 RHS 24-Jul-19 9:00 AM IPC-05 DONE AE
2863 NMSCEW/P-IV/STR/2019/2802 2802 Checking top level & Laying concrete of final lift wall A1 & A2 PUP Km 165+300 RHS 24-Jul-19 9:20 AM IPC-05 DONE AE
2864 NMSCEW/P-IV/STR/2019/2803 2803 Checking of soffit level of top slab PUP Km 165+300 RHS 24-Jul-19 9:30 AM NR
2865 NMSCEW/P-IV/STR/2019/2804 2804 Checking of reinforcement ,shuttering for VUP side wall A1 & A2 1st lift VUP Km 179+983 RHS 24-Jul-19 4:00 PM IPC-08 DONE
2866 NMSCEW/P-IV/STR/2019/2805 2805 Checking top level & Laying concrete for VUP side wall A1 & A2 1st lift VUP Km 179+983 RHS 24-Jul-19 4:10 PM IPC-08 DONE
Checking reinforcement for precast Box Culvert (3x3)(cushion 2 to 4m) at precast yard camp
2867 NMSCEW/P-IV/STR/2019/2806 2806 Box culvert Km 200+200 LHS 24-Jul-19 9:00 AM
-1 Segment NO-120,121,122
2868 NMSCEW/P-IV/STR/2019/2807 2807 Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard cam Box culvert Km 176+250 BHS 24-Jul-19 9:10 AM IPC-05 DONE
2869 NMSCEW/P-IV/STR/2019/2808 2808 Checking reinforcement for precast Box Culvert (2x2)(cushion 0 to 2m) at precast yard cam Box culvert Km 179+390 BHS 24-Jul-19 9:20 AM IPC-05 DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2870 NMSCEW/P-IV/STR/2019/2809 2809 Box culvert Km 200+200 LHS 24-Jul-19 9:30 AM
(3x3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-113,114,120,121,122
2871 NMSCEW/P-IV/STR/2019/2810 2810 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2x2 Box culvert Km 176+250 BHS 24-Jul-19 9:40 AM IPC-05 DONE
2872 NMSCEW/P-IV/STR/2019/2811 2811 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2x2 Box culvert Km 179+390 BHS 24-Jul-19 9:50 AM IPC-05 DONE
2873 NMSCEW/P-IV/STR/2019/2812 2812 Checking of reinforcement ,shuttering for LP-3 pier shaft final lift Viaduct Km 202+190 LHS 24-Jul-19 11:00 AM IPC-08 DONE
2874 NMSCEW/P-IV/STR/2019/2813 2813 Checking top level & Laying concrete for LP-3 pier shaft final lift VIADUCT Km 202+190 LHS 24-Jul-19 12:00 PM IPC-08 DONE
2875 NMSCEW/P-IV/STR/2019/2814 2814 Checking of reinforcement and shuttering for pier starter (150mm) at LP-6 VIADUCT Km 202+190 LHS 24-Jul-19 2:00 PM
2876 NMSCEW/P-IV/STR/2019/2815 2815 Checking top level & Laying concrete for pier starter (150mm) at LP-6 VIADUCT Km 202+190 LHS 24-Jul-19 3:00 PM
2877 NMSCEW/P-IV/STR/2019/2816 2816 Checking of reinforcement ,shuttering for LP-2 pier shaft 1st or final lift Viaduct Km 202+190 LHS 24-Jul-19 4:00 PM IPC-08 DONE
2878 NMSCEW/P-IV/STR/2019/2817 2817 Checking top level & Laying concrete for LP-2 pier shaft 1st or final lift VIADUCT Km 202+190 LHS 24-Jul-19 4:30 PM IPC-08 DONE
2879 NMSCEW/P-IV/STR/2019/2818 2818 Checking top level & Laying concrete for raft at LP-4 (M-35) VIADUCT Km 195+900 RHS 24-Jul-19 11:30 AM
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
2880 NMSCEW/P-IV/STR/2019/2819 2819 Box culvert Km 200+200 LHS 25-Jul-19 8:30 AM DONE
-2 Segment
Checking forNO-201,202,203,204,205,206,207.
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2881 NMSCEW/P-IV/STR/2019/2820 2820 Box culvert Km 200+200 LHS 25-Jul-19 11:40 AM DONE
(2x2) (Cushion
Checking 2 to 4m) for
reinforcement at precast
precastyard
Boxcamp-2,Segment no.-201,202,203,204,205,206,207.
Culvert (3x3)(cushion 2 to 4m) at precast yard camp
2882 NMSCEW/P-IV/STR/2019/2821 2821 Box culvert Km 200+200 LHS 25-Jul-19 10:46 AM DONE
-2 Segment
Checking forNO-25.
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2883 NMSCEW/P-IV/STR/2019/2822 2822 Box culvert Km 200+200 LHS 25-Jul-19 12:58 PM DONE
(3x3) (Cushion 2 to 4m) at precast yard camp-2,Segment no.-25.
2884 NMSCEW/P-IV/STR/2019/2823 2823 Checking reinforcement & shuttering for wall W2 1st lift at box culvert Box culvert Km 204+920 LHS 25-Jul-19 9:30 AM IPC-05 DONE
2885 NMSCEW/P-IV/STR/2019/2824 2824 Checking and concrete pouring for wall W2 1st lift at box culvert Box culvert Km 204+920 LHS 25-Jul-19 10:32 AM IPC-05 DONE
2886 NMSCEW/P-IV/STR/2019/2825 2825 Checking layout & level for Box Culvert Box culvert Km 193+940 BHS 25-Jul-19 11:00 AM DONE
2887 NMSCEW/P-IV/STR/2019/2826 2826 Checking top Level & Laying concrete(M-10) PCC for Box Culvert Box culvert Km 193+940 BHS 25-Jul-19 12:00 PM DONE
2888 NMSCEW/P-IV/STR/2019/2827 2827 Checking reinforcement and shuttering wall final wall with top slab and top haunch A1 & A2 Box culvert Km 186+352 RHS 25-Jul-19 2:10 PM IPC-05 DONE
2889 NMSCEW/P-IV/STR/2019/2828 2828 Checking and pourimg for wall final wall with top slab and top haunch A1 & A2 Box Culvert Box culvert Km 186+352 RHS 25-Jul-19 3:22 PM IPC-05 DONE
Checking reinforcement for precast Box Culvert (3x3)(cushion 0 to 2m) at precast yard camp
2890 NMSCEW/P-IV/STR/2019/2829 2829 Box culvert Km 200+200 LHS 25-Jul-19 12:22 PM DONE
-2 Segment
Checking forNO-92,93,94.
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2891 NMSCEW/P-IV/STR/2019/2830 2830 Box culvert Km 200+200 LHS 25-Jul-19 2:02 PM DONE
(3x3) (Cushion 0 to 2m) at precast yard camp-2,Segment no.-92,93,94.
2892 NMSCEW/P-IV/STR/2019/2831 2831 Checking of annular filling at LP-6 Viaduct Km 202+190 LHS 25-Jul-19 9:02 AM
2893 NMSCEW/P-IV/STR/2019/2832 2832 Checking and concrete of annular filling at LP-6 Viaduct Km 202+190 LHS 25-Jul-19 10:08 AM
2894 NMSCEW/P-IV/STR/2019/2833 2833 Checking of reinforcement ,shuttering & top level of raft at RP-3 Viaduct Km 196+560 RHS 25-Jul-19 10:30 AM IPC-05 DONE AE
2895 NMSCEW/P-IV/STR/2019/2834 2834 Checking and Pouring concrete(M35) for raft RP3 Viaduct Km 196+560 RHS 25-Jul-19 11:42 AM IPC-05 DONE AE
2896 NMSCEW/P-IV/STR/2019/2835 2835 Checking of reinforcement ,shuttering of Side Wall A1 & A2 2nd Lift at PUP PUP Km 187+850 RHS 25-Jul-19 12:40 PM NR
2897 NMSCEW/P-IV/STR/2019/2836 2836 Checking and Pouring concrete(M30) of Side Wall A1 & A2 2nd Lift at PUP PUP Km 187+850 RHS 25-Jul-19 2:20 PM NR
2898 NMSCEW/P-IV/STR/2019/2837 2837 Checking layout ,level and structural excavation of Retaining wall A1 & A2 Retaining wall Km 172+190 BHS 25-Jul-19 2:30 PM NR
2899 NMSCEW/P-IV/STR/2019/2838 2838 Checking of reinforcement, shuttering for final lift, top slab and top hauch A1 & A2 at PUP PUP Km 187+835 LHS 25-Jul-19 2:52 PM IPC-05 DONE
2900 NMSCEW/P-IV/STR/2019/2839 2839 Checking top level & Laying concrete (M-30) for final lift, top slab & top hauch A1 & A2 a PUP Km 187+835 LHS 25-Jul-19 3:12 PM IPC-05 DONE
2901 NMSCEW/P-IV/STR/2019/2840 2840 Checking top Level & Laying concrete(M-10) PCC of Retaining wall A1 & A2 Retaining wall Km 174+095 BHS 25-Jul-19 3:56 PM NR
Checking reinforcement for precast Box Culvert (3x3)(cushion 2 to 4m) at precast yard camp
2902 NMSCEW/P-IV/STR/2019/2841 2841 Box culvert Km 175+500 LHS 25-Jul-19 8:16 AM DONE
-1 Segment NO.-123,124,125,126.
2903 NMSCEW/P-IV/STR/2019/2842 2842 Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard cam Box culvert Km 176+250 BHS 25-Jul-19 9:20 AM IPC-05 DONE
2904 NMSCEW/P-IV/STR/2019/2843 2843 Checking reinforcement for precast Box Culvert (2x2)(cushion 0 to 2m) at precast yard camp Box culvert Km 179+390 BHS 25-Jul-19 11:20 AM IPC-05 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2905 NMSCEW/P-IV/STR/2019/2844 2844 Box culvert Km 175+500 LHS 25-Jul-19 10:10 AM DONE
(3x3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-119,123,124,125,126.
2906 NMSCEW/P-IV/STR/2019/2845 2845 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2x2 Box culvert Km 176+250 BHS 25-Jul-19 11:52 AM IPC-05 DONE
2907 NMSCEW/P-IV/STR/2019/2846 2846 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2x2 Box culvert Km 179+390 BHS 25-Jul-19 2:22 PM IPC-05 DONE AE
2908 NMSCEW/P-IV/STR/2019/2847 2847 Checking of reinforcement ,shuttering & top level of raft at LP-4 Viaduct Km 196+560 LHS 25-Jul-19 2:00 PM
2909 NMSCEW/P-IV/STR/2019/2848 2848 Checking and Pouring concrete(M35) for raft LP-4 Viaduct Km 196+560 LHS 25-Jul-19 3:30 PM
Checking reinforcement for precast Box Culvert (3x3)(cushion 0 to 2m) at precast yard camp
2910 NMSCEW/P-IV/STR/2019/2849 2849 Box culvert Km 200+200 LHS 26-Jul-19 9:00 AM DONE
-2 Segment
Checking forNO-94,95,96
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2911 NMSCEW/P-IV/STR/2019/2850 2850 Box culvert Km 200+200 LHS 26-Jul-19 9:15 AM DONE
(3x3) (Cushion
Checking 0 to 2m) for
reinforcement at precast
precastyard
Boxcamp-2,Segment no.-94,95,96
Culvert (2x2)(cushion 2 to 4m) at precast yard camp
2912 NMSCEW/P-IV/STR/2019/2851 2851 Box culvert Km 200+200 LHS 26-Jul-19 9:30 AM DONE
-2 Segment
Checking forNO-207,208,209,210,211,212,213
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2913 NMSCEW/P-IV/STR/2019/2852 2852 Box culvert Km 200+200 LHS 26-Jul-19 9:35 AM DONE
(2x2) (Cushion 2 to 4m) at precast yard camp-2,Segment no.-207,208,209,210,211,212,213
2914 NMSCEW/P-IV/STR/2019/2853 2853 Checking reinforcement and shuttering wall final wall with top slab and top haunch A1 & A2 PUP Km 186+352 LHS 26-Jul-19 10:00 AM IPC-05 DONE
2915 NMSCEW/P-IV/STR/2019/2854 2854 Checking and pourimg for wall final wall with top slab and top haunch A1 & A2 Box Culvert PUP Km 186+352 LHS 26-Jul-19 11:00 AM IPC-05 DONE
2916 NMSCEW/P-IV/STR/2019/2855 2855 Checking of raft reinforcement & shuttering for RP - 8 Box culvert Km 196+560 RHS 26-Jul-19 3:00 PM IPC-05 DONE
2917 NMSCEW/P-IV/STR/2019/2856 2856 Checking of raft reinforcement & shuttering for Box Culvert Box culvert Km 208+675 LHS 26-Jul-19 3:20 PM DONE
2918 NMSCEW/P-IV/STR/2019/2857 2857 Checking and Pouring concrete for Box Culvert Box culvert Km 208+675 LHS 26-Jul-19 3:30 PM DONE
2919 NMSCEW/P-IV/STR/2019/2858 2858 Checking of reinforcement and shuttering for raft at Lp-8 VIADUCT Km 202+190 LHS 26-Jul-19 10:00 AM IPC-08 DONE
2920 NMSCEW/P-IV/STR/2019/2859 2859 Checking top level & Laying concrete raft at Lp-8 VIADUCT Km 202+190 LHS 26-Jul-19 11:00 AM IPC-08 DONE
2921 NMSCEW/P-IV/STR/2019/2860 2860 Checking of reinforcement and shuttering of pier starter at LP-6 VIADUCT Km 202+190 LHS 26-Jul-19 2:00 PM
2922 NMSCEW/P-IV/STR/2019/2861 2861 Checking top level & Laying concrete of pier starter at LP-6 VIADUCT Km 202+190 LHS 26-Jul-19 3:00 PM
2923 NMSCEW/P-IV/STR/2019/2862 2862 Checking of reinforcement and shuttering of starter at LP-7 VIADUCT Km 202+190 LHS 26-Jul-19 2:30 PM
2924 NMSCEW/P-IV/STR/2019/2863 2863 Checking top level & Laying concrete of starter at LP-7 VIADUCT Km 202+190 LHS 26-Jul-19 3:30 PM
2925 NMSCEW/P-IV/STR/2019/2864 2864 Checking layout ,level and structural excavation of utility duct (2x2) Utility duct Km 180+300 BHS 26-Jul-19 11:00 AM NR
2926 NMSCEW/P-IV/STR/2019/2865 2865 Checking of reinforcement and shuttering at LP-5 pier shaft 1st Lift VIADUCT Km 169+800 LHS 26-Jul-19 10:00 AM IPC-08 DONE
2927 NMSCEW/P-IV/STR/2019/2866 2866 Checking top level & Laying concrete at LP-5 pier shaft 1st Lift (M-45) VIADUCT Km 169+800 LHS 26-Jul-19 10:15 AM IPC-08 DONE
2928 NMSCEW/P-IV/STR/2019/2867 2867 Checking of reinforcement and shuttering at LP-7 pier shaft 1st Lift VIADUCT Km 169+800 LHS 26-Jul-19 10:30 AM IPC-08 DONE AE
2929 NMSCEW/P-IV/STR/2019/2868 2868 Checking top level & Laying concrete at LP-7 pier shaft 1st Lift (M-45) VIADUCT Km 169+800 LHS 26-Jul-19 11:00 AM IPC-08 DONE AE
2930 NMSCEW/P-IV/STR/2019/2869 2869 Checking of reinforcement and shuttering at LP-3 pier shaft 2nd Lift VIADUCT Km 169+800 Km 00+000 LHS 26-Jul-19 1:00 PM IPC-09 DONE
2931 NMSCEW/P-IV/STR/2019/2870 2870 Checking top level & Laying concrete at LP-3 pier shaft 2nd Lift (M-45) VIADUCT Km 169+800 Km 00+000 LHS 26-Jul-19 2:00 PM IPC-09 DONE
2932 NMSCEW/P-IV/STR/2019/2871 2871 Checking of reinforcement and shuttering in wall 1st lift of PUP PUP Km 190+650 LHS 26-Jul-19 8:00 AM NR
2933 NMSCEW/P-IV/STR/2019/2872 2872 Checking top level & Laying concrete (M-30) in wall 1st lift of PUP PUP Km 190+650 LHS 26-Jul-19 8:15 AM NR
2934 NMSCEW/P-IV/STR/2019/2873 2873 Checking of reinforcement and shuttering in wall 1st lift of PUP PUP Km 190+650 LHS 26-Jul-19 8:00 AM REPEATED
2935 NMSCEW/P-IV/STR/2019/2874 2874 Checking top level & Laying concrete (M-30) in wall 1st lift of PUP PUP Km 190+650 LHS 26-Jul-19 8:15 AM REPEATED
2936 NMSCEW/P-IV/STR/2019/2875 2875 Checking of reinforcement and shuttering in wall 2nd lift of PUP A1 & A2 PUP Km 187+835 RHS 26-Jul-19 10:00 AM IPC-05 DONE
2937 NMSCEW/P-IV/STR/2019/2876 2876 Checking top level & Laying concrete (M-30) in wall 2nd lift of PUP A1 & A2 PUP Km 187+835 RHS 26-Jul-19 10:20 AM IPC-05 DONE
2938 NMSCEW/P-IV/STR/2019/2877 2877 Checking for layout,level structural excavation bed at A1 & A2 for retaining wall Retaining wall Km 184+190 RHS 26-Jul-19 12:30 PM NR
2939 NMSCEW/P-IV/STR/2019/2878 2878 Checking top Level & Laying concrete PCC at A1 & A2 for retaining wall Retaining wall Km 184+190 RHS 26-Jul-19 12:40 PM NR
Checking reinforcement for precast Box Culvert (3x3)(cushion 2 to 4m) at precast yard camp
2940 NMSCEW/P-IV/STR/2019/2879 2879 Box culvert Km 175+500 LHS 26-Jul-19 9:30 AM DONE
-1 Segment NO-127,128,129,130,131
2941 NMSCEW/P-IV/STR/2019/2880 2880 Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard cam Box culvert Km 176+250 BHS 26-Jul-19 10:00 AM IPC-05 DONE
Checking reinforcement for precast Box Culvert (2x2)(cushion 0 to 2m) at precast yard camp
2942 NMSCEW/P-IV/STR/2019/2881 2881 Box culvert Km 175+500 LHS 26-Jul-19 10:10 AM DONE
-1 Segment
Checking forNO-132,133,134,135
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2943 NMSCEW/P-IV/STR/2019/2882 2882 Box culvert Km 175+500 LHS 26-Jul-19 10:20 AM DONE
(3x3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-127,128,129,130,131
2944 NMSCEW/P-IV/STR/2019/2883 2883 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2x2 Box culvert Km 176+250 BHS 26-Jul-19 10:30 AM IPC-05 DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2945 NMSCEW/P-IV/STR/2019/2884 2884 Box culvert Km 175+500 LHS 26-Jul-19 10:40 AM DONE
(2x2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-132,133,134,135
2946 NMSCEW/P-IV/STR/2019/2885 2885 Checking of reinforcement and shuttering for VUP side wall A1 & A2 2nd lift VUP Km 179+983 RHS 26-Jul-19 4:00 PM IPC-08 DONE AE
2947 NMSCEW/P-IV/STR/2019/2886 2886 Checking top level & Laying concrete (M-35) for VUP side wall A1 & A2 2nd lift VUP Km 179+983 RHS 26-Jul-19 4:10 PM IPC-08 DONE AE
2948 NMSCEW/P-IV/STR/2019/2887 2887 Checking and pourimg for wall final wall with top slab and top haunch A1 & A2 Box Culvert Box culvert Km 186+352 LHS 26-Jul-19 11:30 AM IPC-05 DONE
2949 NMSCEW/P-IV/STR/2019/2888 2888 Checking reinforcement and shuttering wall final wall with top slab and top haunch A1 & A2 Box culvert Km 186+352 LHS 26-Jul-19 11:40 AM IPC-05 DONE
2950 NMSCEW/P-IV/STR/2019/2889 2889 Checking of reinforcement and shuttering at RP-8 pier shaft 1st Lift VIADUCT Km 169+800 RHS 26-Jul-19 12:00 PM IPC-08 DONE
2951 NMSCEW/P-IV/STR/2019/2890 2890 Checking top level & Laying concrete at RP-8 pier shaft 1st Lift (M-45) VIADUCT Km 169+800 RHS 26-Jul-19 2:10 PM IPC-08 DONE
2952 NMSCEW/P-IV/STR/2019/2891 2891 Checking top Level & Laying concrete(M-10) PCC of Retaining wall A1 & A2 Retaining wall Km 172+190 BHS 26-Jul-19 10:50 AM DONE
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
2953 NMSCEW/P-IV/STR/2019/2892 2892 Box culvert Km 200+200 LHS 27-Jul-19 8:30 AM DONE
-2 Segment
Checking forNO-210,211,212,213,214,215,216
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2954 NMSCEW/P-IV/STR/2019/2893 2893 Box culvert Km 200+200 LHS 27-Jul-19 8:40 AM DONE
(2x2) (Cushion
Checking 2 to 4m) for
reinforcement at precast
precastyard
Boxcamp-2,Segment no.-210,211,212,213,214,215,216
Culvert (3x3)(cushion 2 to 4m) at precast yard camp
2955 NMSCEW/P-IV/STR/2019/2894 2894 Box culvert Km 200+200 LHS 27-Jul-19 8:50 AM DONE
-2 Segment
Checking forNO-26
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2956 NMSCEW/P-IV/STR/2019/2895 2895 Box culvert Km 200+200 LHS 27-Jul-19 8:40 AM DONE
(3x3) (Cushion 2 to 4m) at precast yard camp-2,Segment no.-26
2957 NMSCEW/P-IV/STR/2019/2896 2896 Checking of reinforcement and shuttering for LVUP side wall A1 & A2 2nd lift LVUP Km 178+323 RHS 27-Jul-19 4:00 PM NR
2958 NMSCEW/P-IV/STR/2019/2897 2897 Checking top level & Laying concrete for LVUP side wall A1 & A2 2nd lift LVUP Km 178+323 RHS 27-Jul-19 4:10 PM NR
2959 NMSCEW/P-IV/STR/2019/2898 2898 Checking of reinforcement and shuttering for LVUP wall final lift LVUP Km 173+400 RHS 27-Jul-19 5:00 PM NR
2960 NMSCEW/P-IV/STR/2019/2899 2899 Checking top level & Laying concrete for (M-35) LVUP wall final lift LVUP Km 173+400 RHS 27-Jul-19 5:10 PM NR
2961 NMSCEW/P-IV/STR/2019/2900 2900 Checking of reinforcement and shuttering for LVUP top haunch & top slab LVUP Km 173+400 RHS 27-Jul-19 6:00 PM NR
2962 NMSCEW/P-IV/STR/2019/2901 2901 Checking top level & Laying concrete (M-35) for LVUP top haunch & top slab LVUP Km 173+400 RHS 27-Jul-19 6:15 PM NR
2963 NMSCEW/P-IV/STR/2019/2902 2902 Checking of reinforcement and shuttering for PUP side wall A1 & A2 1st lift PUP Km 190+650 LHS 27-Jul-19 10:30 AM NR
2964 NMSCEW/P-IV/STR/2019/2903 2903 Checking top level & Laying concrete (M-30) for PUP side wall A1 & A2 1st lift PUP Km 190+650 LHS 27-Jul-19 11:00 AM NR
2965 NMSCEW/P-IV/STR/2019/2904 2904 Checking of reinforcement and shuttering for top level of raft at RP 8 Viaduct Km 196+560 RHS 27-Jul-19 10:00 AM
2966 NMSCEW/P-IV/STR/2019/2905 2905 Checking top level & Laying concrete for top level of raft at RP 8 Viaduct Km 196+560 RHS 27-Jul-19 10:30 AM
2967 NMSCEW/P-IV/STR/2019/2906 2906 Checking of reinforcement, shuttering & layout of pier shaft 1st lift at LP-6 Viaduct Km 195+900 LHS 27-Jul-19 3:00 PM
2968 NMSCEW/P-IV/STR/2019/2907 2907 Checking top level & Laying concrete of pier shaft 1st lift at LP-6 Viaduct Km 195+900 LHS 27-Jul-19 3:30 PM
2969 NMSCEW/P-IV/STR/2019/2908 2908 Checking of reinforcement, shuttering & layout of starter of LP-05 Viaduct Km 195+900 LHS 27-Jul-19 4:00 PM
2970 NMSCEW/P-IV/STR/2019/2909 2909 Checking top level & Laying concrete of starter of LP-05 Viaduct Km 195+900 LHS 27-Jul-19 4:30 PM
2971 NMSCEW/P-IV/STR/2019/2910 2910 Checking of reinforcement, shuttering in wall 2nd lift of Box Culvert Box culvert Km 186+352 RHS 27-Jul-19 8:00 AM NR
2972 NMSCEW/P-IV/STR/2019/2911 2911 Checking top level & Laying concrete (M-30) in wall 2nd lift of Box Culvert Box culvert Km 186+352 RHS 27-Jul-19 8:10 AM NR
2973 NMSCEW/P-IV/STR/2019/2912 2912 Checking of reinforcement, shuttering in wall 1st lift of Box Culvert A1 Box culvert Km 182+350 RHS 27-Jul-19 3:00 PM NR
2974 NMSCEW/P-IV/STR/2019/2913 2913 Checking top level & Laying concrete (M-30) in wall 1st lift of Box Culvert A1 Box culvert Km 182+350 RHS 27-Jul-19 3:10 PM NR
2975 NMSCEW/P-IV/STR/2019/2914 2914 Checking of excavation bed,level & layout of MNB MNB Km 01+980 27-Jul-19 9:00 AM NR 1980(Loop)
2976 NMSCEW/P-IV/STR/2019/2915 2915 Checking top level & Laying concrete PCC (M-15) of MNB MNB Km 01+980 27-Jul-19 9:10 AM NR 1980(Loop)
Checking reinforcement for precast Box Culvert (2x2)(cushion 0 to 2m) at precast yard camp
2977 NMSCEW/P-IV/STR/2019/2916 2916 Box culvert Km 175+500 LHS 27-Jul-19 9:00 AM DONE
-1 Segment
Checking forNO-136
shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2978 NMSCEW/P-IV/STR/2019/2917 2917 Box culvert Km 175+500 LHS 27-Jul-19 9:30 AM DONE
(3x3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-120,121,122,125,126
2979 NMSCEW/P-IV/STR/2019/2918 2918 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2x2 Box culvert Km 179+390 BHS 31-Jul-19 9:45 AM IPC-05 DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
2980 NMSCEW/P-IV/STR/2019/2919 2919 Box culvert Km 175+500 LHS 27-Jul-19 9:50 AM DONE
(2x2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-129,130,131,136
2981 NMSCEW/P-IV/STR/2019/2920 2920 Checking top Level & Laying concrete PCC for retaining wall Retaining wall Km 174+095 BHS 27-Jul-19 8:00 AM NR
2982 NMSCEW/P-IV/STR/2019/2921 2921 Checking of reinforcement and shuttering for pier starter (150mm) at LP-5 Viaduct Km 196+560 LHS 27-Jul-19 10:00 AM
2983 NMSCEW/P-IV/STR/2019/2922 2922 Checking top level & Laying concrete for pier starter (150mm) at LP-5 Viaduct Km 196+560 LHS 27-Jul-19 10:30 AM
2984 NMSCEW/P-IV/STR/2019/2923 2923 Checking of reinforcement and shuttering for starter (150mm) at RP-10 Viaduct Km 196+560 RHS 27-Jul-19 11:00 AM
2985 NMSCEW/P-IV/STR/2019/2924 2924 Checking top level & Laying concrete for starter (150mm) at RP-10 Viaduct Km 196+560 RHS 27-Jul-19 11:30 AM
2986 NMSCEW/P-IV/STR/2019/2925 2925 Checking of reinforcement, shuttering for final lift, top slab and top haunch A1 &A2 at PUP PUP Km 189+000 LHS 27-Jul-19 12:00 PM IPC-05 DONE
2987 NMSCEW/P-IV/STR/2019/2926 2926 Checking top level & Laying concrete (M-30) for final lift, top slab & top haunch A1 &A2 PUP Km 189+000 LHS 27-Jul-19 12:30 PM IPC-05 DONE
2988 NMSCEW/P-IV/STR/2019/2927 2927 Checking of reinforcement, shuttering for top slab and top haunch A1 &A2 at PUP PUP Km 165+300 RHS 27-Jul-19 3:00 PM IPC-05 DONE
2989 NMSCEW/P-IV/STR/2019/2928 2928 Checking top level & Laying concrete (M-30) for top slab top haunch A1 &A2 at PUP PUP Km 165+300 RHS 27-Jul-19 3:10 PM IPC-05 DONE
2990 NMSCEW/P-IV/STR/2019/2929 2929 Checkingof level & layout for top Slab LVUP Km 193+880 RHS 28-Jul-19 5:00 PM IPC-05 DONE
2991 NMSCEW/P-IV/STR/2019/2930 2930 Checking of reinforcement and shuttering and Pouring for top slab LVUP Km 193+880 RHS 28-Jul-19 5:10 PM IPC-05 DONE
2992 NMSCEW/P-IV/STR/2019/2931 2931 checking for reinforcement and shuttering for W1 & W2 for 1st Lift LVUP Km 203+886 LHS 28-Jul-19 5:20 PM IPC-05 DONE
2993 NMSCEW/P-IV/STR/2019/2932 2932 Checking and concrete pouring for W1 & W2 for 1st Lift LVUP Km 203+886 LHS 28-Jul-19 6:00 PM IPC-05 DONE
2994 NMSCEW/P-IV/STR/2019/2933 2933 Checking top Level & Laying concrete PCC (M-10) for retaining wall Retaining wall Km 174+095 BHS 28-Jul-19 8:00 AM NR
2995 NMSCEW/P-IV/STR/2019/2934 2934 Checking of reinforcement, shuttering & layout of pier shaft 1st lift at LP-6 Viaduct Km 195+900 LHS 28-Jul-19 10:00 AM
2996 NMSCEW/P-IV/STR/2019/2935 2935 Checking top level & Laying concrete (M-35) pier shaft 1st lift at LP-6 Viaduct Km 195+900 LHS 28-Jul-19 10:30 AM
2997 NMSCEW/P-IV/STR/2019/2936 2936 Checking of reinforcement, shuttering of starter of LP-05 Viaduct Km 195+900 LHS 28-Jul-19 3:00 PM
2998 NMSCEW/P-IV/STR/2019/2937 2937 Checking top level & Laying concrete (M-35) of starter of LP-05 Viaduct Km 195+900 LHS 28-Jul-19 3:30 PM
2999 NMSCEW/P-IV/STR/2019/2938 2938 Checking of reinforcement, shuttering & top level of raft at RP-4 Viaduct Km 200+920 RHS 28-Jul-19 11:00 AM
3000 NMSCEW/P-IV/STR/2019/2939 2939 Checking top level & Laying concrete (M-35) OF RAFT at RP-4 Viaduct Km 200+920 RHS 28-Jul-19 12:00 PM
3001 NMSCEW/P-IV/STR/2019/2940 2940 Checking for completion of segment erection at utility duct Utility duct Km 193+350 BHS 29-Jul-19 11:10 AM IPC-05 DONE
3002 NMSCEW/P-IV/STR/2019/2941 2941 Checking of reinforcement, shuttering for top slab and top haunch A1 &A2 at PUP PUP Km 187+835 RHS 29-Jul-19 4:00 PM IPC-05 DONE
3003 NMSCEW/P-IV/STR/2019/2942 2942 Checking top level & Laying concrete (M-30) for top slab top haunch A1 &A2 at PUP PUP Km 187+835 RHS 29-Jul-19 4:10 PM IPC-05 DONE
3004 NMSCEW/P-IV/STR/2019/2943 2943 Checking of reinforcement and shuttering for raft with bottom haunch at wall A1 & A2 PUP Km 164+380 Km 00+000 RHS 29-Jul-19 4:30 PM IPC-09 DONE
3005 NMSCEW/P-IV/STR/2019/2944 2944 Checking top level & Laying concrete for raft with bottom haunch at wall A1 & A2 PUP Km 164+380 Km 00+000 RHS 29-Jul-19 4:40 PM IPC-09 DONE
3006 NMSCEW/P-IV/STR/2019/2945 2945 Checking top level & Laying concrete for LP-4 raft Viaduct Km 196+560 LHS 29-Jul-19 10:00 AM
3007 NMSCEW/P-IV/STR/2019/2946 2946 Checking of Completion of precast segment erection Viaduct Km 199+580 BHS 29-Jul-19 10:15 AM IPC-05 DONE
3008 NMSCEW/P-IV/STR/2019/2947 2947 Checking top level & Laying concrete (M-35) for raft at RP-8 Viaduct Km 196+560 RHS 29-Jul-19 10:30 AM IPC-05 DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3009 NMSCEW/P-IV/STR/2019/2948 2948 Box culvert Km 175+500 LHS 29-Jul-19 11:20 AM DONE
(3x3) (Cushion
Checking 2 to 4m)&
for shuttering at Pouring
precast yard camp-1,Segment
of Concreting no.-122,125,126
Grade =(M-30) for Precast Box Culvert
3010 NMSCEW/P-IV/STR/2019/2949 2949 Box culvert Km 175+500 LHS 29-Jul-19 12:10 PM DONE
(2x2) (Cushion
Checking 2 to 4m)&
for shuttering at Pouring
precast yard camp-1,Segment
of Concreting no.-104 for Precast Box Culvert
Grade =(M-30)
3011 NMSCEW/P-IV/STR/2019/2950 2950 Box culvert Km 175+500 LHS 29-Jul-19 3:10 PM DONE
(2x2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-130,131,136
3012 NMSCEW/P-IV/STR/2019/2951 2951 Checking reinforcement and shuttering for wall final Lift at LVUP LVUP Km 173+400 RHS 29-Jul-19 4:20 PM IPC-05 DONE
3013 NMSCEW/P-IV/STR/2019/2952 2952 Checking and concrete (M35) pouring for wall final Lift at LVUP LVUP Km 173+400 RHS 29-Jul-19 5:00 PM IPC-05 DONE
3014 NMSCEW/P-IV/STR/2019/2953 2953 Checking reinforcement and shuttering for top haunch and top slab at LVUP LVUP Km 173+400 RHS 29-Jul-19 4:30 PM IPC-05 DONE
3015 NMSCEW/P-IV/STR/2019/2954 2954 Checking and concrete (M35) pouring for top haunch and top slab at LVUP LVUP Km 173+400 RHS 29-Jul-19 5:32 PM IPC-05 DONE
3016 NMSCEW/P-IV/STR/2019/2955 2955 Checking of reinforcement and shuttering for pier starter at LP-6 Viaduct Km 202+190 LHS 30-Jul-19 10:00 AM
3017 NMSCEW/P-IV/STR/2019/2956 2956 Checking top level & Laying concrete for pier starter at LP-6 Viaduct Km 202+190 LHS 30-Jul-19 10:30 AM
3018 NMSCEW/P-IV/STR/2019/2957 2957 Checking of reinforcement and shuttering for pier starter at LP-7 Viaduct Km 202+190 LHS 30-Jul-19 2:00 PM IPC-08 DONE
3019 NMSCEW/P-IV/STR/2019/2958 2958 Checking top level & Laying concrete for pier starter at LP-7 Viaduct Km 202+190 LHS 30-Jul-19 3:00 PM IPC-08 DONE
3020 NMSCEW/P-IV/STR/2019/2959 2959 Checking of reinforcement and shuttering for pier starter at RP-1 Viaduct Km 202+190 Km 00+000 RHS 30-Jul-19 2:30 PM IPC-10 DONE
3021 NMSCEW/P-IV/STR/2019/2960 2960 Checking for concrete pouring for pier shaft starter at RP-1 Viaduct Km 202+190 Km 00+000 RHS 30-Jul-19 3:30 PM IPC-10 DONE
3022 NMSCEW/P-IV/STR/2019/2961 2961 Checking of reinforcement and shuttering for pier starter at RP-2 Viaduct Km 202+190 LHS 30-Jul-19 11:00 AM
3023 NMSCEW/P-IV/STR/2019/2962 2962 Checking top level & Laying concrete for pier starter at RP-2 Viaduct Km 202+190 LHS 30-Jul-19 11:50 AM
3024 NMSCEW/P-IV/STR/2019/2963 2963 Checking of reinforcement, shuttering & top level of raft at RP-4 Viaduct Km 200+920 RHS 30-Jul-19 11:10 AM
3025 NMSCEW/P-IV/STR/2019/2964 2964 Checking top level & Laying concrete (M-35) OF RAFT at RP-4 Viaduct Km 200+920 RHS 30-Jul-19 12:00 PM
3026 NMSCEW/P-IV/STR/2019/2965 2965 Checking top level & Laying concrete for LP-4 raft Viaduct Km 196+560 LHS 30-Jul-19 12:32 PM
3027 NMSCEW/P-IV/STR/2019/2966 2966 Checking of reinforcement,shuttering for raft at RP-8 Viaduct Km 196+560 RHS 30-Jul-19 11:50 AM
3028 NMSCEW/P-IV/STR/2019/2967 2967 Checking top level & Laying concrete (M-35) for raft at RP-8 Viaduct Km 196+560 RHS 30-Jul-19 12:45 PM
Checking reinforcement for precast Box Culvert (3x3)(cushion 2 to 2m) at precast yard camp
3029 NMSCEW/P-IV/STR/2019/2968 2968 Box culvert Km 175+500 LHS 30-Jul-19 10:15 AM NR
-1 Segment NO-132,133,134.
3030 NMSCEW/P-IV/STR/2019/2969 2969 Checking reinforcement for precast Box Culvert (2x2)(cushion 0 to 2m) at precast yard camp Box culvert Km 179+390 BHS 30-Jul-19 10:10 AM IPC-05 DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3031 NMSCEW/P-IV/STR/2019/2970 2970 Box culvert Km 175+500 LHS 30-Jul-19 10:20 AM NR
(3x3) (Cushion
Checking 2 to 4m)&
for shuttering at Pouring
precast yard camp-1,Segment
of Concreting no.-64,131,132,133,134.
Grade =(M-30) for Precast Box Culvert
3032 NMSCEW/P-IV/STR/2019/2971 2971 Box culvert Km 175+500 LHS 30-Jul-19 10:30 AM NR
(2x2) (Cushion
Checking 0 to 2m)&
for shuttering at Pouring
precast yard camp-1,Segment
of Concreting no.-137,138,139,140.
Grade =(M-30) for Precast Box Culvert
3033 NMSCEW/P-IV/STR/2019/2972 2972 Box culvert Km 175+500 LHS 30-Jul-19 10:30 AM NR
(2x2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-95,106,107
3034 NMSCEW/P-IV/STR/2019/2973 2973 checking for excvation of box culvert Box culvert Km 200+286 LHS 30-Jul-19 11:40 AM
3035 NMSCEW/P-IV/STR/2019/2974 2974 Checking of irrection and fixing segment of utility duct (2×2) Utility duct Km 176+250 BHS 30-Jul-19 10:00 AM IPC-05 DONE
3036 NMSCEW/P-IV/STR/2019/2972/A 2972/A checking for layout of box culvert Box culvert Km 200+286 LHS 30-Jul-19 10:40 AM
3037 NMSCEW/P-IV/STR/2019/2975 2975 Checking of reinforcement and shuttering for Top Slab Box Culvert Km 203+886 LHS 31-Jul-19 4:00 PM IPC-05 DONE
3038 NMSCEW/P-IV/STR/2019/2976 2976 Checking top level & Laying concrete for Top Slab Box Culvert Km 203+886 LHS 31-Jul-19 4:10 PM IPC-05 DONE
3039 NMSCEW/P-IV/STR/2019/2977 2977 Checking of reinforcement, shuttering for final lift wall A1 & A2 wall PUP Km 165+300 LHS 31-Jul-19 3:00 PM IPC-05 DONE
3040 NMSCEW/P-IV/STR/2019/2978 2978 Checking top level & Laying concrete for final lift wall A1 & A2 wall PUP Km 165+300 LHS 31-Jul-19 3:10 PM IPC-05 DONE
3041 NMSCEW/P-IV/STR/2019/2979 2979 Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard cam Box culvert Km 176+250 BHS 31-Jul-19 9:10 AM IPC-05 DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3042 NMSCEW/P-IV/STR/2019/2980 2980 Box culvert Km 175+500 LHS 31-Jul-19 9:20 AM DONE
(3x3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-64,131,132,133,134
3043 NMSCEW/P-IV/STR/2019/2981 2981 Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert (2x2 Box culvert Km 176+250 BHS 31-Jul-19 10:20 AM IPC-05 DONE
3044 NMSCEW/P-IV/STR/2019/2982 2982 Checking of irrection and fixing segment of utility duct (2×2) Utility duct Km 179+390 BHS 31-Jul-19 11.20 AM IPC-05 DONE
3045 NMSCEW/P-IV/STR/2019/2983 2983 Checking of reinforcement, shuttering for final lift, top slab and top haunch A1 &A2 at PUP PUP Km 190+650 RHS 31-Jul-19 3:30 PM IPC-05 DONE
3046 NMSCEW/P-IV/STR/2019/2984 2984 Checking top level & Laying concrete (M-30) for final lift, top slab & top haunch A1 &A2 PUP Km 190+650 RHS 31-Jul-19 3:40 PM IPC-05 DONE
3047 NMSCEW/P-IV/STR/2019/2985 2985 Checking of reinforcement and shuttering for pier starter at LP-6 Viaduct Km 202+190 LHS 31-Jul-19 10:00 AM
3048 NMSCEW/P-IV/STR/2019/2986 2986 Checking top level & Laying concrete for pier starter at Lp-6 Viaduct Km 202+190 LHS 31-Jul-19 11:00 AM
3049 NMSCEW/P-IV/STR/2019/2987 2987 Checking of reinforcement and shuttering for pier starter at RP-2 Viaduct Km 202+190 RHS 31-Jul-19 11:10 AM
3050 NMSCEW/P-IV/STR/2019/2988 2988 Checking top level & Laying concrete for pier starter at RP-2 Viaduct Km 202+190 RHS 31-Jul-19 11:30 AM
3051 NMSCEW/P-IV/STR/2019/2989 2989 Checking reinforcement ,shuttering for top slab with top haunch at wall A1 & A2 of pup PUP Km 165+300 LHS 31-Jul-19 10:00 AM IPC-05 DONE
3052 NMSCEW/P-IV/STR/2019/2990 2990 Checking top level & Laying concrete (M-30) for top slab at PUP PUP Km 165+300 LHS 31-Jul-19 3:10 PM IPC-05 DONE
3053 NMSCEW/P-IV/STR/2019/2991 2991 Checking & Pouring concrete for top slab Box culvert Km 204+920 LHS 31-Jul-19 10:30 AM IPC-05 DONE
3054 NMSCEW/P-IV/STR/2019/2992 2992 Checking of reinforcement, shuttering and top level of raft at RP-4 Viaduct Km 200+920 RHS 1-Aug-19 2:00 PM IPC-08 DONE AE
3055 NMSCEW/P-IV/STR/2019/2993 2993 Checking top level & Laying concrete (M-35) for raft at RP-4 Viaduct Km 200+920 RHS 1-Aug-19 3:00 PM IPC-08 DONE AE
3056 NMSCEW/P-IV/STR/2019/2994 2994 Checking of reinforcement, shuttering of pier starter at LP-6 Viaduct Km 202+190 LHS 1-Aug-19 10:00 AM IPC-08 DONE AE
3057 NMSCEW/P-IV/STR/2019/2995 2995 Checking top level & Laying concrete of pier starter at LP-6 Viaduct Km 202+190 LHS 1-Aug-19 11:00 AM IPC-08 DONE AE
3058 NMSCEW/P-IV/STR/2019/2996 2996 Checking of reinforcement, shuttering of pier starter at RP-2 Viaduct Km 202+190 Km 00+000 RHS 1-Aug-19 11:00 AM IPC-10 DONE AE
3059 NMSCEW/P-IV/STR/2019/2997 2997 Checking top level & Laying concrete of pier starter at RP-2 Viaduct Km 202+190 Km 00+000 RHS 1-Aug-19 11:30 AM IPC-10 DONE AE
3060 NMSCEW/P-IV/STR/2019/2998 2998 Checking of reinforcement, shuttering of pier starter at RP-3 Viaduct Km 202+190 Km 00+000 RHS 1-Aug-19 12:00 PM IPC-10 DONE
3061 NMSCEW/P-IV/STR/2019/2999 2999 Checking top level & Laying concrete of pier starter at RP-3 Viaduct Km 202+190 Km 00+000 RHS 1-Aug-19 12:30 PM IPC-10 DONE AE
3062 NMSCEW/P-IV/STR/2019/3000 3000 Checking of reinforcement, shuttering of wall W1 2nd lift at PUP PUP Km 199+060 RHS 1-Aug-19 9:00 AM DONE
3063 NMSCEW/P-IV/STR/2019/3001 3001 Checking top level & Laying concrete of wall W1 2nd lift at PUP PUP Km 199+060 RHS 1-Aug-19 10:00 AM DONE
3064 NMSCEW/P-IV/STR/2019/3002 3002 Checking top level & Laying concrete (M-35) for raft at LP-4 Viaduct Km 196+560 LHS 1-Aug-19 10:00 AM
3065 NMSCEW/P-IV/STR/2019/3003 3003 Checking for shuttering and reinforcement for raft at Box Culvert Box culvert Km 180+427 RHS 1-Aug-19 3:30 PM IPC-08 DONE AE
3066 NMSCEW/P-IV/STR/2019/3004 3004 Checking top level & Laying concrete (M-35) for raft at Box Culvert Box culvert Km 180+427 RHS 1-Aug-19 4:30 PM IPC-08 DONE AE
3067 NMSCEW/P-IV/STR/2019/3005 3005 Checking of reinforcement, shuttering for 3rd lift wall A1 & A2 wall VUP Km 179+983 RHS 2-Aug-19 11:30 AM NR
3068 NMSCEW/P-IV/STR/2019/3006 3006 Checking top level & Laying concrete for 3rd lift wall A1 & A2 wall VUP Km 179+983 RHS 2-Aug-19 2:00 PM NR
3069 NMSCEW/P-IV/STR/2019/3007 3007 Checking of reinforcement, shuttering for 1st lift wall A1 & A2 wall LVUP Km 169+291 LHS 2-Aug-19 4:00 PM IPC-08 DONE AE A1 DONE
3070 NMSCEW/P-IV/STR/2019/3008 3008 Checking top level & Laying concrete for 1st lift wall A1 & A2 wall LVUP Km 169+291 LHS 2-Aug-19 4:20 PM IPC-08 DONE AE A1 DONE
3071 NMSCEW/P-IV/STR/2019/3009 3009 Checking of reinforcement and shuttering for pier shaft 1st lift at LP-6 Viaduct Km 195+900 LHS 2-Aug-19 4:00 PM
3072 NMSCEW/P-IV/STR/2019/3010 3010 Checking top level & Laying concrete for pier shaft 1st lift at LP-6 Viaduct Km 195+900 LHS 2-Aug-19 4:30 PM
3073 NMSCEW/P-IV/STR/2019/3011 3011 Checking of reinforcement and shuttering for raft at RP-8 Viaduct Km 196+560 RHS 2-Aug-19 10:00 AM
3074 NMSCEW/P-IV/STR/2019/3012 3012 Checking top level & Laying concrete (M-35) for raft at RP-8 Viaduct Km 196+560 RHS 2-Aug-19 10:30 AM
Checking for stressing and remove slagness of H.T. wires at Girder no 1,2,3,4 at bed no -1 at
3075 NMSCEW/P-IV/STR/2019/3013 3013 Girder Type-2 Km 200+200 LHS 2-Aug-19 10:00 AM
casting yard camp -2
Checking reinforcement for precast Box Culvert (3x3)(cushion 4 to 6m) at precast yard camp
3076 NMSCEW/P-IV/STR/2019/3014 3014 Box culvert Km 175+500 LHS 2-Aug-19 11:20 AM DONE
-1 Segment NO-1,2,3.
Checking reinforcement for precast Box Culvert (3x3)(cushion 2 to 4m) at precast yard camp
3077 NMSCEW/P-IV/STR/2019/3015 3015 Box culvert Km 175+500 LHS 2-Aug-19 11:40 AM DONE
-1 Segment NO-135,136..
Checking reinforcement for precast Box Culvert (2x2)(cushion 0 to 2m) at precast yard camp
3078 NMSCEW/P-IV/STR/2019/3016 3016 Box culvert Km 175+500 LHS 2-Aug-19 12:50 PM IPC-08 141, 142, 143, 144
-1 Segment NO-141,142,143,144. DONE AE
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
3079 NMSCEW/P-IV/STR/2019/3017 3017 Box culvert Km 175+500 LHS 2-Aug-19 2:00 PM DONE
-1 Segment NO-114,115,116.
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3080 NMSCEW/P-IV/STR/2019/3018 3018 Box culvert Km 175+500 LHS 2-Aug-19 2:40 PM DONE
(3×3) (Cushion 4 to 6m) at precast yard camp-1,Segment no.-1,2,3.
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3081 NMSCEW/P-IV/STR/2019/3019 3019 Box culvert Km 175+500 LHS 2-Aug-19 3:20 PM DONE
(3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-135,136.
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3082 NMSCEW/P-IV/STR/2019/3020 3020 Box culvert Km 175+500 LHS 2-Aug-19 3:40 PM IPC-08 141, 142, 143
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-141,142,143,144.
DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3083 NMSCEW/P-IV/STR/2019/3021 3021 Box culvert Km 175+500 LHS 2-Aug-19 4:30 PM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-114,115,116.
3084 NMSCEW/P-IV/STR/2019/3022 3022 Checking of reinforcement, shuttering for 3rd lift at A1 & A2 wall VUP Km 179+983 RHS 3-Aug-19 4:30 PM NR
3085 NMSCEW/P-IV/STR/2019/3023 3023 Checking & Pouring concrete (M-35) for 3rd lift at A1 & A2 wall VUP Km 179+983 RHS 3-Aug-19 5:15 PM NR
3086 NMSCEW/P-IV/STR/2019/3024 3024 Checking of reinforcement, shuttering for 3rd lift at A1 & A2 wall VUP Km 176+614 Km 00+000 RHS 3-Aug-19 9:30 AM IPC-10 DONE
3087 NMSCEW/P-IV/STR/2019/3025 3025 Checking & Pouring concrete (M-35) for 3rd lift at A1 & A2 wall VUP Km 176+614 Km 00+000 RHS 3-Aug-19 10:30 AM IPC-10 DONE
3088 NMSCEW/P-IV/STR/2019/3026 3026 Checking Layout & Level for top slab Box culvert Km 204+920 RHS 3-Aug-19 3:30 PM DONE
3089 NMSCEW/P-IV/STR/2019/3027 3027 Checking of reinforcement & shuttering for top slab Box culvert Km 204+920 RHS 3-Aug-19 3:40 PM DONE
3090 NMSCEW/P-IV/STR/2019/3028 3028 Checking & Pouring concrete for top slab Box culvert Km 204+920 RHS 3-Aug-19 4:30 PM DONE
3091 NMSCEW/P-IV/STR/2019/3029 3029 Checking of reinforcement, shuttering for 2nd lift at W2 wall PUP Km 199+060 RHS 3-Aug-19 11:00 AM DONE
3092 NMSCEW/P-IV/STR/2019/3030 3030 Checking & Pouring concrete for 2nd lift at W2 wall PUP Km 199+060 RHS 3-Aug-19 12:00 PM DONE
3093 NMSCEW/P-IV/STR/2019/3031 3031 Checking of reinforcement, shuttering for pier shaft final lift at LP-1 Viaduct Km 202+190 LHS 3-Aug-19 11:05 AM
3094 NMSCEW/P-IV/STR/2019/3032 3032 Checking & pouring concrete for pier shaft final lift at LP-1 Viaduct Km 202+190 LHS 3-Aug-19 11:32 AM
3095 NMSCEW/P-IV/STR/2019/3033 3033 Checking of reinforcement, shuttering for pier starter at RP-4 Viaduct Km 202+190 RHS 3-Aug-19 12:05 PM
3096 NMSCEW/P-IV/STR/2019/3034 3034 Checking & pouring concrete for pier starter at RP-4 Viaduct Km 202+190 RHS 3-Aug-19 12:03 PM
3097 NMSCEW/P-IV/STR/2019/3035 3035 Checking of reinforcement, shuttering for raft at RP-9 Viaduct Km 202+190 RHS 3-Aug-19 3:11 PM
3098 NMSCEW/P-IV/STR/2019/3036 3036 Checking & pouring concrete for raft at RP-9 Viaduct Km 202+190 RHS 3-Aug-19 4:12 PM
3099 NMSCEW/P-IV/STR/2019/3037 3037 Checking of reinforcement, shuttering for raft at RP-5 Viaduct Km 200+920 RHS 3-Aug-19 10:00 AM IPC-08 DONE AE
3100 NMSCEW/P-IV/STR/2019/3038 3038 Checking top level & pouring concrete(M-35) for raft at RP-5 Viaduct Km 200+920 RHS 3-Aug-19 11:20 AM IPC-08 DONE AE
3101 NMSCEW/P-IV/STR/2019/3039 3039 Checking of reinforcement, shuttering for pier shaft 1st lift at RP-9 Viaduct Km 169+800 RHS 3-Aug-19 2:00 PM NR
3102 NMSCEW/P-IV/STR/2019/3040 3040 Checking & pouring concrete for pier shaft 1st lift at RP-9 Viaduct Km 169+800 RHS 3-Aug-19 2:30 PM NR
3103 NMSCEW/P-IV/STR/2019/3041 3041 Checking of reinforcement, shuttering for pier shaft 1st lift at LP-9 Viaduct Km 169+800 LHS 3-Aug-19 3:00 PM NR
3104 NMSCEW/P-IV/STR/2019/3042 3042 Checking & pouring concrete for pier shaft 1st lift at LP-9 Viaduct Km 169+800 LHS 3-Aug-19 3:44 PM NR
3105 NMSCEW/P-IV/STR/2019/3043 3043 Checking of reinforcement, shuttering for 1st lift at A1 & A2 wall PUP Km 187+835 LHS 3-Aug-19 10:18 AM NR
3106 NMSCEW/P-IV/STR/2019/3044 3044 Checking & Pouring concrete (M-30) for 1st lift at A1 & A2 wall PUP Km 187+835 LHS 3-Aug-19 10:50 AM NR
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
3107 NMSCEW/P-IV/STR/2019/3045 3045 Box culvert Km 175+500 LHS 3-Aug-19 9:26 AM DONE
-1. Segment NO-117,118,119
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3108 NMSCEW/P-IV/STR/2019/3046 3046 Box culvert Km 175+500 LHS 3-Aug-19 10:29 AM DONE
(2x2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-117,118,119
Checking reinforcement for precast Box Culvert (3x3) (Cushion 4 to 6 m) at precast yard camp
3109 NMSCEW/P-IV/STR/2019/3047 3047 Box culvert Km 175+500 LHS 3-Aug-19 12:37 PM DONE
-1. Segment NO-4,5,6,7,8
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3110 NMSCEW/P-IV/STR/2019/3048 3048 Box culvert Km 175+500 LHS 3-Aug-19 4:29 PM DONE
(3x3) (Cushion 4 to 6 m) at precast yard camp-1,Segment no.-4,5,6,7,8
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
3111 NMSCEW/P-IV/STR/2019/3049 3049 Box culvert Km 175+500 LHS 3-Aug-19 12:52 PM IPC-08 145, 146, 147, 148
-1. Segment NO-145,146,147,148 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3112 NMSCEW/P-IV/STR/2019/3050 3050 Box culvert Km 175+500 LHS 3-Aug-19 5:38 PM IPC-08 145, 146, 147, 148
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-145,146,147,148
DONE
3113 NMSCEW/P-IV/STR/2019/3051 3051 Checking of reinforcement, shuttering for pier shaft 1st lift at LP-6 Viaduct Km 195+900 LHS 4-Aug-19 9:00 AM
3114 NMSCEW/P-IV/STR/2019/3052 3052 Checking & pouring concrete for pier shaft 1st lift at LP-6 Viaduct Km 195+900 LHS 4-Aug-19 9:30 AM
3115 NMSCEW/P-IV/STR/2019/3053 3053 Checking of reinforcement, shuttering for pier shaft 1st lift at LP-9 Viaduct Km 169+800 LHS 5-Aug-19 11:00 AM IPC-08 DONE AE
3116 NMSCEW/P-IV/STR/2019/3054 3054 Checking & pouring concrete for pier shaft 1st lift at RP-9 Viaduct Km 169+800 RHS 5-Aug-19 10:30 AM NR
3117 NMSCEW/P-IV/STR/2019/3055 3055 Checking & pouring concrete for pier shaft 1st lift at LP-9 Viaduct Km 169+800 LHS 5-Aug-19 10:44 AM IPC-08 DONE AE
3118 NMSCEW/P-IV/STR/2019/3056 3056 Checking & pouring concrete for pier shaft 1st lift at LP-9 Viaduct Km 169+800 LHS 5-Aug-19 11:30 AM NR
3119 NMSCEW/P-IV/STR/2019/3057 3057 Checking of reinforcement, shuttering for pier starter at LP-5 Viaduct Km 195+900 LHS 5-Aug-19 3:00 PM
3120 NMSCEW/P-IV/STR/2019/3058 3058 Checking & pouring concrete for pier starter at LP-5 Viaduct Km 195+900 LHS 5-Aug-19 3:30 PM
3121 NMSCEW/P-IV/STR/2019/3059 3059 Checking of side shuttering girder no- 1,2,3 & 4 at bed no-01,Girder Type-2 Girder Km 200+200 LHS 5-Aug-19 10:15 AM
Approval for pouring of girder no- 1,2,3 & 4 at bed no-1.(Grade of concrete M-50)
3122 NMSCEW/P-IV/STR/2019/3060 3060 Girder Km 200+200 LHS 5-Aug-19 10:45 AM
Girder Type- 2
3123 NMSCEW/P-IV/STR/2019/3061-A 3061A Checking of reinforcement & shuttering for raft at LP-4 Viaduct Km 196+560 LHS 5-Aug-19 9:15 AM IPC-08 DONE AE
3124 NMSCEW/P-IV/STR/2019/3061 3061 Checking & pouring concrete(M-35) for raft at LP-4 Viaduct Km 196+560 LHS 5-Aug-19 9:15 AM IPC-08 DONE AE
3125 NMSCEW/P-IV/STR/2019/3062 3062 Checking & pouring concrete(M-35) for raft at RP-8 Viaduct Km 196+560 LHS 5-Aug-19 12:00 PM
3126 NMSCEW/P-IV/STR/2019/3063 3063 Checking of reinforcement, shuttering for pier starter at RP-5 Viaduct Km 202+190 RHS 5-Aug-19 12:15 PM
3127 NMSCEW/P-IV/STR/2019/3064 3064 Checking & pouring concrete for pier starter at RP-5 Viaduct Km 202+190 RHS 5-Aug-19 12:30 PM
3128 NMSCEW/P-IV/STR/2019/3065 3065 Checking of reinforcement, shuttering for raft at RP-9 Viaduct Km 202+190 RHS 5-Aug-19 3:15 PM IPC-08 DONE AE
3129 NMSCEW/P-IV/STR/2019/3066 3066 Checking & pouring concrete for raft at RP-9 Viaduct Km 202+190 RHS 5-Aug-19 3:40 PM IPC-08 DONE AE
3130 NMSCEW/P-IV/STR/2019/3067 3067 Checking layout & level for raft at RP-13 Viaduct Km 202+190 Km 00+000 RHS 5-Aug-19 2:00 PM IPC-10 DONE AE
3131 NMSCEW/P-IV/STR/2019/3068 3068 Checking of reinforcement, shuttering for raft at RP-13 Viaduct Km 202+190 Km 00+000 RHS 5-Aug-19 2:15 PM IPC-10 DONE AE
3132 NMSCEW/P-IV/STR/2019/3069 3069 Checking & pouring concrete for raft at RP-13 Viaduct Km 202+190 Km 00+000 RHS 5-Aug-19 2:30 PM IPC-10 DONE AE
3133 NMSCEW/P-IV/STR/2019/3070 3070 Checking layout & level for pcc at RP-2 Viaduct Km 200+920 RHS 5-Aug-19 2:10 PM
3134 NMSCEW/P-IV/STR/2019/3071 3071 Checking top level & Laying concrete for pcc at RP-2 Viaduct Km 200+920 RHS 5-Aug-19 3:10 PM
3135 NMSCEW/P-IV/STR/2019/3072 3072 Checking Layout & Level for top slab CUP Km 203+560 RHS 5-Aug-19 11:10 AM IPC-08 DONE AE
3136 NMSCEW/P-IV/STR/2019/3073 3073 Checking of reinforcement & shuttering for top slab CUP Km 203+560 RHS 5-Aug-19 11:25 AM IPC-08 DONE AE
3137 NMSCEW/P-IV/STR/2019/3074 3074 Checking & Pouring concrete for top slab CUP Km 203+560 RHS 5-Aug-19 2:20 PM IPC-08 DONE AE
3138 NMSCEW/P-IV/STR/2019/3075 3075 Checking of reinforcement, shuttering for 3rd lift at A1 & A2 wall VUP Km 179+983 RHS 5-Aug-19 10:33 AM IPC-08 DONE AE
3139 NMSCEW/P-IV/STR/2019/3076 3076 Checking & Pouring concrete (M-35) for 3rd lift at A1 & A2 wall VUP Km 179+983 RHS 5-Aug-19 11:11 AM IPC-08 DONE AE
3140 NMSCEW/P-IV/STR/2019/3077 3077 Checking of reinforcement, shuttering for 1st lift at A2 wall LVUP Km 169+291 LHS 5-Aug-19 4:00 PM IPC-08 DONE AE
3141 NMSCEW/P-IV/STR/2019/3078 3078 Checking & Pouring concrete for 1st lift at A2 wall LVUP Km 169+291 LHS 5-Aug-19 5:00 PM IPC-08 DONE AE
Checking reinforcement for precast Box Culvert (3x3) (Cushion 4 to 6 m) at precast yard camp
3142 NMSCEW/P-IV/STR/2019/3079 3079 Box culvert Km 175+500 LHS 5-Aug-19 12:37 PM DONE
-1. Segment NO-9,10,11,12,13
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3143 NMSCEW/P-IV/STR/2019/3080 3080 Box culvert Km 175+500 LHS 5-Aug-19 4:29 PM DONE
(3x3) (Cushion 4 to 6 m) at precast yard camp-1,Segment no.-9,10,11,12,13
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
3144 NMSCEW/P-IV/STR/2019/3081 3081 Box culvert Km 175+500 LHS 5-Aug-19 9:26 AM DONE
-1. Segment NO-120,121,122,123
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3145 NMSCEW/P-IV/STR/2019/3082 3082 Box culvert Km 175+500 LHS 5-Aug-19 10:29 AM DONE
(2x2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-120,121,122,123
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
3146 NMSCEW/P-IV/STR/2019/3083 3083 Box culvert Km 175+500 LHS 5-Aug-19 12:52 PM IPC-08 149, 150, 151, 152
-1. Segment NO-149,150,151,152 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3147 NMSCEW/P-IV/STR/2019/3084 3084 Box culvert Km 175+500 LHS 5-Aug-19 5:38 PM IPC-08 149
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-149,150,151,152
DONE
3148 NMSCEW/P-IV/STR/2019/3085 3085 Checking of reinforcement, shuttering for 2nd lift at A1 & A2 wall Box culvert Km 186+352 RHS 5-Aug-19 4:00 PM NR
3149 NMSCEW/P-IV/STR/2019/3086 3086 Checking & Pouring concrete(M-30) for 2nd lift at A1 & A2 wall Box culvert Km 186+352 RHS 5-Aug-19 4:37 PM NR
3150 NMSCEW/P-IV/STR/2019/3087 3087 Checking of reinforcement, shuttering for 1st lift at A1 wall Box culvert Km 182+350 RHS 5-Aug-19 9:00 AM IPC-08 DONE AE
3151 NMSCEW/P-IV/STR/2019/3088 3088 Checking & Pouring concrete(M-30) for 1st lift at A1 wall Box culvert Km 182+350 RHS 5-Aug-19 9:35 AM IPC-08 DONE AE
3152 NMSCEW/P-IV/STR/2019/3089 3089 Checking layout ,level and structural excavation MNB( LOOP) Km 01+980 BHS 5-Aug-19 9:15 AM NR
3153 NMSCEW/P-IV/STR/2019/3090 3090 Checking top Level & Laying concrete(M-15) PCC MNB( LOOP) Km 01+980 BHS 5-Aug-19 9:50 AM NR
3154 NMSCEW/P-IV/STR/2019/3091 3091 Checking layout ,level and structural excavation for retaining wall A1 & A2 PUP Km 184+190 RHS 5-Aug-19 11:30 AM NR
3155 NMSCEW/P-IV/STR/2019/3092 3092 Checking top Level & Laying concrete(M-10) PCC for retaining wall A1 & A2 PUP Km 184+190 RHS 5-Aug-19 12:30 PM NR
3156 NMSCEW/P-IV/STR/2019/3093 3093 Checking of reinforcement, shuttering for raft at RP-5 Viaduct Km 196+560 RHS 5-Aug-19 3:00 PM SPOT RFI
3157 NMSCEW/P-IV/STR/2019/3094 3094 Checking & pouring concrete(M-35) for raft at RP-5 Viaduct Km 196+560 RHS 5-Aug-19 4:00 PM SPOT RFI
3158 NMSCEW/P-IV/STR/2019/3095 3095 Checking of reinforcement, shuttering for 1st lift at A1 & A2 wall PUP Km 164+380 Km 00+000 RHS 6-Aug-19 4:00 PM IPC-09 DONE AE
3159 NMSCEW/P-IV/STR/2019/3096 3096 Checking & Pouring concrete for 1st lift at A1 & A2 wall PUP Km 164+380 Km 00+000 RHS 6-Aug-19 4:45 PM IPC-09 DONE AE
3160 NMSCEW/P-IV/STR/2019/3097 3097 Checking of reinforcement, shuttering for 2nd lift at A1 & A2 wall Box culvert Km 186+352 RHS 6-Aug-19 4:15 PM NR
3161 NMSCEW/P-IV/STR/2019/3098 3098 Checking & Pouring concrete(M-30) for 2nd lift at A1 & A2 wall Box culvert Km 186+352 RHS 6-Aug-19 5:00 PM NR
3162 NMSCEW/P-IV/STR/2019/3099 3099 Checking layout ,level and structural excavation MNB( LOOP) 1+980 Km 00+000 BHS 6-Aug-19 8:00 AM IPC-10 DONE AE
3163 NMSCEW/P-IV/STR/2019/3100 3100 Checking top Level & Laying concrete(M-15) PCC MNB( LOOP) 1+980 Km 00+000 BHS 6-Aug-19 9:15 AM IPC-10 DONE
3164 NMSCEW/P-IV/STR/2019/3101 3101 Checking layout ,level and structural excavation for retaining wall A1 & A2 PUP Km 184+190 RHS 6-Aug-19 11:30 AM NR
3165 NMSCEW/P-IV/STR/2019/3102 3102 Checking top Level & Laying concrete(M-10) PCC for retaining wall A1 & A2 PUP Km 184+190 RHS 6-Aug-19 12:30 PM NR
3166 NMSCEW/P-IV/STR/2019/3103 3103 Checking of reinforcement, shuttering for 1st lift at A1 & A2 wall PUP Km 187+835 LHS 6-Aug-19 9:00 AM NR
3167 NMSCEW/P-IV/STR/2019/3104 3104 Checking & Pouring concrete(M-30) for 1st lift at A1 & A2 wall PUP Km 187+835 LHS 6-Aug-19 9:30 AM NR
Checking reinforcement for precast Box Culvert (3x3) (Cushion 4 to 6 m) at precast yard camp
3168 NMSCEW/P-IV/STR/2019/3105 3105 Box culvert Km 175+500 LHS 6-Aug-19 12:40 PM DONE
-1. Segment NO-14,15,16,17,18
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3169 NMSCEW/P-IV/STR/2019/3106 3106 Box culvert Km 175+500 LHS 6-Aug-19 4:32 PM DONE
(3x3) (Cushion 4 to 6 m) at precast yard camp-1,Segment no.-14,15,16,17,18
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
3170 NMSCEW/P-IV/STR/2019/3107 3107 Box culvert Km 175+500 LHS 6-Aug-19 9:27 AM DONE
-1. Segment NO-124,125,126
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3171 NMSCEW/P-IV/STR/2019/3108 3108 Box culvert Km 175+500 LHS 6-Aug-19 10:33 AM DONE
(2x2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-124,125,126
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
3172 NMSCEW/P-IV/STR/2019/3109 3109 Box culvert Km 175+500 LHS 6-Aug-19 12:49 PM IPC-08 150, 151, 152, 153
-1. Segment NO-150, 151, 152, 153 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3173 NMSCEW/P-IV/STR/2019/3110 3110 Box culvert Km 175+500 LHS 6-Aug-19 5:37 PM IPC-08 150, 151, 152, 153
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-150, 151, 152, 153
DONE
3174 NMSCEW/P-IV/STR/2019/3111 3111 Checking of reinforcement, shuttering for pier starter at RP-4 Viaduct Km 202+190 Km 00+000 RHS 6-Aug-19 12:07 PM IPC-10 DONE AE
3175 NMSCEW/P-IV/STR/2019/3112 3112 Checking & pouring concrete for pier starter at RP-4 Viaduct Km 202+190 Km 00+000 RHS 6-Aug-19 12:42 PM IPC-10 DONE AE
3176 NMSCEW/P-IV/STR/2019/3113 3113 Checking of reinforcement, shuttering for pier shaft final lift at LP-4 Viaduct Km 202+190 LHS 6-Aug-19 11:12 AM
3177 NMSCEW/P-IV/STR/2019/3114 3114 Checking & pouring concrete for pier shaft final lift at LP-4 Viaduct Km 202+190 LHS 6-Aug-19 12:18 PM
3178 NMSCEW/P-IV/STR/2019/3115 3115 Checking of reinforcement, shuttering for pier shaft 1st lift at RP-9 Viaduct Km 169+800 RHS 6-Aug-19 10:00 AM IPC-08 DONE AE
3179 NMSCEW/P-IV/STR/2019/3116 3116 Checking & pouring concrete for pier shaft 1st lift at RP-9 Viaduct Km 169+800 RHS 6-Aug-19 10:05 AM IPC-08 DONE AE
3180 NMSCEW/P-IV/STR/2019/3117 3117 Checking layout ,level and structural excavation for median wall PUP Km 172+190 BHS 7-Aug-19 8:30 AM DONE
3181 NMSCEW/P-IV/STR/2019/3118 3118 Checking top Level & Laying concrete PCC for median wall PUP Km 172+190 BHS 7-Aug-19 12:59 PM DONE
3182 NMSCEW/P-IV/STR/2019/3119 3119 Checking layout ,level and structural excavation for median wall PUP Km 174+095 BHS 7-Aug-19 11:30 AM DONE
3183 NMSCEW/P-IV/STR/2019/3120 3120 Checking top Level & Laying concrete PCC for median wall PUP Km 174+095 BHS 7-Aug-19 2:20 PM DONE
3184 NMSCEW/P-IV/STR/2019/3121 3121 Checking layout ,level and structural excavation Box culvert Km 180+110 BHS 7-Aug-19 9:30 AM DONE
3185 NMSCEW/P-IV/STR/2019/3122 3122 Checking of reinforcement, shuttering & layout for pier shaft 1st lift at LP-6 Viaduct Km 195+900 LHS 7-Aug-19 11:00 AM IPC-14
3186 NMSCEW/P-IV/STR/2019/3123 3123 Checking & pouring concrete for pier shaft 1st lift at LP-6 Viaduct Km 195+900 LHS 7-Aug-19 11:45 AM
3187 NMSCEW/P-IV/STR/2019/3124 3124 Checking & pouring concrete(M-35) for raft at RP-5 Viaduct Km 196+560 RHs 7-Aug-19 10:00 AM
3188 NMSCEW/P-IV/STR/2019/3125 3125 Checking layout ,level and structural excavation VUP Km 166+987 BHS 7-Aug-19 10:30 AM DONE
3189 NMSCEW/P-IV/STR/2019/3126 3126 Checking top Level & Laying concrete PCC VUP Km 166+987 RHs 7-Aug-19 12:00 PM DONE
Checking reinforcement for precast Box Culvert (3x3) (Cushion 4 to 6 m) at precast yard camp
3190 NMSCEW/P-IV/STR/2019/3127 3127 Box culvert Km 175+500 LHS 7-Aug-19 12:35 PM DONE
-1. Segment NO-14,15
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3191 NMSCEW/P-IV/STR/2019/3128 3128 Box culvert Km 175+500 LHS 7-Aug-19 4:22 PM DONE
(3x3) (Cushion 4 to 6 m) at precast yard camp-1,Segment no.-11,12,13,14,15
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
3192 NMSCEW/P-IV/STR/2019/3129 3129 Box culvert Km 175+500 LHS 7-Aug-19 9:18 AM DONE
-1. Segment NO-124,125
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3193 NMSCEW/P-IV/STR/2019/3130 3130 Box culvert Km 175+500 LHS 7-Aug-19 10:21 AM DONE
(2x2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-116,124,125
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
3194 NMSCEW/P-IV/STR/2019/3131 3131 Box culvert Km 175+500 LHS 7-Aug-19 12:55 PM MISSING
-1. Segment NO-153
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3195 NMSCEW/P-IV/STR/2019/3132 3132 Box culvert Km 175+500 LHS 7-Aug-19 5:52 PM MISSING
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-150,151,152,153
3196 NMSCEW/P-IV/STR/2019/3133 3133 Checking of reinforcement, shuttering for pier starter at RP-5 Viaduct Km 202+190 Km 00+000 RHS 7-Aug-19 12:15 PM IPC-10 DONE
3197 NMSCEW/P-IV/STR/2019/3134 3134 Checking & pouring concrete for pier starter at RP-5 Viaduct Km 202+190 Km 00+000 RHS 7-Aug-19 12:45 PM IPC-10 DONE AE
3198 NMSCEW/P-IV/STR/2019/3135 3135 Checking of reinforcement, shuttering for 2nd lift at A1 & A2 wall Box culvert Km 186+352 RHS 7-Aug-19 11:30 AM REPEATED SPOT RFI
3199 NMSCEW/P-IV/STR/2019/3136 3136 Checking & Pouring concrete(M-30) for 2nd lift at A1 & A2 wall Box culvert Km 186+352 RHS 7-Aug-19 12:15 PM REPEATED SPOT RFI
3200 NMSCEW/P-IV/STR/2019/3137 3137 Checking of reinforcement, shuttering for 1st lift at A1 & A2 wall Box culvert Km 186+352 LHS 7-Aug-19 11:00 AM NR SPOT RFI
3201 NMSCEW/P-IV/STR/2019/3138 3138 Checking & Pouring concrete(M-30) for 1st lift at A1 & A2 wall Box culvert Km 186+352 LHS 7-Aug-19 12:30 PM NR SPOT RFI
3202 NMSCEW/P-IV/STR/2019/3139 3139 Checking of reinforcement, shuttering for 1st lift at A1 & A2 wall PUP Km 187+835 LHS 7-Aug-19 11:45 AM NR SPOT RFI
3203 NMSCEW/P-IV/STR/2019/3140 3140 Checking & Pouring concrete(M-30) for 1st lift at A1 & A2 wall PUP Km 187+835 LHS 7-Aug-19 12:45 PM NR SPOT RFI
3204 NMSCEW/P-IV/STR/2019/3141 3141 Checking of reinforcement, shuttering for pier shaft final lift at LP-1 Viaduct Km 202+190 LHS 7-Aug-19 3:15 PM SPOT RFI
3205 NMSCEW/P-IV/STR/2019/3142 3142 Checking & pouring concrete for pier shaft final lift at LP-1 Viaduct Km 202+190 LHS 7-Aug-19 3:50 PM SPOT RFI
3206 NMSCEW/P-IV/STR/2019/3143 3143 Checking of reinforcement & shuttering for bottom hunch of wall A1& A2 Box culvert Km 180+427 RHS 8-Aug-19 10:30 AM NR
3207 NMSCEW/P-IV/STR/2019/3144 3144 Checking & pouring concrete for bottom hunch of wall A1& A2 Box culvert Km 180+427 RHS 8-Aug-19 11:30 AM NR
Checking reinforcement for precast Box Culvert (3x3) (cushion 2 to 4m) at precast yard camp
3208 NMSCEW/P-IV/STR/2019/3145 3145 Box culvert Km 200+200 LHS 8-Aug-19 9:00 AM DONE
-2. Segment NO-27,28,29
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3209 NMSCEW/P-IV/STR/2019/3146 3146 Box culvert Km 200+200 LHS 8-Aug-19 10:30 AM DONE
(3x3),(Cushion 2 to 4m) at precast yard camp-2,Segment no.-27,28,29
Checking reinforcement for precast Box Culvert (3x3) (cushion 0 to 2m) at precast yard camp
3210 NMSCEW/P-IV/STR/2019/3147 3147 Box culvert Km 200+200 LHS 8-Aug-19 9:30 AM DONE
-2. Segment NO-97,98,99,100,101
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3211 NMSCEW/P-IV/STR/2019/3148 3148 Box culvert Km 200+200 LHS 8-Aug-19 11:30 AM DONE
(3x3),(cushion 0 to 2m)) at precast yard camp-2,Segment no.-97,98,99,100,101
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
3212 NMSCEW/P-IV/STR/2019/3149 3149 Box culvert Km 200+200 LHS 8-Aug-19 12:30 PM DONE
-2. Segment NO-217,218,219,220,221,222,223
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3213 NMSCEW/P-IV/STR/2019/3150 3150 Box culvert Km 200+200 LHS 8-Aug-19 2:30 PM DONE
(2×2),(Cushion 2 to 4m) at precast yard camp-2,Segment no.-217,218,219,220,221,222,223
Checking reinforcement for precast Box Culvert (3x3) (Cushion 4 to 6 m) at precast yard camp
3214 NMSCEW/P-IV/STR/2019/3151 3151 Box culvert Km 175+500 LHS 8-Aug-19 12:20 PM DONE
-1. Segment NO-19,20,21,22,23
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3215 NMSCEW/P-IV/STR/2019/3152 3152 Box culvert Km 175+500 LHS 8-Aug-19 4:10 PM DONE
(3x3) (Cushion 4 to 6 m) at precast yard camp-1,Segment no.-19,20,21,22,23
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
3216 NMSCEW/P-IV/STR/2019/3153 3153 Box culvert Km 175+500 LHS 8-Aug-19 9:25 AM DONE
-1. Segment NO-127,128,129
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3217 NMSCEW/P-IV/STR/2019/3154 3154 Box culvert Km 175+500 LHS 8-Aug-19 10:15 AM DONE
(2x2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-127,128,129
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
3218 NMSCEW/P-IV/STR/2019/3155 3155 Box culvert Km 175+500 LHS 8-Aug-19 12:40 PM IPC-08 154, 155, 156, 157
-1. Segment NO-154, 155, 156, 157 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3219 NMSCEW/P-IV/STR/2019/3156 3156 Box culvert Km 175+500 LHS 8-Aug-19 5:21 PM IPC-08 154, 155, 156, 157
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-154,155,156,157
DONE
3220 NMSCEW/P-IV/STR/2019/3157 3157 Checking top Level & Laying concrete PCC VUP Km 166+987 LHS 8-Aug-19 4:02 PM NR
3221 NMSCEW/P-IV/STR/2019/3158 3158 Checking of reinforcement, shuttering for 2nd lift at A1 wall LVUP Km 169+291 LHS 8-Aug-19 5:00 PM NR
3222 NMSCEW/P-IV/STR/2019/3159 3159 Checking & Pouring concrete for 2nd lift at A1 wall LVUP Km 169+291 LHS 8-Aug-19 5:35 PM NR
3223 NMSCEW/P-IV/STR/2019/3160 3160 Checking of reinforcement, shuttering for pier shaft 1st lift at RP-11 Viaduct Km 169+800 RHS 8-Aug-19 2:00 PM NR
3224 NMSCEW/P-IV/STR/2019/3161 3161 Checking & pouring concrete for pier shaft 1st lift at RP-11 Viaduct Km 169+800 RHS 8-Aug-19 2:30 PM NR
3225 NMSCEW/P-IV/STR/2019/3162 3162 Checking of reinforcement, shuttering for pier shaft 1st lift at LP-10 Viaduct Km 169+800 LHS 8-Aug-19 3:00 PM NR
3226 NMSCEW/P-IV/STR/2019/3163 3163 Checking & pouring concrete for pier shaft 1st lift at LP-10 Viaduct Km 169+800 LHS 8-Aug-19 3:30 PM NR
3227 NMSCEW/P-IV/STR/2019/3164 3164 Checking of reinforcement, shuttering for pier starter at RP-10 Viaduct Km 196+560 Km 00+000 RHS 8-Aug-19 10:00 AM IPC-09 DONE AE
3228 NMSCEW/P-IV/STR/2019/3165 3165 Checking & pouring concrete for pier starter at RP-10 Viaduct Km 196+560 Km 00+000 RHS 8-Aug-19 10:30 AM IPC-09 DONE AE
3229 NMSCEW/P-IV/STR/2019/3166 3166 Checking of reinforcement, shuttering for pier starter at LP-4 Viaduct Km 196+560 Km 00+000 LHS 8-Aug-19 11:30 AM IPC-10 DONE AE
3230 NMSCEW/P-IV/STR/2019/3167 3167 Checking & pouring concrete for pier starter at LP-4 Viaduct Km 196+560 Km 00+000 LHS 8-Aug-19 12:00 PM IPC-10 DONE AE
3231 NMSCEW/P-IV/STR/2019/3168 3168 Checking of layput & level, reinforcement, shuttering for pier shaft 1st lift at LP-7 Viaduct Km 202+190 LHS 8-Aug-19 12:05 PM
3232 NMSCEW/P-IV/STR/2019/3169 3169 Checking & pouring concrete for pier shaft 1st lift at LP-7 Viaduct Km 202+190 LHS 8-Aug-19 12:39 PM
Checking reinforcement for precast Box Culvert (3x3) (cushion 0 to 2m) at precast yard camp
3233 NMSCEW/P-IV/STR/2019/3170 3170 Box culvert Km 200+200 LHS 9-Aug-19 9:00 AM DONE
-2. Segment NO-102,103,104
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3234 NMSCEW/P-IV/STR/2019/3171 3171 Box culvert Km 200+200 LHS 9-Aug-19 10:30 AM DONE
(3x3),(cushion 0 to 2m)) at precast yard camp-2,Segment no.-102,103,104
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
3235 NMSCEW/P-IV/STR/2019/3172 3172 Box culvert Km 200+200 LHS 9-Aug-19 9:30 AM DONE
-2. Segment NO-224,225,226,227,228,229,230,231,232,233,234
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3236 NMSCEW/P-IV/STR/2019/3173 3173 (2×2),(Cushion 2 to 4m) at precast yard camp-2,Segment no.- Box culvert Km 200+200 LHS 9-Aug-19 11:00 AM DONE
224,225,226,227,228,229,230,231,232,233,234
3237 NMSCEW/P-IV/STR/2019/3174 3174 Checking & pouring concrete for pier shaft 1st lift at LP-06 Viaduct Km 195+000 LHS 9-Aug-19 11:45 AM IPC-14
3238 NMSCEW/P-IV/STR/2019/3175 3175 Checking of reinforcement, shuttering for pier shaft final lift at LP-4 Viaduct Km 202+190 LHS 9-Aug-19 10:00 AM IPC-08 DONE AE
3239 NMSCEW/P-IV/STR/2019/3176 3176 Checking & pouring concrete for pier shaft final lift at LP-4 Viaduct Km 202+190 LHS 9-Aug-19 11:15 AM IPC-08 DONE AE
3240 NMSCEW/P-IV/STR/2019/3177 3177 Checking of reinforcement, shuttering for pier shaft final lift at LP-1 Viaduct Km 202+190 LHS 9-Aug-19 11:30 AM IPC-08 DONE AE
3241 NMSCEW/P-IV/STR/2019/3178 3178 Checking & pouring concrete for pier shaft final lift at LP-1 Viaduct Km 202+190 LHS 9-Aug-19 12:15 PM IPC-08 DONE AE
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
3242 NMSCEW/P-IV/STR/2019/3179 3179 Box culvert Km 200+200 LHS 10-Aug-19 9:35 AM DONE
-2. Segment NO-235,236,237,238,239,240,241,242,243,244
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3243 NMSCEW/P-IV/STR/2019/3180 3180 (2×2),(Cushion 2 to 4m) at precast yard camp-2,Segment no.- Box culvert Km 200+200 LHS 10-Aug-19 11:10 AM DONE
235,236,237,238,239,240,241,242,243,244
Checking reinforcement for precast Box Culvert (3x3) (cushion 0 to 2m) at precast yard camp
3244 NMSCEW/P-IV/STR/2019/3181 3181 Box culvert Km 200+200 LHS 10-Aug-19 9:10 AM DONE
-2. Segment NO-105,106,107
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3245 NMSCEW/P-IV/STR/2019/3182 3182 Box culvert Km 200+200 LHS 10-Aug-19 10:45 AM DONE
(3x3),(cushion 0 to 2m)) at precast yard camp-2,Segment no.-105,106,107
3246 NMSCEW/P-IV/STR/2019/3183 3183 Checking layout ,level for top slab PUP Km 191+740 RHS 10-Aug-19 11:00 AM DONE
3247 NMSCEW/P-IV/STR/2019/3184 3184 Checking reinforcement ,shuttering for top slab PUP Km 191+740 RHS 10-Aug-19 11:20 AM DONE
3248 NMSCEW/P-IV/STR/2019/3185 3185 Checking and concrete pouring for top slab PUP Km 191+740 RHS 10-Aug-19 12:35 PM DONE
3249 NMSCEW/P-IV/STR/2019/3186 3186 Checking of reinforcement, shuttering for bottom haunch at A1 & A2 wall Box culvert Km 180+427 RHS 10-Aug-19 10:22 AM IPC-08 DONE AE
3250 NMSCEW/P-IV/STR/2019/3187 3187 Checking & Pouring concrete for bottom haunch at A1 & A2 wall Box culvert Km 180+427 RHS 10-Aug-19 11:50 AM IPC-08 DONE AE
Stressing and remove slagness of H. T. Wires at Girder No. 5,6,7,8 for Casting Bed no. 2,
3251 NMSCEW/P-IV/STR/2019/3188 3188 Girder Km 200+200 LHS 10-Aug-19 10:12 AM
Girder Type-2, at Casting Yard-Camp-2
3252 NMSCEW/P-IV/STR/2019/3189 3189 Checking of reinforcement, shuttering for pier shaft 1st lift at RP-11 Viaduct Km 169+800 Km 00+000 RHS 10-Aug-19 2:00 PM IPC-09 DONE AE
3253 NMSCEW/P-IV/STR/2019/3190 3190 Checking & pouring concrete for pier shaft 1st lift at RP-11 Viaduct Km 169+800 Km 00+000 RHS 10-Aug-19 2:30 PM IPC-09 DONE AE
3254 NMSCEW/P-IV/STR/2019/3191 3191 Checking of reinforcement, shuttering for pier shaft 1st lift at LP-10 Viaduct Km 169+800 LHS 10-Aug-19 3:00 PM IPC-08 DONE AE
3255 NMSCEW/P-IV/STR/2019/3192 3192 Checking & pouring concrete for pier shaft 1st lift at LP-10 Viaduct Km 169+800 LHS 10-Aug-19 3:30 PM IPC-08 DONE AE
Checking of reinforcement of girder no- 5,6,7,8 for Bed no-2,Girder Type-2, at Casting Yard-
3256 NMSCEW/P-IV/STR/2019/3193 3193 Girder Km 200+200 LHS 10-Aug-19 11:23 AM
Camp-2
3257 NMSCEW/P-IV/STR/2019/3194 3194 Checking of reinforcement, shuttering for pier starter at RP-10 Viaduct Km 196+560 RHS 10-Aug-19 3:05 PM
3258 NMSCEW/P-IV/STR/2019/3195 3195 Checking & pouring concrete for pier starter at RP-10 Viaduct Km 196+560 RHS 10-Aug-19 3:35 PM
3259 NMSCEW/P-IV/STR/2019/3196 3196 Checking of reinforcement, shuttering for pier starter at LP-4 Viaduct Km 196+560 LHS 10-Aug-19 11:34 AM
3260 NMSCEW/P-IV/STR/2019/3197 3197 Checking & pouring concrete for pier starter at LP-4 Viaduct Km 196+560 LHS 10-Aug-19 12:12 PM
3261 NMSCEW/P-IV/STR/2019/3198 3198 Checking of reinforcement, shuttering for pier starter at LP-5 Viaduct Km 196+560 Km 00+000 LHS 10-Aug-19 12:35 PM IPC-10 DONE AE
3262 NMSCEW/P-IV/STR/2019/3199 3199 Checking & pouring concrete for pier starter at LP-5 Viaduct Km 196+560 Km 00+000 LHS 10-Aug-19 1:00 PM IPC-10 DONE AE
3263 NMSCEW/P-IV/STR/2019/3200 3200 Checking of reinforcement, shuttering for raft at RP-5 Viaduct Km 196+560 RHS 10-Aug-19 10:50 AM IPC-08 DONE AE
3264 NMSCEW/P-IV/STR/2019/3201 3201 Checking & pouring concrete for raft at RP-5 Viaduct Km 196+560 RHS 10-Aug-19 11:26 AM IPC-08 DONE AE
3265 NMSCEW/P-IV/STR/2019/3202 3202 Checking top Level & Laying concrete PCC VUP Km 166+987 LHS 10-Aug-19 4:00 PM DONE
Checking reinforcement for precast Box Culvert (3x3) (Cushion 4 to 6 m) at precast yard camp
3266 NMSCEW/P-IV/STR/2019/3203 3203 Box culvert Km 175+500 LHS 10-Aug-19 9:30 AM DONE
-1. Segment NO-20
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3267 NMSCEW/P-IV/STR/2019/3204 3204 Box culvert Km 175+500 LHS 10-Aug-19 10:15 AM DONE
(3x3) (Cushion 4 to 6 m) at precast yard camp-1,Segment no.-13,14,15,16,20
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
3268 NMSCEW/P-IV/STR/2019/3205 3205 Box culvert Km 175+500 LHS 10-Aug-19 12:18 PM DONE
-1. Segment NO-130,131,132
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3269 NMSCEW/P-IV/STR/2019/3206 3206 Box culvert Km 175+500 LHS 10-Aug-19 2:20 PM DONE
(2x2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-130,131,132
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
3270 NMSCEW/P-IV/STR/2019/3207 3207 Box culvert Km 175+500 LHS 10-Aug-19 4:10 PM IPC-08 158, 159, 160
-1. Segment NO-158,159,160 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3271 NMSCEW/P-IV/STR/2019/3208 3208 Box culvert Km 175+500 LHS 10-Aug-19 5:10 PM IPC-08 144, 158, 159, 160
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-144,158,159,160
DONE
3272 NMSCEW/P-IV/STR/2019/3209 3209 Checking of reinforcement, shuttering for 2nd lift at A1 & A2 wall LVUP Km 178+323 RHS 11-Aug-19 10:30 AM NR
3273 NMSCEW/P-IV/STR/2019/3210 3210 Checking & Pouring concrete for 2nd lift at A1 & A2 wall LVUP Km 178+323 RHS 11-Aug-19 11:30 AM NR
3274 NMSCEW/P-IV/STR/2019/3211 3211 Checking layout ,level and structural excavation for median wall PUP Km 171+110 BHS 11-Aug-19 8:15 AM DONE
3275 NMSCEW/P-IV/STR/2019/3212 3212 Checking top Level & Laying concrete PCC for median wall PUP Km 171+110 BHS 11-Aug-19 3:50 PM DONE
3276 NMSCEW/P-IV/STR/2019/3213 3213 Checking layout ,level and structural excavation Box culvert Km 180+180 BHS 11-Aug-19 8:50 AM DONE
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
3277 NMSCEW/P-IV/STR/2019/3214 3214 Box culvert Km 200+200 LHS 11-Aug-19 9:35 AM DONE
-2. Segment NO-245,246,247,248,249,250,251,252,253,254
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3278 NMSCEW/P-IV/STR/2019/3215 3215 (2×2),(Cushion 2 to 4m) at precast yard camp-2,Segment no.- Box culvert Km 200+200 LHS 11-Aug-19 11:10 AM DONE
245,246,247,248,249,250,251,252,253,254
3279 NMSCEW/P-IV/STR/2019/3216 3216 Checking of reinforcement, shuttering for 1st lift at W1 wall Box culvert Km 203+886 LHS 11-Aug-19 9:00 AM
3280 NMSCEW/P-IV/STR/2019/3217 3217 Checking & Pouring concrete for 1st lift at W1 wall Box culvert Km 203+886 LHS 11-Aug-19 9:10 AM
3281 NMSCEW/P-IV/STR/2019/3218 3218 Checking layout ,level and structural excavation Box culvert Km 187+677 BHS 11-Aug-19 9:20 AM NR
3282 NMSCEW/P-IV/STR/2019/3219 3219 Checking top Level & Laying concrete(M-15) PCC Box culvert Km 187+677 BHS 11-Aug-19 10:50 AM NR
3283 NMSCEW/P-IV/STR/2019/3220 3220 Checking of reinforcement, shuttering for pier starter at RP-3 Viaduct Km 196+560 Km 00+000 RHS 11-Aug-19 12:05 PM IPC-10 DONE AE
3284 NMSCEW/P-IV/STR/2019/3221 3221 Checking & pouring concrete for pier starter at RP-3 Viaduct Km 196+560 Km 00+000 RHS 11-Aug-19 12:37 PM IPC-10 DONE AE
3285 NMSCEW/P-IV/STR/2019/3222 3222 Checking of reinforcement,shuttering & pouring concrete for pier starter at RP-5 Viaduct Km 196+560 Km 00+000 RHS 11-Aug-19 10:48 AM IPC-11 Approved AE
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
3286 NMSCEW/P-IV/STR/2019/3223 3223 Box culvert Km 200+200 LHS 12-Aug-19 9:40 AM DONE
-2. Segment NO-255,256,257,258,259,260,261,262
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3287 NMSCEW/P-IV/STR/2019/3224 3224 (2×2),(Cushion 2 to 4m) at precast yard camp-2,Segment no.- Box culvert Km 200+200 LHS 12-Aug-19 10:35 AM DONE
255,256,257,258,259,260,261,262
Checking reinforcement for precast Box Culvert (3x3) (cushion 2 to 4m) at precast yard camp
3288 NMSCEW/P-IV/STR/2019/3225 3225 Box culvert Km 200+200 LHS 12-Aug-19 2:20 PM DONE
-2. Segment NO-30,31
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3289 NMSCEW/P-IV/STR/2019/3226 3226 Box culvert Km 200+200 LHS 12-Aug-19 3:30 PM DONE
(3x3),(Cushion 2 to 4m) at precast yard camp-2,Segment no.-30,31
Checking reinforcement for precast Box Culvert (3x3) (cushion 0 to 2m) at precast yard camp
3290 NMSCEW/P-IV/STR/2019/3227 3227 Box culvert Km 200+200 LHS 12-Aug-19 11:35 AM DONE
-2. Segment NO-108,109,110,111
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3291 NMSCEW/P-IV/STR/2019/3228 3228 Box culvert Km 200+200 LHS 12-Aug-19 12:30 PM DONE
(3x3),(cushion 0 to 2m)) at precast yard camp-2,Segment no.-108,109,110,111
3292 NMSCEW/P-IV/STR/2019/3229 3229 Checking of reinforcement, shuttering for pier starter at RP-6 Viaduct Km 202+190 RHS 12-Aug-19 10:00 AM
3293 NMSCEW/P-IV/STR/2019/3230 3230 Checking & pouring concrete for pier starter at RP-6 Viaduct Km 202+190 RHS 12-Aug-19 10:30 AM
3294 NMSCEW/P-IV/STR/2019/3231 3231 Checking of reinforcement, shuttering for pier starter at RP-7 Viaduct Km 202+190 RHS 12-Aug-19 10:15 AM
3295 NMSCEW/P-IV/STR/2019/3232 3232 Checking & pouring concrete for pier starter at RP-7 Viaduct Km 202+190 RHS 12-Aug-19 10:45 AM
3296 NMSCEW/P-IV/STR/2019/3233 3233 Checking layout ,level for PCC at RA1 Viaduct Km 202+190 RHS 12-Aug-19 2:00 PM IPC-08 DONE AE
3297 NMSCEW/P-IV/STR/2019/3234 3234 Checking top Level & Laying concrete for PCC at RA1 Viaduct Km 202+190 RHS 12-Aug-19 2:40 PM IPC-08 DONE AE
3298 NMSCEW/P-IV/STR/2019/3235 3235 Checking of reinforcement, shuttering for pier starter at RP-13 Viaduct Km 202+190 RHS 12-Aug-19 11:15 AM
3299 NMSCEW/P-IV/STR/2019/3236 3236 Checking layout ,level for pier starter at RP-13 Viaduct Km 202+190 RHS 12-Aug-19 11:30 AM
3300 NMSCEW/P-IV/STR/2019/3237 3237 Checking & pouring concrete for pier starter at RP-13 Viaduct Km 202+190 RHS 12-Aug-19 11:50 AM
3301 NMSCEW/P-IV/STR/2019/3238 3238 Checking of reinforcement, shuttering for pier shaft 1st lift at LP-7 Viaduct Km 202+190 LHS 12-Aug-19 12:10 PM IPC-08 DONE AE
3302 NMSCEW/P-IV/STR/2019/3239 3239 Checking & pouring concrete for pier shaft 1st lift at LP-7 Viaduct Km 202+190 LHS 12-Aug-19 12:40 PM IPC-08 DONE AE
3303 NMSCEW/P-IV/STR/2019/3240 3240 Checking of reinforcement, shuttering for pier shaft 2nd lift at RP-6 Viaduct Km 169+800 RHS 12-Aug-19 2:15 PM IPC-08 DONE AE
3304 NMSCEW/P-IV/STR/2019/3241 3241 Checking & pouring concrete for pier shaft 2nd lift at RP-6 Viaduct Km 169+800 RHS 12-Aug-19 2:45 PM IPC-08 DONE AE
3305 NMSCEW/P-IV/STR/2019/3242 3242 Checking of reinforcement, shuttering for pier shaft 2nd lift at LP-4 Viaduct Km 169+800 LHS 12-Aug-19 3:15 PM IPC-08 DONE AE
3306 NMSCEW/P-IV/STR/2019/3243 3243 Checking & pouring concrete for pier shaft 2nd lift at LP-4 Viaduct Km 169+800 LHS 12-Aug-19 3:45 PM IPC-08 DONE
Checking of side shuttering girder no- 5,6,7 & 8 at bed no-02 ,Girder Type-2, at Casting Yard-
3307 NMSCEW/P-IV/STR/2019/3244 3244 Camp-2 Girder Km 200+200 LHS 12-Aug-19 2:20 PM
Checking & pouring concrete(M-50) of girder no- 5,6,7 & 8 at bed no-02 ,Girder Type-2, at
3308 NMSCEW/P-IV/STR/2019/3245 3245 Casting Yard-Camp-2 Girder Km 200+200 LHS 12-Aug-19 4:10 PM
Checking reinforcement for precast Box Culvert (3x3) (Cushion 4 to 6 m) at precast yard camp
3309 NMSCEW/P-IV/STR/2019/3246 3246 Box culvert Km 175+500 LHS 12-Aug-19 9:18 AM DONE
-1. Segment NO-21,22,23,24,25
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3310 NMSCEW/P-IV/STR/2019/3247 3247 Box culvert Km 175+500 LHS 12-Aug-19 10:27 AM DONE
(3x3) (Cushion 4 to 6 m) at precast yard camp-1,Segment no.-21,22,23,24,25
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
3311 NMSCEW/P-IV/STR/2019/3248 3248 Box culvert Km 175+500 LHS 12-Aug-19 12:22 PM DONE
-1. Segment NO-133,134,135
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3312 NMSCEW/P-IV/STR/2019/3249 3249 Box culvert Km 175+500 LHS 12-Aug-19 2:34 PM DONE
(2x2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-133,134,135
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
3313 NMSCEW/P-IV/STR/2019/3250 3250 Box culvert Km 175+500 LHS 12-Aug-19 4:19 PM IPC-08 161, 162, 163, 164
-1. Segment NO-161,162,163,164 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3314 NMSCEW/P-IV/STR/2019/3251 3251 Box culvert Km 175+500 LHS 12-Aug-19 5:36 PM IPC-08 161
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-161,162,163,164
DONE
3315 NMSCEW/P-IV/STR/2019/3252 3252 Checking of reinforcement, shuttering for 2nd lift at A1 & A2 wall LVUP Km 169+291 LHS 12-Aug-19 4:33 PM IPC-08 DONE AE
3316 NMSCEW/P-IV/STR/2019/3253 3253 Checking & Pouring concrete for 2nd lift at A1 & A2 wall LVUP Km 169+291 LHS 12-Aug-19 4:55 PM IPC-08 DONE AE
3317 NMSCEW/P-IV/STR/2019/3254 3254 Checking of reinforcement, shuttering for 1st lift at A1 & A2 wall PUP Km 187+835 LHS 12-Aug-19 11:02 AM REPEATED
3318 NMSCEW/P-IV/STR/2019/3255 3255 Checking & Pouring concrete(M-30) for 1st lift at A1 & A2 wall PUP Km 187+835 LHS 12-Aug-19 11:39 AM REPEATED
3319 NMSCEW/P-IV/STR/2019/3256 3256 Checking of reinforcement, shuttering for 1st lift at A1 & A2 wall Box culvert Km 186+352 LHS 12-Aug-19 11:14 AM REPEATED
3320 NMSCEW/P-IV/STR/2019/3257 3257 Checking & Pouring concrete(M-30) for 1st lift at A1 & A2 wall Box culvert Km 186+352 LHS 12-Aug-19 11:55 AM REPEATED
3321 NMSCEW/P-IV/STR/2019/3258 3258 Checking layout ,level and structural excavation Box culvert Km 187+677 Km 00+000 BHS 12-Aug-19 2:00 PM IPC-09 DONE SPOT RFI
3322 NMSCEW/P-IV/STR/2019/3259 3259 Checking top Level & Laying concrete PCC Box culvert Km 187+677 Km 00+000 BHS 12-Aug-19 2:20 PM IPC-09 DONE SPOT RFI
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
3323 NMSCEW/P-IV/STR/2019/3260 3260 Box culvert Km 200+200 LHS 13-Aug-19 9:30 AM DONE
-2. Segment NO-263,264,265,266,267,268,269
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3324 NMSCEW/P-IV/STR/2019/3261 3261 Box culvert Km 200+200 LHS 13-Aug-19 10:50 AM DONE
(2×2),(Cushion 2 to 4m) at precast yard camp-2,Segment no.-263,264,265,266,267,268,269
3325 NMSCEW/P-IV/STR/2019/3262 3262 Checking of reinforcement, shuttering for 4th lift at A1 & A2 wall VUP Km 179+983 RHS 13-Aug-19 10:30 AM IPC-08 DONE AE
3326 NMSCEW/P-IV/STR/2019/3263 3263 Checking & Pouring concrete for 4th lift at A1 & A2 wall VUP Km 179+983 RHS 13-Aug-19 11:30 AM IPC-08 DONE AE
3327 NMSCEW/P-IV/STR/2019/3264 3264 Checking of reinforcement, shuttering for 5th lift at A1 & A2 wall VUP Km 176+614 LHS 13-Aug-19 11:40 AM IPC-08 DONE AE
3328 NMSCEW/P-IV/STR/2019/3265 3265 Checking & Pouring concrete for 5th lift at A1 & A2 wall VUP Km 176+614 LHS 13-Aug-19 12:40 PM IPC-08 DONE AE
3329 NMSCEW/P-IV/STR/2019/3266 3266 Checking of reinforcement, shuttering for raft at RP-2 Viaduct Km 196+560 RHS 13-Aug-19 11:00 AM IPC-08 DONE
3330 NMSCEW/P-IV/STR/2019/3267 3267 Checking & pouring concrete for raft at RP-2 Viaduct Km 196+560 RHS 13-Aug-19 11:30 AM
3331 NMSCEW/P-IV/STR/2019/3268 3268 Checking of reinforcement, shuttering for pier shaft 1st lift at RP-10 Viaduct Km 169+800 RHS 13-Aug-19 11:15 AM IPC-08 DONE AE
3332 NMSCEW/P-IV/STR/2019/3269 3269 Checking & pouring concrete for pier shaft 1st lift at RP-10 Viaduct Km 169+800 RHS 13-Aug-19 11:45 AM NR
3333 NMSCEW/P-IV/STR/2019/3270 3270 Checking of reinforcement, shuttering for pier starter at RP-6 Viaduct Km 202+190 Km 00+000 RHS 13-Aug-19 4:30 PM IPC-10 DONE AE
3334 NMSCEW/P-IV/STR/2019/3271 3271 Checking & pouring concrete for pier starter at RP-6 Viaduct Km 202+190 Km 00+000 RHS 13-Aug-19 5:00 PM IPC-10 DONE AE
3335 NMSCEW/P-IV/STR/2019/3272 3272 Checking of reinforcement, shuttering for pier starter at RP-7 Viaduct Km 202+190 Km 00+000 RHS 13-Aug-19 3:30 PM IPC-10 DONE AE
3336 NMSCEW/P-IV/STR/2019/3273 3273 Checking & pouring concrete for pier starter at RP-7 Viaduct Km 202+190 Km 00+000 RHS 13-Aug-19 4:05 PM IPC-10 DONE AE
3337 NMSCEW/P-IV/STR/2019/3274 3274 Checking layout ,level for raft at LA1 Viaduct Km 202+190 LHS 13-Aug-19 3:00 PM
3338 NMSCEW/P-IV/STR/2019/3275 3275 Checking of reinforcement, shuttering for raft at LA1 Viaduct Km 202+190 LHS 13-Aug-19 3:15 PM IPC-08 DONE AE
3339 NMSCEW/P-IV/STR/2019/3276 3276 Checking & pouring concrete for raft at LA1 Viaduct Km 202+190 LHS 13-Aug-19 3:35 PM IPC-08 DONE AE
3340 NMSCEW/P-IV/STR/2019/3277 3277 Checking layout ,level for pier starter at RP-13 Viaduct Km 202+190 Km 00+000 RHS 13-Aug-19 2:00 PM IPC-10 DONE AE
3341 NMSCEW/P-IV/STR/2019/3278 3278 Checking of reinforcement, shuttering for pier starter at RP-13 Viaduct Km 202+190 Km 00+000 RHS 13-Aug-19 2:15 PM IPC-10 DONE AE
3342 NMSCEW/P-IV/STR/2019/3279 3279 Checking & pouring concrete for pier starter at RP-13 Viaduct Km 202+190 Km 00+000 RHS 13-Aug-19 2:30 PM IPC-10 DONE AE
3343 NMSCEW/P-IV/STR/2019/3280 3280 Checking of reinforcement, shuttering for pier shaft 1st lift at LP-11 Viaduct Km 169+800 LHS 13-Aug-19 12:00 PM NR
3344 NMSCEW/P-IV/STR/2019/3281 3281 Checking & pouring concrete for pier shaft 1st lift at LP-11 Viaduct Km 169+800 LHS 13-Aug-19 12:42 PM NR
Checking reinforcement for precast Box Culvert (3x3) (Cushion 4 to 6 m) at precast yard camp
3345 NMSCEW/P-IV/STR/2019/3282 3282 Box culvert Km 175+500 LHS 13-Aug-19 9:20 AM DONE
-1. Segment NO-26,27,28
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3346 NMSCEW/P-IV/STR/2019/3283 3283 Box culvert Km 175+500 LHS 13-Aug-19 10:42 AM DONE
(3x3) (Cushion 4 to 6 m) at precast yard camp-1,Segment no.-24,25,26,27,28
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
3347 NMSCEW/P-IV/STR/2019/3284 3284 Box culvert Km 175+500 LHS 13-Aug-19 12:33 PM DONE
-1. Segment NO-136,137
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3348 NMSCEW/P-IV/STR/2019/3285 3285 Box culvert Km 175+500 LHS 13-Aug-19 2:26 PM DONE
(2x2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-135,136,137
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
3349 NMSCEW/P-IV/STR/2019/3286 3286 Box culvert Km 175+500 LHS 13-Aug-19 4:11 PM IPC-08 165
-1. Segment NO-165 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3350 NMSCEW/P-IV/STR/2019/3287 3287 Box culvert Km 175+500 LHS 13-Aug-19 5:42 PM IPC-08 162, 163
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-162,163,164,165
DONE
3351 NMSCEW/P-IV/STR/2019/3288 3288 Checking of reinforcement, shuttering for 1st lift at W2 wall PUP Km 193+880 LHS 13-Aug-19 9:00 AM
3352 NMSCEW/P-IV/STR/2019/3289 3289 Checking & Pouring concrete for 1st lift at W2 wall PUP Km 193+880 LHS 13-Aug-19 10:00 AM
3353 NMSCEW/P-IV/STR/2019/3290 3290 Checking of reinforcement, shuttering for 1st lift at W1 wall PUP Km 193+880 LHS 13-Aug-19 12:00 PM
3354 NMSCEW/P-IV/STR/2019/3291 3291 Checking & Pouring concrete for 1st lift at W1 wall PUP Km 193+880 LHS 13-Aug-19 2:00 PM
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
3355 NMSCEW/P-IV/STR/2019/3292 3292 Box culvert Km 200+200 LHS 14-Aug-19 9:20 AM DONE
-2. Segment NO-270,271,272,273,274,275,276
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3356 NMSCEW/P-IV/STR/2019/3293 3293 Box culvert Km 200+200 LHS 14-Aug-19 10:40 AM DONE
(2×2),(Cushion 2 to 4m) at precast yard camp-2,Segment no.-270,271,272,273,274,275,276
3357 NMSCEW/P-IV/STR/2019/3294 3294 Checking of completion of segment errection for 2x2 utility duct Utility duct Km 198+770 BHS 14-Aug-19 10:00 AM IPC-08 DONE
3358 NMSCEW/P-IV/STR/2019/3295 3295 Checking of reinforcement, shuttering for 1st lift at W2 wall Box culvert Km 203+886 RHS 14-Aug-19 4:00 PM
3359 NMSCEW/P-IV/STR/2019/3296 3296 Checking & Pouring concrete for 1st lift at W2 wall Box culvert Km 203+886 RHS 14-Aug-19 5:00 PM
3360 NMSCEW/P-IV/STR/2019/3297 3297 Checking layout ,level for raft Box culvert Km 192+039 RHS 14-Aug-19 9:00 AM DONE
3361 NMSCEW/P-IV/STR/2019/3298 3298 Checking of reinforcement, shuttering for raft Box culvert Km 192+039 RHS 14-Aug-19 9:30 AM DONE
3362 NMSCEW/P-IV/STR/2019/3299 3299 Checking & pouring concrete for raft Box culvert Km 192+039 RHS 14-Aug-19 10:15 AM DONE
3363 NMSCEW/P-IV/STR/2019/3300 3300 Checking of reinforcement, shuttering for 1st lift at A1 wall Box culvert Km 186+352 LHS 14-Aug-19 11:30 AM REPEATED
3364 NMSCEW/P-IV/STR/2019/3301 3301 Checking & Pouring concrete(M-30) for 1st lift at A1 wall Box culvert Km 186+352 LHS 14-Aug-19 12:30 PM REPEATED
3365 NMSCEW/P-IV/STR/2019/3302 3302 Checking of reinforcement, shuttering for 1st lift at A2 wall Box culvert Km 182+350 RHS 14-Aug-19 2:15 PM IPC-08 DONE AE
3366 NMSCEW/P-IV/STR/2019/3303 3303 Checking & Pouring concrete(M-30) for 1st lift at A2 wall Box culvert Km 182+350 RHS 14-Aug-19 3:15 PM IPC-08 DONE AE
Checking reinforcement for precast Box Culvert (3x3) (Cushion 4 to 6 m) at precast yard camp
3367 NMSCEW/P-IV/STR/2019/3304 3304 Box culvert Km 175+500 LHS 14-Aug-19 9:40 AM DONE
-1. Segment NO-29,30,31,32
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3368 NMSCEW/P-IV/STR/2019/3305 3305 Box culvert Km 175+500 LHS 14-Aug-19 10:35 AM DONE
(3x3) (Cushion 4 to 6 m) at precast yard camp-1,Segment no.-29,30,31
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
3369 NMSCEW/P-IV/STR/2019/3306 3306 Box culvert Km 175+500 LHS 14-Aug-19 4:21 PM IPC-08 166
-1. Segment NO-166 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3370 NMSCEW/P-IV/STR/2019/3307 3307 Box culvert Km 175+500 LHS 14-Aug-19 5:50 PM IPC-08 126
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-126,128,129 DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3371 NMSCEW/P-IV/STR/2019/3308 3308 Box culvert Km 175+500 LHS 14-Aug-19 2:50 PM DONE
(2x2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-126,128,129
3372 NMSCEW/P-IV/STR/2019/3309 3309 Checking of reinforcement, shuttering for pier shaft 2nd lift at RP-03 Viaduct Km 169+800 RHS 14-Aug-19 2:00 PM NR
3373 NMSCEW/P-IV/STR/2019/3310 3310 Checking & pouring concrete for pier shaft 2nd lift at RP-03 Viaduct Km 169+800 RHS 14-Aug-19 2:30 PM NR
3374 NMSCEW/P-IV/STR/2019/3311 3311 Checking of reinforcement, shuttering for pier shaft 1st lift at LP-11 Viaduct Km 169+800 Km 00+000 LHS 14-Aug-19 3:00 PM IPC-09 DONE AE
3375 NMSCEW/P-IV/STR/2019/3312 3312 Checking & pouring concrete for pier shaft 1st lift at LP-11 Viaduct Km 169+800 Km 00+000 LHS 14-Aug-19 3:30 PM IPC-09 DONE AE
3376 NMSCEW/P-IV/STR/2019/3313 3313 Checking layout ,level for pier shaft 1st lift at RP-06 Viaduct Km 196+560 RHS 14-Aug-19 2:50 PM
3377 NMSCEW/P-IV/STR/2019/3314 3314 Checking of reinforcement, shuttering for pier shaft 1st lift at RP-06 Viaduct Km 196+560 RHS 14-Aug-19 3:10 PM
3378 NMSCEW/P-IV/STR/2019/3315 3315 Checking & pouring concrete for pier shaft 1st lift at RP-06 Viaduct Km 196+560 RHS 14-Aug-19 3:40 PM
3379 NMSCEW/P-IV/STR/2019/3316 3316 Checking & pouring concrete for raft at RP-02 Viaduct Km 196+560 RHS 14-Aug-19 10:12 AM
3380 NMSCEW/P-IV/STR/2019/3317 3317 Checking & pouring concrete for pier shaft 1st lift at RP-10 Viaduct Km 169+800 RHS 14-Aug-19 8:00 AM IPC-08 DONE AE
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
3381 NMSCEW/P-IV/STR/2019/3318 3318 Box culvert Km 200+200 LHS 16-Aug-19 9:20 AM DONE
-2. Segment NO-277,278,279,280,281,282,283
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3382 NMSCEW/P-IV/STR/2019/3319 3319 Box culvert Km 200+200 LHS 16-Aug-19 10:30 AM DONE
(2×2),(Cushion 2 to 4m) at precast yard camp-2,Segment no.-277,278,279,280,281,282,283
Checking reinforcement for precast Box Culvert (3x3) (cushion 0 to 2m) at precast yard camp
3383 NMSCEW/P-IV/STR/2019/3320 3320 Box culvert Km 200+200 LHS 16-Aug-19 12:00 PM DONE
-2. Segment NO-112,113,114,115
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3384 NMSCEW/P-IV/STR/2019/3321 3321 Box culvert Km 200+200 LHS 16-Aug-19 2:20 PM DONE
(3x3),(cushion 0 to 2m)) at precast yard camp-2,Segment no.-112,113,114,115
Checking reinforcement for precast Box Culvert (3x3) (Cushion 4 to 6 m) at precast yard camp
3385 NMSCEW/P-IV/STR/2019/3322 3322 Box culvert Km 175+500 LHS 16-Aug-19 9:22 AM DONE
-1. Segment NO-32,33,34
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3386 NMSCEW/P-IV/STR/2019/3323 3323 Box culvert Km 175+500 LHS 16-Aug-19 10:44 AM DONE
(3x3) (Cushion 4 to 6 m) at precast yard camp-1,Segment no.-32,33,34
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
3387 NMSCEW/P-IV/STR/2019/3324 3324 Box culvert Km 175+500 LHS 16-Aug-19 12:37 PM DONE
-1. Segment NO-137,138,139
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3388 NMSCEW/P-IV/STR/2019/3325 3325 Box culvert Km 175+500 LHS 16-Aug-19 2:46 PM DONE
(2x2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-137,138,139
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
3389 NMSCEW/P-IV/STR/2019/3326 3326 Box culvert Km 175+500 LHS 16-Aug-19 4:19 PM IPC-08 164, 165, 166
-1. Segment NO-164,165,166 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3390 NMSCEW/P-IV/STR/2019/3327 3327 Box culvert Km 175+500 LHS 16-Aug-19 5:52 PM IPC-08 164, 166, 167, 165
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-164,165,166, 167
DONE
3391 NMSCEW/P-IV/STR/2019/3328 3328 Checking of reinforcement, shuttering for 2nd lift at A1 & A2 wall PUP Km 187+835 LHS 16-Aug-19 10:10 AM DONE
3392 NMSCEW/P-IV/STR/2019/3329 3329 Checking & Pouring concrete(M-30) for 2nd lift at A1 & A2 wall PUP Km 187+835 LHS 16-Aug-19 11:27 AM DONE
3393 NMSCEW/P-IV/STR/2019/3330 3330 Checking of reinforcement, shuttering for 3rd lift at W1 wall PUP Km 193+800 RHS 16-Aug-19 9:00 AM
3394 NMSCEW/P-IV/STR/2019/3331 3331 Checking & Pouring concrete for 3rd lift at W1 wall PUP Km 193+800 RHS 16-Aug-19 10:00 AM
3395 NMSCEW/P-IV/STR/2019/3332 3332 Checking of reinforcement, shuttering for 3rd lift at A1 & A2 wall PUP Km 189+000 LHS 16-Aug-19 11:25 AM NR
3396 NMSCEW/P-IV/STR/2019/3333 3333 Checking & Pouring concrete(M-30) for 3rd lift at A1 & A2 wall PUP Km 189+000 LHS 16-Aug-19 12:28 PM NR
3397 NMSCEW/P-IV/STR/2019/3334 3334 Checking of reinforcement, shuttering for 1st lift at A1 & A2 wall PUP Km 190+650 LHS 16-Aug-19 2:35 PM NR
3398 NMSCEW/P-IV/STR/2019/3335 3335 Checking & Pouring concrete(M-30) for 1st lift at A1 & A2 wall PUP Km 190+650 LHS 16-Aug-19 3:46 PM NR
3399 NMSCEW/P-IV/STR/2019/3336 3336 Checking of reinforcement, shuttering for bottom slab Box culvert Km 180+922 RHS 16-Aug-19 3:11 PM NR
3400 NMSCEW/P-IV/STR/2019/3337 3337 Checking & Pouring concrete(M-30) for bottom slab Box culvert Km 180+922 RHS 16-Aug-19 4:26 PM NR
3401 NMSCEW/P-IV/STR/2019/3338 3338 Checking layout ,level for PCC at LA1 Viaduct Km 195+900 LHS 16-Aug-19 3:02 PM
3402 NMSCEW/P-IV/STR/2019/3339 3339 Checking top Level & Laying concrete for PCC at LA1 Viaduct Km 195+900 LHS 16-Aug-19 3:32 PM
Checking for stressing and remove slagness of H.T. wires at Girder no-9,10,11,12 at bed no -4
3403 NMSCEW/P-IV/STR/2019/3340 3340 Girder Type-2 Km 200+200 LHS 16-Aug-19 12:05 PM
at casting yard camp -2
3404 NMSCEW/P-IV/STR/2019/3341 3341 Checking of reinforcement, shuttering and layout for pier shaft 1st lift at RP-06 Viaduct Km 196+560 RHS 16-Aug-19 3:19 PM
3405 NMSCEW/P-IV/STR/2019/3342 3342 Checking & pouring concrete for pier shaft 1st lift at RP-06 Viaduct Km 196+560 RHS 16-Aug-19 3:49 PM
3406 NMSCEW/P-IV/STR/2019/3343 3343 Checking & pouring concrete for raft at RP-02 Viaduct Km 196+560 RHS 16-Aug-19 10:13 AM IPC-08 DONE AE
3407 NMSCEW/P-IV/STR/2019/3344 3344 Checking of reinforcement, shuttering for raft at LP-05 Viaduct Km 200+920 LHS 16-Aug-19 11:03 AM IPC-08 DONE AE
3408 NMSCEW/P-IV/STR/2019/3345 3345 Checking & pouring concrete for raft at Lp-05 Viaduct Km 200+920 LHS 16-Aug-19 11:43 AM IPC-08 DONE AE
3409 NMSCEW/P-IV/STR/2019/3346 3346 Checking of reinforcement, shuttering and layout for pier shaft final lift at RP-01 Viaduct Km 202+190 Km 00+000 RHS 16-Aug-19 3:21 PM IPC-10 DONE
3410 NMSCEW/P-IV/STR/2019/3347 3347 Checking & pouring concrete for pier shaft final lift at RP-01 Viaduct Km 202+190 RHS 16-Aug-19 4:17 PM
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
3411 NMSCEW/P-IV/STR/2019/3348 3348 Box culvert Km 200+200 LHS 17-Aug-19 9:30 AM DONE
-2. Segment NO-284,285,286,287,288,289
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3412 NMSCEW/P-IV/STR/2019/3349 3349 Box culvert Km 200+200 LHS 17-Aug-19 10:30 AM DONE
(2×2),(Cushion 2 to 4m) at precast yard camp-2,Segment no.-284,285,286,287,288,289
Checking reinforcement for precast Box Culvert (3x3) (Cushion 4 to 6 m) at precast yard camp
3413 NMSCEW/P-IV/STR/2019/3350 3350 Box culvert Km 175+500 LHS 17-Aug-19 10:00 AM DONE
-1. Segment NO-33,34,35,36
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3414 NMSCEW/P-IV/STR/2019/3351 3351 Box culvert Km 175+500 LHS 17-Aug-19 10:45 AM DONE
(3x3) (Cushion 4 to 6 m) at precast yard camp-1,Segment no.-33,34,35,36
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
3415 NMSCEW/P-IV/STR/2019/3352 3352 Box culvert Km 175+500 LHS 17-Aug-19 11:15 AM DONE
-1. Segment NO-137,138,139,140
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3416 NMSCEW/P-IV/STR/2019/3353 3353 Box culvert Km 175+500 LHS 17-Aug-19 12:15 PM DONE
(2x2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-137,138,139,140
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
3417 NMSCEW/P-IV/STR/2019/3354 3354 Box culvert Km 175+500 LHS 17-Aug-19 3:15 PM IPC-08 166, 167, 168, 169
-1. Segment NO-166,167,168,169 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3418 NMSCEW/P-IV/STR/2019/3355 3355 Box culvert Km 175+500 LHS 17-Aug-19 4:15 PM IPC-08 168, 169
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-166,167,168,169
DONE
3419 NMSCEW/P-IV/STR/2019/3356 3356 Checking reinforcement ,shuttering for top haunch at wall A1 & A2 with top slab Box culvert Km 186+352 RHS 17-Aug-19 11:00 AM REPEATED
3420 NMSCEW/P-IV/STR/2019/3357 3357 Checking and concrete pouring for top haunch at wall A1 & A2 with top slab Box culvert Km 186+352 RHS 17-Aug-19 11:30 AM REPEATED
3421 NMSCEW/P-IV/STR/2019/3358 3358 Checking layout ,level and structural excavation Box culvert Km 170+439 Km 00+000 BHS 17-Aug-19 9:45 AM IPC-09 DONE
3422 NMSCEW/P-IV/STR/2019/3359 3359 Checking reinforcement ,shuttering for raft of U type retaining wall PUP Km 204+470 BHS 17-Aug-19 3:00 PM DONE
3423 NMSCEW/P-IV/STR/2019/3360 3360 Checking and concrete pouring for raft of U type retaining wall PUP Km 204+470 BHS 17-Aug-19 3:45 PM DONE
3424 NMSCEW/P-IV/STR/2019/3361 3361 Checking of reinforcement, shuttering for pier shaft 2nd lift at RP-03 Viaduct Km 169+800 Km 00+000 RHS 17-Aug-19 2:00 PM IPC-09 DONE AE
3425 NMSCEW/P-IV/STR/2019/3362 3362 Checking & pouring concrete for pier shaft 2nd lift at RP-03 Viaduct Km 169+800 Km 00+000 RHS 17-Aug-19 2:30 PM IPC-09 DONE AE
3426 NMSCEW/P-IV/STR/2019/3363 3363 Checking of reinforcement, shuttering for pier shaft 1st lift at RP-12 Viaduct Km 169+800 Km 00+000 RHS 17-Aug-19 3:05 PM IPC-09 DONE AE
3427 NMSCEW/P-IV/STR/2019/3364 3364 Checking & pouring concrete for pier shaft 1st lift at RP-12 Viaduct Km 169+800 Km 00+000 RHS 17-Aug-19 3:40 PM IPC-09 DONE AE
3428 NMSCEW/P-IV/STR/2019/3365 3365 Checking of reinforcement, shuttering for pier shaft 2nd lift at LP-9 Viaduct Km 169+800 LHS 17-Aug-19 4:00 PM IPC-08 DONE AE
3429 NMSCEW/P-IV/STR/2019/3366 3366 Checking & pouring concrete for pier shaft 2nd lift at LP-9 Viaduct Km 169+800 LHS 17-Aug-19 4:30 PM IPC-08 DONE AE
3430 NMSCEW/P-IV/STR/2019/3367 3367 Checking of reinforcement, shuttering & layout for pier shaft 1st lift at RP-06 Viaduct Km 196+560 Km 00+000 RHS 17-Aug-19 12:35 PM IPC-09 DONE AE
3431 NMSCEW/P-IV/STR/2019/3368 3368 Checking & pouring concrete for pier shaft 1st lift at RP-06 Viaduct Km 196+560 Km 00+000 RHS 17-Aug-19 2:15 PM IPC-09 DONE AE
3432 NMSCEW/P-IV/STR/2019/3369 3369 Checking of reinforcement, shuttering for raft at LP-04 Viaduct Km 200+920 LHS 17-Aug-19 3:50 PM
3433 NMSCEW/P-IV/STR/2019/3370 3370 Checking & pouring concrete for raft at Lp-04 Viaduct Km 200+920 LHS 17-Aug-19 3:50 PM
3434 NMSCEW/P-IV/STR/2019/3371 3371 Checking of reinforcement, shuttering for 3rd lift at A1 & A2 wall PUP Km 189+000 LHS 17-Aug-19 12:12 PM NR
3435 NMSCEW/P-IV/STR/2019/3372 3372 Checking & Pouring concrete(M-30) for 3rd lift at A1 & A2 wall PUP Km 189+000 LHS 17-Aug-19 12:42 PM NR
3436 NMSCEW/P-IV/STR/2019/3373 3373 Checking of reinforcement, shuttering for 1st lift at A1 & A2 wall PUP Km 190+650 LHS 17-Aug-19 12:55 PM NR
3437 NMSCEW/P-IV/STR/2019/3374 3374 Checking & Pouring concrete(M-30) for 1st lift at A1 & A2 wall PUP Km 190+650 LHS 17-Aug-19 2:22 PM NR
3438 NMSCEW/P-IV/STR/2019/3375 3375 Checking reinforcement ,shuttering for bottom slab Box culvert Km 180+922 RHS 17-Aug-19 2:18 PM NR
3439 NMSCEW/P-IV/STR/2019/3376 3376 Checking and concrete pouring for bottom slab Box culvert Km 180+922 RHS 17-Aug-19 3:11 PM NR
3440 NMSCEW/P-IV/STR/2019/3377 3377 Checking of reinforcement, shuttering & layout for pier shaft final lift at LP-05 Viaduct Km 202+190 LHS 17-Aug-19 2:37 PM
3441 NMSCEW/P-IV/STR/2019/3378 3378 Checking & pouring concrete for pier shaft final lift at LP-05 Viaduct Km 202+190 LHS 17-Aug-19 3:47 PM
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
3442 NMSCEW/P-IV/STR/2019/3379 3379 Box culvert Km 200+200 LHS 18-Aug-19 9:15 AM DONE
-2. Segment NO-290,291,292,293,294,295,296,297
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3443 NMSCEW/P-IV/STR/2019/3380 3380 (2×2),(Cushion 2 to 4m) at precast yard camp-2,Segment no.- Box culvert Km 200+200 LHS 18-Aug-19 10:15 AM DONE
290,291,292,293,294,295,296,297
Checking reinforcement for precast Box Culvert (3x3) (cushion 0 to 2m) at precast yard camp
3444 NMSCEW/P-IV/STR/2019/3381 3381 Box culvert Km 200+200 LHS 18-Aug-19 10:30 AM DONE
-2. Segment NO-116,117,118
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3445 NMSCEW/P-IV/STR/2019/3382 3382 Box culvert Km 200+200 LHS 18-Aug-19 11:30 AM DONE
(3x3),(cushion 0 to 2m)) at precast yard camp-2,Segment no.-116,117,118
Checking reinforcement for precast Box Culvert (3x3) (cushion 2m to 4m) at precast yard
3446 NMSCEW/P-IV/STR/2019/3383 3383 Box culvert Km 200+200 LHS 18-Aug-19 2:30 PM DONE
camp -2. Segment NO-32,33
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3447 NMSCEW/P-IV/STR/2019/3384 3384 Box culvert Km 200+200 LHS 18-Aug-19 3:30 PM DONE
(3x3),(cushion 2m to 4m)) at precast yard camp-2,Segment no.-32,33
3448 NMSCEW/P-IV/STR/2019/3385 3385 Checking of reinforcement, shuttering for 3rd lift at A1 & A2 wall PUP Km 189+000 LHS 18-Aug-19 11:00 AM NR
3449 NMSCEW/P-IV/STR/2019/3386 3386 Checking & Pouring concrete(M-30) for 3rd lift at A1 & A2 wall PUP Km 189+000 LHS 18-Aug-19 12:00 PM NR
3450 NMSCEW/P-IV/STR/2019/3387 3387 Checking of reinforcement, shuttering for 1st lift at A1 & A2 wall PUP Km 190+650 LHS 18-Aug-19 12:15 PM REPEATED
3451 NMSCEW/P-IV/STR/2019/3388 3388 Checking & Pouring concrete(M-30) for 1st lift at A1 & A2 wall PUP Km 190+650 LHS 18-Aug-19 2:20 PM REPEATED
3452 NMSCEW/P-IV/STR/2019/3389 3389 Checking of reinforcement, shuttering for 4th lift at A1 & A2 wall VUP Km 176+614 Km 00+000 RHS 18-Aug-19 12:00 AM IPC-10 DONE
3453 NMSCEW/P-IV/STR/2019/3390 3390 Checking & Pouring concrete for 4th lift at A1 & A2 wall VUP Km 176+614 Km 00+000 RHS 18-Aug-19 4:30 AM IPC-10 DONE
Checking reinforcement for precast Box Culvert (3x3) (Cushion 4 to 6 m) at precast yard camp
3454 NMSCEW/P-IV/STR/2019/3391 3391 Box culvert Km 175+500 LHS 18-Aug-19 10:05 AM DONE
-1. Segment NO-33,34,35,36,37,38
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3455 NMSCEW/P-IV/STR/2019/3392 3392 Box culvert Km 175+500 LHS 18-Aug-19 10:50 AM DONE
(3x3) (Cushion 4 to 6 m) at precast yard camp-1,Segment no.-33,34,35,36,37,38
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
3456 NMSCEW/P-IV/STR/2019/3393 3393 Box culvert Km 175+500 LHS 18-Aug-19 11:19 AM DONE
-1. Segment NO-137,138,139,140
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3457 NMSCEW/P-IV/STR/2019/3394 3394 Box culvert Km 175+500 LHS 18-Aug-19 12:26 PM DONE
(2x2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-137,138,139,140
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
3458 NMSCEW/P-IV/STR/2019/3395 3395 Box culvert Km 175+500 LHS 18-Aug-19 3:37 PM IPC-08
-1. Segment NO-166,167,168,169 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3459 NMSCEW/P-IV/STR/2019/3396 3396 Box culvert Km 175+500 LHS 18-Aug-19 4:35 PM IPC-08 170
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-166,167,168,169
DONE
Checking of side shuttering girder no-9,10,11,12 at bed no-04 ,Girder Type-2, at Casting
3460 NMSCEW/P-IV/STR/2019/3397 3397 Yard-Camp-2 Girder Km 200+200 LHS 18-Aug-19 3:15 PM
Checking & pouring concrete(M-50) of girder no- 9,10,11,12 at bed no-04 ,Girder Type-2, at
3461 NMSCEW/P-IV/STR/2019/3398 3398 Casting Yard-Camp-2 Girder Km 200+200 LHS 18-Aug-19 4:00 PM
3462 NMSCEW/P-IV/STR/2019/3399 3399 Checking of reinforcement, shuttering for raft at LP-06 Viaduct Km 196+560 LHS 18-Aug-19 10:55 AM
3463 NMSCEW/P-IV/STR/2019/3400 3400 Checking & pouring concrete for raft at Lp-06 Viaduct Km 196+560 LHS 18-Aug-19 11:29 AM
3464 NMSCEW/P-IV/STR/2019/3401 3401 Checking of reinforcement, shuttering & layout for pier starter at RP-08 Viaduct Km 196+560 Km 00+000 RHS 18-Aug-19 12:00 PM IPC-09 DONE AE
3465 NMSCEW/P-IV/STR/2019/3402 3402 Checking & pouring concrete for pier starter at RP-08 Viaduct Km 196+560 Km 00+000 RHS 18-Aug-19 12:40 PM IPC-09 DONE AE
3466 NMSCEW/P-IV/STR/2019/3403 3403 Checking of reinforcement, shuttering for raft at LP-04 Viaduct Km 200+920 LHS 18-Aug-19 3:45 PM
3467 NMSCEW/P-IV/STR/2019/3404 3404 Checking & pouring concrete for raft at Lp-04 Viaduct Km 200+920 LHS 18-Aug-19 4:50 PM
3468 NMSCEW/P-IV/STR/2019/3405 3405 Checking & pouring concrete for pier shaft final lift at RP-01 Viaduct Km 202+190 Km 00+000 RHS 18-Aug-19 2:40 PM IPC-10 DONE AE
3469 NMSCEW/P-IV/STR/2019/3406 3406 Checking of reinforcement, shuttering for 2nd lift at W1 & W2 wall PUP Km 193+880 LHS 19-Aug-19 9:00 AM
3470 NMSCEW/P-IV/STR/2019/3407 3407 Checking & Pouring concrete for 2nd lift at W1 & W2 wall PUP Km 193+880 LHS 19-Aug-19 10:00 AM
3471 NMSCEW/P-IV/STR/2019/3408 3408 Checking layout ,level for top slab Box culvert Km 204+920 LHS 19-Aug-19 3:00 PM
3472 NMSCEW/P-IV/STR/2019/3409 3409 Checking of reinforcement, shuttering top slab Box culvert Km 204+920 LHS 19-Aug-19 3:30 PM
3473 NMSCEW/P-IV/STR/2019/3410 3410 Checking & pouring concrete top slab Box culvert Km 204+920 LHS 19-Aug-19 4:00 PM
Checking for stressing and remove slagness of H.T. wires at Girder no-1,2,3,4 at bed no -6 at
3474 NMSCEW/P-IV/STR/2019/3411 3411 Girder Type-1 Km 200+200 LHS 19-Aug-19 12:00 PM
casting yard camp -2
Checking of side shuttering girder no-9,10,11,12 at bed no-04 ,Girder Type-2, at Casting
3475 NMSCEW/P-IV/STR/2019/3412 3412 Yard-Camp-2 Girder Km 200+200 LHS 19-Aug-19 9:30 AM
Checking & pouring concrete(M-50) of girder no- 9,10,11,12 at bed no-04 ,Girder Type-2, at
3476 NMSCEW/P-IV/STR/2019/3413 3413 Casting Yard-Camp-2 Girder Km 200+200 LHS 19-Aug-19 10:00 AM
3477 NMSCEW/P-IV/STR/2019/3414 3414 Checking of reinforcement, shuttering for pier shaft 2nd lift at RP-01 Viaduct Km 169+800 RHS 19-Aug-19 2:00 PM NR
3478 NMSCEW/P-IV/STR/2019/3415 3415 Checking & pouring concrete for pier shaft 2nd lift at RP-01 Viaduct Km 169+800 RHS 19-Aug-19 2:30 PM NR
3479 NMSCEW/P-IV/STR/2019/3416 3416 Checking of reinforcement, shuttering for pier shaft 1st lift at LP-08 Viaduct Km 169+800 LHS 19-Aug-19 12:15 PM IPC-08 DONE AE
3480 NMSCEW/P-IV/STR/2019/3417 3417 Checking & pouring concrete for pier shaft 1st lift at LP-08 Viaduct Km 169+800 LHS 19-Aug-19 12:45 PM NR
3481 NMSCEW/P-IV/STR/2019/3418 3418 Checking layout ,level and structural for median drain outlets Pipe culvert Km 168+400 LHS 19-Aug-19 4:20 PM DONE
Checking reinforcement for precast Box Culvert (3x3) (Cushion 4 to 6 m) at precast yard camp
3482 NMSCEW/P-IV/STR/2019/3419 3419 Box culvert Km 175+500 LHS 19-Aug-19 10:30 AM DONE SPOT RFI
-1. Segment NO-28,39,40,41,42,43
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3483 NMSCEW/P-IV/STR/2019/3420 3420 Box culvert Km 175+500 LHS 19-Aug-19 11:30 AM DONE SPOT RFI
(3x3) (Cushion 4 to 6 m) at precast yard camp-1,Segment no.-28,39,40,41,42,43
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
3484 NMSCEW/P-IV/STR/2019/3421 3421 Box culvert Km 175+500 LHS 19-Aug-19 11:19 AM DONE SPOT RFI
-1. Segment NO-107,109,110,141
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3485 NMSCEW/P-IV/STR/2019/3422 3422 Box culvert Km 175+500 LHS 19-Aug-19 12:26 PM DONE SPOT RFI
(2x2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-107,109,110,141
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
3486 NMSCEW/P-IV/STR/2019/3423 3423 Box culvert Km 175+500 LHS 19-Aug-19 3:37 PM IPC-08 170, 171, 172, 136, 140
-1. Segment NO-170,171,172,136,140 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3487 NMSCEW/P-IV/STR/2019/3424 3424 Box culvert Km 175+500 LHS 19-Aug-19 4:35 PM IPC-08 171, 172, 136, 140
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-170,171,172,136,140
DONE
3488 NMSCEW/P-IV/STR/2019/3425 3425 Checking reinforcement ,shuttering for top haunch at wall A1 & A2 with top slab PUP Km 189+000 LHS 19-Aug-19 11:00 AM REPEATED SPOT RFI
3489 NMSCEW/P-IV/STR/2019/3426 3426 Checking and concrete M30 pouring for top haunch at wall A1 & A2 with top slab PUP Km 189+000 LHS 19-Aug-19 11:50 AM REPEATED SPOT RFI
3490 NMSCEW/P-IV/STR/2019/3427 3427 Checking layout ,level for top slab CUP Km 203+560 LHS 20-Aug-19 3:00 PM IPC-08 DONE AE
3491 NMSCEW/P-IV/STR/2019/3428 3428 Checking reinforcement ,shuttering for top slab CUP Km 203+560 LHS 20-Aug-19 3:30 PM IPC-08 DONE AE
3492 NMSCEW/P-IV/STR/2019/3429 3429 Checking and concrete pouring for top slab CUP Km 203+560 LHS 20-Aug-19 4:00 PM IPC-08 DONE AE
3493 NMSCEW/P-IV/STR/2019/3430 3430 Checking of reinforcement, shuttering for 2nd lift at A1 & A2 wall LVUP Km 178+323 RHS 20-Aug-19 9:30 AM NR
3494 NMSCEW/P-IV/STR/2019/3431 3431 Checking & Pouring concrete for 2nd lift at A1 & A2 wall LVUP Km 178+323 RHS 20-Aug-19 10:33 AM NR
3495 NMSCEW/P-IV/STR/2019/3432 3432 Checking top Level & Laying concrete (M-10) for PCC Box culvert Km 180+180 BHS 20-Aug-19 12:00 PM DONE
3496 NMSCEW/P-IV/STR/2019/3433 3433 Checking of reinforcement, shuttering for 2nd lift at A1 & A2 wall Box culvert Km 186+352 LHS 20-Aug-19 10:00 AM NR
3497 NMSCEW/P-IV/STR/2019/3434 3434 Checking & Pouring concrete(M-30) for 2nd lift at A1 & A2 wall Box culvert Km 186+352 LHS 20-Aug-19 10:50 AM NR
3498 NMSCEW/P-IV/STR/2019/3435 3435 Checking & pouring concrete for pier shaft 1st lift at LP-08 Viaduct Km 169+800 LHS 20-Aug-19 8:30 AM IPC-08 DONE AE
3499 NMSCEW/P-IV/STR/2019/3436 3436 Checking & pouring concrete for pier shaft 2nd lift at RP-01 Viaduct Km 169+800 RHS 20-Aug-19 9:00 AM NR
3500 NMSCEW/P-IV/STR/2019/3437 3437 Checking of reinforcement, shuttering for pier shaft 2nd lift at RP-08 Viaduct Km 169+800 RHS 20-Aug-19 12:15 PM IPC-08 DONE AE
3501 NMSCEW/P-IV/STR/2019/3438 3438 Checking & pouring concrete for pier shaft 2nd lift at RP-08 Viaduct Km 169+800 RHS 20-Aug-19 12:45 PM IPC-08 DONE AE
3502 NMSCEW/P-IV/STR/2019/3439 3439 Checking of reinforcement, shuttering for pier shaft 2nd lift at LP-05 Viaduct Km 169+800 LHS 20-Aug-19 3:15 PM NR
3503 NMSCEW/P-IV/STR/2019/3440 3440 Checking & pouring concrete for pier shaft 2nd lift at LP-05 Viaduct Km 169+800 LHS 20-Aug-19 3:45 PM NR
3504 NMSCEW/P-IV/STR/2019/3441 3441 Checking of reinforcement, shuttering for raft at LP-04 Viaduct Km 200+920 LHS 20-Aug-19 10:15 AM IPC-08 DONE AE
3505 NMSCEW/P-IV/STR/2019/3442 3442 Checking & pouring concrete for raft at Lp-04 Viaduct Km 200+920 LHS 20-Aug-19 10:30 AM IPC-08 DONE AE
3506 NMSCEW/P-IV/STR/2019/3443 3443 Checking of reinforcement, shuttering for raft at LP-06 Viaduct Km 196+560 LHS 20-Aug-19 10:20 AM IPC-08 DONE AE
3507 NMSCEW/P-IV/STR/2019/3444 3444 Checking & pouring concrete for raft at Lp-06 Viaduct Km 196+560 LHS 20-Aug-19 10:55 AM IPC-08 DONE AE
3508 NMSCEW/P-IV/STR/2019/3445 3445 Checking of reinforcement, shuttering & layout for pier shaft 1st lift at RP-03 Viaduct Km 196+560 RHS 20-Aug-19 2:00 PM
3509 NMSCEW/P-IV/STR/2019/3446 3446 Checking & pouring concrete for pier shaft 1st lift at RP-03 Viaduct Km 196+560 RHS 20-Aug-19 2:30 PM
3510 NMSCEW/P-IV/STR/2019/3447 3447 Checking of reinforcement, shuttering & layout for pier shaft 1st lift at RP-07 Viaduct Km 196+560 RHS 20-Aug-19 4:15 PM
3511 NMSCEW/P-IV/STR/2019/3448 3448 Checking & pouring concrete for pier shaft 1st lift at RP-07 Viaduct Km 196+560 RHS 20-Aug-19 4:30 PM
Checking reinforcement for precast Box Culvert (3x3) (Cushion 4 to 6 m) at precast yard camp
3512 NMSCEW/P-IV/STR/2019/3449 3449 Box culvert Km 175+500 LHS 20-Aug-19 10:33 AM DONE
-1. Segment NO-44,45,46,47,48,49
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3513 NMSCEW/P-IV/STR/2019/3450 3450 Box culvert Km 175+500 LHS 20-Aug-19 11:42 AM DONE
(3x3) (Cushion 4 to 6 m) at precast yard camp-1,Segment no.-44,45,46,47,48,49
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
3514 NMSCEW/P-IV/STR/2019/3451 3451 Box culvert Km 175+500 LHS 20-Aug-19 11:26 AM DONE
-1. Segment NO-142,143,144,145
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3515 NMSCEW/P-IV/STR/2019/3452 3452 Box culvert Km 175+500 LHS 20-Aug-19 12:23 PM DONE
(2x2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-142,143,144,145
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
3516 NMSCEW/P-IV/STR/2019/3453 3453 Box culvert Km 175+500 LHS 20-Aug-19 3:38 PM IPC-08 173, 174, 175, 176, 177
-1. Segment NO-173,174,175,176,177 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3517 NMSCEW/P-IV/STR/2019/3454 3454 Box culvert Km 175+500 LHS 20-Aug-19 4:27 PM IPC-08 173, 174, 175, 176
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-173,174,175,176,177
DONE
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
3518 NMSCEW/P-IV/STR/2019/3455 3455 Box culvert Km 200+200 LHS 20-Aug-19 9:45 AM DONE
-2. Segment NO-298,299,300,301,302,303,304
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3519 NMSCEW/P-IV/STR/2019/3456 3456 Box culvert Km 200+200 LHS 20-Aug-19 11:20 AM DONE
(2×2),(Cushion 2 to 4m) at precast yard camp-2,Segment no.-298,299,300,301,302,303,304
3520 NMSCEW/P-IV/STR/2019/3457 3457 Checking layout ,level for raft MNB Km 199+360 LHS 20-Aug-19 2:05 PM IPC-08 DONE
3521 NMSCEW/P-IV/STR/2019/3458 3458 Checking of reinforcement, shuttering for raft MNB Km 199+360 LHS 20-Aug-19 2:40 PM IPC-08 DONE
3522 NMSCEW/P-IV/STR/2019/3459 3459 Checking & pouring concrete for raft MNB Km 199+360 LHS 20-Aug-19 3:11 PM IPC-08 DONE
Checking of Shuttering and reinforcement for precast type RE Wall Panel Nos -A-26 RE
3523 NMSCEW/P-IV/STR/2019/3460 3460 panel precast yard camp-2 RE Wall Panel Km 200+200 LHS 20-Aug-19 3:37 PM DONE
Checking Pouring of Concrete for precast type RE Wall Panel Nos -A-26 at RE panel precast
3524 NMSCEW/P-IV/STR/2019/3461 3461 yard camp-2 RE Wall Panel Km 200+200 LHS 20-Aug-19 4:13 PM DONE
3525 NMSCEW/P-IV/STR/2019/3462 3462 Checking of reinforcement, shuttering for 2nd lift at A1 & A2 wall LVUP Km 178+323 RHS 21-Aug-19 11:50 AM IPC-08 DONE AE
3526 NMSCEW/P-IV/STR/2019/3463 3463 Checking & Pouring concrete for 2nd lift at A1 & A2 wall LVUP Km 178+323 RHS 21-Aug-19 1:30 AM IPC-08 DONE AE
3527 NMSCEW/P-IV/STR/2019/3464 3464 Checking of reinforcement, shuttering for retaining wall at A1 & A2 PUP Km 172+190 RHS 21-Aug-19 10:30 AM NR
3528 NMSCEW/P-IV/STR/2019/3465 3465 Checking & Pouring concrete for retaining wall at A1 & A2 PUP Km 172+190 RHS 21-Aug-19 11:40 AM NR
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
3529 NMSCEW/P-IV/STR/2019/3466 3466 Box culvert Km 200+200 LHS 21-Aug-19 9:30 AM DONE
-2. Segment NO-305,306,307,308,309,310,311
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3530 NMSCEW/P-IV/STR/2019/3467 3467 Box culvert Km 200+200 LHS 21-Aug-19 10:45 AM DONE
(2×2),(Cushion 2 to 4m) at precast yard camp-2,Segment no.-305,306,307,308,309,310,311
3531 NMSCEW/P-IV/STR/2019/3468 3468 Checking layout ,level for PCC MNB Km 203+409 BHS 21-Aug-19 2:00 PM IPC-08 DONE AE
3532 NMSCEW/P-IV/STR/2019/3469 3469 Checking excavated bed level for PCC MNB Km 203+409 BHS 21-Aug-19 2:15 PM IPC-08 DONE AE
3533 NMSCEW/P-IV/STR/2019/3470 3470 Checking top Level & Laying concrete for PCC MNB Km 203+409 BHS 21-Aug-19 2:30 PM IPC-08 DONE AE
3534 NMSCEW/P-IV/STR/2019/3471 3471 Checking layout ,level for PCC at RP-02 Viaduct Km 200+920 RHS 21-Aug-19 11:00 AM
3535 NMSCEW/P-IV/STR/2019/3472 3472 Checking top Level & Laying concrete for PCC at RP-02 Viaduct Km 200+920 RHS 21-Aug-19 11:30 AM
3536 NMSCEW/P-IV/STR/2019/3473 3473 Checking of reinforcement, shuttering for pier shaft 2nd lift at LP-12 Viaduct Km 169+800 Km 00+000 LHS 21-Aug-19 2:05 PM IPC-09 DONE AE
3537 NMSCEW/P-IV/STR/2019/3474 3474 Checking & pouring concrete for pier shaft 2nd lift at LP-12 Viaduct Km 169+800 Km 00+000 LHS 21-Aug-19 2:35 PM IPC-09 DONE AE
3538 NMSCEW/P-IV/STR/2019/3475 3475 Checking of reinforcement, shuttering for pier shaft 2nd lift at LP-05 Viaduct Km 169+800 LHS 21-Aug-19 3:11 PM IPC-08 DONE AE
3539 NMSCEW/P-IV/STR/2019/3476 3476 Checking & pouring concrete for pier shaft 2nd lift at LP-05 Viaduct Km 169+800 LHS 21-Aug-19 3:44 PM IPC-08 DONE AE
3540 NMSCEW/P-IV/STR/2019/3477 3477 Checking of reinforcement, shuttering for pier shaft 1st & final lift at LP-13 Viaduct Km 169+800 Km 00+000 LHS 21-Aug-19 4:00 PM IPC-09 DONE AE
3541 NMSCEW/P-IV/STR/2019/3478 3478 Checking & pouring concrete for pier shaft 1st & final lift at LP-13 Viaduct Km 169+800 Km 00+000 LHS 21-Aug-19 4:30 PM IPC-09 DONE AE
3542 NMSCEW/P-IV/STR/2019/3479 3479 Checking of reinforcement, shuttering & layout for pier shaft 1st lift at RP-03 Viaduct Km 196+560 RHS 21-Aug-19 10:18 AM
3543 NMSCEW/P-IV/STR/2019/3480 3480 Checking & pouring concrete for pier shaft 1st lift at RP-03 Viaduct Km 196+560 RHS 21-Aug-19 10:54 AM
3544 NMSCEW/P-IV/STR/2019/3481 3481 Checking of reinforcement, shuttering & layout for pier shaft 1st lift at RP-07 Viaduct Km 196+560 RHS 21-Aug-19 11:27 AM
3545 NMSCEW/P-IV/STR/2019/3482 3482 Checking & pouring concrete for pier shaft 1st lift at RP-07 Viaduct Km 196+560 RHS 21-Aug-19 11:51 AM
3546 NMSCEW/P-IV/STR/2019/3483 3483 Checking layout ,level for PCC at LA-01 Viaduct Km 195+900 LHS 21-Aug-19 3:00 PM IPC-08 DONE AE
3547 NMSCEW/P-IV/STR/2019/3484 3484 Checking top Level & Laying concrete for PCC at LA-01 Viaduct Km 195+900 LHS 21-Aug-19 3:30 PM IPC-08 DONE AE
3548 NMSCEW/P-IV/STR/2019/3485 3485 Checking of reinforcement, shuttering & layout for pier shaft 1st lift at RP-02 Viaduct Km 202+190 RHS 21-Aug-19 2:27 PM
3549 NMSCEW/P-IV/STR/2019/3486 3486 Checking & pouring concrete for pier shaft 1st lift at RP-02 Viaduct Km 202+190 RHS 21-Aug-19 2:42 PM
3550 NMSCEW/P-IV/STR/2019/3487 3487 Checking of reinforcement, shuttering & layout for pier shaft final lift at LP-06 Viaduct Km 202+190 LHS 21-Aug-19 3:25 PM
3551 NMSCEW/P-IV/STR/2019/3488 3488 Checking & pouring concrete for pier shaft final lift at LP-06 Viaduct Km 202+190 RHS 21-Aug-19 3:50 PM
3552 NMSCEW/P-IV/STR/2019/3489 3489 Checking layout ,level and structural excavation Utility duct Km 170+300 Km 00+000 BHS 21-Aug-19 10:11 AM IPC-09 DONE
3553 NMSCEW/P-IV/STR/2019/3490 3490 Checking top Level & Laying concrete (M-10) PCC for median drain outlets Pipe culvert Km 168+400 LHS 21-Aug-19 2:13 PM DONE
3554 NMSCEW/P-IV/STR/2019/3491 3491 Checking of reinforcement, shuttering for 3rd lift at A1 & A2 wall LVUP Km 169+291 LHS 21-Aug-19 4:15 PM IPC-08 DONE AE
3555 NMSCEW/P-IV/STR/2019/3492 3492 Checking & Pouring concrete for 3rd lift at A1 & A2 wall LVUP Km 169+291 LHS 21-Aug-19 4:45 PM IPC-08 DONE AE
3556 NMSCEW/P-IV/STR/2019/3493 3493 Checking of reinforcement, shuttering for 2nd lift at A1 & A2 wall Box culvert Km 186+352 LHS 21-Aug-19 10:05 AM REPEATED
3557 NMSCEW/P-IV/STR/2019/3494 3494 Checking & Pouring concrete(M-30) for 2nd lift at A1 & A2 wall Box culvert Km 186+352 LHS 21-Aug-19 10:38 AM REPEATED
Checking reinforcement for precast Box Culvert (3x3) (Cushion 4 to 6 m) at precast yard camp
3558 NMSCEW/P-IV/STR/2019/3495 3495 Box culvert Km 175+500 LHS 21-Aug-19 10:32 AM DONE
-1. Segment NO-50,51,52,53,54
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3559 NMSCEW/P-IV/STR/2019/3496 3496 Box culvert Km 175+500 LHS 21-Aug-19 11:47 AM DONE
(3x3) (Cushion 4 to 6 m) at precast yard camp-1,Segment no.-50,51,52,53,54
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
3560 NMSCEW/P-IV/STR/2019/3497 3497 Box culvert Km 175+500 LHS 21-Aug-19 11:29 AM DONE
-1. Segment NO-141,146,147
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3561 NMSCEW/P-IV/STR/2019/3498 3498 Box culvert Km 175+500 LHS 21-Aug-19 12:26 PM DONE
(2x2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-141,146,147
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
3562 NMSCEW/P-IV/STR/2019/3499 3499 Box culvert Km 175+500 LHS 21-Aug-19 3:31 PM IPC-08 178, 179, 180, 181
-1. Segment NO-178,179,180,181 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3563 NMSCEW/P-IV/STR/2019/3500 3500 Box culvert Km 175+500 LHS 21-Aug-19 4:24 PM IPC-08 178, 179
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-178,179,180,181
DONE
3564 NMSCEW/P-IV/STR/2019/3501 3501 Checking of reinforcement, shuttering for pier shaft 2nd lift at RP-01 Viaduct Km 169+800 Km 00+000 RHS 21-Aug-19 3:23 PM IPC-09 DONE
3565 NMSCEW/P-IV/STR/2019/3502 3502 Checking & pouring concrete for pier shaft 2nd lift at RP-01 Viaduct Km 169+800 Km 00+000 RHS 21-Aug-19 4:11 PM IPC-09 DONE AE
3566 NMSCEW/P-IV/STR/2019/3503 3503 Checking of reinforcement, shuttering for raft Box culvert Km 180+427 LHS 22-Aug-19 10:30 AM IPC-08 DONE AE
3567 NMSCEW/P-IV/STR/2019/3504 3504 Checking & pouring concrete for raft Box culvert Km 180+427 LHS 22-Aug-19 12:15 PM IPC-08 DONE AE
Checking of Shuttering and reinforcement for RE WALL PANEL precast TYPE -A
3568 NMSCEW/P-IV/STR/2019/3505 3505 32, TYPE -B 10, TYPE -Sta 2, TYPE -Stb 2, TYPE -Stc 2, TYPE -Std 2, TYPE -Ltc 1, RE Wall Panel Km 200+200 LHS 22-Aug-19 11:30 AM DONE
TYPE -Ltd 2,
Checking and Pouring concrete for RE WALL PANEL precastTYPE -A
3569 NMSCEW/P-IV/STR/2019/3506 3506 32, TYPE -B 10, TYPE -Sta 2, TYPE -Stb 2, TYPE -Stc 2, TYPE -Std 2, TYPE -Ltc 1, RE Wall Panel Km 200+200 LHS 22-Aug-19 12:00 PM DONE
TYPE -Ltd 2,
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
3570 NMSCEW/P-IV/STR/2019/3507 3507 Box culvert Km 200+200 LHS 22-Aug-19 9:30 AM DONE
-2. Segment NO-312,313,314,315,316,317
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3571 NMSCEW/P-IV/STR/2019/3508 3508 Box culvert Km 200+200 LHS 22-Aug-19 11:00 AM DONE
(2×2),(Cushion 2 to 4m) at precast yard camp-2,Segment no.-312,313,314,315,316,317
Checking reinforcement for precast Box Culvert (3x3) (cushion 0 to 2m) at precast yard camp
3572 NMSCEW/P-IV/STR/2019/3509 3509 Box culvert Km 200+200 LHS 22-Aug-19 2:00 PM DONE
-2. Segment NO-119,120,121
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3573 NMSCEW/P-IV/STR/2019/3510 3510 Box culvert Km 200+200 LHS 22-Aug-19 3:00 PM DONE
(3x3),(cushion 0 to 2m)) at precast yard camp-2,Segment no.-119,120,121
Checking reinforcement for precast Box Culvert (3x3) (Cushion 4 to 6 m) at precast yard camp
3574 NMSCEW/P-IV/STR/2019/3511 3511 Box culvert Km 175+500 LHS 22-Aug-19 10:32 AM DONE
-1. Segment NO-48,49,55,56
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3575 NMSCEW/P-IV/STR/2019/3512 3512 Box culvert Km 175+500 LHS 22-Aug-19 11:47 AM DONE
(3x3) (Cushion 4 to 6 m) at precast yard camp-1,Segment no.-48,49,55,56
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
3576 NMSCEW/P-IV/STR/2019/3513 3513 Box culvert Km 175+500 LHS 22-Aug-19 11:29 AM DONE
-1. Segment NO-144,145,148,149
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3577 NMSCEW/P-IV/STR/2019/3514 3514 Box culvert Km 175+500 LHS 22-Aug-19 12:26 PM DONE
(2x2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-144,145,148,149
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
3578 NMSCEW/P-IV/STR/2019/3515 3515 Box culvert Km 175+500 LHS 22-Aug-19 3:31 PM IPC-08 177, 182, 183
-1. Segment NO-177,182,183 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3579 NMSCEW/P-IV/STR/2019/3516 3516 Box culvert Km 175+500 LHS 22-Aug-19 4:24 PM IPC-08 177, 182
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-177,182,183 DONE AE
3580 NMSCEW/P-IV/STR/2019/3517 3517 Checking of reinforcement, shuttering for 3rd lift at A1 & A2 wall PUP Km 187+835 RHS 22-Aug-19 11:09 AM
NR
3581 NMSCEW/P-IV/STR/2019/3518 3518 Checking & Pouring concrete(M-30) for 3rd lift at A1 & A2 wall PUP Km 187+835 RHS 22-Aug-19 11:37 AM
NR
3582 NMSCEW/P-IV/STR/2019/3519 3519 Checking of reinforcement, shuttering for 2nd lift at A1 & A2 wall PUP Km 190+650 LHS 22-Aug-19 2:30 PM
NR
3583 NMSCEW/P-IV/STR/2019/3520 3520 Checking & Pouring concrete(M-30) for 2nd lift at A1 & A2 wall PUP Km 190+650 LHS 22-Aug-19 3:20 PM
NR
3584 NMSCEW/P-IV/STR/2019/3521 3521 Checking of reinforcement, shuttering for pier shaft 2nd lift at LP-06 Viaduct Km 169+800 LHS 23-Aug-19 2:00 PM
NR
3585 NMSCEW/P-IV/STR/2019/3522 3522 Checking & pouring concrete for pier shaft 2nd lift at LP-06 Viaduct Km 169+800 LHS 23-Aug-19 2:30 PM
NR
3586 NMSCEW/P-IV/STR/2019/3523 3523 Checking of reinforcement, shuttering for pier shaft 2nd lift at LP-07 Viaduct Km 169+800 LHS 23-Aug-19 3:00 PM
NR
3587 NMSCEW/P-IV/STR/2019/3524 3524 Checking & pouring concrete for pier shaft 2nd lift at LP-07 Viaduct Km 169+800 LHS 23-Aug-19 3:30 PM
NR
3588 NMSCEW/P-IV/STR/2019/3525 3525 Checking of side shuttering girder no- 1,2,3 & 4 at bed no-06,Girder Type-1 Girder Km 200+200 LHS 23-Aug-19 11:00 AM
Approval for pouring of girder no- 1,2,3 & 4 at bed no-6.(Grade of concrete M-50)
3589 NMSCEW/P-IV/STR/2019/3526 3526 Girder Km 200+200 LHS 23-Aug-19 11:30 AM
Girder Type- 1
3590 NMSCEW/P-IV/STR/2019/3527 3527 Checking of reinforcement, shuttering and layout for pier shaft 1st lift at RP-03 Viaduct Km 196+560 Km 00+000 RHS 23-Aug-19 9:00 AM IPC-10 DONE
AE
3591 NMSCEW/P-IV/STR/2019/3528 3528 Checking & pouring concrete for pier shaft 1st lift at RP-03 Viaduct Km 196+560 Km 00+000 RHS 23-Aug-19 9:30 AM IPC-10 DONE AE
3592 NMSCEW/P-IV/STR/2019/3529 3529 Checking of reinforcement, shuttering and layout for pier shaft 1st lift at RP-07 Viaduct Km 196+560 Km 00+000 RHS 23-Aug-19 10:40 AM IPC-09 DONE AE
3593 NMSCEW/P-IV/STR/2019/3530 3530 Checking & pouring concrete for pier shaft 1st lift at RP-07 Viaduct Km 196+560 Km 00+000 RHS 23-Aug-19 11:20 AM IPC-09 DONE AE
3594 NMSCEW/P-IV/STR/2019/3531 3531 Checking of reinforcement, shuttering for pier cap at RP-07 Viaduct Km 169+800 RHS 23-Aug-19 4:00 PM NR
3595 NMSCEW/P-IV/STR/2019/3532 3532 Checking & pouring concrete for pier cap at RP-07 Viaduct Km 169+800 RHS 23-Aug-19 4:30 PM NR
3596 NMSCEW/P-IV/STR/2019/3533 3533 Checking of layout ,level ,reinforcement, shuttering for pier shaft 1st lift at RP-02 Viaduct Km 202+190 Km 00+000 RHS 23-Aug-19 10:00 AM IPC-10 DONE AE
3597 NMSCEW/P-IV/STR/2019/3534 3534 Checking & pouring concrete for pier shaft 1st lift at RP-02 Viaduct Km 202+190 Km 00+000 RHS 23-Aug-19 10:30 AM IPC-10 DONE AE
3598 NMSCEW/P-IV/STR/2019/3535 3535 Checking of layout ,level ,reinforcement, shuttering for pier shaft final lift at LP-06 Viaduct Km 202+190 LHS 23-Aug-19 11:10 AM
3599 NMSCEW/P-IV/STR/2019/3536 3536 Checking & pouring concrete for pier shaft final lift at LP-06 Viaduct Km 202+190 LHS 23-Aug-19 11:50 AM
3600 NMSCEW/P-IV/STR/2019/3537 3537 Checking of layout ,level ,reinforcement, shuttering for pier shaft 1st lift at RP-04 Viaduct Km 202+190 Km 00+000 RHS 23-Aug-19 3:15 PM IPC-10 DONE AE
3601 NMSCEW/P-IV/STR/2019/3538 3538 Checking & pouring concrete for pier shaft 1st lift at RP-04 Viaduct Km 202+190 Km 00+000 RHS 23-Aug-19 3:45 PM IPC-10 DONE AE
3602 NMSCEW/P-IV/STR/2019/3539 3539 Checking layout ,level for PCC at RP-02 Viaduct Km 200+920 RHS 23-Aug-19 2:00 PM IPC-08 DONE AE
3603 NMSCEW/P-IV/STR/2019/3540 3540 Checking top Level & Laying concrete for PCC at RP-02 Viaduct Km 200+920 RHS 23-Aug-19 3:20 PM IPC-08 DONE AE
Checking reinforcement for precast Box Culvert (3x3) (Cushion 2 to 4 m) at precast yard camp
3604 NMSCEW/P-IV/STR/2019/3541 3541 Box culvert Km 175+500 LHS 23-Aug-19 10:39 AM DONE
-1. Segment NO-136,137,138,139,140
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3605 NMSCEW/P-IV/STR/2019/3542 3542 Box culvert Km 175+500 LHS 23-Aug-19 11:52 AM DONE
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.-136,137,138,139,140
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
3606 NMSCEW/P-IV/STR/2019/3543 3543 Box culvert Km 175+500 LHS 23-Aug-19 11:18 AM DONE
-1. Segment NO-150,151,152
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3607 NMSCEW/P-IV/STR/2019/3544 3544 Box culvert Km 175+500 LHS 23-Aug-19 12:44 PM DONE
(2x2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-150,151,152
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
3608 NMSCEW/P-IV/STR/2019/3545 3545 Box culvert Km 175+500 LHS 23-Aug-19 3:55 PM IPC-08 180, 181, 184
-1. Segment NO-180,181,184 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3609 NMSCEW/P-IV/STR/2019/3546 3546 Box culvert Km 175+500 LHS 23-Aug-19 4:55 PM IPC-08 180, 181, 184
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-180,181,184 DONE AE
Checking of Hume pipe ( 1000×2500) mm. Laying & fixing for pipe culvert median drain
3610 NMSCEW/P-IV/STR/2019/3547 3547 Pipe culvert Km 168+400 LHS 23-Aug-19 11:11 AM DONE
outlets.
3611 NMSCEW/P-IV/STR/2019/3548 3548 Checking of reinforcement, shuttering for 2nd lift at A1 & A2 wall PUP Km 190+650 LHS 23-Aug-19 10:11 AM NR
3612 NMSCEW/P-IV/STR/2019/3549 3549 Checking & Pouring concrete(M-30) for 2nd lift at A1 & A2 wall PUP Km 190+650 LHS 23-Aug-19 10:42 AM NR
3613 NMSCEW/P-IV/STR/2019/3550 3550 Checking of reinforcement, shuttering for 2nd lift at A1 wall Box culvert Km 182+350 RHS 23-Aug-19 4:16 PM NR
3614 NMSCEW/P-IV/STR/2019/3551 3551 Checking & Pouring concrete(M-30) for 2nd lift at A1 wall Box culvert Km 182+350 RHS 23-Aug-19 5:10 PM NR
3615 NMSCEW/P-IV/STR/2019/3552 3552 Checking of reinforcement, shuttering for final lift at A1 & A2 wall PUP Km 187+835 RHS 23-Aug-19 10:09 AM REPEATED
3616 NMSCEW/P-IV/STR/2019/3553 3553 Checking & Pouring concrete(M-30) for final lift at A1 & A2 wall PUP Km 187+835 RHS 23-Aug-19 10:38 AM REPEATED
3617 NMSCEW/P-IV/STR/2019/3554 3554 Checking of reinforcement, shuttering for final lift at LP-10 Viaduct Km 169+800 LHS 23-Aug-19 6:30 PM IPC-08 DONE AE SPOT RFI
3618 NMSCEW/P-IV/STR/2019/3555 3555 Checking & pouring concrete for final lift at LP-10 Viaduct Km 169+800 LHS 23-Aug-19 6:45 PM IPC-08 DONE AE SPOT RFI
3619 NMSCEW/P-IV/STR/2019/3556 3556 Checking of reinforcement, shuttering for final lift at RP-09 Viaduct Km 169+800 RHS 23-Aug-19 6:35 PM IPC-08 DONE AE SPOT RFI
3620 NMSCEW/P-IV/STR/2019/3557 3557 Checking & pouring concrete for final lift at RP-09 Viaduct Km 169+800 RHS 23-Aug-19 6:50 PM IPC-08 DONE AE SPOT RFI
3621 NMSCEW/P-IV/STR/2019/3558 3558 Checking of completion of segment errection for 2x2 utility duct. Utility duct Km 198+300 BHS 24-Aug-19 10:00 AM IPC-08 DONE
Checking of Shuttering and reinforcement for RE WALL PANEL precast TYPE -A
3622 NMSCEW/P-IV/STR/2019/3559 3559 32, TYPE -B 10, TYPE -Sta 2, TYPE -Stb 2, TYPE -Stc 2, TYPE -Std 2, TYPE -Ltc 1, RE Wall Panel Km 200+200 LHS 24-Aug-19 11:30 AM DONE
TYPE -Ltd 2,
Checking and Pouring concrete for RE WALL PANEL precastTYPE -A
3623 NMSCEW/P-IV/STR/2019/3560 3560 32, TYPE -B 10, TYPE -Sta 2, TYPE -Stb 2, TYPE -Stc 2, TYPE -Std 2, TYPE -Ltc 1, RE Wall Panel Km 200+200 LHS 24-Aug-19 12:00 PM DONE
TYPE -Ltd 2,
3624 NMSCEW/P-IV/STR/2019/3561 3561 Checking of Shuttering and reinforcement for raft of U type retaining wall PUP Km 205+430 BHS 24-Aug-19 11:00 AM DONE
3625 NMSCEW/P-IV/STR/2019/3562 3562 Checking and Pouring concrete for raft of U type retaining wall PUP Km 205+430 BHS 24-Aug-19 11:30 AM DONE
3626 NMSCEW/P-IV/STR/2019/3563 3563 Checking of reinforcement, shuttering for 1st lift at W2 wall Box culvert Km 203+886 LHS 24-Aug-19 2:00 PM
3627 NMSCEW/P-IV/STR/2019/3564 3564 Checking & Pouring concrete for 1st lift at W2 wall Box culvert Km 203+886 LHS 24-Aug-19 3:00 PM
3628 NMSCEW/P-IV/STR/2019/3565 3565 Checking of reinforcement, shuttering for raft at RA-02 Viaduct Km 196+560 RHS 24-Aug-19 12:15 PM IPC-08 DONE AE
3629 NMSCEW/P-IV/STR/2019/3566 3566 Checking & pouring concrete for raft at RA-02 Viaduct Km 196+560 RHS 24-Aug-19 12:45 PM IPC-08 DONE AE
3630 NMSCEW/P-IV/STR/2019/3567 3567 Checking of reinforcement, shuttering for raft at RP-01 Viaduct Km 200+920 RHS 24-Aug-19 4:00 PM IPC-08 DONE AE
3631 NMSCEW/P-IV/STR/2019/3568 3568 Checking & pouring concrete for raft at RP-01 Viaduct Km 200+920 RHS 24-Aug-19 4:30 PM IPC-08 DONE AE
Checking reinforcement for precast Box Culvert (3x3) (Cushion 2 to 4 m) at precast yard camp
3632 NMSCEW/P-IV/STR/2019/3569 3569 Box culvert Km 175+500 LHS 24-Aug-19 10:23 AM DONE
-1. Segment NO-141,142,143,144,145
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3633 NMSCEW/P-IV/STR/2019/3570 3570 Box culvert Km 175+500 LHS 24-Aug-19 11:46 AM DONE
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.-141,142,143,144,145
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
3634 NMSCEW/P-IV/STR/2019/3571 3571 Box culvert Km 175+500 LHS 24-Aug-19 11:16 AM DONE
-1. Segment NO-149,153,154
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3635 NMSCEW/P-IV/STR/2019/3572 3572 Box culvert Km 175+500 LHS 24-Aug-19 12:52 PM DONE
(2x2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-149,153,154
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
3636 NMSCEW/P-IV/STR/2019/3573 3573 Box culvert Km 175+500 LHS 24-Aug-19 3:56 PM IPC-08 183, 186, 187, 188
-1. Segment NO-183,186,187,188 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3637 NMSCEW/P-IV/STR/2019/3574 3574 Box culvert Km 175+500 LHS 24-Aug-19 5:10 PM IPC-08 183, 186
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-183,186,187,188
DONE
3638 NMSCEW/P-IV/STR/2019/3575 3575 Checking of reinforcement, shuttering for final lift at A1 wall Box culvert Km 182+350 RHS 24-Aug-19 11:25 AM IPC-08 DONE AE
3639 NMSCEW/P-IV/STR/2019/3576 3576 Checking & Pouring concrete(M-30) for final lift at A1 wall Box culvert Km 182+350 RHS 24-Aug-19 12:13 PM IPC-08 DONE AE
3640 NMSCEW/P-IV/STR/2019/3577 3577 Checking of reinforcement, shuttering for 3rd lift at A1 & A2 wall PUP Km 190+650 RHS 24-Aug-19 2:18 PM REPEATED
3641 NMSCEW/P-IV/STR/2019/3578 3578 Checking & Pouring concrete(M-30) for 3rd lift at A1 & A2 wall PUP Km 190+650 RHS 24-Aug-19 2:50 PM REPEATED
3642 NMSCEW/P-IV/STR/2019/3579 3579 Checking of reinforcement, shuttering for 6th lift at A1 & A2 wall VUP Km 176+614 LHS 24-Aug-19 9:33 AM IPC-08 DONE
3643 NMSCEW/P-IV/STR/2019/3580 3580 Checking & Pouring concrete for 6th lift at A1 & A2 wall VUP Km 176+614 LHS 24-Aug-19 10:44 AM IPC-08 DONE
3644 NMSCEW/P-IV/STR/2019/3581 3581 Checking of reinforcement, shuttering for raft at retaining wall A1 & A2 PUP Km 172+190 RHS 24-Aug-19 1:30 AM DONE
3645 NMSCEW/P-IV/STR/2019/3582 3582 Checking & Pouring concrete for raft at retaining wall A1 & A2 PUP Km 172+190 RHS 24-Aug-19 2:40 PM DONE
3646 NMSCEW/P-IV/STR/2019/3583 3583 Checking of reinforcement, shuttering for raft at retaining wall A2 PUP Km 172+190 LHS 24-Aug-19 2:50 PM NR
3647 NMSCEW/P-IV/STR/2019/3584 3584 Checking & Pouring concrete for raft at retaining wall A2 PUP Km 172+190 LHS 24-Aug-19 4:10 PM NR
3648 NMSCEW/P-IV/STR/2019/3585 3585 Checking of reinforcement, shuttering for pier shaft 2nd & final lift at LP-07 Viaduct Km 169+800 LHS 24-Aug-19 9:31 AM IPC-08 DONE AE
3649 NMSCEW/P-IV/STR/2019/3586 3586 Checking & pouring concrete(M-45) for pier shaft 2nd & final lift at LP-07 Viaduct Km 169+800 LHS 24-Aug-19 10:13 AM IPC-08 DONE AE
3650 NMSCEW/P-IV/STR/2019/3587 3587 Checking of reinforcement, shuttering for pier shaft 2nd & final lift at LP-06 Viaduct Km 169+800 LHS 24-Aug-19 10:39 AM IPC-08 DONE AE
3651 NMSCEW/P-IV/STR/2019/3588 3588 Checking & pouring concrete(M-45) for pier shaft 2nd & final lift at LP-06 Viaduct Km 169+800 LHS 24-Aug-19 11:22 AM IPC-08 DONE AE
3652 NMSCEW/P-IV/STR/2019/3589 3589 Checking of reinforcement, shuttering for pier cap at RP-07 Viaduct Km 169+800 RHS 24-Aug-19 2:32 PM IPC-08 DONE AE
3653 NMSCEW/P-IV/STR/2019/3590 3590 Checking & pouring concrete for pier cap at RP-07 Viaduct Km 169+800 RHS 24-Aug-19 3:09 PM IPC-08 DONE AE
3654 NMSCEW/P-IV/STR/2019/3591 3591 Checking of reinforcement, shuttering for pier cap at RP-05 Viaduct Km 169+800 RHS 24-Aug-19 3:37 PM NR
3655 NMSCEW/P-IV/STR/2019/3592 3592 Checking & pouring concrete for pier cap at RP-05 Viaduct Km 169+800 RHS 24-Aug-19 4:16 PM NR
3656 NMSCEW/P-IV/STR/2019/3593 3593 Checking of reinforcement, shuttering for 2nd lift at A1 & A2 wall PUP Km 190+650 LHS 24-Aug-19 10:00 AM REPEATED SPOT RFI
3657 NMSCEW/P-IV/STR/2019/3594 3594 Checking & Pouring concrete(M-30) for 2nd lift at A1 & A2 wall PUP Km 190+650 LHS 24-Aug-19 11:30 AM REPEATED SPOT RFI
3658 NMSCEW/P-IV/STR/2019/3595 3595 Checking of reinforcement, shuttering for median wall raft PUP Km 171+110 BHS 25-Aug-19 9:30 AM
NR
3659 NMSCEW/P-IV/STR/2019/3596 3596 Checking & pouring concrete for median wall raft PUP Km 171+110 BHS 25-Aug-19 10:30 AM
NR
3660 NMSCEW/P-IV/STR/2019/3597 3597 Checking of reinforcement, shuttering for median wall raft PUP Km 194+095 LHS 25-Aug-19 11:00 AM
3661 NMSCEW/P-IV/STR/2019/3598 3598 Checking & pouring concrete for median wall raft PUP Km 194+095 LHS 25-Aug-19 12:30 PM
3662 NMSCEW/P-IV/STR/2019/3599 3599 Checking of reinforcement, shuttering for raft VUP Km 179+983 Km 00+000 LHS 25-Aug-19 10:45 AM IPC-10 DONE
3663 NMSCEW/P-IV/STR/2019/3600 3600 Checking & pouring concrete for raft & Hunch VUP Km 179+983 Km 00+000 LHS 25-Aug-19 11:30 AM IPC-10 DONE
3664 NMSCEW/P-IV/STR/2019/3601 3601 Checking of reinforcement, shuttering for pier cap at RP-05 Viaduct Km 169+800 RHS 25-Aug-19 9:15 AM IPC-08
DONE AE
3665 NMSCEW/P-IV/STR/2019/3602 3602 Checking & pouring concrete for pier cap at RP-05 Viaduct Km 169+800 RHS 25-Aug-19 10:00 AM IPC-08
DONE AE
Checking for stressing and remove slagness of H.T. wires at Girder no-5,6,7,8 at bed no -5 at
3666 NMSCEW/P-IV/STR/2019/3603 3603 Girder Type-1 Km 200+200 LHS 25-Aug-19 10:09 AM
casting yard camp -2
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3667 NMSCEW/P-IV/STR/2019/3604 3604 Box culvert Km 175+500 LHS 25-Aug-19 2:30 PM DONE
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.-140
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3668 NMSCEW/P-IV/STR/2019/3605 3605 Box culvert Km 175+500 LHS 25-Aug-19 3:00 PM IPC-08 185, 187, 188
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-185
DONE AE
Checking of Shuttering and reinforcement for RE WALL PANEL precast TYPE -A
3669 NMSCEW/P-IV/STR/2019/3606 3606 32, TYPE -B 10, TYPE -Sta 2, TYPE -Stb 2, TYPE -Stc 2, TYPE -Std 2, TYPE -Ltc 1, RE Wall Panel Km 200+200 LHS 25-Aug-19 11:35 AM DONE
TYPE -Ltd 2,
Checking and Pouring concrete for RE WALL PANEL precastTYPE -A
3670 NMSCEW/P-IV/STR/2019/3607 3607 32, TYPE -B 10, TYPE -Sta 2, TYPE -Stb 2, TYPE -Stc 2, TYPE -Std 2, TYPE -Ltc 1, RE Wall Panel Km 200+200 LHS 25-Aug-19 12:11 PM DONE
TYPE -Ltd 2,
3671 NMSCEW/P-IV/STR/2019/3608 3608 Checking layout ,level and structural excavation at retaining wall A1 & A2 PUP Km 184+190 LHS 25-Aug-19 10:20 AM DONE
3672 NMSCEW/P-IV/STR/2019/3609 3609 Checking top Level & Laying concrete(M-10) PCC at retaining wall A1 & A2 PUP Km 184+190 LHS 25-Aug-19 11:19 AM DONE
3673 NMSCEW/P-IV/STR/2019/3610 3610 Checking of reinforcement, shuttering for final lift at A1 & A2 wall PUP Km 190+650 RHS 25-Aug-19 4:05 PM NR
3674 NMSCEW/P-IV/STR/2019/3611 3611 Checking & Pouring concrete(M-30) for final lift at A1 & A2 wall PUP Km 190+650 RHS 25-Aug-19 4:30 PM NR
3675 NMSCEW/P-IV/STR/2019/3612 3612 Checking layout ,level for PCC CUP 206+985 Km 00+000 BHS 25-Aug-19 8:45 AM IPC-09 DONE AE
3676 NMSCEW/P-IV/STR/2019/3613 3613 Checking top Level & Laying concrete PCC CUP 206+985 Km 00+000 BHS 25-Aug-19 3:15 PM IPC-09 DONE AE
3677 NMSCEW/P-IV/STR/2019/3614 3614 Checking layout ,level for raft Box culvert Km 208+675 LHS 25-Aug-19 11:03 AM DONE
3678 NMSCEW/P-IV/STR/2019/3615 3615 Checking & pouring concrete for raft Box culvert Km 208+675 LHS 25-Aug-19 11:32 AM DONE
3679 NMSCEW/P-IV/STR/2019/3616 3616 Checking of reinforcement, shuttering and layout,level for raft RA-1 Viaduct Km 202+190 RHS 26-Aug-19 3:00 PM IPC-08 DONE AE
3680 NMSCEW/P-IV/STR/2019/3617 3617 Checking & pouring concrete for raft RA-1 Viaduct Km 202+190 RHS 26-Aug-19 3:30 PM IPC-08 DONE AE
3681 NMSCEW/P-IV/STR/2019/3618 3618 Checking of reinforcement, shuttering for raft LP-2 Viaduct Km 200+920 LHS 26-Aug-19 4:00 PM
3682 NMSCEW/P-IV/STR/2019/3619 3619 Checking & pouring concrete for raft LP-2 Viaduct Km 200+920 LHS 26-Aug-19 4:30 PM
Checking of reinforcement, shuttering for final lift with top haunch at A1 & A2 wall and top
3683 NMSCEW/P-IV/STR/2019/3620 3620 PUP Km 165+300 LHS 26-Aug-19 4:15 PM REPEATED
slab
3684 NMSCEW/P-IV/STR/2019/3621 3621 Checking & Pouring concrete for final lift with top haunch at A1 & A2 wall and top slab PUP Km 165+300 LHS 26-Aug-19 5:10 PM REPEATED
3685 NMSCEW/P-IV/STR/2019/3622 3622 Checking layout ,level and structural for median drain outlets Pipe culvert Km 174+070 LHS 26-Aug-19 2:45 PM NR
3686 NMSCEW/P-IV/STR/2019/3623 3623 Checking top Level & Laying concrete(M-10) PCC Utility duct Km 170+300 BHS 26-Aug-19 1:00 PM NR
3687 NMSCEW/P-IV/STR/2019/3624 3624 Checking layout ,level and structural excavation Utility duct Km 171+570 Km 00+000 BHS 26-Aug-19 10:00 AM IPC-09 DONE
3688 NMSCEW/P-IV/STR/2019/3625 3625 Checking of reinforcement, shuttering for pier shaft 1st lift at RP3 Viaduct Km 202+190 Km 00+000 RHS 26-Aug-19 11:00 AM IPC-10 DONE SPOT RFI
3689 NMSCEW/P-IV/STR/2019/3626 3626 Checking & pouring concrete for pier shaft 1st lift at RP3 Viaduct Km 202+190 Km 00+000 RHS 26-Aug-19 11:30 AM IPC-10 DONE SPOT RFI
3690 NMSCEW/P-IV/STR/2019/3627 3627 Checking of layout and level for retaining wall at PUP PUP Km 205+430 LHS 27-Aug-19 8:00 AM DONE
3691 NMSCEW/P-IV/STR/2019/3628 3628 Checking & pouring concrete PCC for retaining wall at PUP PUP Km 205+430 LHS 27-Aug-19 8:30 AM DONE
3692 NMSCEW/P-IV/STR/2019/3629 3629 Checking top Level & Laying concrete PCC(M-10) at Utility duct Utility duct Km 170+300 BHS 27-Aug-19 1:00 PM NR
3693 NMSCEW/P-IV/STR/2019/3630 3630 Checking of layout excavation and level for retaining wall at A1 & A2 side PUP Km 185+235 RHS 27-Aug-19 10:30 AM NR
3694 NMSCEW/P-IV/STR/2019/3631 3631 Checking & pouring concrete PCC for retaining wall at A1 & A2 side PUP Km 185+235 RHS 27-Aug-19 10:40 AM NR
3695 NMSCEW/P-IV/STR/2019/3632 3632 Checking of layout,level and structural excavation for utility duct Utility duct Km 170+830 BHS 27-Aug-19 10:00 AM NR
3696 NMSCEW/P-IV/STR/2019/3633 3633 Checking of reinforcement & shuttering for 3rd lift A1 & A2 wall PUP Km 190+650 RHS 27-Aug-19 3:00 PM NR
3697 NMSCEW/P-IV/STR/2019/3634 3634 Checking and pouring concrete (M-30) for 3rd lift A1 & A2 wall PUP Km 190+650 RHS 27-Aug-19 3:10 PM NR
3698 NMSCEW/P-IV/STR/2019/3635 3635 Checking of reinforcement and shuttering and layout for pier shaft 1st lift at RP8 Viaduct Km 196+560 RHS 27-Aug-19 12:00 PM
3699 NMSCEW/P-IV/STR/2019/3636 3636 Checking and Pouring concrete for pier shaft 1st lift at RP8 Viaduct Km 196+560 RHS 27-Aug-19 12:30 PM
3700 NMSCEW/P-IV/STR/2019/3637 3637 Checking of reinforcement and shuttering and layout for pier starter at RP-5 Viaduct Km 196+560 RHS 27-Aug-19 3:20 PM
3701 NMSCEW/P-IV/STR/2019/3638 3638 Checking and Pouring concrete for pier starter at RP-5 Viaduct Km 196+560 RHS 27-Aug-19 3:40 PM
Checking reinforcement for precast Box Culvert (3x3) (cushion 2 to 4m) at precast yard camp
3702 NMSCEW/P-IV/STR/2019/3639 3639 Box culvert Km 175+500 LHS 27-Aug-19 10:00 AM DONE
-1. Segment NO-146,147,148,149,150
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
3703 NMSCEW/P-IV/STR/2019/3640 3640 Box culvert Km 175+500 LHS 27-Aug-19 10:20 AM DONE
-1. Segment NO-155,156,157
Checking reinforcement for precast Box Culvert (2x2) (cushion 0 to 2m) at precast yard camp
3704 NMSCEW/P-IV/STR/2019/3641 3641 Box culvert Km 175+500 LHS 27-Aug-19 10:30 AM IPC-08 189, 190, 191, 192
-1. Segment NO-189,190,191,192 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3705 NMSCEW/P-IV/STR/2019/3642 3642 Box culvert Km 175+500 LHS 27-Aug-19 10:40 AM DONE
(3×3) ,(Cushion 2 to 4m) at precast yard camp-1,Segment no.-146,147,148,149,150
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3706 NMSCEW/P-IV/STR/2019/3643 3643 Box culvert Km 175+500 LHS 27-Aug-19 10:50 AM DONE
(2×2) ,(Cushion 2 to 4m) at precast yard camp-1,Segment no.-155,156,157
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3707 NMSCEW/P-IV/STR/2019/3644 3644 Box culvert Km 175+500 LHS 27-Aug-19 11:00 AM IPC-08 189,190, 191, 192
(2×2) ,(Cushion 0 to 2m) at precast yard camp-1,Segment no.-189,190,191,192
DONE AE
3708 NMSCEW/P-IV/STR/2019/3645 3645 Checking of reinforcement and shuttering of final lift wall A1 & A2 PUP Km 165+300 LHS 27-Aug-19 4:00 PM REPEATED
3709 NMSCEW/P-IV/STR/2019/3646 3646 Checking and Pouring concrete of final lift wall A1 & A2 PUP Km 165+300 LHS 27-Aug-19 4:10 PM REPEATED
3710 NMSCEW/P-IV/STR/2019/3647 3647 Checking of reinforcement and shuttering and layout for pier shaft final lift at LP6 Viaduct Km 202+190 LHS 27-Aug-19 11:00 AM IPC-08 DONE AE
3711 NMSCEW/P-IV/STR/2019/3648 3648 Checking and Pouring concrete for pier shaft final lift at LP6 Viaduct Km 202+190 LHS 27-Aug-19 11:30 AM IPC-08 DONE AE
3712 NMSCEW/P-IV/STR/2019/3649 3649 Checking of reinforcement and shuttering and layout for RAFT at LP13 Viaduct Km 202+190 LHS 27-Aug-19 3:00 PM
3713 NMSCEW/P-IV/STR/2019/3650 3650 Checking and Pouring concrete for RAFT at LP13 Viaduct Km 202+190 LHS 27-Aug-19 3:30 PM
3714 NMSCEW/P-IV/STR/2019/3651 3651 Checking of reinforcement and shuttering and layout for pier shaft 1st lift at RP6 Viaduct Km 202+190 Km 00+000 RHS 27-Aug-19 2:00 PM IPC-10 DONE AE
3715 NMSCEW/P-IV/STR/2019/3652 3652 Checking and Pouring concrete for pier shaft 1st lift at RP6 Viaduct Km 202+190 Km 00+000 RHS 27-Aug-19 2:30 PM IPC-10 DONE AE
Checking reinforcement for precast Box Culvert (3x3) (cushion 2 to 4m) at precast yard camp
3716 NMSCEW/P-IV/STR/2019/3653 3653 Box culvert Km 175+500 LHS 27-Aug-19 11:00 AM DONE SPOT RFI
-1. Segment NO-151,152,153
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
3717 NMSCEW/P-IV/STR/2019/3654 3654 Box culvert Km 175+500 LHS 27-Aug-19 11:20 AM DONE SPOT RFI
-1. Segment NO-158,159,160
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3718 NMSCEW/P-IV/STR/2019/3655 3655 Box culvert Km 175+500 LHS 27-Aug-19 11:30 AM SPOT RFI
(3×3) ,(Cushion 2 to 4m) at precast yard camp-1,Segment no.-151,152,153 NR
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3719 NMSCEW/P-IV/STR/2019/3656 3656 Box culvert Km 175+500 LHS 27-Aug-19 11:40 AM DONE SPOT RFI
(2×2) ,(Cushion 2 to 4m) at precast yard camp-1,Segment no.-158,159,160
Checking reinforcement for precast Box Culvert (3x3) (cushion 2 to 4m) at precast yard camp
3720 NMSCEW/P-IV/STR/2019/3657 3657 Box culvert Km 175+500 LHS 28-Aug-19 9:14 AM DONE
-1. Segment NO-154,155,156,157,158.
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
3721 NMSCEW/P-IV/STR/2019/3658 3658 Box culvert Km 175+500 LHS 28-Aug-19 10:34 AM DONE
-1. Segment NO-161,162,163.
Checking reinforcement for precast Box Culvert (2x2) (cushion 0 to 2m) at precast yard camp
3722 NMSCEW/P-IV/STR/2019/3659 3659 Box culvert Km 175+500 LHS 28-Aug-19 11:46 AM IPC-08 193, 194, 195, 195
-1. Segment NO-193,194,195,196. DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3723 NMSCEW/P-IV/STR/2019/3660 3660 Box culvert Km 175+500 LHS 28-Aug-19 2:26 PM DONE
(3×3) ,(Cushion 2 to 4m) at precast yard camp-1,Segment no.-154,155,156,157,158.
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3724 NMSCEW/P-IV/STR/2019/3661 3661 Box culvert Km 175+500 LHS 28-Aug-19 2:58 PM DONE
(2×2) ,(Cushion 2 to 4m) at precast yard camp-1,Segment no.-161,162,163.
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3725 NMSCEW/P-IV/STR/2019/3662 3662 Box culvert Km 175+500 LHS 28-Aug-19 3:48 PM IPC-08 193, 194, 195, 196
(2×2) ,(Cushion 0 to 2m) at precast yard camp-1,Segment no.-193,194,195,196.
DONE AE
3726 NMSCEW/P-IV/STR/2019/3663 3663 Checking of reinforcement and shuttering and layout for pier starter at LP-8 Viaduct Km 202+190 LHS 28-Aug-19 2:30 PM
3727 NMSCEW/P-IV/STR/2019/3664 3664 Checking and Pouring concrete for pier starter at LP-8 Viaduct Km 202+190 LHS 28-Aug-19 3:00 PM
3728 NMSCEW/P-IV/STR/2019/3665 3665 Checking of reinforcement and shuttering and layout for pier starter at LP-9 Viaduct Km 202+190 LHS 28-Aug-19 2:00 PM
3729 NMSCEW/P-IV/STR/2019/3666 3666 Checking and Pouring concrete for pier starter at LP-9 Viaduct Km 202+190 LHS 28-Aug-19 2:30 PM
3730 NMSCEW/P-IV/STR/2019/3667 3667 Checking of reinforcement and shuttering and layout for raft at LP-13 Viaduct Km 202+190 LHS 28-Aug-19 3:00 PM IPC-08 DONE AE
3731 NMSCEW/P-IV/STR/2019/3668 3668 Checking and Pouring concrete for raft at LP-13 Viaduct Km 202+190 LHS 28-Aug-19 3:30 PM
3732 NMSCEW/P-IV/STR/2019/3669 3669 Checking of reinforcement and shuttering for pier shaft 2nd and final lift at RP-10 Viaduct Km 169+800 RHS 28-Aug-19 3:02 PM NR
3733 NMSCEW/P-IV/STR/2019/3670 3670 Checking and Pouring concrete for pier shaft 2nd and final lift at RP-10 Viaduct Km 169+800 RHS 28-Aug-19 3:36 PM NR
3734 NMSCEW/P-IV/STR/2019/3671 3671 Checking of reinforcement and shuttering and layout for raft at LP-02 Viaduct Km 200+920 LHS 28-Aug-19 10:39 AM IPC-08 DONE AE
3735 NMSCEW/P-IV/STR/2019/3672 3672 Checking and Pouring concrete for raft at LP-02 Viaduct Km 200+920 LHS 28-Aug-19 11:13 AM IPC-08 DONE AE
3736 NMSCEW/P-IV/STR/2019/3673 3673 Checking of reinforcement and shuttering and layout for raft at RP-01 Viaduct Km 196+560 RHS 28-Aug-19 11:30 AM IPC-08 DONE AE
3737 NMSCEW/P-IV/STR/2019/3674 3674 Checking and Pouring concrete for raft at RP-01 Viaduct Km 196+560 RHS 28-Aug-19 12:10 PM IPC-08 DONE
3738 NMSCEW/P-IV/STR/2019/3675 3675 Checking and Pouring concrete for pier shaft starter at LP-06 Viaduct Km 196+560 Km 00+000 LHS 28-Aug-19 11:40 AM IPC-10 DONE AE
3739 NMSCEW/P-IV/STR/2019/3676 3676 Checking and Pouring concrete for pier shaft starter at LP-06 Viaduct Km 196+560 Km 00+000 LHS 28-Aug-19 12:10 PM IPC-10 DONE
Checking of side shuttering girder no- 5,6,7 & 8 at bed no-05 ,Girder Type-1, at Casting Yard-
3740 NMSCEW/P-IV/STR/2019/3677 3677 Camp-2 Girder Km 200+200 LHS 28-Aug-19 2:30 PM
Checking & pouring concrete(M-50) of girder no- 5,6,7 & 8 at bed no-05 ,Girder Type-1, at
3741 NMSCEW/P-IV/STR/2019/3678 3678 Casting Yard-Camp-2 Girder Km 200+200 LHS 28-Aug-19 3:00 PM
3753 NMSCEW/P-IV/STR/2019/3690 3690 Checking layout ,level for PCC at RA-01 Viaduct Km 200+920 RHS 29-Aug-19 2:00 PM IPC-08
DONE AE
3754 NMSCEW/P-IV/STR/2019/3691 3691 Checking top Level & Laying concrete for PCC at RA-01 Viaduct Km 200+920 RHS 29-Aug-19 3:00 PM IPC-08
DONE AE
3755 NMSCEW/P-IV/STR/2019/3692 3692 Checking of reinforcement, shuttering & layout for pier shaft 1st lift at RP-08 Viaduct Km 196+560 Km 00+000 RHS 29-Aug-19 9:00 AM IPC-09 DONE
AE
3756 NMSCEW/P-IV/STR/2019/3693 3693 Checking & pouring concrete for pier shaft 1st lift at RP-08 Viaduct Km 196+560 Km 00+000 RHS 29-Aug-19 9:45 AM IPC-09 DONE
AE
3757 NMSCEW/P-IV/STR/2019/3694 3694 Checking of reinforcement, shuttering & layout for pier shaft 1st lift at RP-05 Viaduct Km 202+190 Km 00+000 RHS 29-Aug-19 11:40 AM IPC-10 DONE
AE
3758 NMSCEW/P-IV/STR/2019/3695 3695 Checking & pouring concrete for pier shaft 1st lift at RP-05 Viaduct Km 202+190 Km 00+000 RHS 29-Aug-19 12:50 PM IPC-10 DONE
AE
3759 NMSCEW/P-IV/STR/2019/3696 3696 Checking of reinforcement and shuttering for pier shaft 2nd and final lift at RP-10 Viaduct Km 169+800 RHS 29-Aug-19 2:15 PM IPC-08
DONE AE
3760 NMSCEW/P-IV/STR/2019/3697 3697 Checking and Pouring concrete for pier shaft 2nd and final lift at RP-10 Viaduct Km 169+800 RHS 29-Aug-19 3:20 PM IPC-08
DONE AE
3761 NMSCEW/P-IV/STR/2019/3698 3698 Checking of reinforcement, shuttering for pier shaft 2nd lift at LP-11 Viaduct Km 169+800 LHS 29-Aug-19 3:44 PM
NR
3762 NMSCEW/P-IV/STR/2019/3699 3699 Checking & pouring concrete for pier shaft 2nd lift at LP-11 Viaduct Km 169+800 LHS 29-Aug-19 4:20 PM
NR
3763 NMSCEW/P-IV/STR/2019/3700 3700 Checking top Level & Laying concrete (M-10) for PCC Utility duct Km 170+300 Km 00+000 BHS 29-Aug-19 10:15 AM IPC-09 DONE
Checking reinforcement for precast Box Culvert (3x3) (Cushion 2 to 4 m) at precast yard camp
3764 NMSCEW/P-IV/STR/2019/3701 3701 Box culvert Km 175+500 LHS 29-Aug-19 10:23 AM DONE
-1. Segment NO-150,151,152,153,159
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3765 NMSCEW/P-IV/STR/2019/3702 3702 Box culvert Km 175+500 LHS 29-Aug-19 11:46 AM DONE
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.-150,151,152,153,159
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
3766 NMSCEW/P-IV/STR/2019/3703 3703 Box culvert Km 175+500 LHS 29-Aug-19 11:16 AM DONE
-1. Segment NO-160,164,165
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3767 NMSCEW/P-IV/STR/2019/3704 3704 Box culvert Km 175+500 LHS 29-Aug-19 12:52 PM DONE
(2x2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-160,164,165
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
3768 NMSCEW/P-IV/STR/2019/3705 3705 Box culvert Km 175+500 LHS 29-Aug-19 3:56 PM IPC-08 197, 198, 199, 200
-1. Segment NO-197,198,199,200 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3769 NMSCEW/P-IV/STR/2019/3706 3706 Box culvert Km 175+500 LHS 29-Aug-19 5:10 PM IPC-08 197, 198, 199, 200
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-197,198,199,200
DONE AE
3770 NMSCEW/P-IV/STR/2019/3707 3707 Checking reinforcement & shuttering for Median raft PUP Km 171+110 BHS 29-Aug-19 4:00 PM DONE SPOT RFI
3771 NMSCEW/P-IV/STR/2019/3708 3708 Checking and concrete pouring for Median raft PUP Km 171+110 BHS 29-Aug-19 4:30 PM DONE SPOT RFI
3772 NMSCEW/P-IV/STR/2019/3709 3709 Checking of reinforcement, shuttering for raft at LP-09 Viaduct Km 195+900 LHS 30-Aug-19 10:00 AM IPC-08 DONE AE
3773 NMSCEW/P-IV/STR/2019/3710 3710 Checking layout ,level for raft at LP-09 Viaduct Km 195+900 LHS 30-Aug-19 10:30 AM IPC-08 DONE AE
3774 NMSCEW/P-IV/STR/2019/3711 3711 Checking & pouring concrete for raft at LP-09 Viaduct Km 195+900 LHS 30-Aug-19 11:00 AM IPC-08 DONE
Checking of pipe culvert median drain outlets shuttering for cradle & pouring of concrete
3775 NMSCEW/P-IV/STR/2019/3712 3712 Pipe culvert Km 168+400 LHS 30-Aug-19 10:00 AM DONE
M -15 grade concrete
3776 NMSCEW/P-IV/STR/2019/3713 3713 Checking of reinforcement, shuttering for raft with bottom haunch at A1 & A2 wall PUP Km 164+380 Km 00+000 LHS 30-Aug-19 5:00 PM IPC-10 DONE
3777 NMSCEW/P-IV/STR/2019/3714 3714 Checking & Pouring concrete for raft with bottom haunch at A1 & A2 wall PUP Km 164+380 Km 00+000 LHS 30-Aug-19 5:30 PM IPC-10 DONE
Checking reinforcement for precast Box Culvert (3x3) (Cushion 2 to 4 m) at precast yard camp
3778 NMSCEW/P-IV/STR/2019/3715 3715 Box culvert Km 175+500 LHS 30-Aug-19 9:30 AM
-1. Segment NO-160,161,162,163,164 NR
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3779 NMSCEW/P-IV/STR/2019/3716 3716 Box culvert Km 175+500 LHS 30-Aug-19 11:05 AM
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.-160,161,162,163,164
NR
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
3780 NMSCEW/P-IV/STR/2019/3717 3717 Box culvert Km 175+500 LHS 30-Aug-19 11:30 AM
-1. Segment NO-167,168,169,170 NR
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3781 NMSCEW/P-IV/STR/2019/3718 3718 Box culvert Km 175+500 LHS 30-Aug-19 12:45 PM
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-167,168,169,170
NR
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
3782 NMSCEW/P-IV/STR/2019/3719 3719 Box culvert Km 175+500 LHS 30-Aug-19 3:25 PM
-1. Segment NO-200,201,202,203 NR
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3783 NMSCEW/P-IV/STR/2019/3720 3720 Box culvert Km 175+500 LHS 30-Aug-19 4:22 PM
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-200,201,202,203
NR
3784 NMSCEW/P-IV/STR/2019/3721 3721 Checking of reinforcement and shuttering for pier shaft 2nd and final lift at LP-11 Viaduct Km 169+800 Km 00+000 LHS 30-Aug-19 2:00 PM IPC-09 DONE
3785 NMSCEW/P-IV/STR/2019/3722 3722 Checking and Pouring concrete for pier shaft 2nd and final lift at LP-11 Viaduct Km 169+800 Km 00+000 LHS 30-Aug-19 2:30 PM IPC-09 DONE
3786 NMSCEW/P-IV/STR/2019/3723 3723 Checking of reinforcement, shuttering for 1st lift at A1 & A2 wall Box culvert Km 180+427 RHS 30-Aug-19 9:35 AM IPC-08 DONE AE
3787 NMSCEW/P-IV/STR/2019/3724 3724 Checking & Pouring concrete for 1st lift at A1 & A2 wall Box culvert Km 180+427 RHS 30-Aug-19 10:33 AM IPC-08 DONE AE
3788 NMSCEW/P-IV/STR/2019/3725 3725 Checking of reinforcement, shuttering for median wall raft PUP Km 172+190 BHS 30-Aug-19 11:44 AM DONE
3789 NMSCEW/P-IV/STR/2019/3726 3726 Checking & Pouring concrete for median wall farft PUP Km 172+190 BHS 30-Aug-19 12:35 PM DONE
3790 NMSCEW/P-IV/STR/2019/3727 3727 Checking of reinforcement, shuttering,layout for pier shaft 1st lift at LP-4 Viaduct Km 196+560 Km 00+000 LHS 30-Aug-19 11:30 AM IPC-10 DONE AE
3791 NMSCEW/P-IV/STR/2019/3728 3728 Checking & pouring concrete for pier shaft 1st lift at LP-4 Viaduct Km 196+560 Km 00+000 LHS 30-Aug-19 11:50 AM IPC-10 DONE
3792 NMSCEW/P-IV/STR/2019/3729 3729 Checking layout ,level for PCC at Retaining wall PUP Km 204+470 RHS 30-Aug-19 8:00 AM DONE
3793 NMSCEW/P-IV/STR/2019/3730 3730 Checking top level & laying concrete for PCC at Retaining wall PUP Km 204+470 RHS 30-Aug-19 8:30 AM DONE
3794 NMSCEW/P-IV/STR/2019/3731 3731 Checking layout ,level for PCC at Retaining wall PUP Km 203+560 RHS 30-Aug-19 9:05 AM DONE
3795 NMSCEW/P-IV/STR/2019/3732 3732 Checking top level & laying concrete for PCC at Retaining wall PUP Km 203+560 RHS 30-Aug-19 9:35 AM DONE
3796 NMSCEW/P-IV/STR/2019/3733 3733 Checking of reinforcement, shuttering for 1st lift at U- type retaining wall W2 PUP Km 204+470 BHS 30-Aug-19 11:00 AM DONE
3797 NMSCEW/P-IV/STR/2019/3734 3734 Checking & pouring concrete for 1st lift at U- type retaining wall W2 PUP Km 204+470 BHS 30-Aug-19 11:30 AM DONE
3798 NMSCEW/P-IV/STR/2019/3735 3735 Checking & pouring concrete for raft at LP-13 Viaduct Km 202+190 LHS 30-Aug-19 11:30 AM IPC-08 DONE
3799 NMSCEW/P-IV/STR/2019/3736 3736 Checking of reinforcement, shuttering for bottom slab & haunch PUP Km 189+000 RHS 30-Aug-19 12:00 PM IPC-08 DONE AE SPOT RFI
3800 NMSCEW/P-IV/STR/2019/3737 3737 Checking & Pouring concrete (M-30) for bottom slab & haunch PUP Km 189+000 RHS 30-Aug-19 12:30 PM IPC-08 DONE AE SPOT RFI
3801 NMSCEW/P-IV/STR/2019/3738 3738 Checking of reinforcement and shuttering for raft at MNB MNB Km 203+409 BHS 30-Aug-19 5:00 PM IPC-08 DONE AE
3802 NMSCEW/P-IV/STR/2019/3739 3739 Checking & pouring concrete for raft at MNB MNB Km 203+409 BHS 30-Aug-19 5:30 PM IPC-08 DONE AE
3803 NMSCEW/P-IV/STR/2019/3740 3740 Checking of reinforcement, shuttering for 1st lift at U- type retaining wall W1 PUP Km 204+470 BHS 31-Aug-19 8:00 AM DONE
3804 NMSCEW/P-IV/STR/2019/3741 3741 Checking & pouring concrete for 1st lift at U- type retaining wall W1 PUP Km 204+470 BHS 31-Aug-19 8:30 AM DONE
3805 NMSCEW/P-IV/STR/2019/3742 3742 Checking of reinforcement, shuttering for 1st lift at U- type retaining wall W1 & W2 PUP Km 205+430 BHS 31-Aug-19 11:30 AM DONE
3806 NMSCEW/P-IV/STR/2019/3743 3743 Checking & pouring concrete for 1st lift at U- type retaining wall W1 & W2 PUP Km 205+430 BHS 31-Aug-19 12:10 PM DONE
Checking reinforcement for precast Box Culvert (3x3) (Cushion 2 to 4 m) at precast yard camp
3807 NMSCEW/P-IV/STR/2019/3744 3744 Box culvert Km 200+200 LHS 31-Aug-19 9:30 AM
-2. Segment NO-36,37.
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3808 NMSCEW/P-IV/STR/2019/3745 3745 Box culvert Km 200+200 LHS 31-Aug-19 11:05 AM
(3x3) (Cushion 2 to 4 m) at precast yard camp-2,Segment no.-36,37.
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
3809 NMSCEW/P-IV/STR/2019/3746 3746 Box culvert Km 200+200 LHS 31-Aug-19 11:30 AM
-2. Segment NO-331,332,333,334,335,336,337,338,339,340,341,342,343,344,345.
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3810 NMSCEW/P-IV/STR/2019/3747 3747 (2×2)(Cushion 2 to 4m) at precast yard camp-2,Segment no.- Box culvert Km 200+200 LHS 31-Aug-19 12:45 PM
331,332,333,334,335,336,337,338,339,340,341,342,343,344,345.
Checking reinforcement for precast Box Culvert (3x3)(Cushion 0 to 2m) at precast yard camp
3811 NMSCEW/P-IV/STR/2019/3748 3748 Box culvert Km 200+200 LHS 31-Aug-19 3:25 PM
-2. Segment NO-133,134,135,136.
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3812 NMSCEW/P-IV/STR/2019/3749 3749 Box culvert Km 200+200 LHS 31-Aug-19 4:22 PM
(3×3) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-133,134,135,136.
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3846 NMSCEW/P-IV/STR/2019/3783 3783 Box culvert Km 175+500 LHS 31-Aug-19 11:19 AM DONE
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.-165,166,167,168,169
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
3847 NMSCEW/P-IV/STR/2019/3784 3784 Box culvert Km 175+500 LHS 31-Aug-19 11:36 AM DONE
-1. Segment NO-166,171,172,173
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3848 NMSCEW/P-IV/STR/2019/3785 3785 Box culvert Km 175+500 LHS 31-Aug-19 12:42 PM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-166,171,172,173
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
3849 NMSCEW/P-IV/STR/2019/3786 3786 Box culvert Km 175+500 LHS 31-Aug-19 3:27 PM IPC-08 204, 205, 206, 207
-1. Segment NO-204,205,206,207 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3850 NMSCEW/P-IV/STR/2019/3787 3787 Box culvert Km 175+500 LHS 31-Aug-19 4:47 PM IPC-08 204, 205, 206, 207
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-204,205,206,207
DONE AE
3851 NMSCEW/P-IV/STR/2019/3788 3788 Checking of reinforcement and shuttering for pier shaft 2nd & final lift at LP-11 Viaduct Km 169+800 LHS 31-Aug-19 8:30 AM NR
3852 NMSCEW/P-IV/STR/2019/3789 3789 Checking and Pouring concrete for pier shaft 2nd & final lift at LP-11 Viaduct Km 169+800 LHS 31-Aug-19 9:10 AM NR
3853 NMSCEW/P-IV/STR/2019/3790 3790 Checking of reinforcement and shuttering for pier cap at RP-06 Viaduct Km 169+800 RHS 31-Aug-19 4:12 PM IPC-08 DONE AE
3854 NMSCEW/P-IV/STR/2019/3791 3791 Checking and Pouring concrete for pier cap at RP-06 Viaduct Km 169+800 RHS 31-Aug-19 4:49 PM IPC-08 DONE AE
3855 NMSCEW/P-IV/STR/2019/3792 3792 Checking of Shuttering and reinforcement for raft at retaining wall A2 PUP Km 172+190 LHS 1-Sep-19 8:30 AM DONE
3856 NMSCEW/P-IV/STR/2019/3793 3793 Checking and Pouring concrete for raft at retaining wall A2 PUP Km 172+190 LHS 1-Sep-19 9:10 AM DONE
3857 NMSCEW/P-IV/STR/2019/3794 3794 Checking reinforcement ,shuttering for bottom haunch at wall A1 & A2 Box culvert Km 180+427 LHS 1-Sep-19 10:30 AM IPC-08
DONE
3858 NMSCEW/P-IV/STR/2019/3795 3795 Checking and concrete pouring for for bottom haunch at wall A1 & A2 Box culvert Km 180+427 LHS 1-Sep-19 11:30 AM IPC-08
DONE
3859 NMSCEW/P-IV/STR/2019/3796 3796 Checking layout ,level and structural excavation for median wall PUP Km 177+810 BHS 1-Sep-19 10:45 AM DONE
3860 NMSCEW/P-IV/STR/2019/3797 3797 Checking of reinforcement, shuttering for 5th lift at A1 & A2 wall VUP Km 179+983 RHS 1-Sep-19 12:30 PM IPC-08
DONE
3861 NMSCEW/P-IV/STR/2019/3798 3798 Checking & Pouring concrete for 5th lift at A1 & A2 wall VUP Km 179+983 RHS 1-Sep-19 1:30 AM IPC-08
DONE
3862 NMSCEW/P-IV/STR/2019/3799 3799 Checking reinforcement ,shuttering for bottom slab Box culvert Km 180+922 RHS 1-Sep-19 10:15 AM
NR
3863 NMSCEW/P-IV/STR/2019/3800 3800 Checking and concrete (M30) pouring for bottom slab Box culvert Km 180+922 RHS 1-Sep-19 10:50 AM
NR
3864 NMSCEW/P-IV/STR/2019/3801 3801 Checking and concrete (M30) pouring for bottom slab of loop-A MNB loop-A Km 01+980 1-Sep-19 8:00 AM
NR
3865 NMSCEW/P-IV/STR/2019/3802 3802 Checking of side shuttering girder no- 9,10,11,12 at bed no-07,Girder Type-1 Girder Km 200+200 LHS 1-Sep-19 8:15 AM
Approval for pouring of girder no- 9,10,11,12 at bed no-07. (Grade of concrete M-50)
3866 NMSCEW/P-IV/STR/2019/3803 3803 Girder Km 200+200 LHS 1-Sep-19 8:30 AM
Girder Type- 1
Checking reinforcement for precast Box Culvert (3x3) (Cushion 2 to 4 m) at precast yard camp
3867 NMSCEW/P-IV/STR/2019/3804 3804 Box culvert Km 200+200 LHS 1-Sep-19 9:35 AM DONE
-2. Segment NO-38.
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3868 NMSCEW/P-IV/STR/2019/3805 3805 Box culvert Km 200+200 LHS 1-Sep-19 11:11 AM DONE
(3x3) (Cushion 2 to 4 m) at precast yard camp-2,Segment no.-38.
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
3869 NMSCEW/P-IV/STR/2019/3806 3806 Box culvert Km 200+200 LHS 1-Sep-19 11:30 AM DONE
-2. Segment NO-346,347,348,349,350,351,352,353,354,355,356,357,358,359,360.
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3870 NMSCEW/P-IV/STR/2019/3807 3807 (2×2)(Cushion 2 to 4m) at precast yard camp-2,Segment no.- Box culvert Km 200+200 LHS 1-Sep-19 2:20 PM DONE
346,347,348,349,350,351,352,353,354,355,356,357,358,359,360.
Checking reinforcement for precast Box Culvert (3x3)(Cushion 0 to 2m) at precast yard camp
3871 NMSCEW/P-IV/STR/2019/3808 3808 Box culvert Km 200+200 LHS 1-Sep-19 3:30 PM DONE
-2. Segment NO-137,138,139
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3872 NMSCEW/P-IV/STR/2019/3809 3809 Box culvert Km 200+200 LHS 1-Sep-19 4:26 PM DONE
(3×3) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-137,138,139
3873 NMSCEW/P-IV/STR/2019/3810 3810 Checking of Shuttering and reinforcement for raft at retaining wall W2 PUP Km 205+430 LHS 1-Sep-19 9:09 AM DONE
3874 NMSCEW/P-IV/STR/2019/3811 3811 Checking and Pouring concrete for raft at retaining wall W2 PUP Km 205+430 LHS 1-Sep-19 9:39 AM DONE
Checking reinforcement for precast Box Culvert (3x3) (Cushion 2 to 4 m) at precast yard camp
3875 NMSCEW/P-IV/STR/2019/3812 3812 Box culvert Km 175+500 LHS 1-Sep-19 9:21 AM
-1. Segment NO-160,161,162,163,164
NR
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3876 NMSCEW/P-IV/STR/2019/3813 3813 Box culvert Km 175+500 LHS 1-Sep-19 11:05 AM
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.-160,161,162,163,164
NR
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
3877 NMSCEW/P-IV/STR/2019/3814 3814 Box culvert Km 175+500 LHS 1-Sep-19 11:47 AM
-1. Segment NO-167,168,169,170
NR
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3878 NMSCEW/P-IV/STR/2019/3815 3815 Box culvert Km 175+500 LHS 1-Sep-19 12:51 PM
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-167,168,169,170
NR
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
3879 NMSCEW/P-IV/STR/2019/3816 3816 Box culvert Km 175+500 LHS 1-Sep-19 3:44 PM
-1. Segment NO-200,201,202,203
NR
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3880 NMSCEW/P-IV/STR/2019/3817 3817 Box culvert Km 175+500 LHS 1-Sep-19 5:10 PM
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-200,201,202,203
NR
3881 NMSCEW/P-IV/STR/2019/3818 3818 Checking of Line, level and layout of bed-8 for Girder, casting yard at Camp-2 Girder Km 200+200 LHS 1-Sep-19 9:15 AM
3882 NMSCEW/P-IV/STR/2019/3819 3819 Checking top Level & Laying concrete for PCC at median wall PUP Km 177+810 BHS 2-Sep-19 10:30 AM DONE
3883 NMSCEW/P-IV/STR/2019/3820 3820 Checking of side shuttering girder no- 13,14,15,16 at bed no-03,Girder Type-2 Girder Km 200+200 LHS 2-Sep-19 3:00 PM
Approval for pouring of girder no- 13,14,15,16 at bed no-03. (Grade of concrete M-50)
3884 NMSCEW/P-IV/STR/2019/3821 3821 Girder Km 200+200 LHS 2-Sep-19 3:30 PM
Girder Type- 2
3885 NMSCEW/P-IV/STR/2019/3822 3822 Checking of reinforcement and shuttering for pier shaft 1st lift at RP-07 Viaduct Km 202+190 RHS 2-Sep-19 11:00 AM
3886 NMSCEW/P-IV/STR/2019/3823 3823 Checking and Pouring concrete for pier shaft 1st lift at RP-07 Viaduct Km 202+190 RHS 2-Sep-19 11:30 AM
3887 NMSCEW/P-IV/STR/2019/3824 3824 Checking of reinforcement and shuttering for pier shaft final lift at LP-07 Viaduct Km 202+190 LHS 2-Sep-19 12:00 PM
3888 NMSCEW/P-IV/STR/2019/3825 3825 Checking and Pouring concrete for pier shaft final lift at LP-07 Viaduct Km 202+190 LHS 2-Sep-19 12:30 PM
3889 NMSCEW/P-IV/STR/2019/3826 3826 Checking of reinforcement , shuttering, level & layout for pier shaft final lift at RP-6 Viaduct Km 202+190 RHS 2-Sep-19 11:45 AM
3890 NMSCEW/P-IV/STR/2019/3827 3827 Checking and Pouring concrete for pier shaft final lift at RP-6 Viaduct Km 202+190 RHS 2-Sep-19 12:30 PM
3891 NMSCEW/P-IV/STR/2019/3828 3828 Checking of Shuttering and reinforcement for raft at LP-01 Viaduct Km 200+920 LHS 2-Sep-19 2:00 PM
3892 NMSCEW/P-IV/STR/2019/3829 3829 Checking and Pouring concrete for raft at LP-01 Viaduct Km 200+920 LHS 2-Sep-19 2:30 PM
3893 NMSCEW/P-IV/STR/2019/3830 3830 Checking of reinforcement and shuttering for pier shaft 2nd & final lift at LP-02 Viaduct Km 169+800 Km 00+000 LHS 2-Sep-19 2:15 PM IPC-09 DONE
3894 NMSCEW/P-IV/STR/2019/3831 3831 Checking and Pouring concrete for pier shaft 2nd & final lift at LP-02 Viaduct Km 169+800 Km 00+000 LHS 2-Sep-19 2:45 PM IPC-09 DONE
3895 NMSCEW/P-IV/STR/2019/3832 3832 Checking of reinforcement and shuttering for pier shaft 2nd & final lift at RP-12 Viaduct Km 169+800 Km 00+000 RHS 2-Sep-19 3:15 PM IPC-09 DONE
3896 NMSCEW/P-IV/STR/2019/3833 3833 Checking and Pouring concrete for pier shaft 2nd & final lift at RP-12 Viaduct Km 169+800 Km 00+000 RHS 2-Sep-19 3:45 PM IPC-09 DONE
3897 NMSCEW/P-IV/STR/2019/3834 3834 Checking of reinforcement and shuttering for pier shaft 2nd & final lift at RP-11 Viaduct Km 169+800 Km 00+000 RHS 2-Sep-19 4:00 PM IPC-09 DONE
3898 NMSCEW/P-IV/STR/2019/3835 3835 Checking and Pouring concrete for pier shaft 2nd & final lift at RP-11 Viaduct Km 169+800 Km 00+000 RHS 2-Sep-19 4:30 PM IPC-09 DONE
Checking reinforcement for precast Box Culvert (3x3) (Cushion 2 to 4 m) at precast yard camp
3899 NMSCEW/P-IV/STR/2019/3836 3836 Box culvert Km 175+500 LHS 2-Sep-19 9:35 AM
-1. Segment NO-170,171,172,173,174 NR
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3900 NMSCEW/P-IV/STR/2019/3837 3837 Box culvert Km 175+500 LHS 2-Sep-19 11:11 AM
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.-170,171,172,173,174
NR
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
3901 NMSCEW/P-IV/STR/2019/3838 3838 Box culvert Km 175+500 LHS 2-Sep-19 11:40 AM
-1. Segment NO-174,175,176,177 NR
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3902 NMSCEW/P-IV/STR/2019/3839 3839 Box culvert Km 175+500 LHS 2-Sep-19 12:50 PM
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-174,175,176,177
NR
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
3903 NMSCEW/P-IV/STR/2019/3840 3840 Box culvert Km 175+500 LHS 2-Sep-19 3:35 PM
-1. Segment NO-208,209,210,211 NR
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3904 NMSCEW/P-IV/STR/2019/3841 3841 Box culvert Km 175+500 LHS 2-Sep-19 5:15 PM
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-208,209,210,211
NR
3905 NMSCEW/P-IV/STR/2019/3842 3842 Checking of reinforcement and shuttering for haunch at median wall PUP Km 171+110 BHS 2-Sep-19 3:25 PM DONE
3906 NMSCEW/P-IV/STR/2019/3843 3843 Checking and Pouring concrete for haunch at median wall PUP Km 171+110 BHS 2-Sep-19 3:55 PM DONE
3907 NMSCEW/P-IV/STR/2019/3844 3844 Checking and concrete (M35) pouring for bottom slab of loop-A MNB loop-A Km 01+980 Km 00+000 BHS 2-Sep-19 11:18 AM IPC-10 DONE AE SPOT RFI
3908 NMSCEW/P-IV/STR/2019/3845 3845 Checking of Shuttering and reinforcement for 1st lift at retaining wall A1 & A2 PUP Km 172+190 RHS 3-Sep-19 3:30 PM NR
3909 NMSCEW/P-IV/STR/2019/3846 3846 Checking and Pouring concrete for 1st lift at retaining wall A1 & A2 PUP Km 172+190 RHS 3-Sep-19 4:00 PM NR
Approval for pouring of girder no- 9,10,11,12 at bed no-07. (Grade of concrete M-50)
3910 NMSCEW/P-IV/STR/2019/3847 3847 Girder Km 200+200 LHS 3-Sep-19 8:15 AM
Girder Type- 1
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
3911 NMSCEW/P-IV/STR/2019/3848 3848 Box culvert Km 200+200 LHS 3-Sep-19 9:30 AM DONE
-2. Segment NO-361,362,363,364,365,366,367,368,369,370,371,372,373,374,375.
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3912 NMSCEW/P-IV/STR/2019/3849 3849 (2×2)(Cushion 2 to 4m) at precast yard camp-2,Segment no.- Box culvert Km 200+200 LHS 3-Sep-19 11:00 AM DONE
361,362,363,364,365,366,367,368,369,370,371,372,373,374,375.
Checking reinforcement for precast Box Culvert (3x3)(Cushion 0 to 2m) at precast yard camp
3913 NMSCEW/P-IV/STR/2019/3850 3850 Box culvert Km 200+200 LHS 3-Sep-19 2:30 PM DONE
-2. Segment NO-140
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3914 NMSCEW/P-IV/STR/2019/3851 3851 Box culvert Km 200+200 LHS 3-Sep-19 3:00 PM DONE
(3×3) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-140
Checking of Shuttering and reinforcement for RE WALL PANEL precast TYPE -A
3915 NMSCEW/P-IV/STR/2019/3852 3852 32, TYPE -B 10, TYPE -Sta 2, TYPE -Stb 2, TYPE -Stc 2, TYPE -Std 2, TYPE -Ltc 1, RE Wall Panel Km 200+200 LHS 3-Sep-19 10:00 AM DONE
TYPE -Ltd 2,
Checking and Pouring concrete for RE WALL PANEL precastTYPE -A
3916 NMSCEW/P-IV/STR/2019/3853 3853 32, TYPE -B 10, TYPE -Sta 2, TYPE -Stb 2, TYPE -Stc 2, TYPE -Std 2, TYPE -Ltc 1, RE Wall Panel Km 200+200 LHS 3-Sep-19 11:15 AM DONE
TYPE -Ltd 2,
Checking reinforcement for precast Box Culvert (3x3) (Cushion 2 to 4 m) at precast yard camp
3917 NMSCEW/P-IV/STR/2019/3854 3854 Box culvert Km 175+500 LHS 3-Sep-19 9:25 AM IPC-08 160
-1. Segment NO-160,161,162,163,164 DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3918 NMSCEW/P-IV/STR/2019/3855 3855 Box culvert Km 175+500 LHS 3-Sep-19 11:30 AM IPC-08 160
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.-160,161,162,163,164
DONE
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
3919 NMSCEW/P-IV/STR/2019/3856 3856 Box culvert Km 175+500 LHS 3-Sep-19 11:50 AM DONE
-1. Segment NO-167,168,169,170,173
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3920 NMSCEW/P-IV/STR/2019/3857 3857 Box culvert Km 175+500 LHS 3-Sep-19 12:45 PM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-167,168,169,170,173
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
3921 NMSCEW/P-IV/STR/2019/3858 3858 Box culvert Km 175+500 LHS 3-Sep-19 3:40 PM IPC-08 232, 201, 202, 204
-1. Segment NO-200,201,202,203 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3922 NMSCEW/P-IV/STR/2019/3859 3859 Box culvert Km 175+500 LHS 3-Sep-19 4:40 PM IPC-08 232, 201, 202, 203
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-200,201,202,203
DONE AE
3923 NMSCEW/P-IV/STR/2019/3860 3860 Checking of Shuttering and reinforcement for 2nd lift at U-type retaining wall W2 PUP Km 205+430 BHS 3-Sep-19 8:00 AM DONE
3924 NMSCEW/P-IV/STR/2019/3861 3861 Checking and Pouring concrete for 2nd lift at U-type retaining wall W2 PUP Km 205+430 BHS 3-Sep-19 8:30 AM DONE
3925 NMSCEW/P-IV/STR/2019/3862 3862 Checking of Shuttering and reinforcement for 2nd lift at U-type retaining wall W2 PUP Km 204+470 BHS 3-Sep-19 10:10 AM DONE
3926 NMSCEW/P-IV/STR/2019/3863 3863 Checking and Pouring concrete for 2nd lift at U-type retaining wall W2 PUP Km 204+470 BHS 3-Sep-19 10:44 AM DONE
3927 NMSCEW/P-IV/STR/2019/3864 3864 Checking of Shuttering and reinforcement for 3rd lift at wall W1 PUP Km 193+880 LHS 3-Sep-19 9:00 AM IPC-08 DONE AE
3928 NMSCEW/P-IV/STR/2019/3865 3865 Checking and Pouring concrete for 3rd lift at wall W1 PUP Km 193+880 LHS 3-Sep-19 9:50 AM IPC-08 DONE AE
3929 NMSCEW/P-IV/STR/2019/3866 3866 Checking of reinforcement and shuttering for pier shaft starter at LP-13 Viaduct Km 202+190 Km 00+000 LHS 3-Sep-19 10:05 AM IPC-11 Approved AE
3930 NMSCEW/P-IV/STR/2019/3867 3867 Checking and Pouring concrete for pier shaft starter at LP-13 Viaduct Km 202+190 Km 00+000 LHS 3-Sep-19 10:32 AM IPC-11 Approved
3931 NMSCEW/P-IV/STR/2019/3868 3868 Checking of reinforcement ,shuttering,layout & level for pier shaft starter at LP-10 Viaduct Km 202+190 Km 00+000 LHS 3-Sep-19 11:12 AM IPC-10 DONE AE
3932 NMSCEW/P-IV/STR/2019/3869 3869 Checking and Pouring concrete for pier shaft starter at LP-10 Viaduct Km 202+190 Km 00+000 LHS 3-Sep-19 11:44 AM IPC-10 DONE
3933 NMSCEW/P-IV/STR/2019/3870 3870 Checking of reinforcement and shuttering for pier shaft final lift at LP-5 Viaduct Km 202+190 LHS 3-Sep-19 2:00 PM
3934 NMSCEW/P-IV/STR/2019/3871 3871 Checking and Pouring concrete for pier shaft final lift at LP-5 Viaduct Km 202+190 LHS 3-Sep-19 2:35 PM
3935 NMSCEW/P-IV/STR/2019/3872 3872 Checking of reinforcement and shuttering for pier shaft 1st lift at RA-01 Viaduct Km 169+800 RHS 3-Sep-19 2:15 PM NR
3936 NMSCEW/P-IV/STR/2019/3873 3873 Checking and Pouring concrete for pier shaft 1st lift at RA-01 Viaduct Km 169+800 RHS 3-Sep-19 2:47 PM NR
3937 NMSCEW/P-IV/STR/2019/3874 3874 Checking of Shuttering and reinforcement for 1st lift at wall A1 & A2 PUP Km 165+790 RHS 3-Sep-19 4:05 PM IPC-08 DONE AE
3938 NMSCEW/P-IV/STR/2019/3875 3875 Checking and Pouring concrete for 1st lift at wall A1 & A2 PUP Km 165+790 RHS 3-Sep-19 4:50 PM IPC-08 DONE AE
3939 NMSCEW/P-IV/STR/2019/3876 3876 Checking of reinforcement and shuttering for pier shaft starter at RP-05 Viaduct Km 200+920 RHS 3-Sep-19 10:23 AM
3940 NMSCEW/P-IV/STR/2019/3877 3877 Checking and Pouring concrete for pier shaft starter at RP-05 Viaduct Km 200+920 RHS 3-Sep-19 10:46 AM
3941 NMSCEW/P-IV/STR/2019/3878 3878 Checking of reinforcement and shuttering for pier shaft starter at LP-05 Viaduct Km 200+920 Km 00+000 LHS 3-Sep-19 11:24 AM IPC-11 Approved AE
3942 NMSCEW/P-IV/STR/2019/3879 3879 Checking and Pouring concrete for pier shaft starter at LP-05 Viaduct Km 200+920 Km 00+000 LHS 3-Sep-19 11:55 AM IPC-11 Approved
3943 NMSCEW/P-IV/STR/2019/3880 3880 Checking of reinforcement and shuttering for pier shaft starter at RP-01 Viaduct Km 196+560 Km 00+000 RHS 3-Sep-19 3:09 PM IPC-11 Approved
3944 NMSCEW/P-IV/STR/2019/3881 3881 Checking and Pouring concrete for pier shaft starter at RP-01 Viaduct Km 196+560 Km 00+000 RHS 3-Sep-19 3:47 PM IPC-11 Approved
3945 NMSCEW/P-IV/STR/2019/3882 3882 Checking of reinforcement and shuttering for pier shaft starter at RP-02 Viaduct Km 196+560 Km 00+000 RHS 3-Sep-19 4:20 PM IPC-10 DONE AE
3946 NMSCEW/P-IV/STR/2019/3883 3883 Checking and Pouring concrete for pier shaft starter at RP-02 Viaduct Km 196+560 Km 00+000 RHS 3-Sep-19 5:00 PM IPC-10 DONE
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
3947 NMSCEW/P-IV/STR/2019/3884 3884 Box culvert Km 200+200 LHS 4-Sep-19 9:30 AM DONE
-2. Segment NO-376,377,378,379,380,381,382.
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3948 NMSCEW/P-IV/STR/2019/3885 3885 Box culvert Km 200+200 LHS 4-Sep-19 11:30 AM DONE
(2×2)(Cushion 2 to 4m) at precast yard camp-2,Segment no.-376,377,378,379,380,381,382
Checking reinforcement for precast Box Culvert (3x3)(Cushion 2 to 4m) at precast yard camp
3949 NMSCEW/P-IV/STR/2019/3886 3886 Box culvert Km 200+200 LHS 4-Sep-19 2:30 PM DONE
-2. Segment NO-39
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3950 NMSCEW/P-IV/STR/2019/3887 3887 Box culvert Km 200+200 LHS 4-Sep-19 3:15 PM DONE
(3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-39
Checking reinforcement for precast Box Culvert (3x3)(Cushion 0 to 2m) at precast yard camp
3951 NMSCEW/P-IV/STR/2019/3888 3888 Box culvert Km 200+200 LHS 4-Sep-19 3:25 PM DONE
-2. Segment NO-141,142
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3952 NMSCEW/P-IV/STR/2019/3889 3889 Box culvert Km 200+200 LHS 4-Sep-19 4:11 PM DONE
(3×3) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-141,142
3953 NMSCEW/P-IV/STR/2019/3890 3890 Checking of reinforcement, shuttering for 1st lift at A1 & A2 wall VUP Km 179+983 Km 00+000 LHS 4-Sep-19 10:30 AM IPC-10 DONE
3954 NMSCEW/P-IV/STR/2019/3891 3891 Checking & Pouring concrete for 1st lift at A1 & A2 wall VUP Km 179+983 Km 00+000 LHS 4-Sep-19 11:45 AM IPC-10 DONE
Checking reinforcement for precast Box Culvert (3x3) (Cushion 2 to 4 m) at precast yard camp
3955 NMSCEW/P-IV/STR/2019/3892 3892 Box culvert Km 175+500 LHS 4-Sep-19 9:15 AM IPC-08 170, 171, 172, 173, 174
-1. Segment NO-170,171,172,173,174 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3956 NMSCEW/P-IV/STR/2019/3893 3893 Box culvert Km 175+500 LHS 4-Sep-19 11:50 AM IPC-08 170, 171, 172, 173, 175
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.-170,171,172,173,174
DONE AE
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
3957 NMSCEW/P-IV/STR/2019/3894 3894 Box culvert Km 175+500 LHS 4-Sep-19 12:10 PM DONE
-1. Segment NO-174,175,176,177
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3958 NMSCEW/P-IV/STR/2019/3895 3895 Box culvert Km 175+500 LHS 4-Sep-19 12:50 PM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-174,175,176,177
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
3959 NMSCEW/P-IV/STR/2019/3896 3896 Box culvert Km 175+500 LHS 4-Sep-19 4:00 PM IPC-08 208, 209, 210, 211
-1. Segment NO-208,209,210,211 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3960 NMSCEW/P-IV/STR/2019/3897 3897 Box culvert Km 175+500 LHS 4-Sep-19 4:50 PM IPC-08 208, 209, 210
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-208,209,210,211
DONE AE
3961 NMSCEW/P-IV/STR/2019/3898 3898 Checking layout ,level and structural excavation Utility duct Km 172+520 BHS 4-Sep-19 10:00 AM IPC-08 DONE
3962 NMSCEW/P-IV/STR/2019/3899 3899 Checking of reinforcement, shuttering for 1st lift at A1 & A2 wall PUP Km 189+000 RHS 4-Sep-19 10:15 AM NR
3963 NMSCEW/P-IV/STR/2019/3900 3900 Checking & Pouring concrete(M-30) for 1st lift at A1 & A2 wall PUP Km 189+000 RHS 4-Sep-19 10:50 AM NR
3964 NMSCEW/P-IV/STR/2019/3901 3901 Checking of reinforcement, shuttering for bottom slab Box culvert Km 180+922 BHS 4-Sep-19 4:10 PM NR
3965 NMSCEW/P-IV/STR/2019/3902 3902 Checking & Pouring concrete (M-35) for bottom slab Box culvert Km 180+922 BHS 4-Sep-19 4:30 PM NR
3966 NMSCEW/P-IV/STR/2019/3903 3903 Checking of side shuttering girder no- 13,14,15,16 at bed no-03,Girder Type-2 Girder Km 200+200 LHS 4-Sep-19 9:40 AM
Approval for pouring of girder no- 13,14,15,16 at bed no-03. (Grade of concrete M-50)
3967 NMSCEW/P-IV/STR/2019/3904 3904 Girder Km 200+200 LHS 4-Sep-19 10:20 AM
Girder Type- 2
3968 NMSCEW/P-IV/STR/2019/3905 3905 Checking of reinforcement and shuttering for pier shaft 1st lift at RA-01 Viaduct Km 169+800 RHS 4-Sep-19 2:00 PM DONE
3969 NMSCEW/P-IV/STR/2019/3906 3906 Checking and Pouring concrete for pier shaft 1st lift at RA-01 Viaduct Km 169+800 RHS 4-Sep-19 2:30 PM NR
3970 NMSCEW/P-IV/STR/2019/3907 3907 Checking of reinforcement and shuttering for pier shaft 2nd & final lift at LP-01 Viaduct Km 169+800 Km 00+000 LHS 4-Sep-19 3:00 PM IPC-09 DONE
3971 NMSCEW/P-IV/STR/2019/3908 3908 Checking and Pouring concrete for pier shaft 2nd & final lift at LP-01 Viaduct Km 169+800 Km 00+000 LHS 4-Sep-19 3:30 PM IPC-09 DONE
3972 NMSCEW/P-IV/STR/2019/3909 3909 Checking of Shuttering and reinforcement for raft at LP-01 Viaduct Km 200+920 LHS 4-Sep-19 11:00 AM IPC-08 DONE AE
3973 NMSCEW/P-IV/STR/2019/3910 3910 Checking and Pouring concrete for raft at LP-01 Viaduct Km 200+920 LHS 4-Sep-19 11:55 AM IPC-08 DONE AE
3974 NMSCEW/P-IV/STR/2019/3911 3911 Checking of reinforcement and shuttering for pier shaft final lift at LP-07 Viaduct Km 202+190 LHS 4-Sep-19 12:00 PM
3975 NMSCEW/P-IV/STR/2019/3912 3912 Checking and Pouring concrete for pier shaft final lift at LP-07 Viaduct Km 202+190 LHS 4-Sep-19 12:30 PM
3976 NMSCEW/P-IV/STR/2019/3913 3913 Checking of reinforcement and shuttering for pier shaft final lift at RP-02 Viaduct Km 202+190 RHS 4-Sep-19 2:15 PM
3977 NMSCEW/P-IV/STR/2019/3914 3914 Checking and Pouring concrete for pier shaft final lift at RP-02 Viaduct Km 202+190 RHS 4-Sep-19 2:45 PM
3978 NMSCEW/P-IV/STR/2019/3915 3915 Checking of reinforcement and shuttering for pier shaft final lift at RP-06 Viaduct Km 202+190 RHS 4-Sep-19 3:22 PM
3979 NMSCEW/P-IV/STR/2019/3916 3916 Checking and Pouring concrete for pier shaft final lift at RP-06 Viaduct Km 202+190 RHS 4-Sep-19 3:50 PM
3980 NMSCEW/P-IV/STR/2019/3917 3917 Checking of reinforcement and shuttering for pier shaft final lift at RP-09 Viaduct Km 196+560 RHS 4-Sep-19 3:40 PM
3981 NMSCEW/P-IV/STR/2019/3918 3918 Checking and Pouring concrete for pier shaft final lift at RP-09 Viaduct Km 196+560 RHS 4-Sep-19 4:23 PM
3982 NMSCEW/P-IV/STR/2019/3919 3919 Checking of reinforcement, shuttering for final lift at A2 wall Box culvert Km 182+350 RHS 4-Sep-19 11:09 AM IPC-08 DONE
3983 NMSCEW/P-IV/STR/2019/3920 3920 Checking & Pouring concrete(M-30) for final lift at A2 wall Box culvert Km 182+350 RHS 4-Sep-19 11:52 AM IPC-08 DONE
3984 NMSCEW/P-IV/STR/2019/3921 3921 Checking of reinforcement and shuttering for pier shaft 1st lift at RP-07 Viaduct Km 202+190 Km 00+000 RHS 4-Sep-19 3:00 PM IPC-10 DONE AE SPOT RFI
3985 NMSCEW/P-IV/STR/2019/3922 3922 Checking and Pouring concrete for pier shaft 1st lift at RP-07 Viaduct Km 202+190 Km 00+000 RHS 4-Sep-19 3:30 PM IPC-10 DONE AE SPOT RFI
Checking of Shuttering and reinforcement for RE WALL PANEL precast TYPE -A
3986 NMSCEW/P-IV/STR/2019/3923 3923 32, TYPE -B 10, TYPE -Sta 2, TYPE -Stb 2, TYPE -Stc 2, TYPE -Std 2, TYPE -Ltc 1, RE Wall Panel Km 200+200 LHS 5-Sep-19 10:00 AM DONE
TYPE -Ltd 2,
Checking and Pouring concrete for RE WALL PANEL precastTYPE -A
3987 NMSCEW/P-IV/STR/2019/3924 3924 32, TYPE -B 10, TYPE -Sta 2, TYPE -Stb 2, TYPE -Stc 2, TYPE -Std 2, TYPE -Ltc 1, RE Wall Panel Km 200+200 LHS 5-Sep-19 11:00 AM DONE
TYPE -Ltd 2,
3988 NMSCEW/P-IV/STR/2019/3925 3925 Checking of Shuttering and reinforcement for 1st lift at retaining wall A1 & A2 PUP Km 172+190 RHS 5-Sep-19 9:30 AM DONE
3989 NMSCEW/P-IV/STR/2019/3926 3926 Checking and Pouring concrete for 1st lift at retaining wall A1 & A2 PUP Km 172+190 RHS 5-Sep-19 10:15 AM DONE
3990 NMSCEW/P-IV/STR/2019/3927 3927 Checking top Level & Laying concrete (M-10) for PCC Utility duct Km 171+570 BHS 5-Sep-19 1:00 PM NR
3991 NMSCEW/P-IV/STR/2019/3928 3928 Checking of reinforcement, shuttering for 1st lift at median wall A1 & A2 PUP Km 171+110 BHS 5-Sep-19 11:15 AM NR
3992 NMSCEW/P-IV/STR/2019/3929 3929 Checking & Pouring concrete for 1st lift at median wall A1 & A2 PUP Km 171+110 BHS 5-Sep-19 11:30 AM NR
Checking reinforcement for precast Box Culvert (3x3) (Cushion 2 to 4 m) at precast yard camp
3993 NMSCEW/P-IV/STR/2019/3930 3930 Box culvert Km 175+500 LHS 5-Sep-19 9:10 AM IPC-08 175, 176, 177, 178, 179
-1. Segment NO-175,176,177,178,179 DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3994 NMSCEW/P-IV/STR/2019/3931 3931 Box culvert Km 175+500 LHS 5-Sep-19 12:00 PM IPC-08 175, 176, 177, 178, 179
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.-175,176,177,178,179
DONE AE
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
3995 NMSCEW/P-IV/STR/2019/3932 3932 Box culvert Km 175+500 LHS 5-Sep-19 12:15 PM DONE
-1. Segment NO-178,179,180
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3996 NMSCEW/P-IV/STR/2019/3933 3933 Box culvert Km 175+500 LHS 5-Sep-19 12:45 PM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-178,179,180
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
3997 NMSCEW/P-IV/STR/2019/3934 3934 Box culvert Km 175+500 LHS 5-Sep-19 4:10 PM IPC-08 212, 213, 214, 215
-1. Segment NO-212,213,214,215 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
3998 NMSCEW/P-IV/STR/2019/3935 3935 Box culvert Km 175+500 LHS 5-Sep-19 5:00 PM IPC-08 212, 213, 214, 215
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-212,213,214,215
DONE AE
3999 NMSCEW/P-IV/STR/2019/3936 3936 Checking of reinforcement and shuttering for pier shaft final lift at LP-07 Viaduct Km 202+190 LHS 5-Sep-19 2:00 PM IPC-08 DONE AE
4000 NMSCEW/P-IV/STR/2019/3937 3937 Checking and Pouring concrete for pier shaft final lift at LP-07 Viaduct Km 202+190 LHS 5-Sep-19 2:30 PM IPC-08 DONE AE
4001 NMSCEW/P-IV/STR/2019/3938 3938 Checking of reinforcement and shuttering for pier shaft final lift at RP-02 Viaduct Km 202+190 Km 00+000 RHS 5-Sep-19 2:45 PM IPC-10 DONE AE
4002 NMSCEW/P-IV/STR/2019/3939 3939 Checking and Pouring concrete for pier shaft final lift at RP-02 Viaduct Km 202+190 Km 00+000 RHS 5-Sep-19 3:15 PM IPC-10 DONE AE
4003 NMSCEW/P-IV/STR/2019/3940 3940 Checking of reinforcement and shuttering for pier shaft final lift at LP-05 Viaduct Km 202+190 LHS 5-Sep-19 12:11 PM IPC-08 DONE AE
4004 NMSCEW/P-IV/STR/2019/3941 3941 Checking and Pouring concrete for pier shaft final lift at LP-05 Viaduct Km 202+190 LHS 5-Sep-19 12:44 PM IPC-08 DONE AE
4005 NMSCEW/P-IV/STR/2019/3942 3942 Checking of reinforcement and shuttering for pier shaft final lift at RP-10 Viaduct Km 196+560 RHS 5-Sep-19 3:20 PM
4006 NMSCEW/P-IV/STR/2019/3943 3943 Checking and Pouring concrete for pier shaft final lift at RP-10 Viaduct Km 196+560 RHS 5-Sep-19 3:50 PM
4007 NMSCEW/P-IV/STR/2019/3944 3944 Checking of reinforcement and shuttering for pier shaft final lift at RP-9 Viaduct Km 196+560 RHS 5-Sep-19 2:25 PM
4008 NMSCEW/P-IV/STR/2019/3945 3945 Checking and Pouring concrete for pier shaft final lift at RP-9 Viaduct Km 196+560 RHS 5-Sep-19 3:00 PM
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
4009 NMSCEW/P-IV/STR/2019/3946 3946 Box culvert Km 200+200 LHS 5-Sep-19 9:33 AM DONE
-2. Segment NO-383,384
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4010 NMSCEW/P-IV/STR/2019/3947 3947 Box culvert Km 200+200 LHS 5-Sep-19 11:39 AM DONE
(2×2)(Cushion 2 to 4m) at precast yard camp-2,Segment no.-383,384
Checking reinforcement for precast Box Culvert (3x3)(Cushion 2 to 4m) at precast yard camp
4011 NMSCEW/P-IV/STR/2019/3948 3948 Box culvert Km 200+200 LHS 5-Sep-19 2:34 PM DONE
-2. Segment NO-40
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4012 NMSCEW/P-IV/STR/2019/3949 3949 Box culvert Km 200+200 LHS 5-Sep-19 3:18 PM DONE
(3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-40
4013 NMSCEW/P-IV/STR/2019/3950 3950 Checking of Shuttering and reinforcement for 2nd lift at U-type retaining wall W1 PUP Km 205+430 BHS 5-Sep-19 8:00 AM DONE
4014 NMSCEW/P-IV/STR/2019/3951 3951 Checking and Pouring concrete for 2nd lift at U-type retaining wall W1 PUP Km 205+430 BHS 5-Sep-19 8:30 AM DONE
4015 NMSCEW/P-IV/STR/2019/3952 3952 Checking layout ,level for PCC at retaining wall W2 PUP Km 205+430 RHS 5-Sep-19 8:15 AM DONE
4016 NMSCEW/P-IV/STR/2019/3953 3953 Checking top Level & Laying concrete at retaining wall W2 PUP Km 205+430 RHS 5-Sep-19 9:00 AM DONE
4017 NMSCEW/P-IV/STR/2019/3954 3954 Checking layout ,level for PCC at U-type retaining wall W2 PUP Km 203+560 BHS 5-Sep-19 2:05 PM DONE
4018 NMSCEW/P-IV/STR/2019/3955 3955 Checking top Level & Laying concrete at U-type retaining wall W2 PUP Km 203+560 BHS 5-Sep-19 2:37 PM DONE
4019 NMSCEW/P-IV/STR/2019/3956 3956 Checking layout ,level for PCC Utility duct Km 205+100 BHS 5-Sep-19 8:30 AM IPC-08 DONE
4020 NMSCEW/P-IV/STR/2019/3957 3957 Checking top Level & Laying concrete (M-10) for PCC Utility duct Km 205+100 BHS 5-Sep-19 8:58 AM IPC-08 DONE AE
4021 NMSCEW/P-IV/STR/2019/3958 3958 Checking of Shuttering and reinforcement for raft Box culvert Km 180+922 RHS 5-Sep-19 9:30 AM NR SPOT RFI
4022 NMSCEW/P-IV/STR/2019/3959 3959 Checking and Pouring concrete(M-30) for raft Box culvert Km 180+922 RHS 5-Sep-19 10:30 AM NR SPOT RFI
4023 NMSCEW/P-IV/STR/2019/3960 3960 Checking of reinforcement, shuttering for 1st lift at A1 & A2 wall PUP Km 189+000 RHS 5-Sep-19 4:00 PM IPC-08 DONE SPOT RFI
4024 NMSCEW/P-IV/STR/2019/3961 3961 Checking & Pouring concrete(M-30) for 1st lift at A1 & A2 wall PUP Km 189+000 RHS 5-Sep-19 4:30 PM IPC-08 DONE SPOT RFI
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
4025 NMSCEW/P-IV/STR/2019/3962 3962 Box culvert Km 200+200 LHS 6-Sep-19 9:30 AM DONE
-2. Segment NO-385,386,387,388,389,390,391
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4026 NMSCEW/P-IV/STR/2019/3963 3963 Box culvert Km 200+200 LHS 6-Sep-19 10:45 AM DONE
(2×2)(Cushion 2 to 4m) at precast yard camp-2,Segment no.-385,386,387,388,389,390,391
4027 NMSCEW/P-IV/STR/2019/3964 3964 Checking of Shuttering and reinforcement for 2nd lift at U-type retaining wall W1 PUP Km 204+470 BHS 6-Sep-19 9:00 AM DONE
4028 NMSCEW/P-IV/STR/2019/3965 3965 Checking and Pouring concrete for 2nd lift at U-type retaining wall W1 PUP Km 204+470 BHS 6-Sep-19 9:20 AM DONE
4029 NMSCEW/P-IV/STR/2019/3966 3966 Checking of Shuttering and reinforcement for 3rd lift at U-type retaining wall W2 PUP Km 204+470 BHS 6-Sep-19 9:15 AM DONE
4030 NMSCEW/P-IV/STR/2019/3967 3967 Checking and Pouring concrete for 3rd lift at U-type retaining wall W2 PUP Km 204+470 BHS 6-Sep-19 10:00 AM DONE
4031 NMSCEW/P-IV/STR/2019/3968 3968 Checking of reinforcement, shuttering for 2nd lift at A1 wall PUP Km 165+790 RHS 6-Sep-19 4:15 PM IPC-08 DONE AE
4032 NMSCEW/P-IV/STR/2019/3969 3969 Checking & Pouring concrete for 2nd lift at A1 wall PUP Km 165+790 RHS 6-Sep-19 5:00 PM IPC-08 DONE AE
4033 NMSCEW/P-IV/STR/2019/3970 3970 Checking layout ,level and structural excavation at retaining wall A1 & A2 PUP Km 165+300 RHS 6-Sep-19 4:00 PM DONE
4034 NMSCEW/P-IV/STR/2019/3971 3971 Checking top Level & Laying concrete for PCC at retaining wall A1 & A2 PUP Km 165+300 RHS 6-Sep-19 5:30 PM DONE
Checking reinforcement for precast Box Culvert (3x3) (Cushion 2 to 4 m) at precast yard camp
4035 NMSCEW/P-IV/STR/2019/3972 3972 Box culvert Km 175+500 LHS 6-Sep-19 9:18 AM
-1. Segment NO-180,181,182,183,184,185 NR
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4036 NMSCEW/P-IV/STR/2019/3973 3973 Box culvert Km 175+500 LHS 6-Sep-19 12:12 PM
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.-180,181,182,183,184,185
NR
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
4037 NMSCEW/P-IV/STR/2019/3974 3974 Box culvert Km 175+500 LHS 6-Sep-19 12:36 PM
-1. Segment NO-177,181,182 NR
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4038 NMSCEW/P-IV/STR/2019/3975 3975 Box culvert Km 175+500 LHS 6-Sep-19 12:50 PM
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-177,181,182 NR
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
4039 NMSCEW/P-IV/STR/2019/3976 3976 Box culvert Km 175+500 LHS 6-Sep-19 4:20 PM
-1. Segment NO-211,216,217,218 NR
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4040 NMSCEW/P-IV/STR/2019/3977 3977 Box culvert Km 175+500 LHS 6-Sep-19 5:10 PM
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-211,216,217,218
NR
4041 NMSCEW/P-IV/STR/2019/3978 3978 Checking of reinforcement, shuttering at retaining wall A1 footing PUP Km 184+190 LHS 6-Sep-19 2:00 PM NR
4042 NMSCEW/P-IV/STR/2019/3979 3979 Checking & Pouring concrete(M-30) at retaining wall A1 footing PUP Km 184+190 LHS 6-Sep-19 2:30 PM NR
4043 NMSCEW/P-IV/STR/2019/3980 3980 Checking of reinforcement and shuttering for pier shaft 2nd & final lift at RP-02 Viaduct Km 169+800 Km 00+000 RHS 6-Sep-19 2:15 PM IPC-09 DONE
4044 NMSCEW/P-IV/STR/2019/3981 3981 Checking and Pouring concrete for pier shaft 2nd & final lift at RP-02 Viaduct Km 169+800 Km 00+000 RHS 6-Sep-19 2:45 PM IPC-09 DONE
4045 NMSCEW/P-IV/STR/2019/3982 3982 Checking of Shuttering and reinforcement for raft at RA-02 Viaduct Km 169+800 Km 00+000 RHS 6-Sep-19 3:00 PM IPC-09 DONE MNB
4046 NMSCEW/P-IV/STR/2019/3983 3983 Checking and Pouring concrete for raft at RA-02 Viaduct Km 169+800 Km 00+000 RHS 6-Sep-19 3:30 PM IPC-09 DONE MNB
4047 NMSCEW/P-IV/STR/2019/3984 3984 Checking of reinforcement and shuttering for pier shaft starter at LP-09 Viaduct Km 195+900 LHS 6-Sep-19 3:10 PM
4048 NMSCEW/P-IV/STR/2019/3985 3985 Checking and Pouring concrete for pier shaft starter at LP-09 Viaduct Km 195+900 LHS 6-Sep-19 3:44 PM
4049 NMSCEW/P-IV/STR/2019/3986 3986 Checking of Shuttering and reinforcement for raft at RP-02 Viaduct Km 195+900 RHS 6-Sep-19 2:35 PM
4050 NMSCEW/P-IV/STR/2019/3987 3987 Checking and Pouring concrete for raft at RP-02 Viaduct Km 195+900 RHS 6-Sep-19 3:05 PM
4051 NMSCEW/P-IV/STR/2019/3988 3988 Checking of reinforcement and shuttering for pier shaft final lift at RP-10 Viaduct Km 196+560 RHS 6-Sep-19 10:05 AM
4052 NMSCEW/P-IV/STR/2019/3989 3989 Checking and Pouring concrete for pier shaft final lift at RP-10 Viaduct Km 196+560 RHS 6-Sep-19 10:35 AM
4053 NMSCEW/P-IV/STR/2019/3990 3990 Checking of reinforcement and shuttering for pier shaft final lift at RP-09 Viaduct Km 196+560 RHS 6-Sep-19 11:11 AM
4054 NMSCEW/P-IV/STR/2019/3991 3991 Checking and Pouring concrete for pier shaft final lift at RP-09 Viaduct Km 196+560 RHS 6-Sep-19 11:42 AM
4055 NMSCEW/P-IV/STR/2019/3992 3992 Checking of reinforcement and shuttering for pier shaft 1st lift at LP-06 Viaduct Km 196+560 Km 00+000 LHS 6-Sep-19 2:25 PM IPC-10 DONE AE
4056 NMSCEW/P-IV/STR/2019/3993 3993 Checking and Pouring concrete for pier shaft 1st lift at LP-06 Viaduct Km 196+560 Km 00+000 LHS 6-Sep-19 2:50 PM IPC-10 DONE AE
4057 NMSCEW/P-IV/STR/2019/3994 3994 Checking and Pouring concrete for pier shaft 1st lift at RA-01 Viaduct Km 169+800 RHS 6-Sep-19 12:00 PM DONE
4058 NMSCEW/P-IV/STR/2019/3995 3995 Checking of reinforcement, shuttering for 1st lift at median wall A1 & A2 PUP Km 171+110 BHS 6-Sep-19 2:00 PM DONE SPOT RFI
4059 NMSCEW/P-IV/STR/2019/3996 3996 Checking & Pouring concrete for 1st lift at median wall A1 & A2 PUP Km 171+110 BHS 6-Sep-19 2:45 PM DONE SPOT RFI
4060 NMSCEW/P-IV/STR/2019/3996-A 3996-A Checking layout ,level & structural excavation for PCC at retaining wall A1 & A2 PUP Km 177+810 BHS 6-Sep-19 10:30 AM DONE SPOT RFI
4061 NMSCEW/P-IV/STR/2019/3997 3997 Checking top Level & Laying concrete for PCC at A1 & A2 wall PUP Km 177+810 BHS 7-Sep-19 10:30 AM DONE
4062 NMSCEW/P-IV/STR/2019/3998 3998 Checking of reinforcement and shuttering for final lift at A1 & A2 wall LVUP Km 178+323 RHS 7-Sep-19 11:30 AM IPC-08 DONE
4063 NMSCEW/P-IV/STR/2019/3999 3999 Checking and Pouring concrete for final lift at A1 & A2 wall LVUP Km 178+323 RHS 7-Sep-19 12:30 PM IPC-08 DONE
4064 NMSCEW/P-IV/STR/2019/4000 4000 Checking of Shuttering and reinforcement for 3rd lift at wall W2 PUP Km 193+880 LHS 7-Sep-19 10:00 AM IPC-08 DONE
4065 NMSCEW/P-IV/STR/2019/4001 4001 Checking and Pouring concrete for 3rd lift at wall W2 PUP Km 193+880 LHS 7-Sep-19 10:45 AM IPC-08 DONE
4066 NMSCEW/P-IV/STR/2019/4002 4002 Checking of Shuttering and reinforcement for 1st lift at wall W1 Box culvert Km 204+920 LHS 7-Sep-19 8:00 AM DONE
4067 NMSCEW/P-IV/STR/2019/4003 4003 Checking and Pouring concrete for 1st lift at wall W1 Box culvert Km 204+920 LHS 7-Sep-19 8:30 AM DONE
4068 NMSCEW/P-IV/STR/2019/4004 4004 Checking layout ,level for PCC at retaining wall W1 & W2 PUP Km 204+470 LHS 7-Sep-19 9:00 AM DONE
4069 NMSCEW/P-IV/STR/2019/4005 4005 Checking top Level & Laying concrete for PCC at retaining wall W1 & W2 PUP Km 204+470 LHS 7-Sep-19 9:30 AM DONE
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
4070 NMSCEW/P-IV/STR/2019/4006 4006 Box culvert Km 200+200 LHS 7-Sep-19 9:40 AM DONE
-2. Segment NO-392,393,394,395,396,397,398
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4071 NMSCEW/P-IV/STR/2019/4007 4007 Box culvert Km 200+200 LHS 7-Sep-19 11:00 AM DONE
(2×2)(Cushion 2 to 4m) at precast yard camp-2,Segment no.-392,393,394,395,396,397,398
4072 NMSCEW/P-IV/STR/2019/4008 4008 Checking of Shuttering and reinforcement for 1st lift at retaining wall A2 PUP Km 172+190 RHS 7-Sep-19 9:10 AM DONE
4073 NMSCEW/P-IV/STR/2019/4009 4009 Checking and Pouring concrete for 1st lift at retaining wall A2 PUP Km 172+190 RHS 7-Sep-19 9:50 AM DONE
4074 NMSCEW/P-IV/STR/2019/4010 4010 Checking reinforcement ,shuttering for top haunch with top slab PUP Km 190+650 RHS 7-Sep-19 2:00 PM NR
4075 NMSCEW/P-IV/STR/2019/4011 4011 Checking and concrete (M30) pouring for top haunch with top slab PUP Km 190+650 RHS 7-Sep-19 2:30 PM NR
4076 NMSCEW/P-IV/STR/2019/4012 4012 Checking of reinforcement and shuttering for final lift at A1 & A2 wall PUP Km 187+835 LHS 7-Sep-19 11:20 AM DONE
4077 NMSCEW/P-IV/STR/2019/4013 4013 Checking and Pouring concrete for final lift at A1 & A2 wall PUP Km 187+835 LHS 7-Sep-19 11:50 AM DONE
Checking reinforcement for precast Box Culvert (3x3) (Cushion 2 to 4 m) at precast yard camp
4078 NMSCEW/P-IV/STR/2019/4014 4014 Box culvert Km 175+500 LHS 7-Sep-19 9:15 AM DONE
-1. Segment NO-186,187,188,189,190,
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4079 NMSCEW/P-IV/STR/2019/4015 4015 Box culvert Km 175+500 LHS 7-Sep-19 12:23 PM DONE
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.-186,187,188,189,190,
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
4080 NMSCEW/P-IV/STR/2019/4016 4016 Box culvert Km 175+500 LHS 7-Sep-19 12:44 PM DONE
-1. Segment NO-180,183,184
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4081 NMSCEW/P-IV/STR/2019/4017 4017 Box culvert Km 175+500 LHS 7-Sep-19 12:50 PM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-180,183,184
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
4082 NMSCEW/P-IV/STR/2019/4018 4018 Box culvert Km 175+500 LHS 7-Sep-19 4:15 PM IPC-08 215, 219, 220, 221
-1. Segment NO-215, 219, 220, 221 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4083 NMSCEW/P-IV/STR/2019/4019 4019 Box culvert Km 175+500 LHS 7-Sep-19 5:05 PM IPC-08 215, 219, 220, 221
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-215, 219, 220, 221
DONE
4084 NMSCEW/P-IV/STR/2019/4020 4020 Checking top Level & Laying concrete(M-10) for PCC Utility duct Km 171+570 BHS 7-Sep-19 1:00 PM NR
4085 NMSCEW/P-IV/STR/2019/4021 4021 Checking of reinforcement and shuttering for pier shaft 1st lift at RP-13 Viaduct Km 202+190 Km 00+000 RHS 7-Sep-19 12:00 PM IPC-10 DONE
4086 NMSCEW/P-IV/STR/2019/4022 4022 Checking and Pouring concrete for pier shaft 1st lift at RP-13 Viaduct Km 202+190 RHS 7-Sep-19 12:30 PM
4087 NMSCEW/P-IV/STR/2019/4023 4023 Checking of reinforcement and shuttering for pier shaft 1st lift at RP-09 Viaduct Km 202+190 Km 00+000 RHS 7-Sep-19 2:30 PM IPC-10 DONE
4088 NMSCEW/P-IV/STR/2019/4024 4024 Checking and Pouring concrete for pier shaft 1st lift at RP-09 Viaduct Km 202+190 RHS 7-Sep-19 3:00 PM
4089 NMSCEW/P-IV/STR/2019/4025 4025 Checking of Shuttering and reinforcement for raft at RP-02 Viaduct Km 195+900 Km 00+000 RHS 7-Sep-19 11:33 AM IPC-10 DONE AE
4090 NMSCEW/P-IV/STR/2019/4026 4026 Checking and Pouring concrete for raft at RP-02 Viaduct Km 195+900 Km 00+000 RHS 7-Sep-19 1:00 PM IPC-10 DONE
4091 NMSCEW/P-IV/STR/2019/4027 4027 Checking of Shuttering and reinforcement for raft at RA-01 Viaduct Km 195+900 RHS 7-Sep-19 12:33 PM IPC-08 DONE AE
4092 NMSCEW/P-IV/STR/2019/4028 4028 Checking and Pouring concrete for raft at RA-01 Viaduct Km 195+900 RHS 7-Sep-19 1:00 PM
4093 NMSCEW/P-IV/STR/2019/4029 4029 Checking of reinforcement and shuttering for pier shaft final lift at RP-10 Viaduct Km 196+560 Km 00+000 RHS 7-Sep-19 10:36 AM IPC-09 DONE AE
4094 NMSCEW/P-IV/STR/2019/4030 4030 Checking and Pouring concrete for pier shaft final lift at RP-10 Viaduct Km 196+560 Km 00+000 RHS 7-Sep-19 10:55 AM IPC-09 DONE AE
4095 NMSCEW/P-IV/STR/2019/4031 4031 Checking of reinforcement, shuttering for pier cap at LP-05 Viaduct Km 169+800 LHS 7-Sep-19 2:05 PM IPC-08 DONE AE
4096 NMSCEW/P-IV/STR/2019/4032 4032 Checking & pouring concrete for pier cap at LP-05 Viaduct Km 169+800 LHS 7-Sep-19 2:38 PM NR
4097 NMSCEW/P-IV/STR/2019/4033 4033 Checking of reinforcement, shuttering for pier cap at LP-04 Viaduct Km 169+800 LHS 7-Sep-19 3:11 PM IPC-08 DONE
4098 NMSCEW/P-IV/STR/2019/4034 4034 Checking & pouring concrete for pier cap at LP-04 Viaduct Km 169+800 LHS 7-Sep-19 3:49 PM NR
4099 NMSCEW/P-IV/STR/2019/4035 4035 Checking of Shuttering and reinforcement for raft at LA-02 Viaduct Km 169+800 LHS 7-Sep-19 2:19 PM NR
4100 NMSCEW/P-IV/STR/2019/4036 4036 Checking of Shuttering and reinforcement for median raft PUP Km 177+810 BHS 8-Sep-19 10:30 AM DONE
4101 NMSCEW/P-IV/STR/2019/4037 4037 Checking and Pouring concrete for median raft PUP Km 177+810 BHS 8-Sep-19 12:30 PM DONE
Checking for stressing and remove slagness of H.T. wires at Girder no 17,18,19,20 at bed no
4102 NMSCEW/P-IV/STR/2019/4038 4038 Girder Type-2 Km 200+200 LHS 8-Sep-19 10:00 AM
-1 at casting yard camp -2
4103 NMSCEW/P-IV/STR/2019/4039 4039 Checking of reinforcement and shuttering for pier shaft final lift at RP-09 Viaduct Km 196+560 Km 00+000 RHS 8-Sep-19 9:30 AM IPC-09 DONE AE
4104 NMSCEW/P-IV/STR/2019/4040 4040 Checking and Pouring concrete for pier shaft final lift at RP-09 Viaduct Km 196+560 Km 00+000 RHS 8-Sep-19 9:50 AM IPC-09 DONE AE
4105 NMSCEW/P-IV/STR/2019/4041 4041 Checking of reinforcement and shuttering for pier shaft final lift at RP-07 Viaduct Km 196+560 RHS 8-Sep-19 10:20 AM
4106 NMSCEW/P-IV/STR/2019/4042 4042 Checking and Pouring concrete for pier shaft final lift at RP-07 Viaduct Km 196+560 RHS 8-Sep-19 11:00 AM
4107 NMSCEW/P-IV/STR/2019/4043 4043 Checking of reinforcement and shuttering for pier shaft 1st lift at LP-09 Viaduct Km 202+190 Km 00+000 LHS 8-Sep-19 4:00 PM IPC-10 DONE AE
4108 NMSCEW/P-IV/STR/2019/4044 4044 Checking and Pouring concrete for pier shaft 1st lift at LP-09 Viaduct Km 202+190 LHS 8-Sep-19 2:30 PM
4109 NMSCEW/P-IV/STR/2019/4045 4045 Checking of reinforcement and shuttering for pier shaft final lift at RP-06 Viaduct Km 202+190 RHS 8-Sep-19 3:00 PM
4110 NMSCEW/P-IV/STR/2019/4046 4046 Checking and Pouring concrete for pier shaft final lift at RP-06 Viaduct Km 202+190 RHS 8-Sep-19 3:30 PM
4111 NMSCEW/P-IV/STR/2019/4047 4047 Checking of reinforcement, shuttering for 2nd lift at A1 & A2 wall PUP Km 189+000 RHS 8-Sep-19 1:30 AM NR
4112 NMSCEW/P-IV/STR/2019/4048 4048 Checking & Pouring concrete(M-30) for 2nd lift at A1 & A2 wall PUP Km 189+000 RHS 8-Sep-19 2:15 PM NR
4113 NMSCEW/P-IV/STR/2019/4049 4049 Checking layout ,level for PCC MNB Km 181+700 BHS 8-Sep-19 10:15 AM NR
4114 NMSCEW/P-IV/STR/2019/4050 4050 Checking top Level & Laying concrete (M-15) for PCC MNB Km 181+700 BHS 8-Sep-19 11:20 AM NR
4115 NMSCEW/P-IV/STR/2019/4051 4051 Checking of reinforcement, shuttering for 2nd lift at A2 wall PUP Km 165+790 RHS 8-Sep-19 2:25 PM IPC-08 DONE AE
4116 NMSCEW/P-IV/STR/2019/4052 4052 Checking & Pouring concrete for 2nd lift at A2 wall PUP Km 165+790 RHS 8-Sep-19 3:05 PM IPC-08 DONE AE
4117 NMSCEW/P-IV/STR/2019/4053 4053 Checking of Shuttering and reinforcement for raft with bottom haunch at A1 & A2 LVUP Km 169+291 RHS 9-Sep-19 3:00 PM NR
4118 NMSCEW/P-IV/STR/2019/4054 4054 Checking and Pouring concrete for raft for raft with bottom haunch at A1 & A2 LVUP Km 169+291 RHS 9-Sep-19 3:00 PM NR
4119 NMSCEW/P-IV/STR/2019/4055 4055 Checking of Shuttering and reinforcement for 2nd lift at retaining wall A2 PUP Km 172+190 RHS 9-Sep-19 9:00 AM DONE
4120 NMSCEW/P-IV/STR/2019/4056 4056 Checking and Pouring concrete for 2nd lift at retaining wall A2 PUP Km 172+190 RHS 9-Sep-19 9:45 AM DONE
Checking for stressing and remove slagness of H.T. wires at Girder no- 13,14,15,16 at bed no
4121 NMSCEW/P-IV/STR/2019/4057 4057 Girder Type-1 Km 200+200 LHS 9-Sep-19 11:00 AM
-6 at casting yard camp -2
4122 NMSCEW/P-IV/STR/2019/4058 4058 Checking of Shuttering and reinforcement for raft at retaining wall W2 PUP Km 203+560 RHS 9-Sep-19 8:00 AM DONE
4123 NMSCEW/P-IV/STR/2019/4059 4059 Checking and Pouring concrete for raft at retaining wall W2 PUP Km 203+560 RHS 9-Sep-19 8:30 AM DONE
4124 NMSCEW/P-IV/STR/2019/4060 4060 Checking of Shuttering and reinforcement for 3rd lift at U-type retaining wall W1 & W2 PUP Km 205+430 BHS 9-Sep-19 11:15 AM DONE
4125 NMSCEW/P-IV/STR/2019/4061 4061 Checking and Pouring concrete for 3rd lift at U-type retaining wall W1 & W2 PUP Km 205+430 BHS 9-Sep-19 11:45 AM DONE
Checking reinforcement for precast Box Culvert (3x3) (Cushion 2 to 4 m) at precast yard camp
4126 NMSCEW/P-IV/STR/2019/4062 4062 Box culvert Km 175+500 LHS 9-Sep-19 9:20 AM
-1. Segment NO-180,181,182,183,184, 185 NR
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4127 NMSCEW/P-IV/STR/2019/4063 4063 Box culvert Km 175+500 LHS 9-Sep-19 12:25 PM
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.-180,181,182,183,184, 185
NR
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
4128 NMSCEW/P-IV/STR/2019/4064 4064 Box culvert Km 175+500 LHS 9-Sep-19 12:45 PM DONE
-1. Segment NO-177,181,182
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4129 NMSCEW/P-IV/STR/2019/4065 4065 Box culvert Km 175+500 LHS 9-Sep-19 12:55 PM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-177,181,182
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
4130 NMSCEW/P-IV/STR/2019/4066 4066 Box culvert Km 175+500 LHS 9-Sep-19 4:13 PM IPC-08 211, 216, 217, 218
-1. Segment NO-211, 216, 217, 218 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4131 NMSCEW/P-IV/STR/2019/4067 4067 Box culvert Km 175+500 LHS 9-Sep-19 5:11 PM IPC-08 211, 216, 217, 218
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-211, 216, 217, 218
DONE
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
4132 NMSCEW/P-IV/STR/2019/4068 4068 Box culvert Km 200+200 LHS 9-Sep-19 9:42 AM
-2. Segment NO-399,400,401,402,403,404
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4133 NMSCEW/P-IV/STR/2019/4069 4069 Box culvert Km 200+200 LHS 9-Sep-19 11:18 AM
(2×2)(Cushion 2 to 4m) at precast yard camp-2,Segment no.-399,400,401,402,403,404
Checking reinforcement for precast Box Culvert (3x3)(Cushion 2 to 4m) at precast yard camp
4134 NMSCEW/P-IV/STR/2019/4070 4070 Box culvert Km 200+200 LHS 9-Sep-19 2:38 PM
-2. Segment NO-41
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4135 NMSCEW/P-IV/STR/2019/4071 4071 Box culvert Km 200+200 LHS 9-Sep-19 3:25 PM
(3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-41
4136 NMSCEW/P-IV/STR/2019/4072 4072 Checking & pouring concrete for pier cap at LP-05 Viaduct Km 169+800 LHS 9-Sep-19 8:10 AM IPC-08 DONE AE
4137 NMSCEW/P-IV/STR/2019/4073 4073 Checking & pouring concrete for pier cap at LP-04 Viaduct Km 169+800 LHS 9-Sep-19 8:30 AM IPC-08 DONE
4138 NMSCEW/P-IV/STR/2019/4074 4074 Checking of Shuttering and reinforcement for raft at LA-02 Viaduct Km 169+800 Km 00+000 LHS 9-Sep-19 12:00 PM IPC-09 DONE MNB
4139 NMSCEW/P-IV/STR/2019/4075 4075 Checking & pouring concrete for raft at LA-02 Viaduct Km 169+800 Km 00+000 LHS 9-Sep-19 12:30 PM IPC-09 DONE MNB
4140 NMSCEW/P-IV/STR/2019/4076 4076 Checking of reinforcement, shuttering for 2nd lift at A1 & A2 wall PUP Km 189+000 RHS 9-Sep-19 12:35 PM NR
4141 NMSCEW/P-IV/STR/2019/4077 4077 Checking & Pouring concrete(M-30) for 2nd lift at A1 & A2 wall PUP Km 189+000 RHS 9-Sep-19 1:20 PM NR
4142 NMSCEW/P-IV/STR/2019/4078 4078 Checking layout ,level for PCC MNB Km 181+700 BHS 9-Sep-19 9:11 AM NR
4143 NMSCEW/P-IV/STR/2019/4079 4079 Checking top Level & Laying concrete (M-15) for PCC MNB Km 181+700 BHS 9-Sep-19 9:45 AM NR
4144 NMSCEW/P-IV/STR/2019/4080 4080 Checking of Shuttering and reinforcement for 2nd lift at A1 & A2 wall VUP Km 179+983 Km 00+000 LHS 9-Sep-19 11:05 AM IPC-10 DONE spot rfi
4145 NMSCEW/P-IV/STR/2019/4081 4081 Checking and Pouring concrete for 2nd lift at A1 & A2 wall VUP Km 179+983 Km 00+000 LHS 9-Sep-19 11:46 AM IPC-10 DONE spot rfi
4146 NMSCEW/P-IV/STR/2019/4082 4082 Checking of Shuttering and reinforcement for raft at retaining wall A1 & A2 PUP Km 165+300 RHS 10-Sep-19 11:00 AM DONE
4147 NMSCEW/P-IV/STR/2019/4083 4083 Checking and Pouring concrete for raft at retaining wall A1 & A2 PUP Km 165+300 RHS 10-Sep-19 11:30 AM DONE
4148 NMSCEW/P-IV/STR/2019/4084 4084 Checking of reinforcement, shuttering for 2nd lift at median wall A1 & A2 PUP Km 171+110 LHS 10-Sep-19 10:00 AM DONE
4149 NMSCEW/P-IV/STR/2019/4085 4085 Checking & Pouring concrete for 2nd lift at median wall A1 & A2 PUP Km 171+110 LHS 10-Sep-19 10:30 AM DONE
4150 NMSCEW/P-IV/STR/2019/4086 4086 Checking top Level & Laying concrete(M-10) for PCC Utility duct Km 171+570 BHS 10-Sep-19 1:00 PM NR
4151 NMSCEW/P-IV/STR/2019/4087 4087 Checking layout ,level and structural excavation Utility duct Km 173+000 BHS 10-Sep-19 10:15 AM IPC-08 DONE
4152 NMSCEW/P-IV/STR/2019/4088 4088 Checking of reinforcement, shuttering for 1st lift at A1 & A2 wall PUP Km 164+380 Km 00+000 LHS 10-Sep-19 4:30 PM IPC-10 DONE AE
4153 NMSCEW/P-IV/STR/2019/4089 4089 Checking & Pouring concrete for 1st lift at A1 & A2 wall PUP Km 164+380 Km 00+000 LHS 10-Sep-19 4:30 PM IPC-10 DONE AE
4154 NMSCEW/P-IV/STR/2019/4090 4090 Checking of side shuttering girder no- 17,18,19,20 at bed no-01,Girder Type-2 Girder Km 200+200 LHS 10-Sep-19 2:30 PM
Approval for pouring of girder no- 17,18,19,20 at bed no-01. (Grade of concrete M-50)
4155 NMSCEW/P-IV/STR/2019/4091 4091 Girder Km 200+200 LHS 10-Sep-19 3:00 PM
Girder Type- 2
4156 NMSCEW/P-IV/STR/2019/4092 4092 Checking & pouring concrete for raft at RA-01 Viaduct Km 195+900 RHS 10-Sep-19 10:18 AM IPC-08 DONE AE
4157 NMSCEW/P-IV/STR/2019/4093 4093 Checking & pouring concrete for raft at RP-02 Viaduct Km 195+900 RHS 10-Sep-19 8:00 AM
4158 NMSCEW/P-IV/STR/2019/4094 4094 Checking of reinforcement and shuttering for pier shaft final lift at RP-07 Viaduct Km 196+560 Km 00+000 RHS 10-Sep-19 10:20 AM IPC-09 DONE AE
4159 NMSCEW/P-IV/STR/2019/4095 4095 Checking and Pouring concrete for pier shaft final lift at RP-07 Viaduct Km 196+560 Km 00+000 RHS 10-Sep-19 10:50 AM IPC-09 DONE AE
4160 NMSCEW/P-IV/STR/2019/4096 4096 Checking of reinforcement and shuttering for pier shaft starter at RP-04 Viaduct Km 195+900 RHS 10-Sep-19 3:15 PM
4161 NMSCEW/P-IV/STR/2019/4097 4097 Checking and Pouring concrete for pier shaft starter at RP-04 Viaduct Km 195+900 RHS 10-Sep-19 3:45 PM
4162 NMSCEW/P-IV/STR/2019/4098 4098 Checking and Pouring concrete for pier shaft 1st lift at LP-09 Viaduct Km 202+190 LHS 10-Sep-19 9:00 AM
4163 NMSCEW/P-IV/STR/2019/4099 4099 Checking and Pouring concrete for pier shaft 1st lift at RP-09 Viaduct Km 202+190 Km 00+000 RHS 10-Sep-19 9:50 AM IPC-10 DONE
4164 NMSCEW/P-IV/STR/2019/4100 4100 Checking and Pouring concrete for pier shaft 1st lift at RP-13 Viaduct Km 202+190 Km 00+000 RHS 10-Sep-19 11:11 AM IPC-10 DONE
4165 NMSCEW/P-IV/STR/2019/4101 4101 Checking of reinforcement and shuttering for pier shaft starter at LP-08 Viaduct Km 202+190 Km 00+000 LHS 10-Sep-19 11:25 AM IPC-10 DONE
4166 NMSCEW/P-IV/STR/2019/4102 4102 Checking and Pouring concrete for pier shaft starter at LP-08 Viaduct Km 202+190 Km 00+000 LHS 10-Sep-19 11:46 AM IPC-10 DONE
4167 NMSCEW/P-IV/STR/2019/4103 4103 Checking of reinforcement, shuttering for pier cap at LP-04 Viaduct Km 202+190 LHS 10-Sep-19 3:30 PM
4168 NMSCEW/P-IV/STR/2019/4104 4104 Checking & pouring concrete for pier cap at LP-04 Viaduct Km 202+190 LHS 10-Sep-19 4:10 PM
4169 NMSCEW/P-IV/STR/2019/4105 4105 Checking of reinforcement and shuttering for pier shaft final lift at RP-06 Viaduct Km 202+190 Km 00+000 RHS 10-Sep-19 2:10 PM IPC-10 DONE
4170 NMSCEW/P-IV/STR/2019/4106 4106 Checking and Pouring concrete for pier shaft final lift at RP-06 Viaduct Km 202+190 RHS 10-Sep-19 2:44 PM
Checking reinforcement for precast Box Culvert (3x3)(Cushion 0 to 2m) at precast yard camp
4171 NMSCEW/P-IV/STR/2019/4107 4107 Box culvert Km 200+200 LHS 10-Sep-19 9:20 AM DONE
-2. Segment NO-143,144
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4172 NMSCEW/P-IV/STR/2019/4108 4108 Box culvert Km 200+200 LHS 10-Sep-19 10:37 AM DONE
(3×3) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-143,144
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
4173 NMSCEW/P-IV/STR/2019/4109 4109 Box culvert Km 200+200 LHS 10-Sep-19 11:05 AM DONE
-2. Segment NO-405,406,407,408,409,410,411
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4174 NMSCEW/P-IV/STR/2019/4110 4110 Box culvert Km 200+200 LHS 10-Sep-19 12:45 PM DONE
(2×2)(Cushion 2 to 4m) at precast yard camp-2,Segment no.-405,406,407,408,409,410,411
Checking reinforcement for precast Box Culvert (3x3)(Cushion 2 to 4m) at precast yard camp
4175 NMSCEW/P-IV/STR/2019/4111 4111 Box culvert Km 200+200 LHS 10-Sep-19 3:05 PM DONE
-2. Segment NO-42
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4176 NMSCEW/P-IV/STR/2019/4112 4112 Box culvert Km 200+200 LHS 10-Sep-19 4:11 PM DONE
(3×3) (Cushion 2 to 4m) at precast yard camp-2,Segment no.-42
4177 NMSCEW/P-IV/STR/2019/4113 4113 Checking layout ,level & structural excavation MNB MNB Km 181+700 Km 00+000 BHS 10-Sep-19 9:00 AM IPC-11 DONE SPOT RFI
4178 NMSCEW/P-IV/STR/2019/4114 4114 Checking top Level & Laying concrete (M-15) for PCC MNB Km 181+700 Km 00+000 BHS 10-Sep-19 9:34 AM IPC-11 DONE AE SPOT RFI
4179 NMSCEW/P-IV/STR/2019/4115 4115 Checking of reinforcement, shuttering for pier cap at LP-07 Viaduct Km 169+800 LHS 10-Sep-19 3:00 PM IPC-08 DONE SPOT RFI
4180 NMSCEW/P-IV/STR/2019/4116 4116 Checking of Shuttering and reinforcement for raft at retaining wall W1 PUP Km 203+560 RHS 11-Sep-19 8:00 AM DONE
4181 NMSCEW/P-IV/STR/2019/4117 4117 Checking and Pouring concrete for raft at retaining wall W1 PUP Km 203+560 RHS 11-Sep-19 8:30 AM DONE
4182 NMSCEW/P-IV/STR/2019/4118 4118 Checking of Shuttering and reinforcement for 1st lift at retaining wall W2 PUP Km 205+430 LHS 11-Sep-19 9:00 AM DONE
4183 NMSCEW/P-IV/STR/2019/4119 4119 Checking and Pouring concrete for 1st lift at retaining wall W2 PUP Km 205+430 LHS 11-Sep-19 9:30 AM DONE
4184 NMSCEW/P-IV/STR/2019/4120 4120 Checking layout ,level for PCC at retaining wall W1 PUP Km 205+430 RHS 11-Sep-19 11:00 AM DONE
4185 NMSCEW/P-IV/STR/2019/4121 4121 Checking top Level & Laying concrete for PCC at retaining wall W1 PUP Km 205+430 RHS 11-Sep-19 11:30 AM DONE
4186 NMSCEW/P-IV/STR/2019/4122 4122 Checking of side shuttering girder no- 13,14,15,16 at bed no-06,Girder Type-1 Girder Km 200+200 LHS 11-Sep-19 2:30 PM
Approval for pouring of girder no- 13,14,15,16 at bed no-06. (Grade of concrete M-50)
4187 NMSCEW/P-IV/STR/2019/4123 4123 Girder Km 200+200 LHS 11-Sep-19 3:00 PM
Girder Type- 1
Checking for stressing and remove slagness of H.T. wires at Girder no 21,22,23,24 at bed no
4188 NMSCEW/P-IV/STR/2019/4124 4124 Girder Type-2 Km 200+200 LHS 11-Sep-19 12:00 PM
-4 at casting yard camp -2
4189 NMSCEW/P-IV/STR/2019/4125 4125 Checking of reinforcement Girder no 21,22,23,24 at bed no -4 at casting yard camp -2 Girder Type-2 Km 200+200 LHS 11-Sep-19 12:30 PM
4190 NMSCEW/P-IV/STR/2019/4126 4126 Checking & pouring concrete for pier cap at LP-07 Viaduct Km 169+800 LHS 11-Sep-19 10:00 AM IPC-08 DONE
4191 NMSCEW/P-IV/STR/2019/4127 4127 Checking of reinforcement, shuttering for pier cap at LP-06 Viaduct Km 169+800 LHS 11-Sep-19 10:30 AM IPC-08 DONE
4192 NMSCEW/P-IV/STR/2019/4128 4128 Checking & pouring concrete for pier cap at LP-06 Viaduct Km 169+800 LHS 11-Sep-19 11:32 AM NR
4193 NMSCEW/P-IV/STR/2019/4129 4129 Checking of reinforcement and shuttering for pier shaft starter at RP-06 Viaduct Km 195+900 RHS 11-Sep-19 11:15 AM
4194 NMSCEW/P-IV/STR/2019/4130 4130 Checking and Pouring concrete for pier shaft starter at RP-06 Viaduct Km 195+900 RHS 11-Sep-19 11:45 AM
4195 NMSCEW/P-IV/STR/2019/4131 4131 Checking of reinforcement and shuttering for raft at RP-09 Viaduct Km 195+900 RHS 11-Sep-19 3:30 PM
4196 NMSCEW/P-IV/STR/2019/4132 4132 Checking and Pouring concrete or raft at RP-09 Viaduct Km 195+900 RHS 11-Sep-19 2:10 PM
4197 NMSCEW/P-IV/STR/2019/4133 4133 Checking of reinforcement and shuttering for pier shaft final lift at RP-06 Viaduct Km 196+560 RHS 11-Sep-19 11:20 AM
4198 NMSCEW/P-IV/STR/2019/4134 4134 Checking and Pouring concrete for pier shaft final lift at RP-06 Viaduct Km 196+560 RHS 11-Sep-19 11:50 AM
4199 NMSCEW/P-IV/STR/2019/4135 4135 Checking of reinforcement, shuttering for pier cap at LP-04 Viaduct Km 202+190 LHS 11-Sep-19 2:00 PM IPC-08 DONE AE
4200 NMSCEW/P-IV/STR/2019/4136 4136 Checking & pouring concrete for pier cap at LP-04 Viaduct Km 202+190 LHS 11-Sep-19 2:34 PM IPC-08 DONE AE
4201 NMSCEW/P-IV/STR/2019/4137 4137 Checking of reinforcement and shuttering for pier shaft final lift at LA-01 Viaduct Km 202+190 LHS 11-Sep-19 12:10 PM IPC-08 DONE AE
4202 NMSCEW/P-IV/STR/2019/4138 4138 Checking and Pouring concrete for pier shaft final lift at LA-01 Viaduct Km 202+190 LHS 11-Sep-19 12:37 PM IPC-08 DONE AE
4203 NMSCEW/P-IV/STR/2019/4139 4139 Checking layout ,level for top slab PUP Km 199+060 RHS 11-Sep-19 9:10 AM IPC-08 DONE AE
4204 NMSCEW/P-IV/STR/2019/4140 4140 Checking reinforcement ,shuttering for top slab PUP Km 199+060 RHS 11-Sep-19 9:44 AM IPC-08 DONE AE
4205 NMSCEW/P-IV/STR/2019/4141 4141 Checking and concrete pouring for top slab PUP Km 199+060 RHS 11-Sep-19 11:18 AM IPC-08 DONE AE
4206 NMSCEW/P-IV/STR/2019/4142 4142 Checking of Shuttering and reinforcement for raft at retaining wall A1 PUP Km 172+190 LHS 11-Sep-19 3:08 PM DONE
4207 NMSCEW/P-IV/STR/2019/4143 4143 Checking and Pouring concrete for raft at retaining wall A1 PUP Km 172+190 LHS 11-Sep-19 3:40 PM DONE
4208 NMSCEW/P-IV/STR/2019/4144 4144 Checking of Shuttering and reinforcement for 2nd lift at retaining wall A2 PUP Km 172+190 LHS 11-Sep-19 4:00 PM DONE
4209 NMSCEW/P-IV/STR/2019/4145 4145 Checking and Pouring concrete for 2nd lift at retaining wall A2 PUP Km 172+190 LHS 11-Sep-19 4:36 PM DONE
Checking reinforcement for precast Box Culvert (3x3) (Cushion 2 to 4 m) at precast yard camp
4210 NMSCEW/P-IV/STR/2019/4146 4146 Box culvert Km 175+500 LHS 11-Sep-19 9:23 AM IPC-08 191, 192, 193, 194, 195
-1. Segment NO-191, 192, 193, 194, 195 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4211 NMSCEW/P-IV/STR/2019/4147 4147 Box culvert Km 175+500 LHS 11-Sep-19 12:27 PM
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.-191, 192, 193, 194, 195
NR
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
4212 NMSCEW/P-IV/STR/2019/4148 4148 Box culvert Km 175+500 LHS 11-Sep-19 12:49 PM DONE
-1. Segment NO-185,186,187
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4213 NMSCEW/P-IV/STR/2019/4149 4149 Box culvert Km 175+500 LHS 11-Sep-19 12:52 PM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-185,186,187
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
4214 NMSCEW/P-IV/STR/2019/4150 4150 Box culvert Km 175+500 LHS 11-Sep-19 4:16 PM IPC-08 222, 223, 224, 225
-1. Segment NO-222, 223, 224, 225 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4215 NMSCEW/P-IV/STR/2019/4151 4151 Box culvert Km 175+500 LHS 11-Sep-19 5:21 PM IPC-08 222, 223
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-222, 223, 224, 225
DONE AE
4216 NMSCEW/P-IV/STR/2019/4152 4152 Checking of Shuttering and reinforcement for raft with bottom haunch at A1 & A2 PUP Km 165+790 LHS 11-Sep-19 4:12 PM IPC-08 DONE AE
4217 NMSCEW/P-IV/STR/2019/4153 4153 Checking and Pouring concrete for raft for raft with bottom haunch at A1 & A2 PUP Km 165+790 LHS 11-Sep-19 4:56 PM IPC-08 DONE AE
4218 NMSCEW/P-IV/STR/2019/4154 4154 Checking of reinforcement, shuttering for 2nd lift at A1 & A2 wall PUP Km 189+000 RHS 11-Sep-19 9:19 AM NR
4219 NMSCEW/P-IV/STR/2019/4155 4155 Checking & Pouring concrete(M-30) for 2nd lift at A1 & A2 wall PUP Km 189+000 RHS 11-Sep-19 9:41 AM NR
4220 NMSCEW/P-IV/STR/2019/4156 4156 Checking of Shuttering and reinforcement for raft at retaining wall A1 PUP Km 184+190 LHS 11-Sep-19 8:05 AM DONE
4221 NMSCEW/P-IV/STR/2019/4157 4157 Checking and Pouring concrete(M-30) for raft at retaining wall A1 PUP Km 184+190 LHS 11-Sep-19 8:34 AM NR
4222 NMSCEW/P-IV/STR/2019/4158 4158 Checking reinforcement ,shuttering for bottom slab of loop-B MNB loop-B Km 01+980 11-Sep-19 4:13 PM NR
4223 NMSCEW/P-IV/STR/2019/4159 4159 Checking and concrete (M30) pouring for bottom slab of loop-B MNB loop-B Km 01+980 11-Sep-19 4:46 PM NR
4224 NMSCEW/P-IV/STR/2019/4160 4160 Checking of Shuttering and reinforcement for raft with bottom haunch at A1 & A2 LVUP Km 169+291 LHS 11-Sep-19 4:30 PM NR
4225 NMSCEW/P-IV/STR/2019/4161 4161 Checking and Pouring concrete for raft for raft with bottom haunch at A1 & A2 LVUP Km 169+291 LHS 11-Sep-19 5:10 PM NR
Checking reinforcement for precast Box Culvert (3x3)(Cushion 0 to 2m) at precast yard camp
4226 NMSCEW/P-IV/STR/2019/4162 4162 Box culvert Km 200+200 LHS 11-Sep-19 9:22 AM DONE
-2. Segment NO-145
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4227 NMSCEW/P-IV/STR/2019/4163 4163 Box culvert Km 200+200 LHS 11-Sep-19 10:38 AM DONE
(3×3) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-145
Checking reinforcement for precast Box Culvert (3x3)(Cushion 2 to 4m) at precast yard camp
4228 NMSCEW/P-IV/STR/2019/4164 4164 Box culvert Km 200+200 LHS 11-Sep-19 3:09 PM DONE
-2. Segment NO-43
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4229 NMSCEW/P-IV/STR/2019/4165 4165 Box culvert Km 200+200 LHS 11-Sep-19 4:17 PM DONE
(3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-43
4230 NMSCEW/P-IV/STR/2019/4166 4166 Checking top Level & Laying concrete(M-10) for PCC Utility duct Km 171+570 Km 00+000 BHS 11-Sep-19 12:30 PM IPC-09 DONE
4231 NMSCEW/P-IV/STR/2019/4167 4167 Checking top Level & Laying concrete(M-10) for PCC Utility duct Km 172+520 BHS 11-Sep-19 1:00 PM IPC-08 DONE
Checking of Shuttering and reinforcement for RE WALL PANEL precast TYPE -A
4232 NMSCEW/P-IV/STR/2019/4168 4168 32, TYPE -B 10, TYPE -Sta 2, TYPE -Stb 2, TYPE -Stc 2, TYPE -Std 2, TYPE -Ltc 1, RE Wall Panel Km 200+200 LHS 12-Sep-19 10:00 AM DONE
TYPE -Ltd 2,
Checking and Pouring concrete for RE WALL PANEL precastTYPE -A
4233 NMSCEW/P-IV/STR/2019/4169 4169 32, TYPE -B 10, TYPE -Sta 2, TYPE -Stb 2, TYPE -Stc 2, TYPE -Std 2, TYPE -Ltc 1, RE Wall Panel Km 200+200 LHS 12-Sep-19 11:00 AM DONE
TYPE -Ltd 2,
4234 NMSCEW/P-IV/STR/2019/4170 4170 Checking of reinforcement and shuttering for pier shaft 1st lift at LA-01 Viaduct Km 169+800 LHS 12-Sep-19 2:00 PM NR
4235 NMSCEW/P-IV/STR/2019/4171 4171 Checking and Pouring concrete for pier shaft 1st lift at LA-01 Viaduct Km 169+800 LHS 12-Sep-19 2:30 PM NR
4236 NMSCEW/P-IV/STR/2019/4172 4172 Checking of side shuttering girder no- 13,14,15,16 at bed no-06,Girder Type-1 Girder Km 200+200 LHS 12-Sep-19 2:45 PM
Approval for pouring of girder no- 13,14,15,16 at bed no-06. (Grade of concrete M-50)
4237 NMSCEW/P-IV/STR/2019/4173 4173 Girder Km 200+200 LHS 12-Sep-19 3:00 PM
Girder Type- 1
4238 NMSCEW/P-IV/STR/2019/4174 4174 Checking of reinforcement and shuttering for pier shaft starter at RP-06 Viaduct Km 195+900 RHS 12-Sep-19 11:15 AM
4239 NMSCEW/P-IV/STR/2019/4175 4175 Checking and Pouring concrete for pier shaft starter at RP-06 Viaduct Km 195+900 RHS 12-Sep-19 11:45 AM
4240 NMSCEW/P-IV/STR/2019/4176 4176 Checking of reinforcement and shuttering for raft at RP-09 Viaduct Km 195+900 RHS 12-Sep-19 12:00 PM
4241 NMSCEW/P-IV/STR/2019/4177 4177 Checking and Pouring concrete or raft at RP-09 Viaduct Km 195+900 RHS 12-Sep-19 1:00 PM
4242 NMSCEW/P-IV/STR/2019/4178 4178 Checking of reinforcement and shuttering for pier shaft final lift at LP-05 Viaduct Km 196+560 LHS 12-Sep-19 3:00 PM
4243 NMSCEW/P-IV/STR/2019/4179 4179 Checking and Pouring concrete for pier shaft final lift at LP-05 Viaduct Km 196+560 LHS 12-Sep-19 3:30 PM
4244 NMSCEW/P-IV/STR/2019/4180 4180 Checking and Pouring concrete for pier shaft final lift at RP-06 Viaduct Km 202+190 Km 00+000 RHS 12-Sep-19 12:30 PM IPC-10 DONE
4245 NMSCEW/P-IV/STR/2019/4181 4181 Checking and Pouring concrete for pier shaft 1st lift at LP-09 Viaduct Km 202+190 Km 00+000 LHS 12-Sep-19 11:10 AM IPC-10 DONE
4246 NMSCEW/P-IV/STR/2019/4182 4182 Checking layout ,level and structural excavation for median wall raft LVUP Km 173+400 BHS 12-Sep-19 1:10 PM DONE
4247 NMSCEW/P-IV/STR/2019/4183 4183 Checking top Level & Laying concrete(M-10) for PCC at median wall raft LVUP Km 173+400 BHS 12-Sep-19 1:30 PM DONE
Checking reinforcement for precast Box Culvert (3x3) (Cushion 2 to 4 m) at precast yard camp
4248 NMSCEW/P-IV/STR/2019/4184 4184 Box culvert Km 175+500 LHS 12-Sep-19 9:40 AM IPC-08 180, 181, 182, 183, 184, 185
-1. Segment NO-180, 181, 182, 183, 184,185 DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4249 NMSCEW/P-IV/STR/2019/4185 4185 Box culvert Km 175+500 LHS 12-Sep-19 12:15 PM IPC-08 180, 181, 182, 183, 184, 185
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.-180, 181, 182, 183, 184,185
DONE
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
4250 NMSCEW/P-IV/STR/2019/4186 4186 Box culvert Km 175+500 LHS 12-Sep-19 12:41 PM DONE
-1. Segment NO-188,189,190
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4251 NMSCEW/P-IV/STR/2019/4187 4187 Box culvert Km 175+500 LHS 12-Sep-19 2:20 PM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-188,189,190
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
4252 NMSCEW/P-IV/STR/2019/4188 4188 Box culvert Km 175+500 LHS 12-Sep-19 4:21 PM IPC-08 227, 228,
-1. Segment NO-226, 227, 228, 229 DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4253 NMSCEW/P-IV/STR/2019/4189 4189 Box culvert Km 175+500 LHS 12-Sep-19 5:20 PM IPC-08 227, 228,
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-226, 227, 228, 229
DONE
4254 NMSCEW/P-IV/STR/2019/4190 4190 Checking of Shuttering and reinforcement for raft at retaining wall A1 PUP Km 184+190 LHS 12-Sep-19 8:05 AM NR
4255 NMSCEW/P-IV/STR/2019/4191 4191 Checking and Pouring concrete(M-30) for raft at retaining wall A1 PUP Km 184+190 LHS 12-Sep-19 8:34 AM NR
4256 NMSCEW/P-IV/STR/2019/4192 4192 Checking reinforcement ,shuttering for bottom slab of loop-B MNB loop-B Km 01+980 12-Sep-19 10:22 AM NR
4257 NMSCEW/P-IV/STR/2019/4193 4193 Checking and concrete (M30) pouring for bottom slab of loop-B MNB loop-B Km 01+980 12-Sep-19 10:55 AM NR
4258 NMSCEW/P-IV/STR/2019/4194 4194 Checking of reinforcement and shuttering for raft at RP-02 Viaduct Km 200+920 RHS 12-Sep-19 5:00 PM
4259 NMSCEW/P-IV/STR/2019/4195 4195 Checking and Pouring concrete or raft at RP-02 Viaduct Km 200+920 RHS 12-Sep-19 5:30 PM
4260 NMSCEW/P-IV/STR/2019/4196 4196 Checking of reinforcement, shuttering for 2nd lift at A1 & A2 wall PUP Km 189+000 RHS 12-Sep-19 9:35 AM IPC-08 DONE AE
4261 NMSCEW/P-IV/STR/2019/4197 4197 Checking & Pouring concrete(M-30) for 2nd lift at A1 & A2 wall PUP Km 189+000 RHS 12-Sep-19 10:05 AM IPC-08 DONE AE
4262 NMSCEW/P-IV/STR/2019/4198 4198 Checking of reinforcement, shuttering for 1st lift at A1 & A2 wall Box culvert Km 180+427 LHS 13-Sep-19 11:30 AM IPC-08 DONE AE
4263 NMSCEW/P-IV/STR/2019/4199 4199 Checking & Pouring concrete for 1st lift at A1 & A2 wall Box culvert Km 180+427 LHS 13-Sep-19 12:30 PM IPC-08 DONE AE
4264 NMSCEW/P-IV/STR/2019/4200 4200 Checking layout ,level for PCC at LA-2 MJB 205+610 Km 00+000 LHS 13-Sep-19 4:00 PM IPC-09 DONE AE
4265 NMSCEW/P-IV/STR/2019/4201 4201 Checking top Level & Laying concrete for PCC at LA-2 MJB 205+610 Km 00+000 LHS 13-Sep-19 11:30 AM IPC-09 DONE AE
4266 NMSCEW/P-IV/STR/2019/4202 4202 Checking of Shuttering and reinforcement for raft at retaining wall W1 PUP Km 204+470 LHS 13-Sep-19 9:00 AM DONE
4267 NMSCEW/P-IV/STR/2019/4203 4203 Checking and Pouring concrete for raft at retaining wall W1 PUP Km 204+470 LHS 13-Sep-19 9:30 AM DONE
4268 NMSCEW/P-IV/STR/2019/4204 4204 Checking of reinforcement and shuttering for pier shaft final lift at LP-07 Viaduct Km 195+900 LHS 13-Sep-19 10:00 AM
4269 NMSCEW/P-IV/STR/2019/4205 4205 Checking and Pouring concrete for pier shaft final lift at LP-07 Viaduct Km 195+900 LHS 13-Sep-19 10:30 AM
4270 NMSCEW/P-IV/STR/2019/4206 4206 Checking of reinforcement and shuttering for raft at LP-1 Viaduct Km 195+900 LHS 13-Sep-19 11:33 AM IPC-08 DONE AE
4271 NMSCEW/P-IV/STR/2019/4207 4207 Checking and Pouring concrete or raft at LP-1 Viaduct Km 195+900 LHS 13-Sep-19 12:00 PM IPC-08 DONE AE
4272 NMSCEW/P-IV/STR/2019/4208 4208 Checking of reinforcement, shuttering & layout for pier shaft 2nd/final lift RP-06 Viaduct Km 196+560 Km 00+000 RHS 13-Sep-19 10:35 AM IPC-09 DONE AE
4273 NMSCEW/P-IV/STR/2019/4209 4209 Checking & pouring concrete for pier shaft 2nd/final lift at RP-06 Viaduct Km 196+560 Km 00+000 RHS 13-Sep-19 11:15 AM IPC-09 DONE AE
4274 NMSCEW/P-IV/STR/2019/4210 4210 Checking of reinforcement and shuttering for pier shaft starter at RP-05 Viaduct Km 195+900 RHS 13-Sep-19 1:00 PM
4275 NMSCEW/P-IV/STR/2019/4211 4211 Checking and Pouring concrete for pier shaft starter at RP-05 Viaduct Km 195+900 RHS 13-Sep-19 1:30 PM
4276 NMSCEW/P-IV/STR/2019/4212 4212 Checking of reinforcement and shuttering for pier shaft starter at RP-04 Viaduct Km 195+900 RHS 13-Sep-19 2:05 PM
4277 NMSCEW/P-IV/STR/2019/4213 4213 Checking and Pouring concrete for pier shaft starter at RP-04 Viaduct Km 195+900 RHS 13-Sep-19 2:37 PM
4278 NMSCEW/P-IV/STR/2019/4214 4214 Checking of reinforcement and shuttering for raft at RP-02 Viaduct Km 200+920 RHS 13-Sep-19 11:20 AM
4279 NMSCEW/P-IV/STR/2019/4215 4215 Checking and Pouring concrete for raft at RP-02 Viaduct Km 200+920 RHS 13-Sep-19 11:50 AM
4280 NMSCEW/P-IV/STR/2019/4216 4216 Checking of reinforcement, shuttering for 3rd lift at retaining wall A1 & A2 PUP Km 172+190 RHS 13-Sep-19 1:10 PM DONE
4281 NMSCEW/P-IV/STR/2019/4217 4217 Checking & Pouring concrete for 3rd lift at retaining wall A1 & A2 PUP Km 172+190 RHS 13-Sep-19 1:40 PM DONE
4282 NMSCEW/P-IV/STR/2019/4218 4218 Checking of reinforcement, shuttering for median haunch at wall A1 & A2 PUP Km 172+190 BHS 13-Sep-19 10:11 AM DONE
4283 NMSCEW/P-IV/STR/2019/4219 4219 Checking & Pouring concrete for median haunch at wall A1 & A2 PUP Km 172+190 BHS 13-Sep-19 10:34 AM DONE
4284 NMSCEW/P-IV/STR/2019/4220 4220 Checking reinforcement ,shuttering for bottom slab & haunch Box culvert Km 180+922 Km 00+000 RHS 13-Sep-19 8:00 AM IPC-10 DONE AE
4285 NMSCEW/P-IV/STR/2019/4221 4221 Checking and concrete (M35) pouring for bottom slab & haunch. Box culvert Km 180+922 Km 00+000 RHS 13-Sep-19 8:30 AM IPC-10 DONE AE
4286 NMSCEW/P-IV/STR/2019/4222 4222 Checking layout ,level and structural excavation PUP Km 165+300 BHS 13-Sep-19 8:05 AM DONE
4287 NMSCEW/P-IV/STR/2019/4223 4223 Checking top Level & Laying concrete for PCC PUP Km 165+300 BHS 13-Sep-19 8:35 AM DONE
4288 NMSCEW/P-IV/STR/2019/4224 4224 Checking errection of 3*3 box culvert Box culvert Km 178+730 BHS 13-Sep-19 9:35 AM IPC-08 DONE
4289 NMSCEW/P-IV/STR/2019/4225 4225 Checking of reinforcement and shuttering for raft with bottom haunch A1 & A2 LVUP Km 169+291 Km 00+000 RHS 13-Sep-19 4:00 PM IPC-10 DONE AE
4290 NMSCEW/P-IV/STR/2019/4226 4226 Checking and Pouring concrete for raft with bottom haunch A1 & A2 LVUP Km 169+291 Km 00+000 RHS 13-Sep-19 4:30 PM IPC-10 DONE
4291 NMSCEW/P-IV/STR/2019/4227 4227 Checking layout ,level and structural excavation for PCC at wall A1 & A2 PUP Km 183+290 RHS 13-Sep-19 11:11 AM DONE
4292 NMSCEW/P-IV/STR/2019/4228 4228 Checking top Level & Laying concrete for PCC at wall A1 & A2 PUP Km 183+290 RHS 13-Sep-19 11:41 AM DONE
4293 NMSCEW/P-IV/STR/2019/4229 4229 Checking of reinforcement, shuttering for raft at retaining wall A2 PUP Km 171+110 RHS 13-Sep-19 12:05 PM DONE
4294 NMSCEW/P-IV/STR/2019/4230 4230 Checking & Pouring concrete for raft at retaining wall A2 PUP Km 171+110 RHS 13-Sep-19 12:42 PM DONE
4295 NMSCEW/P-IV/STR/2019/4231 4231 Checking & pouring concrete for pier cap at LP-06 Viaduct Km 169+800 LHS 13-Sep-19 8:00 AM IPC-08 DONE
4296 NMSCEW/P-IV/STR/2019/4232 4232 Checking of reinforcement, shuttering for pier cap at LP-08 Viaduct Km 169+800 LHS 13-Sep-19 3:08 PM NR
4297 NMSCEW/P-IV/STR/2019/4233 4233 Checking & pouring concrete for pier cap at LP-08 Viaduct Km 169+800 LHS 13-Sep-19 3:44 PM NR
Checking reinforcement for precast Box Culvert (3x3)(Cushion 0 to 2m) at precast yard camp
4298 NMSCEW/P-IV/STR/2019/4234 4234 Box culvert Km 200+200 LHS 14-Sep-19 9:30 AM DONE
-2. Segment NO-146,147,148,149
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4299 NMSCEW/P-IV/STR/2019/4235 4235 Box culvert Km 200+200 LHS 14-Sep-19 10:30 AM DONE
(3×3) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-146,147,148,149
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
4300 NMSCEW/P-IV/STR/2019/4236 4236 -2. Segment NO-412,413,414,415,416,417,418,419,420,421 Box culvert Km 200+200 LHS 14-Sep-19 10:45 AM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
(2×2)(Cushion 2 to 4m) at precast yard camp-2,Segment no.-
4301 NMSCEW/P-IV/STR/2019/4237 4237 Box culvert Km 200+200 LHS 14-Sep-19 12:00 PM DONE
412,413,414,415,416,417,418,419,420,421
Checking reinforcement for precast Box Culvert (3x3)(Cushion 2 to 4m) at precast yard camp
4302 NMSCEW/P-IV/STR/2019/4238 4238 Box culvert Km 200+200 LHS 14-Sep-19 3:00 PM DONE
-2. Segment NO-44
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4303 NMSCEW/P-IV/STR/2019/4239 4239 Box culvert Km 200+200 LHS 14-Sep-19 3:30 PM DONE
(3×3) (Cushion 2 to 4m) at precast yard camp-2,Segment no.-44
4304 NMSCEW/P-IV/STR/2019/4240 4240 Checking of reinforcement, shuttering for 2nd lift at wall A1 & A2 LVUP Km 178+323 Km 00+000 LHS 14-Sep-19 10:35 AM IPC-09 DONE AE
4305 NMSCEW/P-IV/STR/2019/4241 4241 Checking & Pouring concrete(M-35) for 2nd lift at wall A1 & A2 LVUP Km 178+323 Km 00+000 LHS 14-Sep-19 11:40 AM IPC-09 DONE AE
4306 NMSCEW/P-IV/STR/2019/4242 4242 Checking layout ,level and structural excavation Utility duct Km 180+800 BHS 14-Sep-19 9:45 AM DONE
4307 NMSCEW/P-IV/STR/2019/4243 4243 Checking layout ,level and structural excavation for PCC at retaining wall A1 & A2 LVUP Km 173+400 RHS 14-Sep-19 11:35 AM DONE
4308 NMSCEW/P-IV/STR/2019/4244 4244 Checking top Level & Laying concrete for PCC(M-10) at retaining wall A1 & A2 LVUP Km 173+400 RHS 14-Sep-19 12:15 PM DONE
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
4309 NMSCEW/P-IV/STR/2019/4245 4245 Box culvert Km 175+500 LHS 14-Sep-19 9:15 AM DONE
-1. Segment NO-191,192,193
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4310 NMSCEW/P-IV/STR/2019/4246 4246 Box culvert Km 175+500 LHS 14-Sep-19 10:15 AM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-191,192,193
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
4311 NMSCEW/P-IV/STR/2019/4247 4247 Box culvert Km 175+500 LHS 14-Sep-19 10:40 AM DONE
-1. Segment NO-224,225,230,231,233,234
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4312 NMSCEW/P-IV/STR/2019/4248 4248 Box culvert Km 175+500 LHS 14-Sep-19 12:18 PM DONE
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-224,225,230,231,233,234
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4313 NMSCEW/P-IV/STR/2019/4249 4249 Box culvert Km 175+500 LHS 14-Sep-19 2:20 PM
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.-191,192,193,194,195
NR
4314 NMSCEW/P-IV/STR/2019/4250 4250 Checking layout ,level and structural excavation for PCC at retaining wall A1 & A2 PUP Km 165+300 LHS 14-Sep-19 3:15 PM DONE
4315 NMSCEW/P-IV/STR/2019/4251 4251 Checking top Level & Laying concrete for PCC at retaining wall A1 & A2 PUP Km 165+300 LHS 14-Sep-19 3:45 PM DONE
4316 NMSCEW/P-IV/STR/2019/4252 4252 Checking of side shuttering girder no- 21,22,23,24 at bed no-04,Girder Type-2 Girder Km 200+200 LHS 14-Sep-19 9:00 AM
Approval for pouring of girder no- 21,22,23,24 at bed no-04. (Grade of concrete M-50)
4317 NMSCEW/P-IV/STR/2019/4253 4253 Girder Km 200+200 LHS 14-Sep-19 9:25 AM
Girder Type- 2
Checking for stressing and remove slagness of H.T. wires at Girder no 25,26,27,28 at bed no
4318 NMSCEW/P-IV/STR/2019/4254 4254 Girder Type-2 Km 200+200 LHS 14-Sep-19 3:25 PM
-2 at casting yard camp -2
4319 NMSCEW/P-IV/STR/2019/4255 4255 Checking of reinforcement Girder no 25,26,27,28 at bed no -2 at casting yard camp -2 Girder Type-2 Km 200+200 LHS 14-Sep-19 2:20 PM
4320 NMSCEW/P-IV/STR/2019/4256 4256 Checking of reinforcement, shuttering for pier cap at LP-09 Viaduct Km 169+800 LHS 14-Sep-19 12:06 PM IPC-08 DONE
4321 NMSCEW/P-IV/STR/2019/4257 4257 Checking & pouring concrete for pier cap at LP-09 Viaduct Km 169+800 LHS 14-Sep-19 12:34 PM IPC-08 DONE
4322 NMSCEW/P-IV/STR/2019/4258 4258 Checking of reinforcement, shuttering for pier cap at LP-10 Viaduct Km 169+800 LHS 14-Sep-19 2:11 PM NR
4323 NMSCEW/P-IV/STR/2019/4259 4259 Checking & pouring concrete for pier cap at LP-10 Viaduct Km 169+800 LHS 14-Sep-19 2:44 PM NR
4324 NMSCEW/P-IV/STR/2019/4260 4260 Checking of reinforcement, shuttering for pier cap at RP-09 Viaduct Km 169+800 RHS 14-Sep-19 3:15 PM IPC-08 DONE AE
4325 NMSCEW/P-IV/STR/2019/4261 4261 Checking & pouring concrete for pier cap at RP-09 Viaduct Km 169+800 RHS 14-Sep-19 3:54 PM IPC-08 DONE AE
4326 NMSCEW/P-IV/STR/2019/4262 4262 Checking of reinforcement, shuttering for pier cap at LP-08 Viaduct Km 169+800 LHS 14-Sep-19 11:11 AM IPC-08 DONE AE
4327 NMSCEW/P-IV/STR/2019/4263 4263 Checking & pouring concrete for pier cap at LP-08 Viaduct Km 169+800 LHS 14-Sep-19 11:46 AM IPC-08 DONE AE
4328 NMSCEW/P-IV/STR/2019/4264 4264 Checking of reinforcement and shuttering for pier shaft 1st lift at LA-01 Viaduct Km 169+800 LHS 14-Sep-19 4:22 PM DONE
4329 NMSCEW/P-IV/STR/2019/4265 4265 Checking and Pouring concrete for pier shaft 1st lift at LA-01 Viaduct Km 169+800 LHS 14-Sep-19 5:10 PM DONE
4330 NMSCEW/P-IV/STR/2019/4266 4266 Checking of reinforcement and shuttering for raft at RP-09 Viaduct Km 195+900 RHS 14-Sep-19 9:28 AM
4331 NMSCEW/P-IV/STR/2019/4267 4267 Checking and Pouring concrete or raft at RP-09 Viaduct Km 195+900 RHS 14-Sep-19 10:10 AM
4332 NMSCEW/P-IV/STR/2019/4268 4268 Checking of reinforcement and shuttering for pier shaft final lift at LP-05 Viaduct Km 196+560 Km 00+000 LHS 14-Sep-19 10:32 AM IPC-10 DONE AE
4333 NMSCEW/P-IV/STR/2019/4269 4269 Checking and Pouring concrete for pier shaft final lift at LP-05 Viaduct Km 196+560 Km 00+000 LHS 14-Sep-19 11:23 AM IPC-10 DONE AE
4334 NMSCEW/P-IV/STR/2019/4270 4270 Checking of reinforcement and shuttering for pier shaft final lift at RP-08 Viaduct Km 196+560 RHS 14-Sep-19 2:22 PM
4335 NMSCEW/P-IV/STR/2019/4271 4271 Checking and Pouring concrete for pier shaft final lift at RP-08 Viaduct Km 196+560 RHS 14-Sep-19 2:52 PM
4336 NMSCEW/P-IV/STR/2019/4272 4272 Checking layout ,level for PCC at LA-2 MJB Km 205+610 LHS 14-Sep-19 2:01 PM
4337 NMSCEW/P-IV/STR/2019/4273 4273 Checking top Level & Laying concrete for PCC at LA-2 MJB Km 205+610 LHS 14-Sep-19 3:03 PM
4338 NMSCEW/P-IV/STR/2019/4274 4274 Checking reinforcement ,shuttering for top slab & top haunch Box culvert Km 182+350 RHS 14-Sep-19 12:22 PM IPC-08 DONE AE SPOT RFI
4339 NMSCEW/P-IV/STR/2019/4275 4275 Checking and concrete (M30) pouring for top slab & top haunch. Box culvert Km 182+350 RHS 14-Sep-19 12:50 PM IPC-08 DONE AE SPOT RFI
4340 NMSCEW/P-IV/STR/2019/4276 4276 Checking of reinforcement, shuttering for 3rd lift at A1 & A2 wall VUP Km 179+983 Km 00+000 LHS 14-Sep-19 2:30 PM IPC-10 DONE SPOT RFI
4341 NMSCEW/P-IV/STR/2019/4277 4277 Checking & Pouring concrete(M-35) for 3rd lift at A1 & A2 wall VUP Km 179+983 Km 00+000 LHS 14-Sep-19 2:40 PM IPC-10 DONE SPOT RFI
4342 NMSCEW/P-IV/STR/2019/4278 4278 Checking of layout ,level, reinforcement, shuttering for raft at RP-2 Viaduct Km 200+920 RHS 14-Sep-19 12:15 PM IPC-08 DONE AE
4343 NMSCEW/P-IV/STR/2019/4279 4279 Checking & Pouring concrete for raft at RP-2 Viaduct Km 200+920 RHS 14-Sep-19 12:44 PM IPC-08 DONE AE
4344 NMSCEW/P-IV/STR/2019/4280 4280 Checking of reinforcement, shuttering for raft at retaining wall W2 PUP Km 205+430 RHS 15-Sep-19 8:00 AM DONE
4345 NMSCEW/P-IV/STR/2019/4281 4281 Checking & Pouring concrete for raft at retaining wall W2 PUP Km 205+430 RHS 15-Sep-19 8:30 AM DONE
4346 NMSCEW/P-IV/STR/2019/4282 4282 Checking of reinforcement, shuttering for raft at retaining wall W2 PUP Km 204+470 LHS 15-Sep-19 10:00 AM DONE
4347 NMSCEW/P-IV/STR/2019/4283 4283 Checking & Pouring concrete for raft at retaining wall W2 PUP Km 204+470 LHS 15-Sep-19 10:30 AM DONE
4348 NMSCEW/P-IV/STR/2019/4284 4284 Checking of reinforcement, shuttering for raft at median PUP Km 191+740 15-Sep-19 8:15 AM DONE
4349 NMSCEW/P-IV/STR/2019/4285 4285 Checking & Pouring concrete for raft at median PUP Km 191+740 15-Sep-19 8:45 AM DONE
4350 NMSCEW/P-IV/STR/2019/4286 4286 Checking of reinforcement, shuttering for 1st lift at retaining wall A1 & A2 PUP Km 165+300 RHS 15-Sep-19 4:30 PM DONE
4351 NMSCEW/P-IV/STR/2019/4287 4287 Checking & Pouring concrete for 1st lift at retaining wall A1 & A2 PUP Km 165+300 RHS 15-Sep-19 5:00 PM DONE
Checking for stressing and remove slagness of H.T. wires at Girder no 17,18,19,20 at bed no
4352 NMSCEW/P-IV/STR/2019/4288 4288 Girder Type-1 Km 200+200 LHS 15-Sep-19 11:00 AM
-5 at casting yard camp -2
4353 NMSCEW/P-IV/STR/2019/4289 4289 Checking of reinforcement Girder no 17,18,19,20 at bed no -5 at casting yard camp -2 Girder Type-1 Km 200+200 LHS 15-Sep-19 11:30 AM
4354 NMSCEW/P-IV/STR/2019/4290 4290 Checking of reinforcement and shuttering for raft at RP-09 Viaduct Km 195+900 RHS 15-Sep-19 9:44 AM IPC-08 DONE
4355 NMSCEW/P-IV/STR/2019/4291 4291 Checking and Pouring concrete or raft at RP-09 Viaduct Km 195+900 RHS 15-Sep-19 10:12 AM
4356 NMSCEW/P-IV/STR/2019/4292 4292 Checking of reinforcement and shuttering for pier shaft final lift at RP-08 Viaduct Km 196+560 Km 00+000 RHS 15-Sep-19 9:25 AM IPC-09 DONE AE
4357 NMSCEW/P-IV/STR/2019/4293 4293 Checking and Pouring concrete for pier shaft final lift at RP-08 Viaduct Km 196+560 Km 00+000 RHS 15-Sep-19 10:20 AM IPC-09 DONE AE
4358 NMSCEW/P-IV/STR/2019/4294 4294 Checking of reinforcement and shuttering for pier shaft final lift at LP-07 Viaduct Km 195+900 Km 00+000 LHS 15-Sep-19 10:34 AM IPC-11 Approved AE
4359 NMSCEW/P-IV/STR/2019/4295 4295 Checking and Pouring concrete for pier shaft final lift at LP-07 Viaduct Km 195+900 Km 00+000 LHS 15-Sep-19 11:11 AM IPC-11 Approved AE
4360 NMSCEW/P-IV/STR/2019/4296 4296 Checking layout ,level for PCC at RP-08 Viaduct Km 202+190 RHS 15-Sep-19 10:17 AM
4361 NMSCEW/P-IV/STR/2019/4297 4297 Checking top Level & Laying concrete for PCC at RP-08 Viaduct Km 202+190 RHS 15-Sep-19 10:45 AM
4362 NMSCEW/P-IV/STR/2019/4298 4298 Checking of reinforcement, shuttering for pier cap at LP-01 Viaduct Km 202+190 LHS 15-Sep-19 11:15 AM IPC-08 DONE AE
4363 NMSCEW/P-IV/STR/2019/4299 4299 Checking & pouring concrete for pier cap at LP-01 Viaduct Km 202+190 LHS 15-Sep-19 11:42 AM IPC-08 DONE AE
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
4364 NMSCEW/P-IV/STR/2019/4300 4300 -2. Segment NO-422,423,424,425,426 Box culvert Km 200+200 LHS 16-Sep-19 9:30 AM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4365 NMSCEW/P-IV/STR/2019/4301 4301 (2×2)(Cushion 2 to 4m) at precast yard camp-2,Segment no.-422,423,424,425,426 Box culvert Km 200+200 LHS 16-Sep-19 10:30 AM DONE
4366 NMSCEW/P-IV/STR/2019/4302 4302 Checking of Shuttering and reinforcement for raft at U-type retaining wall PUP Km 203+560 16-Sep-19 8:00 AM DONE
4367 NMSCEW/P-IV/STR/2019/4303 4303 Checking and Pouring concrete for raft at U-type retaining wall PUP Km 203+560 16-Sep-19 8:30 AM DONE
4368 NMSCEW/P-IV/STR/2019/4304 4304 Checking of Shuttering and reinforcement for 1st lift at retaining wall W2 PUP Km 203+560 RHS 16-Sep-19 9:00 AM DONE
4369 NMSCEW/P-IV/STR/2019/4305 4305 Checking and Pouring concrete for 1st lift at retaining wall W2 PUP Km 203+560 RHS 16-Sep-19 9:10 AM DONE
4370 NMSCEW/P-IV/STR/2019/4306 4306 Checking of Shuttering and reinforcement for raft at retaining wall W2 PUP Km 204+470 RHS 16-Sep-19 10:00 AM DONE
4371 NMSCEW/P-IV/STR/2019/4307 4307 Checking and Pouring concrete for raft at retaining wall W2 PUP Km 204+470 RHS 16-Sep-19 10:30 AM DONE
4372 NMSCEW/P-IV/STR/2019/4308 4308 Checking of Shuttering and reinforcement for raft at retaining wall W1 PUP Km 205+430 RHS 16-Sep-19 2:00 PM DONE
4373 NMSCEW/P-IV/STR/2019/4309 4309 Checking and Pouring concrete for raft at retaining wall W1 PUP Km 205+430 RHS 16-Sep-19 2:30 PM DONE
4374 NMSCEW/P-IV/STR/2019/4310 4310 Checking layout ,level for raft MNB Km 199+360 RHS 16-Sep-19 11:00 AM IPC-08 DONE AE
4375 NMSCEW/P-IV/STR/2019/4311 4311 Checking of Shuttering and reinforcement for raft MNB Km 199+360 RHS 16-Sep-19 11:30 AM IPC-08 DONE AE
4376 NMSCEW/P-IV/STR/2019/4312 4312 Checking and Pouring concrete for raft MNB Km 199+360 RHS 16-Sep-19 2:00 PM IPC-08 DONE AE
4377 NMSCEW/P-IV/STR/2019/4313 4313 Checking of reinforcement, shuttering for pier cap at LP-10 Viaduct Km 169+800 LHS 16-Sep-19 2:15 PM IPC-08 DONE
4378 NMSCEW/P-IV/STR/2019/4314 4314 Checking & pouring concrete for pier cap at LP-10 Viaduct Km 169+800 LHS 16-Sep-19 2:45 PM IPC-08 DONE
4379 NMSCEW/P-IV/STR/2019/4315 4315 Checking of Shuttering and reinforcement for raft at LA-01 Viaduct Km 195+900 LHS 16-Sep-19 10:33 AM IPC-08 DONE AE
4380 NMSCEW/P-IV/STR/2019/4316 4316 Checking and Pouring concrete for raft at LA-01 Viaduct Km 195+900 LHS 16-Sep-19 11:15 AM
4381 NMSCEW/P-IV/STR/2019/4317 4317 Checking layout ,level for PCC at LA-02 Viaduct Km 200+920 LHS 16-Sep-19 11:25 AM
4382 NMSCEW/P-IV/STR/2019/4318 4318 Checking top Level & Laying concrete for PCC at LA-02 Viaduct Km 200+920 LHS 16-Sep-19 11:50 AM
4383 NMSCEW/P-IV/STR/2019/4319 4319 Checking top Level & Laying concrete(M-10) for PCC Utility duct Km 173+000 BHS 16-Sep-19 10:16 AM IPC-08 DONE
4384 NMSCEW/P-IV/STR/2019/4320 4320 Checking of Shuttering and reinforcement for 3rd lift at retaining wall A2 PUP Km 172+190 LHS 16-Sep-19 8:10 AM DONE
4385 NMSCEW/P-IV/STR/2019/4321 4321 Checking of Shuttering and reinforcement for 1st lift at retaining wall A1 PUP Km 172+190 LHS 16-Sep-19 8:20 AM DONE
4386 NMSCEW/P-IV/STR/2019/4322 4322 Checking and Pouring concrete or 3rd lift at retaining wall A2 PUP Km 172+190 LHS 16-Sep-19 8:50 AM DONE
4387 NMSCEW/P-IV/STR/2019/4323 4323 Checking and Pouring concrete for 1st lift at retaining wall A1 PUP Km 172+190 LHS 16-Sep-19 9:23 AM DONE
4388 NMSCEW/P-IV/STR/2019/4324 4324 Checking layout ,level for PCC at retaining wall A1 & A2 PUP Km 174+095 RHS 16-Sep-19 2:00 PM DONE
4389 NMSCEW/P-IV/STR/2019/4325 4325 Checking top Level & Laying concrete for PCC at retaining wall A1 & A2 PUP Km 174+095 RHS 16-Sep-19 2:42 PM DONE
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
4390 NMSCEW/P-IV/STR/2019/4326 4326 Box culvert Km 175+500 LHS 16-Sep-19 9:18 AM DONE
-1. Segment NO-194,195,196
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4391 NMSCEW/P-IV/STR/2019/4327 4327 Box culvert Km 175+500 LHS 16-Sep-19 10:12 AM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-194,195,196
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
4392 NMSCEW/P-IV/STR/2019/4328 4328 Box culvert Km 175+500 LHS 16-Sep-19 10:55 AM DONE
-1. Segment NO-235,236,237,238
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4393 NMSCEW/P-IV/STR/2019/4329 4329 Box culvert Km 175+500 LHS 16-Sep-19 12:20 PM
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-235,236,237,238
NR
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4394 NMSCEW/P-IV/STR/2019/4330 4330 Box culvert Km 175+500 LHS 16-Sep-19 3:00 PM IPC-08 191, 192, 193, 194, 195
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.-191,192,193,194,195
DONE AE
4395 NMSCEW/P-IV/STR/2019/4331 4331 Checking of layout,level, reinforcement and shuttering for pier shaft 1st lift at LP-13 Viaduct Km 202+190 Km 00+000 LHS 16-Sep-19 11:45 AM IPC-11 Approved AE SPOT RFI
4396 NMSCEW/P-IV/STR/2019/4332 4332 Checking and Pouring concrete for pier shaft 1st lift at LP-13 Viaduct Km 202+190 Km 00+000 LHS 16-Sep-19 12:00 PM IPC-11 Approved AE SPOT RFI
4397 NMSCEW/P-IV/STR/2019/4333 4333 Checking of Shuttering and reinforcement for 1st lift at wall A2 Box culvert Km 180+427 LHS 17-Sep-19 9:30 AM DONE
4398 NMSCEW/P-IV/STR/2019/4334 4334 Checking and Pouring concrete for 1st lift at wall A2 Box culvert Km 180+427 LHS 17-Sep-19 10:30 AM DONE
4399 NMSCEW/P-IV/STR/2019/4335 4335 Checking of Shuttering and reinforcement for 3rd lift at wall A1 & A2 LVUP Km 178+323 Km 00+000 LHS 17-Sep-19 11:30 AM IPC-09 DONE AE
4400 NMSCEW/P-IV/STR/2019/4336 4336 Checking and Pouring concrete for 3rd lift at wall A1 & A2 LVUP Km 178+323 Km 00+000 LHS 17-Sep-19 12:30 PM IPC-09 DONE AE
4401 NMSCEW/P-IV/STR/2019/4337 4337 Checking layout ,level and structural excavation for wall A1 MNB Km 174+173 BHS 17-Sep-19 10:00 AM NR
4402 NMSCEW/P-IV/STR/2019/4338 4338 Checking layout ,level and structural excavation Utility duct Km 173+680 BHS 17-Sep-19 10:15 AM NR
Checking reinforcement for precast Box Culvert (3x3) (Cushion 2 to 4 m) at precast yard camp
4403 NMSCEW/P-IV/STR/2019/4339 4339 Box culvert Km 175+500 LHS 17-Sep-19 9:00 AM IPC-08 184, 185, 196, 197, 198
-1. Segment NO-184,185,196,197,198 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4404 NMSCEW/P-IV/STR/2019/4340 4340 Box culvert Km 175+500 LHS 17-Sep-19 10:10 AM
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.-184,185,196,197,198
NR
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
4405 NMSCEW/P-IV/STR/2019/4341 4341 Box culvert Km 175+500 LHS 17-Sep-19 11:00 AM DONE
-1. Segment NO-197,198,199
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4406 NMSCEW/P-IV/STR/2019/4342 4342 Box culvert Km 175+500 LHS 17-Sep-19 12:00 PM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-197,198,199
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
4407 NMSCEW/P-IV/STR/2019/4343 4343 Box culvert Km 175+500 LHS 17-Sep-19 3:00 PM DONE
-1. Segment NO-239,240,241,242
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4408 NMSCEW/P-IV/STR/2019/4344 4344 Box culvert Km 175+500 LHS 17-Sep-19 4:00 PM DONE
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-239,240,241,242
4409 NMSCEW/P-IV/STR/2019/4345 4345 Checking of reinforcement, shuttering for 3rd lift at median wall A1 & A2 PUP Km 171+110 BHS 17-Sep-19 10:18 AM NR
4410 NMSCEW/P-IV/STR/2019/4346 4346 Checking & Pouring concrete for 3rd lift at median wall A1 & A2 PUP Km 171+110 BHS 17-Sep-19 10:50 AM NR
4411 NMSCEW/P-IV/STR/2019/4347 4347 Checking errection of 2*2 utility duct Utility duct Km 178+540 BHS 17-Sep-19 9:42 AM IPC-08 DONE
Checking of Shuttering and reinforcement for RE WALL PANEL precast TYPE -A
4412 NMSCEW/P-IV/STR/2019/4348 4348 32, TYPE -B 10, TYPE -Sta 2, TYPE -Stb 2, TYPE -Stc 2, TYPE -Std 2, TYPE -Ltc 1, RE Wall Panel Km 200+200 LHS 17-Sep-19 10:11 AM
TYPE -Ltd 2,
Checking and Pouring concrete for RE WALL PANEL precastTYPE -A
4413 NMSCEW/P-IV/STR/2019/4349 4349 32, TYPE -B 10, TYPE -Sta 2, TYPE -Stb 2, TYPE -Stc 2, TYPE -Std 2, TYPE -Ltc 1, RE Wall Panel Km 200+200 LHS 17-Sep-19 11:11 AM
TYPE -Ltd 2,
4414 NMSCEW/P-IV/STR/2019/4350 4350 Checking of reinforcement, shuttering for pier cap at LP6 Viaduct Km 202+190 LHS 18-Sep-19 2:00 PM IPC-08 DONE
4415 NMSCEW/P-IV/STR/2019/4351 4351 Checking and Pouring concrete for pier cap at LP6 Viaduct Km 202+190 LHS 18-Sep-19 3:00 PM IPC-08 DONE
4416 NMSCEW/P-IV/STR/2019/4352 4352 Checking layout ,level for PCC at LA-02 Viaduct Km 200+920 Km 00+000 LHS 18-Sep-19 11:00 AM IPC-10 DONE
4417 NMSCEW/P-IV/STR/2019/4353 4353 Checking top Level & Laying concrete for PCC at LA-02 Viaduct Km 200+920 Km 00+000 LHS 18-Sep-19 11:30 AM IPC-10 DONE
4418 NMSCEW/P-IV/STR/2019/4354 4354 Checking of reinforcement and shuttering for pier shaft final lift at RP-03 Viaduct Km 196+560 RHS 18-Sep-19 11:40 AM
4419 NMSCEW/P-IV/STR/2019/4355 4355 Checking and Pouring concrete for pier shaft final lift at RP-03 Viaduct Km 196+560 RHS 18-Sep-19 11:55 AM
4420 NMSCEW/P-IV/STR/2019/4356 4356 Checking of reinforcement and shuttering for pier shaft 1st lift at RP-01 Viaduct Km 196+560 RHS 18-Sep-19 3:10 PM
4421 NMSCEW/P-IV/STR/2019/4357 4357 Checking and Pouring concrete for pier shaft 1st lift at RP-01 Viaduct Km 196+560 RHS 18-Sep-19 3:30 PM
4422 NMSCEW/P-IV/STR/2019/4358 4358 Checking and Pouring concrete for raft at LA-01 Viaduct Km 195+900 LHS 18-Sep-19 4:00 PM IPC-08 DONE AE
4423 NMSCEW/P-IV/STR/2019/4359 4359 Checking and Pouring concrete for raft at RP-09 Viaduct Km 195+900 RHS 18-Sep-19 10:00 AM IPC-08 DONE
4424 NMSCEW/P-IV/STR/2019/4360 4360 Checking of reinforcement and shuttering for pier shaft 1st lift at RP-04 Viaduct Km 195+900 RHS 18-Sep-19 10:37 AM IPC-14
4425 NMSCEW/P-IV/STR/2019/4361 4361 Checking and Pouring concrete for pier shaft 1st lift at RP-04 Viaduct Km 195+900 RHS 18-Sep-19 11:11 AM IPC-14
4426 NMSCEW/P-IV/STR/2019/4362 4362 Checking of side shuttering girder no- 25,26,27,28 at bed no-02,Girder Type-2 Girder Km 200+200 LHS 18-Sep-19 4:05 PM
Approval for pouring of girder no- 25,26,27,28 at bed no-02 (Grade of concrete M-50)
4427 NMSCEW/P-IV/STR/2019/4363 4363 Girder Km 200+200 LHS 18-Sep-19 4:34 PM
Girder Type- 2
4428 NMSCEW/P-IV/STR/2019/4364 4364 Checking of reinforcement and shuttering for pier shaft 1st lift at LP-08 Viaduct Km 202+190 Km 00+000 LHS 18-Sep-19 11:32 AM IPC-10 DONE AE
4429 NMSCEW/P-IV/STR/2019/4365 4365 Checking and Pouring concrete for pier shaft 1st lift at LP-08 Viaduct Km 202+190 Km 00+000 LHS 18-Sep-19 11:50 AM IPC-10 DONE AE
4430 NMSCEW/P-IV/STR/2019/4366 4366 Checking of reinforcement and shuttering for pier shaft final lift at RP-04 Viaduct Km 202+190 RHS 18-Sep-19 2:00 PM
4431 NMSCEW/P-IV/STR/2019/4367 4367 Checking and Pouring concrete for pier shaft final lift at RP-04 Viaduct Km 202+190 RHS 18-Sep-19 2:30 PM
4432 NMSCEW/P-IV/STR/2019/4368 4368 Checking of reinforcement, shuttering for pier cap at LP-02 Viaduct Km 202+190 LHS 18-Sep-19 3:05 PM
4433 NMSCEW/P-IV/STR/2019/4369 4369 Checking & pouring concrete for pier cap at LP-02 Viaduct Km 202+190 LHS 18-Sep-19 3:34 PM
4434 NMSCEW/P-IV/STR/2019/4370 4370 Checking of Shuttering and reinforcement for final lift at wall A1 & A2 PUP Km 189+000 RHS 18-Sep-19 5:45 PM IPC-08 DONE SPOT RFI
4435 NMSCEW/P-IV/STR/2019/4371 4371 Checking and Pouring concrete(M-30) for final lift at wall A1 & A2 PUP Km 189+000 RHS 18-Sep-19 6:10 PM IPC-08 DONE SPOT RFI
4436 NMSCEW/P-IV/STR/2019/4372 4372 Checking of Shuttering and reinforcement for raft Box culvert Km 180+180 LHS 19-Sep-19 11:30 AM DONE
4437 NMSCEW/P-IV/STR/2019/4373 4373 Checking and Pouring concrete for raft Box culvert Km 180+180 LHS 19-Sep-19 1:30 PM DONE
4438 NMSCEW/P-IV/STR/2019/4374 4374 Checking of Shuttering and reinforcement for 1st lift at retaining wall W2 PUP Km 204+470 LHS 19-Sep-19 10:00 AM DONE
4439 NMSCEW/P-IV/STR/2019/4375 4375 Checking and Pouring concrete for 1st lift at retaining wall W2 PUP Km 204+470 LHS 19-Sep-19 10:30 AM DONE
4440 NMSCEW/P-IV/STR/2019/4376 4376 Checking of Shuttering and reinforcement for 1st lift at retaining wall W1 PUP Km 203+560 RHS 19-Sep-19 8:00 AM DONE
4441 NMSCEW/P-IV/STR/2019/4377 4377 Checking and Pouring concrete for 1st lift at retaining wall W1 PUP Km 203+560 RHS 19-Sep-19 8:30 AM DONE
4442 NMSCEW/P-IV/STR/2019/4378 4378 Checking of Shuttering and reinforcement for raft Utility duct Km 207+220 RHS 19-Sep-19 9:00 AM DONE
4443 NMSCEW/P-IV/STR/2019/4379 4379 Checking and Pouring concrete for raft Utility duct Km 207+220 RHS 19-Sep-19 9:30 AM DONE
4444 NMSCEW/P-IV/STR/2019/4380 4380 Checking of Shuttering and reinforcement for 1st lift at wall A1 & A2 PUP Km 165+790 LHS 19-Sep-19 10:15 AM IPC-08 DONE
4445 NMSCEW/P-IV/STR/2019/4381 4381 Checking and Pouring concrete for 1st lift at wall A1 & A2 PUP Km 165+790 LHS 19-Sep-19 10:45 AM IPC-08 DONE
4446 NMSCEW/P-IV/STR/2019/4382 4382 Checking of Shuttering and reinforcement for 2nd lift at retaing wall A1 & A2 PUP Km 165+300 RHS 19-Sep-19 4:30 PM DONE
4447 NMSCEW/P-IV/STR/2019/4383 4383 Checking and Pouring concrete for 2nd lift at retaing wall A1 & A2 PUP Km 165+300 RHS 19-Sep-19 5:00 PM DONE
4448 NMSCEW/P-IV/STR/2019/4384 4384 Checking top Level & Laying concrete for PCC at retaining wall A1 & A2 PUP Km 165+300 LHS 19-Sep-19 12:30 PM NR
4449 NMSCEW/P-IV/STR/2019/4385 4385 Checking of Shuttering and reinforcement for 4th lift at retaing wall A1 & A2 PUP Km 172+190 RHS 19-Sep-19 2:00 PM NR
4450 NMSCEW/P-IV/STR/2019/4386 4386 Checking and Pouring concrete for 4th lift at retaining wall A1 & A2 PUP Km 172+190 RHS 19-Sep-19 2:30 PM NR
4451 NMSCEW/P-IV/STR/2019/4387 4387 Checking of reinforcement, shuttering for 3rd lift at median wall PUP Km 171+110 19-Sep-19 11:00 AM NR
4452 NMSCEW/P-IV/STR/2019/4388 4388 Checking & Pouring concrete for 3rd lift at median wall PUP Km 171+110 19-Sep-19 11:36 AM NR
Checking reinforcement for precast Box Culvert (3x3) (Cushion 2 to 4 m) at precast yard camp
4453 NMSCEW/P-IV/STR/2019/4389 4389 Box culvert Km 175+500 LHS 19-Sep-19 9:15 AM IPC-08 199,200, 201, 202, 203
-1. Segment NO-199,200,201,202,203 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4454 NMSCEW/P-IV/STR/2019/4390 4390 Box culvert Km 175+500 LHS 19-Sep-19 10:20 AM IPC-08 199,200, 201, 202, 203
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.-199,200,201,202,203
DONE AE
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
4455 NMSCEW/P-IV/STR/2019/4391 4391 Box culvert Km 175+500 LHS 19-Sep-19 10:40 AM DONE
-1. Segment NO-200,201,202
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4456 NMSCEW/P-IV/STR/2019/4392 4392 Box culvert Km 175+500 LHS 19-Sep-19 12:12 PM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-200,201,202
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4457 NMSCEW/P-IV/STR/2019/4393 4393 Box culvert Km 175+500 LHS 19-Sep-19 3:30 PM DONE
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-235,236,237,238
4458 NMSCEW/P-IV/STR/2019/4394 4394 Checking layout ,level for excavated bed PCC Utility duct Km 180+300 BHS 19-Sep-19 9:05 AM DONE
4459 NMSCEW/P-IV/STR/2019/4395 4395 Checking top Level & Laying concrete(M-10) for excavated bed PCC Utility duct Km 180+300 BHS 19-Sep-19 9:42 AM DONE
4460 NMSCEW/P-IV/STR/2019/4396 4396 Checking layout ,level for PCC at retaining wall W1 & W2 PUP Km 191+740 RHS 19-Sep-19 8:00 AM DONE
4461 NMSCEW/P-IV/STR/2019/4397 4397 Checking top Level & Laying concrete for PCC at retaining wall W1 & W2 PUP Km 191+740 RHS 19-Sep-19 8:32 AM DONE
4462 NMSCEW/P-IV/STR/2019/4398 4398 Checking layout ,level for PCC at retaining wall W1 & W2 PUP Km 199+060 LHS 19-Sep-19 9:06 AM DONE
4463 NMSCEW/P-IV/STR/2019/4399 4399 Checking top Level & Laying concrete for PCC at retaining wall W1 & W2 PUP Km 199+060 LHS 19-Sep-19 9:35 AM DONE
4464 NMSCEW/P-IV/STR/2019/4400 4400 Checking layout ,level for PCC at U type median wall PUP Km 199+060 19-Sep-19 11:11 AM DONE
4465 NMSCEW/P-IV/STR/2019/4401 4401 Checking top Level & Laying concrete for PCC at U type median wall PUP Km 199+060 19-Sep-19 11:44 AM DONE
4466 NMSCEW/P-IV/STR/2019/4402 4402 Checking layout ,level for raft Box culvert Km 201+280 Km 00+000 LHS 19-Sep-19 8:10 AM IPC-11 Approved
4467 NMSCEW/P-IV/STR/2019/4403 4403 Checking of Shuttering and reinforcement for raft Box culvert Km 201+280 Km 00+000 LHS 19-Sep-19 8:40 AM IPC-11 Approved AE
4468 NMSCEW/P-IV/STR/2019/4404 4404 Checking and Pouring concrete for raft Box culvert Km 201+280 Km 00+000 LHS 19-Sep-19 9:12 AM IPC-11 Approved AE
4469 NMSCEW/P-IV/STR/2019/4405 4405 Checking of Shuttering and reinforcement for bottom slab at Loop-B MNB Km 01+980 19-Sep-19 8:16 AM DONE
4470 NMSCEW/P-IV/STR/2019/4406 4406 Checking and Pouring concrete( M-35) for bottom slab at Loop-B MNB Km 01+980 19-Sep-19 8:50 AM DONE
4471 NMSCEW/P-IV/STR/2019/4407 4407 Checking errection of 2*2 utility duct Utility duct Km 177+300 BHS 19-Sep-19 9:55 AM IPC-08 DONE
4472 NMSCEW/P-IV/STR/2019/4408 4408 Checking of side shuttering girder no-17,18,19,20 at bed no-05,Girder Type-1 Girder Km 200+200 LHS 19-Sep-19 8:06 AM
Approval for pouring of girder no- 17,18,19,20 at bed no-05 (Grade of concrete M-50)
4473 NMSCEW/P-IV/STR/2019/4409 4409 Girder Km 200+200 LHS 19-Sep-19 8:21 AM
Girder Type- 1
4474 NMSCEW/P-IV/STR/2019/4410 4410 Checking layout ,level for pier shaft starter at LP-04 Viaduct Km 200+920 LHS 19-Sep-19 3:32 PM
4475 NMSCEW/P-IV/STR/2019/4411 4411 Checking and Pouring concrete for pier shaft starter at LP-04 Viaduct Km 200+920 LHS 19-Sep-19 4:13 PM
4476 NMSCEW/P-IV/STR/2019/4412 4412 Checking of reinforcement and shuttering for pier shaft final lift at RP-04 Viaduct Km 202+190 Km 00+000 RHS 19-Sep-19 2:00 PM IPC-10 DONE
4477 NMSCEW/P-IV/STR/2019/4413 4413 Checking and Pouring concrete for pier shaft final lift at RP-04 Viaduct Km 202+190 RHS 19-Sep-19 2:39 PM
4478 NMSCEW/P-IV/STR/2019/4414 4414 Checking of reinforcement, shuttering for pier cap at LP-02 Viaduct Km 202+190 LHS 19-Sep-19 3:02 PM IPC-08 DONE AE
4479 NMSCEW/P-IV/STR/2019/4415 4415 Checking & pouring concrete for pier cap at LP-02 Viaduct Km 202+190 LHS 19-Sep-19 3:39 PM IPC-08 DONE AE
Checking for stressing and remove slagness of H.T. wires at Girder no 29,30,31,32 at bed no
4480 NMSCEW/P-IV/STR/2019/4416 4416 Girder Km 200+200 LHS 19-Sep-19 4:23 PM
-3, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no 29,30,31,32 at bed no -3 ,Girder Type-2 at casting yard
4481 NMSCEW/P-IV/STR/2019/4417 4417 Girder Km 200+200 LHS 19-Sep-19 5:25 PM
camp -2
4482 NMSCEW/P-IV/STR/2019/4418 4418 Checking of Shuttering and reinforcement for bottom slab Box culvert Km 187+677 RHS 19-Sep-19 3:21 PM NR
4483 NMSCEW/P-IV/STR/2019/4419 4419 Checking and Pouring concrete( M-30) for bottom slab Box culvert Km 187+677 RHS 19-Sep-19 3:55 PM NR
4484 NMSCEW/P-IV/STR/2019/4420 4420 Checking layout ,level and structural excavation for PCC at wall A1 PUP Km 187+835 RHS 19-Sep-19 9:11 AM NR
4485 NMSCEW/P-IV/STR/2019/4421 4421 Checking top Level & Laying concrete for PCC at wall A1 PUP Km 187+835 RHS 19-Sep-19 9:49 AM NR
Checking for stressing and remove slagness of H.T. wires at Girder no 21,22,23,24 at bed no
4486 NMSCEW/P-IV/STR/2019/4422 4422 Girder Km 200+200 LHS 20-Sep-19 2:30 PM
-6, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no 21,22,23,24 at bed no -6, Girder Type-1 at casting yard
4487 NMSCEW/P-IV/STR/2019/4423 4423 Girder Km 200+200 LHS 20-Sep-19 2:45 PM
camp -2
4488 NMSCEW/P-IV/STR/2019/4424 4424 Checking of reinforcement and shuttering for pier shaft final lift at LP-06 Viaduct Km 195+900 LHS 20-Sep-19 4:00 PM
4489 NMSCEW/P-IV/STR/2019/4425 4425 Checking and Pouring concrete for pier shaft final lift at LP-06 Viaduct Km 195+900 LHS 20-Sep-19 4:30 PM
4490 NMSCEW/P-IV/STR/2019/4426 4426 Checking of reinforcement and shuttering for pier shaft final lift at RP-03 Viaduct Km 196+560 Km 00+000 RHS 20-Sep-19 9:30 AM IPC-10 DONE
4491 NMSCEW/P-IV/STR/2019/4427 4427 Checking and Pouring concrete for pier shaft final lift at RP-03 Viaduct Km 196+560 Km 00+000 RHS 20-Sep-19 10:00 AM IPC-10 DONE
4492 NMSCEW/P-IV/STR/2019/4428 4428 Checking of reinforcement and shuttering for pier shaft 1st lift at RP-01 Viaduct Km 196+560 RHS 20-Sep-19 11:10 AM
4493 NMSCEW/P-IV/STR/2019/4429 4429 Checking and Pouring concrete for pier shaft 1st lift at RP-01 Viaduct Km 196+560 RHS 20-Sep-19 11:30 AM
4494 NMSCEW/P-IV/STR/2019/4430 4430 Checking of reinforcement and shuttering for pier shaft final lift at RA-02 Viaduct Km 196+560 RHS 20-Sep-19 2:30 PM
4495 NMSCEW/P-IV/STR/2019/4431 4431 Checking and Pouring concrete for pier shaft final lift at RA-02 Viaduct Km 196+560 RHS 20-Sep-19 3:00 PM
4496 NMSCEW/P-IV/STR/2019/4432 4432 Checking of reinforcement and shuttering and layout for pier shaft final lift at LP7 Viaduct Km 202+190 LHS 20-Sep-19 2:00 PM IPC-08 DONE
4497 NMSCEW/P-IV/STR/2019/4433 4433 Checking and Pouring concrete for pier shaft final lift at LP7 Viaduct Km 202+190 LHS 20-Sep-19 3:15 PM IPC-08 DONE
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
4498 NMSCEW/P-IV/STR/2019/4434 4434 Box culvert Km 175+500 LHS 20-Sep-19 9:17 AM DONE
-1. Segment NO-203,204,205
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4499 NMSCEW/P-IV/STR/2019/4435 4435 Box culvert Km 175+500 LHS 20-Sep-19 10:22 AM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-203,204,205
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
4500 NMSCEW/P-IV/STR/2019/4436 4436 Box culvert Km 175+500 LHS 20-Sep-19 10:44 AM DONE
-1. Segment NO-243,244,245,246
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4501 NMSCEW/P-IV/STR/2019/4437 4437 Box culvert Km 175+500 LHS 20-Sep-19 12:12 PM DONE
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-243,244,245,246
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4502 NMSCEW/P-IV/STR/2019/4438 4438 Box culvert Km 175+500 LHS 20-Sep-19 3:35 PM IPC-08 184, 196,
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.-184,185,196,197,198
DONE
4503 NMSCEW/P-IV/STR/2019/4439 4439 Checking layout ,level for PCC at RA-02 MJB 205+610 Km 00+000 RHS 20-Sep-19 4:15 PM IPC-09 DONE
4504 NMSCEW/P-IV/STR/2019/4440 4440 Checking of completion of segment errection for 2x2 utility duct Utility duct Km 204+700 BHS 20-Sep-19 12:00 PM IPC-08 DONE
4505 NMSCEW/P-IV/STR/2019/4441 4441 Checking of reinforcement and shuttering for pier shaft 1st lift at LP-10 Viaduct Km 202+190 LHS 20-Sep-19 12:15 PM
4506 NMSCEW/P-IV/STR/2019/4442 4442 Checking and Pouring concrete for pier shaft 1st lift at LP-10 Viaduct Km 202+190 LHS 20-Sep-19 3:45 PM
4507 NMSCEW/P-IV/STR/2019/4443 4443 Checking and Pouring concrete for pier shaft 1st lift at LP-08 Viaduct Km 202+190 LHS 20-Sep-19 2:40 PM
4508 NMSCEW/P-IV/STR/2019/4444 4444 Checking of Shuttering and reinforcement for raft at retaining wall W1 PUP Km 205+430 LHS 20-Sep-19 9:00 AM DONE
4509 NMSCEW/P-IV/STR/2019/4445 4445 Checking and Pouring concrete for raft at retaining wall W1 PUP Km 205+430 LHS 20-Sep-19 9:30 AM DONE
4510 NMSCEW/P-IV/STR/2019/4446 4446 Checking of Shuttering and reinforcement for 3rd lift at U- type retaining wall W1 PUP Km 204+470 20-Sep-19 8:00 AM DONE
4511 NMSCEW/P-IV/STR/2019/4447 4447 Checking and Pouring concrete for 3rd lift at U- type retaining wall W1 PUP Km 204+470 20-Sep-19 8:30 AM DONE
4512 NMSCEW/P-IV/STR/2019/4448 4448 Checking layout ,level for PCC at retaining wall W1 PUP Km 203+560 LHS 20-Sep-19 8:15 AM DONE
4513 NMSCEW/P-IV/STR/2019/4449 4449 Checking top Level & Laying concrete for PCC at retaining wall W1 PUP Km 203+560 LHS 20-Sep-19 8:45 AM DONE
4514 NMSCEW/P-IV/STR/2019/4450 4450 Checking of Shuttering and reinforcement for bottom slab Box culvert Km 187+677 Km 00+000 RHS 20-Sep-19 7:00 AM IPC-09 DONE
4515 NMSCEW/P-IV/STR/2019/4451 4451 Checking and Pouring concrete( M-30) for bottom slab Box culvert Km 187+677 Km 00+000 RHS 20-Sep-19 7:30 AM IPC-09 DONE
4516 NMSCEW/P-IV/STR/2019/4452 4452 Checking layout ,level and structural excavation for PCC at wall A1 PUP Km 187+835 RHS 20-Sep-19 11:15 AM NR
4517 NMSCEW/P-IV/STR/2019/4453 4453 Checking top Level & Laying concrete for PCC at wall A1 PUP Km 187+835 RHS 20-Sep-19 11:45 AM NR
4518 NMSCEW/P-IV/STR/2019/4454 4454 Checking of Shuttering and reinforcement for raft at retaining wall A2 PUP Km 183+290 RHS 20-Sep-19 9:20 AM NR
4519 NMSCEW/P-IV/STR/2019/4455 4455 Checking and Pouring concrete(M-30) for raft at retaining wall A2 PUP Km 183+290 RHS 20-Sep-19 9:47 AM NR
4520 NMSCEW/P-IV/STR/2019/4456 4456 Checking of Shuttering and reinforcement for 1st lift at wall A1 & A2 Box culvert Km 182+350 LHS 20-Sep-19 11:25 AM IPC-08 DONE AE
4521 NMSCEW/P-IV/STR/2019/4457 4457 Checking and Pouring concrete for 1st lift at wall A1 & A2 Box culvert Km 182+350 LHS 20-Sep-19 11:55 AM IPC-08 DONE AE
4522 NMSCEW/P-IV/STR/2019/4458 4458 Checking reinforcement ,shuttering for bottom slab of loop-C MNB loop-C Km 01+980 20-Sep-19 4:15 PM NR
4523 NMSCEW/P-IV/STR/2019/4459 4459 Checking and concrete (M35) pouring for bottom slab of loop-C MNB loop-C Km 01+980 20-Sep-19 5:10 PM NR
4524 NMSCEW/P-IV/STR/2019/4460 4460 Checking layout ,level for PCC at RP-08 Viaduct Km 202+190 RHS 20-Sep-19 11:05 AM
4525 NMSCEW/P-IV/STR/2019/4461 4461 Checking top Level & Laying concrete for PCC at RP-08 Viaduct Km 202+190 RHS 20-Sep-19 11:37 AM
4526 NMSCEW/P-IV/STR/2019/4462 4462 Checking of reinforcement and shuttering for pier shaft 1st & final lift at LA-02 Viaduct Km 169+800 Km 00+000 LHS 20-Sep-19 2:17 PM IPC-09 DONE MNB
4527 NMSCEW/P-IV/STR/2019/4463 4463 Checking and Pouring concrete for pier shaft 1st & final lift at LA-02 Viaduct Km 169+800 Km 00+000 LHS 20-Sep-19 2:50 PM IPC-09 DONE MNB
Checking of Shuttering and reinforcement for raft with bottom haunch A1 & A2 at median
4528 NMSCEW/P-IV/STR/2019/4464 4464 PUP Km 165+300 21-Sep-19 3:00 PM DONE
walll
4529 NMSCEW/P-IV/STR/2019/4465 4465 Checking and Pouring concrete for raft with bottom haunch A1 & A2 at median walll PUP Km 165+300 21-Sep-19 3:20 PM NR
Checking of Shuttering and reinforcement for raft with bottom haunch A1 & A2 at median
4530 NMSCEW/P-IV/STR/2019/4466 4466 LVUP Km 173+400 BHS 21-Sep-19 3:30 PM DONE
walll
4531 NMSCEW/P-IV/STR/2019/4467 4467 Checking and Pouring concrete for raft with bottom haunch A1 & A2 at median walll LVUP Km 173+400 BHS 21-Sep-19 3:50 PM DONE
4532 NMSCEW/P-IV/STR/2019/4468 4468 Checking of Shuttering and reinforcement for raft at wall A2 PUP Km 174+095 RHS 21-Sep-19 4:30 PM DONE
4533 NMSCEW/P-IV/STR/2019/4469 4469 Checking and Pouring concrete for raft for raft at wall A2 PUP Km 174+095 RHS 21-Sep-19 5:00 PM DONE
4534 NMSCEW/P-IV/STR/2019/4470 4470 Checking of Shuttering and reinforcement for raft with bottom haunch at A1 & A2 walll VUP Km 166+987 RHS 21-Sep-19 4:45 PM DONE
4535 NMSCEW/P-IV/STR/2019/4471 4471 Checking and Pouring concrete for raft with bottom haunch at A1 & A2 walll VUP Km 166+987 RHS 21-Sep-19 5:15 PM NR
4536 NMSCEW/P-IV/STR/2019/4472 4472 Checking errection of 3*3 box culvert Box culvert Km 178+014 BHS 21-Sep-19 9:30 AM IPC-08 DONE
Checking reinforcement for precast Box Culvert (3x3) (Cushion 2 to 4 m) at precast yard camp
4537 NMSCEW/P-IV/STR/2019/4473 4473 Box culvert Km 175+500 LHS 21-Sep-19 9:23 AM IPC-08 204, 205, 206, 207, 208
-1. Segment NO- 204, 205, 206, 207, 208 DONE AE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4538 NMSCEW/P-IV/STR/2019/4474 4474 Box culvert Km 175+500 LHS 21-Sep-19 12:27 PM IPC-08 204, 205, 206, 207
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.- 204, 205, 206, 207, 208
DONE AE
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
4539 NMSCEW/P-IV/STR/2019/4475 4475 Box culvert Km 175+500 LHS 21-Sep-19 12:49 PM DONE
-1. Segment NO-206,207,208
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4540 NMSCEW/P-IV/STR/2019/4476 4476 Box culvert Km 175+500 LHS 21-Sep-19 12:52 PM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-206,207,208
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
4541 NMSCEW/P-IV/STR/2019/4477 4477 Box culvert Km 175+500 LHS 21-Sep-19 4:16 PM DONE
-1. Segment NO-247, 248, 249, 250
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4542 NMSCEW/P-IV/STR/2019/4478 4478 Box culvert Km 175+500 LHS 21-Sep-19 5:21 PM DONE
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-247, 248, 249, 250
4543 NMSCEW/P-IV/STR/2019/4479 4479 Checking of side shuttering girder no-29,30,31,32 at bed no-03,Girder Type-2 Girder Km 200+200 LHS 21-Sep-19 4:00 PM
Approval for pouring of girder no- 29,30,31,32 at bed no-03 (Grade of concrete M-50)
4544 NMSCEW/P-IV/STR/2019/4480 4480 Girder Km 200+200 LHS 21-Sep-19 4:40 PM
Girder Type- 2
4545 NMSCEW/P-IV/STR/2019/4481 4481 Checking of reinforcement, shuttering for pier cap at RP-08 Viaduct Km 169+800 RHS 21-Sep-19 2:00 PM IPC-08 DONE AE
4546 NMSCEW/P-IV/STR/2019/4482 4482 Checking & pouring concrete for pier cap at RP-08 Viaduct Km 169+800 RHS 21-Sep-19 2:30 PM IPC-08 DONE AE
4547 NMSCEW/P-IV/STR/2019/4483 4483 Checking of reinforcement, shuttering for pier cap at RP-10 Viaduct Km 169+800 RHS 21-Sep-19 3:10 PM IPC-08 DONE
4548 NMSCEW/P-IV/STR/2019/4484 4484 Checking & pouring concrete for pier cap at RP-10 Viaduct Km 169+800 RHS 21-Sep-19 3:40 PM IPC-08 DONE
4549 NMSCEW/P-IV/STR/2019/4485 4485 Checking of reinforcement, shuttering for U trough bottom slab PUP Km 187+835 21-Sep-19 12:00 PM NR
4550 NMSCEW/P-IV/STR/2019/4486 4486 Checking & pouring concrete(M-30) for U trough bottom slab PUP Km 187+835 21-Sep-19 12:30 PM NR
4551 NMSCEW/P-IV/STR/2019/4487 4487 Checking of Shuttering and reinforcement for raft at RA-02 Viaduct Km 202+190 RHS 21-Sep-19 4:00 PM
4552 NMSCEW/P-IV/STR/2019/4488 4488 Checking and Pouring concrete(M-30) for raft at at RA-02 Viaduct Km 202+190 RHS 21-Sep-19 4:30 PM
4553 NMSCEW/P-IV/STR/2019/4489 4489 Checking of reinforcement, shuttering at retaining wall A2 footing PUP Km 183+290 RHS 21-Sep-19 9:05 AM NR
4554 NMSCEW/P-IV/STR/2019/4490 4490 Checking & Pouring concrete(M-30) at retaining wall A2 footing PUP Km 183+290 RHS 21-Sep-19 9:32 AM NR
4555 NMSCEW/P-IV/STR/2019/4491 4491 Checking reinforcement ,shuttering for bottom slab of loop-C MNB loop-C Km 01+980 21-Sep-19 4:06 PM NR
4556 NMSCEW/P-IV/STR/2019/4492 4492 Checking and concrete (M35) pouring for bottom slab of loop-C MNB loop-C Km 01+980 21-Sep-19 4:43 PM NR
4557 NMSCEW/P-IV/STR/2019/4493 4493 Checking layout ,level for PCC Utility duct Km 180+800 BHS 21-Sep-19 10:05 AM REPEATED
4558 NMSCEW/P-IV/STR/2019/4494 4494 Checking top Level & Laying concrete(M-10) for PCC Utility duct Km 180+800 BHS 21-Sep-19 10:25 AM DONE
4559 NMSCEW/P-IV/STR/2019/4495 4495 Checking layout ,level for PCC at RP-08 Viaduct Km 202+190 RHS 22-Sep-19 10:00 AM
4560 NMSCEW/P-IV/STR/2019/4496 4496 Checking top Level & Laying concrete for PCC at RP-08 Viaduct Km 202+190 RHS 22-Sep-19 10:30 AM
4561 NMSCEW/P-IV/STR/2019/4497 4497 Checking of reinforcement and shuttering for abuttment shaft 2nd lift at LA-01 Viaduct Km 169+800 LHS 22-Sep-19 9:00 AM NR
4562 NMSCEW/P-IV/STR/2019/4498 4498 Checking and Pouring concrete for abuttment shaft 2nd lift at LA-01 Viaduct Km 169+800 LHS 22-Sep-19 10:15 AM NR
4563 NMSCEW/P-IV/STR/2019/4499 4499 Checking of reinforcement and shuttering for Pier shaft final lift at RA-2 Viaduct Km 196+560 Km 00+000 RHS 22-Sep-19 11:00 AM IPC-09 DONE AE
4564 NMSCEW/P-IV/STR/2019/4500 4500 Checking and Pouring concrete for Pier shaft final lift at RA-2 Viaduct Km 196+560 Km 00+000 RHS 22-Sep-19 11:20 AM IPC-09 DONE AE
4565 NMSCEW/P-IV/STR/2019/4501 4501 Checking layout ,level for pier shaft starter at RP-02 Viaduct Km 200+920 RHS 22-Sep-19 10:10 AM
4566 NMSCEW/P-IV/STR/2019/4502 4502 Checking and Pouring concrete for pier shaft starter at RP-02 Viaduct Km 200+920 RHS 22-Sep-19 10:45 AM
4567 NMSCEW/P-IV/STR/2019/4503 4503 Checking layout ,level for pier shaft starter at LP-04 Viaduct Km 200+920 LHS 22-Sep-19 9:15 AM
4568 NMSCEW/P-IV/STR/2019/4504 4504 Checking and Pouring concrete for pier shaft starter at LP-04 Viaduct Km 200+920 LHS 22-Sep-19 9:45 AM
4569 NMSCEW/P-IV/STR/2019/4505 4505 Checking of Shuttering and reinforcement for wall 4th lift A1 & A2 VUP Km 179+983 LHS 23-Sep-19 11:30 AM
4570 NMSCEW/P-IV/STR/2019/4506 4506 Checking and Pouring concrete for wall 4th lift A1 & A2 VUP Km 179+983 LHS 23-Sep-19 12:40 PM
4571 NMSCEW/P-IV/STR/2019/4507 4507 Checking layout ,level for PCC at RP-02 Viaduct Km 213+915 RHS 23-Sep-19 2:10 PM
4572 NMSCEW/P-IV/STR/2019/4508 4508 Checking top Level & Laying concrete for PCC at RP-02 Viaduct Km 213+915 RHS 23-Sep-19 3:00 PM
4573 NMSCEW/P-IV/STR/2019/4509 4509 Checking layout ,level for PCC at LP-02 Viaduct Km 213+915 LHS 23-Sep-19 3:10 PM
4574 NMSCEW/P-IV/STR/2019/4510 4510 Checking top Level & Laying concrete for PCC at LP-02 Viaduct Km 213+915 LHS 23-Sep-19 4:00 PM
4575 NMSCEW/P-IV/STR/2019/4511 4511 Checking of side shuttering of girder no-21,22,23 & 24 at bed no-07,Girder Type- 1 Girder Km 200+200 LHS 23-Sep-19 4:00 PM
Approval for pouring of girder no- 21,22,23 & 24 at bed no-07 (Grade of concrete M-50)
4576 NMSCEW/P-IV/STR/2019/4512 4512 Girder Km 200+200 LHS 23-Sep-19 4:30 PM
Girder Type- 1
4577 NMSCEW/P-IV/STR/2019/4513 4513 Checking of reinforcement , shuttering & pouring of concrete for LP-10 pier shaft 1st lift Viaduct Km 202+190 Km 00+000 LHS 23-Sep-19 12:30 PM IPC-10 DONE
AE
4578 NMSCEW/P-IV/STR/2019/4514 4514 Checking & pouring concrete for RP-4 pier shaft final lift Viaduct Km 202+190 Km 00+000 RHS 23-Sep-19 2:00 PM IPC-10 DONE AE
4579 NMSCEW/P-IV/STR/2019/4515 4515 Checking of Shuttering and reinforcement for RA-2 raft Viaduct Km 202+190 RHS 23-Sep-19 3:00 PM IPC-08 DONE AE
4580 NMSCEW/P-IV/STR/2019/4516 4516 Checking & pouring concrete for RA-2 raft Viaduct Km 202+190 RHS 23-Sep-19 3:30 PM
4581 NMSCEW/P-IV/STR/2019/4517 4517 Checking of Shuttering and reinforcement for LP-4 pier shaft final lift Viaduct Km 196+560 LHS 23-Sep-19 12:30 PM
4582 NMSCEW/P-IV/STR/2019/4518 4518 Checking & pouring concrete for LP-4 pier shaft final lift Viaduct Km 196+560 LHS 23-Sep-19 12:45 PM
4583 NMSCEW/P-IV/STR/2019/4519 4519 Checking of Shuttering and reinforcement for RP-2 pier shaft 1st & final lift Viaduct Km 196+560 LHS 23-Sep-19 3:20 PM
4584 NMSCEW/P-IV/STR/2019/4520 4520 Checking & pouring concrete for RP-2 pier shaft 1st & final lift Viaduct Km 196+560 LHS 23-Sep-19 3:40 PM
4585 NMSCEW/P-IV/STR/2019/4521 4521 Checking of Shuttering and reinforcement for LP-5 pier shaft 1st lift Viaduct Km 200+920 LHS 23-Sep-19 4:00 PM
4586 NMSCEW/P-IV/STR/2019/4522 4522 Checking & pouring concrete for LP-5 pier shaft 1st lift Viaduct Km 200+920 LHS 23-Sep-19 4:30 PM
4587 NMSCEW/P-IV/STR/2019/4523 4523 Checking of Shuttering and reinforcement for LA-1abutment shaft 2nd lift Viaduct Km 169+800 LHS 23-Sep-19 9:00 AM DONE
4588 NMSCEW/P-IV/STR/2019/4524 4524 Checking & pouring concrete for LA-1 abutment shaft 2nd lift Viaduct Km 169+800 LHS 23-Sep-19 10:00 AM DONE
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
4589 NMSCEW/P-IV/STR/2019/4525 4525 Box culvert Km 200+200 LHS 23-Sep-19 10:10 AM DONE
-2. Segment NO-427,428,429,430,431,432,433,434,435
Checking reinforcement for precast Box Culvert (3x3) (cushion 0 to 2m) at precast yard camp
4590 NMSCEW/P-IV/STR/2019/4526 4526 Box culvert Km 200+200 LHS 23-Sep-19 10:20 AM DONE
-2. Segment NO-150,151
Checking reinforcement for precast Box Culvert (3x3) (cushion 2 to 4m) at precast yard camp
4591 NMSCEW/P-IV/STR/2019/4527 4527 Box culvert Km 200+200 LHS 23-Sep-19 10:30 AM DONE
-2. Segment NO-45,46
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4592 NMSCEW/P-IV/STR/2019/4528 4528 (2×2),(Cushion 2 to 4m) at precast yard camp-2,Segment no.- Box culvert Km 200+200 LHS 23-Sep-19 11:00 AM DONE
427,428,429,430,431,432,433,434,435
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4593 NMSCEW/P-IV/STR/2019/4529 4529 Box culvert Km 200+200 LHS 23-Sep-19 11:20 AM DONE
(3×3),(Cushion 0 to 2m) at precast yard camp-2,Segment no.-150,151
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4594 NMSCEW/P-IV/STR/2019/4530 4530 Box culvert Km 200+200 LHS 23-Sep-19 11:30 AM DONE
(3×3),(Cushion 2 to 4m) at precast yard camp-2,Segment no.-45,46
4595 NMSCEW/P-IV/STR/2019/4531 4531 Checking of side shuttering of girder no-29,30,31 & 32 at bed no-03,Girder Type- 02 Girder Km 200+200 LHS 23-Sep-19 2:00 PM
Approval for pouring of girder no- 29,30,31 & 32 at bed no-03 (Grade of concrete M-50)
4596 NMSCEW/P-IV/STR/2019/4532 4532 Girder Km 200+200 LHS 23-Sep-19 2:30 PM
Girder Type- 02
Checking for stressing and remove slagness of H.T. wires at Girder no-33,34,35 & 36 at bed
4597 NMSCEW/P-IV/STR/2019/4533 4533 Girder Type-2 Km 200+200 LHS 23-Sep-19 4:00 PM
no -1 at casting yard camp -2
4598 NMSCEW/P-IV/STR/2019/4534 4534 Checking of reinforcement for bed no-1 & Girder no-33,34,35 & 36 Girder Type-2 Km 200+200 LHS 23-Sep-19 4:30 PM
4599 NMSCEW/P-IV/STR/2019/4535 4535 Checking and Pouring of concrete for raft with bottom haunch VUP Km 166+987 RHS 23-Sep-19 8:00 AM DONE
4600 NMSCEW/P-IV/STR/2019/4536 4536 Checking and Pouring of concrete for median wall raft PUP Km 165+300 BHS 23-Sep-19 3:00 PM DONE
4601 NMSCEW/P-IV/STR/2019/4537 4537 Checking of Shuttering and reinforcement for 2nd lift wall A1 side PUP Km 165+790 LHS 23-Sep-19 4:00 PM NR
4602 NMSCEW/P-IV/STR/2019/4538 4538 Checking and Pouring concrete for 2nd lift wall A1 side PUP Km 165+790 LHS 23-Sep-19 4:30 PM NR
Checking reinforcement for precast Box Culvert (3x3) (cushion 2 to 4m) at precast yard camp
4603 NMSCEW/P-IV/STR/2019/4539 4539 Box culvert Km 175+500 LHS 23-Sep-19 10:10 AM IPC-08 209, 210
-1. Segment NO-209,210 DONE
Checking reinforcement for precast Box Culvert (2x2) (cushion 2 to 4m) at precast yard camp
4604 NMSCEW/P-IV/STR/2019/4540 4540 Box culvert Km 175+500 LHS 23-Sep-19 10:20 AM DONE SPOT RFI
-1. Segment NO-209
Checking reinforcement for precast Box Culvert (2x2) (cushion 0 to 2m) at precast yard camp
4605 NMSCEW/P-IV/STR/2019/4541 4541 Box culvert Km 175+500 LHS 23-Sep-19 10:30 AM DONE SPOT RFI
-1. Segment NO-251
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4606 NMSCEW/P-IV/STR/2019/4542 4542 Box culvert Km 175+500 LHS 23-Sep-19 11:00 AM IPC-08 197, 198, 208, 209, 210
(3×3),(Cushion 2 to 4m) at precast yard camp-1,Segment no.-197,198,208,209,210
DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4607 NMSCEW/P-IV/STR/2019/4543 4543 Box culvert Km 175+500 LHS 23-Sep-19 11:20 AM DONE SPOT RFI
(2×2),(Cushion 2 to 4m) at precast yard camp-1,Segment no.-204,205,209
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4608 NMSCEW/P-IV/STR/2019/4544 4544 Box culvert Km 175+500 LHS 23-Sep-19 11:30 AM DONE SPOT RFI
(2×2),(Cushion 0 to 2m) at precast yard camp-1,Segment no.-244,245,246,251
Checking reinforcement for precast Box Culvert (3x3)(cushion 2 to 4m) at precast yard camp
4609 NMSCEW/P-IV/STR/2019/4545 4545 Box culvert Km 175+500 LHS 24-Sep-19 10:00 AM IPC-08 211,212, 213, 214, 214
-1. Segment NO-211,212,213,214,215 DONE
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
4610 NMSCEW/P-IV/STR/2019/4546 4546 Box culvert Km 175+500 LHS 24-Sep-19 10:10 AM DONE
-1. Segment NO-210,211,212
Checking reinforcement for precast Box Culvert (2x2)(cushion 0 to 2m) at precast yard camp
4611 NMSCEW/P-IV/STR/2019/4547 4547 Box culvert Km 175+500 LHS 24-Sep-19 10:20 AM DONE
-1. Segment NO-252,253,254,255
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4612 NMSCEW/P-IV/STR/2019/4548 4548 Box culvert Km 175+500 LHS 24-Sep-19 10:30 AM IPC-08 211,212, 213, 214, 215
(3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-211,212,213,214,215
DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4613 NMSCEW/P-IV/STR/2019/4549 4549 Box culvert Km 175+500 LHS 24-Sep-19 10:40 AM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-210,211,212
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4614 NMSCEW/P-IV/STR/2019/4550 4550 Box culvert Km 175+500 LHS 24-Sep-19 10:50 AM
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-252,253,254,255 NR
4615 NMSCEW/P-IV/STR/2019/4551 4551 Checking of reinforcement, shuttering for raft at retaining wall A2 Retaining wall Km 174+095 RHS 24-Sep-19 2:00 PM DONE
4616 NMSCEW/P-IV/STR/2019/4552 4552 Checking & Pouring concrete for raft at retaining wall A2 Retaining wall Km 174+095 RHS 24-Sep-19 2:20 PM DONE
4617 NMSCEW/P-IV/STR/2019/4553 4553 Checking reinforcement ,shuttering for bottom slab of loop-C MNB loop-C Km 01+980 24-Sep-19 9:10 AM NR
4618 NMSCEW/P-IV/STR/2019/4554 4554 Checking and concrete (M30) pouring for bottom slab of loop-C MNB loop-C Km 01+980 24-Sep-19 9:30 AM NR
4619 NMSCEW/P-IV/STR/2019/4555 4555 Checking of Shuttering and reinforcement for U-type retaining wall at W1 & W2 1st lift PUP Km 203+560 24-Sep-19 8:00 AM DONE
4620 NMSCEW/P-IV/STR/2019/4556 4556 Checking and Pouring concrete for U-type retaining wall at W1 & W2 1st lift PUP Km 203+560 24-Sep-19 8:30 AM DONE
4621 NMSCEW/P-IV/STR/2019/4557 4557 Checking of reinforcement, shuttering for retaining wall at W1 & W2 2nd lift PUP Km 203+560 RHS 24-Sep-19 10:00 AM DONE
4622 NMSCEW/P-IV/STR/2019/4558 4558 Checking & Pouring concrete for raft at retaining wall at W1 & W2 2nd lift PUP Km 203+560 RHS 24-Sep-19 10:30 AM DONE
4623 NMSCEW/P-IV/STR/2019/4559 4559 Checking of Shuttering and reinforcement for wall 1st lift MNB Km 199+360 LHS 24-Sep-19 10:00 AM IPC-08 DONE
4624 NMSCEW/P-IV/STR/2019/4560 4560 Checking and Pouring concrete for wall 1st lift MNB Km 199+360 LHS 24-Sep-19 10:30 AM IPC-08 DONE
4625 NMSCEW/P-IV/STR/2019/4561 4561 Checking of level, reinforcement and shuttering for RA-1 raft Viaduct Km 200+920 RHS 24-Sep-19 4:00 PM
4626 NMSCEW/P-IV/STR/2019/4562 4562 Checking and Pouring concrete for RA-1 abutment raft Viaduct Km 200+920 RHS 24-Sep-19 4:30 PM
Checking of Shuttering and reinforcement for RE WALL PANEL precast TYPE -A
4627 NMSCEW/P-IV/STR/2019/4563 4563 50 NOS, TYPE -B 25 NOS, TYPE -Sta 6 NOS, TYPE -Stb 7 NOS, TYPE -Stc 6 NOS, RE Wall Panel Km 200+200 LHS 24-Sep-19 10:00 AM DONE
TYPE -Std 5 NOS, TYPE -Ltc 1 NOS, TYPE -Ltd 14 NOS,
Checking and Pouring concrete for RE WALL PANEL precast TYPE -A
4628 NMSCEW/P-IV/STR/2019/4564 4564 50 NOS, TYPE -B 25 NOS, TYPE -Sta 6 NOS, TYPE -Stb 7 NOS, TYPE -Stc 6 NOS, RE Wall Panel Km 200+200 LHS 24-Sep-19 11:00 AM DONE
TYPE -Std 5 NOS, TYPE -Ltc 1 NOS, TYPE -Ltd 14 NOS,
Checking reinforcement for precast Box Culvert (2x2)(cushion 2 to 4m) at precast yard camp
4629 NMSCEW/P-IV/STR/2019/4565 4565 Box culvert Km 200+200 LHS 24-Sep-19 10:00 AM DONE
-2. Segment NO-436,437,438,439,440
Checking reinforcement for precast Box Culvert (3x3)(cushion 0 to 2m) at precast yard camp
4630 NMSCEW/P-IV/STR/2019/4566 4566 Box culvert Km 200+200 LHS 24-Sep-19 10:10 AM DONE
-2. Segment NO-152
Checking reinforcement for precast Box Culvert (3x3)(cushion 2 to 4m) at precast yard camp
4631 NMSCEW/P-IV/STR/2019/4567 4567 Box culvert Km 200+200 LHS 24-Sep-19 10:20 AM DONE
-2. Segment NO-47
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4632 NMSCEW/P-IV/STR/2019/4568 4568 Box culvert Km 200+200 LHS 24-Sep-19 10:30 AM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-2,Segment no.-436,437,438,439
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4633 NMSCEW/P-IV/STR/2019/4569 4569 Box culvert Km 200+200 LHS 24-Sep-19 10:40 AM DONE
(3×3) (Cushion 0 to 2m) at precast yard camp-2,Segment no.-152
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4634 NMSCEW/P-IV/STR/2019/4570 4570 Box culvert Km 200+200 LHS 24-Sep-19 10:50 AM DONE
(3X3) (Cushion 2 to 4m) at precast yard camp-2,Segment no.-47
4635 NMSCEW/P-IV/STR/2019/4571 4571 Checking of Shuttering and reinforcement for VUP LHS final lift A1 & A2 and top slab VUP Km 176+614 LHS 24-Sep-19 11:00 AM
NR
4636 NMSCEW/P-IV/STR/2019/4572 4572 Checking and Pouring concrete for VUP LHS final lift A1 & A2 and top slab VUP Km 176+614 LHS 24-Sep-19 11:30 AM NR
4637 NMSCEW/P-IV/STR/2019/4573 4573 Checking of Shuttering and reinforcement for U-trough bottom slab PUP Km 187+835 24-Sep-19 8:00 AM DONE
4638 NMSCEW/P-IV/STR/2019/4574 4574 Checking and Pouring concrete for U-trough bottom slab PUP Km 187+835 24-Sep-19 8:30 AM DONE
4639 NMSCEW/P-IV/STR/2019/4575 4575 Checking of Shuttering and reinforcement for W-2 1st lift at median wall PUP Km 191+740 24-Sep-19 11:00 AM DONE
4640 NMSCEW/P-IV/STR/2019/4576 4576 Checking and Pouring concrete for raft W-2 1st lift at median wall PUP Km 191+740 24-Sep-19 11:30 AM DONE
4641 NMSCEW/P-IV/STR/2019/4577 4577 Checking of Shuttering and reinforcement for RP-13 pier cap Viaduct Km 169+800 Km 00+000 RHS 24-Sep-19 2:00 PM IPC-09 DONE
4642 NMSCEW/P-IV/STR/2019/4578 4578 Checking and Pouring concrete for for RP-13 pier cap Viaduct Km 169+800 Km 00+000 RHS 24-Sep-19 2:20 PM IPC-09 DONE
4643 NMSCEW/P-IV/STR/2019/4579 4579 Checking of Shuttering and reinforcement for LP-12 pier cap Viaduct Km 169+800 Km 00+000 LHS 24-Sep-19 3:00 PM IPC-09 DONE
4644 NMSCEW/P-IV/STR/2019/4580 4580 Checking and Pouring concrete for for LP-12 pier cap Viaduct Km 169+800 Km 00+000 LHS 24-Sep-19 3:30 PM IPC-09 DONE
4645 NMSCEW/P-IV/STR/2019/4581 4581 Checking erection of 2x2 utility duct ` Utility duct Km 172+520 BHS 24-Sep-19 9:30 AM IPC-08 DONE
4646 NMSCEW/P-IV/STR/2019/4582 4582 Checking of Shuttering and reinforcement for final lift at wall A1 & A2 Box culvert Km 180+427 LHS 25-Sep-19 11:30 AM IPC-08 DONE AE
4647 NMSCEW/P-IV/STR/2019/4583 4583 Checking and Pouring concrete for final lift at wall A1 & A2 Box culvert Km 180+427 LHS 25-Sep-19 12:30 PM IPC-08 DONE
4648 NMSCEW/P-IV/STR/2019/4584 4584 Checking reinforcement ,shuttering for top haunch at wall A1 & A2 with top slab Box culvert Km 180+427 LHS 25-Sep-19 2:30 PM IPC-08 DONE
4649 NMSCEW/P-IV/STR/2019/4585 4585 Checking and concrete pouring for top haunch at wall A1 & A2 with top slab Box culvert Km 180+427 LHS 25-Sep-19 3:40 PM IPC-08 DONE
4650 NMSCEW/P-IV/STR/2019/4586 4586 Checking top Level & Laying concrete for PCC at RA-02 MJB 205+610 Km 00+000 RHS 25-Sep-19 11:00 AM IPC-09 DONE AE
Checking of Shuttering and reinforcement for RE WALL PANEL precast TYPE -A
4651 NMSCEW/P-IV/STR/2019/4587 4587 50 NOS, TYPE -B 25 NOS, TYPE -Sta 2 NOS, TYPE -Stb 2 NOS, TYPE -Stc 2 NOS, RE Wall Panel Km 200+200 LHS 25-Sep-19 10:00 AM DONE
TYPE -Std 2 NOS, TYPE -Ltc 1 NOS, TYPE -Ltd 2 NOS,
Checking and Pouring concrete for RE WALL PANEL precast TYPE -A
4652 NMSCEW/P-IV/STR/2019/4588 4588 50 NOS, TYPE -B 25 NOS, TYPE -Sta 2 NOS, TYPE -Stb 2 NOS, TYPE -Stc 2 NOS, RE Wall Panel Km 200+200 LHS 25-Sep-19 11:15 AM DONE
TYPE -Std 2 NOS, TYPE -Ltc 1 NOS, TYPE -Ltd 2 NOS,
Checking reinforcement for precast Box Culvert (3x3) (Cushion 2 to 4 m) at precast yard camp
4653 NMSCEW/P-IV/STR/2019/4589 4589 Box culvert Km 175+500 LHS 25-Sep-19 9:23 AM DONE
-1. Segment NO- 216, 217, 218, 219, 220
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4654 NMSCEW/P-IV/STR/2019/4590 4590 Box culvert Km 175+500 LHS 25-Sep-19 12:27 PM
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.- 216, 217, 218, 219, 220
NR
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
4655 NMSCEW/P-IV/STR/2019/4591 4591 Box culvert Km 175+500 LHS 25-Sep-19 12:49 PM DONE
-1. Segment NO-213, 214
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4656 NMSCEW/P-IV/STR/2019/4592 4592 Box culvert Km 175+500 LHS 25-Sep-19 12:52 PM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-209, 213, 214
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
4657 NMSCEW/P-IV/STR/2019/4593 4593 Box culvert Km 175+500 LHS 25-Sep-19 4:16 PM DONE
-1. Segment NO-256, 257, 258, 259
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4658 NMSCEW/P-IV/STR/2019/4594 4594 Box culvert Km 175+500 LHS 25-Sep-19 5:21 PM DONE
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-256, 257, 258, 259
4659 NMSCEW/P-IV/STR/2019/4595 4595 Checking of Shuttering and reinforcement for 2nd lift at wall A1 & A2 PUP Km 165+790 LHS 25-Sep-19 4:05 PM IPC-08 DONE AE
4660 NMSCEW/P-IV/STR/2019/4596 4596 Checking and Pouring concrete for 2nd lift at wall A1 & A2 PUP Km 165+790 LHS 25-Sep-19 4:32 PM IPC-08 DONE AE
4661 NMSCEW/P-IV/STR/2019/4597 4597 Checking of Shuttering and reinforcement for 2nd lift at retaining wall A1 PUP Km 172+190 LHS 25-Sep-19 8:00 AM NR
4662 NMSCEW/P-IV/STR/2019/4598 4598 Checking and Pouring concrete for 2nd lift at retaining wall A1 PUP Km 172+190 LHS 25-Sep-19 8:30 AM NR
4663 NMSCEW/P-IV/STR/2019/4599 4599 Checking top Level & Laying concrete(M-10) for PCC Utility duct Km 173+680 BHS 25-Sep-19 2:00 PM
NR
4664 NMSCEW/P-IV/STR/2019/4600 4600 Checking reinforcement ,shuttering for top slab PUP Km 189+000 RHS 25-Sep-19 5:00 PM NR
4665 NMSCEW/P-IV/STR/2019/4601 4601 Checking and concrete(M-30) pouring for top slab PUP Km 189+000 RHS 25-Sep-19 5:30 PM NR
4666 NMSCEW/P-IV/STR/2019/4602 4602 Checking layout ,level for PCC at abutment RA-02 Viaduct Km 200+920 RHS 25-Sep-19 10:10 AM
4667 NMSCEW/P-IV/STR/2019/4603 4603 Checking top Level & Laying concrete for PCC at abutment RA-02 Viaduct Km 200+920 RHS 25-Sep-19 10:40 AM
4668 NMSCEW/P-IV/STR/2019/4604 4604 Checking of reinforcement and shuttering for pier shaft final lift at LP-06 Viaduct Km 195+900 LHS 25-Sep-19 12:00 PM IPC-14
4669 NMSCEW/P-IV/STR/2019/4605 4605 Checking and Pouring concrete for pier shaft final lift at LP-06 Viaduct Km 195+900 LHS 25-Sep-19 12:30 PM IPC-14
4670 NMSCEW/P-IV/STR/2019/4606 4606 Checking of reinforcement and shuttering for pier shaft final lift at LP-09 Viaduct Km 195+900 LHS 25-Sep-19 3:00 PM
4671 NMSCEW/P-IV/STR/2019/4607 4607 Checking and Pouring concrete for pier shaft final lift at LP-09 Viaduct Km 195+900 LHS 25-Sep-19 3:30 PM
4672 NMSCEW/P-IV/STR/2019/4608 4608 Checking of side shuttering girder no-21,22,23,24 at bed no-07,Girder Type-1 Girder Km 200+200 LHS 25-Sep-19 9:00 AM
Approval for pouring of girder no- 21,22,23,24 at bed no-07 (Grade of concrete M-50)
4673 NMSCEW/P-IV/STR/2019/4609 4609 Girder Km 200+200 LHS 25-Sep-19 9:30 AM
Girder Type- 1
4674 NMSCEW/P-IV/STR/2019/4610 4610 Checking layout ,level for PCC at LP-02 Viaduct Km 213+915 LHS 25-Sep-19 2:00 PM
4675 NMSCEW/P-IV/STR/2019/4611 4611 Checking layout ,level for PCC at RP-02 Viaduct Km 213+915 RHS 25-Sep-19 2:15 PM
4676 NMSCEW/P-IV/STR/2019/4612 4612 Checking top Level & Laying concrete for PCC at LP-02 Viaduct Km 213+915 LHS 25-Sep-19 3:08 PM
4677 NMSCEW/P-IV/STR/2019/4613 4613 Checking top Level & Laying concrete for PCC at RP-02 Viaduct Km 213+915 RHS 25-Sep-19 3:25 PM
4678 NMSCEW/P-IV/STR/2019/4614 4614 Checking of side shuttering girder no-33,34,35,36 at bed no-01,Girder Type-2 Girder Km 200+200 LHS 25-Sep-19 4:16 PM
Approval for pouring of girder no- 33,34,35,36 at bed no-01 (Grade of concrete M-50)
4679 NMSCEW/P-IV/STR/2019/4615 4615 Girder Km 200+200 LHS 25-Sep-19 4:44 PM
Girder Type- 2
4680 NMSCEW/P-IV/STR/2019/4616 4616 Checking of reinforcement and shuttering for pier shaft final lift at LP-04 Viaduct Km 196+560 Km 00+000 LHS 25-Sep-19 10:33 AM IPC-10 DONE AE
4681 NMSCEW/P-IV/STR/2019/4617 4617 Checking and Pouring concrete for pier shaft final lift at LP-04 Viaduct Km 196+560 Km 00+000 LHS 25-Sep-19 10:50 AM IPC-10 DONE AE
4682 NMSCEW/P-IV/STR/2019/4618 4618 Checking of reinforcement and shuttering for pier shaft 1st & final lift at RP-02 Viaduct Km 196+560 RHS 25-Sep-19 12:34 PM
4683 NMSCEW/P-IV/STR/2019/4619 4619 Checking and Pouring concrete for pier shaft 1st & final lift at RP-02 Viaduct Km 196+560 RHS 25-Sep-19 12:50 PM
4684 NMSCEW/P-IV/STR/2019/4620 4620 Checking of reinforcement and shuttering for pier shaft final lift at RP-05 Viaduct Km 202+190 RHS 25-Sep-19 12:05 PM
4685 NMSCEW/P-IV/STR/2019/4621 4621 Checking and Pouring concrete for pier shaft final lift at RP-05 Viaduct Km 202+190 RHS 25-Sep-19 12:32 PM
4686 NMSCEW/P-IV/STR/2019/4622 4622 Checking & pouring concrete for RA-2 raft Viaduct Km 202+190 RHS 25-Sep-19 10:22 AM IPC-08 DONE AE
4687 NMSCEW/P-IV/STR/2019/4623 4623 Checking layout ,level for PCC at RP-08 Viaduct Km 202+190 RHS 25-Sep-19 2:14 PM
4688 NMSCEW/P-IV/STR/2019/4624 4624 Checking top Level & Laying concrete for PCC at RP-08 Viaduct Km 202+190 RHS 25-Sep-19 2:52 PM
4689 NMSCEW/P-IV/STR/2019/4625 4625 Checking reinforcement ,shuttering for bottom slab of loop-C MNB loop-C Km 01+980 25-Sep-19 9:13 AM NR
4690 NMSCEW/P-IV/STR/2019/4626 4626 Checking and concrete (M30) pouring for bottom slab of loop-C MNB loop-C Km 01+980 25-Sep-19 9:53 AM NR
4691 NMSCEW/P-IV/STR/2019/4627 4627 Checking of reinforcement and shuttering for pier shaft abuttmet final lift at RA-02 Viaduct Km 169+800 Km 00+000 RHS 25-Sep-19 9:00 AM IPC-09 DONE MNB
4692 NMSCEW/P-IV/STR/2019/4628 4628 Checking and Pouring concrete(M-45) for pier shaft abuttmet final lift at RA-02 Viaduct Km 169+800 Km 00+000 RHS 25-Sep-19 9:30 AM IPC-09 DONE MNB
4693 NMSCEW/P-IV/STR/2019/4629 4629 Checking of Shuttering and reinforcement for final lift at wall A1 & A2 VUP Km 179+983 RHS 26-Sep-19 10:30 AM IPC-08 DONE
4694 NMSCEW/P-IV/STR/2019/4630 4630 Checking and Pouring concrete for final lift at wall A1 & A2 VUP Km 179+983 RHS 26-Sep-19 11:30 AM IPC-08 DONE
4695 NMSCEW/P-IV/STR/2019/4631 4631 Checking reinforcement ,shuttering for top haunch at wall A1 & A2 with top slab VUP Km 179+983 RHS 26-Sep-19 2:30 PM DONE
4696 NMSCEW/P-IV/STR/2019/4632 4632 Checking and concrete pouring for top haunch at wall A1 & A2 with top slab VUP Km 179+983 RHS 26-Sep-19 4:30 PM DONE
4697 NMSCEW/P-IV/STR/2019/4633 4633 Checking of Shuttering and reinforcement for 4th lift at wall A1 & A2 VUP Km 179+983 Km 00+000 LHS 26-Sep-19 9:30 AM IPC-10 DONE
4698 NMSCEW/P-IV/STR/2019/4634 4634 Checking and Pouring concrete for 4th lift at wall A1 & A2 VUP Km 179+983 Km 00+000 LHS 26-Sep-19 10:30 AM IPC-10 DONE
4699 NMSCEW/P-IV/STR/2019/4635 4635 Checking of Shuttering and reinforcement for 1st lift at retaining wall W1 & W2 PUP Km 205+430 RHS 26-Sep-19 8:00 AM DONE
4700 NMSCEW/P-IV/STR/2019/4636 4636 Checking and Pouring concrete for 1st lift at retaining wall W1 & W2 PUP Km 205+430 RHS 26-Sep-19 8:30 AM DONE
4701 NMSCEW/P-IV/STR/2019/4637 4637 Checking of Shuttering and reinforcement for 3rd lift at retaining wall W2 PUP Km 205+430 LHS 26-Sep-19 9:00 AM DONE
4702 NMSCEW/P-IV/STR/2019/4638 4638 Checking and Pouring concrete for 3rd lift at retaining wall W2 PUP Km 205+430 LHS 26-Sep-19 9:20 AM DONE
4703 NMSCEW/P-IV/STR/2019/4639 4639 Checking of Shuttering and reinforcement for 1st lift at retaining wall W1 & W2 PUP Km 204+470 RHS 26-Sep-19 11:00 AM DONE
4704 NMSCEW/P-IV/STR/2019/4640 4640 Checking and Pouring concrete for 1st lift at retaining wall W1 & W2 PUP Km 204+470 RHS 26-Sep-19 11:30 AM DONE
4705 NMSCEW/P-IV/STR/2019/4641 4641 Checking of Shuttering and reinforcement for 1st lift at retaining wall W1 PUP Km 204+470 LHS 26-Sep-19 11:35 AM DONE
4706 NMSCEW/P-IV/STR/2019/4642 4642 Checking and Pouring concrete for 1st lift at retaining wall W1 PUP Km 204+470 LHS 26-Sep-19 11:55 AM DONE
4707 NMSCEW/P-IV/STR/2019/4643 4643 Checking of Shuttering and reinforcement for 2nd lift at retaining wall W2 PUP Km 204+470 LHS 26-Sep-19 2:00 PM DONE
4708 NMSCEW/P-IV/STR/2019/4644 4644 Checking and Pouring concrete for 2nd lift at retaining wall W2 PUP Km 204+470 LHS 26-Sep-19 2:30 PM DONE
4709 NMSCEW/P-IV/STR/2019/4645 4645 Checking of Shuttering and reinforcement for 1st lift wall MNB Km 203+409 RHS 26-Sep-19 8:35 AM IPC-08 DONE
4710 NMSCEW/P-IV/STR/2019/4646 4646 Checking and Pouring concrete for 1st lift wall MNB Km 203+409 RHS 26-Sep-19 9:10 AM IPC-08 DONE
Checking of Shuttering and reinforcement for RE WALL PANEL precast TYPE -A
4711 NMSCEW/P-IV/STR/2019/4647 4647 50 NOS, TYPE -B 25 NOS, TYPE -Sta 2 NOS, TYPE -Stb 2 NOS, TYPE -Stc 2 NOS, RE Wall Panel Km 200+200 LHS 26-Sep-19 10:11 AM DONE
TYPE -Std 2 NOS, TYPE -Ltc 1 NOS, TYPE -Lta 2 NOS,
Checking and Pouring concrete for RE WALL PANEL precast TYPE -A
4712 NMSCEW/P-IV/STR/2019/4648 4648 50 NOS, TYPE -B 25 NOS, TYPE -Sta 2 NOS, TYPE -Stb 2 NOS, TYPE -Stc 2 NOS, RE Wall Panel Km 200+200 LHS 26-Sep-19 11:12 AM DONE
TYPE -Std 2 NOS, TYPE -Ltc 1 NOS, TYPE -Lta 2 NOS,
4713 NMSCEW/P-IV/STR/2019/4649 4649 Checking of Shuttering and reinforcement for raft at retaining wall W1 PUP Km 199+060 LHS 26-Sep-19 2:10 PM DONE
4714 NMSCEW/P-IV/STR/2019/4650 4650 Checking and Pouring concrete for raft at retaining wall W1 PUP Km 199+060 LHS 26-Sep-19 3:05 PM DONE
Checking reinforcement for precast Box Culvert (3x3) (Cushion 2 to 4 m) at precast yard camp
4715 NMSCEW/P-IV/STR/2019/4651 4651 Box culvert Km 175+500 LHS 26-Sep-19 9:22 AM DONE
-1. Segment NO- 221,222,223,224,225
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4716 NMSCEW/P-IV/STR/2019/4652 4652 Box culvert Km 175+500 LHS 26-Sep-19 12:26 PM
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.-221,222,223,224,225
NR
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
4717 NMSCEW/P-IV/STR/2019/4653 4653 Box culvert Km 175+500 LHS 26-Sep-19 12:51 PM DONE
-1. Segment NO-215
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4718 NMSCEW/P-IV/STR/2019/4654 4654 Box culvert Km 175+500 LHS 26-Sep-19 12:42 PM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-211,212,215
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4719 NMSCEW/P-IV/STR/2019/4655 4655 Box culvert Km 175+500 LHS 26-Sep-19 5:35 PM DONE
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-252,253,254,255
4720 NMSCEW/P-IV/STR/2019/4656 4656 Checking of Shuttering and reinforcement for final lift at wall A1 & A2 Box culvert Km 182+350 LHS 26-Sep-19 9:10 AM IPC-08 DONE
4721 NMSCEW/P-IV/STR/2019/4657 4657 Checking and Pouring concrete(M-30) for final lift at wall A1 & A2 Box culvert Km 182+350 LHS 26-Sep-19 9:46 AM IPC-08 DONE
4722 NMSCEW/P-IV/STR/2019/4658 4658 Checking of Shuttering and reinforcement for 1st lift at wall A1 & A2 Box culvert Km 180+922 RHS 26-Sep-19 11:33 AM DONE
4723 NMSCEW/P-IV/STR/2019/4659 4659 Checking and Pouring concrete(M-35) for 1st lift at wall A1 & A2 Box culvert Km 180+922 RHS 26-Sep-19 12:12 PM DONE
4724 NMSCEW/P-IV/STR/2019/4660 4660 Checking reinforcement ,shuttering for bottom slab & haunch Box culvert Km 180+922 Km 00+000 LHS 26-Sep-19 2:14 PM IPC-10 DONE
4725 NMSCEW/P-IV/STR/2019/4661 4661 Checking and concrete (M35) pouring for bottom slab & haunch. Box culvert Km 180+922 Km 00+000 LHS 26-Sep-19 2:47 PM IPC-10 DONE
4726 NMSCEW/P-IV/STR/2019/4662 4662 Checking of reinforcement, shuttering for pier cap at LP-13 Viaduct Km 169+800 LHS 26-Sep-19 2:30 PM NR
4727 NMSCEW/P-IV/STR/2019/4663 4663 Checking & pouring concrete for pier cap at LP-13 Viaduct Km 169+800 LHS 26-Sep-19 3:02 PM NR
4728 NMSCEW/P-IV/STR/2019/4664 4664 Checking of reinforcement, shuttering for pier cap at LP-11 Viaduct Km 169+800 LHS 26-Sep-19 3:34 PM NR
4729 NMSCEW/P-IV/STR/2019/4665 4665 Checking & pouring concrete for pier cap at LP-11 Viaduct Km 169+800 LHS 26-Sep-19 4:00 PM NR
4730 NMSCEW/P-IV/STR/2019/4666 4666 Checking of Shuttering and reinforcement for 2nd lift at wall A1 & A2 PUP Km 164+380 Km 00+000 RHS 26-Sep-19 12:00 PM IPC-09 DONE
4731 NMSCEW/P-IV/STR/2019/4667 4667 Checking and Pouring concrete for 2nd lift at wall A1 & A2 PUP Km 164+380 Km 00+000 RHS 26-Sep-19 12:30 PM IPC-09 DONE
4732 NMSCEW/P-IV/STR/2019/4668 4668 Checking of Shuttering and reinforcement for final lift at wall A1 & A2 PUP Km 165+790 RHS 26-Sep-19 4:06 PM NR
4733 NMSCEW/P-IV/STR/2019/4669 4669 Checking and Pouring concrete for final lift at wall A1 & A2 PUP Km 165+790 RHS 26-Sep-19 4:36 PM NR
4734 NMSCEW/P-IV/STR/2019/4670 4670 Checking top Level & Laying concrete for PCC at retaining wall A1 & A2 PUP Km 174+095 BHS 26-Sep-19 10:22 AM DONE
4735 NMSCEW/P-IV/STR/2019/4671 4671 Checking of Shuttering and reinforcement for 3rd lift at retaining wall A1 & A2 PUP Km 172+190 LHS 26-Sep-19 2:22 PM DONE
4736 NMSCEW/P-IV/STR/2019/4672 4672 Checking and Pouring concrete for 3rd lift at retaining wall A1 & A2 PUP Km 172+190 LHS 26-Sep-19 2:50 PM DONE
4737 NMSCEW/P-IV/STR/2019/4673 4673 Checking of Shuttering and reinforcement for 4th lift at retaining wall A1 & A2 PUP Km 172+190 LHS 26-Sep-19 4:08 PM DONE
4738 NMSCEW/P-IV/STR/2019/4674 4674 Checking and Pouring concrete for 4th lift at retaining wall A1 & A2 PUP Km 172+190 LHS 26-Sep-19 4:39 PM DONE
4739 NMSCEW/P-IV/STR/2019/4675 4675 Checking of Shuttering and reinforcement for 1st lift at wall A1 LVUP Km 169+291 Km 00+000 RHS 26-Sep-19 4:25 PM IPC-10 DONE
4740 NMSCEW/P-IV/STR/2019/4676 4676 Checking and Pouring concrete for 1st lift at wall A1 LVUP Km 169+291 Km 00+000 RHS 26-Sep-19 4:55 PM IPC-10 DONE
4741 NMSCEW/P-IV/STR/2019/4677 4677 Checking of Shuttering and reinforcement for raft at wall A1 & A2 PUP Km 183+290 RHS 26-Sep-19 9:01 AM DONE
4742 NMSCEW/P-IV/STR/2019/4678 4678 Checking and Pouring concrete(M-30) for footing at retaining wall A1 & A2 PUP Km 183+290 RHS 26-Sep-19 9:23 AM DONE
4743 NMSCEW/P-IV/STR/2019/4679 4679 Checking top Level & Laying concrete(M-10) for PCC Utility duct Km 173+680 BHS 26-Sep-19 10:13 AM NR
Checking for stressing and remove slagness of H.T. wires at Girder no 37,38,39,40 at bed no
4744 NMSCEW/P-IV/STR/2019/4680 4680 Girder Km 200+200 LHS 26-Sep-19 4:00 PM
-4, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no 37,38,39,40 at bed no -4 ,Girder Type-2 at casting yard
4745 NMSCEW/P-IV/STR/2019/4681 4681 Girder Km 200+200 LHS 26-Sep-19 4:30 PM
camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-25,26,27,28 at bed no
4746 NMSCEW/P-IV/STR/2019/4682 4682 Girder Km 200+200 LHS 26-Sep-19 3:00 PM
-6, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no 25,26,27,28 at bed no -6 ,Girder Type-1 at casting yard
4747 NMSCEW/P-IV/STR/2019/4683 4683 Girder Km 200+200 LHS 26-Sep-19 3:30 PM
camp -2
4748 NMSCEW/P-IV/STR/2019/4684 4684 Checking of Shuttering and reinforcement for raft at RA-01 Viaduct Km 200+920 RHS 26-Sep-19 11:00 AM
4749 NMSCEW/P-IV/STR/2019/4685 4685 Checking & pouring concrete for raft at RA-01 Viaduct Km 200+920 RHS 26-Sep-19 11:30 AM
4750 NMSCEW/P-IV/STR/2019/4686 4686 Checking of reinforcement and shuttering for pier shaft 1st lift at LP-05 Viaduct Km 200+920 Km 00+000 LHS 26-Sep-19 2:00 PM IPC-11 Approved
4751 NMSCEW/P-IV/STR/2019/4687 4687 Checking and Pouring concrete for pier shaft 1st lift at LP-05 Viaduct Km 200+920 Km 00+000 LHS 26-Sep-19 2:30 PM IPC-11 Approved
4752 NMSCEW/P-IV/STR/2019/4688 4688 Checking layout ,level for pier shaft starter at RP-01 Viaduct Km 200+920 RHS 26-Sep-19 3:30 PM
4753 NMSCEW/P-IV/STR/2019/4689 4689 Checking and Pouring concrete for pier shaft starter at RP-01 Viaduct Km 200+920 RHS 26-Sep-19 4:00 PM
4754 NMSCEW/P-IV/STR/2019/4690 4690 Checking of reinforcement, shuttering for pier cap at LP-1 Viaduct Km 195+900 Km 00+000 LHS 26-Sep-19 3:00 PM IPC-09 DONE
4755 NMSCEW/P-IV/STR/2019/4691 4691 Checking & pouring concrete for pier cap at LP-1 Viaduct Km 195+900 Km 00+000 LHS 26-Sep-19 3:30 PM IPC-09 DONE
4756 NMSCEW/P-IV/STR/2019/4692 4692 Checking layout ,level for PCC at abutment RA-02 Viaduct Km 200+920 RHS 26-Sep-19 10:00 AM
4757 NMSCEW/P-IV/STR/2019/4693 4693 Checking and Pouring concrete for PCC at abutment RA-02 Viaduct Km 200+920 RHS 26-Sep-19 10:30 AM
Checking of Shuttering and reinforcement for RE WALL PANEL precast TYPE -A
4758 NMSCEW/P-IV/STR/2019/4694 4694 50 NOS, TYPE -B 25 NOS, TYPE -Sta 2 NOS, TYPE -Stb 2 NOS, TYPE -Stc 2 NOS, RE Wall Panel Km 200+200 LHS 27-Sep-19 10:00 AM DONE
TYPE -Std 2 NOS, TYPE -Ltc 1 NOS, TYPE -Lta 2 NOS,
Checking and Pouring concrete for RE WALL PANEL precast TYPE -A
4759 NMSCEW/P-IV/STR/2019/4695 4695 50 NOS, TYPE -B 25 NOS, TYPE -Sta 2 NOS, TYPE -Stb 2 NOS, TYPE -Stc 2 NOS, RE Wall Panel Km 200+200 LHS 27-Sep-19 11:00 AM DONE
TYPE -Std 2 NOS, TYPE -Ltc 1 NOS, TYPE -Lta 2 NOS,
4760 NMSCEW/P-IV/STR/2019/4696 4696 Checking reinforcement ,shuttering for bottom haunch at wall A1 & A2 Box culvert Km 180+180 LHS 27-Sep-19 2:30 PM DONE
4761 NMSCEW/P-IV/STR/2019/4697 4697 Checking and concrete pouring for bottom haunch at wall A1 & A2 Box culvert Km 180+180 LHS 27-Sep-19 3:30 PM DONE
4762 NMSCEW/P-IV/STR/2019/4698 4698 Checking of reinforcement and shuttering for raft Box culvert Km 180+180 RHS 27-Sep-19 10:30 AM NR
4763 NMSCEW/P-IV/STR/2019/4699 4699 Checking and Pouring of concrete for raft Box culvert Km 180+180 RHS 27-Sep-19 11:40 AM NR
4764 NMSCEW/P-IV/STR/2019/4700 4700 Checking of reinforcement and shuttering for pier shaft final lift at LP-09 Viaduct Km 195+900 LHS 27-Sep-19 11:15 AM
4765 NMSCEW/P-IV/STR/2019/4701 4701 Checking and Pouring concrete for pier shaft final lift at LP-09 Viaduct Km 195+900 LHS 27-Sep-19 11:50 AM
4766 NMSCEW/P-IV/STR/2019/4702 4702 Checking of reinforcement, shuttering for pier cap at LP-03 Viaduct Km 202+190 LHS 27-Sep-19 2:35 PM
4767 NMSCEW/P-IV/STR/2019/4703 4703 Checking & pouring concrete for pier cap at LP-03 Viaduct Km 202+190 LHS 27-Sep-19 3:00 PM
4768 NMSCEW/P-IV/STR/2019/4704 4704 Checking and Pouring concrete for pier shaft final lift at LP-05 Viaduct Km 202+190 LHS 27-Sep-19 10:05 AM
4769 NMSCEW/P-IV/STR/2019/4705 4705 Checking and Pouring concrete for PCC at RP-08 Viaduct Km 202+190 RHS 27-Sep-19 5:40 PM
4770 NMSCEW/P-IV/STR/2019/4706 4706 Checking layout ,level for PCC at abutment RA-02 Viaduct Km 200+920 RHS 27-Sep-19 10:15 AM
4771 NMSCEW/P-IV/STR/2019/4707 4707 Checking and Pouring concrete for PCC at abutment RA-02 Viaduct Km 200+920 RHS 27-Sep-19 10:45 AM
4772 NMSCEW/P-IV/STR/2019/4708 4708 Checking layout ,level for PCC at LP-02 Viaduct Km 213+915 LHS 27-Sep-19 2:00 PM
4773 NMSCEW/P-IV/STR/2019/4709 4709 Checking layout ,level for PCC at RP-02 Viaduct Km 213+915 RHS 27-Sep-19 2:15 PM
4774 NMSCEW/P-IV/STR/2019/4710 4710 Checking top Level & Laying concrete for PCC at LP-02 Viaduct Km 213+915 LHS 27-Sep-19 3:08 PM
4775 NMSCEW/P-IV/STR/2019/4711 4711 Checking top Level & Laying concrete for PCC at RP-02 Viaduct Km 213+915 RHS 27-Sep-19 3:25 PM
4776 NMSCEW/P-IV/STR/2019/4712 4712 Checking errection of 2*2 precast utility duct Utility duct Km 173+000 BHS 27-Sep-19 10:30 AM IPC-08 DONE
4777 NMSCEW/P-IV/STR/2019/4713 4713 Checking reinforcement ,shuttering for top haunch at wall A1 & A2 with top slab Box culvert Km 182+350 LHS 27-Sep-19 9:00 AM IPC-08 DONE
4778 NMSCEW/P-IV/STR/2019/4714 4714 Checking and concrete(M-30) pouring for top haunch at wall A1 & A2 with top slab Box culvert Km 182+350 LHS 27-Sep-19 9:30 AM IPC-08 DONE
4779 NMSCEW/P-IV/STR/2019/4715 4715 Checking of Shuttering and reinforcement for final lift at wall A1 & A2 Box culvert Km 180+922 RHS 27-Sep-19 12:00 PM DONE
4780 NMSCEW/P-IV/STR/2019/4716 4716 Checking and Pouring concrete(M-35) for final lift at wall A1 & A2 Box culvert Km 180+922 RHS 27-Sep-19 12:30 PM DONE
4781 NMSCEW/P-IV/STR/2019/4717 4717 Checking of Shuttering and reinforcement for 1st lift at wall A1 & A2 Box culvert Km 180+922 Km 00+000 LHS 27-Sep-19 2:50 PM IPC-10 DONE
4782 NMSCEW/P-IV/STR/2019/4718 4718 Checking and Pouring concrete(M-35) for 1st lift at wall A1 & A2 Box culvert Km 180+922 Km 00+000 LHS 27-Sep-19 3:20 PM IPC-10 DONE
4783 NMSCEW/P-IV/STR/2019/4719 4719 Checking reinforcement ,shuttering for bottom slab with bottom haunch at wall A1 & A2 Box culvert Km 187+677 Km 00+000 LHS 27-Sep-19 8:00 AM IPC-09 DONE
4784 NMSCEW/P-IV/STR/2019/4720 4720 Checking and concrete(M-30) pouring for bottom slab with bottom haunch at wall A1 & A2 Box culvert Km 187+677 Km 00+000 LHS 27-Sep-19 8:30 AM IPC-09 DONE
4785 NMSCEW/P-IV/STR/2019/4721 4721 Checking of Shuttering and reinforcement for 1st lift at wall A1 & A2 Box culvert Km 187+677 Km 00+000 RHS 27-Sep-19 4:30 PM IPC-09 DONE
4786 NMSCEW/P-IV/STR/2019/4722 4722 Checking and Pouring concrete(M-30) for 1st lift at wall A1 & A2 Box culvert Km 187+677 Km 00+000 RHS 27-Sep-19 5:00 PM IPC-09 DONE
4787 NMSCEW/P-IV/STR/2019/4723 4723 Checking of reinforcement, shuttering for pier cap at LP-13 Viaduct Km 169+800 LHS 27-Sep-19 2:34 PM NR
4788 NMSCEW/P-IV/STR/2019/4724 4724 Checking & pouring concrete for pier cap at LP-13 Viaduct Km 169+800 LHS 27-Sep-19 3:08 PM NR
4789 NMSCEW/P-IV/STR/2019/4725 4725 Checking of reinforcement, shuttering for pier cap at LP-11 Viaduct Km 169+800 LHS 27-Sep-19 3:37 PM NR
4790 NMSCEW/P-IV/STR/2019/4726 4726 Checking & pouring concrete for pier cap at LP-11 Viaduct Km 169+800 LHS 27-Sep-19 4:06 PM NR
4791 NMSCEW/P-IV/STR/2019/4727 4727 Checking of Shuttering and reinforcement for final lift at wall A1 & A2 PUP Km 165+790 RHS 27-Sep-19 5:00 PM NR
4792 NMSCEW/P-IV/STR/2019/4728 4728 Checking and Pouring concrete for final lift at wall A1 & A2 PUP Km 165+790 RHS 27-Sep-19 5:30 PM NR
4793 NMSCEW/P-IV/STR/2019/4729 4729 Checking of Shuttering and reinforcement for final lift at wall A1 & A2 PUP Km 164+380 RHS 27-Sep-19 12:05 PM NR
4794 NMSCEW/P-IV/STR/2019/4730 4730 Checking and Pouring concrete for final lift at wall A1 & A2 PUP Km 164+380 RHS 27-Sep-19 12:40 PM NR
4795 NMSCEW/P-IV/STR/2019/4731 4731 Checking of Shuttering and reinforcement for 3rd lift at retaining wall A1 & A2 PUP Km 165+300 RHS 27-Sep-19 11:11 AM DONE
4796 NMSCEW/P-IV/STR/2019/4732 4732 Checking and Pouring concrete for 3rd lift at retaining wall A1 & A2 PUP Km 165+300 RHS 27-Sep-19 11:44 AM DONE
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
4797 NMSCEW/P-IV/STR/2019/4733 4733 Box culvert Km 175+500 LHS 27-Sep-19 9:32 AM DONE
-1. Segment NO-216,217
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4798 NMSCEW/P-IV/STR/2019/4734 4734 Box culvert Km 175+500 LHS 27-Sep-19 10:22 AM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-214,216,217
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
4799 NMSCEW/P-IV/STR/2019/4735 4735 Box culvert Km 175+500 LHS 27-Sep-19 11:42 AM DONE
-1. Segment NO-260,261,262,263
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4800 NMSCEW/P-IV/STR/2019/4736 4736 Box culvert Km 175+500 LHS 27-Sep-19 12:22 PM DONE
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-260,261,262,263
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4801 NMSCEW/P-IV/STR/2019/4737 4737 Box culvert Km 175+500 LHS 27-Sep-19 2:10 PM DONE
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.- 216, 217, 218, 219, 220
2*2(2to4m) segment no.,441,442 ,443,444,445,446,447, II)
4802 NMSCEW/P-IV/STR/2019/4738 4738 Box culvert Km 200+200 LHS 27-Sep-19 9:21 AM DONE
3*3(0to2m) segment
2*2(2to4m) segment no.,441,442
no. 153,154,,443,444,445,446,447, III)II)3*3(2to4m)
4803 NMSCEW/P-IV/STR/2019/4739 4739 Box culvert Km 200+200 LHS 27-Sep-19 10:10 AM DONE
3*3(0to2m) segment no. 153,154, III) 3*3(2to4m)
4804 NMSCEW/P-IV/STR/2019/4740 4740 Checking of reinforcement and shuttering for pier shaft 1st & final lift at RP-02 Viaduct Km 196+560 RHS 27-Sep-19 10:31 AM
4805 NMSCEW/P-IV/STR/2019/4741 4741 Checking and Pouring concrete for pier shaft 1st & final lift at RP-02 Viaduct Km 196+560 RHS 27-Sep-19 10:55 AM
4806 NMSCEW/P-IV/STR/2019/4742 4742 Checking of layout,level and Shuttering ,reinforcement for raft at RA-01 Viaduct Km 200+920 RHS 27-Sep-19 10:10 AM IPC-08 DONE AE
4807 NMSCEW/P-IV/STR/2019/4743 4743 Checking & pouring concrete for raft at RA-01 Viaduct Km 200+920 RHS 27-Sep-19 10:32 AM IPC-08 DONE AE
4808 NMSCEW/P-IV/STR/2019/4744 4744 Checking of reinforcement, shuttering for raft at retaining wall W2 PUP Km 199+060 LHS 27-Sep-19 9:06 AM DONE
4809 NMSCEW/P-IV/STR/2019/4745 4745 Checking & Pouring concrete for raft at retaining wall W2 PUP Km 199+060 LHS 27-Sep-19 10:09 AM DONE
4810 NMSCEW/P-IV/STR/2019/4746 4746 Checking reinforcement ,shuttering for final lift & top haunch at wall A1 & A2 with top slab VUP Km 176+614 LHS 27-Sep-19 2:30 PM IPC-08
DONE AE
Checking and concrete(M-35) pouring for final lift & top haunch at wall A1 & A2 with top
4811 NMSCEW/P-IV/STR/2019/4747 4747 VUP Km 176+614 LHS 27-Sep-19 4:30 PM IPC-08
slab DONE AE
4812 NMSCEW/P-IV/STR/2019/4748 4748 Checking of reinforcement, shuttering for raft at retaining wall A2 LVUP Km 173+400 RHS 27-Sep-19 4:20 PM SPOT RFI
4813 NMSCEW/P-IV/STR/2019/4749 4749 Checking & Pouring concrete for raft at retaining wall A2 LVUP Km 173+400 RHS 27-Sep-19 5:00 PM DONE SPOT RFI
4814 NMSCEW/P-IV/STR/2019/4750 4750 Checking reinforcement ,shuttering for bottom haunch at wall A1 & A2 Box culvert Km 180+180 RHS 28-Sep-19 9:30 AM DONE
4815 NMSCEW/P-IV/STR/2019/4751 4751 Checking and concrete pouring for bottom haunch at wall A1 & A2 Box culvert Km 180+180 RHS 28-Sep-19 10:30 AM
4816 NMSCEW/P-IV/STR/2019/4752 4752 Checking reinforcement ,shuttering for top haunch at wall A1 & A2 with top slab LVUP Km 178+323 RHS 28-Sep-19 11:30 AM IPC-08 DONE
4817 NMSCEW/P-IV/STR/2019/4753 4753 Checking and concrete pouring for top haunch at wall A1 & A2 with top slab LVUP Km 178+323 RHS 28-Sep-19 2:30 PM IPC-08 DONE
4818 NMSCEW/P-IV/STR/2019/4754 4754 Checking reinforcement ,shuttering for 1st lift at wall A1 & A2 Box culvert Km 180+180 LHS 28-Sep-19 3:40 PM
4819 NMSCEW/P-IV/STR/2019/4755 4755 Checking and concrete pouring for 1st lift at wall A1 & A2 Box culvert Km 180+180 LHS 28-Sep-19 4:30 PM
4820 NMSCEW/P-IV/STR/2019/4756 4756 Checking reinforcement ,shuttering for final lift at wall A1 & A2 Box culvert Km 180+427 RHS 28-Sep-19 12:10 PM IPC-08 DONE
4821 NMSCEW/P-IV/STR/2019/4757 4757 Checking and concrete pouring for final lift at wall A1 & A2 Box culvert Km 180+427 RHS 28-Sep-19 12:50 PM IPC-08 DONE
4822 NMSCEW/P-IV/STR/2019/4758 4758 Checking reinforcement ,shuttering for top haunch at wall A1 & A2 with top slab Box culvert Km 180+427 RHS 28-Sep-19 2:40 PM IPC-08 DONE
4823 NMSCEW/P-IV/STR/2019/4759 4759 Checking and concrete pouring for top haunch at wall A1 & A2 with top slab Box culvert Km 180+427 RHS 28-Sep-19 4:40 PM IPC-08 DONE
4824 NMSCEW/P-IV/STR/2019/4760 4760 Checking reinforcement ,shuttering for 1st lift at wall A1 & A2 Box culvert Km 187+677 Km 00+000 LHS 28-Sep-19 8:30 AM IPC-09 DONE
4825 NMSCEW/P-IV/STR/2019/4761 4761 Checking and concrete(M-30) pouring for 1st lift at wall A1 & A2 Box culvert Km 187+677 Km 00+000 LHS 28-Sep-19 9:00 AM IPC-09 DONE
4826 NMSCEW/P-IV/STR/2019/4762 4762 Checking of reinforcement, shuttering for pier cap at LP-13 Viaduct Km 169+800 Km 00+000 LHS 28-Sep-19 2:00 PM IPC-09 DONE
4827 NMSCEW/P-IV/STR/2019/4763 4763 Checking & pouring concrete(M-35) for pier cap at LP-13 Viaduct Km 169+800 Km 00+000 LHS 28-Sep-19 2:34 PM IPC-09 DONE
4828 NMSCEW/P-IV/STR/2019/4764 4764 Checking of reinforcement, shuttering for pier cap at LP-11 Viaduct Km 169+800 Km 00+000 LHS 28-Sep-19 3:00 PM IPC-09 DONE
4829 NMSCEW/P-IV/STR/2019/4765 4765 Checking & pouring concrete(M-35) for pier cap at LP-11 Viaduct Km 169+800 Km 00+000 LHS 28-Sep-19 3:35 PM IPC-09 DONE
4830 NMSCEW/P-IV/STR/2019/4766 4766 Checking reinforcement ,shuttering for 2nd lift at wall A1 & A2 Box culvert Km 187+677 RHS 28-Sep-19 2:20 PM DONE
4831 NMSCEW/P-IV/STR/2019/4767 4767 Checking and concrete(M-30) pouring for 2nd lift at wall A1 & A2 Box culvert Km 187+677 RHS 28-Sep-19 3:10 PM DONE
4832 NMSCEW/P-IV/STR/2019/4768 4768 Checking reinforcement ,shuttering for top slab with top haunch Box culvert Km 180+922 RHS 28-Sep-19 9:15 AM DONE
4833 NMSCEW/P-IV/STR/2019/4769 4769 Checking and concrete(M-35) pouring for top slab with top haunch Box culvert Km 180+922 RHS 28-Sep-19 10:00 AM DONE
4834 NMSCEW/P-IV/STR/2019/4770 4770 Checking reinforcement ,shuttering for final lift at wall A1 & A2, top haunch & top slab Box culvert Km 180+922 LHS 28-Sep-19 11:45 AM DONE
4835 NMSCEW/P-IV/STR/2019/4771 4771 Checking and concrete(M-35) pouring for final lift at wall A1 & A2, top haunch & top slab Box culvert Km 180+922 LHS 28-Sep-19 12:30 PM DONE
4836 NMSCEW/P-IV/STR/2019/4772 4772 Checking of reinforcement, shuttering for raft at retaining wall A1 LVUP Km 173+400 RHS 28-Sep-19 4:15 PM DONE
4837 NMSCEW/P-IV/STR/2019/4773 4773 Checking & Pouring concrete for raft at retaining wall A1 LVUP Km 173+400 RHS 28-Sep-19 4:50 PM DONE
4838 NMSCEW/P-IV/STR/2019/4774 4774 Checking reinforcement ,shuttering for 3rd lift at median wall A1 & A2 PUP Km 171+110 BHS 28-Sep-19 11:00 AM DONE
4839 NMSCEW/P-IV/STR/2019/4775 4775 Checking and concrete pouring for 3rd lift at median wall A1 & A2 PUP Km 171+110 BHS 28-Sep-19 11:35 AM DONE
Checking of Shuttering and reinforcement for RE WALL PANEL precast TYPE -A
4840 NMSCEW/P-IV/STR/2019/4776 4776 50 NOS, TYPE -B 25 NOS, TYPE -Sta 2 NOS, TYPE -Stb 2 NOS, TYPE -Stc 2 NOS, RE Wall Panel Km 200+200 LHS 28-Sep-19 10:05 AM DONE
TYPE -Std 2 NOS, TYPE -Ltc 1 NOS, TYPE -Lta 2 NOS,
Checking and Pouring concrete for RE WALL PANEL precast TYPE -A
4841 NMSCEW/P-IV/STR/2019/4777 4777 50 NOS, TYPE -B 25 NOS, TYPE -Sta 2 NOS, TYPE -Stb 2 NOS, TYPE -Stc 2 NOS, RE Wall Panel Km 200+200 LHS 28-Sep-19 11:05 AM DONE
TYPE -Std 2 NOS, TYPE -Ltc 1 NOS, TYPE -Lta 2 NOS,
2*2(2to4m) segment no-448,449,450,451,452,453,455,456,457,458 II)
4842 NMSCEW/P-IV/STR/2019/4778 4778 Box culvert Km 200+200 LHS 28-Sep-19 9:45 AM DONE
3*3(0to2m) segment
2*2(2to4m) segment no-448,449,450,451,452,453,455,456,457,458
no-155,156 III) 3*3(2to4m)II)
4843 NMSCEW/P-IV/STR/2019/4779 4779 Box culvert Km 200+200 LHS 28-Sep-19 10:40 AM DONE
3*3(0to2m) segment no-155,156 III) 3*3(2to4m)
4844 NMSCEW/P-IV/STR/2019/4780 4780 Checking of side shuttering girder no-37,38,39,40 at bed no-04,Girder Type-1 Girder Km 200+200 LHS 28-Sep-19 4:00 PM
Approval for pouring of girder no- 37,38,39,40 at bed no-04 (Grade of concrete M-50)
4845 NMSCEW/P-IV/STR/2019/4781 4781 Girder Km 200+200 LHS 28-Sep-19 4:30 PM
Girder Type- 1
4846 NMSCEW/P-IV/STR/2019/4782 4782 Checking of side shuttering girder no-25,26,27,28 at bed no-06,Girder Type-1 Girder Km 200+200 LHS 28-Sep-19 4:33 PM
Approval for pouring of girder no- 25,26,27,28 at bed no-06 (Grade of concrete M-50)
4847 NMSCEW/P-IV/STR/2019/4783 4783 Girder Km 200+200 LHS 28-Sep-19 5:03 PM
Girder Type- 1
4848 NMSCEW/P-IV/STR/2019/4784 4784 Checking of layout,level and Shuttering ,reinforcement for raft at LP-03 Viaduct Km 195+900 LHS 28-Sep-19 3:32 PM IPC-08 DONE AE
4849 NMSCEW/P-IV/STR/2019/4785 4785 Checking & pouring concrete for raft at LP-03 Viaduct Km 195+900 LHS 28-Sep-19 4:16 PM IPC-08 DONE
4850 NMSCEW/P-IV/STR/2019/4786 4786 Checking of reinforcement, shuttering for pier cap at LP-03 Viaduct Km 202+190 LHS 28-Sep-19 11:30 AM IPC-08 DONE AE
4851 NMSCEW/P-IV/STR/2019/4787 4787 Checking & pouring concrete for pier cap at LP-03 Viaduct Km 202+190 LHS 28-Sep-19 12:00 PM
4852 NMSCEW/P-IV/STR/2019/4788 4788 Checking and Pouring concrete for pier shaft final lift at LP-05 Viaduct Km 202+190 LHS 28-Sep-19 11:11 AM
4853 NMSCEW/P-IV/STR/2019/4789 4789 Checking reinforcement ,shuttering for top slab with top haunch at wall A1 & A2 PUP Km 164+380 RHS 28-Sep-19 2:00 PM NR
4854 NMSCEW/P-IV/STR/2019/4790 4790 Checking and concrete pouring for top slab with top haunch at wall A1 & A2 PUP Km 164+380 RHS 28-Sep-19 2:33 PM NR
4855 NMSCEW/P-IV/STR/2019/4791 4791 Checking reinforcement ,shuttering for final lift at wall A1 & A2 PUP Km 165+790 LHS 28-Sep-19 4:00 PM IPC-08 DONE AE
4856 NMSCEW/P-IV/STR/2019/4792 4792 Checking and concrete pouring for final lift at wall A1 & A2 PUP Km 165+790 LHS 28-Sep-19 4:34 PM IPC-08 DONE AE
4857 NMSCEW/P-IV/STR/2019/4793 4793 Checking reinforcement ,shuttering for raft with bottom haunch at wall A1 & A2 Box culvert Km 163+570 BHS 28-Sep-19 5:30 PM
4858 NMSCEW/P-IV/STR/2019/4794 4794 Checking and concrete pouring for raft with bottom haunch at wall A1 & A2 Box culvert Km 163+570 BHS 28-Sep-19 5:50 PM
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
4859 NMSCEW/P-IV/STR/2019/4795 4795 Box culvert Km 175+500 LHS 28-Sep-19 9:21 AM DONE
-1. Segment NO-215
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4860 NMSCEW/P-IV/STR/2019/4796 4796 Box culvert Km 175+500 LHS 28-Sep-19 10:33 AM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-218,219,220
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
4861 NMSCEW/P-IV/STR/2019/4797 4797 Box culvert Km 175+500 LHS 28-Sep-19 11:23 AM DONE
-1. Segment NO-264,265,266
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4862 NMSCEW/P-IV/STR/2019/4798 4798 Box culvert Km 175+500 LHS 28-Sep-19 12:26 PM DONE
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-255,264,265,266
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4863 NMSCEW/P-IV/STR/2019/4799 4799 Box culvert Km 175+500 LHS 28-Sep-19 3:25 PM DONE
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.- 221,222,223,224,225
4864 NMSCEW/P-IV/STR/2019/4800 4800 Checking top Level & Laying concrete(M-10) for PCC Utility duct Km 173+680 BHS 28-Sep-19 10:00 AM SPOT RFI
4865 NMSCEW/P-IV/STR/2019/4801 4801 Checking of reinforcement and shuttering for pier shaft final lift at LP-09 Viaduct Km 195+900 Km 00+000 LHS 28-Sep-19 9:30 AM IPC-09 DONE
4866 NMSCEW/P-IV/STR/2019/4802 4802 Checking and Pouring concrete for pier shaft final lift at LP-09 Viaduct Km 195+900 Km 00+000 LHS 28-Sep-19 11:00 AM IPC-09 DONE
4867 NMSCEW/P-IV/STR/2019/4803 4803 Checking reinforcement ,shuttering for final lift at wall A1 & A2 Box culvert Km 180+180 LHS 29-Sep-19 9:30 AM NR
4868 NMSCEW/P-IV/STR/2019/4804 4804 Checking and concrete pouring for final lift at wall A1 & A2 Box culvert Km 180+180 LHS 29-Sep-19 10:30 AM NR
4869 NMSCEW/P-IV/STR/2019/4805 4805 Checking reinforcement ,shuttering for top haunch at wall A1 & A2 with top slab Box culvert Km 180+180 LHS 29-Sep-19 3:40 PM NR
4870 NMSCEW/P-IV/STR/2019/4806 4806 Checking and concrete pouring for top haunch at wall A1 & A2 with top slab Box culvert Km 180+180 LHS 29-Sep-19 5:40 PM NR
4871 NMSCEW/P-IV/STR/2019/4807 4807 Checking reinforcement ,shuttering for 1st lift at wall A1 & A2 Box culvert Km 180+180 RHS 29-Sep-19 10:40 AM NR
4872 NMSCEW/P-IV/STR/2019/4808 4808 Checking and concrete pouring for 1st lift at wall A1 & A2 Box culvert Km 180+180 RHS 29-Sep-19 11:30 AM NR
4873 NMSCEW/P-IV/STR/2019/4809 4809 Checking reinforcement ,shuttering for final lift at wall A1 & A2 LVUP Km 178+323 LHS 29-Sep-19 11:35 AM
4874 NMSCEW/P-IV/STR/2019/4810 4810 Checking and concrete pouring for final lift at wall A1 & A2 LVUP Km 178+323 LHS 29-Sep-19 12:30 PM
4875 NMSCEW/P-IV/STR/2019/4811 4811 Checking of Shuttering and reinforcement for 1st lift at retaining wall W1 & W2 PUP Km 199+060 LHS 29-Sep-19 9:00 AM DONE
4876 NMSCEW/P-IV/STR/2019/4812 4812 Checking and Pouring concrete for 1st lift at retaining wall W1 & W2 PUP Km 199+060 LHS 29-Sep-19 9:30 AM DONE
4877 NMSCEW/P-IV/STR/2019/4813 4813 Checking of Shuttering and reinforcement for1st lift of wall MNB Km 199+360 RHS 29-Sep-19 11:00 AM IPC-08 DONE
4878 NMSCEW/P-IV/STR/2019/4814 4814 Checking and Pouring concrete 1st lift wall MNB Km 199+360 RHS 29-Sep-19 11:30 AM IPC-08 DONE
4879 NMSCEW/P-IV/STR/2019/4815 4815 Checking layout ,level for top slab PUP Km 193+880 LHS 29-Sep-19 2:00 PM IPC-08 DONE
4880 NMSCEW/P-IV/STR/2019/4816 4816 Checking of Shuttering and reinforcement for top slab PUP Km 193+880 LHS 29-Sep-19 3:00 PM IPC-08 DONE
4881 NMSCEW/P-IV/STR/2019/4817 4817 Checking and Pouring concrete for top slab PUP Km 193+880 LHS 29-Sep-19 3:30 PM IPC-08 DONE
Checking of Shuttering and reinforcement for RE WALL PANEL precast TYPE -A
4882 NMSCEW/P-IV/STR/2019/4818 4818 50 NOS, TYPE -B 25 NOS, TYPE -Sta 2 NOS, TYPE -Stb 2 NOS, TYPE -Stc 2 NOS, RE Wall Panel Km 200+200 LHS 29-Sep-19 10:05 AM DONE
TYPE -Std 2 NOS, TYPE -Ltc 1 NOS, TYPE -Lta 2 NOS,
Checking and Pouring concrete for RE WALL PANEL precast TYPE -A
4883 NMSCEW/P-IV/STR/2019/4819 4819 50 NOS, TYPE -B 25 NOS, TYPE -Sta 2 NOS, TYPE -Stb 2 NOS, TYPE -Stc 2 NOS, RE Wall Panel Km 200+200 LHS 29-Sep-19 11:11 AM DONE
TYPE -Std 2 NOS, TYPE -Ltc 1 NOS, TYPE -Lta 2 NOS,
4884 NMSCEW/P-IV/STR/2019/4820 4820 Checking of Shuttering and reinforcement for 1st lift at retaining wall W1 PUP Km 204+470 RHS 29-Sep-19 8:00 AM DONE
4885 NMSCEW/P-IV/STR/2019/4821 4821 Checking and Pouring concrete for 1st lift at retaining wall W1 PUP Km 204+470 RHS 29-Sep-19 8:20 AM DONE
4886 NMSCEW/P-IV/STR/2019/4822 4822 Checking of Shuttering and reinforcement for 1st lift at retaining wall W2 PUP Km 205+430 RHS 29-Sep-19 9:09 AM DONE
4887 NMSCEW/P-IV/STR/2019/4823 4823 Checking and Pouring concrete for 1st lift at retaining wall W2 PUP Km 205+430 RHS 29-Sep-19 9:26 AM DONE
4888 NMSCEW/P-IV/STR/2019/4824 4824 Checking of Shuttering and reinforcement for 3rd lift at retaining wall W1 & W2 PUP Km 203+560 RHS 29-Sep-19 10:00 AM DONE
4889 NMSCEW/P-IV/STR/2019/4825 4825 Checking and Pouring concrete for 3rd lift at retaining wall W1 & W2 PUP Km 203+560 RHS 29-Sep-19 10:30 AM DONE
2*2(2to4m) segment no-459,460,461,462,463,464 II) 3*3(0to2m)
4890 NMSCEW/P-IV/STR/2019/4826 4826 Box culvert Km 200+200 LHS 29-Sep-19 9:00 AM DONE
segment no-157,158,159,160,161,162
2*2(2to4m) segment no-459,460,461,462,463,464 III)
II)
4891 NMSCEW/P-IV/STR/2019/4827 4827 Box culvert Km 200+200 LHS 29-Sep-19 10:50 AM DONE
3*3(0to2m) segment no-157,158,159,160,161,162
4892 NMSCEW/P-IV/STR/2019/4828 4828 Checking of reinforcement and shuttering for pier shaft 1st lift at RP-01 Viaduct Km 196+560 Km 00+000 RHS 29-Sep-19 9:30 AM IPC-11 Approved AE
4893 NMSCEW/P-IV/STR/2019/4829 4829 Checking and Pouring concrete for pier shaft 1st lift at RP-01 Viaduct Km 196+560 Km 00+000 RHS 29-Sep-19 9:50 AM IPC-11 Approved
4894 NMSCEW/P-IV/STR/2019/4830 4830 Checking of reinforcement and shuttering for pier shaft 1st & final lift at RP-02 Viaduct Km 196+560 Km 00+000 RHS 29-Sep-19 10:30 AM IPC-10 DONE AE
4895 NMSCEW/P-IV/STR/2019/4831 4831 Checking and Pouring concrete for pier shaft 1st & final lift at RP-02 Viaduct Km 196+560 Km 00+000 RHS 29-Sep-19 10:40 AM IPC-10 DONE
4896 NMSCEW/P-IV/STR/2019/4832 4832 Checking of reinforcement and shuttering for pier shaft final lift at LP-06 Viaduct Km 196+560 LHS 29-Sep-19 3:20 PM
4897 NMSCEW/P-IV/STR/2019/4833 4833 Checking and Pouring concrete for pier shaft final lift at LP-06 Viaduct Km 196+560 LHS 29-Sep-19 3:50 PM
4898 NMSCEW/P-IV/STR/2019/4834 4834 Checking layout ,level for pier starter at LP-04 Viaduct Km 200+920 LHS 29-Sep-19 10:00 AM
4899 NMSCEW/P-IV/STR/2019/4835 4835 Checking and Pouring concrete for pier starter at LP-04 Viaduct Km 200+920 LHS 29-Sep-19 10:30 AM
4900 NMSCEW/P-IV/STR/2019/4836 4836 Checking layout ,level for pier starter at RP-04 Viaduct Km 200+920 RHS 29-Sep-19 11:05 AM
4901 NMSCEW/P-IV/STR/2019/4837 4837 Checking and Pouring concrete for pier starter at RP-04 Viaduct Km 200+920 RHS 29-Sep-19 11:33 AM
4902 NMSCEW/P-IV/STR/2019/4838 4838 Checking & pouring concrete for pier cap at LP-03 Viaduct Km 202+190 LHS 29-Sep-19 12:00 PM IPC-08 DONE AE
4903 NMSCEW/P-IV/STR/2019/4839 4839 Checking and Pouring concrete for pier shaft final lift at RP-05 Viaduct Km 202+190 Km 00+000 RHS 29-Sep-19 11:00 AM IPC-10 DONE
4904 NMSCEW/P-IV/STR/2019/4840 4840 Checking of reinforcement and shuttering for pier shaft final lift at LP-08 Viaduct Km 202+190 LHS 29-Sep-19 12:15 PM
4905 NMSCEW/P-IV/STR/2019/4841 4841 Checking and Pouring concrete for pier shaft final lift at LP-08 Viaduct Km 202+190 LHS 29-Sep-19 12:45 PM
4906 NMSCEW/P-IV/STR/2019/4842 4842 Checking top Level & Laying concrete for PCC at RP-08 Viaduct Km 202+190 RHS 29-Sep-19 12:10 PM
4907 NMSCEW/P-IV/STR/2019/4843 4843 Checking layout ,level and structural excavation Utility duct Km 174+360 Km 00+000 BHS 29-Sep-19 10:15 AM IPC-09 DONE
4908 NMSCEW/P-IV/STR/2019/4844 4844 Checking reinforcement ,shuttering for final lift at wall A1 & A2 PUP Km 165+790 RHS 29-Sep-19 4:16 PM IPC-08 DONE
4909 NMSCEW/P-IV/STR/2019/4845 4845 Checking and concrete pouring for final lift at wall A1 & A2 PUP Km 165+790 RHS 29-Sep-19 4:42 PM IPC-08 DONE
4910 NMSCEW/P-IV/STR/2019/4846 4846 Checking reinforcement ,shuttering for top slab with top haunch at wall A1 & A2 PUP Km 165+790 LHS 29-Sep-19 5:10 PM DONE
4911 NMSCEW/P-IV/STR/2019/4847 4847 Checking and concrete pouring for top slab with top haunch at wall A1 & A2 PUP Km 165+790 LHS 29-Sep-19 5:35 PM DONE
4912 NMSCEW/P-IV/STR/2019/4848 4848 Checking of Shuttering and reinforcement for raft at retaining wall A1 PUP Km 171+110 RHS 29-Sep-19 10:20 AM DONE
4913 NMSCEW/P-IV/STR/2019/4849 4849 Checking and Pouring concrete (M-30) for raft at retaining wall A1 PUP Km 171+110 RHS 29-Sep-19 10:46 AM DONE
4914 NMSCEW/P-IV/STR/2019/4850 4850 Checking reinforcement ,shuttering for top slab with top haunch PUP Km 189+000 RHS 29-Sep-19 11:40 AM IPC-08 DONE
4915 NMSCEW/P-IV/STR/2019/4851 4851 Checking and concrete(M-30) pouring for top slab with top haunch PUP Km 189+000 RHS 29-Sep-19 12:20 PM IPC-08 DONE
4916 NMSCEW/P-IV/STR/2019/4852 4852 Checking reinforcement ,shuttering for top slab PUP Km 190+650 LHS 29-Sep-19 8:30 AM REPEATED
4917 NMSCEW/P-IV/STR/2019/4853 4853 Checking and concrete(M-30) pouring for top slab with top PUP Km 190+650 LHS 29-Sep-19 9:02 AM REPEATED
4918 NMSCEW/P-IV/STR/2019/4854 4854 Checking of reinforcement, shuttering for 1st lift U trough median wall A1 & A2 PUP Km 187+835 29-Sep-19 10:03 AM NR
4919 NMSCEW/P-IV/STR/2019/4855 4855 Checking & pouring concrete(M-30) for 1st lift U trough median wall A1 & A2 PUP Km 187+835 29-Sep-19 10:33 AM NR
4920 NMSCEW/P-IV/STR/2019/4856 4856 Checking layout ,level and structural excavation for PCC at U trough bottom (median) PUP Km 189+000 29-Sep-19 12:30 PM NR
4921 NMSCEW/P-IV/STR/2019/4857 4857 Checking top Level & Laying concretem(M-10) for PCC at U trough bottom (median) PUP Km 189+000 29-Sep-19 12:50 PM
NR
4922 NMSCEW/P-IV/STR/2019/4858 4858 Checking layout ,level and structural excavation for PCC at retaining wall A2 PUP Km 189+000 LHS 29-Sep-19 2:00 PM NR
4923 NMSCEW/P-IV/STR/2019/4859 4859 Checking top Level & Laying concrete(M-10) for PCC at retaining wall A2 PUP Km 189+000 LHS 29-Sep-19 2:15 PM NR
4924 NMSCEW/P-IV/STR/2019/4860 4860 Checking reinforcement ,shuttering for bottom slab of loop-C MNB loop-C Km 01+980 29-Sep-19 10:00 AM DONE SPOT RFI
4925 NMSCEW/P-IV/STR/2019/4861 4861 Checking and concrete (M35) pouring for bottom slab of loop-C MNB loop-C Km 01+980 29-Sep-19 10:30 AM DONE SPOT RFI
4926 NMSCEW/P-IV/STR/2019/4862 4862 Checking reinforcement ,shuttering for top slab with top haunch at wall A1 & A2 PUP Km 165+790 RHS 30-Sep-19 4:00 PM IPC-08 DONE
4927 NMSCEW/P-IV/STR/2019/4863 4863 Checking and concrete pouring for top slab with top haunch at wall A1 & A2 PUP Km 165+790 RHS 30-Sep-19 4:30 PM IPC-08 DONE
4928 NMSCEW/P-IV/STR/2019/4864 4864 Checking reinforcement ,shuttering for top slab with top haunch at wall A1 & A2 LVUP Km 169+291 LHS 30-Sep-19 12:00 PM IPC-08 DONE
4929 NMSCEW/P-IV/STR/2019/4865 4865 Checking and concrete pouring for top slab with top haunch at wall A1 & A2 LVUP Km 169+291 LHS 30-Sep-19 12:30 PM IPC-08 DONE
4930 NMSCEW/P-IV/STR/2019/4866 4866 Checking reinforcement ,shuttering for raft with bottom haunch at wall A1 & A2 Box culvert Km 163+570 Km 00+000 BHS 30-Sep-19 4:35 PM IPC-10 DONE
4931 NMSCEW/P-IV/STR/2019/4867 4867 Checking and concrete pouring for raft with bottom haunch at wall A1 & A2 Box culvert Km 163+570 Km 00+000 BHS 30-Sep-19 5:00 PM IPC-10 DONE
4932 NMSCEW/P-IV/STR/2019/4868 4868 Checking of Shuttering and reinforcement for raft at retaining wall A2 LVUP Km 173+400 LHS 30-Sep-19 4:10 PM DONE
4933 NMSCEW/P-IV/STR/2019/4869 4869 Checking and Pouring concrete (M-30) for raft at retaining wall A2 LVUP Km 173+400 LHS 30-Sep-19 4:50 PM DONE
4934 NMSCEW/P-IV/STR/2019/4870 4870 Checking reinforcement ,shuttering for 2nd lift at wall A1 & A2 Box culvert Km 187+677 LHS 30-Sep-19 8:30 AM DONE
4935 NMSCEW/P-IV/STR/2019/4871 4871 Checking and concrete(M-30) pouring for 2nd lift at wall A1 & A2 Box culvert Km 187+677 LHS 30-Sep-19 9:00 AM NR
4936 NMSCEW/P-IV/STR/2019/4872 4872 Checking of Shuttering and reinforcement for raft at retaining wall A2 PUP Km 174+095 LHS 30-Sep-19 3:00 PM DONE
4937 NMSCEW/P-IV/STR/2019/4873 4873 Checking and Pouring concrete (M-30) for raft at retaining wall A2 PUP Km 174+095 LHS 30-Sep-19 3:30 PM DONE
4938 NMSCEW/P-IV/STR/2019/4874 4874 Checking reinforcement ,shuttering for top slab Box culvert Km 187+677 RHS 30-Sep-19 2:30 PM DONE
4939 NMSCEW/P-IV/STR/2019/4875 4875 Checking and concrete(M-30) pouring for top slab with top Box culvert Km 187+677 RHS 30-Sep-19 3:10 PM NR
4940 NMSCEW/P-IV/STR/2019/4876 4876 Checking layout ,level for PCC at LP-02 Viaduct Km 213+915 LHS 30-Sep-19 2:00 PM
4941 NMSCEW/P-IV/STR/2019/4877 4877 Checking layout ,level for PCC at RP-02 Viaduct Km 213+915 RHS 30-Sep-19 2:15 PM
4942 NMSCEW/P-IV/STR/2019/4878 4878 Checking top Level & Laying concrete for PCC at LP-02 Viaduct Km 213+915 LHS 30-Sep-19 3:08 PM
4943 NMSCEW/P-IV/STR/2019/4879 4879 Checking top Level & Laying concrete for PCC at RP-02 Viaduct Km 213+915 RHS 30-Sep-19 3:25 PM
4944 NMSCEW/P-IV/STR/2019/4880 4880 Checking of layout,level and Shuttering ,reinforcement for raft at LP-02 Viaduct Km 195+900 LHS 30-Sep-19 11:30 AM IPC-08 DONE
4945 NMSCEW/P-IV/STR/2019/4881 4881 Checking & pouring concrete for raft at LP-02 Viaduct Km 195+900 LHS 30-Sep-19 12:00 PM IPC-08 DONE
4946 NMSCEW/P-IV/STR/2019/4882 4882 Checking of reinforcement, shuttering for pier cap at RP-02 Viaduct Km 195+900 Km 00+000 RHS 30-Sep-19 3:40 PM IPC-09 DONE AE
4947 NMSCEW/P-IV/STR/2019/4883 4883 Checking & pouring concrete for pier cap at RP-02 Viaduct Km 195+900 Km 00+000 RHS 30-Sep-19 3:40 PM IPC-09 DONE AE
4948 NMSCEW/P-IV/STR/2019/4884 4884 Checking layout ,level for PCC at abutment RA-02 Viaduct Km 200+920 RHS 30-Sep-19 2:00 PM
4949 NMSCEW/P-IV/STR/2019/4885 4885 Checking top Level & Laying concrete for PCC at abutment RA-02 Viaduct Km 200+920 RHS 30-Sep-19 2:30 PM
4950 NMSCEW/P-IV/STR/2019/4886 4886 Checking of reinforcement and shuttering for pier shaft 1st lift at RP-05 Viaduct Km 200+920 RHS 30-Sep-19 4:00 PM
4951 NMSCEW/P-IV/STR/2019/4887 4887 Checking and Pouring concrete for pier shaft 1st lift at RP-05 Viaduct Km 200+920 RHS 30-Sep-19 4:30 PM
Checking for stressing and remove slagness of H.T. wires at Girder no 41,42,43,44 at bed no
4952 NMSCEW/P-IV/STR/2019/4888 4888 Girder Km 200+200 LHS 30-Sep-19 9:00 AM
-2, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no 41,42,43,44 at bed no -2 ,Girder Type-2 at casting yard
4953 NMSCEW/P-IV/STR/2019/4889 4889 Girder Km 200+200 LHS 30-Sep-19 9:30 AM
camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-29,30,31,32 at bed no
4954 NMSCEW/P-IV/STR/2019/4890 4890 Girder Km 200+200 LHS 30-Sep-19 3:55 PM
-5, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no 29,30,31,32 at bed no -5 ,Girder Type-1 at casting yard
4955 NMSCEW/P-IV/STR/2019/4891 4891 Girder Km 200+200 LHS 30-Sep-19 4:25 PM
camp -2
4956 NMSCEW/P-IV/STR/2019/4892 4892 Checking of reinforcement, shuttering for pier cap at LP-05 Viaduct Km 202+190 LHS 30-Sep-19 5:05 PM IPC-08 DONE
4957 NMSCEW/P-IV/STR/2019/4893 4893 Checking & pouring concrete for pier cap at LP-05 Viaduct Km 202+190 LHS 30-Sep-19 5:40 PM IPC-08 DONE
4958 NMSCEW/P-IV/STR/2019/4894 4894 Checking of side shuttering girder no-25,26,27,28 at bed no-06,Girder Type-1 Girder Km 200+200 LHS 30-Sep-19 9:30 AM
Approval for pouring of girder no- 25,26,27,28 at bed no-06 (Grade of concrete M-50)
4959 NMSCEW/P-IV/STR/2019/4895 4895 Girder Km 200+200 LHS 30-Sep-19 10:10 AM
Girder Type- 1
4960 NMSCEW/P-IV/STR/2019/4896 4896 Checking reinforcement ,shuttering for top haunch at wall A1 & A2 with top slab Box culvert Km 180+180 RHS 30-Sep-19 10:40 AM NR
4961 NMSCEW/P-IV/STR/2019/4897 4897 Checking and concrete pouring for top haunch at wall A1 & A2 with top slab Box culvert Km 180+180 RHS 30-Sep-19 12:30 PM NR
Checking reinforcement for precast Box Culvert (3x3) (cushion 2 to 4m) at precast yard camp
4962 NMSCEW/P-IV/STR/2019/4898 4898 Box culvert Km 175+500 LHS 30-Sep-19 9:00 AM DONE
-1. Segment NO-226,227
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4963 NMSCEW/P-IV/STR/2019/4899 4899 Box culvert Km 175+500 LHS 30-Sep-19 10:20 AM DONE
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.- 218,219,220,226,227
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
4964 NMSCEW/P-IV/STR/2019/4900 4900 Box culvert Km 175+500 LHS 30-Sep-19 10:55 AM DONE
-1. Segment NO-221,222,223
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4965 NMSCEW/P-IV/STR/2019/4901 4901 Box culvert Km 175+500 LHS 30-Sep-19 12:00 PM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-221,222,223
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
4966 NMSCEW/P-IV/STR/2019/4902 4902 Box culvert Km 175+500 LHS 30-Sep-19 3:12 PM DONE
-1. Segment NO-267,268,269
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
4967 NMSCEW/P-IV/STR/2019/4903 4903 Box culvert Km 175+500 LHS 30-Sep-19 4:10 PM DONE
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-267,268,269
4968 NMSCEW/P-IV/STR/2019/4904 4904 Checking of reinforcement, shuttering for 1st lift U trough retaining wall A1 & A2(Median) PUP Km 187+835 30-Sep-19 10:00 AM DONE
4969 NMSCEW/P-IV/STR/2019/4905 4905 Checking & pouring concrete(M-30) for 1st lift U trough retaining wall A1 & A2(Median) PUP Km 187+835 30-Sep-19 10:15 AM DONE
4970 NMSCEW/P-IV/STR/2019/4906 4906 Checking layout ,level and structural excavation for PCC PUP Km 187+113 BHS 30-Sep-19 4:00 PM NR
4971 NMSCEW/P-IV/STR/2019/4907 4907 Checking top Level & Laying concretem(M-10) for PCC PUP Km 187+113 BHS 30-Sep-19 4:15 PM NR
4972 NMSCEW/P-IV/STR/2019/4908 4908 Checking reinforcement ,shuttering for 2nd lift at wall A1 & A2 Box culvert Km 182+350 LHS 30-Sep-19 9:00 AM REPEATED
4973 NMSCEW/P-IV/STR/2019/4909 4909 Checking and concrete(M-30) pouring for 2nd lift at wall A1 & A2 Box culvert Km 182+350 LHS 30-Sep-19 9:39 AM REPEATED
4974 NMSCEW/P-IV/STR/2019/4910 4910 Checking errection of 3*3 precast Box culvert Box culvert Km 171+334 BHS 30-Sep-19 10:30 AM IPC-08 DONE
4975 NMSCEW/P-IV/STR/2019/4911 4911 Checking reinforcement ,shuttering for raft at wall A1 & A2 PUP Km 165+300 LHS 30-Sep-19 4:00 PM SPOT RFI
4976 NMSCEW/P-IV/STR/2019/4912 4912 Checking and concrete pouring for raft at wall A1 & A2 PUP Km 165+300 LHS 30-Sep-19 4:30 PM SPOT RFI
4977 NMSCEW/P-IV/STR/2019/4913 4913 Checking of reinforcement, shuttering for pier cap at RP-01 Viaduct Km 169+800 Km 00+000 RHS 30-Sep-19 3:00 PM IPC-09 DONE
4978 NMSCEW/P-IV/STR/2019/4914 4914 Checking & pouring concrete(M-35) for pier cap at RP-01 Viaduct Km 169+800 Km 00+000 RHS 30-Sep-19 3:15 PM IPC-09 DONE
4979 NMSCEW/P-IV/STR/2019/4915 4915 Checking of reinforcement, shuttering for pier cap at RP-03 Viaduct Km 169+800 Km 00+000 RHS 30-Sep-19 3:30 PM IPC-09 DONE
4980 NMSCEW/P-IV/STR/2019/4916 4916 Checking & pouring concrete(M-35) for pier cap at RP-03 Viaduct Km 169+800 Km 00+000 RHS 30-Sep-19 3:45 PM IPC-09 DONE
4981 NMSCEW/P-IV/STR/2019/4917 4917 Checking of reinforcement, shuttering for pier cap at RP-09 Viaduct Km 196+560 RHS 30-Sep-19 5:00 PM SPOT RFI
4982 NMSCEW/P-IV/STR/2019/4918 4918 Checking & pouring concrete for pier cap at RP-09 Viaduct Km 196+560 RHS 30-Sep-19 5:30 PM SPOT RFI
4983 NMSCEW/P-IV/STR/2019/4919 4919 Checking of reinforcement, shuttering for pier cap at LA-01 Viaduct Km 202+190 LHS 30-Sep-19 11:30 AM IPC-08 DONE
4984 NMSCEW/P-IV/STR/2019/4920 4920 Checking & pouring concrete for pier cap at LA-01 Viaduct Km 202+190 LHS 30-Sep-19 11:45 AM IPC-08 DONE
4985 NMSCEW/P-IV/STR/2019/4921 4921 Checking of Shuttering and reinforcement for 1st lift wall MNB Km 203+409 LHS 30-Sep-19 8:00 AM IPC-08 DONE
4986 NMSCEW/P-IV/STR/2019/4922 4922 Checking and Pouring concrete for 1st lift wall MNB Km 203+409 LHS 30-Sep-19 8:20 AM IPC-08 DONE
4987 NMSCEW/P-IV/STR/2019/4923 4923 Checking of Shuttering and reinforcement for 2nd lift at retaining wall W1 PUP Km 204+470 LHS 30-Sep-19 9:00 AM DONE SPOT RFI
4988 NMSCEW/P-IV/STR/2019/4924 4924 Checking and Pouring concrete for 2nd lift at retaining wall W1 PUP Km 204+470 LHS 30-Sep-19 9:20 AM DONE SPOT RFI
4989 NMSCEW/P-IV/STR/2019/4925 4925 Checking of Shuttering and reinforcement for 2nd lift at retaining wall W1 & W2 PUP Km 204+470 RHS 30-Sep-19 2:00 PM DONE SPOT RFI
4990 NMSCEW/P-IV/STR/2019/4926 4926 Checking and Pouring concrete for 2nd lift at retaining wall W1 & W2 PUP Km 204+470 RHS 30-Sep-19 2:20 PM DONE SPOT RFI
4991 NMSCEW/P-IV/STR/2019/4927 4927 Checking of Shuttering and reinforcement for 3rd lift at retaining wall W1 PUP Km 205+430 RHS 30-Sep-19 3:00 PM DONE SPOT RFI
4992 NMSCEW/P-IV/STR/2019/4928 4928 Checking and Pouring concrete for 3rd lift at retaining wall W1 PUP Km 205+430 RHS 30-Sep-19 3:20 PM DONE SPOT RFI
4993 NMSCEW/P-IV/STR/2019/4929 4929 Checking of Shuttering and reinforcement for 2nd lift at retaining wall W2 PUP Km 205+430 RHS 30-Sep-19 3:30 PM DONE SPOT RFI
4994 NMSCEW/P-IV/STR/2019/4930 4930 Checking and Pouring concrete for 2nd lift at retaining wall W2 PUP Km 205+430 RHS 30-Sep-19 4:00 PM DONE SPOT RFI
4995 NMSCEW/P-IV/STR/2019/4931 4931 Checking of layout,level and Shuttering ,reinforcement for raft at RA-02 MJB 205+610 Km 00+000 RHS 30-Sep-19 11:00 AM IPC-09 DONE
4996 NMSCEW/P-IV/STR/2019/4932 4932 Checking & pouring concrete for raft at RA-02 MJB 205+610 Km 00+000 RHS 30-Sep-19 3:00 PM IPC-09 DONE
4997 NMSCEW/P-IV/STR/2019/4933 4933 Checking of layout,level and Shuttering ,reinforcement for raft CUP 206+985 Km 00+000 LHS 30-Sep-19 4:15 PM IPC-09 DONE
4998 NMSCEW/P-IV/STR/2019/4934 4934 Checking & pouring concrete for raft CUP 206+985 Km 00+000 LHS 30-Sep-19 9:00 AM IPC-09 DONE
4999 NMSCEW/P-IV/STR/2019/4935 4935 Checking of completion of segment errection for 2x2 utility duct Utility duct Km 205+100 BHS 30-Sep-19 5:00 PM IPC-08 DONE
Checking of Shuttering and reinforcement for RE WALL PANEL precast TYPE -A
5000 NMSCEW/P-IV/STR/2019/4936 4936 50 NOS, TYPE -B 25 NOS, TYPE -Sta 2 NOS, TYPE -Stb 2 NOS, TYPE -Stc 2 NOS, RE Wall Panel Km 200+200 LHS 1-Oct-19 10:00 AM DONE
TYPE -Std 2 NOS, TYPE -Ltc 1 NOS, TYPE -Lta 2 NOS,
Checking and Pouring concrete for RE WALL PANEL precast TYPE -A
5001 NMSCEW/P-IV/STR/2019/4937 4937 50 NOS, TYPE -B 25 NOS, TYPE -Sta 2 NOS, TYPE -Stb 2 NOS, TYPE -Stc 2 NOS, RE Wall Panel Km 200+200 LHS 1-Oct-19 11:00 AM DONE
TYPE -Std 2 NOS, TYPE -Ltc 1 NOS, TYPE -Lta 2 NOS,
Checking reinforcement for precast Box Culvert - I)
5002 NMSCEW/P-IV/STR/2019/4938 4938 2*2(2to4m) segment no-465,466,467,468,469,470,471,472 Box culvert Km 200+200 LHS 1-Oct-19 9:40 AM DONE
II) 3*3(2to4m) segment no-51
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert I)
5003 NMSCEW/P-IV/STR/2019/4939 4939 2*2(2to4m) segment no-465,466,467,468,469,470,471,472 Box culvert Km 200+200 LHS 1-Oct-19 11:00 AM DONE
II) 3*3(2to4m) segment no-51
Checking reinforcement for precast Box Culvert (3x3) (cushion 2 to 4m) at precast yard camp
5004 NMSCEW/P-IV/STR/2019/4940 4940 Box culvert Km 175+500 LHS 1-Oct-19 9:30 AM
-1. Segment NO-228,229,230,231,232
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
5005 NMSCEW/P-IV/STR/2019/4941 4941 Box culvert Km 175+500 LHS 1-Oct-19 10:50 AM
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.- 228,229,230,231,232
NR
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
5006 NMSCEW/P-IV/STR/2019/4942 4942 Box culvert Km 175+500 LHS 1-Oct-19 11:30 AM DONE
-1. Segment NO-224,225,226
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
5007 NMSCEW/P-IV/STR/2019/4943 4943 Box culvert Km 175+500 LHS 1-Oct-19 12:30 PM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-224,225,226
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
5008 NMSCEW/P-IV/STR/2019/4944 4944 Box culvert Km 175+500 LHS 1-Oct-19 2:30 PM DONE
-1. Segment NO-271,272,273,274
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
5009 NMSCEW/P-IV/STR/2019/4945 4945 Box culvert Km 175+500 LHS 1-Oct-19 3:30 PM DONE
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-271,272,273,274
5010 NMSCEW/P-IV/STR/2019/4946 4946 Checking of reinforcement and shuttering for pier shaft final lift at RP-09 Viaduct Km 195+900 RHS 1-Oct-19 11:00 AM
5011 NMSCEW/P-IV/STR/2019/4947 4947 Checking and Pouring concrete for pier shaft final lift at RP-09 Viaduct Km 195+900 RHS 1-Oct-19 11:30 AM
5012 NMSCEW/P-IV/STR/2019/4948 4948 Checking of reinforcement and shuttering for pier shaft final lift at LP-06 Viaduct Km 196+560 Km 00+000 LHS 1-Oct-19 11:05 AM IPC-10 DONE
5013 NMSCEW/P-IV/STR/2019/4949 4949 Checking and Pouring concrete for pier shaft final lift at LP-06 Viaduct Km 196+560 Km 00+000 LHS 1-Oct-19 11:30 AM IPC-10 DONE AE
5014 NMSCEW/P-IV/STR/2019/4950 4950 Checking of Shuttering and reinforcement for 1st lift at inner wall A1 & A2 MNB loop-A Km 01+980 Km 00+000 BHS 1-Oct-19 9:00 AM IPC-10 DONE AE
5015 NMSCEW/P-IV/STR/2019/4951 4951 Checking and Pouring concrete(M-35) for 1st lift at at inner wall A1 & A2 MNB loop-A Km 01+980 Km 00+000 BHS 1-Oct-19 9:46 AM IPC-10 DONE AE
5016 NMSCEW/P-IV/STR/2019/4952 4952 Checking layout ,level and structural excavation for PCC VUP Km 187+113 BHS 1-Oct-19 4:00 PM NR
5017 NMSCEW/P-IV/STR/2019/4953 4953 Checking top Level & Laying concretem(M-10) for PCC VUP Km 187+113 BHS 1-Oct-19 4:30 PM NR
5018 NMSCEW/P-IV/STR/2019/4954 4954 Checking of reinforcement and shuttering for pier shaft final lift at LP-08 Viaduct Km 202+190 Km 00+000 LHS 1-Oct-19 12:00 PM IPC-10 DONE AE
5019 NMSCEW/P-IV/STR/2019/4955 4955 Checking and Pouring concrete for pier shaft final lift at LP-08 Viaduct Km 202+190 Km 00+000 LHS 1-Oct-19 12:33 PM IPC-10 DONE AE
5020 NMSCEW/P-IV/STR/2019/4956 4956 Checking top Level & Laying concrete for PCC at RP-08 Viaduct Km 202+190 RHS 1-Oct-19 12:10 PM
5021 NMSCEW/P-IV/STR/2019/4957 4957 Checking of reinforcement, shuttering for pier cap at LP-05 Viaduct Km 202+190 LHS 1-Oct-19 2:15 PM
5022 NMSCEW/P-IV/STR/2019/4958 4958 Checking & pouring concrete for pier cap at LP-05 Viaduct Km 202+190 LHS 1-Oct-19 2:45 PM
5023 NMSCEW/P-IV/STR/2019/4959 4959 Checking of Shuttering and reinforcement for 1st lift at wall W1 Box culvert Km 192+039 RHS 1-Oct-19 11:00 AM DONE
5024 NMSCEW/P-IV/STR/2019/4960 4960 Checking and Pouring concrete for 1st lift at wall W1 Box culvert Km 192+039 RHS 1-Oct-19 11:30 AM DONE
5025 NMSCEW/P-IV/STR/2019/4961 4961 Checking of Shuttering and reinforcement for 2nd lift at wall W1 PUP Km 199+060 LHS 1-Oct-19 2:00 PM DONE
5026 NMSCEW/P-IV/STR/2019/4962 4962 Checking and Pouring concrete for 2nd lift at wall W1 PUP Km 199+060 LHS 1-Oct-19 3:00 PM DONE
5027 NMSCEW/P-IV/STR/2019/4963 4963 Checking of Shuttering and reinforcement for 2nd lift at median wall W2 PUP Km 191+740 1-Oct-19 3:10 PM DONE
5028 NMSCEW/P-IV/STR/2019/4964 4964 Checking and Pouring concrete for 2nd lift at median wall W2 PUP Km 191+740 1-Oct-19 3:40 PM DONE
5029 NMSCEW/P-IV/STR/2019/4965 4965 Checking of Shuttering and reinforcement for 1st lift at median wall W1 PUP Km 191+740 1-Oct-19 9:00 AM DONE
5030 NMSCEW/P-IV/STR/2019/4966 4966 Checking and Pouring concrete for 1st lift at median wall W1 PUP Km 191+740 1-Oct-19 9:30 AM DONE
5031 NMSCEW/P-IV/STR/2019/4967 4967 Checking of Shuttering and reinforcement for 1st lift at wall W1 & W2 PUP Km 206+985 LHS 2-Oct-19 9:00 AM DONE
5032 NMSCEW/P-IV/STR/2019/4968 4968 Checking and Pouring concrete for 1st lift at wall W1 & W2 PUP Km 206+985 LHS 2-Oct-19 10:00 AM DONE
5033 NMSCEW/P-IV/STR/2019/4969 4969 Checking of Shuttering and reinforcement for raft at retaining wall W1 PUP Km 171+110 LHS 2-Oct-19 11:30 AM DONE
5034 NMSCEW/P-IV/STR/2019/4970 4970 Checking and Pouring concrete for raft at retaining wall W1 PUP Km 171+110 LHS 2-Oct-19 12:00 PM NR
5035 NMSCEW/P-IV/STR/2019/4971 4971 Checking top Level & Laying concrete(M-10) for PCC at retaining wall LVUP Km 173+400 LHS 2-Oct-19 11:00 AM DONE
5036 NMSCEW/P-IV/STR/2019/4972 4972 Checking layout ,level and structural excavation for PCC at U trough bottom slab PUP Km 190+650 2-Oct-19 11:15 AM DONE
5037 NMSCEW/P-IV/STR/2019/4973 4973 Checking top Level & Laying concretem(M-10) for PCC at U trough bottom slab PUP Km 190+650 2-Oct-19 11:45 AM DONE
5038 NMSCEW/P-IV/STR/2019/4974 4974 Checking reinforcement ,shuttering for 2nd lift at U-type wall A1 & A2 PUP Km 187+835 2-Oct-19 3:00 PM DONE
5039 NMSCEW/P-IV/STR/2019/4975 4975 Checking and concrete(M-30) pouring for 2nd lift at U-type wall A1 & A2 PUP Km 187+835 2-Oct-19 3:30 PM DONE
5040 NMSCEW/P-IV/STR/2019/4976 4976 Checking of Shuttering and reinforcement for raft at median PUP Km 199+060 2-Oct-19 2:00 PM DONE
5041 NMSCEW/P-IV/STR/2019/4977 4977 Checking and Pouring concrete for raft at median PUP Km 199+060 2-Oct-19 3:10 PM DONE
5042 NMSCEW/P-IV/STR/2019/4978 4978 Checking of Shuttering and reinforcement for 2nd lift at retaining wall W2 PUP Km 199+060 LHS 2-Oct-19 4:00 PM DONE
5043 NMSCEW/P-IV/STR/2019/4979 4979 Checking and Pouring concrete for 2nd lift at retaining wall W2 PUP Km 199+060 LHS 2-Oct-19 4:30 PM DONE
Checking reinforcement for precast Box Culvert (3x3) (cushion 2 to 4m) at precast yard camp
5044 NMSCEW/P-IV/STR/2019/4980 4980 Box culvert Km 175+500 LHS 2-Oct-19 9:30 AM
-1. Segment NO-233
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
5045 NMSCEW/P-IV/STR/2019/4981 4981 Box culvert Km 175+500 LHS 2-Oct-19 10:40 AM
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.- 219,220,226,227,233
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
5046 NMSCEW/P-IV/STR/2019/4982 4982 Box culvert Km 175+500 LHS 2-Oct-19 11:10 AM DONE
-1. Segment NO-227,228,229
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
5047 NMSCEW/P-IV/STR/2019/4983 4983 Box culvert Km 175+500 LHS 2-Oct-19 12:15 PM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-227,228,229
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
5048 NMSCEW/P-IV/STR/2019/4984 4984 Box culvert Km 175+500 LHS 2-Oct-19 2:40 PM
-1. Segment NO-275,276,277,278
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
5049 NMSCEW/P-IV/STR/2019/4985 4985 Box culvert Km 175+500 LHS 2-Oct-19 3:30 PM
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-275,276,277,278
Approval for pouring of girder no- 41,42,43,44 at bed no-02, (Grade of concrete M-50)
5070 NMSCEW/P-IV/STR/2019/5006 5006 Girder Km 200+200 LHS 3-Oct-19 10:10 AM
Girder Type- 2
Checking for stressing and remove slagness of H.T. wires at Girder no 45,46,47,48 at bed no
5071 NMSCEW/P-IV/STR/2019/5007 5007 Girder Km 200+200 LHS 3-Oct-19 4:16 PM
-03, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no 45,46,47,48 at bed no -03 ,Girder Type-2 at casting yard
5072 NMSCEW/P-IV/STR/2019/5008 5008 Girder Km 200+200 LHS 3-Oct-19 4:40 PM
camp -2
5073 NMSCEW/P-IV/STR/2019/5009 5009 Checking of reinforcement and shuttering for pier shaft final lift at RP-04 Viaduct Km 195+900 RHS 3-Oct-19 11:11 AM IPC-14
5074 NMSCEW/P-IV/STR/2019/5010 5010 Checking and Pouring concrete for pier shaft final lift at RP-04 Viaduct Km 195+900 RHS 3-Oct-19 11:44 AM IPC-14
5075 NMSCEW/P-IV/STR/2019/5011 5011 Checking of reinforcement and shuttering for pier shaft 1st lift at RP-05 Viaduct Km 200+920 RHS 3-Oct-19 2:18 PM
5076 NMSCEW/P-IV/STR/2019/5012 5012 Checking and Pouring concrete for pier shaft 1st lift at RP-05 Viaduct Km 200+920 RHS 3-Oct-19 2:46 PM
5077 NMSCEW/P-IV/STR/2019/5013 5013 Checking of reinforcement and shuttering for pier shaft final lift at RP-13 Viaduct Km 202+190 RHS 3-Oct-19 2:26 PM
5078 NMSCEW/P-IV/STR/2019/5014 5014 Checking and Pouring concrete for pier shaft final lift at RP-13 Viaduct Km 202+190 RHS 3-Oct-19 3:05 PM
5079 NMSCEW/P-IV/STR/2019/5015 5015 Checking layout ,level and excavated bed for PCC at RP-08 Viaduct Km 202+190 Km 00+000 RHS 3-Oct-19 7:45 AM IPC-10 DONE
5080 NMSCEW/P-IV/STR/2019/5016 5016 Checking top Level & Laying concrete for PCC at RP-08 Viaduct Km 202+190 Km 00+000 RHS 3-Oct-19 8:00 AM IPC-10 DONE
5081 NMSCEW/P-IV/STR/2019/5017 5017 Checking of reinforcement, shuttering for pier cap at LP-06 Viaduct Km 202+190 LHS 3-Oct-19 5:00 PM
5082 NMSCEW/P-IV/STR/2019/5018 5018 Checking & pouring concrete for pier cap at LP-06 Viaduct Km 202+190 LHS 3-Oct-19 5:30 PM
5083 NMSCEW/P-IV/STR/2019/5019 5019 Checking of reinforcement and shuttering for pier shaft final lift at RP-09 Viaduct Km 195+900 Km 00+000 RHS 3-Oct-19 10:18 AM IPC-11 Approved AE
5084 NMSCEW/P-IV/STR/2019/5020 5020 Checking and Pouring concrete for pier shaft final lift at RP-09 Viaduct Km 195+900 Km 00+000 RHS 3-Oct-19 10:47 AM IPC-11 Approved
5085 NMSCEW/P-IV/STR/2019/5021 5021 Checking of reinforcement, shuttering for pier cap at RP-09 Viaduct Km 196+560 Km 00+000 RHS 3-Oct-19 10:05 AM IPC-09 DONE
5086 NMSCEW/P-IV/STR/2019/5022 5022 Checking & pouring concrete for pier cap at RP-09 Viaduct Km 196+560 Km 00+000 RHS 3-Oct-19 10:50 AM IPC-09 DONE
5087 NMSCEW/P-IV/STR/2019/5023 5023 Checking of reinforcement, shuttering for pier cap at RP-11 Viaduct Km 169+800 Km 00+000 RHS 3-Oct-19 3:11 PM IPC-09 DONE AE
5088 NMSCEW/P-IV/STR/2019/5024 5024 Checking & pouring concrete for pier cap at RP-11 Viaduct Km 169+800 Km 00+000 RHS 3-Oct-19 3:38 PM IPC-09 DONE AE
5089 NMSCEW/P-IV/STR/2019/5025 5025 Checking of reinforcement, shuttering for pier cap at RP-12 Viaduct Km 169+800 Km 00+000 RHS 3-Oct-19 4:10 PM IPC-09 DONE AE
5090 NMSCEW/P-IV/STR/2019/5026 5026 Checking & pouring concrete for pier cap at RP-12 Viaduct Km 169+800 Km 00+000 RHS 3-Oct-19 4:47 PM IPC-09 DONE AE
Checking for stressing and remove slagness of H.T. wires at Girder no 29,30,31,32 at bed no
5091 NMSCEW/P-IV/STR/2019/5027 5027 Girder Km 200+200 LHS 3-Oct-19 2:50 PM
-05, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no 29,30,31,32 at bed no -05 ,Girder Type-1 at casting yard
5092 NMSCEW/P-IV/STR/2019/5028 5028 Girder Km 200+200 LHS 3-Oct-19 3:25 PM
camp -2
5093 NMSCEW/P-IV/STR/2019/5029 5029 Checking of reinforcement, shuttering for pier cap at RP-10 Viaduct Km 196+560 RHS 3-Oct-19 4:33 PM
5094 NMSCEW/P-IV/STR/2019/5030 5030 Checking & pouring concrete for pier cap at RP-10 Viaduct Km 196+560 RHS 3-Oct-19 4:55 PM
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
5095 NMSCEW/P-IV/STR/2019/5031 5031 Box culvert Km 175+500 LHS 3-Oct-19 9:20 AM DONE
-1. Segment NO-227,228,229
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
5096 NMSCEW/P-IV/STR/2019/5032 5032 Box culvert Km 175+500 LHS 3-Oct-19 10:20 AM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-227,228,229
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
5097 NMSCEW/P-IV/STR/2019/5033 5033 Box culvert Km 175+500 LHS 3-Oct-19 11:13 AM
-1. Segment NO-275,276,277,278
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
5098 NMSCEW/P-IV/STR/2019/5034 5034 Box culvert Km 175+500 LHS 3-Oct-19 12:20 PM
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-275,276,277,278
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
5099 NMSCEW/P-IV/STR/2019/5035 5035 Box culvert Km 175+500 LHS 3-Oct-19 3:35 PM
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.- 228,229,230,231,232
5100 NMSCEW/P-IV/STR/2019/5036 5036 Checking of Shuttering and reinforcement for final lift at retaining wall A2 LVUP Km 173+400 LHS 4-Oct-19 11:00 AM DONE
5101 NMSCEW/P-IV/STR/2019/5037 5037 Checking and Pouring concrete for final lift at retaining wall A2 LVUP Km 173+400 LHS 4-Oct-19 11:30 AM NR
5102 NMSCEW/P-IV/STR/2019/5038 5038 Checking layout ,level and structural excavation for PCC at bottom slab VUP Km 187+113 4-Oct-19 10:00 AM DONE
5103 NMSCEW/P-IV/STR/2019/5039 5039 Checking top Level & Laying concretem(M-10) for PCC at bottom slab VUP Km 187+113 4-Oct-19 10:30 AM DONE
5104 NMSCEW/P-IV/STR/2019/5040 5040 Checking of reinforcement and shuttering for abuttment shaft 2nd lift at RA-01 Viaduct Km 169+800 RHS 4-Oct-19 2:00 PM DONE
5105 NMSCEW/P-IV/STR/2019/5041 5041 Checking and Pouring concrete(M-45) for abuttment shaft 2nd lift at RA-01 Viaduct Km 169+800 RHS 4-Oct-19 2:30 PM DONE
5106 NMSCEW/P-IV/STR/2019/5042 5042 Checking of Shuttering and reinforcement for Pedestal at LP-07 Viaduct Km 169+800 LHS 4-Oct-19 3:00 PM DONE
5107 NMSCEW/P-IV/STR/2019/5043 5043 Checking & pouring concrete(M-45) for Pedestal at LP-07 Viaduct Km 169+800 LHS 4-Oct-19 3:30 PM DONE
5108 NMSCEW/P-IV/STR/2019/5044 5044 Checking of Shuttering and reinforcement for Pedestal at LP-04 Viaduct Km 169+800 LHS 4-Oct-19 4:00 PM DONE
5109 NMSCEW/P-IV/STR/2019/5045 5045 Checking & pouring concrete(M-45) for Pedestal at LP-04 Viaduct Km 169+800 LHS 4-Oct-19 4:30 PM DONE
Checking for stressing and remove slagness of H.T. wires at Girder no 49,50,51,52 at bed no
5110 NMSCEW/P-IV/STR/2019/5046 5046 Girder Km 200+200 LHS 4-Oct-19 5:00 PM
-01, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no 49,50,51,52 at bed no -01, Girder Type-2 at casting
5111 NMSCEW/P-IV/STR/2019/5047 5047 Girder Km 200+200 LHS 4-Oct-19 5:30 PM
yard camp -2
5112 NMSCEW/P-IV/STR/2019/5048 5048 Checking of side shuttering girder no-45,46,47,48 at bed no-03,Girder Type-2 Girder Km 200+200 LHS 4-Oct-19 9:30 AM
Approval for pouring of girder no- 45,46,47,48 at bed no-03, (Grade of concrete M-50)
5113 NMSCEW/P-IV/STR/2019/5049 5049 Girder Km 200+200 LHS 4-Oct-19 10:10 AM
Girder Type- 2
5114 NMSCEW/P-IV/STR/2019/5050 5050 Checking of reinforcement, shuttering for foundation/ (Pier) cap at RP-01 Viaduct Km 195+900 Km 00+000 RHS 4-Oct-19 3:05 PM IPC-09 DONE AE
5115 NMSCEW/P-IV/STR/2019/5051 5051 Checking & pouring concrete for foundation ( Pier) cap at RP-01 Viaduct Km 195+900 Km 00+000 RHS 4-Oct-19 11:10 AM IPC-09 DONE AE
5116 NMSCEW/P-IV/STR/2019/5052 5052 Checking of Shuttering and reinforcement for 3rd lift at retaining wall W1 PUP Km 203+560 LHS 4-Oct-19 2:15 PM DONE
5117 NMSCEW/P-IV/STR/2019/5053 5053 Checking and Pouring concrete for 3rd lift at retaining wall W1 PUP Km 203+560 LHS 4-Oct-19 2:45 PM DONE
5118 NMSCEW/P-IV/STR/2019/5054 5054 Checking of Shuttering and reinforcement for 3rd lift at retaining wall W1 & W2 PUP Km 204+470 RHS 4-Oct-19 9:00 AM DONE
5119 NMSCEW/P-IV/STR/2019/5055 5055 Checking and Pouring concrete for 3rd lift at retaining wall W1 & W2 PUP Km 204+470 RHS 4-Oct-19 10:00 AM DONE
5120 NMSCEW/P-IV/STR/2019/5056 5056 Checking of Shuttering and reinforcement for 4th lift at retaining wall W1 PUP Km 205+430 RHS 4-Oct-19 11:20 AM DONE
5121 NMSCEW/P-IV/STR/2019/5057 5057 Checking and Pouring concrete for 4th lift at retaining wall W1 PUP Km 205+430 RHS 4-Oct-19 11:50 AM DONE
Checking of Shuttering and reinforcement for RE WALL PANEL precast TYPE -A
5122 NMSCEW/P-IV/STR/2019/5058 5058 50 NOS, TYPE -B 25 NOS, TYPE -Sta 2 NOS, TYPE -Stb 2 NOS, TYPE -Stc 2 NOS, RE Wall Panel Km 200+200 LHS 4-Oct-19 10:15 AM DONE
TYPE -Std 2 NOS, TYPE -Ltc 1 NOS, TYPE -Lta 2 NOS,
Checking and Pouring concrete for RE WALL PANEL precast TYPE -A
5123 NMSCEW/P-IV/STR/2019/5059 5059 50 NOS, TYPE -B 25 NOS, TYPE -Sta 2 NOS, TYPE -Stb 2 NOS, TYPE -Stc 2 NOS, RE Wall Panel Km 200+200 LHS 4-Oct-19 11:05 AM DONE
TYPE -Std 2 NOS, TYPE -Ltc 1 NOS, TYPE -Lta 2 NOS,
5124 NMSCEW/P-IV/STR/2019/5060 5060 Checking of Shuttering and reinforcement for 2nd lift at median wall W1 & W2 PUP Km 191+740 4-Oct-19 3:00 PM DONE
5125 NMSCEW/P-IV/STR/2019/5061 5061 Checking and Pouring concrete for 2nd lift at median wall W1 & W2 PUP Km 191+740 4-Oct-19 3:30 PM DONE
5126 NMSCEW/P-IV/STR/2019/5062 5062 Checking of Shuttering and reinforcement for 1st lift at wall W2 MNB Km 199+360 LHS 4-Oct-19 8:00 AM DONE
5127 NMSCEW/P-IV/STR/2019/5063 5063 Checking and Pouring concrete for 1st lift at wall W2 MNB Km 199+360 LHS 4-Oct-19 8:30 AM DONE
5128 NMSCEW/P-IV/STR/2019/5064 5064 Checking of Shuttering and reinforcement for 1st lift at wall W4 MNB Km 199+360 LHS 4-Oct-19 2:00 PM DONE
5129 NMSCEW/P-IV/STR/2019/5065 5065 Checking and Pouring concrete for 1st lift at wall W4 MNB Km 199+360 LHS 4-Oct-19 2:30 PM DONE
5130 NMSCEW/P-IV/STR/2019/5066 5066 Checking layout ,level for PCC at median wall PUP Km 193+880 4-Oct-19 9:00 AM DONE
5131 NMSCEW/P-IV/STR/2019/5067 5067 Checking top Level & Laying concrete for PCC at median wall PUP Km 193+880 4-Oct-19 9:40 AM DONE
5132 NMSCEW/P-IV/STR/2019/5068 5068 Checking of Shuttering and reinforcement for 1st lift at U trough median wall A1 & A2 PUP Km 165+300 BHS 4-Oct-19 3:12 PM DONE
5133 NMSCEW/P-IV/STR/2019/5069 5069 Checking and Pouring concrete for 1st lift at U trough median wall A1 & A2 PUP Km 165+300 BHS 4-Oct-19 3:35 PM DONE
5134 NMSCEW/P-IV/STR/2019/5070 5070 Checking of Shuttering and reinforcement for 1st lift at retaining wall A1 & A2 PUP Km 165+300 LHS 4-Oct-19 4:05 PM NR
5135 NMSCEW/P-IV/STR/2019/5071 5071 Checking and Pouring concrete for 1st lift at retaining wall A1 & A2 PUP Km 165+300 LHS 4-Oct-19 4:40 PM NR
5136 NMSCEW/P-IV/STR/2019/5072 5072 Checking of reinforcement and shuttering for pier shaft final lift at RP-13 Viaduct Km 202+190 RHS 4-Oct-19 2:50 PM
5137 NMSCEW/P-IV/STR/2019/5073 5073 Checking and Pouring concrete for pier shaft final lift at RP-13 Viaduct Km 202+190 RHS 4-Oct-19 3:25 PM
5138 NMSCEW/P-IV/STR/2019/5074 5074 Checking of reinforcement and shuttering for pier shaft final lift at LP-09 Viaduct Km 202+190 Km 00+000 LHS 4-Oct-19 12:00 PM IPC-10 DONE AE
5139 NMSCEW/P-IV/STR/2019/5075 5075 Checking and Pouring concrete for pier shaft final lift at LP-09 Viaduct Km 202+190 Km 00+000 LHS 4-Oct-19 12:30 PM IPC-10 DONE AE
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
5140 NMSCEW/P-IV/STR/2019/5076 5076 Box culvert Km 175+500 LHS 4-Oct-19 9:20 AM DONE
-1. Segment NO-233,234,235
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
5141 NMSCEW/P-IV/STR/2019/5077 5077 Box culvert Km 175+500 LHS 4-Oct-19 10:20 AM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-233,234,235
Checking reinforcement for precast Box Culvert (2x2)(Cushion 0 to 2m) at precast yard camp
5142 NMSCEW/P-IV/STR/2019/5078 5078 Box culvert Km 175+500 LHS 4-Oct-19 11:13 AM
-1. Segment NO-283,284,285,286
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
5143 NMSCEW/P-IV/STR/2019/5079 5079 Box culvert Km 175+500 LHS 4-Oct-19 12:20 PM
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-283,284,285,286
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
5144 NMSCEW/P-IV/STR/2019/5080 5080 Box culvert Km 175+500 LHS 4-Oct-19 3:35 PM
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.- 219,220,226,227,233
5145 NMSCEW/P-IV/STR/2019/5081 5081 Checking top Level & Laying concrete(M-10) for PCC Utility duct Km 174+630 BHS 4-Oct-19 10:00 AM NR
5146 NMSCEW/P-IV/STR/2019/5082 5082 Checking of side shuttering girder no-29,30,31,32 at bed no-05,Girder Type-1 Girder Km 200+200 LHS 5-Oct-19 3:00 PM
Approval for pouring of girder no-29,30,31,32 at bed no-05, (Grade of concrete M-50)
5147 NMSCEW/P-IV/STR/2019/5083 5083 Girder Km 200+200 LHS 5-Oct-19 3:30 PM
Girder Type- 1
5148 NMSCEW/P-IV/STR/2019/5084 5084 Checking layout ,level for PCC at LP-02 Viaduct Km 213+915 LHS 5-Oct-19 2:05 PM
5149 NMSCEW/P-IV/STR/2019/5085 5085 Checking layout ,level for PCC at RP-02 & RP-03 Viaduct Km 213+915 RHS 5-Oct-19 2:20 PM
5150 NMSCEW/P-IV/STR/2019/5086 5086 Checking top Level & Laying concrete for PCC at LP-02 Viaduct Km 213+915 LHS 5-Oct-19 3:15 PM
5151 NMSCEW/P-IV/STR/2019/5087 5087 Checking top Level & Laying concrete for PCC at RP-02 & RP-03 Viaduct Km 213+915 RHS 5-Oct-19 3:35 PM
5152 NMSCEW/P-IV/STR/2019/5088 5088 Checking of reinforcement, shuttering for pier cap at RP-10 Viaduct Km 196+560 RHS 5-Oct-19 3:20 PM
5153 NMSCEW/P-IV/STR/2019/5089 5089 Checking & pouring concrete for pier cap at RP-10 Viaduct Km 196+560 RHS 5-Oct-19 3:40 PM
5154 NMSCEW/P-IV/STR/2019/5090 5090 Checking of reinforcement and shuttering for pier shaft 2nd & final lift at RP-01 Viaduct Km 196+560 RHS 5-Oct-19 12:30 PM
5155 NMSCEW/P-IV/STR/2019/5091 5091 Checking and Pouring concrete for pier shaft 2nd & final lift at RP-01 Viaduct Km 196+560 RHS 5-Oct-19 12:50 PM
5156 NMSCEW/P-IV/STR/2019/5092 5092 Checking of reinforcement and shuttering for pier shaft final lift at RA-01 Viaduct Km 202+190 RHS 5-Oct-19 3:00 PM
5157 NMSCEW/P-IV/STR/2019/5093 5093 Checking and Pouring concrete for pier shaft final lift at RA-01 Viaduct Km 202+190 RHS 5-Oct-19 3:30 PM
5158 NMSCEW/P-IV/STR/2019/5094 5094 Checking of reinforcement, shuttering for pier cap at LP-07 Viaduct Km 202+190 LHS 5-Oct-19 4:00 PM
5159 NMSCEW/P-IV/STR/2019/5095 5095 Checking & pouring concrete for pier cap at LP-07 Viaduct Km 202+190 LHS 5-Oct-19 4:30 PM
5160 NMSCEW/P-IV/STR/2019/5096 5096 Checking of reinforcement, shuttering for pier cap at RP-02 Viaduct Km 169+800 Km 00+000 RHS 5-Oct-19 2:00 PM IPC-09 DONE
5161 NMSCEW/P-IV/STR/2019/5097 5097 Checking & pouring concrete(M-35) for pier cap at RP-02 Viaduct Km 169+800 Km 00+000 RHS 5-Oct-19 2:30 PM IPC-09 DONE
5162 NMSCEW/P-IV/STR/2019/5098 5098 Checking of reinforcement and shuttering for abuttment shaft 3rd & final lift & at LA-01 Viaduct Km 169+800 LHS 5-Oct-19 2:50 PM
NR
5163 NMSCEW/P-IV/STR/2019/5099 5099 Checking and Pouring concrete(M-45) for abuttment shaft 3rd & final lift & at LA-01 Viaduct Km 169+800 LHS 5-Oct-19 3:40 PM NR
Checking reinforcement for precast Box Culvert (3x3) (cushion 2 to 4m) at precast yard camp
5164 NMSCEW/P-IV/STR/2019/5100 5100 Box culvert Km 175+500 LHS 5-Oct-19 9:30 AM
-1. Segment NO-234,235,236,237
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
5165 NMSCEW/P-IV/STR/2019/5101 5101 Box culvert Km 175+500 LHS 5-Oct-19 10:40 AM
(3x3) (Cushion 2 to 4 m) at precast yard camp-1,Segment no.- 219,220,226,227,233
Checking reinforcement for precast Box Culvert (2x2)(Cushion 2 to 4m) at precast yard camp
5166 NMSCEW/P-IV/STR/2019/5102 5102 Box culvert Km 175+500 LHS 5-Oct-19 11:10 AM DONE
-1. Segment NO-236,237
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
5167 NMSCEW/P-IV/STR/2019/5103 5103 Box culvert Km 175+500 LHS 5-Oct-19 12:15 PM DONE
(2×2) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-232,236,237
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert
5168 NMSCEW/P-IV/STR/2019/5104 5104 Box culvert Km 175+500 LHS 5-Oct-19 4:15 PM
(2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-279,280,281,282
5169 NMSCEW/P-IV/STR/2019/5105 5105 Checking layout ,level and structural excavation for PCC at retaining wall A2 PUP Km 190+650 LHS 5-Oct-19 10:00 AM NR
5170 NMSCEW/P-IV/STR/2019/5106 5106 Checking top Level & Laying concretem(M-10) for PCC at retaining wall A2 PUP Km 190+650 LHS 5-Oct-19 10:33 AM NR
Checking reinforcement for precast Box Culvert - I)
5171 NMSCEW/P-IV/STR/2019/5107 5107 2*2(2to4m) segment no-483,484,485,486,487,488,489,490,491,492 Box culvert Km 200+200 LHS 5-Oct-19 9:45 AM DONE
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert I)
5172 NMSCEW/P-IV/STR/2019/5108 5108 2*2(2to4m) segment no-483,484,485,486,487,488,489,490,491,492 Box culvert Km 200+200 LHS 5-Oct-19 10:45 AM DONE
5173 NMSCEW/P-IV/STR/2019/5109 5109 Checking reinforcement ,shuttering for 2nd lift at wall A1 ,A2 & inner wall of loop-A MNB loop-A Km 01+980 Km 00+000 BHS 5-Oct-19 9:00 AM IPC-10 DONE AE
5174 NMSCEW/P-IV/STR/2019/5110 5110 Checking and concrete (M35) pouring for 2nd lift at wall A1 ,A2 & inner wall of loop-A MNB loop-A Km 01+980 Km 00+000 BHS 5-Oct-19 9:30 AM IPC-10 DONE
AE
5175 NMSCEW/P-IV/STR/2019/5111 5111 Checking of layout,level and Shuttering ,reinforcement for raft at RP-11 Viaduct Km 202+190 Km 00+000 RHS 5-Oct-19 3:10 PM IPC-10 DONE AE
5176 NMSCEW/P-IV/STR/2019/5112 5112 Checking & pouring concrete for raft at RP-11 Viaduct Km 202+190 Km 00+000 RHS 5-Oct-19 3:50 PM IPC-10 DONE AE
5177 NMSCEW/P-IV/STR/2019/5113 5113 Checking of Shuttering and reinforcement for Pedestal at LP-05 Viaduct Km 169+800 LHS 5-Oct-19 4:00 PM DONE SPOT RFI
5178 NMSCEW/P-IV/STR/2019/5114 5114 Checking & pouring concrete for Pedestal at LP-05 Viaduct Km 169+800 LHS 5-Oct-19 4:30 PM DONE SPOT RFI
5179 NMSCEW/P-IV/STR/2019/5115 5115 Checking of Shuttering and reinforcement for Pedestal at LP-06 Viaduct Km 169+800 LHS 5-Oct-19 5:00 PM NR SPOT RFI
5180 NMSCEW/P-IV/STR/2019/5116 5116 Checking & pouring concrete for Pedestal at LP-06 Viaduct Km 169+800 LHS 5-Oct-19 5:30 PM NR SPOT RFI
5181 NMSCEW/P-IV/STR/2019/5117 5117 Checking of Shuttering and reinforcement for 3rd lift at retaining wall W1 PUP Km 204+470 LHS 6-Oct-19 8:00 AM DONE
5182 NMSCEW/P-IV/STR/2019/5118 5118 Checking and Pouring concrete for 3rd lift at retaining wall W1 PUP Km 204+470 LHS 6-Oct-19 8:30 AM DONE
5183 NMSCEW/P-IV/STR/2019/5119 5119 Checking of Shuttering and reinforcement for 3rd lift at retaining wall W1 PUP Km 205+430 LHS 6-Oct-19 9:00 AM DONE
5184 NMSCEW/P-IV/STR/2019/5120 5120 Checking and Pouring concrete for 3rd lift at retaining wall W1 PUP Km 205+430 LHS 6-Oct-19 9:30 AM DONE
5185 NMSCEW/P-IV/STR/2019/5121 5121 Checking of Shuttering and reinforcement for 3rd lift at wall A1 & A2 (U trough) PUP Km 187+835 6-Oct-19 10:00 AM DONE
5186 NMSCEW/P-IV/STR/2019/5122 5122 Checking and Pouring concrete(M-30) for 3rd lift at wall A1 & A2 (U trough) PUP Km 187+835 6-Oct-19 10:30 AM DONE
5187 NMSCEW/P-IV/STR/2019/5123 5123 Checking layout ,level and structural excavation for PCC at retaining wall A2 PUP Km 190+650 LHS 6-Oct-19 10:40 AM DONE
5188 NMSCEW/P-IV/STR/2019/5124 5124 Checking top Level & Laying concretem(M-10) for PCC at retaining wall A2 PUP Km 190+650 LHS 6-Oct-19 11:00 AM DONE
5189 NMSCEW/P-IV/STR/2019/5125 5125 Checking reinforcement ,shuttering for top slab Box culvert Km 182+350 LHS 6-Oct-19 4:00 PM DONE
5190 NMSCEW/P-IV/STR/2019/5126 5126 Checking and concrete(M-30) pouring for top slab Box culvert Km 182+350 LHS 6-Oct-19 4:30 PM DONE
5191 NMSCEW/P-IV/STR/2019/5127 5127 Checking of Shuttering and reinforcement for 2nd lift at median wall A1 & A2 PUP Km 165+300 6-Oct-19 5:00 PM DONE
5192 NMSCEW/P-IV/STR/2019/5128 5128 Checking and Pouring concrete for 2nd lift at median wall A1 & A2 PUP Km 165+300 6-Oct-19 5:30 PM DONE
5193 NMSCEW/P-IV/STR/2019/5129 5129 Checking of reinforcement, shuttering for pier cap at RA-02 Viaduct Km 202+190 Km 00+000 RHS 6-Oct-19 11:00 AM IPC-10 DONE
5194 NMSCEW/P-IV/STR/2019/5130 5130 Checking & pouring concrete for pier cap at RA-02 Viaduct Km 202+190 Km 00+000 RHS 6-Oct-19 11:30 AM IPC-10 DONE
5195 NMSCEW/P-IV/STR/2019/5131 5131 Checking of Shuttering and reinforcement for Pedestal at LP-01 Viaduct Km 202+190 LHS 6-Oct-19 10:10 AM
5196 NMSCEW/P-IV/STR/2019/5132 5132 Checking & pouring concrete for Pedestal at LP-01 Viaduct Km 202+190 LHS 6-Oct-19 10:45 AM
5197 NMSCEW/P-IV/STR/2019/5133 5133 Checking of reinforcement and shuttering for pier shaft final lift at RP-13 Viaduct Km 202+190 Km 00+000 RHS 6-Oct-19 12:00 PM IPC-10 DONE
5198 NMSCEW/P-IV/STR/2019/5134 5134 Checking and Pouring concrete for pier shaft final lift at RP-13 Viaduct Km 202+190 Km 00+000 RHS 6-Oct-19 12:30 PM IPC-10 DONE AE
Checking reinforcement for precast Box Culvert - I)
5199 NMSCEW/P-IV/STR/2019/5135 5135 2*2(2to4m) segment no-493,494,495,496,497,498,499 Box culvert Km 200+200 LHS 7-Oct-19 9:30 AM DONE
II) 3*3(2to4m) segment no-52,53
Checking for shuttering & Pouring of Concreting Grade =(M-30) for Precast Box Culvert I)
5200 NMSCEW/P-IV/STR/2019/5136 5136 2*2(2to4m) segment no-493,494,495,496,497,498,499 Box culvert Km 200+200 LHS 7-Oct-19 10:30 AM DONE
II) 3*3(2to4m) segment no-52,53
Checking of Shuttering and reinforcement for RE WALL PANEL precast TYPE -A
5201 NMSCEW/P-IV/STR/2019/5137 5137 50 NOS, TYPE -Sta 2 NOS, TYPE -Stb 3 NOS, TYPE -Stc 4 NOS, TYPE -Std 5 NOS, RE Wall Panel Km 200+200 LHS 7-Oct-19 10:00 AM DONE
TYPE -Ltc 12 NOS, TYPE -Ltd 4 NOS, at RE panel precast yard camp 2
Checking and Pouring concrete for RE WALL PANEL precast TYPE -A
5202 NMSCEW/P-IV/STR/2019/5138 5138 50 NOS, TYPE -Sta 2 NOS, TYPE -Stb 3 NOS, TYPE -Stc 4 NOS, TYPE -Std 5 NOS, RE Wall Panel Km 200+200 LHS 7-Oct-19 11:00 AM DONE
TYPE -Ltc 12 NOS, TYPE -Ltd 4 NOS, at RE panel precast yard camp 2
5203 NMSCEW/P-IV/STR/2019/5139 5139 Checking of side shuttering girder no-49,50,51,52 at bed no-01,Girder Type-2 Girder Km 200+200 LHS 7-Oct-19 11:10 AM
Approval for pouring of girder no- 49,50,51,52 at bed no-01, (Grade of concrete M-50)
5204 NMSCEW/P-IV/STR/2019/5140 5140 Girder Km 200+200 LHS 7-Oct-19 11:40 AM
Girder Type- 2
Checking for stressing and remove slagness of H.T. wires at Girder no-33,34,35,36 at bed no
5205 NMSCEW/P-IV/STR/2019/5141 5141 Girder Km 200+200 LHS 7-Oct-19 4:00 PM
-07, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no 33,34,35,36 at bed no -07, Girder Type-1 at casting yard
5206 NMSCEW/P-IV/STR/2019/5142 5142 Girder Km 200+200 LHS 7-Oct-19 4:30 PM
camp -2
5207 NMSCEW/P-IV/STR/2019/5143 5143 Checking of reinforcement and shuttering for pier shaft 1st lift at LP-03 Viaduct Km 195+900 Km 00+000 LHS 7-Oct-19 4:10 PM IPC-11 Approved
5208 NMSCEW/P-IV/STR/2019/5144 5144 Checking and Pouring concrete for pier shaft 1st lift at LP-03 Viaduct Km 195+900 Km 00+000 LHS 7-Oct-19 4:40 PM IPC-11 Approved AE
5209 NMSCEW/P-IV/STR/2019/5145 5145 Checking layout ,level for PCC at LP-03 Viaduct Km 213+915 LHS 7-Oct-19 11:15 AM
5210 NMSCEW/P-IV/STR/2019/5146 5146 Checking layout ,level for PCC at RP-01 Viaduct Km 213+915 RHS 7-Oct-19 11:25 AM
5211 NMSCEW/P-IV/STR/2019/5147 5147 Checking top Level & Laying concrete for PCC at LP-03 Viaduct Km 213+915 LHS 7-Oct-19 12:10 PM
5212 NMSCEW/P-IV/STR/2019/5148 5148 Checking top Level & Laying concrete for PCC at RP-01 Viaduct Km 213+915 RHS 7-Oct-19 12:20 PM
5213 NMSCEW/P-IV/STR/2019/5149 5149 Checking of reinforcement and shuttering for pier shaft 1st lift at LP-04 Viaduct Km 200+920 LHS 7-Oct-19 4:25 PM
5214 NMSCEW/P-IV/STR/2019/5150 5150 Checking and Pouring concrete for pier shaft 1st lift at LP-04 Viaduct Km 200+920 LHS 7-Oct-19 4:45 PM
5215 NMSCEW/P-IV/STR/2019/5151 5151 Checking of reinforcement, shuttering for abutment cap at LA-01 Viaduct Km 195+900 Km 00+000 LHS 7-Oct-19 3:15 PM IPC-09 DONE
5216 NMSCEW/P-IV/STR/2019/5152 5152 Checking & pouring concrete for abutment cap at LA-01 Viaduct Km 195+900 Km 00+000 LHS 7-Oct-19 3:44 PM IPC-09 DONE
5217 NMSCEW/P-IV/STR/2019/5153 5153 Checking of reinforcement, shuttering for pier cap at RP-10 Viaduct Km 196+560 Km 00+000 RHS 7-Oct-19 10:33 AM IPC-09 DONE AE
5218 NMSCEW/P-IV/STR/2019/5154 5154 Checking & pouring concrete(M-35) for pier cap at RP-10 Viaduct Km 196+560 Km 00+000 RHS 7-Oct-19 10:50 AM IPC-09 DONE AE
5219 NMSCEW/P-IV/STR/2019/5155 5155 Checking of reinforcement and shuttering for pier shaft 2nd & final lift at RP-01 Viaduct Km 196+560 RHS 7-Oct-19 12:00 PM
5220 NMSCEW/P-IV/STR/2019/5156 5156 Checking and Pouring concrete for pier shaft 2nd & final lift at RP-01 Viaduct Km 196+560 RHS 7-Oct-19 12:30 PM
5221 NMSCEW/P-IV/STR/2019/5157 5157 Checking of reinforcement, shuttering for pier cap at LP-01 Viaduct Km 169+800 Km 00+000 LHS 7-Oct-19 3:20 PM IPC-09 DONE AE
5222 NMSCEW/P-IV/STR/2019/5158 5158 Checking & pouring concrete for pier cap at LP-01 Viaduct Km 169+800 Km 00+000 LHS 7-Oct-19 3:45 PM IPC-09 DONE AE
5223 NMSCEW/P-IV/STR/2019/5159 5159 Checking of Shuttering and reinforcement for Pedestal at LP-06 Viaduct Km 169+800 LHS 7-Oct-19 4:08 PM DONE
5224 NMSCEW/P-IV/STR/2019/5160 5160 Checking & pouring concrete for Pedestal at LP-06 Viaduct Km 169+800 LHS 7-Oct-19 4:42 PM DONE
5225 NMSCEW/P-IV/STR/2019/5161 5161 Checking of reinforcement and shuttering for pier shaft 3rd & final lift at LA-01 Viaduct Km 169+800 LHS 7-Oct-19 11:18 AM DONE
5226 NMSCEW/P-IV/STR/2019/5162 5162 Checking and Pouring concrete for pier shaft 3rd & final lift at LA-01 Viaduct Km 169+800 LHS 7-Oct-19 11:50 AM DONE
5227 NMSCEW/P-IV/STR/2019/5163 5163 Checking reinforcement ,shuttering for U type bottom slab with haunch PUP Km 190+650 7-Oct-19 9:30 AM NR
5228 NMSCEW/P-IV/STR/2019/5164 5164 Checking and concrete(M-30) pouring for U type bottom slab with haunch PUP Km 190+650 7-Oct-19 10:12 AM NR
5229 NMSCEW/P-IV/STR/2019/5165 5165 Checking of Shuttering and reinforcement for 1st lift at median wall W1 & W2 PUP Km 199+060 7-Oct-19 11:05 AM DONE
5230 NMSCEW/P-IV/STR/2019/5166 5166 Checking and Pouring concrete for 1st lift at median wall W1 & W2 PUP Km 199+060 7-Oct-19 11:35 AM DONE
5231 NMSCEW/P-IV/STR/2019/5167 5167 Checking of Shuttering and reinforcement for 2nd lift at wall W2 MNB Km 199+360 LHS 7-Oct-19 2:00 PM DONE
5232 NMSCEW/P-IV/STR/2019/5168 5168 Checking and Pouring concrete for 2nd lift at W2 MNB Km 199+360 LHS 7-Oct-19 2:30 PM DONE
5233 NMSCEW/P-IV/STR/2019/5169 5169 Checking of Shuttering and reinforcement for 3rd lift at retaining wall W2 PUP Km 205+430 RHS 7-Oct-19 8:00 AM DONE
5234 NMSCEW/P-IV/STR/2019/5170 5170 Checking and Pouring concrete for 3rd lift at retaining wall W2 PUP Km 205+430 RHS 7-Oct-19 8:30 AM DONE
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5235 NMSCEW/P-IV/STR/2019/5171 5171 Box culvert Km 175+500 LHS 7-Oct-19 10:17 AM
Culvert (3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-238,239,240,241,242
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5236 NMSCEW/P-IV/STR/2019/5172 5172 Box culvert Km 175+500 LHS 7-Oct-19 11:50 AM
Culvert (2×2) (Cushion 4 to 6m) at precast yard camp-1,Segment no.-1,2,3
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5237 NMSCEW/P-IV/STR/2019/5173 5173 Box culvert Km 175+500 LHS 7-Oct-19 2:40 PM
Culvert (2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-291,292,293,294
5238 NMSCEW/P-IV/STR/2019/5174 5174 Checking layout ,level for PCC at LP-02 Viaduct Km 213+915 LHS 7-Oct-19 10:03 AM
5239 NMSCEW/P-IV/STR/2019/5175 5175 Checking layout ,level for PCC at RP-02 Viaduct Km 213+915 Km 00+000 RHS 7-Oct-19 10:13 AM IPC-11 Approved AE
5240 NMSCEW/P-IV/STR/2019/5176 5176 Checking top Level & Laying concrete for PCC at LP-02 Viaduct Km 213+915 LHS 7-Oct-19 10:41 AM
5241 NMSCEW/P-IV/STR/2019/5177 5177 Checking top Level & Laying concrete for PCC at RP-02 Viaduct Km 213+915 Km 00+000 RHS 7-Oct-19 10:52 AM IPC-11 Approved AE
5242 NMSCEW/P-IV/STR/2019/5178 5178 Checking of Shuttering,reinforcement & Pouring concrete for 2nd lift at median wall W1 PUP Km 199+060 8-Oct-19 9:00 AM DONE
5243 NMSCEW/P-IV/STR/2019/5179 5179 Checking of Shuttering,reinforcement & Pouring concrete for raft at retaining wall A1 LVUP Km 173+400 LHS 8-Oct-19 5:00 PM DONE
5244 NMSCEW/P-IV/STR/2019/5180 5180 Checking of Shuttering,reinforcement & Pouring concrete for 1st lift at retaining wall A1 LVUP Km 173+400 RHS 8-Oct-19 2:00 PM DONE
5245 NMSCEW/P-IV/STR/2019/5181 5181 Checking layout ,level and structural excavation for PCC at U- type bottom slab PUP Km 189+000 8-Oct-19 2:15 PM DONE
5246 NMSCEW/P-IV/STR/2019/5182 5182 Checking top Level & Laying concretem(M-10) for PCC at U- type bottom slab PUP Km 189+000 8-Oct-19 3:10 PM DONE
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5247 NMSCEW/P-IV/STR/2019/5183 5183 Box culvert Km 175+500 LHS 8-Oct-19 10:20 AM
Culvert (3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-243,244,245,246,247
NR
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5248 NMSCEW/P-IV/STR/2019/5184 5184 Box culvert Km 175+500 LHS 8-Oct-19 12:00 PM
Culvert (2×2) (Cushion 4 to 6m) at precast yard camp-1,Segment no.-4,5,6
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5249 NMSCEW/P-IV/STR/2019/5185 5185 Box culvert Km 175+500 LHS 8-Oct-19 3:30 PM
Culvert (2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-295,296,297,298
Checking reinforcement ,shuttering and concrete(M-30) pouring for U type bottom slab with
5250 NMSCEW/P-IV/STR/2019/5186 5186 PUP Km 190+650 8-Oct-19 4:30 PM DONE
haunch
Checking for stressing and remove slagness of H.T. wires at Girder no-53,54,55,56 at bed no
5251 NMSCEW/P-IV/STR/2019/5187 5187 Girder Km 200+200 LHS 9-Oct-19 12:00 PM
-04, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no -53,54,55,56 at bed no -04, Girder Type-2 at casting yard
5252 NMSCEW/P-IV/STR/2019/5188 5188 Girder Km 200+200 LHS 9-Oct-19 12:30 PM
camp -2
5253 NMSCEW/P-IV/STR/2019/5189 5189 Checking layout ,level for PCC at abutment RA-02 Viaduct Km 200+920 RHS 9-Oct-19 4:00 PM
5254 NMSCEW/P-IV/STR/2019/5190 5190 Checking top Level & Laying concrete for PCC at abutment RA-02 Viaduct Km 200+920 RHS 9-Oct-19 4:30 PM
5255 NMSCEW/P-IV/STR/2019/5191 5191 Checking of reinforcement,shuttering and Pouring concrete for pier shaft 1st lift at LP-04 Viaduct Km 200+920 LHS 9-Oct-19 4:45 PM
Checking of reinforcement,shuttering and Pouring concrete for pier shaft 2nd & final lift at
5256 NMSCEW/P-IV/STR/2019/5192 5192 Viaduct Km 196+560 Km 00+000 RHS 9-Oct-19 10:20 AM IPC-11 Approved
RP-01
5257 NMSCEW/P-IV/STR/2019/5193 5193 Checking of reinforcement,shuttering and Pouring concrete for pier shaft 1st lift at LP-02 Viaduct Km 195+900 LHS 9-Oct-19 3:00 PM
5258 NMSCEW/P-IV/STR/2019/5194 5194 Checking layout ,level for PCC at RP-01 Viaduct Km 213+915 Km 00+000 RHS 9-Oct-19 10:00 AM IPC-11 Approved
5259 NMSCEW/P-IV/STR/2019/5195 5195 Checking layout ,level for PCC at LP-02 Viaduct Km 213+915 Km 00+000 LHS 9-Oct-19 10:00 AM IPC-11 Approved AE
5260 NMSCEW/P-IV/STR/2019/5196 5196 Checking top Level & Laying concrete for PCC at RP-01 Viaduct Km 213+915 Km 00+000 RHS 9-Oct-19 11:00 AM IPC-11 Approved AE
5261 NMSCEW/P-IV/STR/2019/5197 5197 Checking top Level & Laying concrete for PCC at LP-02 Viaduct Km 213+915 Km 00+000 LHS 9-Oct-19 11:15 AM IPC-11 Approved AE
Checking of reinforcement,shuttering and Pouring concrete for pier shaft first and final lift at
5262 NMSCEW/P-IV/STR/2019/5198 5198 Viaduct Km 202+190 Km 00+000 RHS 9-Oct-19 2:30 PM IPC-10 DONE
RA-01 AE
5263 NMSCEW/P-IV/STR/2019/5199 5199 Checking of reinforcement,shuttering and Pouring concrete for pier shaft final lift at LP-10 Viaduct Km 202+190 Km 00+000 LHS 9-Oct-19 4:15 PM IPC-10 DONE
5264 NMSCEW/P-IV/STR/2019/5200 5200 Checking of Shuttering,reinforcement and pouring concrete for Pedestal at LP-01 Viaduct Km 202+190 LHS 9-Oct-19 2:50 PM
5265 NMSCEW/P-IV/STR/2019/5201 5201 Checking of Shuttering,reinforcement and pouring concrete for abutment raft at LA-02 MJB 205+610 Km 00+000 LHS 9-Oct-19 2:00 PM IPC-09 DONE AE
Checking of Shuttering,reinforcement and Pouring concrete for RE WALL PANEL precast
TYPE -A 50 NOS, TYPE-B 10NOS, TYPE -Sta 2 NOS, TYPE -Stb 2 NOS, TYPE -Stc 2
5266 NMSCEW/P-IV/STR/2019/5202 5202 RE Wall Panel Km 200+200 LHS 9-Oct-19 10:50 AM DONE
NOS, TYPE -Std 2 NOS, TYPE -Ltc 2 NOS, TYPE -Ltd 2 NOS, at RE panel precast yard
camp 2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no- 49,50,51,52 at
5267 NMSCEW/P-IV/STR/2019/5203 5203 Girder Km 200+200 LHS 9-Oct-19 8:00 AM
bed no-01,Girder Type- 2
5268 NMSCEW/P-IV/STR/2019/5204 5204 Checking top Level & Laying concrete(M-10) for PCC Utility Duct Km 174+360 BHS 9-Oct-19 11:05 AM NR
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at retaining wall A1 &
5269 NMSCEW/P-IV/STR/2019/5205 5205 PUP Km 165+300 LHS 9-Oct-19 4:30 PM DONE
A2
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert
5270 NMSCEW/P-IV/STR/2019/5206 5206 I)2*2(2to4m) segment no- 500,501,502,503,504,505,506,507,508,509,510,511,512,513 Box culvert Km 200+200 LHS 10-Oct-19 10:00 AM DONE
II)3x3(2to4) segment no. 54,55
Checking of reinforcement,shuttering and Pouring concrete for 4th lift at U type retaining wall
5271 NMSCEW/P-IV/STR/2019/5207 5207 PUP Km 203+560 BHS 10-Oct-19 8:30 AM DONE
W1 & W2
5272 NMSCEW/P-IV/STR/2019/5208 5208 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall W2 MNB Km 203+409 RHS 10-Oct-19 2:00 PM DONE
5273 NMSCEW/P-IV/STR/2019/5209 5209 Checking of Shuttering,reinforcement & Pouring concrete for 2nd lift at median wall W2 PUP Km 199+060 10-Oct-19 3:00 PM DONE
5274 NMSCEW/P-IV/STR/2019/5210 5210 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at wall W2 MNB Km 199+360 LHS 10-Oct-19 8:45 AM DONE
5275 NMSCEW/P-IV/STR/2019/5211 5211 Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at wall W1 & W2 PUP Km 199+060 LHS 10-Oct-19 4:30 PM DONE
5276 NMSCEW/P-IV/STR/2019/5212 5212 Checking layout ,level for PCC Box culvert Km 193+940 BHS 10-Oct-19 8:00 AM DONE
5277 NMSCEW/P-IV/STR/2019/5213 5213 Checking top Level & Laying concrete for PCC Box culvert Km 193+940 BHS 10-Oct-19 9:00 AM DONE
5278 NMSCEW/P-IV/STR/2019/5214 5214 Checking of reinforcement,shuttering and Pouring concrete for 5th lift at wall A1 & A2 VUP Km 176+614 Km 00+000 RHS 10-Oct-19 10:30 AM IPC-10 DONE
5279 NMSCEW/P-IV/STR/2019/5215 5215 Checking of reinforcement,shuttering and Pouring concrete for 5th lift at wall A1 & A2 VUP Km 179+983 Km 00+000 LHS 10-Oct-19 3:30 PM IPC-10 DONE
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at retaining wall A1 &
5280 NMSCEW/P-IV/STR/2019/5216 5216 PUP Km 171+110 RHS 10-Oct-19 2:00 PM DONE
A2
5281 NMSCEW/P-IV/STR/2019/5217 5217 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at retaining wall A1 PUP Km 171+110 LHS 10-Oct-19 2:30 PM DONE
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at retaining wall A1 &
5282 NMSCEW/P-IV/STR/2019/5218 5218 PUP Km 174+095 LHS 10-Oct-19 12:00 PM DONE
A2
5283 NMSCEW/P-IV/STR/2019/5219 5219 Checking top Level & Laying concrete(M-10) for PCC Utility Duct Km 174+360 Km 00+000 BHS 10-Oct-19 10:05 AM IPC-09 DONE
5284 NMSCEW/P-IV/STR/2019/5220 5220 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-08 Viaduct Km 169+800 LHS 10-Oct-19 2:40 PM NR
5285 NMSCEW/P-IV/STR/2019/5221 5221 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-09 Viaduct Km 169+800 LHS 10-Oct-19 4:00 PM DONE
5286 NMSCEW/P-IV/STR/2019/5222 5222 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-10 Viaduct Km 169+800 LHS 10-Oct-19 4:30 PM DONE
5287 NMSCEW/P-IV/STR/2019/5223 5223 Checking layout ,level and structural excavation for PCC Utility Duct Km 180+800 BHS 10-Oct-19 10:08 AM DONE
5288 NMSCEW/P-IV/STR/2019/5224 5224 Checking top Level & Laying concretem(M-10) for PCC Utility Duct Km 180+800 BHS 10-Oct-19 10:35 AM DONE
Checking for stressing and remove slagness of H.T. wires at Girder no-37,38,39,40 at bed no
5289 NMSCEW/P-IV/STR/2019/5225 5225 Girder Km 200+200 LHS 10-Oct-19 3:30 PM
-06, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no 37,38,39,40 at bed no -06, Girder Type-1 at casting yard
5290 NMSCEW/P-IV/STR/2019/5226 5226 Girder Km 200+200 LHS 10-Oct-19 4:00 PM
camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-33,34,35,36 at bed no
5291 NMSCEW/P-IV/STR/2019/5227 5227 Girder Km 200+200 LHS 10-Oct-19 11:30 AM
-07, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no 33,34,35,36 at bed no -07, Girder Type-1 at casting yard
5292 NMSCEW/P-IV/STR/2019/5228 5228 Girder Km 200+200 LHS 10-Oct-19 12:00 PM
camp -2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no- 53,54,55,56 at
5293 NMSCEW/P-IV/STR/2019/5229 5229 Girder Km 200+200 LHS 10-Oct-19 6:00 PM
bed no-04,Girder Type- 2
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5294 NMSCEW/P-IV/STR/2019/5230 5230 Box culvert Km 175+500 LHS 10-Oct-19 9:35 AM DONE
Culvert (3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-242,243
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5295 NMSCEW/P-IV/STR/2019/5231 5231 Box culvert Km 175+500 LHS 10-Oct-19 10:50 AM
Culvert (3×3) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-1,2,3
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5296 NMSCEW/P-IV/STR/2019/5232 5232 Box culvert Km 175+500 LHS 10-Oct-19 12:15 PM
Culvert (2×2) (Cushion 4 to 6m) at precast yard camp-1,Segment no.-7,8,9,10
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5297 NMSCEW/P-IV/STR/2019/5233 5233 Box culvert Km 175+500 LHS 10-Oct-19 3:28 PM
Culvert (2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-294,295,296,297,298
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert
5298 NMSCEW/P-IV/STR/2019/5234 5234 Box culvert Km 200+200 LHS 11-Oct-19 10:00 AM DONE
I)2*2(2to4m) segment no- 514,515,516,517,518,519,520
II)3x3(2to4) segment no- 56
5299 NMSCEW/P-IV/STR/2019/5235 5235 Checking of Shuttering,reinforcement & Pouring concrete for 3rd lift at median wall W1 PUP Km 199+060 11-Oct-19 9:30 AM DONE
5300 NMSCEW/P-IV/STR/2019/5236 5236 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at wall W4 MNB Km 199+360 LHS 11-Oct-19 3:00 PM DONE
5301 NMSCEW/P-IV/STR/2019/5237 5237 Checking layout ,level for PCC at retaining wall W1 & W2 PUP Km 199+060 RHS 11-Oct-19 9:00 AM DONE
5302 NMSCEW/P-IV/STR/2019/5238 5238 Checking top Level & Laying concrete for PCC at retaining wall W1 & W2 PUP Km 199+060 RHS 11-Oct-19 10:15 AM DONE
5303 NMSCEW/P-IV/STR/2019/5239 5239 Checking layout ,level for raft MNB Km 203+409 LHS 11-Oct-19 2:00 PM WRONG RFI
5304 NMSCEW/P-IV/STR/2019/5240 5240 Checking of Shuttering,reinforcement & Pouring concrete for raft MNB Km 203+409 LHS 11-Oct-19 2:30 PM WRONG RFI
5305 NMSCEW/P-IV/STR/2019/5241 5241 Checking of reinforcement, shuttering & pouring concrete(M-35) for pier cap at LP-02 Viaduct Km 169+800 LHS 11-Oct-19 2:10 PM
NR
5306 NMSCEW/P-IV/STR/2019/5242 5242 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-08 Viaduct Km 169+800 LHS 11-Oct-19 12:00 PM DONE
5307 NMSCEW/P-IV/STR/2019/5243 5243 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-11 Viaduct Km 169+800 LHS 11-Oct-19 1:00 PM DONE
5308 NMSCEW/P-IV/STR/2019/5244 5244 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-12 Viaduct Km 169+800 LHS 11-Oct-19 2:50 PM NR
5309 NMSCEW/P-IV/STR/2019/5245 5245 Checking of Shuttering,reinforcement & pouring concrete(M-45) for Pedestal at LP-13 Viaduct Km 169+800 LHS 11-Oct-19 4:00 PM NR
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at retaining wall A1 &
5310 NMSCEW/P-IV/STR/2019/5246 5246 LVUP Km 173+400 RHS 11-Oct-19 2:25 PM DONE
A2
5311 NMSCEW/P-IV/STR/2019/5247 5247 Checking layout ,level and structural excavation Utility Duct Km 170+830 BHS 11-Oct-19 10:10 AM DONE
Checking for stressing and remove slagness of H.T. wires at Girder no-57,58,59,60 at bed no
5312 NMSCEW/P-IV/STR/2019/5248 5248 Girder Km 200+200 LHS 11-Oct-19 4:10 PM
-02, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no 57,58,59,60 at bed no -02, Girder Type-2 at casting yard
5313 NMSCEW/P-IV/STR/2019/5249 5249 Girder Km 200+200 LHS 11-Oct-19 4:30 PM
camp -2
5314 NMSCEW/P-IV/STR/2019/5250 5250 Checking of reinforcement, shuttering & pouring concrete for pier cap at RP-08 Viaduct Km 196+560 Km 00+000 RHS 11-Oct-19 11:40 AM IPC-09 DONE AE
5315 NMSCEW/P-IV/STR/2019/5251 5251 Checking of reinforcement, shuttering & pouring concrete for abutment cap at RA-01 Viaduct Km 195+900 Km 00+000 RHS 11-Oct-19 2:00 PM IPC-09 DONE
5316 NMSCEW/P-IV/STR/2019/5252 5252 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st/final lift at LP-02 Viaduct Km 195+900 Km 00+000 LHS 11-Oct-19 3:00 PM IPC-11 Approved AE
5317 NMSCEW/P-IV/STR/2019/5253 5253 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-13 Viaduct Km 202+190 LHS 11-Oct-19 4:16 PM
5318 NMSCEW/P-IV/STR/2019/5254 5254 Checking of reinforcement, shuttering & pouring concrete for raft at RP-08 Viaduct Km 202+190 RHS 11-Oct-19 3:15 PM
5319 NMSCEW/P-IV/STR/2019/5255 5255 Checking of reinforcement, shuttering & pouring concrete for abutment raft at LA-02 Viaduct Km 200+920 Km 00+000 LHS 11-Oct-19 10:35 AM IPC-10 DONE AE
5320 NMSCEW/P-IV/STR/2019/5256 5256 Checking layout ,level for PCC at LP-01,LP-03 Viaduct Km 213+915 LHS 11-Oct-19 2:14 PM
5321 NMSCEW/P-IV/STR/2019/5257 5257 Checking top Level & Laying concrete for PCC at LP-01 Viaduct Km 213+915 Km 00+000 LHS 11-Oct-19 3:09 PM IPC-11 Approved AE
5322 NMSCEW/P-IV/STR/2019/5258 5258 Checking of reinforcement, shuttering & pouring concrete for raft at LP-12 Viaduct Km 202+190 LHS 11-Oct-19 5:00 PM
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5323 NMSCEW/P-IV/STR/2019/5259 5259 Box culvert Km 175+500 LHS 11-Oct-19 9:22 AM
Culvert (3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-244,243
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5324 NMSCEW/P-IV/STR/2019/5260 5260 Box culvert Km 175+500 LHS 11-Oct-19 10:42 AM
Culvert (3×3) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-1,2,3
NR
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5325 NMSCEW/P-IV/STR/2019/5261 5261 Box culvert Km 175+500 LHS 11-Oct-19 12:18 PM
Culvert (2×2) (Cushion 4 to 6m) at precast yard camp-1,Segment no.-11,12,13
NR
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5326 NMSCEW/P-IV/STR/2019/5262 5262 Box culvert Km 175+500 LHS 11-Oct-19 3:37 PM
Culvert (2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-303,304,305,306
NR
5327 NMSCEW/P-IV/STR/2019/5263 5263 Checking of reinforcement, shuttering & pouring concrete for bottom slab Box culvert Km 187+677 RHS 11-Oct-19 10:05 AM DONE
5328 NMSCEW/P-IV/STR/2019/5264 5264 Checking layout ,level and structural excavation at U type retaining wall VUP Km 176+614 12-Oct-19 9:30 AM DONE
5329 NMSCEW/P-IV/STR/2019/5265 5265 Checking layout ,level and structural excavation at U type retaining wall A1 & A2 MNB Km 176+875 12-Oct-19 11:30 AM NR
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no- 33,34,35,36 at
5330 NMSCEW/P-IV/STR/2019/5266 5266 Girder Km 200+200 LHS 12-Oct-19 4:00 PM
bed no-07,Girder Type- 1
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no- 37,38,39,40 at
5331 NMSCEW/P-IV/STR/2019/5267 5267 Girder Km 200+200 LHS 12-Oct-19 6:00 PM
bed no-08,Girder Type- 1
5332 NMSCEW/P-IV/STR/2019/5268 5268 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-03 Viaduct Km 195+900 LHS 12-Oct-19 2:00 PM
5333 NMSCEW/P-IV/STR/2019/5269 5269 Checking layout ,level and structural excavation Box culvert Km 162+832 BHS 12-Oct-19 2:30 PM NR
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 1st lift at U type wall
5334 NMSCEW/P-IV/STR/2019/5270 5270 PUP Km 190+650 12-Oct-19 5:00 PM
A1 & A2 NR
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert
5335 NMSCEW/P-IV/STR/2019/5271 5271 Box culvert Km 200+200 LHS 12-Oct-19 10:00 AM DONE
I)2*2(2to4m) segment no- 521,522,523,524,525,526,527
5336 NMSCEW/P-IV/STR/2019/5272 5272 Checking of reinforcement,shuttering and Pouring concrete for 5th lift at retaining wall W1 PUP Km 205+430 RHS 12-Oct-19 8:00 AM DONE
5337 NMSCEW/P-IV/STR/2019/5273 5273 Checking of reinforcement, shuttering & pouring concrete for raft at RP-08 Viaduct Km 202+190 RHS 12-Oct-19 3:30 PM
5338 NMSCEW/P-IV/STR/2019/5274 5274 Checking of reinforcement, shuttering & pouring concrete for raft at LP-12 Viaduct Km 202+190 Km 00+000 LHS 12-Oct-19 4:30 PM IPC-10 DONE AE
5339 NMSCEW/P-IV/STR/2019/5275 5275 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-02 Viaduct Km 202+190 LHS 12-Oct-19 3:00 PM
Checking of Shuttering,reinforcement & pouring concrete(M-35) for 1st lift at wall A1 & A2
5340 NMSCEW/P-IV/STR/2019/5276 5276 MNB loop-B Km 01+980 12-Oct-19 10:15 AM DONE
(Loop-B)
Checking of Shuttering,reinforcement & pouring concrete(M-35) for 3rd lift at wall A1 & A2
5341 NMSCEW/P-IV/STR/2019/5277 5277 MNB loop-A Km 01+980 12-Oct-19 2:12 PM
(Loop-A) NR
5342 NMSCEW/P-IV/STR/2019/5278 5278 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-12 Viaduct Km 169+800 LHS 12-Oct-19 2:00 PM DONE
5343 NMSCEW/P-IV/STR/2019/5279 5279 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-13 Viaduct Km 169+800 LHS 12-Oct-19 2:30 PM NR
5344 NMSCEW/P-IV/STR/2019/5280 5280 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at RP-11 Viaduct Km 169+800 RHS 12-Oct-19 3:30 PM NR
5345 NMSCEW/P-IV/STR/2019/5281 5281 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at RP-12 Viaduct Km 169+800 RHS 12-Oct-19 3:45 PM NR
5346 NMSCEW/P-IV/STR/2019/5282 5282 Checking of reinforcement, shuttering & pouring concrete for pier cap at LP-03 Viaduct Km 169+800 LHS 12-Oct-19 3:10 PM NR
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5347 NMSCEW/P-IV/STR/2019/5283 5283 Box culvert Km 175+500 LHS 12-Oct-19 10:15 AM
Culvert (2×2) (Cushion 4 to 6m) at precast yard camp-1,Segment no.-14,15,16
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5348 NMSCEW/P-IV/STR/2019/5284 5284 Box culvert Km 175+500 LHS 12-Oct-19 11:40 AM
Culvert (2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-302,307,308,309
5349 NMSCEW/P-IV/STR/2019/5285 5285 Checking of Shuttering,reinforcement & pouring concrete for 3rd lift at median wall A1 & A2 PUP Km 165+300 12-Oct-19 4:30 PM
NR
5350 NMSCEW/P-IV/STR/2019/5286 5286 Checking top Level & Laying concrete for PCC at U type retaining wall VUP Km 176+614 13-Oct-19 12:30 PM DONE
5351 NMSCEW/P-IV/STR/2019/5287 5287 Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall W2 PUP Km 205+430 RHS 13-Oct-19 8:00 AM DONE
5352 NMSCEW/P-IV/STR/2019/5288 5288 Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall W2 PUP Km 205+430 LHS 13-Oct-19 10:00 AM DONE
5353 NMSCEW/P-IV/STR/2019/5289 5289 Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall W2 PUP Km 203+560 RHS 13-Oct-19 11:00 AM DONE
5354 NMSCEW/P-IV/STR/2019/5290 5290 Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at median wall W2 PUP Km 199+060 13-Oct-19 9:30 AM DONE
5355 NMSCEW/P-IV/STR/2019/5291 5291 Checking layout ,Level & Laying concrete for PCC at retaining wall W1 & W2 PUP Km 193+880 LHS 13-Oct-19 9:15 AM DONE
5356 NMSCEW/P-IV/STR/2019/5292 5292 Checking layout ,Level & Laying concrete for PCC at retaining wall W2 PUP Km 203+560 LHS 13-Oct-19 9:00 AM DONE
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at median wall A1 &
5357 NMSCEW/P-IV/STR/2019/5293 5293 PUP Km 165+300 13-Oct-19 4:30 PM DONE
A2
5358 NMSCEW/P-IV/STR/2019/5294 5294 Checking top Level & Laying concrete for PCC at median wall VUP Km 166+987 13-Oct-19 3:00 PM DONE
5359 NMSCEW/P-IV/STR/2019/5295 5295 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at RP-10 Viaduct Km 169+800 RHS 13-Oct-19 9:06 AM DONE
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5360 NMSCEW/P-IV/STR/2019/5296 5296 Box culvert Km 175+500 LHS 13-Oct-19 9:29 AM
Culvert (3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-245,246
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5361 NMSCEW/P-IV/STR/2019/5297 5297 Box culvert Km 175+500 LHS 13-Oct-19 10:43 AM DONE
Culvert (3×3) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-4,5,6
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5362 NMSCEW/P-IV/STR/2019/5298 5298 Box culvert Km 175+500 LHS 13-Oct-19 12:27 PM
Culvert (2×2) (Cushion 4 to 6m) at precast yard camp-1,Segment no.-11,12,13
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5363 NMSCEW/P-IV/STR/2019/5299 5299 Box culvert Km 175+500 LHS 13-Oct-19 3:57 PM
Culvert (2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-303,304,305,306
Checking reinforcement ,shuttering and concrete(M-30) pouring for bottom slab at retaining
5364 NMSCEW/P-IV/STR/2019/5300 5300 PUP Km 187+835 RHS 13-Oct-19 8:39 AM DONE
wall A1
5365 NMSCEW/P-IV/STR/2019/5301 5301 Checking reinforcement ,shuttering and concrete(M-30) pouring for 1st lift at U trough wall PUP Km 190+650 13-Oct-19 2:00 PM
NR
Checking of Shuttering,reinforcement & pouring concrete(M-35) for 3rd lift at wall A1 & A2
5366 NMSCEW/P-IV/STR/2019/5302 5302 MNB loop-A Km 01+980 13-Oct-19 2:12 PM DONE
(Loop-A)
Checking of Shuttering,reinforcement & pouring concrete(M-35) for 2nd lift at wall A1 & A2
5367 NMSCEW/P-IV/STR/2019/5303 5303 MNB loop-B Km 01+980 13-Oct-19 4:00 PM
(Loop-B) NR
5368 NMSCEW/P-IV/STR/2019/5304 5304 Checking of Shuttering,reinforcement & pouring concrete(M-30) for raft at retaining wall PUP Km 184+190 13-Oct-19 5:00 PM DONE
5369 NMSCEW/P-IV/STR/2019/5305 5305 Checking of Shuttering,reinforcement & pouring concrete for pier cap at LP-02 Viaduct Km 169+800 Km 00+000 LHS 13-Oct-19 9:15 AM IPC-09 DONE AE
5370 NMSCEW/P-IV/STR/2019/5306 5306 Checking of Shuttering,reinforcement & pouring concrete for abutment at RA-02 MJB Km 205+610 RHS 14-Oct-19 11:00 AM DONE
5371 NMSCEW/P-IV/STR/2019/5307 5307 Checking layout ,Level & Laying concrete for PCC MJB 205+610 Km 00+000 LHS 14-Oct-19 2:00 PM IPC-09 DONE AE
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert I)
5372 NMSCEW/P-IV/STR/2019/5308 5308 2*2(2to4m) segment no.528,529,530,531,532,533,534 Box culvert Km 200+200 LHS 14-Oct-19 9:30 AM DONE
II) 3x3 (0to2m) segment no - 166
III) 3x3 (2to4m) segment no. - 57,58
5373 NMSCEW/P-IV/STR/2019/5309 5309 Checking of Shuttering,reinforcement & pouring concrete(M-30) for raft at retaining wall W2 PUP Km 203+560 LHS 14-Oct-19 8:00 AM DONE
5374 NMSCEW/P-IV/STR/2019/5310 5310 Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall W1 PUP Km 204+470 RHS 14-Oct-19 10:00 AM DONE
5375 NMSCEW/P-IV/STR/2019/5311 5311 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at wall W2 MNB Km 203+409 RHS 14-Oct-19 2:00 PM DONE
5376 NMSCEW/P-IV/STR/2019/5312 5312 Checking reinforcement ,shuttering and concrete(M-30) pouring for final lift at U trough wall PUP Km 187+835 14-Oct-19 10:10 AM
NR
5377 NMSCEW/P-IV/STR/2019/5313 5313 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall A2 Box culvert Km 163+570 Km 00+000 BHS 14-Oct-19 4:00 PM IPC-10 DONE AE
5378 NMSCEW/P-IV/STR/2019/5314 5314 Checking of reinforcement, shuttering & pouring concrete for pier cap at LP-08 Viaduct Km 202+190 Km 00+000 LHS 14-Oct-19 10:30 AM IPC-10 DONE AE
5379 NMSCEW/P-IV/STR/2019/5315 5315 Checking layout ,Level & Laying concrete for PCC at LP-03 Viaduct Km 213+915 LHS 14-Oct-19 3:00 PM IPC-14
5380 NMSCEW/P-IV/STR/2019/5316 5316 Checking layout ,Level & Laying concrete for PCC at RP-01,RP-07 Viaduct Km 213+915 RHS 14-Oct-19 4:00 PM
5381 NMSCEW/P-IV/STR/2019/5317 5317 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-03 Viaduct Km 202+190 RHS 14-Oct-19 4:30 PM
5382 NMSCEW/P-IV/STR/2019/5318 5318 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1stl lift at LP-04 Viaduct Km 200+920 LHS 14-Oct-19 5:00 PM
5383 NMSCEW/P-IV/STR/2019/5319 5319 Checking of reinforcement, shuttering & pouring concrete for raft at RP-08 Viaduct Km 202+190 Km 00+000 RHS 14-Oct-19 9:30 AM IPC-10 DONE AE
5384 NMSCEW/P-IV/STR/2019/5320 5320 Checking layout ,Level & Laying for PCC at RP-10 Viaduct Km 202+190 RHS 14-Oct-19 3:10 PM
Checking for stressing and remove slagness of H.T. wires at Girder no-41,42,43,44 at bed no
5385 NMSCEW/P-IV/STR/2019/5321 5321 Girder Km 200+200 LHS 14-Oct-19 5:10 PM
-06, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no 41,42,43,44 at bed no -06, Girder Type-1 at casting yard
5386 NMSCEW/P-IV/STR/2019/5322 5322 Girder Km 200+200 LHS 14-Oct-19 5:40 PM
camp -2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no- 57,58,59,60 at
5387 NMSCEW/P-IV/STR/2019/5323 5323 Girder Km 200+200 LHS 14-Oct-19 2:45 PM
bed no-02,Girder Type- 2
5388 NMSCEW/P-IV/STR/2019/5324 5324 Checking of reinforcement,shuttering and Pouring concrete(M-30) for 1st lift at U type wall PUP Km 190+650 14-Oct-19 11:00 AM DONE
5389 NMSCEW/P-IV/STR/2019/5325 5325 Checking of reinforcement, shuttering & pouring concrete for pier cap at LP-03 Viaduct Km 169+800 Km 00+000 LHS 14-Oct-19 11:00 AM IPC-09 DONE
5390 NMSCEW/P-IV/STR/2019/5326 5326 Checking of reinforcement and Pouring concrete for raft at 2x2 utility duct Utility duct Km 207+560 LHS 15-Oct-19 10:00 AM DONE
5391 NMSCEW/P-IV/STR/2019/5327 5327 Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall W1 PUP Km 203+560 RHS 15-Oct-19 8:00 AM DONE
5392 NMSCEW/P-IV/STR/2019/5328 5328 Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall W1 PUP Km 204+470 LHS 15-Oct-19 9:00 AM DONE
5393 NMSCEW/P-IV/STR/2019/5329 5329 Checking of reinforcement,shuttering and Pouring concrete for 5th lift at retaining wall W2 PUP Km 205+430 RHS 15-Oct-19 2:00 PM DONE
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert I)
5394 NMSCEW/P-IV/STR/2019/5330 5330 2*2(2to4m) segment no.535,536,537,538,539,540,541 Box culvert Km 200+200 LHS 15-Oct-19 9:30 AM DONE
II) 3x3 (0to2m) segment no - 167
III) 3x3 (2to4m) segment no. - 59,60,61
5395 NMSCEW/P-IV/STR/2019/5331 5331 Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall W1 PUP Km 205+430 LHS 15-Oct-19 10:30 AM DONE
5396 NMSCEW/P-IV/STR/2019/5332 5332 Checking layout ,level and structural excavation at U type retaining wall LVUP Km 178+323 15-Oct-19 10:40 AM DONE
Checking layout ,level ,structural excavation and pouring of concrete (M-10) for PCC at U
5397 NMSCEW/P-IV/STR/2019/5333 5333 PUP Km 183+290 15-Oct-19 10:10 AM DONE
type bottom slab
Checking layout ,level ,structural excavation and pouring concrete (M-15) PCC at Pier raft P-
5398 NMSCEW/P-IV/STR/2019/5334 5334 VOP Km 181+420 LHS 15-Oct-19 4:00 PM
3 NR
5399 NMSCEW/P-IV/STR/2019/5335 5335 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-13 Viaduct Km 169+800 LHS 15-Oct-19 10:00 AM DONE
5400 NMSCEW/P-IV/STR/2019/5336 5336 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at RP-13 Viaduct Km 169+800 RHS 15-Oct-19 10:05 AM DONE
5401 NMSCEW/P-IV/STR/2019/5337 5337 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at RP-12 Viaduct Km 169+800 RHS 15-Oct-19 10:15 AM DONE
5402 NMSCEW/P-IV/STR/2019/5338 5338 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at RP-11 Viaduct Km 169+800 RHS 15-Oct-19 10:20 AM DONE
5403 NMSCEW/P-IV/STR/2019/5339 5339 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at RP-09 Viaduct Km 169+800 RHS 15-Oct-19 10:25 AM DONE
5404 NMSCEW/P-IV/STR/2019/5340 5340 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at RP-08 Viaduct Km 169+800 RHS 15-Oct-19 10:30 AM DONE
5405 NMSCEW/P-IV/STR/2019/5341 5341 Checking of Shuttering,reinforcement & pouring concrete for abutment cap at RA-02 Viaduct Km 169+800 Km 00+000 RHS 15-Oct-19 2:30 PM IPC-09 DONE MNB
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at retaining wall A1 &
5406 NMSCEW/P-IV/STR/2019/5342 5342 PUP Km 174+095 LHS 15-Oct-19 11:00 AM
A2 NR
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 2nd lift at retaining
5407 NMSCEW/P-IV/STR/2019/5343 5343 PUP Km 171+110 RHS 15-Oct-19 2:00 PM
wall A1 & A2 NR
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 2nd lift at retaining
5408 NMSCEW/P-IV/STR/2019/5344 5344 PUP Km 171+110 LHS 15-Oct-19 2:40 PM
wall A1 NR
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5409 NMSCEW/P-IV/STR/2019/5345 5345 Box culvert Km 175+500 LHS 15-Oct-19 9:30 AM
Culvert (3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-247,248
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5410 NMSCEW/P-IV/STR/2019/5346 5346 Box culvert Km 175+500 LHS 15-Oct-19 10:50 AM DONE
Culvert (3×3) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-1,2,3
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5411 NMSCEW/P-IV/STR/2019/5347 5347 Box culvert Km 175+500 LHS 15-Oct-19 12:40 PM
Culvert (2×2) (Cushion 4 to 6m) at precast yard camp-1,Segment no.-10,17,18
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5412 NMSCEW/P-IV/STR/2019/5348 5348 Box culvert Km 175+500 LHS 15-Oct-19 4:00 PM
Culvert (2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-310,311,312,313,314
5413 NMSCEW/P-IV/STR/2019/5349 5349 Checking errection of precast Box culvert (3*3) Box culvert Km 171+334 BHS 15-Oct-19 10:30 AM NR
5414 NMSCEW/P-IV/STR/2019/5350 5350 Checking of reinforcement,shuttering and Pouring concrete(M-30) for 1st lift at wall A1 & A2 Box culvert Km 187+677 LHS 15-Oct-19 4:30 PM
NR
Checking of Shuttering,reinforcement & pouring concrete(M-35) for 2nd lift at wall A1 & A2
5415 NMSCEW/P-IV/STR/2019/5351 5351 MNB loop-B Km 01+980 15-Oct-19 2:15 PM DONE
(Loop-B)
5416 NMSCEW/P-IV/STR/2019/5352 5352 Checking reinforcement ,shuttering and concrete(M-30) pouring for bottom slab MNB Km 181+700 LHS 15-Oct-19 4:10 PM NR
5417 NMSCEW/P-IV/STR/2019/5353 5353 Checking layout ,Level & Laying concrete for PCC at RA-02 Viaduct Km 195+900 RHS 15-Oct-19 2:00 PM
5418 NMSCEW/P-IV/STR/2019/5354 5354 Checking of reinforcement, shuttering & pouring concrete for raft at LP-03 Viaduct Km 196+560 LHS 15-Oct-19 4:30 PM
5419 NMSCEW/P-IV/STR/2019/5355 5355 Checking of reinforcement, shuttering & pouring concrete for pier cap at RA-02 Viaduct Km 196+560 RHS 15-Oct-19 4:22 PM
Checking for stressing and remove slagness of H.T. wires at Girder no-61,62,63,64 at bed no
5420 NMSCEW/P-IV/STR/2019/5356 5356 Girder Km 200+200 LHS 15-Oct-19 3:00 PM
-03, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no 61,62,63,64 at bed no -03, Girder Type-2 at casting yard
5421 NMSCEW/P-IV/STR/2019/5357 5357 Girder Km 200+200 LHS 15-Oct-19 3:30 PM
camp -2
5422 NMSCEW/P-IV/STR/2019/5358 5358 Checking layout ,Level & Laying concrete for PCC at RP-09 Viaduct Km 213+915 RHS 15-Oct-19 4:05 PM IPC-14
5423 NMSCEW/P-IV/STR/2019/5359 5359 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-13 Viaduct Km 202+190 LHS 15-Oct-19 2:35 PM
5424 NMSCEW/P-IV/STR/2019/5360 5360 Checking layout ,Level & Laying concrete for PCC at RP-10 Viaduct Km 202+190 RHS 15-Oct-19 3:22 PM
5425 NMSCEW/P-IV/STR/2019/5361 5361 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-02 Viaduct Km 202+190 LHS 15-Oct-19 3:37 PM
5426 NMSCEW/P-IV/STR/2019/5362 5362 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-03 Viaduct Km 202+190 LHS 15-Oct-19 4:11 PM
5427 NMSCEW/P-IV/STR/2019/5363 5363 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall W1 Box culvert Km 201+280 Km 00+000 LHS 15-Oct-19 2:30 PM IPC-11 Approved AE
5428 NMSCEW/P-IV/STR/2019/5364 5364 Checking layout ,level and structural excavation Box culvert Km 177+760 Km 00+000 BHS 16-Oct-19 10:20 AM IPC-10 DONE
5429 NMSCEW/P-IV/STR/2019/5365 5365 Checking layout ,Level & Laying concrete for PCC at RA-01 MJB 205+610 Km 00+000 RHS 16-Oct-19 3:00 PM IPC-09 DONE AE
Checking for stressing and remove slagness of H.T. wires at Girder no-45,46,47,48 at bed no
5430 NMSCEW/P-IV/STR/2019/5366 5366 Girder Km 200+200 LHS 16-Oct-19 3:30 PM
-05, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no -45,46,47,48 at bed no -05, Girder Type-1 at casting yard
5431 NMSCEW/P-IV/STR/2019/5367 5367 Girder Km 200+200 LHS 16-Oct-19 4:00 PM
camp -2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no- 61,62,63,64 at
5432 NMSCEW/P-IV/STR/2019/5368 5368 Girder Km 200+200 LHS 16-Oct-19 6:00 PM
bed no -03, Girder Type-2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-41,42,43,44 at
5433 NMSCEW/P-IV/STR/2019/5369 5369 Girder Km 200+200 LHS 16-Oct-19 5:00 PM
bed no -06, Girder Type-1
5434 NMSCEW/P-IV/STR/2019/5370 5370 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-03 Viaduct Km 195+900 Km 00+000 LHS 16-Oct-19 10:00 AM IPC-11 Approved AE
5435 NMSCEW/P-IV/STR/2019/5371 5371 Checking of reinforcement, shuttering & pouring concrete for pier cap at LP-09 Viaduct Km 195+900 LHS 16-Oct-19 4:15 PM
5436 NMSCEW/P-IV/STR/2019/5372 5372 Checking layout ,level and structural excavation Box culvert Km 162+832 BHS 16-Oct-19 2:00 PM DONE
5437 NMSCEW/P-IV/STR/2019/5373 5373 Checking top Level & Laying concrete for PCC Box culvert Km 162+832 BHS 16-Oct-19 4:20 PM DONE
Checking of reinforcement, shuttering & pouring concrete(M-45) for abutment shaft final lift
5438 NMSCEW/P-IV/STR/2019/5374 5374 Viaduct Km 169+800 RHS 16-Oct-19 12:00 PM DONE
at RA-01
5439 NMSCEW/P-IV/STR/2019/5375 5375 Checking reinforcement ,shuttering and concrete(M-30) pouring for bottom slab With Haunch MNB Km 181+700 Km 00+000 LHS 16-Oct-19 3:50 PM IPC-11 DONE AE
5440 NMSCEW/P-IV/STR/2019/5376 5376 Checking of reinforcement,shuttering and Pouring concrete(M-30) for 1st lift at wall A1 & A2 Box culvert Km 187+677 LHS 16-Oct-19 4:45 PM DONE
5441 NMSCEW/P-IV/STR/2019/5377 5377 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall A2 LVUP Km 169+291 Km 00+000 RHS 16-Oct-19 2:00 PM IPC-10 DONE AE
5442 NMSCEW/P-IV/STR/2019/5378 5378 Checking of Shuttering,reinforcement & pouring concrete(M-30) for raft at retaining wall W2 PUP Km 199+060 RHS 16-Oct-19 2:38 PM DONE
5443 NMSCEW/P-IV/STR/2019/5379 5379 Checking of Shuttering,reinforcement & pouring concrete(M-30) for raft at retaining wall W2 PUP Km 191+740 RHS 16-Oct-19 9:00 AM DONE
5444 NMSCEW/P-IV/STR/2019/5380 5380 Checking of reinforcement, shuttering & pouring concrete for pier cap at LP-09 Viaduct Km 202+190 LHS 16-Oct-19 3:00 PM
5445 NMSCEW/P-IV/STR/2019/5381 5381 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-13 Viaduct Km 202+190 Km 00+000 LHS 16-Oct-19 10:00 AM IPC-11 Approved
5446 NMSCEW/P-IV/STR/2019/5382 5382 Checking layout ,Level & Laying concrete for PCC at abutment RA-02 Viaduct Km 200+920 Km 00+000 RHS 16-Oct-19 10:25 AM IPC-10 DONE
5447 NMSCEW/P-IV/STR/2019/5383 5383 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-04 Viaduct Km 200+920 Km 00+000 LHS 16-Oct-19 4:22 PM IPC-11 Approved AE
5448 NMSCEW/P-IV/STR/2019/5384 5384 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-05 Viaduct Km 200+920 LHS 16-Oct-19 5:40 PM
5449 NMSCEW/P-IV/STR/2019/5385 5385 Checking layout ,Level & Laying concrete for PCC at RP-07 Viaduct Km 213+915 RHS 16-Oct-19 3:50 PM
5450 NMSCEW/P-IV/STR/2019/5386 5386 Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at wall W2 MNB Km 199+360 LHS 16-Oct-19 9:30 AM DONE
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5451 NMSCEW/P-IV/STR/2019/5387 5387 Box culvert Km 175+500 LHS 16-Oct-19 9:25 AM DONE
Culvert (3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-249,250
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5452 NMSCEW/P-IV/STR/2019/5388 5388 Box culvert Km 175+500 LHS 16-Oct-19 10:55 AM DONE
Culvert (3×3) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-7,8,9
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5453 NMSCEW/P-IV/STR/2019/5389 5389 Box culvert Km 175+500 LHS 16-Oct-19 12:42 PM DONE
Culvert (2×2) (Cushion 4 to 6m) at precast yard camp-1,Segment no.-19,20,21
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5454 NMSCEW/P-IV/STR/2019/5390 5390 Box culvert Km 175+500 LHS 16-Oct-19 4:05 PM DONE
Culvert (2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-315,316,317,318
5455 NMSCEW/P-IV/STR/2019/5391 5391 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at retaining wall W2 PUP Km 203+560 LHS 17-Oct-19 8:00 AM DONE
5456 NMSCEW/P-IV/STR/2019/5392 5392 Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall W1 PUP Km 203+560 LHS 17-Oct-19 9:00 AM DONE
Checking of Shuttering and reinforcement for RE WALL PANEL precast TYPE -A 200 NOS,
5457 NMSCEW/P-IV/STR/2019/5393 5393 TYPE -B 119 NOS,TYPE -Sta 11 NOS, TYPE -Stb 15, NOS, TYPE -Stc 12 NOS, TYPE RE Wall Panel Km 200+200 LHS 17-Oct-19 4:00 PM DONE
-Std 11 NOS, TYPE -Ltc 14 NOS, TYPE -Lta 3 NOS, at RE panel precast yard camp 2
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert I)
5458 NMSCEW/P-IV/STR/2019/5394 5394 2x2(2to4m) segment no.542,543,544,545,546,547,548,489 Box culvert Km 200+200 LHS 17-Oct-19 10:00 AM DONE
II) 3x3 (0to2m) segment no - 168
III) 3x3 (2to4m) segment no. - 62,63,64
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 2nd lift at U type
5459 NMSCEW/P-IV/STR/2019/5395 5395 PUP Km 190+650 17-Oct-19 5:00 PM
retaining wall A1 & A2 NR
5460 NMSCEW/P-IV/STR/2019/5396 5396 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at median wall A1 PUP Km 172+190 17-Oct-19 1:30 PM
NR
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at median wall A1 &
5461 NMSCEW/P-IV/STR/2019/5397 5397 LVUP Km 173+400 17-Oct-19 1:50 PM
A2 NR
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5462 NMSCEW/P-IV/STR/2019/5398 5398 Box culvert Km 175+500 LHS 17-Oct-19 9:25 AM DONE
Culvert (3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-251,252
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5463 NMSCEW/P-IV/STR/2019/5399 5399 Box culvert Km 175+500 LHS 17-Oct-19 10:55 AM DONE
Culvert (3×3) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-10,11,12
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5464 NMSCEW/P-IV/STR/2019/5400 5400 Box culvert Km 175+500 LHS 17-Oct-19 12:42 PM DONE
Culvert (2×2) (Cushion 4 to 6m) at precast yard camp-1,Segment no.-22,23,24
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5465 NMSCEW/P-IV/STR/2019/5401 5401 Box culvert Km 175+500 LHS 17-Oct-19 4:05 PM DONE
Culvert (2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-319,320,321,322
5466 NMSCEW/P-IV/STR/2019/5402 5402 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at RP-01 Viaduct Km 169+800 RHS 17-Oct-19 2:00 PM DONE
5467 NMSCEW/P-IV/STR/2019/5403 5403 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at RP-02 Viaduct Km 169+800 RHS 17-Oct-19 2:30 PM DONE
5468 NMSCEW/P-IV/STR/2019/5404 5404 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at RP-03 Viaduct Km 169+800 RHS 17-Oct-19 3:00 PM DONE
5469 NMSCEW/P-IV/STR/2019/5405 5405 Checking layout ,Level & Laying concrete for PCC at LP-15 Viaduct Km 213+915 LHS 17-Oct-19 4:05 PM
5470 NMSCEW/P-IV/STR/2019/5406 5406 Checking of reinforcement, shuttering & pouring concrete for raft at LP-03 Viaduct Km 196+560 Km 00+000 LHS 17-Oct-19 10:37 AM IPC-11 Approved AE
5471 NMSCEW/P-IV/STR/2019/5407 5407 Checking of reinforcement, shuttering & pouring concrete for pier cap at RA-02 Viaduct Km 196+560 Km 00+000 RHS 17-Oct-19 12:20 PM IPC-09 DONE
5472 NMSCEW/P-IV/STR/2019/5408 5408 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at retaining wall W2 PUP Km 203+560 LHS 18-Oct-19 8:00 AM DONE
5473 NMSCEW/P-IV/STR/2019/5409 5409 Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall W2 PUP Km 204+470 RHS 18-Oct-19 9:00 AM DONE
5474 NMSCEW/P-IV/STR/2019/5410 5410 Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at retaining wall W2 PUP Km 204+470 LHS 18-Oct-19 11:00 AM DONE
5475 NMSCEW/P-IV/STR/2019/5411 5411 Checking of top bracket reinforcement,shuttering and Pouring concrete at retaining wall W1 PUP Km 205+430 RHS 18-Oct-19 10:00 AM DONE
5476 NMSCEW/P-IV/STR/2019/5412 5412 Checking of Shuttering,reinforcement & pouring concrete for raft at retaining wall W1 PUP Km 199+060 RHS 18-Oct-19 2:30 PM DONE
5477 NMSCEW/P-IV/STR/2019/5413 5413 Checking of Shuttering,reinforcement & pouring concrete for 1st lift at retaining wall W2 PUP Km 191+740 RHS 18-Oct-19 11:30 AM DONE
5478 NMSCEW/P-IV/STR/2019/5414 5414 Checking of Shuttering,reinforcement & pouring concrete for 1st lift at retaining wall W2 PUP Km 199+060 RHS 18-Oct-19 4:00 PM DONE
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5479 NMSCEW/P-IV/STR/2019/5415 5415 Box culvert Km 175+500 LHS 18-Oct-19 9:30 AM
Culvert (3×3) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-3,13
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5480 NMSCEW/P-IV/STR/2019/5416 5416 Box culvert Km 175+500 LHS 18-Oct-19 11:15 AM
Culvert (2×2) (Cushion 4 to 6m) at precast yard camp-1,Segment no.-3,6,25
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5481 NMSCEW/P-IV/STR/2019/5417 5417 Box culvert Km 175+500 LHS 18-Oct-19 3:00 PM
Culvert (2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-323,324,325,326
5482 NMSCEW/P-IV/STR/2019/5418 5418 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-01 Viaduct Km 169+800 LHS 18-Oct-19 2:05 PM NR
5483 NMSCEW/P-IV/STR/2019/5419 5419 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-02 Viaduct Km 169+800 LHS 18-Oct-19 2:34 PM NR
5484 NMSCEW/P-IV/STR/2019/5420 5420 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-03 Viaduct Km 169+800 LHS 18-Oct-19 3:10 PM
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-45,46,47,48 at
5485 NMSCEW/P-IV/STR/2019/5421 5421 Girder Km 200+200 LHS 18-Oct-19 3:35 PM
bed no -05, Girder Type-1
Checking for stressing and remove slagness of H.T. wires at Girder no-49,50,51,52 at bed no
5486 NMSCEW/P-IV/STR/2019/5422 5422 Girder Km 200+200 LHS 18-Oct-19 5:30 PM
-08, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no -49,50,51,52 at bed no -08, Girder Type-1 at casting yard
5487 NMSCEW/P-IV/STR/2019/5423 5423 Girder Km 200+200 LHS 18-Oct-19 6:00 PM
camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-65,66,67,68 at bed no
5488 NMSCEW/P-IV/STR/2019/5424 5424 Girder Km 200+200 LHS 18-Oct-19 5:00 PM
-01, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no -65,66,67,68 at bed no -01, Girder Type-2 at casting yard
5489 NMSCEW/P-IV/STR/2019/5425 5425 Girder Km 200+200 LHS 18-Oct-19 5:40 PM
camp -2
5490 NMSCEW/P-IV/STR/2019/5426 5426 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-12 Viaduct Km 202+190 Km 00+000 LHS 18-Oct-19 3:05 PM IPC-11 Approved
5491 NMSCEW/P-IV/STR/2019/5427 5427 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP-11 Viaduct Km 202+190 Km 00+000 RHS 18-Oct-19 4:10 PM IPC-11 Approved
5492 NMSCEW/P-IV/STR/2019/5428 5428 Checking of reinforcement, shuttering & pouring concrete for pier cap at LP-09 Viaduct Km 202+190 Km 00+000 LHS 18-Oct-19 10:00 AM IPC-10 DONE AE
5493 NMSCEW/P-IV/STR/2019/5429 5429 Checking layout ,Level & Laying concrete for PCC at LP-13 Viaduct Km 213+915 LHS 18-Oct-19 4:15 PM
5494 NMSCEW/P-IV/STR/2019/5430 5430 Checking layout ,Level & Laying concrete for PCC at LP15 Viaduct Km 213+915 Km 00+000 LHS 18-Oct-19 4:33 PM IPC-11 Approved AE
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert I)
5495 NMSCEW/P-IV/STR/2019/5431 5431 2*2(2to4m) segment no.-550,551,552,553,554,555,556 Box culvert Km 200+200 LHS 19-Oct-19 10:00 AM DONE
II) 3x3 (0to2m) segment no.- 169,170
III) 3x3 (2to4m) segment no.- 65,66,67
5496 NMSCEW/P-IV/STR/2019/5432 5432 Checking of Shuttering,reinforcement & pouring concrete for raft at retaining wall A2 PUP Km 171+110 LHS 19-Oct-19 12:00 PM DONE
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 2nd lift at U type wall
5497 NMSCEW/P-IV/STR/2019/5433 5433 PUP Km 190+650 19-Oct-19 11:00 AM DONE
A1 & A2
5498 NMSCEW/P-IV/STR/2019/5434 5434 Checking of reinforcement, shuttering & pouring concrete for abutment cap at LA-02 Viaduct Km 169+800 Km 00+000 LHS 19-Oct-19 2:30 PM IPC-09 DONE MNB
Checking layout, structural excavation,level and pouring Concrete(M-15) for PCC in abutment
5499 NMSCEW/P-IV/STR/2019/5435 5435 MNB Km 186+550 LHS 19-Oct-19 4:00 PM
A-1 NR
5500 NMSCEW/P-IV/STR/2019/5436 5436 Checking of reinforcement, shuttering & pouring concrete for pier cap at LP-10 Viaduct Km 202+190 LHS 19-Oct-19 3:00 PM
5501 NMSCEW/P-IV/STR/2019/5437 5437 Checking of reinforcement, shuttering & pouring concrete for pier cap at RP-07 Viaduct Km 196+560 Km 00+000 RHS 19-Oct-19 10:40 AM IPC-09 DONE AE
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no- 49,50,51,52 at
5502 NMSCEW/P-IV/STR/2019/5438 5438 Girder Km 200+200 LHS 19-Oct-19 6:30 PM
bed no -08, Girder Type-01
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no- 65,66,67,68 at
5503 NMSCEW/P-IV/STR/2019/5439 5439 Girder Km 200+200 LHS 19-Oct-19 5:30 PM
bed no -01, Girder Type-02
5504 NMSCEW/P-IV/STR/2019/5440 5440 Checking layout ,Level & Laying concrete for PCC at LP-16 Viaduct Km 213+915 LHS 19-Oct-19 3:15 PM
5505 NMSCEW/P-IV/STR/2019/5441 5441 Checking layout ,Level & Laying concrete for PCC at LP-17 Viaduct Km 213+915 LHS 19-Oct-19 4:10 PM
5506 NMSCEW/P-IV/STR/2019/5442 5442 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-03 Viaduct Km 202+190 Km 00+000 RHS 19-Oct-19 12:30 PM IPC-10 DONE
5507 NMSCEW/P-IV/STR/2019/5443 5443 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-03 Viaduct Km 202+190 LHS 19-Oct-19 2:45 PM
Checking of reinforcement,shuttering and Pouring concrete for 4th lift at U type retaining wall
5508 NMSCEW/P-IV/STR/2019/5444 5444 PUP Km 205+430 19-Oct-19 8:00 AM DONE
W1
Checking of reinforcement,shuttering and Pouring concrete for 4th lift at U type retaining wall
5509 NMSCEW/P-IV/STR/2019/5445 5445 PUP Km 205+430 19-Oct-19 2:00 PM DONE
W2
5510 NMSCEW/P-IV/STR/2019/5446 5446 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-01 Viaduct Km 169+800 LHS 19-Oct-19 3:05 PM NR
5511 NMSCEW/P-IV/STR/2019/5447 5447 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-02 Viaduct Km 169+800 LHS 19-Oct-19 3:33 PM NR
5512 NMSCEW/P-IV/STR/2019/5448 5448 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-03 Viaduct Km 169+800 LHS 19-Oct-19 4:07 PM NR
5513 NMSCEW/P-IV/STR/2019/5449 5449 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at retaining wall W2 PUP Km 191+740 RHS 19-Oct-19 11:30 AM
5514 NMSCEW/P-IV/STR/2019/5450 5450 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at retaining wall W2 PUP Km 199+060 RHS 19-Oct-19 4:00 PM
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at retaining wall A1 &
5515 NMSCEW/P-IV/STR/2019/5451 5451 PUP Km 171+110 RHS 20-Oct-19 12:30 PM DONE
A2
5516 NMSCEW/P-IV/STR/2019/5452 5452 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at retaining wall A1 PUP Km 171+110 LHS 20-Oct-19 12:50 PM DONE
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at retaining wall A1 &
5517 NMSCEW/P-IV/STR/2019/5453 5453 LVUP Km 173+400 RHS 20-Oct-19 1:30 PM DONE
A2
5518 NMSCEW/P-IV/STR/2019/5454 5454 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at median wall A1 LVUP Km 173+400 20-Oct-19 1:40 PM DONE
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at retaining wall A1 &
5519 NMSCEW/P-IV/STR/2019/5455 5455 PUP Km 174+095 LHS 20-Oct-19 1:50 PM DONE
A2
5520 NMSCEW/P-IV/STR/2019/5456 5456 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at wall A1 LVUP Km 169+291 Km 00+000 RHS 20-Oct-19 3:00 PM IPC-10 DONE AE
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5521 NMSCEW/P-IV/STR/2019/5457 5457 Box culvert Km 175+500 LHS 20-Oct-19 10:00 AM
Culvert (2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-327,328,329,330
Checking layout, structural excavation,level and pouring Concrete(M-15) for PCC in abutment
5522 NMSCEW/P-IV/STR/2019/5458 5458 MNB Km 186+550 LHS 20-Oct-19 4:00 PM
A-1 NR
Checking of Shuttering,reinforcement & pouring concrete(M-30) for raft at U type retaining
5523 NMSCEW/P-IV/STR/2019/5459 5459 PUP Km 183+290 20-Oct-19 4:20 PM DONE
wall
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 1st lift at retaining wall
5524 NMSCEW/P-IV/STR/2019/5460 5460 PUP Km 187+835 RHS 20-Oct-19 4:50 PM DONE
A1
5525 NMSCEW/P-IV/STR/2019/5461 5461 Checking of reinforcement, shuttering & pouring concrete for pier cap at LP-09 Viaduct Km 195+900 Km 00+000 LHS 20-Oct-19 11:40 AM IPC-09 DONE AE
5526 NMSCEW/P-IV/STR/2019/5462 5462 Checking layout ,Level & Laying concrete for PCC at RA-02 Viaduct Km 195+900 Km 00+000 RHS 20-Oct-19 11:30 AM IPC-10 DONE AE
5527 NMSCEW/P-IV/STR/2019/5463 5463 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-08 Viaduct Km 195+900 LHS 20-Oct-19 10:20 AM IPC-14 DONE
Checking for stressing and remove slagness of H.T. wires at Girder no-69,70,71,72 at bed no
5528 NMSCEW/P-IV/STR/2019/5464 5464 Girder Km 200+200 LHS 20-Oct-19 12:00 PM IPC-14 DONE
-04, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no -69,70,71,72 at bed no -04, Girder Type-2 at casting yard
5529 NMSCEW/P-IV/STR/2019/5465 5465 Girder Km 200+200 LHS 20-Oct-19 12:35 PM IPC-14 DONE
camp -2
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert I)
5530 NMSCEW/P-IV/STR/2019/5466 5466 2*2(2to4m) segment no.-557,558,559,560,561,562,563 Box culvert Km 200+200 LHS 21-Oct-19 10:00 AM DONE
II) 3x3 (0to2m) segment no.- 171
III) 3x3 (2to4m) segment no.-68,69
5531 NMSCEW/P-IV/STR/2019/5467 5467 Checking layout ,Level & Laying concrete for PCC at LP-13 Viaduct Km 213+915 LHS 21-Oct-19 3:00 PM DONE
5532 NMSCEW/P-IV/STR/2019/5468 5468 Checking layout ,Level & Laying concrete for PCC at RP-17 Viaduct Km 213+915 RHS 21-Oct-19 4:00 PM DONE
Checking for stressing and remove slagness of H.T. wires at Girder no-53,54,55,56 at bed no
5533 NMSCEW/P-IV/STR/2019/5469 5469 Girder Km 200+200 LHS 21-Oct-19 5:00 PM DONE
-07, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no -53,54,55,56 at bed no -07, Girder Type-1 at casting yard
5534 NMSCEW/P-IV/STR/2019/5470 5470 Girder Km 200+200 LHS 21-Oct-19 5:30 PM DONE
camp -2
5535 NMSCEW/P-IV/STR/2019/5471 5471 Checking of reinforcement, shuttering & pouring concrete for pier cap at LP-10 Viaduct Km 202+190 Km 00+000 LHS 21-Oct-19 10:15 AM IPC-10 DONE AE
5536 NMSCEW/P-IV/STR/2019/5472 5472 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall A1 Box culvert Km 163+570 Km 00+000 BHS 21-Oct-19 3:00 PM IPC-10 DONE AE
5537 NMSCEW/P-IV/STR/2019/5473 5473 Checking layout, levels and structural excavation for utility duct 2x2 Utility duct Km 187+360 Km 00+000 BHS 21-Oct-19 9:30 AM IPC-09 DONE
5538 NMSCEW/P-IV/STR/2019/5474 5474 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-01 Viaduct Km 169+800 LHS 21-Oct-19 2:00 PM DONE
5539 NMSCEW/P-IV/STR/2019/5475 5475 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-02 Viaduct Km 169+800 LHS 21-Oct-19 2:34 PM DONE
5540 NMSCEW/P-IV/STR/2019/5476 5476 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-03 Viaduct Km 169+800 LHS 21-Oct-19 3:05 PM DONE
5541 NMSCEW/P-IV/STR/2019/5477 5477 Checking of layout,level, Shuttering,reinforcement & pouring concrete for raft Box culvert Km 208+675 RHS 21-Oct-19 8:00 AM DONE
5542 NMSCEW/P-IV/STR/2019/5478 5478 Checking of reinforcement,shuttering and Pouring concrete(M-30) for raft at retaining wall A1 PUP Km 190+650 RHS 21-Oct-19 5:00 PM
NR
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5543 NMSCEW/P-IV/STR/2019/5479 5479 Box culvert Km 175+500 LHS 21-Oct-19 9:30 AM DONE
Culvert (3×3) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-12,13
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5544 NMSCEW/P-IV/STR/2019/5480 5480 Box culvert Km 175+500 LHS 21-Oct-19 11:15 AM
Culvert (2×2) (Cushion 4 to 6m) at precast yard camp-1,Segment no.-25,26,3
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5545 NMSCEW/P-IV/STR/2019/5481 5481 Box culvert Km 175+500 LHS 21-Oct-19 3:00 PM
Culvert (2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-330,331,332,333
5546 NMSCEW/P-IV/STR/2019/5482 5482 Checking layout ,Level & Laying concrete for PCC at LP-16 Viaduct Km 213+915 LHS 21-Oct-19 3:15 PM DONE
5547 NMSCEW/P-IV/STR/2019/5483 5483 Checking layout ,Level & Laying concrete for PCC at LP-17 Viaduct Km 213+915 LHS 21-Oct-19 4:10 PM DONE
Checking of Shuttering,reinforcement & pouring concrete for bottom haunch at U type
5548 NMSCEW/P-IV/STR/2019/5484 5484 PUP Km 177+810 22-Oct-19 12:30 PM
retaining wall A1 & A2 NR
5549 NMSCEW/P-IV/STR/2019/5485 5485 Checking layout ,Level & Laying concrete for PCC at U type retaining wall LVUP Km 178+323 22-Oct-19 10:30 AM DONE
Checking of layout,level, Shuttering,reinforcement & pouring concrete for raft at abutment
5550 NMSCEW/P-IV/STR/2019/5486 5486 MJB Km 205+610 Km 00+000 LHS 22-Oct-19 4:15 PM IPC-09 DONE
LA-01 AE
5551 NMSCEW/P-IV/STR/2019/5487 5487 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall W2 Box culvert Km 201+280 Km 00+000 LHS 22-Oct-19 8:00 AM IPC-11 Approved AE
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert I)
5552 NMSCEW/P-IV/STR/2019/5488 5488 2*2(2to4m) segment no.-564,565,567,568,569,570 Box culvert Km 200+200 LHS 22-Oct-19 9:45 AM DONE
II) 3x3 (0to2m) segment no.- 172
III) 3x3 (2to4m) segment no.-70,71
5553 NMSCEW/P-IV/STR/2019/5489 5489 Checking of top bracket reinforcement,shuttering and Pouring concrete at retaining wall W2 PUP Km 205+430 RHS 22-Oct-19 8:15 AM DONE
5554 NMSCEW/P-IV/STR/2019/5490 5490 Checking of reinforcement,shuttering and Pouring concrete at Upstand wall PUP Km 205+430 RHS 22-Oct-19 8:30 AM DONE
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at U type
5555 NMSCEW/P-IV/STR/2019/5491 5491 PUP Km 190+650 22-Oct-19 2:00 PM DONE
median wall
5556 NMSCEW/P-IV/STR/2019/5492 5492 Checking of reinforcement,shuttering and Pouring concrete for raft at median wall VUP Km 166+987 22-Oct-19 4:00 PM DONE
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5557 NMSCEW/P-IV/STR/2019/5493 5493 Box culvert Km 175+500 LHS 22-Oct-19 9:30 AM DONE
Culvert (3×3) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-8,9
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5558 NMSCEW/P-IV/STR/2019/5494 5494 Box culvert Km 175+500 LHS 22-Oct-19 10:35 AM
Culvert (3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-251,252
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5559 NMSCEW/P-IV/STR/2019/5495 5495 Box culvert Km 175+500 LHS 22-Oct-19 11:40 AM
Culvert (2×2) (Cushion 4 to 6m) at precast yard camp-1,Segment no.-7,28,29
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5560 NMSCEW/P-IV/STR/2019/5496 5496 Box culvert Km 175+500 LHS 22-Oct-19 3:00 PM
Culvert (2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-334,335,336,337
5561 NMSCEW/P-IV/STR/2019/5497 5497 Checking layout ,Level & Laying concrete for PCC at RP-10 Viaduct Km 202+190 Km 00+000 RHS 22-Oct-19 3:45 PM IPC-10 DONE AE
5562 NMSCEW/P-IV/STR/2019/5498 5498 Checking of reinforcement, shuttering & pouring concrete for pier cap at RP-01 Viaduct Km 202+190 Km 00+000 RHS 22-Oct-19 2:15 PM IPC-10 DONE AE
5563 NMSCEW/P-IV/STR/2019/5499 5499 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-04 Viaduct Km 202+190 LHS 22-Oct-19 4:10 PM DONE
5564 NMSCEW/P-IV/STR/2019/5500 5500 Checking layout ,Level & Laying concrete for PCC at LP-13 Viaduct Km 213+915 LHS 22-Oct-19 3:30 PM DONE
5565 NMSCEW/P-IV/STR/2019/5501 5501 Checking layout ,Level & Laying concrete for PCC at RP-18 Viaduct Km 213+915 RHS 22-Oct-19 3:10 PM DONE
Checking for stressing and remove slagness of H.T. wires at Girder no-73,74,75,76 at bed no
5566 NMSCEW/P-IV/STR/2019/5502 5502 Girder Km 200+200 LHS 22-Oct-19 5:30 PM DONE
-02, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no -73,74,75,76 at bed no -02, Girder Type-2 at casting yard
5567 NMSCEW/P-IV/STR/2019/5503 5503 Girder Km 200+200 LHS 22-Oct-19 6:00 PM DONE
camp -2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no- 69,70,71,72 at
5568 NMSCEW/P-IV/STR/2019/5504 5504 Girder Km 200+200 LHS 22-Oct-19 5:15 PM DONE
bed no -04, Girder Type-02
5569 NMSCEW/P-IV/STR/2019/5505 5505 Checking of girder launching and positioning of module no.- 2 at LP4 to LP7 Viaduct Km 169+800 LHS 22-Oct-19 9:00 AM DONE
5570 NMSCEW/P-IV/STR/2019/5506 5506 Checking layout ,level and structural excavation at U type retaining wall VUP Km 179+983 23-Oct-19 10:30 AM DONE
5571 NMSCEW/P-IV/STR/2019/5507 5507 Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at retaining wall W2 MNB Km 203+409 RHS 23-Oct-19 8:00 AM DONE
5572 NMSCEW/P-IV/STR/2019/5508 5508 Checking of reinforcement,shuttering and Pouring concrete at RCC Upstand wall W1 PUP Km 205+430 LHS 23-Oct-19 8:30 AM DONE
5573 NMSCEW/P-IV/STR/2019/5509 5509 Checking of reinforcement,shuttering and Pouring concrete at RCC Upstand wall W2 PUP Km 205+430 RHS 23-Oct-19 10:00 AM DONE
Checking of reinforcement,shuttering and Pouring concrete for 4th lift at U type retaining wall
5574 NMSCEW/P-IV/STR/2019/5510 5510 PUP Km 204+470 23-Oct-19 2:00 PM DONE
W2
5575 NMSCEW/P-IV/STR/2019/5511 5511 Checking of completion of segment errection for 3×3 box culvert Box Culvert Km 204+409 Km 00+000 BHS 23-Oct-19 10:45 AM IPC-09 DONE
5576 NMSCEW/P-IV/STR/2019/5512 5512 Checking of completion of segment errection for 3×3 box culvert Box Culvert Km 206+490 Km 00+000 BHS 23-Oct-19 12:00 PM IPC-09 DONE
5577 NMSCEW/P-IV/STR/2019/5513 5513 Checking of completion of segment errection for 2×2 utility duct Utility duct Km 203+980 Km 00+000 BHS 23-Oct-19 2:30 PM IPC-09 DONE
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert I)
5578 NMSCEW/P-IV/STR/2019/5514 5514 2*2(2to4m) segment no.-571,572,573,574,575,576 Box culvert Km 200+200 LHS 23-Oct-19 10:15 AM DONE
II) 3x3 (0to2m) segment no.- 173
III) 3x3 (2to4m) segment no.-72,73
5579 NMSCEW/P-IV/STR/2019/5515 5515 Checking of reinforcement, shuttering & pouring concrete for raft at 2x2 utility duct Utility duct Km 207+560 RHS 23-Oct-19 11:00 AM DONE
5580 NMSCEW/P-IV/STR/2019/5516 5516 Checking layout ,Level & Laying concrete for PCC at RP-12 Viaduct Km 202+190 RHS 23-Oct-19 3:00 PM DONE
5581 NMSCEW/P-IV/STR/2019/5517 5517 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-07 Viaduct Km 202+190 Km 00+000 RHS 23-Oct-19 10:05 AM IPC-10 DONE
5582 NMSCEW/P-IV/STR/2019/5518 5518 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-09 Viaduct Km 202+190 Km 00+000 RHS 23-Oct-19 12:00 PM IPC-10 DONE
5583 NMSCEW/P-IV/STR/2019/5519 5519 Checking of reinforcement, shuttering & pouring concrete for pier shaft first lift at RP-08 Viaduct Km 202+190 Km 00+000 RHS 23-Oct-19 11:00 AM IPC-11 Approved
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5590 NMSCEW/P-IV/STR/2019/5526 5526 Box culvert Km 175+500 LHS 23-Oct-19 10:20 AM
Culvert (3×3) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-12,13
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5591 NMSCEW/P-IV/STR/2019/5527 5527 Box culvert Km 175+500 LHS 23-Oct-19 12:09 PM
Culvert (2×2) (Cushion 4 to 6m) at precast yard camp-1,Segment no.-30,31,32
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5592 NMSCEW/P-IV/STR/2019/5528 5528 Box culvert Km 175+500 LHS 23-Oct-19 3:40 PM
Culvert (2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-338,339,340,341
5593 NMSCEW/P-IV/STR/2019/5529 5529 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at RP-05 Viaduct Km 169+800 RHS 23-Oct-19 3:18 PM DONE
5594 NMSCEW/P-IV/STR/2019/5530 5530 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at RP-06 Viaduct Km 169+800 RHS 23-Oct-19 4:19 PM DONE
5595 NMSCEW/P-IV/STR/2019/5531 5531 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at wall A2 LVUP Km 169+291 Km 00+000 RHS 23-Oct-19 3:00 PM IPC-10 DONE
5596 NMSCEW/P-IV/STR/2019/5532 5532 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at wall A1 & A2 Box culvert Km 187+677 LHS 23-Oct-19 11:00 AM
NR
Checking layout, structural excavation,level and pouring Concrete(M-10) for PCC at U type
5597 NMSCEW/P-IV/STR/2019/5533 5533 PUP Km 185+235 23-Oct-19 10:00 AM DONE
retaining wall(median)
Checking of Shuttering,reinforcement & pouring concrete(M-35) for 3rd lift at wall A1 & A2
5598 NMSCEW/P-IV/STR/2019/5534 5534 MNB loop-A Km 01+980 Km 00+000 BHS 23-Oct-19 11:05 AM IPC-10 DONE
(Loop-A)
Checking of Shuttering,reinforcement & pouring concrete(M-35) for 2nd lift at wall A2 &
5599 NMSCEW/P-IV/STR/2019/5535 5535 MNB loop-B Km 01+980 23-Oct-19 2:26 PM DONE
intermediate wall (Loop-B)
5600 NMSCEW/P-IV/STR/2019/5536 5536 Checking layout, structural excavation,level and pouring Concrete(M-10) for PCC Utility duct Km 187+360 Km 00+000 BHS 23-Oct-19 4:10 PM IPC-09 DONE
5601 NMSCEW/P-IV/STR/2019/5537 5537 Checking layout ,Level & Laying concrete for PCC at U type retaining wall VUP Km 179+983 24-Oct-19 10:15 AM DONE
5602 NMSCEW/P-IV/STR/2019/5538 5538 Checking of top bracket reinforcement,shuttering and Pouring concrete at retaining wall W2 PUP Km 205+430 LHS 24-Oct-19 8:00 AM DONE
5603 NMSCEW/P-IV/STR/2019/5539 5539 Checking of reinforcement,shuttering and Pouring concrete at RCC Upstand wall W2 PUP Km 205+430 LHS 24-Oct-19 8:30 AM DONE
5604 NMSCEW/P-IV/STR/2019/5540 5540 Checking of Shuttering,reinforcement & pouring concrete for 1st lift at wall W1 & W2 CUP Km 206+985 Km 00+000 LHS 24-Oct-19 10:00 AM IPC-09 DONE
Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall A1 &
5605 NMSCEW/P-IV/STR/2019/5541 5541 LVUP Km 173+400 RHS 24-Oct-19 11:30 AM
A2 NR
Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall A1 &
5606 NMSCEW/P-IV/STR/2019/5542 5542 PUP Km 174+095 LHS 24-Oct-19 12:00 PM
A2 NR
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5607 NMSCEW/P-IV/STR/2019/5543 5543 Box culvert Km 175+500 LHS 24-Oct-19 10:22 AM
Culvert (3×3) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-14,15
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5608 NMSCEW/P-IV/STR/2019/5544 5544 Box culvert Km 175+500 LHS 24-Oct-19 12:15 PM
Culvert (2×2) (Cushion 4 to 6m) at precast yard camp-1,Segment no.-33,34,35
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5609 NMSCEW/P-IV/STR/2019/5545 5545 Box culvert Km 175+500 LHS 24-Oct-19 4:00 PM
Culvert (2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-342,343,344,345
5610 NMSCEW/P-IV/STR/2019/5546 5546 Checking and concrete(M-30) pouring for final lift at wall A1 & A2, top haunch & top slab Box culvert Km 187+677 Km 00+000 LHS 24-Oct-19 11:00 AM IPC-09 DONE
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 2nd lift at retaining wall
5611 NMSCEW/P-IV/STR/2019/5547 5547 PUP Km 187+835 RHS 24-Oct-19 12:25 PM DONE
A1
Checking layout, structural excavation,level and pouring Concrete(M-10) for PCC at retaining
5612 NMSCEW/P-IV/STR/2019/5548 5548 PUP Km 187+835 LHS 24-Oct-19 9:00 AM DONE
wall A1
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 1st lift at retaining wall
5613 NMSCEW/P-IV/STR/2019/5549 5549 PUP Km 183+290 RHS 24-Oct-19 10:45 AM
A1 NR
Checking for stressing and remove slagness of H.T. wires at Girder no-73,74,75,76 at bed no
5614 NMSCEW/P-IV/STR/2019/5550 5550 Girder Km 200+200 LHS 24-Oct-19 5:30 PM DONE
-02, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no -73,74,75,76 at bed no -02, Girder Type-2 at casting yard
5615 NMSCEW/P-IV/STR/2019/5551 5551 Girder Km 200+200 LHS 24-Oct-19 6:00 PM DONE
camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-61,62,63,64 at bed no
5616 NMSCEW/P-IV/STR/2019/5552 5552 Girder Km 200+200 LHS 24-Oct-19 5:00 PM DONE
-05, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no -61,62,63,64 at bed no -05, Girder Type-1 at casting yard
5617 NMSCEW/P-IV/STR/2019/5553 5553 Girder Km 200+200 LHS 24-Oct-19 5:35 PM DONE
camp -2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-57,58,59,60 at
5618 NMSCEW/P-IV/STR/2019/5554 5554 Girder Km 200+200 LHS 24-Oct-19 6:30 PM DONE
bed no -06, Girder Type-01
5619 NMSCEW/P-IV/STR/2019/5555 5555 Checking layout ,Level & Laying concrete for PCC at RP-17 Viaduct Km 213+915 RHS 24-Oct-19 4:30 PM DONE
5620 NMSCEW/P-IV/STR/2019/5556 5556 Checking of reinforcement, shuttering & pouring concrete for pier cap at RP-02 Viaduct Km 202+190 Km 00+000 RHS 24-Oct-19 10:20 AM IPC-10 DONE
5621 NMSCEW/P-IV/STR/2019/5557 5557 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 1st lift at wall A1 & A2 Box culvert Km 180+922 Km 00+000 RHS 24-Oct-19 10:08 AM IPC-10 DONE
5622 NMSCEW/P-IV/STR/2019/5558 5558 Checking reinforcement, shuttering and concrete(M-30) pouring for top slab with top haunch Box culvert Km 187+677 Km 00+000 RHS 24-Oct-19 2:00 PM IPC-09 DONE
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert I)
5623 NMSCEW/P-IV/STR/2019/5559 5559 Box culvert Km 200+200 LHS 24-Oct-19 10:35 AM DONE
2*2(2to4m) segment no.-577,578,579,580,581,582,583
II) 3x3 (2to4m) segment no.-74,75
5624 NMSCEW/P-IV/STR/2019/5560 5560 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall A1 & A2 Box culvert Km 180+180 LHS 25-Oct-19 10:30 AM NR
5625 NMSCEW/P-IV/STR/2019/5561 5561 Checking reinforcement ,shuttering and and Pouring concrete for top haunch and top slab VUP Km 179+983 Km 00+000 RHS 25-Oct-19 12:30 PM IPC-09 DONE
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5637 NMSCEW/P-IV/STR/2019/5573 5573 Box culvert Km 175+500 LHS 25-Oct-19 10:23 AM DONE
Culvert (3×3) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-13,16
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5638 NMSCEW/P-IV/STR/2019/5574 5574 Box culvert Km 175+500 LHS 25-Oct-19 12:18 PM
Culvert (2×2) (Cushion 4 to 6m) at precast yard camp-1,Segment no.-36,37,38
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5639 NMSCEW/P-IV/STR/2019/5575 5575 Box culvert Km 175+500 LHS 25-Oct-19 3:15 PM
Culvert (2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-346,347,348,349
5640 NMSCEW/P-IV/STR/2019/5576 5576 Checking layout ,Level & Laying concrete for PCC at RP-12 Viaduct Km 202+190 Km 00+000 RHS 25-Oct-19 4:15 PM IPC-10 DONE
5641 NMSCEW/P-IV/STR/2019/5577 5577 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LA-01 Viaduct Km 202+190 LHS 25-Oct-19 10:00 AM DONE
5642 NMSCEW/P-IV/STR/2019/5578 5578 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-12 Viaduct Km 202+190 LHS 25-Oct-19 2:00 PM DONE
5643 NMSCEW/P-IV/STR/2019/5579 5579 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-08 Viaduct Km 202+190 RHS 25-Oct-19 4:00 PM DONE
5644 NMSCEW/P-IV/STR/2019/5580 5580 Checking layout ,Level & Laying concrete for PCC at LP-16 Viaduct Km 213+915 LHS 25-Oct-19 9:20 AM DONE
5645 NMSCEW/P-IV/STR/2019/5581 5581 Checking layout ,Level & Laying concrete for PCC at LP-17 Viaduct Km 213+915 LHS 25-Oct-19 10:15 AM DONE
5646 NMSCEW/P-IV/STR/2019/5582 5582 Checking layout ,Level & Laying concrete for PCC at RP-18 Viaduct Km 213+915 RHS 25-Oct-19 3:00 PM DONE
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert I)
5647 NMSCEW/P-IV/STR/2019/5583 5583 Box culvert Km 200+200 LHS 25-Oct-19 10:13 AM DONE
2*2(2to4m) segment no.-584,585,586,587,588,589,590
II) 3x3 (2to4m) segment no.-76
Checking of Shuttering,reinforcement & pouring concrete for top haunch at wall A1 & A2
5648 NMSCEW/P-IV/STR/2019/5584 5584 LVUP Km 178+323 LHS 26-Oct-19 10:30 AM DONE
with top slab
Checking of Shuttering,reinforcement & pouring concrete for raft with bottom haunch at wall
5649 NMSCEW/P-IV/STR/2019/5585 5585 Box culvert Km 180+180 RHS 26-Oct-19 12:30 PM
A1 & A2 NR
Checking of Shuttering and reinforcement for RE WALL PANEL precast TYPE -A 124 NOS,
5650 NMSCEW/P-IV/STR/2019/5586 5586 TYPE -B 50 NOS,TYPE -Sta 7 NOS, TYPE -Stb 6 NOS, TYPE -Stc 6 NOS, TYPE -Std 6 RE Wall Panel Km 200+200 LHS 26-Oct-19 4:00 PM
NOS, TYPE -Ltc 12 NOS, TYPE -Lta 5 NOS, at RE panel precast yard camp 2
5651 NMSCEW/P-IV/STR/2019/5587 5587 Checking of Shuttering,reinforcement & pouring concrete for top slab with top haunch PUP Km 165+790 Km 00+000 LHS 26-Oct-19 11:00 AM IPC-09 DONE
5652 NMSCEW/P-IV/STR/2019/5588 5588 Checking of Shuttering,reinforcement & pouring concrete for final lift at wall A1 & A2 PUP Km 164+380 Km 00+000 RHS 26-Oct-19 4:00 PM IPC-09 DONE
5653 NMSCEW/P-IV/STR/2019/5589 5589 Checking of Shuttering,reinforcement & pouring concrete for 2nd lift at wall A1 & A2 PUP Km 164+380 LHS 26-Oct-19 4:30 PM DONE
5654 NMSCEW/P-IV/STR/2019/5590 5590 Checking top levels and laying of concrete M10 for PCC of box culvert (3x3) Box culvert Km 170+439 Km 00+000 BHS 26-Oct-19 10:00 AM IPC-09 DONE
5655 NMSCEW/P-IV/STR/2019/5591 5591 Checking layout, levels and structural excavation for box culvert (3x3) Box culvert Km 171+980 Km 00+000 BHS 26-Oct-19 9:30 AM IPC-09 DONE
5656 NMSCEW/P-IV/STR/2019/5592 5592 Checking top levels and laying of concrete M10 for PCC of box culvert (3x3) Box culvert Km 171+980 Km 00+000 BHS 26-Oct-19 11:30 AM IPC-09 DONE
5657 NMSCEW/P-IV/STR/2019/5593 5593 Checking Errection and jointing of segments for utility culvert (2x2) Utility duct Km 170+300 Km 00+000 BHS 26-Oct-19 12:00 PM IPC-09 DONE
5658 NMSCEW/P-IV/STR/2019/5594 5594 Checking of Shuttering,reinforcement & pouring concrete(M-30) for top slab with top haunch Box culvert Km 187+667 LHS 26-Oct-19 8:00 AM DONE
5659 NMSCEW/P-IV/STR/2019/5595 5595 Checking of Shuttering,reinforcement & pouring concrete(M-30) for 2nd lift at wall A1 & A2 Box culvert Km 187+667 RHS 26-Oct-19 6:00 PM DONE
5660 NMSCEW/P-IV/STR/2019/5596 5596 Checking layout & levels and laying of concrete M10 for PCC of utility culvert (2x2) Utility duct Km 170+890 Km 00+000 BHS 26-Oct-19 2:00 PM IPC-10 DONE
5661 NMSCEW/P-IV/STR/2019/5597 5597 Checking Errection and jointing of segments for utility culvert (2x2) Utility duct Km 171+570 Km 00+000 BHS 26-Oct-19 3:00 PM IPC-09 DONE
5662 NMSCEW/P-IV/STR/2019/5598 5598 Checking Errection and jointing of segments for utility culvert (2x2) Utility duct Km 174+360 Km 00+000 BHS 26-Oct-19 12:30 PM IPC-09 DONE
5663 NMSCEW/P-IV/STR/2019/5599 5599 Checking of Shuttering,reinforcement & pouring concrete(M-30) for U trough final lift wall PUP Km 190+650 26-Oct-19 12:05 PM DONE
5664 NMSCEW/P-IV/STR/2019/5600 5600 Checking of Shuttering,reinforcement & pouring concrete(M-30) for U trough final lift wall PUP Km 187+835 26-Oct-19 5:00 PM
NR
Checking layout, structural excavation,level and pouring Concrete(M-15) for PCC in abutment
5665 NMSCEW/P-IV/STR/2019/5601 5601 MNB Km 186+550 LHS 26-Oct-19 3:10 PM
A-1 NR
Checking of Shuttering,reinforcement & pouring concrete(M-30) for footing at retaining wall
5666 NMSCEW/P-IV/STR/2019/5602 5602 PUP Km 187+835 LHS 26-Oct-19 4:00 PM DONE
A1
5667 NMSCEW/P-IV/STR/2019/5603 5603 Checking of reinforcement, shuttering & pouring concrete for pier cap at RP-06 Viaduct Km 196+560 RHS 26-Oct-19 4:30 PM DONE
Checking for stressing and remove slagness of H.T. wires at Girder no-61,62,63,64 at bed no
5668 NMSCEW/P-IV/STR/2019/5604 5604 Girder Km 200+200 LHS 26-Oct-19 11:00 AM DONE
-05, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no -61,62,63,64 at bed no -05, Girder Type-1 at casting yard
5669 NMSCEW/P-IV/STR/2019/5605 5605 Girder Km 200+200 LHS 26-Oct-19 11:30 AM DONE
camp -2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-57,58,59,60 at
5670 NMSCEW/P-IV/STR/2019/5606 5606 Girder Km 200+200 LHS 26-Oct-19 6:30 PM DONE
bed no -06, Girder Type-01
5671 NMSCEW/P-IV/STR/2019/5607 5607 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-08 Viaduct Km 202+190 RHS 26-Oct-19 2:00 PM DONE
5672 NMSCEW/P-IV/STR/2019/5608 5608 Checking of reinforcement, shuttering & pouring concrete for pier cap at RP-03 Viaduct Km 202+190 RHS 26-Oct-19 3:00 PM DONE
5673 NMSCEW/P-IV/STR/2019/5609 5609 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-12 Viaduct Km 202+190 LHS 26-Oct-19 4:05 PM DONE
5674 NMSCEW/P-IV/STR/2019/5610 5610 Checking layout ,Level & Laying concrete for PCC at RP-17 Viaduct Km 213+915 RHS 26-Oct-19 2:30 PM DONE
5675 NMSCEW/P-IV/STR/2019/5611 5611 Checking of Shuttering,reinforcement & pouring concrete for 3rd lift at medan wall A1 & A2 LVUP Km 173+400 26-Oct-19 10:40 AM DONE
5676 NMSCEW/P-IV/STR/2019/5612 5612 Checking of Shuttering,reinforcement & pouring concrete for 1st lift at retaining wall A2 LVUP Km 173+400 LHS 26-Oct-19 11:33 AM DONE
Checking of Shuttering,reinforcement & pouring concrete for 4th lift at retaining wall A1 &
5677 NMSCEW/P-IV/STR/2019/5613 5613 LVUP Km 173+400 RHS 26-Oct-19 10:40 AM DONE
A2
Checking of Shuttering,reinforcement & pouring concrete for 4th lift at retaining wall A1 &
5678 NMSCEW/P-IV/STR/2019/5614 5614 PUP Km 174+095 LHS 26-Oct-19 11:17 AM DONE
A2
5679 NMSCEW/P-IV/STR/2019/5615 5615 Checking of Shuttering,reinforcement & pouring concrete for 2nd lift at wall W1 MNB Km 199+360 RHS 26-Oct-19 8:00 AM DONE
5680 NMSCEW/P-IV/STR/2019/5616 5616 Checking of Shuttering,reinforcement & pouring concrete(M-30) for top slab with top haunch Box culvert Km 187+667 RHS 29-Oct-19 10:00 AM DONE
Checking of reinforcement,shuttering and Pouring concrete for final lift at wall A1 & A2 and
5681 NMSCEW/P-IV/STR/2019/5617 5617 Box culvert Km 180+180 LHS 29-Oct-19 11:30 AM
top haunch with top slab NR
5682 NMSCEW/P-IV/STR/2019/5618 5618 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall A1 & A2 Box culvert Km 180+180 RHS 29-Oct-19 4:30 PM NR
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-69,70,71,72 at
5683 NMSCEW/P-IV/STR/2019/5619 5619 Girder Km 200+200 LHS 29-Oct-19 9:30 AM DONE
bed no -04, Girder Type-02
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-73,74,75,76 at
5684 NMSCEW/P-IV/STR/2019/5620 5620 Girder Km 200+200 LHS 29-Oct-19 5:30 PM DONE
bed no -02, Girder Type-02
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-53,54,55,56 at
5685 NMSCEW/P-IV/STR/2019/5621 5621 Girder Km 200+200 LHS 29-Oct-19 8:30 AM DONE
bed no -07, Girder Type-01
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-57,58,59,60 at
5686 NMSCEW/P-IV/STR/2019/5622 5622 Girder Km 200+200 LHS 29-Oct-19 6:30 PM DONE
bed no -06, Girder Type-01
5687 NMSCEW/P-IV/STR/2019/5623 5623 Checking Errection and jointing of segments for box culvert (3x3) Box culvert Km 170+439 Km 00+000 BHS 29-Oct-19 10:30 AM IPC-09 DONE
5688 NMSCEW/P-IV/STR/2019/5624 5624 Checking Errection and jointing of segments for box culvert (3x3) Box culvert Km 171+980 Km 00+000 BHS 29-Oct-19 11:33 AM IPC-09 DONE
5689 NMSCEW/P-IV/STR/2019/5625 5625 Checking Errection and jointing of segments for utility culvert (2x2) Utility duct Km 170+890 Km 00+000 BHS 29-Oct-19 2:26 PM IPC-10 DONE
5690 NMSCEW/P-IV/STR/2019/5626 5626 Checking Errection and jointing of segments for utility culvert (2x2) Utility duct Km 187+360 BHS 29-Oct-19 4:00 PM DONE
5691 NMSCEW/P-IV/STR/2019/5627 5627 Checking of Shuttering,reinforcement & pouring concrete(M-30) for U trough bottom slab PUP Km 185+235 29-Oct-19 8:00 AM DONE
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 1st lift at retaining wall
5692 NMSCEW/P-IV/STR/2019/5628 5628 PUP Km 184+190 LHS 29-Oct-19 9:00 AM DONE
A1
Checking layout, structural excavation,level and pouring Concrete(M-10) for PCC for U
5693 NMSCEW/P-IV/STR/2019/5629 5629 PUP Km 184+190 29-Oct-19 10:00 AM
trough bottom slab NR
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 1st lift at retaining wall
5694 NMSCEW/P-IV/STR/2019/5630 5630 PUP Km 183+290 RHS 29-Oct-19 10:30 AM DONE
A2
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 1st lift at retaining wall
5695 NMSCEW/P-IV/STR/2019/5631 5631 PUP Km 187+835 LHS 29-Oct-19 11:00 AM DONE
A1
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 3rd lift at retaining wall
5696 NMSCEW/P-IV/STR/2019/5632 5632 PUP Km 187+835 RHS 29-Oct-19 12:00 PM
A1 NR
Checking of Shuttering,reinforcement & pouring concrete(M-30) for footing at retaining wall
5697 NMSCEW/P-IV/STR/2019/5633 5633 PUP Km 187+835 LHS 29-Oct-19 2:00 PM DONE
A2
Checking of Shuttering,reinforcement & pouring concrete(M-30) for footing at retaining wall
5698 NMSCEW/P-IV/STR/2019/5634 5634 PUP Km 190+650 RHS 29-Oct-19 4:00 PM
A1 NR
5699 NMSCEW/P-IV/STR/2019/5635 5635 Checking of completion of segments errection for 2×2 utility duct Utility duct Km 190+910 Km 00+000 BHS 30-Oct-19 10:00 AM IPC-09 DONE AE
5700 NMSCEW/P-IV/STR/2019/5636 5636 Checking of Shuttering,reinforcement & pouring concrete for 3rd lift at wall W1,W2,W3 MNB Km 203+409 Km 00+000 RHS 30-Oct-19 2:00 PM IPC-09 DONE
Checking of reinforcement,shuttering and Pouring concrete for final lift at wall A1 & A2 and
5701 NMSCEW/P-IV/STR/2019/5637 5637 Box culvert Km 180+180 RHS 30-Oct-19 4:30 PM
top haunch with top slab NR
5702 NMSCEW/P-IV/STR/2019/5638 5638 Checking Errection and jointing of segments for utility culvert (2x2) Utility duct Km 187+360 Km 00+000 BHS 30-Oct-19 10:30 AM IPC-09 DONE
5703 NMSCEW/P-IV/STR/2019/5639 5639 Checking of reinforcement,shuttering and Pouring concrete for final lift at wall A1 & A2 PUP Km 164+380 LHS 30-Oct-19 4:00 PM DONE
5704 NMSCEW/P-IV/STR/2019/5640 5640 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at RP-04 Viaduct Km 169+800 RHS 30-Oct-19 3:00 PM NR
Checking of Shuttering,reinforcement & pouring concrete(M-35) for 1st lift at retaining wall
5705 NMSCEW/P-IV/STR/2019/5641 5641 Box culvert Km 180+922 RHS 30-Oct-19 11:00 AM DONE
A1
5706 NMSCEW/P-IV/STR/2019/5642 5642 Checking of reinforcement, shuttering & pouring concrete for pier cap at RP-06 Viaduct Km 196+560 Km 00+000 RHS 30-Oct-19 9:30 AM IPC-09 DONE
5707 NMSCEW/P-IV/STR/2019/5643 5643 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-03 Viaduct Km 196+560 LHS 30-Oct-19 2:30 PM DONE
5709 NMSCEW/P-IV/STR/2019/5645 5645 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-08 Viaduct Km 202+190 Km 00+000 RHS 30-Oct-19 10:00 AM IPC-11 Approved AE
5710 NMSCEW/P-IV/STR/2019/5646 5646 Checking of reinforcement, shuttering & pouring concrete for pier cap at RP-03 Viaduct Km 202+190 Km 00+000 RHS 30-Oct-19 12:00 PM IPC-10 DONE AE
5711 NMSCEW/P-IV/STR/2019/5647 5647 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LA-01 Viaduct Km 202+190 LHS 30-Oct-19 2:00 PM DONE
5712 NMSCEW/P-IV/STR/2019/5648 5648 Checking of reinforcement, shuttering & pouring concrete for raft at RP-10 Viaduct Km 202+190 RHS 30-Oct-19 4:00 PM DONE
Checking for stressing and remove slagness of H.T. wires at Girder no-77,78,79,80 at bed no
5713 NMSCEW/P-IV/STR/2019/5649 5649 Girder Km 200+200 LHS 30-Oct-19 11:20 AM DONE
-03, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no -77,78,79,80 at bed no -03, Girder Type-2 at casting yard
5714 NMSCEW/P-IV/STR/2019/5650 5650 Girder Km 200+200 LHS 30-Oct-19 12:15 PM DONE
camp -2
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 2nd lift at retaining wall
5715 NMSCEW/P-IV/STR/2019/5651 5651 PUP Km 187+835 LHS 30-Oct-19 5:15 PM DONE SPOT RFI
A1
Checking of reinforcement,shuttering and Pouring concrete for top haunch at wall A1 & A2
5716 NMSCEW/P-IV/STR/2019/5652 5652 PUP Km 164+380 Km 00+000 RHS 31-Oct-19 4:00 PM IPC-09 DONE
with top slab
5717 NMSCEW/P-IV/STR/2019/5653 5653 Checking of Shuttering,reinforcement & pouring concrete for 2nd lift at wall W1 & W2 CUP Km 206+985 Km 00+000 LHS 31-Oct-19 10:00 AM IPC-09 DONE
5718 NMSCEW/P-IV/STR/2019/5654 5654 Checking of reinforcement, shuttering & pouring concrete for abutment raft at RA-01 MJB 205+610 Km 00+000 RHS 31-Oct-19 4:00 PM IPC-09 DONE
5719 NMSCEW/P-IV/STR/2019/5655 5655 Checking layout,levels,reinforcement, shuttering & pouring concrete for top slab MNB Km 203+409 Km 00+000 RHS 31-Oct-19 5:00 PM IPC-09 DONE
5720 NMSCEW/P-IV/STR/2019/5656 5656 Checking of reinforcement,shuttering and Pouring concrete at RCC Upstand wall W2 PUP Km 204+470 RHS 31-Oct-19 8:00 AM DONE
5721 NMSCEW/P-IV/STR/2019/5657 5657 Checking of reinforcement,shuttering and Pouring concrete at RCC Upstand wall W2 PUP Km 204+470 LHS 31-Oct-19 11:00 AM DONE
5722 NMSCEW/P-IV/STR/2019/5658 5658 Checking layout ,Level & Laying concrete for PCC at Wing wall W1 MNB Km 203+409 RHS 31-Oct-19 9:00 AM DONE
5723 NMSCEW/P-IV/STR/2019/5659 5659 Checking of Shuttering,reinforcement & pouring concrete for 1st lift at wall A1 & A2 PUP Km 174+095 RHS 31-Oct-19 10:00 AM DONE
5724 NMSCEW/P-IV/STR/2019/5660 5660 Checking of Shuttering,reinforcement & pouring concrete for 1st lift at wall A1 LVUP Km 173+400 LHS 31-Oct-19 11:30 AM DONE
5725 NMSCEW/P-IV/STR/2019/5661 5661 Checking of Shuttering,reinforcement & pouring concrete for 2nd lift at wall A2 LVUP Km 173+400 LHS 31-Oct-19 12:30 PM DONE
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-77,78,79,80 at
5726 NMSCEW/P-IV/STR/2019/5662 5662 Girder Km 200+200 LHS 31-Oct-19 3:00 PM DONE
bed no -03, Girder Type-02
Checking for stressing and remove slagness of H.T. wires at Girder no-65,66,67,68 at bed no
5727 NMSCEW/P-IV/STR/2019/5663 5663 Girder Km 200+200 LHS 31-Oct-19 2:00 PM DONE
-08, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no -65,66,67,68 at bed no -08, Girder Type-1 at casting yard
5728 NMSCEW/P-IV/STR/2019/5664 5664 Girder Km 200+200 LHS 31-Oct-19 2:30 PM DONE
camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-81,82,83,84 at bed no
5729 NMSCEW/P-IV/STR/2019/5665 5665 Girder Km 200+200 LHS 31-Oct-19 5:30 PM DONE
-01, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no -81,82,83,84 at bed no -01, Girder Type-2 at casting yard
5730 NMSCEW/P-IV/STR/2019/5666 5666 Girder Km 200+200 LHS 31-Oct-19 6:00 PM DONE
camp -2
5731 NMSCEW/P-IV/STR/2019/5667 5667 Checking layout ,Level & Laying concrete for PCC at LP-17 Viaduct Km 213+915 Km 00+000 LHS 31-Oct-19 9:35 AM IPC-11 Approved AE
5732 NMSCEW/P-IV/STR/2019/5668 5668 Checking layout ,Level & Laying concrete for PCC at RP-18 Viaduct Km 213+915 RHS 31-Oct-19 10:20 AM DONE
5733 NMSCEW/P-IV/STR/2019/5669 5669 Checking layout ,Level & Laying concrete for PCC at RP-16 Viaduct Km 213+915 RHS 31-Oct-19 4:10 PM DONE
5734 NMSCEW/P-IV/STR/2019/5670 5670 Checking layout ,Level & Laying concrete for PCC at RP-17 Viaduct Km 213+915 RHS 31-Oct-19 5:15 PM DONE
5735 NMSCEW/P-IV/STR/2019/5671 5671 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at RP-04 Viaduct Km 169+800 RHS 31-Oct-19 9:00 AM NR
Checking of Shuttering,reinforcement & pouring concrete(M-30) for footing at retaining wall
5736 NMSCEW/P-IV/STR/2019/5672 5672 PUP Km 187+835 RHS 31-Oct-19 10:00 AM DONE
A2
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 1st lift at retaining wall
5737 NMSCEW/P-IV/STR/2019/5673 5673 PUP Km 187+835 LHS 31-Oct-19 11:00 AM DONE
A2
Checking of Shuttering,reinforcement & pouring concrete(M-30) for footing at retaining wall
5738 NMSCEW/P-IV/STR/2019/5674 5674 PUP Km 190+650 RHS 31-Oct-19 9:10 AM DONE
A1
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 3rd lift at retaining wall
5739 NMSCEW/P-IV/STR/2019/5675 5675 PUP Km 187+835 LHS 31-Oct-19 12:12 PM
A1 NR
5740 NMSCEW/P-IV/STR/2019/5676 5676 Checking of Shuttering,reinforcement & pouring concrete(M-35) for bottom slab MNB Km 181+700 RHS 31-Oct-19 5:10 PM NR
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 1st lift at U trough wall
5741 NMSCEW/P-IV/STR/2019/5677 5677 PUP Km 183+290 31-Oct-19 4:23 PM
A1 & A2 NR
Checking of Shuttering,reinforcement & pouring concrete for top slab with top haunch at wall
5742 NMSCEW/P-IV/STR/2019/5678 5678 PUP Km 164+380 RHS 1-Nov-19 5:00 PM DONE
A1 & A2
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 3rd lift at retaining wall
5743 NMSCEW/P-IV/STR/2019/5679 5679 PUP Km 187+835 LHS 1-Nov-19 9:00 AM DONE
A1
5744 NMSCEW/P-IV/STR/2019/5680 5680 Checking of Shuttering,reinforcement & pouring concrete(M-30) for 1st lift at wall A1 & A2 PUP Km 187+677 RHS 1-Nov-19 5:00 PM REPEATED
5746 NMSCEW/P-IV/STR/2019/5682 5682 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-05 Viaduct Km 200+920 LHS 1-Nov-19 4:00 PM
5747 NMSCEW/P-IV/STR/2019/5683 5683 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-05 Viaduct Km 202+190 LHS 1-Nov-19 11:00 AM
5748 NMSCEW/P-IV/STR/2019/5684 5684 Checking of reinforcement, shuttering & pouring concrete for raft at RP-10 Viaduct Km 202+190 RHS 1-Nov-19 10:00 AM
5749 NMSCEW/P-IV/STR/2019/5685 5685 Checking of Shuttering,reinforcement & pouring concrete for 2nd lift at wall A1 & A2 PUP Km 174+095 RHS 1-Nov-19 3:00 PM DONE
5750 NMSCEW/P-IV/STR/2019/5686 5686 Checking of Shuttering,reinforcement & pouring concrete for 1st lift at wall A1 LVUP Km 173+400 LHS 1-Nov-19 4:30 PM DONE
5751 NMSCEW/P-IV/STR/2019/5687 5687 Checking of Shuttering,reinforcement & pouring concrete for 3rd lift at wall A1 & A2 PUP Km 171+110 RHS 1-Nov-19 5:50 PM DONE
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert I)
5752 NMSCEW/P-IV/STR/2019/5688 5688 2x2(2to4m) segment no.-591 Box culvert Km 200+200 LHS 1-Nov-19 10:30 AM
II) 2x2 (4 to 6m) segment no.-1,2,3,4
III) 3x3 (2to4m) segment no.- 77,78,79
5753 NMSCEW/P-IV/STR/2019/5689 5689 Checking of Shuttering,reinforcement & pouring concrete for 2nd lift at wall W1 & W4 MNB Km 199+360 RHS 1-Nov-19 8:00 AM
5754 NMSCEW/P-IV/STR/2019/5690 5690 Checking layout ,Level & Laying concrete for PCC at RP-16 Viaduct Km 213+915 RHS 1-Nov-19 3:30 PM
5755 NMSCEW/P-IV/STR/2019/5691 5691 Checking layout ,Level & Laying concrete for PCC at RP-17 Viaduct Km 213+915 Km 00+000 RHS 1-Nov-19 10:30 AM IPC-11 Approved AE
5756 NMSCEW/P-IV/STR/2019/5692 5692 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-03 Viaduct Km 196+560 Km 00+000 LHS 1-Nov-19 10:10 AM IPC-11 Approved AE
5757 NMSCEW/P-IV/STR/2019/5693 5693 Checking layout ,Level & Laying concrete for PCC at LA-01 Viaduct Km 200+920 LHS 1-Nov-19 4:30 PM
5758 NMSCEW/P-IV/STR/2019/5694 5694 Checking layout ,Level & Laying concrete for PCC at LA-02 Viaduct Km 195+900 LHS 2-Nov-19 3:30 PM
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-77,78,79,80 at
5759 NMSCEW/P-IV/STR/2019/5695 5695 Girder Km 200+200 LHS 2-Nov-19 8:00 AM
bed no -03, Girder Type-02
Checking for stressing and remove slagness of H.T. wires at Girder no-81,82,83,84 at bed no
5760 NMSCEW/P-IV/STR/2019/5696 5696 Girder Km 200+200 LHS 2-Nov-19 8:30 AM
-01, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no -81,82,83,84 at bed no -01, Girder Type-2 at casting yard
5761 NMSCEW/P-IV/STR/2019/5697 5697 Girder Km 200+200 LHS 2-Nov-19 9:00 AM
camp -2
5762 NMSCEW/P-IV/STR/2019/5698 5698 Checking of Shuttering,reinforcement & pouring concrete for cross girder LP-07 to LP-06 Viaduct Km 169+800 LHS 2-Nov-19 3:00 PM
NR
5763 NMSCEW/P-IV/STR/2019/5699 5699 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at RP-04 Viaduct Km 169+800 RHS 2-Nov-19 9:30 AM DONE
5764 NMSCEW/P-IV/STR/2019/5700 5700 Checking of Shuttering,reinforcement & pouring concrete for final lift at wall A2 LVUP Km 169+291 Km 00+000 RHS 2-Nov-19 4:00 PM IPC-10 DONE AE
5765 NMSCEW/P-IV/STR/2019/5701 5701 Checking of reinforcement,shuttering and Pouring concrete at RCC Upstand wall W1 PUP Km 204+470 LHS 2-Nov-19 8:00 AM
5766 NMSCEW/P-IV/STR/2019/5702 5702 Checking of reinforcement,shuttering and Pouring concrete at RCC Upstand wall W1 & W2 PUP Km 203+560 LHS 2-Nov-19 11:00 AM
5767 NMSCEW/P-IV/STR/2019/5703 5703 Checking of top bracket reinforcement,shuttering and Pouring concrete at retaining wall W2 PUP Km 204+470 RHS 2-Nov-19 9:15 AM
5768 NMSCEW/P-IV/STR/2019/5704 5704 Checking layout ,Level & Laying concrete for PCC at RP-14 Viaduct Km 213+915 RHS 2-Nov-19 2:30 PM
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 1st lift at retaining wall
5769 NMSCEW/P-IV/STR/2019/5705 5705 PUP Km 187+835 RHS 2-Nov-19 11:00 AM
A2 NR
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 2nd lift at retaining wall
5770 NMSCEW/P-IV/STR/2019/5706 5706 PUP Km 187+835 LHS 2-Nov-19 12:00 PM
A2 NR
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 4th lift at retaining wall
5771 NMSCEW/P-IV/STR/2019/5707 5707 PUP Km 187+835 LHS 2-Nov-19 2:00 PM
A1 NR
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 4th lift at retaining wall
5772 NMSCEW/P-IV/STR/2019/5708 5708 PUP Km 187+835 RHS 2-Nov-19 3:15 PM
A1 NR
Checking of Shuttering,reinforcement & pouring concrete(M-30) for footing at retaining wall
5773 NMSCEW/P-IV/STR/2019/5709 5709 PUP Km 190+650 LHS 2-Nov-19 4:18 PM
A1 NR
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 1st lift at U trough wall
5774 NMSCEW/P-IV/STR/2019/5710 5710 PUP Km 185+235 2-Nov-19 9:22 AM
A1 & A2 NR
5775 NMSCEW/P-IV/STR/2019/5711 5711 Checking layout ,Level & Laying concrete for PCC at retaining wall W-1 PUP Km 193+880 LHS 2-Nov-19 8:16 AM
5776 NMSCEW/P-IV/STR/2019/5712 5712 Checking of Shuttering,reinforcement & pouring concrete for 1st lift at retaining wall W2 PUP Km 199+060 RHS 3-Nov-19 8:00 AM
5777 NMSCEW/P-IV/STR/2019/5713 5713 Checking of Shuttering,reinforcement & pouring concrete for 1st lift at retaining wall W1 PUP Km 199+060 RHS 3-Nov-19 8:30 AM
5778 NMSCEW/P-IV/STR/2019/5714 5714 Checking of top bracket reinforcement,shuttering and Pouring concrete at retaining wall W1 PUP Km 204+470 RHS 3-Nov-19 9:00 AM
5779 NMSCEW/P-IV/STR/2019/5715 5715 Checking of reinforcement,shuttering and Pouring concrete at RCC Upstand wall W1 PUP Km 204+470 RHS 3-Nov-19 9:30 AM
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-81,82,83,84 at
5780 NMSCEW/P-IV/STR/2019/5716 5716 Girder Km 200+200 LHS 3-Nov-19 11:30 AM
bed no -01, Girder Type-02
5781 NMSCEW/P-IV/STR/2019/5717 5717 Checking layout ,Level & Laying concrete for PCC at RP-13 Viaduct Km 213+915 RHS 3-Nov-19 11:00 AM
5782 NMSCEW/P-IV/STR/2019/5718 5718 Checking layout ,Level & Laying concrete for PCC at RP-18 Viaduct Km 213+915 RHS 3-Nov-19 10:00 AM
5785 NMSCEW/P-IV/STR/2019/5721 5721 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-05 Viaduct Km 200+920 Km 00+000 LHS 3-Nov-19 10:45 AM IPC-11 Approved AE
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 3rd lift at retaining wall
5786 NMSCEW/P-IV/STR/2019/5722 5722 PUP Km 187+835 RHS 3-Nov-19 8:10 AM DONE
A1
5787 NMSCEW/P-IV/STR/2019/5723 5723 Checking of Shuttering,reinforcement & pouring concrete for 3rd lift at retaining wall A2 LVUP Km 173+400 LHS 3-Nov-19 2:00 PM
NR
5788 NMSCEW/P-IV/STR/2019/5724 5724 Checking of Shuttering,reinforcement & pouring concrete(M-30) for bottom slab MNB Km 181+700 RHS 3-Nov-19 8:45 AM DONE
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 1st lift at U trough wall
5789 NMSCEW/P-IV/STR/2019/5725 5725 PUP Km 183+290 3-Nov-19 9:05 AM
A1 & A2 NR
Checking for stressing and remove slagness of H.T. wires at Girder no-85,86,87,88 at bed no
5790 NMSCEW/P-IV/STR/2019/5726 5726 Girder Km 200+200 LHS 4-Nov-19 10:30 AM
-04, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no -85,86,87,88 at bed no -04, Girder Type-2 at casting yard
5791 NMSCEW/P-IV/STR/2019/5727 5727 Girder Km 200+200 LHS 4-Nov-19 11:00 AM
camp -2
5792 NMSCEW/P-IV/STR/2019/5728 5728 Checking of reinforcement, shuttering & pouring concrete for pier cap at LP-06 Viaduct Km 196+560 Km 00+000 LHS 4-Nov-19 2:00 PM IPC-10 DONE
AE
5793 NMSCEW/P-IV/STR/2019/5729 5729 Checking of reinforcement, shuttering & pouring concrete for raft at RP-10 Viaduct Km 202+190 Km 00+000 RHS 4-Nov-19 10:00 AM IPC-10 DONE
5794 NMSCEW/P-IV/STR/2019/5730 5730 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-05 Viaduct Km 202+190 LHS 4-Nov-19 11:30 AM
5795 NMSCEW/P-IV/STR/2019/5731 5731 Checking layout ,Level & Laying concrete for PCC at LP-11 Viaduct Km 213+915 LHS 4-Nov-19 11:15 AM
5796 NMSCEW/P-IV/STR/2019/5732 5732 Checking layout ,Level & Laying concrete for PCC at LP-12 Viaduct Km 213+915 LHS 4-Nov-19 2:30 PM
5797 NMSCEW/P-IV/STR/2019/5733 5733 Checking layout ,Level & Laying concrete for PCC at RP-07 Viaduct Km 213+915 RHS 4-Nov-19 5:30 PM
5798 NMSCEW/P-IV/STR/2019/5734 5734 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP-04 Viaduct Km 200+920 RHS 4-Nov-19 4:00 PM
Checking of reinforcement, shuttering & pouring concrete(M-30) for 2nd lift at median wall
5799 NMSCEW/P-IV/STR/2019/5735 5735 PUP Km 172+190 4-Nov-19 2:00 PM
A1 NR
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 4th lift at retaining wall
5800 NMSCEW/P-IV/STR/2019/5736 5736 PUP Km 187+835 RHS 4-Nov-19 8:30 AM
A1 NR
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 1st lift at retaining wall
5801 NMSCEW/P-IV/STR/2019/5737 5737 PUP Km 187+835 RHS 4-Nov-19 11:00 AM
A2 NR
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 2nd lift at retaining wall
5802 NMSCEW/P-IV/STR/2019/5738 5738 PUP Km 187+835 LHS 4-Nov-19 12:00 PM DONE
A2
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 4th lift at retaining wall
5803 NMSCEW/P-IV/STR/2019/5739 5739 PUP Km 187+835 LHS 4-Nov-19 2:10 PM DONE
A1
Checking of Shuttering,reinforcement & pouring concrete(M-30) for footing at retaining wall
5804 NMSCEW/P-IV/STR/2019/5740 5740 PUP Km 190+650 LHS 4-Nov-19 4:00 PM
A1 NR
5805 NMSCEW/P-IV/STR/2019/5741 5741 Checking of Shuttering,reinforcement & pouring concrete(M-30) for final lift at U trough wall PUP Km 187+838 4-Nov-19 5:00 PM
NR
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert
5806 NMSCEW/P-IV/STR/2019/5742 5742 Box culvert Km 200+200 LHS 5-Nov-19 9:30 AM
I) 2x2 (4 to 6m) segment no.-1,2,3,4
5807 NMSCEW/P-IV/STR/2019/5743 5743 Checking of Shuttering,reinforcement & pouring concrete for 2nd lift at wall W2 & W3 MNB Km 199+360 RHS 5-Nov-19 11:30 AM
5808 NMSCEW/P-IV/STR/2019/5744 5744 Checking of reinforcement,shuttering and Pouring concrete at RCC Upstand wall W1 PUP Km 203+560 RHS 5-Nov-19 8:00 AM
5809 NMSCEW/P-IV/STR/2019/5745 5745 Checking layout ,Level & Laying concrete PCC for wing wall W2 MNB Km 203+406 RHS 5-Nov-19 9:00 AM
5810 NMSCEW/P-IV/STR/2019/5746 5746 Checking of Shuttering,reinforcement & pouring concrete for cross girder LP-07 to LP-06 Viaduct Km 169+800 LHS 5-Nov-19 4:00 PM
NR
5811 NMSCEW/P-IV/STR/2019/5747 5747 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at RP-07 Viaduct Km 169+800 RHS 5-Nov-19 3:00 PM NR
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5812 NMSCEW/P-IV/STR/2019/5748 5748 Culvert (2×2) (Cushion 4 to 6m) at precast yard camp-1,Segment no.- Box culvert Km 175+500 LHS 5-Nov-19 9:15 AM DONE
39,40,41,42,43,44,45,46,47,48,49,50,51,52,53,54,55.
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5813 NMSCEW/P-IV/STR/2019/5749 5749 Culvert (2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.- Box culvert Km 175+500 LHS 5-Nov-19 12:30 PM DONE
349,350,351,352,353,354,355
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5814 NMSCEW/P-IV/STR/2019/5750 5750 Culvert (3×3) (Cushion 0 to 2m) at precast yard camp-1,Segment no.- Box culvert Km 175+500 LHS 5-Nov-19 3:00 PM DONE
17,18,19,20,21,22,23,24,25,26,27,28,29,30,31,32,33,34.
5815 NMSCEW/P-IV/STR/2019/5751 5751 Checking layout, structural excavation,level and pouring Concrete(M-15) for PCC at Pier-P3 VOP Km 181+420 LHS 5-Nov-19 8:00 AM DONE
Checking of reinforcement, shuttering & pouring concrete(M-30) for 1st lift at U type
5816 NMSCEW/P-IV/STR/2019/5752 5752 PUP Km 185+235 5-Nov-19 9:00 AM DONE
retaining wall (Median) A1 & A2
Checking of reinforcement, shuttering & pouring concrete(M-30) for 1st lift at U type
5817 NMSCEW/P-IV/STR/2019/5753 5753 PUP Km 183+290 5-Nov-19 11:00 AM DONE
retaining wall (Median) A1 & A2
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 1st lift at retaining wall
5818 NMSCEW/P-IV/STR/2019/5754 5754 PUP Km 187+835 RHS 5-Nov-19 2:00 PM
A2 NR
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 3rd lift at retaining wall
5819 NMSCEW/P-IV/STR/2019/5755 5755 PUP Km 187+835 LHS 5-Nov-19 12:00 PM DONE
A2
Checking of Shuttering,reinforcement & pouring concrete(M-30) for final lift at retaining wall
5820 NMSCEW/P-IV/STR/2019/5756 5756 PUP Km 187+835 LHS 5-Nov-19 3:00 PM
A1 NR
Checking of Shuttering,reinforcement & pouring concrete(M-30) for footing at retaining wall
5821 NMSCEW/P-IV/STR/2019/5757 5757 PUP Km 190+650 LHS 5-Nov-19 4:00 PM
A1 NR
5822 NMSCEW/P-IV/STR/2019/5758 5758 Checking of Shuttering,reinforcement & pouring concrete(M-30) for final lift at U trough wall PUP Km 187+835 5-Nov-19 8:30 AM DONE
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 3rd lift at retaining wall
5823 NMSCEW/P-IV/STR/2019/5759 5759 LVUP Km 173+400 LHS 5-Nov-19 2:10 PM DONE
A2
Checking for stressing and remove slagness of H.T. wires at Girder no-69,70,71,72 at bed no
5824 NMSCEW/P-IV/STR/2019/5760 5760 Girder Km 200+200 LHS 5-Nov-19 2:00 PM
-06, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no -69,70,71,72 at bed no -06, Girder Type-1 at casting yard
5825 NMSCEW/P-IV/STR/2019/5761 5761 Girder Km 200+200 LHS 5-Nov-19 2:30 PM
camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-73,74,75,76 at bed no
5826 NMSCEW/P-IV/STR/2019/5762 5762 Girder Km 200+200 LHS 5-Nov-19 4:00 PM
-07, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no -73,74,75,76 at bed no -07, Girder Type-1 at casting yard
5827 NMSCEW/P-IV/STR/2019/5763 5763 Girder Km 200+200 LHS 5-Nov-19 4:30 PM
camp -2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-85,86,87,88 at
5828 NMSCEW/P-IV/STR/2019/5764 5764 Girder Km 200+200 LHS 5-Nov-19 6:30 PM
bed no -04, Girder Type-02
5829 NMSCEW/P-IV/STR/2019/5765 5765 Checking layout ,Level & Laying concrete for PCC at RP-14 Viaduct Km 213+915 Km 00+000 RHS 5-Nov-19 9:40 AM IPC-11 Approved AE
5830 NMSCEW/P-IV/STR/2019/5766 5766 Checking layout ,Level & Laying concrete for PCC at RP-13 Viaduct Km 213+915 RHS 5-Nov-19 2:15 PM
5831 NMSCEW/P-IV/STR/2019/5767 5767 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-12 Viaduct Km 202+190 Km 00+000 LHS 5-Nov-19 10:00 AM IPC-11 Approved AE
5832 NMSCEW/P-IV/STR/2019/5768 5768 Checking of layout,level, Shuttering,reinforcement & pouring concrete for raft Box culvert Km 201+280 RHS 5-Nov-19 12:00 PM SPOT RFI
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 2nd lift at retaining wall
5833 NMSCEW/P-IV/STR/2019/5769 5769 PUP Km 199+060 RHS 6-Nov-19 10:00 AM
W1 & W2
5834 NMSCEW/P-IV/STR/2019/5770 5770 Checking layout ,Level & Laying concrete for PCC at LA-02 Viaduct Km 195+900 Km 00+000 LHS 6-Nov-19 9:30 AM IPC-10 DONE
5835 NMSCEW/P-IV/STR/2019/5771 5771 Checking of reinforcement, shuttering & pouring concrete for raft at RP-12 Viaduct Km 202+190 Km 00+000 RHS 6-Nov-19 10:30 AM IPC-10 DONE AE
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-69,70,71,72 at
5836 NMSCEW/P-IV/STR/2019/5772 5772 Girder Km 200+200 LHS 6-Nov-19 12:00 PM
bed no -06, Girder Type-01
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-73,74,75,76 at
5837 NMSCEW/P-IV/STR/2019/5773 5773 Girder Km 200+200 LHS 6-Nov-19 5:30 PM
bed no -07, Girder Type-01
5838 NMSCEW/P-IV/STR/2019/5774 5774 Checking of Shuttering,reinforcement & pouring concrete for 1st lift at wall A1 & A2 VUP Km 166+987 LHS 6-Nov-19 3:00 PM DONE
Checking of Shuttering,reinforcement & pouring concrete for 3rd lift at retaining wall A1 &
5839 NMSCEW/P-IV/STR/2019/5775 5775 PUP Km 174+095 RHS 6-Nov-19 11:30 AM DONE
A2
5840 NMSCEW/P-IV/STR/2019/5776 5776 Checking of Shuttering,reinforcement & pouring concrete for 4th lift at retaining wall A2 LVUP Km 173+400 LHS 6-Nov-19 1:00 PM DONE
5841 NMSCEW/P-IV/STR/2019/5777 5777 Checking of Shuttering,reinforcement & pouring concrete for 2nd lift at retaining wall A1 LVUP Km 173+400 LHS 6-Nov-19 2:00 PM
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 5th lift at retaining wall
5842 NMSCEW/P-IV/STR/2019/5778 5778 PUP Km 187+835 LHS 6-Nov-19 8:00 AM
A1 NR
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 4th lift at retaining wall
5843 NMSCEW/P-IV/STR/2019/5779 5779 PUP Km 187+835 RHS 6-Nov-19 11:00 AM
A1
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 4th lift at retaining wall
5844 NMSCEW/P-IV/STR/2019/5780 5780 PUP Km 187+835 LHS 6-Nov-19 9:00 AM
A2
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 1st lift at retaining wall
5845 NMSCEW/P-IV/STR/2019/5781 5781 PUP Km 187+835 RHS 6-Nov-19 10:15 AM DONE
A2
5846 NMSCEW/P-IV/STR/2019/5782 5782 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-03 Viaduct Km 200+920 Km 00+000 LHS 6-Nov-19 4:00 PM IPC-11 Approved
5847 NMSCEW/P-IV/STR/2019/5783 5783 Checking layout ,Level & Laying concrete for PCC at abutment LA-01 Viaduct Km 200+920 Km 00+000 LHS 6-Nov-19 10:20 AM IPC-10 DONE
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
5848 NMSCEW/P-IV/STR/2019/5784 5784 Culvert Box culvert Km 200+200 LHS 6-Nov-19 9:15 AM
I) 2x2 (4 to 6m) segment no.-7,8,9,10,11,12,13
5849 NMSCEW/P-IV/STR/2019/5785 5785 Checking layout ,Level & Laying concrete for PCC at LP-13 Viaduct Km 213+915 LHS 6-Nov-19 2:30 PM
5850 NMSCEW/P-IV/STR/2019/5786 5786 Checking layout ,Level & Laying concrete for PCC at LP-11 Viaduct Km 213+915 LHS 6-Nov-19 3:30 PM
5851 NMSCEW/P-IV/STR/2019/5787 5787 Checking of reinforcement, shuttering & pouring concrete for pier cap at RP-05 Viaduct Km 202+190 Km 00+000 RHS 6-Nov-19 5:00 PM IPC-10 DONE
5852 NMSCEW/P-IV/STR/2019/5788 5788 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at RP-07 Viaduct Km 169+800 RHS 6-Nov-19 2:00 PM DONE
Checking of Shuttering and reinforcement for RE WALL PANEL precast TYPE -A 144 NOS,
5853 NMSCEW/P-IV/STR/2019/5789 5789 TYPE -B 50 NOS,TYPE -Sta 9 NOS, TYPE -Stb 10 NOS, TYPE -Stc 10 NOS, TYPE -Std 8 RE Wall Panel Km 200+200 LHS 6-Nov-19 4:10 PM
NOS, TYPE -Ltc 15 NOS, TYPE -Lta 5 NOS, at RE panel precast yard camp 2
5854 NMSCEW/P-IV/STR/2019/5790 5790 Checking of Shuttering,reinforcement & pouring concrete for final lift at wall A1 LVUP Km 169+291 Km 00+000 RHS 7-Nov-19 4:00 PM IPC-10 DONE
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 2nd lift at median wall
5855 NMSCEW/P-IV/STR/2019/5791 5791 PUP Km 172+190 BHS 7-Nov-19 2:00 PM DONE
A1
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 1st lift at median wall
5856 NMSCEW/P-IV/STR/2019/5792 5792 PUP Km 172+190 BHS 7-Nov-19 2:30 PM DONE
A2
Checking layout, structural excavation,level and pouring Concrete(M-10) for PCC at U trough
5857 NMSCEW/P-IV/STR/2019/5793 5793 PUP Km 188+575 7-Nov-19 4:15 PM
bottom slab NR
Checking of Shuttering,reinforcement & pouring concrete(M-30) for footing at retaining wall
5858 NMSCEW/P-IV/STR/2019/5794 5794 PUP Km 190+650 LHS 7-Nov-19 10:00 AM DONE
A1
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 5th lift at retaining wall
5859 NMSCEW/P-IV/STR/2019/5795 5795 PUP Km 187+835 RHS 7-Nov-19 2:15 PM
A1 NR
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 4th lift at retaining wall
5860 NMSCEW/P-IV/STR/2019/5796 5796 PUP Km 171+110 RHS 7-Nov-19 11:00 AM DONE
A2
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 3rd lift at retaining wall
5861 NMSCEW/P-IV/STR/2019/5797 5797 PUP Km 171+110 LHS 7-Nov-19 11:30 AM DONE
A1
Checking for stressing and remove slagness of H.T. wires at Girder no-89,90,91,92 at bed no
5862 NMSCEW/P-IV/STR/2019/5798 5798 Girder Km 200+200 LHS 7-Nov-19 5:00 PM
-02, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no -89,90,91,92 at bed no -02, Girder Type-2 at casting yard
5863 NMSCEW/P-IV/STR/2019/5799 5799 Girder Km 200+200 LHS 7-Nov-19 5:30 PM
camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-77,78,79,80 at bed no
5864 NMSCEW/P-IV/STR/2019/5800 5800 Girder Km 200+200 LHS 7-Nov-19 6:00 PM
-05, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no -77,78,79,80 at bed no -05, Girder Type-1 at casting yard
5865 NMSCEW/P-IV/STR/2019/5801 5801 Girder Km 200+200 LHS 7-Nov-19 6:30 PM
camp -2
5866 NMSCEW/P-IV/STR/2019/5802 5802 Checking of reinforcement, shuttering & pouring concrete for pier cap at LP-05 Viaduct Km 196+560 Km 00+000 LHS 7-Nov-19 3:30 PM IPC-10 DONE AE
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
5867 NMSCEW/P-IV/STR/2019/5803 5803 Culvert Box culvert Km 200+200 LHS 7-Nov-19 10:15 AM
I) 2x2 (4 to 6m) segment no.-14,15,16,17,18,19
Checking layout, structural excavation,level and pouring Concrete(M-10) for PCC at U type
5868 NMSCEW/P-IV/STR/2019/5804 5804 PUP Km 184+190 7-Nov-19 8:00 AM
retaining wall
5869 NMSCEW/P-IV/STR/2019/5805 5805 Checking of Shuttering,reinforcement & pouring concrete(M-35) for bottom slab Box culvert Km 180+922 LHS 7-Nov-19 4:00 PM NR
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 2nd lift at retaining wall
5870 NMSCEW/P-IV/STR/2019/5806 5806 PUP Km 183+290 RHS 7-Nov-19 4:35 PM DONE
A2
5871 NMSCEW/P-IV/STR/2019/5807 5807 Checking layout ,Level & Laying concrete for PCC at LP-12 Viaduct Km 213+915 LHS 7-Nov-19 2:20 PM
5872 NMSCEW/P-IV/STR/2019/5808 5808 Checking layout ,Level & Laying concrete for PCC at RP-11 Viaduct Km 213+915 RHS 7-Nov-19 10:40 AM
Checking of Shuttering,reinforcement & pouring concrete(M-45) for cross girder LP-07 to LP-
5873 NMSCEW/P-IV/STR/2019/5809 5809 Viaduct Km 169+800 LHS 7-Nov-19 9:00 AM DONE
06
5874 NMSCEW/P-IV/STR/2019/5810 5810 Checking of layout,level, Shuttering,reinforcement & pouring concrete for raft Box culvert Km 201+280 Km 00+000 RHS 7-Nov-19 12:00 PM IPC-11 Approved AE
Checking layout, structural excavation,level and pouring Concrete(M-10) for PCC at (5x3) box
5875 NMSCEW/P-IV/STR/2019/5811 5811 Box culvert Km 177+760 Km 00+000 BHS 7-Nov-19 11:30 AM IPC-10 DONE
culvert AE
5876 NMSCEW/P-IV/STR/2019/5812 5812 Checking of Shuttering,reinforcement & pouring concrete for raft at U type retaining wall VUP Km 176+614 7-Nov-19 4:30 PM DONE
5877 NMSCEW/P-IV/STR/2019/5813 5813 Checking layout,level,structural excavation PUP Km 179+050 BHS 8-Nov-19 10:30 AM DONE
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 3rd lift at retaining wall
5878 NMSCEW/P-IV/STR/2019/5814 5814 PUP Km 199+060 RHS 8-Nov-19 11:00 AM
W1 & W2
5879 NMSCEW/P-IV/STR/2019/5815 5815 Checking of Shuttering,reinforcement & pouring concrete(M-35) for bottom slab Box culvert Km 180+922 LHS 8-Nov-19 4:00 PM DONE
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 2nd lift at U type
5880 NMSCEW/P-IV/STR/2019/5816 5816 PUP Km 185+235 8-Nov-19 4:30 PM DONE
retaining wall
5881 NMSCEW/P-IV/STR/2019/5817 5817 Checking of Shuttering,reinforcement & pouring concrete(M-35) for raft at Pier-P3 VOP Km 181+420 LHS 8-Nov-19 2:00 PM NR
5882 NMSCEW/P-IV/STR/2019/5818 5818 Checking layout, structural excavation,level and pouring Concrete(M-15) for PCC at Pier-P3 VOP Km 181+420 RHS 8-Nov-19 5:00 PM
NR
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 2nd lift at retaining wall
5883 NMSCEW/P-IV/STR/2019/5819 5819 PUP Km 187+835 RHS 8-Nov-19 11:05 AM DONE
A2
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 1st lift at retaining wall
5884 NMSCEW/P-IV/STR/2019/5820 5820 PUP Km 190+650 LHS 8-Nov-19 3:00 PM DONE
A1
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 2nd lift at Box culvert
5885 NMSCEW/P-IV/STR/2019/5821 5821 Box culvert Km 187+677 RHS 8-Nov-19 5:15 PM
wall
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-89,90,91,92 at
5886 NMSCEW/P-IV/STR/2019/5822 5822 Girder Km 200+200 LHS 8-Nov-19 6:00 PM
bed no -02, Girder Type-02
5887 NMSCEW/P-IV/STR/2019/5823 5823 Checking of layout,level, Shuttering,reinforcement & pouring concrete for raft at RA-2 Viaduct Km 195+900 RHS 8-Nov-19 3:30 PM
5888 NMSCEW/P-IV/STR/2019/5824 5824 Checking of Shuttering,reinforcement & pouring concrete for raft at wing wall W1 & W2 MNB Km 203+409 RHS 8-Nov-19 8:00 AM
Checking of Shuttering,reinforcement & pouring concrete for 4th lift at U type retaining wall
5889 NMSCEW/P-IV/STR/2019/5825 5825 PUP Km 204+470 8-Nov-19 10:00 AM
W1
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 4th lift at retaining wall
5890 NMSCEW/P-IV/STR/2019/5826 5826 PUP Km 174+095 RHS 8-Nov-19 2:10 PM DONE
A1 & a2
Checking of Shuttering,reinforcement & pouring concrete(M-30) for bottom haunch at median
5891 NMSCEW/P-IV/STR/2019/5827 5827 PUP Km 174+095 BHS 8-Nov-19 10:20 AM DONE
wall A1 & a2
5892 NMSCEW/P-IV/STR/2019/5828 5828 Checking layout ,Level & Laying concrete for PCC at LP-11 Viaduct Km 213+915 Km 00+000 LHS 8-Nov-19 10:40 AM IPC-11 Approved AE
5893 NMSCEW/P-IV/STR/2019/5829 5829 Checking layout ,Level & Laying concrete for PCC at RP-13 Viaduct Km 213+915 Km 00+000 RHS 8-Nov-19 11:35 AM IPC-11 Approved
5894 NMSCEW/P-IV/STR/2019/5830 5830 Checking layout ,Level & Laying concrete for PCC at LP-13 Viaduct Km 213+915 LHS 8-Nov-19 3:45 PM
5895 NMSCEW/P-IV/STR/2019/5831 5831 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-11 Viaduct Km 202+190 RHS 8-Nov-19 10:18 AM
5896 NMSCEW/P-IV/STR/2019/5832 5832 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP-03 Viaduct Km 200+920 RHS 8-Nov-19 4:00 PM
5897 NMSCEW/P-IV/STR/2019/5833 5833 Checking of Shuttering,reinforcement & pouring concrete for 1st lift at wing wall W1 & W2 MNB Km 203+409 RHS 9-Nov-19 8:00 AM
5898 NMSCEW/P-IV/STR/2019/5834 5834 Checking layout ,Level & Laying concrete for PCC at wing wall W2 MNB Km 203+409 LHS 9-Nov-19 9:00 AM
Checking of Shuttering,reinforcement & pouring concrete for raft with bottom haunch at U
5899 NMSCEW/P-IV/STR/2019/5835 5835 PUP Km 179+983 9-Nov-19 10:30 AM DONE
type retaining wall A1 & A2
5900 NMSCEW/P-IV/STR/2019/5836 5836 Checking of reinforcement, shuttering & pouring concrete for pier cap at RP-06 Viaduct Km 202+190 Km 00+000 RHS 9-Nov-19 10:00 AM IPC-10 DONE
AE
5901 NMSCEW/P-IV/STR/2019/5837 5837 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-06 Viaduct Km 202+190 LHS 9-Nov-19 12:00 PM
Checking for stressing and remove slagness of H.T. wires at Girder no-77,78,79,80 at bed no
5902 NMSCEW/P-IV/STR/2019/5838 5838 Girder Km 200+200 LHS 9-Nov-19 8:15 AM
-05, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no -77,78,79,80 at bed no -05, Girder Type-1 at casting yard
5903 NMSCEW/P-IV/STR/2019/5839 5839 Girder Km 200+200 LHS 9-Nov-19 8:45 AM
camp -2
Checking of Shuttering,reinforcement & pouring concrete(M-45) for cross girder LP-06 to LP-
5904 NMSCEW/P-IV/STR/2019/5840 5840 Viaduct Km 169+800 LHS 9-Nov-19 3:00 PM
05 NR
Checking of Shuttering,reinforcement & pouring concrete(M-30) for footing at retaining wall
5905 NMSCEW/P-IV/STR/2019/5841 5841 PUP Km 185+235 RHS 9-Nov-19 10:15 AM DONE
A1
5906 NMSCEW/P-IV/STR/2019/5842 5842 Checking of Shuttering,reinforcement & pouring concrete(M-35) for raft at Pier-P3 VOP Km 181+420 LHS 9-Nov-19 11:00 AM DONE
5907 NMSCEW/P-IV/STR/2019/5843 5843 Checking layout, structural excavation,level and pouring Concrete(M-15) for PCC at Pier-P3 VOP Km 181+420 RHS 9-Nov-19 5:00 PM DONE
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 3rd lift at retaining wall
5908 NMSCEW/P-IV/STR/2019/5844 5844 PUP Km 187+835 RHS 9-Nov-19 12:00 PM DONE
A2
Checking layout, structural excavation,level and pouring Concrete(M-10) for PCC at U trough
5909 NMSCEW/P-IV/STR/2019/5845 5845 PUP Km 188+575 9-Nov-19 2:00 PM
bottom slab NR
5910 NMSCEW/P-IV/STR/2019/5846 5846 Checking layout ,Level & Laying concrete for PCC at LP-12 Viaduct Km 213+915 LHS 9-Nov-19 11:20 AM
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-77,78,79,80 at
5911 NMSCEW/P-IV/STR/2019/5847 5847 Girder Km 200+200 LHS 9-Nov-19 7:00 PM
bed no -05, Girder Type-01
5912 NMSCEW/P-IV/STR/2019/5848 5848 Checking of layout,level, Shuttering,reinforcement & pouring concrete for raft at LP-2 Viaduct Km 213+915 LHS 9-Nov-19 4:30 PM
5913 NMSCEW/P-IV/STR/2019/5849 5849 Checking of girder launching and positioning of module no.- 1 at LP-10 to LA-02 Viaduct Km 169+800 LHS 9-Nov-19 9:00 AM DONE
5914 NMSCEW/P-IV/STR/2019/5850 5850 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at RA-02 Viaduct Km 169+800 RHS 9-Nov-19 4:00 PM NR
5915 NMSCEW/P-IV/STR/2019/5851 5851 Checking of layout,level, Shuttering,reinforcement & pouring concrete for raft at RA-1 MJB Km 205+610 RHS 10-Nov-19 6:00 PM
5916 NMSCEW/P-IV/STR/2019/5852 5852 Checking of Shuttering,reinforcement & pouring concrete for 2nd lift at wing wall W1 & W2 MNB Km 203+409 RHS 10-Nov-19 8:00 AM
5917 NMSCEW/P-IV/STR/2019/5853 5853 Checking of Shuttering,reinforcement & pouring concrete for raft at median PUP Km 193+880 10-Nov-19 9:45 AM
5918 NMSCEW/P-IV/STR/2019/5854 5854 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LA-02 Viaduct Km 169+800 LHS 10-Nov-19 9:00 AM DONE
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 1st lift at retaining wall
5919 NMSCEW/P-IV/STR/2019/5855 5855 PUP Km 190+650 RHS 10-Nov-19 5:00 PM DONE
A1
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 2nd lift at U type
5920 NMSCEW/P-IV/STR/2019/5856 5856 PUP Km 183+290 10-Nov-19 10:00 AM DONE
retaining wall
5921 NMSCEW/P-IV/STR/2019/5857 5857 Checking layout, structural excavation,level and pouring Concrete(M-15) for PCC at Pier-P1 VOP Km 181+420 RHS 10-Nov-19 5:15 PM DONE
5922 NMSCEW/P-IV/STR/2019/5858 5858 Checking of Shuttering,reinforcement & pouring concrete(M-35) for bottom slab VUP Km 187+113 10-Nov-19 10:30 AM DONE
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 4th lift at retaining wall
5923 NMSCEW/P-IV/STR/2019/5859 5859 PUP Km 187+835 RHS 10-Nov-19 12:00 PM DONE
A2
Checking for stressing and remove slagness of H.T. wires at Girder no-81,82,83,84 at bed no
5924 NMSCEW/P-IV/STR/2019/5860 5860 Girder Km 200+200 LHS 10-Nov-19 10:15 AM
-08, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no -81,82,83,84 at bed no -08, Girder Type-1 at casting yard
5925 NMSCEW/P-IV/STR/2019/5861 5861 Girder Km 200+200 LHS 10-Nov-19 10:45 AM
camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-93,94,95,96 at bed no
5926 NMSCEW/P-IV/STR/2019/5862 5862 Girder Km 200+200 LHS 10-Nov-19 9:15 AM
-03, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no -93,94,95,96 at bed no -03, Girder Type-2 at casting yard
5927 NMSCEW/P-IV/STR/2019/5863 5863 Girder Km 200+200 LHS 10-Nov-19 9:45 AM
camp -2
5928 NMSCEW/P-IV/STR/2019/5864 5864 Checking of layout,level, Shuttering,reinforcement & pouring concrete for raft at RA-02 Viaduct Km 195+900 Km 00+000 RHS 10-Nov-19 11:00 AM IPC-10 DONE
5929 NMSCEW/P-IV/STR/2019/5865 5865 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-02 Viaduct Km 200+920 LHS 10-Nov-19 11:30 AM
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
5930 NMSCEW/P-IV/STR/2019/5866 5866 Culvert Box culvert Km 200+200 LHS 10-Nov-19 10:20 AM
I) 2x2 (4 to 6m) segment no.-20,21,22,23,24
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5931 NMSCEW/P-IV/STR/2019/5867 5867 Culvert (2×2) (Cushion 4 to 6m) at precast yard camp-1,Segment no.- Box culvert Km 175+500 LHS 10-Nov-19 8:30 AM DONE
56,57,58,59,60,61,62,63,64,65,66,67,68,69,70,71.
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
Culvert (2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-
5932 NMSCEW/P-IV/STR/2019/5868 5868 Box culvert Km 175+500 LHS 10-Nov-19 9:50 AM DONE
356,357,358,359,360,361,362,363,364,365,366,367,368,369,370,371,372,373,374,375,376,37
7,378,379,380,381,382,383,384,385,386
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 3rd lift at retaining wall
5933 NMSCEW/P-IV/STR/2019/5869 5869 LVUP Km 173+400 LHS 10-Nov-19 10:19 AM DONE
A1
5934 NMSCEW/P-IV/STR/2019/5870 5870 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-11 Viaduct Km 202+190 RHS 10-Nov-19 11:50 AM
5939 NMSCEW/P-IV/STR/2019/5875 5875 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP-10 Viaduct Km 202+190 Km 00+000 RHS 11-Nov-19 11:30 AM IPC-11 Approved AE
5940 NMSCEW/P-IV/STR/2019/5876 5876 Checking of layout,level, Shuttering,reinforcement & pouring concrete for raft at LP-2 Viaduct Km 213+915 LHS 11-Nov-19 3:30 PM
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 1st lift at median wall
5941 NMSCEW/P-IV/STR/2019/5877 5877 PUP Km 174+095 BHS 11-Nov-19 4:45 PM DONE
A1 & A2
Checking of Shuttering,reinforcement & pouring concrete(M-45) for cross girder LP-06 to LP-
5942 NMSCEW/P-IV/STR/2019/5878 5878 Viaduct Km 169+800 LHS 11-Nov-19 3:00 PM
05 NR
5943 NMSCEW/P-IV/STR/2019/5879 5879 Checking of reinforcement, shuttering & pouring concrete for abutment cap at RA-01 Viaduct Km 169+800 RHS 11-Nov-19 4:15 PM NR
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5944 NMSCEW/P-IV/STR/2019/5880 5880 Box culvert Km 175+500 LHS 11-Nov-19 9:00 AM DONE
Culvert (2×2) (Cushion 4 to 6m) at precast yard camp-1,Segment no.- 72,73,74,75,76,77.
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5945 NMSCEW/P-IV/STR/2019/5881 5881 Culvert (2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-387,388,389, 390, Box culvert Km 175+500 LHS 11-Nov-19 11:30 AM DONE
391,392,393,394.
5946 NMSCEW/P-IV/STR/2019/5882 5882 Checking layout, structural excavation & level Box culvert Km 179+715 Km 00+000 BHS 12-Nov-19 10:00 AM IPC-10 DONE AE
5947 NMSCEW/P-IV/STR/2019/5883 5883 Checking layout, structural excavation & level at A2 side MNB Km 176+875 BHS 12-Nov-19 11:00 AM DONE
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert
5948 NMSCEW/P-IV/STR/2019/5884 5884 Box culvert Km 200+200 LHS 12-Nov-19 9:00 AM
I) 2x2 (4 to 6m) segment no.-25,26,27,28,29,30,31,32
II) 3x3 (2 to 4m) segment no.-77,78
Checking layout, structural excavation,level and pouring Concrete(M-10) for PCC at U trough
5949 NMSCEW/P-IV/STR/2019/5885 5885 PUP Km 188+575 12-Nov-19 3:00 PM DONE
bottom slab
Checking layout, structural excavation,level and pouring Concrete(M-10) PCC for footing at
5950 NMSCEW/P-IV/STR/2019/5886 5886 PUP Km 188+575 RHS 12-Nov-19 10:30 AM
retaining wall A1 NR
Checking layout, structural excavation,level and pouring Concrete(M-10) PCC for footing at
5951 NMSCEW/P-IV/STR/2019/5887 5887 PUP Km 188+575 LHS 12-Nov-19 11:00 AM
retaining wall A1 NR
Checking layout, structural excavation,level and pouring Concrete(M-10) PCC for footing at
5952 NMSCEW/P-IV/STR/2019/5888 5888 PUP Km 188+575 LHS 12-Nov-19 11:30 AM
retaining wall A2 NR
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 2nd lift at retaining wall
5953 NMSCEW/P-IV/STR/2019/5889 5889 PUP Km 190+650 LHS 12-Nov-19 9:30 AM
A1 NR
Checking of Shuttering,reinforcement & pouring concrete(M-45) for cross girder LP-06 to LP-
5954 NMSCEW/P-IV/STR/2019/5890 5890 Viaduct Km 169+800 LHS 12-Nov-19 10:00 AM DONE
05 to LP-04
5955 NMSCEW/P-IV/STR/2019/5891 5891 Checking of reinforcement, shuttering & pouring concrete for abutment cap at RA-01 Viaduct Km 169+800 RHS 12-Nov-19 11:15 AM DONE
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 4th lift at retaining wall
5956 NMSCEW/P-IV/STR/2019/5892 5892 LVUP Km 173+400 LHS 12-Nov-19 2:00 PM DONE
A1
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 3rd lift at median wall
5957 NMSCEW/P-IV/STR/2019/5893 5893 PUP Km 172+190 BHS 12-Nov-19 2:30 PM DONE
A1
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 2nd lift at median wall
5958 NMSCEW/P-IV/STR/2019/5894 5894 PUP Km 172+190 BHS 12-Nov-19 3:00 PM DONE
A2
Checking for stressing and remove slagness of H.T. wires at Girder no-85,86,87,88 at bed no
5959 NMSCEW/P-IV/STR/2019/5895 5895 Girder Km 200+200 LHS 12-Nov-19 6:00 PM
-06, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no -85,86,87,88 at bed no -06, Girder Type-1 at casting yard
5960 NMSCEW/P-IV/STR/2019/5896 5896 Girder Km 200+200 LHS 12-Nov-19 6:30 PM
camp -2
5961 NMSCEW/P-IV/STR/2019/5897 5897 Checking of reinforcement, shuttering & pouring concrete for pier cap at LP-04 Viaduct Km 196+560 LHS 12-Nov-19 3:45 PM
5962 NMSCEW/P-IV/STR/2019/5898 5898 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-03 Viaduct Km 196+560 LHS 12-Nov-19 2:45 PM
5963 NMSCEW/P-IV/STR/2019/5899 5899 Checking layout ,Level & Laying concrete for PCC at LP-12 Viaduct Km 213+915 LHS 12-Nov-19 10:15 AM
5964 NMSCEW/P-IV/STR/2019/5900 5900 Checking layout ,Level & Laying concrete for PCC at LP-13 Viaduct Km 213+915 LHS 12-Nov-19 2:20 PM
5965 NMSCEW/P-IV/STR/2019/5901 5901 Checking of reinforcement,shuttering and Pouring concrete for final lift at wall A1 & A2 Box culvert Km 163+570 BHS 12-Nov-19 4:30 PM
NR
5966 NMSCEW/P-IV/STR/2019/5902 5902 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at wall A1 & A2 PUP Km 164+380 Km 00+000 LHS 12-Nov-19 4:00 PM IPC-10 DONE
AE
5967 NMSCEW/P-IV/STR/2019/5903 5903 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-11 Viaduct Km 202+190 RHS 12-Nov-19 3:00 PM
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5968 NMSCEW/P-IV/STR/2019/5904 5904 Box culvert Km 175+500 LHS 12-Nov-19 9:35 AM DONE
Culvert (3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-253,254
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5969 NMSCEW/P-IV/STR/2019/5905 5905 Box culvert Km 175+500 LHS 12-Nov-19 10:55 AM
Culvert (3×3) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-13,16
NR
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5970 NMSCEW/P-IV/STR/2019/5906 5906 Box culvert Km 175+500 LHS 12-Nov-19 12:46 PM DONE
Culvert (2×2) (Cushion 4 to 6m) at precast yard camp-1,Segment no.-78,79,80
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
5971 NMSCEW/P-IV/STR/2019/5907 5907 Box culvert Km 175+500 LHS 12-Nov-19 4:12 PM DONE
Culvert (2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-395,396,397,398
5972 NMSCEW/P-IV/STR/2019/5908 5908 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-02 Viaduct Km 200+920 Km 00+000 LHS 12-Nov-19 10:10 AM IPC-11 Approved AE
Checking of Shuttering,reinforcement & pouring concrete for 1st lift at U type retaining wall
5973 NMSCEW/P-IV/STR/2019/5909 5909 VUP Km 179+983 13-Nov-19 11:30 AM DONE
A1 & A2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-97,98,99,100 at
5974 NMSCEW/P-IV/STR/2019/5910 5910 Girder Km 200+200 LHS 13-Nov-19 4:30 PM
bed no -01, Girder Type-02
Checking for stressing and remove slagness of H.T. wires at Girder no-89,90,91,92 at bed no
5975 NMSCEW/P-IV/STR/2019/5911 5911 Girder Km 200+200 LHS 13-Nov-19 4:00 PM
-07, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no -89,90,91,92 at bed no -07, Girder Type-1 at casting yard
5976 NMSCEW/P-IV/STR/2019/5912 5912 Girder Km 200+200 LHS 13-Nov-19 4:45 PM
camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-101,102,103,104 at bed
5977 NMSCEW/P-IV/STR/2019/5913 5913 Girder Km 200+200 LHS 13-Nov-19 2:00 PM
no -04, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no -101,102,103,104 at bed no -04, Girder Type-2 at casting
5978 NMSCEW/P-IV/STR/2019/5914 5914 Girder Km 200+200 LHS 13-Nov-19 2:30 PM
yard camp -2
5979 NMSCEW/P-IV/STR/2019/5915 5915 Checking of reinforcement, shuttering & pouring concrete for pier cap at RP-04 Viaduct Km 202+190 RHS 13-Nov-19 11:45 AM
5980 NMSCEW/P-IV/STR/2019/5916 5916 Checking of Shuttering,reinforcement & pouring concrete for Pedestal at LP-06 Viaduct Km 202+190 LHS 13-Nov-19 10:00 AM
5981 NMSCEW/P-IV/STR/2019/5917 5917 Checking of layout,level, Shuttering,reinforcement & pouring concrete for raft at LP-02 Viaduct Km 213+915 LHS 13-Nov-19 10:30 AM
5982 NMSCEW/P-IV/STR/2019/5918 5918 Checking of girder launching and positioning of module no.- 2 at LP-07 to LP-10 Viaduct Km 169+800 LHS 13-Nov-19 9:00 AM DONE
Checking reinforcement ,shuttering and and Pouring concrete for final lift with top haunch at
5983 NMSCEW/P-IV/STR/2019/5919 5919 Box culvert Km 163+570 RHS 13-Nov-19 4:00 PM
wall A1 & A2 and top slab NR
Checking layout, structural excavation,level and laying Concrete for PCC at (2x2) Utility duct
5984 NMSCEW/P-IV/STR/2019/5920 5920 Utility duct Km 186+650 BHS 13-Nov-19 3:30 PM
culvert NR
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 4th lift at retaining wall
5985 NMSCEW/P-IV/STR/2019/5921 5921 PUP Km 171+110 LHS 13-Nov-19 11:00 AM DONE
A1
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 2nd lift at U type
5986 NMSCEW/P-IV/STR/2019/5922 5922 PUP Km 183+290 13-Nov-19 10:30 AM REPEATED
retaining wall
Checking layout, structural excavation,level and laying Concrete(M-15) for PCC at abutment
5987 NMSCEW/P-IV/STR/2019/5923 5923 VOP Km 181+420 BHS 13-Nov-19 11:10 AM DONE
A1
5988 NMSCEW/P-IV/STR/2019/5924 5924 Checking layout, structural excavation,level and pouring Concrete(M-35) for raft at Pier-P3 VOP Km 181+420 RHS 13-Nov-19 9:35 AM DONE
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 3rd lift at retaining wall
5989 NMSCEW/P-IV/STR/2019/5925 5925 PUP Km 183+290 RHS 13-Nov-19 2:20 PM DONE
A2
Checking of reinforcement, shuttering & pouring concrete(M-30) for footing at U type
5990 NMSCEW/P-IV/STR/2019/5926 5926 PUP Km 184+190 13-Nov-19 3:00 PM DONE
retaining wall (Median)
5991 NMSCEW/P-IV/STR/2019/5927 5927 Checking of Shuttering,reinforcement & pouring concrete for 2nd lift at wall A1 VUP Km 166+987 LHS 13-Nov-19 3:20 PM DONE
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 1st lift at wall A1 & A2
5992 NMSCEW/P-IV/STR/2019/5928 5928 MNB( LOOP) Km 01+980 13-Nov-19 4:25 PM
Loop-C NR
5993 NMSCEW/P-IV/STR/2019/5929 5929 Checking layout, structural excavation,level and laying Concrete for PCC at median wall PUP Km 165+790 13-Nov-19 3:50 PM
NR
5994 NMSCEW/P-IV/STR/2019/5930 5930 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP-02 Viaduct Km 200+920 RHS 13-Nov-19 4:16 PM IPC-14
Checking of reinforcement, shuttering & pouring concrete for abutment shaft 1st & final lift at
5995 NMSCEW/P-IV/STR/2019/5931 5931 Viaduct Km 200+920 LHS 13-Nov-19 4:52 PM
LA-02
5996 NMSCEW/P-IV/STR/2019/5932 5932 Checking of Shuttering,reinforcement & pouring concrete for 3rd lift at wing wall W1 & W2 MNB Km 203+409 RHS 14-Nov-19 11:00 AM
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert
5997 NMSCEW/P-IV/STR/2019/5933 5933 Box culvert Km 200+200 LHS 14-Nov-19 10:00 AM
I) 2x2 (4 to 6m) segment no.-33,34,35,36,37,38,39,40
II) 3x3 (2 to 4m) segment no.-79,80,81
5999 NMSCEW/P-IV/STR/2019/5935 5935 Checking of Shuttering,reinforcement & pouring concrete for 3rd lift at wall W2 & W3 MNB Km 199+360 RHS 14-Nov-19 11:15 AM
6000 NMSCEW/P-IV/STR/2019/5936 5936 Checking of Shuttering,reinforcement & pouring concrete for raft at retaining wall W1 PUP Km 193+880 RHS 14-Nov-19 6:00 PM
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 3rd lift at U type
6001 NMSCEW/P-IV/STR/2019/5937 5937 PUP Km 185+235 14-Nov-19 11:30 AM
retaining wall A1 NR
Checking layout, structural excavation,level and pouring Concrete(M-10) for PCC at retaining
6002 NMSCEW/P-IV/STR/2019/5938 5938 PUP Km 185+235 RHS 14-Nov-19 2:30 PM
wall A2 NR
Checking layout, structural excavation,level and laying Concrete for PCC at (2x2) Utility duct
6003 NMSCEW/P-IV/STR/2019/5939 5939 Utility duct Km 185+640 BHS 14-Nov-19 3:00 PM DONE
culvert
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
6004 NMSCEW/P-IV/STR/2019/5940 5940 Box culvert Km 175+500 LHS 14-Nov-19 9:42 AM DONE
Culvert (3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-255,256, 257, 258
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
6005 NMSCEW/P-IV/STR/2019/5941 5941 Box culvert Km 175+500 LHS 14-Nov-19 10:46 AM
Culvert (3×3) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-13, 16
NR
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
6006 NMSCEW/P-IV/STR/2019/5942 5942 Box culvert Km 175+500 LHS 14-Nov-19 12:35 PM DONE
Culvert (2×2) (Cushion 4 to 6m) at precast yard camp-1,Segment no.-81,82,83
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
6007 NMSCEW/P-IV/STR/2019/5943 5943 Culvert (2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-399,400,401,402, Box culvert Km 175+500 LHS 14-Nov-19 4:16 PM DONE
403,404
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 3rd lift at retaining wall
6008 NMSCEW/P-IV/STR/2019/5944 5944 PUP Km 183+290 RHS 14-Nov-19 10:00 AM REPEATED
A2
Checking of reinforcement, shuttering & pouring concrete(M-30) for footing at U type
6009 NMSCEW/P-IV/STR/2019/5945 5945 PUP Km 184+190 14-Nov-19 11:00 AM DONE
retaining wall (Median)
Checking of Shuttering,reinforcement & pouring concrete(M-35) for 1st lift at wall A1 & A2
6010 NMSCEW/P-IV/STR/2019/5946 5946 MNB( LOOP) Km 01+980 14-Nov-19 2:00 PM DONE
Loop-C
Checking of reinforcement, shuttering & pouring concrete(M-30) for final lift at median wall
6011 NMSCEW/P-IV/STR/2019/5947 5947 PUP Km 172+190 BHS 14-Nov-19 2:40 PM
A2 NR
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 1st lift at retaining wall
6012 NMSCEW/P-IV/STR/2019/5948 5948 PUP Km 171+110 LHS 14-Nov-19 3:00 PM DONE
A2
6013 NMSCEW/P-IV/STR/2019/5949 5949 Checking of Shuttering,reinforcement & pouring concrete for 2nd lift at wall A2 VUP Km 166+987 LHS 14-Nov-19 3:30 PM DONE
Checking layout, structural excavation,level and pouring Concrete(M-10) for PCC at retaining
6014 NMSCEW/P-IV/STR/2019/5950 5950 PUP Km 188+575 LHS 14-Nov-19 8:00 AM DONE
wall footing A2
Checking layout, structural excavation,level and pouring Concrete(M-10) for PCC at retaining
6015 NMSCEW/P-IV/STR/2019/5951 5951 PUP Km 188+575 LHS 14-Nov-19 8:30 AM DONE
wall footing A1
Checking layout, structural excavation,level and pouring Concrete(M-10) for PCC at retaining
6016 NMSCEW/P-IV/STR/2019/5952 5952 PUP Km 188+575 RHS 14-Nov-19 8:45 AM DONE
wall footing A1
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 2nd lift at retaining wall
6017 NMSCEW/P-IV/STR/2019/5953 5953 PUP Km 190+650 LHS 14-Nov-19 9:00 AM DONE
A1
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 1st lift at retaining wall
6018 NMSCEW/P-IV/STR/2019/5954 5954 PUP Km 190+650 RHS 14-Nov-19 9:45 AM DONE
A1
6019 NMSCEW/P-IV/STR/2019/5955 5955 Checking of Shuttering,reinforcement & pouring concrete(M-30) for U trough bottom slab PUP Km 188+575 14-Nov-19 4:00 PM DONE
6031 NMSCEW/P-IV/STR/2019/5967 5967 Checking of Shuttering,reinforcement & pouring concrete for cross girder LP-05 to LP-04 Viaduct Km 169+800 LHS 15-Nov-19 3:00 PM DONE
Checking layout, structural excavation,level and laying Concrete for PCC at (2x2) Utility duct
6032 NMSCEW/P-IV/STR/2019/5968 5968 Utility duct Km 186+650 BHS 15-Nov-19 3:30 PM DONE
culvert
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 2nd lift at median wall
6033 NMSCEW/P-IV/STR/2019/5969 5969 PUP Km 174+095 BHS 15-Nov-19 12:00 PM DONE
A1 & A2
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
6034 NMSCEW/P-IV/STR/2019/5970 5970 Box culvert Km 175+500 LHS 15-Nov-19 9:40 AM DONE
Culvert (3×3) (Cushion 2 to 4m) at precast yard camp-1,Segment no.-259,260
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
6035 NMSCEW/P-IV/STR/2019/5971 5971 Box culvert Km 175+500 LHS 15-Nov-19 12:22 PM DONE
Culvert (2×2) (Cushion 4 to 6m) at precast yard camp-1,Segment no.-84,85,86
Checking reinforcement , shuttering & Pouring of Concreting Grade (M-30) for Precast Box
6036 NMSCEW/P-IV/STR/2019/5972 5972 Box culvert Km 175+500 LHS 15-Nov-19 4:10 PM DONE
Culvert (2×2) (Cushion 0 to 2m) at precast yard camp-1,Segment no.-405,406,407,408,409
6045 NMSCEW/P-IV/STR/2019/5981 5981 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-01 Viaduct Km 200+920 LHS 15-Nov-19 3:00 PM
Checking of reinforcement, shuttering & pouring concrete for abutment shaft final lift at LA-
6046 NMSCEW/P-IV/STR/2019/5982 5982 Viaduct Km 200+920 LHS 15-Nov-19 2:00 PM
02
6047 NMSCEW/P-IV/STR/2019/5983 5983 Checking of Shuttering,reinforcement & pouring concrete(M-35) for raft at pier P1 VOP Km 181+420 RHS 15-Nov-19 11:26 AM NR
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-105,106,107 &
6048 NMSCEW/P-IV/STR/2019/5984 5984 Girder Km 200+200 LHS 16-Nov-19 6:30 PM
108 at bed no -02, Girder Type-02
6049 NMSCEW/P-IV/STR/2019/5985 5985 Checking of reinforcement, shuttering & pouring concrete for pier cap at RP-04 Viaduct Km 202+190 Km 00+000 RHS 16-Nov-19 10:00 AM IPC-10 DONE AE
6050 NMSCEW/P-IV/STR/2019/5986 5986 Checking of reinforcement, shuttering & pouring concrete for pier cap at RP-07 Viaduct Km 202+190 RHS 16-Nov-19 11:00 AM
6051 NMSCEW/P-IV/STR/2019/5987 5987 Checking of reinforcement, shuttering & pouring concrete for abutment cap at RA-1 Viaduct Km 202+190 RHS 16-Nov-19 2:00 PM
6052 NMSCEW/P-IV/STR/2019/5988 5988 Checking of reinforcement, shuttering & pouring concrete for pier cap at RP-09 Viaduct Km 195+900 RHS 16-Nov-19 10:30 AM
Checking for stressing and remove slagness of H.T. wires at Girder no-92,94,95 & 96 at bed
6053 NMSCEW/P-IV/STR/2019/5989 5989 Girder Km 200+200 LHS 16-Nov-19 6:00 PM
no -08, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no -93,94,95 & 96 at bed no -08, Girder Type-1 at casting
6054 NMSCEW/P-IV/STR/2019/5990 5990 Girder Km 200+200 LHS 16-Nov-19 6:30 PM
yard camp -2
6055 NMSCEW/P-IV/STR/2019/5991 5991 Checking of bearing & grouting at LP-5 & LP-6 Viaduct Km 169+800 LHS 16-Nov-19 3:00 PM DONE
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert
6056 NMSCEW/P-IV/STR/2019/5992 5992 I) 3x3 (2 to 4m) segment no.-261,262 Box culvert Km 175+500 LHS 16-Nov-19 10:00 AM DONE
II) 2x2 (4 to 6m) segment no.-87,88,89
III)2x2 (0 to 2m) segment no.-410,412,413,414,415
Checking of Shuttering,reinforcement & pouring concrete(M-35) for final lift at wall A1 & A2
6057 NMSCEW/P-IV/STR/2019/5993 5993 MNB( LOOP) Km 01+980 16-Nov-19 8:00 AM
Loop-A NR
6058 NMSCEW/P-IV/STR/2019/5994 5994 Checking of Shuttering,reinforcement & pouring concrete(M-35) in pier (P1) Raft at VOP VOP Km 181+420 RHS 16-Nov-19 10:00 AM DONE
6059 NMSCEW/P-IV/STR/2019/5995 5995 Checking of excavation bed,level & layout of VOP of abutment (A2) VOP Km 181+420 LHS 16-Nov-19 10:10 AM NR
6060 NMSCEW/P-IV/STR/2019/5996 5996 Checking for pouring of concrete(M-35) of VOP of abutment (A2) VOP Km 181+420 LHS 16-Nov-19 10:20 AM NR
6061 NMSCEW/P-IV/STR/2019/5997 5997 Checking of reinforcement, shuttering & concrete pouring at raft (M-30) at median wall PUP Km 172+190 BHS 16-Nov-19 12:00 PM NR
Checking of reinforcement, shuttering & concrete pouring at raft (M-30) in retaining wall
6062 NMSCEW/P-IV/STR/2019/5998 5998 PUP Km 188+575 LHS 16-Nov-19 12:00 PM DONE
footing at A2 side
Checking of reinforcement, shuttering & concrete pouring at raft (M-30) in retaining wall 3rd
6063 NMSCEW/P-IV/STR/2019/5999 5999 PUP Km 190+650 LHS 16-Nov-19 5:00 PM
lift at A1 side NR
6064 NMSCEW/P-IV/STR/2019/6000 6000 Checking of reinforcement, shuttering & concrete pouring of wing wall W2 raft MNBR Km 203+409 LHS 16-Nov-19 2:30 PM
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert
6065 NMSCEW/P-IV/STR/2019/6001 6001 I) 2x2 (4 to 6m) segment no.-46,47,48,49,50,51 Box culvert Km 200+200 LHS 16-Nov-19 10:30 AM
Checking for stressing and remove slagness of H.T. wires at Girder no 109,110,111,112 at bed
6079 NMSCEW/P-IV/STR/2019/6015 6015 Girder Type-2 Km 200+200 LHS 17-Nov-19 12:00 PM
no -5. at casting yard camp -2
Checking for reinforcement of H.T. wires at Girder no 109,110,111,112 Type-02 at bed no -5
6080 NMSCEW/P-IV/STR/2019/6016 6016 Girder Type-2 Km 200+200 LHS 17-Nov-19 12:20 PM
at casting yard camp -2
6081 NMSCEW/P-IV/STR/2019/6017 6017 Checking of Shuttering,reinforcement & pouring concrete for cross girder LP-07 to LP-08 Viaduct Km 169+800 LHS 17-Nov-19 10:00 AM
NR
Checking of reinforcement, shuttering & concrete pouring (M-35) in wall final lift of
6082 NMSCEW/P-IV/STR/2019/6018 6018 MNBR 1+980 Km 00+000 BHS 17-Nov-19 8:00 AM IPC-10 DONE
MNB(Loop A) A1 & A2 & inner side AE
Checking of excavation bed,level,layout& pouring of PCC (M-15) grade of abutment (A2) at
6083 NMSCEW/P-IV/STR/2019/6019 6019 VOP Km 181+420 17-Nov-19 10:00 AM DONE
VOP
Checking of reinforcement, shuttering & concrete pouring (M-30) in retaining wall 2nd lift at
6084 NMSCEW/P-IV/STR/2019/6020 6020 VOP Km 184+190 LHS 17-Nov-19 11:00 AM
LA2 NR
Checking of reinforcement, shuttering & concrete pouring (M-30) in retaining wall footing of
6085 NMSCEW/P-IV/STR/2019/6021 6021 PUP Km 185+235 RHS 17-Nov-19 5:00 PM DONE
PUP at RA2
6086 NMSCEW/P-IV/STR/2019/6022 6022 Checking of reinforcement, shuttering & concrete pouring (M-30) in retaining wall 2nd lift PUP Km 171+110 LHS 17-Nov-19 8:00 AM DONE
Checking of reinforcement, shuttering & concrete pouring (M-30) in retaining wall footing at
6087 NMSCEW/P-IV/STR/2019/6023 6023 PUP Km 188+575 RHS 17-Nov-19 4:00 PM DONE
A1 side
Checking of excavation bed,level,layout& pouring of PCC (M-15) grade in U type wing Wall
6088 NMSCEW/P-IV/STR/2019/6024 6024 B.C. Km 187+677 RHS 17-Nov-19 8:30 AM
bottom slab NR
6089 NMSCEW/P-IV/STR/2019/6025 6025 Checking of excavation,level, layout & pourinng of concrete of utility duct(2x2) Utility duct Km 209+940 Km 00+000 BHS 17-Nov-19 10:00 AM IPC-11 Approved
6090 NMSCEW/P-IV/STR/2019/6026 6026 Checking of reinforcement, shuttering & pouring of concrete for LP1 pier shaft 1st lift Viaduct Km 200+920 RHS 17-Nov-19 11:30 AM
6091 NMSCEW/P-IV/STR/2019/6027 6027 Checking of reinforcement, shuttering & pouring of concrete for RP11 pier shaft final lift Viaduct Km 202+190 RHS 17-Nov-19 12:00 PM
6092 NMSCEW/P-IV/STR/2019/6028 6028 Checking of reinforcement, shuttering & pouring of concrete for RP7 pier cap Viaduct Km 202+190 RHS 17-Nov-19 11:30 AM
6093 NMSCEW/P-IV/STR/2019/6029 6029 Checking of reinforcement, shuttering & pouring of concrete for LP7 pedestal Viaduct Km 202+190 RHS 17-Nov-19 12:30 PM
6094 NMSCEW/P-IV/STR/2019/6030 6030 Checking of reinforcement, shuttering & pouring of concrete for RA 1 abutment cap Viaduct Km 202+190 RHS 17-Nov-19 4:00 PM
6095 NMSCEW/P-IV/STR/2019/6031 6031 Checking erection & jointing of UTILITY DUCT Utility Duct Km 168+020 Km 00+000 BHS 17-Nov-19 10:00 AM IPC-10 DONE
6096 NMSCEW/P-IV/STR/2019/6032 6032 Checking of reinforcement, shuttering & pouring of concrete for raft(5x3) B.C. Km 193+940 RHS 17-Nov-19 3:00 PM
Checking of reinforcement, shuttering & concrete pouring of abutment and return wall 1st lift
6097 NMSCEW/P-IV/STR/2019/6034 6034 CUP Km 205+610 RHS 18-Nov-19 9:30 AM
of RA 1
6098 NMSCEW/P-IV/STR/2019/6035 6035 Checking of reinforcement, shuttering & concrete pouring of Raft at box culvert Box Culvert Km 193+940 RHS 18-Nov-19 10:40 AM
6099 NMSCEW/P-IV/STR/2019/6036 6036 Checking layout and level for PCC at RP-07 Viaduct Km 213+915 RHS 18-Nov-19 12:30 PM
6100 NMSCEW/P-IV/STR/2019/6037 6037 Checking pouring of concrete for PCC at RP-07 Viaduct Km 213+915 RHS 18-Nov-19 2:20 PM
6101 NMSCEW/P-IV/STR/2019/6038 6038 Checking layout and level for PCC at RP-07 Viaduct Km 213+915 LHS 18-Nov-19 2:40 PM
6102 NMSCEW/P-IV/STR/2019/6039 6039 Checking pouring of concrete for PCC at RP-07 Viaduct Km 213+915 LHS 18-Nov-19 3:20 PM
6103 NMSCEW/P-IV/STR/2019/6040 6040 Checking of reinforcement, shuttering & top level of raft LP-02 Viaduct Km 213+915 Km 00+000 LHS 18-Nov-19 8:00 AM IPC-11 Approved AE
6104 NMSCEW/P-IV/STR/2019/6041 6041 Checking concrete pouring of raft LP-02 Viaduct Km 213+915 Km 00+000 LHS 18-Nov-19 10:00 AM IPC-11 Approved AE
6105 NMSCEW/P-IV/STR/2019/6042 6042 Checking of excavation,level, layout & pourinng of concrete of utility duct(2x2) B.C. Km 185+030 BHS 18-Nov-19 10:30 AM DONE
6106 NMSCEW/P-IV/STR/2019/6043 6043 Checking top level and laying of PCC B.C. Km 185+030 BHS 18-Nov-19 12:40 PM DONE
6107 NMSCEW/P-IV/STR/2019/6044 6044 Checking of bearing & grouting at LP-4 & LP-7 Viaduct Km 169+800 LHS 18-Nov-19 2:20 PM DONE
Checking of reinforcement, shuttering & concrete pouring (M-30) in retaining wall footing at
6108 NMSCEW/P-IV/STR/2019/6045 6045 PUP Km 188+575 RHS 18-Nov-19 2:40 PM
A1 side NR
Checking of reinforcement, shuttering & concrete pouring (M-30) at U through wall 1st lift
6109 NMSCEW/P-IV/STR/2019/6046 6046 PUP Km 188+575 RHS 18-Nov-19 8:30 AM DONE
A1 & A2
Checking of reinforcement, shuttering & concrete pouring (M-30) at U through bottom slab
6110 NMSCEW/P-IV/STR/2019/6047 6047 PUP Km 189+000 RHS 18-Nov-19 10:00 AM DONE
A1 & A2
6111 NMSCEW/P-IV/STR/2019/6048 6048 Checking of reinforcement, shuttering & concrete pouring (M-30) in retaining wall 3RD lift PUP Km 190+650 RHS 18-Nov-19 11:30 AM
NR
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert
6112 NMSCEW/P-IV/STR/2019/6049 6049 I) 3x3 (2 to 4m) segment no.-263,264 Box culvert Km 175+500 LHS 18-Nov-19 2:40 PM DONE
II) 2x2 (4 to 6m) segment no.-90,91,92
III)2x2 (0 to 2m) segment no.-411,416,417,418
6113 NMSCEW/P-IV/STR/2019/6050 6050 Checking of steel , shuttering & concrete pouring (M-30) in median wall final lift A2 PUP Km 172+190 BHS 18-Nov-19 10:00 AM DONE
6114 NMSCEW/P-IV/STR/2019/6051 6051 Checking of steel , shuttering & concrete pouring (M-30) in median wall final lift A1& A2 PUP Km 174+095 BHS 18-Nov-19 10:20 AM
NR
Checking for stressing and remove slagness of H.T. wires at Girder no 97,98,99&100 (Type-
6115 NMSCEW/P-IV/STR/2019/6052 6052 Girder Type-1 Km 200+200 LHS 18-Nov-19 6:00 PM
01) at bed no -5 at casting yard camp -2
Checking for reinforcement at Girder no 97,98,99&100 (Type-01) at bed no -5 at casting yard
6116 NMSCEW/P-IV/STR/2019/6053 6053 Girder Type-1 Km 200+200 LHS 18-Nov-19 6:30 PM
camp -2
Checking of side shuttering & Concrete pouring(M-50) of Girder no 109,110,111&112 (Type-
6117 NMSCEW/P-IV/STR/2019/6054 6054 Girder Type-2 Km 200+200 LHS 18-Nov-19 6:30 PM
02) at bed no -3 at casting yard camp -2
Checking of side shuttering & Concrete pouring(M-50) of Girder no 93,94,95 & 96 (Type-01)
6118 NMSCEW/P-IV/STR/2019/6055 6055 Girder Type-1 Km 200+200 LHS 18-Nov-19 7:00 PM
at bed no -8 at casting yard camp -2
Checking of reinforcement, shuttering & concrete pouring (M-30) in pier shaft 1 st lift for
6119 NMSCEW/P-IV/STR/2019/6056 6056 Viaduct Km 200+920 RHS 18-Nov-19 11:00 AM
RP1
Checking of reinforcement, shuttering & concrete pouring (M-30) in pier shaft 1 st lift for
6120 NMSCEW/P-IV/STR/2019/6057 6057 Viaduct Km 202+190 RHS 18-Nov-19 12:30 PM
RP12
6121 NMSCEW/P-IV/STR/2019/6058 6058 Checking of reinforcement, shuttering & concrete pouring (M-30) in abutment cap for RA1 Viaduct Km 202+190 RHS 18-Nov-19 4:00 PM
6122 NMSCEW/P-IV/STR/2019/6059 6059 Checking of reinforcement, shuttering & concrete pouring of wing wall W2 1st lift MNBR Km 203+409 LHS 19-Nov-19 10:00 AM
6123 NMSCEW/P-IV/STR/2019/6060 6060 Checking of reinforcement, shuttering & concrete pouring of wing wall W1 4th lift MNBR Km 203+409 LHS 19-Nov-19 1:00 PM
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert
6124 NMSCEW/P-IV/STR/2019/6061 6061 I) 3x3(2 to 4m) segment no.-265,266 Box culvert Km 175+500 LHS 19-Nov-19 10:00 AM DONE
II) 2x2 (4 to 6m) segment no.-75,76,77
III) 2x2 (0 to 2m) segment no.-419,420,421,422
6125 NMSCEW/P-IV/STR/2019/6062 6062 Checking of reinforcement, shuttering & concrete pouring(M-30) in retaning wall 1st lift at A2 PUP Km 188+575 LHS 19-Nov-19 10:00 AM DONE
6126 NMSCEW/P-IV/STR/2019/6063 6063 Checking of reinforcement, shuttering & concrete pouring(M-30) in retaning wall 1st lift at A1 PUP Km 188+575 LHS 19-Nov-19 11:00 AM DONE
Checking of reinforcement, shuttering & concrete pouring(M-30) in wall 2nd lift U-trough (A1
6127 NMSCEW/P-IV/STR/2019/6064 6064 PUP Km 188+575 LHS 19-Nov-19 11:30 AM DONE
& A2) side
6128 NMSCEW/P-IV/STR/2019/6065 6065 Checking of reinforcement, shuttering & concrete pouring(M-30) in wall 1st lift A2 VUP Km 187+113 LHS 19-Nov-19 4:00 PM DONE
Checking of reinforcement, shuttering & concrete pouring of cross girder at LP7 to LP8 & LP9
6129 NMSCEW/P-IV/STR/2019/6066 6066 Viaduct Km 169+800 LHS 19-Nov-19 3:00 PM DONE
to LP10
6130 NMSCEW/P-IV/STR/2019/6067 6067 Checking of reinforcement, shuttering & concrete pouring(M-35) in wall 1st lift atA1 & A2 MNB Km 181+700 Km 00+000 LHS 19-Nov-19 8:00 AM IPC-11 DONE
Checking of reinforcement, shuttering & concrete pouring(M-30) in retaining wall 2nd lift at
6131 NMSCEW/P-IV/STR/2019/6068 6068 PUP Km 184+190 LHS 19-Nov-19 11:00 AM DONE
A2
Checking of reinforcement, shuttering & concrete pouring(M-30) in retaining wall 1st lift at
6132 NMSCEW/P-IV/STR/2019/6069 6069 PUP Km 185+235 LHS 19-Nov-19 5:00 PM DONE
A1 & A2
Checking of reinforcement, shuttering & concrete pouring(M-30) in retaining wall 2ND lift at
6133 NMSCEW/P-IV/STR/2019/6070 6070 PUP Km 184+190 LHS 19-Nov-19 11:00 AM
A2
6134 NMSCEW/P-IV/STR/2019/6071 6071 Checking of reinforcement, shuttering & concrete pouring(M-30) in retaining wall 1st lift A1 PUP Km 185+235 RHS 19-Nov-19 5:00 PM DONE
6135 NMSCEW/P-IV/STR/2019/6072 6072 Checking of reinforcement, shuttering & concrete pouring(M-30) in retaining wall 1st lift A2 PUP Km 185+235 RHS 19-Nov-19 5:00 PM DONE
Checking for stressing and remove slagness of H.T. wires at Girder no 113,114,115 &116
6136 NMSCEW/P-IV/STR/2019/6073 6073 Girder Type-1 Km 200+200 LHS 19-Nov-19 4:00 PM
(Type-02) at bed no -1 at casting yard camp -2
Checking for reinforcement at Girder no 113,114,115 &116 (Type-02) at bed no -1 at casting
6137 NMSCEW/P-IV/STR/2019/6074 6074 Girder Type-1 Km 200+200 LHS 19-Nov-19 4:30 PM
yard camp -2
Checking for side shuttering & concrete (M-50) pouring of Girder no 97,98,99 & 100 (Type-
6138 NMSCEW/P-IV/STR/2019/6075 6075 Girder Type-1 Km 200+200 LHS 19-Nov-19 7:00 PM
01) at bed no -5 at casting yard camp -2
6139 NMSCEW/P-IV/STR/2019/6076 6076 Checking of reinforcement, shuttering & concrete pouring(M-30) at RP 3 pier cap Viaduct Km 196+560 RHS 19-Nov-19 2:30 PM
6140 NMSCEW/P-IV/STR/2019/6077 6077 Checking founding level, layout and laying Concrete for PCC at abutment of RA-01 Viaduct Km 196+560 RHS 19-Nov-19 12:10 PM
6141 NMSCEW/P-IV/STR/2019/6078 6078 Checking founding level, layout and laying Concrete for PCC for LP-12 Viaduct Km 213+915 LHS 19-Nov-19 9:00 AM
6142 NMSCEW/P-IV/STR/2019/6079 6079 Checking founding level, layout and laying Concrete for PCC for LP-13 Viaduct Km 213+915 LHS 19-Nov-19 10:30 AM
6143 NMSCEW/P-IV/STR/2019/6080 6080 Checking of reinforcement, shuttering & concrete pouring(M-30) at RP 12 pier shaft final lift Viaduct Km 202+190 RHS 19-Nov-19 12:00 PM
6144 NMSCEW/P-IV/STR/2019/6081 6081 Checking of reinforcement, shuttering & concrete pouring(M-30) at RP 07 pier cap Viaduct Km 202+190 Km 00+000 RHS 19-Nov-19 11:30 AM IPC-10 DONE
6145 NMSCEW/P-IV/STR/2019/6082 6082 Checking of reinforcement, shuttering & concrete pouring(M-30) at LP 07 pedestal Viaduct Km 202+190 LHS 19-Nov-19 12:30 PM
6146 NMSCEW/P-IV/STR/2019/6083 6083 Checking of reinforcement, shuttering & concrete pouring(M-30) at LP 01 pier shaft first lift Viaduct Km 200+920 LHS 19-Nov-19 10:00 AM
6147 NMSCEW/P-IV/STR/2019/6084 6084 Checking of reinforcement, shuttering & concrete pouring(M-30) at RP 01 pier shaft first lift Viaduct Km 200+920 RHS 19-Nov-19 11:30 AM
6148 NMSCEW/P-IV/STR/2019/6085 6085 Checking of Shuttering,reinforcement & pouring concrete of wing wall W2 2nd lift MNB Km 203+409 LHS 20-Nov-19 9:00 AM
6149 NMSCEW/P-IV/STR/2019/6086 6086 Checking layout ,Level & Laying concrete for PCC at Wing wall W1 MNB Km 203+409 LHS 20-Nov-19 10:00 AM
Checking of Shuttering,reinforcement & pouring concrete of wing wall W2 5th lift at W1 &
6150 NMSCEW/P-IV/STR/2019/6087 6087 MNB Km 203+409 RHS 20-Nov-19 11:00 AM
W2
6151 NMSCEW/P-IV/STR/2019/6088 6088 Checking of Shuttering,reinforcement & pouring concrete of W1 WALL 2nd lift PUP Km 206+985 Km 00+000 LHS 20-Nov-19 11:20 AM IPC-11 Approved AE
Checking for stressing and remove slagness of H.T. wires at Girder no-101,102,103&104 at
6152 NMSCEW/P-IV/STR/2019/6089 6089 Girder Km 200+200 LHS 20-Nov-19 6:00 PM
bed no -06, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no -101,102,103&104 at bed no -06, Girder Type-1 at
6153 NMSCEW/P-IV/STR/2019/6090 6090 Girder Km 200+200 LHS 20-Nov-19 6:30 PM
casting yard camp -2
6154 NMSCEW/P-IV/STR/2019/6091 6091 Checking of Shuttering,reinforcement & pouring concrete of pier cap at RP-09 Viaduct Km 195+900 Km 00+000 RHS 20-Nov-19 9:30 AM IPC-11 Approved
6155 NMSCEW/P-IV/STR/2019/6092 6092 Checking layout ,Level & Laying concrete for PCC for RP-07 Viaduct Km 213+915 RHS 20-Nov-19 3:30 PM
6156 NMSCEW/P-IV/STR/2019/6093 6093 Checking layout ,Level for structural excavation of pipe culvert median drain outlets Pipe Culvert Km 188+040 LHS 20-Nov-19 2:00 PM NR
6157 NMSCEW/P-IV/STR/2019/6094 6094 Checking of top level of PCC of pipe culvert median drain outlets Pipe Culvert Km 188+040 LHS 20-Nov-19 4:00 PM DONE
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert
6158 NMSCEW/P-IV/STR/2019/6095 6095 I) 2x2(4 to 6m) segment no.-56,92,93 Box culvert Km 175+500 LHS 20-Nov-19 10:00 AM DONE
II) 2x2 (0 to 2m) segment no.-393,394,418,423
6159 NMSCEW/P-IV/STR/2019/6096 6096 Checking of steel, Shuttering,& pouring concrete of retaning wall 3rd lift at A2 PUP Km 171+110 LHS 20-Nov-19 12:00 PM DONE
6160 NMSCEW/P-IV/STR/2019/6097 6097 Checking of Shuttering,reinforcement & pouring concrete (M-30) wall 1st lift U trough PUP Km 189+000 BHS 20-Nov-19 3:00 PM NR
6161 NMSCEW/P-IV/STR/2019/6098 6098 Checking layout ,Level, excavation & pouring M-15 grade concrete in bottom slab PUP Km 189+705 BHS 20-Nov-19 10:00 AM DONE
Checking of Shuttering,reinforcement & pouring concrete (M-35) in wall 2nd lift of Box
6162 NMSCEW/P-IV/STR/2019/6099 6099 Box culvert Km 180+922 Km 00+000 RHS 20-Nov-19 8:00 AM IPC-10 DONE
Culvert AE
6163 NMSCEW/P-IV/STR/2019/6100 6100 Checking of Shuttering,reinforcement & pouring concrete (M-35) in abutment(A1) raft VOP Km 181+420 LHS 20-Nov-19 4:00 PM NR
Checking layout ,Level, excavation bed & pouring M-10 grade concrete in U-Type retaning
6164 NMSCEW/P-IV/STR/2019/6101 6101 PUP Km 186+000 LHS 20-Nov-19 4:30 PM DONE
wall PCC
Checking layout ,Level, excavation bed & pouring M-10 grade concrete in retaning wall PCC
6165 NMSCEW/P-IV/STR/2019/6102 6102 PUP Km 186+000 LHS 20-Nov-19 5:00 PM DONE
A2
6166 NMSCEW/P-IV/STR/2019/6103 6103 Checking of Shuttering,reinforcement & pouring concrete (M-35) in abutment Cap at RA-2 Viaduct Km 195+900 Km 00+000 RHS 20-Nov-19 3:20 PM IPC-11 Approved AE
6167 NMSCEW/P-IV/STR/2019/6104 6104 Checking of Shuttering,reinforcement & pouring concrete (M-35) for RP11 pier shaft final lift Viaduct Km 202+190 Km 00+000 RHS 20-Nov-19 2:00 PM IPC-11 Approved AE
6168 NMSCEW/P-IV/STR/2019/6105 6105 Checking of Shuttering,reinforcement & pouring concrete (M-35) for RP8 pier cap Viaduct Km 202+190 RHS 20-Nov-19 3:30 PM
6169 NMSCEW/P-IV/STR/2019/6106 6106 Checking of Shuttering,reinforcement & pouring concrete (M-35) for LP8 pedestal Viaduct Km 202+190 LHS 20-Nov-19 4:00 PM
6170 NMSCEW/P-IV/STR/2019/6107 6107 Checking of Shuttering,reinforcement & pouring concrete (M-35) for RA1 pier cap Viaduct Km 202+190 Km 00+000 RHS 20-Nov-19 3:30 PM IPC-10 DONE
Checking of Shuttering,reinforcement & pouring concrete (M-35) for abutment shaft LA1 (2nd
6171 NMSCEW/P-IV/STR/2019/6108 6108 MJB Km 205+610 RHS 21-Nov-19 10:00 AM
lift)
6172 NMSCEW/P-IV/STR/2019/6109 6109 Checking of Shuttering,reinforcement & pouring concrete (M-35) for raft at Box Culver (5x3) B.C. Km 206+843 LHS 21-Nov-19 5:00 PM
6173 NMSCEW/P-IV/STR/2019/6110 6110 Checking layout ,Level, & pouring concrete in median wall A2 side MJB Km 205+610 BHS 21-Nov-19 4:00 PM
6174 NMSCEW/P-IV/STR/2019/6111 6111 Checking of Shuttering,reinforcement & pouring concrete (M-35) for 3rd lift wall A1 & A2 VUP Km 166+987 LHS 21-Nov-19 12:30 PM DONE
Checking of Shuttering,reinforcement & pouring concrete (M-35) of median raft with bottom
6175 NMSCEW/P-IV/STR/2019/6112 6112 PUP Km 165+790 BHS 21-Nov-19 3:00 PM DONE
haunch A1 & A2 side
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-1
6176 NMSCEW/P-IV/STR/2019/6113 6113 Box culvert Km 175+500 LHS 21-Nov-19 3:10 PM DONE
I) 3x3(2 to 4m) segment no.-265,266,267,268
II) 2x2 (4 to 6m) segment no.-94,95,96
II) 2x2 (0 to 2m) segment no.-424,425,426,427
6177 NMSCEW/P-IV/STR/2019/6114 6114 Checking of Shuttering,reinforcement & pouring concrete for raft at Box Culvert B.C. Km 177+760 Km 00+000 LHS 21-Nov-19 10:30 AM IPC-10 DONE
Checking of Shuttering,reinforcement & pouring concrete for Utype retaning wall A1 & A2
6178 NMSCEW/P-IV/STR/2019/6115 6115 VUP Km 179+983 LHS 21-Nov-19 2:30 PM DONE
4th lift
6179 NMSCEW/P-IV/STR/2019/6116 6116 Checking of steel,Shuttering & pouring concrete (M-30) for median wall final lift A1 & A2 PUP Km 174+095 BHS 21-Nov-19 12:30 PM DONE
Checking of Shuttering,reinforcement & pouring concrete in wall 3rd lift (A1 & A2) at U-
6180 NMSCEW/P-IV/STR/2019/6117 6117 PUP Km 188+575 BHS 21-Nov-19 12:30 PM DONE
trough
6181 NMSCEW/P-IV/STR/2019/6118 6118 Checking of Shuttering,reinforcement & pouring concrete in retaning wall footing at A1 PUP Km 188+575 RHS 21-Nov-19 4:30 PM DONE
6182 NMSCEW/P-IV/STR/2019/6119 6119 Checking of Shuttering,reinforcement & pouring concrete of cross girder LP8 to LP9 Viaduct Km 169+800 LHS 21-Nov-19 3:00 PM DONE
Checking of Shuttering,reinforcement & pouring concrete (M-30) wall 1st lift of u-type
6183 NMSCEW/P-IV/STR/2019/6120 6120 PUP Km 184+190 LHS 21-Nov-19 8:00 AM DONE
retaning wall
6184 NMSCEW/P-IV/STR/2019/6121 6121 Checking of Shuttering,reinforcement & pouring concrete (M-30) in abutment (A1) raft VOP Km 181+420 LHS 21-Nov-19 4:00 PM DONE
6185 NMSCEW/P-IV/STR/2019/6122 6122 Checking excavation bed ,layout ,Level, & pouring concrete PCC in PIER (P1) VOP Km 181+420 LHS 21-Nov-19 11:00 AM DONE
6186 NMSCEW/P-IV/STR/2019/6123 6123 Checking excavation bed ,layout ,Level, & pouring concrete PCC in retaning wall A1 PUP Km 186+000 LHS 21-Nov-19 5:00 PM DONE
Checking for stressing and remove slagness of H.T. wires at Girder no-105,106,107 & 108 at
6187 NMSCEW/P-IV/STR/2019/6124 6124 Girder Km 200+200 LHS 21-Nov-19 2:00 PM
bed no -07, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no -105,106,107 &108 at bed no -07, Girder Type-1 at
6188 NMSCEW/P-IV/STR/2019/6125 6125 Girder Km 200+200 LHS 21-Nov-19 2:30 PM
casting yard camp -2
Checking of side shuttering of girder no -113,114,115 & 116 at bed no -01, Girder Type-2 at
6189 NMSCEW/P-IV/STR/2019/6126 6126 Girder Km 200+200 LHS 21-Nov-19 8:00 AM
casting yard camp -2
Checking of approval of pouring of concrete(M-50) of girder no -113,114,115 & 116 at bed no
6190 NMSCEW/P-IV/STR/2019/6127 6127 Girder Km 200+200 LHS 21-Nov-19 8:30 AM
-01, Girder Type-2 at casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-117,118,119,120 at bed
6191 NMSCEW/P-IV/STR/2019/6128 6128 Girder Km 200+200 LHS 21-Nov-19 6:00 PM
no -04, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no -117,118,119,120 at bed no -04, Girder Type-2 at casting
6192 NMSCEW/P-IV/STR/2019/6129 6129 Girder Km 200+200 LHS 21-Nov-19 6:30 PM
yard camp -2
6193 NMSCEW/P-IV/STR/2019/6130 6130 Checking layout ,Level, & pouring concrete PCC for LP-12 Viaduct Km 213+915 LHS 21-Nov-19 9:00 AM
6194 NMSCEW/P-IV/STR/2019/6131 6131 Checking layout ,Level, & pouring concrete PCC for LP-13 Viaduct Km 213+915 Km 00+000 LHS 21-Nov-19 10:30 AM IPC-11 Approved
6195 NMSCEW/P-IV/STR/2019/6132 6132 Checking of Shuttering,reinforcement & pouring concrete of pier cap at RP3 Viaduct Km 196+560 Km 00+000 RHS 21-Nov-19 10:00 AM IPC-10 DONE
AE
6196 NMSCEW/P-IV/STR/2019/6133 6133 Checking of founding level, layout & laying PCC of RA1 abutment Viaduct Km 196+560 Km 00+000 RHS 21-Nov-19 10:20 AM IPC-11 Approved AE
6197 NMSCEW/P-IV/STR/2019/6134 6134 Checking of Shuttering,reinforcement & pouring concrete of pier shaft 1st lift for RP1 Viaduct Km 200+920 RHS 21-Nov-19 10:00 AM IPC-14
6198 NMSCEW/P-IV/STR/2019/6135 6135 Checking of Shuttering,reinforcement & pouring concrete of pier shaft 1st lift for RP12 Viaduct Km 202+190 Km 00+000 RHS 21-Nov-19 2:00 PM IPC-11 Approved
6199 NMSCEW/P-IV/STR/2019/6136 6136 Checking layout ,Level, & pouring concrete PCC for RA-2 Viaduct Km 202+190 RHS 21-Nov-19 3:00 PM
6200 NMSCEW/P-IV/STR/2019/6137 6137 Checking of Shuttering,reinforcement & pouring concrete of R/W raft sie PUP Km 193+880 RHS 21-Nov-19 5:30 PM
6201 NMSCEW/P-IV/STR/2019/6138 6138 Checking of bearing & grouting at LP8 & LP9 Viaduct Km 169+800 LHS 21-Nov-19 3:00 PM DONE
6202 NMSCEW/P-IV/STR/2019/6139 6139 Checking of Shuttering,reinforcement & pouring concrete(M-35) in top slab of MNB(Loop A) MNB 1+980 Km 00+000 BHS 21-Nov-19 4:00 PM IPC-10 DONE
6203 NMSCEW/P-IV/STR/2019/6140 6140 Checking for completion of segment erection at utility duct (2x2) Utility duct Km 190+200 Km 00+000 BHS 22-Nov-19 2:30 PM IPC-10 DONE
6204 NMSCEW/P-IV/STR/2019/6141 6141 Checking of reinforcement, shuttering & pouring concrete for W1, W2 & W3 4th lift MNBR Km 203+409 Km 00+000 LHS 22-Nov-19 9:30 AM IPC-10 DONE
6205 NMSCEW/P-IV/STR/2019/6142 6142 Checking of reinforcement, shuttering & pouring concrete of wing wall raft W1 MNBR Km 203+409 LHS 22-Nov-19 11:00 AM
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-1 ,2x2(4 to 6m) segment no.-52,53,54,55,56,57,58,59,60
6206 NMSCEW/P-IV/STR/2019/6143 6143 Box culvert Km 175+500 LHS 22-Nov-19 11:20 AM
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-1 ,3x3(2 to 4m) segment no.-87,88,89,90
6207 NMSCEW/P-IV/STR/2019/6144 6144 Box culvert Km 175+500 LHS 22-Nov-19 11:30 AM
6212 NMSCEW/P-IV/STR/2019/6149 6149 Checking layout ,Level, & pouring concrete PCC for RP-7 Viaduct Km 213+915 RHS 22-Nov-19 3:30 PM
6213 NMSCEW/P-IV/STR/2019/6150 6150 Checking of reinforcement, shuttering & pouring concrete of RP-8 pier cap Viaduct Km 202+190 Km 00+000 RHS 22-Nov-19 3:30 PM IPC-11 Approved
6214 NMSCEW/P-IV/STR/2019/6151 6151 Checking of reinforcement, shuttering & pouring concrete of LP-8 pedestal Viaduct Km 202+190 LHS 22-Nov-19 4:00 PM
6215 NMSCEW/P-IV/STR/2019/6152 6152 Checking of reinforcement, shuttering & pouring concrete of RA-2 abutment shaft 1st lift Viaduct Km 200+920 RHS 22-Nov-19 4:00 PM
6216 NMSCEW/P-IV/STR/2019/6153 6153 Checking pouring concrete PCC for box culvert Box culvert Km 179+715 Km 00+000 BHS 22-Nov-19 10:30 AM IPC-10 DONE AE
Checking layout ,Level,structural excavation & pouring concrete of pipe culvert median drain
6217 NMSCEW/P-IV/STR/2019/6154 6154 Median drain Km 187+810 BHS 22-Nov-19 4:30 PM DONE
outlets
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
6218 NMSCEW/P-IV/STR/2019/6155 6155 Box culvert Km 175+500 LHS 22-Nov-19 10:20 AM DONE
Culvert at precast yard Camp-1 ,2x2(4 to 6m) segment no.-97,98,99
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
6219 NMSCEW/P-IV/STR/2019/6156 6156 Box culvert Km 175+500 LHS 22-Nov-19 10:30 AM DONE
Culvert at precast yard Camp-1 ,2x2(0 to 2m) segment no.-428,429,430
6220 NMSCEW/P-IV/STR/2019/6157 6157 Checking layout ,Level & structural excavation for utility duct Utility duct Km 174+920 BHS 22-Nov-19 10:00 AM DONE
Checking of reinforcement, shuttering & pouring concrete (M-30) in retaning wall 3rd lift at
6221 NMSCEW/P-IV/STR/2019/6158 6158 PUP Km 188+575 LHS 22-Nov-19 10:00 AM DONE
A1 side
Checking of reinforcement, shuttering & pouring concrete (M-30) in retaning wall 2nd lift at
6222 NMSCEW/P-IV/STR/2019/6159 6159 PUP Km 188+575 LHS 22-Nov-19 10:30 AM
A2 side
6223 NMSCEW/P-IV/STR/2019/6160 6160 Checking of reinforcement, shuttering & pouring concrete (M-30) in wall 2nd lift at A1 side PUP Km 189+000 LHS 22-Nov-19 3:00 PM DONE
Checking of reinforcement, shuttering & pouring concrete (M-30) in retaning wall footing at
6224 NMSCEW/P-IV/STR/2019/6161 6161 Viaduct Km 169+800 LHS 22-Nov-19 3:00 PM
A1 side NR
6225 NMSCEW/P-IV/STR/2019/6162 6162 Checking of bearing & grouting at LP9 & LP10 22-Nov-19 4:00 PM
6226 NMSCEW/P-IV/STR/2019/6163 6163 Checking layout ,Level,structural excavation & pouring concrete PCC of Bottom slab Box culvert Km 189+705 BHS 22-Nov-19 9:30 AM
6227 NMSCEW/P-IV/STR/2019/6164 6164 Checking of reinforcement, shuttering & pouring concrete (M-30) in raft PUP Km 206+985 Km 00+000 RHS 23-Nov-19 8:00 AM IPC-11 Approved
6228 NMSCEW/P-IV/STR/2019/6165 6165 Checking of reinforcement, shuttering & pouring concrete (M-30) in raft Utility Duct Km 209+280 BHS 23-Nov-19 9:30 AM
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
6229 NMSCEW/P-IV/STR/2019/6166 6166 Box culvert Km 200+200 LHS 23-Nov-19 10:00 AM
Culvert at precast yard Camp-2 ,2x2(4 to 6m) segment no.-52,53,54,55,56,57,58
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
6230 NMSCEW/P-IV/STR/2019/6167 6167 Box culvert Km 200+200 LHS 23-Nov-19 10:10 AM
Culvert at precast yard Camp-2 ,3x3 (2 to 4m) segment no.-87,88,89,90
6231 NMSCEW/P-IV/STR/2019/6168 6168 Checking top Level & pouring concrete PCC for utility duct (2x2) Box culvert Km 174+920 BHS 23-Nov-19 10:00 AM NR
6232 NMSCEW/P-IV/STR/2019/6169 6169 Checking layout ,Level,structural excavation & pouring concrete PCC (M-15) at RA1 of MNB MNBR Km 174+173 RHS 23-Nov-19 10:20 AM
NR
6233 NMSCEW/P-IV/STR/2019/6170 6170 Checking of steel,Shuttering & pouring concrete (M-30) for retaning wall final lift A2 PUP Km 171+110 LHS 23-Nov-19 11:00 AM DONE
Checking of reinforcement ,Shuttering & pouring concrete (M-30) for retaning wall 5th lift A1
6234 NMSCEW/P-IV/STR/2019/6171 6171 PUP Km 179+983 LHS 23-Nov-19 12:30 PM DONE
& A2
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
6235 NMSCEW/P-IV/STR/2019/6172 6172 Box culvert Km 175+500 LHS 23-Nov-19 10:10 AM DONE
Culvert at precast yard Camp-2 ,2x2 (4 to 6m) segment no.-96,100,101
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
6236 NMSCEW/P-IV/STR/2019/6173 6173 Box culvert Km 175+500 LHS 23-Nov-19 10:20 AM DONE
Culvert at precast yard Camp-2 ,2x2 (0 to 2m) segment no.-432,433,434
6237 NMSCEW/P-IV/STR/2019/6174 6174 Checking for laying of hume pipe (2500x1000) pipe culverts median drain outlets Box culvert Km 188+040 LHS 23-Nov-19 4:00 PM DONE
6238 NMSCEW/P-IV/STR/2019/6175 6175 Checking for laying of hume pipe (2500x1000) pipe culverts median drain outlets Box culvert Km 187+810 LHS 23-Nov-19 11:00 AM DONE
Checking of side shuttering & pouring concrete (M-50) of girder no -117,118,119 & 120 at
6239 NMSCEW/P-IV/STR/2019/6176 6176 Girder Km 200+200 LHS 23-Nov-19 10:00 AM
bed no -4, Girder Type-2 at casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no 121,122,123 &124 at
6240 NMSCEW/P-IV/STR/2019/6177 6177 Girder Type-2 Km 200+200 LHS 23-Nov-19 11:00 AM
bed no -2 at casting yard camp -2,Girder Type-2
Checking for reinforcement at Girder no 121,122,123 &124 at bed no -2 at casting yard camp
6241 NMSCEW/P-IV/STR/2019/6178 6178 Girder Type-2 Km 200+200 LHS 23-Nov-19 11:30 AM
-2,Girder Type-2
6242 NMSCEW/P-IV/STR/2019/6179 6179 Checking of reinforcement ,Shuttering & pouring concrete (M-30) for RP2 pier cap Viaduct Km 196+560 Km 00+000 RHS 23-Nov-19 3:45 PM IPC-10 DONE AE
6243 NMSCEW/P-IV/STR/2019/6180 6180 Checking founding Level,layout & pouring concrete PCC for LA1 abutment Viaduct Km 196+560 LHS 23-Nov-19 11:00 AM
Checking of reinforcement ,Shuttering & pouring concrete (M-30) in bottom slab of U type
6244 NMSCEW/P-IV/STR/2019/6181 6181 PUP Km 186+000 BHS 23-Nov-19 8:00 AM DONE
retaning wall
6245 NMSCEW/P-IV/STR/2019/6182 6182 Checking of reinforcement ,Shuttering & pouring concrete (M-30) in abutment (A1) raft VOP Km 181+420 RHS 23-Nov-19 4:00 PM DONE
6246 NMSCEW/P-IV/STR/2019/6183 6183 Checking of reinforcement ,Shuttering & pouring concrete (M-30) in wall 1st lift of MNB A1 MNBR Km 181+700 RHS 23-Nov-19 5:00 PM DONE
6247 NMSCEW/P-IV/STR/2019/6184 6184 Checking layout ,Level & pouring concrete PCC (M-15) at LP-12 Viaduct Km 213+915 LHS 23-Nov-19 9:30 AM
6248 NMSCEW/P-IV/STR/2019/6185 6185 Checking of reinforcement ,Shuttering & pouring concrete (M-30) in LP11 raft Viaduct Km 202+190 LHS 23-Nov-19 4:00 PM
Checking of Shuttering, reinforcement & pouring of concrete for RE WALL PANEL precast
TYPE -A
6249 NMSCEW/P-IV/STR/2019/6186 6186 205 NOS, TYPE -B 70 NOS, TYPE -Sta 14 NOS, TYPE -Stb 14 NOS, TYPE -Stc 14 NOS, RE Wall Panel Km 200+200 LHS 23-Nov-19 4:00 PM
TYPE -Std 14 NOS, TYPE -Lta 14 NOS, TYPE -Ltd 14 NOS, at RE panel precast yard camp
2
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-2
6250 NMSCEW/P-IV/STR/2019/6187 6187 Box culvert Km 175+500 LHS 24-Nov-19 10:00 AM
I) 2x2 (4 to 6m) segment no.-59,60,61,62,63,64,65,66
6258 NMSCEW/P-IV/STR/2019/6195 6195 Checking of Shuttering,reinforcement & pouring concrete (M-30) in retaning walll raft A1 PUP Km 188+575 RHS 24-Nov-19 5:00 PM DONE
6259 NMSCEW/P-IV/STR/2019/6196 6196 Checking of Shuttering,reinforcement & pouring concrete (M-30) OF 3rd lift wall A2 side VUP Km 166+987 LHS 24-Nov-19 12:30 PM
NR
Checking for stressing and remove slagness of H.T. wires at Girder no-109,110,111 & 112 at
6260 NMSCEW/P-IV/STR/2019/6197 6197 Girder Km 200+200 LHS 24-Nov-19 12:00 PM IPC-14
bed no -08, Girder Type-1 at casting yard camp -2
Checking for reinforcement at Girder no-109,110,111 & 112 at bed no -08, Girder Type-1 at
6261 NMSCEW/P-IV/STR/2019/6198 6198 Girder Km 200+200 LHS 24-Nov-19 10:00 AM IPC-14
casting yard camp -2
Checking for side shuttering & pouring concrete(M-50) Girder no-121,122,123 & 124 at bed
6262 NMSCEW/P-IV/STR/2019/6199 6199 Girder Km 200+200 LHS 24-Nov-19 10:30 AM
no -08, Girder Type-2 at casting yard camp -2
6263 NMSCEW/P-IV/STR/2019/6200 6200 Checking of Shuttering,reinforcement, pouring concrete (M-30) for RP9 pier cap PUP Km 202+190 RHS 24-Nov-19 10:00 AM
6264 NMSCEW/P-IV/STR/2019/6201 6201 Checking of Shuttering,reinforcement, pouring concrete (M-30) for RP13 pier cap PUP Km 202+190 Km 00+000 RHS 24-Nov-19 10:30 AM IPC-10 DONE AE
6265 NMSCEW/P-IV/STR/2019/6202 6202 Checking of Shuttering,reinforcement, pouring concrete (M-30) for final lift wall A1 & A2 PUP Km 164+380 Km 00+000 LHS 24-Nov-19 2:00 PM IPC-10 DONE
Checking for stressing and remove slagness of H.T. wires at Girder no-125,126,127 & 128 at
6266 NMSCEW/P-IV/STR/2019/6203 6203 Girder Km 200+200 LHS 25-Nov-19 5:00 PM
bed no -03, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no -125,126,127 & 128 at bed no -04, Girder Type-2 at
6267 NMSCEW/P-IV/STR/2019/6204 6204 Girder Km 200+200 LHS 25-Nov-19 5:30 PM
casting yard camp -2
Checking for side shuttering & pouring concrete(M-50) Girder no-109,110,111 & 112 at bed
6268 NMSCEW/P-IV/STR/2019/6205 6205 Girder Km 200+200 LHS 25-Nov-19 7:00 PM IPC-14
no -08, Girder Type-1 at casting yard camp -2
6269 NMSCEW/P-IV/STR/2019/6206 6206 Checking of Shuttering,reinforcement, pouring concrete (M-30) for raft at LP1 Viaduct Km 213+915 LHS 25-Nov-19 10:30 AM
6270 NMSCEW/P-IV/STR/2019/6207 6207 Checking layout ,Level, & pouring concrete PCC (M-15) at RP 7 Viaduct Km 213+915 RHS 25-Nov-19 2:30 PM
6271 NMSCEW/P-IV/STR/2019/6208 6208 Checking of Shuttering,reinforcement, pouring concrete (M-30) for abutment raft at LA1 Viaduct Km 200+920 Km 00+000 LHS 25-Nov-19 4:00 PM IPC-10 DONE
AE
Checking of Shuttering,reinforcement, pouring concrete (M-30) for abutment shaft at RA 2
6272 NMSCEW/P-IV/STR/2019/6209 6209 Viaduct Km 200+920 RHS 25-Nov-19 10:00 AM IPC-14
1st lift
Checking of Shuttering,reinforcement, pouring concrete (M-30) for cross girder between LP10
6273 NMSCEW/P-IV/STR/2019/6210 6210 Viaduct Km 169+800 LHS 25-Nov-19 4:00 PM DONE
TO LP 11
6274 NMSCEW/P-IV/STR/2019/6211 6211 Checking for pouring concrete PCC (M-15) at box culvert Box Culvert Km 18+110 BHS 25-Nov-19 10:30 AM
Checking of Shuttering,reinforcement, pouring concrete (M-30) for top slab with top haunch
6275 NMSCEW/P-IV/STR/2019/6212 6212 CUP Km 164+380 LHS 25-Nov-19 5:30 PM
A1 & A2 side NR
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-2
6276 NMSCEW/P-IV/STR/2019/6213 6213 Box culvert Km 200+200 LHS 25-Nov-19 10:00 AM DONE
I) 2x2 (4 to 6m) segment no.-102,103,104
II) 2x2 (0 to 2m) segment no.-436,437,438,439
Checking layout ,excavation bed Level, & pouring concrete PCC (M-15) of RA1 & LA1 at
6277 NMSCEW/P-IV/STR/2019/6214 6214 MNBR Km 174+570 BHS 25-Nov-19 2:00 PM DONE
MNB
6278 NMSCEW/P-IV/STR/2019/6215 6215 Checking of Shuttering,reinforcement, pouring concrete (M-30) of wall W1 & W2 1st lift PUP Km 212+080 Km 00+000 LHS 25-Nov-19 10:00 AM IPC-10 DONE
AE
6279 NMSCEW/P-IV/STR/2019/6216 6216 Checking of girder launching and positioning of module no.- 1 at RP2 to RP10 Viaduct Km 169+800 LHS 25-Nov-19 9:00 AM DONE
6280 NMSCEW/P-IV/STR/2019/6217 6217 Checking top level & laying of PCC (M-10) of for utility duct (2x2) Utility Duct Km 174+920 BHS 25-Nov-19 10:00 AM DONE
6281 NMSCEW/P-IV/STR/2019/6218 6218 Checking for erection & jointing of precast box culvert (3x3) Box culvert Km 179+715 Km 00+000 BHS 25-Nov-19 10:00 AM IPC-10 DONE
6282 NMSCEW/P-IV/STR/2019/6219 6219 Checking of Shuttering,reinforcement, pouring concrete (M-30) of abutment RA1 2nd lift PUP Km 205+610 LHS 26-Nov-19 10:00 AM
6283 NMSCEW/P-IV/STR/2019/6220 6220 Checking of Shuttering,reinforcement, pouring concrete (M-30) of wall W1 & W2 1st lift PUP Km 206+985 Km 00+000 RHS 26-Nov-19 8:00 AM IPC-11 Approved
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-2
6284 NMSCEW/P-IV/STR/2019/6221 6221 Box culvert Km 200+200 LHS 26-Nov-19 10:00 AM
I) 2x2 (4 to 6m) segment no.-67,68,69,70,71,72,73
II) 3x3 (2 to 4m) segment no.-94,95,96
6285 NMSCEW/P-IV/STR/2019/6222 6222 Checking of Shuttering,reinforcement, pouring concrete (M-30) of slab MNBR Km 203+409 Km 00+000 LHS 26-Nov-19 1:00 PM IPC-10 DONE
Checking of Shuttering,reinforcement, pouring concrete (M-30) of 1ST LIFT w1 WING
6286 NMSCEW/P-IV/STR/2019/6223 6223 MNBR Km 203+409 LHS 26-Nov-19 10:00 AM
WALL
Checking of Shuttering,reinforcement, pouring concrete (M-30) of 3RD LIFT w2 WING
6287 NMSCEW/P-IV/STR/2019/6224 6224 MNBR Km 203+409 LHS 26-Nov-19 11:00 AM
WALL
Checking for stressing and remove slagness of H.T. wires at Girder no-113,114,115 & 116 at
6288 NMSCEW/P-IV/STR/2019/6225 6225 Girder Km 200+200 LHS 26-Nov-19 10:00 AM IPC-14
bed no -05, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no -113,114,115 & 116 at bed no -05, Girder Type-2 at
6289 NMSCEW/P-IV/STR/2019/6226 6226 Girder Km 200+200 LHS 26-Nov-19 5:30 PM IPC-14
casting yard camp -2
6290 NMSCEW/P-IV/STR/2019/6227 6227 Checking of Shuttering,reinforcement, pouring concrete of RP1 pier cap Viaduct Km 196+560 RHS 26-Nov-19 2:30 PM
6291 NMSCEW/P-IV/STR/2019/6228 6228 Checking layout , Founding Level, & pouring concrete PCC at LA1 abutment Viaduct Km 196+560 LHS 26-Nov-19 10:30 AM
6292 NMSCEW/P-IV/STR/2019/6229 6229 Checking of Shuttering,reinforcement, pouring concrete of LP8 pier shaft final lift Viaduct Km 195+900 LHS 26-Nov-19 3:30 PM
6293 NMSCEW/P-IV/STR/2019/6230 6230 Checking of Shuttering,reinforcement, pouring concrete of RP9 pier cap Viaduct Km 202+190 Km 00+000 RHS 26-Nov-19 12:00 PM IPC-10 DONE AE
6294 NMSCEW/P-IV/STR/2019/6231 6231 Checking of Shuttering,reinforcement, pouring concrete of RP10 pier shaft final lift Viaduct Km 202+190 RHS 26-Nov-19 3:30 PM
6295 NMSCEW/P-IV/STR/2019/6232 6232 Checking of Shuttering,reinforcement, pouring concrete of RP8 padestal Viaduct Km 202+190 RHS 26-Nov-19 2:00 PM
6296 NMSCEW/P-IV/STR/2019/6233 6233 Checking of Shuttering,reinforcement, pouring concrete of LP11 raft Viaduct Km 202+190 Km 00+000 LHS 26-Nov-19 3:00 PM IPC-10 DONE
6297 NMSCEW/P-IV/STR/2019/6234 6234 Checking layout , Level, & pouring concrete PCC at LA2 abutment Viaduct Km 202+190 LHS 26-Nov-19 3:30 PM
6298 NMSCEW/P-IV/STR/2019/6235 6235 Checking of Shuttering,reinforcement, pouring concrete at A1 & A2 1st lift Box culvert Km 177+760 Km 00+000 BHS 26-Nov-19 10:30 AM IPC-10 DONE
Checking of Shuttering,reinforcement, pouring concrete at top haunch A1 & A2 final lift &
6299 NMSCEW/P-IV/STR/2019/6236 6236 VUP Km 179+983 Km 00+000 LHS 26-Nov-19 4:30 PM IPC-10 DONE
top slab AE
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-1
6300 NMSCEW/P-IV/STR/2019/6237 6237 Box culvert Km 175+500 LHS 26-Nov-19 10:20 AM DONE
I) 2x2 (4 to 6m) segment no.-105,106,107
II) 2x2 (0 to 2m) segment no.-440,441,442 & 443
6301 NMSCEW/P-IV/STR/2019/6238 6238 Checking of Shuttering,reinforcement, pouring concrete (M-30) at retaning wall A1 4th lift PUP Km 188+575 LHS 26-Nov-19 4:00 PM DONE
6302 NMSCEW/P-IV/STR/2019/6239 6239 Checking of Shuttering,reinforcement, pouring concrete (M-30) at retaning wall A2 3rd lift PUP Km 188+575 LHS 26-Nov-19 5:00 PM DONE
6303 NMSCEW/P-IV/STR/2019/6240 6240 Checking of Shuttering,reinforcement, pouring concrete (M-30) at retaning wall A1 1st lift PUP Km 188+575 RHS 26-Nov-19 5:30 PM DONE
Checking of Shuttering,reinforcement, pouring concrete (M-35) in wall 2nd lift (A2) of MNB
6304 NMSCEW/P-IV/STR/2019/6241 6241 MNBR Km 01+980 26-Nov-19 8:00 AM DONE
(Loop C)
6305 NMSCEW/P-IV/STR/2019/6242 6242 Checking of Shuttering,reinforcement, pouring concrete (M-30) in wall 2nd lift A1 & A2 MNB Km 181+700 Km 00+000 LHS 26-Nov-19 11:00 AM IPC-11 DONE
6306 NMSCEW/P-IV/STR/2019/6243 6243 Checking of Shuttering,reinforcement, pouring concrete (M-35) in pier (P1) raft at VOP VOP Km 181+420 RHS 26-Nov-19 11:00 AM DONE
6311 NMSCEW/P-IV/STR/2019/6248 6248 Checking of Shuttering,reinforcement, pouring concrete (M-30) in retaning wall footing at A2 PUP Km 186+000 LHS 26-Nov-19 4:00 PM DONE
6312 NMSCEW/P-IV/STR/2019/6249 6249 Checking layout , Founding Level, & pouring concrete PCC at utility duct (2x2) Utility Duct Km 189+320 LHS 27-Nov-19 11:00 AM
6313 NMSCEW/P-IV/STR/2019/6250 6250 Checking of Shuttering,reinforcement, pouring concrete of wall W1 & W2 1st lift PUP Km 212+080 Km 00+000 RHS 27-Nov-19 8:00 AM IPC-10 DONE AE
Checking of Shuttering,reinforcement, pouring concrete (M-30) at final lift top haunch A1 &
6314 NMSCEW/P-IV/STR/2019/6251 6251 Box culvert Km 177+760 Km 00+000 LHS 27-Nov-19 11:30 AM IPC-10 DONE
A2 with top slab AE
Checking of Shuttering,reinforcement, pouring concrete (M-30) at top haunch A1 & A2 with
6315 NMSCEW/P-IV/STR/2019/6252 6252 LVUP Km 178+323 Km 00+000 LHS 27-Nov-19 4:30 PM IPC-10 DONE
top slab AE
Checking of Shuttering,reinforcement, pouring concrete (M-30) at top haunch A1 & A2 with
6316 NMSCEW/P-IV/STR/2019/6253 6253 PUP Km 164+380 Km 00+000 LHS 27-Nov-19 2:00 PM IPC-10 DONE
top slab AE
6317 NMSCEW/P-IV/STR/2019/6254 6254 Checking of reinforcement, shuttering & pouring concrete for median wall A1 & A2 3rd lift PUP Km 183+290 BHS 27-Nov-19 10:00 AM DONE
6318 NMSCEW/P-IV/STR/2019/6255 6255 Checking of reinforcement, shuttering & pouring concrete for A1 3rd lift PUP Km 184+190 LHS 27-Nov-19 10:20 AM DONE
6319 NMSCEW/P-IV/STR/2019/6256 6256 Checking of reinforcement, shuttering & pouring concrete for A1 & A2 2nd lift PUP Km 185+235 RHS 27-Nov-19 10:30 AM DONE
6320 NMSCEW/P-IV/STR/2019/6257 6257 Checking of reinforcement, shuttering & pouring concrete for A1 & A2 final lift Box Culvert Km 180+922 Km 00+000 LHS 27-Nov-19 10:50 AM IPC-10 DONE
6321 NMSCEW/P-IV/STR/2019/6258 6258 Checking of Shuttering,reinforcement, pouring concrete (M-30) at top haunch with top slab Box Culvert Km 180+922 Km 00+000 RHS 27-Nov-19 11:00 AM IPC-10 DONE
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-1
6322 NMSCEW/P-IV/STR/2019/6259 6259 Box culvert Km 175+500 LHS 27-Nov-19 10:30 AM DONE
I) 2x2 (4 to 6m) segment no.-108,109,110
II) 2x2 (0 to 2m) segment no.-444,445,446 & 447
6323 NMSCEW/P-IV/STR/2019/6260 6260 Checking of Shuttering,reinforcement, pouring concrete (M-30) in retaning wall footing A1 Box Culvert Km 186+000 RHS 27-Nov-19 11:00 AM DONE
6324 NMSCEW/P-IV/STR/2019/6261 6261 Checking of Shuttering,reinforcement, pouring concrete (M-30) in retaning wall A1 2nd lift Box Culvert Km 188+575 RHS 27-Nov-19 2:00 PM DONE
6325 NMSCEW/P-IV/STR/2019/6262 6262 Checking of Shuttering,reinforcement, pouring concrete (M-30) in retaning wall A2 3rd lift Box Culvert Km 188+575 LHS 27-Nov-19 2:30 PM DONE
6326 NMSCEW/P-IV/STR/2019/6263 6263 Checking layout , Level, & pouring concrete PCC (M-10) for retaning wall A1 PUP Km 189+000 LHS 27-Nov-19 3:00 PM NR
6327 NMSCEW/P-IV/STR/2019/6264 6264 Checking layout ,excavation Level, & pouring concrete PCC (M-10) for retaning wall A2 PUP Km 189+000 LHS 27-Nov-19 3:10 PM DONE
6328 NMSCEW/P-IV/STR/2019/6265 6265 Checking layout ,excavation Level, & pouring concrete PCC (M-10) for retaning wall A1 PUP Km 189+000 RHS 27-Nov-19 4:00 PM
NR
6329 NMSCEW/P-IV/STR/2019/6266 6266 Checking layout ,excavation Level, & pouring concrete PCC (M-10) for retaning wall A2 PUP Km 189+000 RHS 27-Nov-19 4:30 PM DONE
6330 NMSCEW/P-IV/STR/2019/6267 6267 Checking of Shuttering,reinforcement, pouring concrete in 1st lift wall A1 & A2 Box Culvert Km 166+987 RHS 27-Nov-19 12:00 PM DONE
6331 NMSCEW/P-IV/STR/2019/6268 6268 Checking of Shuttering,reinforcement, pouring concrete (M-35) in abutment A2 raft VOP Km 181+420 LHS 27-Nov-19 5:00 PM NR
6332 NMSCEW/P-IV/STR/2019/6269 6269 Checking of Shuttering,reinforcement, pouring concrete (M-30) in retaning wall 4th lift at RA2 PUP Km 183+290 RHS 27-Nov-19 10:00 AM DONE
6333 NMSCEW/P-IV/STR/2019/6270 6270 Checking layout ,excavation Level, & pouring concrete PCC (M-5) in abutment RA2 VOP Km 181+420 RHS 27-Nov-19 4:00 PM DONE
Checking of Shuttering,reinforcement, pouring concrete for cross girder between LP11 to
6334 NMSCEW/P-IV/STR/2019/6271 6271 Viaduct Km 169+800 LHS 27-Nov-19 4:00 PM DONE
LP12
6335 NMSCEW/P-IV/STR/2019/6272 6272 Checking of Shuttering,reinforcement, pouring concrete for top level of raft at LP1 Viaduct Km 213+915 Km 00+000 LHS 27-Nov-19 9:30 AM IPC-11 Approved AE
Checking for stressing and remove slagness of H.T. wires at Girder no-125,126,127 & 128 at
6336 NMSCEW/P-IV/STR/2019/6273 6273 Girder Km 200+200 LHS 27-Nov-19 9:00 AM
bed no -03, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no -125,126,127 & 128 at bed no -03, Girder Type-2 at
6337 NMSCEW/P-IV/STR/2019/6274 6274 Girder Km 200+200 LHS 27-Nov-19 9:30 AM
casting yard camp -2
Checking for side shuttering & pouring concrete(M-50) Girder no-113,114,115 & 116 at bed
6338 NMSCEW/P-IV/STR/2019/6275 6275 Girder Km 200+200 LHS 27-Nov-19 7:00 PM IPC-14
no -05, Girder Type-1 at casting yard camp -2
Checking for side shuttering & pouring concrete(M-50) Girder no-125,126,127 & 128 at bed
6339 NMSCEW/P-IV/STR/2019/6276 6276 Girder Km 200+200 LHS 27-Nov-19 5:30 PM
no -03, Girder Type-1 at casting yard camp -2
6340 NMSCEW/P-IV/STR/2019/6277 6277 Checking of Shuttering,reinforcement, pouring concrete (M-30) for LP4 pier shaft final lift Viaduct Km 200+920 LHS 27-Nov-19 4:00 PM
6341 NMSCEW/P-IV/STR/2019/6278 6278 Checking of Shuttering,reinforcement, pouring concrete for retaning wall W-1 2nd lift PUP Km 193+880 RHS 27-Nov-19 8:00 AM
6342 NMSCEW/P-IV/STR/2019/6279 6279 Checking layout , Level, & pouring concrete PCC for retaning wall w-2 MNBR Km 199+360 RHS 27-Nov-19 8:00 AM
6343 NMSCEW/P-IV/STR/2019/6280 6280 Checking of Shuttering,reinforcement, pouring concrete for retaning wall W-1 raft PUP Km 191+740 RHS 27-Nov-19 3:00 PM
6344 NMSCEW/P-IV/STR/2019/6281 6281 Checking of Shuttering,reinforcement, pouring concrete for raft at retaning wall A1 & A2 side PUP Km 165+790 RHS 27-Nov-19 6:00 PM DONE
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-2
6345 NMSCEW/P-IV/STR/2019/6282 6282 Box culvert Km 200+200 LHS 28-Nov-19 10:10 AM
I) 2x2 (4 to 6m) segment no.-74,75,76,77,78,79,80
II) 3x3 (2 to 4m) segment no.-,97,98,99
6346 NMSCEW/P-IV/STR/2019/6283 6283 Checking of level, layout Shuttering,reinforcement, pouring concrete in top slab PUP Km 206+985 Km 00+000 LHS 28-Nov-19 10:00 AM IPC-11 Approved
6347 NMSCEW/P-IV/STR/2019/6284 6284 Checking of Shuttering,reinforcement & pouring concrete of wing wall W1 2nd lift MNBR Km 203+409 LHS 28-Nov-19 11:00 AM
6348 NMSCEW/P-IV/STR/2019/6285 6285 Checking of Shuttering,reinforcement & pouring concrete of wing wall W2 4TH lift MNBR Km 203+409 LHS 28-Nov-19 1:00 PM
Checking for stressing and remove slagness of H.T. wires at Girder no-129,130,131 & 132 at
6349 NMSCEW/P-IV/STR/2019/6286 6286 Girder Km 200+200 LHS 28-Nov-19 11:00 AM
bed no -01, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no -129,130,131 & 132 at bed no -01, Girder Type-2 at
6350 NMSCEW/P-IV/STR/2019/6287 6287 Girder Km 200+200 LHS 28-Nov-19 11:30 AM
casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-117,118,119 & 120 at
6351 NMSCEW/P-IV/STR/2019/6288 6288 Girder Km 200+200 LHS 28-Nov-19 5:00 PM IPC-14
bed no -07, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no -117,118,119 & 120 at bed no -07, Girder Type-1 at
6352 NMSCEW/P-IV/STR/2019/6289 6289 Girder Km 200+200 LHS 28-Nov-19 5:30 PM IPC-14
casting yard camp -2
6353 NMSCEW/P-IV/STR/2019/6290 6290 Checking layout , Level, & pouring concrete PCC (M-10) for RP-8 Viaduct Km 213+915 RHS 28-Nov-19 2:00 PM
6354 NMSCEW/P-IV/STR/2019/6291 6291 Checking layout , Level, & pouring concrete PCC (M-10) for RP-7 Viaduct Km 213+915 RHS 28-Nov-19 12:30 PM
6355 NMSCEW/P-IV/STR/2019/6292 6292 Checking of Shuttering,reinforcement & pouring concrete of RP1 pier cap Viaduct Km 196+560 Km 00+000 RHS 28-Nov-19 9:30 AM IPC-11 Approved
6356 NMSCEW/P-IV/STR/2019/6293 6293 Checking layout ,founding Level, & pouring concrete PCC (M-10) for LA-1 abutment Viaduct Km 196+560 Km 00+000 LHS 28-Nov-19 10:00 AM IPC-11 Approved
6357 NMSCEW/P-IV/STR/2019/6294 6294 Checking of Shuttering,reinforcement & pouring concrete of RP 10 pier shaft final lift Viaduct Km 202+190 Km 00+000 RHS 28-Nov-19 3:30 PM IPC-11 Approved
6358 NMSCEW/P-IV/STR/2019/6295 6295 Checking of Shuttering,reinforcement & pouring concrete of LP-8 pedestal Viaduct Km 202+190 LHS 28-Nov-19 2:00 PM
6359 NMSCEW/P-IV/STR/2019/6296 6296 Checking of Shuttering,reinforcement & pouring concrete of LP-9 pedestal Viaduct Km 202+190 LHS 28-Nov-19 3:00 PM
Checking of Shuttering,reinforcement & pouring concrete of top haunch A1 & A2 final lift &
6360 NMSCEW/P-IV/STR/2019/6297 6297 VUP Km 176+614 Km 00+000 RHS 28-Nov-19 4:30 PM IPC-10 DONE
top slab
6361 NMSCEW/P-IV/STR/2019/6298 6298 Checking of Shuttering,reinforcement & pouring concrete of final lift wall A1 & A2 side Box culvert Km 163+570 Km 00+000 LHS 28-Nov-19 2:00 PM IPC-10 DONE
Checking of Shuttering,reinforcement & pouring concrete of TOP slab with top haunch wall
6362 NMSCEW/P-IV/STR/2019/6299 6299 LVUP Km 169+291 Km 00+000 RHS 28-Nov-19 2:20 PM IPC-10 DONE
A1 & A2 side.
6363 NMSCEW/P-IV/STR/2019/6300 6300 Checking of bearing & grouting at LP-11 & LP-12 Viaduct Km 169+800 LHS 28-Nov-19 9:00 AM DONE
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert
6364 NMSCEW/P-IV/STR/2019/6301 6301 Box culvert Km 175+500 LHS 28-Nov-19 10:00 AM DONE
I) 2X2 (4 to 6m) segment no.-,111,112,113
II) 2x2 (0 to 2m) segment no.-448,449,450 & 451
6365 NMSCEW/P-IV/STR/2019/6302 6302 Checking layout ,excavation bed Level, & pouring concrete PCC (M-15) at LA1 & RA1 MNBR Km 174+173 BHS 28-Nov-19 3:00 PM DONE
Checking of Shuttering,reinforcement & pouring concrete at median wall final lift at raft (M-
6366 NMSCEW/P-IV/STR/2019/6303 6303 PUP Km 183+290 BHS 28-Nov-19 10:00 AM DONE
30) at A1 & A2.
6367 NMSCEW/P-IV/STR/2019/6304 6304 Checking of Shuttering,reinforcement & pouring concrete (M-30) at retaning wall 4th lift A1 PUP Km 184+190 LHS 28-Nov-19 10:30 AM DONE
6375 NMSCEW/P-IV/STR/2019/6312 6312 Checking of Shuttering,reinforcement & pouring concrete in wall 1st lift of retaning wall A2 PUP Km 186+000 LHS 28-Nov-19 4:10 PM DONE
6376 NMSCEW/P-IV/STR/2019/6313 6313 Checking of Shuttering,reinforcement & pouring concrete RP-9 pier cap Viaduct Km 202+190 RHS 28-Nov-19 3:30 PM
6377 NMSCEW/P-IV/STR/2019/6314 6314 Checking of Shuttering,reinforcement & pouring concrete for LA-2 raft Viaduct Km 195+900 Km 00+000 LHS 28-Nov-19 3:30 PM IPC-10 DONE
6378 NMSCEW/P-IV/STR/2019/6315 6315 Checking layout , Level, & pouring concrete PCC for LA2 Viaduct Km 202+190 Km 00+000 LHS 28-Nov-19 2:30 PM IPC-10 DONE
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-2
6379 NMSCEW/P-IV/STR/2019/6316 6316 Box culvert Km 200+200 LHS 29-Nov-19 10:00 AM
I) 2x2 (4 to 6m) segment no.-81,82,83,84,85,86,87
II) 3x3 (2 to 4m) segment no.-100,101,102
6380 NMSCEW/P-IV/STR/2019/6317 6317 Checking for erection & jointing of precast box culvert (3x3) Box culvert Km 164+156 Km 00+000 BHS 29-Nov-19 10:00 AM IPC-10 DONE
6381 NMSCEW/P-IV/STR/2019/6318 6318 Checking for erection & jointing of precast utility duct (2x2) Box culvert Km 174+920 BHS 29-Nov-19 8:30 AM DONE
Checking of Shuttering,reinforcement, pouring concrete of top slab with top haunch wall A1 &
6382 NMSCEW/P-IV/STR/2019/6319 6319 Box culvert Km 163+570 Km 00+000 LHS 29-Nov-19 2:00 PM IPC-10 DONE
A2 side
6383 NMSCEW/P-IV/STR/2019/6320 6320 Checking of Shuttering,reinforcement, pouring concrete in 4th lift of retaning wall A2 PUP Km 188+575 RHS 29-Nov-19 9:00 AM DONE
Checking of Shuttering,reinforcement, pouring concrete in 2nd lift U-type retaning wall A2
6384 NMSCEW/P-IV/STR/2019/6321 6321 PUP Km 189+000 29-Nov-19 9:30 AM DONE
side
Checking of Shuttering,reinforcement, pouring concrete in 3rd lift U-type retaning wall A1
6385 NMSCEW/P-IV/STR/2019/6322 6322 PUP Km 189+000 29-Nov-19 10:00 AM DONE
side
6386 NMSCEW/P-IV/STR/2019/6323 6323 Checking of Shuttering,reinforcement, pouring concrete in 3rd lift A1 side VUP Km 187+113 29-Nov-19 11:00 AM DONE
Checking for stressing and remove slagness of H.T. wires at Girder no-121,122,123 & 124 at
6387 NMSCEW/P-IV/STR/2019/6324 6324 Girder Km 200+200 LHS 29-Nov-19 2:00 PM
bed no -06, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no -121,122,123 & 124 at bed no -06, Girder Type-1 at
6388 NMSCEW/P-IV/STR/2019/6325 6325 Girder Km 200+200 LHS 29-Nov-19 2:30 PM
casting yard camp -2
Checking for side shuttering & pouring concrete(M-50) Girder no-129,130,131,& 132 at bed
6389 NMSCEW/P-IV/STR/2019/6326 6326 Girder Km 200+200 LHS 29-Nov-19 2:30 PM
no -01, Girder Type-1 at casting yard camp -2
Checking for side shuttering & pouring concrete(M-50) Girder no-1117,118,119 & 120 at bed
6390 NMSCEW/P-IV/STR/2019/6327 6327 Girder Km 200+200 LHS 29-Nov-19 7:00 PM
no -07, Girder Type-1 at casting yard camp -2
6391 NMSCEW/P-IV/STR/2019/6328 6328 Checking of Shuttering,reinforcement, pouring concrete for RP-5 pier shaft final lift Viaduct Km 196+560 Km 00+000 RHS 29-Nov-19 2:30 PM IPC-11 Approved
6392 NMSCEW/P-IV/STR/2019/6329 6329 Checking of layout,level, Shuttering,reinforcement, pouring concrete for top slab Box culvert Km 201+280 Km 00+000 LHS 29-Nov-19 6:00 PM IPC-11 Approved
6393 NMSCEW/P-IV/STR/2019/6330 6330 Checking of Shuttering,reinforcement, pouring concrete for median wall W-1 1st lift PUP Km 193+880 RHS 29-Nov-19 2:00 PM
6394 NMSCEW/P-IV/STR/2019/6331 6331 Checking of layout,level, Shuttering,reinforcement, pouring concrete W-2 1st lift Box culvert Km 201+280 Km 00+000 RHS 29-Nov-19 9:00 AM IPC-11 Approved
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-1
6395 NMSCEW/P-IV/STR/2019/6332 6332 Box culvert Km 175+500 LHS 29-Nov-19 10:00 AM DONE
I) 2x2 (2 to 4m) segment no.-239,240,241,242,243,244
II) 2x2 (0 to 2m) segment no.-452,453,454,455
Checking of layout,level, Shuttering,reinforcement, pouring concrete for LP-4 pier shaft final
6396 NMSCEW/P-IV/STR/2019/6333 6333 Viaduct Km 200+920 LHS 29-Nov-19 10:00 AM
lift
Checking of layout,level, Shuttering,reinforcement, pouring concrete for LP-3 pier shaft final
6397 NMSCEW/P-IV/STR/2019/6334 6334 Viaduct Km 200+920 LHS 29-Nov-19 4:00 PM
lift
6398 NMSCEW/P-IV/STR/2019/6335 6335 Checking of layout,level, pouring concrete PCC for LP-12 Viaduct Km 213+915 LHS 29-Nov-19 4:30 PM
Checking of layout,level, Shuttering,reinforcement, pouring concrete for 3rd lift of retaining
6399 NMSCEW/P-IV/STR/2019/6336 6336 PUP Km 188+575 RHS 29-Nov-19 8:00 AM DONE
wall A1
6400 NMSCEW/P-IV/STR/2019/6337 6337 Checking of Shuttering,reinforcement, pouring concrete for in wall 3rd lift (A1 & A2) Loop B MNB Km 01+980 29-Nov-19 8:00 AM DONE
6401 NMSCEW/P-IV/STR/2019/6338 6338 Checking of layout,excavation bed level, pouring concrete for PCC of retaining wall A1 PUP Km 185+235 LHS 29-Nov-19 10:00 AM DONE
6402 NMSCEW/P-IV/STR/2019/6339 6339 Checking of Shuttering,reinforcement, pouring concrete for in retaning wall 2nd lift A1 PUP Km 186+000 LHS 29-Nov-19 11:00 AM DONE
6403 NMSCEW/P-IV/STR/2019/6340 6340 Checking of Shuttering,reinforcement, pouring concrete for in retaning wall raft A1 PUP Km 186+000 LHS 29-Nov-19 11:30 AM DONE
6404 NMSCEW/P-IV/STR/2019/6341 6341 Checking of Shuttering,reinforcement, pouring concrete for in wall 3rd lift VUP Km 187+113 29-Nov-19 1:00 PM
6405 NMSCEW/P-IV/STR/2019/6342 6342 Checking of Shuttering,reinforcement, pouring concrete for in retaning wall 2nd lift A2 PUP Km 187+113 29-Nov-19 3:00 PM
6406 NMSCEW/P-IV/STR/2019/6343 6343 Checking of layout,excavation bed level, pouring concrete for retaining wall A2 PUP Km 185+235 LHS 29-Nov-19 10:00 AM DONE
6407 NMSCEW/P-IV/STR/2019/6344 6344 Checking of Shuttering,reinforcement, pouring concrete for in retaning wall raft A2 PUP Km 186+000 LHS 29-Nov-19 11:30 AM DONE
6408 NMSCEW/P-IV/STR/2019/6345 6345 Checking of Shuttering,reinforcement, pouring concrete for RP-12 pier shaft Final lift PUP Km 202+190 RHS 29-Nov-19 3:30 PM
Checking for side shuttering & pouring concrete(M-50) Girder no-121,122,123 & 124 at bed
6409 NMSCEW/P-IV/STR/2019/6346 6346 Girder Km 200+200 LHS 30-Nov-19 7:00 PM
no -06, Girder Type-1 at casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-133,134,135 & 136 at
6410 NMSCEW/P-IV/STR/2019/6347 6347 Girder Km 200+200 LHS 30-Nov-19 5:00 PM
bed no -04, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no -133,134,135 & 136 at bed no -06, Girder Type-2 at
6411 NMSCEW/P-IV/STR/2019/6348 6348 Girder Km 200+200 LHS 30-Nov-19 5:30 PM
casting yard camp -2
Checking of Shuttering,reinforcement, pouring concrete for final lift top haunch A1 & A2 with
6412 NMSCEW/P-IV/STR/2019/6349 6349 Box culvert Km 177+760 Km 00+000 RHS 30-Nov-19 4:30 PM IPC-10 DONE
top slab
6413 NMSCEW/P-IV/STR/2019/6350 6350 Checking for erection & jointing of precast Utility Duct (2x2) Box culvert Km 162+930 BHS 30-Nov-19 10:00 AM DONE
6414 NMSCEW/P-IV/STR/2019/6351 6351 Checking for erection & jointing of precast Utility Duct (2x2) Box culvert Km 173+860 BHS 30-Nov-19 8:30 AM
6415 NMSCEW/P-IV/STR/2019/6352 6352 Checking for erection & jointing of precast Utility Duct (2x2) Box culvert Km 169+000 BHS 30-Nov-19 4:00 PM DONE
6416 NMSCEW/P-IV/STR/2019/6353 6353 Checking layout , Level, & excavation of MNB MNB Km 176+875 30-Nov-19 9:30 AM
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-2
6417 NMSCEW/P-IV/STR/2019/6354 6354 Box culvert Km 200+200 LHS 30-Nov-19 10:00 AM
I) 2x2 (4 to 6m) segment no.-88,89,90,91,92,93
II) 3x3 (2 to 4m) segment no.-103,104,105
6418 NMSCEW/P-IV/STR/2019/6355 6355 Checking of Shuttering,reinforcement, pouring concrete for raft A2 (median) VUP Km 177+760 RHS 30-Nov-19 4:00 PM
6419 NMSCEW/P-IV/STR/2019/6356 6356 Checking of layout,level Shuttering,reinforcement, pouring concrete for top slab Box culvert Km 192+039 RHS 30-Nov-19 6:00 PM
6420 NMSCEW/P-IV/STR/2019/6357 6357 Checking of layout,level Shuttering,reinforcement, pouring concrete for raft Box culvert Km 193+940 LHS 30-Nov-19 4:00 PM
6421 NMSCEW/P-IV/STR/2019/6358 6358 Checking of Shuttering,reinforcement, pouring concrete for W-1 raft at retaning wall PUP Km 193+880 LHS 30-Nov-19 12:00 PM
6422 NMSCEW/P-IV/STR/2019/6359 6359 Checking of layout,level ,Shuttering,reinforcement, pouring concrete for raft Box culvert Km 198+478 Km 00+000 RHS 30-Nov-19 5:00 PM IPC-11 Approved
6423 NMSCEW/P-IV/STR/2019/6360 6360 Checking of layout,level ,Shuttering,reinforcement, pouring concrete for raft at RP3 VIADUCT Km 213+915 RHS 30-Nov-19 4:30 PM
Checking of layout,level ,Shuttering,reinforcement, pouring concrete for IN 4TH LIFT of
6424 NMSCEW/P-IV/STR/2019/6361 6361 PUP Km 188+575 RHS 30-Nov-19 9:00 AM
retaning wall A1 NR
Checking of layout,level ,Shuttering,reinforcement, pouring concrete for IN 3rd LIFT of U-
6425 NMSCEW/P-IV/STR/2019/6362 6362 PUP Km 189+000 BHS 30-Nov-19 10:00 AM DONE
type retaning wall A2
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-1
6426 NMSCEW/P-IV/STR/2019/6363 6363 Box culvert Km 175+500 LHS 30-Nov-19 10:20 AM DONE
I) 2x2 (2 to 4m) segment no.-242,243,244
II) 2x2 (0 to 2m) segment no.-449,450,451,456
6427 NMSCEW/P-IV/STR/2019/6364 6364 Checking of Shuttering,reinforcement, pouring concrete for LP-9 pedestal VIADUCT. Km 202+190 LHS 30-Nov-19 3:00 PM
6428 NMSCEW/P-IV/STR/2019/6365 6365 Checking of Shuttering,reinforcement, pouring concrete for in wall 2nd lift inner loop C MNB Km 01+980 LHS 30-Nov-19 8:00 AM DONE
6429 NMSCEW/P-IV/STR/2019/6366 6366 Checking of Shuttering,reinforcement, pouring concrete in wall 1st lift of U type retaning wall PUP Km 186+000 LHS 30-Nov-19 11:00 AM DONE
6430 NMSCEW/P-IV/STR/2019/6367 6367 Checking of Shuttering,reinforcement, pouring concrete in abutment (A2) raft VOP Km 181+420 RHS 30-Nov-19 1:00 PM DONE
6431 NMSCEW/P-IV/STR/2019/6368 6368 Checking of Shuttering,reinforcement, pouring concrete in TOP slab Box culvert Km 180+922 RHS 30-Nov-19 4:00 PM NR
Checking of Shuttering,reinforcement, pouring concrete in wall 1st lift of median wall A1&
6432 NMSCEW/P-IV/STR/2019/6369 6369 PUP Km 165+790 BHS 30-Nov-19 5:00 PM DONE
A2 ide
6433 NMSCEW/P-IV/STR/2019/6370 6370 Checking of Shuttering,reinforcement, pouring concrete for LA2 raft VIADUCT Km 202+190 Km 00+000 LHS 30-Nov-19 2:00 PM IPC-10 DONE
6434 NMSCEW/P-IV/STR/2019/6371 6371 Checking of Shuttering,reinforcement, pouring concrete for LA4 pier shaft final lift VIADUCT Km 200+920 LHS 30-Nov-19 10:00 AM
6435 NMSCEW/P-IV/STR/2019/6372 6372 Checking of Shuttering,reinforcement, pouring concrete for LP3 pier shaft final lift VIADUCT Km 200+920 LHS 30-Nov-19 4:00 PM
6436 NMSCEW/P-IV/STR/2019/6373 6373 Checking of completion of segment erection for 3x3 box culvert Box culvert Km 190+750 Km 00+000 BHS 30-Nov-19 11:00 AM IPC-11 Approved
6437 NMSCEW/P-IV/STR/2019/6374 6374 Checking of completion of segment erection for 3x3 box culvert Box culvert Km 192+575 Km 00+000 BHS 30-Nov-19 11:20 AM IPC-11 Approved
6438 NMSCEW/P-IV/STR/2019/6375 6375 Checking of Shuttering,reinforcement, pouring concrete for raft A2 (median) MJB Km 205+610 BHS 30-Nov-19 4:00 PM
Checking of Shuttering and reinforcement for RE WALL PANEL precast TYPE -A
210 NOS,TYPE B- 70 NOS, TYPE -Sta 12 NOS, TYPE -Stb 14 NOS, TYPE -Stc 14 NOS,
6439 NMSCEW/P-IV/STR/2019/6376 6376 RE Wall Panel Km 200+200 LHS 1-Dec-19 10:00 AM
TYPE -Std 14 NOS, TYPE -Lta 14 NOS, TYPE -Ltd 21 NOS, at RE panel precast yard camp
2
Checking of Shuttering,reinforcement, pouring concrete for U-type retaning wall A1 & A2 1st
6440 NMSCEW/P-IV/STR/2019/6377 6377 R.E. wall Km 176+614 LHS 1-Dec-19 4:30 PM
lift
6441 NMSCEW/P-IV/STR/2019/6378 6378 Checking of Shuttering,reinforcement, pouring concrete in wall 3rd lift of retaning wall A1 R.E. wall Km 186+000 RHS 1-Dec-19 8:00 AM
6442 NMSCEW/P-IV/STR/2019/6379 6379 Checking of Shuttering,reinforcement, pouring concrete in wall 3rd lift of retaning wall A2 R.E. wall Km 186+000 LHS 1-Dec-19 8:10 AM
6443 NMSCEW/P-IV/STR/2019/6380 6380 Checking of Shuttering,reinforcement, pouring concrete in retaning wall raft A1 & A2 R.E. wall Km 185+235 LHS 1-Dec-19 10:00 AM
6444 NMSCEW/P-IV/STR/2019/6381 6381 Checking of Shuttering,reinforcement, pouring concrete for U-type retaning wall 3rd lift PUP Km 184+190 LHS 1-Dec-19 4:00 PM
6445 NMSCEW/P-IV/STR/2019/6382 6382 Checking of layout,level,structural excavation & pouring concrete PCC of median wall PUP Km 164+380 BHS 1-Dec-19 11:00 AM
6446 NMSCEW/P-IV/STR/2019/6389 6389 Checking of layout,level & pouring concrete PCC of RP 8 viaduct Km 213+915 BHS 1-Dec-19 9:30 AM
6447 NMSCEW/P-IV/STR/2019/6390 6390 Checking of Shuttering,reinforcement, pouring concrete for 4th lift wall A1 & A2 VUP Km 166+987 LHS 1-Dec-19 2:00 PM
6448 NMSCEW/P-IV/STR/2019/6391 6391 Checking of Shuttering,reinforcement, pouring concrete for RP 12 pier shaft final lift viaduct Km 202+190 RHS 1-Dec-19 3:30 PM
6449 NMSCEW/P-IV/STR/2019/6392 6392 Checking of Shuttering,reinforcement, pouring concrete for LP 9 pedestal viaduct Km 202+190 LHS 1-Dec-19 12:00 PM
6450 NMSCEW/P-IV/STR/2019/6393 6393 Checking of Shuttering,reinforcement, pouring concrete for RP 11 pier cap viaduct Km 202+190 RHS 1-Dec-19 12:30 PM
6451 NMSCEW/P-IV/STR/2019/6394 6394 Checking of layout,level & pouring concrete PCC of LP-12 viaduct Km 213+915 LHS 1-Dec-19 9:30 AM
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no- 117,118,119 &
6452 NMSCEW/P-IV/STR/2019/6395 6395 Girder Km 200+200 LHS 1-Dec-19 11:00 AM Spot RFI IPC-14
120 at bed no-07,Girder Type- 1
6453 NMSCEW/P-IV/STR/2019/6396 6396 Checking of bearing fixing & grouting at LA 2 & RP-12 Viaduct Km 169+800 BHS 2-Dec-19 2:00 PM
Checking of Shuttering,reinforcement & pouring concrete(M-35) for abutmnet shaft LA1 3rd
6454 NMSCEW/P-IV/STR/2019/6397 6397 MJB Km 205+610 LHS 2-Dec-19 2:00 PM
lift
Checking for stressing and remove slagness of H.T. wires at Girder no-137,138,139 & 140 at
6455 NMSCEW/P-IV/STR/2019/6398 6398 Girder Km 200+200 LHS 2-Dec-19 11:00 AM
bed no -02, Girder Type-2 at casting yard camp -2
Checking for reinforcemnt at Girder no-137,138,139 & 140 at bed no -02, Girder Type-2 at
6456 NMSCEW/P-IV/STR/2019/6399 6399 Girder Km 200+200 LHS 2-Dec-19 11:30 AM
casting yard camp -2
Checking of side shuttering of girder no -133,134,135 & 136 at bed no -04, Girder Type-2 at
6457 NMSCEW/P-IV/STR/2019/6400 6400 Girder Km 200+200 LHS 2-Dec-19 5:00 PM
casting yard camp -2
Checking of approval of pouring of concrete(M-50) of girder no -133,134,135 & 136 at bed no
6458 NMSCEW/P-IV/STR/2019/6401 6401 Girder Km 200+200 LHS 2-Dec-19 5:30 PM
-04, Girder Type-2 at casting yard camp -2
6459 NMSCEW/P-IV/STR/2019/6402 6402 Checking of Shuttering,reinforcement & pouring concrete(M-35) for pier shaft final lift at LP8 Viaduct Km 195+900 LHS 2-Dec-19 11:30 AM
6460 NMSCEW/P-IV/STR/2019/6403 6403 Checking layout ,Level, & pouring concrete PCC for LA-2 Viaduct Km 213+915 LHS 2-Dec-19 10:30 AM
6461 NMSCEW/P-IV/STR/2019/6404 6404 Checking layout ,Level, & pouring concrete PCC for RP-8 Viaduct Km 213+915 RHS 2-Dec-19 9:30 AM
6462 NMSCEW/P-IV/STR/2019/6405 6405 Checking of Shuttering,reinforcement & pouring concrete for pier shaft final lift at LP2 Viaduct Km 200+920 LHS 2-Dec-19 4:00 PM
6463 NMSCEW/P-IV/STR/2019/6406 6406 Checking of Shuttering,reinforcement & pouring concrete for top level of raft at LP-17 Viaduct Km 213+915 LHS 2-Dec-19 4:30 PM
6464 NMSCEW/P-IV/STR/2019/6407 6407 Checking of Shuttering,reinforcement & pouring concrete for pier cap at LP-13 Viaduct Km 202+190 Km 00+000 LHS 2-Dec-19 3:30 PM IPC-11 Approved AE
6465 NMSCEW/P-IV/STR/2019/6408 6408 Checking of Shuttering,reinforcement & pouring concrete for top level of raft at RP-3 Viaduct Km 213+915 Km 00+000 RHS 2-Dec-19 9:30 AM IPC-11 Approved AE
6466 NMSCEW/P-IV/STR/2019/6409 6409 Checking of Shuttering,reinforcement & pouring concrete for raft at RA-1 Viaduct Km 196+560 RHS 2-Dec-19 10:30 AM
Checking of side shuttering & pouring of concrete of girder no -121,122,123 & 124 at bed no
6467 NMSCEW/P-IV/STR/2019/6410 6410 Girder Km 200+200 LHS 2-Dec-19 8:00 AM
-06, Girder Type-2 at casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-133,134,135 & 136 at
6468 NMSCEW/P-IV/STR/2019/6411 6411 Girder Type-2 Km 200+200 LHS 2-Dec-19 8:00 AM
bed no -4 at casting yard camp -2, girder type-2
Checking for reinforcement at Girder no-133,134,135 & 136 at bed no -4 at casting yard
6469 NMSCEW/P-IV/STR/2019/6412 6412 Girder Type-2 Km 200+200 LHS 2-Dec-19 8:30 AM
camp -2, girder type-2
6470 NMSCEW/P-IV/STR/2019/6413 6413 Checking of level & pouring concrete PCC for LA-2 Viaduct Km 202+190 LHS 2-Dec-19 3:30 PM
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-1
6471 NMSCEW/P-IV/STR/2019/6414 6414 Box culvert Km 175+500 LHS 2-Dec-19 10:00 AM
I) 3x3 segment no.-22,23
II) 2x2 (2 to 4m) segment no.-245,246,247
III) 2x2 (0 to 2m) segment no.-487,458,459
6472 NMSCEW/P-IV/STR/2019/6415 6415 Checking layout ,excavation Level, & pouring concrete PCC of box culvert Box culvert Km 167+696 BHS 2-Dec-19 4:30 PM
6473 NMSCEW/P-IV/STR/2019/6416 6416 Checking of reinforcement, shuttering & concrete pouring of 2nd lift at median wall W1 PUP Km 193+880 3-Dec-19 2:00 PM
6474 NMSCEW/P-IV/STR/2019/6417 6417 Checking of reinforcement, shuttering & concrete pouring of wing wall W1 3rd Lift MNBR Km 203+409 LHS 3-Dec-19 11:00 AM
6475 NMSCEW/P-IV/STR/2019/6418 6418 Checking of reinforcement, shuttering & concrete pouring of wing wall W2 5th Lift MNBR Km 203+409 LHS 3-Dec-19 1:00 PM
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at camp-2 casting yard
6476 NMSCEW/P-IV/STR/2019/6419 6419 Box culvert Km 200+200 LHS 3-Dec-19 9:30 AM
I) 2x2 (4 to 6m) segment no.-94,95,96,97,98
6486 NMSCEW/P-IV/STR/2019/6429 6429 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 1st lift at pier P-3 VOP Km 181+420 RHS 3-Dec-19 4:15 PM
6487 NMSCEW/P-IV/STR/2019/6430 6430 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at wall A1 & A2 VUP Km 166+987 RHS 3-Dec-19 10:00 AM
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at U trough wall A1 &
6488 NMSCEW/P-IV/STR/2019/6431 6431 PUP Km 166+987 3-Dec-19 4:30 PM
A2
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-1
6489 NMSCEW/P-IV/STR/2019/6432 6432 Box culvert Km 175+500 LHS 3-Dec-19 10:00 AM
I) 3x3 (0 to 2m) segment no.-24,25,26,27
II) 2x2 (2 to 4m) segment no.-248,249,250,451,452,453
III) 2x2 (0 to 2m) segment no.-461,462,463,464,465,466,467,468
Checking for stressing and remove slagness of H.T. wires at Girder no-137,138,139,140 at bed
6490 NMSCEW/P-IV/STR/2019/6433 6433 Girder Km 200+200 LHS 3-Dec-19 9:00 AM
no -02, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no -137,138,139,140 at bed no -02, Girder Type-2 at casting
6491 NMSCEW/P-IV/STR/2019/6434 6434 Girder Km 200+200 LHS 3-Dec-19 9:30 AM
yard camp -2
6492 NMSCEW/P-IV/STR/2019/6435 6435 Checking layout , Level, & pouring concrete PCC (M-10) for RP-7 Viaduct Km 213+915 RHS 3-Dec-19 9:45 AM
6493 NMSCEW/P-IV/STR/2019/6436 6436 Checking of Shuttering,reinforcement, pouring concrete of LP17 raft Viaduct Km 213+915 Km 00+000 LHS 3-Dec-19 2:30 PM IPC-11 Approved AE
6494 NMSCEW/P-IV/STR/2019/6437 6437 Checking of Shuttering,reinforcement, pouring concrete of pier starter LP1 Viaduct Km 213+915 LHS 3-Dec-19 10:33 AM
6495 NMSCEW/P-IV/STR/2019/6438 6438 Checking of Shuttering,reinforcement, pouring concrete of pier starter LP2 Viaduct Km 213+915 LHS 3-Dec-19 11:10 AM
6496 NMSCEW/P-IV/STR/2019/6439 6439 Checking of Shuttering,reinforcement, pouring concrete of RP12 pier shaft final lift Viaduct Km 202+190 Km 00+000 RHS 3-Dec-19 3:30 PM IPC-11 Approved
6497 NMSCEW/P-IV/STR/2019/6440 6440 Checking of Shuttering,reinforcement, pouring concrete of LP9 padestal Viaduct Km 202+190 LHS 3-Dec-19 12:00 PM
6498 NMSCEW/P-IV/STR/2019/6441 6441 Checking of Shuttering,reinforcement, pouring concrete of RP11 pier cap Viaduct Km 202+190 RHS 3-Dec-19 12:30 PM
6499 NMSCEW/P-IV/STR/2019/6442 6442 Checking of Shuttering,reinforcement, pouring concrete of LP4 pier shaft final lift Viaduct Km 200+920 Km 00+000 LHS 3-Dec-19 10:00 AM IPC-11 Approved AE
6500 NMSCEW/P-IV/STR/2019/6443 6443 Checking of Shuttering,reinforcement, pouring concrete of LP3 pier shaft final lift Viaduct Km 200+920 Km 00+000 LHS 3-Dec-19 11:00 AM IPC-11 Approved
6501 NMSCEW/P-IV/STR/2019/6444 6444 Checking of Shuttering,reinforcement, pouring concrete of RA1 abutment column 1st lift Viaduct Km 200+920 RHS 3-Dec-19 4:00 PM
Checking of Shuttering,reinforcement & pouring concrete (M-35) for abutment shaft RA1 3rd
6502 NMSCEW/P-IV/STR/2019/6445 6445 MJB Km 205+610 RHS 4-Dec-19 10:00 AM
lift
6503 NMSCEW/P-IV/STR/2019/6446 6446 Checking layout ,Level & Laying concrete (M-15) for PCC at pier LP-2 MJB Km 205+610 LHS 4-Dec-19 5:00 PM
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at camp-2 casting yard
6504 NMSCEW/P-IV/STR/2019/6447 6447 Box culvert Km 200+200 LHS 4-Dec-19 9:45 AM
I) 3x3 (2 to 4m) segment no.-110,111,112,113,114,115,116
6505 NMSCEW/P-IV/STR/2019/6448 6448 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at median wall PUP Km 165+790 RHS 4-Dec-19 4:30 PM
6506 NMSCEW/P-IV/STR/2019/6449 6449 Checking of bearings & grouting at RP-8 Viaduct Km 169+800 RHS 4-Dec-19 12:00 PM
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
6507 NMSCEW/P-IV/STR/2019/6450 6450 Girder Km 200+200 LHS 4-Dec-19 8:00 AM
137,138,139,140 at bed no -02, Girder Type-02
6508 NMSCEW/P-IV/STR/2019/6451 6451 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-08 Viaduct Km 195+900 LHS 4-Dec-19 11:30 AM IPC-14
6509 NMSCEW/P-IV/STR/2019/6452 6452 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP-04 Viaduct Km 196+560 Km 00+000 RHS 4-Dec-19 4:30 PM IPC-11 Approved AE
6510 NMSCEW/P-IV/STR/2019/6453 6453 Checking of Shuttering,reinforcement & pouring concrete for raft at RA-01 Viaduct Km 196+560 Km 00+000 RHS 4-Dec-19 9:30 AM IPC-11 Approved AE
6511 NMSCEW/P-IV/STR/2019/6454 6454 Checking layout ,Level & Laying concrete for PCC at LA-2 Viaduct Km 202+190 LHS 4-Dec-19 3:30 PM
6512 NMSCEW/P-IV/STR/2019/6455 6455 Checking layout ,Level & Laying concrete for PCC at LP-18 Viaduct Km 213+915 Km 00+000 LHS 4-Dec-19 9:00 AM IPC-11 Approved
6513 NMSCEW/P-IV/STR/2019/6456 6456 Checking layout ,Level & Laying concrete for PCC at LP-12 Viaduct Km 213+915 LHS 4-Dec-19 10:30 AM
6514 NMSCEW/P-IV/STR/2019/6457 6457 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-02 Viaduct Km 200+920 LHS 4-Dec-19 4:00 PM
HDPE PIPE
6515 NMSCEW/P-IV/STR/2019/6458 6458 Inspection of suplying & laying HDPE pipe line for fermers water supply through uyility. Km 170+830 4-Dec-19 4:00 PM SPOT RFI
LAYING
6516 NMSCEW/P-IV/STR/2019/6459 6459 Checking of Shuttering,reinforcement & pouring concrete for raft with bottom haunch Box culvert Km 180+180 RHS 5-Dec-19 10:00 AM
Checking for stressing and remove slagness of H.T. wires at Girder no-125,126,127,128 at bed
6517 NMSCEW/P-IV/STR/2019/6460 6460 Girder Km 200+200 LHS 5-Dec-19 5:00 PM
no -07, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no -125,126,127,128 at bed no -07, Girder Type-1 at casting
6518 NMSCEW/P-IV/STR/2019/6461 6461 Girder Km 200+200 LHS 5-Dec-19 5:30 PM
yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-141,142,143,144 at bed
6519 NMSCEW/P-IV/STR/2019/6462 6462 Girder Km 200+200 LHS 5-Dec-19 5:30 PM
no -01, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no -141,142,143,144 at bed no -01, Girder Type-2 at casting
6520 NMSCEW/P-IV/STR/2019/6463 6463 Girder Km 200+200 LHS 5-Dec-19 6:00 PM
yard camp -2
6521 NMSCEW/P-IV/STR/2019/6464 6464 Checking of Shuttering,reinforcement, pouring concrete of RA1 abutment column 1st lift Viaduct Km 200+920 RHS 5-Dec-19 10:00 AM
6522 NMSCEW/P-IV/STR/2019/6465 6465 Checking of Shuttering,reinforcement, pouring concrete for raft at LP-11 Viaduct Km 213+915 Km 00+000 LHS 5-Dec-19 3:30 PM IPC-11 Approved AE
6523 NMSCEW/P-IV/STR/2019/6466 6466 Checking of Shuttering,reinforcement, pouring concrete for pier starter at RP-3 Viaduct Km 213+915 RHS 5-Dec-19 9:30 AM
6524 NMSCEW/P-IV/STR/2019/6467 6467 Checking of Shuttering,reinforcement, pouring concrete for padestal at LP-9 & LP-10 Viaduct Km 202+190 LHS 5-Dec-19 12:00 PM
6525 NMSCEW/P-IV/STR/2019/6468 6468 Checking of Shuttering,reinforcement, pouring concrete for pier cap at RP-11 Viaduct Km 202+190 Km 00+000 RHS 5-Dec-19 10:00 AM IPC-11 Approved AE
6526 NMSCEW/P-IV/STR/2019/6469 6469 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall A1 VUP Km 187+113 5-Dec-19 5:00 PM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 2nd lift at retaining wall
6527 NMSCEW/P-IV/STR/2019/6470 6470 PUP Km 186+000 LHS 5-Dec-19 8:00 AM
A1
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 2nd lift at retaining wall
6528 NMSCEW/P-IV/STR/2019/6471 6471 PUP Km 186+000 RHS 5-Dec-19 8:15 AM
A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 2nd lift at retaining wall
6529 NMSCEW/P-IV/STR/2019/6472 6472 PUP Km 185+235 LHS 5-Dec-19 9:00 AM
A1
6530 NMSCEW/P-IV/STR/2019/6473 6473 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 2nd lift at pier P-3 VOP Km 181+420 LHS 5-Dec-19 11:00 AM
6531 NMSCEW/P-IV/STR/2019/6474 6474 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 2nd lift at pier P-3 VOP Km 181+420 RHS 5-Dec-19 11:30 AM
6532 NMSCEW/P-IV/STR/2019/6475 6475 Checking of reinforcement for intermediate diaphragm at LP-5 & LP-6 Viaduct Km 169+800 LHS 5-Dec-19 2:00 PM spot rfi
6533 NMSCEW/P-IV/STR/2019/6476 6476 Checking of reinforcement for intermediate diaphragm at LP-4 & LP-7 Viaduct Km 169+800 LHS 5-Dec-19 2:30 PM spot rfi
6534 NMSCEW/P-IV/STR/2019/6477 6477 Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at wall A1 MNB Km 181+700 Km 00+000 LHS 5-Dec-19 12:45 PM IPC-11 DONE AE
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at camp-2 casting yard
6535 NMSCEW/P-IV/STR/2019/6478 6478 Box culvert Km 200+200 LHS 6-Dec-19 9:30 AM
I) 3x3 (2 to 4m) segment no.-117,118,119,120,121,122.123
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at retaining wall A1 &
6536 NMSCEW/P-IV/STR/2019/6479 6479 PUP Km 165+790 RHS 6-Dec-19 4:30 PM
A2
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at median wall A1 &
6537 NMSCEW/P-IV/STR/2019/6480 6480 VUP Km 166+987 6-Dec-19 2:00 PM
A2
Checking of reinforcement,shuttering and Pouring concrete(M-35) for 6th lift at median wall
6538 NMSCEW/P-IV/STR/2019/6481 6481 VUP Km 179+983 BHS 6-Dec-19 11:00 AM
A2
6539 NMSCEW/P-IV/STR/2019/6482 6482 Checking of bearings & grouting at RP-5 pedustal Viaduct Km 169+800 RHS 6-Dec-19 3:00 PM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 1st lift at retaining wall
6540 NMSCEW/P-IV/STR/2019/6483 6483 PUP Km 183+290 RHS 6-Dec-19 9:00 AM
A1
Checking of reinforcement,shuttering and Pouring concrete(M-35) for 3rd lift at wall A1 &
6541 NMSCEW/P-IV/STR/2019/6484 6484 MNB Km 01+980 6-Dec-19 10:00 AM
A2 Loop-B
6542 NMSCEW/P-IV/STR/2019/6485 6485 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 1st lift at pier P-1 VOP Km 181+420 RHS 6-Dec-19 12:00 PM
Checking for stressing and remove slagness of H.T. wires at Girder no-129,130,131,132 at bed
6543 NMSCEW/P-IV/STR/2019/6486 6486 Girder Km 200+200 LHS 6-Dec-19 2:00 PM
no -05, Girder Type-1 at casting yard camp -2
Checking of reinforcement Girder no -129,130,131,132 at bed no -05, Girder Type-1 at casting
6544 NMSCEW/P-IV/STR/2019/6487 6487 Girder Km 200+200 LHS 6-Dec-19 2:30 PM
yard camp -2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
6545 NMSCEW/P-IV/STR/2019/6488 6488 Girder Km 200+200 LHS 6-Dec-19 6:30 PM
125,126,127,128 at bed no -07, Girder Type-01
6546 NMSCEW/P-IV/STR/2019/6489 6489 Checking layout ,Level & Laying concrete for PCC at LP-12 Viaduct Km 213+915 Km 00+000 LHS 6-Dec-19 9:35 AM IPC-11 Approved
6547 NMSCEW/P-IV/STR/2019/6490 6490 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-02 Viaduct Km 200+920 Km 00+000 LHS 6-Dec-19 11:00 AM IPC-11 Approved
6548 NMSCEW/P-IV/STR/2019/6491 6491 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-03 Viaduct Km 200+920 RHS 6-Dec-19 4:00 PM
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at retaining wall A1 &
6549 NMSCEW/P-IV/STR/2019/6492 6492 PUP Km 165+790 RHS 7-Dec-19 4:30 PM
A2
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at U type median wall
6550 NMSCEW/P-IV/STR/2019/6493 6493 PUP Km 165+790 7-Dec-19 5:30 PM
A1 & A2
Checking of reinforcement,shuttering and Pouring concrete for raft with bottom haunch at U
6551 NMSCEW/P-IV/STR/2019/6494 6494 PUP Km 164+380 7-Dec-19 6:00 PM
type median wall A1 & A2
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at U type median wall
6552 NMSCEW/P-IV/STR/2019/6495 6495 VUP Km 176+614 7-Dec-19 11:30 AM
A1
Checking of reinforcement,shuttering and Pouring concrete for raft with bottom haunch at U
6553 NMSCEW/P-IV/STR/2019/6496 6496 LVUP Km 178+323 7-Dec-19 4:00 PM
type median wall A1 & A2
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-1
6554 NMSCEW/P-IV/STR/2019/6497 6497 Box culvert Km 175+500 LHS 7-Dec-19 9:30 AM
I) 2x2 (2 to 4m) segment no.-254, 255, 256, 457, 458, 459
II) 2x2 (0 to 2m) segment no.-469,470, 471, 472, 473, 474, 475, 476
Checking of reinforcement,shuttering and Pouring concrete(M-35) for 3rd lift at wall A1 &
6555 NMSCEW/P-IV/STR/2019/6498 6498 MNB( Loop-C) Km 01+980 7-Dec-19 8:00 AM
A2 Loop-C
6556 NMSCEW/P-IV/STR/2019/6499 6499 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 1st lift at pier P-1 VOP Km 181+420 RHS 7-Dec-19 10:00 AM
6557 NMSCEW/P-IV/STR/2019/6500 6500 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 3rd lift at pier P-3 VOP Km 181+420 LHS 7-Dec-19 10:30 AM
6558 NMSCEW/P-IV/STR/2019/6501 6501 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 3rd lift at pier P-3 VOP Km 181+420 RHS 7-Dec-19 11:45 AM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 1st lift at retaining wall
6559 NMSCEW/P-IV/STR/2019/6502 6502 PUP Km 185+235 LHS 7-Dec-19 2:00 PM
A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at retaining wall
6560 NMSCEW/P-IV/STR/2019/6503 6503 PUP Km 185+235 LHS 7-Dec-19 3:00 PM
A1
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 2nd lift at retaining wall
6561 NMSCEW/P-IV/STR/2019/6504 6504 PUP Km 183+290 RHS 7-Dec-19 12:00 PM
A1
6562 NMSCEW/P-IV/STR/2019/6505 6505 Checking layout ,level, & laying concrete PCC(M-15) for Pier P-2 VOP Km 181+420 RHS 7-Dec-19 11:16 AM
6563 NMSCEW/P-IV/STR/2019/6506 6506 Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at wall A1 & A2 VUP Km 166+987 RHS 7-Dec-19 12:10 PM
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
6564 NMSCEW/P-IV/STR/2019/6507 6507 Girder Km 200+200 LHS 7-Dec-19 6:30 PM
129,130,131,132 at bed no -05, Girder Type-01
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
6565 NMSCEW/P-IV/STR/2019/6508 6508 Girder Km 200+200 LHS 7-Dec-19 11:30 AM
141,142,143,144 at bed no -01, Girder Type-02
6566 NMSCEW/P-IV/STR/2019/6509 6509 Checking layout ,level, & laying concrete for PCC at LA-2 Viaduct Km 213+915 LHS 7-Dec-19 9:45 AM
6567 NMSCEW/P-IV/STR/2019/6510 6510 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-11 Viaduct Km 202+190 Km 00+000 LHS 7-Dec-19 3:00 PM IPC-11 Approved
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 2nd lift at retaining wall
6568 NMSCEW/P-IV/STR/2019/6511 6511 PUP Km 185+235 LHS 8-Dec-19 9:00 AM
A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 4th lift at retaining wall
6569 NMSCEW/P-IV/STR/2019/6512 6512 PUP Km 185+235 LHS 8-Dec-19 11:00 AM
A1
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at median wall
6570 NMSCEW/P-IV/STR/2019/6513 6513 PUP Km 186+000 8-Dec-19 12:00 PM
A1 & A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at retaining wall
6571 NMSCEW/P-IV/STR/2019/6514 6514 PUP Km 186+000 LHS 8-Dec-19 2:30 PM
A1
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at retaining wall
6572 NMSCEW/P-IV/STR/2019/6515 6515 PUP Km 186+000 RHS 8-Dec-19 4:00 PM
A2
Checking of reinforcement,shuttering and Pouring concrete(M-35) for 4th lift at wall A1 &
6573 NMSCEW/P-IV/STR/2019/6516 6516 MNB( Loop-B) Km 01+980 8-Dec-19 10:00 AM
A2 Loop-B
6574 NMSCEW/P-IV/STR/2019/6517 6517 Checking layout ,excavation Level, & laying concrete PCC (M-10) for retaning wall A1 & A2 PUP Km 165+380 RHS 8-Dec-19 9:15 AM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at median wall
6575 NMSCEW/P-IV/STR/2019/6518 6518 VUP Km 166+987 8-Dec-19 2:15 PM
A1 & A2
6576 NMSCEW/P-IV/STR/2019/6519 6519 Checking of bearings & grouting at RA-2 Viaduct Km 169+800 RHS 8-Dec-19 10:15 AM
6577 NMSCEW/P-IV/STR/2019/6520 6520 Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-03 Viaduct Km 196+560 Km 00+000 LHS 8-Dec-19 10:35 AM IPC-11 Approved AE
6578 NMSCEW/P-IV/STR/2019/6521 6521 Checking of Shuttering,reinforcement, pouring concrete for pier cap at RP-10 Viaduct Km 202+190 RHS 8-Dec-19 12:20 PM
6579 NMSCEW/P-IV/STR/2019/6522 6522 Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-10 Viaduct Km 202+190 LHS 8-Dec-19 11:00 AM
6580 NMSCEW/P-IV/STR/2019/6523 6523 Checking layout ,level, & laying concrete for PCC at RA-2 Viaduct Km 213+915 RHS 8-Dec-19 9:25 AM
6581 NMSCEW/P-IV/STR/2019/6524 6524 Checking of Shuttering,reinforcement & pouring concrete for raft at LP-15 Viaduct Km 213+915 Km 00+000 LHS 8-Dec-19 11:30 AM IPC-11 Approved AE
6582 NMSCEW/P-IV/STR/2019/6525 6525 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-03 Viaduct Km 200+920 RHS 8-Dec-19 10:20 AM
Checking of Shuttering,reinforcement & pouring concrete for cross girder between LP-13 to
6583 NMSCEW/P-IV/STR/2019/6526 6526 Viaduct Km 169+800 LHS 8-Dec-19 12:25 PM
LA-2
Checking of layout,level,structural excavation & laying concrete PCC at retaining wall A1 &
6584 NMSCEW/P-IV/STR/2019/6527 6527 PUP Km 164+380 RHS 9-Dec-19 9:00 AM
A2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
6585 NMSCEW/P-IV/STR/2019/6528 6528 Girder Km 200+200 LHS 9-Dec-19 8:00 AM
133,134,135,136 at bed no -08, Girder Type-01
Checking for stressing and remove slagness of H.T. wires at Girder no-145,146,147,148 at bed
6586 NMSCEW/P-IV/STR/2019/6529 6529 Girder Km 200+200 LHS 9-Dec-19 11:00 AM
no -03, Girder Type-2 at casting yard camp -2
Checking of reinforcement Girder no -145,146,147,148 at bed no -03, Girder Type-2 at casting
6587 NMSCEW/P-IV/STR/2019/6530 6530 Girder Km 200+200 LHS 9-Dec-19 11:30 AM
yard camp -2
6588 NMSCEW/P-IV/STR/2019/6531 6531 Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-12 Viaduct Km 202+190 LHS 9-Dec-19 3:30 PM
6589 NMSCEW/P-IV/STR/2019/6532 6532 Checking layout ,level, & laying concrete for PCC at RP-11 Viaduct Km 213+915 RHS 9-Dec-19 10:00 AM
6590 NMSCEW/P-IV/STR/2019/6533 6533 Checking of Shuttering,reinforcement & pouring concrete for raft at RP-17 Viaduct Km 213+915 Km 00+000 RHS 9-Dec-19 3:30 PM IPC-11 Approved AE
6591 NMSCEW/P-IV/STR/2019/6534 6534 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-17 Viaduct Km 213+915 LHS 9-Dec-19 9:00 AM
6592 NMSCEW/P-IV/STR/2019/6535 6535 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-11 Viaduct Km 213+915 LHS 9-Dec-19 10:30 AM
6593 NMSCEW/P-IV/STR/2019/6536 6536 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-04 Viaduct Km 200+920 RHS 9-Dec-19 10:00 AM
Checking of Shuttering,reinforcement & pouring concrete for cross girder between LP-12 to
6594 NMSCEW/P-IV/STR/2019/6537 6537 Viaduct Km 169+800 LHS 9-Dec-19 4:00 PM
LP-13
6595 NMSCEW/P-IV/STR/2019/6538 6538 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 1st lift at wall A1 VUP Km 187+113 9-Dec-19 8:00 AM
6596 NMSCEW/P-IV/STR/2019/6539 6539 Checking layout ,Level,structural excavation for 3x3 box culvert Box culvert Km 183+326 BHS 9-Dec-19 10:00 AM
6597 NMSCEW/P-IV/STR/2019/6540 6540 Checking layout ,excavation Level, & laying concrete PCC for retaning wall A1 & A2 PUP Km 165+790 LHS 9-Dec-19 4:00 PM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 2nd lift at median wall
6598 NMSCEW/P-IV/STR/2019/6541 6541 PUP Km 177+810 9-Dec-19 2:00 PM
A1 & A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 6th lift at median wall
6599 NMSCEW/P-IV/STR/2019/6542 6542 VUP Km 179+983 9-Dec-19 11:00 AM
A1
6600 NMSCEW/P-IV/STR/2019/6543 6543 Checking of Shuttering,reinforcement & pouring concrete for raft at retaining wall A1 & A2 PUP Km 164+380 RHS 9-Dec-19 6:00 PM
6601 NMSCEW/P-IV/STR/2019/6544 6544 Checking of Shuttering,reinforcement & pouring concrete for 1st lift at retaining wall W1 PUP Km 193+880 LHS 9-Dec-19 9:00 AM
6602 NMSCEW/P-IV/STR/2019/6545 6545 Checking of Shuttering,reinforcement & pouring concrete for 3rd lift at retaining wall W1 PUP Km 193+880 RHS 9-Dec-19 9:30 AM
6603 NMSCEW/P-IV/STR/2019/6546 6546 Checking of Shuttering,reinforcement & pouring concrete for 3rd lift at median wall W1 PUP Km 193+880 9-Dec-19 10:08 AM
6604 NMSCEW/P-IV/STR/2019/6547 6547 Checking of Shuttering,reinforcement & pouring concrete for 4th lift at median wall W1 & W2 PUP Km 199+060 9-Dec-19 11:00 AM
Checking of reinforcement, shuttering & pouring concrete(M-45) for abutment shaft final lift
6605 NMSCEW/P-IV/STR/2019/6548 6548 MJB Km 205+610 LHS 9-Dec-19 10:15 AM
at LA-01
Checking of layout,level,structural excavation & laying concrete PCC at retaining wall A1 &
6606 NMSCEW/P-IV/STR/2019/6549 6549 PUP Km 164+380 LHS 9-Dec-19 2:15 PM
A2
Checking for stressing and remove slagness of H.T. wires at Girder no-133,134,135,136 at bed
6607 NMSCEW/P-IV/STR/2019/6550 6550 Girder Km 200+200 LHS 9-Dec-19 8:45 AM
no -08, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -133,134,135,136 at bed no -08, Girder Type-01 at
6608 NMSCEW/P-IV/STR/2019/6551 6551 Girder Km 200+200 LHS 9-Dec-19 9:30 AM
casting yard camp -2
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at camp-2 casting yard
6609 NMSCEW/P-IV/STR/2019/6552 6552 Box culvert Km 200+200 LHS 10-Dec-19 9:30 AM
I) 3x3 (2 to 4m) segment no.-124,125,126,127,128,129,130
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at retaining wall A1 &
6610 NMSCEW/P-IV/STR/2019/6553 6553 PUP Km 165+790 RHS 10-Dec-19 5:00 PM
A2
6611 NMSCEW/P-IV/STR/2019/6554 6554 Checking of reinforcement,shuttering and Pouring concrete for raft at retaining wall A1 & A2 PUP Km 165+790 LHS 10-Dec-19 4:00 PM
6612 NMSCEW/P-IV/STR/2019/6555 6555 Checking of reinforcement,shuttering and Pouring concrete(M-35) for raft at LA-1 MNB Km 174+570 LHS 10-Dec-19 2:30 PM
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-1
6613 NMSCEW/P-IV/STR/2019/6556 6556 Box culvert Km 175+500 LHS 10-Dec-19 10:00 AM
I) 2x2 (2 to 4m) segment no.-260, 261, 262, 263, 264, 265, 266, 267, 268, 269, 270
II) 2x2 (0 to 2m) segment no.-477,478, 479, 480, 481, 482
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
6614 NMSCEW/P-IV/STR/2019/6557 6557 Girder Km 200+200 LHS 10-Dec-19 6:30 PM
133,134,135,136 at bed no -08, Girder Type-01
Checking for stressing and remove slagness of H.T. wires at Girder no-149,150,151,152 at bed
6615 NMSCEW/P-IV/STR/2019/6558 6558 Girder Km 200+200 LHS 10-Dec-19 2:00 PM
no -04, Girder Type-02 at casting yard camp -2
Checking of reinforcement Girder no -149,150,151,152 at bed no -04, Girder Type-02 at
6616 NMSCEW/P-IV/STR/2019/6559 6559 Girder Km 200+200 LHS 10-Dec-19 2:30 PM
casting yard camp -2
6617 NMSCEW/P-IV/STR/2019/6560 6560 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-02 Viaduct Km 196+560 Km 00+000 LHS 10-Dec-19 4:30 PM IPC-11 Approved
6618 NMSCEW/P-IV/STR/2019/6561 6561 Checking of Shuttering,reinforcement, pouring concrete for padestal at RP-10 Viaduct Km 196+560 RHS 10-Dec-19 2:45 PM
6619 NMSCEW/P-IV/STR/2019/6562 6562 Checking of Shuttering,reinforcement, pouring concrete for padestal at RA-02 Viaduct Km 196+560 RHS 10-Dec-19 3:10 PM
6620 NMSCEW/P-IV/STR/2019/6563 6563 Checking of Shuttering,reinforcement, pouring concrete for pier cap at RP-10 Viaduct Km 202+190 Km 00+000 RHS 10-Dec-19 2:20 PM IPC-11 Approved AE
6621 NMSCEW/P-IV/STR/2019/6564 6564 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 3rd lift at pier P-3 VOP Km 181+420 LHS 10-Dec-19 9:45 AM
6622 NMSCEW/P-IV/STR/2019/6565 6565 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 4th lift at pier P-3 VOP Km 181+420 RHS 10-Dec-19 10:10 AM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 4th lift at median wall
6623 NMSCEW/P-IV/STR/2019/6566 6566 PUP Km 184+190 10-Dec-19 10:30 AM
A1 & A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for final lift at retaining
6624 NMSCEW/P-IV/STR/2019/6567 6567 PUP Km 184+190 LHS 10-Dec-19 11:10 AM
wall A1
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at retaining wall
6625 NMSCEW/P-IV/STR/2019/6568 6568 PUP Km 183+290 RHS 10-Dec-19 11:50 AM
A1
6626 NMSCEW/P-IV/STR/2019/6569 6569 Checking of reinforcement,shuttering and Pouring concrete(M-30) for 1st lift at wall A2 MNB Km 181+700 RHS 10-Dec-19 12:35 PM
6627 NMSCEW/P-IV/STR/2019/6570 6570 Checking of reinforcement,shuttering and Pouring concrete(M-30) for 4th lift at wall A2 PUP Km 185+235 LHS 10-Dec-19 2:40 PM
6628 NMSCEW/P-IV/STR/2019/6571 6571 Checking of Shuttering,reinforcement, pouring concrete for padestal at LP-09 Viaduct Km 202+190 LHS 10-Dec-19 10:05 AM
6629 NMSCEW/P-IV/STR/2019/6572 6572 Checking of Shuttering,reinforcement, pouring concrete for padestal at LP-10 Viaduct Km 202+190 LHS 10-Dec-19 11:11 AM
6630 NMSCEW/P-IV/STR/2019/6573 6573 Checking layout ,level, & laying concrete(M-15) for PCC at median raft abutment A1 MJB Km 205+610 10-Dec-19
Checking of reinforcement,shuttering and Pouring concrete(M-30) for raft at retaining wall W1
6631 NMSCEW/P-IV/STR/2019/6574 6574 PUP Km 191+740 LHS 10-Dec-19 9:30 AM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 4th lift at median wall
6633 NMSCEW/P-IV/STR/2019/6576 6576 PUP Km 193+880 10-Dec-19 11:00 AM
W1
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at retaining wall
6634 NMSCEW/P-IV/STR/2019/6577 6577 PUP Km 191+740 RHS 10-Dec-19 2:00 PM
W1
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 1st lift at retaining wall
6635 NMSCEW/P-IV/STR/2019/6578 6578 Box culvert Km 193+940 RHS 10-Dec-19 3:00 PM
W1
6636 NMSCEW/P-IV/STR/2019/6579 6579 Checking of reinforcement,shuttering and Pouring concrete for raft at retaining wall W2 PUP Km 191+740 LHS 11-Dec-19 10:30 AM
6637 NMSCEW/P-IV/STR/2019/6580 6580 Checking of reinforcement,shuttering and Pouring concrete for raft at retaining wall W2 PUP Km 193+880 LHS 11-Dec-19 1:00 PM
6638 NMSCEW/P-IV/STR/2019/6581 6581 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at side wall W1 PUP Km 206+985 Km 00+000 RHS 11-Dec-19 9:00 AM IPC-11 Approved
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall W1(Main
6639 NMSCEW/P-IV/STR/2019/6582 6582 Box culvert Km 206+843 LHS 11-Dec-19 10:00 AM
carriageway)
Checking of Shuttering,reinforcement and Pouring concrete for RE WALL PANEL precast
TYPE -A
6640 NMSCEW/P-IV/STR/2019/6583 6583 205 NOS,TYPE B- 60 NOS, TYPE -Sta 12 NOS, TYPE -Stb 12 NOS, TYPE -Stc 12 NOS, RE Wall Panel Km 200+200 LHS 11-Dec-19 4:00 PM
TYPE -Std 12 NOS, TYPE -Lta 13 NOS, TYPE -Ltd 18 NOS, at RE panel precast yard camp
2
6641 NMSCEW/P-IV/STR/2019/6584 6584 Checking of reinforcement,shuttering and Pouring concrete for 4th lift at RA1 MJB Km 205+610 RHS 11-Dec-19 11:00 AM
6642 NMSCEW/P-IV/STR/2019/6585 6585 Checking of layout,level,structural excavation & laying concrete PCC(M-15) at RA2 MNB Km 174+570 RHS 11-Dec-19 2:00 PM
6643 NMSCEW/P-IV/STR/2019/6586 6586 Checking of layout,level,structural excavation & laying concrete PCC(M-15) at LA2 MNB Km 174+570 LHS 11-Dec-19 2:30 PM
6644 NMSCEW/P-IV/STR/2019/6587 6587 Checking of reinforcement,shuttering and Pouring concrete(M-30) for raft at retaining wall A2 PUP Km 177+810 11-Dec-19 3:00 PM
Checking of Shuttering,reinforcement & pouring concrete(M-45) for cross girder RA-2 to RP-
6645 NMSCEW/P-IV/STR/2019/6588 6588 Viaduct Km 169+800 RHS 11-Dec-19 5:00 PM
13
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at median wall A1 &
6646 NMSCEW/P-IV/STR/2019/6589 6589 VUP Km 166+987 11-Dec-19 2:00 PM
A2
6647 NMSCEW/P-IV/STR/2019/6590 6590 Checking layout ,level, & laying concrete for PCC(M-10) for 3x3 box culvert Box culvert Km 183+326 BHS 11-Dec-19 10:00 AM
6648 NMSCEW/P-IV/STR/2019/6591 6591 Checking of layout,level,structural excavation & laying concrete PCC at median wall LVUP Km 169+291 11-Dec-19 12:00 PM
6649 NMSCEW/P-IV/STR/2019/6592 6592 Checking of layout,level for bearing & grouting at RP-10 Viaduct Km 169+800 RHS 11-Dec-19 5:15 PM
Checking for stressing and remove slagness of H.T. wires at Girder no-145,146,147,148 at bed
6650 NMSCEW/P-IV/STR/2019/6593 6593 Girder Km 200+200 LHS 11-Dec-19 11:00 AM
no -03, Girder Type-02 at casting yard camp -2
Checking of reinforcement Girder no -145,146,147,148 at bed no -03, Girder Type-02 at
6651 NMSCEW/P-IV/STR/2019/6594 6594 Girder Km 200+200 LHS 11-Dec-19 11:30 AM
casting yard camp -2
6652 NMSCEW/P-IV/STR/2019/6595 6595 Checking of Shuttering,reinforcement, pouring concrete for abutment cap at LA-2 Viaduct Km 195+900 LHS 11-Dec-19 3:00 PM
6653 NMSCEW/P-IV/STR/2019/6596 6596 Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-12 Viaduct Km 202+190 Km 00+000 LHS 11-Dec-19 3:30 PM IPC-11 Approved
6654 NMSCEW/P-IV/STR/2019/6597 6597 Checking layout ,level, & laying concrete for PCC at RP-15 Viaduct Km 213+915 Km 00+000 RHS 11-Dec-19 9:20 AM IPC-11 Approved AE
6655 NMSCEW/P-IV/STR/2019/6598 6598 Checking layout ,level, & laying concrete for PCC at RP-11 Viaduct Km 213+915 RHS 11-Dec-19 11:40 AM
6656 NMSCEW/P-IV/STR/2019/6599 6599 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-02 Viaduct Km 213+915 LHS 11-Dec-19 4:00 PM
6657 NMSCEW/P-IV/STR/2019/6600 6600 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-01 Viaduct Km 200+920 RHS 11-Dec-19 4:25 PM
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at camp-2 casting yard
6658 NMSCEW/P-IV/STR/2019/6601 6601 Box culvert Km 200+200 LHS 12-Dec-19 9:30 AM
I) 3x3 (2 to 4m) segment no.-131,132,133,134,135,136,137
6659 NMSCEW/P-IV/STR/2019/6602 6602 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at median wall A1 & A2 PUP Km 164+380 12-Dec-19 9:00 AM
6660 NMSCEW/P-IV/STR/2019/6603 6603 Checking of reinforcement,shuttering and Pouring concrete for raft at LA1 MNB Km 174+570 LHS 12-Dec-19 11:00 AM
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at median wall A1 &
6661 NMSCEW/P-IV/STR/2019/6604 6604 PUP Km 177+810 12-Dec-19 10:00 AM
A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for raft at retaining wall A2
6662 NMSCEW/P-IV/STR/2019/6605 6605 PUP Km 189+000 RHS 12-Dec-19 9:10 AM
6664 NMSCEW/P-IV/STR/2019/6607 6607 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 2nd lift at wall A1 VUP Km 187+113 12-Dec-19 2:00 PM
6665 NMSCEW/P-IV/STR/2019/6608 6608 Checking of layout,level,structural excavation & laying concrete PCC at retaining wall A2 PUP Km 190+650 RHS 12-Dec-19 8:30 AM
6666 NMSCEW/P-IV/STR/2019/6609 6609 Checking of layout,level,structural excavation & laying concrete PCC at retaining wall A2 PUP Km 190+650 LHS 12-Dec-19 10:45 AM
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at retaining wall A1 &
6667 NMSCEW/P-IV/STR/2019/6610 6610 PUP Km 165+790 LHS 12-Dec-19 6:00 PM
A2
6668 NMSCEW/P-IV/STR/2019/6611 6611 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 4th lift at pier P-3 VOP Km 181+420 BHS 12-Dec-19 9:20 AM
6669 NMSCEW/P-IV/STR/2019/6612 6612 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 1st lift at pier P-1 VOP Km 181+420 LHS 12-Dec-19 10:20 AM
6670 NMSCEW/P-IV/STR/2019/6613 6613 Checking of reinforcement,shuttering and Pouring concrete(M-30) for 1st lift at wall A1 MNB Km 181+700 RHS 12-Dec-19 11:30 AM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 4th lift at median wall
6673 NMSCEW/P-IV/STR/2019/6616 6616 PUP Km 187+190 12-Dec-19 2:40 PM
A1 & A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 4th lift at median wall
6674 NMSCEW/P-IV/STR/2019/6617 6617 PUP Km 186+000 12-Dec-19 3:00 PM
A1 & A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 4th lift at retaining wall
6675 NMSCEW/P-IV/STR/2019/6618 6618 PUP Km 186+000 LHS 12-Dec-19 4:00 PM
A1
Checking for stressing and remove slagness of H.T. wires at Girder no-137,138,139,140 at bed
6676 NMSCEW/P-IV/STR/2019/6619 6619 Girder Km 200+200 LHS 12-Dec-19 8:00 AM
no -06, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -137,138,139,140 at bed no -06, Girder Type-01 at
6677 NMSCEW/P-IV/STR/2019/6620 6620 Girder Km 200+200 LHS 12-Dec-19 8:30 AM
casting yard camp -2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
6678 NMSCEW/P-IV/STR/2019/6621 6621 Girder Km 200+200 LHS 12-Dec-19 11:35 AM
145,146,147,148 at bed no -03, Girder Type-02
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
6679 NMSCEW/P-IV/STR/2019/6622 6622 Girder Km 200+200 LHS 12-Dec-19 2:30 PM
149,150,151,152 at bed no -04, Girder Type-02
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
6680 NMSCEW/P-IV/STR/2019/6623 6623 Girder Km 200+200 LHS 12-Dec-19 7:00 PM
137,138,139,140 at bed no -06, Girder Type-01
6681 NMSCEW/P-IV/STR/2019/6624 6624 Checking of Shuttering,reinforcement, pouring concrete for pier cap at RP-5 Viaduct Km 196+560 RHS 12-Dec-19 2:50 PM
6682 NMSCEW/P-IV/STR/2019/6625 6625 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-4 Viaduct Km 196+560 RHS 12-Dec-19 3:40 PM
6683 NMSCEW/P-IV/STR/2019/6626 6626 Checking layout ,level, & laying concrete for PCC at RA-2 Viaduct Km 213+915 RHS 12-Dec-19 3:15 PM
6684 NMSCEW/P-IV/STR/2019/6627 6627 Checking of Shuttering,reinforcement & pouring concrete for raft at LP-13 Viaduct Km 213+915 Km 00+000 LHS 12-Dec-19 4:16 PM IPC-11 Approved AE
6685 NMSCEW/P-IV/STR/2019/6628 6628 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-11 Viaduct Km 213+915 LHS 12-Dec-19 10:21 AM
6686 NMSCEW/P-IV/STR/2019/6629 6629 Checking of Shuttering,reinforcement & pouring concrete for pier starter at RP-17 Viaduct Km 213+915 RHS 12-Dec-19 11:05 AM
Checking of reinforcement,shuttering and Pouring concrete for raft with bottom haunch at
6687 NMSCEW/P-IV/STR/2019/6630 6630 Box culvert Km 162+832 BHS 12-Dec-19 5:00 PM
wall A1 & A2
6688 NMSCEW/P-IV/STR/2019/6631 6631 Checking of fixing geocomposite sheet and 150 mm perofated pipe for 2x2 Utility duct Utility duct Km 163+830 13-Dec-19 8:00 AM
6689 NMSCEW/P-IV/STR/2019/6632 6632 Checking of fixing geocomposite sheet and 150 mm perofated pipe Utility duct Km 171+570 13-Dec-19 8:15 AM
6690 NMSCEW/P-IV/STR/2019/6633 6633 Checking of fixing geocomposite sheet and 150 mm perofated pipe Box culvert Km 171+980 13-Dec-19 8:40 AM
6691 NMSCEW/P-IV/STR/2019/6634 6634 Checking of fixing geocomposite sheet and 150 mm perofated pipe for 2x2 Utility duct Utility duct Km 172+520 13-Dec-19 9:30 AM
6692 NMSCEW/P-IV/STR/2019/6635 6635 Checking of fixing geocomposite sheet and 150 mm perofated pipe Utility duct Km 173+000 13-Dec-19 10:10 AM
6693 NMSCEW/P-IV/STR/2019/6636 6636 Checking of fixing geocomposite sheet and 150 mm perofated pipe Utility duct Km 174+360 13-Dec-19 11:00 AM
6694 NMSCEW/P-IV/STR/2019/6637 6637 Checking of fixing geocomposite sheet and 150 mm perofated pipe for 2x2 Utility duct Utility duct Km 176+250 13-Dec-19 11:30 AM
6695 NMSCEW/P-IV/STR/2019/6638 6638 Checking of fixing geocomposite sheet and 150 mm perofated pipe for 2x2 Utility duct Utility duct Km 177+300 13-Dec-19 11:50 AM
6696 NMSCEW/P-IV/STR/2019/6639 6639 Checking of fixing geocomposite sheet and 150 mm perofated pipe for 3x3 Box culvert Box culvert Km 178+014 13-Dec-19 12:20 PM
6697 NMSCEW/P-IV/STR/2019/6640 6640 Checking of fixing geocomposite sheet and 150 mm perofated pipe for 2x2 Utility duct Utility duct Km 178+540 13-Dec-19 2:00 PM
6698 NMSCEW/P-IV/STR/2019/6641 6641 Checking of fixing geocomposite sheet and 150 mm perofated pipe for 3x3 Box culvert Box culvert Km 178+730 13-Dec-19 2:30 PM
6699 NMSCEW/P-IV/STR/2019/6642 6642 Checking of fixing geocomposite sheet and 150 mm perofated pipe for 2x2 Utility duct Utility duct Km 179+390 13-Dec-19 3:30 PM
6700 NMSCEW/P-IV/STR/2019/6643 6643 Checking of laying composite drain at A1 & A2 side Utility duct Km 187+360 BHS 13-Dec-19 4:10 PM
6701 NMSCEW/P-IV/STR/2019/6644 6644 Checking of laying composite drain at A1 & A2 side Box culvert Km 186+352 BHS 13-Dec-19 5:30 PM
6702 NMSCEW/P-IV/STR/2019/6645 6645 Checking of laying composite drain at A1 & A2 side Box culvert Km 187+677 BHS 13-Dec-19 6:00 PM
6703 NMSCEW/P-IV/STR/2019/6646 6646 Checking of Shuttering,reinforcement, pouring concrete for deck slab between LP-4 to LP-7 Viaduct Km 169+800 LHS 13-Dec-19 10:00 AM
Checking for stressing and remove slagness of H.T. wires at Girder no-153,154,155,156 at bed
6704 NMSCEW/P-IV/STR/2019/6647 6647 Girder Km 200+200 LHS 13-Dec-19 4:00 PM
no -02, Girder Type-02 at casting yard camp -2
Checking of reinforcement Girder no -153,154,155,156 at bed no -02, Girder Type-02 at
6705 NMSCEW/P-IV/STR/2019/6648 6648 Girder Km 200+200 LHS 13-Dec-19 4:30 PM
casting yard camp -2
6706 NMSCEW/P-IV/STR/2019/6649 6649 Checking layout ,level, & laying concrete for PCC at RP-15 Viaduct Km 213+915 RHS 13-Dec-19 9:25 AM
6707 NMSCEW/P-IV/STR/2019/6650 6650 Checking of reinforcement,shuttering and Pouring concrete for raft at LP-16 Viaduct Km 213+915 Km 00+000 LHS 13-Dec-19 3:22 PM IPC-11 Approved AE
6708 NMSCEW/P-IV/STR/2019/6651 6651 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-17 Viaduct Km 213+915 LHS 13-Dec-19 10:22 AM IPC-14
6709 NMSCEW/P-IV/STR/2019/6652 6652 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-1 Viaduct Km 200+920 RHS 13-Dec-19 10:11 AM
6710 NMSCEW/P-IV/STR/2019/6653 6653 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-11 Viaduct Km 202+190 LHS 13-Dec-19 4:42 PM
6711 NMSCEW/P-IV/STR/2019/6654 6654 Checking of reinforcement, shuttering & pouring concrete for pedestal at RP-4 Viaduct Km 202+190 RHS 13-Dec-19 4:20 PM
6712 NMSCEW/P-IV/STR/2019/6655 6655 Checking of Shuttering,reinforcement, pouring concrete for abutment cap at LA-2 Viaduct Km 195+900 Km 00+000 LHS 13-Dec-19 3:35 PM IPC-11 Approved AE
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at U type retaining wall
6713 NMSCEW/P-IV/STR/2019/6656 6656 LVUP Km 178+323 13-Dec-19 11:30 AM
A1 & A2
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at U type retaining wall
6714 NMSCEW/P-IV/STR/2019/6657 6657 VUP Km 176+614 13-Dec-19 12:30 PM
A1 & A2
6715 NMSCEW/P-IV/STR/2019/6658 6658 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 2nd lift at pier P-1 VOP Km 181+420 RHS 13-Dec-19 8:00 AM
6716 NMSCEW/P-IV/STR/2019/6659 6659 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 1st lift at pier P-1 VOP Km 181+420 LHS 13-Dec-19 9:00 AM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 4th lift at retaining wall
6717 NMSCEW/P-IV/STR/2019/6660 6660 PUP Km 183+290 RHS 13-Dec-19 10:00 AM
A1
Checking of layout,level,structural excavation & laying concrete PCC(M-10) at retaining wall
6718 NMSCEW/P-IV/STR/2019/6661 6661 PUP Km 190+650 RHS 13-Dec-19 11:00 AM
A2
Checking of layout,level,structural excavation & laying concrete PCC(M-10) at retaining wall
6719 NMSCEW/P-IV/STR/2019/6662 6662 PUP Km 190+650 LHS 13-Dec-19 11:30 AM
A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 2nd lift at retaining wall
6720 NMSCEW/P-IV/STR/2019/6663 6663 PUP Km 190+650 RHS 13-Dec-19 12:30 PM
A1
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at retaining wall
6721 NMSCEW/P-IV/STR/2019/6664 6664 PUP Km 190+650 LHS 13-Dec-19 2:00 PM
A1
Checking of reinforcement,shuttering and Pouring concrete(M-30) for raft at retaining wall A2
6722 NMSCEW/P-IV/STR/2019/6665 6665 PUP Km 189+000 RHS 13-Dec-19 3:00 PM
6727 NMSCEW/P-IV/STR/2019/6670 6670 Checking of fixing geocomposite sheet and 150 mm perofated pipe for 2x2 Utility duct Utility duct Km 170+300 14-Dec-19 9:00 AM
6728 NMSCEW/P-IV/STR/2019/6671 6671 Checking of fixing geocomposite sheet and 150 mm perofated pipe for 3x3 box culvert Box culvert Km 170+439 14-Dec-19 10:30 AM
6729 NMSCEW/P-IV/STR/2019/6672 6672 Checking of fixing geocomposite sheet and 150 mm perofated pipe for 2x2 Utility duct Utility duct Km 170+890 14-Dec-19 12:00 PM
6730 NMSCEW/P-IV/STR/2019/6673 6673 Checking of fixing geocomposite sheet and 150 mm perofated pipe PUP Km 171+110 14-Dec-19 2:00 PM
6731 NMSCEW/P-IV/STR/2019/6674 6674 Checking of fixing geocomposite sheet and 150 mm perofated pipe PUP Km 172+190 14-Dec-19 4:00 PM
6732 NMSCEW/P-IV/STR/2019/6675 6675 Checking of fixing geocomposite sheet and 150 mm perofated pipe PUP Km 187+835 LHS 14-Dec-19 9:45 AM
6733 NMSCEW/P-IV/STR/2019/6676 6676 Checking of fixing geocomposite sheet and 150 mm perofated pipe PUP Km 187+835 RHS 14-Dec-19 11:45 AM
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at median wall A1 &
6734 NMSCEW/P-IV/STR/2019/6677 6677 PUP Km 164+380 14-Dec-19 5:00 PM
A2
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at retaining wall A1 &
6735 NMSCEW/P-IV/STR/2019/6678 6678 PUP Km 165+790 LHS 14-Dec-19 5:15 PM
A2
6736 NMSCEW/P-IV/STR/2019/6679 6679 Checking of Shuttering,reinforcement & pouring concrete for 2nd lift at wall W2 PUP Km 206+985 Km 00+000 RHS 14-Dec-19 8:00 AM IPC-11 Approved AE
6737 NMSCEW/P-IV/STR/2019/6680 6680 Checking of Shuttering,reinforcement & pouring concrete for 1st lift at median wall W1 & W2 PUP Km 206+985 14-Dec-19 9:00 AM
6738 NMSCEW/P-IV/STR/2019/6681 6681 Checking of Shuttering,reinforcement & pouring concrete for 1st lift at retaining wall W2 PUP Km 208+930 LHS 14-Dec-19 2:00 PM
6739 NMSCEW/P-IV/STR/2019/6682 6682 Checking of Shuttering,reinforcement & pouring concrete for raft at median PUP Km 208+930 14-Dec-19 3:00 PM
6740 NMSCEW/P-IV/STR/2019/6683 6683 Checking layout ,level, & laying concrete & Structural Excavation (M-15) for PCC at LP-2 MJB Km 205+610 Km 00+000 LHS 14-Dec-19 10:00 AM IPC-11 Approved AE
Checking of Shuttering,reinforcement & pouring concrete(M-45) for cross girder between RP-
6741 NMSCEW/P-IV/STR/2019/6684 6684 Viaduct Km 169+800 RHS 14-Dec-19 5:30 PM
12 to RP-13
Checking for stressing and remove slagness of H.T. wires at Girder no-157,158,159,160 at bed
6742 NMSCEW/P-IV/STR/2019/6685 6685 Girder Km 200+200 LHS 14-Dec-19 4:00 PM
no -01, Girder Type-02 at casting yard camp -2
Checking of reinforcement Girder no -157,158,159,160 at bed no -01, Girder Type-02 at
6743 NMSCEW/P-IV/STR/2019/6686 6686 Girder Km 200+200 LHS 14-Dec-19 4:30 PM
casting yard camp -2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
6744 NMSCEW/P-IV/STR/2019/6687 6687 Girder Km 200+200 LHS 14-Dec-19 6:30 PM
153,154,155,156 at bed no -04, Girder Type-02
Checking for stressing and remove slagness of H.T. wires at Girder no-141,142,143,144 at bed
6745 NMSCEW/P-IV/STR/2019/6688 6688 Girder Km 200+200 LHS 14-Dec-19 5:05 PM
no -05, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -141,142,143,144 at bed no -05, Girder Type-01 at
6746 NMSCEW/P-IV/STR/2019/6689 6689 Girder Km 200+200 LHS 14-Dec-19 5:35 PM
casting yard camp -2
6747 NMSCEW/P-IV/STR/2019/6690 6690 Checking layout ,level, & laying concrete for PCC at RP-11 Viaduct Km 213+915 RHS 14-Dec-19 4:20 PM
6748 NMSCEW/P-IV/STR/2019/6691 6691 Checking of reinforcement,shuttering and Pouring concrete for raft at LP-13 Viaduct Km 213+915 LHS 14-Dec-19 9:20 AM
6749 NMSCEW/P-IV/STR/2019/6692 6692 Checking layout ,level, & laying concrete for PCC at RA-02 Viaduct Km 213+915 RHS 14-Dec-19 4:05 PM
6750 NMSCEW/P-IV/STR/2019/6693 6693 Checking of reinforcement,shuttering and Pouring concrete(M-35) for raft at pier P-2 VOP Km 181+420 LHS 14-Dec-19 11:00 AM
6751 NMSCEW/P-IV/STR/2019/6694 6694 Checking of reinforcement,shuttering and Pouring concrete(M-30) for 2nd lift at wall A2 MNB Km 181+700 RHS 14-Dec-19 11:30 AM
6752 NMSCEW/P-IV/STR/2019/6695 6695 Checking of reinforcement,shuttering and Pouring concrete(M-30) for raft at retaining wall A1 PUP Km 183+290 LHS 14-Dec-19 2:00 PM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at retaining wall
6753 NMSCEW/P-IV/STR/2019/6696 6696 PUP Km 190+650 RHS 14-Dec-19 12:30 PM
A1
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 4th lift at retaining wall
6754 NMSCEW/P-IV/STR/2019/6697 6697 PUP Km 188+575 RHS 14-Dec-19 2:14 PM
A1
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 1st lift at retaining wall
6755 NMSCEW/P-IV/STR/2019/6698 6698 PUP Km 189+000 LHS 14-Dec-19 3:00 PM
A2
6756 NMSCEW/P-IV/STR/2019/6699 6699 Checking of layout,level,structural excavation & laying concrete PCC(M-15) MNB Km 189+705 BHS 14-Dec-19 3:21 PM
6757 NMSCEW/P-IV/STR/2019/6700 6700 Checking of Shuttering,reinforcement, pouring concrete for pier cap at RP-5 Viaduct Km 196+560 Km 00+000 RHS 14-Dec-19 10:42 AM IPC-11 Approved AE
6758 NMSCEW/P-IV/STR/2019/6701 6701 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-4 Viaduct Km 196+560 Km 00+000 RHS 14-Dec-19 11:50 AM IPC-11 Approved AE
6759 NMSCEW/P-IV/STR/2019/6702 6702 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-11 Viaduct Km 202+190 LHS 15-Dec-19 12:30 PM
6760 NMSCEW/P-IV/STR/2019/6703 6703 Checking of reinforcement,shuttering and Pouring concrete for raft at retaining wall A1 PUP Km 177+810 15-Dec-19 11:30 AM
6761 NMSCEW/P-IV/STR/2019/6704 6704 Checking of layout,level,structural excavation & laying concrete PCC at median wall A2 PUP Km 179+050 15-Dec-19 11:00 AM
6762 NMSCEW/P-IV/STR/2019/6705 6705 Checking of layout,level,structural excavation & laying concrete PCC PUP Km 179+050 BHS 15-Dec-19 11:45 AM
6763 NMSCEW/P-IV/STR/2019/6706 6706 Checking of layout,level for bearing & grouting at RP-17 Viaduct Km 169+800 RHS 15-Dec-19 12:30 PM
Checking of reinforcement,shuttering and Pouring concrete for 4th lift at median wall A1 &
6764 NMSCEW/P-IV/STR/2019/6707 6707 VUP Km 166+987 15-Dec-19 2:00 PM
A2
Checking of reinforcement,shuttering and Pouring concrete for raft with bottom haunch at wall
6765 NMSCEW/P-IV/STR/2019/6708 6708 Box culvert Km 162+832 BHS 15-Dec-19 1:00 PM
A1 & A2 side
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at retaining wall A1 &
6766 NMSCEW/P-IV/STR/2019/6709 6709 PUP Km 165+790 LHS 15-Dec-19 5:00 PM
A2
Checking for stressing and remove slagness of H.T. wires at Girder no-145,146,147,148 at bed
6767 NMSCEW/P-IV/STR/2019/6710 6710 Girder Km 200+200 LHS 15-Dec-19 11:00 AM
no -07, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -145,146,147,148 at bed no -07, Girder Type-01 at
6768 NMSCEW/P-IV/STR/2019/6711 6711 Girder Km 200+200 LHS 15-Dec-19 11:30 AM
casting yard camp -2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
6769 NMSCEW/P-IV/STR/2019/6712 6712 Girder Km 200+200 LHS 15-Dec-19 8:15 AM
157,158,159,160 at bed no -01, Girder Type-02
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-1
6770 NMSCEW/P-IV/STR/2019/6713 6713 Box culvert Km 175+500 LHS 15-Dec-19 10:35 AM
I) 2x2 (2 to 4m) segment no.-271,272,273,274
II) 2x2 (0 to 2m) segment no.-481,482,483
6771 NMSCEW/P-IV/STR/2019/6714 6714 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 3rd lift at pier P-1 VOP Km 181+420 RHS 15-Dec-19 10:00 AM
6772 NMSCEW/P-IV/STR/2019/6715 6715 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 2nd lift at pier P-1 VOP Km 181+420 LHS 15-Dec-19 11:30 AM
6773 NMSCEW/P-IV/STR/2019/6716 6716 Checking of reinforcement,shuttering and Pouring concrete(M-30) for raft at retaining wall A1 PUP Km 183+290 LHS 15-Dec-19 11:00 AM
6774 NMSCEW/P-IV/STR/2019/6717 6717 Checking of reinforcement,shuttering and Pouring concrete(M-30) for raft at retaining wall A2 PUP Km 190+650 RHS 15-Dec-19 12:30 PM
6775 NMSCEW/P-IV/STR/2019/6718 6718 Checking of reinforcement,shuttering and Pouring concrete(M-30) for raft at retaining wall A2 PUP Km 190+650 LHS 15-Dec-19 2:10 PM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 1st lift at retaining wall
6776 NMSCEW/P-IV/STR/2019/6719 6719 PUP Km 189+000 RHS 15-Dec-19 3:00 PM
A2
6777 NMSCEW/P-IV/STR/2019/6720 6720 Checking layout ,level, & laying concrete(M-15) for PCC MNB Km 189+705 BHS 15-Dec-19 3:15 PM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 2nd lift at retaining wall
6778 NMSCEW/P-IV/STR/2019/6721 6721 PUP Km 189+000 LHS 15-Dec-19 3:30 PM
A2
Checking of reinforcement,shuttering and Pouring concrete(M-35) for 3rd lift at retaining wall
6779 NMSCEW/P-IV/STR/2019/6722 6722 VUP Km 187+113 15-Dec-19 4:00 PM
A1
6780 NMSCEW/P-IV/STR/2019/6723 6723 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at retaining wall W2 PUP Km 193+880 RHS 15-Dec-19 9:30 AM
6781 NMSCEW/P-IV/STR/2019/6724 6724 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall W1 Box culvert Km 198+478 Km 00+000 LHS 15-Dec-19 2:22 PM IPC-11 Approved AE
6782 NMSCEW/P-IV/STR/2019/6725 6725 Checking erection & jointing of pre cast utility duct (2*2) Utility duct Km 166+710 BHS 15-Dec-19 10:05 AM
6783 NMSCEW/P-IV/STR/2019/6726 6726 Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at retaining wall W1 PUP Km 193+880 RHS 15-Dec-19 11:30 AM
6784 NMSCEW/P-IV/STR/2019/6727 6727 Checking of reinforcement, shuttering & pouring concrete for abutment shaft 1st lift at LA-2 MJB Km 205+610 LHS 16-Dec-19 10:00 AM
6785 NMSCEW/P-IV/STR/2019/6728 6728 Checking of Coordinates ,level & laying concrete PCC for retaining wall LA1 MJB Km 205+610 LHS 16-Dec-19 2:00 PM
6786 NMSCEW/P-IV/STR/2019/6729 6729 Checking of reinforcement,shuttering and Pouring concrete(M-45) for raft at LP-2 MJB Km 205+610 LHS 16-Dec-19 5:00 PM
Checking for stressing and remove slagness of H.T. wires at Girder no-141,142,143,144 at bed
6787 NMSCEW/P-IV/STR/2019/6730 6730 Girder Km 200+200 LHS 16-Dec-19 8:00 AM
no -05, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -141,142,143,144 at bed no -05, Girder Type-01 at
6788 NMSCEW/P-IV/STR/2019/6731 6731 Girder Km 200+200 LHS 16-Dec-19 8:30 AM
casting yard camp -2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
6789 NMSCEW/P-IV/STR/2019/6732 6732 Girder Km 200+200 LHS 16-Dec-19 3:00 PM
145,146,147,148 at bed no -07, Girder Type-01
Checking for stressing and remove slagness of H.T. wires at Girder no-149,150,151,152 at bed
6790 NMSCEW/P-IV/STR/2019/6733 6733 Girder Km 200+200 LHS 16-Dec-19 5:10 PM
no -08, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -149,150,151,152 at bed no -08, Girder Type-01 at
6791 NMSCEW/P-IV/STR/2019/6734 6734 Girder Km 200+200 LHS 16-Dec-19 5:40 PM
casting yard camp -2
6792 NMSCEW/P-IV/STR/2019/6735 6735 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-1 Viaduct Km 200+920 RHS 16-Dec-19 10:00 AM
6793 NMSCEW/P-IV/STR/2019/6736 6736 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-2 Viaduct Km 200+920 RHS 16-Dec-19 4:00 PM
6794 NMSCEW/P-IV/STR/2019/6737 6737 Checking of reinforcement, shuttering & pouring concrete for pier starter at RP-17 Viaduct Km 213+915 RHS 16-Dec-19 4:25 PM
6795 NMSCEW/P-IV/STR/2019/6738 6738 Checking of reinforcement,shuttering and Pouring concrete for raft at LP-18 Viaduct Km 213+915 Km 00+000 LHS 16-Dec-19 3:50 PM IPC-11 Approved AE
6796 NMSCEW/P-IV/STR/2019/6739 6739 Checking layout ,level, & laying concrete for PCC at RP-12 Viaduct Km 213+915 RHS 16-Dec-19 3:15 PM
6797 NMSCEW/P-IV/STR/2019/6740 6740 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-2 Viaduct Km 213+915 LHS 16-Dec-19 4:45 PM
6803 NMSCEW/P-IV/STR/2019/6746 6746 Checking of reinforcement,shuttering and Pouring concrete for raft at retaining wall A1 & A2 PUP Km 164+380 LHS 16-Dec-19 5:25 PM
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-2
6804 NMSCEW/P-IV/STR/2019/6747 6747 Box culvert Km 200+200 LHS 17-Dec-19 9:30 AM
I) 3x3 (2 to 4m) segment no.-138,139,140,141,142,143,144
6805 NMSCEW/P-IV/STR/2019/6748 6748 Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall W1 PUP Km 193+880 LHS 17-Dec-19 11:00 AM
6806 NMSCEW/P-IV/STR/2019/6749 6749 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at retaining wall W2 PUP Km 193+880 RHS 17-Dec-19 11:30 AM
6807 NMSCEW/P-IV/STR/2019/6750 6750 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at median wall W2 PUP Km 193+880 17-Dec-19 12:30 PM
6808 NMSCEW/P-IV/STR/2019/6751 6751 Checking of layout,level,reinforcement,shuttering and Pouring concrete for final lift top slab Box culvert Km 201+280 Km 00+000 RHS 17-Dec-19 4:30 PM IPC-11 Approved AE
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at U type median wall
6809 NMSCEW/P-IV/STR/2019/6752 6752 PUP Km 164+380 17-Dec-19 5:00 PM
A1 & A2
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at U type median wall
6810 NMSCEW/P-IV/STR/2019/6753 6753 VUP Km 176+614 17-Dec-19 11:30 AM
A1 & A2
6811 NMSCEW/P-IV/STR/2019/6754 6754 Checking of reinforcement,shuttering and Pouring concrete for raft at RA-1 MNB Km 174+570 RHS 17-Dec-19 11:00 AM
6812 NMSCEW/P-IV/STR/2019/6755 6755 Checking of reinforcement,shuttering and Pouring concrete for raft at retaining wall A2 PUP Km 177+810 LHS 17-Dec-19 12:30 PM
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-1
6813 NMSCEW/P-IV/STR/2019/6756 6756 Box culvert Km 175+500 LHS 17-Dec-19 10:44 AM
I) 2x2 (2 to 4m) segment no.-271, 272, 273, 274, 275, 276, 277, 278, 279, 280, 281, 282
II) 2x2 (0 to 2m) segment no.- 483, 484, 485, 486, 487
6814 NMSCEW/P-IV/STR/2019/6757 6757 Checking of layout,level,structural excavation & laying concrete PCC at RA-1 MNB Km 167+547 RHS 17-Dec-19 5:00 PM
6815 NMSCEW/P-IV/STR/2019/6758 6758 Checking of layout,level,structural excavation & laying concrete PCC at LA-1 MNB Km 167+547 LHS 17-Dec-19 5:30 PM
6816 NMSCEW/P-IV/STR/2019/6759 6759 Checking of reinforcement,shuttering and Pouring concrete(M-30) for raft at retaining wall A2 PUP Km 177+810 LHS 17-Dec-19 2:00 PM
Checking of layout,level,structural excavation & laying concrete PCC at retaining wall A1 &
6817 NMSCEW/P-IV/STR/2019/6760 6760 LVUP Km 169+291 LHS 17-Dec-19 5:05 PM
A2
Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall A1 &
6818 NMSCEW/P-IV/STR/2019/6761 6761 VUP Km 166+987 RHS 17-Dec-19 2:00 PM
A2
6819 NMSCEW/P-IV/STR/2019/6762 6762 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 2nd lift at pier P-1 VOP Km 181+420 LHS 17-Dec-19 10:00 AM
6820 NMSCEW/P-IV/STR/2019/6763 6763 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 5th lift at pier P-3 VOP Km 181+420 RHS 17-Dec-19 11:30 AM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 1st lift at retaining wall
6821 NMSCEW/P-IV/STR/2019/6764 6764 PUP Km 190+650 RHS 17-Dec-19 12:00 PM
A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 1st lift at retaining wall
6822 NMSCEW/P-IV/STR/2019/6765 6765 PUP Km 190+650 LHS 17-Dec-19 12:30 PM
A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 1st lift at retaining wall
6823 NMSCEW/P-IV/STR/2019/6766 6766 PUP Km 189+000 RHS 17-Dec-19 2:05 PM
A2
6824 NMSCEW/P-IV/STR/2019/6767 6767 Checking of layout,level,structural excavation & laying concrete PCC(M-15) MNB Km 189+705 BHS 17-Dec-19 3:00 PM
Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall A1 &
6825 NMSCEW/P-IV/STR/2019/6768 6768 PUP Km 165+790 RHS 17-Dec-19 5:44 PM
A2
6826 NMSCEW/P-IV/STR/2019/6769 6769 Checking of layout,level,structural excavation & laying concrete PCC(M-15) at A2 MNB Km 186+550 LHS 17-Dec-19 2:50 PM
Checking for stressing and remove slagness of H.T. wires at Girder no-149,150,151,152 at bed
6827 NMSCEW/P-IV/STR/2019/6770 6770 Girder Km 200+200 LHS 17-Dec-19 6:00 PM
no -08, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -149,150,151,152 at bed no -08, Girder Type-01 at
6828 NMSCEW/P-IV/STR/2019/6771 6771 Girder Km 200+200 LHS 17-Dec-19 6:30 PM
casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-161,162,163,164 at bed
6829 NMSCEW/P-IV/STR/2019/6772 6772 Girder Km 200+200 LHS 17-Dec-19 5:00 PM
no -04, Girder Type-02 at casting yard camp -2
Checking of reinforcement Girder no -161,162,163,164 at bed no -04, Girder Type-02 at
6830 NMSCEW/P-IV/STR/2019/6773 6773 Girder Km 200+200 LHS 17-Dec-19 5:30 PM
casting yard camp -2
6831 NMSCEW/P-IV/STR/2019/6774 6774 Checking of reinforcement, shuttering & pouring concrete for pier starter at LP-11 Viaduct Km 213+915 LHS 17-Dec-19 4:15 PM
6832 NMSCEW/P-IV/STR/2019/6775 6775 Checking of reinforcement, shuttering & pouring concrete for pier starter at RP-17 Viaduct Km 213+915 RHS 17-Dec-19 4:35 PM
6833 NMSCEW/P-IV/STR/2019/6776 6776 Checking layout ,level, & laying concrete for PCC at RP-11 Viaduct Km 213+915 RHS 17-Dec-19 3:30 PM
6834 NMSCEW/P-IV/STR/2019/6777 6777 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-11 Viaduct Km 202+190 Km 00+000 LHS 17-Dec-19 2:32 PM IPC-11 Approved AE
6835 NMSCEW/P-IV/STR/2019/6778 6778 Checking of Shuttering,reinforcement, pouring concrete for padestal at RP-5 Viaduct Km 202+190 RHS 17-Dec-19 3:00 PM
6836 NMSCEW/P-IV/STR/2019/6779 6779 Checking of Shuttering,reinforcement, pouring concrete for padestal at RP-6 Viaduct Km 202+190 RHS 17-Dec-19 3:22 PM
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall W2(Main
6837 NMSCEW/P-IV/STR/2019/6780 6780 Box culvert Km 206+843 LHS 17-Dec-19 8:00 AM
carriageway)
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-2
6838 NMSCEW/P-IV/STR/2019/6781 6781 Box culvert Km 200+200 LHS 18-Dec-19 9:30 AM
I) 2x2 (2 to 4m) segment no.-489,490,491
II) 3x3 (2 to 4m) segment no.-
145,146,147,148,149
6839 NMSCEW/P-IV/STR/2019/6782 6782 Checking of reinforcement,shuttering and Pouring concrete for raft at retaining wall W2 MNB Km 199+360 LHS 18-Dec-19 4:00 PM
6840 NMSCEW/P-IV/STR/2019/6783 6783 Checking of reinforcement,shuttering and Pouring concrete for raft at retaining wall W2 MNB Km 199+360 RHS 18-Dec-19 4:30 PM
6841 NMSCEW/P-IV/STR/2019/6784 6784 Checking of reinforcement,shuttering and Pouring concrete for raft at retaining wall W1 PUP Km 208+930 RHS 18-Dec-19 8:00 AM
Checking of layout,level,reinforcement,shuttering and Pouring concrete for top slab with final
6842 NMSCEW/P-IV/STR/2019/6785 6785 Box culvert Km 208+675 RHS 18-Dec-19 10:00 AM
lift W1 & W2
Checking of Shuttering,reinforcement & pouring concrete(M-45) for cross girder between RP-
6843 NMSCEW/P-IV/STR/2019/6786 6786 Viaduct Km 169+800 RHS 18-Dec-19 2:30 PM
11 to RP-12
6844 NMSCEW/P-IV/STR/2019/6787 6787 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 4th lift at pier P-1 VOP Km 181+420 RHS 18-Dec-19 10:00 AM
6845 NMSCEW/P-IV/STR/2019/6788 6788 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 6th lift at pier P-3 VOP Km 181+420 LHS 18-Dec-19 11:30 AM
6846 NMSCEW/P-IV/STR/2019/6789 6789 Checking of Shuttering,reinforcement & pouring concrete(M-35) for final lift at wall (Loop-B) MNB loop-B Km 01+980 18-Dec-19 12:30 PM
6848 NMSCEW/P-IV/STR/2019/6791 6791 Checking of layout,level,structural excavation & laying concrete PCC(M-15) at abutment A2 MNB Km 186+550 LHS 18-Dec-19 2:00 PM
6849 NMSCEW/P-IV/STR/2019/6792 6792 Checking of layout,level,structural excavation & laying concrete PCC(M-15) MNB Km 189+705 RHS 18-Dec-19 3:00 PM
6850 NMSCEW/P-IV/STR/2019/6793 6793 Checking of Shuttering,reinforcement & pouring concrete(M-35) for bottom slab MNB Km 189+705 LHS 18-Dec-19 4:00 PM
6851 NMSCEW/P-IV/STR/2019/6794 6794 Checking of reinforcement,shuttering and Pouring concrete for raft at retaining wall A2 PUP Km 184+190 LHS 18-Dec-19 4:23 PM
6852 NMSCEW/P-IV/STR/2019/6795 6795 Checking of layout,level,structural excavation & laying concrete PCC(M-15) MNB Km 181+078 LHS 18-Dec-19 5:00 PM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 2nd lift at retaining wall
6853 NMSCEW/P-IV/STR/2019/6796 6796 PUP Km 190+650 LHS 18-Dec-19 2:30 PM
A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 2nd lift at retaining wall
6854 NMSCEW/P-IV/STR/2019/6797 6797 PUP Km 190+650 RHS 18-Dec-19 3:00 PM
A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at retaining wall
6855 NMSCEW/P-IV/STR/2019/6798 6798 PUP Km 189+000 LHS 18-Dec-19 2:00 PM
A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 2nd lift at retaining wall
6856 NMSCEW/P-IV/STR/2019/6799 6799 PUP Km 189+000 RHS 18-Dec-19 2:45 PM
A2
Checking of reinforcement,shuttering and Pouring concrete for raft with bottom haunch at A1
6857 NMSCEW/P-IV/STR/2019/6800 6800 Box culvert Km 166+440 BHS 18-Dec-19 5:00 PM
& A2
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-1
6858 NMSCEW/P-IV/STR/2019/6801 6801 Box culvert Km 175+500 LHS 18-Dec-19 10:00 AM
I) 2x2 (2 to 4m) segment no.-283, 284, 285, 286, 287, 288, 289, 290, 291, 292, 293, 294
II) 3x3 (0 to 2m) segment no.- 25,26,27
6859 NMSCEW/P-IV/STR/2019/6802 6802 Checking of Shuttering,reinforcement, pouring concrete for deck slab between LP-4 to LP-7 Viaduct Km 169+800 LHS 18-Dec-19 9:30 AM
Checking for stressing and remove slagness of H.T. wires at Girder no-153,154,155,156 at bed
6871 NMSCEW/P-IV/STR/2019/6814 6814 Girder Km 200+200 LHS 19-Dec-19 8:00 AM
no -06, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -153,154,155,156 at bed no -06, Girder Type-01 at
6872 NMSCEW/P-IV/STR/2019/6815 6815 Girder Km 200+200 LHS 19-Dec-19 8:30 AM
casting yard camp -2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
6873 NMSCEW/P-IV/STR/2019/6816 6816 Girder Km 200+200 LHS 19-Dec-19 6:30 PM
153,154,155,156 at bed no -06, Girder Type-01
Checking for stressing and remove slagness of H.T. wires at Girder no-161,162,163,164 at bed
6874 NMSCEW/P-IV/STR/2019/6817 6817 Girder Km 200+200 LHS 19-Dec-19 8:20 AM
no -04, Girder Type-02 at casting yard camp -2
Checking of reinforcement Girder no -161,162,163,164 at bed no -04, Girder Type-02 at
6875 NMSCEW/P-IV/STR/2019/6818 6818 Girder Km 200+200 LHS 19-Dec-19 8:44 AM
casting yard camp -2
6876 NMSCEW/P-IV/STR/2019/6819 6819 Checking of Shuttering,reinforcement, pouring concrete for padestal at RP-7 Viaduct Km 202+190 RHS 19-Dec-19 2:30 PM
6877 NMSCEW/P-IV/STR/2019/6820 6820 Checking of reinforcement,shuttering and Pouring concrete for raft at RP-1 Viaduct Km 213+915 RHS 19-Dec-19 4:32 PM
6878 NMSCEW/P-IV/STR/2019/6821 6821 Checking of reinforcement,shuttering and Pouring concrete for raft at RP-13 Viaduct Km 213+915 RHS 19-Dec-19 5:05 PM
6879 NMSCEW/P-IV/STR/2019/6822 6822 Checking layout ,level, & laying concrete for PCC at RA-02 Viaduct Km 213+915 RHS 19-Dec-19 3:35 PM
6880 NMSCEW/P-IV/STR/2019/6823 6823 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-1 Viaduct Km 196+560 LHS 19-Dec-19 2:44 PM IPC-14
6881 NMSCEW/P-IV/STR/2019/6824 6824 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-2 Viaduct Km 196+560 Km 00+000 LHS 19-Dec-19 3:50 PM IPC-11 Approved
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at retaining wall A1 &
6882 NMSCEW/P-IV/STR/2019/6825 6825 PUP Km 164+380 RHS 19-Dec-19 5:00 PM
A2
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at U type retaining wall
6883 NMSCEW/P-IV/STR/2019/6826 6826 VUP Km 176+614 19-Dec-19 10:30 AM
A1 & A2
Checking of reinforcement,shuttering and Pouring concrete for final lift at U type retaining
6884 NMSCEW/P-IV/STR/2019/6827 6827 PUP Km 177+810 19-Dec-19 1:30 PM
wall A1 & A2
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at U type retaining wall
6885 NMSCEW/P-IV/STR/2019/6828 6828 LVUP Km 178+323 19-Dec-19 5:34 PM
A1 & A2
6886 NMSCEW/P-IV/STR/2019/6829 6829 Checking of reinforcement,shuttering and Pouring concrete for raft at RA1 MNB Km 174+570 RHS 19-Dec-19 11:00 AM
6887 NMSCEW/P-IV/STR/2019/6830 6830 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 4th lift at pier P-1 VOP Km 181+420 RHS 19-Dec-19 8:00 AM
6888 NMSCEW/P-IV/STR/2019/6831 6831 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 6th lift at pier P-3 VOP Km 181+420 LHS 19-Dec-19 10:00 AM
6889 NMSCEW/P-IV/STR/2019/6832 6832 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 6th lift at pier P-3 VOP Km 181+420 RHS 19-Dec-19 10:25 AM
6890 NMSCEW/P-IV/STR/2019/6833 6833 Checking of layout,level,structural excavation & laying concrete PCC(M-15) at abutment A2 MNB Km 186+550 LHS 19-Dec-19 2:00 PM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 1st lift at retaining wall
6891 NMSCEW/P-IV/STR/2019/6834 6834 PUP Km 183+290 LHS 19-Dec-19 8:20 AM
A2
6892 NMSCEW/P-IV/STR/2019/6835 6835 Checking of layout,level,structural excavation & laying concrete PCC(M-15) MNB Km 181+078 LHS 19-Dec-19 4:17 PM
Checking for stressing and remove slagness of H.T. wires at Girder no-165,166,167,168 at bed
6893 NMSCEW/P-IV/STR/2019/6836 6836 Girder Km 200+200 LHS 19-Dec-19 6:15 PM
no -03, Girder Type-02 at casting yard camp -2
Checking of reinforcement Girder no -165,166,167,168 at bed no -03, Girder Type-02 at
6894 NMSCEW/P-IV/STR/2019/6837 6837 Girder Km 200+200 LHS 19-Dec-19 6:45 PM
casting yard camp -2
6895 NMSCEW/P-IV/STR/2019/6838 6838 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at median wall W2 PUP Km 193+880 20-Dec-19 8:30 AM
Checking of reinforcement,shuttering and Pouring concrete for raft at U-type median with
6896 NMSCEW/P-IV/STR/2019/6839 6839 LVUP Km 169+291 20-Dec-19 9:00 AM
bottom haunch A1 & A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at retaining wall
6897 NMSCEW/P-IV/STR/2019/6840 6840 PUP Km 190+650 LHS 20-Dec-19 2:30 PM
A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at retaining wall
6898 NMSCEW/P-IV/STR/2019/6841 6841 PUP Km 190+650 RHS 20-Dec-19 3:00 PM
A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 4th lift at retaining wall
6899 NMSCEW/P-IV/STR/2019/6842 6842 PUP Km 189+000 LHS 20-Dec-19 3:30 PM
A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 2nd lift at retaining wall
6900 NMSCEW/P-IV/STR/2019/6843 6843 PUP Km 190+650 RHS 20-Dec-19 4:30 PM
A2
Checking of layout,level,structural excavation & laying concrete PCC(M-10) at retaining wall
6901 NMSCEW/P-IV/STR/2019/6844 6844 PUP Km 188+575 RHS 20-Dec-19 8:00 AM
A2
6902 NMSCEW/P-IV/STR/2019/6845 6845 Checking of layout,level,excavation at wing wall A1 VUP Km 176+614 LHS 20-Dec-19 9:30 AM
6903 NMSCEW/P-IV/STR/2019/6846 6846 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall A1 & A2 Box culvert Km 181+180 LHS 20-Dec-19 12:30 PM
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
6904 NMSCEW/P-IV/STR/2019/6847 6847 Girder Km 200+200 LHS 20-Dec-19 8:00 AM
161,162,163,164 at bed no -04, Girder Type-02
6905 NMSCEW/P-IV/STR/2019/6848 6848 Checking of reinforcement, shuttering & pouring concrete for pier cap at LP-04 Viaduct Km 200+920 LHS 20-Dec-19 4:00 PM
6906 NMSCEW/P-IV/STR/2019/6849 6849 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-01 Viaduct Km 200+920 RHS 20-Dec-19 9:00 AM IPC-14
6907 NMSCEW/P-IV/STR/2019/6850 6850 Checking of reinforcement,shuttering and Pouring concrete for raft at RP-15 Viaduct Km 213+915 RHS 20-Dec-19 4:25 PM
6908 NMSCEW/P-IV/STR/2019/6851 6851 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-02 Viaduct Km 213+915 LHS 20-Dec-19 4:40 PM
6909 NMSCEW/P-IV/STR/2019/6852 6852 Checking of layout,level,structural excavation & laying concrete PCC(M-15) at abutment A2 MNB Km 186+550 LHS 20-Dec-19 10:00 AM
6910 NMSCEW/P-IV/STR/2019/6853 6853 Checking of layout,level,structural excavation & laying concrete PCC(M-15) MNB Km 181+078 LHS 20-Dec-19 4:05 PM
6911 NMSCEW/P-IV/STR/2019/6854 6854 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 4th lift at pier P-1 VOP Km 181+420 RHS 20-Dec-19 8:00 AM
6912 NMSCEW/P-IV/STR/2019/6855 6855 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 6th lift at pier P-3 VOP Km 181+420 LHS 20-Dec-19 10:00 AM
6913 NMSCEW/P-IV/STR/2019/6856 6856 Checking of reinforcement,shuttering and Pouring concrete(M-30) for raft at retaining wall A2 PUP Km 184+190 LHS 20-Dec-19 2:00 PM
6914 NMSCEW/P-IV/STR/2019/6857 6857 Checking of reinforcement,shuttering and Pouring concrete(M-35) for bottom slab MNB Km 189+705 20-Dec-19 4:00 PM
6915 NMSCEW/P-IV/STR/2019/6858 6858 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall W2 Box culvert Km 198+478 Km 00+000 LHS 20-Dec-19 11:00 AM IPC-11 Approved
6916 NMSCEW/P-IV/STR/2019/6859 6859 Checking of layout,level and Pouring concrete(M-30) for raft at retaining wall LA-1 MJB Km 205+610 LHS 21-Dec-19 9:00 AM
Checking of reinforcement,shuttering and Pouring concrete(M-45) for 1st lift at median wall
6917 NMSCEW/P-IV/STR/2019/6860 6860 MJB Km 205+610 21-Dec-19 12:00 PM
A-2 side
6918 NMSCEW/P-IV/STR/2019/6861 6861 Checking of reinforcement,shuttering and Pouring concrete for raft PUP Km 179+050 LHS 21-Dec-19 10:30 AM
Checking of layout,level,structural excavation & laying concrete PCC(M-10) for 2x2 utility
6919 NMSCEW/P-IV/STR/2019/6862 6862 Utility duct Km 183+500 BHS 21-Dec-19 2:00 PM
duct
6920 NMSCEW/P-IV/STR/2019/6863 6863 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 4th lift at wall A2 VUP Km 187+113 21-Dec-19 11:00 AM
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-1
6921 NMSCEW/P-IV/STR/2019/6864 6864 Box culvert Km 175+500 LHS 21-Dec-19 11:30 AM
I) 2x2 (2 to 4m) segment no.-295, 296, 297, 298, 299, 300
II) 2x2 (0 to 2m) segment no.- 488, 489, 490, 491, 492, 493, 494, 495
Checking of Shuttering,reinforcement & pouring concrete(M-45) for cross girder between RP-
6922 NMSCEW/P-IV/STR/2019/6865 6865 Viaduct Km 169+800 RHS 21-Dec-19 11:15 AM
10 to RP-11
6923 NMSCEW/P-IV/STR/2019/6866 6866 Checking of Shuttering,reinforcement & pouring concrete for 5th lift at median wall A1 & A2 VUP Km 166+987 21-Dec-19 2:15 PM
Checking of Shuttering,reinforcement & pouring concrete for 1st lift at retaining wall A1 &
6924 NMSCEW/P-IV/STR/2019/6867 6867 PUP Km 164+380 LHS 21-Dec-19 9:16 AM
A2
6925 NMSCEW/P-IV/STR/2019/6868 6868 Checking of layout,level and laying concrete PCC for wing wall A-1 VUP Km 176+614 LHS 21-Dec-19 12:10 PM
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
6926 NMSCEW/P-IV/STR/2019/6869 6869 Girder Km 200+200 LHS 21-Dec-19 11:45 AM
165,166,167,168 at bed no -03, Girder Type-02
6927 NMSCEW/P-IV/STR/2019/6870 6870 Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-2 Viaduct Km 195+900 LHS 21-Dec-19 3:30 PM
6928 NMSCEW/P-IV/STR/2019/6871 6871 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-2 Viaduct Km 196+560 LHS 21-Dec-19 2:50 PM
6929 NMSCEW/P-IV/STR/2019/6872 6872 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-5 Viaduct Km 200+920 RHS 21-Dec-19 4:00 PM
6930 NMSCEW/P-IV/STR/2019/6873 6873 Checking of reinforcement,shuttering and Pouring concrete for raft at RP-1 Viaduct Km 213+915 Km 00+000 RHS 21-Dec-19 4:30 PM IPC-11 Approved
6931 NMSCEW/P-IV/STR/2019/6874 6874 Checking of reinforcement,shuttering and Pouring concrete for raft at RP-13 Viaduct Km 213+915 Km 00+000 RHS 21-Dec-19 9:37 AM IPC-11 Approved AE
6932 NMSCEW/P-IV/STR/2019/6875 6875 Checking layout ,level, & laying concrete for PCC at RP-11 Viaduct Km 213+915 RHS 21-Dec-19 9:50 AM
6933 NMSCEW/P-IV/STR/2019/6876 6876 Checking of reinforcement, shuttering & pouring concrete for pier starter at LP-13 Viaduct Km 213+915 LHS 21-Dec-19 5:00 PM
6934 NMSCEW/P-IV/STR/2019/6877 6877 Checking of reinforcement, shuttering & pouring concrete for pier starter at RP-17 Viaduct Km 213+915 RHS 21-Dec-19 5:34 PM IPC-14
6935 NMSCEW/P-IV/STR/2019/6878 6878 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at retaining wall W2 PUP Km 193+880 LHS 21-Dec-19 11:05 AM
6936 NMSCEW/P-IV/STR/2019/6879 6879 Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at retaining wall W2 PUP Km 193+880 RHS 21-Dec-19 11:26 AM
6937 NMSCEW/P-IV/STR/2019/6880 6880 Checking of layout,level,structural excavation & laying concrete PCC(M-15) at abutment A2 MNB Km 186+550 LHS 21-Dec-19 10:00 AM
6938 NMSCEW/P-IV/STR/2019/6881 6881 Checking of reinforcement,shuttering and Pouring concrete(M-30) for 2nd lift at wall A1 MNB Km 181+700 RHS 21-Dec-19 9:06 AM
6939 NMSCEW/P-IV/STR/2019/6882 6882 Checking of layout,level,structural excavation & laying concrete PCC(M-15) MNB Km 189+705 BHS 21-Dec-19 11:17 AM
6940 NMSCEW/P-IV/STR/2019/6883 6883 Checking of Shuttering,reinforcement & pouring concrete(M-35) for bottom slab MNB Km 189+705 LHS 21-Dec-19 8:00 AM
6941 NMSCEW/P-IV/STR/2019/6884 6884 Checking of reinforcement,shuttering and Pouring concrete for raft (Main carriageway) PUP Km 211+210 22-Dec-19 10:30 AM
6942 NMSCEW/P-IV/STR/2019/6885 6885 Checking of reinforcement,shuttering and Pouring concrete for raft at retaining wall W1 PUP Km 208+930 LHS 22-Dec-19 8:00 AM
6943 NMSCEW/P-IV/STR/2019/6886 6886 Checking of bearing & grouting at LP-13 Viaduct Km 169+800 LHS 22-Dec-19 9:00 AM
6944 NMSCEW/P-IV/STR/2019/6887 6887 Checking of bearing & grouting at RP-11 & RP-13 Viaduct Km 169+800 RHS 22-Dec-19 9:30 AM
Checking for stressing and remove slagness of H.T. wires at Girder no-157,158,159,160 at bed
6945 NMSCEW/P-IV/STR/2019/6888 6888 Girder Km 200+200 LHS 22-Dec-19 11:00 AM
no -05, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -157,158,159,160 at bed no -05, Girder Type-01 at
6946 NMSCEW/P-IV/STR/2019/6889 6889 Girder Km 200+200 LHS 22-Dec-19 11:30 AM
casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-169,170,171,172 at bed
6947 NMSCEW/P-IV/STR/2019/6890 6890 Girder Km 200+200 LHS 22-Dec-19 12:00 PM
no -02, Girder Type-02 at casting yard camp -2
Checking of reinforcement Girder no -169,170,171,172 at bed no -02, Girder Type-02 at
6948 NMSCEW/P-IV/STR/2019/6891 6891 Girder Km 200+200 LHS 22-Dec-19 12:30 PM
casting yard camp -2
Checking of Shuttering,reinforcement & pouring concrete for 2nd lift at retaining wall A1 &
6949 NMSCEW/P-IV/STR/2019/6892 6892 PUP Km 164+380 LHS 22-Dec-19 2:00 PM
A2
Checking of Shuttering,reinforcement and Pouring concrete for RE WALL PANEL precast
TYPE -A
6950 NMSCEW/P-IV/STR/2019/6893 6893 258 NOS,TYPE B- 80 NOS, TYPE -Sta 15 NOS, TYPE -Stb 14 NOS, TYPE -Stc 15 NOS, RE Wall Panel Km 200+200 LHS 22-Dec-19 4:00 PM
TYPE -Std 15 NOS, TYPE -Lta 16 NOS, Ltc 16 NOS,TYPE -Ltd 7 NOS, at RE panel precast
yard camp 2
Checking of Shuttering,reinforcement & pouring concrete for cross girder between LP-04 to
6951 NMSCEW/P-IV/STR/2019/6894 6894 Viaduct Km 202+190 LHS 22-Dec-19 10:00 AM
LP-5
Checking of Shuttering,reinforcement & pouring concrete for cross girder between LP-05 to
6952 NMSCEW/P-IV/STR/2019/6895 6895 Viaduct Km 202+190 LHS 22-Dec-19 11:00 AM
LP-6
6953 NMSCEW/P-IV/STR/2019/6896 6896 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 1st lift at abutment A2 VOP Km 181+420 LHS 22-Dec-19 8:00 AM
6954 NMSCEW/P-IV/STR/2019/6897 6897 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 1st lift at abutment A1 VOP Km 181+420 RHS 22-Dec-19 9:00 AM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 2nd lift at retaining wall
6955 NMSCEW/P-IV/STR/2019/6898 6898 PUP Km 183+290 LHS 22-Dec-19 11:10 AM
A1
Checking of reinforcement,shuttering and Pouring concrete(M-30) for raft at retaining wall A1
6956 NMSCEW/P-IV/STR/2019/6899 6899 PUP Km 184+190 RHS 22-Dec-19 2:16 PM
& A2
6957 NMSCEW/P-IV/STR/2019/6900 6900 Checking of layout,level,structural excavation & laying concrete PCC(M-15) MNB Km 181+078 LHS 22-Dec-19 4:00 PM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 4th lift at retaining wall
6958 NMSCEW/P-IV/STR/2019/6901 6901 PUP Km 190+650 RHS 22-Dec-19 11:33 AM
A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 4th lift at retaining wall
6959 NMSCEW/P-IV/STR/2019/6902 6902 PUP Km 190+650 LHS 22-Dec-19 12:00 PM
A2
6960 NMSCEW/P-IV/STR/2019/6903 6903 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at median wall A-2 side MJB Km 205+610 23-Dec-19 10:00 AM
6961 NMSCEW/P-IV/STR/2019/6904 6904 Checking layout ,level, & laying concrete & Structural Excavation (M-15) for PCC at LP-1 MJB Km 205+610 Km 00+000 LHS 23-Dec-19 4:00 PM IPC-11 Approved
6962 NMSCEW/P-IV/STR/2019/6905 6905 Checking of Shuttering,reinforcement, pouring concrete for padestal at RP-7 Viaduct Km 202+190 RHS 23-Dec-19 2:30 PM
6963 NMSCEW/P-IV/STR/2019/6906 6906 Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-5 Viaduct Km 200+920 LHS 23-Dec-19 4:10 PM
6964 NMSCEW/P-IV/STR/2019/6907 6907 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-5 Viaduct Km 200+920 RHS 23-Dec-19 9:00 AM
6965 NMSCEW/P-IV/STR/2019/6908 6908 Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-2 Viaduct Km 195+900 Km 00+000 LHS 23-Dec-19 3:30 PM IPC-11 Approved AE
6966 NMSCEW/P-IV/STR/2019/6909 6909 Checking of Shuttering,reinforcement & pouring concrete for raft at RP-14 Viaduct Km 213+915 RHS 23-Dec-19 4:30 PM
6967 NMSCEW/P-IV/STR/2019/6910 6910 Checking layout ,level, & laying concrete for PCC at LP-14 Viaduct Km 213+915 LHS 23-Dec-19 9:18 AM
6968 NMSCEW/P-IV/STR/2019/6911 6911 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-13 Viaduct Km 213+915 LHS 23-Dec-19 4:20 PM
6969 NMSCEW/P-IV/STR/2019/6912 6912 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-15 Viaduct Km 213+915 LHS 23-Dec-19 4:46 PM
6970 NMSCEW/P-IV/STR/2019/6913 6913 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-2 Viaduct Km 213+915 LHS 23-Dec-19 9:26 AM
6971 NMSCEW/P-IV/STR/2019/6914 6914 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-17 Viaduct Km 213+915 LHS 23-Dec-19 3:33 PM
Checking of reinforcement,shuttering and Pouring concrete for 5th lift at median wall A1 &
6977 NMSCEW/P-IV/STR/2019/6920 6920 VUP Km 166+987 23-Dec-19 2:00 PM
A2
6978 NMSCEW/P-IV/STR/2019/6921 6921 Checking of reinforcement,shuttering and Pouring concrete for 4th lift at wall A1 & A2 VUP Km 165+790 RHS 23-Dec-19 2:30 PM
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-2
6979 NMSCEW/P-IV/STR/2019/6922 6922 Box culvert Km 200+200 LHS 24-Dec-19 10:30 AM
I) 2x2 (2 to 4m) segment no.-595,596,597,598
II) 3x3 (2 to 4m) segment no.-
155,156,157,158
6980 NMSCEW/P-IV/STR/2019/6923 6923 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall A1 & A2 PUP Km 177+810 BHS 24-Dec-19 10:30 AM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 4th lift at retaining wall
6981 NMSCEW/P-IV/STR/2019/6924 6924 PUP Km 190+650 LHS 24-Dec-19 11:00 AM
A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 4th lift at retaining wall
6982 NMSCEW/P-IV/STR/2019/6925 6925 PUP Km 190+650 RHS 24-Dec-19 11:30 AM
A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 4th lift at retaining wall
6983 NMSCEW/P-IV/STR/2019/6926 6926 PUP Km 188+575 RHS 24-Dec-19 3:00 PM
A1
Checking of layout,level,structural excavation & laying concrete PCC(M-10) at retaining wall
6984 NMSCEW/P-IV/STR/2019/6927 6927 PUP Km 188+575 RHS 24-Dec-19 4:00 PM
A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at retaining wall
6985 NMSCEW/P-IV/STR/2019/6928 6928 PUP Km 189+000 RHS 24-Dec-19 5:00 PM
A2
Checking of layout,level,structural excavation & laying concrete PCC(M-10) at retaining wall
6986 NMSCEW/P-IV/STR/2019/6929 6929 PUP Km 189+000 LHS 24-Dec-19 2:00 PM
A1
Checking of layout,level,structural excavation & laying concrete PCC(M-10) at retaining wall
6987 NMSCEW/P-IV/STR/2019/6930 6930 PUP Km 189+000 RHS 24-Dec-19 2:30 PM
A1
6988 NMSCEW/P-IV/STR/2019/6931 6931 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at median wall A1 LVUP Km 169+291 24-Dec-19 2:10 PM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at retaining wall
6989 NMSCEW/P-IV/STR/2019/6932 6932 PUP Km 183+290 LHS 24-Dec-19 11:05 AM
A1
Checking of reinforcement,shuttering and Pouring concrete(M-30) for raft at retaining wall
6990 NMSCEW/P-IV/STR/2019/6933 6933 PUP Km 184+190 RHS 24-Dec-19 4:00 PM
A1
6991 NMSCEW/P-IV/STR/2019/6934 6934 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 1st lift at abutment A2 VOP Km 181+420 LHS 24-Dec-19 8:00 AM
6992 NMSCEW/P-IV/STR/2019/6935 6935 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 1st lift at abutment A1 VOP Km 181+420 BHS 24-Dec-19 9:00 AM
6993 NMSCEW/P-IV/STR/2019/6936 6936 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 5th lift at pier P-1 VOP Km 181+420 RHS 24-Dec-19 10:00 AM
6994 NMSCEW/P-IV/STR/2019/6937 6937 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 1st lift at pier P-2 VOP Km 181+420 LHS 24-Dec-19 11:00 AM
6995 NMSCEW/P-IV/STR/2019/6938 6938 Checking of reinforcement,shuttering and Pouring concrete(M-35) for final lift at wall Loop-C MNB( Loop-C) Km 01+980 24-Dec-19 2:14 PM
6996 NMSCEW/P-IV/STR/2019/6939 6939 Checking of layout,level,structural excavation & laying concrete PCC(M-15) MNB Km 181+078 LHS 24-Dec-19 4:16 PM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for raft at retaining wall
6997 NMSCEW/P-IV/STR/2019/6940 6940 MJB Km 205+610 RHS 24-Dec-19 10:00 AM
RA1
Checking of reinforcement,shuttering and Pouring concrete(M-45) for 5th lift at abutment shaft
6998 NMSCEW/P-IV/STR/2019/6941 6941 MJB Km 205+610 RHS 24-Dec-19 4:00 PM
RA1
Checking for stressing and remove slagness of H.T. wires at Girder no-161,162,163,164 at bed
6999 NMSCEW/P-IV/STR/2019/6942 6942 Girder Km 200+200 LHS 24-Dec-19 6:00 PM
no -07, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -161,162,163,164 at bed no -07, Girder Type-01 at
7000 NMSCEW/P-IV/STR/2019/6943 6943 Girder Km 200+200 LHS 24-Dec-19 6:30 PM
casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-173,174,175,176 at bed
7001 NMSCEW/P-IV/STR/2019/6944 6944 Girder Km 200+200 LHS 24-Dec-19 5:00 PM
no -01, Girder Type-02 at casting yard camp -2
Checking of reinforcement Girder no -173,174,175,176 at bed no -01, Girder Type-02 at
7002 NMSCEW/P-IV/STR/2019/6945 6945 Girder Km 200+200 LHS 24-Dec-19 5:30 PM
casting yard camp -2
7003 NMSCEW/P-IV/STR/2019/6946 6946 Checking layout ,level, & laying concrete for PCC at LP-14 Viaduct Km 213+915 LHS 24-Dec-19 4:30 PM
7004 NMSCEW/P-IV/STR/2019/6947 6947 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-11 Viaduct Km 213+915 LHS 24-Dec-19 3:15 PM
7005 NMSCEW/P-IV/STR/2019/6948 6948 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-18 Viaduct Km 213+915 LHS 24-Dec-19 4:33 PM
7006 NMSCEW/P-IV/STR/2019/6949 6949 Checking of Shuttering,reinforcement, pouring concrete for padestal at RP-8 Viaduct Km 202+190 RHS 24-Dec-19 2:32 PM
7007 NMSCEW/P-IV/STR/2019/6950 6950 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at retaining wall W2 MNB Km 199+360 LHS 24-Dec-19 4:00 PM
7008 NMSCEW/P-IV/STR/2019/6951 6951 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall W2 Box culvert Km 198+478 Km 00+000 RHS 24-Dec-19 9:00 AM IPC-11 Approved
7009 NMSCEW/P-IV/STR/2019/6952 6952 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at retaining wall W2 PUP Km 193+880 LHS 24-Dec-19 2:00 PM
7010 NMSCEW/P-IV/STR/2019/6953 6953 Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at median wall W2 PUP Km 193+880 24-Dec-19 2:30 PM
7011 NMSCEW/P-IV/STR/2019/6954 6954 Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall W2 PUP Km 193+880 RHS 24-Dec-19 3:05 PM
7012 NMSCEW/P-IV/STR/2019/6955 6955 Checking of layout,level & laying concrete PCC(M-15) at median PUP Km 212+080 24-Dec-19 1:00 PM SPOT RFI
7013 NMSCEW/P-IV/STR/2019/6956 6956 Checking of reinforcement,shuttering and Pouring concrete for raft PUP Km 179+050 RHS 24-Dec-19 4:30 PM SPOT RFI
7014 NMSCEW/P-IV/STR/2019/6957 6957 Checking of layout,level,reinforcement,shuttering and Pouring concrete for slab PUP Km 206+985 Km 00+000 RHS 25-Dec-19 4:00 PM IPC-11 Approved
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at median wall W1 &
7015 NMSCEW/P-IV/STR/2019/6958 6958 PUP Km 206+985 25-Dec-19 2:00 PM
W2
7016 NMSCEW/P-IV/STR/2019/6959 6959 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at retaining wall W2 PUP Km 208+930 LHS 25-Dec-19 10:00 AM
7017 NMSCEW/P-IV/STR/2019/6960 6960 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at retaining wall W1 PUP Km 208+930 RHS 25-Dec-19 11:00 AM
7021 NMSCEW/P-IV/STR/2019/6964 6964 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at retaining wall W2 PUP Km 191+740 LHS 25-Dec-19 10:15 AM
7022 NMSCEW/P-IV/STR/2019/6965 6965 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at retaining wall W1 PUP Km 191+740 LHS 25-Dec-19 10:30 AM
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at retaining wall A1 &
7023 NMSCEW/P-IV/STR/2019/6966 6966 PUP Km 164+380 LHS 25-Dec-19 11:00 AM
A2
7024 NMSCEW/P-IV/STR/2019/6967 6967 Checking of Shuttering,reinforcement, pouring concrete for abutment cap at LA-1 Viaduct Km 169+800 LHS 25-Dec-19 4:00 PM
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-1
7025 NMSCEW/P-IV/STR/2019/6968 6968 Box culvert Km 175+500 LHS 25-Dec-19 10:40 AM
I) 2x2 (2 to 4m) segment no.-306,307,308,309,310,311,312, 313, 314, 315, 316, 317
II) 2x2 (0 to 2m) segment no.-504, 505, 506, 507
7026 NMSCEW/P-IV/STR/2019/6969 6969 Checking of reinforcement,shuttering and Pouring concrete for raft PUP Km 179+050 LHS 25-Dec-19 10:30 AM
7027 NMSCEW/P-IV/STR/2019/6970 6970 Checking of reinforcement,shuttering and Pouring concrete for raft at RA-1 MNB Km 174+173 RHS 25-Dec-19 4:10 PM
Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall A1 &
7028 NMSCEW/P-IV/STR/2019/6971 6971 PUP Km 165+790 LHS 25-Dec-19 5:30 PM
A2
7029 NMSCEW/P-IV/STR/2019/6972 6972 Checking of Shuttering,reinforcement & pouring concrete for raft at RP-1 Viaduct Km 213+915 RHS 25-Dec-19 9:00 AM
7030 NMSCEW/P-IV/STR/2019/6973 6973 Checking layout ,level, & laying concrete for PCC at LP-14 Viaduct Km 213+915 LHS 25-Dec-19 4:13 PM
7031 NMSCEW/P-IV/STR/2019/6974 6974 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-11 Viaduct Km 213+915 LHS 25-Dec-19 4:30 PM
7032 NMSCEW/P-IV/STR/2019/6975 6975 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-18 Viaduct Km 213+915 LHS 25-Dec-19 5:10 PM
7033 NMSCEW/P-IV/STR/2019/6976 6976 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-2 Viaduct Km 213+915 LHS 25-Dec-19 10:38 AM
7034 NMSCEW/P-IV/STR/2019/6977 6977 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-17 Viaduct Km 213+915 LHS 25-Dec-19 3:42 PM
7050 NMSCEW/P-IV/STR/2019/6993 6993 Checking of reinforcement,shuttering and Pouring concrete(M-35) for top slab at loop -C MNB loop-C Km 01+980 25-Dec-19 4:00 PM
7051 NMSCEW/P-IV/STR/2019/6994 6994 Checking of layout,level,structural excavation & laying concrete PCC(M-15) at abutment A1 VUP Km 182+420 LHS 25-Dec-19 10:00 AM
Checking of reinforcement, shuttering & pouring concrete(M-45) for abutment shaft 5th
7052 NMSCEW/P-IV/STR/2019/6995 6995 MJB Km 205+610 RHS 26-Dec-19 10:00 AM
lift(final lift) at RA-1
7053 NMSCEW/P-IV/STR/2019/6996 6996 Checking of layout,level,reinforcement,shuttering and Pouring concrete for slab MNB Km 199+360 Km 00+000 LHS 26-Dec-19 5:00 PM IPC-11 Approved
7054 NMSCEW/P-IV/STR/2019/6997 6997 Checking of layout,level,reinforcement,shuttering and Pouring concrete for slab Box culvert Km 208+675 RHS 26-Dec-19 8:00 AM
7055 NMSCEW/P-IV/STR/2019/6998 6998 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at retaining wall W2 PUP Km 208+930 RHS 26-Dec-19 12:00 PM
7056 NMSCEW/P-IV/STR/2019/6999 6999 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at retaining wall W1 PUP Km 208+930 RHS 26-Dec-19 1:00 PM
7057 NMSCEW/P-IV/STR/2019/7000 7000 Checking of layout,level & laying concrete PCC at box culvert ( Service road) Box culvert Km 206+843 LHS 26-Dec-19 10:00 AM
7058 NMSCEW/P-IV/STR/2019/7001 7001 Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at retaining wall W2 PUP Km 193+880 LHS 26-Dec-19 11:00 AM
7059 NMSCEW/P-IV/STR/2019/7002 7002 Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at median wall W2 PUP Km 193+880 26-Dec-19 11:30 AM
7060 NMSCEW/P-IV/STR/2019/7003 7003 Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall W2 PUP Km 193+880 RHS 26-Dec-19 12:30 PM
7061 NMSCEW/P-IV/STR/2019/7004 7004 Checking of completion of segment erection for 3x3 box culvert Box culvert Km 191+870 Km 00+000 BHS 26-Dec-19 10:30 AM IPC-11 Approved
7062 NMSCEW/P-IV/STR/2019/7005 7005 Checking of completion of segment erection for 3x3 box culvert Box culvert Km 193+484 Km 00+000 BHS 26-Dec-19 2:20 PM IPC-11 Approved
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 4th lift at retaining wall
7063 NMSCEW/P-IV/STR/2019/7006 7006 PUP Km 188+575 RHS 26-Dec-19 9:00 AM
A1 side
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 4th lift at retaining wall
7064 NMSCEW/P-IV/STR/2019/7007 7007 PUP Km 190+650 LHS 26-Dec-19 11:00 AM
A2 side
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 4th lift at retaining wall
7065 NMSCEW/P-IV/STR/2019/7008 7008 PUP Km 190+650 RHS 26-Dec-19 11:30 AM
A2 side
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 4th lift at retaining wall
7066 NMSCEW/P-IV/STR/2019/7009 7009 PUP Km 189+000 RHS 26-Dec-19 3:00 PM
A2 side
7067 NMSCEW/P-IV/STR/2019/7010 7010 Checking of reinforcement,shuttering and Pouring concrete(M-30) for 5th lift at wall A2 side VUP Km 187+113 BHS 26-Dec-19 4:00 PM
7070 NMSCEW/P-IV/STR/2019/7013 7013 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 2nd lift at abutment A2 VOP Km 181+420 LHS 26-Dec-19 5:00 PM
7071 NMSCEW/P-IV/STR/2019/7014 7014 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 2nd lift at pier P2 VOP Km 181+420 LHS 26-Dec-19 8:00 AM
7072 NMSCEW/P-IV/STR/2019/7015 7015 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 6th lift at pier P1 VOP Km 181+420 RHS 26-Dec-19 11:00 AM
7073 NMSCEW/P-IV/STR/2019/7016 7016 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 2nd lift at abutment A1 VOP Km 181+420 RHS 26-Dec-19 4:23 PM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 4th lift at wall A1 &
7074 NMSCEW/P-IV/STR/2019/7017 7017 MNB Km 181+700 LHS 26-Dec-19 4:40 PM
A2 side
7075 NMSCEW/P-IV/STR/2019/7018 7018 Checking of reinforcement,shuttering and Pouring concrete(M-35) for raft at abutment A1 VUP Km 182+420 RHS 26-Dec-19 11:00 AM
Checking of reinforcement,shuttering and Pouring concrete for raft with bottom haunch A1 &
7076 NMSCEW/P-IV/STR/2019/7019 7019 PUP Km 168+380 RHS 26-Dec-19 5:00 PM
A2 side
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-1
7077 NMSCEW/P-IV/STR/2019/7020 7020 Box culvert Km 175+500 LHS 26-Dec-19 10:05 AM
I) 3x3 (0 to 2m) segment no.-26,27,13,16
7078 NMSCEW/P-IV/STR/2019/7021 7021 Checking of Shuttering,reinforcement & pouring concrete for raft at LA-2 Viaduct Km 196+560 LHS 26-Dec-19 12:30 PM
Checking for stressing and remove slagness of H.T. wires at Girder no-177,178,179,180 at bed
7079 NMSCEW/P-IV/STR/2019/7022 7022 Girder Km 200+200 LHS 26-Dec-19 5:00 PM
no -04, Girder Type-02 at casting yard camp -2
Checking of reinforcement Girder no -177,178,179,180 at bed no -04, Girder Type-02 at
7080 NMSCEW/P-IV/STR/2019/7023 7023 Girder Km 200+200 LHS 26-Dec-19 5:30 PM
casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-165,166,167,168 at bed
7081 NMSCEW/P-IV/STR/2019/7024 7024 Girder Km 200+200 LHS 26-Dec-19 6:00 PM
no -08, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -165,166,167,168 at bed no -08, Girder Type-01 at
7082 NMSCEW/P-IV/STR/2019/7025 7025 Girder Km 200+200 LHS 26-Dec-19 6:30 PM
casting yard camp -2
7083 NMSCEW/P-IV/STR/2019/7026 7026 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-15 Viaduct Km 213+915 LHS 26-Dec-19 11:30 AM
7084 NMSCEW/P-IV/STR/2019/7027 7027 Checking of Errection and jointing of segments for Utility duct (2x2) Utility duct Km 165+020 BHS 26-Dec-19 10:24 AM
Checking of layout,level,structural excavation & laying concrete PCC(M-10) at 3x3 box
7085 NMSCEW/P-IV/STR/2019/7028 7028 Box culvert Km 184+823 BHS 27-Dec-19 3:30 PM
culvert
Checking of reinforcement,shuttering and Pouring concrete for 4th lift at U type retaining wall
7086 NMSCEW/P-IV/STR/2019/7029 7029 VUP Km 176+614 27-Dec-19 10:30 AM
A1 & A2
7087 NMSCEW/P-IV/STR/2019/7030 7030 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall A1 & A2 Box culvert Km 180+180 RHS 27-Dec-19 12:30 PM
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at retaining wall A1 &
7088 NMSCEW/P-IV/STR/2019/7031 7031 PUP Km 177+810 RHS 27-Dec-19 5:30 PM
A2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
7089 NMSCEW/P-IV/STR/2019/7032 7032 Girder Km 200+200 LHS 27-Dec-19 5:30 PM
177,178,179,180 at bed no -04, Girder Type-02
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
7090 NMSCEW/P-IV/STR/2019/7033 7033 Girder Km 200+200 LHS 27-Dec-19 6:30 PM
165,166,167,168 at bed no -08, Girder Type-01
Checking of reinforcement,shuttering and Pouring concrete(M-30) for raft at retaining wall
7091 NMSCEW/P-IV/STR/2019/7034 7034 PUP Km 188+575 RHS 27-Dec-19 2:00 PM
A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for raft at retaining wall
7092 NMSCEW/P-IV/STR/2019/7035 7035 PUP Km 189+000 LHS 27-Dec-19 3:00 PM
A1
Checking of reinforcement,shuttering and Pouring concrete(M-30) for raft at retaining wall
7093 NMSCEW/P-IV/STR/2019/7036 7036 PUP Km 189+000 RHS 27-Dec-19 5:00 PM
A1
7094 NMSCEW/P-IV/STR/2019/7037 7037 Checking of reinforcement,shuttering and Pouring concrete for raft at LA1 MNB Km 174+173 LHS 27-Dec-19 4:00 PM
7095 NMSCEW/P-IV/STR/2019/7038 7038 Checking of Shuttering,reinforcement, pouring concrete for pier cap at RP-4 Viaduct Km 196+560 Km 00+000 RHS 27-Dec-19 3:30 PM IPC-11 Approved
7096 NMSCEW/P-IV/STR/2019/7039 7039 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at retaining wall W1 PUP Km 191+740 LHS 27-Dec-19 11:00 AM
7097 NMSCEW/P-IV/STR/2019/7040 7040 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at retaining wall W2 PUP Km 191+740 LHS 27-Dec-19 11:30 AM
7098 NMSCEW/P-IV/STR/2019/7041 7041 Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at retaining wall W2 MNB Km 199+360 LHS 27-Dec-19 2:00 PM
7099 NMSCEW/P-IV/STR/2019/7042 7042 Checking of layout,level,reinforcement,shuttering and Pouring concrete for slab Box culvert Km 198+478 Km 00+000 LHS 27-Dec-19 5:00 PM IPC-11 Approved
7100 NMSCEW/P-IV/STR/2019/7043 7043 Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-5 Viaduct Km 200+920 Km 00+000 LHS 27-Dec-19 3:00 PM IPC-11 Approved AE
7101 NMSCEW/P-IV/STR/2019/7044 7044 Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-3 Viaduct Km 200+920 Km 00+000 LHS 27-Dec-19 3:30 PM IPC-11 Approved AE
7102 NMSCEW/P-IV/STR/2019/7045 7045 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-1 Viaduct Km 200+920 LHS 27-Dec-19 10:00 AM
Checking of reinforcement, shuttering & pouring concrete for abutment column 1st & final lift
7103 NMSCEW/P-IV/STR/2019/7046 7046 Viaduct Km 200+920 LHS 27-Dec-19 4:00 PM
at LA-1
7104 NMSCEW/P-IV/STR/2019/7047 7047 Checking layout ,level, & laying concrete for PCC at LP-14 Viaduct Km 213+915 LHS 27-Dec-19 4:30 PM
7105 NMSCEW/P-IV/STR/2019/7048 7048 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-11 Viaduct Km 213+915 LHS 27-Dec-19 4:45 PM
7106 NMSCEW/P-IV/STR/2019/7049 7049 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-18 Viaduct Km 213+915 LHS 27-Dec-19 5:15 PM
7107 NMSCEW/P-IV/STR/2019/7050 7050 Checking of Shuttering,reinforcement & pouring concrete for pier starter at RP-13 Viaduct Km 213+915 RHS 27-Dec-19 5:30 PM
7108 NMSCEW/P-IV/STR/2019/7051 7051 Checking of Shuttering,reinforcement, pouring concrete for padestal at RP-8 Viaduct Km 202+190 RHS 27-Dec-19 2:30 PM
Checking of Shuttering,reinforcement & pouring concrete for cross girder between LP-6 to
7109 NMSCEW/P-IV/STR/2019/7052 7052 Viaduct Km 202+190 LHS 27-Dec-19 3:00 PM
LP-7
Checking of Shuttering,reinforcement & pouring concrete for cross girder between LP-5 to
7110 NMSCEW/P-IV/STR/2019/7053 7053 Viaduct Km 202+190 LHS 27-Dec-19 3:30 PM
LP-6
7111 NMSCEW/P-IV/STR/2019/7054 7054 Checking of Shuttering,reinforcement, pouring concrete for pier cap at RP-12 Viaduct Km 202+190 RHS 27-Dec-19 2:00 PM
Checking of layout,level,structural excavation & laying concrete PCC(M-15) for footing at
7112 NMSCEW/P-IV/STR/2019/7055 7055 MNB Km 186+550 LHS 27-Dec-19 11:00 AM
abutment A2
7113 NMSCEW/P-IV/STR/2019/7056 7056 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 2nd lift at abutment A2 VOP Km 181+420 LHS 27-Dec-19 10:00 AM
7114 NMSCEW/P-IV/STR/2019/7057 7057 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 3rd lift at pier P-2 VOP Km 181+420 LHS 27-Dec-19 4:00 PM
7115 NMSCEW/P-IV/STR/2019/7058 7058 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 2nd lift at abutment A1 VOP Km 181+420 RHS 27-Dec-19 4:15 PM
7116 NMSCEW/P-IV/STR/2019/7059 7059 Checking of reinforcement,shuttering and Pouring concrete(M-30) for 4th lift at wall A1 & A2 MNB Km 181+700 Km 00+000 LHS 27-Dec-19 10:00 AM IPC-11 DONE
7117 NMSCEW/P-IV/STR/2019/7060 7060 Checking of level,Shuttering,reinforcement & pouring concrete for raft at LP-12 Viaduct Km 213+915 Km 00+000 LHS 27-Dec-19 3:19 PM IPC-11 Approved AE
7118 NMSCEW/P-IV/STR/2019/7061 7061 Checking of level,Shuttering,reinforcement & pouring concrete for raft at RP-14 Viaduct Km 213+915 Km 00+000 RHS 27-Dec-19 4:33 PM IPC-11 Approved
7119 NMSCEW/P-IV/STR/2019/7062 7062 Checking of Errection and jointing of segments for Utility duct (2x2) Utility duct Km 183+500 BHS 27-Dec-19 10:10 AM
Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall A1 &
7120 NMSCEW/P-IV/STR/2019/7063 7063 PUP Km 165+790 LHS 27-Dec-19 11:00 AM SPOT RFI
A2 side
7121 NMSCEW/P-IV/STR/2019/7064 7064 Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-3 Viaduct Km 195+900 Km 00+000 LHS 28-Dec-19 3:30 PM IPC-11 Approved
7122 NMSCEW/P-IV/STR/2019/7065 7065 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-4 Viaduct Km 195+900 LHS 28-Dec-19 3:00 PM
Checking for stressing and remove slagness of H.T. wires at Girder no-169,170,171,172 at bed
7123 NMSCEW/P-IV/STR/2019/7066 7066 Girder Km 200+200 LHS 28-Dec-19 2:00 PM
no -06, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -169,170,171,172 at bed no -06, Girder Type-01 at
7124 NMSCEW/P-IV/STR/2019/7067 7067 Girder Km 200+200 LHS 28-Dec-19 2:30 PM
casting yard camp -2
7125 NMSCEW/P-IV/STR/2019/7068 7068 Checking of Shuttering,reinforcement & pouring concrete for raft at RP-2 Viaduct Km 213+915 Km 00+000 RHS 28-Dec-19 4:00 PM IPC-11 Approved
7126 NMSCEW/P-IV/STR/2019/7069 7069 Checking of Shuttering,reinforcement & pouring concrete for raft at RP-16 Viaduct Km 213+915 RHS 28-Dec-19 4:30 PM
7127 NMSCEW/P-IV/STR/2019/7070 7070 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-15 Viaduct Km 213+915 LHS 28-Dec-19 3:15 PM
7128 NMSCEW/P-IV/STR/2019/7071 7071 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-18 Viaduct Km 213+915 LHS 28-Dec-19 3:45 PM
7129 NMSCEW/P-IV/STR/2019/7072 7072 Checking layout ,level, & laying concrete for PCC at RP-8 Viaduct Km 213+915 RHS 28-Dec-19 4:15 PM
7130 NMSCEW/P-IV/STR/2019/7073 7073 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-17 Viaduct Km 213+915 LHS 28-Dec-19 9:00 AM IPC-14
7131 NMSCEW/P-IV/STR/2019/7074 7074 Checking of Shuttering,reinforcement, pouring concrete for padestal at RP-9 Viaduct Km 202+190 RHS 28-Dec-19 2:30 PM
7132 NMSCEW/P-IV/STR/2019/7075 7075 Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-2 Viaduct Km 196+560 Km 00+000 LHS 28-Dec-19 4:45 PM IPC-11 Approved
7133 NMSCEW/P-IV/STR/2019/7076 7076 Checking of Shuttering,reinforcement & pouring concrete for raft at LA-1 Viaduct Km 196+560 Km 00+000 LHS 28-Dec-19 9:30 AM IPC-11 Approved AE
Checking of layout,level,structural excavation & laying concrete PCC(M-10) at 3x3 box
7134 NMSCEW/P-IV/STR/2019/7077 7077 Box culvert Km 184+823 BHS 28-Dec-19 10:00 AM
culvert
7135 NMSCEW/P-IV/STR/2019/7078 7078 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall A1 side Box culvert Km 162+832 LHS 28-Dec-19 2:00 PM
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at retaining wall A1 &
7136 NMSCEW/P-IV/STR/2019/7079 7079 PUP Km 177+810 LHS 28-Dec-19 10:30 AM
A2
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at retaining wall A1 &
7137 NMSCEW/P-IV/STR/2019/7080 7080 PUP Km 177+810 RHS 28-Dec-19 4:35 PM
A2
Checking of Shuttering,reinforcement & pouring concrete for raft with bottom haunch A1 &
7138 NMSCEW/P-IV/STR/2019/7081 7081 Box culvert Km 168+330 RHS 28-Dec-19 4:05 PM
A2 side
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-1
7139 NMSCEW/P-IV/STR/2019/7082 7082 Box culvert Km 175+500 LHS 28-Dec-19 10:25 AM
I) 2x2 (2 to 4m) segment no.- 318,319,320,,321,322, 323, 324, 325, 326
II) 3x3 (0 to 2m) segment no.-30, 31, 32, 33
7140 NMSCEW/P-IV/STR/2019/7083 7083 Checking of excavated bed layout,level, & laying concrete PCC(M-10) at retaining wall A2 PUP Km 183+290 LHS 28-Dec-19 1:00 PM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 1st lift at retaining wall
7141 NMSCEW/P-IV/STR/2019/7084 7084 PUP Km 188+575 RHS 28-Dec-19 2:00 PM
A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 1st lift at retaining wall
7142 NMSCEW/P-IV/STR/2019/7085 7085 PUP Km 189+000 LHS 28-Dec-19 3:00 PM
A1
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 1st lift at retaining wall
7143 NMSCEW/P-IV/STR/2019/7086 7086 PUP Km 189+000 RHS 28-Dec-19 3:20 PM
A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at retaining wall
7144 NMSCEW/P-IV/STR/2019/7087 7087 PUP Km 184+190 RHS 28-Dec-19 5:00 PM
A1 & A2
Checking of Shuttering,reinforcement & pouring concrete for raft with bottom haunch A1 &
7145 NMSCEW/P-IV/STR/2019/7088 7088 PUP Km 168+380 RHS 28-Dec-19 4:23 PM
A2 side
7146 NMSCEW/P-IV/STR/2019/7089 7089 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LA-2 Viaduct Km 202+190 Km 00+000 LHS 28-Dec-19 2:31 PM IPC-11 Approved
7147 NMSCEW/P-IV/STR/2019/7090 7090 Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-11 Viaduct Km 202+190 Km 00+000 LHS 28-Dec-19 3:16 PM IPC-11 Approved
7148 NMSCEW/P-IV/STR/2019/7091 7091 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 3rd lift at abutment A2 VOP Km 181+420 LHS 28-Dec-19 2:00 PM
7149 NMSCEW/P-IV/STR/2019/7092 7092 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 4th lift at pier P-2 VOP Km 181+420 LHS 28-Dec-19 4:00 PM
7150 NMSCEW/P-IV/STR/2019/7093 7093 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 3rd lift at abutment A1 VOP Km 181+420 RHS 28-Dec-19 4:40 PM
7151 NMSCEW/P-IV/STR/2019/7094 7094 Checking of excavated bed layout,level, & laying concrete PCC(M-15) at abutment A2 VUP Km 182+420 BHS 28-Dec-19 10:08 AM
7152 NMSCEW/P-IV/STR/2019/7095 7095 Checking of completion of segment erection for 2×2 utility duct Utility duct Km 192+130 Km 00+000 BHS 28-Dec-19 9:40 AM IPC-11 Approved
7153 NMSCEW/P-IV/STR/2019/7096 7096 Checking of layout,level,reinforcement,shuttering and Pouring concrete for slab PUP Km 212+080 Km 00+000 LHS 28-Dec-19 8:00 AM IPC-11 Approved
7154 NMSCEW/P-IV/STR/2019/7097 7097 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall W2 Box culvert Km 193+940 RHS 28-Dec-19 2:05 PM
7155 NMSCEW/P-IV/STR/2019/7098 7098 Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall W2 MNB Km 199+360 LHS 28-Dec-19 4:07 PM
7156 NMSCEW/P-IV/STR/2019/7099 7099 Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at wall W2 MNB Km 199+360 RHS 28-Dec-19 4:33 PM
7157 NMSCEW/P-IV/STR/2019/7100 7100 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at retaining wall W1 PUP Km 208+930 RHS 29-Dec-19 10:00 AM
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-2
7158 NMSCEW/P-IV/STR/2019/7101 7101 Box culvert Km 200+200 LHS 29-Dec-19 11:00 AM
I) 3x3 (2 to 4m) segment no.-159,160,161,162,163,164,165
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at retaining wall A1 &
7159 NMSCEW/P-IV/STR/2019/7102 7102 PUP Km 177+810 LHS 29-Dec-19 12:30 PM
A2
Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall A1 &
7160 NMSCEW/P-IV/STR/2019/7103 7103 PUP Km 177+810 RHS 29-Dec-19 4:30 PM
A2
7161 NMSCEW/P-IV/STR/2019/7104 7104 Checking of reinforcement,shuttering and Pouring concrete for raft at U type retaining wall PUP Km 179+050 29-Dec-19 10:30 AM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at retaining wall
7162 NMSCEW/P-IV/STR/2019/7105 7105 PUP Km 184+190 LHS 29-Dec-19 5:00 PM
A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 2nd lift at retaining
7163 NMSCEW/P-IV/STR/2019/7106 7106 PUP Km 188+575 RHS 29-Dec-19 2:00 PM
wall A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 2nd lift at retaining
7164 NMSCEW/P-IV/STR/2019/7107 7107 PUP Km 189+000 LHS 29-Dec-19 3:00 PM
wall A1
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 2nd lift at retaining
7165 NMSCEW/P-IV/STR/2019/7108 7108 PUP Km 189+000 RHS 29-Dec-19 3:30 PM
wall A2
7166 NMSCEW/P-IV/STR/2019/7109 7109 Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-7 Viaduct Km 195+900 Km 00+000 RHS 29-Dec-19 3:45 PM IPC-11 Approved
7167 NMSCEW/P-IV/STR/2019/7110 7110 Checking of lavel and layout for bearing fixing at LP-6 Viaduct Km 202+190 LHS 29-Dec-19 12:00 PM
7168 NMSCEW/P-IV/STR/2019/7111 7111 Checking of lavel and layout for bearing fixing at LP-5 Viaduct Km 202+190 LHS 29-Dec-19 12:30 PM
Checking of Shuttering,reinforcement & pouring concrete for cross girder between LP-5 to
7169 NMSCEW/P-IV/STR/2019/7112 7112 Viaduct Km 202+190 LHS 29-Dec-19 12:22 PM
LP-6
Checking of Shuttering,reinforcement & pouring concrete for cross girder between LP-6 to
7170 NMSCEW/P-IV/STR/2019/7113 7113 Viaduct Km 202+190 LHS 29-Dec-19 12:10 PM
LP-7
7171 NMSCEW/P-IV/STR/2019/7114 7114 Checking of level,Shuttering,reinforcement & pouring concrete for raft at RP-11 Viaduct Km 213+915 RHS 29-Dec-19 12:30 PM
7172 NMSCEW/P-IV/STR/2019/7115 7115 Checking layout ,level, & laying concrete for PCC at RP-12 Viaduct Km 213+915 RHS 29-Dec-19 12:45 PM
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
7173 NMSCEW/P-IV/STR/2019/7116 7116 Girder Km 200+200 LHS 29-Dec-19 8:00 AM
169,170,171,172 at bed no -06, Girder Type-01
7174 NMSCEW/P-IV/STR/2019/7117 7117 Checking of reinforcement, shuttering & pouring concrete for pier shaft 2nd lift at LP-1 Viaduct Km 196+560 LHS 29-Dec-19 10:30 AM IPC-14
Checking of reinforcement,shuttering and Pouring concrete for final lift at U type retaining
7175 NMSCEW/P-IV/STR/2019/7118 7118 LVUP Km 178+323 29-Dec-19 2:25 PM
wall A1 & A2
Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall A1 &
7176 NMSCEW/P-IV/STR/2019/7119 7119 PUP Km 164+380 LHS 29-Dec-19 3:00 PM
A2
Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall A1 &
7177 NMSCEW/P-IV/STR/2019/7120 7120 PUP Km 164+380 RHS 29-Dec-19 11:00 AM
A2
Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall A1 &
7178 NMSCEW/P-IV/STR/2019/7121 7121 PUP Km 165+300 RHS 29-Dec-19 10:00 AM
A2
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at retaining wall A1 &
7179 NMSCEW/P-IV/STR/2019/7122 7122 PUP Km 165+300 LHS 29-Dec-19 10:37 AM
A2
7180 NMSCEW/P-IV/STR/2019/7123 7123 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 3rd lift at abutment A1 VOP Km 181+420 RHS 29-Dec-19 2:00 PM
7181 NMSCEW/P-IV/STR/2019/7124 7124 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 1st lift at abutment A1 VOP Km 181+420 LHS 29-Dec-19 4:00 PM
7182 NMSCEW/P-IV/STR/2019/7125 7125 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 4th lift at pier P-2 VOP Km 181+420 LHS 29-Dec-19 4:25 PM
7183 NMSCEW/P-IV/STR/2019/7126 7126 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 3rd lift at abutment A2 VOP Km 181+420 LHS 29-Dec-19 5:00 PM
7184 NMSCEW/P-IV/STR/2019/7127 7127 Checking of excavated bed layout,level, & laying concrete PCC(M-15) at abutment A2 VUP Km 182+420 RHS 29-Dec-19 11:26 AM
7185 NMSCEW/P-IV/STR/2019/7128 7128 Checking of reinforcement,shuttering and Pouring concrete(M-35) for raft at abutment A1 VUP Km 182+420 RHS 29-Dec-19 12:30 PM
7186 NMSCEW/P-IV/STR/2019/7129 7129 Checking of reinforcement,shuttering and Pouring concrete(M-30) for final lift at A1 & A2 MNB Km 181+700 Km 00+000 LHS 29-Dec-19 9:52 AM IPC-11 DONE
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 4th lift at retaining wall
7187 NMSCEW/P-IV/STR/2019/7130 7130 PUP Km 183+290 LHS 29-Dec-19 5:00 PM
A1
Checking of layout, level,Shuttering,reinforcement & pouring concrete(M-45) for pier raft at
7188 NMSCEW/P-IV/STR/2019/7131 7131 MJB Km 205+610 Km 00+000 LHS 30-Dec-19 4:00 PM IPC-11 Approved
LP-1
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at retaining wall A1 &
7189 NMSCEW/P-IV/STR/2019/7132 7132 PUP Km 165+300 LHS 30-Dec-19 11:00 AM
A2
Checking of Shuttering,reinforcement & pouring concrete for raft with bottom haunch A1 &
7190 NMSCEW/P-IV/STR/2019/7133 7133 Box culvert Km 168+330 BHS 30-Dec-19 9:00 AM
A2 side
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at median wall A1 &
7191 NMSCEW/P-IV/STR/2019/7134 7134 LVUP Km 169+291 30-Dec-19 2:00 PM
A2
7192 NMSCEW/P-IV/STR/2019/7135 7135 Checking of level,Shuttering,reinforcement & pouring concrete for raft at RP-18 Viaduct Km 213+915 RHS 30-Dec-19 3:00 PM
7193 NMSCEW/P-IV/STR/2019/7136 7136 Checking of level,Shuttering,reinforcement & pouring concrete for raft at LA-2 Viaduct Km 213+915 LHS 30-Dec-19 4:30 PM
7194 NMSCEW/P-IV/STR/2019/7137 7137 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-15 Viaduct Km 213+915 LHS 30-Dec-19 3:15 PM
7195 NMSCEW/P-IV/STR/2019/7138 7138 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-18 Viaduct Km 213+915 LHS 30-Dec-19 3:30 PM
7196 NMSCEW/P-IV/STR/2019/7139 7139 Checking layout ,level, & laying concrete for PCC at RP-7 Viaduct Km 213+915 RHS 30-Dec-19 4:15 PM
7197 NMSCEW/P-IV/STR/2019/7140 7140 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP-17 Viaduct Km 213+915 RHS 30-Dec-19 4:45 PM
7198 NMSCEW/P-IV/STR/2019/7141 7141 Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-2 Viaduct Km 200+920 Km 00+000 LHS 30-Dec-19 10:00 AM IPC-11 Approved AE
7199 NMSCEW/P-IV/STR/2019/7142 7142 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-2 Viaduct Km 200+920 RHS 30-Dec-19 4:05 PM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at retaining wall
7200 NMSCEW/P-IV/STR/2019/7143 7143 PUP Km 188+575 RHS 30-Dec-19 2:00 PM
A2 side
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at retaining wall
7201 NMSCEW/P-IV/STR/2019/7144 7144 PUP Km 189+000 RHS 30-Dec-19 3:00 PM
A1 side
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at retaining wall
7202 NMSCEW/P-IV/STR/2019/7145 7145 PUP Km 189+000 LHS 30-Dec-19 4:00 PM
A1 side
7203 NMSCEW/P-IV/STR/2019/7146 7146 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 4th lift at wall A1 side VUP Km 187+113 30-Dec-19 5:00 PM
7207 NMSCEW/P-IV/STR/2019/7150 7150 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 4th lift at abutment A2 VOP Km 181+420 LHS 30-Dec-19 2:00 PM
7208 NMSCEW/P-IV/STR/2019/7151 7151 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 5th lift at pier P-2 VOP Km 181+420 LHS 30-Dec-19 4:00 PM
7209 NMSCEW/P-IV/STR/2019/7152 7152 Checking of Shuttering,reinforcement & pouring concrete(M-30) for top slab with top haunch MNB Km 181+700 Km 00+000 LHS 30-Dec-19 11:30 AM IPC-11 DONE
7210 NMSCEW/P-IV/STR/2019/7153 7153 Checking of layout,level,reinforcement,shuttering and Pouring concrete for slab Box culvert Km 198+478 Km 00+000 RHS 30-Dec-19 5:00 PM IPC-11 Approved
Checking for stressing and remove slagness of H.T. wires at Girder no-173,174,175,176 at bed
7211 NMSCEW/P-IV/STR/2019/7154 7154 Girder Km 200+200 LHS 31-Dec-19 4:00 PM
no -05, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -173,174,175,176 at bed no -05, Girder Type-01 at
7212 NMSCEW/P-IV/STR/2019/7155 7155 Girder Km 200+200 LHS 31-Dec-19 4:30 PM
casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-181,182,183,184 at bed
7213 NMSCEW/P-IV/STR/2019/7156 7156 Girder Km 200+200 LHS 31-Dec-19 11:30 AM
no -02, Girder Type-02 at casting yard camp -2
Checking of reinforcement Girder no -181,182,183,184 at bed no -02, Girder Type-02 at
7214 NMSCEW/P-IV/STR/2019/7157 7157 Girder Km 200+200 LHS 31-Dec-19 12:00 PM
casting yard camp -2
7215 NMSCEW/P-IV/STR/2019/7158 7158 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-4 Viaduct Km 195+900 LHS 31-Dec-19 11:00 AM IPC-14
7224 NMSCEW/P-IV/STR/2019/7167 7167 Checking of Shuttering,reinforcement, pouring concrete for pier cap at RP-5 Viaduct Km 200+920 RHS 31-Dec-19 4:15 PM
7225 NMSCEW/P-IV/STR/2019/7168 7168 Checking layout ,level, & laying concrete for PCC at RP-12 Viaduct Km 213+915 RHS 31-Dec-19 4:25 PM
7226 NMSCEW/P-IV/STR/2019/7169 7169 Checking of Shuttering,reinforcement & pouring concrete for pier starter at RP-1 Viaduct Km 213+915 RHS 31-Dec-19 4:50 PM
7227 NMSCEW/P-IV/STR/2019/7170 7170 Checking of Shuttering,reinforcement, pouring concrete for pier cap at LA-2 Viaduct Km 202+190 Km 00+000 LHS 31-Dec-19 2:44 PM IPC-11 Approved
Checking of excavated bed layout,level, & laying concrete PCC(M-15) for box culvert at loop- Box
7228 NMSCEW/P-IV/STR/2019/7171 7171 Km 0+457.121 31-Dec-19 3:13 PM
D culvert(Loop-D)
Checking of Shuttering,reinforcement & pouring concrete(M-45) for deck slab module LP-4 to
7229 NMSCEW/P-IV/STR/2019/7172 7172 Viaduct Km 169+800 LHS 31-Dec-19 9:30 AM
LP-7
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at retaining wall
7230 NMSCEW/P-IV/STR/2019/7173 7173 PUP Km 184+190 RHS 31-Dec-19 5:00 PM
A1 & A2
7231 NMSCEW/P-IV/STR/2019/7174 7174 Checking of completion of segment erection for 2×2 utility duct Utility duct Km 208+560 Km 00+000 BHS 31-Dec-19 10:10 AM IPC-11 Approved
7232 NMSCEW/P-IV/STR/2019/7175 7175 Checking of completion of segment erection for 2×2 utility duct Utility duct Km 209+940 Km 00+000 BHS 31-Dec-19 11:30 AM IPC-11 Approved
7233 NMSCEW/P-IV/STR/2019/7176 7176 Checking of layout,level,reinforcement,shuttering and Pouring concrete for slab MNB Km 199+360 RHS 31-Dec-19 5:00 PM
Checking of Shuttering,reinforcement and Pouring concrete for RE WALL PANEL precast
TYPE -A
7234 NMSCEW/P-IV/STR/2019/7177 7177 194 NOS,TYPE B- 51 NOS, TYPE -Sta 10 NOS, TYPE -Stb 11 NOS, TYPE -Stc 10 NOS, RE Wall Panel Km 200+200 LHS 31-Dec-19 12:09 PM
TYPE -Std 10 NOS, TYPE -Lta 11 NOS, Ltc 10 NOS,TYPE -Ltd 5 NOS, at RE panel precast
yard camp 2
7235 NMSCEW/P-IV/STR/2019/7178 7178 Checking of layout,level,reinforcement,shuttering and Pouring concrete for raft MNB Km 208+455 RHS 31-Dec-19 8:00 AM
7236 NMSCEW/P-IV/STR/2019/7179 7179 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall W2 Box culvert Km 193+940 LHS 31-Dec-19 2:00 PM
7237 NMSCEW/P-IV/STR/2019/7180 7180 Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at retaining wall W2 PUP Km 191+740 LHS 31-Dec-19 2:00 PM
7238 NMSCEW/P-IV/STR/2019/7181 7181 Checking layout ,level, & laying concrete for PCC at P-2 POP Km 202+820 31-Dec-19 3:00 PM
7239 NMSCEW/P-IV/STR/2019/7182 7182 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at retaining wall W1 PUP Km 191+740 LHS 31-Dec-19 4:30 PM
7240 NMSCEW/P-IV/STR/2019/7183 7183 Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall W2 PUP Km 193+880 LHS 31-Dec-19 9:15 AM
7241 NMSCEW/P-IV/STR/2019/7184 7184 Checking of reinforcement,shuttering and Pouring concrete for 4th lift at median wall W2 PUP Km 193+880 31-Dec-19 10:46 AM
7242 NMSCEW/P-IV/STR/2019/7185 7185 Checking of reinforcement,shuttering and Pouring concrete for 5th lift at retaining wall W2 PUP Km 193+880 RHS 31-Dec-19 5:50 PM
7243 NMSCEW/P-IV/STR/2019/7186 7186 Checking of completion of segment erection for 2×2 utility duct Utility duct Km 207+560 Km 00+000 BHS 31-Dec-19 2:35 PM IPC-11 Approved
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at retaining wall
7244 NMSCEW/P-IV/STR/2019/7187 7187 PUP Km 183+290 LHS 31-Dec-19 9:10 AM
A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 4th lift at retaining wall
7245 NMSCEW/P-IV/STR/2019/7188 7188 PUP Km 183+290 LHS 31-Dec-19 5:00 PM
A2
7246 NMSCEW/P-IV/STR/2019/7189 7189 Checking of completion of segment erection for 2×2 utility duct Utility duct Km 206+700 Km 00+000 BHS 31-Dec-19 12:00 PM IPC-11 Approved
7247 NMSCEW/P-IV/STR/2019/7190 7190 Checking of completion of segment erection for 3×3 box culvert Box culvert Km 198+128 Km 00+000 BHS 31-Dec-19 12:30 PM IPC-11 Approved
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
7248 NMSCEW/P-IV/STR/2019/7191 7191 Girder Km 200+200 LHS 31-Dec-19 6:30 PM SPOT RFI
181,182,183,184 at bed no -02, Girder Type-02
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
7249 NMSCEW/P-IV/STR/2020/7192 7192 Girder Km 200+200 LHS 1-Jan-20 2:30 PM
173,174,175,176 at bed no -05, Girder Type-01
Checking for stressing and remove slagness of H.T. wires at Girder no-185,186,187,188 at bed
7250 NMSCEW/P-IV/STR/2020/7193 7193 Girder Km 200+200 LHS 1-Jan-20 3:00 PM
no -03, Girder Type-02 at casting yard camp -2
Checking of reinforcement Girder no -185,186,187,188 at bed no -03, Girder Type-02 at
7251 NMSCEW/P-IV/STR/2020/7194 7194 Girder Km 200+200 LHS 1-Jan-20 3:30 PM
casting yard camp -2
7252 NMSCEW/P-IV/STR/2020/7195 7195 Checking layout ,level, & laying concrete for PCC at RP-6 Viaduct Km 213+915 RHS 1-Jan-20 4:00 PM
7253 NMSCEW/P-IV/STR/2020/7196 7196 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP-17 Viaduct Km 213+915 RHS 1-Jan-20 10:00 AM
7254 NMSCEW/P-IV/STR/2020/7197 7197 Checking layout ,level, & laying concrete for PCC at RP-8 Viaduct Km 213+915 RHS 1-Jan-20 3:15 PM
7255 NMSCEW/P-IV/STR/2020/7198 7198 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-15 Viaduct Km 213+915 LHS 1-Jan-20 10:30 AM IPC-14
Checking of Shuttering,reinforcement & pouring concrete for cross girder between LP-7 to
7256 NMSCEW/P-IV/STR/2020/7199 7199 Viaduct Km 202+190 LHS 1-Jan-20 2:00 PM
LP-8
7257 NMSCEW/P-IV/STR/2020/7200 7200 Checking of Shuttering,reinforcement & pouring concrete for pedistal at RP-09 Viaduct Km 202+190 LHS 1-Jan-20 2:45 PM
Checking of reinforcement, shuttering & pouring concrete for abutment column 1st & final lift
7258 NMSCEW/P-IV/STR/2020/7201 7201 Viaduct Km 200+920 LHS 1-Jan-20 10:45 AM
at LA-1
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 4th lift at retaining wall
7259 NMSCEW/P-IV/STR/2020/7202 7202 PUP Km 184+190 LHS 1-Jan-20 5:00 PM
A2
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 4th lift at retaining wall
7260 NMSCEW/P-IV/STR/2020/7203 7203 PUP Km 184+190 RHS 1-Jan-20 5:10 PM
A1 & A2
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-1
7261 NMSCEW/P-IV/STR/2020/7204 7204 Box culvert Km 175+500 LHS 1-Jan-20 10:45 AM
I) 2x2 (2 to 4m) segment no.- 327,328,329,330,331,332, 333, 334, 335, 336,337,338
II) 3x3 (0 to 2m) segment no.-34, 35, 36, 37, 38, 39
Checking of layout,level,structural excavation & laying concrete PCC(M-10) at 2x2 utility
7262 NMSCEW/P-IV/STR/2020/7205 7205 Utility duct Km 183+870 BHS 1-Jan-20 3:10 PM
duct
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-2
7263 NMSCEW/P-IV/STR/2020/7206 7206 Box culvert Km 200+200 LHS 2-Jan-20 10:30 AM
I) 2x2 (2 to 4m) segment no.-599,600,601,602,603,604
II) 3x3 (2 to 4m) segment no.-
166,167,168,169
Checking of reinforcement,shuttering and Pouring concrete for raft with bottom haunch at A1
7264 NMSCEW/P-IV/STR/2020/7207 7207 Box culvert Km 167+696 LHS 2-Jan-20 4:00 PM
& A2 side
Checking of reinforcement, shuttering & pouring concrete for abutment shaft 1st lift at median
7265 NMSCEW/P-IV/STR/2020/7208 7208 MJB Km 205+610 2-Jan-20 10:00 AM
A1
7266 NMSCEW/P-IV/STR/2020/7209 7209 Checking layout ,level, & laying concrete for PCC at pier P-2 POP Km 202+820 3-Jan-20 3:00 PM
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
7267 NMSCEW/P-IV/STR/2020/7210 7210 Girder Km 200+200 LHS 3-Jan-20 10:30 AM
185,186,187,188 at bed no -03, Girder Type-02
7268 NMSCEW/P-IV/STR/2020/7211 7211 Checking layout ,level, & laying concrete for PCC at RP-12 Viaduct Km 213+915 RHS 3-Jan-20 4:00 PM
7269 NMSCEW/P-IV/STR/2020/7212 7212 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP-17 Viaduct Km 213+915 RHS 3-Jan-20 10:00 AM
7270 NMSCEW/P-IV/STR/2020/7213 7213 Checking layout ,level, & laying concrete for PCC at RP-8 Viaduct Km 213+915 RHS 3-Jan-20 3:15 PM
7271 NMSCEW/P-IV/STR/2020/7214 7214 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-17 Viaduct Km 213+915 LHS 3-Jan-20 4:30 PM
Checking of Shuttering,reinforcement & pouring concrete(M-45) for deck slab module (type-
7272 NMSCEW/P-IV/STR/2020/7215 7215 Viaduct Km 169+800 LHS 3-Jan-20 6:00 PM
2) LP-4 to LP-7
Checking of Shuttering,reinforcement & pouring concrete for cross girder between LP-7 to
7273 NMSCEW/P-IV/STR/2020/7216 7216 Viaduct Km 202+190 LHS 3-Jan-20 2:00 PM
LP-8
7274 NMSCEW/P-IV/STR/2020/7217 7217 Checking layout ,level for bearing fixing at LP-7 Viaduct Km 202+190 LHS 3-Jan-20 3:40 PM
7275 NMSCEW/P-IV/STR/2020/7218 7218 Checking of level,Shuttering,reinforcement & pouring concrete(M-35) for raft at RA-2 MNB Km 174+570 RHS 3-Jan-20 4:15 PM
7276 NMSCEW/P-IV/STR/2020/7219 7219 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall A1 & A2 PUP Km 179+050 LHS 3-Jan-20 11:30 AM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 4th lift at retaining wall
7277 NMSCEW/P-IV/STR/2020/7220 7220 PUP Km 184+190 RHS 3-Jan-20 8:00 AM
A1 & A2
7278 NMSCEW/P-IV/STR/2020/7221 7221 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 5th lift at abutment A2 VOP Km 181+420 LHS 3-Jan-20 2:05 PM
7279 NMSCEW/P-IV/STR/2020/7222 7222 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 4th lift at abutment A1 VOP Km 181+420 RHS 3-Jan-20 4:25 PM
7280 NMSCEW/P-IV/STR/2020/7223 7223 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 2nd lift at abutment A1 VOP Km 181+420 LHS 3-Jan-20 4:16 PM
7281 NMSCEW/P-IV/STR/2020/7224 7224 Checking of reinforcement,shuttering and Pouring concrete(M-35) for raft at abutment A1 VUP Km 182+420 LHS 3-Jan-20 4:50 PM
7282 NMSCEW/P-IV/STR/2020/7225 7225 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-2 Viaduct Km 200+920 RHS 3-Jan-20 4:44 PM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 1st lift at retaining wall
7283 NMSCEW/P-IV/STR/2020/7226 7226 MJB Km 205+610 LHS 4-Jan-20 10:00 AM
LA1
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 1st lift at retaining wall
7284 NMSCEW/P-IV/STR/2020/7227 7227 MJB Km 205+610 RHS 4-Jan-20 5:00 PM
RA1
Checking of layout,level,reinforcement,shuttering and Pouring concrete for raft (Main
7285 NMSCEW/P-IV/STR/2020/7228 7228 Box culvert Km 206+843 RHS 4-Jan-20 8:00 AM
Carriageway)
7286 NMSCEW/P-IV/STR/2020/7229 7229 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall W1 Box culvert Km 208+567 LHS 4-Jan-20 2:00 PM
7287 NMSCEW/P-IV/STR/2020/7230 7230 Checking of layout,level,reinforcement,shuttering and Pouring concrete for raft (Service road) PUP Km 211+210 RHS 4-Jan-20 5:00 PM
7288 NMSCEW/P-IV/STR/2020/7231 7231 Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall W2 PUP Km 199+360 RHS 4-Jan-20 2:15 PM
7289 NMSCEW/P-IV/STR/2020/7232 7232 Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at retaining wall W1 PUP Km 191+740 LHS 4-Jan-20 5:15 PM
7290 NMSCEW/P-IV/STR/2020/7233 7233 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall W1 Box culvert Km 193+940 LHS 4-Jan-20 3:30 PM
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-2
7291 NMSCEW/P-IV/STR/2020/7234 7234 Box culvert Km 200+200 LHS 4-Jan-20 10:40 AM
I) 2x2 (2 to 4m) segment no.-605,606,607,608,609
II) 3x3 (2 to 4m) segment no.-
170,171,172,173
Checking of layout,level,structural excavation & laying concrete PCC(M-10) at 2x2 utility
7292 NMSCEW/P-IV/STR/2020/7235 7235 Utility duct Km 183+870 BHS 4-Jan-20 11:30 AM
duct
7293 NMSCEW/P-IV/STR/2020/7236 7236 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall A2 Box culvert Km 162+832 LHS 4-Jan-20 4:00 PM
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at median wall A1 &
7294 NMSCEW/P-IV/STR/2020/7237 7237 LVUP Km 169+291 4-Jan-20 4:25 PM
A2
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-1
7295 NMSCEW/P-IV/STR/2020/7238 7238 Box culvert Km 175+500 LHS 4-Jan-20 11:21 AM
I) 2x2 (4 to 6m) segment no.- 111,112, 113, 114, 115, 116,117,118, 119,120,121,122
II) 3x3 (0 to 2m) segment no.-40, 41, 42, 43, 44, 45
Checking of reinforcement,shuttering and Pouring concrete for 5th lift at U type retaining wall
7296 NMSCEW/P-IV/STR/2020/7239 7239 VUP Km 176+614 4-Jan-20 11:37 AM
A1 & A2
Checking of layout, excavated bed level, & laying concrete PCC(M-10) for wing wall
7297 NMSCEW/P-IV/STR/2020/7240 7240 Box culvert Km 186+352 RHS 4-Jan-20 10:00 AM
foundation
7298 NMSCEW/P-IV/STR/2020/7241 7241 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 6th lift at abutment A2 VOP Km 181+420 LHS 4-Jan-20 2:05 PM
7299 NMSCEW/P-IV/STR/2020/7242 7242 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 5th lift at abutment A1 VOP Km 181+420 RHS 4-Jan-20 4:25 PM
7300 NMSCEW/P-IV/STR/2020/7243 7243 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 3rd lift at abutment A1 VOP Km 181+420 LHS 4-Jan-20 4:16 PM
7301 NMSCEW/P-IV/STR/2020/7244 7244 Checking of reinforcement,shuttering and Pouring concrete(M-35) for raft at abutment A1 VUP Km 182+420 LHS 4-Jan-20 8:00 AM
7302 NMSCEW/P-IV/STR/2020/7245 7245 Checking of excavated bed layout,level, & laying concrete PCC(M-15) at pier P-2 VOP Km 181+420 RHS 4-Jan-20 2:14 PM
7303 NMSCEW/P-IV/STR/2020/7246 7246 Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-7 Viaduct Km 195+900 LHS 4-Jan-20 3:44 PM
7304 NMSCEW/P-IV/STR/2020/7247 7247 Checking of reinforcement,shuttering and Pouring concrete for 5th lift at retaining wall W2 PUP Km 193+880 LHS 4-Jan-20 3:00 PM
7305 NMSCEW/P-IV/STR/2020/7248 7248 Checking layout ,level, & laying concrete for PCC at RP-12 Viaduct Km 213+915 RHS 5-Jan-20 11:00 AM
7306 NMSCEW/P-IV/STR/2020/7249 7249 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP-17 Viaduct Km 213+915 RHS 5-Jan-20 10:00 AM
7307 NMSCEW/P-IV/STR/2020/7250 7250 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-17 Viaduct Km 213+915 LHS 5-Jan-20 12:30 PM
7308 NMSCEW/P-IV/STR/2020/7251 7251 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP-3 Viaduct Km 213+915 RHS 5-Jan-20 11:30 AM
Checking of Shuttering,reinforcement & pouring concrete(M-45) for deck slab module (type-
7309 NMSCEW/P-IV/STR/2020/7252 7252 Viaduct Km 169+800 LHS 5-Jan-20 8:00 AM
2) LP-7 to LP-10
7310 NMSCEW/P-IV/STR/2020/7253 7253 Checking layout ,level for bearing fixing at LP-7 Viaduct Km 202+190 LHS 5-Jan-20 12:45 PM
7311 NMSCEW/P-IV/STR/2020/7254 7254 Checking layout ,level for bearing fixing at LP-8 Viaduct Km 202+190 LHS 5-Jan-20 11:40 AM
7312 NMSCEW/P-IV/STR/2020/7255 7255 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 1st lift at abutment A2 VOP Km 181+420 RHS 5-Jan-20 10:15 AM
Checking for stressing and remove slagness of H.T. wires at Girder no-177,178,179,180 at bed
7313 NMSCEW/P-IV/STR/2020/7256 7256 Girder Km 200+200 LHS 6-Jan-20 8:00 AM
no -07, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -177,178,179,180 at bed no -07, Girder Type-01 at
7314 NMSCEW/P-IV/STR/2020/7257 7257 Girder Km 200+200 LHS 6-Jan-20 8:30 AM
casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-189,190,191,192 at bed
7315 NMSCEW/P-IV/STR/2020/7258 7258 Girder Km 200+200 LHS 6-Jan-20 11:00 AM
no -01, Girder Type-02 at casting yard camp -2
Checking of reinforcement Girder no -189,190,191,192 at bed no -01, Girder Type-02 at
7316 NMSCEW/P-IV/STR/2020/7259 7259 Girder Km 200+200 LHS 6-Jan-20 11:30 AM
casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-193,194,195,196 at bed
7317 NMSCEW/P-IV/STR/2020/7260 7260 Girder Km 200+200 LHS 6-Jan-20 5:00 PM
no -04, Girder Type-02 at casting yard camp -2
Checking of reinforcement Girder no -193,194,195,196 at bed no -04, Girder Type-02 at
7318 NMSCEW/P-IV/STR/2020/7261 7261 Girder Km 200+200 LHS 6-Jan-20 5:30 PM
casting yard camp -2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
7319 NMSCEW/P-IV/STR/2020/7262 7262 Girder Km 200+200 LHS 6-Jan-20 6:00 PM
177,178,179,180 at bed no -07, Girder Type-01
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
7320 NMSCEW/P-IV/STR/2020/7263 7263 Girder Km 200+200 LHS 6-Jan-20 7:00 PM
189,190,191,192 at bed no -01, Girder Type-02
7321 NMSCEW/P-IV/STR/2020/7264 7264 Checking layout ,level, & laying concrete for PCC at RP-12 Viaduct Km 213+915 RHS 6-Jan-20 4:00 PM
7322 NMSCEW/P-IV/STR/2020/7265 7265 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-17 Viaduct Km 213+915 LHS 6-Jan-20 3:30 PM
7323 NMSCEW/P-IV/STR/2020/7266 7266 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP-3 Viaduct Km 213+915 RHS 6-Jan-20 2:30 PM
7324 NMSCEW/P-IV/STR/2020/7267 7267 Checking of Shuttering,reinforcement & pouring concrete for pier starter at RP-1 Viaduct Km 213+915 RHS 6-Jan-20 2:40 PM
7325 NMSCEW/P-IV/STR/2020/7268 7268 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-18 Viaduct Km 213+915 LHS 6-Jan-20 3:00 PM
7326 NMSCEW/P-IV/STR/2020/7269 7269 Checking of Shuttering,reinforcement & pouring concrete for pier starter at RP-15 Viaduct Km 213+915 RHS 6-Jan-20 2:00 PM
7327 NMSCEW/P-IV/STR/2020/7270 7270 Checking of reinforcement,shuttering and Pouring concrete(M-35) for raft at abutment A2 MNB Km 186+550 LHS 6-Jan-20 4:15 PM
7328 NMSCEW/P-IV/STR/2020/7271 7271 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 5th lift at wall A1 side VUP Km 187+113 6-Jan-20 10:00 AM
7329 NMSCEW/P-IV/STR/2020/7272 7272 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 2nd lift at abutment A2 VOP Km 181+420 RHS 6-Jan-20 10:15 AM
7330 NMSCEW/P-IV/STR/2020/7273 7273 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 4th lift at abutment A1 VOP Km 181+420 LHS 6-Jan-20 11:17 AM
Checking of excavated bed layout,level, & laying concrete PCC(M-15) at retaining wall A2
7331 NMSCEW/P-IV/STR/2020/7274 7274 MNB(Loop-B) Km 01+980 6-Jan-20 2:00 PM
side loop-B
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 1st lift at retaining wall
7332 NMSCEW/P-IV/STR/2020/7275 7275 MJB Km 205+610 RHS 7-Jan-20 10:00 AM
RA1
Checking of reinforcement,shuttering and Pouring concrete(M-35) for 2nd lift at median wall
7333 NMSCEW/P-IV/STR/2020/7276 7276 MJB Km 205+610 7-Jan-20 2:00 PM
A1
7334 NMSCEW/P-IV/STR/2020/7277 7277 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall W1 & W2 Box culvert Km 208+675 LHS 7-Jan-20 8:00 AM
7335 NMSCEW/P-IV/STR/2020/7278 7278 Checking of layout ,Level,reinforcement,shuttering and Pouring concrete for raft at median PUP Km 212+080 BHS 7-Jan-20 10:30 AM
Checking of reinforcement,shuttering and Pouring concrete for 5th lift at retaining wall W1 &
7336 NMSCEW/P-IV/STR/2020/7279 7279 PUP Km 193+880 RHS 7-Jan-20 2:30 PM
W2
7337 NMSCEW/P-IV/STR/2020/7280 7280 Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall W2 PUP Km 191+740 LHS 7-Jan-20 4:00 PM
7338 NMSCEW/P-IV/STR/2020/7281 7281 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall W1 Box culvert Km 193+940 LHS 7-Jan-20 8:15 AM
Checking for stressing and remove slagness of H.T. wires at Girder no-181,182,183,184 at bed
7339 NMSCEW/P-IV/STR/2020/7282 7282 Girder Km 200+200 LHS 7-Jan-20 8:00 AM
no -04, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -181,182,183,184 at bed no -04, Girder Type-01 at
7340 NMSCEW/P-IV/STR/2020/7283 7283 Girder Km 200+200 LHS 7-Jan-20 8:30 AM
casting yard camp -2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
7341 NMSCEW/P-IV/STR/2020/7284 7284 Girder Km 200+200 LHS 7-Jan-20 6:00 PM
181,182,183,184 at bed no -04, Girder Type-01
Checking for stressing and remove slagness of H.T. wires at Girder no-185,186,187,188 at bed
7342 NMSCEW/P-IV/STR/2020/7285 7285 Girder Km 200+200 LHS 7-Jan-20 11:00 AM
no -06, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -185,186,187,188 at bed no -06, Girder Type-01 at
7343 NMSCEW/P-IV/STR/2020/7286 7286 Girder Km 200+200 LHS 7-Jan-20 11:30 AM
casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-189,190,191,192 at bed
7344 NMSCEW/P-IV/STR/2020/7287 7287 Girder Km 200+200 LHS 7-Jan-20 3:00 PM
no -08, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -189,190,191,192 at bed no -08, Girder Type-01 at
7345 NMSCEW/P-IV/STR/2020/7288 7288 Girder Km 200+200 LHS 7-Jan-20 3:30 PM
casting yard camp -2
Checking of Shuttering,reinforcement & pouring concrete for cross girder between LP-8 to
7346 NMSCEW/P-IV/STR/2020/7289 7289 Viaduct Km 202+190 LHS 7-Jan-20 3:20 PM
LP-9
Checking of reinforcement,shuttering and Pouring concrete for 5th lift at U type retaining wall
7347 NMSCEW/P-IV/STR/2020/7290 7290 VUP Km 176+614 7-Jan-20 1:40 PM
A1 & A2
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at median wall A1 &
7348 NMSCEW/P-IV/STR/2020/7291 7291 LVUP Km 169+291 7-Jan-20 4:00 PM
A2 side
7349 NMSCEW/P-IV/STR/2020/7292 7292 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall A1 & A2 side PUP Km 168+380 RHS 7-Jan-20 4:40 PM
7350 NMSCEW/P-IV/STR/2020/7293 7293 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 2nd lift at abutment A2 VOP Km 181+420 RHS 7-Jan-20 10:00 AM
7351 NMSCEW/P-IV/STR/2020/7294 7294 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 4th lift at abutment A1 VOP Km 181+420 LHS 7-Jan-20 11:10 AM
Checking of excavated bed layout,level, & laying concrete PCC(M-15) at retaining wall A2
7352 NMSCEW/P-IV/STR/2020/7295 7295 MNB(Loop-C) Km 01+980 7-Jan-20 3:00 PM
side loop-C
7353 NMSCEW/P-IV/STR/2020/7296 7296 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-1 MJB Km 205+610 LHS 8-Jan-20 12:00 PM
7354 NMSCEW/P-IV/STR/2020/7297 7297 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at retaining wall LA1 MJB Km 205+610 LHS 8-Jan-20 2:00 PM
7355 NMSCEW/P-IV/STR/2020/7298 7298 Checking of reinforcement,shuttering and Pouring concrete for 5th lift at retaining wall W2 MNB Km 199+360 RHS 8-Jan-20 3:00 PM
7360 NMSCEW/P-IV/STR/2020/7303 7303 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP-3 Viaduct Km 213+915 RHS 8-Jan-20 2:30 PM
7361 NMSCEW/P-IV/STR/2020/7304 7304 Checking of Shuttering,reinforcement & pouring concrete for pier starter at RP-1 Viaduct Km 213+915 RHS 8-Jan-20 2:45 PM
7362 NMSCEW/P-IV/STR/2020/7305 7305 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-18 Viaduct Km 213+915 LHS 8-Jan-20 3:10 PM
7363 NMSCEW/P-IV/STR/2020/7306 7306 Checking of Shuttering,reinforcement & pouring concrete for pier starter at RP-15 Viaduct Km 213+915 RHS 8-Jan-20 2:15 PM
7364 NMSCEW/P-IV/STR/2020/7307 7307 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP-17 Viaduct Km 213+915 RHS 8-Jan-20 4:15 PM
7365 NMSCEW/P-IV/STR/2020/7308 7308 Checking of Shuttering,reinforcement, pouring concrete for padestal at RP-10 Viaduct Km 202+190 RHS 8-Jan-20 4:30 PM
7366 NMSCEW/P-IV/STR/2020/7309 7309 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-2 Viaduct Km 200+920 RHS 8-Jan-20 4:45 PM IPC-14
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-1
7367 NMSCEW/P-IV/STR/2020/7310 7310 Box culvert Km 175+500 LHS 8-Jan-20 10:32 AM
I) 2x2 (2 to 4m) segment no.- 339,340,341,342,
343,344,345,346,347,348,349,350,351,352,353,354,355,356
II) 3x3 (0 to 2m) segment no.-46,47,48,49,50,51
Checking of layout ,level ,structural excavation & laying concrete PCC for Pipe culvert
7368 NMSCEW/P-IV/STR/2020/7311 7311 Pipe culvert Km 171+130 LHS 8-Jan-20 3:30 PM
median drain outlet
7369 NMSCEW/P-IV/STR/2020/7312 7312 Checking of reinforcement,shuttering and Pouring concrete(M-35) for raft at RA-2 MNB Km 174+570 RHS 8-Jan-20 11:00 AM
7370 NMSCEW/P-IV/STR/2020/7313 7313 Checking of reinforcement,shuttering and Pouring concrete(M-35) for footing at abutment A2 MNB Km 186+550 LHS 8-Jan-20 2:00 PM
Checking of reinforcement,shuttering and Pouring concrete(M-35) for 5th lift at retaining wall
7371 NMSCEW/P-IV/STR/2020/7314 7314 VUP Km 187+113 BHS 8-Jan-20 4:00 PM
A1
Checking of excavated bed layout,level, & laying concrete PCC(M-15) for wing wall
7372 NMSCEW/P-IV/STR/2020/7315 7315 Box culvert Km 186+352 LHS 8-Jan-20 5:00 PM
foundation
7373 NMSCEW/P-IV/STR/2020/7316 7316 Checking of reinforcement,shuttering and Pouring concrete(M-35) for raft at pier P2 VOP Km 181+420 RHS 8-Jan-20 3:00 PM
Checking of excavated bed layout,level, & laying concrete PCC(M-15) at retaining wall A1
7374 NMSCEW/P-IV/STR/2020/7317 7317 MNB(Loop-B) Km 01+980 8-Jan-20 8:00 AM
side loop-B
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
7375 NMSCEW/P-IV/STR/2020/7318 7318 Girder Km 200+200 LHS 8-Jan-20 10:30 AM SPOT RFI
189,190,191,192 at bed no -01, Girder Type-02
7376 NMSCEW/P-IV/STR/2020/7319 7319 Checking of layout,level, & laying concrete PCC at retaining wall W2 MNB Km 199+360 LHS 9-Jan-20 3:00 PM
7377 NMSCEW/P-IV/STR/2020/7320 7320 Checking of reinforcement,shuttering and Pouring concrete for 5th lift at median wall W2 PUP Km 193+880 9-Jan-20 2:00 PM
7378 NMSCEW/P-IV/STR/2020/7321 7321 Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall W1 PUP Km 191+740 LHS 9-Jan-20 4:00 PM
7379 NMSCEW/P-IV/STR/2020/7322 7322 Checking of excavated bed layout,level, & laying concrete PCC for curtain wall Box culvert Km 163+570 BHS 9-Jan-20 10:30 AM
7380 NMSCEW/P-IV/STR/2020/7323 7323 Checking of Shuttering,reinforcement, pouring concrete for padestal at RA-1 Viaduct Km 169+800 RHS 9-Jan-20 3:15 PM
7381 NMSCEW/P-IV/STR/2020/7324 7324 Checking of Shuttering,reinforcement, pouring concrete for padestal at LA-1 Viaduct Km 169+800 LHS 9-Jan-20 3:30 PM
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-1
7382 NMSCEW/P-IV/STR/2020/7325 7325 Box culvert Km 175+500 LHS 9-Jan-20 10:00 AM
I) 2x2 (2 to 4m) segment no.-357,358,359,360,361,362,363,364,365,366,367,368
II) 3x3 (0 to 2m) segment no.-52, 53, 54
Checking of Hume pipe ( 1000×2500 mm) Laying & fixing for Pipe culvert median drain
7383 NMSCEW/P-IV/STR/2020/7326 7326 Pipe culvert Km 171+130 LHS 9-Jan-20 2:50 PM
outlets.
7384 NMSCEW/P-IV/STR/2020/7327 7327 Checking of layout ,Level,reinforcement,shuttering and Pouring concrete for raft at median MNB Km 208+455 9-Jan-20 10:15 AM
7385 NMSCEW/P-IV/STR/2020/7328 7328 Checking of layout ,Level,reinforcement,shuttering and Pouring concrete for raft MNB Km 208+455 RHS 9-Jan-20 10:46 AM
7386 NMSCEW/P-IV/STR/2020/7329 7329 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at retaining wall W1 PUP Km 208+930 RHS 9-Jan-20 8:00 AM
7387 NMSCEW/P-IV/STR/2020/7330 7330 Checking of excavated bed layout,level, & laying concrete PCC for RP1 raft MJB Km 205+610 RHS 9-Jan-20 5:00 PM
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
7388 NMSCEW/P-IV/STR/2020/7331 7331 Girder Km 200+200 LHS 9-Jan-20 8:30 AM
181,182,183,184 at bed no -04, Girder Type-01
Checking for stressing and remove slagness of H.T. wires at Girder no-193,194,195,196 at bed
7389 NMSCEW/P-IV/STR/2020/7332 7332 Girder Km 200+200 LHS 9-Jan-20 2:50 PM
no -02, Girder Type-02 at casting yard camp -2
Checking of reinforcement Girder no -193,194,195,196 at bed no -02, Girder Type-02 at
7390 NMSCEW/P-IV/STR/2020/7333 7333 Girder Km 200+200 LHS 9-Jan-20 3:20 PM
casting yard camp -2
7391 NMSCEW/P-IV/STR/2020/7334 7334 Checking of layout,level,structural excavation & laying concrete PCC at RA2 MNB Km 167+547 RHS 9-Jan-20 4:00 PM
7392 NMSCEW/P-IV/STR/2020/7335 7335 Checking of layout,level,structural excavation & laying concrete PCC at LA2 MNB Km 167+547 LHS 9-Jan-20 4:30 PM
7393 NMSCEW/P-IV/STR/2020/7336 7336 Checking of reinforcement,shuttering and Pouring concrete(M-35) for raft at pier P2 VOP Km 181+420 RHS 9-Jan-20 3:00 PM
Checking of excavated bed layout,level, & laying concrete PCC(M-15) at retaining wall A1
7394 NMSCEW/P-IV/STR/2020/7337 7337 MNB(Loop-B) Km 01+980 9-Jan-20 8:00 AM
side loop-B
7395 NMSCEW/P-IV/STR/2020/7338 7338 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-5 Viaduct Km 195+190 LHS 9-Jan-20 11:00 AM IPC-14
7396 NMSCEW/P-IV/STR/2020/7339 7339 Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-1 Viaduct Km 200+920 LHS 9-Jan-20 4:00 PM
7397 NMSCEW/P-IV/STR/2020/7340 7340 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall W1 MNB Km 208+455 RHS 10-Jan-20 8:00 AM
7398 NMSCEW/P-IV/STR/2020/7341 7341 Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall W1 PUP Km 193+880 RHS 10-Jan-20 4:00 PM
Checking of layout,level,structural excavation & laying concrete PCC for pipe culvert median
7399 NMSCEW/P-IV/STR/2020/7342 7342 Pipe culvert Km 174+070 LHS 10-Jan-20 4:30 PM
drain outlets
Checking of reinforcement,shuttering and Pouring concrete for Final lift with top haunch and
7400 NMSCEW/P-IV/STR/2020/7343 7343 PUP Km 179+050 RHS 10-Jan-20 11:30 AM
top slab
7401 NMSCEW/P-IV/STR/2020/7344 7344 Checking of layout,level,structural excavation & laying concrete PCC at A2 MNB Km 176+875 BHS 10-Jan-20 4:30 PM
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall A2 side wall
7402 NMSCEW/P-IV/STR/2020/7345 7345 Box culvert Km 162+832 10-Jan-20 11:00 AM
(median)
7403 NMSCEW/P-IV/STR/2020/7346 7346 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 1st lift at middle wall MNB Km 189+705 10-Jan-20 10:00 AM
Checking for stressing and remove slagness of H.T. wires at Girder no-193,194,195,196 at bed
7404 NMSCEW/P-IV/STR/2020/7347 7347 Girder Km 200+200 LHS 10-Jan-20 8:15 AM
no -05, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -193,194,195,196 at bed no -05, Girder Type-01 at
7405 NMSCEW/P-IV/STR/2020/7348 7348 Girder Km 200+200 LHS 10-Jan-20 8:40 AM
casting yard camp -2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
7406 NMSCEW/P-IV/STR/2020/7349 7349 Girder Km 200+200 LHS 10-Jan-20 3:30 PM
193,194,195,196 at bed no -02, Girder Type-01
Checking of Shuttering,reinforcement & pouring concrete for cross girder between LP-8 to
7407 NMSCEW/P-IV/STR/2020/7350 7350 Viaduct Km 202+190 LHS 10-Jan-20 3:20 PM
LP-9
7408 NMSCEW/P-IV/STR/2020/7351 7351 Checking layout ,level, & laying concrete for PCC at RP-12 Viaduct Km 213+915 RHS 10-Jan-20 4:00 PM
7409 NMSCEW/P-IV/STR/2020/7352 7352 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-17 Viaduct Km 213+915 LHS 10-Jan-20 3:30 PM
7410 NMSCEW/P-IV/STR/2020/7353 7353 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP-3 Viaduct Km 213+915 RHS 10-Jan-20 2:30 PM
7411 NMSCEW/P-IV/STR/2020/7354 7354 Checking of Shuttering,reinforcement & pouring concrete for pier starter at RP-1 Viaduct Km 213+915 RHS 10-Jan-20 2:49 PM
7412 NMSCEW/P-IV/STR/2020/7355 7355 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-18 Viaduct Km 213+915 LHS 10-Jan-20 3:00 PM IPC-14
7413 NMSCEW/P-IV/STR/2020/7356 7356 Checking of Shuttering,reinforcement & pouring concrete for pier starter at RP-15 Viaduct Km 213+915 RHS 10-Jan-20 2:00 PM IPC-14
7414 NMSCEW/P-IV/STR/2020/7357 7357 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP-17 Viaduct Km 213+915 RHS 10-Jan-20 2:30 PM
7415 NMSCEW/P-IV/STR/2020/7358 7358 Checking of Shuttering,reinforcement, pouring concrete for pier cap at RP-4 Viaduct Km 200+920 RHS 10-Jan-20 4:00 PM
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
7416 NMSCEW/P-IV/STR/2020/7359 7359 Girder Km 200+200 LHS 10-Jan-20 8:30 AM
189,190,191,192 at bed no -08, Girder Type-01
7417 NMSCEW/P-IV/STR/2020/7360 7360 Checking of reinforcement,shuttering and Pouring concrete(M-35) for raft at pier P-2 VOP Km 181+420 RHS 10-Jan-20 8:00 AM SPOT RFI
7418 NMSCEW/P-IV/STR/2020/7361 7361 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 4th lift at abutment A1 VOP Km 181+420 LHS 10-Jan-20 10:00 AM SPOT RFI
7419 NMSCEW/P-IV/STR/2020/7362 7362 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 3rd lift at abutment A2 VOP Km 181+420 RHS 10-Jan-20 10:30 AM SPOT RFI
7420 NMSCEW/P-IV/STR/2020/7363 7363 Checking of reinforcement,shuttering and Pouring concrete(M-35) for raft at abutment A2 VUP Km 182+420 LHS 10-Jan-20 3:00 PM SPOT RFI
7421 NMSCEW/P-IV/STR/2020/7364 7364 Checking of reinforcement, shuttering & pouring concrete(M-45) for pier shaft 1st lift at LP-1 MJB Km 205+610 LHS 11-Jan-20 9:00 AM
7423 NMSCEW/P-IV/STR/2020/7366 7366 Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at median wall W2 PUP Km 191+740 11-Jan-20 4:00 PM
7425 NMSCEW/P-IV/STR/2020/7368 7368 Checking of layout ,Level,reinforcement,shuttering and Pouring concrete for median raft PUP Km 212+080 11-Jan-20 10:00 AM
7426 NMSCEW/P-IV/STR/2020/7369 7369 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at wall A1 & A2 side PUP Km 168+380 RHS 11-Jan-20 6:00 PM
7434 NMSCEW/P-IV/STR/2020/7377 7377 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-15 Viaduct Km 213+915 LHS 11-Jan-20 9:30 AM
7435 NMSCEW/P-IV/STR/2020/7378 7378 Checking of Shuttering,reinforcement & pouring concrete for pier starter at RP-14 Viaduct Km 213+915 RHS 11-Jan-20 2:30 PM IPC-14
7436 NMSCEW/P-IV/STR/2020/7379 7379 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-12 Viaduct Km 213+915 LHS 11-Jan-20 3:00 PM
7437 NMSCEW/P-IV/STR/2020/7380 7380 Checking of Shuttering,reinforcement & pouring concrete for pier starter at RP-15 Viaduct Km 213+915 RHS 11-Jan-20 2:00 PM
7438 NMSCEW/P-IV/STR/2020/7381 7381 Checking layout ,level, & laying concrete for PCC at RP-8 Viaduct Km 213+915 RHS 11-Jan-20 3:15 PM
7439 NMSCEW/P-IV/STR/2020/7382 7382 Checking layout ,level, & laying concrete for PCC at RP-7 Viaduct Km 213+915 RHS 11-Jan-20 4:00 PM
7440 NMSCEW/P-IV/STR/2020/7383 7383 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 5th lift at abutment A1 VOP Km 181+420 LHS 11-Jan-20 10:00 AM
7441 NMSCEW/P-IV/STR/2020/7384 7384 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 4th lift at abutment A2 VOP Km 181+420 RHS 11-Jan-20 10:30 AM
7442 NMSCEW/P-IV/STR/2020/7385 7385 Checking of reinforcement,shuttering and Pouring concrete(M-35) for raft at abutment A2 VUP Km 182+420 LHS 11-Jan-20 3:00 PM
7443 NMSCEW/P-IV/STR/2020/7386 7386 Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at wall A2 side MNB Km 181+700 RHS 11-Jan-20 2:00 PM
Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st and final lift at
7444 NMSCEW/P-IV/STR/2020/7387 7387 Viaduct Km 196+560 LHS 12-Jan-20 10:30 AM IPC-14
LA-2
7445 NMSCEW/P-IV/STR/2020/7388 7388 Checking of Shuttering,reinforcement, pouring concrete for padestal at RP-9 Viaduct Km 196+560 RHS 12-Jan-20 11:20 AM
7446 NMSCEW/P-IV/STR/2020/7389 7389 Checking of reinforcement, shuttering & pouring concrete for raft at RP-11 Viaduct Km 213+915 RHS 12-Jan-20 10:35 AM
7447 NMSCEW/P-IV/STR/2020/7390 7390 Checking of reinforcement, shuttering & pouring concrete for raft at RP-18 Viaduct Km 213+915 RHS 12-Jan-20 9:30 AM
7448 NMSCEW/P-IV/STR/2020/7391 7391 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-18 Viaduct Km 213+915 LHS 12-Jan-20 2:00 PM
7449 NMSCEW/P-IV/STR/2020/7392 7392 Checking of Shuttering,reinforcement & pouring concrete for pier starter at RP-1 Viaduct Km 213+915 RHS 12-Jan-20 2:15 PM
7450 NMSCEW/P-IV/STR/2020/7393 7393 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP-3 Viaduct Km 213+915 RHS 12-Jan-20 2:30 PM
7451 NMSCEW/P-IV/STR/2020/7394 7394 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP-17 Viaduct Km 213+915 RHS 12-Jan-20 3:00 PM IPC-14
7452 NMSCEW/P-IV/STR/2020/7395 7395 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-17 Viaduct Km 213+915 LHS 12-Jan-20 3:30 PM IPC-14
7453 NMSCEW/P-IV/STR/2020/7396 7396 Checking of Shuttering,reinforcement & pouring concrete for pier starter at RP-2 Viaduct Km 213+915 RHS 12-Jan-20 2:45 PM
7454 NMSCEW/P-IV/STR/2020/7397 7397 Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-8 Viaduct Km 195+190 LHS 12-Jan-20 11:00 AM
7455 NMSCEW/P-IV/STR/2020/7398 7398 Checking of I-girder launching and positioning for RP-7 to RP-10( module no.- 2) Viaduct Km 169+800 RHS 12-Jan-20 9:00 AM
7456 NMSCEW/P-IV/STR/2020/7399 7399 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 5th lift at abutment A1 VOP Km 181+420 LHS 12-Jan-20 10:00 AM
7457 NMSCEW/P-IV/STR/2020/7400 7400 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 4th lift at abutment A2 VOP Km 181+420 RHS 12-Jan-20 10:30 AM
7459 NMSCEW/P-IV/STR/2020/7402 7402 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 1st lift at middle wall MNB Km 189+705 LHS 12-Jan-20 10:00 AM
7460 NMSCEW/P-IV/STR/2020/7403 7403 Checking of Shuttering & pouring concrete for curtain wall Box culvert Km 163+570 LHS 12-Jan-20 10:23 AM
7461 NMSCEW/P-IV/STR/2020/7404 7404 Checking of Shuttering,reinforcement, pouring concrete for pier cap at RP-5 Viaduct Km 200+920 RHS 13-Jan-20 4:00 PM
7462 NMSCEW/P-IV/STR/2020/7405 7405 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall A1 side Box culvert Km 168+330 RHS 13-Jan-20 4:30 PM
7463 NMSCEW/P-IV/STR/2020/7406 7406 Checking of layout,level,structural excavation & laying concrete PCC for median wall PUP Km 168+380 13-Jan-20 3:00 PM
7464 NMSCEW/P-IV/STR/2020/7407 7407 Checking of bearing & grouting at RP-9 Viaduct Km 169+800 RHS 13-Jan-20 3:30 PM
7465 NMSCEW/P-IV/STR/2020/7408 7408 Checking of bearing & grouting at RP-6 Viaduct Km 169+800 RHS 13-Jan-20 4:05 PM
Checking for stressing and remove slagness of H.T. wires at Girder no-197,198,199,200 at bed
7466 NMSCEW/P-IV/STR/2020/7409 7409 Girder Km 200+200 LHS 13-Jan-20 5:00 PM
no -03, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -197,198,199,200 at bed no -03, Girder Type-01 at
7467 NMSCEW/P-IV/STR/2020/7410 7410 Girder Km 200+200 LHS 13-Jan-20 5:30 PM
casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-201,202,203,204 at bed
7468 NMSCEW/P-IV/STR/2020/7411 7411 Girder Km 200+200 LHS 13-Jan-20 6:00 PM
no -07, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -201,202,203,204 at bed no -07, Girder Type-01 at
7469 NMSCEW/P-IV/STR/2020/7412 7412 Girder Km 200+200 LHS 13-Jan-20 6:30 PM
casting yard camp -2
7470 NMSCEW/P-IV/STR/2020/7413 7413 Checking of layout,level,structural excavation & laying concrete PCC for RA-2 MNB Km 167+547 RHS 13-Jan-20 4:15 PM
7471 NMSCEW/P-IV/STR/2020/7414 7414 Checking of layout,level,structural excavation & laying concrete PCC for LA-2 MNB Km 167+547 LHS 13-Jan-20 4:45 PM
7472 NMSCEW/P-IV/STR/2020/7415 7415 Checking lavel and layout for bearing fixing at RP-5 Viaduct Km 202+190 RHS 13-Jan-20 3:20 PM
7473 NMSCEW/P-IV/STR/2020/7416 7416 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 1st lift at wall A1 side MNB Km 189+705 LHS 13-Jan-20 12:00 PM
7474 NMSCEW/P-IV/STR/2020/7417 7417 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 3rd lift at pier P-1 VOP Km 181+420 LHS 13-Jan-20 10:10 AM
7475 NMSCEW/P-IV/STR/2020/7418 7418 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 5th lift at abutment A2 VOP Km 181+420 RHS 13-Jan-20 10:44 AM
7476 NMSCEW/P-IV/STR/2020/7419 7419 Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at wall A1 side MNB Km 181+700 RHS 13-Jan-20 4:00 PM
7477 NMSCEW/P-IV/STR/2020/7420 7420 Checking of reinforcement, shuttering & pouring concrete for raft at LA-2 Viaduct Km 213+915 LHS 13-Jan-20 11:30 AM
7478 NMSCEW/P-IV/STR/2020/7421 7421 Checking of Shuttering,reinforcement & pouring concrete for pier starter at RP-1 Viaduct Km 213+915 RHS 13-Jan-20 2:00 PM
7479 NMSCEW/P-IV/STR/2020/7422 7422 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-16 Viaduct Km 213+915 LHS 13-Jan-20 2:30 PM
7480 NMSCEW/P-IV/STR/2020/7423 7423 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-15 Viaduct Km 213+915 LHS 13-Jan-20 3:05 PM IPC-14
7481 NMSCEW/P-IV/STR/2020/7424 7424 Checking layout ,level, & laying concrete for PCC at RP-12 Viaduct Km 213+915 RHS 13-Jan-20 3:32 PM
7482 NMSCEW/P-IV/STR/2020/7425 7425 Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at median wall A1 side MJB Km 205+610 13-Jan-20 10:00 AM
7483 NMSCEW/P-IV/STR/2020/7426 7426 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall W2 MNB Km 208+455 RHS 13-Jan-20 8:15 AM
7484 NMSCEW/P-IV/STR/2020/7427 7427 Checking of layout,level, laying concrete for PCC retaining wall W1 & W2 PUP Km 212+080 RHS 13-Jan-20 10:15 AM
7485 NMSCEW/P-IV/STR/2020/7428 7428 Checking of layout,level, laying concrete for PCC retaining wall W1 & W2 PUP Km 212+080 LHS 13-Jan-20 10:45 AM
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-2
7486 NMSCEW/P-IV/STR/2020/7429 7429 Box culvert Km 200+200 LHS 14-Jan-20 10:30 AM
I) 2x2 (2 to 4m) segment no.-
610,611,612,613,614,615,616,617,618,619,620,621,622,623,624,625
Checking of layout,level,reinforcement,shuttering and Pouring concrete for raft at retaining
7487 NMSCEW/P-IV/STR/2020/7430 7430 MNB Km 199+360 LHS 14-Jan-20 10:00 AM
wall W1
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
7488 NMSCEW/P-IV/STR/2020/7431 7431 Girder Km 200+200 LHS 14-Jan-20 3:30 PM
197,198,199,200 at bed no -03, Girder Type-01
Checking of reinforcement,shuttering and Pouring concrete for 6th lift at U type retaining wall
7489 NMSCEW/P-IV/STR/2020/7432 7432 VUP Km 176+614 14-Jan-20 11:00 AM
A1 & A2
Checking of layout,level,structural excavation & laying concrete PCC(M-10) at 2x2 utility
7490 NMSCEW/P-IV/STR/2020/7433 7433 Utility duct Km 183+100 BHS 14-Jan-20 4:00 PM
duct
Checking of Shuttering,reinforcement & pouring concrete for cross girder between LP-9 to
7491 NMSCEW/P-IV/STR/2020/7434 7434 Viaduct Km 202+190 LHS 14-Jan-20 3:20 PM
LP-10
7492 NMSCEW/P-IV/STR/2020/7435 7435 Checking of reinforcement, shuttering & pouring concrete for abutment shaft final lift at RA-2 Viaduct Km 200+920 RHS 14-Jan-20 2:30 PM IPC-14
7493 NMSCEW/P-IV/STR/2020/7436 7436 Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-1 Viaduct Km 196+560 LHS 14-Jan-20 4:30 PM
7494 NMSCEW/P-IV/STR/2020/7437 7437 Checking of reinforcement,shuttering and Pouring concrete for 5th lift at median wall W1 PUP Km 193+880 14-Jan-20 4:10 PM
Checking of top bracket reinforcement,shuttering and Pouring concrete for at retaining wall
7495 NMSCEW/P-IV/STR/2020/7438 7438 PUP Km 191+740 LHS 14-Jan-20 10:00 AM
W1
7496 NMSCEW/P-IV/STR/2020/7439 7439 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 4th lift at pier P-1 VOP Km 181+420 LHS 14-Jan-20 2:00 PM
7497 NMSCEW/P-IV/STR/2020/7440 7440 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 6th lift at abutment A2 VOP Km 181+420 RHS 14-Jan-20 3:00 PM
7498 NMSCEW/P-IV/STR/2020/7441 7441 Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at wall A1 side MNB Km 181+700 RHS 14-Jan-20 4:50 PM
7499 NMSCEW/P-IV/STR/2020/7442 7442 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 2nd lift at middle wall MNB Km 189+705 LHS 14-Jan-20 11:30 AM
7500 NMSCEW/P-IV/STR/2020/7443 7443 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-12 Viaduct Km 213+915 LHS 14-Jan-20 2:05 PM
7501 NMSCEW/P-IV/STR/2020/7444 7444 Checking of Shuttering,reinforcement & pouring concrete for pier starter at RP-18 Viaduct Km 213+915 RHS 14-Jan-20 2:38 PM
7502 NMSCEW/P-IV/STR/2020/7445 7445 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-18 Viaduct Km 213+915 LHS 14-Jan-20 4:25 PM
7503 NMSCEW/P-IV/STR/2020/7446 7446 Checking layout ,level, & laying concrete for PCC at RP-7 Viaduct Km 213+915 RHS 14-Jan-20 3:06 PM
7504 NMSCEW/P-IV/STR/2020/7447 7447 Checking layout ,level, & laying concrete for PCC at RP-8 Viaduct Km 213+915 RHS 14-Jan-20 3:23 PM
7505 NMSCEW/P-IV/STR/2020/7448 7448 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at median wall W1 MNB Km 208+455 15-Jan-20 8:00 AM
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at retaining wall W1 &
7506 NMSCEW/P-IV/STR/2020/7449 7449 PUP Km 208+930 RHS 15-Jan-20 10:00 AM
W2
Checking of top bracket reinforcement,shuttering and Pouring concrete for at retaining wall
7508 NMSCEW/P-IV/STR/2020/7451 7451 PUP Km 191+740 LHS 15-Jan-20 3:00 PM
W2
7509 NMSCEW/P-IV/STR/2020/7452 7452 Checking of reinforcement,shuttering and Pouring concrete for 4th lift at median wall W1 PUP Km 191+740 15-Jan-20 4:30 PM
7510 NMSCEW/P-IV/STR/2020/7453 7453 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at retaining wall W1 MNB Km 199+360 LHS 15-Jan-20 5:00 PM
7517 NMSCEW/P-IV/STR/2020/7460 7460 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 6th lift at abutment A2 VOP Km 181+420 RHS 15-Jan-20 3:00 PM
7531 NMSCEW/P-IV/STR/2020/7474 7474 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall A1 side(Median) Box culvert Km 162+832 16-Jan-20 11:00 AM
7532 NMSCEW/P-IV/STR/2020/7475 7475 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 1st lift at wall A1 & A2 MNB Km 189+705 LHS 16-Jan-20 4:00 PM
7533 NMSCEW/P-IV/STR/2020/7476 7476 Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-1 Viaduct Km 196+560 LHS 16-Jan-20 10:00 AM IPC-14
7534 NMSCEW/P-IV/STR/2020/7477 7477 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 5th lift at pier P-1 VOP Km 181+420 LHS 16-Jan-20 2:00 PM
7535 NMSCEW/P-IV/STR/2020/7478 7478 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 1st lift at pier P-2 VOP Km 181+420 RHS 16-Jan-20 3:00 PM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 1st lift at retaining wall
7536 NMSCEW/P-IV/STR/2020/7479 7479 MNB(Loop-C) Km 01+980 16-Jan-20 10:00 AM
A-2(Loop-C)
Checking of excavated bed layout,level, & laying concrete PCC(M-15) for abutmentA1 at
7537 NMSCEW/P-IV/STR/2020/7480 7480 VOP(Loop-A) Km 3+131.586 RHS 16-Jan-20 11:00 AM
loop-A
7538 NMSCEW/P-IV/STR/2020/7481 7481 Checking of excavated bed layout,level, & laying concrete PCC(M-15) MNB Km 181+078 RHS 16-Jan-20 3:30 PM
Checking for stressing and remove slagness of H.T. wires at Girder no-205,206,207,208 at bed
7540 NMSCEW/P-IV/STR/2020/7483 7483 Girder Km 200+200 LHS 16-Jan-20 6:00 PM
no -06, Girder Type-01 at casting yard camp -2
7542 NMSCEW/P-IV/STR/2020/7485 7485 Checking of Shuttering,reinforcement & pouring concrete for pier starter at RP-11 Viaduct Km 213+915 RHS 16-Jan-20 10:00 AM
7543 NMSCEW/P-IV/STR/2020/7486 7486 Checking of Shuttering,reinforcement & pouring concrete for pier starter at RP-18 Viaduct Km 213+915 RHS 16-Jan-20 2:30 PM
7544 NMSCEW/P-IV/STR/2020/7487 7487 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-18 Viaduct Km 213+915 LHS 16-Jan-20 3:30 PM
7545 NMSCEW/P-IV/STR/2020/7488 7488 Checking layout ,level, & laying concrete for PCC at RP-7 Viaduct Km 213+915 RHS 16-Jan-20 3:00 PM IPC-14
7546 NMSCEW/P-IV/STR/2020/7489 7489 Checking layout ,level, & laying concrete for PCC at LA-1 Viaduct Km 213+915 LHS 16-Jan-20 9:00 AM
7547 NMSCEW/P-IV/STR/2020/7490 7490 Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-8 Viaduct Km 195+900 LHS 16-Jan-20 11:00 AM IPC-14
7548 NMSCEW/P-IV/STR/2020/7491 7491 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-4 Viaduct Km 195+900 LHS 16-Jan-20 12:00 PM IPC-14
7549 NMSCEW/P-IV/STR/2020/7492 7492 Checking of reinforcement,shuttering and Pouring concrete for 4th lift at median wall W2 PUP Km 191+740 17-Jan-20 4:30 PM
7550 NMSCEW/P-IV/STR/2020/7493 7493 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at retaining wall W1 MNB Km 199+360 LHS 17-Jan-20 5:00 PM
7551 NMSCEW/P-IV/STR/2020/7494 7494 Checking layout ,level, reinforcement,shuttering and Pouring concrete for raft at pier RP-1 MJB Km 205+610 RHS 17-Jan-20 2:00 PM
Checking layout ,level, reinforcement,shuttering and Pouring concrete for raft at retaining wall
7552 NMSCEW/P-IV/STR/2020/7495 7495 PUP Km 206+985 LHS 17-Jan-20 10:00 AM
W2
7553 NMSCEW/P-IV/STR/2020/7496 7496 Checking of layout,level, & laying concrete PCC at retaining wall A1 & A2 LVUP Km 178+323 BHS 17-Jan-20 10:30 AM
7554 NMSCEW/P-IV/STR/2020/7497 7497 Checking of reinforcement,shuttering and Pouring concrete for 4th lift at median wall A2 LVUP Km 173+400 17-Jan-20 10:15 AM
7555 NMSCEW/P-IV/STR/2020/7498 7498 Checking of Shuttering,reinforcement & pouring concrete for pier shaft starter at RA-1 MNB Km 174+173 RHS 17-Jan-20 2:15 PM
7556 NMSCEW/P-IV/STR/2020/7499 7499 Checking erection & jointing of pre cast utility duct (2*2) Utility duct Km 183+100 BHS 17-Jan-20 11:00 AM
Checking of layout,level,structural excavation & laying concrete PCC(M-10) for utility duct
7557 NMSCEW/P-IV/STR/2020/7500 7500 Utility duct Km 182+670 BHS 17-Jan-20 2:45 PM
(2*2)
7558 NMSCEW/P-IV/STR/2020/7501 7501 Checking of reinforcement, shuttering & pouring concrete(M-35) for raft at LA-2 MNB Km 174+570 LHS 17-Jan-20 12:00 PM
7559 NMSCEW/P-IV/STR/2020/7502 7502 Checking of reinforcement, shuttering & pouring concrete(M-35) for raft at RA-2 MNB Km 174+570 RHS 17-Jan-20 12:30 PM
Box
7560 NMSCEW/P-IV/STR/2020/7503 7503 Checking of reinforcement, shuttering & pouring concrete(M-35) for bottom slab at Loop-B Km 0+457.121 17-Jan-20 12:45 PM
culvert(Loop-B)
Checking of excavated bed layout,level, & laying concrete PCC(M-15) for abutment A2 at
7561 NMSCEW/P-IV/STR/2020/7504 7504 VOP(Loop-A) Km 3+131.586 LHS 17-Jan-20 9:00 AM
loop-A
Checking of excavated bed layout,level, & laying concrete PCC(M-15) for retaining wall A1
7562 NMSCEW/P-IV/STR/2020/7505 7505 MNB(Loop-B) Km 01+980 17-Jan-20 8:00 AM
side at loop-B
7563 NMSCEW/P-IV/STR/2020/7506 7506 Checking of layout,level,structural excavation for retaining wall A1 & A2 PUP Km 179+050 BHS 17-Jan-20 9:30 AM
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at U type retaining wall
7564 NMSCEW/P-IV/STR/2020/7507 7507 PUP Km 179+050 17-Jan-20 10:42 AM
A1 & A2
7565 NMSCEW/P-IV/STR/2020/7508 7508 Checking of bearing & grouting at RA-1 Viaduct Km 169+800 RHS 17-Jan-20 3:00 PM
Checking for stressing and remove slagness of H.T. wires at Girder no-197,198,199,200 at bed
7566 NMSCEW/P-IV/STR/2020/7509 7509 Girder Km 200+200 LHS 17-Jan-20 10:00 AM
no -01, Girder Type-02 at casting yard camp -2
Checking of reinforcement Girder no -197,198,199,200 at bed no -01, Girder Type-02 at
7567 NMSCEW/P-IV/STR/2020/7510 7510 Girder Km 200+200 LHS 17-Jan-20 10:30 AM
casting yard camp -2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
7568 NMSCEW/P-IV/STR/2020/7511 7511 Girder Km 200+200 LHS 17-Jan-20 6:30 PM
205,206,207,208 at bed no -6, Girder Type-01
7569 NMSCEW/P-IV/STR/2020/7512 7512 Checking of Shuttering,reinforcement & pouring concrete for pier starter at RP-11 Viaduct Km 213+915 RHS 17-Jan-20 10:00 AM
7570 NMSCEW/P-IV/STR/2020/7513 7513 Checking of Shuttering,reinforcement & pouring concrete for pier starter at RP-18 Viaduct Km 213+915 RHS 17-Jan-20 2:30 PM
7571 NMSCEW/P-IV/STR/2020/7514 7514 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-18 Viaduct Km 213+915 LHS 17-Jan-20 3:30 PM
7572 NMSCEW/P-IV/STR/2020/7515 7515 Checking layout ,level, & laying concrete for PCC at RP-7 Viaduct Km 213+915 RHS 17-Jan-20 3:00 PM
7573 NMSCEW/P-IV/STR/2020/7516 7516 Checking layout ,level, & laying concrete for PCC at LA-1 Viaduct Km 213+915 LHS 17-Jan-20 9:00 AM
7574 NMSCEW/P-IV/STR/2020/7517 7517 Checking layout ,level, & laying concrete for PCC at RP-8 Viaduct Km 213+915 RHS 17-Jan-20 3:17 PM
7575 NMSCEW/P-IV/STR/2020/7518 7518 Checking of reinforcement,shuttering and Pouring concrete for 5th lift at median wall W1 PUP Km 193+880 17-Jan-20 5:17 PM
7576 NMSCEW/P-IV/STR/2020/7519 7519 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-16 Viaduct Km 213+915 LHS 17-Jan-20 10:00 AM
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-2
7577 NMSCEW/P-IV/STR/2020/7520 7520 Box culvert Km 200+200 LHS 18-Jan-20 10:00 AM
I) 2x2 (0 to 2m) segment no.-1,2,3,4,5,6,7,8,9,10
7578 NMSCEW/P-IV/STR/2020/7521 7521 Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at retaining wall W1 MNB Km 199+360 LHS 18-Jan-20 3:00 PM
7579 NMSCEW/P-IV/STR/2020/7522 7522 Checking of reinforcement,shuttering and Pouring concrete for 5th lift at median wall W1 PUP Km 193+880 18-Jan-20 10:00 AM
7580 NMSCEW/P-IV/STR/2020/7523 7523 Checking of top bracket reinforcement,shuttering and Pouring concrete at retaining wall W1 PUP Km 191+740 RHS 18-Jan-20 4:00 PM
7581 NMSCEW/P-IV/STR/2020/7524 7524 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall W1 & W2 MNB Km 208+455 LHS 18-Jan-20 8:00 AM
Checking for stressing and remove slagness of H.T. wires at Girder no-209,210,211,212 at bed
7582 NMSCEW/P-IV/STR/2020/7525 7525 Girder Km 200+200 LHS 18-Jan-20 8:00 AM
no -08, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -209,210,211,212 at bed no -08, Girder Type-01 at
7583 NMSCEW/P-IV/STR/2020/7526 7526 Girder Km 200+200 LHS 18-Jan-20 8:30 AM
casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-213,214,215,216 at bed
7584 NMSCEW/P-IV/STR/2020/7527 7527 Girder Km 200+200 LHS 18-Jan-20 11:00 AM
no -04, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -213,214,215,216 at bed no -04, Girder Type-01 at
7585 NMSCEW/P-IV/STR/2020/7528 7528 Girder Km 200+200 LHS 18-Jan-20 11:30 AM
casting yard camp -2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
7586 NMSCEW/P-IV/STR/2020/7529 7529 Girder Km 200+200 LHS 18-Jan-20 10:15 AM
197,198,199,200 at bed no -1, Girder Type-02
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
7587 NMSCEW/P-IV/STR/2020/7530 7530 Girder Km 200+200 LHS 18-Jan-20 6:30 PM
209,210,211,212 at bed no -8, Girder Type-01
7588 NMSCEW/P-IV/STR/2020/7531 7531 Checking of layout,level for bearing fixing at RP-6 Viaduct Km 202+190 RHS 18-Jan-20 3:20 PM
7589 NMSCEW/P-IV/STR/2020/7532 7532 Checking of bearing & grouting at RP-3 Viaduct Km 169+800 RHS 18-Jan-20 3:00 PM
Box
7590 NMSCEW/P-IV/STR/2020/7533 7533 Checking of reinforcement, shuttering & pouring concrete(M-35) for bottom slab at Loop-B Km 0+457.121 18-Jan-20 12:30 PM
culvert(Loop-B)
7591 NMSCEW/P-IV/STR/2020/7534 7534 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 2nd lift at pier P-2 VOP Km 181+420 RHS 18-Jan-20 2:00 PM
7592 NMSCEW/P-IV/STR/2020/7535 7535 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 1st lift at wall A1 & A2 MNB Km 189+705 LHS 18-Jan-20 3:00 PM
7594 NMSCEW/P-IV/STR/2020/7537 7537 Checking of bearing & grouting at pedustal LP-13 Viaduct Km 202+190 LHS 18-Jan-20 2:20 PM
7595 NMSCEW/P-IV/STR/2020/7538 7538 Checking of bearing & grouting at pedustal RA-2 Viaduct Km 202+190 RHS 18-Jan-20 3:00 PM
7596 NMSCEW/P-IV/STR/2020/7539 7539 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP-15 Viaduct Km 213+915 RHS 18-Jan-20 2:30 PM IPC-14
7597 NMSCEW/P-IV/STR/2020/7540 7540 Checking of reinforcement, shuttering & pouring concrete for raft at RP-6 Viaduct Km 213+915 RHS 18-Jan-20 4:00 PM
7598 NMSCEW/P-IV/STR/2020/7541 7541 Checking of reinforcement, shuttering & pouring concrete for raft at LP-14 Viaduct Km 213+915 LHS 18-Jan-20 3:30 PM
7599 NMSCEW/P-IV/STR/2020/7542 7542 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP-1 Viaduct Km 213+915 RHS 18-Jan-20 3:00 PM
7600 NMSCEW/P-IV/STR/2020/7543 7543 Checking of reinforcement, shuttering & pouring concrete for pier shaft 2nd lift at LP-2 Viaduct Km 213+915 LHS 18-Jan-20 12:30 PM
7601 NMSCEW/P-IV/STR/2020/7544 7544 Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall W1 MNB Km 199+360 LHS 19-Jan-20 3:00 PM
7602 NMSCEW/P-IV/STR/2020/7545 7545 Checking of bearing & grouting at RA-4 Viaduct Km 169+800 RHS 19-Jan-20 3:30 PM
7603 NMSCEW/P-IV/STR/2020/7546 7546 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LA-1 Viaduct Km 196+560 LHS 19-Jan-20 10:50 AM
7604 NMSCEW/P-IV/STR/2020/7547 7547 Checking layout , reinforcement, shuttering & pouring concrete for pedestal at RP-8 Viaduct Km 196+560 RHS 19-Jan-20 11:20 AM
7605 NMSCEW/P-IV/STR/2020/7548 7548 Checking layout ,reinforcement, shuttering & pouring concrete for pedestal at RP-1 Viaduct Km 195+900 RHS 19-Jan-20 12:00 PM
7606 NMSCEW/P-IV/STR/2020/7549 7549 Checking layout ,reinforcement, shuttering & pouring concrete for pedestal at LP-1 Viaduct Km 195+900 LHS 19-Jan-20 12:30 PM
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at U type retaining wall
7607 NMSCEW/P-IV/STR/2020/7550 7550 PUP Km 179+050 19-Jan-20 9:30 AM
A1 & A2
Box
7608 NMSCEW/P-IV/STR/2020/7551 7551 Checking of reinforcement, shuttering & pouring concrete(M-35) for bottom slab at Loop-B Km 0+457.121 19-Jan-20 12:30 PM
culvert(Loop-B)
7609 NMSCEW/P-IV/STR/2020/7552 7552 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 2nd lift at pier P-2 VOP Km 181+420 RHS 19-Jan-20 8:00 AM
7610 NMSCEW/P-IV/STR/2020/7553 7553 Checking of reinforcement, shuttering & pouring concrete(M-35) for bottom slab MNB Km 181+078 LHS 19-Jan-20 12:50 PM
Checking of reinforcement, shuttering & pouring concrete(M-30) for1st lift at retaining wall
7611 NMSCEW/P-IV/STR/2020/7554 7554 MNB(Loop-B) Km 01+980 19-Jan-20 8:33 AM
A2 side Loop-B
Checking of excavated bed layout,level, & laying concrete PCC(M-15) for retaining wall A1
7612 NMSCEW/P-IV/STR/2020/7555 7555 MNB(Loop-C) Km 01+980 19-Jan-20 10:30 AM
side at loop-C
7613 NMSCEW/P-IV/STR/2020/7556 7556 Checking of excavated bed layout,level, & laying concrete PCC(M-15) for U type wing wall Box culvert Km 182+350 RHS 19-Jan-20 11:00 AM
7614 NMSCEW/P-IV/STR/2020/7557 7557 Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at retaining wall LA-1 MJB Km 205+610 LHS 20-Jan-20 10:00 AM
7615 NMSCEW/P-IV/STR/2020/7558 7558 Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at retaining wall RA-1 MJB Km 205+610 RHS 20-Jan-20 2:00 PM
7616 NMSCEW/P-IV/STR/2020/7559 7559 Checking of reinforcement,shuttering and Pouring concrete for raft at retaining wall A2 LVUP Km 178+323 LHS 20-Jan-20 2:30 PM
7617 NMSCEW/P-IV/STR/2020/7560 7560 Checking of layout,level, & laying concrete PCC at retaining wall A1 & A2 PUP Km 179+050 BHS 20-Jan-20 10:30 AM
7618 NMSCEW/P-IV/STR/2020/7561 7561 Checking of Shuttering,reinforcement & pouring concrete for abutment starter at LA-1 MNB Km 174+173 LHS 20-Jan-20 11:30 AM
7619 NMSCEW/P-IV/STR/2020/7562 7562 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 1st lift at wall A2 side Box culvert Km 168+330 LHS 20-Jan-20 4:00 PM
7620 NMSCEW/P-IV/STR/2020/7563 7563 Checking of layout,level,structural excavation & laying concrete PCC at wall A1 MNB Km 176+875 BHS 20-Jan-20 10:45 AM
Checking for stressing and remove slagness of H.T. wires at Girder no-217,218,219,220 at bed
7621 NMSCEW/P-IV/STR/2020/7564 7564 Girder Km 200+200 LHS 20-Jan-20 11:00 AM
no -05, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -217,218,219,220 at bed no -05, Girder Type-01 at
7622 NMSCEW/P-IV/STR/2020/7565 7565 Girder Km 200+200 LHS 20-Jan-20 11:30 AM
casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-201,202,203,204 at bed
7623 NMSCEW/P-IV/STR/2020/7566 7566 Girder Km 200+200 LHS 20-Jan-20 2:00 PM
no -02, Girder Type-02 at casting yard camp -2
Checking of reinforcement Girder no -201,202,203,204 at bed no -02, Girder Type-02 at
7624 NMSCEW/P-IV/STR/2020/7567 7567 Girder Km 200+200 LHS 20-Jan-20 2:30 PM
casting yard camp -2
7625 NMSCEW/P-IV/STR/2020/7568 7568 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-1 Viaduct Km 213+915 LHS 20-Jan-20 10:00 AM
7626 NMSCEW/P-IV/STR/2020/7569 7569 Checking of reinforcement, shuttering & pouring concrete for pier shaft 2nd lift at LP-2 Viaduct Km 213+915 LHS 20-Jan-20 2:30 PM
7627 NMSCEW/P-IV/STR/2020/7570 7570 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-18 Viaduct Km 213+915 LHS 20-Jan-20 3:00 PM
7628 NMSCEW/P-IV/STR/2020/7571 7571 Checking layout ,level, & laying concrete for PCC at LA-1 Viaduct Km 213+915 LHS 20-Jan-20 3:30 PM
7629 NMSCEW/P-IV/STR/2020/7572 7572 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-16 Viaduct Km 213+915 LHS 20-Jan-20 2:45 PM
7630 NMSCEW/P-IV/STR/2020/7573 7573 Checking of Shuttering,reinforcement & pouring concrete for pier starter at RP-16 Viaduct Km 213+915 RHS 20-Jan-20 3:10 PM
7631 NMSCEW/P-IV/STR/2020/7574 7574 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-17 Viaduct Km 213+915 RHS 20-Jan-20 2:20 PM IPC-14
7632 NMSCEW/P-IV/STR/2020/7575 7575 Checking of reinforcement, shuttering & pouring concrete for raft at LP-14 Viaduct Km 213+915 LHS 20-Jan-20 9:30 AM
7633 NMSCEW/P-IV/STR/2020/7576 7576 Checking of reinforcement, shuttering & pouring concrete for raft at RP-6 Viaduct Km 213+915 RHS 20-Jan-20 3:30 PM
7634 NMSCEW/P-IV/STR/2020/7577 7577 Checking of reinforcement, shuttering & pouring concrete(M-35) for bottom slab MNB Km 189+705 RHS 20-Jan-20 3:00 PM
7635 NMSCEW/P-IV/STR/2020/7578 7578 Checking of reinforcement, shuttering & pouring concrete(M-35) for 1st lift at wall A1 & A2 MNB Km 189+705 LHS 20-Jan-20 4:00 PM
7636 NMSCEW/P-IV/STR/2020/7579 7579 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 2nd lift at pier P-2 VOP Km 181+420 RHS 20-Jan-20 8:00 AM
7637 NMSCEW/P-IV/STR/2020/7580 7580 Checking of reinforcement, shuttering & pouring concrete(M-35) for bottom slab MNB Km 181+078 LHS 20-Jan-20 10:00 AM
Checking of reinforcement, shuttering & pouring concrete(M-30) for1st lift at retaining wall
7638 NMSCEW/P-IV/STR/2020/7581 7581 MNB(Loop-B) Km 01+980 20-Jan-20 8:33 AM
A2 side Loop-B
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
7639 NMSCEW/P-IV/STR/2020/7582 7582 Girder Km 200+200 LHS 20-Jan-20 9:30 AM SPOT RFI
213,214,215,216 at bed no -4, Girder Type-01
7640 NMSCEW/P-IV/STR/2020/7583 7583 Checking erection & jointing of pre cast utility duct (2*2) Utility duct Km 182+670 BHS 21-Jan-20 4:00 PM
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
7641 NMSCEW/P-IV/STR/2020/7584 7584 Girder Km 200+200 LHS 21-Jan-20 7:00 PM
217,218,219,220 at bed no -5, Girder Type-01
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
7642 NMSCEW/P-IV/STR/2020/7585 7585 Girder Km 200+200 LHS 21-Jan-20 6:30 PM
201,202,203,204 at bed no -2, Girder Type-02
Checking of layout,level, reinforcement,shuttering and Pouring concrete for raft at retaining
7643 NMSCEW/P-IV/STR/2020/7586 7586 PUP Km 206+985 LHS 21-Jan-20 8:00 AM
wall W1
7644 NMSCEW/P-IV/STR/2020/7587 7587 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at wall W1 MNB Km 208+455 RHS 21-Jan-20 9:00 AM
7645 NMSCEW/P-IV/STR/2020/7588 7588 Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at retaining wall W2 PUP Km 208+930 LHS 21-Jan-20 11:00 AM
7646 NMSCEW/P-IV/STR/2020/7589 7589 Checking of layout,level, reinforcement,shuttering and Pouring concrete for top slab PUP Km 212+080 RHS 21-Jan-20 3:30 PM
7647 NMSCEW/P-IV/STR/2020/7590 7590 Checking layout ,level, & laying concrete for PCC at pier RP-2 MJB Km 205+610 RHS 21-Jan-20 5:00 PM
Checking of top bracket reinforcement,shuttering and Pouring concrete for at retaining wall
7648 NMSCEW/P-IV/STR/2020/7591 7591 PUP Km 191+740 RHS 21-Jan-20 4:15 PM
W2
Checking of Shuttering,reinforcement & pouring concrete for cross girder between RP-5 to
7649 NMSCEW/P-IV/STR/2020/7592 7592 Viaduct Km 202+190 RHS 21-Jan-20 2:20 PM
RP-6
7650 NMSCEW/P-IV/STR/2020/7593 7593 Checking of Shuttering,reinforcement, pouring concrete for padestal at RP-1 Viaduct Km 195+900 RHS 21-Jan-20 3:00 PM
7651 NMSCEW/P-IV/STR/2020/7594 7594 Checking of Shuttering,reinforcement, pouring concrete for padestal at LP-1 Viaduct Km 195+900 LHS 21-Jan-20 3:30 PM
7652 NMSCEW/P-IV/STR/2020/7595 7595 Checking of bearing & grouting at RA-2 Viaduct Km 169+800 RHS 21-Jan-20 3:10 PM
7653 NMSCEW/P-IV/STR/2020/7596 7596 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 3rd lift at pier P-2 VOP Km 181+420 RHS 21-Jan-20 2:00 PM
7654 NMSCEW/P-IV/STR/2020/7597 7597 Checking of reinforcement,shuttering and Pouring concrete(M-35) for raft at abutment A1 VOP(LOOP-A) Km 3+131.586 RHS 21-Jan-20 3:00 PM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 2nd lift at retaining wall
7655 NMSCEW/P-IV/STR/2020/7598 7598 MNB(Loop-C) Km 01+980 21-Jan-20 8:10 AM
A-2(Loop-C)
Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st & final lift at LA-
7656 NMSCEW/P-IV/STR/2020/7599 7599 Viaduct Km 196+560 LHS 21-Jan-20 10:50 AM IPC-14
1
7657 NMSCEW/P-IV/STR/2020/7600 7600 Checking of Shuttering,reinforcement, pouring concrete for padestal at RP-8 Viaduct Km 196+560 RHS 21-Jan-20 11:20 AM
7658 NMSCEW/P-IV/STR/2020/7601 7601 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at wall W2 Box culvert Km 206+843 LHS 22-Jan-20 8:00 AM
7659 NMSCEW/P-IV/STR/2020/7602 7602 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at retaining wall W1 PUP Km 208+930 LHS 22-Jan-20 10:00 AM
7660 NMSCEW/P-IV/STR/2020/7603 7603 Checking of reinforcement, shuttering & pouring concrete for abutment shaft 1st lift at RA-1 Viaduct Km 196+560 RHS 22-Jan-20 3:20 PM IPC-14
Checking for stressing and remove slagness of H.T. wires at Girder no-221,222,223,224 at bed
7661 NMSCEW/P-IV/STR/2020/7604 7604 Girder Km 200+200 LHS 22-Jan-20 4:00 PM
no -03, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -221,222,223,224 at bed no -03, Girder Type-01 at
7662 NMSCEW/P-IV/STR/2020/7605 7605 Girder Km 200+200 LHS 22-Jan-20 4:30 PM
casting yard camp -2
Checking of Shuttering,reinforcement & pouring concrete for cross girder between RP-6 to
7663 NMSCEW/P-IV/STR/2020/7606 7606 Viaduct Km 202+190 RHS 22-Jan-20 2:20 PM
RP-7
7664 NMSCEW/P-IV/STR/2020/7607 7607 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-18 Viaduct Km 213+915 LHS 22-Jan-20 4:10 PM IPC-14
7665 NMSCEW/P-IV/STR/2020/7608 7608 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-16 Viaduct Km 213+915 LHS 22-Jan-20 9:30 AM
7666 NMSCEW/P-IV/STR/2020/7609 7609 Checking of Shuttering,reinforcement & pouring concrete for pier starter at RP-18 Viaduct Km 213+915 RHS 22-Jan-20 9:45 AM IPC-14
7667 NMSCEW/P-IV/STR/2020/7610 7610 Checking layout ,level, & laying concrete for PCC at LA-1 Viaduct Km 213+915 LHS 22-Jan-20 3:00 PM
7668 NMSCEW/P-IV/STR/2020/7611 7611 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-15 Viaduct Km 213+915 LHS 22-Jan-20 4:30 PM
7669 NMSCEW/P-IV/STR/2020/7612 7612 Checking of Shuttering,reinforcement & pouring concrete for raft at LA-1 MNB Km 167+547 LHS 22-Jan-20 4:05 PM
7670 NMSCEW/P-IV/STR/2020/7613 7613 Checking of reinforcement, shuttering & pouring concrete(M-35) for bottom slab MNB Km 189+705 RHS 22-Jan-20 5:30 PM
7671 NMSCEW/P-IV/STR/2020/7614 7614 Checking of reinforcement, shuttering & pouring concrete(M-35) for 1st lift at wall A1 & A2 MNB Km 189+705 LHS 22-Jan-20 3:10 PM
7672 NMSCEW/P-IV/STR/2020/7615 7615 Checking of bearing & grouting at RP-1 Viaduct Km 169+800 RHS 22-Jan-20 4:20 PM
7673 NMSCEW/P-IV/STR/2020/7616 7616 Checking of Shuttering,reinforcement & pouring concrete for raft at retaining wall A1 & A2 LVUP Km 169+291 LHS 22-Jan-20 3:50 PM
7674 NMSCEW/P-IV/STR/2020/7617 7617 Checking of Shuttering,reinforcement & pouring concrete for 5th lift at retaining wall W1 PUP Km 193+880 LHS 22-Jan-20 10:55 AM
7675 NMSCEW/P-IV/STR/2020/7618 7618 Checking of Shuttering,reinforcement & pouring concrete for 4th lift at retaining wall RA1 MJB Km 205+610 RHS 23-Jan-20 11:00 AM
7676 NMSCEW/P-IV/STR/2020/7619 7619 Checking of Shuttering,reinforcement & pouring concrete for 4th lift at median wall W1 & W2 MJB Km 205+610 23-Jan-20 2:00 PM
7677 NMSCEW/P-IV/STR/2020/7620 7620 Checking layout ,level, & laying concrete for PCC at pier RP-2 MJB Km 205+610 RHS 23-Jan-20 4:00 PM
Checking of Shuttering,reinforcement & pouring concrete for 1st lift at retaining wall W1 &
7678 NMSCEW/P-IV/STR/2020/7621 7621 PUP Km 206+985 LHS 23-Jan-20 8:00 AM
W2
7679 NMSCEW/P-IV/STR/2020/7622 7622 Checking of Shuttering,reinforcement & pouring concrete for 2nd lift at wall W2 MNB Km 208+455 RHS 23-Jan-20 10:00 AM
7680 NMSCEW/P-IV/STR/2020/7623 7623 Checking of Shuttering,reinforcement & pouring concrete for 1st lift at median wall W1 & W2 PUP Km 208+930 23-Jan-20 2:30 PM
7681 NMSCEW/P-IV/STR/2020/7624 7624 Checking layout ,level,Shuttering,reinforcement & pouring concrete for raft (service road) PUP Km 211+210 LHS 23-Jan-20 11:30 AM
Checking of Shuttering,reinforcement & pouring concrete for deck slab between LP-10 to LA-
7682 NMSCEW/P-IV/STR/2020/7625 7625 Viaduct Km 169+800 LHS 23-Jan-20 5:00 PM
2
7683 NMSCEW/P-IV/STR/2020/7626 7626 Checking of layout, Shuttering,reinforcement, pouring concrete for padestal at RP-5 Viaduct Km 196+560 RHS 23-Jan-20 10:30 AM
7684 NMSCEW/P-IV/STR/2020/7627 7627 Checking of Shuttering,reinforcement, pouring concrete for padestal at RA-2 Viaduct Km 202+190 RHS 23-Jan-20 2:20 PM
7685 NMSCEW/P-IV/STR/2020/7628 7628 Checking of Shuttering,reinforcement, pouring concrete for padestal at LP-13 Viaduct Km 202+190 LHS 23-Jan-20 3:30 PM
7686 NMSCEW/P-IV/STR/2020/7629 7629 Checking of Shuttering,reinforcement, pouring concrete for padestal at RP-13 Viaduct Km 202+190 RHS 23-Jan-20 4:30 PM
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
7687 NMSCEW/P-IV/STR/2020/7630 7630 Girder Km 200+200 LHS 23-Jan-20 5:30 PM
221,222,223,224 at bed no -3, Girder Type-01
Checking for stressing and remove slagness of H.T. wires at Girder no-225,226,227,228 at bed
7688 NMSCEW/P-IV/STR/2020/7631 7631 Girder Km 200+200 LHS 23-Jan-20 6:00 PM
no -07, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -225,226,227,228 at bed no -07, Girder Type-01 at
7689 NMSCEW/P-IV/STR/2020/7632 7632 Girder Km 200+200 LHS 23-Jan-20 6:30 PM
casting yard camp -2
7690 NMSCEW/P-IV/STR/2020/7633 7633 Checking of Shuttering,reinforcement & pouring concrete for raft at retaining wall A1 LVUP Km 178+323 LHS 23-Jan-20 11:30 AM
Checking of Shuttering,reinforcement & pouring concrete(M-30) for 5th lift at retaining wall
7691 NMSCEW/P-IV/STR/2020/7634 7634 LVUP Km 173+400 LHS 23-Jan-20 2:00 PM
A2
7692 NMSCEW/P-IV/STR/2020/7635 7635 Checking of completion of segment erection for 2×2 utility duct Utility duct Km 188+390 23-Jan-20 10:15 AM
7693 NMSCEW/P-IV/STR/2020/7636 7636 Checking of completion of segment erection for 3×3 box culvert Box culvert Km 188+726 23-Jan-20 11:15 AM
Checking of Shuttering,reinforcement & pouring concrete for raft with bottom haunch A1 &
7694 NMSCEW/P-IV/STR/2020/7637 7637 Box culvert Km 165+510 LHS 23-Jan-20 5:30 PM
A2
7695 NMSCEW/P-IV/STR/2020/7638 7638 Checking of reinforcement,shuttering and Pouring concrete(M-35) for raft at abutment A1 VOP(LOOP-A) Km 3+131.586 RHS 23-Jan-20 10:00 AM
7696 NMSCEW/P-IV/STR/2020/7639 7639 Checking of excavated bed layout,level, & laying concrete PCC(M-15) for butment A2 VOP(LOOP-A) Km 3+131.586 RHS 23-Jan-20 8:00 AM
Checking of reinforcement, shuttering & pouring concrete(M-30) for raft at retaining wall A1
7697 NMSCEW/P-IV/STR/2020/7640 7640 MNB(Loop-B) Km 01+980 23-Jan-20 2:00 PM
side Loop-B
7698 NMSCEW/P-IV/STR/2020/7641 7641 Checking of reinforcement, shuttering & pouring concrete(M-30) for U type wing wall Box culvert Km 182+350 RHS 23-Jan-20 11:00 AM
7699 NMSCEW/P-IV/STR/2020/7642 7642 Checking of reinforcement,shuttering and Pouring concrete(M-35) for raft at abutment A1 VOP(LOOP-A) Km 3+131.586 LHS 23-Jan-20 10:30 AM
7700 NMSCEW/P-IV/STR/2020/7643 7643 Checking of excavated bed layout,level, & laying concrete PCC(M-15) for butment A2 VOP(LOOP-A) Km 3+131.586 LHS 23-Jan-20 8:30 AM
Checking of reinforcement,shuttering and Pouring concrete for retaining wall W1 & W2 top
7701 NMSCEW/P-IV/STR/2020/7644 7644 PUP Km 193+880 LHS 24-Jan-20 4:00 PM
bracket
7702 NMSCEW/P-IV/STR/2020/7645 7645 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at wall W1 & W2 Box culvert Km 193+940 LHS 24-Jan-20 2:00 PM
Checking of Shuttering,reinforcement & pouring concrete for 2nd lift at retaining wall W1 &
7703 NMSCEW/P-IV/STR/2020/7646 7646 PUP Km 206+985 LHS 24-Jan-20 10:00 AM
W2
7704 NMSCEW/P-IV/STR/2020/7647 7647 Checking of Shuttering,reinforcement & pouring concrete for 2nd lift at median wall W1 MNB Km 208+455 24-Jan-20 2:15 PM
7705 NMSCEW/P-IV/STR/2020/7648 7648 Checking layout ,level,Shuttering,reinforcement & pouring concrete for top slab Box culvert Km 208+675 LHS 24-Jan-20 4:15 PM
7706 NMSCEW/P-IV/STR/2020/7649 7649 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at MCW wall W1 PUP Km 211+210 24-Jan-20 5:00 PM
7710 NMSCEW/P-IV/STR/2020/7653 7653 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP-18 Viaduct Km 213+915 RHS 24-Jan-20 3:00 PM IPC-14
7711 NMSCEW/P-IV/STR/2020/7654 7654 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-15 Viaduct Km 213+915 LHS 24-Jan-20 2:00 PM IPC-14
7712 NMSCEW/P-IV/STR/2020/7655 7655 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-18 Viaduct Km 213+915 LHS 24-Jan-20 4:00 PM
7713 NMSCEW/P-IV/STR/2020/7656 7656 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-15 Viaduct Km 213+915 RHS 24-Jan-20 4:30 PM
7714 NMSCEW/P-IV/STR/2020/7657 7657 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-16 Viaduct Km 213+915 LHS 24-Jan-20 9:30 AM IPC-14
7715 NMSCEW/P-IV/STR/2020/7658 7658 Checking of Shuttering,reinforcement & pouring concrete for pier starter at RP-16 Viaduct Km 213+915 RHS 24-Jan-20 9:45 AM IPC-14
7716 NMSCEW/P-IV/STR/2020/7659 7659 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP-1 Viaduct Km 213+915 RHS 24-Jan-20 4:45 PM
7717 NMSCEW/P-IV/STR/2020/7660 7660 Checking of layout,level for bearing fixing at RP-7 Viaduct Km 202+190 RHS 24-Jan-20 3:20 PM
Checking of Shuttering,reinforcement & pouring concrete for final lift with top haunch and top
7718 NMSCEW/P-IV/STR/2020/7661 7661 Box culvert Km 180+180 RHS 24-Jan-20 11:30 AM
slab
Checking of Shuttering,reinforcement & pouring concrete for final lift with top haunch A1, A2
7719 NMSCEW/P-IV/STR/2020/7662 7662 VUP Km 166+987 LHS 24-Jan-20 4:10 PM
and top slab
7720 NMSCEW/P-IV/STR/2020/7663 7663 Checking of Shuttering,reinforcement & pouring concrete for raft at LA-1 MNB Km 167+547 LHS 24-Jan-20 4:44 PM
7721 NMSCEW/P-IV/STR/2020/7664 7664 Checking of Shuttering,reinforcement & pouring concrete(M-30) for wing wall raft Box culvert Km 186+352 RHS 24-Jan-20 3:00 PM
Checking of excavated bed layout,level, & laying concrete PCC(M-10) for wing wall
7722 NMSCEW/P-IV/STR/2020/7665 7665 VUP Km 187+113 LHS 24-Jan-20 4:20 PM
foundation at A2 side
7723 NMSCEW/P-IV/STR/2020/7666 7666 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall W1 & W2 Utility duct Km 209+280 BHS 25-Jan-20 8:00 AM
7724 NMSCEW/P-IV/STR/2020/7667 7667 Checking of Shuttering,reinforcement & pouring concrete for 4th lift at median wall A1 MJB Km 205+610 25-Jan-20 10:00 AM
7725 NMSCEW/P-IV/STR/2020/7668 7668 Checking layout ,level,Shuttering,reinforcement & pouring concrete for MCW slab Box culvert Km 206+843 LHS 25-Jan-20 8:00 AM
7726 NMSCEW/P-IV/STR/2020/7669 7669 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at wall W1 MNB Km 208+455 LHS 25-Jan-20 10:15 AM
7727 NMSCEW/P-IV/STR/2020/7670 7670 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at retaining wall W1 PUP Km 208+930 LHS 25-Jan-20 11:00 AM
7728 NMSCEW/P-IV/STR/2020/7671 7671 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at MCW wall W2 PUP Km 211+210 25-Jan-20 2:00 PM
7729 NMSCEW/P-IV/STR/2020/7672 7672 Checking layout ,level,Shuttering,reinforcement & pouring concrete for top slab Box culvert Km 193+940 LHS 25-Jan-20 10:30 AM
7730 NMSCEW/P-IV/STR/2020/7673 7673 Checking layout ,level,Shuttering,reinforcement & pouring concrete for raft Box culvert Km 192+039 LHS 25-Jan-20 5:00 PM
7731 NMSCEW/P-IV/STR/2020/7674 7674 Checking layout ,level, & laying concrete for PCC at pier RP-2 MJB Km 205+610 RHS 25-Jan-20 10:45 AM
Checking of Shuttering,reinforcement & pouring concrete for raft with bottom haunch A1 &
7732 NMSCEW/P-IV/STR/2020/7675 7675 Box culvert Km 167+696 RHS 25-Jan-20 4:00 PM
A2
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-1
7733 NMSCEW/P-IV/STR/2020/7676 7676 Box culvert Km 175+500 LHS 25-Jan-20 9:30 AM
I) 2x2 (2 to 4m) segment no.-
415,416,417,418,419,420,421,422,423,424,425,426,427,428,429,430,431,432,433,434,435
7734 NMSCEW/P-IV/STR/2020/7677 7677 Checking of reinforcement,shuttering and Pouring concrete(M-35) for raft at abutment A2 VOP(Loop-A) Km 3+131.586 RHS 25-Jan-20 10:00 AM
7736 NMSCEW/P-IV/STR/2020/7679 7679 Checking of reinforcement, shuttering & pouring concrete(M-30) for U type wing wall Box culvert Km 182+350 RHS 25-Jan-20 11:00 AM
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 2nd lift at retaining wall
7737 NMSCEW/P-IV/STR/2020/7680 7680 MNB(Loop-B) Km 01+980 25-Jan-20 8:00 AM
(Loop-B)
Checking of reinforcement,shuttering and Pouring concrete(M-30) for 3rd lift at retaining wall
7738 NMSCEW/P-IV/STR/2020/7681 7681 MNB(Loop-C) Km 01+980 25-Jan-20 9:00 AM
(Loop-C)
7739 NMSCEW/P-IV/STR/2020/7682 7682 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 3rd lift at pier P-2 VOP Km 181+420 RHS 25-Jan-20 11:30 AM
7740 NMSCEW/P-IV/STR/2020/7683 7683 Checking of reinforcement,shuttering and Pouring concrete(M-35) for raft at abutment A2 VOP(Loop-A) Km 3+131.586 LHS 25-Jan-20 10:37 AM
Checking of excavated bed layout,level, & laying concrete PCC(M-10) for wing wall
7741 NMSCEW/P-IV/STR/2020/7684 7684 VUP Km 187+113 RHS 25-Jan-20 10:00 AM
foundation at A2 side
7742 NMSCEW/P-IV/STR/2020/7685 7685 Checking of excavated bed layout,level, & laying concrete PCC(M-10) for curtain wall Box culvert Km 186+352 LHS 25-Jan-20 11:00 AM
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
7743 NMSCEW/P-IV/STR/2020/7686 7686 Girder Km 200+200 LHS 25-Jan-20 8:30 AM
221,222,223,224 at bed no -3, Girder Type-01
Checking for stressing and remove slagness of H.T. wires at Girder no-233,234,235,236 at bed
7744 NMSCEW/P-IV/STR/2020/7687 7687 Girder Km 200+200 LHS 25-Jan-20 6:00 PM
no -08, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -233,234,235,236 at bed no -08, Girder Type-01 at
7745 NMSCEW/P-IV/STR/2020/7688 7688 Girder Km 200+200 LHS 25-Jan-20 6:30 PM
casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-205,206,207,208 at bed
7746 NMSCEW/P-IV/STR/2020/7689 7689 Girder Km 200+200 LHS 25-Jan-20 8:00 AM
no -01, Girder Type-02 at casting yard camp -2
Checking of reinforcement Girder no -205,206,207,208 at bed no -01, Girder Type-02 at
7747 NMSCEW/P-IV/STR/2020/7690 7690 Girder Km 200+200 LHS 25-Jan-20 8:30 AM
casting yard camp -2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
7748 NMSCEW/P-IV/STR/2020/7691 7691 Girder Km 200+200 LHS 25-Jan-20 6:40 PM
205,206,207,208 at bed no -01, Girder Type-02
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
7749 NMSCEW/P-IV/STR/2020/7692 7692 Girder Km 200+200 LHS 25-Jan-20 7:00 PM
229,230,231,232 at bed no -06, Girder Type-01
7750 NMSCEW/P-IV/STR/2020/7693 7693 Checking of Shuttering,reinforcement, pouring concrete for padestal at RA-2 Viaduct Km 202+190 RHS 25-Jan-20 2:20 PM
7751 NMSCEW/P-IV/STR/2020/7694 7694 Checking of Shuttering,reinforcement, pouring concrete for padestal at LP-13 Viaduct Km 202+190 LHS 25-Jan-20 3:30 PM
7752 NMSCEW/P-IV/STR/2020/7695 7695 Checking of Shuttering,reinforcement, pouring concrete for padestal at RP-13 Viaduct Km 202+190 RHS 25-Jan-20 4:30 PM
7753 NMSCEW/P-IV/STR/2020/7696 7696 Checking of Shuttering,reinforcement, pouring concrete for abutment cap at LA2 Viaduct Km 200+920 LHS 25-Jan-20 10:00 AM
7754 NMSCEW/P-IV/STR/2020/7697 7697 Checking of Shuttering,reinforcement, pouring concrete for pier cap at RP-3 Viaduct Km 200+920 RHS 25-Jan-20 4:00 PM
Checking of reinforcement,shuttering and Pouring concrete for final lift with top haunch at
7755 NMSCEW/P-IV/STR/2020/7698 7698 Box culvert Km 162+832 LHS 25-Jan-20 4:16 PM
wall A1 & A2 and top slab
Checking of reinforcement,shuttering and Pouring concrete(M-35) for raft foundation at
7756 NMSCEW/P-IV/STR/2020/7699 7699 MJB Km 205+610 RHS 27-Jan-20 4:00 PM
retaining wall RA2
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at retaining wall W1 &
7757 NMSCEW/P-IV/STR/2020/7700 7700 PUP Km 206+985 LHS 27-Jan-20 8:00 AM
W2
7758 NMSCEW/P-IV/STR/2020/7701 7701 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at wall W2 MNB Km 208+455 LHS 27-Jan-20 10:00 AM
7759 NMSCEW/P-IV/STR/2020/7702 7702 Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at retaining wall W1 PUP Km 208+930 LHS 27-Jan-20 11:00 AM
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at median wall W1 &
7760 NMSCEW/P-IV/STR/2020/7703 7703 PUP Km 208+930 27-Jan-20 2:00 PM
W2
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall W1 & W2
7761 NMSCEW/P-IV/STR/2020/7704 7704 PUP Km 211+210 RHS 27-Jan-20 3:00 PM
(service road)
7762 NMSCEW/P-IV/STR/2020/7705 7705 Checking of completion of segment erection for 2×2 utility duct Utility duct Km 189+380 27-Jan-20 10:30 AM
Checking layout ,level,Shuttering,reinforcement & pouring concrete for raft at retaining wall
7763 NMSCEW/P-IV/STR/2020/7706 7706 PUP Km 212+080 LHS 27-Jan-20 12:00 PM
W1 & W2
7764 NMSCEW/P-IV/STR/2020/7707 7707 Checking of reinforcement,shuttering and Pouring concrete for 5th lift at retaining wall A2 LVUP Km 173+400 LHS 27-Jan-20 2:00 PM
Checking of reinforcement,shuttering and Pouring concrete for final lift with top haunch at
7765 NMSCEW/P-IV/STR/2020/7708 7708 Box culvert Km 162+832 LHS 27-Jan-20 4:00 PM
wall A1 & A2 and top slab
Checking of reinforcement,shuttering and Pouring concrete for final lift with top haunch at
7766 NMSCEW/P-IV/STR/2020/7709 7709 VUP Km 166+987 LHS 27-Jan-20 4:30 PM
wall A1 & A2 and top slab
7767 NMSCEW/P-IV/STR/2020/7710 7710 Checking of reinforcement,shuttering and Pouring concrete(M-30) for curtain wall Box culvert Km 186+352 LHS 27-Jan-20 2:15 PM
7768 NMSCEW/P-IV/STR/2020/7711 7711 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 2nd lift at wall A1 & A2 MNB Km 189+705 LHS 27-Jan-20 3:00 PM
7771 NMSCEW/P-IV/STR/2020/7714 7714 Checking of reinforcement, shuttering & pouring concrete for abutmenr shaft 2nd lift at RA-1 Viaduct Km 196+560 RHS 27-Jan-20 3:30 PM
Checking for stressing and remove slagness of H.T. wires at Girder no-233,234,235,236 at bed
7772 NMSCEW/P-IV/STR/2020/7715 7715 Girder Km 200+200 LHS 27-Jan-20 2:00 PM
no -08, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -233,234,235,236 at bed no -08, Girder Type-01 at
7773 NMSCEW/P-IV/STR/2020/7716 7716 Girder Km 200+200 LHS 27-Jan-20 2:30 PM
casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-237,238,239,240 at bed
7774 NMSCEW/P-IV/STR/2020/7717 7717 Girder Km 200+200 LHS 27-Jan-20 6:00 PM
no -04, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -237,238,239,240 at bed no -04, Girder Type-01 at
7775 NMSCEW/P-IV/STR/2020/7718 7718 Girder Km 200+200 LHS 27-Jan-20 6:40 PM
casting yard camp -2
7776 NMSCEW/P-IV/STR/2020/7719 7719 Checking of Shuttering,reinforcement & pouring concrete(M-35) for abutment raft at A2 VUP Km 182+420 RHS 27-Jan-20 4:00 PM
7780 NMSCEW/P-IV/STR/2020/7723 7723 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 4th lift at pier P-2 VOP Km 181+420 RHS 27-Jan-20 11:18 AM
7781 NMSCEW/P-IV/STR/2020/7724 7724 Checking of Shuttering,reinforcement, pouring concrete for pier cap at RP-3 Viaduct Km 200+920 RHS 27-Jan-20 3:00 PM
Checking of Shuttering,reinforcement & pouring concrete for cross girder between RP-7 to
7782 NMSCEW/P-IV/STR/2020/7725 7725 Viaduct Km 202+190 RHS 27-Jan-20 2:20 PM
RP-8
7783 NMSCEW/P-IV/STR/2020/7726 7726 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-16 Viaduct Km 213+915 LHS 27-Jan-20 3:00 PM
7784 NMSCEW/P-IV/STR/2020/7727 7727 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-18 Viaduct Km 213+915 LHS 27-Jan-20 10:00 AM
7785 NMSCEW/P-IV/STR/2020/7728 7728 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-15 Viaduct Km 213+915 RHS 27-Jan-20 4:30 PM
7786 NMSCEW/P-IV/STR/2020/7729 7729 Checking of Shuttering,reinforcement & pouring concrete for raft at RP-12 Viaduct Km 213+915 RHS 27-Jan-20 4:45 PM
7787 NMSCEW/P-IV/STR/2020/7730 7730 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP-1 Viaduct Km 213+915 RHS 27-Jan-20 2:30 PM
7789 NMSCEW/P-IV/STR/2020/7732 7732 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall W1 & W2 Box culvert Km 192+039 LHS 28-Jan-20 2:00 PM
7790 NMSCEW/P-IV/STR/2020/7733 7733 Checking layout ,level,Shuttering,reinforcement & pouring concrete for top slab Box culvert Km 193+940 RHS 28-Jan-20 5:00 PM
7791 NMSCEW/P-IV/STR/2020/7734 7734 Checking of layout,level, & laying concrete PCC for U type wing wall Box culvert Km 204+920 28-Jan-20 10:00 AM
Checking layout ,level,Shuttering,reinforcement & pouring concrete for raft at retaining wall
7792 NMSCEW/P-IV/STR/2020/7735 7735 MNB Km 199+360 RHS 28-Jan-20 10:15 AM
W1
Checking of reinforcement,shuttering and Pouring concrete for retaining wall W1 & W2 top
7793 NMSCEW/P-IV/STR/2020/7736 7736 PUP Km 208+930 RHS 28-Jan-20 8:00 AM
bracket
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall W1 & W2
7794 NMSCEW/P-IV/STR/2020/7737 7737 PUP Km 211+210 LHS 28-Jan-20 10:30 AM
(service road)
7795 NMSCEW/P-IV/STR/2020/7738 7738 Checking layout ,level,Shuttering,reinforcement & pouring concrete for MCW slab Box culvert Km 206+843 LHS 28-Jan-20 9:00 AM
7796 NMSCEW/P-IV/STR/2020/7739 7739 Checking layout ,level,& laying concrete PCC at MCW Box culvert Km 214+805 BHS 28-Jan-20 10:05 AM
Checking of Shuttering,reinforcement & pouring concrete for raft with bottom haunch at wall
7797 NMSCEW/P-IV/STR/2020/7740 7740 Box culvert Km 184+823 BHS 28-Jan-20 4:00 PM
A1 & A2
Checking of layout ,level structural excavation & laying concrete PCC for Pipe culvert
7798 NMSCEW/P-IV/STR/2020/7741 7741 Pipe culvert Km 170+080 LHS 28-Jan-20 4:16 PM
median drain outlet
Checking of Shuttering,reinforcement & pouring concrete for raft with bottom haunch at wall
7799 NMSCEW/P-IV/STR/2020/7742 7742 PUP Km 168+380 LHS 28-Jan-20 5:00 PM
A1 & A2
7800 NMSCEW/P-IV/STR/2020/7743 7743 Checking of Shuttering,reinforcement & pouring concrete(M-45) for deck slab RP-10 to RA-2 Viaduct Km 169+800 RHS 28-Jan-20 4:30 PM
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-1
7801 NMSCEW/P-IV/STR/2020/7744 7744 Box culvert Km 175+500 LHS 28-Jan-20 11:00 AM
I) 2x2 (2 to 4m) segment no.-436,437,438,439,440,441,442,443,444,445,446,447,448,449,450
Checking of excavated bed layout,level, & laying concrete PCC(M-10) for retaining wall A1
7802 NMSCEW/P-IV/STR/2020/7745 7745 VUP Km 181+700 LHS 28-Jan-20 11:30 AM
& A2 side
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
7803 NMSCEW/P-IV/STR/2020/7746 7746 Girder Km 200+200 LHS 28-Jan-20 7:00 PM
233,234,235,236 at bed no -8, Girder Type-01
Checking of Shuttering,reinforcement & pouring concrete for cross girder between RP-6 to
7804 NMSCEW/P-IV/STR/2020/7747 7747 Viaduct Km 202+190 RHS 28-Jan-20 3:00 PM
RP-7
7805 NMSCEW/P-IV/STR/2020/7748 7748 Checking of Shuttering,reinforcement & pouring concrete for raft at retaining wall A1 LVUP Km 178+323 RHS 28-Jan-20 11:30 AM
7806 NMSCEW/P-IV/STR/2020/7749 7749 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at median wall W2 MNB Km 208+455 29-Jan-20 8:00 AM
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at median wall W1 &
7807 NMSCEW/P-IV/STR/2020/7750 7750 PUP Km 208+930 29-Jan-20 10:00 AM
W2
7808 NMSCEW/P-IV/STR/2020/7751 7751 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP-7 Viaduct Km 195+900 RHS 29-Jan-20 3:00 PM IPC-14
7818 NMSCEW/P-IV/STR/2020/7761 7761 Checking of reinforcement,shuttering and Pouring concrete(M-35) for raft at abutment A2 VUP Km 182+420 RHS 29-Jan-20 4:20 PM
7819 NMSCEW/P-IV/STR/2020/7762 7762 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at retaining wall W-1 MNB Km 199+360 RHS 29-Jan-20 10:00 AM
Checking of reinforcement,shuttering and Pouring concrete for retaining wall W1 & W2 top
7820 NMSCEW/P-IV/STR/2020/7763 7763 PUP Km 193+880 RHS 29-Jan-20 2:15 PM
bracket
7821 NMSCEW/P-IV/STR/2020/7764 7764 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-16 Viaduct Km 213+915 LHS 29-Jan-20 3:00 PM
7822 NMSCEW/P-IV/STR/2020/7765 7765 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-18 Viaduct Km 213+915 LHS 29-Jan-20 2:30 PM
7823 NMSCEW/P-IV/STR/2020/7766 7766 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-15 Viaduct Km 213+915 RHS 29-Jan-20 10:30 AM
Checking for stressing and remove slagness of H.T. wires at Girder no-241,242,243,244 at bed
7824 NMSCEW/P-IV/STR/2020/7767 7767 Girder Km 200+200 LHS 29-Jan-20 6:00 PM
no -05, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -241,242,243,244 at bed no -05, Girder Type-01 at
7825 NMSCEW/P-IV/STR/2020/7768 7768 Girder Km 200+200 LHS 29-Jan-20 6:30 PM
casting yard camp -2
7826 NMSCEW/P-IV/STR/2020/7769 7769 Checking of excavation, layout ,level & laying concrete PCC for median drain outlet Pipe culvert Km 196+360 RHS 29-Jan-20 11:15 AM
7827 NMSCEW/P-IV/STR/2020/7770 7770 Checking errection and jointing of segments for utility culvert (2x2) Utility duct Km 166+330 BHS 29-Jan-20 10:10 AM
7828 NMSCEW/P-IV/STR/2020/7771 7771 Checking errection and jointing of segments for box culvert (3x3) Box culvert Km 164+756 BHS 29-Jan-20 4:10 PM
7829 NMSCEW/P-IV/STR/2020/7772 7772 Checking of reinforcement,shuttering and Pouring concrete for slab at (2x2) utility duct Utility duct Km 209+280 BHS 30-Jan-20 8:00 AM
7830 NMSCEW/P-IV/STR/2020/7773 7773 Checking of reinforcement, shuttering & pouring concrete for abutment shaft 2nd lift LA2 MJB Km 205+610 LHS 30-Jan-20 10:00 AM
Checking layout ,level,Shuttering,reinforcement & pouring concrete for raft at retaining wall
7831 NMSCEW/P-IV/STR/2020/7774 7774 MJB Km 205+610 LHS 30-Jan-20 2:00 PM
LA2
Checking of reinforcement,shuttering and Pouring concrete for median wall W1 & W2 top
7832 NMSCEW/P-IV/STR/2020/7775 7775 PUP Km 208+930 30-Jan-20 8:15 AM
bracket
Checking of reinforcement,shuttering and Pouring concrete for retaining wall W1 & W2 top
7833 NMSCEW/P-IV/STR/2020/7776 7776 PUP Km 208+930 LHS 30-Jan-20 10:15 AM
bracket
7834 NMSCEW/P-IV/STR/2020/7777 7777 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at retaining wall W1 MNB Km 199+360 RHS 30-Jan-20 10:30 AM
7835 NMSCEW/P-IV/STR/2020/7778 7778 Checking layout ,level,Shuttering,reinforcement & pouring concrete for top slab Box culvert Km 192+039 LHS 30-Jan-20 5:00 PM
Checking of reinforcement,shuttering and Pouring concrete for final lift with top haunch at
7836 NMSCEW/P-IV/STR/2020/7779 7779 PUP Km 168+380 RHS 30-Jan-20 12:00 PM
wall A1 & A2 and top slab
Checking of reinforcement,shuttering and Pouring concrete for final lift with top haunch at
7837 NMSCEW/P-IV/STR/2020/7780 7780 Box culvert Km 168+330 RHS 30-Jan-20 5:00 PM
wall A1 & A2 and top slab
7838 NMSCEW/P-IV/STR/2020/7781 7781 Checking of layout,level, structural excavation for U type wing wall A2 VUP Km 179+983 LHS 30-Jan-20 9:30 AM
7839 NMSCEW/P-IV/STR/2020/7782 7782 Checking layout ,level,Shuttering,reinforcement & pouring concrete for raft Box culvert Km 180+110 BHS 30-Jan-20 10:30 AM
Checking of reinforcement,shuttering and Pouring concrete for final lift with top haunch at
7840 NMSCEW/P-IV/STR/2020/7783 7783 Box culvert Km 180+180 LHS 30-Jan-20 4:30 PM
wall A1 & A2 and top slab
Checking of Hume pipe (1000×2500)mm Laying , fixing & jointing for Median drain pipe
7841 NMSCEW/P-IV/STR/2020/7784 7784 Pipe culvert Km 170+080 LHS 30-Jan-20 9:00 AM
culvert outlets
7842 NMSCEW/P-IV/STR/2020/7785 7785 Checking of layout,level,structural excavation & laying concrete PCC for wing wall A1 & A2 VUP Km 166+987 LHS 30-Jan-20 3:00 PM
Checking of reinforcement,shuttering and Pouring concrete(M-35) for 1st lift at abutment wall
7843 NMSCEW/P-IV/STR/2020/7786 7786 VOP(Loop-A) Km 3+131.586 RHS 30-Jan-20 2:00 PM
A1
7844 NMSCEW/P-IV/STR/2020/7787 7787 Checking of reinforcement,shuttering and Pouring concrete(M-35) for 5th lift at pier P-2 VOP Km 181+420 RHS 30-Jan-20 11:00 AM
Checking of reinforcement,shuttering and Pouring concrete(M-35) for 1st lift at abutment wall
7845 NMSCEW/P-IV/STR/2020/7788 7788 VOP(Loop-A) Km 3+131.586 LHS 30-Jan-20 2:30 PM
A1
7846 NMSCEW/P-IV/STR/2020/7789 7789 Checking of reinforcement,shuttering and Pouring concrete for final lift at wall A1 & A2 side MNB Km 181+700 RHS 30-Jan-20 2:45 PM
Checking reinforcement, shuttering & Pouring of Concreting Grade =(M-30) for Precast Box
Culvert at precast yard Camp-1
7847 NMSCEW/P-IV/STR/2020/7790 7790 Box culvert Km 175+500 LHS 30-Jan-20 10:15 AM
I) 2x2 (2 to 4m) segment no.-
451,452,453,454,455,456,457,458,459,460,461,462,463,464,465,466
7848 NMSCEW/P-IV/STR/2020/7791 7791 Checking erection & jointing of pre cast utility duct Utility duct Km 173+680 BHS 30-Jan-20 10:00 AM
7849 NMSCEW/P-IV/STR/2020/7792 7792 Checking erection & jointing of pre cast utility duct Utility duct Km 174+920 BHS 30-Jan-20 4:00 PM
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
7850 NMSCEW/P-IV/STR/2020/7793 7793 Girder Km 200+200 LHS 30-Jan-20 5:00 PM
241,242,243,244 at bed no -5, Girder Type-01
7851 NMSCEW/P-IV/STR/2020/7794 7794 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP-16 Viaduct Km 213+915 RHS 30-Jan-20 4:30 PM
7852 NMSCEW/P-IV/STR/2020/7795 7795 Checking of reinforcement,shuttering and Pouring concrete for raft at abutment RA2 Viaduct Km 213+915 RHS 30-Jan-20 11:30 AM
7853 NMSCEW/P-IV/STR/2020/7796 7796 Checking of reinforcement,shuttering and Pouring concrete for raft at RP7 Viaduct Km 213+915 RHS 30-Jan-20 2:30 PM
7854 NMSCEW/P-IV/STR/2020/7797 7797 Checking of reinforcement,shuttering and Pouring concrete for raft at RP8 Viaduct Km 213+915 RHS 30-Jan-20 3:30 PM
7855 NMSCEW/P-IV/STR/2020/7798 7798 Checking layout ,level, & laying concrete for PCC at RP-4 Viaduct Km 213+915 RHS 30-Jan-20 4:30 PM
7856 NMSCEW/P-IV/STR/2020/7799 7799 Checking of layout ,level for I-girder launching between at RP-07 to RP-04 Viaduct Km 169+800 RHS 30-Jan-20 5:00 PM
Checking layout ,level,Shuttering,reinforcement & pouring concrete for raft at RP-2
7857 NMSCEW/P-IV/STR/2020/7800 7800 MJB Km 205+610 RHS 31-Jan-20 2:00 PM
foundation
7858 NMSCEW/P-IV/STR/2020/7801 7801 Checking layout ,level,Shuttering,reinforcement & pouring concrete for service road raft Box culvert Km 206+843 LHS 31-Jan-20 4:00 PM
7859 NMSCEW/P-IV/STR/2020/7802 7802 Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at retaining wall W1 MNB Km 199+360 RHS 31-Jan-20 10:00 AM
Checking of reinforcement,shuttering and Pouring concrete for 4th lift at median wall W1 &
7860 NMSCEW/P-IV/STR/2020/7803 7803 PUP Km 208+930 31-Jan-20 10:30 AM
W2
7861 NMSCEW/P-IV/STR/2020/7804 7804 Checking of Shuttering,reinforcement, pouring concrete for padestal at RP-7 Viaduct Km 196+560 RHS 31-Jan-20 10:45 AM
7862 NMSCEW/P-IV/STR/2020/7805 7805 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP-16 Viaduct Km 213+915 RHS 31-Jan-20 12:30 PM
7863 NMSCEW/P-IV/STR/2020/7806 7806 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at LP-16 Viaduct Km 213+915 LHS 31-Jan-20 9:33 AM IPC-14
7864 NMSCEW/P-IV/STR/2020/7807 7807 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-15 Viaduct Km 213+915 RHS 31-Jan-20 2:30 PM IPC-14
7865 NMSCEW/P-IV/STR/2020/7808 7808 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP-18 Viaduct Km 213+915 LHS 31-Jan-20 4:30 PM IPC-14
7866 NMSCEW/P-IV/STR/2020/7809 7809 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-18 Viaduct Km 213+915 RHS 31-Jan-20 5:30 PM
Checking of reinforcement,shuttering and Pouring concrete(M-35) for 1st lift at abutment wall
7867 NMSCEW/P-IV/STR/2020/7810 7810 VOP(Loop-A) Km 3+131.586 RHS 31-Jan-20 9:00 AM
A1
Checking of reinforcement,shuttering and Pouring concrete(M-35) for 1st lift at abutment wall
7868 NMSCEW/P-IV/STR/2020/7811 7811 VOP(Loop-A) Km 3+131.586 LHS 31-Jan-20 9:35 AM
A1
Checking of reinforcement,shuttering and Pouring concrete(M-35) for 1st lift at abutment wall
7869 NMSCEW/P-IV/STR/2020/7812 7812 VUP Km 182+420 LHS 31-Jan-20 11:00 AM
A2
7870 NMSCEW/P-IV/STR/2020/7813 7813 Checking of reinforcement,shuttering and Pouring concrete(M-30) for top haunch and top slab VUP Km 187+113 BHS 31-Jan-20 8:00 AM
7871 NMSCEW/P-IV/STR/2020/7814 7814 Checking of reinforcement,shuttering and Pouring concrete(M-30) for top haunch and top slab MNB Km 181+700 RHS 31-Jan-20 8:15 AM
Checking of excavated bed layout,level, & laying concrete PCC(M-10) for retaining wall A2
7872 NMSCEW/P-IV/STR/2020/7815 7815 MNB Km 181+700 LHS 31-Jan-20 2:00 PM
side
Checking of Shuttering,reinforcement & pouring concrete for LP-4 to LP-7 deck slab module
7873 NMSCEW/P-IV/STR/2020/7816 7816 Viaduct Km 202+190 LHS 31-Jan-20 8:30 AM
type-2
7874 NMSCEW/P-IV/STR/2020/7817 7817 Checking of layout,level for bearing fixing at LP-10 Viaduct Km 202+190 LHS 31-Jan-20 4:30 PM
Checking of layout,level, excavation & laying concrete PCC(M-15) for abutment footing A2
7875 NMSCEW/P-IV/STR/2020/7818 7818 MNB Km 186+550 RHS 31-Jan-20 4:00 PM
side
Checking of side shuttering and pouring(Grade of concrete M-50) of girder
NMSCEW/P-IV/STR/2020/7822 Girder Km 200+200 LHS 2/1/2020 9:30 AM
no-241,242,243,244 at bed no -5, Girder Type-01
Checking of reinforcement, shuttering & pouring concrete for pier shaft
NMSCEW/P-IV/STR/2020/7823 Viaduct Km 195+900 LHS 2/1/2020 3:30 PM IPC-14
final lift at LP-5
Checking of Shuttering,reinforcement & pouring concrete for cross girder
NMSCEW/P-IV/STR/2020/7824 Viaduct Km 202+190 RHS 2/1/2020 4:30 PM
between RP-8 to RP-9
NMSCEW/P-IV/STR/2020/7825 Checking of layout,level for bearing fixing at RP-8 Viaduct Km 202+190 RHS 2/1/2020 2:00 PM
Checking of layout,level, reinforcement, shuttering & pouring concrete for
NMSCEW/P-IV/STR/2020/7826 PUP Km 212+080 RHS 2/1/2020 10:00 AM
retaining wall W1
Checking of Shuttering,reinforcement and Pouring concrete for RE WALL
PANEL precast Type A- 426 nos,
NMSCEW/P-IV/STR/2020/7827 Type B- 11 nos, Type Sta-18 nos, Type Stb-20 nos, Type Stc-20 nos, Type RE Wall Panel Km 200+200 LHS 2/2/2020 4:00 PM
Std-19 nos, Type Lta-25 nos, Type Ltc- 20 nos, Type Ltd-10 nos at RE
panel precast yard camp 2
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/7829 Girder Km 200+200 LHS 2/2/2020 11:00 AM
209,210,211,212 at bed no -01, Girder Type-02 at casting yard camp -2
Checking of reinforcement Girder no -209,210,211,212 at bed no -01,
NMSCEW/P-IV/STR/2020/7830 Girder Km 200+200 LHS 2/2/2020 11:30 AM
Girder Type-02 at casting yard camp -2
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at
NMSCEW/P-IV/STR/2020/7835 Box culvert Km 206+843 RHS 2/4/2020 12:00 PM
MCW wall W1
Checking of side shuttering and pouring(Grade of concrete M-50) of girder
NMSCEW/P-IV/STR/2020/7836 Girder Km 200+200 LHS 2/4/2020 8:30 AM
no-209,210,211,212 at bed no -2, Girder Type-02
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/7837 Girder Km 200+200 LHS 2/4/2020 9:00 AM
245,246,247,248 at bed no -03, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -245,246,247,248 at bed no -03,
NMSCEW/P-IV/STR/2020/7838 Girder Km 200+200 LHS 2/4/2020 9:30 AM
Girder Type-01 at casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/7839 Girder Km 200+200 LHS 2/4/2020 11:00 AM
249,250,251,252 at bed no -07, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -249,250,251,252 at bed no -07,
NMSCEW/P-IV/STR/2020/7840 Girder Km 200+200 LHS 2/4/2020 11:30 AM
Girder Type-01 at casting yard camp -2
Checking of reinforcement, shuttering & pouring concrete for pier shaft
NMSCEW/P-IV/STR/2020/7841 Viaduct Km 213+915 LHS 2/4/2020 3:30 PM
final lift at LP-16
Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st
NMSCEW/P-IV/STR/2020/7842 Viaduct Km 213+915 RHS 2/4/2020 4:30 PM
lift at RP-13
NMSCEW/P-IV/STR/2020/7843 Checking layout ,level, & laying concrete for PCC at RP-4 Viaduct Km 213+915 RHS 2/4/2020 4:45 PM
Checking of Shuttering,reinforcement, pouring concrete for pier cap at RP-
NMSCEW/P-IV/STR/2020/7844 Viaduct Km 200+920 RHS 2/4/2020 4:00 PM
2
for Precast Box Culvert at precast yard Camp-2
NMSCEW/P-IV/STR/2020/7846 Box culvert Km 200+200 LHS 2/4/2020 10:00 AM
I) 2x2 (0 to 2m) segment no.-11,12,13,14,15,16,17,18,19,20
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at
NMSCEW/P-IV/STR/2020/7847 MJB Km 205+610 LHS 2/4/2020 10:15 AM
retaining wall LA2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder
NMSCEW/P-IV/STR/2020/7850 Girder Km 200+200 LHS 2/4/2020 5:00 PM
no-245,246,247,248 at bed no -03, Girder Type-01
Checking of Shuttering,reinforcement, pouring concrete for padestal at RP-
NMSCEW/P-IV/STR/2020/7851 Viaduct Km 196+560 RHS 2/4/2020 3:30 PM
6
NMSCEW/P-IV/STR/2020/7852 Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-6 Viaduct Km 195+900 LHS 2/4/2020 3:45 PM
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/7853 Girder Km 200+200 LHS 2/4/2020 4:45 PM
257,258,259,260 at bed no -08, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -257,258,259,260 at bed no -08,
NMSCEW/P-IV/STR/2020/7854 Girder Km 200+200 LHS 2/4/2020 5:15 PM
Girder Type-01 at casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/7855 Girder Km 200+200 LHS 2/4/2020 11:00 AM
253,254,255,256 at bed no -06, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -253,254,255,256 at bed no -06,
NMSCEW/P-IV/STR/2020/7856 Girder Km 200+200 LHS 2/4/2020 11:30 AM
Girder Type-01 at casting yard camp -2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder
NMSCEW/P-IV/STR/2020/7857 Girder Km 200+200 LHS 2/4/2020 3:15 PM
no-249,250,251,252 at bed no -07, Girder Type-01
Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st
NMSCEW/P-IV/STR/2020/7864 Viaduct Km 213+915 RHS 2/4/2020 9:32 AM IPC-14
lift at RP-16
Checking of reinforcement, shuttering & pouring concrete for pier shaft
NMSCEW/P-IV/STR/2020/7865 Viaduct Km 213+915 RHS 2/4/2020 12:30 PM IPC-14
final lift at RP-18
Checking of Shuttering,reinforcement & pouring concrete for cross girder
NMSCEW/P-IV/STR/2020/7866 Viaduct Km 202+190 RHS 2/4/2020 2:20 PM
RP-8 to RP-9
Checking of Shuttering,reinforcement & pouring concrete for cross girder
NMSCEW/P-IV/STR/2020/7867 Viaduct Km 202+190 RHS 2/4/2020 3:00 PM
RP-9 to RP-10
Checking of excavation level,layout & laying concrete PCC(M-15) for
NMSCEW/P-IV/STR/2020/7868 Pipe culvert Km 196+760 RHS 2/5/2020 10:00 AM
median drain outlet
NMSCEW/P-IV/STR/2020/7869 Checking layout ,level,Shuttering,reinforcement & pouring concrete for raft MNB Km 193+135 LHS 2/5/2020 5:00 PM
Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st
NMSCEW/P-IV/STR/2020/7870 MJB Km 205+610 LHS 2/5/2020 12:00 PM
lift at LP-2
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at
NMSCEW/P-IV/STR/2020/7871 PUP Km 206+985 2/5/2020 4:00 PM
retaining wall W1 & W2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder
NMSCEW/P-IV/STR/2020/7873 Girder Km 200+200 LHS 2/5/2020 2:30 PM
no-253,254,255,256 at bed no -06, Girder Type-01
Checking of side shuttering and pouring(Grade of concrete M-50) of girder
NMSCEW/P-IV/STR/2020/7874 Girder Km 200+200 LHS 2/5/2020 3:30 PM
no-245,246,247,248 at bed no -03, Girder Type-01
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/7875 Girder Km 200+200 LHS 2/5/2020 4:05 PM
213,214,215,216 at bed no -01, Girder Type-02 at casting yard camp -2
Checking of reinforcement Girder no -213,214,215,216 at bed no -01,
NMSCEW/P-IV/STR/2020/7876 Girder Km 200+200 LHS 2/5/2020 4:30 PM
Girder Type-02 at casting yard camp -2
NMSCEW/P-IV/STR/2020/7877 Checking of Shuttering,reinforcement, pouring concrete for RAFT at RP-7 Viaduct Km 213+915 LHS 2/5/2020 3:00 PM IPC-14
NMSCEW/P-IV/STR/2020/7878 Checking layout ,level, & laying concrete for PCC at RA-1 Viaduct Km 213+915 RHS 2/5/2020 4:45 PM
NMSCEW/P-IV/STR/2020/7888 Checking of layout,level & laying concrete PCC at 2x2 utility duct Utility duct Km 211+800 BHS 2/6/2020 8:00 AM
Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st
NMSCEW/P-IV/STR/2020/7893 Viaduct Km 213+915 RHS 2/6/2020 4:30 PM
lift at RP-13
NMSCEW/P-IV/STR/2020/7894 Checking layout ,level, & laying concrete for PCC at RP-4 Viaduct Km 213+915 RHS 2/6/2020 4:45 PM
NMSCEW/P-IV/STR/2020/7895 Checking layout ,level, & laying concrete for PCC at RA-1 Viaduct Km 213+915 RHS 2/6/2020 3:30 PM IPC-14
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/7896 Girder Km 200+200 LHS 2/6/2020 4:16 PM
261,262,263,264 at bed no -04, Girder Type-01 at casting yard camp -2
Checking of bottom level, top level,layout and laying concrete for PCC RE
NMSCEW/P-IV/STR/2020/7905 wall panel leveling pad. RE wall panel Km 210+135 LHS 2/7/2020 11:00 AM
NMSCEW/P-IV/STR/2020/7906 Checking of layout,level, excavation & laying concrete for PCC(M-15) Box culvert Km 214+805 BHS 2/7/2020 8:30 AM
Checking of side shuttering and pouring(Grade of concrete M-50) of girder
NMSCEW/P-IV/STR/2020/7907 Girder Km 200+200 LHS 2/7/2020 3:30 PM
no-213,214,215,216 at bed no -01, Girder Type-02
Checking of side shuttering and pouring(Grade of concrete M-50) of girder
NMSCEW/P-IV/STR/2020/7908 Girder Km 200+200 LHS 2/7/2020 6:00 PM
no-261,262,263,264 at bed no -04, Girder Type-01
Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-
NMSCEW/P-IV/STR/2020/7909 Viaduct Km 213+915 LHS 2/7/2020 2:30 PM IPC-14
17
Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st
NMSCEW/P-IV/STR/2020/7910 Viaduct Km 195+900 RHS 2/7/2020 3:00 PM IPC-14
lift at RP-6
Checking layout ,level,Shuttering,reinforcement & pouring concrete for raft
NMSCEW/P-IV/STR/2020/7918 PUP Km 212+080 RHS 2/7/2020 12:00 PM
at retaining wall W2
Checking of reinforcement, shuttering & pouring concrete for abutment
NMSCEW/P-IV/STR/2020/7919 MJB Km 205+610 RHS 2/8/2020 4:00 PM
2nd lift RA2 wall
Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st
NMSCEW/P-IV/STR/2020/7920 MJB Km 205+610 RHS 2/8/2020 8:00 AM
lift at RP-2
Checking of reinforcement, shuttering & pouring concrete for 2nd lift at
NMSCEW/P-IV/STR/2020/7921 MJB Km 205+610 LHS 2/8/2020 12:00 PM
retaining wall LA2
Checking layout ,level,Shuttering,reinforcement & pouring concrete for raft
NMSCEW/P-IV/STR/2020/7922 Box culvert Km 209+470 BHS 2/8/2020 8:15 AM
at 3x3 box culvert
Checking layout ,level,Shuttering,reinforcement & pouring concrete for raft
NMSCEW/P-IV/STR/2020/7923 Box culvert Km 210+285 BHS 2/8/2020 9:00 AM
at 3x3 box culvert
Checking of Shuttering,reinforcement, pouring concrete for abutment cap
NMSCEW/P-IV/STR/2020/7929 Viaduct Km 196+560 LHS 2/8/2020 3:30 PM
at LA-2
Checking of layout,Shuttering,reinforcement, pouring concrete for padestal
NMSCEW/P-IV/STR/2020/7930 Viaduct Km 196+560 RHS 2/8/2020 4:10 PM
at RP-4
Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st
NMSCEW/P-IV/STR/2020/7931 Viaduct Km 213+915 RHS 2/8/2020 10:00 AM
lift at RP-13
NMSCEW/P-IV/STR/2020/7932 Checking layout ,level, & laying concrete for PCC at RP-4 Viaduct Km 213+915 RHS 2/8/2020 4:37 PM
NMSCEW/P-IV/STR/2020/7936 Checking of layout,level for bearing fixing at RP-10 Viaduct Km 202+190 RHS 2/8/2020 3:00 PM
NMSCEW/P-IV/STR/2020/7941 Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-6 Viaduct Km 195+900 LHS 2/8/2020 3:35 PM IPC-14
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/7942 Girder Km 200+200 LHS 2/9/2020 11:00 AM
265,266,267,268 at bed no -05, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -265,266,267,268 at bed no -05,
NMSCEW/P-IV/STR/2020/7943 Girder Km 200+200 LHS 2/9/2020 11:30 AM
Girder Type-01 at casting yard camp -2
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at
NMSCEW/P-IV/STR/2020/7949 PUP Km 212+080 2/9/2020 4:15 PM
median wall W1 & W2
Checking of layout,level, reinforcement,shuttering and Pouring concrete for
NMSCEW/P-IV/STR/2020/7950 PUP Km 212+080 RHS 2/9/2020 8:15 AM
raft at retaining wall W2
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at
NMSCEW/P-IV/STR/2020/7951 Box culvert Km 206+843 RHS 2/10/2020 4:00 PM
MCW wall W2
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at
NMSCEW/P-IV/STR/2020/7952 MJB Km 205+610 RHS 2/10/2020 4:30 PM
abutment wall RA2
Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st
NMSCEW/P-IV/STR/2020/7953 MJB Km 205+610 RHS 2/10/2020 8:00 AM
lift at RP2
Checking of reinforcement, shuttering & pouring concrete for 2nd lift at
NMSCEW/P-IV/STR/2020/7954 MJB Km 205+610 LHS 2/10/2020 12:00 PM
retaining wall LA2
Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st
NMSCEW/P-IV/STR/2020/7959 Viaduct Km 195+900 RHS 2/10/2020 3:00 PM
lift at RP5
Checking of side shuttering and pouring(Grade of concrete M-50) of girder
NMSCEW/P-IV/STR/2020/7960 Girder Km 200+200 LHS 2/10/2020 6:00 PM
no-265,266,267,268 at bed no -05, Girder Type-01
NMSCEW/P-IV/STR/2020/7961 Checking of Shuttering,reinforcement, pouring concrete for padestal at LA2 Viaduct Km 202+190 LHS 2/10/2020 3:20 PM
NMSCEW/P-IV/STR/2020/7964 Checking layout ,level, & laying concrete for PCC at RP-4 Viaduct Km 213+915 RHS 2/10/2020 4:35 PM IPC-14
NMSCEW/P-IV/STR/2020/8010 Checking of Shuttering,reinforcement, pouring concrete for padestal at LA2 Viaduct Km 200+920 LHS 2/12/2020 4:05 PM
for Precast Box Culvert at precast yard Camp-2
NMSCEW/P-IV/STR/2020/8013 I) 2x2 (0 to 2m) segment no.- Box culvert Km 200+200 LHS 2/13/2020 10:30 AM
21,22,23,24,25,26,27,28,29,30,31,32,33,44,35
NMSCEW/P-IV/STR/2020/8064 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP1 Viaduct Km 213+915 RHS 2/16/2020 12:30 PM
NMSCEW/P-IV/STR/2020/8065 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP16 Viaduct Km 213+915 LHS 2/16/2020 2:30 PM
NMSCEW/P-IV/STR/2020/8066 Checking of Shuttering,reinforcement, pouring concrete for padestal at LA-2 Viaduct Km 202+190 LHS 2/16/2020 10:20 AM
NMSCEW/P-IV/STR/2020/8067 Checking of Shuttering,reinforcement, pouring concrete for padestal at RP-11 Viaduct Km 202+190 RHS 2/16/2020 11:30 AM
NMSCEW/P-IV/STR/2020/8068 Checking of layout,level for bearing fixing at LP-09 Viaduct Km 202+190 LHS 2/16/2020 12:00 PM
NMSCEW/P-IV/STR/2020/8069 Checking of Shuttering,reinforcement, pouring concrete for padestal at LP-4 Viaduct Km 200+920 LHS 2/16/2020 10:00 AM
NMSCEW/P-IV/STR/2020/8074 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP7 Viaduct Km 195+900 RHS 2/17/2020 3:30 PM
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
NMSCEW/P-IV/STR/2020/8075
221,222,223,224 at bed no -1, Girder Type-02
Girder Km 200+200 LHS 2/17/2020 5:30 PM
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8076
285,286,287,288 at bed no -04, Girder Type-01 at casting yard camp -2
Girder Km 200+200 LHS 2/17/2020 3:00 PM
Checking of reinforcement Girder no -285,286,287,288 at bed no -04, Girder Type-01
NMSCEW/P-IV/STR/2020/8077
at casting yard camp -2
Girder Km 200+200 LHS 2/17/2020 3:45 PM
NMSCEW/P-IV/STR/2020/8078 Checking of reinforcement,shuttering and Pouring concrete for raft at RP9 Viaduct Km 213+915 RHS 2/17/2020 4:00 PM IPC-14
NMSCEW/P-IV/STR/2020/8079 Checking of Shuttering,reinforcement & pouring concrete for pier starter at RP-11 Viaduct Km 213+915 RHS 2/17/2020 3:40 PM
NMSCEW/P-IV/STR/2020/8080 Checking of Shuttering,reinforcement & pouring concrete for pier starter at LP-12 Viaduct Km 213+915 LHS 2/17/2020 2:30 PM
NMSCEW/P-IV/STR/2020/8081 Checking of Shuttering,reinforcement, pouring concrete for padestal at LP-3 Viaduct Km 200+920 LHS 2/17/2020 11:00 AM
NMSCEW/P-IV/STR/2020/8089 Checking of reinforcement,shuttering and Pouring concrete for raft at LP3 Viaduct Km 213+915 LHS 2/17/2020 9:30 AM IPC-14
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at U-type wing
NMSCEW/P-IV/STR/2020/8090
wall W1 & W2
Box culvert Km 204+920 RHS 2/18/2020 3:00 PM
NMSCEW/P-IV/STR/2020/8091 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall W1 & W3 MNB Km 193+135 LHS 2/18/2020 4:00 PM
NMSCEW/P-IV/STR/2020/8092 Checking layout ,level,Shuttering,reinforcement & pouring concrete for service road raft Box culvert Km 206+843 RHS 2/18/2020 8:00 AM
NMSCEW/P-IV/STR/2020/8093 Checking layout ,level, & laying concrete for MCW PCC VUP Km 207+874 2/18/2020 12:00 PM
Checking layout ,level,Shuttering,reinforcement & pouring concrete for final lift at wall
NMSCEW/P-IV/STR/2020/8094
W1 & W2 with top slab
MNB Km 208+455 RHS 2/18/2020 4:30 PM
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8095
289,290,291,292 at bed no -05, Girder Type-01 at casting yard camp -2
Girder Km 200+200 LHS 2/18/2020 5:00 PM
Checking of reinforcement Girder no -289,290,291,292 at bed no -05, Girder Type-01
NMSCEW/P-IV/STR/2020/8096
at casting yard camp -2
Girder Km 200+200 LHS 2/18/2020 5:30 PM
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
NMSCEW/P-IV/STR/2020/8097
285,286,287,288 at bed no -04, Girder Type-01
Girder Km 200+200 LHS 2/18/2020 5:45 PM
NMSCEW/P-IV/STR/2020/8098 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP1 Viaduct Km 213+915 RHS 2/18/2020 4:15 PM
NMSCEW/P-IV/STR/2020/8099 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP16 Viaduct Km 213+915 LHS 2/18/2020 3:30 PM IPC-14
NMSCEW/P-IV/STR/2020/8100 Checking of Shuttering,reinforcement, pouring concrete for padestal at LP-18 Viaduct Km 213+915 LHS 2/18/2020 4:40 PM
Checking of reinforcement, shuttering & pouring concrete for abutment shaft 1st lift at
NMSCEW/P-IV/STR/2020/8101
RA2
Viaduct Km 213+915 RHS 2/18/2020 4:10 PM
NMSCEW/P-IV/STR/2020/8102 Checking of layout, Shuttering,reinforcement, pouring concrete for padestal at RP3 Viaduct Km 196+560 RHS 2/18/2020 3:44 PM
NMSCEW/P-IV/STR/2020/8103 Checking of lavel and layout for bearing fixing at RP-9 Viaduct Km 202+190 RHS 2/18/2020 4:00 PM
NMSCEW/P-IV/STR/2020/8112 Checking of layout, Shuttering,reinforcement, pouring concrete for padestal at LP5 Viaduct Km 200+920 LHS 2/18/2020 5:00 PM
NMSCEW/P-IV/STR/2020/8113 Checking of layout, Shuttering,reinforcement, pouring concrete for padestal at LP3 Viaduct Km 200+920 LHS 2/18/2020 11:00 AM
NMSCEW/P-IV/STR/2020/8114 Checking of layout, Shuttering,reinforcement, pouring concrete for padestal at LP4 Viaduct Km 200+920 LHS 2/18/2020 10:00 AM
Checking of reinforcement,shuttering and Pouring concrete for 4th lift at retaining wall
NMSCEW/P-IV/STR/2020/8115
W1 & W2
PUP Km 206+985 LHS 2/19/2020 10:00 AM
Checking of reinforcement, shuttering & pouring concrete for abutment shaft 3rd lift at
NMSCEW/P-IV/STR/2020/8116
RA2
MJB Km 205+610 RHS 2/19/2020 4:00 PM
NMSCEW/P-IV/STR/2020/8124 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP-14 Viaduct Km 213+915 RHS 2/19/2020 4:00 PM
NMSCEW/P-IV/STR/2020/8125 Checking of Shuttering,reinforcement & pouring concrete for pier starter at RP-11 Viaduct Km 213+915 RHS 2/19/2020 4:30 PM
NMSCEW/P-IV/STR/2020/8126 Checking of Shuttering,reinforcement & pouring concrete for pier starter at RP-12 Viaduct Km 213+915 RHS 2/19/2020 4:16 PM
NMSCEW/P-IV/STR/2020/8127 Checking of layout, Shuttering,reinforcement, pouring concrete for PEIR CAP AT LP-18 Km 193+135 LHS 2/19/2020 IPC-14 SPOT
9:00 AM
NMSCEW/P-IV/STR/2020/8128 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall W2 MNB Km 193+135 LHS 2/20/2020 4:00 PM
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at service road
NMSCEW/P-IV/STR/2020/8129
wall W1
Box culvert Km 206+843 RHS 2/20/2020 12:00 PM
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at median wall
NMSCEW/P-IV/STR/2020/8130
W1 & W2
PUP Km 212+080 2/20/2020 8:00 AM
Checking of reinforcement,shuttering and Pouring concrete for final lift at wall W1 & W2
NMSCEW/P-IV/STR/2020/8131
with top slab (MCW)
Box culvert Km 206+843 RHS 2/20/2020 8:15 AM
NMSCEW/P-IV/STR/2020/8132 Checking layout ,level, & laying concrete PCC for retaining wall W1 PUP Km 206+985 RHS 2/20/2020 10:00 AM
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8142
293,294,295,296 at bed no -07, Girder Type-01 at casting yard camp -2
Girder Km 200+200 LHS 2/20/2020 8:00 AM
Checking of reinforcement Girder no -293,294,295,296 at bed no -07, Girder Type-01
NMSCEW/P-IV/STR/2020/8143
at casting yard camp -2
Girder Km 200+200 LHS 2/20/2020 8:30 AM
NMSCEW/P-IV/STR/2020/8145 Checking of Shuttering,reinforcement, pouring concrete for padestal at RA-1 Viaduct Km 202+190 RHS 2/20/2020 2:20 PM
NMSCEW/P-IV/STR/2020/8146 Checking of Shuttering,reinforcement, pouring concrete for padestal at RP-1 Viaduct Km 202+190 RHS 2/20/2020 3:30 PM
NMSCEW/P-IV/STR/2020/8147 Checking of Shuttering,reinforcement, pouring concrete for raft at RA-1 Viaduct Km 213+915 RHS 2/20/2020 10:05 AM IPC-14
NMSCEW/P-IV/STR/2020/8148 Checking layout ,level, & laying concrete for PCC at LP-4 Viaduct Km 213+915 LHS 2/20/2020 3:33 PM
Checking of reinforcement, shuttering & pouring concrete for abutment shaft 1st lift at
NMSCEW/P-IV/STR/2020/8149
RA-2
Viaduct Km 213+915 RHS 2/20/2020 2:14 PM
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift U-type wing wall
NMSCEW/P-IV/STR/2020/8150
W1 & W2
Box culvert Km 204+920 RHS 2/21/2020 3:00 PM
NMSCEW/P-IV/STR/2020/8151 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall W2 MNB Km 193+135 RHS 2/21/2020 3:30 PM
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8160
225,226,227,228 at bed no -02, Girder Type-02 at casting yard camp -2
Girder Km 200+200 LHS 2/21/2020 5:00 PM
NMSCEW/P-IV/STR/2020/8166 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP7 Viaduct Km 195+900 RHS 2/21/2020 10:10 AM IPC-14
NMSCEW/P-IV/STR/2020/8167 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP14 Viaduct Km 213+915 RHS 2/21/2020 4:00 PM IPC-14
Checking of reinforcement, shuttering & pouring concrete for abutment shaft 1st lift at
NMSCEW/P-IV/STR/2020/8168
RA-2
Viaduct Km 213+915 RHS 2/21/2020 10:30 AM
NMSCEW/P-IV/STR/2020/8169 Checking of Shuttering,reinforcement, pouring concrete for pier cap at RP-15 Viaduct Km 213+915 RHS 2/21/2020 4:30 PM IPC-14
Checking of reinforcement, shuttering & pouring concrete for abutment shaft 1st lift at
NMSCEW/P-IV/STR/2020/8170
RP-12
Viaduct Km 213+915 RHS 2/21/2020 4:45 PM
NMSCEW/P-IV/STR/2020/8172 Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-4 Viaduct Km 195+900 LHS 2/22/2020 3:30 PM IPC-14
NMSCEW/P-IV/STR/2020/8173 Checking of Shuttering,reinforcement, pouring concrete for padestal at LP-5 Viaduct Km 200+920 LHS 2/22/2020 3:00 PM
NMSCEW/P-IV/STR/2020/8174 Checking of Shuttering,reinforcement, pouring concrete for padestal at LP-2 Viaduct Km 200+920 LHS 2/22/2020 4:00 PM
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8175
297,298,299,300 at bed no -08, Girder Type-01 at casting yard camp -2
Girder Km 200+200 LHS 2/22/2020 8:00 AM
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8177
301,302,303,304 at bed no -06, Girder Type-01 at casting yard camp -2
Girder Km 200+200 LHS 2/22/2020 5:00 PM
Checking of reinforcement Girder no -301,302,303,304 at bed no -06, Girder Type-01
NMSCEW/P-IV/STR/2020/8178
at casting yard camp -2
Girder Km 200+200 LHS 2/22/2020 5:30 PM
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
NMSCEW/P-IV/STR/2020/8179
225,226,227,228 at bed no -02, Girder Type-01
Girder Km 200+200 LHS 2/22/2020 2:30 PM
NMSCEW/P-IV/STR/2020/8180 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP14 Viaduct Km 213+915 LHS 2/22/2020 4:05 PM
NMSCEW/P-IV/STR/2020/8181 Checking of Shuttering,reinforcement & pouring concrete for pier starter at RP-11 Viaduct Km 213+915 RHS 2/22/2020 4:30 PM
NMSCEW/P-IV/STR/2020/8182 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1stl lift at RP2 Viaduct Km 213+915 RHS 2/22/2020 4:45 PM
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
NMSCEW/P-IV/STR/2020/8183
297,298,299,300 at bed no -08, Girder Type-01
Girder Km 200+200 LHS 2/22/2020 6:00 PM
NMSCEW/P-IV/STR/2020/8192 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1stl lift at RP12 Viaduct Km 213+915 RHS 2/22/2020 4:16 PM
NMSCEW/P-IV/STR/2020/8193 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1stl lift at LP11 Viaduct Km 213+915 LHS 2/22/2020 4:45 PM
NMSCEW/P-IV/STR/2020/8194 Checking layout ,level, & laying concrete for PCC at LP-9 Viaduct Km 213+915 LHS 2/22/2020 11:10 AM
NMSCEW/P-IV/STR/2020/8196 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at wall W3 MNB Km 193+135 LHS 2/23/2020 5:00 PM
NMSCEW/P-IV/STR/2020/8197 Checking of reinforcement,shuttering and Pouring concrete for 1st lift at wall W1 MNB Km 193+135 RHS 2/23/2020 2:00 PM
Checking of reinforcement, shuttering & pouring concrete(M-45) for pier shaft 2nd lift
NMSCEW/P-IV/STR/2020/8198
at LP-1
MJB Km 205+610 LHS 2/23/2020 10:00 AM
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at service road
NMSCEW/P-IV/STR/2020/8199
wall W1
Box culvert Km 206+843 RHS 2/23/2020 8:00 AM
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at median wall
NMSCEW/P-IV/STR/2020/8200
W1 & W2
PUP Km 212+080 2/23/2020 9:00 AM
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8202
305,306,307,308 at bed no -03, Girder Type-01 at casting yard camp -2
Girder Km 200+200 LHS 2/23/2020 11:00 AM
NMSCEW/P-IV/STR/2020/8204 Checking layout ,level, & laying concrete for PCC at LP-4 Viaduct Km 213+915 LHS 2/23/2020 4:00 PM IPC-14
NMSCEW/P-IV/STR/2020/8205 Checking layout ,level, & laying concrete for PCC at LP-9 Viaduct Km 213+915 LHS 2/23/2020 4:30 PM
NMSCEW/P-IV/STR/2020/8213 Checking of Shuttering,reinforcement, pouring concrete for padestal at RA-1 Viaduct Km 202+190 RHS 2/23/2020 11:20 AM
NMSCEW/P-IV/STR/2020/8214 Checking of Shuttering,reinforcement, pouring concrete for padestal at RP-1 Viaduct Km 202+190 RHS 2/23/2020 12:30 PM
NMSCEW/P-IV/STR/2020/8215 Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at wall W1 MNB Km 193+135 LHS 2/24/2020 5:00 PM
NMSCEW/P-IV/STR/2020/8217 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at LP14 Viaduct Km 213+915 LHS 2/24/2020 4:00 PM
NMSCEW/P-IV/STR/2020/8218 Checking of Shuttering,reinforcement, pouring concrete for pier cap at RP-16 Viaduct Km 213+915 RHS 2/24/2020 3:30 PM IPC-14
NMSCEW/P-IV/STR/2020/8219 Checking of Shuttering,reinforcement, pouring concrete for raft foundation at RP-4 Viaduct Km 213+915 RHS 2/24/2020 4:30 PM IPC-14
NMSCEW/P-IV/STR/2020/8220 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP13 Viaduct Km 213+915 RHS 2/24/2020 4:45 PM
NMSCEW/P-IV/STR/2020/8221 Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st lift at RP2 Viaduct Km 213+915 RHS 2/24/2020 2:30 PM
NMSCEW/P-IV/STR/2020/8222 Checking of reinforcement, shuttering & pouring concrete for pier shaft final lift at RP6 Viaduct Km 195+900 RHS 2/24/2020 3:30 PM
NMSCEW/P-IV/STR/2020/8223 Checking of Shuttering,reinforcement, pouring concrete for abutment cap at RA-1 Viaduct Km 196+560 RHS 2/24/2020 3:45 PM IPC-14
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
NMSCEW/P-IV/STR/2020/8224
305,306,307,308 at bed no -03, Girder Type-01
Girder Km 200+200 LHS 2/24/2020 5:30 PM
Checking of side shuttering and pouring(Grade of concrete M-50) of girder no-
NMSCEW/P-IV/STR/2020/8225
301,302,303,304 at bed no -06, Girder Type-01
Girder Km 200+200 LHS 2/24/2020 6:30 PM
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8226
229,230,231,232 at bed no -01, Girder Type-02 at casting yard camp -2
Girder Km 200+200 LHS 2/24/2020 5:00 PM
Checking of reinforcement Girder no -229,230,231,232 at bed no -01, Girder Type-02
NMSCEW/P-IV/STR/2020/8227
at casting yard camp -2
Girder Km 200+200 LHS 2/24/2020 5:40 PM
NMSCEW/P-IV/STR/2020/8229 Checking of completion for segment erection for 2×2 utility duct Utility duct Km 207+220 2/25/2020 9:40 AM
Checking of reinforcement, shuttering & pouring concrete for pier shaft
NMSCEW/P-IV/STR/2020/8230 MJB Km 205+610 LHS 2/25/2020 3:00 PM
5th and final lift at LA2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder
NMSCEW/P-IV/STR/2020/8234 Girder Km 200+200 LHS 2/25/2020 4:30 PM
no-229,230,231,232 at bed no -01, Girder Type-02
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8235 Girder Km 200+200 LHS 2/25/2020 5:00 PM
309,310,311,312 at bed no -04, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -309,310,311,312 at bed no -04,
NMSCEW/P-IV/STR/2020/8236 Girder Km 200+200 LHS 2/25/2020 5:30 PM
Girder Type-01 at casting yard camp -2
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at
NMSCEW/P-IV/STR/2020/8239 Box culvert Km 206+843 RHS 2/26/2020 2:00 PM
service road wall W2
Checking of reinforcement,shuttering and Pouring concrete for 4th lift at
NMSCEW/P-IV/STR/2020/8240 PUP Km 206+985 LHS 2/26/2020 8:00 AM
retaining wall W1 & W2
Checking layout ,level,Shuttering,reinforcement & pouring concrete for
NMSCEW/P-IV/STR/2020/8241 Box culvert Km 206+843 RHS 2/26/2020 4:00 PM
final at wall W1 & W2 lift with MCW slab
NMSCEW/P-IV/STR/2020/8242 Checking layout ,level,Shuttering,reinforcement & pouring concrete for raft VUP Km 215+609 BHS 2/26/2020 9:00 AM
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at
NMSCEW/P-IV/STR/2020/8243 MNB Km 193+135 RHS 2/26/2020 4:00 PM
wall W3
Checking of Shuttering,reinforcement & pouring concrete for LP-7 to LP-10
NMSCEW/P-IV/STR/2020/8244 Viaduct Km 202+190 LHS 2/26/2020 4:30 PM
deck slab module type-2
Checking of Shuttering,reinforcement, pouring concrete for abutment cap
NMSCEW/P-IV/STR/2020/8245 Viaduct Km 196+560 LHS 2/26/2020 2:30 PM
at LA-1
Checking of reinforcement, shuttering & pouring concrete for pier shaft
NMSCEW/P-IV/STR/2020/8258 Viaduct Km 213+915 LHS 2/26/2020 4:00 PM IPC-14
final lift at LP14
Checking of Shuttering,reinforcement & pouring concrete for pier starter at
NMSCEW/P-IV/STR/2020/8259 Viaduct Km 213+915 RHS 2/26/2020 4:30 PM
RP-11
Checking of Shuttering,reinforcement & pouring concrete for pier starter at
NMSCEW/P-IV/STR/2020/8260 Viaduct Km 213+915 RHS 2/26/2020 4:45 PM
RP-6
Checking of reinforcement, shuttering & pouring concrete for abutment
NMSCEW/P-IV/STR/2020/8261 Viaduct Km 213+915 LHS 2/26/2020 5:00 PM
shaft 2nd lift at LA2
Checking of reinforcement, shuttering & pouring concrete for pier shaft
NMSCEW/P-IV/STR/2020/8262 Viaduct Km 195+900 RHS 2/26/2020 3:00 PM IPC-14
final lift at RP6
NMSCEW/P-IV/STR/2020/8264 Checking of completion of segment erection for 2×2 utility duct Utility duct Km 211+800 2/27/2020 9:45 AM
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at
NMSCEW/P-IV/STR/2020/8265 MNB Km 193+135 BHS 2/27/2020 3:10 PM
wall W2
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at
NMSCEW/P-IV/STR/2020/8266 MNB Km 193+135 RHS 2/27/2020 3:35 PM
wall W2
NMSCEW/P-IV/STR/2020/8274 Checking layout ,level, & laying concrete for PCC at LP-9 Viaduct Km 213+915 LHS 2/27/2020 9:00 AM IPC-14
Checking of Shuttering,reinforcement, pouring concrete for pier cap at RP-
NMSCEW/P-IV/STR/2020/8275 Viaduct Km 213+915 RHS 2/27/2020 4:30 PM
18
Checking of reinforcement, shuttering & pouring concrete for pier shaft
NMSCEW/P-IV/STR/2020/8276 Viaduct Km 213+915 RHS 2/27/2020 3:30 PM
final lift at RP13
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8278 Girder Km 200+200 LHS 2/27/2020 5:00 PM
309,310,311,312 at bed no -04, Girder Type-01 at casting yard camp -2
NMSCEW/P-IV/STR/2020/8339 Checking of reinforcement,shuttering and Pouring concrete for raft at LP8 Viaduct Km 213+915 LHS 3/2/2020 2:30 PM
Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-
NMSCEW/P-IV/STR/2020/8340 Viaduct Km 213+915 LHS 3/2/2020 2:30 PM IPC-14
16
Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st
NMSCEW/P-IV/STR/2020/8341 Viaduct Km 213+915 RHS 3/2/2020 3:30 PM
lift at RP-06
Checking of side shuttering and pouring(Grade of concrete M-50) of girder
NMSCEW/P-IV/STR/2020/8343 Girder Km 200+200 LHS 3/2/2020 2:30 PM
no-321,322,323,324 at bed no -08, Girder Type-01
Checking Layout,Level, reinforcement,shuttering and Pouring concrete for
NMSCEW/P-IV/STR/2020/8344 PUP Km 206+985 RHS 3/2/2020 8:00 AM
raft at retaining wall W1
Checking of reinforcement, shuttering & pouring concrete for abutment
NMSCEW/P-IV/STR/2020/8347 MJB Km 205+610 RHS 3/3/2020 10:00 AM
shaft 4th lift at RA-2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder
NMSCEW/P-IV/STR/2020/8360 Girder Km 200+200 LHS 3/3/2020 2:30 PM
no-313,314,315,316 at bed no -05, Girder Type-01
Checking of side shuttering and pouring(Grade of concrete M-50) of girder
NMSCEW/P-IV/STR/2020/8361 Girder Km 200+200 LHS 3/3/2020 6:30 PM
no-317,318,319,320 at bed no -07, Girder Type-01
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8362 Girder Km 200+200 LHS 3/3/2020 5:00 PM
237,238,239,240 at bed no -01, Girder Type-02 at casting yard camp -2
Checking of reinforcement Girder no -237,238,239,240 at bed no -01,
NMSCEW/P-IV/STR/2020/8363 Girder Km 200+200 LHS 3/3/2020 5:30 PM
Girder Type-02 at casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8364 Girder Km 200+200 LHS 3/3/2020 6:00 PM
325,326,327,328 at bed no -06, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -325,326,327,328 at bed no -06,
NMSCEW/P-IV/STR/2020/8365 Girder Km 200+200 LHS 3/3/2020 6:30 PM
Girder Type-01 at casting yard camp -2
Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st
NMSCEW/P-IV/STR/2020/8366 Viaduct Km 213+915 LHS 3/3/2020 3:30 PM
lift at LP-13
Checking of Shuttering,reinforcement, pouring concrete for pier cap at RP-
NMSCEW/P-IV/STR/2020/8367 Viaduct Km 195+900 RHS 3/3/2020 10:30 AM
7
Checking of reinforcement, shuttering & pouring concrete for pier shaft
NMSCEW/P-IV/STR/2020/8368 Viaduct Km 195+900 RHS 3/3/2020 10:00 AM IPC-14
final lift at RP-5
Checking of Shuttering,reinforcement, pouring concrete for padestal at LP-
NMSCEW/P-IV/STR/2020/8371 Viaduct Km 196+560 LHS 3/4/2020 9:00 AM
5
Checking of Shuttering,reinforcement, pouring concrete for padestal at LA-
NMSCEW/P-IV/STR/2020/8372 Viaduct Km 196+560 LHS 3/4/2020 9:30 AM
2
NMSCEW/P-IV/STR/2020/8373 Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-5 Viaduct Km 195+900 LHS 3/4/2020 3:30 PM
Checking of side shuttering and pouring(Grade of concrete M-50) of girder
NMSCEW/P-IV/STR/2020/8374 Girder Km 200+200 LHS 3/4/2020 3:00 PM
no-237,238,239,240 at bed no -01, Girder Type-02
Checking of side shuttering and pouring(Grade of concrete M-50) of girder
NMSCEW/P-IV/STR/2020/8375 Girder Km 200+200 LHS 3/4/2020 6:30 PM
no-325,326,327,328 at bed no -06, Girder Type-01
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8376 Girder Km 200+200 LHS 3/4/2020 5:00 PM
329,330,331,332 at bed no -03, Girder Type-01 at casting yard camp -2
NMSCEW/P-IV/STR/2020/8445 Checking of reinforcement,shuttering and Pouring concrete for raft at LP-8 Viaduct Km 213+915 LHS 3/8/2020 10:30 AM
Checking of side shuttering and pouring(Grade of concrete M-50) of girder
NMSCEW/P-IV/STR/2020/8446 Girder Km 200+200 LHS 3/8/2020 9:30 AM
no-333,334,335,336 at bed no -04, Girder Type-01
Checking of reinforcement Girder no -241,242,243,244 at bed no -02,
NMSCEW/P-IV/STR/2020/8447 Girder Km 200+200 LHS 3/9/2020 11:00 AM
Girder Type-02 at casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8448 Girder Km 200+200 LHS 3/9/2020 11:30 AM
241,242,243,244 at bed no -02, Girder Type-02 at casting yard camp -2
Checking of Shuttering,reinforcement, pouring concrete for pier cap at RP-
NMSCEW/P-IV/STR/2020/8449 Viaduct Km 195+900 RHS 3/9/2020 3:30 PM
6
Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st
NMSCEW/P-IV/STR/2020/8450 Viaduct Km 213+915 LHS 3/9/2020 11:30 AM
lift at LP-12
Checking of reinforcement, shuttering & pouring concrete for pier shaft
NMSCEW/P-IV/STR/2020/8451 Viaduct Km 213+915 LHS 3/9/2020 2:00 PM
final lift at LP-2
Checking of reinforcement, shuttering & pouring concrete for abutment
NMSCEW/P-IV/STR/2020/8452 Viaduct Km 213+915 RHS 3/9/2020 4:30 PM
shaft 2nd lift at RA-2
NMSCEW/P-IV/STR/2020/8453 Checking of reinforcement, shuttering & pouring concrete for raft at LP-9 Viaduct Km 213+915 LHS 3/9/2020 4:45 PM
Checking of reinforcement Girder no -337,338,339,340 at bed no -08,
NMSCEW/P-IV/STR/2020/8454 Girder Km 200+200 LHS 3/9/2020 6:00 PM
Girder Type-01 at casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8455 Girder Km 200+200 LHS 3/9/2020 6:30 PM
337,338,339,340 at bed no -08, Girder Type-01 at casting yard camp -2
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at
NMSCEW/P-IV/STR/2020/8456 Box culvert Km 206+843 LHS 3/9/2020 11:00 AM
service road wall W1
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at
NMSCEW/P-IV/STR/2020/8457 PUP Km 206+985 RHS 3/9/2020 11:15 AM
retaining wall W1
Checking of reinforcement, shuttering & pouring concrete for abutment
NMSCEW/P-IV/STR/2020/8458 MJB Km 205+610 RHS 3/11/2020 11:00 AM
shaft final lift(5th) at RA-2
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at
NMSCEW/P-IV/STR/2020/8459 PUP Km 212+080 LHS 3/11/2020 10:00 AM
retaining wall W1
Checking of reinforcement Girder no -337,338,339,340 at bed no -08,
NMSCEW/P-IV/STR/2020/8461 Girder Km 200+200 LHS 3/11/2020 8:00 AM
Girder Type-01 at casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8462 Girder Km 200+200 LHS 3/11/2020 8:30 AM
337,338,339,340 at bed no -08, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -241,242,243,244 at bed no -02,
NMSCEW/P-IV/STR/2020/8463 Girder Km 200+200 LHS 3/11/2020 9:00 AM
Girder Type-02 at casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8464 Girder Km 200+200 LHS 3/11/2020 9:30 AM
241,242,243,244 at bed no -02, Girder Type-02 at casting yard camp -2
Checking of reinforcement Girder no -341,342,343,344 at bed no -05,
NMSCEW/P-IV/STR/2020/8465 Girder Km 200+200 LHS 3/11/2020 5:00 PM
Girder Type-01 at casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8466 Girder Km 200+200 LHS 3/11/2020 5:30 PM
341,342,343,344 at bed no -05, Girder Type-01 at casting yard camp -2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder
NMSCEW/P-IV/STR/2020/8467 Girder Km 200+200 LHS 3/11/2020 6:30 PM
no-241,242,243,244 at bed no -02, Girder Type-02
Checking of side shuttering and pouring(Grade of concrete M-50) of girder
NMSCEW/P-IV/STR/2020/8468 Girder Km 200+200 LHS 3/11/2020 7:30 PM
no-337,338,339,340 at bed no -08, Girder Type-01
Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st
NMSCEW/P-IV/STR/2020/8469 Viaduct Km 213+915 RHS 3/11/2020 3:30 PM
lift at RP-8
NMSCEW/P-IV/STR/2020/8470 Checking of reinforcement, shuttering & pouring concrete for raft at LP-9 Viaduct Km 213+915 LHS 3/11/2020 4:30 PM
Checking of Shuttering,reinforcement, pouring concrete for pier cap at RP-
NMSCEW/P-IV/STR/2020/8471 Viaduct Km 195+900 RHS 3/11/2020 11:30 AM IPC-14
6
Checking of Shuttering,reinforcement & pouring concrete for cross girder
NMSCEW/P-IV/STR/2020/8472 Viaduct Km 202+190 LHS 3/11/2020 12:30 PM
between LP-11 to LP-12
Checking of Shuttering,reinforcement & pouring concrete for cross girder
NMSCEW/P-IV/STR/2020/8473 Viaduct Km 202+190 RHS 3/11/2020 2:00 PM
between RP-11 to RP-12
NMSCEW/P-IV/STR/2020/8474 Checking of layout,level for bearing fixing at LP-11 Viaduct Km 202+190 LHS 3/11/2020 2:30 PM
NMSCEW/P-IV/STR/2020/8475 Checking of layout,level for bearing fixing at LP-13 Viaduct Km 202+190 LHS 3/11/2020 3:00 PM
Checking of Shuttering,reinforcement, pouring concrete for padestal at LP-
NMSCEW/P-IV/STR/2020/8476 Viaduct Km 196+560 LHS 3/11/2020 3:00 PM
1
Checking of Shuttering,reinforcement, pouring concrete for padestal at LP-
NMSCEW/P-IV/STR/2020/8477 Viaduct Km 196+560 LHS 3/11/2020 3:30 PM
2
NMSCEW/P-IV/STR/2020/8478 Checking of reinforcement, shuttering & pouring concrete for raft at LP-8 Viaduct Km 213+915 LHS 3/11/2020 9:30 AM IPC-14
Checking layout ,level,Shuttering,reinforcement & pouring concrete for
NMSCEW/P-IV/STR/2020/8480 PUP Km 211+210 BHS 3/12/2020 8:00 AM
final lift at wall W1 & W2 with MCW slab
Checking of side shuttering and pouring(Grade of concrete M-50) of girder
NMSCEW/P-IV/STR/2020/8486 Girder Km 200+200 LHS 3/12/2020 7:00 PM
no-341,342,343,344 at bed no -05, Girder Type-01
Checking layout ,level,Shuttering,reinforcement & pouring concrete for
NMSCEW/P-IV/STR/2020/8491 VUP Km 215+609 Median 3/13/2020 12:00 PM
median raft
Checking of reinforcement, shuttering & pouring concrete for pier shaft
NMSCEW/P-IV/STR/2020/8492 MJB Km 205+610 RHS 3/13/2020 4:00 PM
3rd lift (4.5m) at RP-2
Checking of reinforcement, shuttering & pouring concrete for median shaft
NMSCEW/P-IV/STR/2020/8493 MJB Km 205+610 Median 3/13/2020 2:00 PM
3rd lift at A2
Checking of reinforcement Girder no -245,246,247,248 at bed no -01,
NMSCEW/P-IV/STR/2020/8495 Girder Km 200+200 LHS 3/13/2020 6:00 PM
Girder Type-02 at casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8496 Girder Km 200+200 LHS 3/13/2020 6:30 PM
245,246,247,248 at bed no -01, Girder Type-02 at casting yard camp -2
Checking of reinforcement Girder no -345,346,347,348 at bed no -07,
NMSCEW/P-IV/STR/2020/8497 Girder Km 200+200 LHS 3/13/2020 5:00 PM
Girder Type-01 at casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8498 Girder Km 200+200 LHS 3/13/2020 5:30 PM
345,346,347,348 at bed no -07, Girder Type-01 at casting yard camp -2
Checking of Shuttering,reinforcement, pouring concrete for abutment cap
NMSCEW/P-IV/STR/2020/8499 Viaduct Km 196+560 LHS 3/13/2020 3:30 PM IPC-14
at LA-1
NMSCEW/P-IV/STR/2020/8500 Checking of reinforcement, shuttering & pouring concrete for raft at LP-9 Viaduct Km 213+915 LHS 3/13/2020 11:30 AM IPC-14
Checking of Shuttering,reinforcement, pouring concrete for pier cap at LP-
NMSCEW/P-IV/STR/2020/8501 Viaduct Km 213+915 LHS 3/13/2020 2:30 PM IPC-14
14
NMSCEW/P-IV/STR/2020/8503 Checking of layout,level for bearing fixing at LP-12 Viaduct Km 202+190 LHS 3/13/2020 2:30 PM
Checking of reinforcement Girder no -349,350,351,352 at bed no -03,
NMSCEW/P-IV/STR/2020/8507 Girder Km 200+200 LHS 3/14/2020 8:00 AM
Girder Type-01 at casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8508 Girder Km 200+200 LHS 3/14/2020 8:30 AM
349,350,351,352 at bed no -03, Girder Type-01 at casting yard camp -2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder
NMSCEW/P-IV/STR/2020/8509 Girder Km 200+200 LHS 3/14/2020 6:00 PM
no-345,346,347,348 at bed no -07, Girder Type-01
Checking of side shuttering and pouring(Grade of concrete M-50) of girder
NMSCEW/P-IV/STR/2020/8510 Girder Km 200+200 LHS 3/14/2020 7:00 PM
no-349,350,351,352 at bed no -03, Girder Type-01
Checking of side shuttering and pouring(Grade of concrete M-50) of girder
NMSCEW/P-IV/STR/2020/8511 Girder Km 200+200 LHS 3/14/2020 3:30 PM
no-245,246,247,248 at bed no -01, Girder Type-02
Checking of Shuttering,reinforcement, pouring concrete for padestal at LP-
NMSCEW/P-IV/STR/2020/8512 Viaduct Km 200+920 LHS 3/14/2020 5:00 PM
1
Checking of Shuttering,reinforcement, pouring concrete for padestal at LP-
NMSCEW/P-IV/STR/2020/8513 Viaduct Km 200+920 LHS 3/14/2020 4:30 PM
2
Checking of Shuttering,reinforcement, pouring concrete for padestal at LA-
NMSCEW/P-IV/STR/2020/8514 Viaduct Km 200+920 LHS 3/14/2020 5:30 PM
1
NMSCEW/P-IV/STR/2020/8515 Checking of layout ,level & laying concrete PCC for U-trough Box culvert Km 193+940 BHS 3/15/2020 9:00 AM
Checking of Shuttering,reinforcement, pouring concrete for pier cap at RP-
NMSCEW/P-IV/STR/2020/8524 Viaduct Km 213+915 RHS 3/15/2020 9:30 AM
1
Checking of reinforcement, shuttering & pouring concrete for pier shaft
NMSCEW/P-IV/STR/2020/8525 Viaduct Km 213+915 LHS 3/15/2020 11:15 AM
2nd lift at LP-13
Checking of reinforcement, shuttering & pouring concrete for pier shaft
NMSCEW/P-IV/STR/2020/8526 Viaduct Km 213+915 RHS 3/15/2020 2:30 PM
2nd lift at RP-12
Checking of reinforcement, shuttering & pouring concrete for abutment
NMSCEW/P-IV/STR/2020/8527 Viaduct Km 213+915 LHS 3/15/2020 12:00 PM
shaft 1st and final lift at LA-1
Checking of Shuttering,reinforcement, pouring concrete for pier cap at RP-
NMSCEW/P-IV/STR/2020/8528 Viaduct Km 195+900 RHS 3/15/2020 10:30 AM IPC-14
3
Checking of Shuttering,reinforcement & pouring concrete for cross girder
NMSCEW/P-IV/STR/2020/8529 Viaduct Km 202+190 LHS 3/15/2020 12:30 PM
between LP-12 to LP-13
Checking of Shuttering,reinforcement, pouring concrete for abutment cap
NMSCEW/P-IV/STR/2020/8530 Viaduct Km 200+920 RHS 3/15/2020 11:00 AM
at RA-2
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at
NMSCEW/P-IV/STR/2020/8531 PUP Km 211+210 LHS 3/16/2020 8:00 AM
service road wall W1 & W2
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at
NMSCEW/P-IV/STR/2020/8532 PUP Km 211+210 RHS 3/16/2020 8:30 AM
service road wall W1 & W2
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at
NMSCEW/P-IV/STR/2020/8533 PUP Km 212+080 LHS 3/16/2020 9:00 AM
retaining wall W1
Checking layout ,level,Shuttering,reinforcement & pouring concrete for
NMSCEW/P-IV/STR/2020/8534 PUP Km 215+609 3/16/2020 10:00 AM
median raft
NMSCEW/P-IV/STR/2020/8536 Closing of NCR No-2 for raft at RP-7 Viaduct Km 213+915 RHS 3/16/2020 10:30 AM
Checking of reinforcement, shuttering & pouring concrete for pier shaft
NMSCEW/P-IV/STR/2020/8537 MJB Km 205+610 RHS 3/16/2020 2:00 PM
3rd lift at RP-2
Checking of reinforcement,shuttering and Pouring concrete for 4th lift at
NMSCEW/P-IV/STR/2020/8538 MJB Km 205+610 LHS 3/16/2020 4:00 PM
retaining wall LA-1
Checking of reinforcement, shuttering & pouring concrete for median shaft
NMSCEW/P-IV/STR/2020/8539 MJB Km 205+610 3/16/2020 6:00 PM
4th lift at A-2
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at
NMSCEW/P-IV/STR/2020/8540 MJB Km 205+610 RHS 3/17/2020 2:00 PM
retaining wall RA-2
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at
NMSCEW/P-IV/STR/2020/8541 PUP Km 212+080 LHS 3/17/2020 8:00 AM
retaining wall W-2
Checking of layout ,level structural excavation & laying concrete PCC for
NMSCEW/P-IV/STR/2020/8542 Utility duct Km 214+600 3/17/2020 10:00 AM
2x2 Utility duct
Checking of side shuttering and pouring(Grade of concrete M-50) of girder
NMSCEW/P-IV/STR/2020/8546 Girder Km 200+200 LHS 3/17/2020 6:00 PM
no-353,354,355,356 at bed no -06, Girder Type-01
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at
NMSCEW/P-IV/STR/2020/8547 MNB Km 193+135 RHS 3/17/2020 4:00 PM
wall W-3
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at
NMSCEW/P-IV/STR/2020/8548 MNB Km 193+135 LHS 3/17/2020 4:30 PM
wall W-2 & W-3
Checking of reinforcement Girder no -357,358,359,360 at bed no -04,
NMSCEW/P-IV/STR/2020/8549 Girder Km 200+200 LHS 3/17/2020 5:00 PM
Girder Type-01 at casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8550 Girder Km 200+200 LHS 3/17/2020 5:30 PM
357,358,359,360 at bed no -04, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -353,354,355,356 at bed no -06,
NMSCEW/P-IV/STR/2020/8551 Girder Km 200+200 LHS 3/17/2020 8:00 AM
Girder Type-01 at casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8552 Girder Km 200+200 LHS 3/17/2020 8:30 AM
353,354,355,356 at bed no -06, Girder Type-01 at casting yard camp -2
Checking of Shuttering,reinforcement, pouring concrete for abutment cap
NMSCEW/P-IV/STR/2020/8554 Viaduct Km 200+920 RHS 3/17/2020 3:00 PM IPC-14
at RA-2
NMSCEW/P-IV/STR/2020/8567 Closing of NCR No-2 for raft at RP-7 Viaduct Km 213+915 RHS 3/17/2020 11:00 AM
Checking of reinforcement, shuttering & pouring concrete for pier shaft
NMSCEW/P-IV/STR/2020/8568 Viaduct Km 213+915 LHS 3/17/2020 11:35 AM
2nd lift at LP-13
Checking of reinforcement, shuttering & pouring concrete for abutment
NMSCEW/P-IV/STR/2020/8569 Viaduct Km 213+915 LHS 3/17/2020 2:00 PM
shaft 1st and final lift at LA-1
Checking of reinforcement, shuttering & pouring concrete for pier shaft
NMSCEW/P-IV/STR/2020/8570 Viaduct Km 213+915 RHS 3/17/2020 4:30 PM
2nd lift at RP-12
NMSCEW/P-IV/STR/2020/8571 Checking of layout ,level & laying concrete PCC Box culvert Km 215+575 LHS 3/17/2020 10:00 AM
NMSCEW/P-IV/STR/2020/8572 Checking of layout ,level & laying concrete PCC for U-trough Box culvert Km 193+940 BHS 3/17/2020 2:00 PM
Checking of reinforcement, shuttering & pouring concrete for median shaft
NMSCEW/P-IV/STR/2020/8573 MJB Km 205+610 3/18/2020 2:00 PM
4th lift at A-2
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at
NMSCEW/P-IV/STR/2020/8574 PUP Km 212+080 LHS 3/18/2020 11:00 AM
retaining wall W2
NMSCEW/P-IV/STR/2020/8575 Checking of layout ,level structural excavation & laying concrete PCC Box culvert Km 215+575 RHS 3/18/2020 8:00 AM
Checking of Shuttering,reinforcement & pouring concrete for pier shaft 1st
NMSCEW/P-IV/STR/2020/8579 Viaduct Km 213+915 LHS 3/18/2020 2:00 PM
lift at LP-4
NMSCEW/P-IV/STR/2020/8580 Checking of reinforcement, shuttering & pouring concrete of LP-6 pedestal Viaduct Km 196+560 LHS 3/18/2020 3:00 PM
NMSCEW/P-IV/STR/2020/8581 Checking of reinforcement, shuttering & pouring concrete of RA-1 pedestal Viaduct Km 196+560 RHS 3/18/2020 3:30 PM
Checking of reinforcement Girder no -249,250,251,252 at bed no -02,
NMSCEW/P-IV/STR/2020/8582 Girder Km 200+200 LHS 3/18/2020 9:00 AM
Girder Type-02 at casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8583 Girder Km 200+200 LHS 3/18/2020 9:30 AM
249,250,251,252 at bed no -02, Girder Type-02 at casting yard camp -2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder
NMSCEW/P-IV/STR/2020/8584 Girder Km 200+200 LHS 3/18/2020 7:00 PM
no-249,250,251,252 at bed no -02, Girder Type-02
Checking of Shuttering,reinforcement & pouring concrete for pier shaft 1st
NMSCEW/P-IV/STR/2020/8585 Viaduct Km 195+900 RHS 3/18/2020 3:30 PM
lift at RP-8
Checking of Shuttering,reinforcement & pouring concrete for cross girder
NMSCEW/P-IV/STR/2020/8586 Viaduct Km 202+190 RHS 3/18/2020 10:00 AM
between RP-12 to RP-13
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at
NMSCEW/P-IV/STR/2020/8589 MJB Km 205+610 RHS 3/19/2020 2:00 PM
retaining wall RA-2
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at
NMSCEW/P-IV/STR/2020/8590 MJB Km 205+610 RHS 3/19/2020 11:00 AM
pier shaft RP-2
NMSCEW/P-IV/STR/2020/8591 Checking of layout ,level structural excavation & laying concrete PCC VUP Km 192+885.5 BHS 3/19/2020 2:30 PM
Checking of reinforcement, shuttering & pouring concrete for abutment
NMSCEW/P-IV/STR/2020/8595 Viaduct Km 213+915 LHS 3/19/2020 4:00 PM
shaft final lift at LA-2
Checking of reinforcement Girder no -01,02,03,04 at bed no -08, Girder
NMSCEW/P-IV/STR/2020/8597 Girder Km 200+200 LHS 3/19/2020 10:00 AM
Type-03 at casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8598 Girder Km 200+200 LHS 3/19/2020 10:30 AM
01,02,03,04 at bed no -08, Girder Type-03 at casting yard camp -2
Checking of reinforcement Girder no -357,358,359,360 at bed no -05,
NMSCEW/P-IV/STR/2020/8599 Girder Km 200+200 LHS 3/19/2020 6:00 PM
Girder Type-01 at casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8600 Girder Km 200+200 LHS 3/19/2020 6:30 PM
357,358,359,360 at bed no -05, Girder Type-01 at casting yard camp -2
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at
NMSCEW/P-IV/STR/2020/8601 MNB Km 193+135 MNB 3/19/2020 4:00 PM
wall W-2 & W-3
NMSCEW/P-IV/STR/2020/8602 Checking of layout ,level structural excavation & laying concrete PCC Box culvert Km 216+260 BHS 3/20/2020 9:30 AM
NMSCEW/P-IV/STR/2020/8603 Checking of layout ,level structural excavation & laying concrete PCC Box culvert Km 214+805 BHS 3/20/2020 10:00 AM
NMSCEW/P-IV/STR/2020/8604 Checking of layout ,level structural excavation & laying concrete PCC Box culvert Km 216+950 BHS 3/20/2020 11:00 AM
NMSCEW/P-IV/STR/2020/8605 Checking of layout ,level structural excavation & laying concrete PCC WUP Km 216+430 BHS 3/20/2020 12:00 PM
Checking of reinforcement,shuttering and Pouring concrete for 1st lift at
NMSCEW/P-IV/STR/2020/8606 PUP Km 212+080 RHS 3/20/2020 11:30 AM
retaining wall W-2
Checking of Shuttering,reinforcement & pouring concrete for pier shaft final
NMSCEW/P-IV/STR/2020/8607 MJB Km 205+610 RHS 3/20/2020 5:00 PM
lift at RP-2
NMSCEW/P-IV/STR/2020/8610 Checking of layout ,level & laying concrete for AP2 PCC VUP Km 210+520 BHS 3/20/2020 10:00 AM
Checking of layout ,level, Shuttering,reinforcement & pouring concrete for
NMSCEW/P-IV/STR/2020/8611 PUP Km 215+609 Median 3/20/2020 8:30 AM
median raft
Checking of Shuttering,reinforcement & pouring concrete for median shaft
NMSCEW/P-IV/STR/2020/8616 MJB Km 205+610 Median 3/21/2020 11:00 AM
5th lift at A2
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at
NMSCEW/P-IV/STR/2020/8617 MNB Km 208+455 Median 3/21/2020 10:00 AM
median wall W-1
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at
NMSCEW/P-IV/STR/2020/8618 VUP Km 215+609 RHS 3/21/2020 11:30 AM
wall W-1 & W-2
NMSCEW/P-IV/STR/2020/8619 Checking of layout ,level & laying concrete for PCC VUP Km 192+885.5 BHS 3/21/2020 2:00 PM
Checking of Shuttering,reinforcement, pouring concrete for pier cap at RP-
NMSCEW/P-IV/STR/2020/8620 Viaduct Km 195+900 RHS 3/21/2020 3:30 PM IPC-14
5
Checking of reinforcement, shuttering & pouring concrete for pier shaft
NMSCEW/P-IV/STR/2020/8621 Viaduct Km 213+915 LHS 3/21/2020 2:00 PM
2nd lift at LP-12
Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st
NMSCEW/P-IV/STR/2020/8622 Viaduct Km 213+915 RHS 3/21/2020 4:00 PM
lift at RP-11
Checking of reinforcement, shuttering & pouring concrete for abutment
NMSCEW/P-IV/STR/2020/8626 Viaduct Km 200+920 RHS 3/21/2020 3:00 PM
shaft final lift at RA-1
Checking of reinforcement,shuttering and Pouring concrete for 3rd lift at
NMSCEW/P-IV/STR/2020/8629 MJB Km 205+610 RHS 3/23/2020 10:00 AM
retaining wall RA-2
Checking of reinforcement,shuttering and Pouring concrete for 5th lift at
NMSCEW/P-IV/STR/2020/8630 MJB Km 205+610 LHS 3/23/2020 4:00 PM
retaining wall LA-2
Checking of reinforcement Girder no -357,358,359,360 at bed no -03,
NMSCEW/P-IV/STR/2020/8631 Girder Km 200+200 LHS 3/23/2020 8:00 AM
Girder Type-01 at casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8632 Girder Km 200+200 LHS 3/23/2020 8:30 AM
357,358,359,360 at bed no -03, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -361,362,363,364 at bed no -05,
NMSCEW/P-IV/STR/2020/8633 Girder Km 200+200 LHS 3/23/2020 2:00 PM
Girder Type-01 at casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8634 Girder Km 200+200 LHS 3/23/2020 2:30 PM
361,362,363,364 at bed no -05, Girder Type-01 at casting yard camp -2
Checking of reinforcement Girder no -01,02,03,04 at bed no -08, Girder
NMSCEW/P-IV/STR/2020/8635 Girder Km 200+200 LHS 3/23/2020 11:00 AM
Type-03 at casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8636 Girder Km 200+200 LHS 3/23/2020 11:30 AM
01,02,03,04 at bed no -08, Girder Type-03 at casting yard camp -2
Checking of reinforcement Girder no -253,254,255,256 at bed no -01,
NMSCEW/P-IV/STR/2020/8637 Girder Km 200+200 LHS 3/23/2020 3:00 PM
Girder Type-02 at casting yard camp -2
Checking for stressing and remove slagness of H.T. wires at Girder no-
NMSCEW/P-IV/STR/2020/8638 Girder Km 200+200 LHS 3/23/2020 3:30 PM
253,254,255,256 at bed no -01, Girder Type-02 at casting yard camp -2
Checking of side shuttering and pouring(Grade of concrete M-50) of girder
NMSCEW/P-IV/STR/2020/8639 Girder Km 200+200 LHS 3/23/2020 7:00 PM
no-357,358,359,360 at bed no -03, Girder Type-01
Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st
NMSCEW/P-IV/STR/2020/8640 Viaduct Km 213+915 RHS 3/23/2020 2:15 PM
lift at RP-11
Checking of reinforcement, shuttering & pouring concrete for pier shaft 1st
NMSCEW/P-IV/STR/2020/8641 Viaduct Km 213+915 RHS 3/23/2020 4:00 PM
and final lift at RA-1
Checking of reinforcement,shuttering and Pouring concrete for 2nd lift at
NMSCEW/P-IV/STR/2020/8642 VUP Km 215+609 LHS 3/23/2020 10:00 AM
wall W-1 & W-2
Checking of layout level reinforecement shuttering and pouring of concrete
NMSCEW/P-IV/STR/2020/8643 Box culvert Km 206+843 BHS 3/24/2020 8:00 AM
for service road slab and wall w1 w2 final lift
Checking of layout level reinforecement shuttering and pouring of concrete
NMSCEW/P-IV/STR/2020/8644 PUP Km 211+210 BHS 3/24/2020 9:00 AM
for service road slab and wall w1 w2 final lift
Checking of reinforecement shuttering and pouring of concrete for wall w1
NMSCEW/P-IV/STR/2020/8645 VUP Km 215+609 RHS 3/24/2020 12:00 PM
& w2 3rd lift
Checking of reinforecement shuttering and pouring of concrete for wall w1
NMSCEW/P-IV/STR/2020/8646 VUP Km 215+609 LHS 3/24/2020 5:00 PM
& w2 3rd lift
Attendence sheet