DRIVEN OF PRECAST CONCRETE PILES
Project.
Area / Location: Common Equipment Tag: None P.O Ref. No.: N/A
Pre-inspection a. Review QC document as below: All document approved and Approved WPS • QC document w H H/R
meeting & quality • Verify latest approved ITP & quality complete IQWQ-KE package (ITP,
control program record/check sheet CSPDS-D8- project spec.,
reviewing • Verify latest approved project spec. 0002 Spec. of method
• Verify latest approved drawing Concrete statement,
(layout/coordinate) drawing, survey
• Verify approved WPS & welder IQWQ-KE procedure, IMTE
qualification (structural weld) CSPDS-D8- log for survey
• Verify latest approved method statement 0009 Precast device
• Verify calibration of pile testing & survey Concrete Spec. ■ Independent
equipment inspection/testing
b. Verify 3rd party pile testing & NDT company IQWQ-KE firm qualification
• Qualification KPMTH-D8- report & record
• Verify field lab. facilities 0044 1 MS for Minutes of
c. Pre-activity quality meeting Pile - meeting
manufacturing
and driving • AWS D1.1
works
2 Inspection prior to a. Review pile final inspection from fabrication • Final inspection report & IQWQ-KE • IQ324-000-QA R w s
driving (released for placement/driving) clearance complete and CSPDS-D8- FRM-00091
b. Inspect pile handling & stockpiling condition accepted 0002 Concrete Final
c. Inspect pile marking and identification • Pile move/transport to site Inspection
only after reaching min. Record
strength 31.5 N/mm2
strength and after 7 days
curing
• Stockpile done as per
spec. and method
statement (4 stack max.)
and no damage on the pile
Pile had proper marking and
identification
3 Pile coordinate a. Measure pile coordinate location as per • Pile type and coordinate as • Approved • IQ324-000-QA w w s
location survey layout drawing per approved pile layout drawing FRM-00027
b. Ensure pile type is correct as per pile layout drawing Q324-000-QA
drawing (PCP-1 or PCP-2) FRM-00027
General
Survey
Measurement
Report
* Inspection Point Type Codes: S - Surveillance (Random); W - Witness Point; H - Mandatory Hold Point; R - Review
INSPECTION AND TEST PLAN
Page 4 of 6
DRIVEN OF PRECAST CONCRETE PILES
Area I Location: Common Equipment Tag: None P.O Ref. No.: N/A
5 Pile jointing and a. Inspect fit up of pile cap to pile cap (shaft a. Fit up done as per IQWQ-KE • IO324-000-QA w w w
welding rod, bracket) and splice plate approved drawings RSPDS-D8- FRM-00001
b. Inspect the pile welding joint b. 100 % visual inspection of 0009 Structural Fit-Up & Visual
c. NDT inspection on welding joint seams according to AWS steel welding Inspection
D1.1/D1.1M and inspection Report
c. Only visual inspection done specification • MPI report
on each pile joint during IQWQ-KE • IO324-000-QA
day shift. KPMTH-D8- FRM-00090
d. 20% of MT and visual 0044 1 MS for Pile Driving
inspection done on each Pile - Splice Pad
pile joint during night shift. manufacturing Welding &
and driving NDE Summary
works Sheet
• IQWQ-KE
QPQAC-D8-
0042 Visual
Examination
Procedure
■ Tohama
Magnetic Test
Procedure
• AWS
D1.1/D1.1M
Structural
Welding
Code-Steel
* Inspection Point Type Codes: S- Surveillance (Random); W- Witness Point; H - Mandatory Hold Point; R- Review
INSPECTION AND TEST PLAN
Page 5 of 6
DRIVEN OF PRECAST CONCRETE PILES
Rev.4 Project.
Area I Location: Common EquipmentTag:None P.O Ref. No.:N/A
Contractor Signature /Stamp and Date Company Signature /Stamp and Date
* Inspection Point Type Codes: S - Surveillance (Random); W - Witness Point; H - Mandatory Hold Point; R - Review