MS Bored Piling Works - Inner Ring Rev2 30.9.2020
MS Bored Piling Works - Inner Ring Rev2 30.9.2020
MS Bored Piling Works - Inner Ring Rev2 30.9.2020
METHOD STATEMENT
FOR
TABLE OF CONTENTS
1.0 INTRODUCTION......................................................................................................................................3
2.0 REFERENCES..........................................................................................................................................5
3.0 MATERIALS.............................................................................................................................................5
5.0 MANPOWER.............................................................................................................................................7
1
CONSTRUCTION AND COMPLETION
OF THE PROPOSED INNER RING ROAD
KUCHING DIVISION – PACKAGE B
11.0 APPENDIX............................................................................................................................................19
2
CONSTRUCTION AND COMPLETION
OF THE PROPOSED INNER RING ROAD
KUCHING DIVISION – PACKAGE B
1.0 INTRODUCTION
3
CONSTRUCTION AND COMPLETION
OF THE PROPOSED INNER RING ROAD
KUCHING DIVISION – PACKAGE B
This method statement illustrated the installation of the 600mm bored piling
work for upgrading the existing Sg Siol bridge to a dual-carriageway bridge
which is located along Petra Jaya, Kuching for the project “CONSTRUCTION
AND COMPLETION OF THE PROPOSED INNER RING ROAD KUCHING DIVISION
– PACKAGE B”. The locality and site phone as shown in Figure 1.1 and 1.2.
The new bridge consists of 2 abutments, each with 12 bored pile points and 2
piers, each with 16 bored pile points. For each abutment, 6 of pile facing the
4
CONSTRUCTION AND COMPLETION
OF THE PROPOSED INNER RING ROAD
KUCHING DIVISION – PACKAGE B
river pier is to be installed raked at a ratio of 1:5 while the other 6 are vertical
pile. For the 2 piers, all the pile is vertical. Total bored pile points to be
installed are 44 vertical and 12 raked.
5
CONSTRUCTION AND COMPLETION
OF THE PROPOSED INNER RING ROAD
KUCHING DIVISION – PACKAGE B
zone. The remaining points will be stabilized using temporary casing. The
work sequence and detailed working schedule shall conform with the site
condition and after further discussion with main contractor.
2.0 REFERENCES
3.0 MATERIALS
NO MATERIAL PURPOSE
1 Rebar T32 Main bar
2 Rebar T25 Main bar
3 Rebar T20 Main bar
4 Rebar T12 Spiral link
6
CONSTRUCTION AND COMPLETION
OF THE PROPOSED INNER RING ROAD
KUCHING DIVISION – PACKAGE B
5.0 MANPOWER
7
CONSTRUCTION AND COMPLETION
OF THE PROPOSED INNER RING ROAD
KUCHING DIVISION – PACKAGE B
8
CONSTRUCTION AND COMPLETION
OF THE PROPOSED INNER RING ROAD
KUCHING DIVISION – PACKAGE B
i. The setting out of piles shall be carried out by a licensed surveyor and the
information shall be submitted for assessment as per stated in the contract
drawing. For abutment A and B, the river bank will be backfilled as access
and staging of machine. For pier 1 and 2, sheet pile cofferdam is proposed
to be installed and backfilled for piling work and pile cap construction
work to be carried out. The platform will be top up of 1.5 meter from
expected cut off level of piling and resurveyed by licensed surveyor to
confirm the final levels. Before mobilization of machinery in, main
Contractor’s licensed surveyor will peg up the exact piling points,
planning of test pile points & the overall piling work sequence.
9
CONSTRUCTION AND COMPLETION
OF THE PROPOSED INNER RING ROAD
KUCHING DIVISION – PACKAGE B
ii. The survey control points, typically the TBMs are determined by the main
Contractor's surveyor. A numbers of control points will be established
using closed traversing method.
iii. These control points are rechecked periodically by the main Contractor's
surveyor to ensure continued accuracy. The location of these points shall
be sited at a place unlikely to be disturbed and are clearly marked.
v. Since the pegged position is the center of pile, before boring work
commences, the center peg will be offset to 2 axis for reference and cross
checking.
vi. The verticality of the drilling rod will be checked before the drilling
process starts and confirmed by the consultant. For raked pile the drilling
rod should be adjusted to the desired raked ratio as per design. For
example, 1: 5 ratio checks with 100mm: 500mm template to confirm the
inclined angle.
10
CONSTRUCTION AND COMPLETION
OF THE PROPOSED INNER RING ROAD
KUCHING DIVISION – PACKAGE B
i. The rebar reinforcement cage for the pile shall be fabricated according to
the requirement and specification stated in BS5135 standards. Before any
reinforcement steel is brought to site, the mill certificates and reports of
tensile test will be submitted for acceptance by the S.O. The steel
reinforcement will be stored in clean and dry conditions where it is free
from loose rust, mill scale, oil, grease, paint, dirt or anything which may
reduce its bond with concrete.
ii. Main bars of correct lengths are lapped, and spiral reinforcement are fitted
into position. Three sets of rebar cage, with different main bar size will be
prepared with required jointing length (min 50x bar diameter) and the
lapping of main bars will be staggered to alternate bars. Plastic, concrete
or steel spacers will be used (subject to specification) to ensure that the
cage maintain at the correct position and to achieve concrete cover of
75mm.
iii. Links on the top and bottom of the cage will be welded accordingly to
provide a rigid reinforcement cage. Hooks will be welded to the top of the
steel cage to enable lifting of the cage into the borehole during installation
11
CONSTRUCTION AND COMPLETION
OF THE PROPOSED INNER RING ROAD
KUCHING DIVISION – PACKAGE B
iv. Concrete spacers or metal pads (BS-EN-1536 (1)) will be used to provide
75mm of cover where the spacers will be threaded onto the links and the
spacing of the spacer block shall be of 3m interval along the reinforcement
cage. A minimum of 4 layers of 4 nos. of concrete spacers or metal pads
per layer will also be provided for each 12m length of the concrete cage.
In addition, centralizer will be installed with 1500mm spacing at the main
reinforcement bar.
v. Tubes for integrity test using sonic logging method shall be installed in all
bored pile reinforcement cages equally spaced and secured with welding.
Figure 6.5 Spiral link preparation Figure 6.6 Completed rebar cage
12
CONSTRUCTION AND COMPLETION
OF THE PROPOSED INNER RING ROAD
KUCHING DIVISION – PACKAGE B
i. After checking and ensuring that the pegged position of the borehole is
accurate, the borehole will be drilled using appropriate drilling tools. The
borehole will be stabilized with the cased method which the permanent
casing was allowed in the contract otherwise stabilizing fluids bentonite /
water shall be used to stabilize the bored hole.
ii. After fixing the casing into its position, the borehole will be drilled to its
required depth by using bucket and auger as stated in the drawing provided.
For drilling into soils and weathered rock above the solid rock formation, a
suitable tool will be used, depending on the type of soil condition. Upon
encounter with rock surface where the soil drilling tools is unable to
penetrate through, the reduced level of the rock will be determined by SPT
test, and drilling shall be continued using rock drilling tools to drill through
the rock until the final socket length of 5500mm in sandstone.
iii. When cavity or weaker material is encountered, the founding level shall be
lower than the provision level or that established by the test pile. SPT shall
be carried out at every 2.0m interval to establish the strength of the
socketing material and the founding levels. SPT shall be carried out in two
stages, which seating drive and test drive
iv. When the designed depth has been achieved and approved by the S.O., the
base of the borehole will be cleaned by flushing out soil particles with
recirculation water or air. Then, the depth of the borehole will be measured
again by using a tape and the reading obtained will be recorded.
13
CONSTRUCTION AND COMPLETION
OF THE PROPOSED INNER RING ROAD
KUCHING DIVISION – PACKAGE B
i. After the depth of borehole approved by S.O. and cleaned, rebar cage will
be installed and joint to required length. Otherwise if the steel casing
length is not enough to socketing, casing will be extended to required
length by butt weld and driven to level.
ii. Rebar cage will be placed into the borehole by using a lifting chain after
sufficient laps have been provided to ensure there is no slippage of cages
while lowering the cage into the borehole. Welding shall be carried out
according to BS5135 and BS638 and as specified in detailed drawings for
14
CONSTRUCTION AND COMPLETION
OF THE PROPOSED INNER RING ROAD
KUCHING DIVISION – PACKAGE B
15
CONSTRUCTION AND COMPLETION
OF THE PROPOSED INNER RING ROAD
KUCHING DIVISION – PACKAGE B
i. Concrete mix will be discharged into the borehole by using a tremie pipe
of 190 mm diameter which will be lowered to the bottom of the bored hole
prior to filling it with concrete.
ii. The tremie pipe will be joined and lowered into the borehole where each
joint will be secured with thread method to ensure that it is water tight.
The concrete will be placed via a hopper which is attached to the top of
the tremie pipe. Before placing concrete, the borehole is cleaned by
air/water flushing method till clear water is obtained.
iii. The concrete shall be discharged continuously and the tremie pipe shall be
withdrawn upward as the concrete level in the borehole rises and the
bottom of the tremie pipe is ensured to be embedded at least 2m below the
concrete level in the borehole. Concrete level of the borehole will be
measured and recorded accordingly after each concrete truck discharged.
Concrete will be cast above the cut off level for minimum 1.3m.
iv. If temporary casing was used, it will be extracted slowly after the
concreting process completed.
vi. Concrete and cement grout test cubes for bored piles shall be taken from
the concrete overflowing from the top of the bored shaft. Test cubes shall
16
CONSTRUCTION AND COMPLETION
OF THE PROPOSED INNER RING ROAD
KUCHING DIVISION – PACKAGE B
only be taken after the discharge from the shaft comprises clean concrete
that is free from soil contaminant.
Figure 6.11 Lower of tremie pipe Figure 6.12 Overflow of fresh concrete
i. Maintained load test (MLT), Pile integrity test (PIT), Sonic Logging Test
(SLT) and Pile Driving Analysis (PDA) will be elaborated in separated
method statement. MLT will be carried out for the test pile after the
concrete achieved required design strength, before commencing of other
piling works. All the test pile points will be confirmed and agreed with
S.O. before testing. After the sonic logging test was carried out, all the
sonic logging tube will be infilled with cement grout suit to pile concrete
strength. After testing was completed, pile head will be hacked to cut off,
elaborated in separated method statement.
ii. All the piling point as built will be surveyed and recorded by main
Contractor’s licensed surveyor after piling work was completed and
passed testing. The data will then be submitted to consultant for record.
17
CONSTRUCTION AND COMPLETION
OF THE PROPOSED INNER RING ROAD
KUCHING DIVISION – PACKAGE B
iii. The 28 pilot boreholes will be arranged by main Contractor prior to bored
piling work.
7.0 SAFETY AND HEALTH
All control measures required in Job Safety and Health Analysis will be
disseminated to site personals including consultant, engineer, supervisor
and worker through Safety Induction Briefing, Tool Box Briefing, Notice
Board, Safety & Health Meeting and Campaign.
Safety helmets & safety boots must be worn at all time on the
project/operation area and the helmet shall be properly adjusted.
18
CONSTRUCTION AND COMPLETION
OF THE PROPOSED INNER RING ROAD
KUCHING DIVISION – PACKAGE B
Helmets shall not be drill, cut or otherwise altered but it can be labelled
with stick on nametags.
Glove shall be worn when necessary and type of glove shall suite the
operation and hazard.
19
CONSTRUCTION AND COMPLETION
OF THE PROPOSED INNER RING ROAD
KUCHING DIVISION – PACKAGE B
The potential environmental impacts shall be identified for all the related
activities and control measures shall be developed concurrently based on
the identified impacts. This control measures shall be implemented to
reduce or minimize the environmental impacts to the environment and the
local public.
- NOT APPLICABLE
11.0 APPENDIX
20