Nothing Special   »   [go: up one dir, main page]

CHE4170 Workshop 9 Project Viability and Things To Consider in Developing PID

Download as pdf or txt
Download as pdf or txt
You are on page 1of 27

CHE4170 DESIGN PROJECT

WORKSHOP 9

PROJECT VIABILITY AND THINGS TO


CONSIDER IN DEVELOPING PIPING AND
INSTRUMENTATION DIAGRAM
SUMMARY OF LECTURE
• Project viability

• Overall requirement of a piping and instrumentation diagram

• Cause and Effect Matrix

2
PROJECT VIABILITY

• The final section of Progress Report 3 and Final Report 1

• A concluding assessment based on your


1. Technical Viability (Technology capable of meeting specifications including safety)
2. Economic Viability (based on detailed economic analysis)
3. Environmental Viability (based on environmental impact assessment)

• Group is expected to make a recommendation to the stakeholders based on the items listed
above

3
TECHNICAL VIABILITY/SAFETY
▪ The project is technically viable, if the following conditions are met:
• Meets the defined capacity rating and throughput rate as defined in the project description

• Meets product specifications ,i.e. domestic market, global commercial standards

• Adaptable to different feedstocks.

• Has engineering flexibility to meet moderate changes in product specifications in line with the evolving
needs of the customer.

• ISD considerations have been extensively critiqued and factored in and plant subjected to HAZID and
HAZOP studies

• Risk Assessment Studies- Bow Tie Analysis – Adequacy of Preventive and Mitigative Measures

• Is the facility a CIMAH site - Has the applicable regulations and conditional requirements factored in ?

4
TECHNICAL VIABILITY/SAFETY 2
• The project is technically viable, if the following conditions are met:

• Site selection criteria meets no only various regulatory requirements but also addresses transportation
and logistics requirements

• Best practices and proven technologies have been selected.

• Engineering and hardware selection follow global standards

• Plant layout has been optimized

• Reliability engineering and an effective MPS defines manufacturing excellence and hence remove
unnecessary redundancies.
▪ What factors in the design could be further reviewed to improve the Technical Viability and Safety
adequacy? Be factual with regards to errors/omissions and assumptions.

5
ECONOMIC VIABILITY
The project is economically viable if an acceptable rate of return can be achieved over the project life
(IRR = 12-15% or higher).

▪ Does the NPV look realistic ? How significant are the risks?
• Increased capital cost
• Increase in variable costs, in particular, raw materials
• Delayed start-up
• Reduced sales in the first few years as market grows
• Reduced plant availability
• Reduction in selling prices
What factors in the design could be used to improve the Economic Viability of the project, i.e. sensitivity
analysis, i.e. individual and a combination of adverse impacts and how they can be addressed.
6
ENVIRONMENTAL VIABILITY

▪ What risks does the plant pose to the environment and are these acceptable?

• Emissions to air, water and land


✓ Aquatic
✓ Scheduled waste
✓ Atmospheric emissions
✓ Land/Groundwater contamination
✓ Community Impacts
✓ Disturbance to flora and fauna (endangered species)

▪ What factors in the design could be reviewed to further improve the overall environmental viability ?

7
STRATEGIC AND TECHNOLOGY IMPACTS

What external factors could change the project viability? Start by assuming the project is NOT viable.

▪ Technically Viability → is there a new process or technology that could improve viability ?
• Increase yield and efficiency
• Better purification technology
• Reengineered, optimized technology, i.e reduced unit operations, reduced
• hardware.

▪ Economic viability
• Reduced tax regime, i.e corporate tax rates, IT allowances
• Government incentives, i.e reduced tariffs
• Long term supply contracts
• Price escalation formula built into sales contracts.
• Cheaper sources of raw materials

8
RECOMMENDATIONS TO STAKEHOLDERS
▪ State clearly the project viability. If the project viability is adverse or suspect, you need to make some
recommendations as to how to proceed based on this study using the enablers provided in the earlier
slides.

• General Rule
1. Summarise, keep it short. Don’t introduce new data – Avoid reproducing key figures from previous sections,
but synopsize/distill to suit concluding remarks

2. everything should have been discussed in more detail in previous sections, i.e.

a. Process Evaluation Selection

b. Process Description /Efficiencies/Optimisation

c. General Safety & Environmental risks

d. Project Economics/Viability
9
REQUIREMENT OF DRAWING P&ID

• Part of Progress Report 4

• Piping and Instrumentation Diagram is an engineering drawing – technical drawing to fully define your
engineered items (process and equipment)

• A good P&ID could be easily read by an experienced engineer.

• It is a form of language: needs professional personnel to interpret it (PIDs)

• It is not a sketch (like art drawing) hence it needs to have certain details before you can call it an engineering
drawings.

• Apart from putting automatic on/off valves, you need to include cause and effect matrix to complete the
safety later of your P&ID

10
Example Piping
and
Instrumentation
Diagram

N1 N4 N2

N3 You are not required


N5
N6
to draw to such
details but you have
to at least get the
drawing format right
N1 N4 N2

N3

N6

N5

DDrawing no
11
D
Equipment block – note that operating
temperature and pressure is optional

N1 N4 N2

N3

N6

Drawing N5

connectors: with
connecting
drawing numbers
in the connectors N1 N4 N2

N3 Drawing number
N6

Drawing N5

Borders Authors and Title block: Avoid


Drawing short forms like
Notes Section Checkers Section
Revision section PID

Scale = just put


DDrawing no
1: if not known 12
D
SOME MINOR DETAILS THAT YOU MIGHT MISS…
Your P&ID should include:

1. All process equipment identified by an equipment number: D201


2. Should be drawn roughly in proportion, and show the location of nozzles: N1, N2 (Nozzle numbers should
be consistent with your process datasheet during detailed design)
3. All pipes should be identified by a line number: P201-150-16H10
4. All valves, incl. control and manual valves, with an identification number:
• Symbol, valve number:

5. Ancillary fittings, such as flange, strainers, steam traps, etc

6. All control loops and instruments/safety instrument, with an instrument tag number:

7. Provision for startup, shutdown and maintenance purpose – e,g. bypass lines, purging connection and etc.

8. Do not forget to include P&ID legend.

13
SIMPLE CHECKLIST TO BE DONE IN P&ID

1. Equipment type (For example, centrifugal, gear, reciprocating)


2. Line Numbering (size, pressure rating and etc.)
3. Valve selection (Gate, plug, ball, globe, butterfly)
4. Material for construction selection (SS304, SS316, carbon steel, mild steel)
5. Control systems selection (data transmission type – very much depend on your local facility)
6. Fittings selection and others (strainer, steam trap, flange, flow meter, insulation, etc)
7. Safety aspect (Shutdown valves, cause and matrix effect and etc)
8. Flexible design (start-up and shutdown)
9. Handling of out spec products
10. Maintenance and services

14
SOME GENERAL TIPS FOR P&ID
• Use A3 paper at the very least - Drawing Border (~1 cm from edge)

• Develop P&ID drawing form the PFD – recommend to only put 2 to 3 pieces of equipment per drawing sheet.
Avoid cluttering your drawing.

• Use bold lines for main process lines and thin lines for utility/by-pass lines.

• Think if you need the following: interlock systems, drains, isolations and utility connections.

• You will most likely discuss your start-up, shutdown and maintenance of your equipment based on revised
PFD and P&ID. Make sure you include all the start-up, shutdown or bypass lines in your drawings.

15
SOME GENERAL TIPS FOR P&ID 2

• Draw main process line entering from the left and leaving on the right (whenever possible)

• Draw utility process line entering from the left and leaving on the right (whenever possible)

• Minimise lines crossing

• All lines must have


1. Line identification
2. Directional arrow
3. Lines entering diagram should have: - from …..‟ (equipment item/other P&ID etc)
4. Lines exiting diagram should have: - to …..‟ (equipment item/other P&ID etc)

16
EQUIPMENT BLOCK EXAMPLE
PLANT ITEM NO V-101 P-101 A/B E-101
DESCRIPTION HCL HOLDING TANK CAUSTIC FEED PUMP SULPHURIC ACID COOLER
The one in highlighted in
yellow is not needed for your
DRAWING NO DWG-FD 1234 DWG – X 645 DWG – E 234 exercise
EQUIPMENT NUMBER 1 2 x 100% 1

SIZE/DIMENSIONS (MM) 1500 (D) × 3500 (H) 70 2200


/SHAFT POWER (kW)/HEAT Note*: The description of this
EXCHANGED (kW) * row changes with type of
MATERIALS OF SS 316L TITANIUM HASTELLOY C process equipment.
CONSTRUCTION
WORKING CAPACITY 4.6M3 35 M3/HR ACID 40,00O KG/HR
COOLING WATER 70,000
KG/HR
DESIGN TEMPERATURE 65 80 ACID – 120, CW – 80
(°C)
DESIGN PRESURE BAR (G) 10 18 ACID - 7 BAR (G)
CW – 7 BAR (G)
SUPPLIER ABC SDN. BHD PKE SDN BHD KPJ SDN. BHD

ORDER NO. CP 0001 CP 0002 CP 0003

17
WHAT YOU SHOULD NOT DO

• No title block/title

• Hand drawn

• Submit a P&ID drawing which do not match with the legend

• Complex control schemes that do not make sense

• Inconsistent equipment/line or valve labelling between different members.

18
P&ID IN PROGRESS REPORT 4 AND FINAL REPORT 2
▪ This is an individual task. Each team member will submit a P&ID for the whole section (process block) that
he or she is responsible for.

▪ The P&ID should be drawn on A3 paper and submitted explanation per individual (recommend to keep this
within 2 pages), containing the following :
• Control and operation strategy for the particular process block (to achieve design objectives)*
• A write up on your maintenance layer, simple procedure for the maintenance work of one item or
equipment which may need to be replaced*, e.g. a dry gas line , 50-PG-12061-150CS-25H is
connected to process line to dry the moisture in process line 150-PG-12001-600CS-N and equipment
XX during maintenance.
• A write up on your safety layer, how you handle abnormal operations – a brief description your cause
and effect matrix, e.g. Shutdown valves 10-SDV-001 will trigger in the event vessel the pressure of V-
1002 exceeds XX barg.

*Note: If you have covered this writeup in the detailed design section, you can omit this.
19
OTHER DETAILS IN P&ID WRITE UP

▪ The information provided must be as complete and comprehensive as possible , so that there is absolute
clarity and the subsequent HAZOP study picks up only minor issues.

▪ All team members should agree and use a standard set of symbols and this should be captured in the P&ID
legend sheet and form part of the Progress Report 4/Final Report submission.

▪ A common numbering system is also recommended, with one team member numbering lines equipment etc
starting with 1xx, the next student with 2xx etc, remembering that where lines and signals cross P&ID
boundaries, the numbering system between sheets needs also to be consistent.

20
CAUSE AND EFFECT MATRIX

• This is required to record all the causes and actions of your multiple-inputs and multiple-outputs (MIMO)
actions.

• If you include a MIMO instrument in your P&ID, you will need to include this after your P&ID. Only the cause
and matrix of the drawn P&ID is required.

• This cause and effect matrix will supplement the safety considerations you provide in your detailed design.

• List all your “cause(s)” in the horizontal rows and all the “effect(s)” in the vertical columns.

Note: Only include MIMO items like safety shutdown, blowdown valves and PSV (multiple trigger causes).
Control valves are not part of cause and effect matrix.

21
Drawing/ Document No.
22
CASE STUDY 13 – CONSTRUCTING P&ID FOR V-1000
We have briefly discuss about the
detailed design of V-1000 in the gas
processing facility. Assuming that you
are the person in charge of the detailed
design of V-1000 and a draft P&ID is
given to you by your teammate (see
picture on the right). Using what we
have developed earlier,

1. Discuss what items/details would


you add to this drawing (Safety
considerations, instrument,
maintenance provision)?
2. Discuss how you start-up, shutdown
and maintain this equipment

23
CASE STUDY 13 – NOTES

24
CASE STUDY 14 – CAUSE AND EFFECT MATRIX

• Continuing from our discussion on the P&ID of V-1000, you are now required to construct the cause and
effect matrix for this section. Discuss how would you construct the cause and effect matrix for this item?
• Note: You might want to keep the drawing of case study 13 beside you for easy reference.

25
CASE STUDY 14 – NOTES

26
THANK YOU
lee.chernleing@monash.edu

https://lms.monash.edu/course/view.php?id=71767

You might also like